REDUCTION OF TOXICS LOADINGS TO
THE NIAGARA RIVER FROM HAZARDOUS
WASTE SITES IN THE UNITED STATES:
2009 Annual Status Report
Prepared by the United States Environmental Protection Agency-Region 2
in conjunction with the New York State Department of Environmental
Conservation-Region 9
FINAL
November 2009

-------
[This Page Intentionally Left Blank]

-------
TABLE OF CONTENTS
Executive Summary
Introduction	1
Status of Remediation Progress	7
O vervi e w	7
Project Highlights	8
Estimated Remediation Costs	12
Future Challenges and Opportunities for the NRTMP	12
Acronym s	19
Glossary	20
References	24
Priority Niagara River Hazardous Waste Site Summaries	Appendix A
1)	Occidental Chemical Corporation, Buffalo Avenue
2)	Niagara County Refuse Disposal
3)	DuPont Necco Park
4)	CECOS International
5)	Occidental Chemical Corporation, Hyde Park
6)	102nd Street
7)	Bell Aerospace Textron
8)	Durez Corporation, Packard Rd. Facility, Niagara Falls (formerly OCC-Durez Div)
9)	Occidental Chemical Corporation, S-Area
10)	Stauffer Chemical
11)	Solvent Chemical
12)	Vanadium Corporation of America (formerly SKW Alloys)
13)	Olin Corporation
14)	DuPont, Buffalo Avenue
15)	Buffalo Color Corporation Site
16)	Buffalo Color Corporation, Area D
17)	Bethlehem Steel Corporation Site
18)	River Road (INS Equipment)
19)	Niagara Mohawk — Cherry Farm
20)	Frontier Chemical, Pendleton
21)	Frontier Chemical, Royal Avenue
22)	Occidental Chemical Corporation, Durez Division, North Tonawanda
23)	Gratwick Riverside Park
24)	Mobil Oil
25)	Iroquois Gas-Westwood Pharmaceutical
26)	Booth Oil
Remediation of Additional Pollutant Source Summaries
Appendix B

-------
[This Page Intentionally Left Blank]

-------
Executive Summary
For over two decades, the Niagara River has been the focus of attention between four environmental
agencies in the United States and Canada (Athe Four PartiesiS). On February 4, 1987, the Four Parties
signed a Declaration of Intent (DOI) to achieve significant reductions of toxic chemical pollutants in the
Niagara River. The DOI outlined the principles and activities to be followed and was combined with a
detailed annual work plan which forms the Niagara River Toxics Management Plan (NRTMP). The Four
Parties agreed upon a specific list of 18 'priority toxics" targeted for reduction through the NRTMP. A
key sub-objective and milestone of the NRTMP DOI was to achieve a 50% reduction of ten specific
priority toxics believed to be from significant Niagara River sources by 1996.
In a 1988 study report, 33 hazardous waste site clusters were identified and prioritized in order of
potential for toxic pollutant loadings to the Niagara River. The 33 cluster sites were placed into three
categories: Category I (sites with loadings greater than 50 lbs/day), Category II (sites with loadings
between 1 and 50 lbs/day), and Category III (sites with loadings less than 1 lb/day). The EPA and
NYSDEC consolidated the list of 33 cluster sites into a priority list of 26 sites consisting mostly of
Category I and II, which were determined to be responsible for -700 lbs/day of the 18 priority toxic
chemical loadings to the Niagara River, and, represented the most significant input of non-point source
loadings (99.9%) from the U.S. side of the basin. The complete remediation of these sites became the
primary focus of the NRTMP to achieve the common goals of the Four Parties agreement. In December
1996, the Four Parties formally re-affirmed, by Letter of Support, their commitment to continue
reductions of priority toxic loadings to the Niagara River. Overall, the NRTMP has met its 50% reduction
goal for the ten targeted priority toxics, and some by more than 75% through actions addressing point and
non-point sources of toxic contamination. Key actions addressing non-point sources include completing
21 of the total 26 priority hazardous waste sites to date. Water quality monitoring data for the period
April 2004 through March 2005 shows annual average concentrations for 6 of the 18 priority toxics
(Arsenic, Lead, total chlordane, pp-DDD, octachlorostyrene (OCS), and benzo(a)anthracene (a PAH) are
now substantially below the most stringent agency water quality criteria at Fort Erie (FE) and Niagara-on-
the-Lake (NOTL).
Today, the commitment to reduce toxic loadings through the NRTMP continues. The Four Parties are in
the process of evaluating past achievements and future opportunities that exist to coordinate with other
related program initiatives occurring within the basin utilizing available expertise and resources. Further
evaluation is needed on the opportunities that exist to continue to reduce toxic contaminant levels from
U.S. sources within the Niagara River. To meet this challenge, the Niagara River Secretariat is currently
evaluating input received over the past year from the general public and involved public and private
stakeholders on the future of the NRTMP. The Secretariat plans to integrate the input received into an
Options White Paper with recommendations to be presented to the Four Parties Coordinating Committee.
Based on feedback and direction on course of action received from the Coordinating Committee, the
Secretariat will revise the NRTMP Scope and Workplan based on consensus reached among the
Coordinating Committee members.

-------
[This Page Intentionally Left Blank]

