NIAGARA RIVER
TOXICS MANAGEMENT PLAN (NRTMP)
INTERIM PROGRESS REPORT
AND
WORK PLAN
June 2004
Prepared by:
Donald J. Williams, Environment Canada
and
Marie L. O'Shea, USEPA
FOR THE NIAGARA RIVER SECRETARIAT
¦~I	a epa
Environ went Canada	Uwtecf State
CiwittMrtfiWetii Canada Envirwirrwn
Ontario
New tqi-jc mm
Department of
tfwIiiwiBwnial
Conservation

-------
TABLE OF CONTENTS
PROGRESS REPORT
1.0 INTRODUCTION	1
Change in Reporting and Public Meeting Schedules	1
2.0 STATUS OF THE NIAGARA FROM THE JUNE 2003 PROGRESS REPORT	2
3.0 ADDITIONAL ACTIVITIES	3
Niagara Power Project Re-licensing	3
Contaminated Sediment Assessments in the Niagara River AOC	4
Lyons Creek East Remediation Strategy	5
Retrospective Analysis of Upstream/Downstream Program
Suspended Sediments	6
Published Papers on the Niagara River	6
Sampling the Sir Adam Beck Power Reservoir	6
Seasonality in Contaminant Concentrations in the Niagara River	7
4.0 REFERENCES	8
WORK PLAN	W-1

-------
Niagara River Toxics Management Plan (NRTMP)
Progress Report and Work Plan
June 2004
1.0 INTRODUCTION
The Niagara River flows 60 kilometers or 37 miles from Lake Erie to Lake Ontario. The
River serves as a source for drinking water, fish and wildlife habitat and recreation. It
generates electricity and provides employment to millions of people. Unfortunately, the
River is also the recipient of toxic chemicals that pollute its waters, and prevent us from
fully enjoying its beneficial uses.
In February 1987, Environment Canada (EC), the U. S. Environmental Protection
Agency Region II (USEPA), the Ontario Ministry of the Environment (MOE) and the New
York State Department of Environmental Conservation (NYSDEC) - the "Four Parties" -
- signed the Niagara River Declaration of Intent (DOI). The purpose of the DOI is to
reduce the concentrations of toxic pollutants in the Niagara River.
Eighteen "priority toxics" were specifically targeted for reduction, ten of which were
designated for 50% reduction by 1996 because they were thought to have significant
Niagara River sources. The Niagara River Toxics Management Plan (NRTMP) is the
program designed to achieve these reductions.
The Four Parties re-affirmed their commitment to the NRTMP in a "Letter of Support"
signed in December, 1996. The revised goal, as stated in that letter, is "to reduce toxic
chemical inputs to the Niagara River to achieve ambient water quality that will protect
human health, aquatic life, and wildlife, and while doing so, improve and protect water
quality in Lake Ontario as well".
Change in Reporting and Public Meeting Schedules
In early 2004, the Niagara River Coordination Committee (NRCC) reassessed its
reporting and public meeting commitments. It was decided that a detailed NRTMP
Progress Report would be produced every three years, with the next such report
scheduled for 2006. This decision was made in recognition of the fact that, for various
reasons (e.g., changes in the monitoring frequency of some programs, time required for
data collection, analysis, and review) new information would not necessarily be
available for the NRTMP to report every year. The NRCC also decided that public
meetings would be held every three years with the next public meeting scheduled for
2006 to coincide with the release of the next detailed NRTMP report and the 2006 Lake
Ontario Lakewide Management Plan (LaMP) Biennial report. In the intervening years, a
brief newsletter-style NRTMP report would be prepared to highlight any new significant
findings and accomplishments. Steps will also be taken to ensure that the public has
1

