Technical Support Document (TSD) for the CAA Section 111(d) Emission Guidelines for Existing Power
Plants
New Source Complements to Mass Goals
Technical Support Document for CPP
Final Rule
U.S Environmental Protection Agency
Office of Air and Radiation
August 2015

-------
New Source Complements to Mass Goals under 111(d)
This Technical Support Document (TSD) provides information that supports the EPA's quantification of
new source complements in Section VIII. J of the preamble. These new source complements represent the
EPA's estimated new source emissions associated with satisfying incremental demand from 2012. States
may add these new source complements to the final rule's mass goals in pursuing a mass-based
compliance pathway inclusive of both affected EGUs and new fossil fuel-fired sources. The methodology
for quantifying these new source complements is presented in five steps:
1.	Calculate incremental generation needed for each interconnection to satisfy projected load growth
from 2012 levels1
2.	Subtract generation from under construction facilities included in the final rule
3.	Subtract generation growth from affected EGUs and incremental renewable energy (RE)
accounted for in the calculation of mass goals
4.	Apportion remaining incremental generation to states on the basis of each state's 2012 share of
the interconnection's affected EGU generation total2
5.	Convert state-level incremental generation to state-level incremental emissions by assuming the
New Source Performance Standard emission rate for NGCC of 1,030 lbs/MWh
The spreadsheet 'New Source Complements' is available in the docket and provides the complete set of
calculations for each state.
1. Calculate incremental generation needed for each interconnection to satisfy projected load
growth from 2012 levels
For this step, the EPA relies on the projected net energy for load values from the Energy Information
Administration's (EIA's) 2015 Annual Energy Outlook (AEO2015).3 Those values are presented in
Table 1 for the baseline year of 2012 and all years, 2022 through 2030.
Table 1. Net Energy for Load by Interconnection (TWh)
Year
Eastern
Interconnection
Western
Interconnection
Texas
Interconnection
2012
2,881
730
333
2022
3,094
775
361
2023
3,114
782
365
2024
3,137
789
369
2025
3,158
797
372
2026
3,178
803
376
2027
3,196
810
380
2028
3,213
816
383
1	In this document, unless otherwise indicated, "incremental" means beyond the level observed in 2012.
2	Affected EGU generation total is equal to the 2012 adjusted baseline used to calculate goal rates
3	Net energy for load is defined by the EIA as the net generation of main generating units that are system-owned or
system-operated, plus energy receipts minus energy deliveries
2

-------
2029
3,231
823
387
2030
3,245
829
391
The AEO projections are then converted into a percent increase in net energy for load, relative to 2012,
for each interconnection and each year. Conversion to a percent increase enables the EPA to apply the
projected demand growth to 2012 historical data.
Table 2. Increase in Net Energy for Load From 2012 (%)
Year
Eastern
Interconnection
Western
Interconnection
Texas
Interconnection
2022
7.4%
6.2%
8.6%
2023
8.1%
7.1%
9.6%
2024
8.9%
8.2%
10.8%
2025
9.6%
9.2%
11.9%
2026
10.3%
10.1%
13.0%
2027
10.9%
11.0%
14.0%
2028
11.5%
11.9%
15.1%
2029
12.2%
12.8%
16.3%
2030
12.7%
13.6%
17.4%
The historical generation associated with each interconnection is calculated as 2012 historical sales
adjusted to account for an average transmission loss factor of 7.51%:4
•	2012 Generation = 2012 Sales x (1+ Transmission Losses)
•	2012 Eastern Interconnection Generation = 2,626,988 GWh x 1.0751 = 2,824,274 GWh
•	2012 Western Interconnection Generation = 671,260 GWh x 1.0751 = 721,672 GWh
•	2012 Texas Interconnection Generation = 365,467 GWh x 1.0751 = 392,914 GWh
For each year, 2022 through 2030, the incremental generation required to support demand growth is 2012
sales multiplied by the percent increase in net energy for load for that year.5 For example:
•	2030 Incremental Generation to Support Demand Growth in the Eastern Interconnection =
2,824,274 GWh x 12.7% = 357,353 GWh
Table 3 contains the incremental generation to support demand growth for each interconnection in each
year:
Table 3. Incremental Generation to Support Demand Growth
(GWh)
Year
Eastern
Interconnection
Western
Interconnection
Texas
Interconnection
4	The 7.51% scalar represents an average historical difference between total net generation of electricity and retail
sales of electricity, http://www.eia.gov/electricity/state/pdf/sep2010.pdf a
5	This relationship assumes that the international export/import balance remains constant at 2012 levels and all
incremental demand is met with generation from the U.S.
3