-------
Introduction
Since 1987, the Niagara River has
been the focus of attention for four
environmental agencies in the U.S.
and Canada, called AThe Four
Parties®1. The Four Parties signed a
Niagara River Declaration of Intent,
pledging cooperation to achieve significant reductions of toxic chemical pollutants in the
Niagara River (DOI 1987). The Declaration of Intent and a work plan form the Niagara River
Toxics Management Plan (NRTMP).
	Tin: Four Parties	
U.S. Environmental Protection Agency (EPA)
Environment Canada (EC)
NY State Diti oi Environmental Conservation (DEC)
Ontario Minis try or Environment (MOE)
IS NRTMP PRIORITY TOXIC
C IIKMIC AI.S
liai/.Ui UinlliKKViK-*
liai/nUi)f>\ iviic*
IJ c 11/.i i (li) 11 u 11 n 1111 k-11 c
liai/.o(k)lluoi;iiiiliaK-:::
( hloakiiK-
( hi \ saic
Dicklnii
I k-vichloiolvn/.aK'*
\lacui\ *
\lnv\ Pliolo\liivv;:
OcUiclilni'iislN raic
P( 13s;:
DDIs
Dio\nr:
Tar;ichloiwlh> laic:
Aisanc
l.akl
Tn\;i|ihaK'
v - Targeted Tor 50° o load reduction by 1996 Ironi point & 11011-
"minl \ i:io:irri N iv.»r vv	nvino 19X7 -w ri 1vw.»Hnr»
Under the NRTMP, the Four Parties identified
18 persistent toxic chemicals as Apriority
toxics! Actions to reduce the inputs of these
priority toxics to the Niagara River have been
aimed at point sources and non-point sources.
Significant point sources on both sides of the
Niagara River have been identified and are
being addressed in U.S. and Canadian point
source plans. The Four Parties summarize
progress in controlling point sources in an
annual report, last issued in October 2007
(The Niagara River Secretariat, 2007). The
next progress report with 20-year trend
analysis is expected to be completed in
2009/10.
Non-point sources of toxic chemicals to the Niagara River (e.g., leachate from hazardous waste
sites, storm water runoff, atmospheric deposition) are more difficult to quantify and control.
Given the limited information available about non-point sources, the U.S. has proceeded with its
actions based on the assumption that hazardous waste sites are the most significant non-point
sources of toxic chemicals to the Niagara River.
In 1988, an EPA study estimated potential toxic pollutant loadings to the Niagara River from all
known hazardous waste sites on the U.S. side of the Niagara River (Gradient Corp/Geotrans Inc
1988). The study compiled a list of 70 sites into 33 "cluster sites" largely based on the manner
in which data has historically been collected. The study further placed them into three categories
based on their potential loadings (in lbs/day) to the Niagara River. Figure 1 shows the locations
of these 33 site clusters, as well as several other additional hazardous waste sites.
1

-------
67
•in- ssi:;i - ...il-
Ro't'sl Am—
5-*.» i * -41 a
iV.wgara
24
207
r-#
flPPHOXlM'iT L yCA_L
107
241
NOTE: First runner grly $ given 1o> gto areas
¦Ailh ni pic ara nurrbirs.
110
Figure 1. Location of significant Niagara River Waste Sites Addressed by the NRTMP
2

-------
SITE
8ERS
41b-49
81
14
78a,b
39
,85,94'
5
66
41a
255
251
1
59,248
19,250
254
20-122
118
136
67
24-37
253
68
141
162
242
22
182
241
108
107
207
25-127
)cciden
Figure 1: LEGEND
SITE NAME
Occidental Chemical Corp. (OCC), Buffalo Ave. Avenue
Niagara County Refuse Disposal
DuPont Necco Park
CECOS International/Niagara Recycling
OCC, Hyde Park
102nd Street
Bell Aerospace Textron
Durez Corporation, Packard Road Facility (formally OCC, Durez Division)
OCC, S-Area
Stauffer Plant (PASNY)
Solvent Chemical
Vanadium Corp. (formerly SKW Alloys)
Olin, Buffalo Avenue
DuPont, Buffalo Avenue Plant
Buffalo Harbor Containment
Buffalo Color Corporation, including Area D
Bethlehem Steel Corporation
River Road (INS Equipment)
Frontier Chemical, Pendleton
OCC, Durez, North Tonawanda
Small Boat Harbor Containment
Gratwick Riverside Park
Mobil Oil
Alltift Realty
Charles Gibson
Great Lakes Carbon
Niagara Mohawk Cherry Farm
Times Beach Containment
Tonawanda Coke
Allied Chemical
Tonawanda Landfill
Dunlop Tire and Rubber
il 102nd Street site (#40), Olin 102nd Street site (#56), Griffon Park (#85), and Niagara
den site (#94)
3

-------
123
38
9-15-141
Columbus-McKinnon
Love Canal
Iroquois Gas/Westwood Pharmaceutical
The study showed that a total estimated 694 lbs/day (315 kg/day) of toxic chemicals have the
potential of migrating from these 33 cluster sites to the Niagara River. Because collection of
site-specific transport data is ongoing, estimates were made based on certain assumptions, e.g.,
that groundwater flow is horizontal, and that pollutants behave in a conservative manner. These
assumptions yielded conservative estimates (i.e., estimates of toxic loadings that are expected to
be higher than the actual loadings).
Table 1 presents the 33 cluster sites divided into the three categories, based on
Gradient/Geotrans 1988 estimates of their potential toxic loads to the Niagara River. The
categories are as follows:
Category I: Sites with loading greater than 50 lb/day
Category II: Sites with loadings from 1 to 50 lb/day
Category III: Sites with loadings less than 1 lb/day
Sites from Category I and II collectively represented 99.9% of the total estimated loadings.
In November 1989, EPA and NYSDEC issued a report which prioritized the 33 cluster sites into
a list of 26 hazardous waste sites, consisting mostly of Category I and II, which were determined
to be responsible for the -700 lbs/day of the 18 priority toxic chemical loadings to the Niagara
River (EPA/NYSDEC 1989). Since 1989, EPA and NYSDEC have reevaluated the universe of
hazardous waste sites to identify those that new information shows are significant sources of
toxic chemicals to the Niagara River. Two sites have been removed as insignificant sources of
toxics, and four sites have been added as significant sources. This update reports on remediation
progress at the resulting 26 priority hazardous waste sites.
EPA estimates actual input loading reductions from completed hazardous waste site remedial
actions ("RAs") have been from -700 lbs/day to less than 50 lbs/day; representing an
approximate 94% reduction from the 1988 baselines for PCBs, DDT, mirex, octachlorostyrene,
chlordane, hexachlorobenzene, benz (a) anthracene, lead and others to the Niagara River. This
estimate is based primarily on assuming 100% reduction at sites where the final RA is
completed. It does not include the load reductions at other sites where interim remedial controls
are in place, e.g., groundwater pump-and-treat systems are functioning at 3 of the 4 sites where
remediation is underway and are expected to have already reduced off-site loadings. Since
estimates could not be made for these sites with on-going remediation, actual reductions to date
may be greater than the estimated 94%. Table 2 identifies the sites where final RAs are
complete and the sites where remediation is not yet completed, but which have interim
operational remedial systems that are expected to have reduced contaminant loads to the Niagara
River.
4

