REDUCTION OF
TOXICS LOADINGS TO
THE NIAGARA RIVER FROM
HAZARDOUS WASTE SITES
IN THE UNITED STATES:
JUNE 2004
A Report by the United States Environmental Protection Agency
and the New York State Department of Environmental Conservation
JUNE 2004
-------
-------
TABLE OF CONTENTS
Executive Summary
Introduction 1
Summary of Remediation Progress 8
Overview of Remediation Status 8
Highlights of Recent Actions 8
Estimated Remediation Costs 14
Acronyms 16
Glossary 17
References 22
Appendix: Priority Niagara River Hazardous Waste Sites:
Site Descriptions & Remediation Schedules
Occidental Chemical — Buffalo Avenue A-l
Niagara County Refuse Disposal A-7
DuPontNecco Park A-10
CECOS International A-14
Occidental Chemical — Hyde Park A-18
102nd Street A-25
Bell Aerospace Textron A-28
Durez Corporation, Packard Road Facility, Niagara Falls
(formerly Occidental Chemical — Durez Division, Niagara Falls) A-31
Occidental Chemical S-Area A-34
Stauffer Chemical A-39
Solvent Chemical A-41
Vanadium Corporation of America (formerly SKW Alloys) A-43
Olin Corporation A-46
DuPont — Buffalo Avenue A-50
Buffalo Color Corporation A-52
Buffalo Color Corporation — Area D A-56
Bethlehem Steel Corporation A-58
River Road (INS Equipment) A-61
Niagara Mohawk — Cherry Farm A-63
Frontier Chemical, Pendleton A-65
Frontier Chemical, Royal Avenue A-67
Occidental Chemical — Durez Division, North Tonawanda A-70
Gratwick Riverside Park A-72
Mobil Oil A-75
Iroquois Gas — Westwood Pharmaceutical A-78
Booth Oil A-81
-------
-------
EXECUTIVE SUMMARY
Since 1987, the Niagara River has been the focus of attention for four environmental agencies in
the United States and Canada ("The Four Parties"). In a Declaration of Intent, the Four Parties
committed to reducing toxic chemical inputs to the Niagara River. Hazardous waste sites were
considered the most significant non-point source of toxics to the river. Therefore, the U.S.
Environmental Protection Agency (EPA) and New York State Department of Environmental
Conservation (DEC) identified 26 U.S. sites responsible for over 99% of the estimated input
from all such sites on the U.S. side of the basin, and put them on ambitious remediation
schedules. Remediation of the sites is intended to virtually eliminate the migration of toxic
pollutants from the sites.
All remedial construction has been
completed at 20 of the sites. The remedial
technology will be operated and monitored
for effectiveness for years to come at those
sites. Remedial Actions (RAs) are underway
at 4 sites. All 4 of these sites are interim
remedies, including 3 sites that are under
interim remediation with significant
remedial controls already operating while
final remedies are being designed or
investigated. For many of these sites, the
load reductions are substantial. Remedial
Actions for the remaining two sites are under
design or study.
Based on various simplifying assumptions,
EPA estimates that remediations to date have
reduced the potential inputs into the river by
approximately 93% This estimate is based
primarily on the sites where the final RA is
completed. It does not include the load
reductions at all the sites where remedial
controls are operating, though the reductions
may be substantial. Therefore, the actual
reductions to date may exceed 93%.
Recent accomplishments include the
following:
Rl Ml DIATION <>l I .S. IIX/.XUIXH S\\ASTT. SlTKS
20si i i:s aki. comi'i.i i i:d:
( L( OS (Niagara falls)
liell Aerospace 'fcMron (Niagara kills)
Dure/. ( nip . PiickiiI'd Ril (Niagara kills)
Sl;iulid" (hemieal (l.exxislon)
DuPonl liul'l'alo Axe (Niagara kills)
frontier ( hemieal (Peiiillelon)
Occidental ("licin Dure/. (North Tonaxxanila)
()lin ( orporalion (Niagara kills)
liul'l'alo Color Area I.) (liul'l'alo)
Occidental (hern. I5iillalo Axe (Niagara kills)
I'i2ikI Street (\uiLiai'Li kills)
Ri\ ci" Roail ( I"onaw anda)
Niagara \lohaxxk ( lierrx kinn ( lunawanda)
\i;uj;im Cnunl\ Refuse Disposal (\Yheal Held)
lroi|uois (ins-\\eslwood Pluuniae (IJuffnlo)
(ii'iilwiek Rixerskle Park (\orlh ToiuixwiikUi)
Oceklenlnl ( hemieal S-.\re;i (\laLiara kills)
Sol\enl ( hemieal (Niagara l-'iills)
lioolli Oil
Oeeklenul ( hem I Kile Park (Niagara falls)
4 SI I I.SNMII.KI. KKMI.DIA I ION IS I NDI.IUVU :
DuPonl \eeeo Park (Niagara falls)
Moliil Oil (liuflalo)
fronlier ( hemieal Ro\al Axe (Niagara falls)
Vanadium ('or|ioralion (Niagara)
Occidental Chemical Corporation (OCC), S-Area - The construction of the final OCC S-area
landfill cap commenced in August 2000 and was completed in March 2002. The securement of
the Drinking Water Treatment Plant intake structures, including the grouting of the 5,000-foot
long bedrock intake tunnel, commenced in summer 2000 and was completed in August 2002.
l
-------
Construction activities for the site are completed. Evaluation and adjustments of the remedial
systems are presently being performed. System efficiency is being adjusted for optimal
performance.
Solvent Chemical - Construction of the groundwater extraction and treatment systems were
completed in 2001 and became fully operational in December 2002. Performance monitoring is
scheduled to begin in 2004.
Booth Oil - After lengthy negotiations between the DEC and the Booth Oil Site Administrative
Group (BOSAG), a group of potentially responsible parties, a final agreement for site
remediation was reached. An Amended Record of Decision (AROD) was issued in August of
2002. The AROD permitted offsite disposal of contaminated media in lieu of onsite treatment.
Approval of the final Remedial Design and execution of the consent order was completed in
March 2003. Construction to implement the remedy selected in the AROD began in July 2003
and was completed substantially in December 2003.
Occidental Chemical Corporation, Hyde Park - Remedial construction at the site was
completed in June 2003. EPA issued a Preliminary Close-out Report (6/03) documenting the
construction completion. EPA will issue a Remedial Action Report in September 2004 which
will document all the remedial actions taken at the site.
Through 2005, completion of RAs is expected at the following two sites:
DuPont, Necco Park - RA completion is expected by November 2005. Because of the
fractured bedrock beneath the site, future complications may arise in achieving effective
hydraulic containment. The target date is intended to allow time to ensure the completion of any
additional remedial work required to achieve effective containment. It is also important to note
that remedial actions already implemented on-Site have resulted in an estimated load reduction
from the Site of approximately 27-55%.
Buffalo Color Corporation (BCC) - The Corrective Measures Study (CMS) was approved in
July 2000. The remedy selection was expected to be finalized in May 2002, with Corrective
Measures Implementation (CMI) start-up expected in March 2003. However, in October of
2002, BCC filed for Chapter 11 Bankruptcy protection. Honeywell Corporation, a successor to
Allied Chemical and a potentially responsible party, and BCC have recently reached an
agreement for implementation of the corrective measures. The DEC is currently negotiating a
Consent Order with Honeywell to implement the remedy. An RFP (Request for Proposal) for
remedy design and construction was issued by Honeywell during 2003. The remedial design is
expected to be completed during 2004.
Estimates of the cost of remediation are available for most of the 26 priority hazardous waste
sites. Based on these estimates, the costs incurred to date are at least $ 393,550,000. Additional
costs expected in the future are estimated at $ 261,450,000.
11
-------
INTRODUCTION
Tin- Four Parties
U.S. Environmental Protection Agency (EPA)
Environment Canada (EC)
NY State Ditioi Environmental Conservation (DEC)
Ontario Ministry or Environment (MOE)
Since 1987, the Niagara River has
been the focus of attention for four
environmental agencies in the
U.S. and Canada, called "The
Four Parties". The Four Parties
signed a Niagara River
Declaration of Intent, pledging
cooperation to achieve significant reductions of toxic chemical pollutants in the Niagara River.
The Declaration of Intent and a work plan form the Niagara River Toxics Management Plan
(NRTMP).
Under the NRTMP, the Four Parties identified 18 persistent toxic chemicals as "priority toxics".
Actions to reduce the inputs of these priority toxics to the Niagara River have been aimed at
point sources and non-point sources. Significant
point sources on both sides of the Niagara River
have been identified and are being addressed in
U.S. and Canadian point source plans. The Four
Parties summarize progress in controlling point
sources in an annual report, last issued in June
2000 (Niagara River Secretariat, 2000).
Non-point sources of toxic chemicals to the
Niagara River (e.g., leachate from hazardous
waste sites, storm water runoff, atmospheric
deposition) are more difficult to quantify and
control. Given the limited information available
about non-point sources, the U.S. has proceeded with its actions based on the assumption that
hazardous waste sites are the most significant non-point sources of toxic chemicals to the
Niagara River.
In 1988, an EPA study estimated potential toxic pollutant loadings to the Niagara River from
U.S. hazardous waste sites (Gradient Corp/Geotrans Inc 1988). All known U.S. waste sites in
the Niagara River area were considered. To help EPA/DEC focus actions on the sites that have
the most significant potential for polluting the Niagara River, the report produced a list of 70
most-significant U.S. sites. The agencies treated the 70 sites as 33 site clusters, largely based on
the manner in which data have historically been collected. Figure 1 shows the locations of these
33 clusters, and several additional hazardous waste sites.
NRTMP PklokllV
roXIC CHEMICALS
liai/.Ui);iiillimcaK-
Mnv\
liai/.oUi)|i\ ivik-
()cl;ichloiosl\ ivik-
liai/.o(h)lluomnihaK'
PC Us
liai/.o(k)lluomnihaK-
DDIs
( hIonianc
Diomiis
( h in saic
1 clmchlomaliN laic
Dicklnii
Aisanc
1 k-\;icliloi'olvii/.aK'
l.akl
Mavui\
Tn\;i|ihaK-
The study showed that an estimated 694 lbs/day (315 kg/day) of toxic chemicals have the
potential of migrating from hazardous waste sites to the Niagara River. Because collection of
site-specific transport data is ongoing, estimates were made based on certain assumptions, e.g.,
1
-------
that groundwater flow is horizontal, and that pollutants behave in a conservative manner. These
assumptions yielded conservative estimates (i.e., estimates of toxic loadings that are expected to
be higher than the actual loadings).
In November 1989, EPA and DEC issued a report prioritizing the 33 hazardous waste clusters in
order of their potential for polluting the Niagara River (EPA/DEC 1989). Table 1 presents the
33 clusters divided into three categories, based on Gradient/Geotrans estimates of their potential
toxic loads to the Niagara River. These categories are as follows:
Category I: Sites with loading greater than 50 lb/day
Category II: Sites with loadings from 1 to 50 lb/day
Category III: Sites with loadings less than 1 lb/day
Sites from Category I and II collectively represented 99.9% of the total estimated loadings.
In keeping with the strategy to reduce inputs from the sites with the potential for contributing the
largest amounts of pollutants to the Niagara River, the EPA/DEC report presented ambitious
remediation schedules for Category I and II sites. The report's best estimates indicated that if
remediation schedules were met, potential inputs of all toxic chemicals from these sites to the
Niagara River would be reduced by 99% by 1996. However, the 1989 schedules were estimates
based on limited knowledge of site conditions and average negotiation periods with Potentially
Responsible Parties (PRPs). Lengthy legal proceedings with PRPs or unanticipated complex site
conditions have since resulted in delays. Consequently, many of the sites have exceeded their
original 1996 targeted completion date. The circumstances surrounding these delays are
summarized below and described in more detail in the site-specific reports contained in the
Appendix.
Since 1989, EPA and DEC have also reevaluated the hazardous waste sites to identify those that
new information shows are significant sources of toxic chemicals to the Niagara River. Two
sites have been removed as insignificant sources of toxics, and four sites have been added as
significant sources. This update reports on remediation progress at the resulting 26 significant
hazardous waste sites.
The EPA estimates that site remediations have to date achieved a reduction of approximately
93% in potential toxic chemical inputs from all sites to the Niagara River. The estimate is based
on the percentage of RAs in place at some of the 24 sites with completed or on-going
remediation (Table 2). A 100% reduction was assumed for 19 of the 20 sites with all RAs in
place. For one site (OCC, Buffalo Avenue), it was estimated that up to 1.5% of the site's toxic
chemical load may be continuing after remediation; this limitation is included in the overall load
reduction estimate. Since estimates could not be made for most of the sites with on-going
remediation, actual reductions to date may be greater than the estimated 93%. Remedial
systems, e.g., groundwater pump-and-treat systems, are functioning at 3 of the 4 sites where
remediation is underway and are expected to have already reduced off-site loadings. Table 2
2
-------
Lake Ontario
255
66
251
58x\. IX* •'
—/ >-41
vNiagara River
67
Frontier Chemical- /^,
Royal Ave. r—
Booth Oil Site
24
40/56
94
207
Grand
Island
123
182
•136
108
025
APPROXIMATE SCALE
8 MILES
107
241
NOTE: First number only Is given for site areas
with multiple site numbers.
141
120
162
254
Lake Erie
253
118
Figure 1: LOCATION OF SIGNIFICANT NIAGARA RIVER HAZARDOUS WASTE SITES
3
-------
; SITE
BERS
41b-49
81
14
78a,b
39
,85,94*
5
66
41a
255
251
1
,59,248
¦19,250
254
20-122
118
136
67
24-37
253
68
141
162
242
22
182
241
108
107
207
25-127
123
38
15-141
Occidei
Figure 1: LEGEND
SITE NAME
Occidental Chemical Corp. (OCC), Buffalo Ave. Avenue
Niagara County Refuse Disposal
DuPont Necco Park
CECOS International/Niagara Recycling
OCC, Hyde Park
102nd Street
Bell Aerospace Textron
Durez Corporation, Packard Road Facility (formally OCC, Durez Division)
OCC, S-Area
Stauffer Plant (PASNY)
Solvent Chemical
Vanadium Corp. (formerly SKW Alloys)
Olin, Buffalo Avenue
DuPont, Buffalo Avenue Plant
Buffalo Harbor Containment
Buffalo Color Corporation, including Area D
Bethlehem Steel Corporation
River Road (INS Equipment)
Frontier Chemical, Pendleton
OCC, Durez, North Tonawanda
Small Boat Harbor Containment
Gratwick Riverside Park
Mobil Oil
Alltift Realty
Charles Gibson
Great Lakes Carbon
Niagara Mohawk Cherry Farm
Times Beach Containment
Tonawanda Coke
Allied Chemical
Tonawanda Landfill
Dunlop Tire and Rubber
Columbus-McKinnon
Love Canal
Iroquois Gas/West wood Pharmaceutical
tal 102nd Street site (#40), Olin 102nd Street site (#56), Griffon Park (#85),
;ara River Bel den site (#94)
-------
identifies the sites where remediation is not yet completed, but which have operational remedial
systems that are expected to have reduced contaminant loads to the Niagara River.
Completion of final RAs are expected at two additional sites through 2005. Based on the
expected implementation of these RAs, EPA's best estimates are that, by the end of 2005, the
estimated toxic chemical inputs from all sites will be reduced by almost 98% from the 1989
inputs. Current schedules call for all sites to be remediated by 2007.
Estimates have recently been made of the potential loadings of the NRTMP priority chemicals to
the Niagara River from priority waste sites. The estimates are based on information that was not
available when the Gradient/Geotrans estimates were developed, such as information on
chemical concentrations in groundwater and groundwater flow. For example, a report by several
site PRPs addressing groundwater loadings for ten of the NRTMP priority waste sites estimated
priority chemical loadings from ten sites at 5.6 lbs/day (2.5 kg/day) pior to RA, and 0.0048
lbs/day (0.002 kg/day) after RA completion, a reduction of over 99% (CRA 1998). Since these
estimates only consider the NRTMP priority chemicals, they are not comparable to the
Gradient/Geotrans estimates of total toxic chemical loading. In addition, the report also used
some assumptions (i.e. non-conservative assumptions) that would tend to reduce load estimates.
Therefore, although actual loadings are probably greater than the estimates, the estimates do
corroborate the reduction in toxic chemical loadings to the Niagara River achieved through
remedial programs.
In addition to remediation efforts at the waste sites themselves, it is also important to recognize
the role of the Niagara Falls Waste Water Treatment Plant (WWTP) in reducing toxic inputs
from a number of waste sites to the Niagara River. Based on information available in 1987, the
U.S. identified the Falls Street Tunnel, a major unlined industrial sewer cut into the bedrock
under the City of Niagara Falls, as the largest source of toxic pollutants from any of its point
sources. By the mid-1980s, the Tunnel was only receiving overflows of wastewater from the
sewers of a Niagara Falls industrial area, in addition to contaminated groundwater infiltrating
from major waste sites via cracks in the Tunnel's bedrock walls. In contrast to flows from other
point sources, effluent from the Falls Street Tunnel entered the Niagara River untreated. In
1993, EPA and DEC required the City of Niagara Falls to treat the Falls Street Tunnel discharges
during dry weather at the Niagara Falls WWTP. Data gathered by the U.S. indicate that WWTP
treatment of the Tunnel's dry weather discharge has reduced mercury loadings by 70% relative
to 1980 loads, tetrachloroethylene loadings by 85%, and the loadings of four other priority toxic
chemicals by almost 100% .
Since the Falls Street Tunnel captures portions of the upper Lockport bedrock groundwater flow
from seven hazardous waste sites, the actions taken to control discharge from the Tunnel reduce
loadings from the following sites:
DuPont, Buffalo Avenue Solvent Chemical
OCC, Buffalo Avenue CECOS International
Frontier Chemical, Royal Avenue DuPont Necco Park
5
-------
Durez Division, Packard Road Facility (formerly OCC, Durez Division)
For this report, estimates of site loading reductions do not include those obtained through
treatment of the Falls Street Tunnel dry weather flow.
6
-------
TABLE 1
Gradient/Geotrans Prioritization of Waste Sites According to
Potential Toxic Loadings to Niagara River in 1988
Category I: greater than 50 lb/dav
Occidental Chemical Corporation (OCC), Buffalo Ave.
Niagara County Refuse Disposal
DuPont Necco Park
CECOS International
Occidental Chemical Corporation, Hyde Park
Category II: between 1-50 lb/dav
Occidental Chemical Corporation, 102nd Street
Bell Aerospace Textron
Durez Corporation, Packard Road Facility (formerly OCC, Durez Division, Niagara Falls)
Occidental Chemical Corporation, S-Area
Stauffer Plant (PASNY)
Solvent Chemical
Vanadium Corp. (formerly SKW Alloys)
Olin, Buffalo Avenue Plant
DuPont, Buffalo Avenue Plant
Buffalo Harbor Containment
Buffalo Color Corporation, including Area D
Bethlehem Steel Corporation
River Road (INS Equipment)
Frontier Chemical, Pendleton
Occidental Chemical Corporation, Durez, North Tonawanda
Small Boat Harbor Containment
Gratwick Riverside Park
Mobil Oil
Category III: less than 1 lb/dav
Alltift Realty
Charles Gibson
Great Lakes Carbon
Niagara Mohawk, Cherry Farm
Times Beach Containment
Tonawanda Coke
Allied Chemical
Tonawanda Landfill
Dunlop Tire and Rubber
Columbus-McKinnon
Love Canal
7
-------
SUMMARY OF REMEDIATION PROGRESS
Overview of Remediation Status
Table 2 and Figure 2 give overviews of remediation status at the 26 waste sites. In summary:
All remediation is in place at 20 of the sites. The remedial technology installed at these
sites will be operated and monitored for effectiveness for years to come.
RAs are underway at 4 sites.
All of these are interim remedies, including 3 sites under interim remediation while
final remedies are being investigated or designed.
RAs are under design or investigation at 4 sites (including 3 of the sites under interim
RA).
Remedial systems are functioning at 3 of the 4 sites where remediation is underway, and these
systems are expected to have already reduced the off-site loadings.
Highlights of Recent Actions
For each site, a detailed description of progress is provided in the Appendix. Highlights of
progress made, in particular since the June 2003 progress report, are summarized below.
Niagara County Refuse Disposal
Construction of the site remedy began in November 1998 and was completed in 2000.
The final Remedial Action Report was approved in December 2000 and operation and
maintenance activities have been ongoing. Operation and maintenance monitoring data
and a Five-year Review, completed by EPA in November 2003, support that the remedy
is effective and operating as designed. In March 2004, EPA proposed the site for
deletion from the National Priorities List.
DuPont. Necco Park
Remedial Design (RD) was completed in April 2004. Some of the additional
groundwater wells installed during the RD will serve as component parts of the hydraulic
containment portion of the Final Remedy.
Construction of the Final Remedy began November 2001 with the installation of the
additional groundwater wells. The following are among the measures included in the
Final Remedial Design:
8
-------
- upgrading the existing cap;
- containment of the overburden and bedrock source areas using hydraulic measures;
- treatment of the extracted groundwater on-site;
- collection and off-site disposal of DNAPL; and,
- comprehensive monitoring and additional site characterization.
RA completion is expected by November 2005. Because of the fractured bedrock beneath
the site, future complications may arise in achieving effective hydraulic containment.
The target date is intended to allow sufficient time to ensure that any additional remedial
work to achieve effective containment can be completed.
Occidental Chemical Corporation. Hyde Park
Remedial construction at the site was completed in June 2003. EPA issued a Preliminary
Close-out Report (6/03) documenting the construction completion. EPA will issue a
Remedial Action Report in September 2004 which will document all the remedial actions
taken at the site.
In 1997, Phase III of the bedrock groundwater extraction system was installed (pumping
and monitoring wells, and force mains connecting the wells to the on-site treatment
plant). However, complex site conditions and difficulties in pumping NAPL resulted in
the need to install additional wells. Three pumping wells and associated monitoring
wells and force mains were installed in 1998. Three additional pumping wells and
associated monitoring wells and force mains were installed in 1999; one additional
pumping well and five monitoring wells were installed in 2000.
