SEPA
United States
Environmental Protection
Agency
U.S. Environmental Protection Agency (EPA)
W.R.G race (Acton Plant) Superfund Site
Community Update
EPA Superfund Community Involvement

July 2009
This community update provides you with information on the activities ongoing at the W.R, Grace Superfund site in Concord & Acton MA.
Northeast Area Remedial
Action Activities
The Northeast Area Groundwater Concept
Design has been reviewed and conditionally
approved by the United States Environmen-
tal Protection Agency (USEPA) and the Mas-
sachusetts Department of Environmental
Protection (MassDEP) with input from key
stakeholders from the Town of Acton, the
Acton Water District and the Acton Citi-
zens for Environmental Safety.The Concept
Design, which is the engineering plans for
the treatment system, includes installation
of up to 3 groundwater extraction wells and
2 reinjection wells as well as a groundwater
treatment system.This work will occur on
Linde Inc. property (formerly known as
BOC Gases) as shown on Figure I .The ba-
sic layout of the extraction, reinjection and
treatment system components is shown on
Figure 2 and will be housed in an enclosed
structure.
The Northeast Area treatment system will
extract and treat contaminated groundwa-
ter focusing on the area of highestVinylidene
Chloride (VDC) concentrations as required
by the 2005 EPA Record of Decision (ROD).
The ROD documented the final site areas
that need to be cleaned up and the ap-
propriate clean up leveis.Treatment of the
extracted groundwater will include air strip-
ping for volatile organic compound (VOC)
removal and a filter for arsenic removal.The
treated water will be re-injected back into
the groundwater in the Northeast Area,
Overall Site Status
In 1984,W. R. Grace installed a groundwater
extraction, treatment and discharge system
know as the Aquifer Restoration System
(ARS). From 1985 until 2008, the ARS has
removed approximately 5,936 pounds of
totalVOC's and pumped over 4,787 million
of gallons of groundwater.
Between 1994 and 1997, approximately
177,000 cubic yards of contaminated soil
and sludge from the former lagoons were
treated and placed on the existing Industrial

"Uv,
Northwest view ofWR Grace (Acton Plant) site from atop the Industrial Landfill
Landfill and the landfill was capped. Between
1997 and 2005, investigations were com-
pleted to define the extent of any remaining
groundwater, sediment and surface water
contamination at the Site.
From early 2007 to the present,W. R. Grace
and their consultants gathered additional
site data and prepared various reports for
the engineering design(s) of the final cleanup
activities at the site.The additional site work
also included installing, sampling and testing
of additional extraction wells and various
monitoring wells both north and south of
the MBTA rail line.W.R.Grace also obtained
additional sediment samples, and character-
ized ecological habitats and wetland char-
acteristics from both Sinking Pond and the
North Lagoon Wetland. W.R.Grace intends
to begin installation of a test extraction and
injection well in the Northeast Area of this site
in June of 2009,These test wells will be used
to complete the final design of the Northeast
Area groundwater extraction, treatment and
reinjection system for this area.
Landfill Area Groundwater Treat-
ment System
In addition to the Northeast Area ground-
water design plan,W. R. Grace is also pre-
paring a separate design plan for the new
groundwater extraction treatment and sur-
face water discharge system for the landfill
area on the Grace property. It is expected
that the Landfill Area Groundwater Concept
Design will be submitted to EPA, MassDEP
and the stakeholders in September 2009.
This second groundwater treatment system
will remove metals and VOC's from the
contaminated groundwater at the former
Industrial Landfill Area.This new treatment
system will be located on the W.R. Grace
property, south of the MBTA rail line.
Acton Water District (AWD)
The Acton Water District continues to op-
erate and maintain air strippers to remove
any volatile organic compounds which may
be present in groundwater pumped from
the Assabet I .Assabet 2'2A,and the School
continued on page 2 >
SDMS DocID 457595

-------
ristofferson 0
/ Scribner,
Area of 2009 ^
Remediatiog^
Activities^ / ,
LINDE PROPERTY
(FORMERLY BOC
@ASES>' ^

		-"t. = • J"
pnrcTr^
/ Hi
' H

Explanation
ACTON WATER DISTRICT
PUBLIC SUPPLY WELL
	APPROXIMATE
PROPERTY BOUNDARY
Figure 1 - Location of Northeast Area Remediation Activities, 2009 / 2010
	W.R. Grace (Acton Plant) Superfund Site	

-------
APPROXIMATE AREA TO BE
CLEARED (0.24 ACRES)
UTILITY TRENCH FOR
TREATMENT SYSTCM
TREATMENT
BUILDING-i
©
MW-5S
EXPLANATION
	 UNDE PROPERTY BOUNDARY
(APPROXIMATE)
MW-06 © MONITORING mi
(SINGLE OR CLUSTER)
NE-t	PROPOSED EXTRACTION WEI1
RE-1	PROPOSED REINJECT10N WELL
d I
UTIUTY POLE
EXISTING
OVERHEAD
UTILITIES
EXISTING
UNDERGROUND
UTILITIES APPROX. 3
FT. FROM PAVEMENT
(WATER 4 ELECTRIC)
©
MW-49
EXISTING FENCE
J
Figure 2 - Northeast Area with Treatment System Location