-------
access to web sites where up-to-date information on the NRTMP and Lake Ontario
LaMP can be obtained.
Accordingly, in the absence of new data to report, an abridged version of the Executive
Summary from the detailed 2003 Progress Report has been included to re-iterate,
briefly, the status of the River. A section describing several activities occurring outside
the scope of the NRTMP is included because of their relevance. And finally, the
updated Work Plan has been included.
2.0 STATUS OF THE NIAGARA FROM THE JUNE 2003 PROGRESS REPORT
The primary method for assessing progress under the NRTMP is the
Upstream/Downstream Program. Results from this Program between 1986/1987, when
the Program began, and 2000/2001 have indicated continuing, statistically significant
reductions in the concentrations/loads of most of the "priority toxics" for which there are
data. Reductions have exceeded 70%. For most chemicals, these reductions have
been due to the effectiveness of remedial activities in reducing chemical inputs to the
River from Niagara River sources. For others (e. g., dieldrin) the reductions have been
due to reduced inputs to the River from Lake Erie/upstream. Biomonitoring Program
results corroborated the decreasing trends seen in the Upstream/Downstream data
reflecting continuing improvement in the Niagara River and its tributaries. Both YOY
(Young-of-Year)-fish, and mussel contaminant data also reflected the effectiveness of
remedial activities at hazardous waste sites. However, while the data for most locations
indicated decreasing trends, there were some locations (e. g., upstream Gill Creek,
Cayuga Creek, and downstream of Gratwick Riverside Park) where the data suggested
the new or continuing presence of contaminants. Further monitoring will be needed to
evaluate these locations. The continuing presence of dioxins and furans in the Pettit
Flume cove also needs additional assessment.
Despite the favorable trend described above, the upper 90% confidence interval
ambient water concentration data for many of the NRTMP "priority toxics" exceeded the
strictest, agency water quality standards/criteria at both Fort Erie (FE) and Niagara-on-
the-Lake (NOTL). Exceedences in 1999/2000 and 2000/2001 were due, largely, to
comparing the data to these more stringent standards, rather than significant increases
in the water concentrations of these chemicals in the River.
The 1999/2000 and 2000/2001 data also indicated that the loads of many of the "priority
toxics", particularly the polynuclear aromatic hydrocarbons (PAHs), from Lake Erie to
the Niagara River may be increasing. Future monitoring will confirm if, indeed, this
"trend" continues. This points to the growing importance of Lake Erie as a source of
many of these contaminants to the Niagara River, and ultimately Lake Ontario.
No changes to New York State fish consumption advisories for the Niagara River have
been issued since 1999. Re-testing of several species offish from the upper and lower
Niagara River in 2002 by MOE, however, resulted in the issuance of a mixture of less
2

-------
restrictive and more restrictive fish consumption advisories for some size classes, and
species of fish. Ontario's Ministry of the Environment has prepared a "Guide to the
Guide" pamphlet on fish consumption advisories which Health Canada translated into
twelve languages. This one page explanation helps the various ethnic communities
understand how to interpret and use the information in the Guide to Eating Ontario
Sport Fish (MOE 2003J. A special outreach program which informs children and families
about the Guide has been implemented under Canada's Niagara River Remedial Action
Plan (RAP).
NYSDEC trackdown activities in Two Mile Creek and in the Falls Street Tunnel (FST)
verified the presence of polychlorinated biphenyls (PCBs) in the Creek and PCBs and
polychlorinated dibenzo-dioxins and furans in the FST. Additional trackdown efforts and
control measures, respectively, are planned to address these findings.
Despite the successes to date, and the continued documented improvements in the
Niagara River, more work needs to be done. Biomonitoring Program results provided
evidence of the continuing presence of low level chemical contamination in the River.
Advisories to limit consumption of sportfish caught in the Niagara River still continue
due to contamination by toxic substances. And, inputs from Lake Erie might be
increasing, and becoming increasingly more important for some chemicals, which will
require additional efforts upstream. Much work has been done to define the actions
necessary to assure continued reductions of toxic chemicals in the Niagara River, and
there are substantial commitments to address current concerns as indicated in the Work
Plan accompanying this Report. Trackdown activities such as those noted above are
but one example of these. These commitments include:
•	Completing the actions described in prior NRTMP Work Plans;
•	Ensuring that these actions have been effective;
•	Implementing additional actions to protect and restore the River; and,
•	Continuing and improving the public reporting of progress.
3.0 ADDITIONAL ACTIVITIES
This section describes several additional activities that are either underway, or have
been completed, on the Niagara River. While these activities are outside the scope of
the NRTMP, and are, therefore, not included in its Work Plan, they are nonetheless
relevant.
Niagara Power Project Re-licensing
The New York Power Authority's (NYPA) license to operate the Niagara Power Project
in Lewiston, NY, as required by the U. S. Federal Energy Regulatory Commission
(FERC), will expire in 2007. The NYPA must file an application for a new license by
2005. As part of the re-licensing process, the NYPA must conduct an Environmental
Assessment (EA) that includes the diversion of water in the Niagara River. During the
3

