Information about this General Permit:
Applicability
Pursuant to the provisions of the Clean Air Act (CAA), Subchapter I, part D and 40 CFR part 49, subpart C, this
permit authorizes the construction or modification and the operation of each stationary petroleum dry cleaning
facility for which a reviewing authority issues an Approval of the Request for Coverage (permitted source).
Eligibility
To be eligible for coverage under this general permit, the permitted source must qualify as a true minor source
as defined in 40 CFR 49.152.
Request for Coverage
Requirements for submitting a Request for Coverage are contained in Section 7 of this general permit.
Incorporation of Documents
The information contained in each reviewing authority's Approval of the Request of Coverage is hereby
incorporated into this general permit.
Termination
Section 6 of this general permit addresses a reviewing authority's ability to revise, revoke and reissue, or
terminate this general permit. It also addresses the reviewing authority's ability to terminate an individual
permitted source's Approval of the Request for Coverage under this general permit.
Definitions
The terms used herein shall have the meaning as defined in 40 CFR 49.152, unless otherwise defined in
Attachment B of this permit. If a term is not defined, it shall be interpreted in accordance with normal business
use.
$
<
33
V
o
w
PRO^t&
III
0

-------
Permit Terms and Conditions
The following applies to each permittee and permitted source with respect to only the affected emissions units
and any associated air pollution control technologies in that permitted source's Approval of the Request for
Coverage.
Section 1: General Provisions
1.	Construction and Operation
The permittee shall construct or modify and shall operate the affected emissions units and any associated
air pollution control technologies in compliance with this permit and all other applicable federal air quality
regulations; and in a manner consistent with representations made by the permittee in the Request for
Coverage, to the extent the reviewing authority relies upon these representations in issuing the Approval of
the Request for Coverage.
2.	Locations
This permit only authorizes the permittee to construct or modify and to operate the permitted source at the
location listed in the reviewing authority's Approval of the Request for Coverage for that permitted source.
3.	Liability
This permit does not release the permittee from any liability for compliance with other applicable federal
and tribal environmental laws and regulations, including the CAA.
4.	Severability
The provisions of this permit are severable. If any portion of this permit is held invalid, the remaining
terms and conditions of this permit shall remain valid and in force.
5.	Compliance
The permittee must comply with all provisions of this permit, including emission limitations that apply to the
affected emissions units at the permitted source. Noncompliance with any permit provision is a violation of
the permit and may constitute a violation of the CAA; is grounds for an enforcement action; and is grounds
for the reviewing authority to revoke the Approval of the Request for Coverage and terminate the permitted
source's coverage under this general permit.
6.	National Ambient Air Quality Standards (NAAQS)/Prevention of Significant Deterioration (PSD) Protection
The permitted source must not cause or contribute to a NAAQS violation or, in an attainment area, must not
cause or contribute to a PSD increment violation.
7.	Unavailable Defense
It is not a defense for the permittee in an enforcement action that it would have been necessary to halt or
reduce the permitted activity in order to maintain compliance with the provisions of this permit.
8.	Property Rights
The permit does not convey any property rights of any sort or any exclusive privilege.
General Permit for Petroleum Dry Cleaning Facilities
Version 1.0
Page 2 of 11