OCC still did not achieve all required inward hydraulic gradients when the additional
wells were installed in 2000. Therefore, OCC created a groundwater model to better
understand groundwater flow in the site vicinity. Model output was utilized to place four
additional wells in 2001.
Hydrogeologic studies conducted from 2000-2003 resulted in a revised conceptual
model for the site which includes eleven discrete flow zones in the bedrock. OCC
modified the existing monitoring well system by retrofitting existing monitoring wells at
the site with 3 one-inch PVC pipes in the four-inch wells. OCC is currently measuring
water levels in 113 retrofitted monitoring wells and these wells are now screened to
monitor the individual flow zones to better delineate the groundwater capture.
• OCC issued the Site Characterization Report: Remedial Characterization Report (6/03)
which concluded that the Bedrock NAPL Plume Containment System satisfies the
performance objectives of the RRT and that the contaminated bedrock groundwater was
being contained.
OCC also issued the Major Ions Study (11/03) which concluded that the relative age of
the groundwater between the pumping wells near the site and the Niagara Gorge is
younger than the age of the groundwater underneath the landfill. This indicates that the
bedrock wells are effectively preventing the migration of groundwater from the site to the
Gorge.
9
-------
TABLE 2
STATUS OF SITE REMEDIATIONS
Investigation and Design:
Potentially Responsible Party (PRP)
Search
none
Site Investigation Underway
Bethlehem Steel Corporation
Frontier Chemical, Royal Avenue1
VANADIUM CORPORATION2
Remedial Design (RD) Underway
Buffalo Color Corporation
Remediation:
Remediation Underway:
Interim Remedy In Place or Under Construction:
MOBIL OIL
Frontier Chemical, Royal Avenue1
VANADIUM CORPORATION2
DUPONT NECCO PARK
Remediation Completed (O&M Underway)
Stauffer Chemical
Frontier Chemical, Pendleton
Bell Aerospace Textron
CECOS International
Durez Corporation, Packard Road Facility
OCC, Durez, North Tonawanda
DuPont Buffalo Avenue
Olin Plant Site
Buffalo Color, Area D
OCC, Buffalo Avenue
102 Street (Olin /OCC)
River Road
Niagara Mohawk, Cherry Farm
Niagara County Refuse Disposal
Iroquois Gas-Westwood Pharmacy
Gratwick Riverside Park
OCC S-Area
Solvent Chemical
Booth Oil
OCC-Hyde Park
The sites in interim remediation are also under investigation or design, and therefore are listed twice.
Sites in bold have achieved progress since the June 2003 report.
These sites, though not completed, have operational remedial systems that are expected to
have reduced contaminant loadings to the Niagara River.
1 A major Superfund Response Action was completed in 1995. Notice letters were issued to PRPs in
December 1999 and in January 2001 the site was referred for RI/FS action. The RI/FS will be completed
in early 2004 with a ROD expected in 2004.
2 Preliminary investigations were completed. Two Interim Remedial Measure (IRMs) have been
completed by PRPs.
10
-------
Figure 2: STATUS OF SITE REMEDIATIONS
Interim
Site Investigation + Interim Remedy in Place (2)
Site Investigation (1)
(Number of sites in parentheses)
No sites are currently under PRP Search.
Remedial Design (1)
Final Remedy in Place (20)
-------
Occidental Chemical Corporation. S-Area
The drain collection system and cap for the old Niagara DWTP property were completed
in 1999.
Operation of the drain collection system for the landfill portion of the site began in 1996;
however, a portion of the system was improperly installed and did not function as
designed. The system was subsequently replaced in 1999-2000, delaying completion of
the RA.
Construction of the final landfill cap began in August 2000.
Securement of the raw water intake structure from the old DWTP began in August 2000.
Construction of the final S-area Landfill cap commenced in August 2000 and was
completed in March 2002.
The securement of the DWTP intake structures, including the grouting of the 5,000- foot
long bedrock tunnel, commenced in summer 2000 and was completed in August 2002.
Construction activities for the site are completed. Evaluation and adjustments of the
remedial systems are currently being performed.
Sodium Permanganate was injected into the small void in the secured intake tunnel to
determine if the low-level contamination observed in the void's water is entrapped or is
due to migration.
Solvent Chemical
Construction of the groundwater extraction and treatment systems were completed in
2001.
The groundwater extraction/treatment system began operation in 2002.
• A performance monitoring program will begin in 2004.
Vanadium Corporation
In November 1998, (SKW Alloys) completed an IRM to cover portions of their parcel
and control site stormwater runoff.
DEC and Airco negotiated an IRM to cap the landfill on their portion of the site. Closure
of the Airco portion of the site was completed by December 2000 (OU No 2).
Niagara Mohawk and the New York Power Authority have agreed to conduct a Remedial
Investigation of their portion of the site (OU No. 3). An RI/FS work plan has been
approved and implementation is ongoing.
Buffalo Color Corporation
The Corrective Measures Study (CMS) was approved in July 2000. The remedy
selection was expected to be finalized in May 2002, with CMI start-up expected in
March 2003. However, in October of 2002 Buffalo Color filed for Chapter 11
Bankruptcy protection. Honeywell Corporation, a successor to Allied Chemical and a
12
-------
potentially responsible party, and BCC have recently reached an agreement for
implementation of the corrective measures. This agreement is subject to approval from
the Bankruptcy Court. The DEC is currently negotiating a Consent Order with
Honeywell to implement the remedy. An RFP for remedy design and construction was
issued by Honeywell during 2003. The remedial design is expected to be installed during
2004.
Bethlehem Steel Corporation (BSC)
BSC has completed the field work for the site investigation, and is preparing Resource
Conservation and Recovery Act Facility Investigation (RFI) and human health risk
assessment reports. These have been delayed due to negotiations over the scope and the
need to collect additional data. Submittal of these reports is anticipated by December
2004.
BSC completed limited remedial technology studies for two areas that appear to be the
primary sources of groundwater contamination at the facility (the Acid Tar Pits and Coke
Oven Areas). The EPA and DEC found the studies to be technically flawed and of
limited value. BSC continues to study various potential remedial technologies.
BSC has submitted a Pre-design Investigation Report for the remediation of the Benzol
Plant Area (i.e., Coke Oven Area). However, a dispute over waste characterization has
delayed implementation.
BSC submitted an application for the construction of a Corrective Action Management
Unit (CAMU) at its facility in November of 2000. The application was deemed
substantially complete and BSC submitted a 30% design document.
A portion of the BSC site was selected as a RCRA brownfield pilot project in March of
2000. The focus of the project is to make approximately 102 acres of the facility
available for potential redevelopment. The 102 acres has been released from the RCRA
RFI Order to allow the property to be addressed under alternative programs.
BSC declared Chapter 11 bankruptcy in October 2001.
BSC closed the coking plant and ceased coke production at the Lackawanna facility in
the Fall of 2001.
In 2003, the Integrated Steel Group (ISG) acquired the BSC Lackawanna facility.
Any future CMS or CMI activities will require a new order, permit or other agreement.
The DEC is currently negotiating a corrective action order with ISG.
Frontier Chemical. Roval Avenue
The company that owned the facility went bankrupt in 1992, and failed to implement a
DEC Order for waste removal. The site was referred to Federal Superfund for a
Response Action that including the removal of thousands of drums, removal of wastes
from 45 tanks on the site, and other actions. The action was completed in 1995.
EPA ruled not to include the site on the National Priorities List.
• DEC initiated PRP search efforts in 1998.
DEC finalized the list of PRPs and issued notice letters to the PRPs in December 1999.
13
-------
In January 2001 the site was referred for RI/FS action under the NY State Superfund
program. The Focused Remedial Investigation was begun in 2001. The RI/FS is
expected to be completed in early 2004, with a final Record of Decision (ROD) expected
in 2004.
Mobil Oil
Following site investigations in the 1980s, DEC re-classified a 3-acre area of concern on
the site as Class 3 (does not present significant threat to public health or the
environment; action may be deferred).
In 1994, the entire Mobil facility was selected for DEC's Multi-Media Pollution
Prevention (M2P2) program.
A multi-media inspection was conducted, leading to the signing of a Consent Order in
May 1997 to undertake further site investigation and remediation. The results of the site
investigation were submitted in November 1998.
Three areas of the site were identified as requiring additional investigation to determine
the extent of contamination. The results of this site facility investigation were submitted
in December 1999.
The results of completion of the investigation of the remaining areas of the site were
submitted in March 2002. In November 2002, the remaining three chambers of the
former Main Inground Oil/Water Separator were permanently closed by dewatering,
cleaning and backfilling of the chambers.
Remedial systems are operating at the Mobil Oil facility. A well point system was
installed in the early 1970s to prevent petroleum seepage to the Buffalo River. In 1993,
six dual-pump recovery wells were activated to recover petroleum product and
groundwater. Five of the six recovery wells are presently being operated in conjunction
with the well point system.
Booth Oil
A PRP proposal for an alternate remedy was accepted in June 1998. In 2001, the DEC
proposed amending the earlier RODs. The Amended Record of Decision, which
incorporated operable units 1 and 2, was issued in August 2002. Approval of the final
Remedial Design and execution of a consent order was completed in March 2003.
Construction to implement the remedy selected in the AROD began in July 2003 and was
completed in December 2003.
Estimated Remediation Costs
Where available, estimated remediation costs incurred to date and expected in the future are
provided in each site description (Appendix). Federal, State, and PRP contributions were
estimated, where possible. Remediation costs were unavailable for Federal/State RCRA sites,
14
-------
because reporting cost information is not a requirement of the RCRA corrective action program,
and facilities have generally been reluctant to provide it. The remediation costs that are provided
are estimates that may change as remediation progress is made at each site. The estimates will
be updated as new information becomes available.
Based on available estimates for 19 sites, following is the total amount incurred to date (costs for
the remaining 7 sites are unavailable):
Federal $ 39.295 million
State $ 6.856 million
PRPs $ 347.407 million
Total $ 393.558 million
Based on available estimates for 12 sites, the total additional costs expected in the future are as
follows (costs for the remaining 14 sites are unavailable):
Federal $ 1.875 million
State $ 0.710 million
PRPs $ 258.864 million
Total $ 261.449 million
The estimated costs to date cannot be compared to the estimated costs expected in the future,
because different sites are included in the estimates. It is also difficult to compare the relative
contributions of federal, state, and PRP expenditures, because cost information for some sites
was incomplete (e.g., some sites may have been able to provide federal or state costs but not PRP
costs, and so on). However, the cost information does provide a sense of the magnitude of U.S.
expenditures for hazardous waste site remediation in the Niagara River basin.
15
-------
ACRONYMS
APL
BCC
BSC
CERCLA
CMI
CMS
DDT
DEC
DNAPL
DWTP
EC
EPA
HSWA
ICM
IIWA
IRM
MOE
NAPL
NRTMP
OCC
PCBs
PRP
PSA
PVC
RA
RCRA
RFA
RFI
RFP
RI/FS
ROD
RRT
SPDES
TCDD
TCP
VOC
Aqueous phase liquids
Buffalo Chemical Corporation
Bethlehem Steel Corporation
Comprehensive Environmental Response, Compensation, and Liability Act of 1980
Corrective Measure Implementation
Corrective Measure Study
primarily l,l'-(2,2,2-trichloroethylidene)-bis/4 chlorobenzene
New York State Department of Environmental Conservation
Dense non-aqueous phase liquids
Drinking Water Treatment Plant
Environment Canada
U.S. Environmental Protection Agency
Hazardous and Solid Waste Amendments
Interim Corrective Measure
Immediately Implementable Work Assignment
Interim Remedial Measure
Ontario Ministry of the Environment
Non-aqueous phase liquids
Niagara River Toxics Management Plan
Occidental Chemical Corporation
Polychlorinated biphenyls
Potentially Responsible Party
Preliminary Site Assessment
Polyvinyl chloride
Remedial Action
Resource Conservation and Recovery Act
RCRA Facility Assessment
RCRA Facility Investigation
Request for Proposal
Remedial Investigation/Feasibility Study
Record of Decision
Requisite Remedial Technology
New York State Pollutant Discharge Elimination System
Tetrachlorodibenzo-p-dioxin
Trichlorophenol
Volatile organic compounds
16
-------
GLOSSARY
A
Ambient
A surrounding medium, such as water or air.
Used in contrast to a specific source.
Aquatic
Growing in, living in, or dependent upon
water.
Atmospheric deposition
Pollution from the atmosphere associated
with dry deposition in the form of dust, wet
deposition in the form of rain and snow, or
as a result of vapor exchanges.
B
Barrier wall
A wall constructed underground in a
hazardous waste site or landfill to stop the
flow of contaminated groundwater.
Basin
The land that drains into a waterbody.
Bedrock groundwater
Water flowing through a rock layer
underground, under a top layer of mixed soil
and loose rock called the overburden.
Benzo(a)pyrene [B(a)P]
A PAH that is formed by the incomplete
combustion of fossil fuels, wood, and
tobacco; the incineration of garbage; and in
steel production.
Bioaccumulation
The process by which chemical substances
accumulate in the tissues of an organism that
drinks contaminated water or eats
contaminated food.
C
Cap
A cover over hazardous waste sites, usually
made of clean soils or clay, that prevents
rainwater from seeping through soil and
causing the contaminants in the soil to flow
into the groundwater.
Capture Zone
Area in which groundwater is flowing
towards a pumping well; used as
remediation technique for hazardous waste
sites, to "capture" contaminated
groundwater and treat it.
Chlordane
A persistent toxic chemical that was used to
control ants, grasshoppers, and other insects
on certain crops.
Collection drain
System of pipes around a hazardous waste
site or landfill that collects surface or
groundwater and directs it toward a
treatment plant.
Combined sewer overflow (CSO)
Water discharged into a waterbody from a
sewer system that carries both sanitary
sewage and stormwater runoff. During dry
weather the combined sewer system's flow
is normally treated at a wastewater treatment
plant, but during rain events, the plant's
capacity may be exceeded and the flow may
be bypassed to discharge, untreated, directly
into a waterbody.
Consent decree
A legal document, approved by a judge,
which puts into effect a remedy (i.e., actions
to correct an environmental problem).
17
-------
Contaminant
A substance that is not naturally present in
the environment or is present in amounts
that can adversely affect the environment.
D
DDT
Di chl oro-diphyny 1 -tri chloroethane. A
persistent toxic chemical that was used as a
pesticide, particularly for mosquito control.
DDT is banned in U.S. and Canada. DDE
and DDD are metabolites of DDT.
Dieldrin
A persistent toxic chemical that was used
mainly as a soil insecticide.
Dioxins/furans
Dioxin: A family of persistent toxic
chemicals known as dibenzo-p-dioxins.
Dioxins can enter the environment as the by-
products of industrial processes or as a
result of combustion processes in
incinerators and motor vehicles using leaded
fuel. The compound called "2,3,7,8-TCDD"
is the most toxic member of the dioxin
family.
Furans are a class of chemicals similar to
dioxins, which are created at high
temperatures, such as incineration of PCBs
and other organic wastes containing
chlorine.
DNAPL (Dense Non-Aqueous Phase
Liquid)
An oily, sludge-like mixture of chemicals
that is denser than water. DNAPL flows
with gravity or along geological formations,
not always in the same direction as
groundwater.
Downstream
In the direction with the flow of a stream or
river; down river. For Niagara River,
downstream is towards Niagara-on-the-Lake
and Lake Ontario.
Dredging
Removal of sediment from the bottom of a
waterbody.
E
Embayment
A bay. A part of a waterbody (such as a
river or lake) that makes an indentation into
the adjacent land.
F
Force main
A pipe that carries contaminated
groundwater drawn out of hazardous waste
sites by pumping wells to a treatment plant.
Four Parties
The four agencies who implement the
Niagara River Toxics Management Plan:
U.S. Environmental Protection Agency,
Environment Canada, New York State
Department of Environmental Protection,
and Ontario Ministry of Environment and
Energy.
G
Groundwater
The fresh or saline waters found beneath the
Earth's surface that often supply wells and
springs. Contrast to "Surface water".
H
Habitat
Place where a particular type of plant or
animal lives. An organism's habitat must
provide all of the basic requirements for its
life.
18
-------
Hazardous waste
Any substance that is a by-product of
society and is classified under U.S. or
Canadian law as potentially harmful to
human health or the environment.
Hazardous wastes are subject to special
handling, shipping, storage, and disposal
requirements under the law.
Hazardous waste site
Land disposal site for hazardous wastes.
Heavy metals
Metallic elements with high atomic weights
that tend to be toxic and bioaccumulate.
Examples are mercury, arsenic, lead, etc.
Hexachlorobenzene (HCB)
A persistent toxic chemical that was
originally manufactured as a fungicide for
cereal crops. It is also generated as a by-
product in the manufacture of pesticides and
can be formed during the combustion of
substances containing chlorine.
I
Infiltration
Passing through or filtering through, as in
rain water that filters through soil to join
groundwater.
Inorganic substance
A chemical compound that does not contain
carbon. Inorganic substances are often
derived from minerals.
Insecticide
A chemical used to kill or control the
growth of insects.
L
Landfill
Land disposal site for hazardous (or non-
hazardous) wastes.
Leachate
Liquid derived from rain or snow melt that
percolates through a hazardous waste site.
Load or Loading
The amount of a material entering a system
over a given time interval.
M
Medium (plural: Media)
A surrounding substance in the
environment: water, air, or sediment.
Metabolite
A substance that is the product of biological
changes to a chemical.
Mirex
A persistent toxic substance that was used as
an insecticide and a fire retardant.
Multi-media
Involving multiple media, such as water and
air, or air and sediment, or all three.
N
National Priorities List (NPL)
An EPA list of the most serious uncontrolled
or abandoned U.S. hazardous waste sites
identified for long-term remedial action
under Superfund.
Non-point source
Diffuse pollution sources (i.e., without a
single point of origin or not introduced into
a waterbody from a specific outlet).
Generally carried off the land by
19
-------
stormwater. Common sources can be
associated with a variety of land-uses (e.g.,
agriculture, forestry, and urban) and
activities (e.g., construction, mining, and
land disposal).Contrast to "Point source".
O
Octachlorostyrene (OCS)
A persistent toxic chemical that was
released as a by-product when chlorine was
manufactured using certain processes that
are no longer used.
Organic substance
A chemical compound that contains carbon.
Overburden groundwater
Water flowing through a layer of mixed soil
and loose rock that lies over the rock layer
called bedrock.
P
PAHs
Polycyclic or polynuclear aromatic
hydrocarbons. A class of persistent toxic
compounds that are formed from the
combustion of organic material, such as
forest fires or gasoline in cars.
PCBs
Polychlorinated biphenyls. A group of
persistent toxic chemicals used in electrical
and hydraulic equipment for insulating or
lubricating purposes.
Persistent toxic chemical
Any toxic chemical that is difficult to
destroy or that breaks down slowly in the
environment (i.e., with a half-life in water
greater than eight weeks).
Pesticide
A chemical used for preventing, destroying,
or repelling any pest.
Point source
Any discernible confined and discrete
conveyance, including, but not
limited to, any pipe, ditch, channel, tunnel,
conduit, well, container, landfill, leachate
collection system, vessel or other floating
craft from which pollutants are or may be
discharged from.
Pollution prevention
Any action that reduces or eliminates
pollutants before they enter the
environment.
Potentially Responsible Party (PRP)
Any individual or company potentially
responsible for, or contributing to, the
contamination problems at U.S. hazardous
waste sites.
Pretreatment
Processes used to reduce, eliminate, or alter
pollutants from industrial sources before
they are discharged into publicly-owned
sewage treatment systems.
Priority toxic chemicals
Under the NRTMP, 18 toxic chemicals that
exceeded water quality or fish tissue
standards in the Niagara River or Lake
Ontario.
R
RCRA
Resource Conservation and Recovery Act.
A U.S. program to remediate active
hazardous waste sites. Sites are remediated
by potentially responsible parties whenever
this can be arranged.
Record of Decision (ROD)
A public document that explains what
actions will be taken to remediate a U.S.
20
-------
hazardous waste site.
Remedial Investigation/Feasibility Study
(RI/FS)
The RI defines the areal and vertical extent
of the hazardous waste problem at a
Superfund site through numerous sampling
wells, an extended environmental sampling
program and a full geophysical survey.
Based on the RI, the FS develops and
evaluates alternative solutions to the
problem.
Requisite Remedial Technology (RRT)
An RRT is the equivalent of an FS (see
RI/FS above) for a pre-CERCLA
agreement.
Runoff
Water that flows over the land surface into a
waterbody.
S
Slurry wall
Barrier made of a thin, watery mixture of
fine, insoluble material (e.g., clay, cement,
soil).
Solid Waste Management Units
(SWMUs)
Areas within a hazardous waste site where
hazardous materials are stored or managed.
SWMUs are generally storage areas,
treatment systems, disposal areas, spill
areas, or containment cells.
Superfund
A U.S. program to remediate inactive or
abandoned hazardous waste sites in an
emergency or for the long-term. Sites are
remediated by potentially responsible parties
whenever this can be arranged.
Surface water
All water open to the atmosphere (e.g.,
rivers, lakes, reservoirs, seas, etc.).Contrast
to "Groundwater".
T
Toxaphene
A persistent toxic chemical that was used as
an insecticide.
Toxic substance
Any substance that adversely affects the
health or well-being of a living organism,
e.g., causing death, disease, birth defects,
behavioral abnormalities, cancer, genetic
mutati ons, phy si ol ogi cal/reproductive
malfunctions, or physical deformities.
U
Upstream
In the direction against the flow of a stream
or river; upriver. For Niagara River,
upstream is towards Fort Erie and Lake Erie.
V
Volatile substance
A substance that evaporates readily.
W
Wetland
An area that is saturated with water or has a
water level at or near the surface. A wetland
has organic soils and plant/animal species
that are adapted to a wet environment.
21
-------
REFERENCES
CRA. 1998. Estimates of Pre-Remedial and Post-Remedial Action Chemical Loading via
Groundwater to the Niagara River. Conestoga-Rovers & Associates, January 1998. Ref. No.
9855(1).
Gradient Corp./Geotrans Inc. 1988. Potential Contaminant Loadings to the Niagara River from
U.S. Hazardous Waste Sites.