-------
public comment phase of the EA, a number of questions were raised that are now being
investigated. The following questions that are being addressed by the NYPA are of
particular relevance to the NRTMP:
•	Do project operations affect surface water quality?
•	Do project operations affect the transport of groundwater and contaminants?
•	Do project operations result in super-saturation of atmospheric gases in the
Lower Niagara River?
•	Do project operations impact the River's water temperature?
•	Do water level fluctuations in the Lewiston Reservoir increase mercury that is
bioavailable?
•	What is the extent of sedimentation and quality of sediment in the Lewiston
Reservoir and fore bay?
•	What is the ecological condition of Gill, Fish, and Cayuga Creeks?
•	What are the water level and flow fluctuations in the Niagara River and
tributaries? and,
•	What are the contaminant levels in fish in the Lewiston Reservoir?
Further information on these questions is available from the NYPA's website at
http://niagara.nypa.gov. The relevance of any new information to the NRTMP that may
result from NYPA's investigation will be considered by the Four Parties.
Contaminated Sediment Assessments in the Niagara River AOC
The Niagara River has been designated as one of the 41 Areas of Concern (AOCs) in
the Great Lakes Basin because of impaired beneficial uses. Under the Great Lakes
Water Quality Agreement (GLWQA), the Canadian and U.S. federal governments, in
cooperation with the state and provincial governments, were required to develop RAPs
to restore the impaired beneficial uses in these areas. Because the Niagara River is a
bi-national AOC, separate U.S. and Canadian RAPs have been developed.
The Canadian Niagara River RAP identified fourteen locations where contaminated
sediments had the potential to impair beneficial uses. The sites fell into three levels:
Level 1 - Four sites where existing information indicates that concentrations of
contaminants are sufficiently elevated that potential risks exist.
Level 2 - Three sites where existing data suggests lower measured levels of
contaminants of concern but no recent data exists to support
management decisions.
Level 3 - Seven sites considered to pose relatively low environmental
concerns.
Contaminants identified in these areas included heavy metals, PCBs, PAHs and, at one
site (Frenchman's Creek), dioxins and furans.
4

-------
One of the Level 1 sites (Atlas Reef in the Welland River) was remediated in 1995. A
second Level 1 site, Lyons Creek East, is currently the subject of detailed assessment
and remedial planning (see discussion below).
In 2003, an assessment of the remaining twelve sites was initiated. Sampling was
undertaken at each of these sites to determine which, if any, warranted further
assessment and possible remediation. Sites falling into this category will be the subject
of a Phase III study that will take the form of a Ecological Risk Assessment. Sites
requiring further remediation will be identified using measured biological effects
determined through in-situ analysis and lab testing. Based on the outcomes of these
analyses and a risk characterization, recommendations regarding risk management will
be made, including the location and type of appropriate remediation. The project will be
completed in 2005. This project is coordinated by the Niagara Peninsula Conservation
Authority (NPCA) in collaboration with EC and MOE; and, to date funding support has
been provided by EC's Great Lakes Sustainability Fund (GLSF) and MOE under the
2002 Canada-Ontario Agreement (COA).
Lyons Creek East Remediation Strategy
Lyons Creek East is one of the fourteen locations in the Canadian portion of the Niagara
River AOC where contaminated sediments were believed to have the potential to impair
beneficial uses. It was identified in the Stage 1 and Stage 2 Niagara River RAP
documents as one of four Level 1 contaminated sediment sites, meaning that the
sediments in the area required remediation and/or further detailed assessments. The
area is contaminated by PCBs and metals. To date no current or historic source for the
contamination has been identified.
In 2002, a detailed assessment of Lyons Creek East was undertaken that included a
sampling program designed to fill gaps from earlier sampling efforts and address data
needs associated with the development of remediation options for the area. One
component of the sampling program was undertaken by EC utilizing the BEnthic
Assessment of SedimenT (BEAST) methodology that assesses sediment by examining
physio-chemistry, sediment toxicity and benthic community structure. The BEAST
assessment was part of a program conducted by EC in several AOCs, and was
supported by MOE funding under the 2002 COA.
In January 2003, MOE, EC and the NPCA signed a memorandum of understanding
(MOU) regarding a sediment management plan for Lyons Creek East. Under this MOU
the NPCA serves as project coordinator for the initial development phases of the
sediment remediation plan. In fiscal year 2003/2004, activities undertaken as part of
this project included the completion of sampling required to characterize the sediments
and inform subsequent decision making, and the completion of initial components of a
human health risk assessment (HHRA) for the area due to be completed in 2004.
5