-------
9.	Information Requests
You, as the permittee, shall furnish to the reviewing authority, within a reasonable time, any information
that the reviewing authority may request in writing to determine whether cause exists for revising, revoking
and reissuing, or terminating the permit or to determine compliance with the permit. For any such
information claimed to be confidential, the permittee must submit a claim of confidentiality in accordance
with 40 CFR part 2 subpart B.
10.	Inspection and Entry
Upon presentation of proper credentials, the permittee must allow a representative of the reviewing
authority to:
a.	Enter upon the premises where a permitted source is located or emissions-related activity is conducted
or where records are required to be kept under the conditions of the permit;
b.	Have access to and copy, at reasonable times, any records that are required to be kept under the
conditions of the permit;
c.	Inspect, during normal business hours or while the permitted source is in operation, any facilities,
equipment (including monitoring and air pollution control equipment), practices or operations regulated
or required under the permit;
d.	Sample or monitor, at reasonable times, substances or parameters for the purpose of assuring
compliance with the permit or other applicable requirements and
e.	Record any inspection by use of written, electronic, magnetic and photographic media.
11.	Posting of Coverage
This general permit, and the most current Approval of the Request for Coverage for the permitted
source, must be posted prominently at the facility, and each affected emissions unit and any associated
air pollution control technology must be labeled with the identification number listed in the Approval of
the Request for Coverage for that permitted source.
12.	Duty to Obtain a Source-specific Permit
If the reviewing authority intends to terminate a permitted source's coverage under this general permit for
cause as provided in Section 6 of this general permit, then the permittee shall apply for and obtain a source-
specific permit as required by the reviewing authority.
13.	Credible Evidence
For the purpose of establishing whether the permittee violated or is in violation of any requirement of this
permit, nothing shall preclude the use, including the exclusive use, of any credible evidence or information
relevant to whether a permitted source would have been in compliance with applicable requirements if the
permittee had performed the appropriate performance or compliance test or procedure.
Section 2: Emission Limitations and Standards
14.	The permittee shall maintain and operate each affected emissions unit, including any associated air
pollution control equipment, in a manner consistent with good air pollution control practices for
minimizing emissions of New Source Review regulated pollutants and considering the manufacturer's
recommended operating procedures at all times, including periods of startup, shutdown,
maintenance and malfunction. The reviewing authority will determine whether the permittee is using
acceptable operating and maintenance procedures based on information available to the reviewing
General Permit for Petroleum Dry Cleaning Facilities
Version 1.0
Page 3 of 11

-------
authority which may include, but is not limited to, monitoring results, opacity observations, review of
operating and maintenance procedures, and inspection of the permitted source.
15.	The permittee shall not consume more than the amount of petroleum solvent specified below:
a.	5,600 gallons per year based on a rolling 12-month total for a facility located in an ozone
attainment area; or
b.	1,300 gallons per year based on a rolling 12-month total for a facility located in an ozone
nonattainment area.
16.	If your facility has a total manufacturer's rated dryer capacity equal to or greater than 38 kilograms (84
pounds), then you shall meet the following requirements:
a. Each petroleum solvent dry cleaning dryer shall be a solvent recovery dryer. The solvent recovery
dryer(s) shall be properly installed, operated, and maintained according to the manufacturer's
specifications.
17.	All solvents shall be stored in closed containers.
18.	Button and lint traps shall be cleaned each working day.
19.	All washer lint traps, button traps, access doors, and other parts of the equipment where solvent may be
exposed to the atmosphere shall be kept closed at all times except when required for proper operation or
maintenance.
20.	The still residue, used filtering material, lint, used solvent and all other wastes containing solvent shall be
stored in sealed containers until properly disposed.
21.	If your facility is located in a serious, severe, or extreme ozone nonattainment area, then the permittee shall
also comply with the additional equipment specifications and operating requirements specified in
Attachment A.
Section 3: Monitoring and Testing Requirements
22.	Each petroleum solvent dry cleaning dryer shall be inspected every 15 calendar days for evidence of leaks
and all vapor or liquid leaks shall be repaired within the subsequent 15 calendar day period.
Section 4: Recordkeeping Requirements
23.	The permittee shall maintain all records required to be kept by this permit for at least five years from the
date of origin, unless otherwise stated, either onsite or at a convenient location, such that they can be
delivered to the reviewing authority within 24 hours of a request.
24.	The permit application and all documentation supporting that application shall be maintained by the
permittee for the duration of time the affected emissions unit(s) is covered under this permit.
25.	The permittee shall maintain a log of:
General Permit for Petroleum Dry Cleaning Facilities
Version 1.0
Page 4 of 11