-------
2022
209,623
44,887
33,605
2023
228,901
51,476
37,525
2024
251,878
59,148
42,332
2025
272,214
66,281
46,616
2026
291,203
72,570
51,229
2027
308,827
79,060
55,042
2028
325,981
85,759
59,323
2029
343,525
92,729
64,065
2030
357,353
98,181
68,244
2. Subtract generation from under construction facilities included in the final rule
The incremental generation to support demand growth calculated in step 1 would be served in part by the
under construction facilities that are part of the final rule but not reflected in the 2012 historical data.
Table 4 displays the under construction capacity that did not commence operations in 2012 for each
facility type - affected coal-fired EGUs, affected natural gas-fired EGUs, and nuclear units that are
eligible for compliance.6
Table 4. Under Construction Facilities by Interconnection (MW)
Facility
Type
Eastern
Interconnection
Western
Interconnection
Texas
Interconnection
NGCC
10,633
2,636
2,489
Coal
655
0
0
Nuclear
5,522
0
0
Each facility type is assigned an annual net capacity factor associated with the amount of generation
expected to meet future demand. This capacity factor does not represent expected total annual output, but
instead represents the portion of total annual output that will deduct from the incremental generation
needed to support demand growth.7 For example, and consistent with the application of building block 2,
under construction NGCC is assigned a capacity factor associated with future demand of 55%; coal-fired
EGUs are assigned a capacity factor of 60%; and nuclear facilities are assigned a capacity factor of 66%.8
6	Under construction facilities that commenced operation in 2012 are excluded from this adjustment due to the
unknown impact their full-year operations would have on the 2012 data. Instead, the assumed output of full-year
operations from these facilities is reflected in each state's adjusted 2012 baseline generation total, which is the
basis for apportioning interconnection-level new source complement generation to state-level new source
complement generation.
7	The amount of generation from under construction facilities that is expected to replace existing source
generation is irrelevant to the calculation of new source emissions associated with satisfying incremental demand
from 2012.
8	The 66% capacity factor assigned to nuclear is set at the same ratio of future demand to total output (66%
dedicated to future demand; total output of 90%) as under construction NGCCs in building block 2 (55% dedicated
to future demand; total output of 75%)
4

-------
The generation totals associated with applying these capacity factors to under construction facilities are
shown in Table 5:
Table 5. Incremental Generation Assumed to Meet Future Demand
from Under Construction Facilities by Interconnection (GWh)
Facility
Type
Eastern
Interconnection
Western
Interconnection
Texas
Interconnection
NGCC
51,231
12,702
11,991
Coal
3,443
0
0
Nuclear
31,926
0
0
3. Subtract generation growth from affected EGUs and incremental RE accounted for in the
calculation of mass goals
The calculation of mass goals incorporates an amount of generation growth from both affected EGUs and
RE that would serve to meet future demand requirements.9 Consequently, because the estimated
emissions from this particular incremental generation are already included in the mass goals, it is
necessary to deduct this amount of generation, listed in Table 6, from the incremental generation needed
to support demand growth that will inform the estimation of the new source complements.
Table 6. Affected EGU and RE Generation Gro
Mass Goal Calculation (GW
wth Incorporated in
h)
Year
Eastern
Interconnection
Western
Interconnection
Texas
Interconnection
2022
138,054
29,209
22,689
2023
131,858
27,898
21,670
2024
135,132
28,591
22,208
2025
149,186
31,565
24,518
2026
161,395
34,148
26,525
2027
164,934
34,897
27,106
2028
191,779
40,576
31,518
2029
218,279
46,183
35,873
2030
241,664
51,131
39,716
The amount of generation remaining after deducting the generation growth incorporated in mass goals is
referred to as the new source complement generation, and it is defined as:
• Interconnection-level new source complement generation = Incremental generation to support
demand growth - Generation from under construction facilities dedicated to serving future
9 For more information, please see section VII of the preamble and the C02 Emission Performance Rate and Goal
Computation TSD
5