-------
Final RAs currently underway are expected to be completed at one additional site by the end of
2010 and another site by the end of 2011. Upon completion of these 2 additional RAs, EPA:s
best estimates are that the estimated toxic chemical inputs from all sites collectively should be
reduced by almost 98% from the 1989 inputs (EPA/NYSDEC 1989).
Other estimates have been made of the potential loadings of the NRTMP priority chemical
concentrations in groundwater and groundwater flow to the Niagara River from priority waste
sites. These estimates are based on information that was not available when the
Gradient/Geotrans estimates were developed. For example, a report by several site PRPs
addressing groundwater loadings for ten of the NRTMP priority waste sites estimated priority
chemical loadings from ten sites at 5.6 lbs/day (2.5 kg/day) prior to RA, and 0.0048 lbs/day
(0.002 kg/day) after RA completion, a reduction of over 99% (CRA 1998). Since these
estimates only consider the NRTMP priority chemicals, they are not comparable to the
Gradient/Geotrans estimates of total toxic chemical loading. In addition, the report also used
some assumptions (i.e. non-conservative assumptions) that would tend to reduce load estimates.
Therefore, although actual loadings are likely greater than the estimates, the estimates do
corroborate the reduction in toxic chemical loadings to the Niagara River achieved through
remedial programs.
In addition to remediation efforts at the waste sites themselves, it is also important to recognize
the role of the Niagara Falls Waste Water Treatment Plant (WWTP) in reducing toxic inputs
from a number of waste sites to the Niagara River. Based on information available in 1987, the
U.S. identified the Falls Street Tunnel, a major unlined industrial sewer cut into the bedrock
under the City of Niagara Falls, as the largest source of toxic pollutants from any of its point
sources. By the mid-1980s, the Tunnel was only receiving overflows of wastewater from the
sewers of a Niagara Falls industrial area, in addition to contaminated groundwater infiltrating
from major waste sites via cracks in the Tunnels bedrock walls. In contrast to flows from other
point sources, effluent from the Falls Street Tunnel entered the Niagara River untreated. In
1993, EPA and NYSDEC required the City of Niagara Falls to treat the Falls Street Tunnel
discharges during dry weather at the Niagara Falls WWTP. Data gathered by the U.S. indicate
that WWTP treatment of the Tunnels dry weather discharge has reduced mercury loadings by
70%) relative to 1980 loads, tetrachloroethylene loadings by 85%, and the loadings of four other
priority toxic chemicals by almost 100%.
Since the Falls Street Tunnel captures portions of the upper Lockport bedrock groundwater flow
from seven hazardous waste sites, the actions taken to control discharge from the Tunnel reduce
loadings from the following sites:
DuPont, Buffalo Avenue	Solvent Chemical
OCC, Buffalo Avenue	CECOS International
Frontier Chemical, Royal Avenue	DuPont Necco Park
Durez Division, Packard Road Facility (formally OCC)
For this report, estimates of site loading reductions do not include those obtained through
treatment of the Falls Street Tunnel dry weather flow.
5

-------
TABLE 1
Gradient/Geotrans Prioritization of Waste Sites According to
Potential Toxic Loadings to Niagara River in 1988
Category I: greater than 50 lb/day
Occidental Chemical Corporation (OCC), Buffalo Ave.
Niagara County Refuse Disposal
DuPont Necco Park combined with CECOS International
Occidental Chemical Corporation, Hyde Park
Category II: between 1-50 lb/day
Occidental Chemical Corporation, 102nd Street
Bell Aerospace Textron
Durez Corporation, Packard Road Facility (formerly OCC, Durez Division, Niagara Falls)
Occidental Chemical Corporation, S-Area
Stauffer Plant (PASNY)
Solvent Chemical
Vanadium Corp. (formerly SKW Alloys)
Olin, Buffalo Avenue Plant
DuPont, Buffalo Avenue Plant
Buffalo Harbor Containment
Buffalo Color Corporation, including Area D
Bethlehem Steel Corporation
River Road (INS Equipment)
Frontier Chemical, Pendleton
Occidental Chemical Corporation, Durez, North Tonawanda
Small Boat Harbor Containment
Gratwick Riverside Park
Mobil Oil
Category III: less than 1 lb/day
Alltift Realty
Charles Gibson
Great Lakes Carbon
Niagara Mohawk, Cherry Farm
Times Beach Containment
Tonawanda Coke
Allied Chemical
Dunlop Tire and Rubber
Columbus-McKinnon
Love Canal
Tonawanda Landfill
6

-------
Status of Remediation Progress
Overview
As of the release of this 2009 NRTMP report, final RAs have been completed at 21 of the 26 sites
which includes all ACategory 1" sites (those with estimated contaminant loads of >50 lbs/day of
priority toxic chemicals to the river). It is expected that the post-remedial Operation, Maintenance
and Monitoring (OM&M) technology installed at certain sites could be operated, maintained and
monitored for continued effectiveness for up to 30 years or longer at other sites.
The remaining five sites (Mobil Oil, Frontier Chemical - Royal Ave., Vanadium Corporation,
Bethlehem Steel Corporation, and Buffalo Color Corporation Plant Site) have RAs pending or
underway. Three of the five sites (Mobil Oil, Vanadium Corporation, and Bethlehem Steel
Corporation) are operating interim remedial systems while progressing with completion of their final
RAs. Estimated RA completion date for Vanadium Corporation is December 2010 and for Mobil Oil,
December 2011. NYSDEC is currently negotiating a Corrective Measures Study (CMS) Consent
Order with Tecumseh Redevelopment (current owner of the Bethlehem Steel Corporation site) to
complete the remaining projects needed at the site with construction schedules. The other two sites
(Frontier Chemical - Royal Ave. and Buffalo Color Corporation Plant Site) have completed their
respective Remedial Investigation/Feasibility Studies (RI/FS) for their sites. The remedial
investigation of the Frontier Chemical - Royal Ave. site, operable unit (OU) No. 2 (deep bedrock
groundwater), is on-going and is expected to be completed in 2010. In 2009, the Buffalo Color
Corporation Plant Site was accepted into the NYS Brownfield Clean-up Program. A Remedial Work
Plan was approved in May 2009 and design activities will continue into 2010 as plant structures are
being demolished.
TABLE 2
Summary Status of the 26 Priority Waste Sites
Investigation and Design Status:
Potentially Responsible Party (PRP) Search
No sites in this phase.
Site Investigation Underway
Frontier Chemical, Royal Avenue2
BETHLEHEM STEEL SITE3
Remedial Design (RD) Underway
VANADIUM CORP. OU#31
Remedial Action Status:
Interim Remedy in Place or Under Construction:
MOBIL OIL OU#l and OU#2
VANADIUM CORP.1: OU#2 & OU#3
Frontier Chemical, Royal Avenue2
7