Niagara River Secretariat. 2002. Niagara River Toxics Management Plan: Progress Report and
Work Plan, May 2002.
U.S. Environmental Protection Agency /New York State Department of Environmental
Conservation (EPA/DEC). 1989. Reduction of Toxics Loadings to the Niagara River from
Hazardous Waste Sites in the United States.
22
-------
APPENDIX
PRIORITY NIAGARA RIVER HAZARDOUS WASTE SITES:
Site Descriptions & Remediation Schedules
-------
-------
A-l
OCCIDENTAL CHEMICAL - BUFFALO AVENUE
Site #4lb -49
Site Program: RCRA (State and Federal)
Summary Prepared by: EPA and DEC
Site Description
Occidental Chemical Corporation's (OCC) Buffalo Avenue Plant is a major manufacturing
facility in central Niagara Falls adjacent to the Robert Moses Parkway, along the Niagara
River.
Starting with seven acres in 1911, the facility has grown to approximately 130 acres, with
hundreds of buildings. During its history, the facility has manufactured over 250 different
chemical products, including halogenated benzenes, toluenes, phenols, and aliphatics.
Chemical raw materials, products and wastes have been buried or spilled at numerous
locations on the plant site. Estimates of the amount of waste disposed in the various
production areas include: 4,200 tons in D-Area, 1,500 tons in F-Area, 11,300 tons in N-
Area, and unknown amounts in U-Area.
Five aquifers exist at this site: one overburden and four bedrock. A clay/till layer serves as
an aquitard (a barrier) between the overburden and the bedrock, except where man-made
influences such as utilities and building foundations have penetrated the layer. The four
bedrock flow zones occur within the Lockport Group (a rock formation) with the three
upper units accounting for nearly 100% of bedrock groundwater at the site.
In the overburden, groundwater flow was historically toward the Niagara River from the
southeast portion of the site. However, an overburden barrier wall constructed in 1994
restricts the direct discharge of this groundwater to the Niagara River. The barrier wall re-
directs the groundwater to the southwest. In the southwest portion of the site, the
overburden groundwater discharges to the New York Power Authority (NYPA) conduit
drain system and then probably discharges from the NYPA drain system to the Falls Street
Tunnel. At other plant areas, the direction of overburden groundwater flow is locally
influenced by man-made structures, particularly the sanitary and outfall sewers as well as
existing groundwater collection systems.
In the bedrock aquifers, groundwater moves northwest, north, and northeast, is recharged
by the river, and is influenced by the NYPA conduits and the Falls Street Tunnel. Most
bedrock groundwater flow leaving the site will enter the NYPA conduit drainage system or
the Falls Street Tunnel. All of the dry weather flow through the Falls Street Tunnel now is
treated by the Niagara Falls Wastewater Treatment Plant before discharge to the River.
-------
A-2
Interim Corrective Measures
OCC completed certain interim corrective measures required under the Resource
Conservation and Recovery Act (RCRA):
Removal and capping of contaminated soils
Installation of a barrier wall
• Collection of DNAPL from bedrock wells
Installation of fences
Removal of spills from secondary containment areas
Removal of fly ash accumulated on the ground.
DEC and EPA issued OCC a state Part 373 permit and an EPA Hazardous and Solid Waste
Amendments permit under RCRA in June 1988, permitting the storage/treatment and
incineration of hazardous wastes.
Site Investigation
Pursuant to the permits, OCC completed the on-site and off-site components of a RCRA
Facility Investigation (RFI). Due to the complexity of site conditions, the remedial
program activities for the facility were subdivided into several components:
bedrock groundwater
overburden groundwater
overburden soils
off-site groundwater contamination.
In accordance with an August 1993 DEC Part 373 permit modification, the remedial
measures are being implemented as stabilization measures, followed by the final remedy
selection after the adequacy of the stabilization measures are assessed. Stabilization
measures for the individual components are being addressed on a priority basis. OCC has
prepared a comprehensive, site-wide CMS, addressing all site components including the
adequacy of the stabilization measures described below. This was submitted in November
1998.
Stabilization Measures (Additional Interim Corrective Measures)
Bedrock Groundwater. All of the bedrock groundwater extraction wells and monitoring
wells have been installed. A new treatment plant designed to treat the contaminated
bedrock groundwater has been constructed. The pump-and-treat system has been started
up. From April 1996 through September 1996, as part of the testing and optimization of
the remedial system, over 700 gallons per minute of contaminated groundwater were
pumped from the upper three bedrock aquifers and treated at the new treatment plant.
Three bedrock wells have collected, through May 1997, approximately 5,840 gallons of
DNAPL from the site. The DNAPL has been incinerated in OCC's hazardous waste
-------
A-3
incinerator which ceased operation in 2003. Since that incinerator was shut down,
DNAPL has been incinerated in RCRA-approved commercial facilities off-site. The
pump-and-treat system was tested and optimized through March 1997. The pumping rates
of each of the 19 bedrock groundwater extraction wells were optimized to achieve a
hydraulic barrier along the northern and western plant boundaries to contain the
contaminated groundwater.
Based on performance monitoring data, OCC determined that additional measures were
necessary to achieve the remedial design objectives. The treatment plant has been
enhanced by adding additional treatment measures (air stripping to address break-through
of vinyl chloride), and expanding the plant's capacity from 800 gpm to 1200 gpm. OCC
subsequently increased the extraction rate of the bedrock groundwater recovery system to
1000 gpm. On average more than 50 pounds per day of organic chemicals are captured by
the bedrock groundwater collection system.
Overburden Groundwater. Construction of a collection system to capture overburden
groundwater along the southern boundary of the site is complete. In the southwestern
portion of the site, an 1,800 foot-long abandoned sewer line has been converted into a
groundwater collection system. Conversion of the line began in February 1996. A 1,400
foot-long section of the line began operation in June 1997. During the sewer line
conversion, a 400 foot-long section of the line was found to be unsuited for capturing the
groundwater. As a result, OCC installed a new groundwater collection drain (trench)
adjacent to this 400 foot-long section of pipe, and extending an additional 400 feet to the
west beyond the original sewer line length. This increased the capture zone to a total of
2,200 feet. This system began operation in December 1997. However, performance
monitoring data indicated that these measures were insufficient to produce the necessary
groundwater capture, so the system was augmented by installation of a tile drain. This was
completed in December 1998. The new collection system extends along the alignment of
the converted sewer to the vicinity of the OCC S-Area site. On average more than 50
pounds per day of organic chemicals are captured by the overburden groundwater
collection system.
The overburden groundwater collection system is now fully operational. The collected
groundwater is being treated on-site at an existing wastewater treatment plant, which was
upgraded to handle the additional flow.
At one time, groundwater infiltration into the on-site industrial waste sewer system was a
significant source of contamination to the river. However, OCC has had an ongoing
program for replacing and repairing pipes since the early 1980s. OCC completed the
investigation of groundwater infiltration into the Plant's Outfall Sewer System in June
1996 and implemented measures to eliminate infiltration points from Fall 1996 through
Spring 1997.
OCC installed a barrier wall in 1994 along the Niagara River to prevent migration of
overburden groundwater contamination into the Niagara River.
-------
A-4
Overburden Soils and Off-site Groundwater. As interim corrective measures, OCC
identified and removed 36 tons of liquid mercury from contaminated soils on-site in U-
Area, and capped dioxin-contaminated soils in X-Area.
OCC submitted a draft CMS for the overburden soils in 1996. In a Fall 1997 comment
letter on the draft CMS, DEC advised OCC not to prepare a separate off-site CMS, but
instead to submit a comprehensive, site-wide, final CMS that addresses remedial measures
for all site components (bedrock, overburden and off-site). That CMS was submitted in
November 1998.
Final Corrective Measures
Future off-site loadings from the Buffalo Avenue site will be effectively eliminated by the
bedrock groundwater stabilization program (completed), and the overburden groundwater
stabilization program (completed).
A draft permit that specifies the Final Corrective Measures for the facility was public
noticed in September 1999. The draft permit proposed to incorporate the Interim
Corrective Measures currently in place as part of the Final Corrective Measures for the
site. After a public comment period, the final permit became effective February 10, 2000.
The Final Corrective Measures in the final permit include:
Extraction of bedrock groundwater on-site; and treatment in accordance with the
applicable SPDES permit at an on-site plant.
Monitoring bedrock groundwater extraction wells for NAPL; and collection of
detected NAPL with on-site or off-site treatment.
Extraction of overburden groundwater on-site; and treatment in accordance with
the applicable SPDES permit at an on-site plant.
Compliance with the limits specified in the applicable Significant Industrial User
Wastewater Discharge Permit for overburden groundwater infiltration into the City
of Niagara Falls sanitary sewers.
Compliance with the provisions of the applicable SPDES permit to restrict
discharge of overburden groundwater from the outfall sewer system.
Monitoring overburden groundwater extraction wells for NAPL; and collection of
detected NAPL with on-site or off-site treatment.
Monitoring the performance of the remedial systems on-site and off-site.
The schedule for implementation of a corrective action program at the plant, including
Corrective Measure Study (CMS) and Corrective Measure Implementation (CMI), is
shown below.
-------
Remediation Costs
A-5
Following are estimated amounts that have been spent to date on remediating this site:
Federal $ (Not available)
State $ (Not available)
PRP $ (Not available)
The following estimated amounts will be spent from now to the completion of remediation:
Federal $ (Not available)
State $ (Not available)
PRP $ (Not available)
-------
A-6
OCCIDENTAL CHEMICAL - BUFFALO AVENUE
Output
Responsible
Party
Previous
Target Date
Current
Schedule
RFI Work Plan Approval
DEC/EPA
Jun 1991
COMPLETED
RFI Completion
Permittee
Dec 1992
COMPLETED
CMS Work Plan Approval
DEC/EPA
Jun 1993
COMPLETED
CMS
Completion:
Bedrock Groundwater
Permittee
Aug 1993
COMPLETED
Overburden Groundwater
Permittee
Dec 1994
COMPLETED
Overburden Soil1
Permittee
Aug 1996
COMPLETED
Off-Site (Groundwater)1
Permittee
Feb 1997
N/A
Site-wide CMS1
Permittee
N/A
COMPLETED
Stabilization
Selection:
Bedrock Groundwater
DEC/EPA
Dec 1994
COMPLETED
Overburden Groundwater
DEC/EPA
Feb 1995
COMPLETED
Overburden Soil1
DEC/EPA
Oct 1997
N/A
Off-Site (Groundwater)1
DEC/EPA
Apr 1998
N/A
Stabilization
Work Plan
Approval:
Bedrock Groundwater
DEC/EPA
Nov 1994
COMPLETED
Overburden Groundwater
DEC/EPA
Jun 1995
COMPLETED
Overburden Soil1
DEC/EPA
Apr 1998
N/A
Off-Site (Groundwater)1
DEC/EPA
Jul 1998
N/A
Start-up:
Stabilization2
Bedrock Groundwater
Permittee
Oct 1995
COMPLETED
Overburden Groundwater
Permittee
Dec 1997
COMPLETED
Overburden Soil1
Permittee
Oct 1998
N/A
Off-Site (Groundwater)1
Permittee
Dec 1998
N/A
Start-up of CMI
Permittee
Dec 1997
COMPLETED
1 The overburden soil remedial measures were delayed so that contaminated soils generated during
both bedrock and overburden groundwater remediation could be addressed at once. Off-site
remedial measures were delayed, pending evaluation of the effectiveness of on-site remedial
measures. None of these remedial measures impact the potential for off-site loadings, which was
eliminated in Dec. 1998, with full operation of the overburden groundwater remedial system. OCC
submitted a comprehensive, site-wide, final CMS in November 1998, addressing all on-site and
off-site components. The DEC issued a draft 373 permit that specifies final corrective measures for
the facility in September 1999. After a public comment period, the final permit became effective
February 10, 2000.
2 Implementation of the Bedrock and Overburden Stabilization Programs will effectively eliminate
future off-site loadings from the Main Plant Site.
-------
A-7
NIAGARA COUNTY REFUSE DISPOSAL
Site #81
Site Program: Federal Superfund
Summary Prepared by: EPA
Site Description
The Niagara County Refuse site occupies approximately 65 acres, about 1000 feet north
of the Niagara River in the Town of Wheatfield, New York.
During its operation period (1968-1976), the Niagara County Refuse Disposal District
(NCRDD) accepted household, yard, agricultural, institutional, commercial, and
industrial waste; demolition and construction debris; sewage treatment plant sludge;
street sweepings; and used tires. More than 100 waste generators or transporters are
thought to have used the site. Disposed materials included heat-treatment salts, plating-
tank sludge, tetrachloroethylene, PVC skins and emulsion, thiazole polymer blends,
polyvinyl alcohol, phenolic resins, and brine sludge containing mercury. At the time that
it was closed by the NCRDD in 1976, the site was covered with a 20 inch thick cap
consisting of a layer of low permeability clay beneath a layer of topsoil. Illegal dumping
of rubbish and hard fill, as well as the erosion of the clay cap, have been concerns at the
site since its closure.
Three overburden zones and one bedrock zone are present under this site. The bedrock
zone and one of the overburden zones are the primary water-bearing formations
(aquifers). The groundwater in these two aquifers generally flows in a south/southwest-
erly direction towards the Niagara River beneath the southern half of the site and in a
north/northwesterly direction towards an area of regulated wetlands beneath the northern
half of the site.
Site Investigation
Niagara County Refuse is an EPA-lead site on the National Priorities List of Superfund
sites. Pursuant to a March 1989 consent order, a group of fourteen Potentially
Responsible Parties (PRPs) performed a Remedial Investigation/Feasibility Study
(RI/FS) for the site. It was completed in September 1993, when EPA signed a Record of
Decision (ROD) for the site.
The RI report indicated that the water-bearing zones beneath the site have generally not
been impacted by site contaminants. Volatile and semi-volatile organic compounds,
pesticides, and metals were found in leachate seeps emanating from the sides of the
landfill, however, which could threaten the groundwater and nearby surface water if left
unaddressed.
-------
A-8
Upon completion of the RI/FS, EPA issued a Proposed Plan for remediation of the site.
After consideration of public comment on the Proposed Plan, EPA executed a ROD on
September 24, 1993, selecting the following remedy:
a full NYCRR part 360 cap with a complete perimeter clay barrier wall
leachate collection and offsite treatment and disposal
gas venting
an ecological assessment of the adjacent wetlands
removal of the field tile drains located to the west of the landfill
long-term operation and maintenance.
The Final Design Report for the remedial action was approved by EPA in September
1997. Due to the Site being a municipal landfill, the municipalities are eligible for State
funding assistance for their respective share of remedial action costs. As such, the
specific state requirements for funding eligibility were completed by May 1998. A call
for bids was issued and the bid was awarded for remedial construction in June 1998.
Construction began in fall 1998.
Construction Progress
On-site construction at the site commenced in November 1998. The site was cleared and
grubbed and a security fence erected. Installation of the leachate collection system and
its tie-in to the City of North Tonawanda sanitary sewer by force main was completed
over the winter months. Early spring was devoted to grading the site and filling the
central swales with clean fill. Placement of the first layer of the cap, gas-vent stone,
began in May 1999. Construction progressed with the placement of a geotextile drainage
layer, a geocomposite barrier layer, a soil barrier protection layer, and a topsoil layer,
respectively. Placement of each layer proceeded in a north-to-south direction over the
entire site. Remedial construction was completed in June 2000. A final inspection was
conducted in September 2000. The final Remedial Action Report was approved in
December 2000 and operation and maintenance activities commenced. Groundwater
monitoring supports that the remedy is effective and operating as designed.
The leachate collection system has been operational since summer 1999, thus eliminating
any potential pathway for leachate to migrate off-site. A Five-Year Review, completed
by EPA in November 2003, concludes that the remedy is effective and operating as
designed and that there is no exposure to human or environmental receptors from site-
related contaminants due to permanent measures in place at the site.
Schedule for Completion
An updated schedule for remediation of the site is shown in the following table.
-------
A-9
Remediation Costs
Following are estimated amounts that have been spent to date in response to this site:
Federal $ 1,350,000
PRP $ 11,650,000
NIAGARA COUNTY REFUSE DISPOSAL
Output
Responsible
Party
Previous
Target Date
Current
Schedule
RI/FS
14 PRPs
Mar 1993
COMPLETED
Record of Decision
EPA
Sept 1993
COMPLETED
Remedial Design Start
13 PRPs
Jul 1994
COMPLETED
Remedial Action Start
13 PRPs
Jan 1997
COMPLETED
Remedial Action Completion
13 PRPs
Dec 1999
COMPLETED
NPL Deletion
EPA
Sept 2003
June 2004
-------
A-10
DUPONT NECCO PARK
Site # 14
Site Program: Federal Superfund
Summary Prepared By: EPA
Site Description
The Necco Park Site, owned by DuPont, is an inactive industrial waste landfill on
approximately 24 acres in Niagara Falls. It is surrounded on three sides by the BFI
Sanitary Landfill and the CECOS site, approximately 1.5 miles from the Niagara River.
DuPont acquired the Site in the 1930s and used it as a landfill to dispose of
approximately 93,000 tons of industrial wastes until its closure in 1977. The following
chemicals are known, from disposal records, to have been disposed at the Site: carbon
tetrachloride, chloroform, hexachlorobenzene, hexachlorobutadiene, hexachloroethane,
methylene chloride, tetrachloroethylene and trichloroethylene.
Eight aquifer zones have been identified under the Site. In the overburden, groundwater
flow is minimal, but is influenced by two water table depressions along the southern
property boundary, which are caused by two recovery wells in the upper bedrock.
Groundwater in the upper bedrock zones is partially captured by the recovery well
system. Otherwise, Site groundwater in the upper bedrock water-bearing zones
discharges down-gradient to the south. A portion of it is presumed to eventually reach
the Falls Street Tunnel (FST). Groundwater in the middle bedrock zones flows generally
to the west and is partially captured by a third recovery well. Groundwater in the middle
and lower bedrock zones flows west toward the New York Power Authority (NYPA)
conduits.
Interim Remedial Measures
Necco Park is not on the National Priorities List. However, DuPont conducted
groundwater investigations pursuant to a RCRA 3013 consent decree and a CERCLA
Administrative Order on Consent (AOC) with EPA.
The Site was capped in 1978. Since 1982, two recovery wells near the center of the
property, when operational, have recovered contaminated groundwater and established a
partial hydraulic barrier in the upper bedrock and overburden along the southern edge of
the landfill. However, some upper bedrock groundwater continued to flow south toward
the Niagara River. In order to improve containment and collection of contaminated
groundwater, an up-gradient grout curtain was installed in the bedrock in August 1989.
A third recovery well, which penetrates the middle bedrock zones at the southern
boundary of Necco Park, went into limited operation in 1992. These on-site remedial
actions have resulted in an estimated load reduction from the site of approximately 27-
55%, based on information collected pursuant to the AOC. DuPont estimates that
-------
A-ll
approximately 174 million gallons of groundwater have been pumped since 1983. Since
1989, 7400 gallons of DNAPL have been recovered, containing approximately 98,580
pounds of organic compounds.
A portion of the groundwater not recovered by the on-Site pumping wells is probably
captured (1) by the New York Power Authority conduit drain system (water in the drain
system may drain to the Falls Street Tunnel or flow north to the Forebay Canal) or (2) by
the Falls Street Tunnel directly. All the dry-weather flow through the Falls Street Tunnel
is treated by the Niagara Falls Wastewater Treatment Plant before discharge to the River.
Final Remedial Action
The remedial investigation began May 1991 and the Investigation Report was approved
in May 1994. The feasibility study (FS) (entitled "Analysis of Alternatives Report") was
approved by EPA and DEC in July 1996.
On September 18, 1998, EPA issued a Record of Decision (ROD) for the site, which set
forth the following remedy:
1. Containment of the Source Area by:
Upgrading the existing cap to meet New York State Part 360, or equivalent
standards;
Using hydraulic measures in the overburden to maintain an inward gradient
within the Source Area or installing a physical barrier (e.g., slurry wall, sheet
pile) on the southern, and portions of the eastern and western Necco Park property
boundaries;
Using hydraulic measures in the bedrock to maintain an inward gradient within
the Source Area and prevent the movement of contaminated groundwater beyond
the Source Area boundary.
2. Treatment of the extracted groundwater from the Source Area, either on-site or
off-site, to achieve the appropriate discharge requirements.
3. Collection, and off-site disposal, of DNAPL in the Source Area by:
Utilizing the existing monitoring wells network;
Utilizing any groundwater recovery wells placed in the Source Area;
The installation of additional dedicated DNAPL recovery well(s).
4. Operation and maintenance (O&M) of the existing systems and the systems
constructed under this remedy.
-------
A-12
5. Comprehensive monitoring to verify hydraulic control, identify DNAPL occurrence,
demonstrate the effectiveness of the remedial measures, and assess the impact of such
measures on far-field groundwater quality.
6. Additional characterization of the Site to assess whether natural attenuation will be
effective in addressing far-field contamination.
7. Development and implementation of institutional controls to restrict Site access, the
use of groundwater at the Site, and control land use such that it is consistent with Site
conditions.
Schedule for Completion
The Proposed Plan was released to the public in July 1996, upon approval of the FS. A
public meeting to discuss the Proposed Plan was held in August 1996, shortly after its
release. Because of extensive public comments received on the Proposed Plan, EPA
revised the Proposed Plan in response to the comments and provided a second public
comment period. A Record of Decision (ROD) was issued in September 1998. Design
studies started in October 1998. The remedial design was completed April 2004.
DuPont commenced installation of additional groundwater wells during the Remedial
Design phase. Some of these wells will serve as component parts of the hydraulic
containment portion of the final remedy. RA completion is expected by November 2005.
