O Baflelle
. . . Putting Technology To Work
Environmental Technology
Verification Program
Advanced Monitoring
Systems Center
Test/QA Plan for
Pilot-Scale Verification of
Continuous Emission
Monitors for Mercury
etVetVety

-------
TEST/QA PLAN
FOR
PILOT-SCALE VERIFICATION OF
CONTINUOUS EMISSION MONITORS FOR MERCURY
November 30, 2000
Prepared by
Battelle
505 King Avenue
Columbus, OH 43201-2693

-------
TABLE OF CONTENTS
Page
1.0 INTRODUCTION 		1
1.1	Test Description 		1
1.2	Test Qbj ective		1
1.3	Organization and Responsibilities 		2
2.0 APPLICABILITY 		10
2.1	Subject		10
2.2	Scope 		12
3.0 SITE DESCRIPTION 		14
3.1	Test Facility		14
3.2	RKIS Operation		18
4.0 EXPERIMENTAL DESIGN 		20
4.1	General Design 		20
4.2	Weekly Schedule		22
4.3	Test Conditions 		23
4.4	Test Procedures 		24
4.5	Data Comparisons 		32
5.0 STATISTICAL CALCULATIONS 		36
5.1	Relative Accuracy 		36
5.2	Correlation with Reference Method 		37
5.3	Precision 		37
5.4	Calibration and Zero Drift		38
5.5	Sampling System Bias 		38
5.6	Interferences 		39
5.7	Response Time 		39
5.8	Low Level Hg Response 		40
6.0 MATERIALS AND EQUIPMENT 		41
6.1	Gases and Chemicals 		41
6.2	Reference Method 		42

-------
TABLE OF CONTENTS (Continued)
Page
6.3	RKIS Monitoring Equipment 		43
6.4	Equipment Used for Performance Evaluation Audits		43
7.0 QUALITY ASSURANCE/QUALITY CONTROL 		45
7.1	Equipment Calibrations 		45
7.2	Assessment and Audits 		46
8.0 Data Analysis and Reporting 		50
8.1	Data Acquisition 		50
8.2	Data Review 		51
8.3	Reporting		51
9.0 HEALTH AND SAFETY 		54
10.0 REFERENCES 		55
Tables
Table 3-1. Design Characteristics of the RKIS 		16
Table 3-2. Summary of RKIS Pollutant CEMs 		18
Table 4-1. Weekly Schedule of Mercury CEM Verification Testing 		22
Table 4-2. Summary of Flue Gas Constituent Concentrations Planned for
Use in Verification Testing 		24
Table 4-3. Interferant Gases and Concentrations to Be Used in
Interference Testing 		30
Table 4-4. Summary of Data to Be Obtained in Mercury CEM Verification Test		33
Table 7-1. Summary of PE Audits on RKIS Measurements 		47
Table 8-1. Summary of Data Recording Process for the Verification Test 		52
Figures
Figure 1. Organization Chart for the Verification Test 		3
Figure 2. Side View (top) and End View (bottom) of the RKIS Test Facility 		15
Figure 3. Schedule of Verification Test Day with Ontario Hydro Sampling 		28
Figure 4. Schedule of Interference Test Day 		29
Figure 5. Schedule for Low-Level Hg Detection Test 		31

-------
DISTRIBUTION LIST
Mr. Joseph Siperstein
Ohio Lumex Co., Inc.
5405 East Schaaf Road
Cleveland, Ohio 44131
Mr. Philip C. Efthimion
EEI, Inc.
P.O. Box 6
Pluckemin, NJ 07978
Dr. Peter Stockwell
Managing Director
P.S. Analytical, Ltd.
Arthur House, Crayfields Industrial Estate
Main Road, Orpington, Kent BR5 3HP
England
Mr. Frank Schaedlich
Tekran, Inc.
1-132 Railside Road
Toronto, Canada M3A 1A3
Dr. Koji Tanida
Director, Tech Center
Nippon Instruments Corp.
14-8, Akaoji, Takatsuki, Osaka, 569-1146,
Japan
Ms. Elizabeth A. Betz
U.S. Environmental Protection Agency
National Exposure Research Laboratory
MD-44
Research Triangle Park, NC 27711
Mr. Robert Fuerst
U.S. Environmental Protection Agency
National Exposure Research Laboratory
MD-46
Research Triangle Park, NC 27711
Mr. Chris Winterrowd
ARCADIS Geraghty & Miller, Inc.
4905 Prospectus Drive, Suite F
Durham, NC 27705
Ms. Elizabeth Hunike
Quality Assurance Specialist
U.S. Environmental Protection Agency
National Exposure Research Laboratory
ERC Annex, MD-46
Research Triangle Park, NC 27711
Mr. Jeffrey V. Ryan
MD-04
USEPA Mailroom
Research Triangle Park, NC 27711

-------
Page 1 of 55
Version 2.1
Date: 11/30/00
1.0 INTRODUCTION
1.1 Test Description
This test/quality assurance (QA) plan provides detailed procedures for a verification test
of continuous emission monitors (CEMs) used to measure total and chemically speciated
mercury (Hg) in source emissions. The verification test will be conducted under the auspices of
the U.S. Environmental Protection Agency's (EPA) Environmental Technology Verification
(ETV) program. The purpose of ETV is to provide objective and quality assured performance
data on environmental technologies, so that users, developers, regulators, and consultants have an
independent and credible assessment of what they are buying and permitting.
The verification test will be performed by Battelle, of Columbus, OH, which is EPA's
partner for the ETV Advanced Monitoring Systems (AMS) Center. The scope of the AMS
Center covers verification of monitoring methods for contaminants and natural species in air,
water, and soil. In performing the verification test, Battelle will follow procedures specified in
this test/QA plan, and will comply with quality requirements in the "Quality Management Plan
for the ETV Advanced Monitoring Systems Pilot" (QMP)/7'
1.2 Test Objective
The objective of the verification test is to quantify the performance of commercial
mercury CEMs, by comparison to reference Hg measurements, and by challenges with mercury
standard gases and interferences, under controlled conditions in a pilot-scale combustion facility.
A subsequent test, based on a separate test/QA plan, is planned to assess performance at a full-
scale facility.

-------
Page 2 of 55
Version 2.1
Date: 11/30/00
1.3 Organization and Responsibilities
The verification test will be performed by Battelle in cooperation with EPA and the
vendors who will be having their analyzers verified. The organization chart in Figure 1 shows
the individuals from Battelle, the vendor companies, and EPA who will have responsibilities in
the verification test. The specific responsibilities of these individuals are detailed in the
following paragraphs.
1.3.1 Battelle
Dr. Thomas J. Kelly is the AMS Center's Verification Testing Leader. In this role, Dr.
Kelly will have overall responsibility for ensuring that the technical, schedule, and cost goals
established for the verification test are met. More specifically, Dr. Kelly will:
•	Coordinate Battelle, EPA, contractor, and vendor staff to conduct the verification test
•	Guide the Battelle/EPA/contractor/vendor team in performing the verification test in
accordance with this test/QA plan
•	Have overall responsibility for ensuring that this test/QA plan is followed.
•	Prepare the draft test/QA plan, verification reports, and verification statements
•	Revise the draft test/QA plan, verification reports, and verification statements in
response to reviewers' comments
•	Respond to any issues raised in assessment reports and audits, including instituting
corrective action as necessary
•	Serve as the primary point of contact for vendor representatives
•	Establish a budget for the verification test and monitor the effort to ensure that budget
is not exceeded
•	Ensure that confidentiality of vendor information is maintained.

-------
Page 3 of 55
Version 2.1
Date: 11/30/00
Battelle
Management
Charles Lawrie
Battelle
Quality Manager
Jeffrey Ryan
EPA Pilot
Scale Facility

Karen Riggs
Battelle
Center Manager
Tom Kelly
Verification
Testing Leader
Robert Fuerst
EPA Center
Manager
Elizabeth Betz
EPA
' Quality Manager
V
Mercury CEM
Vendor
Representatives I
Contractor
Facility Operation and
Reference Measurements
Battelle
Statistics and
Data Analysis
Figure 1. Organization Chart for the Verification Test

-------
Page 4 of 55
Version 2.1
Date: 11/30/00
Ms. Karen Riggs is Battelle's AMS Center manager. As such, Ms. Riggs will:
•	Review the draft test/QA plan
•	Review the draft verification reports and statements
•	Coordinate distribution of final test/QA plan, verification reports, and statements
•	Ensure that necessary Battelle resources, including staff and facilities, are committed
to the verification test
•	Ensure that vendor confidentiality is maintained
•	Support Dr. Kelly in responding to any issues raised in assessment reports and audits
•	Maintain communication with EPA's Center Manager.
Mr. Charles Lawrie is Battelle's Quality Manager for the AMS Center. As such, Mr.
Lawrie will:
•	Review the draft test/QA plan
•	Maintain communication with EPA's Quality Manager for the AMS Center
•	Conduct a technical systems audit once during the verification test
•	Review results of performance evaluation audit(s) specified in this test/QA plan
•	Audit at least 10% of the verification data
•	Prepare and distribute an assessment report for each audit
•	Verify implementation of any necessary corrective action
•	Issue a stop work order if internal audits indicate that data quality is being
compromised; notify Battelle's AMS Center Manager if such an order is issued
•	Provide a summary of the QA/QC activities and results for the verification reports
•	Review the draft verification reports and statements
•	Ensure that all quality procedures specified in this test/QA plan and in the QMP(1) are
followed.