-------
demand (step 2) - Generation growth from affected EGUs and RE assumed in the mass goal
calculation (step 3)10
• Eastern Interconnection new source complement generation in 2030 = 357,353 GWh - 86,600
GWh - 241,664 GWh = 29,090 GWh
The new source complement generation for each interconnection in each year is provided below in Table
7:
Table 7. Interconnection-Level New Source Complement
Generation (GWh)
Year
Eastern
Interconnection
Western
Interconnection
Texas
Interconnection
2022
-
2,976
-
2023
10,443
10,876
3,864
2024
30,146
17,855
8,133
2025
36,428
22,015
10,107
2026
43,208
25,720
12,714
2027
57,294
31,462
15,945
2028
47,602
32,480
15,814
2029
38,647
33,844
16,200
2030
29,090
34,349
16,537
4. Apportion remaining incremental generation to states on the basis of each state's 2012 share of
the interconnection's affected EGU generation total
The apportionment of interconnection-level new source complement generation to states is performed on
the basis of each state's 2012 adjusted share of the interconnection's 2012 adjusted affected EGU
generation.11 For the purposes of this calculation, states that are in multiple interconnections are assigned
the interconnection that contains the majority of that state's territory. Each state's new source
complement generation share is provided in Table 8 below:12
Table 8. Generation Shares for State-Level Apportionment
State
Interconnection
Share of Interconnection
2012 Affected EGU
Generation13
Alabama
Eastern
5.0%
10	For the year 2022, this procedure yields negative incremental generation results in the Eastern and Texas
Interconnections, because under-construction capacity and the amount of generation growth already represented
in the mass goals would suffice to meet projected load growth in that year. As a result, the new source
complement generation in these instances is assigned a value of zero.
11	The goal rates are calculated based on adjusted 2012 generation data to reflect the impact of significant unit
outages, estimated impact of normalizing hydropower output, and all under construction facilities
12	For full generation data, refer to 'New Source Complements' spreadsheet
13	Values rounded to tenth of a percent; for unrounded values refer to 'New Source Complements' spreadsheet
6

-------
Arkansas
Eastern
2.4%
Arizona
Western
12.5%
California
Western
24.9%
Colorado
Western
10.9%
Connecticut
Eastern
0.8%
Delaware
Eastern
0.5%
Florida
Eastern
10.3%
Lands of the Fort
Mojave Tribe
Western
0.3%
Georgia
Eastern
4.0%
Iowa
Eastern
1.8%
Idaho
Western
0.8%
Illinois
Eastern
4.8%
Indiana
Eastern
5.5%
Kansas
Eastern
1.5%
Kentucky
Eastern
4.4%
Louisiana
Eastern
2.9%
Massachusetts
Eastern
1.3%
Maryland
Eastern
1.0%
Maine
Eastern
0.2%
Michigan
Eastern
3.7%
Minnesota
Eastern
1.7%
Missouri
Eastern
3.9%
Mississippi
Eastern
2.4%
Montana
Western
3.7%
Lands of the Navajo
Nation
Western
7.1%
North Carolina
Eastern
4.1%
North Dakota
Eastern
1.4%
Nebraska
Eastern
1.3%
New Hampshire
Eastern
0.4%
New Jersey
Eastern
1.8%
New Mexico
Western
4.6%
Nevada
Western
6.8%
New York
Eastern
3.1%
Ohio
Eastern
5.6%
Oklahoma
Eastern
3.4%
Oregon
Western
4.0%
Pennsylvania
Eastern
7.4%
Rhode Island
Eastern
0.4%
7