-------
a.	The results of the daily leak inspections, any corrective actions taken to repair leaks, and the results of
any corrective actions taken.
b.	Each type of petroleum solvent used at the facility;
c.	The date, type, and amount of solvent (in gallons) added to the solvent tank of each dry cleaning
machine;
d.	The monthly total gallons of petroleum solvent used and the resulting 12-month rolling total of solvent
used. The 12-month rolling total is defined as the sum of the gallons of petroleum solvent used during
the current month and the gallons of petroleum solvent used for the previous eleven (11) months.
Section 5: Notification and Reporting Requirements
26.	Notification of construction or modification, and operations
The permittee shall submit a written or electronic notice to the reviewing authority within 30 days from
when the permittee begins actual construction, and when the permittee begins operations or resumes
operation.
27.	Notification of Change in Ownership
If the permitted source changes ownership, then the permittee must submit a written or electronic notice to
the reviewing authority within 90 days before or after the change in ownership is effective. In the report, the
permittee must provide the reviewing authority a written agreement containing a specific date for transfer
of ownership, and an effective date on which the new owner assumes partial and/or full coverage and
liability under this permit. The submittal must identify the previous owner, and update the name, street
address, mailing address, contact information, and any other information about the permitted source if it
would change as a result of the change of ownership. The permittee shall ensure that the permitted source
remains in compliance with the general permit during any such transfer of ownership.
28.	Notification of Closure
The permittee must submit a report of any permanent or indefinite closure to the reviewing authority in
writing within 90 days after the cessation of all operations at the permitted source. It is not necessary to
submit a report of closure for regular, seasonal closures.
29.	Annual Reports
The permittee shall submit an annual report on or before March 15 of each calendar year to the reviewing
authority. The annual report shall cover the period from January 1 to December 31 of the previous calendar
year and shall include:
a.	An evaluation of the permitted source's compliance status with the requirements in Section 2;
b.	Summaries of the required monitoring and recordkeeping in Sections 3 and 4; and
c.	Summaries of deviation reports submitted pursuant to Condition 30.
30.	Deviation Reports
The permittee shall promptly report to the reviewing authority any deviations from permit requirements
including deviations attributable to upset conditions. Deviation reports shall include:
a.	The identity of affected emissions unit where the deviation occurred.
b.	The nature of the deviation;
c.	The length of time of the deviation;
d.	The probable cause of the deviation; and
General Permit for Petroleum Dry Cleaning Facilities
Version 1.0
Page 5 of 11

-------
e.	Any corrective actions or preventive measures taken as a result of the deviation to minimize emissions
from the deviation and to prevent future deviations.
f.	For the purposes of this permit, promptly shall be defined to mean:
i. At the time the annual report in Condition 29 is submitted.
31.	Reporting and Notification Address
The permittee shall send all required reports to the reviewing authority at the mailing address(es) specified
in the Approval of the Request for Coverage.
32.	Signature Verifying Truth, Accuracy, and Completeness
All reports required by this permit shall be signed by a responsible official as to the truth, accuracy, and
completeness of the information. The report must state that, based on information and belief formed after
reasonable inquiry, the statements and information are true, accurate, and complete. If the permittee
discovers that any reports or notification submitted to the reviewing authority contain false, inaccurate, or
incomplete information, the permittee shall notify the reviewing authority immediately and correct or
amend the report as soon as practicable.
Section 6: Changes to this General Permit
33.	Revising, Reopening, Revoking and Reissuing, or Terminating for Cause
The permit may be revised, reopened, revoked and reissued, or terminated for cause. The filing of a request
by you, the permittee, for a permit revision, revocation and re-issuance, or termination, or of a notification
of planned changes or anticipated noncompliance does not stay any permit condition. This provision also
applies to the documents incorporated by reference.
34.	Terminating Coverage under this Permit
The reviewing authority may terminate a previously issued Approval of the Request for Coverage, and
thereby terminate that permittee's authorization to construct or modify, and that permitted source's
authorization to operate under this general permit for cause as defined in Attachment B. The reviewing
authority may provide the permittee with notice of the intent to terminate, and delay the effective date of
the termination to allow the permittee to obtain a source-specific permit.
35.	Change in ownership
If the permitted source changes ownership, the reviewing authority may change the Approval of the
Request of Coverage to reflect the new ownership in accordance with the administrative amendment
provisions in 40 CFR 49.159(f).
Section 7: Obtaining Coverage under this General Permit
36.	To obtain coverage under this general permit, an applicant must submit a Request for Coverage to the
appropriate reviewing authority for the area in which the permitted source is or will be located. Attachment
D contains a list of reviewing authorities and their area of coverage. You must also submit a copy of the
Request for Coverage to the Indian governing body for any area in which the permitted source will operate.
General Permit for Petroleum Dry Cleaning Facilities
Version 1.0
Page 6 of 11