-------
Page 5 of 55
Version 2.1
Date: 11/30/00
Staff of Battelle's Statistics and Data Analysis Systems (SDAS) department will provide
statistics and data analysis support. In particular, SDAS staff will:
•	Contribute to the planning of statistical treatment of the CEMs data
•	Perform statistical calculations specified in this test/QA plan on the analyzer data
•	Provide results of statistical calculations and associated discussion for the
verification reports
•	Support Dr. Kelly in responding to any issues raised in assessment reports and
audits related to statistics and data reduction.
Staff of Battelle's Atmospheric Science and Applied Technology (ASAT) department
will support Dr. Kelly in planning and conducting the verification test. These staff will:
•	Assist in planning for the test, and making arrangements for the installation of the
CEMs
•	Assist vendors and test facility staff as needed during the CEM installation and
verification testing
•	Assure that test procedures and data acquisition are conducted according to this
test/QA plan
1.3.2 Vendors
Vendor representatives will:
•	Review the draft test/QA plan
•	Approve the final test/QA plan
•	Participate in required safety training at the test facility before installation of their
CEMs

-------
Page 6 of 55
Version 2.1
Date: 11/30/00
•	Attend a pre-study site visit to review facility requirements for testing
•	Provide a mercury CEM for the duration of the verification test
•	Commit a trained technical person to operate, maintain, and repair the CEM
throughout the verification test
•	Participate in verification testing, including providing data acquisition for their
mercury CEMs
•	Provide to Battelle staff the data from their CEM at the conclusion of each test day
•	Review their respective draft verification report and verification statement.
1.3.3 EPA
EPA's responsibilities in the AMS Center are based on the requirements stated in the
"Environmental Technology Verification Program Quality and Management Plan for the Pilot
Period (1995-2000)" (QAMP).(2) The roles of specific EPA staff under the QAMP are as
follows:
Ms. Elizabeth Betz is EPA's Quality Manager. For the verification test, Ms. Betz will:
•	Review the draft test/QA plan
•	Perform, at her option, one external technical systems audit during the verification test
•	Notify the Battelle AMS Center's Quality Manager to facilitate a stop work order if an
external audit indicates that data quality is being compromised
•	Prepare and distribute an assessment report summarizing the results of the external
audit, if one is performed
•	Review the draft verification reports and statements.
Mr. Robert Fuerst is EPA's AMS Center Manager. As such, Mr. Fuerst will:
Review the draft test/QA plan

-------
Page 7 of 55
Version 2.1
Date: 11/30/00
•	Approve the final test/QA plan
•	Review the draft verification reports and verification statements
•	Oversee the EPA review process on the draft test/QA plan, reports, and verification
statements
•	Coordinate the submission of reports and verification statements for final EPA
approval.
This verification test will be conducted in collaboration with Jeffrey Ryan of EPA's
Office of Research and Development, National Risk Management Research Laboratory
(ORD/NRMRL). Mr. Ryan's responsibilities are:
•	Coordinate the operation of the pilot scale facility for the purposes of ETV testing
•	Conduct pre-verification testing to document the capabilities of the pilot scale facility
and reference methods
•	Coordinate the installation of vendors' equipment at the pilot scale facility
•	Communicate needs for safety and other training of staff working at the pilot scale
facility
•	Contribute to the development of the draft test/QA plan
•	Review the draft test/QA plan
•	Provide input for the verification test reports
•	Provide input in responding to any issues raised in assessment reports and audits
related to pilot facility operations.
•	Review draft verification reports and verification statements.

-------
Page 8 of 55
Version 2.1
Date: 11/30/00
1.3.4 Contractor
The RKIS Facility is operated for EPA by an on-site contractor (Arcadis/Geraghty and
Miller). This contractor will perform some duties under contract with EPA, and additional duties
related to the verification test under a subcontract with Battelle. The contractor's responsibilities
will be:
For EPA:
•	Assemble trained technical staff to operate the pilot scale facility
•	Ensure that the facility is fully functional prior to the times/dates needed in the
verification test
•	Oversee technical staff in facility operation during the verification test
•	Ensure that operating conditions and procedures for the pilot scale facility are
recorded during the verification test
•	Review and approve all data and records related to facility operation
For Battelle:
•	Review the draft test/QA plan
•	Adhere to the quality requirements in this test/QA plan and in the QMP
•	Assemble trained technical staff to conduct reference method sampling for the
verification test
•	Contract for and oversee laboratory analysis of the reference method samples
•	Report reference method analytical and quality assurance results to Battelle in an
agreed-upon format
•	Provide input on facility operating conditions and procedures for the verification test
report

-------
Page 9 of 55
Version 2.1
Date: 11/30/00
• Support Dr. Kelly in responding to any issues raised in assessment reports and audits
related to facility operation.

-------
Page 10 of 55
Version 2.1
Date: 11/30/00
2.0 APPLICABILITY
2.1 Subject
This test/QA plan is applicable to the verification testing of commercial continuous
emission monitors for determining total and/or chemically speciated mercury in combustion
source emissions. Total mercury is the sum of mercury in all phases and chemical forms in the
combustion gas, including elemental mercury (Hg°) and oxidized mercury (primarily mercuric
chloride (HgCl2) and mercuric oxide (HgO)) vapors, and particulate-phase mercury. Most
commercial mercury CEMs do not measure the particulate phase mercury; instead they filter out
particulate matter, and measure the total of the vapor-phase mercury species. This approach is
taken because at least for electrical generating facilities, recent stack test results indicate that the
great majority of emitted mercury is in the vapor phase.(3) Commercial CEMs may provide
chemical speciation data, i.e., the oxidized and elemental fractions of the Hg vapor species are
reported separately. This separation is commonly accomplished by a difference measurement, in
which oxidized mercury is intermittently chemically reduced or thermally decomposed to
elemental mercury for detection.
The commercial mercury CEMs also use a variety of final analytical approaches to detect
mercury. Cold vapor atomic absorption spectroscopy (CVAAS), cold vapor atomic fluorescence
spectroscopy (CVAFS), and differential optical absorption spectroscopy (DOAS) are all used, but
can detect only elemental mercury, and so require the speciation approaches outlined above to
determine oxidized mercury. Atomic emission spectroscopy (AES) is used in one commercial
CEM, and has the advantage that in principle all forms of mercury, including particulate mercury,
are converted to elemental mercury and detected equally. This approach provides a true total
mercury measurement, but does not provide any information on speciation.
The terminology to be used in this test/QA plan is as follows:

-------
Page 11 of 55
Version 2.1
Date: 11/30/00
•	Total mercury (TM) - the sum of all vapor and particulate mercury, whether elemental
or oxidized;
•	Total vapor-phase mercury (TVM) - the sum of all vapor-phase mercury species,
whether elemental or oxidized;
•	Elemental mercury (EM) - vapor-phase Hg°;
•	Oxidized mercury (OM) - the sum of vapor-phase non-elemental mercury, regardless
of chemical species (e.g., HgCl2, and others).
•	Particulate mercury (PM) - mercury in the particulate phase.
The CEMs tested according to this plan will be verified for their measurement of any and
all of the applicable mercury components listed above. For example, a monitor that determines
TVM and EM, and by difference determines OM, will be verified for measurements of all three
components. In the U.S., emission regulations on combustion sources are expected to address
only total mercury. However, there are valuable non-regulatory uses of mercury speciation data,
and therefore speciation capabilities of the CEMs will be verified.
Verification testing requires a basis for establishing the quantitative performance of the
tested technologies. For the verification testing conducted under this test/QA plan, the basis of
comparison consists of a reference method of measurement, i.e. the Ontario Hydro (OH)
method,(4) currently recognized as the most suitable procedure to determine oxidized and
elemental mercury in source emissions. This method is specifically designed for use in
environments containing high levels of sulfur dioxide (S02), and has shown agreement within
about 10% for total mercury with EPA Method 101 A, in trial runs at the pilot facility to be used
for this verification/5' and in other sampling tests.(e 8'6)
This test/QA plan calls for the use of a natural gas fired pilot-scale combustion facility as
the test bed for the verification. Such a facility allows flexibility in simulating different sources
of combustion flue gas, such as coal combustion or mixed waste incineration, by injecting
constituents into the combustion zone. However, other combustion sources, such as an

-------
Page 12 of 55
Version 2.1
Date: 11/30/00
incinerator, may also be used, provided they allow appropriate control of test conditions and
mercury levels.
2.2 Scope
The overall objective of the verification test described in this plan is to provide
quantitative verification of the performance of the mercury CEMs in realistic test conditions.
Since mercury CEMs are a relatively new group of instruments, performance expectations, and
procedures to assess their performance, are not fully established. EPA has published the draft
performance specification document designated as PS-12,(7) as a proposed description of how to
assess the acceptability of a mercury CEM upon installation and thereafter. However, the draft
PS-12 is patterned after performance specifications for CEMs for other pollutants, such as S02
and nitrogen oxides (NOx), and as a result it includes requirements which are inappropriate or
currently not feasible. For example, the draft PS-12 calls for the CEM to be able to measure both
vapor and particulate phase mercury. As noted above, most current CEMs do not determine
particulate-phase mercury. Also, the draft PS-12 calls for the use of absolute standards for both
EM and OM (the latter in the form of HgCl2). Although elemental mercury compressed gas
standards are becoming commercially available, they have not yet been widely used. The
stability of such standards appears to be good enough to assess instrumental drift and
precision,ic e X| but their absolute quantitation may not be sufficient to assess instrumental
accuracy. Comparable standards for HgCl2 do not yet exist. As a result of factors such as these,
and because PS-12 is a draft document soon to be revised, it is not appropriate to simply adopt
PS-12 procedures as the basis for this verification test. Instead, this test is designed to evaluate
CEM performance on key monitoring characteristics, while addressing some performance
requirements raised in PS-12 as closely as possible.
The performance parameters that are addressed by this test/QA plan include:

-------
•	Relative accuracy
•	Correlation with reference method
•	Precision
•	Calibration drift
•	Zero drift
•	Sampling system bias
•	Interference response
•	Response time.
Relative accuracy, correlation with the reference method, and precision (i.e., repeatability
at stable test conditions) will be assessed for whichever of the TM, EM, OM, and PM fractions
are measured by the commercial CEM. Calibration and zero drift, response time, and sampling
system bias will be assessed for EM only, using commercial compressed gas standards of EM.
Interference response will be assessed in sampling of the combustion facility flue gas, rather
than in sampling of diluted calibration gases, as called for in PS-12. Calibration error will not be
assessed in this test, because of the absence of absolute standards.
It is beyond the scope of this verification test to simulate the aging and exposures that
may affect a CEM during routine long-term use. This verification test evaluates the performance
of new CEMs, installed in a pilot-scale facility, over a relatively short test period, in the hands of
vendor staff skilled in their operation. It must be noted that long-term performance may be
different from that observed in the testing described here. However, the effort spent in installing
and maintaining each CEM will be documented, and the amount of time each CEM is operational
over the verification test period will be recorded, to assess data completeness.
Page 13 of 55
Version 2.1
Date: 11/30/00