Because of the fractured bedrock beneath the site, future complications may arise in
achieving effective hydraulic containment. The target date is intended to allow sufficient
time to ensure that any additional remedial work to achieve effective containment can be
completed. It is also important to note that, as mentioned above under Interim Remedial
Actions, remedial actions already implemented on-Site have resulted in an estimated load
reduction from the Site of approximately 27-55%.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this Site:
Federal $ 2,155,000 (Includes EPA's indirect costs)
State $ 141,000 (Does not include travel costs)
PRP $ 42,500,000 (Unverified DuPont estimate)
It is estimated that the following amounts will be spent from now to the completion of
remediation:
Federal $ 875,000
State $ 100,000
PRP $ 65,102,000 (includes O&M)
-------
A-13
DUPONT NECCO PARK
Output
Responsible
Party
Previous Target
Date
Current
Schedule
RI
PRP
May 1994
COMPLETED
FS
PRP
Sept 1994
COMPLETED
Record of Decision
EPA
Sept 1996
COMPLETED
Remedial Design Start
PRP
Feb 1997
COMPLETED
Final Remedial Action Start
PRP
Nov 2001
COMPLETED
Remedial
Action
Completion
Grout Curtain
PRP
COMPLETED
3 Pumping Wells
PRP
COMPLETED
Final Action
PRP
Oct 2003
November 2005
-------
A-14
CECOS INTERNATIONAL
Site # 78
Site Program: RCRA (State and Federal)
Summary Prepared by: EPA and DEC
Site Description
CECOS International, Inc. operates a 385-acre commercial solid/industrial waste
management facility in the Town of Niagara and the City of Niagara Falls. The facility is
situated in an industrial and commercial area, bordering residential and recreational
areas, and is about 1.5 miles north of the Niagara River.
The site has been used for waste disposal for over 80 years. The facility managed
hazardous wastes from all Resource Conservation and Recovery Act (RCRA) categories
identified in Part 261 — characteristic wastes, specific and non-specific industrial wastes
and commercial chemical product waste. Current hazardous waste management activities
include a wastewater treatment system and container storage.
The CECOS facility is underlain by an overburden and two bedrock aquifers. A less
permeable layer of native clays and glacial till serves as an aquitard (or barrier) between
the overburden and the bedrock aquifers.
All but a minor percentage of the CECOS site groundwater flows off site to the south and
southeast and is drawn into the Falls Street Tunnel and New York Power Authority
(NYPA) conduit sink on its way to the Niagara River. The potential loading to the
Niagara River from the site overburden aquifer compared to that from the bedrock
aquifers is minor. By the time it reaches the tunnel/conduit system, the groundwater
from the overburden aquifer has found its way into the upper bedrock through
discontinuities and excavations in the native sediments. All of the dry weather flow
through the Falls Street Tunnel is treated by the Niagara Falls Waste Water Treatment
Plant.
Site Investigation
The site encompasses approximately 50 Solid Waste Management Units, including
landfills, waste piles and surface impoundments. An EPA HSWA permit and state Part
373 permit were issued in September 1988, requiring investigation/remediation of all
waste management units.
Pursuant to the requirements of the RCRA permit, in September 1991, CECOS
completed the required investigations at the facility. Groundwater contaminants were
mainly detected in the central area of the site, in the three groundwater transmissive
zones monitored by CECOS. The volatile organic compounds (VOC) detected include
-------
A-15
acetone, 2-butanone, benzene, chloroform, toluene, chlorobenzene, methylene chloride,
and tetrachl or ethane.
Interim Corrective Measures (ICM)
An interim groundwater recovery system has been pumping contaminated groundwater
from all three zones since 1990. The recovery system was started with four recovery
wells and currently consists of 20 recovery wells. The pumped groundwater is treated
on-site and discharged to the City of Niagara Falls wastewater treatment plant. From
July 1991 through August 1998, over 60 million gallons of groundwater have been
treated, and over 2,500 pounds of organic compounds were removed.
In addition, several interim measures consisting of the removal of contaminated soils and
wastes have been completed at the following units: surface impoundments, phenolic
resin area, and sewage sludge area. Post-closure permit/HSWA modification for the
closed hazardous waste landfills was issued in September 1991.
A final remedy for the Scrap Yard Area was incorporated into the DEC/EPA permit
modification of September 1991. The remedy, implemented in 1992, consisted of:
Removal and off-site disposal of approximately 24,000 cubic yards of soil
contaminated with PCBs, organic compounds, and metals
Construction of a low permeability cover
Long-term inspection and maintenance of the cover, and monitoring of the
groundwater.
All of the interim remedial actions that have come due at this site have been
accomplished.
Corrective Measures Study
A RCRA Facility Investigation (RFI) and a Corrective Measures Study have been
completed. The final, site-wide corrective measures for the CECOS site were selected
through the DEC Part 373 permit renewal process. The permit was renewed in February
1995. The final corrective measures consist of:
Groundwater extraction and on-site treatment (prior to discharge to the City of
Niagara Falls Wastewater Treatment Plant);
Maintenance of existing caps and pavement over areas of residual contamination;
Restrictions on future land development; and
Restrictions on public access to the facility.
The interim groundwater pump-and-treat program has been successful in containing and
remediating the groundwater contamination at the facility. However, as part of the final
-------
A-16
remedy, this interim remedial system will be enhanced to expand the groundwater
capture zone and facilitate a more rapid clean-up of the site.
CECOS submitted a Corrective Measure Implementation (CMI) design in August 1995
and prepared an addendum to the design plan that included an aquifer pumping test
program. A short-term pumping test was conducted in October-November 1995 to
evaluate the potential use of existing wells as both pumping wells and monitoring wells
for the CMI. An extended trial CMI pumping test was conducted in February-May 1996
to test additional wells and to optimize pumping rates over a longer duration (to
determine the extent of long-term capture zones to control contaminant migration).
Several existing recovery wells, an existing collection drain, and a new recovery well are
being operated for the CMI. CECOS submitted a new CMI design in November 1996.
The CMI was started up in December 1996. The remedial system continues to be
operated.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
Federal $ (Not available)
State $ (Not available)
PRP $ (Not available)
It is estimated that the following amounts will be spent from now to the completion of
remediation:
Federal $ (Not available)
State $ (Not available)
PRP $ (Not available)
-------
A-17
CECOS INTERNATIONAL
Output
Responsible Party
Previous
Target Date
Current
Schedule
RFI Work Plan Approval
DEC/EPA
Sep 1989
COMPLETED
RFI Completion
Permittee
Sep 1991
COMPLETED
Stabilization Start-up
(Groundwater)
Permittee
COMPLETED
Start-up of CMI (Scrap Yard)
Permittee
COMPLETED
CMS Work Plan Approval
DEC/EPA
Apr 1992
COMPLETED
CMS Completion
Permittee
Apr 1993
COMPLETED
Remedy Selection (site-wide)
DEC/EPA
Dec 1994
COMPLETED
CMI Work Plan Approval
(site-wide)
DEC/EPA
Apr 1995
COMPLETED
Start-up of CMI (site-wide)
Permittee
Apr 1996
COMPLETED
-------
A-18
OCCIDENTAL CHEMICAL - HYDE PARK
Site #39
Site Program: Federal/State Co-lead: Superfund
Summary Prepared by: EPA
Site Description
Occidental Chemical Corporation's (OCC) Hyde Park site is a 15-acre landfill in
northwest Niagara Falls, less than one-half mile from the Niagara River.
From 1953 to 1975, the company (then Hooker Chemicals and Plastics) deposited
approximately 80,000 tons of chemical wastes at the site. The hazardous materials
disposed on site included 3,300 tons of 2,4,5-trichlorophenol (TCP) wastes, which are
known to contain significant amounts of 2,3,7,8-tetrachlorodibenzo-p-dioxin (TCDD);
approximately 0.7 - 1.6 tons of dioxin are believed to be associated with the TCP.
Chlorinated organic wastes, including hexachloropentadiene derivatives, chlorendic acid,
chlorinated toluenes, benzenes and phenols, predominate at the site. The former drainage
stream of the landfill, Bloody Run, which flows into the Niagara River, was historically
contaminated with organic chemicals, including dioxin. A clay cap and a shallow
leachate collection system were installed at the site in 1979.
There is an overburden and a bedrock aquifer present under this site. Groundwater flows
both downward and horizontally through the fractures and layers of the bedrock. The
aquifers flow generally northwest, toward the Niagara River Gorge. Contaminants have
migrated from the site in both aqueous and non-aqueous phases in the overburden and
bedrock. Dioxin from the site has previously been found in contaminated groundwater
seeping to the River from the Gorge face, located 1,600 feet west-northwest of the site.
Remedial construction at the site was completed in June 2003. The remedial actions
taken to date have substantially reduced off-site migration. Since the installation of an
overburden remediation system in 1991, groundwater in the overburden is no longer
migrating horizontally past the remediation system around the site. Therefore, no loading
of hazardous substances from the site to the Niagara River via groundwater in the
overburden is currently taking place. Containment of bedrock groundwater has also been
achieved across the NAPL plume boundary.
Until 2003, OCC was unable to demonstrate that the contaminated bedrock groundwater
was being contained. The original site conceptual model separated the bedrock aquifers
into three groundwater zones (upper, middle and lower). Subsequent to the development
of a groundwater model, OCC conducted field investigations from 2001 to 2003,
including down-borehole geophysics and water-level measurements in 113 piezometers.
The analysis of the field data resulted in a revised hydrolgeologic framework consisting
of eleven discrete flow zones separated by aquitards. OCC has documented its revised
hydrogeologic framework in two documents: Site Characterization Report: Revised
-------
A-19
Geologic and Hydrogeologic Characterization (2/02) and Site Characterization Report:
Hydrologic Characterization (2/03). Groundwater monitoring has been conducted in the
eleven flow zones since late 2002 and OCC is currently building a data base of water-
level measurements.
OCC issued the Site Characterization Report: Remedial Characterization Report (6/03)
which concluded that the Bedrock NAPL Plume Containment System satisfies the
performance objectives of the RRT and that the contaminated bedrock groundwater was
being contained. OCC also performed an analysis of the groundwater chemistry in the
area. OCC concluded in the Major Ions Study (11/03) that the relative age of the
groundwater between the pumping wells near the site and the Niagara Gorge is younger
than the age of the groundwater underneath the landfill. This indicates that the bedrock
wells are effectively preventing the migration of groundwater from the site to the Gorge.
In addition, sampling results indicated that the seeps are primarily surface runoff, not
groundwater. The APL purge wells at the gorge face have dried up the groundwater near
the Gorge. Sampling at the gorge face seeps, conducted annually since 1997, has not
detected dioxin, which was found in previous gorge face surveys.
Requisite Remedial Technology Agreement
The site is a joint EPA/DEC-lead Superfund site on the National Priorities List and is
governed by a pre-CERCLA settlement agreement. EPA sued to require OCC to
remediate the site in 1979. In January 1981, EPA, DEC, and OCC filed a Stipulation and
Judgment Approving Settlement Agreement. Since 1982, OCC has been implementing
the settlement agreement. Agreement on a Requisite Remedial Technology (RRT) was
approved by the court in 1986. The RRT included:
Source Control (prototype landfill extraction wells);
Containment and collection of contaminants in the overburden (overburden
barrier collection system) and the Lockport bedrock (purge and recirculation
wells);
An Intermediate and Deep Formations Study (monitoring wells);
• A Community Monitoring Program (monitoring wells) for early detection of
plumes;
An Industrial Protection Program for neighboring industries;
Treatment and monitoring of collected leachates:
Aqueous-phase liquids to be treated on-site;
Non-aqueous phase liquids to be destroyed by incineration;
Site Capping;
Gorge Face Seep Remediation to isolate seeps from the public;
A TCDD bioaccumulation study in Lake Ontario; and
Bloody Run Creek excavation and monitoring; and
• Long-term monitoring.
-------
A-20
Major Remedial Activities
Action
Start
Complete
Intermediate Formation Wells
10/88
12/89
Leachate Storage Facility
05/89
Leachate Treatment Facility
04/91
Upgrade APL Treatment System
01/98
03/98
Lagoon Closure
07/90
01/92
Phase I Source Control Extraction Wells Installed
04/90
06/90
Phase II Source Control Extraction Wells Installed
04/94
07/94
Overburden Barrier Collection System
11/90
APL/NAPL Plume Redefinition
04/90
07/90
Recirculation Wells
01/91
03/91
Cluster Monitoring Wells
06/90
09/90
Landfill Cap
08/94
12/94
Phase I Prototype Purge Wells Installed
04/90
07/90
Phase II Prototype Purge Wells
03/93
12/93
Phase III Purge Wells
05/96
05/97
3 Bedrock Purge Wells and Force Mains Installed
03/98
12/98
3 Additional Bedrock Purge Wells and Force Mains
03/99
12/99
Groundwater model
4/00
2/01
Conceptual Evaluation of NAPL Plume Containment
12/00
3/01
Upgrade of Leachate Treatment Facility to 400 gpm
4/01
6/01
4 Additional wells installed in NW corner of site
6/01
12/01
Site Characterization (Geophysics, Hydraulic Evaluation)
6/01
12/01
Retrofitting of Site Monitoring Wells
5/02
11/02
Re-eva.lna.ti on of NAPL Plume Containment
17./0?.
6/03
The status of activities included in the schedule follows.
-------
A-21
Community Monitoring Wells provide early detection of chemical migration. They are
sampled and analyzed quarterly to ensure the safety of the community. The well data
confirm that the hydraulic gradient near the community is downward, thereby ensuring
that chemical migration toward the community is not an issue.
Under the Industrial Protection Program, sumps in neighboring industries have been
sealed, as have some manholes.
Fences were used to prevent access to the Gorge Face seeps; seep water has been
diverted into culverts and pipes to prevent humans from being exposed to the potentially
contaminated water; and contaminated sediments were scraped away. Monitoring of the
fenced seeps has been conducted annually since 1989. Results continue to indicate no
need for additional control or remediation of the seep areas. Annual inspections are
performed at all recorded seep locations, and the fences around the seeps are not required
anymore.
The on-site Leachate Storage and Handling Facility was completed in April 1990.
155,000 gallons of NAPL which had been stored on-site in the lagoons and four railroad
tank cars were pumped into the leachate storage facility and the lagoons were closed in
January 1992.
The Treatment Facility was brought on-line in April 1991. The contaminants collected
through the remedial systems are treated on-site. Aqueous-phase liquids pass through an
inclined plane settler, filters, and sacrificial carbon pre-treatment to remove dioxins and
PCBs. This is followed by activated carbon treatment. All vapors in the closed system
are treated. In March 1998, the APL treatment system was upgraded to handle a higher
flow of 100-150 gallons per minute. In the spring of 2001, OCC completed upgrading
the capacity of the treatment system to 400 gallons per minute in June 2001 so it can
adequately handle excess water in wet weather.
NAPL is trucked to Laidlaw Environmental Services in Deer Park, Texas, for
incineration. To date, approximately 400,000 gallons of NAPL have been destroyed.
Prior to the trucking, NAPL was destroyed at OCC's Niagara Plant Incinerator. The
plant's permit was modified by EPA and DEC in November 1990 to allow destruction of
NAPL from Hyde Park (and other Occidental sites). This was the first commercially-
owned incinerator in the U.S. specifically permitted to destroy dioxin wastes.
The Overburden Barrier Collection System (OBCS), a drain system around the entire
landfill, was installed in 1990. Occidental continuously operates its pumps, preventing
the migration of contaminants through the overburden.
Installation of two 36-inch diameter Source Control extraction wells within the landfill
itself was completed in June 1990. Phased pump tests were conducted and evaluated
throughout 1991 and 1992. Based on the results of these pump tests, four additional
-------
A-22
source control wells of smaller diameter were installed in the landfill in 1994. With the
completion of the new cap on the landfill and completion of the OBCS, the need for
source control wells has diminished. Of the original six source control wells, only three
remain in service. These are manually operated on a weekly basis due to very low
recovery rates. Collected liquids are taken to the Leachate Storage Facility.
The Lake Ontario TCDD bioaccumulation study was completed in May 1990. Fish and
sediment samples from Lake Ontario were analyzed for TCDD, and a laboratory study of
the uptake of TCDD by lake trout was conducted.
In 1990, the extent of the aqueous-phase liquid/non-aqueous phase liquid plumes in the
overburden and bedrock were redefined. This information was considered in the
implementation of the remedy for the site.
Excavation of Bloody Run Creek began in October 1992 and was completed in March
1993. Occidental removed 29,200 cubic yards of contaminated sediment and lined the
creek bed with rocks. Samples taken at the bottom and sides of the excavation confirmed
the effectiveness of this remedy.
The sewer under University Drive adjacent to Niagara University was sealed and a new
sewer was installed in 1993. A sewer was relocated at TAMS Ceramics, a neighboring
industrial plant in 1989, and the College Heights sewer was remediated in 1990.
The perimeter cap of the landfill was completed in 1991. A low permeability cap was
placed over the entire landfill in 1994.
The objective of the bedrock NAPL plume containment system is to create a "zone of
capture" around purge wells down gradient of the landfill so that contaminated ground
water can be collected in these purge wells and pumped to the Leachate Treatment
Facility. The bedrock purge well system was installed in a phased approach:
Phase I of the system was installed in the NAPL plume area and pump tests were
performed on individual and multiple wells. Based on these tests, additional
purge wells (Phase II) were installed in late 1993.
Pump tests were performed on the Phase II wells in early 1994 to determine if
there was an adequate zone of capture surrounding these wells. Phase II wells did
not meet the performance criteria and more wells were needed.
OCC installed Phase III wells in 1997, along with the associated monitoring
wells. The force mains to connect these wells to the Hyde Park Leachate
Treatment Plant were completed in May 1997.
Phase III monitoring indicated that the bedrock NAPL collection system in this
area still did not meet performance criteria. Three pumping wells were installed
and connected by force mains to the on-site treatment facility in 1998. Three
additional wells were installed and connected to force mains in 1999; one
additional well and five monitoring wells were installed in 2000.
-------
A-23
Four additional wells were installed in 2002 and a NAPL recovery well was
converted to an extraction well.
Hydrogeologic studies conducted in 2000-2003 resulted in a revised conceptual
model for the site which includes eleven discrete flow zones in the bedrock. OCC
modified the existing monitoring well system and these wells are now screened to
monitor the individual flow zones to better delineate the groundwater capture.
• OCC issued the Site Characterization Report: Remedial Characterization Report
(6/03) which concluded that the Bedrock NAPL Plume Containment System
satisfies the performance objectives of the RRT and that the contaminated
bedrock groundwater was being contained. OCC also issued the Major Ions
Study (11/03) which concluded that the relative age of the groundwater between
the pumping wells near the site and the Niagara Gorge is younger than the age of
the groundwater underneath the landfill. This indicates that the bedrock wells are
effectively preventing the migration of groundwater from the site to the Gorge.
Remedial construction at the site was completed in June 2003. EPA issued a
Preliminary Close-out Report (6/03) documenting the construction completion.
EPA will issue a Remedial Action Report in September 2004 which will
document all the remedial actions taken at the site.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
Federal $ 12,000,000
PRP $ 70,000,000
It is estimated that $ 2,000,000/year will be spent on the Operation and Maintenance of
the site for approximately the next 30 years.
-------
A-24
OCCIDENTAL CHEMICAL - HYDE PARK
Output
Responsible
Party
Target Date
Current Schedule
Remedial Action Completed for
Bloody Run Creek
PRP
Jan 1993
COMPLETED
March 2003
Remedial Systems Construction
Completed (See above table for
detailed list of remedial actions)
PRP
March 1996
COMPLETED
June 2003
Remedial Action Completion*
PRP
March 1997
COMPLETED
June 2003
Remedial systems are considered "operational" when they are operating as designed and are
meeting their performance criteria. Once the remedial systems are declared operational, the
Remedial Action is completed. Then, the Operation and Maintenance period follows.
-------
A-25
102nd STREET
Sites # 40, 56, 85, and 94
Site Program: Federal Superfund
Summary Prepared By: EPA
Site Description
The 102nd Street site is located at the eastern edge of the City of Niagara Falls, on the
banks of the Niagara River. The site encompasses 22.1 acres, owned by two Potentially
Responsible Parties (PRPs): 15.6 acres are owned by Occidental Chemical Corporation
(formerly Hooker Chemical and Plastics Corporation) and 6.5 acres are owned by Olin
Chemical Corporation.
This landfill was used from 1943 to 1971 for the disposal of an estimated 159,000 tons of
wastes, including organic and inorganic phosphates (1,300 tons),
hexachlorocyclohexanes (>1,500 tons), chemical and demolition wastes, and fly ash.
There are overburden and bedrock aquifers present under this site. A clay and till layer
acts as an aquitard (or barrier) between the overburden and the bedrock. Although water
flows in several directions in each aquifer, the average flow direction and ultimate
discharge point is south to the Niagara River.
Site Investigation
This National Priorities List site has been the subject of state and federal litigation, and is
a joint EPA/DEC-lead Superfund site. EPA and the State of New York sued Occidental
Chemical Corporation and the Olin Corporation in December 1979.
Interim remedial efforts taken at this site include bulkheading along the shoreline to
minimize erosion into the river and the installation of a clay cap in the 1970s.
A Remedial Investigation (RI) was performed to determine the nature and extent of
contamination in the soils and ground water. The RI, Feasibility Study (FS) and the
Record of Decision (ROD) were completed in 1990.
The EPA issued an Administrative Order in September 1991, requiring the companies to
perform the remedial design and remedial action. An "Intent-to-Comply" letter was
signed by the PRPs in October 1991, at which time the Remedial Design started.
Remedial Design
The remedial design of this site was delayed when the natural resource trustees (federal
and state) expressed concerns about 5 acres of the embayment that was proposed in the
design to be enclosed within a slurry wall and covered by the final landfill cap. Design
-------
A-26
modifications were explored to reduce the embayment loss to approximately 2 to 3 acres
by constructing the slurry wall closer to the shoreline. The 1990 ROD, however,
required that hot spots of contaminated sediments that would be outside the slurry wall be
excavated and incinerated. The proposed design change would have left known hot spots
of contaminated sediment outside the slurry wall, substantially changing the scope and
cost of the remedy from that initially contemplated. A Record of Decision Amendment,
signed by EPA in June 1995, eliminated the contingency requiring the incineration of any
hot spots of sediments that would be left outside the slurry wall. The amended ROD
required these sediments to be excavated and placed behind the wall within the
encapsulated landfill.
Remedial Activities
Construction of remedial activities began in March 1996. A cofferdam was built around
the embayment. After a fish survey was completed, game fish were removed from the
embayment. Contaminated sediments were removed from the embayment. Perimeter
soils were excavated and placed on-site. The redesign discussed above enabled over 2
acres of embayment water resources to be saved. A slurry wall was built around the site
to prevent contaminants from leaking into the River. The final landfill cap was
completed in 1998, to prevent rainwater from infiltrating the waste and carrying
contamination off-site.