-------
BETHLEHEM STEEL SITE3
Buffalo Color Corporation Site
Remediation Completed (OM&M Ongoing)
Stauffer Chemical
Frontier Chemical, Pendleton
Bell Aerospace Textron
CECOS International
Dupont Necco Park
Durez Corporation, Packard Road Facility
OCC, Durez, North Tonawanda
DuPont Plant Site Buffalo Avenue
Olin Plant Site
Buffalo Color, Area D
OCC, Buffalo Avenue
102nd Street (Olin /OCC)
River Road
Niagara Mohawk, Cherry Farm
Niagara County Refuse Disposal
Iroquois Gas-Westwood Pharmacy
Gratwick Riverside Park
OCC S-Area
Solvent Chemical
Booth Oil
OCC-Hyde Park	
The sites in interim remediation are also under investigation or design, and therefore are listed twice.
	Bolded sites have updated project highlights reported below in more detail.
 These sites, though not completed, have operational remedial systems that are expected to
have reduced contaminant loadings to the Niagara River.
1	Preliminary investigations were completed. Two Interim Remedial Measure (IRMs) have been completed by PRPs for
OU#l and OU#2. A "No Further Action" Record of Decision was issued for OUs #1 and #2 in March 2006.
2	The RI/FS for soils and the upper bedrock (OU1) were completed in 2004 with a ROD issued in March 2006. An RI/FS
is still required for the deeper bedrock groundwater (OU2).
3	In 2004 DEC approved an interim corrective measures plan for the remediation of the Benzol Plant Area (i.e., the Coke
Oven Area). Recovery-well installation was completed in December 2004. The system includes LNAPL recover and
groundwater collection and treatment. The system began operating in April 2005.
Project Highlights
For each individual waste site, status summary tables are provided in Appendix A. Also, detailed site
information for all 26 sites can be found in NYSDEC's Environmental Site Remediation Database
website located at... http://www.dec.nv.gov/cfmx/extapps/derexternal/index.cfm?pageid=3. Updated
highlights of completed hazardous waste sites with continuing work and progress made at the five
remaining sites with RAs underway, particularly since the October 2008 NRTMP progress report, are
summarized below.
8

-------
Occidental Chemical - Durez
•	Initial remediation of the site was completed in 1995. Based on post remedial monitoring
additional contaminated sediment from the bottom of the Pettit Creek cove area was removed
in May 2000. The most recent report from caged mussel bio-monitoring (-2006), indicates
elevated concentrations of dioxins and furans remain in sediment. A work plan for source
investigation and additional sediment removal, as needed, has been submitted by the
Company and approved by NYSDEC. The purpose of the work is to determine the source of
the recontamination and evaluate remedial alternatives. This work began in mid 2008 and a
progress report was submitted in 2009. NYSDEC has requested additional follow-up work
based on the results of the progress report.
Dupont Plant Site. Buffalo Avenue
•	The lower reach of Gill Creek (OU#2), which was heavily contaminated with DuPont and
Olin plant site chemicals, was partially remediated in 1982. The remaining creek remediation
was completed in 1992 under a Consent Order. Pilot testing was conducted in 2002 and
construction of the full scale SW Plant Ground Water Recovery System (GWRS) remedy
began in 2004. The GWRS construction was completed in September 2005 and is in
operation. In 2007, DuPont performed a GWRS overhaul and replacement.
•	Blast fractured bedrock trenches that were installed in the SW plant area to optimize
groundwater collection in that area have greatly increased hydraulic containment and pump
rates. The GWRS upgrades replaced the original steam stripper and added a therm-ox unit to
treat off-gasses to handle additional flow from trenches creating greater treatment reliability
and reducing system down time. Over 133,000 pounds of organic contaminants have been
removed from groundwater since startup through 2009 by the GWRS and Olin pumping
systems.
Vanadium Corporation
$ A Record of Decision compiling the results of operable units OU#l, OU#2, and OU#3 was
issued in March 2006.
$ Remedial actions were completed at OU#l and OU#2 in 2007.
$ The Remedial Design for the last remaining operable unit, OU #3, to address remaining
surficial waste and slag was completed in 2007. The remedial action for OU#3 should begin
in the Spring of 2010. Estimated Completion Date: December 2010
Buffalo Color Corporation Site
$ In March 2005 Honeywell (a potentially responsible party) entered into an Order on Consent
to address groundwater contamination at the site by designing and installing a groundwater
collection system. Design was completed in 2005. The construction was completed in 2007.
9

-------
$ Honeywell performed a bulk chemical removal at the Site starting in December 2005 and it is
presently complete. The site though is not considered RCRA clean. The site has been
transferred from NYSDEC's RCRA unit to the Division of Environmental Remediation.
$ Honeywell has completed their RI/FS for Areas A,B,C and E. as part of the June 30, 2006
Consent Order. The fieldwork began in January 2007 with a draft report Remedial
Investigation Report submitted in September 2007. The RI/FS was completed in 2008. As a
result of the RI/FS, a Brownfield Cleanup Plan application was submitted and was approved
by the NYSDEC in April 2009. The Remedial Work Plan was approved in May 2009.
Demolition of the plant buildings began in late 2009 and will continue through early 2010.
Design activities will continue into 2010. Remedial Action work is expected to be
performed in 2010/11.
Bethlehem Steel Corporation (BSC) Site
$ BSC has completed the field work for the site investigation, and has prepared Resource
Conservation and Recovery Act Facility Investigation (RFI) and human health risk
assessment reports. These had been delayed due to negotiations over the scope and the need
to collect additional data, but were finally submitted in December 2004.BSC completed
limited remedial technology studies for two areas that appear to be the primary sources of
groundwater contamination at the facility (the Acid Tar Pits and Coke Oven Areas). The EPA
and NYSDEC found the studies to be technically flawed and of limited value. BSC continues
to study various potential remedial technologies.
$ In 2004 DEC approved an interim corrective measures plan for the remediation of the Benzol
Plant Area (i.e., the Coke Oven Area). In November 2004, NYSDEC issued a consent order
to administer this project. Recovery-well installation was completed in December 2004. The
system, which began operating in April 2005, includes LNAPL recover and groundwater
collection and treatment.
$ In 2005, Tecumseh Redevelopment Inc., a subsidiary of ISG and Mittal Steel, submitted
brownfield applications to NYSDEC for two more parcels containing about 300 acres. Since
any future CMS or CMI activities will require a new order, permit or other agreement,
NYSDEC is currently negotiating a corrective action order with ISG for this work. Numerous
areas of the site that are not regulated under the RCRA program have been proposed for
clean-up under NYS Brownfield program.
In one of these areas, eight windmills were constructed at the site under the Brownfield
Cleanup Program in 2007. A Corrective Measures Study (CMS) Order with Tecumseh
Redevelopment (current owner) was signed in June 2009. The results of this study should
be complete by the end of 2010.
10