-------
Attachment A: Abbreviations and Acronyms
CAA or the ActFederal Clean Air Act
CFR	Code of Federal Regulations
EPA	United States Environmental Protection Agency
NAAQS	National Ambient Air Quality Standards
NSR	New Source Review
PSD	Prevention of Significant Deterioration
General Permit for Petroleum Dry Cleaning Facilities
Version 1.0
Page 7 of 11

-------
Attachment B: Definitions
For the purposes of this general permit:
Approval of the Request for Coverage means a reviewing authority's letter granting an applicant's request for
construction or modification, and operation of a true minor source under the terms and conditions of this
general permit.
Cause means with respect to the reviewing authority's ability to terminate a permitted source's coverage under
a permit that:
1.	The permittee is not in compliance with the provisions of this general permit;
2.	The reviewing authority determines that the emissions resulting from the construction or modification
of the permitted source significantly contribute to National Ambient Air Quality Standard violations,
which are not adequately addressed by the requirements in this general permit;
3.	The reviewing authority has reason to believe that the permittee obtained Approval of the Request for
Coverage by fraud or misrepresentation; or
4.	The permittee failed to disclose a material fact required by the Request for Coverage or the regulations
applicable to the permitted source of which the applicant had or should have had knowledge at the time
the permittee submitted the Request for Coverage.
Construction means any physical change or change in the method of operation including fabrication, erection,
installation, demolition, or modification of an affected emissions unit that would result in a change of emissions.
Permittee means the owner or operator of a permitted source.
Permitted source means each petroleum drying cleaning facility for which a reviewing authority issues an
Approval of the Request for Coverage.
Request for Coverage means a permit application that contains all the information required in the standard
application form.
Solvent recovery dryer means a class of dry cleaning dyers that employs a condenser to condense and recovery
solvent vapors evaporated in a closed-loop stream of heated air, together with the piping and ductwork used in
the installation of this device.
General Permit for Petroleum Dry Cleaning Facilities
Version 1.0
Page 8 of 11

-------
Attachment C: Petroleum Dry Cleaning Facilities in Certain Nonattainment Areas
For facilities located in serious, severe, or extreme ozone nonattainment areas, the permittee shall operate and
maintain the solvent dry cleaning system in accordance with the requirements specified below and in
accordance with the manufacturer's recommendations:
Section 1: General Specifications
1.	All parts of the dry cleaning system where solvent may be exposed to the atmosphere or workroom shall be
kept closed at all times except when access is required for proper operation and maintenance.
2.	Wastewater evaporators shall be operated to ensure that no liquid solvent or visible emulsion is allowed to
vaporize to the atmosphere.
Section 2: Additional Specification for Closed-Loop Machines
A closed-loop machine means dry cleaning equipment in which washing, extraction, and drying is performed
within the same single affected emissions unit and which re-circulates and recovers the solvent-laden vapor.
3.	A closed-loop machine shall not exhaust to the atmosphere or workroom during operation except when the
vacuum pump exhausts to maintain a continuous vacuum.
4.	For any closed-loop machine that is not equipped with a locking mechanism, the operator shall not open the
door of a closed-loop machine prior to completion of the drying cycle.
5.	For any closed-loop machine that is equipped with a locking mechanism, the operator shall not inactivate
the locking mechanism and open the door of a closed-loop machine prior to completion of the drying cycle.
Section 3: Leak Check and Repair Requirements
6.	No less frequently than monthly, the owner or operator shall inspect the dry cleaning system for liquid and
vapor leaks, including, but not limited to, the following:
a.	Hose connections, unions, couplings, valves, and flanges;
b.	Machine door gasket and seating of the machine cylinder;
c.	Filter head gasket and seating;
d.	Pumps;
e.	Base tanks and storage containers;
f.	Water separators;
g.	Filter sludge recovery;
h.	Seals and gaskets of distillation unit(s);
i.	Diverter valves;
j.	Saturated lint from lint trap basket;
k.	Button trap lid;
I.	Seals, gaskets and the diverter valve of the refrigerated condenser;
m.	Exhaust stream ducts;
General Permit for Petroleum Dry Cleaning Facilities
Version 1.0
Page 9 of 11