-------
ALL LOCATIONS ARE APPROXIMATE
Christoffenson 0
-N-
Lawsbrook
Scrlbner
)
M
LINDE PROPERTY /
--vr
, ,®XA Rail Line


£ I
W.R. GRACE PROPERTY
BOUNDARY
\ INDUSTRIAL
LANDFILL
\f
WRG-3
(Proposed)

Assabet 1
1,000
Scale m feet
Approximate
EXPLANATION
		 — W.R. GRACE PROPERTY BOUNDARY
# PUBUC WATER SUPPLY WELL
FORMER WASTEWATER LAGOON
APPROXIMATE DIRECTION OF
GROUNDWATER FLOW PRIOR TO
OPERATION OF ARS
VDC CONCENTRATION 2008
~j 201 - 560 ugA VDC
| 101-200 ug/L VDC
61-100 ugA VDC
n 31-60 ug/L VDC
7-30 ugA VDC
SAMPLES COLLECTED BETWEEN AUG 13 AND NOV, 5, 2008
VDC CONCENTRATIONS SHOWN ARE MAXIMUM REGARDLESS
OF DEPTH. CONCENTRATION BOUNDARIES ARE
APPROXIMATE.
VDC = MNYUDENE CHLORIDE = 1.1-lXCHLOROETHENE
Figure 3 - Distribution of VDC in Groundwater, 2008

-------
Street we!l field (Christofferson.Lawsbrook,
and Scribrter wells). Low concentrations of
several VOCs have been detected in un-
treated raw water samples from these wells
prior to treatment. The treatment system
for the School Street and AssabetWel! fields
removes any VOC's that are present in the
untreated raw water in these areas. Water
delivered to customers is sampled quar-
terly to ensure the treated water meets or
exceeds all state, federal and Acton Water
District safe drinking water standards.
Current Extent of Groundwater
Contamination
The nature and extent of contaminated
groundwater at the Site has been defined
and documented in the 2005 Public Re-
view Draft Remedial Investigation Report.
Figure 3 depicts the current extent and
concentrations of vinylidene chloride (VDC
or I, I-dichloroethene). VDC is the most
widespread contaminant at the site. As of
2008,VDC levels in groundwater at the site
ranged from less then 7 to S50 parts per
billion.The maximum contaminant level that
EPA considers safe forVDC in groundwater
is 7 parts per billion. Figure 3 shows the
maximum VDC concentrations regardless
of depth, as of fell of 2008.
Northeast Area Schedule
installation of the Northeast Area treatment
system is expected to occur between June
2009 and October 2009, Monday through
Friday during normal business hours. After
being field tested, the North east Area system
wilt operate for a period of approximately
3 to 5 years. Prior to giving final approval,
EPA and MassDEP will review the data from
the system operations and confer with the
local stakeholder's before the Northeast
Area system can be shut down.
History of Site Operations
The W.R. Grace Superfund site located off
Independence Road in South Acton has been
used for industrial purposes since the 1800s.
After purchasing the property in 1954,W.R,
Grace & Co. (Grace) produced a variety of
latex and rubber-based products as well
as cellulose battery separators.The waste
products from these manufacturing opera-
tions were disposed of on-site in unlined
lagoons. In 1980, all on-site waste disposal
operations at the facility ceased. In early
1982,Grace discontinued its organic chemi-
cal operations at the South Acton site which
generated the bulk of the site wastes.
How We Got Here
Record of Decision and Statement
of Work
On September 30, 2005, EPA, with concur-
rence from the MassDEP,selected and docu-
mented the third and final cleanup plan for
the Site in a Record of Decision (ROD).The
ROD addresses clean-up of contaminated
groundwater, sediment and soil in Sinking
Pond and the North Lagoon Wetlands that
pose a potential unacceptable risk to human
health and/or the environment.
Details of the ROD can be found at:
www.epa.gov/regionO I /superfund/sites/
graceacton/237033.pdf
In August 2006, EPA, MassDEP and W. R.
Grace entered into a legally binding agree-
ment known as the remedial design/reme-
dial action Scope ofWork (SOW), under a
Consent Decree previously approved by
the court. The SOW, which was finalized
in August 2006, outlines the framework
for the final cleanup activities and includes
schedules, engineering designs and construc-
tion requirements that Grace must fulfill in
order to complete the final cleanup actions
at the site.
More specific details of the SOW may be
found at: www.epa.gov/regionl/superfund/
sites/graceacton/256924.pdf
Contacts:
EPA Contacts:
Derrick Golden
USEPA New England, Region I
Remedial Project Manager
617-918-1448
golden.derrick@epa.gov
Sarah White
USEPA New England, Region I
Community Involvement Coordinator
617-918-1026
white.sarah@epa.gov
State Contacts:
Jennifer McWeeney - MassDEP
Project Manager
617-654-6560
Jennifer.Mcweeney@state.ma.us
Acton Contacts:
Doug Halley
Acton Board of Health
Health Director
978-264-9634
dhalley@town.acton.ma.us
Matthew Mostoller
Acton Water District (AWD)
Environmental Compliance Manager
978-263-9107
Matt@actonwater.com
Mary Michelman
Acton Citizens for Environmental
Safety (ACES)
978-263-7370
msmichelman@comcast.net
United States
Environmental Protection
M * Agency

-------