-------
Frontier Chemical. Royal Avenue
$ In January 2001 the site was referred for RI/FS action under the NY State Superfund program.
The Focused Remedial Investigation was begun in 2001. The RI/FS for the soils and upper
bedrock (OU#l) was completed in early 2004. A Record of Decision (ROD) for site soils and
upper bedrock groundwater (Operable Unit (OU) #1) was issued in March 2006. It requires
the excavation and off-site treatment/disposal of contaminated soil source areas with
control/treatment of overburden and upper bedrock groundwater. A Consent Order for the
investigation and evaluation of the deeper bedrock groundwater (OU#2) and further
investigation of subsurface soils to delineate on-site contamination was signed on August 15,
2008. The RI/FS for OU#2 and pre-design sampling activities are underway. Subsequent
design, construction and operation of the remedy will either be done by the PRPs under an
Order, or by the NYSDEC using the State Superfund program. Estimated Start of RA:
Late 2010/2011.
Mobil Oil
$ Exxon/Mobil has entered the Brownfield Cleanup Program to complete subsequent
remediation activities under a BCP Agreement with NYSDEC dated April 3, 2006. In spring
2006 a Conceptual Site Plan (CSP) was approved by the State. The Site has been divided into
nine geographic areas for the purpose of assessing environmental conditions and reporting the
results of area-specific activities according to the nature of their historical primary
operations. Now that sitewide remedial investigation is complete, the site was divided into
five OUs based upon the anticipated phasing of subsequent remedial actions considering
environmental media to be addressed, potential remedial approach and geographic areas. The
remaining OUs are:
OU#2: Soil, groundwater and any free product located to the north of Prenatt St. and south of
Elk St.
OU#3: Main Free Product Plume and contaminated soil and groundwater south of Prenatt
Street.
OU#4: Soil and groundwater within the Eastern Tank Yard Area (ETYA).
OU#5: Buffalo River sediment impacted by Exxon/Mobil historical operations
In Spring 2006 the State executed a Brownfield Cleanup Agreement and approved a
Conceptual Site Plan addressing the various operable units of the plant site. OU#l, which
addressed the soil impacts in the Elk Street Properties Area determined to be attributable to
the former Tank 60 release from 1976, was completed in 2007.
Estimated Completion Date: December 2011
11

-------
Estimated Remediation Costs
Estimates of the cost of remediation are available for most of the 26 priority hazardous waste sites.
Where available, individual project costs for each site are provided for quick reference in summary
tables located in Appendix A of this report. As indicated below, the total costs incurred to date are
estimated to be at least $442,869,000. Total future additional remedial and O&M costs are estimated
to reach at least $262,150,000.
Based on available estimates for 21 sites, following is the total amount incurred to date (costs for the
remaining 5 sites are unavailable):
Federal	$ 39.832 million
State	$ 7.425 million
PRPs	$ 395.772 million
Total	$ 443.029 million
Based on available estimates for 12 sites, the total additional remedial and O&M costs expected in
the future are as follows (costs for the remaining 14 sites are unavailable):
Federal	$ 1.875 million
State	$ 0.710 million
PRPs	$ 259.564 million
Total	$ 262.149 million
The estimated costs to date cannot be compared to the estimated costs expected in the future, because
different sites are included in the estimates. It is also difficult to compare the relative contributions of
federal, state, and PRP expenditures, because cost information for some sites was incomplete (e.g.,
some sites may have been able to provide federal or state costs but not PRP costs, and so on).
However, the cost information does provide a sense of the magnitude of U.S. expenditures for
hazardous waste site remediation in the Niagara River basin.
Future Challenges and Opportunities for the NRTMP
A number of related initiatives are underway that present opportunities for possible merging or
coordination with other activities and resources. These current initiatives include coordination of the
NRTMP with the Niagara and Buffalo River AoC RAP process; future monitoring, data collection
and analysis; and remediation of additional pollutant sources.
Area of Concern (AoC) RAP and Delistings - The AoC delisting initiative is a top priority for the
Four Parties over the next several years. The Beneficial Use Impairments (BUIs) listed by both the
binational Niagara River AoC and Buffalo River AoC are believed to be based on impacts of toxics
chemicals which have been closely linked to the hazardous waste site inputs to the rivers. Formal
coordination of the NRTMP and AoC RAP mechanism would achieve greater resource efficiency and
public understandings.
12