-------
n. Lint trap ducts; and
o. Gaskets and ducts of the carbon adsorber.
7.	To inspect for a vapor leak, the operator shall use at least one of the following techniques:
a.	Soap bubble technique in accordance with the procedures in EPA Method 21, Section 4.3.3 - Alternative
Screening Procedure; or
b.	A non-halogenated hydrocarbon detector; or
c.	A portable hydrocarbon analyzer or an alternative method approved by the reviewing authority.
8.	To inspect for a liquid leak, the operator shall visually inspect the equipment for liquid leaking in a visible
mist or at the rate of more than one drop every three minutes.
9.	Any liquid leak or vapor leak that has been detected by the operator shall be repaired within three (3)
working days of detection. If repair parts are not available at the facility, the parts shall be ordered within
two working days of detecting such a leak and the operator shall provide written notification to the
reviewing authority that explains the reason(s) for delaying the leak repair. Such repair parts shall be
installed within five working days after receipt. A facility with a leak that has not been repaired by the end of
the seventh (7th) working day after detection shall not operate the dry cleaning equipment, until the leak is
repaired.
General Permit for Petroleum Dry Cleaning Facilities
Version 1.0
Page 10 of 11

-------
Attachment D - List of Reviewing Authorities and Areas of Coverage
EPA Region
Address
Area Covered
Phone Number
Region 1
1 Congress Street
Suite 1100
Boston, MA 02114-2023
Connecticut, Maine, Massachusetts,
New Hampshire, Rhode Island, and
Vermont
888- 372-7341
617-918-1111
Region II
290 Broadway
25th Floor
New York, NY 10007-1866
New Jersey, New York, Puerto Rico,
and Virgin Islands
877-251-4575
Region III
1650 Arch Street
Philadelphia, PA 19103-2187
Delaware, District of Columbia,
Maryland, Pennsylvania, Virginia,
and West Virginia
800-438-2474
215-814-5000
Region IV
Sam Nunn Atlanta Federal Center
61 Forsyth Street SW
12th Floor
Atlanta, GA 30303
Alabama, Florida, Georgia, Kentucky,
Mississippi, North Carolina, South
Carolina, and Tennessee
800-241-1754
404-562-9000
Region V
77 West Jackson Street
Chicago, IL 60604
Illinois, Indiana, Michigan,
Minnesota, Ohio, and Wisconsin
800-621-8431
312-353-2000
Region VI
1445 Ross Avenue
Dallas, TX 75202
Arkansas, Louisiana, New Mexico,
Oklahoma, and Texas
800-887-6063
214-665-2760
Region VII
11201 Renner Boulevard
Lenexa, KS 66219
Iowa, Kansas, Missouri, and
Nebraska
800-223-0425
913-551-7003
Region VIII
1595 Wynkoop Street
Denver, CO 80202-1129
Colorado, Montana, North Dakota,
South Dakota, Utah, and Wyoming
800-227-8917
303-312-6312
Region IX
75 Hawthorne Street
San Francisco, CA 94105
American Samoa, Arizona,
California, Guam, Hawaii, Nevada,
and Northern Mariana Islands
866-EPA-9378
415-947-8000
Region X
1200 Sixth Avenue
Seattle, WA 98101
Alaska, Idaho, Oregon, and
Washington
800-424-4372
206-553-1200
General Permit for Petroleum Dry Cleaning Facilities
Version 1.0
Page 11 of 11

-------