-------
In 2004-2005, one or more of the following activities will be undertaken as part of this
project depending on the outcomes of the previous year's work:
•	completion of an assessment of the ecological risks utilizing the proposed
framework for sediment decision making;
•	development and evaluation of remedial options based on the outcomes of the
human health and ecological assessments of the area; and,
•	design of the preferred remedial option.
To date, MOE funding has supported this project as part of the 2002 COA.
Retrospective Analysis of Upstream/Downstream Program Suspended Sediments
Archived suspended sediments from the Niagara River Upstream-Downstream program
were recently catalogued and inventoried. The archive consists of freeze-dried
suspended sediments collected by centrifugation on a weekly, or bi-weekly, basis at
both FE and NOTL over the period 1980-2002. This archive presents a unique
opportunity to assess temporal trends in pollutant concentrations for a wide range of
contaminant classes either not previously analyzed for, or analyzed using analytical
methods that have since been improved upon. The future analyses will
encompass contaminants historically associated with the Niagara River watershed (e.g.,
polychlorinated dibenzodioxins and dibenzofurans), as well as pollutants of new
and emerging concern in the Great Lakes basin, including polybrominated diphenyl
ethers (PBDEs) and other brominated flame retardants. Other compound classes of
interest include PCBs, polychlorinated naphthalenes (PCNs), polychlorinated n-alkanes
and toxaphene. All these analyses will be conducted using recently developed high-
resolution mass spectrometric methods. This project is a collaborative effort between
the Ecosystem Health Division-Ontario Region (EHD-OR) and the National Water
Research Institute (NWRI) of EC, and MOE. The analyses are well underway, and
a complete data set for several contaminant classes is expected by the end of 2004.
Published Papers on the Niagara River
Environment Canada published two papers relevant to the Niagara River in the
December, 2003 issue of the Journal of Great Lakes Research. The first paper
examined the concentration and distribution of nutrients and contaminants in the bottom
sediments of the Canadian, Sir Adam Beck Power Plant reservoir (Williams et al.
2003a). The second paper dealt with the seasonality in contaminant concentrations in
the Niagara River (Williams et al. 2003b). Brief descriptions of these studies and their
results are presented below.
Sampling the Sir Adam Beck Power Reservoir
Surficial bottom sediments (top 3cm) in the Sir Adam Beck Power Reservoir were
sampled in December, 1998 to determine the concentration and distribution of a variety
of physical and chemical parameters including trophic indicators (phosphorus, nitrogen,
6