An additional change in the remedial design was made to take advantage of excess
capacity at the Love Canal Treatment Plant. Instead of on-site leachate treatment, a force
main was constructed to pump leachate from the 102nd Street Site to the Love Canal
Treatment Plant. This change did not delay the completion and optimization of the final
remedial action.
The leachate pumping system was completed in December 1998, at which time the
potential for contaminants to run to the River from this site was eliminated. Landscaping
and optimization of the pump-and-treat system was completed in March 1999. The long-
term operation and maintenance of the site is ongoing.
Monitoring
Initial monitoring results obtained at the site indicate that the remedy is performing as
designed.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
Federal $ 9,900,000 (Indirect costs not included.)
State $ (State costs are included with EPA costs)
PRP $ 26,000,000
-------
A-27
Costs for Operation and Maintenance expected to be incurred in the future are
approximately $100,000 per year, and will be paid by the PRPs.
102ND STREET
Output
Responsible Party
Current
Schedule
Final RI/FS Report
PRPs (Olin and
Occidental)
COMPLETED
Record of Decision
EPA/DEC
COMPLETED
Record of Decision Amendment
EPA/DEC
COMPLETED
Remedial Design Start
PRPs
COMPLETED
Remedial Action Start
PRPs
COMPLETED
Remedial Action Completion
PRPs
COMPLETED*
The potential for contaminants to flow to Niagara River from this site was
eliminated in December 1998, when the leachate pumping system was completed.
Landscaping and optimization of the pump-and-treat system was completed in
March 1999.
-------
A-28
BELL AEROSPACE TEXTRON
Site # 5
Site Program: RCRA (State and Federal)
Summary Prepared by: EPA and DEC
Site Description
The Bell Aerospace Textron plant is located approximately 2.5 miles north of the Niagara
River, adjacent to the Niagara Falls International Airport.
Between 1950 and 1980, the company used an unlined 60' X 100' surface impoundment
to collect wash water from rocket engine test firings, storm run-off, and solvent drippings
from cleaning, degreasing, and anodizing operations. Hazardous waste and constituents
of concern include trichloroethylene and dichloroethylene. The wastes were discharged
to a sanitary sewer after pH adjustment.
Beneath the site lies one overburden and two bedrock aquifers. Groundwater flow
through the overburden aquifer is primarily to the south-southeast. There is a potential
vertical flow between the overburden and the upper bedrock aquifer, and at least some of
the groundwater from the overburden discharges to Bergholtz Creek. The upper bedrock
aquifer flows primarily in a southeasterly direction and in the lower bedrock aquifer
groundwater flow is generally to the south. The down-gradient extent of groundwater
contamination in each of the three aquifers has been well defined, and, as of this update,
no contaminated groundwater appears to be discharging directly to the Niagara River.
Remedial Actions
Bell Aerospace Textron is an RCRA site with a closed surface impoundment. The
company excavated 1225 tons of contaminated soil and capped the area in 1987.
All of the remedial actions that were required here have been accomplished on schedule.
Since the initial 1989 hazardous waste site report, an RCRA Facility Investigation (RFI)
has determined the extent of contaminant migration and a Corrective Measures Study
(CMS) has addressed on- and off-site groundwater contamination. A State Part 373 post-
closure permit was issued to Bell Aerospace in September 1992, which will expire in
September 2003. The permit required final Corrective Measures Implementation (CMI),
consisting of groundwater pump-and-treat programs for on- and off-site contamination.
In addition, in October 2001 the facility has installed (on a voluntary basis) monitoring
wells through the cap of the Neutralization Pond as part of an ongoing investigation of
the natural degradation of groundwater contamination at the facility.
-------
A-29
The overall remedial program is designed to intercept the bedrock groundwater that is
migrating off-site toward the Niagara River. It consists of the installation of 11
groundwater extraction wells.
The off-site remedial system was started up in April 1993. It is achieving its designed
objective. The capture zone associated with the system covers the area of groundwater
contamination, and the areal extent of the contamination is diminishing. Five extraction
wells have been installed to contain the off-site groundwater. However, as the off-site
plume has become smaller, four extraction wells were determined to be optimal for
pumping. The extracted groundwater contamination is discharged into the publicly
owned treatment works (POTW) of the Town of Wheatfield. The off-site system is
designed to recover two pounds of volatile compounds daily. The performance of the
off-site remedial system is considered acceptable.
The on-site remedial system began the start-up operating period in April 1995. Several
technical problems prevented the on-site system from attaining all of its design
objectives. The remedial system was redesigned to address these problems, and the
following two modifications were made:
the installation of a 900 foot-long pipeline to divert the cooling water discharge
from a rocket testing facility operating at the site to the storm drainage system;
and,
the installation of a slurry wall barrier along the main sewer line on Walmore
Road to prevent the water migration from the sewer line to the on-site system.
However, even after these modifications, the on-site system was still not attaining
satisfactory hydraulic containment. To address this, an additional extraction well was
installed along the southern boundary of the site. This well was installed in July 1998,
and is currently in operation. The operation of this well has increased the groundwater
capture zone along the southern edge of the facility, but the capture zone was not
consistently continuous from two of the five extraction wells. A higher capacity pump
has been in operation on the new well since August 20, 1999, thus increasing the
groundwater pumping rate.
With the above modifications, the on-site system is achieving its design goals. The on-
site system has been effective in creating a groundwater capture zone over the DNAPL
plume, therefore, all contaminated groundwater is being intercepted and treated on-site,
so that no loading is migrating from the site. Six extraction wells are currently operating
in the on-site system. The operation of the higher capacity pump has maintained a
continuous capture zone. Monitoring data of 2002-2003 indicates a complete capture
zone has been obtained along the southern boundary. The on-site system is designed to
recover four pounds of volatile compounds daily.
-------
Remediation Costs
A-30
Following are estimated amounts that have been spent through March 2004 on
remediating this site:
Federal $ (Oversight costs not available)
State $ (Oversight costs not available)
PRP $ 1,811,391 (Capital/Operation/Maintenance)
It is estimated that the following amounts will be spent from April 2004 over the next ten
years for operation and maintenance.
Federal $ (Not available)
State $ (Not available)
PRP $ 462,500
BELL AEROSPACE TEXTRON
Output
Responsible Party
Previous
Target Date
Current
Schedule
RFI Work Plan Approval
DEC/EPA
May 1990
COMPLETED
RFI Work Plan Approval for
Phase II
DEC/EPA
None
COMPLETED
RFI Completion
Permittee
Jul 1991
COMPLETED
CMS Work Plan Approval
DEC/EPA
Dec 1991
COMPLETED
CMS Completion
Permittee
May 1992
COMPLETED
Remedy Selection
DEC/EPA
Oct 1992
COMPLETED
CMI Work Plan Approval
(off-site)
DEC/EPA
Apr 1993
COMPLETED
CMI Work Plan Approval
(on-site)
DEC/EPA
Sep 1993
COMPLETED
Start-up of CMI (off-site)
Permittee
Apr 1996
COMPLETED
Start-up of CMI (on-site)
Permittee
Nov 1994
COMPLETED
-------
A-31
DUREZ CORPORATION, PACKARD ROAD FACILITY, NIAGARA FALLS
(Formerly Occidental Chemical — Durez Division, Niagara Falls)
Site # 66
Site Program: RCRA (State and Federal)
Summary Prepared by: EPA and DEC
Site Description
Occidental Chemical Corporation (OCC) operates a phenol-formaldehyde resin
manufacturing plant at 5000 Packard Road, Niagara Falls, known until June 1986 as the
Varcum Chemical Division of Reichhold Chemicals, Inc. and until October 1989 as BTL
Specialty Resins. The 5-acre site is approximately 3 miles north of the Niagara River.
The hazardous wastes generated at this site are ignitable and/or toxic solvent washings
from reactor vessels, spilled raw materials and small amounts of laboratory samples.
These wastes are accumulated, stored, treated, and incinerated on site.
Under this site lie one overburden aquifer and four bedrock aquifers. Bedrock
groundwater flow is along both horizontal and vertical fractures. In general, the
groundwater flow direction before remedial activities took place at the site was south to
southwest, with the upper most bedrock aquifer flowing southeast.
Interim Remedial Measures
Three recovery wells began pumping in February 1989 to capture and remediate the
groundwater under the site. These recovery wells affected groundwater flow in the
overburden and the upper bedrock aquifers. Most of the contaminated groundwater from
the uppermost bedrock aquifer and from the aquifer below it is captured by the recovery
wells.
In May 1990, DEC issued OCC a state Part 373 Permit for the storage, treatment, and
incineration of hazardous waste on-site. An EPA Hazardous and Solid Waste
Amendments (HSWA) permit was issued in March 1991. Both permits required
corrective action. As required by the permits:
Four carbon-steel tanks were installed to replace a 30,000 gallon hazardous waste
storage tank;
The incinerator was modified with a larger burner, an expanded combustion
chamber, a new double-layered refractory, a new control system, automatic alarm,
and waste feed cut-off systems, and new instrumentation and piping. Prior to
operation, a trial burn was conducted;
Approximately 3,000 tons of phenolic-contaminated soil were removed from the
tank farm area in 1990. Additional areas with contaminated soils were capped.
-------
A-32
Site Investigation and Additional Interim Remedial Measures
The RCRA Facility Investigation (RFI) Work plan was approved in May 1990, and the
RFI was completed in November 1992. The main area of chemical presence is beneath
the tank farm area on the east side of the facility. The predominant overburden and
bedrock groundwater contaminants are total recoverable phenolics, ethylbenzene, total
xylenes, 1,2-dichlorobenzene, and 1,4-dichlorobenzene. The vertical extent of
groundwater contamination is limited to the overburden and the first three bedrock
aquifer zones. With the exception of the tank farm area, chemical concentrations in the
soils were less than action levels for soil ingestion. The soils are not a significant source
of groundwater contamination; nevertheless, all open spaces on the site have been paved
over.
As an interim corrective measure, beginning in February 1989, OCC has pumped
bedrock ground water contaminated with phenols and other organics (primarily non-
chlorinated solvents) to its biological treatment facility, prior to discharge to the Niagara
Falls Wastewater Treatment Plant. EPA and DEC required OCC to submit interim
reports to assess whether groundwater was being remediated adequately, and to assess
the need for modifications, such as increasing pumping rates or installing additional
wells. The groundwater pumping rate was doubled in 1990 with the addition of new
treatment capacity at OCC's treatment facility which was constructed that year. Also, as
an interim corrective measure to address the overburden groundwater contamination at
the tank farm area, an overburden drain tile collection system began operating in 1993.
The purged water is pretreated in the on-site wastewater treatment facility, prior to
discharge to the Niagara Falls Wastewater Treatment Plant.
From April 1994 through August 1998, 22,624,389 gallons of bedrock groundwater were
pumped and treated. Since the start-up of the drain tile system in January 1993 through
August 1998, 189,620 gallons of overburden groundwater have been removed and
treated. Approximately 25,442 pounds of contaminants have been removed.
Remedial Actions
The Corrective Measures study report has been approved. EPA and DEC have
determined that the existing groundwater recovery systems which have been operating as
interim corrective measures are capable of serving as the final groundwater remedy for
the facility. The DEC Part 373 permit was modified in September 1995 to specify the
final corrective measures. In addition to operation of the groundwater recovery systems,
the final corrective measures include maintaining existing caps and pavement over areas
of contaminated soil, restricting site access, and restricting future site development.
Pursuant to the DEC Part 373 permit, OCC prepares monthly reports on the operating
status of the groundwater recovery systems and is required to prepare comprehensive
annual reports on performance monitoring of the recovery systems. The performance
monitoring includes hydraulic monitoring, to establish the extent of plume capture, and
chemical monitoring, to evaluate changes in groundwater quality.
-------
A-33
The remedial actions that have come due at this site have been accomplished ahead of
schedule, and Corrective Measure Implementation is underway.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
Federal $ (Not available)
State $ (Not available)
PRP $ (Not available)
It is estimated that the following amounts will be spent from now to the completion of
remediation:
Federal $ (Not available)
State $ (Not available)
PRP $ (Not available)
OCC - DUREZ, NIAGARA FALLS
Output
Responsible
Party
Previous
Target Date
Current
Schedule
RFI Work plan Approval
DEC/EPA
Jul 1990
COMPLETED
RFI Completion
Permittee
Sep 1992
COMPLETED
Stabilization Start-up
Permittee
COMPLETED
CMS Work plan Approval
DEC/EPA
Jun 1993
COMPLETED
CMS Completion
Permittee
Dec 1993
COMPLETED
Remedy Selection*
EPA/DEC
Dec 1994
COMPLETED
CMI Work plan Approval
EPA/DEC
Feb 1995
COMPLETED
Start-up of CMI
Permittee
Dec 1996
COMPLETED
EPA and DEC have determined that the existing interim corrective measures groundwater
pump-and-treat program is capable of serving as the final groundwater remedy for the site. The
DEC Part 373 permit was modified in September 1995 to formally select the final remedy.
-------
A-34
OCCIDENTAL CHEMICAL S-AREA
Site # 41A
Site Program: Federal/State Co-lead: Superfund
Summary Prepared by: EPA
Site Description
The S-Area site is an eight-acre landfill on Occidental Chemical Corporation's (OCC)
Buffalo Avenue Plant in Niagara Falls. The site is located approximately 200 yards north
of the Niagara River and immediately to the west of the former location of the old City of
Niagara Falls drinking water treatment plant.
The site was used primarily from 1947 to 1961 for the disposal of approximately 63,000
tons of organic and inorganic chemicals. Chemicals deposited at the site included
chlorobenzenes, organic phosphates, acid chlorides, phenol tars, thionyl chloride,
chlorendic acid, trichlorophenol, benzoyl chloride, liquid and chlorotoluene-based
disulfides, metal chlorides, thiodan, and miscellaneous chlorinated hydrocarbons.
One overburden and four bedrock aquifers exist under this site. While the bedrock
aquifers flow generally north-northwest onto the main OCC - Buffalo Avenue Site, only
the overburden aquifer flows south to the Niagara River.
Requisite Remedial Technology Agreement
This National Priorities List site is a joint EPA/DEC-lead responsibility, governed by a
judicial settlement agreement, effective June 1985. The agreement provided for a source
control remedy, monitoring programs, and a remedial plan for the Niagara Falls Drinking
Water Treatment Plant (DWTP). The DWTP main bedrock intake tunnel was shut down
due to the presence of non-aqueous phase liquid (NAPL) contamination. In the interim,
the City's backup, emergency intake pipe was used to draw water from the Niagara River.
The S-Area site was surveyed by OCC from December 1986 to April 1988 to determine
the extent of chemical migration from the landfill. This survey was the basis for a
Requisite Remedial Technology (RRT) report to EPA in November 1988.
As a result of the RRT Report and subsequent RRT negotiations among EPA/DEC, OCC
and the City of Niagara Falls, an amendment (RRT stipulation) to the 1985 settlement
agreement was submitted to the court in September 1990 and approved in April 1991.
The RRT stipulation included construction of a new DWTP for the City of Niagara Falls
at a new location, to be funded by the City and OCC.
-------
A-35
Remedial Actions
Most of the collection and containment remedial systems were installed at the landfill
from 1990 to 1995. Initial testing and operational start-up began on November 1, 1995.
The remedial systems are designed to eliminate the contaminant loadings from the site to
the Niagara River by containment and collection of contaminated ground water and
NAPL. Contaminated ground water and NAPL are currently being collected.
Contaminated groundwater is treated on-site. NAPL is incinerated at RCRA-approved
facilities off site. Assessment of the remedial systems performance began in early 1997,
and is being done on a semi-annual basis.
One of the components of the landfill remedy (drain collection system) did not function
as designed during its initial operation. An investigation in late 1997 revealed that the
system was improperly installed. OCC's efforts to enhance the performance of the drain
collection system in 1998 were unsuccessful and the EPA/DEC directed OCC to replace
the system in 1999. The new drain collection system was completed in early 2000 and its
performance is presently being evaluated.
The work on the new drain collection system delayed the construction of the final landfill
cap. The construction of the final landfill cap began in August 2000 and was completed
in April 2002.
The new DWTP was completed and fully operational by March 1997. The remedial
activities for the old DWTP and property, including the decommission and demolition of
the plant, had to wait until the new DWTP was built and on-line. The demolition of the
old DWTP was performed in 1997 and early 1998. The eastern barrier wall, which
adjoins the other three sides of the S-Area barrier wall, was completed in May 1998. The
overburden drain collection system for the former DWTP was completed in 1999.
Construction of the DWTP cap was completed in 1999.
Securement of the raw water intake structures from the old DWTP was scheduled for
completion in 2000. The grouting of the 5,000-foot long DWTP bedrock intake tunnel
commenced in August 2000. However, due to problems encountered in the field, the
remediation of this tunnel was not properly completed. A confirmatory boring sampling
program was conducted in the summer of 2001, whereby a major void was discovered in
the tunnel grouting along a portion of the tunnel under Buckhorn Island and the Niagara
River. It has been agreed by all regulatory parties and OCC that this ungrouted section of
tunnel poses no discernable environmental threat and will be used to monitor the
groundwater beneath the Niagara River at this location. A monitoring well was installed
to sample the water in the tunnel in August 2002. This well will be sampled as part of
the overburden sampling program.
Low-level VOC contmination was observed to be present in the void water. It was
agreed by EPA and the State to allow OCC to inject Sodium Permanganate into this void
-------
A-36
and observe the results to determine if the contamination is an artifact of the tunnel
grouting activities or is migrating through the bedrock.
The full remedial program for this site consists of:
A slurry barrier wall in the overburden to contain the NAPL plume;
Installation of a drain system and collection wells (i.e., pumping wells) in the
overburden, within the barrier wall, to: 1) collect contaminated ground water and
NAPL, and 2) create an inward hydraulic gradient across the barrier walls and an
upward hydraulic gradient from the underlying bedrock to the overburden within
the barrier wall;
Installation of wells in the bedrock to contain NAPL by creating an inward
hydraulic gradient across the bedrock NAPL plume boundary, and to collect
NAPL from the bedrock, to the maximum extent practicable;
Capping of the site to reduce infiltration;
Overburden and bedrock monitoring to determine the effectiveness of remedial
systems;
Incineration of non-aqueous-phase liquids; and
Treatment of contaminated groundwater by carbon adsorption and discharge to a
permitted outfall.
The remedial systems will continue to operate for at least 30 years.
The following progress has been made:
The northern, western, and southern portions of the barrier wall were built in late
1994/early 1995.
The drain collection system, collection wells, and the force mains for the drain
and collection wells were completed in 1995 for the landfill. Additional wells
were installed in 1997 to improve the performance of the system in collecting
NAPL. The drain collection system for the former DWTP property was
completed in 1999.
Operation of the landfill drain collection system and collection wells began in
1996. As noted above, the drain collection system did not function as designed
due to damage of the collection pipe and non-functioning stone backfill. The
system was replaced in 1999-2000.
A leachate storage facility and carbon adsorption treatment facility have been
constructed on site and currently receive contaminated groundwater and NAPL
from the overburden and bedrock collection wells.
A perimeter landfill cap was installed between March and August 1996 to reduce
infiltration. It included a 2-foot clay layer and flexible membrane liner near the
Robert Moses Parkway, and asphalt paving west and north of the landfill.
The construction of the final landfill cap commenced in August 2000, and was
completed in August 2002.
-------
A-37
The new DWTP was completed in March 1997, and now supplies the City of
Niagara Falls with its drinking water.
The demolition of the old DWTP was completed in early 1998.
The eastern barrier wall at the DWTP property was completed in May 1998.
The DWTP drain collection system was completed in 1999.
The construction of the DWTP cap was completed in 1999.
The securement of the DWTP intake structure commenced in August 2000 and
was completed in August 2002.
The remedial construction activities are completed as described in the September 2002
Preliminary Closeout Report. Adjustments to the remedial systems continue to optimize
the performance of this action.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
Federal $ 10,500,000
State $ (State costs were covered under EPA costs through grants)
PRP $ 45,000,000
It is estimated that the following amounts will be spent from now to the completion of
remediation:
Federal $ 1,000,000 (oversight)
State $ (Not available)
PRP $ 5,000,000 (Capital costs)
$ 2 to 3,000,000 per year for 30 years (Operation & Maintenance)
-------
A-38
OCC S-AREA
Output
Responsible
Party
Previous Target
Date
Current Schedule
RRT Survey work (RI) Completion
PRP
COMPLETED
RRT Study (FS) approved
PRP
COMPLETED
Record of Decision (RRT Stipulation)
EPA/DEC
Mar 1990
COMPLETED
Remedial Design (RD) Start
PRP
COMPLETED
Remedial
Actions (RA)
Start
PRP
Jun 1991
COMPLETED
Construction of new
DWTP
PRP
Apr 1997
COMPLETED
Demolish old DWTP
PRP
Sep 1997
COMPLETED
DWTP cap & drain
collection system
PRP
1998
COMPLETED
Securement of raw
water intake
structures from the
old DWTP
PRP
1999
COMPLETED1
Perimeter landfill
cap & drain
collection system
PRP
N/A
COMPLETED
Final landfill cap
PRP
1999
COMPLETED2
Construct Eastern
barrier wall
PRP
Jul 1998
COMPLETED
RA Completion
PRP
2000
COMPLETED3
1 The securement of the DWTP intake structures, including the grouting of the 5,000-foot long
bedrock intake tunnel, commenced in summer 2000 and was completed in August 2002.
2 The construction of the final S-area Landfill cap commenced in August 2000 and was
completed in March 2002.
3 Construction activities for the site are completed. Evaluation and performance of the remedial
action are presently being performed.
-------
A-39
STAUFFER CHEMICAL
Site #255
Site Program: New York State DEC Division of Environmental Remediation
Summary Prepared by: DEC
Site Description
The Stauffer Chemical Plant site occupies about 23 acres, located about 1/4 mile east of
the Niagara River in the Town of Lewiston.