-------
Niagara River Area of Concern Remedial Action Plan: The Niagara River Area of Concern (AoC),
located in Erie and Niagara counties, extends from Smokes Creek near the southern end of the
Buffalo Harbor and north to the mouth of the Niagara River at Lake Ontario. In 1994, the NYSDEC,
through an appointed Remedial Advisory Committee (RAC), completed and published a Remedial
Action Plan (RAP). To date, the RAC has identified 5 BUIs to be addressed and 2 BUIs needing
further assessment (see Table 3). Past municipal and industrial discharges and hazardous waste
disposal sites have been a source of contaminants to the Niagara River which have been linked to
several BUIs in the AoC. Of the 26 priority waste sites discussed in this report, 21 sites are located
directly in the Niagara River watershed basin. Of these 21 sites, nineteen sites have completed
remedial construction and two sites (Frontier Chemical Royal Ave. and Vanadium Corporation) have
remedial actions currently underway. It is understood by the Four Parties that the NRTMP initiative
contributes greatly towards the restoration of wildlife and aquatic habitats, re-designation of
beneficial uses from impaired to un-impaired, and the ultimate de-listing of the Niagara River AoC.
Therefore, it is noted by the joint agencies as an example of bi-national cooperation on the Niagara
River and as an important contribution to the RAP process in the AoC. It is expected that RAP
implementation will progress at an aggressive pace over the next several years while the NRTMP
works towards removing all remaining toxic pollutant inputs to the river.
Buffalo River Area of Concern Remedial Action Plan: The Buffalo River AoC is located in the
City of Buffalo in Western New York State. The river flows from the east and discharges into Lake
Erie near the head waters of the Niagara River. In 1989, a RAP was prepared by the NYSDEC for
the Buffalo River AoC. The NYSDEC acted as RAP coordinator from 1989 - 2005 until the U.S.
EPA Great lakes National Program Office selected the Buffalo Niagara Riverkeeper (BNR) as RAP
implementation lead coordinators. To date, the BNR has identified 6 BUIs to be addressed and 3
BUIs needing further assessment (see Table 4). Of the 26 priority waste sites discussed in this report,
one site (Bethlehem Steel Corporation Site) has direct local impacts to Buffalo Harbor to the north
and on the western boundary of Lake Erie and four sites (Buffalo Color Corporation Site, Buffalo
Color - Area D, Mobil Oil, and Iroquois Gas-Westwood Pharmaceutical) have direct local impacts to
the Buffalo River. These five sites are part of the NRTMP 26 priority sites since they in turn have
impacts to the head waters of the Niagara River (see Figure 1). Two of the sites (Buffalo Color-Area
D and Iroquois Gas-Westwood Pharmaceuticals) have completed remedial construction and the other
three sites (Mobil Oil, Buffalo Color Corporation Site, and Bethlehem Steel) have remedial actions
currently underway. Bethlehem Steel and Mobil Oil operate interim remedial systems while final
remedial actions are completed. These NRTMP waste sites are listed as part of the Buffalo River
RAP to be addressed towards restoring beneficial uses. Restoration and re-designation of the BUIs in
Lake Erie, Buffalo and Niagara Rivers will ultimately result in delisting of the Buffalo River AoC as
well as the Niagara River AoC.
13

-------
TABLE 3
TABLE 4
Niagara River AoC Beneficial Use Impairments
Of the 14 beneficial uses, five are impaired for the
Niagara River:
1.	Restrictions on fish and wildlife
consumption
2.	Fish tumors or other deformities
3.	Degradation of Benthos
4.	Restriction on dredging activities
5.	Loss of fish and wildlife habitat
In addition, the designation of two beneficial uses need
further assessment to determine their status:
1.	Degradation of fish and wildlife
populations
2.	Bird or animal deformities or
reproductive problems
Buffalo River AoC Beneficial Use Impairments
Of the 14 beneficial uses, six are impaired for the
Buffalo River:
1.	Restrictions on fish and wildlife
consumption
2.	Fish tumors or other deformities
3.	Degradation of aesthetics
4.	Degradation of Benthos
5.	Restriction on dredging activities
6.	Loss of fish and wildlife habitat
In addition, the designation of three beneficial uses
need further assessment to determine their status:
1.	Tainting of fish and wildlife flavor
2.	Degradation of fish and wildlife
populations
3.	Bird or animal deformities or
reproductive problems
Future Monitoring, Data Collection and Analysis - In addition to the effectiveness of pollutant
removal at the waste sites themselves, it is important to note that there are three components to the
NRTMP monitoring plan: Environment Canada (EC) Upstream/Downstream (U/D Program); Bio-
monitoring (mussels, young-of-year fish, wildlife); and source track down & analysis screening.
Anticipated in 2009/10, the Niagara River Secretariat will prepare a trend analysis report covering the
past 20 years of data collected in-water and compare concentration inputs at Fort Erie and Niagara-
on-the-Lake. The U/D Program is expected to continue to be a valuable tool for assessing overall
progress and future priorities as explained below in more detail.
NRTMP Monitoring Program Plan: The NRTMP's primary mechanism for measuring
improvements in water quality is the Environment Canada (EC) U/D Program. The U/D Program
measures approximately 50 organic chemicals and includes the 18 NRTMP Priority Toxics in the
dissolved and particulate phases at the head (Fort Erie) and the mouth (Niagara-on-the-Lake) of the
Niagara River where it enters Lake Ontario (Figure 2). Water quality data is collected year-round
and EC publishes a formal U/D Program report on every ~2 years of data. The most recent U/D
Program report was published in 2007 and includes data from 2004/2005. Since 1987, high quality
US and Canadian government monitoring program information provide clear evidence of reductions
for most of the 18 Niagara River Priority Toxics in water, sediment and biological indicators in the
range of 50% or greater by the 1996 target year. The Niagara River Secretariat 20-year data trend
report, expected in 2009/10, should be a useful tool for setting priorities such as future track down
and analysis studies to identify potential new sources of contaminants, new emerging chemicals, and
NRTMP management strategies for reducing these chemicals.
14

-------
Lake Ontario
MAGARA-
ON-THE
-LAKE
Lewision
LikcDntirio
~
Like Eric
N
k
Grand
Island
Tonawanda
«•
FORT ERIE
Buffalo
Lake Erie
Figure 2. Environment Canada's Niagara River Upstream/Downstream Surface Water Sampling Locations
Remediation of Additional Pollutant Sources - The 1989 EPA/NYSDEC Hazardous Waste Site
Report identified the NRTMP's original 26 waste sites as highest priorities due to their potential to
contribute over 90% of the total toxic chemical loadings to the Niagara River. These 26 sites and the
estimated loadings were based on earlier studies and often on preliminary data. Although these 26
sites were of top priority for the NRTMP, numerous investigations and remediations at other site
areas, some consisting of multiple individual sites, were being addressed under New York State's
remedial programs. The additional efforts by NYSDEC and EPA have included six additional sites
described below now known to be significant contributors of toxic contamination to the river but for
which insufficient data existed in 1989 to include them in the NRTMP. The NRTMP is considering
the need for a revised assessment of the toxic contamination contributions from all known hazardous
waste sites to the river using current methods and techniques. For a quick reference, see the summary
tables for these projects located in Appendix B of this report. Also, detailed site information for all
sites can be found in NYSDEC's Environmental Site Remediation Database website located at
http://www.dec.ny.gov/cfmx/extapps/derexternal/index.cfm?pageid=3 .
15