-------
organic carbon and nitrogen), metals and persistent organic contaminants. Results
were compared to those from a similar survey conducted MOE in 1983 to determine the
changes that had occurred over the intervening fifteen-year period.
Sediment concentrations and spatial distributions of the above parameters were related
to the sediment physical characteristics, which were dictated by reservoir morphometry
and the daily fluctuations in water levels as water is pumped in and out. The highest
phosphorus, metal and organic contaminant concentrations occurred in the deeper
eastern end of the reservoir. All of the metals, with the exception of lead and zinc at
some stations, exceeded their Provincial Sediment Quality Guideline (Persaud et al.
1993) lowest effect levels (LEL, the level of sediment total metal contamination that can
be tolerated by the majority of benthic organisms). The concentrations of all organic
contaminants, except DDD and DDE, were well below their respective LELs. Of
particular interest, was the 65% decrease in the overall mean concentration of p,p'-DDT
from 10.4 ng/g to 3.5 ng/g between 1983 and 1998 suggesting a decrease in parent
DDT input to the reservoir.
Overall, results from the work indicated that reservoir sediment metal concentrations
were not significantly different from those seen in the rest of the Lake Erie basin, and
that the concentrations of organic contaminants were extremely low. The Sir Adam
Beck Reservoir does not appear to be a major source of contaminants to the River.
Seasonality in Contaminant Concentrations in the Niagara River
Seasonal variation has been observed in both the dissolved and particulate phase
concentrations of many of the organic contaminants measured in the Niagara River over
the period 1986 to 2001. The different seasonal patterns were attributed to three
factors: (1) the temperature dependent exchange of contaminants across the air/water
interface; (2) the seasonal nature of specific activities such as the application of
agricultural insecticides and herbicides, and residential heating; and (3) the seasonal
variation in suspended particulate material (SPM) quantity and composition and its
effect on the particulate phase concentrations of contaminants. The contribution of
these factors to the observed seasonality in contaminant concentrations were illustrated
by four examples (a-HCH, a-endosulfan, acenaphthylene, PCB) discussed in the paper.
The seasonal patterns seen in the River were generally consistent with those seen for
the same contaminants in Lakes Erie and Ontario over the period 1992 to 1995.
Results suggested that the evaluation of contaminant concentrations, cycling and trends
based on once a year samples from the Great Lakes water column should be
questioned. This is a significant issue given its widespread practice. Year-round
sampling of Connecting Channels water may be, in general, a useful alternative to
temporal lake sampling for several reasons. Not the least of these would be ease of
obtaining relatively cheap (compared to vessel costs) year-round data. For lakes, year-
round sampling is pre-empted by winter conditions and the unavailability of ship time.
The trade-off would be foregoing information on the within-lake spatial variability in
contaminant concentrations.
7

-------
4.0 REFERENCES
MOE. 2003. Guide to Eating Ontario Sport Fish, 2003-2004. Ontario Ministry of the
Environment, Toronto, Ontario.
Persaud, D., Jaagumagi, R., and Hayton, A. 1993. Guidelines for the Protection and
Management of Aquatic Sediment Quality in Ontario. Ontario Ministry of the
Environment, Toronto, Ontario.
Williams, D.J., McCrea, R.C., and Sverko, Ed. 2003a. The Bottom Sediments of the Sir
Adam Beck Reservoir, Niagara River, Ontario. J. Great Lakes Res. 29(4):630-640.
Williams, D.J., Kuntz, K.W., and Sverko, Ed. 2003b. Seasonality in Contaminant
Concentrations in the Niagara River. J. Great Lakes Res. 29(4):594-607.
8

-------
NIAGARA RIVER TOXICS MANAGEMENT PLAN (NRTMP) ANNUAL WORK PLAN [2004]
The Four Parties: EPA	= United States Environmental Protection Agency
DEC	= New York State Department of Environmental Conservation
EC	= Environment Canada
MOE	= Ontario Ministry of the Environment


E
D
E
M
COMMITMENTS


ACTIVITY AND COMMENTS
P
A
E
C
c
0
E
2003
2004
STATUS
Controlling Point Sources
A.
Report on U.S. Point Sources

X


Periodically
Periodically
Ongoing; regulatory monitoring and
reporting of all regulated facilities in
the Niagara River basin for
compliance with State Pollutant
Discharge Elimination System
(SPDES) permits will continue.
B.
Report on Canadian Point Sources



X


Ongoing; regulatory monitoring and
reporting of Ontario point sources
as required by Certificates of
Approval and Clean Water
regulations will continue.
C.
Report on actions to further address U.S. point sources
discharging NRTMP Priority Toxics.
X
X


Update in
2003
Annual
updates
Ongoing; Permit reviews and
revision occur routinely according
to programmatic schedules.
Nonregulatory and innovative
voluntary pollution prevention
activities have been implemented
locally by DEC, Erie and Niagara
counties, and various non-
governmental organizations.
W-1

-------
ACTIVITY AND COMMENTS
E
P
A
D
E
C
O m
M
0
E
COMMITMENTS
2003 2004
STATUS
Controlling Non-Point Sources
A.
Waste sites/landfills
1. Update progress report on remediation of U. S.
hazardous waste sites. [Progress at most
significant sites summarized below]
X
X


June 2003
June 2004
Completed
2. Remediate Occidental Chemical-Buffalo Ave
a. Biomonitor effectiveness using caged mussels