-------
3.0 SITE DESCRIPTION
Page 14 of 55
Version 2.1
Date: 11/30/00
This verification test will be conducted at the Rotary Kiln Incinerator Simulator (RKIS) at
the EPA Incineration Research Laboratory in Research Triangle Park (RTP), North Carolina.
This section of the test/QA plan describes the RKIS and the procedures for operating it for this
test.
3.1 Test Facility
A schematic diagram of the RKIS is provided in Figure 2, and the RKIS design
characteristics are provided in Table 3-1. The RKIS was modified in 1997, for a simultaneous
test of eight multi-metals CEMs; Figure 2 and Table 3-1 reflect those modifications. The RKIS
consists of a primary combustion chamber, a transition section, and a fired afterburner in the
secondary combustion chamber. Both the kiln and afterburner are fitted with 73 kW (0.25
MMBtu/h) auxiliary fuel burners. Natural gas is the primary fuel, although liquid waste or fuel
oil can also be fired. Typical firing rates are 29 to 88 kW (0.1 to 0.3 MMBtu/h) to each of the
kiln and the afterburner.
Combustion flue gases exiting the afterburner are rapidly cooled to approximately 540°C
(1000°F) as they pass through a water-jacketed section of ductwork. Further cooling, to
approximately 340°C (650°F) or less, is achieved by adding air via an air dilution damper just
upstream of a 9.9 m (35 ft) long, 20.3 cm (8 in) diameter duct which contains the sampling ports.
Both the CEMs to be tested and the reference method measurements will use these sampling
ports.
Access for isokinetic flue gas sampling is available at several locations in the duct noted
above, via standard 3 inch (7.6 cm) and 4 in (10.2 cm) diameter National Pipe Thread (NPT)
couplings. These sampling ports are located in straight horizontal and vertical runs of circular
cross section, nominally 8 in (20.3 cm) diameter, Schedule 10 stainless steel pipe. The sampling
ports are configured as a ring of three ports, which includes a 10.2 cm (4 in) diameter port

-------
Page 15 of 55
Version 2.1
Date: 11/30/00
mi
TCI
0
""ft 	e
Ssnonrliry fombuSfan
PWSJ
AO#
S*K
, nil
1 i
® *
DO#
Pu#1	t
s egselai
LdgaiiJ
«¦ **rt
V Put
X ftmcsMti
and Ffoar
jSrsunf Plsar
TO
hltQ> 	|p< O
&
tJ
ilraSi&te TtwsttjflSwsiMi
Figure 2. Side View (top) and End View (bottom) of the RKIS Test Facility

-------
Page 16 of 55
Version 2.1
Date: 11/30/00
Table 3-1. Design Characteristics of the RKIS
Characteristics of the Primary Combustion Chamber
Length
1.83 m (6 ft)
Diameter, Outside
1.22 m (4 ft)
Diameter, Inside
Nominal 0.76 m (2.5 ft)
Chamber V olume
0.28 m3 (9.9 ft3)
Construction
0.64 cm (0.25 in) thick cold-rolled steel
Refractory
23 cm (9 in) thick high alumina castable refractory at maximum
I.D. point
Rotation
Counterclockwise, 0.25 to 2 rpm
Solids Retention Time
Batch system - solids remain until physically removed
Burner
Custom burner based on IFRF design rated at 73 kW (0.25
MMBtu/h) with liquid feed capability
Primary Fuel
Natural gas
Feed System:

Liquids
Fuel oil or liquid waste pumped into burner
Solids
Manual batch containers fed with ram rod
Temperature (max.)
1,100 °C (2,000 °F)
Characteristics of the Afterburner Chamber
Length
3 m (10 ft)
Diameter, Outside
1.22 m (4 ft)
Diameter, Inside
0.61 m (2 ft)
Chamber Volume:

Mixing Chamber
0.18 m3 (6.3 ft3)
Plug Flow Chamber
0.45 m3 (16 ft3)
Construction
0.64 cm (0.25 in) thick cold-rolled steel
Refractory
30 cm (12 in) thick high alumina castable refractory
Gas Residence Time
2 to 5 s depending on temperature and excess air
Burner
Custom burner based on IFRF design rated at 73 kW (0.25
MMBtu/h)
Primary Fuel
Natural gas
Temperature (max.)
1,100 °C (2,000 °F)

-------
Page 17 of 55
Version 2.1
Date: 11/30/00
opposite a 7.6 cm (3 in) diameter port and a single 7.6 cm (3 in) diameter port at right angles to
the other two. Eight sets of ports are in place. The first set of ports is located 4.3 m (14 ft)
downstream from the air dilution damper. The second set of ports is 1.4 m (4.5 ft) downstream
of the first set. Two additional sets of ports are located at 0.6 m (2 ft) intervals downstream, and
the remaining ports are at intervals of about two meters further downstream. The Hg CEMs
undergoing testing will be located at ports 5, 6, and 7 (Figure 2); the reference method sampling
will take place at the locations labeled RM1 and RM2 (Figure 2).
Flue gas concentrations of oxygen (02), carbon dioxide (C02), carbon monoxide (CO),
nitric oxide and total nitrogen oxides (NO/NOx), S02, and hydrogen chloride (HC1) are
monitored at the RKIS by means of continuous emission monitors for these species. These
CEMs are calibrated and operated by EPA and/or contractor staff as part of the normal operations
of the RKIS facility. These CEMs, which are identified in Table 3-2, can draw sample from
various points in the duct. In this test 02 content will be measured just downstream of the air
dilution damper and also in a section of duct downstream of the Hg CEM and reference method
locations. Comparing the upstream to downstream 02 measurement will provide verification that
neither the tested CEMs nor the reference method sampling are causing air in-leakage resulting in
flue gas sample dilution. Flue gas at the Hg CEM sampling locations will have a temperature of
up to 340°C (650°F), an oxygen content of about 15%, and a moisture content of about 7 percent
by volume. The duct is at a negative pressure (draft) of nominally 0.25 kPa (- 1 inch water
column). The volumetric flow rate is about 8.8 scm/min (310 scfm), resulting in flow velocities
that are nominally 1.8 to 2.9 m/s (5.9 to 9.5 ft/s). Flow velocities are essentially constant across
the duct diameter.
The RKIS facility CEMs will have two major roles in this verification test. First,
measurements of major diluent gases in the flue gas (02, C02) will be used, along with H20
content results obtained from the Ontario Hydro method, to assess air in-leakage as noted above,
and to establish the flue gas composition for adjustment of all test results to common conditions.
Second, measurements of pollutants (CO, S02, NO/NOx, HC1) will be used to document normal
flue gas composition, and to establish the target levels of interferants added to the RKIS flue gas.
That is, interferant levels will be achieved by actual measurements in the duct using the RKIS

-------
Page 18 of 55
Version 2.1
Date: 11/30/00
CEMs, rather than by calculated dilutions of standards for S02, CO, etc. injected into the flue
gas. In the case of NOx, the injected interferant will be NO; typically 5 to 10 percent of the
injected NO will be converted to N02 in the RKIS. HC1 levels may be prepared by injection of
HC1 gas, or of chlorine gas (Cl2), and will be monitored with the RKIS CEM for HC1. Injection
of Cl2 into the RKIS may produce both Cl2 and HC1, depending on the point of introduction of
the Cl2. In such cases the amount of Cl2 in the flue gas will be calculated as the amount injected
minus the HC1 measured by the HC1 CEM. This approach is made necessary by the absence of a
CEM for Cl2.
Table 3-2. Summary of RKIS Pollutant CEMs
Pollutant
Instrument
Principle
Measurement
Range(s)
02
Rosemount Analytical Model 755R
Paramagnetic
0-25%
co2
Horiba Model VIA510
NDIRa
0-20%
CO
Horiba Model PIR2000
NDIR
0-500 ppm
NOx
TECO Model 10
Chemiluminescent
0-250 ppm
S02
Bodenzeewerk Model MCS 100
GFCIR"
0-250, 0-2500 ppm
HC1
Bodenzeewerk Model MCS 100
GFCIR
0-100, 0-1000 ppm
a: NDIR = nondispersive infrared,
b: GFCIR = gas filter correlation infrared.
3.2 RKIS Operation
For all tests, both the kiln and the afterburner will be fired with natural gas. No waste or
simulated waste feed to the kiln will be employed, however mercury will be introduced into the
flue gas by atomizing an aqueous solution of mercuric nitrate (Hg(N03)2) into the afterburner.
The mercury solution will be atomized into an annulus inside the afterburner natural gas feed
tube. The solution will be atomized at the exit from that annulus, introducing Hg-containing
aerosol droplets directly into the burner flame. The droplets will evaporate rapidly in the flame

-------
Page 19 of 55
Version 2.1
Date: 11/30/00
zone, yielding primarily dry, vapor-phase mercury. The oxidation state of the mercury will be
manipulated by also introducing gaseous chlorine into the RKIS.
Two different mercury solutions will be used in the test, to produce both relatively low
Hg levels simulating those in coal-fired power plant flue gas, and much higher levels simulating
those in incinerator flue gas. In both cases, the solution addition rate will be nominally 10
mL/min. The high concentration solution will be diluted approximately ten-fold to make the
solution for the lower target concentration tests. The target low and high mercury concentrations
are about 8 |-ig/m3 and 80 |ig/m\ respectively.
Particulate matter will also be introduced into the flame zone, to produce a particulate
matter loading in the flue gas downstream. Particulate injection is needed primarily to create a
realistic flue gas environment, and also to provide a particulate Hg sample for the verification of
TM and PM measurement capabilities of any CEMs that determine the PM component. A K-
Tron mass-controlled feeder will be used to inject coal fly ash from a utility boiler directly into
the hot flue gas as it exits the kiln. The fly ash to be used was selected for its low reactivity with
vapor-phase mercury, and will be thoroughly characterized for mercury content. The particulate
loading during verification testing will be determined using the filter and front half catch from
the Ontario Hydro reference method trains, rather than from a separate Method 5 train. One
Ontario Hydro train from each of the two reference sampling locations will be used for
particulate loading determination in each run.
In addition to mercury and particulate matter, other common flue gas constituents will be
introduced, for simulation of flue gas composition, and for evaluation of potential interferences
in Hg CEM measurements. Specifically, Cl2, HC1, CO, S02, and NO will be introduced by
dilution of compressed gases into the flue gas.
Injection of mercury solutions, particulate matter, or gases will take place only after stable
operation of the RKIS is achieved and the RKIS flue gas cleaning system is operating within its
permit limits. Injection will begin at least 30 minutes before any reference sampling or
verification data collection takes place.

