MERCURY REFINING SUPERFUND SITE Towns of Colonie and Guilderland, Albany County, NY SOIL AND GROUND WATER CLEANUP TO RESUME IN JULY Community Update July 2014 The U.S. Environmental Protection Agency has prepared this fact sheet to inform the community, local officials and other interested parties about the status of the soil and ground water cleanup activities at the Mercury Refining Superfund Site. Specifically, this fact sheet provides a summary of the planned and completed construction work at the site. If you have questions or need more information, please contact: Larisa Romanowski EPA Community Involvement Coordinator (518) 747-4389 romanowski.larisa@epa.gov Thomas Mongelii EPA Project Manager (212) 637-4256 monqelli.thomas@epa.gov Local EPA Document Repository: William K. Sanford Town Library 629 Albany Shaker Road Loudonville, NY 12211 From 1956 to 1998, the half-acre Mercury Refining Company, Inc. site, located at 26 Railroad Avenue in Colonie, New York, was used for reclaiming mercury from batteries and other mercury-bearing materials. Soil, ground water and sediment on-site are contaminated with mercury. After an extensive investigation and evaluation of various options for cleanup of the site, the EPA selected its final cleanup plan in 2008. That plan requires a combination of soil excavation and treatment of the soil and ground water. The design of the cleanup, which was prepared by Brown and Caldwell Associates on behalf of the companies responsible for the contamination, was approved by the EPA in September 2013. The design document is available for review at the local repository located at the William K. Sanford Town Library. The cleanup of the Mercury Refining Superfund Site is being conducted in two phases. The first phase was performed in fall 2013 and included contaminated soil and sediment excavation, removal and backfilling. The second phase, which includes the in-situ (in-place) solidification/stabilization portion of the cleanup, is expected to be performed in summer 2014. The main components of the soil, ground water and sediment cleanup include: • Excavation and off-site disposal of mercury contaminated soil that exceeds the 5.7 parts per million (ppm) cleanup objective; • Excavation and off-site disposal of mercury contaminated sediment in the Unnamed Tributary to Patroon Creek which exceed the 1.3 ppm cleanup objective; and • In-situ solidification/stabilization of soil in areas of the site where mercury concentrations in ground water exceed the 0.7 ppm cleanup objective. ------- In-Situ Solidification/Stabilization - Summer 2014 The second phase of work, which includes the in-situ (in-place) solidification/stabilization portion of the cleanup, is expected to be performed in summer 2014. Construction work will take place from 7:00 a.m. to 5:00 p.m., Monday through Saturday. It is estimated that the in-situ solidification/stabilization work will require three months to complete beginning in mid-July 2014. The cleanup is being conducted by WRS Infrastructure & Environment on behalf of the companies responsible for the contamination at the site. The EPA will oversee all of the construction activities. The in-situ solidification/stabilization portion of the cleanup will involve the use of an auger system to blend columns of soil within the in-situ solidification/stabilization area with a mixture of Portland cement and a sulfur containing compound. The sulfur compound acts to chemically stabilize mercury in both the soil and ground water into an immobile state. The specific sulfur compound will be determined after a pilot scale study. The cement significantly restricts the ability of ground water to infiltrate the in-situ solidification/stabilization area and carry mercury off-site. It will also provide the soil strength necessary to allow for site reuse after the cleanup. The solidified soil columns will extend downward approximately 60 to 70 feet, including a minimum of two feet into the clay layer underlying the site, which acts as a natural barrier to the mercury contamination. Due to the anticipated swelling of the solidified soil columns, pre-excavation of approximately 7 to 8-feet of soil located above the water table will be conducted throughout the in-situ solidification/stabilization area, except for those areas adjacent to the on-site building and perimeter of the work area, to maintain structural integrity of the building and optimize safety of the work area. Excavated soil will be direct-loaded into transport vehicles. Liners will be installed in each truck, and plastic sheeting will be placed over the loading side and beneath each truck to minimize the need for decontamination. Transport and disposal of all hazardous and non-hazardous waste will be in accordance with all applicable state and federal laws and regulations. Air monitoring for mercury vapors and particulates (i.e. dust) will be performed at the downwind perimeter of work areas. These include soil excavation, handling, transport, and backfilling, soil staging, stockpiling, stabilization/immobilization, or sampling work areas. Air monitoring will ensure the protection of the downwind community from potential airborne releases associated with site investigation and cleanup work. This air monitoring will be in addition to the air monitoring that will be performed around the work areas for on-site workers' protection. Should the contaminants and particulates approach unacceptable levels, corrective actions to reduce emissions (e.g., dust suppression/control measures via water applications, vehicle speed reductions, materials hauling in tarped or watertight containers, etc.), and/or work shutdown will be implemented. Furthermore, good site management practices will be carried out to keep vapors, dust, and odors at a minimum around the work areas. All safety procedures including equipment decontamination (where necessary), and Health and Safety Contingency Plan protocols will be followed in the same manner as during the soil and sediment excavation. 2 ------- The site will be secured through use of a temporary fence and an existing fence. Entrance to the site will only be permitted for authorized personnel with proper identification. The work that will be performed will be done in a way that accommodates, to the extent practicable, the needs and concerns of the current site operator, adjacent property owners, and the surrounding community. The work will also comply with applicable rules and regulations for the protection of the environment and the health and safety of the personnel performing and overseeing the work. Soil and Sediment Excavation - Fall 2013 (Completed) Soil and sediment excavation activities were conducted at the site by LAND Remediation, Inc. between October and December 2013. A total of 5,588 tons of non-hazardous sediment, soil, debris, concrete, and asphalt and 172 tons of hazardous soil and asphalt containing button batteries were excavated and disposed of off-site. Additionally, 3,500 gallons of water including decontamination water and water pumped from the Unnamed Tributary to Patroon Creek were collected and treated and disposed of off-site. A total of 301 post-excavation soil and sediment samples were collected to confirm that all soil and sediment above the respective 5.7 ppm and 1.3 ppm cleanup objectives, not located within the in-situ solidification/stabilization, were removed. Following excavation, all areas were backfilled with clean soil and paved, covered with stone, or seeded with grass where appropriate. Perimeter air monitoring was conducted throughout the soil and sediment excavation activities. The air quality requirements for particulate matter and mercury vapor were met during work activities. More information about the Mercury Refining Superfund Site is available at http://epa.qov/Reqion2/superfund/npl/mercurvrefininq/. Regional Public Liaison: If you would like information on general environmental concerns or the federal Superfund hazardous waste program, have concerns or complaints about the Superfund program, or if you seek assistance in resolving site-specific issues that were not fully addressed by the EPA, please contact: George Zachos U.S. EPA Regional Public Liaison (732) 321-6621 zachos.qeorqe@epa.gov Or toll free at (888) 283-7626 3 ------- |