X

X
2003
2006
Completed
Last deployment in 2003; next
scheduled for 2006
3. Remediate 102nd Street
a. Biomonitor effectiveness using caged mussels
X


X
2003
2006
Completed
Last deployment in 2003; next
scheduled for 2006
4. Remediate DuPont, Necco Park site
a.	Start construction of final site remedy
b.	Complete Final Remedy
X
X



Nov 2005
Nov 2005
Ongoing
Ongoing
5. Remediate Occidental Chemical, S-Area
a.	Optimize well pumping rates to prevent
contaminated groundwater from leaving site.
b.	Biomonitor effectiveness using caged mussels
X
X


X
2004
2003
2004
2006
Completed
Evaluation and adjustments to
optimize performance underway
Last deployment in 2003; next
scheduled for 2006
6. Remediate Solvent Chemical Site
a. Begin performance monitoring

X
X


2003
2004
Completed
Scheduled to begin in 2004.
7. Remediate Olin plant site
a. Biomonitor effectiveness using caged mussels
X
X

X
2003
2006
Completed
Last deployment in 2003; next
scheduled for 2006
8. Remediate Gratwick Riverside Park site
a. Biomonitor effectiveness using caged mussels

X

X
2003
2006
Completed
Last deployment in 2003; next
scheduled for 2006.
W-2

-------
ACTIVITY AND COMMENTS
E
P
A
D
E
C
o m
M
0
E
COMMITMENTS
2003 2004
STATUS

9. Remediate Hyde Park Site
a.	Conduct annual survey of gorge-face seeps
b.	Conduct ecological risk screening of
contamination at mouth of Bloody Run Creek
c.	Biomonitor effectiveness using caged mussels
XXX


X
June 2003
July 2003
Dec 2003
2003
July 2004
Dec 2004
2006
Completed
Ongoing
See comments
Samples from 2003 deployment
lost; next survey scheduled for
2006.

Comments: Site construction was completed in June 2003 with all overburden groundwater being contained. EPA will issue a Remedial
Action Report in September 2004 which will document all the remedial actions taken at the site. Annual gorge face seep surveying
continues to indicate no need for additional control or remediation of the area. Biomonitoring data from 2000 showed that concentrations of
dioxins and furans in mussels at the mouth of Bloody Run Creek were lower than concentrations detected in 1994, 1995 and 1997. However,
calculated TEQs were still considered high based on samples collected at uncontaminated sites. Samples from the 2003 biomonitoring
survey were lost due to vandalism. Risk screening of this contamination by EPA indicated human health risk to be within its acceptable risk
range. EPA will complete an ecological risk screening by December 2004.

10. Remediate Buffalo Color Corporation site
a.	Complete site investigation
b.	Select site remedy
c.	Implement site remedy

XXX


Aug 2003
July 2004
July 2004
Mar 2005
Completed
See comments
See comments

Comments:. Public notice and implementation of the final remedy has been delayed due to BCC's Chapter 11 Bankruptcy filing in Oct 2002.
Buffalo Color and Honeywell, a PRP, have recently come to an agreement regarding financial arrangements for implementation of the
remedial measures. These agreements have been approved by the Bankruptcy Court. DEC is currently negotiating a Consent Order with
Honeywell to implement the remedy. An Request for Proposal for remedy design and construction was issued. The remedial system is
expected to be installed during 2004. The overall schedule for corrective action is dependant on these actions as well as on field conditions
required.
W-3

-------
ACTIVITY AND COMMENTS
E
P
A
D
E
C
o m
M
0
E
COMMITMENTS
2003 2004
STATUS

11. Remediate Bethlehem Steel site
a.	Complete site investigation
b.	Select site remedy
c.	Begin implementation of site remedy
XX X
XX X


Dec 2003
Oct 2005
Mar 2007
Dec 2004
Apr 2006
Nov 2007
Due to delays caused by several
problems, the proposed schedule,
and all target dates, were
extended. In 2003 the Integrated
Steel Group (ISG) acquired the
BSC Lackawana site. DEC is
currently negotiating a correction
action order with ISG.

12. Remediate Occidental Chemical Durez - North
Tonawanda site








a. Complete construction of site remedy

X


-
-
Completed

b. Assess contamination in Pettit Flume Cove

X


-
-
See comments

c. Biomonitor effectiveness using caged mussels



X
2003
2006
Last deployment conducted in
2003; next scheduled for 2006.