-------
4.0 EXPERIMENTAL DESIGN
Page 20 of 55
Version 2.1
Date: 11/30/00
4.1 General Design
The verification test described in this test/QA plan will be conducted over about a three-
week period, at the RKIS facility. The first week will be spent installing the commercial CEMs
at the RKIS, and conducting a shakedown run of all systems before the verification effort begins.
Testing will not begin until all the reference method equipment and RKIS facilities are fully
operational. Similarly, it is desirable that all the commercial CEMs be fully operational, to
participate in the verification test. However, to avoid delaying the start of the testing, it will be
required that all participating CEMs arrive at the facility by a specified day, and be ready to begin
testing within one week after arrival, or when the RKIS facility itself is fully ready, whichever is
later. CEMs which are not operational at that time may join the testing process once they come
on line.
The two weeks of testing will follow immediately after the setup/shakedown period. A
similar test schedule will be followed in each of the two weeks, but the Hg levels and the levels
of other flue gas constituents will be different in the two weeks. Verification will involve
comparisons of the CEM results with those from a time-integrated reference method (the Ontario
Hydro Method),(4) as well as challenges with interferences and with Hg° compressed gas
standards. In general, different test activities will be conducted on different days, but certain test
procedures will take place on every test day. All participating CEMs, and the reference method
sampling trains, will sample flue gas at the same time from the RKIS duct. However, it will not
be possible to co-locate the sampling points of all the CEMs. Tests at the RKIS facility have
shown that Hg concentrations are conserved in passage through the duct, so the exact location of
individual CEMs is not expected to introduce bias in the verification/5' Reference method
samples will be collected at both the upstream and downstream end of the duct in all verification
testing, to document the mercury levels and mercury speciation.
The performance parameters to be verified and the procedures with which they will be
tested are summarized below:

-------
Page 21 of 55
Version 2.1
Date: 11/30/00
•	Relative accuracy - by comparison to reference method results on flue gas samples;
•	Correlation - with reference method results;
•	Precision - by repeated readings under stable conditions;
•	Calibration drift/zero drift - by sampling of Hg° standard gas or zero gas;
•	Sampling system bias - by sampling of Hg° standard gas both through the CEM's
sampling probe and at the CEM's mercury analyzer;
•	Interferences - by addition of potential interferants to the flue gas;
•	Response time - by observation of instrument response with standard/zero gases;
•	Setup/Maintenance Needs - by observation of installation and maintenance efforts;
•	Data Completeness - by the fraction of the verification test completed.
Throughout the verification test, each CEM undergoing testing will be operated by the
CEM vendor's own staff. However, the intent of the testing is for the CEM to operate
continuously in a manner simulating operation at a combustion facility. As a result, once the
verification test has begun in each week of testing, no adjustment or recalibration will be
performed, other than what would be conducted automatically by the CEM in normal
unattended operation. Adjustments to the CEM may be made between the first and second
weeks of testing. Repair or maintenance procedures may be carried out at any time, but testing
will not be interrupted, and data completeness will be reduced if such activities prevent
completion of verification tests.
The schedule and procedures of this verification test are described in more detail in the
subsequent sections.

-------
4.2 Weekly Schedule
Page 22 of 55
Version 2.1
Date: 11/30/00
The Hg CEM testing will follow the weekly schedule shown in Table 4-1. The first four
days of the week are scheduled for verification test activities of various kinds, and the fifth day is
scheduled to allow for any repeat tests, or completion of items not completed on earlier
Table 4-1. Weekly Schedule of Mercury CEM Verification Testing
Day
AM/PM
Test Activity (Performance Parameter)
Monday
AM
Challenge with Hg° standard/zero gas (Calibration/Zero Drift)
PM
Flue gas sampling (Relative Accuracy, Correlation, Precision)
Tuesday
AM
Challenge with Hg° standard/zero gas (Calibration/Zero Drift)
PM
Flue gas sampling (Relative Accuracy, Correlation, Precision)
Wednesday
AM
Challenge with Hg° standard/zero gas (Calibration/Zero Drift)
PM
Flue gas sampling (Relative Accuracy, Correlation, Precision)
Thursday
AM
Challenge with Hg° standard/zero gas (Calibration/Zero Drift)
PM
Spiking of flue gas (Interferences)3
Friday
AM
Challenge with Hg° standard/zero gas (Calibration/Zero Drift,
Response Time,a Sampling System Bias)
PM
Low level Hg response;3 completion or repetition of tests
Saturday
AM/PM
Test preparations / Maintenance
Seven

Down day - no testing
a: Test performed only in the first week of verification testing.
days. A day for maintenance and a scheduled down day complete the week. As Table 4-1
shows, on Monday, Tuesday, and Wednesday of the test week, verification testing will consist of
challenging each CEM with zero gas and a Hg° gas standard in the morning, followed by flue gas
sampling with both the CEMs and the reference method in the afternoon. As noted above, once
the verification test has begun on Monday, no further adjustment of the CEM will take place until
the end of the first week of testing. On Thursday and Friday of the first test week, the same Hg°

-------
Page 23 of 55
Version 2.1
Date: 11/30/00
challenge will be carried out in the morning, resulting in a series of five successive days for this
test. On Friday morning, a sampling system bias test will also be conducted, in which the Hg°
standard gas will first be sampled through each CEM's sample interface, and then directly at the
CEM's pollutant analyzer. Also on Friday morning, the response time of the CEMs will be
tested, using the Hg° standard gas. The afternoon of Thursday will be devoted to testing of
interferences in the flue gas matrix, and part of the afternoon of Friday will be used to perform a
qualitative test of the CEMs' ability to monitor Hg at levels below 5 |J.g/m3. The rest of Friday
afternoon will be available to repeat tests from earlier days, and to address any unforseen
problems or opportunities in sampling. Saturday of the first week will be used to prepare for the
next week of testing, or to maintain the RKIS or other systems.
The second week of verification testing will be similar to the first, except that the
interference, response time, and low level Hg tests will not be performed. As a result, testing
activities in the second week will be completed by Thursday. This schedule allows ample time
for completion or repetition of any test activities.
The interference testing will be conducted by establishing a stable mercury addition to the
RKIS combustion zone, and then monitoring that Hg level continuously with the CEMs while
adding other flue gas constituents one at a time or together. The effect of the interferants will be
assessed by comparing the CEM response with only Hg added, to the response when Hg and one
or more interferants are added. The Hg level used in this test will be the 8 |J.g/m3 level to be used
in the first week of verification testing. The interferant levels used will be relatively high values
to assure a definite conclusion about the presence or absence of an interference.
4.3 Test Conditions
Table 4-2 shows the approximate levels of mercury and other constituents that will be
prepared in the flue gas stream, for each of the two weeks of testing. Conditions for the first
week are intended to approximate those in a coal-fired power plant, and in the second week those
in a municipal waste incinerator. The order of these two test conditions is chosen so that the
lower mercury concentration is used first, to avoid contaminating the RKIS during testing. The

-------
Page 24 of 55
Version 2.1
Date: 11/30/00
approximate levels shown in Table 4-1 will be maintained throughout all periods of Hg addition
and reference method sampling. It is expected based on past experience at the RKIS that the flue
gas levels of all constituents in Table 4-2 will be maintained withinlO percent of the target levels
shown.
Table 4-2. Summary of Flue Gas Constituent Concentrations Planned for
Use in Verification Testing
Test Week
Hg (|ig/m3)
S02 (ppm)
NOx (ppm)1
HC1 (ppm)b
Particulate (mg/m3)
One
8
1000
250
25
30
Two
80
50
150
100
30
a Produced by injection of NO.
b Produced by injection of stoichiometrically equivalent levels of Cl2.
In all cases when reference method data are being taken, the introduction of the indicated
constituents will be held constant throughout the entire sampling period. The intent of this
approach is to allow comparisons of CEM data to reference method data under constant
conditions. Higher levels of flue gas constituents will be used in the interference testing, as
described in the next section.
4.4 Test Procedures
The RKIS will be operated continuously during the entire test period, and will not be shut
down overnight. Such continuous operation is intended to minimize the potential for retention
and subsequent release of mercury by the refractory or other components of the RKIS. The Hg
CEMs undergoing verification will be located at ports 5, 6, and 7 of the RKIS (see Figure 2).
Locations indicated as RM1 and RM2 in Figure 2 are reserved for reference method sampling,
which will be performed by contractor staff. The sampling ports will be assigned so that no
CEM is affected by the operation of any other CEM upstream.

-------
Page 25 of 55
Version 2.1
Date: 11/30/00
At the beginning of each test day the CEMs undergoing testing will be supplied (one at a
time) with zero gas and then with a commercial compressed gas standard containing elemental
mercury. The response to each gas will be recorded on each test day to assess the zero and
calibration drift of the CEMs. In this test, the mercury standard will be used solely as a stable,
clean sample matrix, not as an absolute mercury standard. On one test day in the first week of
testing, the rise and fall times of the CEMs will be determined by recording their readings as the
Hg° gas is first turned on, and later turned off. Also on one day in each week of testing, the Hg°
standard gas will be delivered first directly to the CEM's mercury analyzer, and then through the
CEM's sample interface, to assess bias introduced by the interface itself.
During performance of the drift checks, the reference method sampling trains will be
assembled and leak checked, and the RKIS combustion gas CEMs will be calibrated in
accordance with facility standard operating procedures. At this time, the RKIS operation will be
stabilized at the desired incineration conditions firing natural gas. After stable RKIS operation is
achieved (as indicated by readings of 02, temperature, and gaseous emissions (e.g., CO, NOx)),
injection of mercury spike solution to give the day's target flue gas concentration will be initiated.
Mercury solution will be fed to the RKIS for at least 30 min before reference method sample
initiation. The addition of the other flue gas constituents will follow this same procedure. The
mercury CEMs will begin recording data as soon as they are brought on-line. However, the
reference method sampling will start no sooner than a time previously agreed upon with the CEM
vendors. The CEM vendors will be given at least 15 minutes notice prior to initiation of
reference method sampling.
The number of reference method samples collected will depend on the target mercury
concentration. The reference method sampling time will be approximately three hours with the
low Hg levels present in the first week of testing, and approximately one hour with the higher Hg
levels in the second week. This duration of sampling will allow two reference method samples
per day (6 per week) in the first week of testing, and three per day (9 per week) in the second
week. During verification testing, sampling will be conducted simultaneously with four trains of
the OH method, two each at the upstream and the downstream end of the RKIS duct. Thus each
of the two or three measurement periods during a test day will provide four OH results for