-------
Fourth Street Site - NYSDEC #915167
The site is located on Fourth and Village Court streets in the City of Buffalo and is located in a mixed
residential, commercial, and recreational setting approximately 1500 feet from the Lake Erie
shoreline. The Citizens Gas Works operated on this property staring from the early 1900's.
From 1934 to 1958, a portion of the property was also used by Greyhound Bus Company to service
its vehicles. During a site evaluation in 1992 black tar material was found in one area of the property.
Soil/tar and groundwater samples were tested during the investigation and results showed contained
up to 3300 ppm of benzene, 3000 ppm of toluene, 2700 ppm of xylenes, 3000 ppm of phenolic
compounds, and 53,000 ppm of PAHs. Site groundwater also exceeded groundwater standards for
benzene, toluene, xylenes, PAHs, and phenolic compounds. In August 1996, NYSDEC/NYSDOH did
additional testing which detected surface soil samples containing up to 420 ppm of PAHs.
The tar material was found to be a hazardous waste as it failed TCLP for benzene. The City of Buffalo
conducted an investigation and submitted the RI/F S report in January 2001. A Record of Decision (ROD)
was issued in 2001 requiring the removal of all contaminated tar materials from the site. The
construction of the remedy began in July 2005 and was completed in early 2006. The site has entered the
long term site management phase. Implementation of the environmental easement and reclassification of
the site is expected in 2010.
Former Buffalo Service Center - NYSDEC #C915194
This site is the location of a former Manufactured Gas Plant (MGP) which was operated by various
companies from 1848 to 1948. The site was initially investigated by the owner - National Fuel Gas
during the period 1989 to 2004. The investigation confirmed the presence of MGP wastes (containing
benzene, toluene, ethylbenzene, xylenes, polycyclic aromatic hydrocarbons, total cyanides) in soil
and groundwater at the site. In June 2005 a volunteer applied to the Brownfield Cleanup Program to
remediate the site in preparation for building an office building. The site remediation consisted of
excavation and off-site disposal of contaminated soils above the predetermined cleanup levels and
backfilling with clean soil/material. Work began in summer 2005 and was completed in early 2006.
An environmental easement requiring a Site Management Plan was filed on September 7, 2006 in the
Erie County Clerk's office. Remaining groundwater contamination will be monitored by an Operation
& Monitoring Plan. A Certificate of Completion was issued on November 30, 2006. The cleanup has
resulted in the construction of an approximately 350,000 square foot Health Now building by Duke
Realty at the remediated site. Groundwater at the site is being monitored in accordance with the Site
Management Plan, dated October 2, 2006.
Alltift Landfill - NYSDEC #915054
This site is a former landfill that was previously used for the disposal of domestic and industrial
wastes. Environmental studies documented surface and groundwater contamination. According to
Phase II Investigation documentation, Allied Corp. (National Aniline Division) disposed
miscellaneous organic chemicals, chrome sludge, copper sulfate, nitrobenzene, monochlorobenzene,
and naphthalene on a monthly basis in the landfill. A smaller landfill containing automobile shredder
wastes, demolition debris, fly-ash and sand wastes was situated on top of the older chemical waste
landfill. This smaller landfill was operated between 1975 and 1984. A Consent Order for the
completion of a RI/FS of the site was signed by Allied Signal in 1991.
16

-------
A RI/FS report was submitted in 1992 indicated that groundwater and the ponds adjacent to the site
were impacted by the landfill. Contaminants of concern include metals, pesticides, PCBs, chlorinated
solvents and PAHs and would be tributary to the Buffalo River drainage basin.
A Record of Decision (ROD) was signed on March 27, 1995 requiring: capping, waste consolidation,
wetlands restoration, and groundwater collection. Remedial action began in 2004 and was completed
in 2005. An operation, maintenance and monitoring plan was put in place in 2006 and
implementation is ongoing.
Steelfields Site - NYSDEC # V00619
The Steelfields Site is located in the City of Buffalo adjacent to the Buffalo River. The site is comprised
of four distinct areas based on the historical operations that occurred there. These areas are known as:
Area I-Republic Steel Area, Area II-Donner-Hanna Coke Plant, Area III- Republic Steel Warehouse, and
the Area IV-Coke Storage Yard. The former above-ground facilities were demolished previously by the
LTV Steel Company. Today the site is largely vacant except for the former "August Feine" building
located just north of Area II where a newly constructed containment cell exists. In 2006, Area IV was
separated from the site and entered into the Brownfield Cleanup Program as Steelfields Area IV
Site#C915204. Area IV is also listed on the NYS Registry as a Class 3 hazardous waste site under Site
#915017. The Steelfields site was the location of a former steel and coke-making facility. The site had
significant amount of fill material (2 to 20 feet in depth) from past activities. The fill consisted of waste
slag and coke, in addition to significant quantities of chemically contaminated soils from past disposal
practices on the site. LTV Steel, the previous Volunteer for this site (V00133) went bankrupt in 2000. In
October 2002 Steelfields Ltd. purchased the site out of bankruptcy. Steelfields Ltd. entered into the
Voluntary Cleanup Program and agreed to undertake the necessary investigation and cleanup of the 218
acres. A work plan outlining the work to be performed was approved in 2002. Remedial work was
completed on approximately 90 acres known as Area 1 in 2004. Remedial work was completed in all
areas of the site by October 2007. Declaration of Covenants and Restrictions were filed for Area I in
2007 and for Areas II & III in 2008. Long term Site Management is ongoing.
Niacet Corporation — NYSDEC # V00373
The Niacet facility, formally a Union Carbide Corporation facility, is located on 19.42 acres at the
intersection of 47th St and Pine Ave in the City of Niagara Falls. The facility is an active manufacturing
facility first constructed in 1925 and operated as the Niacet Chemical Company. The plant originally
produced acetaldehyde, paraldehyde, aldol and crotonaldehyde. The production of acetic acid was begun
in 1928 and the manufacture of sodium acetate and other acetates began in 1935. Vinyl acetate
production was added in 1937. In 1957 the facility name was changed to Union Carbide Corporation. The
plant produced a variety of wastes including mercury/aluminum sludge, 2-ethylexoate, zincacetate, acetic
acid, acetate salts and overflows from the vinyl division. In 1978 Niacet purchased the property from
Union Carbide Corporation and currently manufactures specialty chemical products for food,
pharmaceutical and industrial applications. A site investigation was completed in 2002 indicating the
presence of mercury contaminated soil. A supplemental site investigation was completed in March 2006.
A draft Remedial Action Selection Report (RAS) was submitted in November 2006. The draft RAS was
not acceptable and the Department requested revisions to the RAS were requested. Resubmission of the
RAS is pending resolution of the contaminated soil disposal characterization and classification issues.
17