Comments: The July 2000 mussel biomonitoring study again detected high concentrations of dioxins and furans in deployed mussels and
sediment collected from Pettit Flume. Additional assessment of Pettit Flume Cove will be done in conjunction with OCC's long-term
operation, maintenance and monitoring plan, as well as MOE's ongoing biomonitoring program.

13. Determine whether trace amounts of contaminants
of concern found at 5 landfills are moving to
groundwater off-site


X
X
Ongoing
Ongoing
Ongoing; groundwater monitoring
at these sites has shown that
contaminants are not moving to the
groundwater and off-site. Further
assessment is not required at this
time; however, regulatory
monitoring and reporting of these
non-point sources as required by
certificates of approval will
continue.
B.
Contaminated Sediments

Update NY Great Lake Contaminated Sediment
Inventory

X


Annually
Annually
Update completed for 2003 and
submitted to EPA.
W-4

-------
ACTIVITY AND COMMENTS
E
P
A
D
E
C
O m
M
0
E
COMMITMENTS
2003 2004
STATUS
Monitoring
A.
Complete report on results of Upstream/Downstream
sampling
X
X
X
X
"
"
1999/00 and 2000/01 report
anticipated by December 2004
B.
Collect juvenile spottail shiners or other juvenile fish and
analyze for toxic chemicals, according to Monitoring
Plan

X

X
See
comments
2004
Ongoing.

Comments: In the fall of 2002 and 2003 MOE collected juvenile fish on both the Canadian and US sides of the Niagara River. In 2003,
DEC sampled YOY fish from three locations in the Niagara River (Strawberry Island, Little Niagara River, and Lewiston) and is awaiting
laboratory results.
C.
Track down toxic chemicals in tributaries and sewer
systems to identify sources
X
X


Annual
updates
Annual
updates
See comments

1. Perform post-remediation sediment sampling of
Gill Creek

X


2003
2004
See comments

2. Perform follow-up trackdown-related sampling
in Two-Mile Creek

X


2003
2004
See comments

3. Perform sediment sampling in Cayuga Creek
and Little Niagara River

X


2003
2004
See comments

4. Perform sediment sampling in Scajaquada Creek

X



2005
See comments

Comments: DEC and EPA are working cooperatively to oversee the implementation of New York State Great Lakes basin source trackdown
work, including Lake Ontario, Lake Erie, and the Niagara River. Through DEC/EPA's assessment of past data collected in the Niagara River
and U.S. tributaries, several priority areas were identified for follow-up monitoring and are scheduled for track-down and/or post-remediation
sampling in 2004 by DEC. Additional trackdown-related sampling may be funded through the Great Lakes National Program Office's FY
2004-2005 Request for Proposals.
D.
Biomonitor using caged mussels and analyze for toxic
chemicals, according to Monitoring Plan.



X
2003
2006
Last deployment conducted in
2003; next deployment scheduled
for 2006.
E.
Study use of zebra and quagga mussels as biomonitors.



X
2002
2003
Journal article summarizing results
submitted to J. of Env. Toxicology
and Chemistry. Data collected in
2003 for 2nd study to compare with
1995 results.
W-5

-------
ACTIVITY AND COMMENTS
E
P
A
D
E
C
O m
M
0
E
COMMITMENTS
2003 2004
STATUS
F.
Assess sport fishery in Niagara River, with contaminant
analysis.

X

X
2002
2003
2004-2005 Guide to Eating Ontario
Sport Fish released in March 2004.
MOE collections from Niagara
River completed in fall of 2003;
next field collection scheduled for
2004. NYS DOH's Health
Advisories: Chemicals in Game
and Sportfish issued annually.
G.
Collect sample of Falls Street Tunnel (FST) wet weather
discharge and analyze for NRTMP priority chemicals
using techniques to achieve low detection levels.