Used for manufacturing from 1900 to 1976, the site was occupied by Stauffer Chemical
from 1930 to 1976. Carbon tetrachloride and various metallic chlorides were produced on
site, and methylene chloride and tetrachloroethylene were repackaged from bulk
shipments. Plant operations terminated in 1976, and the site was razed in 1980. Disposal
occurred on the plant site, as well as in two small landfills on the PASNY property to the
east.
There are four significant, and one less significant, bedrock aquifers under the site. The
flow direction for all water-bearing layers is southwest, towards the Power Authority of
New York Forebay and the Niagara River.
Site Investigation
The Stauffer Chemical Plant site is a DEC-lead site. Pursuant to a Consent Order,
Stauffer Chemical completed a Remedial Investigation/Feasibility (RI/FS) study of the
site. The Record of Decision (ROD) was signed July 1992, and consent order for the
remedial design/remedial action was executed in July 1993. The main components of the
remedial plan included bedrock groundwater pumping and treatment, and soil vapor
extraction, both on and off site. The plan also included re-grading of the site.
Delays in the original schedule were due to the need for additional remedial investigative
studies to adequately define the nature and extent of contamination.
Remedial Activities
Remedial construction began in June 1995 and was completed in December 1995.
Extensive design work was necessary for proper de-watering, including pump tests, soil
vacuum extraction pilot test and so on. Construction of the remedy has been completed.
Remedial actions completed include the following:
Installation of a bedrock pump-and-treat system that will operate for the next 30
years.
Installation of a soil vapor extraction and dewatering system that draws
contaminants out of the soil.
-------
A-40
Operational difficulties were encountered with the groundwater treatment system. This
was corrected in 1997. The groundwater treatment system has been modified.
Groundwater now flows through granular activated carbon prior to discharge to the NYPA
Forebay.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
State $ 180,000
PRP $ 5,100,000
It is estimated that the following amounts will be spent from now on Operation and
Maintenance of the remedial system:
State $ 10,000
PRP $ 1,300,000
STAUFFER CHEMICAL
Output
Responsible
Party
Previous Target
Date
Current Schedule
RI/FS
PRP
Sep 1990
COMPLETED
Record of Decision
DEC
Jan 1991
COMPLETED
Remedial Design
PRP
Apr 1993
COMPLETED
Remedial Action Completion
PRP
Dec 1995
COMPLETED
-------
A-41
SOLVENT CHEMICAL
Site #251
Site Program: New York State DEC Division of Environmental Remediation
Summary Prepared by: DEC
Site Description
The Solvent Chemical site occupies approximately 6 acres in the City of Niagara Falls.
The site is located about 1/4 mile north of the Niagara River.
The Solvent Chemical plant site has been used for manufacturing operations at various
times from 1941 to 1978 by DuPont, Hooker Chemical and Solvent Chemical. DuPont
and Hooker produced impregnite; Solvent Chemical manufactured chlorinated
hydrocarbons, zinc chloride and zinc ammonium chloride. Chemicals disposed on site
include zinc, benzene and chlorinated benzenes.
Five water-bearing layers have been significantly impacted by site contaminants: the
saturated overburden layer and four bedrock zones. The groundwater in the overburden
flows to the north. The bedrock aquifers generally flow to the northeast. Groundwater in
the site area is influenced by the Falls Street Tunnel (due north of the site), and the New
York Power Authority (NYPA) conduits (about 1,500 feet east of the site), which drain
bedrock groundwater in the area. The majority of the site ground water flows into the
Falls Street Tunnel, either directly or via the NYPA conduits. All of the dry weather flow
through the Falls Street Tunnel now is treated by the Niagara Falls Wastewater Treatment
Plant before discharge to the River.
Site Investigation
The Solvent Chemical site is a DEC/Department of Law-lead site. An initial Remedial
Investigation [RI] (funded by the Potentially Responsible Party [PRP]) was completed in
June 1991. Despite lengthy negotiations, the PRPs did not agree to undertake the
Feasibility Study [FS], The site was referred to State Superfund for completion of the
RI/FS, while the Attorney General's office litigated the matter. Field work for
supplemental investigations needed to support the FS was completed in November 1994.
The RI/FS report was approved in August 1996. The proposed Remedial Action Plan was
submitted for public comment in September 1996. The resulting Record of Decision
(ROD) was signed in December 1996. The Remedial Action Plan includes the following
components:
• Existing buildings on site to be demolished.
• Storm sewer from the site to Gill Creek is to be removed.
• Site is to be capped.
• Contaminated groundwater is to be hydraulically controlled through pump-
and-treat systems (including an off-site hot spot to the west).
• Pre-treatment system for contaminated groundwater.
-------
A-42
DEC and site PRPs completed legal agreements that require ROD implementation. The
settlement was approved by the U.S. District Court in October 1997. Construction was
started in early 1998, but was delayed by lack of access agreements with adjacent property
owners. Building demolition was completed in 1998. Installation of the extraction system
in the off-site hot spot has been completed. Removal of the off-site storm sewer began in
July 2000.
Construction of the groundwater extraction and treatment systems were completed in
2001. The remedial system became fully operational in December 2002. Bedrock
groundwater pumping rates were evaluated in 2003. The Performance Monitoring
program is expected to be finalized and approved in 2004.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
State $ 1,170,000
PRP $ 2,950,000
It is estimated that the following amounts will be spent from now to the completion of
remediation:
State $ 01
PRP $ 11,250,000
SOLVENT CHEMICAL
Solvent Chemical
Responsible Party
Previous Target
Date
Current
Schedule
RI
PRPs
Dec 1990
COMPLETED
RI/FS
DEC
Sep 1994
COMPLETED
Record of Decision
DEC
Dec 1994
COMPLETED
Remedial Design Start
PRPs
Dec 1995
COMPLETED
Remedial Action Start
PRPs
Dec 1996
COMPLETED
Remedial Action Completion
PRPs
May 2001
COMPLETED
1 PRP will reimburse future state costs.
-------
A-43
VANADIUM CORPORATION OF AMERICA
(Formerly SKW Alloys)
Site # 1
Site Program: New York State DEC Division of Environmental Remediation
Summary Prepared by: DEC
Site Description
The Vanadium site is located approximately 1 V2 miles east of the Niagara River in the
Town of Niagara.
The Vanadium Corporation of America owned and operated a facility at the site from
1920 to 1964 when approximately 594,000 tons of slag and other refuse were disposed at
the site. In 1964, the site was purchased by the Pittsburgh Metallurgical Company, which
subsequently changed its name to Airco Properties, Inc. Airco disposed wastes similar to
the wastes disposed by Vanadium. In 1979, SKW Alloys, Inc. bought 37 acres of the 62
acre parcel owned by Airco, while Airco retained ownership of the eastern 25 acres. The
Vanadium site consists of both properties as well as property owned by the Niagara
Mohawk Power Corporation and the New York Power Authority (NYPA) to the east and
north which also contains waste piles deposited by Vanadium. Chromium is a major
contaminant of concern at the site, as well as a caustic waste which is affecting the pH of
the ground and surface water.
The site contains 11 to 24 feet of overburden, consisting of clay, stratified drift and till,
underlain by Lockport Dolomite. Groundwater flow in the area is influenced by the
NYPA conduits causing a groundwater flow divide which bisects the site. Groundwater
under the SKW site and most of the Airco site flows to the southwest. Groundwater under
the Niagara Mohawk site, the NYPA site, and the remainder of the Airco site flows east
into the conduit drain system.
Site Investigation and Interim Remedial Measures
The Vanadium site is a DEC-lead site. A Phase I investigation was completed in
December 1989. A Preliminary Site Assessment (Phase II investigation) is complete.
Wells were sampled in November 1992 and a report with results and recommendations for
site reclassification was completed in September 1993.
As a result of the Preliminary Site Assessment, the site was reclassified to a class 2
(significant threat to the public health or the environment, action required) on April 3,
1995. In 1997, DEC completed a study (IIWA) to further define the nature and extent of
contamination at the Niagara Mohawk and NYPA properties. For remediation purposes,
the site has been divided into three operable units: OU#l (SKW), OU#2 (Airco), and
OU#3 (Niagara Mohawk and NYPA).
-------
A-44
Under Consent Order, SKW completed an Interim Remedial Measure to cover portions of
their parcel and control site storm water runoff. This remedial measure was completed in
November 1998. DEC and Airco negotiated an Interim Remedial Measure (IRM) to cap
the landfill on their portion of the site. Closure of the Airco portion of the site (OU No. 2)
was completed by December 2000.
Schedule for Completion
A schedule for completion is presented below. The site PRPs have not agreed to act as a
group. This has contributed to delays in the schedule due to the need to negotiate
individually with the PRPs. Niagara Mohawk and the New York Power Authority have
agreed to conduct a Remedial Investigation of OU No. 3. An RI/FS for OU No. 3 has
been approved. Implementation of the work plan is ongoing.
Remediation Costs
Following are estimated amounts for the Interim Remedial Measures:
OU #1:
State $ 30,000
PRP $ 750,000
OU #2:
State: $ 75,000
PRP $ 4,500,000
It is estimated that the following amounts will be spent from now to the completion of
remediation:
State $ (Not available; site has yet
PRP $ to proceed to final remediation)
-------
A-45
VANADIUM CORPORATION OF AMERICA
Output
Responsible Party
Previous
Target Date
Current
Schedule
Phase I Investigation
DEC
Dec 1989
COMPLETED
Phase II Investigation
DEC
Dec 1991
COMPLETED
IIWA Investigation
DEC
Aug 1997
COMPLETED
Interim Remedial Measure-OUl
SKW Alloys, Inc.
Dec 98
COMPLETED
Interim Remedial Measure-OU2
Airco
Dec 2000
COMPLETED
RI/FS (Operable Unit #3)
DEC
Mar 2001
Schedule
dependent on
results of OU
No. 3 Remedial
Investigation.
Record of Decision (site wide)
DEC
July 2001
Remedial Design
PRP or DEC
July 2002
Remedial Action
PRP or DEC
July 2003
-------
A-46
OLIN CORPORATION
Site #58, 59
Site Program: RCRA (State and Federal)
Summary Prepared by: EPA and DEC
Site Description
The Olin Corporation site, 25 acres located on Buffalo Avenue in Niagara Falls, is
actually two plants on separate but contiguous sites, partially separated by the property of
the E.I. DuPont Company. Gill Creek flows through the eastern part of the facility. The
site is about 1/4 mile North of the Niagara River.
Olin Corporation has used this site for inorganic chemical production since 1897. Several
organic chemicals, including benzene, chlorobenzene, trichlorobenzene, and
trichlorophenol were used or manufactured between 1950 and 1956. Wastes handled at
this facility include: ignitable, corrosive, reactive, and EPA toxic characteristic wastes and
Resource Conservation and Recovery Act (RCRA)-listed wastes (brine purification muds
and wastewater treatment sludge from mercury-cell chlorine production). Brine sludge,
containing mercury and possibly polychlorinated bi-phenyl, was used as fill material in
various locations throughout the site.
The site consists of soil and gravel at 0-3.5 feet, sandy clay at 3.5-5 feet. The bedrock
surface lies at 5.5-8 feet. Proximity to the Niagara River and Gill Creek indicates a major
potential for contaminant migration. Ground water on the site exists in shallow
unconsolidated deposits and in a bedrock aquifer composed of 3 monitored zones.
Shallow groundwater infiltrates to Gill Creek, which discharges to the Niagara River.
In 1984, EPA issued Olin Corporation a RCRA permit to operate the hazardous waste
storage and treatment facilities on this site, but since it was issued before the Hazardous
and Solid Waste Amendments to RCRA were enacted, it did not incorporate corrective
actions. EPA issued an order in September 1989, requiring investigation of releases
throughout the site, and particularly from the brine mud storage area, where releases have
occurred. Permitted units were closed in 1990, according to a DEC-approved closure
plan.
Interim Remedial Measures
Under a joint venture with DuPont, Olin conducted the off-site remediation of Gill Creek
from Buffalo Avenue to the Niagara River, which was completed in December 1992.
Contaminated sediment was removed, and the creek has been restored.
An EPA/DEC-approved DNAPL interim corrective measure (ICM) was implemented by
Olin during May and June 1994. The program was intended to identify and characterize
any DNAPL presence in five Olin monitoring wells and to remove any DNAPL
-------
A-47
encountered. DNAPL was only detected in one well and a total volume of less than two
gallons was removed.
Former Olin production wells are currently being used to pump and treat groundwater
from the site through an agreement with the adjacent DuPont facility. The Olin wells
serve as part of DuPont's bedrock groundwater remediation program and exert a large
radius of influence over the Olin site, which effectively reduces the total toxic load
migrating from the Olin site. The radius of influence of the Olin wells extends
approximately halfway (east-west) across Olin's Plant 2 in the B zone, and approximately
to Gill Creek in the lower aquifer zones and CD zones). The remedy approved in the
CMS is designed to capture all groundwater contamination not captured by the Olin
production wells. The wells extract groundwater at a rate of approximately 600 gallons
per minute continuously.
Site Investigation and Remedy Selection
Olin has conducted soil and hydrological studies, and submitted several supplemental RFI
reports to the EPA/DEC. Olin has completed the final phase of the RFI, and the final RFI
report was approved by EPA and DEC in February 1995. Mercury was detected in the
soils in concentrations up to 1,210 parts per million. Volatile and semi-volatile organic
constituents and pesticides were also identified in the soils. Sampling of twenty-four
overburden and bedrock wells identified volatile and semi-volatile constituents, pesticides,
and mercury at levels exceeding federal and state groundwater standards.
Work plans for both Phase I of the CMS (soil & overburden groundwater) and for Phase II
of the CMS (bedrock groundwater) were previously approved by EPA/DEC. In March
1995 Olin submitted a full CMS Report (incorporating both Phases I and II), which was
approved by EPA/DEC in September 1995. In July 1996, the proposed remedy for this
site was public noticed. Following public review, a remedy was selected and the CMI
Work plan approved. The remedy includes the following components:
Drilling and installing 5 groundwater recovery wells at Olin's plant 2 site. The
recovered groundwater will be pumped to a new on-site treatment plant before
being discharged into the City of Niagara Falls sewer system.
Paving all unpaved surfaces in order to minimize the volume of contaminated
groundwater recharge.
DEC issued a Consent Order to implement the selected remedy. The remedial system was
constructed and began operation in October 1997.
Operation & Maintenance is now underway. The remedial system is close to meeting its
performance objectives. There are two small areas along Gill Creek wither A-Zone
(overburden) groundwater capture has not been fully achieved. Additional A-Zone
interceptor wells were installed in 2002 and 2003 to enhance the capture. Recent
performance reports indicate that system performance has improved, but more actions
may be necessary.
-------
A-48
An updated schedule for implementation of a corrective action program, including
Corrective Measure Implementation (CMI), follows. The scheduled project milestones
relate to complete on- and off-site investigation and remediation.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
Federal $ (Not available)
State $ (Not available)
PRP $ (Not available)
It is estimated that the following amounts will be spent from now to the completion of
remediation:
Federal $ (Not available)
State $ (Not available)
PRP $ (Not available)
-------
A-49
OLIN CORPORATION
Output
Responsible
Party
Previous Target
Date
Current Schedule
RFI Work Plan Approval
DEC/EPA
Apr 1990
COMPLETED
RFI
Completi
on
Phase I
Permittee
COMPLETED
Phase II
Permittee
Dec 1994
COMPLETED
Stabilization Start-up
(Groundwater)
COMPLETED
CMS
Work
Plan
Approval
Phase I
Permittee
COMPLETED
Phase II
DEC/EPA
Sep 1993
COMPLETED
CMS Completion
(including approval)
Permittee
Mar 1995
COMPLETED
Remedy Selection
DEC/EPA
Mar 1996
COMPLETED
CMI Work Plan Approval
DEC/EPA
Mar 1996
COMPLETED
Start-up of CMI
Initiation/Stabilization
Permittee
Dec 1996
COMPLETED
ote: Phase I - Overburden soil and groundwater
Phase II - Bedrock groundwater
-------
A-50
DUPONT - BUFFALO AVENUE
Site# 15-19
Site Program: New York State DEC Division of Environmental Remediation
Summary Prepared by: DEC
Site Description
The DuPont Buffalo Avenue Plant site occupies over 50 acres in the City of Niagara Falls.
The plant is separated from the Niagara River by the Robert Moses Parkway.
Manufacturing operations have been conducted at the site since 1898. Chemicals
disposed on the site included: carbon tetrachloride, chloroform, dichloroethylene,
methylene chloride, trichloroethylene, tetrachloroethylene, vinyl chloride, PCBs, barium
and other organic and inorganic compounds.
One overburden and five bedrock aquifers exist under this site, each consisting of two or
three zones with different flow directions. Groundwater flowing south discharges into the
Niagara River and Gill Creek. Groundwater flowing north discharges into the unlined
Falls Street Tunnel, and groundwater flowing east, into the New York Power Authority
(NYPA) conduit drain system.
Remedial Actions
As of January 1992, all remedial systems at this site were completed and operating. More
than 60 studies of subsurface contamination were completed by DuPont on the plant site,
and a Consent Order was negotiated for the implementation of a groundwater remediation
program. In January 1992, an on-site groundwater pump-and-treat system went into
operation. A portion of the flow from the western half of the DuPont site is under the
influence of the Olin production wells. This water is remediated by the Olin Treatment
Plant before discharge to the river.
Additionally, DuPont is a Potentially Responsible Party for the remediation of Gill Creek,
which was completed in December 1992. A total of 8,020 cubic yards of contaminated
sediment was removed, and the creek has been restored. Five-years of post-remediation
monitoring of Gill Creek sediments was completed in 1998. Monitoring reports do not
indicate PCB re-contamination in the sediment of the Gill Creek remediation area.
-------
A-51
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
State $ 50,000
PRP $ 43,600,000 (includes Gill Creek remediation)
It is estimated that $ 1,600,000 will be spent annually by the PRP on the Operation and
Maintenance of this site.
DUPONT BUFFALO AVENUE
Output
Responsible Party
Status
Record of Decision
DEC
COMPLETED
Remedial Design
PRP
COMPLETED
Remedial Action
PRP
COMPLETED
-------
A-52
BUFFALO COLOR CORPORATION
Site # 120, 122
Site Program: RCRA (State and Federal)
Summary Prepared by: EPA and DEC
Site Description
Buffalo Color Corporation, located on 61 acres adjacent to the Buffalo River within the
city of Buffalo, was a major manufacturer of indigo dye.
This plant, which was originally built in 1879 by the Schoelkopf Aniline and Dye
Company, merged with two other companies to form the National Aniline and Dye
Company in 1916, one of five companies forming Allied Chemical Corporation in 1920.
Buffalo Color Corporation purchased and began operating the dye plant in 1977. In 2003,
the facility ceased producing indigo, and switched to packaging indigo produced by other
manufacturers.
Dyestuffs and/or organic chemicals had been continuously produced at the facility for
more than 110 years. The dye manufacturing operations generated approximately 450,000
gallons per day of process waste water. The waste water was a Resource Conservation
and Recovery Act (RCRA) hazardous waste due to its corrosivity (pH >12.5). RCRA
hazardous constituents in this waste stream include: aniline, N-methylaniline, N,N-
dimethylaniline, N,N-diethylaniline, cyanide, methanol, nickel, and chromium. Prior to
1971, these wastes were discharged directly to the Buffalo River. In 1971, Allied
Chemical diverted the waste streams to three surface impoundments for neutralization
prior to release to the Buffalo Sewer Authority, and beginning in March 1989, Buffalo
Color installed a new neutralization tank to treat wastewater before discharge to sewers.
The stratigraphy at the site from the upper to lowermost units is: 2-11 feet of fill, 6-13 feet
of silt and fine sand (upper aquifer), 25-37 feet of silty clay, 5-7 feet of sand and gravel
(lower aquifer), and bedrock of Onondaga Limestone. Groundwater flow in the upper
aquifer is towards the Buffalo River. Groundwater near the surface impoundments is
contaminated with aniline, dimethylaniline, N-ethylaniline, and cyanide, all of which most
likely derive from the surface impoundments.
Site Investigation
A RCRA Facility Assessment (RFA) Preliminary Review and Visual Site Inspection were
completed during 1986 and 1988, respectively. Eight (8) Solid Waste Management units
(SWMUs) have been identified at the site. Overburden ground water monitoring wells at
the impoundments show concentrations of chlorobenzene, dichlorobenzenes, toluene,
anilines and phenol above DEC-promulgated ground water standards. An RFA soil
sampling program for a container storage area was completed in January 1991. EPA and
DEC identified a need to investigate potential releases from both the extensive sewer
system and from two inactive buildings at the site.
-------
A-53
A DEC Part 373 post-closure permit was public noticed in 1992 to address releases. The
facility objected to several conditions of the draft permit and requested an administrative
hearing. All outstanding issues were resolved and the Part 373 permit became effective
on February 10, 1995.
The RFI Work plan has been approved. The RFI includes a subsurface (soil and
groundwater) investigation program for all areas of the plant except for Area D, which is
being remediated under the New York State Inactive Hazardous waste program (see Area
D summary for details).
• Field work for Phase I of the RFI began in April 1996 and consisted of 18
monitoring wells around the perimeter of the site to evaluate groundwater quantity
and potential migration of hazardous constituents off site.
Phase II of the RFI, completed in September 1996, involved the advancement of
24 soil probes within the site to collect near and sub-surface soil samples.
Hazardous contaminants were detected at the perimeter monitoring wells during the Phase
I and II investigations for the RFI. In November 1996, BCC proposed supplemental
investigations (involving 10 additional wells) to determine the off-site extent of
contamination. DEC approved the proposal in December 1996. In January 1997, BCC
proposed the collection of 6 additional surficial samples to provide further support of a
corrective measures study. DEC approved the proposal in March 1997. BCC submitted
the RFI report in November 1997. In response to DEC comments on the RFI, BCC
submitted a second supplemental investigation plan involving 8 new wells, 5 piezometers,
and 10 soil samples. This proposal was approved in July 1998 and implemented during
the summer of 1998. A revised RFI report was submitted in December 1998 and
approved in April 1999. A Corrective Measures Work Plan was submitted in May 1999
and approved in July 1999. In July 2000, the Corrective Measures Study Report was
approved. However the approval does not constitute approval of the Risk Assessment
provided in the report. The Risk Assessment is based in part, on USEPA
Industrial/Commercial Risk-Based Levels, that are not completely accepted by the NYS
Department of Health. In addition, there were cases in which the method detection limits
for soils were not sufficiently low to evaluate comparison with the risk levels.