-------
Page 26 of 55
Version 2.1
Date: 11/30/00
comparison to the CEM data. To ensure that the reference method and CEM data sets are indeed
parallel and comparable for each period, the CEM vendors will be notified of the start and stop
times of each reference method period, so they can report average analyte concentrations that
correspond directly to the reference method measurement period.
The OH sampling trains will sample isokinetically from a single point in the center of the
RKIS duct (i.e., no traversing because of the small size of the duct). The CEMs undergoing
testing will also sample at a single point in the center of the duct, non-isokinetically. Each CEM
will operate with a simple stainless steel probe, and a heated filter and heated transfer line that
mimic those used with the OH trains. The temperature of the heated filters will be approximately
250°F, sufficient to keep the sample gas above its dew point; no attempt will be made to
maintain the sample gas at its stack temperature. An EPA Method 2 traverse will be done at each
reference sampling location before OH sampling, and again after OH sampling. The pre-run
traverse will be used to set the isokinetic sampling rate. The average of the pre- and post-
sampling traverses will be used for final calculations.
The chemical analysis of recovered sample fractions from OH method trains will be
conducted by contractor staff, using contracted laboratory facilities currently used for mercury
research studies at the RKIS. Sample handling, analysis, and all associated QA/QC activities
will conform to the requirements of the OH method.(4) Samples will be recovered from the OH
trains within about two hours after sample collection, and delivered to the analytical laboratory
within 48 hours of sample collection. Samples will be stored under refrigeration until transfer to
the analytical laboratory. Unique sample identification numbers will be implemented so that
final data used for verification can be traced back through the analytical process to the original
sample. Field blank samples will also be recovered from one blank sampling train on each day
that OH method samples are collected. Before sample recovery, that blank train will be
transported to the upstream or downstream sampling location at the RKIS on alternate days.
Care will be taken that the blank train is selected at random from the prepared trains, so that
different trains are used as the blank on different days.
The daily schedule for the first three test days (Monday to Wednesday in Table 4-1) is
illustrated in Figure 3. That figure shows the schedule for a day in the first week of testing when

-------
Page 27 of 55
Version 2.1
Date: 11/30/00
two 3-hour Ontario Hydro runs are conducted. In the second week, three 1-hour runs will be
conducted each day. The test day begins with a challenge of each CEM using zero gas and a
commercial standard gas of Hg°. Two different standard cylinders will be used, of equal
concentrations. One group of the CEMs undergoing testing will always be tested with Hg°
standard cylinder #1, and the remaining CEMs will be challenged with Hg° standard cylinder #2.
The two groups of CEMs will be chosen so that standard gas consumption by the two groups is
approximately equal. This parallel approach will allow testing with the Hg° standards to proceed
efficiently, while assuring that sufficient Hg° standard gas is available to complete the week of
testing.
Following the completion of the Hg° standard gas test, introduction of Hg, S02,
particulate matter, etc., to the RKIS will begin. As shown in Figure 3, introduction of these
species into the RKIS will begin at least 30 minutes before the start of the first OH run, and will
continue until the last OH run is completed. The flue gas composition will be maintained in this
period at the levels shown in Table 4-2.
The daily schedule of the test day on which interference tests are done (Thursday in Table
4-1) is shown in Figure 4. The same Hg° standard gas challenges will be done in the morning as
described above in the context of Figure 3. Then a stable Hg level will be introduced into the
RKIS, and the response of the CEMs being tested will be allowed to stabilize. Then each of
several potential interferants will also be introduced into the RKIS duct, one at a time for periods
of at least one-half hour. The interferant gases and the levels to be introduced in this test are
listed in Table 4-3. After the last individual interferant (Cl2) has been tested alone, the Cl2
addition will be continued, and the NO addition will be resumed, to assess whether the
combination of NOx and Cl2 produces an interference. Subsequently, the other gases (S02, CO,
HC1) will also be injected, to produce a mixture of all five interferants at the concentrations

-------
Page 28 of 55
Version 2.1
Date: 11/30/00
Hg Standard Test
Cylinder#!
Hg Standard Test
Cylinde r #2
13
Introduction of Hg, PM, S02l etc. to the RKIS
m
h-
Ontario Hydro
Run #1
Ontario Hydro
Run #2
i	i	i	i	i	i	i	i	i	i	i	i
7	8	9	10	11	12	13	14	15	16	17	18	19	20
Time of Day
Figure 3. Schedule of Verification Test Day with Ontario Hydro Sampling

-------
Page 29 of 55
Version 2.1
Date: 11/30/00
Hg Standard Test
Cylinder#!
Hg Standard Test
Cylinder #2
Hg injection into RKIS
NO injection
NO injection
S02 injection
S02 injection
CO injection
CO injection
HCI injection
HCI injection
Cl2 injection
	1—
12
—i—
14
10
11
13
Time of Day
15	16
17
19
Figure 4. Schedule of Interference Test Day

-------
Page 30 of 55
Version 2.1
Date: 11/30/00
Table 4-3. Interferant Gases and Concentrations to Be Used in
Interference Testing
Interferant
Concentration
NOx (NO addition)
500 ppm
S02
2000 ppm
CO
500 ppm
HC1
250 ppm
CL,
10 ppm
shown in Table 4-3. Finally, all the interferants will be shut off, and measurements will be made
again with only the Hg injection taking place. Throughout the test, the Hg injection will be held
constant, and the Hg CEM responses in the presence of interferants will be compared to those
with only Hg injected into the RKIS.
A final test will assess qualitatively the ability of the Hg CEMs to measure Hg levels
below 5 |J.g/m3. This test will be conducted on Friday of the first test week (Table 4-1), by
starting with no Hg injection, then establishing a 1 |_ig/m3 Hg level, and then increasing the Hg
concentration in successive steps of two, i.e., to 2 |J,g/m3, then to 4 |ig/m\ then to 8 |i g/m\ The
Ontario Hydro method does not provide good precision at these low levels, so no absolute
comparison of methods will be made. However, the rate of introduction of Hg to the RKIS can
be easily and accurately changed, and provides a valuable test of Hg detection. This test will be
conducted after an overnight period in which no Hg has been introduced into the RKIS, assuring
that background Hg levels are as low as possible prior to injecting Hg. Figure 5 shows the daily
schedule of activities for this test procedure. The response of each CEM with varying levels of
Hg addition will be compared to that with no Hg addition, and the lowest Hg level producing a
positive response will be reported. The remainder of the test day after completion of the low
level Hg test will be used to repeat or finish other test activities as necessary, as indicated in
Table 4-1.

-------
Page 31 of 55
Version 2.1
Date: 11/30/00
Hg Standard Test
Cylinder #1
Hg Standard Test
Cylinder #2
No Hg Injection	No Hg Injection
'¦f	1 ug/m3 Hg
i
«£
2 ug/m3 Hg
4 ugrtn3 Hg
: ugrtn3 Hg
10	11	12	13	14	15	16	17	18	19
Time of Day
Figure 5. Schedule for Low-Level Hg Detection Test

-------
4.5 Data Comparisons
Page 32 of 55
Version 2.1
Date: 11/30/00
This section describes how the reference and CEM data will be used and compared to
quantify the performance of the CEMs. Table 4-4 summarizes the data that will be used for the
verification comparisons.
Relative accuracy will be verified by comparing the CEM results against the reference
results, for each parameter that the CEM measures. That is, if the CEM measures only total
vapor-phase mercury, then only the TVM results from the Ontario Hydro method will be used for
verification. However, if the CEM also measures oxidized, elemental, or particulate mercury,
then those results from the Ontario Hydro method will also be used for verification. A total of 15
Ontario Hydro sampling runs is planned in the verification test (6 with lower Hg levels, and 9
with higher Hg levels), with four Ontario Hydro sampling trains operating simultaneously in each
period. Thus a total of 60 Ontario Hydro samples will be used to evaluate relative accuracy.
The purpose of sampling with dual Ontario Hydro trains at both reference sampling
locations is to assess the variability of the reference method results that are the basis for the CEM
verification. At the mercury concentrations to be used in this verification, it is expected from
previous results that the precision of duplicate Ontario Hydro results will be within about 10
percent. On the basis of those same results, it is expected that day-to-day reproducibility of Hg
levels in the RKIS, and upstream-to-downstream uniformity of the mercury levels, will also be
within that range. Thus, consistent Hg levels are expected throughout each week of testing. As a
result, the entire set of reference method results, not merely those from a single test day, will be
considered in screening for reference data quality. The Ontario Hydro results will be reviewed
before verification comparisons are made, to identify individual outliers from the full set of
reference method results. That is, the Ontario Hydro results will be screened for three factors:
•	Precision of results from co-located sampling trains
•	Consistency of results with others at the respective sampling location
•	Uniformity of upstream and downstream locations.

-------
Page 33 of 55
Version 2.1
Date: 11/30/00
Table 4-4. Summary of Data to Be Obtained in Mercury CEM Verification Test
Performance
Parameter
Objective
Comparison Based On
Total Number of
Data Points for
Verification
Accuracy
Determine degree of quantitative
agreement with reference method
Reference method results
60a
Correlation
Determine degree of correlation with
reference method
Reference method results
60a
Precision
Determine repeatability of successive
measurements at fixed mercury
levels
Repetitive measurements under
constant facility conditions
15b
Cal/Zero Drift
Determine stability of zero gas and
span gas response over successive
days
Zero Gas and Hg° Standard
9C
Sampling
System Bias
Determine effect of the CEM's
sample interface on response to zero
gas and Hg° standard
Response at analyzer vs.
through sample interface
2d
Interferences
Determine the effect of interferants
on response to a constant Hg
concentration
Observation of CEM response
with and without added
interferants
T
Response Time
Estimate rise and fall times of the
CEMs
CEM results at start/stop of Hg
addition
4f
Low Level Hg
Response
Determine ability of CEMs to
respond to Hg below 8 ng/m3
Continuous monitoring of
varied Hg concentrations
5E
(a)	Number of data points refers to total number of Ontario Hydro method sampling runs used for comparison.
Each run will provide a value for TM, OM, EM, and PM.
(b)	Based on the total number of Ontario Hydro method sampling runs in which repeatability of CEM results
will be assessed.
(c)	Based on total number of zero/span challenges done in the two weeks of testing.
(d)	Based on conducting this test once in each week of testing.
(e)	Based on tests for S02, CL2, NOx, CO, HC1, and mixtures of these species, done in the first week of testing.
(f)	Based on rise and fall time tests with pure gases, in each of the two weeks of testing.
(g)	Based on response to 0, 1, 2, 4, and 8 (xg/m3 Hg levels.