-------
South Carolina
Eastern
2.0%
South Dakota
Eastern
0.3%
Tennessee
Eastern
2.1%
Texas
Texas
100.0%
Lands of the Uintah
and Ouray
Reservation
Western
0.7%
Utah
Western
8.6%
Virginia
Eastern
2.7%
Washington
Western
4.7%
Wisconsin
Eastern
2.1%
West Virginia
Eastern
3.6%
Wyoming
Western
10.4%
The new source complement generation level for a state is defined as:
•	State-level new source complement generation = Interconnection-level new source complement
generation x 2012 state share of interconnection affected EGU generation
•	2030 Alabama new source complement generation = 29,090 GWh x 5.0% = 1,467 GWh
State-level new source complement generation totals are provided for each state in each year in the 'New
Source Complements' spreadsheet.
5. Convert state-level generation to state-level emissions assuming the emissions intensity of the
New Source Performance Standard emission rate for NGCC of 1,030 lbs/MWh
Each state-level new source complement generation level is multiplied by the NSPS NGCC emission rate
standard of 1,030 lbs/MWh to produce a mass value:
•	New source complement = State-level new source complement generation * NSPS NGCC
emission rate standard
•	2030 Alabama new source complement = 1,467 GWh x 1,030 lbs/MWh = 755,700 short tons
New source complements are calculated for each year and each state, from 2022 through 2030. The
interim period new source complement is equal to the average of the annual values from 2022 through
2029. The final period new source complement is equal to the 2030 value. The interim and final period
new source complements are provided in Table 9 below:14
14 Final and interim period new source complements are rounded up to the nearest ton. Total mass values for
each period are available in the 'New Source Complements' spreadsheet, available in the docket.
8

-------
Table 9. Average Annual New Source Complement (Short Tons)
State
Interim Period
Final Period
Alabama
856,524
755,700
Arizona
1,424,998
2,209,446
Arkansas
411,315
362,897
California
2,846,529
4,413,516
Colorado
1,239,916
1,922,478
Connecticut
135,410
119,470
Delaware
78,842
69,561
Florida
1,753,276
1,546,891
Georgia
677,284
597,559
Idaho
94,266
146,158
Illinois
818,349
722,018
Indiana
939,343
828,769
Iowa
298,934
263,745
Kansas
260,683
229,997
Kentucky
752,454
663,880
Louisiana
484,308
427,299
Maine
40,832
36,026
Maryland
170,930
150,809
Massachusetts
225,127
198,626
Michigan
623,651
550,239
Minnesota
286,535
252,806
Mississippi
410,440
362,126
Missouri
668,637
589,929
Montana
421,674
653,801
Nebraska
216,149
190,706
Nevada
770,417
1,194,523
New Hampshire
71,419
63,012
New Jersey
313,526
276,619
New Mexico
527,139
817,323
New York
522,227
460,753
North Carolina
692,091
610,623
North Dakota
245,324
216,446
Ohio
949,997
838,170
Oklahoma
581,051
512,654
Oregon
453,663
703,399
Pennsylvania
1,257,336
1,109,330
9

-------
Rhode Island
70,035
61,791
South Carolina
344,885
304,287
South Dakota
46,513
41,038
Tennessee
358,838
316,598
Texas
5,328,758
8,516,408
Utah
981,947
1,522,500
Virginia
450,039
397,063
Washington
531,761
824,490
West Virginia
602,940
531,966
Wisconsin
364,841
321,895
Wyoming
1,185,554
1,838,190
Lands of the Navajo
Nation
809,562
1,255,217
Lands of the Uintah
and Ouray
Reservation
84,440
130,923
Lands of the Fort
Mojave Tribe
37,162
57,619
10

-------