X




Completed; SPDES permit
covering FST discharges was
modified to include additional CSO
controls in June 2003.
H
Develop plans for additional assessment of low-level
contaminant discharges from Niagara River point
sources.
X
X


Annual
updates
Annual
updates
See comments

Comments: DEC/EPA's 1999 assessment of recent available information on toxic contaminant discharges from Niagara River point sources
indicate the need for additional assessment of low-level contaminant discharges from point sources in the Niagara River. The purpose would
be to help determine additional priorities for control of contaminant discharges from point sources. EPA sampling of these point sources is
awaiting the availability of laboratory capacity.
Define Additional Actions to Reduce Toxic Chemical Inputs to the Niagara River
A.
Develop additional materials relating information on
Niagara River contamination and contaminant sources,
and incorporate into NRTMP Progress Report and Work
Plan
X
X
X
X
Update in
2003
Annual
updates as
necessary
See comments

Comments: DEC/EPA have completed three synthesis assessments, utilizing a variety of data sources to address: ambient toxic
concentrations, and the significance of Niagara River sources; point sources of toxics; and characterization of toxic contaminants in
sediments, biota and water of the Niagara River and its tributaries. Information and recommended actions from this synthesis effort were
included in the 2001 Progress Report. DEC/EPA will continue to report on the results of synthesis-related efforts as available.
W-6

-------
ACTIVITY AND COMMENTS
E
P
A
D
E
C
O m
M
0
E
COMMITMENTS
2003 2004
STATUS
B.
Develop plans addressing water-quality limiting
chemicals.
X
X


Beginning
2002
"
See comments

Comments: A DEC/EPA assessment of water quality in the Niagara River indicates exceedences of New York water quality standards for
some NRTMP Priority Toxic Chemicals. Niagara River waters and tributaries have previously appeared on New York's annual list of water
quality-impaired waters (i.e. the Clean Water Act Section 303(d) list) due to water quality standard exceedences of PCBs, dioxin, and mi rex.
In 2002, the Niagara River was additionally listed under Part 3 the 303(d) list (Waters Previously Listed But Requiring Re-Assessment Based
on New Methodology) due to potential exceedences of most stringent applicable NYS standards for the following PAHs: benzo(a)pyrene,
chrysene, benzo(b/k)fluoranthene, and indeno( 123-cd)pyrene. Total Maximum Daily Loads/Wasteload Allocations/Load Allocations
(TMDLs/WLAs/LAs) may be developed, as necessary, for waters on the 303(d) list. The 2004 303(d) list is currently under development.
Since monitoring data suggest several of these exceedences can be attributed to Lake Erie sources, DEC and EPA have communicated
their priorities to the Lake Erie Lakewide Management Plan committee to ensure that their future strategy to address toxic contamination in
Lake Erie be consistent with, and incorporate NRTMP concerns.
Public Involvement
A.
Develop a reader-friendly brochure that gives an
overview of the NRTMP and summarizes progress
made on restoring the Niagara River.
X
X
X
X


Completed
B.
Present remediation progress for U.S. hazardous waste
sites at a public meeting in Niagara Falls.
X
X
X
X
2003
2006
Progress on U.S. hazardous waste
site remediation will be
summarized in the next scheduled
NRTMP/LO LaMP annual public
meeting in 2006.
C.
Make NRTMP information and reports available on the
Internet. Develop a NRTMP web page.
X
X
X
X
As available
As available
See comments

Comments: Summaries of recent Four Party Upstream/Downstream Reports can be found on the GLIMR web site at
http://www.on.ec.gc.ca/glimr/search.html (search "joint evaluation"). U.S. wastesite reports (Reduction of Toxics Loadings to the Niagara
River from Hazardous Waste Sites in the United States) from 1998 and NRTMP progress reports are at
http://www.epa.gov/grtlakes/lakeont/nrtmp. Additional reports will be added as they become available.
D.
Produce a progress report on the condition of the
Niagara River and NRTMP efforts to restore the river.
Update annual work plan for future actions
X
X
X
X
June 2003
June 2004
Last full report released in 2003,
next scheduled for 2006; interim
reports due in 2004 and 2005.
W-7

-------

E
D
E
M
COMMITMENTS

ACTIVITY AND COMMENTS
P
E
C
0
2003
2004
STATUS

A
C

E



E.
Hold a public meeting to present above progress and
X
X
X
X
June 2003
June 2006
See comments

updated annual work plan








Comments: The next NRTMP public meeting is scheduled for 2006, to coincide with the next scheduled full NRTMP report.
W-8

-------