-------
Page 34 of 55
Version 2.1
Date: 11/30/00
Ontario Hydro test results which are identified as outliers on any of these criteria will be
reported, but will not be used for verification. The intent of this approach is to provide a valid
set of reference data for verification purposes, while also illustrating the degree of variability of
the reference method. Identification of outliers will be based on basic statistical tests such as a
t-test comparison of means, or a Q-test evaluation of divergent results. In any case where
rejection of a reference result is suggested, effort will be made to find an assignable cause for the
divergent result.
Correlation of the CEM with the Ontario Hydro method will be verified using the same
data used to assess relative accuracy. Correlation will be calculated for each parameter measured
by the CEM (i.e., TVM, EM, OM, etc.).
Precision of the CEMs will be assessed based on the individual measurements performed
by each CEM over the duration of each Ontario Hydro method sampling run. For example, if a
CEM provides an updated measurement every 5 minutes, then over a one-hour sampling run a
total of 12 readings would be obtained. The average and standard deviation of those
readings will be calculated to assess precision. This procedure will be applied to all 15 of the
Ontario Hydro method sampling intervals.
Calibration and zero drift will be verified based on challenging the CEMs with zero gas
and with a compressed gas standard of Hg° on each test day in each week of the test. Thus at
least nine data points will be used to assess zero drift, and an equal number to assess calibration
drift. Note that only the relative stability of the response will be assessed, i.e., the Hg° standard
will not be used as an absolute calibration standard. The sampling system bias test will be
performed once as part of the calibration/zero drift test procedure, in each week of testing.
Interference effects will be assessed by adding potential interferants one at a time during a
constant addition of mercury to the RKIS flue gas, and comparing the CEM readings with and
without the interferant. This will be done only in the first week of testing (i.e., at the lower
mercury level), for the seven individual interferants or combination of interferants described in
Section 4.4. Thus a total of seven comparisons will be made of interference effects.
CEM response times will be determined by recording successive CEM readings at times
when mercury delivery to the CEM is started or stopped. This procedure will be performed once

-------
Page 35 of 55
Version 2.1
Date: 11/30/00
in each test week as part of the calibration/zero drift test, using the Hg° standard gas. Both rise
and fall time will be determined, resulting in two determinations of rise time and two of fall time.
Low level Hg response will be evaluated once in the first test week, by successively
reducing the Hg level in the RKIS. The lowest Hg level giving a response above the zero air
reading will be reported.
No additional test activities will be required to determine the data completeness achieved
by the CEMs. Data completeness will be assessed by comparing the data recovered from each
CEM to the amount of data that would be recovered upon completion of all portions of these test
procedures.
Setup and maintenance needs will be documented qualitatively, both through observation
and through communication with the vendors during the test. Factors to be noted include the
frequency of scheduled maintenance activities, the downtime of the CEM, and the number of
staff operating or maintaining it during the verification test.

-------
5.0 STATISTICAL CALCULATIONS
Page 36 of 55
Version 2.1
Date: 11/30/00
This statistical calculations to be used to verify CEM performance are described below.
In all cases, measurement results from both the reference method and the CEMs undergoing
testing are to be reported in units of |ig/m ' on a dry basis at 20 °C, 1 atmosphere pressure, and the
actual flue gas 02 content.
5.1 Relative Accuracy
The relative accuracy (RA) of the CEMs with respect to the reference (Ontario Hydro)
method will be assessed by:
~ C, -
RA =	x 100%
v mrw„	^
where d refers to the difference between the Ontario Hydro and CEM results, and x corresponds
to the Ontario Hydro result. Sd denotes the sample standard deviation of the differences, while
t"n.j is the t value for the 100(1 - a)th percentile of the distribution with n-1 degrees of freedom.
The relative accuracy will be determined for an a value of 0.025 (i.e., 97.5 percent confidence
level, one-tailed). The RA calculated in this way can be interpreted as an upper confidence
bound for the relative bias of the analyzer, i.e., , where the superscript bar indicates the
X
average value of the differences or of the reference values. Relative accuracy will be calculated
separately for the first and second week of testing, with up to 24 samples and up to 36 samples,
respectively (assuming all Ontario Hydro method samples can be treated as independent results).
With these numbers of samples, the RA procedure stated in PS-12(6) will be followed, i.e., up to
three results maybe omitted from the RA calculation. The impact of the number of data points
(n) on the RA value will be noted in the verification report. Relative accuracy will be calculated
separately for each parameter measured by each CEM (i.e, TYM, EM, OM, etc.).

-------
5.2 Correlation with Reference Method
Page 37 of 55
Version 2.1
Date: 11/30/00
The degree of correlation of each CEM with the reference method results will be assessed
in terms of the coefficient of determination (r2), which is the square of the correlation coefficient
(r). The coefficient of determination will be calculated for each parameter measured by each
CEM (i.e, TVM, EM, OM, etc.). This calculation will be made separately for the first and
second week of testing, with up to 24 samples and up to 36 samples, respectively (assuming all
Ontario Hydro method samples can be treated as independent results).
5.3 Precision
Precision will be calculated in terms of the percent relative standard deviation (RSD) of a
series of CEM measurements made during stable operation of the RKIS, with Hg injected at a
constant level into the combustion zone. During each Ontario Hydro method sampling run, all
readings from a CEM undergoing testing will be recorded, and the mean and standard deviation
of those readings will be calculated. Precision (P) will then be determined as:
SD
p=^x\m	(2)
X
where SD is the standard deviation of the readings and X is the mean of the readings. The same
calculation will be performed for each parameter measured by the CEM (i.e., TM, EM, OM,
etc.). This calculation will be done for each CEM, using data from every Ontario Hydro method
sampling run (15 in all). The verification report will note that the calculated precision is subject
to the variability of the test facility, not only the CEM variability. However, since precision will
be assessed for all CEMs based on data from the same reference sampling periods, the relative
precision of the tested CEMs will be apparent. Although no comparison among CEMs will be
made, all CEM data from the periods of precision testing will be reviewed, to assess whether the

-------
Page 38 of 55
Version 2.1
Date: 11/30/00
consensus of the CEM data indicates a variation in the test facility itself If such a variation is
indicated, that finding will be noted in all verification reports.
5.4 Calibration and Zero Drift
Calibration and zero drift will be determined in a relative sense, rather than as deviations
from an absolute standard, as in PS-12. That is, calibration and zero drift will be reported in
terms of the mean, relative standard deviation, and range (maximum and minimum) of the
readings obtained from the CEM in the daily sampling of the same Hg° standard gas, and of zero
gas. Up to five Hg° standard readings, and up to five zero readings, will be used for this
calculation, in each of the two weeks of verification testing. The relative standard deviation
(RSD) will be calculated as
SD
RSD = — x 100	(3)
x
where x is the mean, and SD the standard deviation, of the daily readings on standard or zero
gas. This calculation, along with the range of the data, will indicate the day-to-day variation in
zero and standard readings.
5.5 Sampling System Bias
Sampling system bias will be calculated as the difference in CEM response when
sampling Hg° standard gas through the CEM's entire sample interface, compared to that when
sampling the same gas directly at the CEM's pollutant analyzer, expressed as a percentage of the
response at the analyzer. That is,

-------
Page 39 of 55
Version 2.1
Date: 11/30/00
Rd - Ra
B = —		 X 100	(4)
Ra
where B is the percent bias, RSI is the CEM's reading when the standard gas is supplied at the
sampling inlet, and Ra is the reading when the standard is supplied to the analyzer.
5.6 Interferences
Interferences will be determined during sampling of combustion flue gas, in terms of the
difference in response to a constant mercury level when a single interferant is added or removed.
Interferences will be quantified in terms of the relative sensitivity to the interferant species. The
relative sensitivity is calculated as the ratio of the observed change in response of the analyzer to
the concentration of the interferant. For example, a CEM that reports 8 [ig/m ' of total Hg in the
absence of S02, may report 12 |_ig/m3 in the presence of 500 ppm S02. The relative sensitivity of
the CEM is thus 4 |j,g/m3/500 ppm.
5.7 Response Time
The response time will be determined as the time after a step change in mercury
concentration when the CEM reading has reached a level equal to 95 percent of that step change.
Both rise time and fall time will be determined. CEM response times will be determined in
conjunction with a calibration/zero drift check, by starting or stopping delivery of the Hg°
standard gas to the CEM's sampling interface, recording all readings until stable readings are
obtained, and then estimating the 95% response time. For most CEMs, the estimation process
will require interpolating between successive readings, since the measurement process is not
truly continuous.

-------
5.8 Low Level Hg Response
Page 40 of 55
Version 2.1
Date: 11/30/00
The ability of the commercial CEMs to determine low Hg concentrations will be assessed
by comparing responses at successive levels of 0, 1, 2, 4, 8, and 0 |J.g/m3 of added Hg in the
RKIS. The lowest Hg level producing a response above that with no Hg added will be reported.
The data from all CEMs will be reviewed collectively, to indicate whether absence of a response
may be due to the limitations of the Hg injection process, or to limitations of CEM response. For
example, if no CEM shows a response at the 1 |J.g/m3 level, then no conclusion will be drawn
about detection of that level, since inadequate injection rather than lack of detection may be the
cause.