During July 1999, a pump test was performed to aid in the design of Corrective Measures
for Plant Area A, to prevent the discharge of contaminated groundwater into the Buffalo
River. The pump test indicated that conventional pumping wells should be effective in
controlling the migration of contaminated groundwater in Plant Area A, and that
migration control should be achievable with a total system pumping rate on the order of
25-30 gpm. Such a system has been proposed as part of the final corrective measures,
within the CMS report.
The supplemental investigations delayed completion of the RFI. All target dates in the
table below account for these delays. Remedy selection and CMI implementation have
been delayed due to the financial viability of the company. Buffalo Color filed for
Chapter 11 Bankruptcy protection during October 2002. An agreement to share the costs
-------
A-54
of implementing the remedial measures have recently been made between BCC and
Honeywell Corporation, a PRP. These agreements require approval of the Bankruptcy
Court. The DEC is currently negotiating a Consent Order with Honeywell to implement
the remedy. An RFP for remedy design and construction was issued. The remedial
system is expected to be installed during 2004. Completion of the milestones is also
dependent on field conditions encountered, which may delay the overall schedule for
corrective action.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
It is estimated that the following amounts will be spent from now to the completion of
remediation:
Federal
State
PRP
$ 0
$ 0
$ (Not available)
Federal
State
PRP
$ (Not available)
$ (Not available)
$ (Not available)
-------
A-55
BUFFALO COLOR CORPORATION
Output
Responsible Party
Previous
Target Date
Current Schedule
RFA Work Plan Approval
EPA/DEC
Mar 1990
COMPLETED
RFA Completion
Permittee
May 1990
COMPLETED
RFI Work Plan Approval
EPA/DEC
Mar 1995
COMPLETED
RFI Completion
Permittee
July 1997
COMPLETED
Stabilization Start-up
Permittee
Jan 1998
N/A*
CMS Work Plan Approval
EPA/DEC
Jan 1998
COMPLETED
CMS Completion
Permittee
Jul 1998
COMPLETED
Remedy Selection
EPA/DEC
Aug 2003
July 2004
CMI Work Plan Approval
EPA/DEC
Dec 2003
Sep 2004
Start-up of CMI
Permittee
July 2004
Mar 2005
* Results of a 1999 pump test indicated that conventional pumping wells should be effective in
controlling the migration of contaminated groundwater in Plant Area A, and that migration control
should be achievable with a total system pumping rate on the order of 25-30 gpm. Such a system
has been proposed as part of the final corrective measures, within the CMS report.
-------
A-56
BUFFALO COLOR - AREA D
Site# 120-122
Site Program: New York State DEC Division of Environmental Remediation
Summary Prepared by: DEC
Site Description
Area D of the Buffalo Color Plant site occupies about 19 acres adjacent to the Buffalo
River in the City of Buffalo. The site is about 4 miles upstream of the confluence of the
Buffalo and Niagara Rivers.
Area "D" is an inactive hazardous waste site. It was used from 1905 to 1974 as a chemical
manufacturing, handling and disposal site. From 1905 to 1920, acids, chemicals and dye
intermediates were produced by Contact Process Company and by National Aniline
Chemical Company, which merged into Allied Chemical and Dye Corporation in 1920.
Allied Chemical and Dye Corporation manufactured petroleum-based detergents, dye
intermediates, picric acid, and other chemicals at Area "D" from 1920 to 1974. During
that time, a number of structures, railroad tracks and tank parks were built at the site. All
chemical manufacturing operations ceased in 1974, and chemical waste handling ceased in
1976 at Area "D". In 1977, the property was sold to Buffalo Color Corporation and
remained idle. All structures on the site were demolished to grade by Buffalo Color
Corporation in 1984.
The site overburden consists of fill, alluvium, glaciolacustrine deposits and glacial till, and
is underlain by the Onondaga Limestone. The shallow overburden water-bearing zone on
the site is in direct hydraulic connection with the Buffalo River. The major pathways of
contaminant migration from the site to the Buffalo River was shallow ground water and
erosion of the shoreline.
Site Investigation and Remedy Selection
The Buffalo Color Area D site is a DEC-lead site. Pursuant to a Consent Order, the PRPs
(Buffalo Color and Allied Chemical) conducted a Remedial Investigation (RI), which was
first submitted in April 1989 and approved in September 1990. The RI indicated elevated
levels of Polynuclear Aromatic Hydrocarbons (PAHs), chlorinated benzenes and heavy
metals in the site fill layer. The site groundwater was found to be contaminated by
volatile organics, chlorinated benzenes, iron and other heavy metals and non-aqueous
phase liquid (NAPL).
A Feasibility Study (FS) was submitted in December 1990, with final revisions submitted
and approved in July 1991. The FS evaluated 13 alternatives for the remediation of the
site and identified a preferred alternative; all were discussed at a public meeting in
October 1991. A Record of Decision (ROD) was signed in November 1991, setting forth
a selected remedial plan.
-------
A-57
An Order on Consent was signed by Allied Signal and DEC in June 1993 for the
remediation of the site. Construction of the selected remedy began in June 1996. The
Remedial Action was completed in September 1998.
The following are the elements of the remedy completed in September 1998:
A slurry wall was constructed around the entire site;
River sediments adjacent to the site were dredged and deposited on-site. The
shoreline was armored with rip rap;
A high-density polyethylene liner was placed over the entire site and properly
capped;
Groundwater is being pumped and treated at an on-site treatment facility.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
State $ 200,000
PRP $ 14,000,000
BUFFALO COLOR - AREA D
Output
Responsible Party
Current
Schedule
RI/FS
PRPs
COMPLETED
Record of Decision
DEC
COMPLETED
Remedial Design
PRPs
COMPLETED
Begin Remedial
Construction
PRPs
COMPLETED
Remedial Action Completion
PRPs
COMPLETED
-------
A-58
BETHLEHEM STEEL CORPORATION
Site# 118
Site Program: RCRA (State and Federal)
Summary Prepared by: EPA
Site Description
The Bethlehem Steel Corporation (BSC) facility encompasses approximately 2.5 square
miles, located on Hamburg Turnpike, Lackawanna. Buffalo Harbor marks the northern
boundary of the site, and Lake Erie marks its western boundary.
BSC is a former major manufacturing plant that produced structural steel, coke, coke
byproducts and specialty steel products. Processing occurred primarily on the eastern
section of the site. The western section of the site was created by landfilling 440 acres of
Lake Erie with slag from processing. Since 1983 the facility has significantly reduced
manufacturing operations. Most of the former production areas have been closed and
demolished. Until the fall of 2001, the galvanizing and coke production processes were
the only areas in operation. The coke ovens were closed in the fall of 2001 and coke
production ceased. Over 100 Solid Waste Management Units have been identified at the
site. Six surface water bodies on site have been identified as having received hazardous
waste or hazardous constituents from BSC.
Within the Buffalo-Lackawanna area, all surface and ground waters ultimately drain into
Lake Erie. Preliminary information concerning site-wide hydrogeology indicates that
contaminated groundwater flows east to west into Lake Erie. Groundwater also appears to
enter both Smokes Creek and the Ship (or Lackawanna) Canal. In the area immediately
surrounding the two regulated surface impoundments, groundwater flows west towards
Lake Erie. Also, transecting the site are trenches, which drain from the process area into
Smoke and Blasdell Creeks. The Ship Canal drains northward into Buffalo Harbor.
Site Investigation
EPA issued a consent order in August 1990 requiring an on-site RCRA Facility
Investigation (RFI). The RFI investigation is being conducted in a multi-phase approach.
Initial phases of the investigation (Phase I and Phase IIA) were conducted between 1990
and 1993.
BSC submitted the Phase II-B RFI Report in November 1994. These investigations have
identified benzene, naphthalene, phenolic compounds, and metals in groundwater samples
collected from monitoring wells at the facility. Due to the complexity of site conditions
that have been encountered at the facility in previous investigations, EPA and DEC
required BSC to conduct a Phase III RFI investigation to fill in data gaps. Field work for
this investigation was completed in September 1995. Negotiations over the scope of the
human health risk assessment, which is required as part of the RFI report, have delayed
the submittal of the RFI and human health risk assessment. In July 1996, EPA approved
-------
A-59
the Ecological Risk Assessment Work Plan, and BSC completed a draft of this
assessment, which is also a component of the RFI. A review of the draft Ecological Risk
Assessment revealed that additional data collection was necessary to complete the
assessment. As such, BSC submitted an Ecological Sampling Work Plan and a
Supplemental Solid Waste Management Unit Work Plan in May 2000 to address
collection of the additional data. This data was collected in 2001 and will be incorporated
into the RFI Report.
EPA and DEC have identified two areas (Acid Tar Pits and Coke Oven Areas) where
BSC should consider implementing stabilization or interim corrective measures to control
and reduce the further spread and off-site migration of contaminated groundwater from the
facility. These two areas appear to be the primary sources of groundwater contamination
at this facility. BSC has not implemented any interim corrective action or stabilization
activities to address the contamination in these areas to date. However, BSC has
submitted a Pre-design Investigation Report for the remediation of the Benzol Plant Area
(i.e., Coke Oven Area). The implementation of the remedial work in the Benzol Plant
Area has been delayed due to a dispute over the characterization of the wastes in that area.
BSC also previously proposed and performed two remedial technology studies for the acid
tar pit area. These studies were found by the EPA and DEC to be technically flawed and
of limited value. Any future CMS or CMI activities will require a new order, permit or
other agreement.
Following approval of the RFI report, a site-wide CMS Work Plan, with a schedule, will
be required of BSC. The scope of this Work Plan will be partly determined by the results
of the Human Health and Ecological Risk Assessments.
BSC also submitted an application for two Corrective Action Management Units
(CAMUs) to DEC and EPA. The Agencies have determined that BSC's application is
considered "substantially complete." BSC subsequently submitted a 30% design for one
CAMU. This may allow CAMUs to be utilized as part of a future remedy at the facility.
While RFI activities are being completed, EPA has removed approximately 102 acres of
the facility from the RFI Order to facilitate brownfields type redevelopment. This acreage
is not believed to be significantly contaminated and may be suitable for redevelopment.
During 2001 BSC and DEC attempted to negotiate a voluntary cleanup style agreement
for this parcel. BSC abandoned this effort, and shortly thereafter filed for Chapter 11
bankruptcy in October of 2001. This has caused delays in the implementation of various
site activities. In 2003, the Integrated Steel Group (ISG) acquired the BSC Lackawanna
site. The DEC is currently negotiating a corrective action order with ISG.
A current schedule for implementation of a corrective action program at the facility,
including CMI, follows. Due to delays caused by several problems outlined above, the
proposed schedule was extended. All subsequent target dates were extended accordingly.
Completion of the outputs is dependent on 1) the nature and extent of contamination found
on- and off-site (and thus the complexity of remedial measures required); and 2) the
timeliness in which the planning and implementation of work plans and reports are
-------
A-60
submitted by the facility and approved by EPA and DEC. The scheduled project
milestones relate to complete on- and off-site investigation and remediation.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
Federal $ (Not available)
State $ (Not available)
PRP $ (Not available)
It is estimated that the following amounts will be spent from now to the completion of
remediation:
Federal $ (Not available)
State $ (Not available)
PRP $ (Not available)
BETHLEHEM STEEL CORPORATION
Output
Responsible Party
Previous Target
Date
Current
Schedule
RFI Work Plan Approval
EPA
Jan 1990
COMPLETED
RFI Completion
Permittee
June 2003
Dec 2004
RFI Report Approved1
EPA
Dec 2003
Apr 2005
CMS/CMI
Issue CMS/CMI Order
DEC
Dec 2003
Aug 2004
CMS Work Plan Approval2
DEC
June 2004
June 2005
CMS Completion2
Permittee
Mar 2005
Feb 2006
Remedy Selection
DEC
Oct 2005
Apr 2006
CMI Work Plan Approval2
DEC
June 2006
Jan 2007
Start-up of CMI2
Permittee
Mar 2007
Nov 2007
1 RFI to include human health and ecological risk assessments.
2 These outputs will require a new order, permit or other agreement. Target dates
dependent upon facility owner/operator agreement to complete these stages of site
corrective action program.
-------
A-61
RIVER ROAD (INS EQUIPMENT)
Site # 136
Site Program: New York State DEC Division of Environmental Remediation
Summary Prepared by: DEC
Site Description
The River Road site occupies approximately 23 acres in the Town of Tonawanda. The
site is adjacent to the Niagara River.
The River Road site was utilized for waste disposal from the early 1920s through the late
1970s. Disposed on site were steel and coke industry wastes, consisting of foundry sand,
coke sludges, oils, solvents and slags.
The overburden at this site consists of 15 to 20 feet of fill over glaciolacustrine deposits
and till. The overburden is underlain by Onondaga Limestone. The two overburden
aquifers on site flow west towards the Niagara River.
Site Investigation
The River Road site is a DEC-lead site. Negotiations with the six Potentially Responsible
Parties (PRPs) for an RI/FS were not successful, causing a delay in targeted remedial
action dates. The PRPs did not agree to conduct an RI/FS; therefore, the State undertook
the task under State Superfund. The RI/FS was completed in January 1994 and the record
of decision (ROD) was signed in March 1994. The River Road site was combined with
the adjacent Niagara Mohawk-Cherry Farm site for joint remediation (see following site
description). Some PRPs agreed to remediate the site and signed an order of consent in
September 1994. The remedial design was completed in February 1996, that consisted of:
• Capping the site with clean soil;
• Pulling back, grading, and stabilizing the shore line;
• Removing some river sediments; and
• Installing groundwater collection trench and recovery wells.
Remedial Actions have been completed, including sediment removal. Sediment removal
began in July 1998 and was completed November 1998. Final capping of the sediment
disposal area was completed July 1999. The Construction Certification Report and
Operation, Maintenance and Monitoring Plan were approved in January 2000.
Diver inspection of the dredged areas shows good revegetation and recolonization by fish.
Groundwater is collected, treated at an on-site treatment facility, and discharged to the
local POTW.
-------
Remediation Costs
A-62
Following are estimated amounts that have been spent to date on remediating this site:
State $ 546,000
PRP $ 15,000,000*
RIVER ROAD (INS EQUIPMENT)
Output
Responsible Party
Current
Schedule
RI/FS
DEC
COMPLETED
Record of Decision
DEC
COMPLETED
Remedial Design
PRPs
COMPLETED
Remedial Action
Completion
PRPs
COMPLETED
* Costs include Niagara Mohawk Cherry Farm site.
-------
A-63
NIAGARA MOHAWK - CHERRY FARM
Site Program: New York State DEC Division of Environmental Remediation
Summary Prepared by: DEC
Site Description
The Cherry Farm Site is an inactive landfill located between River Road and the Niagara
River in the Town of Tonawanda, New York. The site encompasses approximately 56
acres, 80% of which is covered by various fill materials. The fill material consists
primarily of foundry sand, slag, and cinders. The surface of the fill is between 10 to 20
feet above the original surrounding land surface. The present topography of the filled area
is essentially flat.
The fill area is surrounded by intermittent surface water. A wetland designated as BW-6
by DEC is present on the eastern portion of the Site. This wetland drains into the drainage
ditches which flow along the southern and northern boundaries of the property and
ultimately discharge to the Niagara River, which forms the western side of the Site.
Site Investigation/Remedial Design
A Record of Decision (ROD) for the site was signed by DEC in February 1991. The
selected remedy included covering the site with an impermeable cap, along with ground
water containment, collection, treatment, and disposal. After additional field
investigations and discussions with the PRPs, the ROD was amended on October 7, 1993.
The differences between the remedies include 1) the cover design will include a permeable
soil cover; 2) collected ground water will not be discharged into the Niagara River, but
will be pretreated and discharged to a local water treatment plant; and 3) fencing will not
be installed around the site as part of the remedy. The revised remedy will allow for
development of the site as a park after remedial construction is completed. In addition,
the remedial action includes fish and wildlife habitat enhancements through the
construction of shoreline wetland embayments along the Niagara River.
A consent order between DEC and the PRPs to complete the design and construction of
the remedy was signed in September 1994. The Niagara Mohawk-Cherry Farm site was
combined with the adjacent River Road site for joint remediation. Please see the previous
site description (River Road) for details on the remedial action. The remedial work is
complete.
-------
A-64
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
State $ *
PRP $*
NIAGARA MOHAWK - CHERRY FARM
Output
Responsible
Party
Current Schedule
RI/FS
PRPs
COMPLETED
Record of Decision
DEC
COMPLETED
Remedial Design
PRPs
COMPLETED
Remedial Action
PRPs
COMPLETED
Remediation of the Cherry Farm site was completed as part of the River Road RI/FS.
Costs are reported in the River Road site description.
-------
A-65
FRONTIER CHEMICAL, PENDLETON
Site # 67
Site Program: New York State DEC Division of Environmental Remediation
Summary Prepared by: DEC
Site Description
The Frontier Chemical site in the Town of Pendleton occupies about 21 acres adjacent to
Bull Creek, approximately 4 1/4 miles inland from the Niagara River.
Approximately 7.5 acres of the site were used for treatment and disposal of hazardous
wastes. From about 1958 to 1974, Frontier Chemical used the site for processing, storage
and burial of industrial and hazardous wastes. Unknown volumes of solvents, oils, acids,
dyes, paint wastes, heavy metal sludges, and other wastes were handled on the site. An
on-site lake was used for disposal of metal salt sludges from the neutralization of plating
wastes and pickling liquors.
The site consists of various amounts of fill underlain by glaciolacustrine silty clay to a
depth 20 to 30 feet. The silty clay is underlain by glacial till and then bedrock, which is
believed to be Lockport Dolomite. Shallow groundwater on the site flows radially from
the site, very slowly, with some discharge to the on-site lake.
Site Investigation
DEC completed a remedial investigation/feasibility study (RI/FS) of the site using State
Hazardous Waste Remediation Program funds. The Record of Decision (ROD) was
finalized in March 1992. The remedial design completed in May 1995 calls for the
following: dredging and stabilization of contaminated lake sediments; consolidation of
lake sediments and contaminated soils on the process/fill area; collection, treatment, and
disposal of contaminated groundwater; capping of the site; physical controls for run-on,
run-off and flow from the lake; long term monitoring. A Consent Order requiring a group
of Potentially Responsible Parties (PRPs) to implement the selected remedy was executed.
Remedial Actions
Remedial construction began in June 1995. Quarry Lake was de-watered and
contaminated sediments were removed, stabilized, and consolidated into the onsite
landfill. Construction of the landfill cap and leachate collection system is complete. The
final completion report certification and Operation & Maintenance (O&M) manual were
finalized in March 1997.
Long-term O&M includes pump-and-treat of the leachate from the site. The O&M is
scheduled to continue for a period of 30 years from 1997. Thorough review of the project
-------
A-66
will be done every five years during this period to verify that remediation goals are being
achieved.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
State $ 1,430,000 (of which $1,326,000 has been repaid by PRPs)
PRP $ 14,120,000
It is estimated that the following amounts will be spent for the O&M from now through
completion:
State $ 50,000
PRP $ 1,680,000
FRONTIER CHEMICAL, PENDLETON
Output
Responsible Party
Current
Schedule
RI/FS
DEC
COMPLETED
Record of Decision
DEC
COMPLETED
Remedial Design
PRPs
COMPLETED
Remedial Action
PRPs
COMPLETED
-------
A-67
FRONTIER CHEMICAL, ROYAL AVENUE
Site Program: Superfund
Summary Prepared by: EPA and DEC
Site Description
Frontier Chemical Waste Process, Inc. occupies approximately 9 acres, bordered by Royal
Avenue on the south and 47th Street on the east, in Niagara Falls, New York. The
Niagara River lies within 1 mile south of this site.
The facility treated chemical wastes from 1974 to December 1992 when the facility
closed. The Solid Waste Management Units (SWMUs) at the facility include:
• A treatment and pretreatment system for aqueous waste;
• Synthetic fuel-blending system for waste solvents/oils;
• A solvent recovery system;
• Bulk and drummed material handling, storage, and transfer facilities; and
• A hydrolysis process, tanks, old surface impoundments, an old waste pile,
and site trucks.
When operating, the active waste management units treated or stored approximately
25,140 tons of chemical wastes each year. The waste, which came from businesses
located in the eastern United States and southeastern Canada, can be classified as RCRA-
listed wastes, as well as RCRA-characteristic wastes.
There are two fractured bedrock aquifers present under this site. Groundwater from both
aquifers flows generally in a southeasterly direction. Although the flow is toward the
Niagara River, it is intersected by the Falls Street Tunnel, south of the site, where the
groundwater infiltrates into the tunnel. All of the dry-weather flow from the Tunnel is
diverted to the City of Niagara Falls wastewater treatment plant and treated before
discharge to the River.
The EPA and DEC added Frontier Chemical, Royal Avenue to the list of sites that
contribute a significant amount of contaminants to the Niagara River after extensive
groundwater investigation revealed the following chemicals at the site:
monochlorotoluene, methylene chloride, chloroform, dichlorobenzene, tetrachloroethylene
and other organic contaminants. Dense Non-Aqueous Phase Liquid (DNAPL) is present
at the southern edge of the facility.
In 1999, most of the site buildings were demolished with the rubble remaining on site.
-------
A-68
Interim Remedial Actions
This facility was formerly regulated under RCRA and 6 NYCRR Part 373. The company
that operated the facility went bankrupt in 1992. As a result, New York State issued an
Order in December 1992, requiring the owner to begin cleanup of the site by removing all
stored waste from the facility. When the company failed to meet the required deadline for
waste removal, the State requested that EPA secure the site and begin a Superfund
Response Action to remove the wastes.
Two phases were implemented at the site. Initially, an EPA contractor provided
maintenance to the drums and tanks at the facility. Phase I dealt with enforcement actions
leading to the removal of over 4,000 drums and 6,700 pounds of laboratory chemicals
from the site. Phase II dealt with enforcement actions for the removal of all wastes from
the 45 tanks on site.
Phase I began in October 1993, after approximately 5 months of negotiations with 430
potentially responsible parties (PRPs). The PRPs hired a cleanup contractor to remove all
laboratory chemicals and drums from the site and to send them to multiple disposal
facilities. This field work was completed in May 1994, and all wastes were subsequently
destroyed at off-site disposal facilities.
Phase II began in July 1994, after approximately 3 months of negotiations with over 400
PRPs. A consultant hired by the PRPs sampled the tanks and prepared a removal action
plan that was approved by EPA. Removal of the tank wastes was completed in March
1995.
Schedule for Completion
On April 6, 1994 the State of New York issued an Order which formally revoked the
operating Permit for the facility and revoked all authority to operate a hazardous waste
management facility at the Royal Avenue site. In March 1995, the site was listed on the
NYS Registry of Hazardous Waste sites as Class 2 (significant threat to the public health
or the environment, action required).
In March 1994, while the interim remedial actions were being implemented, the
Superfund Program assigned the site to be evaluated for possible inclusion in the National
Priorities List (NPL), which identifies sites requiring remedial action under Superfund.
EPA has ruled not to include this site on the NPL. The DEC initiated PRP search efforts
in 1998. In mid-1998, DEC contractors completed a review of facility records to identify
PRPs. DEC subsequently reviewed its internal records to finalize the list of PRPs. Notice
letters were issued to PRPs in December 1999.
In January 2001 the site was referred for RI/FS action under the NY State Superfund
program. The Focused Remedial Investigation was begun in 2001. The RI/FS is
expected to be completed in early 2004, with a final Record of Decision expected in 2004.
-------
A-69
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site
(EPA Emergency Removal Action):
Federal $ 3,690,000
State $ 50,000
PRP $ 3,600,000
It is estimated that the following amounts will be spent from now to the completion of
remediation:
Federal $ 0
State $ (Not available)
PRP $ (Not available)
FRONTIER CHEMICAL, ROYAL AVENUE
Output
Responsible Party
Target Date
RFI Work plan Approval (groundwater
investigation)
DEC
COMPLETED
RFI Completion
(groundwater investigation)
Permittee
COMPLETED
Remedial Investigation
DEC
COMPLETED
Feasibility Study
DEC
2004
Remedial Design
Dependent on ROD and subsequent RD/RA
Order negotiations with PRP group.
Remedial Action
-------
A-70
OCCIDENTAL CHEMICAL - DUREZ DIVISION, NORTH TONAWANDA
Site #24-37
Site Program: New York State DEC Division of Environmental Remediation
Summary Prepared by: DEC
Site Description
The Occidental Chemical Corporation (OCC) Durez site occupies about 40 acres in the
city of North Tonawanda. The site is located about 1 1/4 miles east of the Niagara River.
The Durez plant has been in operation since 1926, producing various plastic formulations.
Chemicals deposited on site include: chlorinated benzenes, phenol, chlorinated phenols,
chlorotoluene, and other organic compounds. During 1995, the plant ceased
manufacturing operations and the site facilities were demolished. Operation of remedial
systems at the site continue.
Two aquifers, one overburden and one bedrock, are present under this site. The
overburden aquifer unit is the primary aquifer of concern. The bedrock aquifer, for the
most part, is isolated from overlying chemical contamination by a confining clay layer.
Prior to remediation, groundwater in the overburden flowed in several directions and was
complicated by storm drains and sewers to the north, northwest, and southwest of the site.
The regional overburden and bedrock groundwater flow is to the southwest, toward the
Niagara River.
Remedial Actions
Remedial actions have been conducted under several consent orders and have addressed
the following three areas:
• Plant site: An 8450-feet long groundwater interceptor trench has been constructed
around the entire plant perimeter to collect contaminated groundwater for
treatment at an on-site carbon treatment system.
• Off site: Off-site contaminants from some 22,000 feet of City of North Tonawanda
and OCC Durez plant sewers were removed.
• Pettit Creek Cove: Remediation of the Pettit Creek Cove was completed in 1995
under consent order. This remediation included excavation and removal of
contaminated soils and sediments from the cove and the Little Niagara River,
removal and treatment of dense non-aqueous phase liquid (DNAPL), and
restoration of the cove as a wetland. A total of 23,500 cubic yards of soil and
sediment were removed and transferred to licensed disposal facilities.
All remedial construction activities have been completed. Operation of plant groundwater
systems will continue, probably for decades, until no longer needed. Approximately
-------
A-71
25,000 cubic yards of contaminated sediments from sewers and from Pettit Cove were
removed during the Remedial Action. Biomonitoring sampling by the Ontario Ministry of
the Environment in 1997, and recent water quality sampling by the DEC, detected the
possible release of OCC Durez contaminants of concern into the post-remedial Pettit
Creek Cove. The extent of the sampling was limited to a very small area at the mouth of
the Pettit Creek Flume storm sewer. As a result, OCC agreed to undertake a supplemental
investigation of the Pettit Creek Cove to ascertain the cove's current condition and to
demonstrate the effectiveness of the completed remedial programs. Sampling of cove
sediment, completed October 1999, found that low levels of Durez contaminants were
present in recently deposited sediment emanating from the Pettit Flume storm sewer.
OCC believes the contamination to be residual from the sewer cleaning project of 1994.
In response, OCC completed maintenance dredging of 400 cubic yards of the recently
deposited sediment in May 2000.
Remediation Costs
Following are estimated amounts that have been spent for this remediation project:
State $ 510,000
PRP $ 39,000,000
OCC - DUREZ, NORTH TONAWANDA
Output
Responsible
Party
Current
Schedule
Remedial Construction:
Plant Site
PRP
COMPLETED
Sewer Clean-up
PRP
COMPLETED
Pettit Creek Cove:
RI/FS
PRP
COMPLETED
Record of Decision
DEC
COMPLETED
Remedial Design
PRP
COMPLETED
Remedial Action
PRP
COMPLETED
-------
A-72
GRATWICK RIVERSIDE PARK
Site # 68
Site Program: New York State DEC Division of Environmental Remediation
Summary Prepared by: DEC
Site Description
The Gratwick Riverside Park site occupies about 53 acres in the City of North Tonawanda
and borders the Niagara River.
Prior to 1960, the site was used for the disposal of metallurgical slag. During the period
1960 to 1968, the site was operated as a landfill accepting municipal and industrial wastes.
It is known that phenolic wastes from Occidental Chemical - Durez were disposed at the
Gratwick Park site.
The Gratwick Park site contains about 13 feet of fill underlain by a discontinuous
glaciolacustrine unit above glacial till. The till layer acts as an aquitard (or barrier) to
downward groundwater flow from the overburden/fill aquifer to the next significant
aquifer, in the Camillus Shale bedrock. Each aquifer flows generally to the southwest,
towards the Niagara River.
Site Investigation
Gratwick Riverside Park is a DEC-lead site. After completion of a Remedial
Investigation/ Feasibility Study (RI/FS) of the site under State Superfund, a Record of
Decision (ROD) selecting a remedy was issued in February 1991. In May 1996, after
lengthy and difficult negotiations, the PRPs agreed to design and implement the selected
remedy. In February 1997, the City of North Tonawanda (one of the PRPs) entered into a
Title 3 contract for state funding of its share (approximately 34%) of project design and
construction costs.
Remedial Design (RD) started in early 1996. The design includes:
• Shoreline protection
• Hydraulic barrier (slurry wall) between site and river
• Cap over the site to allow it to be used as a park
• Collection of contaminated groundwater
During design, samples of river sediment along the shoreline indicated the presence of
relatively low levels of site-related contamination. It was also determined that steps
should be taken to improve the habitat value of the shoreline area. To address these issues
and the shoreline protection component of the remedy, the design was modified to include
covering portions of the river bottom with soil that could support selected vegetation to be
planted, and to include features to provide erosion resistance. These changes are
incorporated in an amendment to the ROD issued in January 1999.
-------
A-73
Construction of the remediation measures began in June 1999, and was substantially
completed in November 2001.
The components of the remediation of this site include the following:
a permeable soil cap, which includes a six inch fertile layer for planting of
appropriate vegetation,
a subsurface hydraulic barrier wall along the entire shoreline of the site,
approximately 5600 feet long, to separate the contaminated leachate on the site
from the river waters,
rip rap stabilization and protection of the shoreline,
remediation of three existing storm sewer lines,
removal of an area of soils contaminated by viscous material approximately fifty
feet square, and
a groundwater/1 eachate collection system.
Over the 2001-2002 winter season, erosion of portions of the river shoreline protection
was noted. Designs for repairs to this erosion have been completed and will be
constructed during the 2004 construction.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
It is estimated that the following amounts will be spent from now to the completion of
remediation:
State
PRP
$ 2,550,000
$ 5,000,000
State
PRP
$ 450,000
$ 430,000
Operation and Maintenance costs are estimated at $1,140,000 for ten years.
-------
A-74
GRATWICK RIVERSIDE PARK
Output
Responsible Party
Current
Schedule
RI/FS
DEC
COMPLETED
Record of Decision
DEC
COMPLETED
Remedial Design
Completion
PRPs
COMPLETED
Remedial Action
Completion
PRPs
COMPLETED
-------
A-75
MOBIL OIL
Site # 141
Site Program: New York State DEC Division of Environmental Remediation
Summary Prepared by: EPA/DEC
Site Description
The Mobil Oil site associated with Niagara River Toxics Management Plan (NRTMP)
priority toxic chemicals is a 3-acre area in the southeast portion of an approximately 62-
acre Mobil facility in the City of Buffalo. The site is located adjacent to the Buffalo
River, about 5 miles upstream of the confluence of the Buffalo and Niagara Rivers.
The entire facility was used by Mobil for oil refining from 1951 to 1981. The 3-acre area
of concern was used by the City of Buffalo for disposal of municipal wastes before being
sold to Mobil in 1951. Mobil used it until 1976 for the disposal of unknown quantities of
tetraethyl lead sludge, lubricating sludges, spent catalysts, and other wastes.
The site consists of varying amounts of fill underlain by a sand and gravel unit. Below the
sand and gravel unit is a clay layer, followed by glacial till and then the Onondaga
Limestone. Groundwater flow across the site is generally to the south toward the Buffalo
River.
Site Investigation
From 1982 to 1983, various investigations of the 3-acre site were conducted by the U.S.
Geological Survey and by DEC. In 1985, Mobil and DEC signed a Consent Order to
perform a Phase II investigation. The Phase II investigation, completed in 1987, included
soil sampling, groundwater monitoring, and surface water and sediment sampling from the
Buffalo River. The highest concentrations of lead and volatile organic compounds were
found in the soil and river sediment. The highest concentrations of semi-volatile
base/neutral compounds were found in the soil and groundwater. Liquid petroleum was
found in a monitoring well.
In 1988, based on the site investigations, the 3-acre Mobil site was re-classified as Class 3
(does not present a significant threat to the public health or the environment, action may
be deferred). Tetraethyl lead has extremely low solubility in water and is not expected to
significantly migrate off site through groundwater. However, tetraethyl lead is highly
soluble in petroleum products, so that any spill of fuel oils in the area could mobilize it
and carry it to the Buffalo River.
-------
A-76
Site Remediation
Around 1971 Mobil Oil began operation of a well point system (WPS) installed along the
Buffalo River. The WPS consists of a series of interconnected wells designed to recover
groundwater and petroleum product and prevent petroleum seepage to the Buffalo River.
The WPS extends approximately 1600 feet along the south-facing side of the site, from the
3-acre disposal area toward Babcock Street. In February 1989, Mobil notified DEC of
liquid phase petroleum encountered during the installation of geotechnical borings. This
report prompted additional site investigation, and remedial measures were instituted to
recover petroleum product. In 1993, six dual-pump recovery wells were activated. Each
of the recovery wells is equipped with both groundwater and product recovery pumps.
Five of the six recovery wells are presently being operated in conjunction with the WPS.
The recovery wells are located outside the 3-acre disposal area, within the south-central
portion of the Mobil facility.
In 1994, the entire 62-acre Mobil facility, including the 3-acre area of concern, was
selected for inclusion in the DEC Multimedia Pollution Prevention (M2P2) program based
in part on the facility's involvement with multiple divisions within DEC (Division of Air
Resources, Division of Hazardous Substance Regulation, Division of Environmental
Remediation, Division of Regulatory Affairs, Division of Solid Waste, Division of Water).
The goal of the M2P2 program is to provide an integrated approach to the environmental
management of the facility. The M2P2 facility team conducted a multi-media inspection to
better coordinate the various facility remediation activities. A Consent Order was signed
on May 20, 1997 to undertake further investigation and remediation. The results of the
additional site facility investigation were submitted to the DEC and EPA on November 25,
1998. Three areas of the site (the Elk Street Lot, the Former Lube Building Area & the
Buffalo Terminal Disposal Area) were identified as requiring further investigation to
determine the extent of contamination. The results of the further site facility investigation
were submitted to the DEC and EPA on 12/15/99. The results of additional investigations
of the Babcock Street Properties and the Eastern Tank Yard (Buffalo Terminal Disposal
Area) were submitted on 6/11/01 and 7/5/01, respectively. The results of completion of
the investigation of the remaining areas of the site were submitted in March 2002. In
November 2002, the remaining three chambers of the former Main Inground Oil/Water
separator were permanently closed by dewatering, cleaning and backfilling of the
chambers.
Mobile continues to coordinate with DEC on various means to enhance remedial
system(s) in place at the site. Various field tests were conducted by Mobil in this regard
during 2003.
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
-------
A-77
Federal $ (Not available)
State $ (Not available)
PRP $ (Not available)
It is estimated that the following amounts will be spent from now to the completion of
remediation:
Federal $ (Not available)
State $ (Not available)
PRP $ (Not available)
MOBIL OIL
Output
Responsible Party
Previous
Target Date
Current
Schedule
Phase I Investigation
DEC
Sept 1983
COMPLETED
Phase II Investigation
PRP
Dec 1986
COMPLETED
Re-classification to Class 3*
DEC
Dec 1988
COMPLETED
Site Investigation
PRP
Nov 2000
COMPLETED
Class 3 means that the site does not present a significant threat to the public health or
the environment and that action may be deferred. Further remediation will be
coordinated under the M2P2 program, with the schedule to be determined.
-------
A-78
IROQUOIS GAS - WESTWOOD PHARMACEUTICAL
Site Code 9-15-141
Site Program: New York State DEC Division of Environmental Remediation
Summary Prepared by: DEC
Site Description
The Iroquois Gas - Westwood Pharmaceutical Hazardous Waste Site is 8.8 acres in size.
The site is bounded on the: east by Dart Street, north by the City of Buffalo vehicle
impoundment facility, west by Scajaquada Creek, and south by residential properties. The
site is predominately covered by asphalt or buildings, and is fenced, which precludes
direct exposure to the public. The potential for site contaminants to be transported via
ground water to Scajaquada Creek exists.
Iroquois Gas Company, predecessor to National Fuel Gas Distribution Corporation (NFG)
used the site from the turn of the century to about 1955 to produce manufactured gas.
After 1955, NFG stored natural gas and oil at the site, with such storage believed to have
continued into the 1960's. In 1972 Westwood Pharmaceuticals, Inc. purchased the site and
constructed a 100,000 square foot warehouse on the southwest portion of the site.
In the fall of 1985, during building construction, buried tar separator pits and an oil
storage tank foundation were encountered, along with fill and soils containing tar-like and
oily residues. As a result, construction plans were modified to permit excavation,
evaluation and proper disposal of the potentially contaminated soils, materials and liquids.
In 1985, Westwood also began an investigation of the site. The investigation indicated the
presence of both soil and ground water contamination.
Site Investigation
In 1989 DEC requested that Westwood undertake a Remedial Investigation and Feasibility
Study (RI/FS) to assess the nature and extent of contamination at the site. Ultimately,
Westwood agreed to undertake the RI/FS, with DEC oversight, under a Partial Consent
Decree issued by the Federal Court. The purpose of the RI was to define the nature and
extent of any contamination resulting from previous activities at the site. Field work for
the RI started in April 1992 and was completed in June 1993.
The results of the RI are as follows:
The soil at the site is primarily contaminated with PAHs (Polynuclear Aromatic
Hydrocarbons), BTEX (Benzene, Toluene, Ethylbenzene, Xylene), lead and
cyanide;
Ground water in the upper aquifer (fill, with maximum depth of up to 32 feet) is
contaminated with PAHs and BTEX;
-------
A-79
Substrate below the fill consists of a silty clay layer to a depth of 60 feet, followed
by a layer of sand and gravel, and then bedrock. No significant contamination has
been found in the sand and gravel layer; the direction of ground water flow is
towards Scajaquada Creek.
Based on RI data, the ground water discharge to the creek is estimated to be 7350 gallons
per day; the direction of flow of NAPL (liquid, non-water soluble chemicals) is also
towards the creek. The estimated amount of NAPL entering the creek is 440 lb/year; the
chemicals of concern (BTEX and PAHs) in the NAPL and ground water are estimated to
be migrating to the creek at a rate of 261 lb/year; the creek sediments are primarily
contaminated with the same contaminants which are present in soil, ground water and
NAPL.
In March 1994, the Department signed a Record of Decision which outlined a Remedial
Action Plan calling for:
• Construction of a clay cap to isolate the source area contaminants;
• In Situ (in place) bio-treatment of soil and groundwater, if feasible;
• Installation of a vertical sheet piling barrier wall and extraction wells for ground
water control and removal of contaminated ground water;
• Treatment of extracted ground water and NAPL before proper disposal;
• Long term Operation & Maintenance.
The Remedial Action Plan also addresses contamination in Scajaquada Creek and
includes: excavation of contaminated sediments originating from the site and restoration
of the creek channel to background conditions.
Note that DEC found bio-treatment to be infeasible. DEC will review this decision at
five-year intervals to determine if any new technologies are feasible.
Remedial Actions
For remediation purposes, the site was divided into two operable units: Operable Unit 01
(Main Plant) and Operable Unit 02 (Scajaquada Creek). Westwood is undertaking the
remediation of the Main Plant site and National Fuel Gas is responsible for remediation of
Scajaquada Creek.
Remedial construction began in November 1996, with installation of the sheet pile barrier
wall. All remedial work on the Main Plant site was completed in 1997 and remediation of
Scajaquada Creek sediments commenced in July 1998 and was completed in March 1999.
The Remedial action includes two wells which extract NAPL from beneath the creek bed.
-------
A-80
Remediation Costs
Following are estimated amounts that have been spent to date on remediating this site:
State $ 150,000
PRP $ 6,500,000
It is estimated that the following amounts will be spent from now to the completion of
remediation, including operation and maintenance:
State $ 100,000
PRP $ 500,000
IROQUOIS GAS - WESTWOOD PHARMACEUTICAL
PLANT SITE:
Output
Responsible Party
Current
Schedule
Record of Decision
DEC
COMPLETED
Remedial Design
PRP
COMPLETED
Remedial Action
PRP
COMPLETED
CREEK SITE:
Output
Responsible Party
Current
Schedule
Record of Decision
DEC
COMPLETED
Remedial Design
PRP
COMPLETED
Remedial Action
PRP
COMPLETED
-------
A-81
BOOTH OIL
Site Program: New York State DEC Division of Environmental Remediation
Summary Prepared by: DEC
Site Description
The Booth Oil site is located at 76 Robinson Street in the City of North Tonawanda. The
site occupies approximately 2.7 acres on three parcels of land each separated by railroad
tracks operated by CSX. The site is located about 500 feet from the Little Niagara River.
Waste oils were refined at the site for more than 50 years, until the phased plant closure in
the early 1980's. During processing, frequent spills occurred and oil was periodically
discharged to the Little Niagara River via surface water run-off through the Robinson
Street storm sewer.
Site Investigation
The RI identifies oil saturated soils on site containing PCB, VOCs, Semi-VOCs, and
PAHs. An investigation of the River indicated that oil/PCB waste from the Booth Oil site
is limited to a small area in the vicinity of the outfall.
Two Records of Decision were issued: the first in March 1992 (Operable Unit OU1,
on-site) and the second in March 1993 (Operable Unit OU2, Little Niagara River). The
remedy consisted of the excavation of contaminated on-site soils, sewer sediments and a
limited area of sediment in the Little River. Contaminated ground water will also be
extracted and treated.
The RI/FS was performed under State Superfund. However, many Potentially
Responsible Parties (PRPs) exist, including the site owners and numerous generators who
shipped waste to the site.
A PRP proposal for an alternate remedy was accepted in June 1998. In 2002, the DEC
amended the earlier RODs. The amended remedy is similar to the previously selected
remedies, however, contaminated soil and sediment will be excavated and disposed of off-
site, rather treating these materials on-site. The components of the amended remedy
include:
Contaminated soil excavated down to the clay layer underlying the site;
Storm sewer sediment removed from the Robinson Street storm sewer and its catch
basins;
Contaminated sediments in the Little River excavated and disposed of with the
contaminated site soils;
Water produced during de-watering of excavations treated on site prior to
discharge;
-------
A-82
All contaminated soils and sediments removed during remediation disposed of in a
permitted disposal facility;
Excavations backfilled and graded with clean fill;
Deed restrictions and long-term monitoring program to address any residual
contamination.
Construction to implement the remedy selected in the August 2002 ROD began in July
2003 and was completed in December 2003.
A schedule for remediation of the site follows.
Remediation Costs
Following are estimated amounts that have been spent through 1997 on remediating this
site:
It is estimated that the following amounts will be spent from now to the completion of
remediation:
State
PRP
$ 1,100,000
$ 0
State
Permittee
$ (Not available)
$ 5,000,000
-------
A-83
BOOTH OIL
Output
Responsible Party
Previous
Target Date
Current Schedule
OU1
RI/FS
DEC
Feb 1992
COMPLETED
ROD
DEC
Mar 1992
COMPLETED
Remedial Design
PRP
Mar 2003
COMPLETED
Remedial Action
PRP
June 2004
COMPLETED
OU2
RI/FS
DEC
Feb 1993
COMPLETED
ROD
DEC
Mar 1993
COMPLETED
Remedial Design
PRP
Mar 2003
COMPLETED
Remedial Action
PRP
.Tune 2004
COMPLETED
-------
------- |