-------
6.0 MATERIALS AND EQUIPMENT
Page 41 of 55
Version 2.1
Date: 11/30/00
6.1 Gases and Chemicals
6.1.2	Interference Gases
Compressed gases (S02, NO, CO, HC1, Cl2) for use in simulating combustion gas
composition and testing interference effects will be obtained from a commercial supplier, and
will be of minimum 99% purity. Each interference gas will consist of a single interferant as a
pure gas.
6.1.3	High Purity Nitrogen/Air
The high purity gases used for zeroing of the CEMs will be commercial ultra-high purity
(UHP, i.e., minimum 99.999% purity) air or nitrogen.
6.1.4	Mercury Standard Gases
Two compressed gas standards containing elemental Hg will be obtained from Spectra
Gases for use in assessing drift of the CEMs. These will consist of Hg° in a nitrogen matrix, at
levels of about 1 ppb (8 i-ig/m3) and 5 ppb (40 |ig/m '), for use in the first and second weeks of
testing, respectively. Multiple cylinders of uniform concentration will be obtained, if required to
meet the gas consumption rates of the CEMs during the test. Each Hg°standard cylinder will be
analyzed both before and after the verification test, by sampling the cylinder contents with EPA
Method 101A and analyzing for mercury. That analysis will be done by the University of North
Dakota, Energy and Environmental Research Laboratory (EERC).
6.1.5	Injection Mercury Solutions
The mercury solutions used to introduce mercury into the primary combustion zone of the
RKIS will be made from commercial ACS reagent grade mercury (II) nitrate monohydrate
(minimum 98% purity), using deionized water. A measured mass of the reagent is dissolved in
deionized water with 25 ml concentrated nitric acid (70 wt. percent, ACS reagent grade), and

-------
Page 42 of 55
Version 2.1
Date: 11/30/00
diluted to 4 L with deionized water. Serial dilutions of this stock solution produce the working
injection solutions. Each such solution is made by diluting an aliquot of the stock solution, along
with 25 ml of the nitric acid, in deionized water, up to a 4 L volume. All solution concentrations
are calculated and reported in terms of Hg. The concentration of the injection solution must be
known to calculate Hg feed rate and to fulfill RKIS permit reporting requirements. In terms of
verification testing, while Hg injection solution concentrations and feed rates aid in establishing
the appropriate flue gas Hg concentrations, the actual flue gas Hg content will be determined by
the OH method sampling, and not by calculation of the injected Hg. Solutions will be made up
only as needed for injection into the RKIS, to minimize waste. All stock and injection solutions
will be prepared under the direction of Jeff Ryan of EPA.
6.1.6 Mercury Spiking Standard
A NIST-traceable aqueous Hg standard, obtained from a commercial supplier, will be
used as the spiking solution in the performance evaluation of Ontario Hydro analysis noted in
Section 7.2.2. If spiking of the particle filter in the Ontario Hydro train is required, as a
performance evaluation in verifying CEM determinations of particulate Hg, then a NIST coal fly
ash standard reference material will be used as the spiking material.
6.2 Reference Method
6.2.1 Sampling Trains
The glassware, filters, and associated equipment for performance of the Ontario Hydro
reference method(4) sampling will be supplied by EPA at the RKIS facility. Multiple trains will
be supplied so that as many as twelve trains (i.e., three sampling runs with four trains each) may
be sampled in a single day, in addition to at least one blank train per day. Preparation, sampling,
sample recovery, and cleaning of used trains will be the responsibility of the contractor in this
verification test.

-------
Page 43 of 55
Version 2.1
Date: 11/30/00
6.2.2 Analysis Equipment
Laboratory equipment for sample recovery and analysis will be provided by the laboratory
contractor. This will include all chemicals and solutions for rinsing train components and
recovering impinger samples, as well as cold vapor atomic absorption (CVAA) or atomic
fluorescence (CVAFS) spectroscopy equipment for mercury determination.
6.3 RKIS Monitoring Equipment
This verification will make use of monitoring equipment already integrated into the RKIS
facility. This equipment includes monitors for major flue gas constituents (02, C02) and for
chemical contaminants (CO, NOx, S02, HC1), as well as sensors for temperature and pressure.
These monitors are identified in Table 3-2. These devices are considered part of the RKIS
facility for purposes of this test, and will be operated during this verification according to normal
RKIS procedures.
6.4 Equipment Used for Performance Evaluation Audits
As described in Section 7.2.2, performance evaluation (PE) audits will be performed for
the 02, C02, temperature, and pressure measurements in the RKIS flue gas. Those PE audits will
be performed by conducting a parallel measurement using an independent monitoring device.
The devices to be used will be provided by Battelle, and include the following:
•	Paramagnetic 02 monitor
•	Infrared C02 monitor
•	Thermocouple temperature indicator
•	Aneroid barometer
•	Magnehelic differential pressure indicator.

-------
Page 44 of 55
Version 2.1
Date: 11/30/00
These devices will have been calibrated by the manufacturer or by Battelle's Instrument
Laboratory within the six months immediately preceding the verification test. In addition, a
calibrated set of weights will be used, to audit the balance used to weigh impingers from the OH
trains, for determining flue gas H20 content.

-------
Page 45 of 55
Version 2.1
Date: 11/30/00
7.0 QUALITY ASSURANCE/QUALITY CONTROL
7.1 Equipment Calibrations
7.1.1	RKIS Monitoring Equipment
The RKIS CEMs and other monitoring devices noted in Section 6.3 will be calibrated by
EPA and RKIS contractor staff according to normal facility procedures. However, a distinction
must be made between those measurements which factor directly into verification results, and
those which are secondary in nature.
Measurements which factor directly into verification results are those that are used in
calculation of results from the Ontario Hydro method. Those include flue gas temperature,
pressure, and 02 and C02 content. For these measurements, compliance level calibration
procedures are required, and will be carried out by EPA and/or RKIS contractor staff. The
pertinent calibration procedures will be conducted on a schedule chosen by these staff, and
suitable to assure adequate data quality during the verification. All calibration results must be
documented for inclusion in the verification data files and verification report. The flue gas H20
content will be determined from impinger weights in the Ontario Hydro trains. Calibration
records for the balance used will be documented.
Measurements which do not factor directly into verification results include monitoring of
the pollutant gases CO, NOx, S02, and HC1. These data will indicate the level of flue gas
constituents during interference testing or flue gas sampling. Calibration of the CEMs for these
species need not meet compliance requirements, though for some species such calibration
requirements may be in place due to the emission limits on the RKIS itself. For these species,
single-point calibrations during the verification test, coupled with existing documentation of
linear response, will be sufficient.
7.1.2	Reference Method
The contractors performing the Ontario Hydro method sampling must perform all
required quality assurance/quality control (QA/QC) activities stated in the method. This includes

-------
Page 46 of 55
Version 2.1
Date: 11/30/00
provision of blank sampling trains (one per sampling day, at either the upstream or downstream
location), and of blank sampling materials (filters, reagent solution blanks) in the field.
Documentation of these activities will be required for inclusion in the verification data file.
Deviation from the Ontario Hydro method(4) will occur only in that traversing of the duct will not
be done. Options for making particulate mass measurements, and for quickly turning glassware
around in sample recovery, will be used. Spiking of Ontario Hydro trains, as recommended in
the method(4) will be performed by Battelle staff, as described in Section 7.2.3.
7.1.3 Analytical Laboratory
The laboratory conducting the analysis of samples from the Ontario Hydro method must
provide documentation of all required calibrations conducted on the mercury analysis equipment.
That documentation may be provided as part of an overall data package that includes the
analytical results.
7.2 Assessment and Audits
7.2.1 Technical Systems Audits
Battelle's Quality Manager, Mr. Charles Lawrie, will perform a technical systems audit
(TSA) once during the performance of this verification test. The purpose of this TSA is to ensure
that the verification test is being performed in accordance with this test/QA plan and that all
QA/QC procedures are being implemented. In this audit, Mr. Lawrie may review the reference
sampling and analysis methods used, compare actual test procedures to those specified in this
plan, and review data acquisition and handling procedures. Mr. Lawrie will prepare a TSA
report, the findings of which must be addressed either by modifications of test procedures or by
documentation in the test records and report.
At EPA's discretion, EPA QA staff may also conduct an independent on-site TSA during
the verification test. The TSA findings will be communicated to testing staff at the time of the
audit, and documented in a TSA report.

-------
Page 47 of 55
Version 2.1
Date: 11/30/00
7.2.2 Performance Evaluation Audit
A performance evaluation (PE) audit will be conducted to assess the quality of the
measurements made in this verification test. This audit addresses only those measurements that
factor into the data used for verification, i.e., the CEMs being verified and the vendors operating
these CEMs are not the subject of the performance evaluation audit. This audit will be
performed once during the verification test, and must be performed by analyzing a standard or
comparing to a reference that is independent of standards used during the testing. For most of
the key measurements, this audit will be done by comparing data from the RKIS equipment to
that from a second analyzer or monitor, operated simultaneously. For example, the PE audit of
02 data will involve sampling with a second 02 analyzer at the same point in the duct, and
comparing results. Similar comparisons will be made for temperature, pressure, and C02. In
addition, the balance used to determine flue gas H20 content by means of the OH impinger
samples will be checked with a calibrated set of weights. Table 7-1 summarizes the PE audits
that will be done. These audits will be the responsibility of Battelle staff, and will be carried out
with the cooperation of EPA and contractor staff.
Table 7-1. Summary of PE Audits on RKIS Measurements
Parameter
Audit Procedure
Expected Tolerance
02
Compare to independent 02 measurement
±1% 02
co2
Compare to independent C02 measurement
±10% of C02 reading
Temperature
Compare to independent temperature measurement
±2% absolute temperature
Barometric
Pressure
Compare to independent pressure measurement
±0.5 inch of H20
Flue Gas
Differential
Pressure
Compare to independent pressure measurement
±0.5 inch of H20
Mass (H20)
Check balance with calibrated weights
±1% or 0.5 g, whichever
is larger

-------
Page 48 of 55
Version 2.1
Date: 11/30/00
These PE audits will be carried once during the period of operation at the RKIS. Battelle
will supply the equipment needed to make the independent PE measurements. If agreement
outside the indicated tolerance is found, the test will be repeated. Further failure to achieve
agreement will result in re-calibration of the independent measurement device, or use of a
different measurement device.
For mercury, this PE requirement is difficult, because of the absence of convenient
absolute gas-phase mercury standards or independent measurement devices. Consequently, this
audit will consist of spiking one or more Ontario Hydro sampling trains with known amounts of
mercury, and conducting sample analysis on the train without sampling of combustion gas. If the
CEMs undergoing verification do not determine particulate Hg, then only the impingers of the
OH train will be spiked. A NIST-traceable Hg standard solution will be used for that purpose.
Agreement of Hg determined in sample analysis with that spiked into the sample train is
expected to be within 10 percent. Because of the time required for sample analysis, the PE audit
results for Hg may not be known until after the verification tests are completed. Response to PE
audit results outside the expected tolerance will be to consider possible causes for the
disagreement, and if appropriate to note the implications of Ontario Hydro PE results on CEM
verification results, in the verification reports. If determination of particulate Hg is performed by
one or more of the CEMs undergoing verification, then a Hg standard will also be used to spike
the particle filter in the OH train. Battelle's Quality Manager will assess PE audit results.
7.2.3	Data Quality Audit
Battelle's Quality Manager will audit at least 10 percent of the verification data acquired
in the verification test. The Quality Manager will trace the data from initial acquisition, through
reduction and statistical comparisons, and to final reporting. All calculations performed on the
data undergoing audit will be checked.
7.2.4	Assessment Reports
Each assessment and audit will be documented in accordance with Section 2.9.7 of the
QMP for the AMS pilot.(1) Assessment reports will include the following:

-------
•	Identification of any adverse findings or potential problems
•	Space for response to adverse findings or potential problems
•	Possible recommendations for resolving problems
•	Citation of any noteworthy practices that may be of use to others
•	Confirmation that solutions have been implemented and are effective.
7.2.5 Corrective Action
The Quality Manager during the course of any assessment or audit will identify to the
technical staff performing experimental activities any immediate corrective action that should be
taken. If serious quality problems exist, the Quality Manager is authorized to stop work.
Once the assessment report has been prepared, the Verification Testing Leader will ensure that a
response is provided for each adverse finding or potential problem, and will implement any
necessary followup corrective action. The Quality Manager will ensure that follow-up corrective
action has been taken.
Page 49 of 55
Version 2.1
Date: 11/30/00

-------
8.0 DATA ANALYSIS AND REPORTING
Page 50 of 55
Version 2.1
Date: 11/30/00
8.1 Data Acquisition
Data acquisition in this verification test includes recording of the response data from the
CEMs undergoing testing, documentation of sampling conditions and analytical results from the
reference method, and recording of operational data such as combustion source conditions, test
temperatures, the times of test activities, etc.
Data acquisition for the commercial CEMs undergoing verification will be performed by
the CEM vendors during the test. Each CEM must have some form of data acquisition device,
such as a digital display whose readings can be recorded manually, a printout of analyzer
response, or an electronic data recorder that stores individual analyzer readings. For all tests the
vendor will be responsible for reporting the response of the CEM to the sample provided. The
CEM data are to be provided to Battelle at the end of each test day, and must include the results
of all tests conducted on that day. The CEM data must include all individual readings of the
CEM (i.e., TVM, EM, etc.). listed by time of day. Averaged results, e.g., TVM data averaged
over the period of an Ontario Hydro sampling run, may also be provided, if available. If not
provided, averaging will be performed by Battelle in data processing. Electronic data files are
the preferred means of data transfer, with Excel® or ASCII file formats preferred.
Other data will be recorded in laboratory record books maintained by Battelle, EPA, and
contractor staff involved in the testing. These records will be reviewed on a daily basis to
identify and resolve any inconsistencies. All written records must be in ink. Any corrections to
notebook entries, or changes in recorded data, must be made with a single line through the
original entry. The correction is then to be entered, initialed and dated by the person making the
correction.
In all cases, strict confidentiality of data from each vendor's CEM, and strict separation of
data from different CEMs, will be maintained. Separate files (including manual records,
printouts, and/or electronic data files) will be kept for each CEM. At no time during verification
testing will Battelle staff engage in any comparison or discussion of different CEMs.

-------
Page 51 of 55
Version 2.1
Date: 11/30/00
Table 8-1 summarizes the types of data to be recorded; how, how often, and by whom the
recording is made; and the disposition or subsequent processing of the data. The general
approach is to record all test information immediately and in a consistent format throughout all
tests. Data recorded by the vendors is to be turned over to Battelle staff immediately upon
completion of each test day. Identical file formats will be used to make quantitative evaluations
of the data from all CEMs tested, to assure uniformity of data treatment. This process of data
recording and compiling will be overseen by the Verification Testing Leader and Quality
Manager.
8.2 Data Review
Records generated in the verification test will receive a one-over-one review within two
weeks after generation, before these records are used to calculate, evaluate, or report verification
results. These records may include laboratory record books; operating data from the combustion
source; data from the CEMs; or reference method analytical results. This review will be
performed by a Battelle technical staff member involved in the verification test, but not the staff
member that originally generated the record. EPA/contractor and/or vendor staff will be
consulted as needed to clarify any issues about the data records. The review will be documented
by the person performing the review by adding his/her initials and date to a hard copy of the
record being reviewed. This hard copy will then be returned to the Battelle staff member who
generated or who will be storing the record.
8.3 Reporting
The statistical data comparisons described in Sections 4.5 and 5.0 will be conducted
separately for each commercial Hg CEM. Separate verification reports will then be prepared,
each addressing the CEM provided by one commercial vendor. The verification report will
present the test data, as well as the results of the statistical evaluation of those data.

-------
Page 52 of 55
Version 2.1
Date: 11/30/00
Table 8-1. Summary of Data Recording Process for the Verification Test
Data to be Recorded
Responsible Party
Where Recorded
How Often Recorded
Disposition of Dataw
Dates, times of test events
Battelle/EPA
Laboratory record books
Start/end of test, and at each
change of a test parameter.
Used to organize/check test
results; manually
incorporated in data
spreadsheets as necessary.
Test parameters (temperature,
analyte/interferant identities and
concentrations, gas flows, etc.)
EPA/Contractor/
Battelle
Laboratory record books
When set or changed, or as
needed to document stability.
Used to organize/check test
results, manually
incorporated in data
spreadsheets as necessary.
Hg CEM readings
- digital display
Vendor
Data sheets provided by
Battelle.
At specified points during
each test.
Manually entered into
spreadsheets
- printout
Vendor
Original to Battelle, copy to
vendor.
At specified points during
each test.
Manually entered into
spreadsheets
- electronic output
Vendor
Data acquisition system (data
logger, PC, laptop, etc.).
Continuously at specified
acquisition rate throughout
each test.
Electronically transferred to
spreadsheets
Reference method sampling data
Contractor/EPA
Laboratory record books
At least at start/end of
reference sample, and at each
change of a test parameter.
Used to organize/check test
results; manually
incorporated in data
spreadsheets as necessary.
Reference method sample analysis,
chain of custody, and results
Contractor/EPA
Laboratory record books, data
sheets, or data acquisition
system, as appropriate.
Throughout sample handling
and analysis process
Transferred to spreadsheets
(a) All activities subsequent to data recording are carried out by Battelle.

-------
Page 53 of 55
Version 2.1
Date: 11/30/00
The verification report will briefly describe the ETV program and the AMS Center, and
will describe the procedures used in verification testing. These sections will be common to each
verification report resulting from this verification test. The results of the verification test will
then be stated quantitatively, without comparison to any other CEM tested, or comment on the
acceptability of the CEM's performance. The preparation of draft verification reports, the review
of reports by vendors and others, the revision of the reports, final approval, and the distribution
of the reports, will be conducted as stated in the Generic Verification Protocol for the Advanced
Monitoring Systems Pilot.(9) Preparation, approval, and use of Verification Statements
summarizing the results of this test will also be subject to the requirements of that same Protocol.

-------
9.0 HEALTH AND SAFETY
Page 54 of 55
Version 2.1
Date: 11/30/00
The verification test described in this test/QA plan will be performed at the RKIS facility
at EPA in Research Triangle Park, North Carolina. All participants in this verification test (i.e.,
Battelle, EPA, contractor, and vendor staff) will adhere to the health and safety requirements of
the facility. Those requirements include completion of a 24-hour HAZWOPR training course
before participation in any activities at the facility. Vendor staff will only be operating their Hg
CEMs during the verification test. They are not responsible for, nor permitted to, operate the
combustion source, or perform any other verification activities identified in this test/QA plan.
Operation of the CEMs themselves does not pose any known chemical, fire, mechanical,
electrical, noise, or other potential hazard.
All visiting staff at the RKIS will be given a site-specific safety briefing prior to the
installation and operation of the CEMs. This briefing will include a description of emergency
operating procedures (i.e., in case of fire, tornado, laboratory accident) and identification and
location and operation of safety equipment (e.g., fire alarms, fire extinguishers, eye washes,
exits). The following safe work practices must be followed by all staff involved in the mercury
CEMs verification at the RKIS facility;
All staff will be required to wear protective glasses, buttoned laboratory coats, and
steel-toed safety shoes while working in the facility
•	Hearing protection is recommended
•	Eating, drinking, and smoking are only permitted in designated areas.
A "three warning" system will be enforced by EPA and contractor staff operating the
RKIS facility to assure compliance with these safety practices:
•	First infraction - violator receives a verbal warning
•	Second infraction - violator receives a written warning
•	Third infraction - violator will be requested to leave the facility.

-------
10.0 REFERENCES
Page 55 of 55
Version 2.1
Date: 11/30/00
1.	Quality Management Plan (QMP) for the ETV Advanced Monitoring Systems Pilot, U.S.
EPA Environmental Technology Verification Program, prepared by Battelle, Columbus,
Ohio, September 1998.
2.	Environmental Technology Verification Program Quality and Management Plan for the Pilot
Period (1995-2000), EPA-600/R-98/064, U.S. Environmental Protection Agency, Cincinnati,
Ohio, May 1998.
3.	Speciated Mercury Emission Test Reports produced in response to EPA's Information
Collection Request (ICR) on Utility Mercury Emissions, at
www.epa.gov/ttn/uatw/combust/utiltox/mercurv.html.
4.	Standard Test Method for Elemental, Oxidized, Particle-Bound, and Total Mercury in Flue
Gas Generated from Coal-Fired Stationary Sources (Ontario Hydro Method), American
Society for Testing and Materials, Draft Method, October 27, 1999.
5.	Personal communication from Jeff Ryan, U.S. EPA/ORD/NRMRL, June 28, 2000.
6.	Evaluation of Flue Gas Mercury Speciation Methods, EPRI Technical Report TR-108988,
Electric Power Research Institute, Palo Alto, California, December 1997.
7.	Proposed Performance Specification 12 for Total Mercury Emission Monitoring Systems,
U.S. Environmental Protection Agency, Washington, D.C., April 19, 1996.
8.	Field Evaluation of MERCEM Mercury Emission Analyzer System at the Oak Ridge TSCA
Incinerator, East Tennessee Technology Park, Oak Ridge, Tennessee, Report BJC/OR-374,
prepared for the U.S. Department of Energy by Bechtel Jacobs Company LLC, March 2000.
9.	Generic Verification Protocol for the Advanced Monitoring Systems Pilot, Battelle,
Columbus, Ohio, November 1998.

-------