-------
Spaulding Fiber Site — NYSDEC #915050/E915050
The 46 acre Spaulding Composites Site is located at 310 Wheeler Street in the City of Tonawanda.
Spaulding manufactured composite laminates and vulcanized fiber between 1911 and 1992 at this now
abandoned facility. The paper used to produce vulcanized fiber, and many of the phenolic resins used in
the production of the composite laminates, were also manufactured on site. Site drainage and contaminant
transport was tributary to the Niagara River through the municipal storm sewer system. All
RI/FS/Corrective Measure Studies have been completed for RCRA/Superfund portions of the site. The
Record of Decision (ROD) for this site was issued in March 2003. Seventeen Solid Waste Management
Units (SWMUs)within approximately 2.5 acres of property around the plant buildings were identified
(included in four separate operable units) as requiring remediation as a part of the SSF project; the rest of
the property is being addressed as part of an Environmental Remediation Project (ERP). Remediation of
OU#2 was performed as an IRM to address PCB contamination of surface and subsurface soils.
Remediation of OUs (#1, #3 & #4) is underway and is scheduled to be completed by the Summer of
2010 under the State Superfund Program. The RI/F S for the ERP portion of the site was completed and a
no- action ROD for the project for OU#7 was issued in March 2009. Design documents for OUs (#5 &
#6) have been completed and the remedial work is also expected to be completed by the summer of 2010.
18

-------
Acronyms
APL
BCC
BSC
BUI
CERCLA
CMI
CMS
DDT
DEC
DNAPL
DWTP
EC
EPA
ERP
HSWA
ICM
IIW A
IRM
MOE
NAPL
NRTMP
occ
OM&M
OU
PCBs
PRP
PSA
PVC
RA
RCRA
RFA
RFI
RFP
RI/FS
ROD
RRT
SPDES
TCDD
TBD
TCP
VOC
Aqueous phase liquids
Buffalo Chemical Corporation
Bethlehem Steel Corporation
Beneficial Use Impairment
Comprehensive Environmental Response, Compensation, and Liability Act of 1980
Corrective Measure Implementation
Corrective Measure Study
primarily l,l'-(2,2,2-trichloroethylidene)-bis/4 chlorobenzene
New York State Department of Environmental Conservation
Dense non-aqueous phase liquids
Drinking Water Treatment Plant
Environment Canada
U.S. Environmental Protection Agency
Environmental Remediation Project
Hazardous and Solid Waste Amendments
Interim Corrective Measure
Immediately Implementable Work Assignment
Interim Remedial Measure
Ontario Ministry of the Environment
Non-aqueous phase liquids
Niagara River Toxics Management Plan
Occidental Chemical Corporation
Operation, Maintenance & Monitoring
Operable Unit
Polychlorinated biphenyls
Potentially Responsible Party
Preliminary Site Assessment
Polyvinyl chloride
Remedial Action
Resource Conservation and Recovery Act
RCRA Facility Assessment
RCRA Facility Investigation
Request for Proposal
Remedial Investigation/Feasibility Study
Record of Decision
Requisite Remedial Technology
New York State Pollutant Discharge Elimination System
Tetrachlorodibenzo-p-dioxin
To Be Determined
Trichlorophenol
Volatile organic compounds
19

-------
Glossary
A
Ambient
A surrounding medium, such as water or air.
Used in contrast to a specific source.
Aquatic
Growing in, living in, or dependent upon
water.
Atmospheric deposition
Pollution from the atmosphere associated with
dry deposition in the form of dust, wet
deposition in the form of rain and snow, or as a
result of vapor exchanges.
B
Barrier wall
A wall constructed underground in a
hazardous waste site or landfill to stop the
flow of contaminated groundwater.
Basin
The land that drains into a waterbody.
Bedrock groundwater
Water flowing through a rock layer
underground, under a top layer of mixed soil
and loose rock called the overburden.
Benzo(a)pyrene [B(a)P]
A PAH that is formed by the incomplete
combustion of fossil fuels, wood, and tobacco;
the incineration of garbage; and in steel
production.
Bioaccumulation
The process by which chemical substances
accumulate in the tissues of an organism that
drinks contaminated water or eats
contaminated food.
C
Cap
A cover over hazardous waste sites, usually
made of clean soils or clay, that prevents
rainwater from seeping through soil and
causing the contaminants in the soil to flow
into the groundwater.
Capture Zone
Area in which groundwater is flowing towards
a pumping well; used as remediation technique
for hazardous waste sites, to Acapture@
contaminated groundwater and treat it.
Chlordane
A persistent toxic chemical that was used to
control ants, grasshoppers, and other insects on
certain crops.
Collection drain
System of pipes around a hazardous waste site
or landfill that collects surface or groundwater
and directs it toward a treatment plant.
Combined sewer overflow (CSO)
Water discharged into a waterbody from a
sewer system that carries both sanitary sewage
and stormwater runoff. During dry weather
the combined sewer systems flow is normally
treated at a wastewater treatment plant, but
during rain events, the plants capacity may be
exceeded and the flow may be bypassed to
discharge, untreated, directly into a waterbody.
Consent decree
A legal document, approved by a judge, which
puts into effect a remedy (i.e., actions to
correct an environmental problem).
20

-------
Contaminant
A substance that is not naturally present in the
environment or is present in amounts that can
adversely affect the environment.
D
Dredging
Removal of sediment from the bottom of a
waterbody.
DDT
Di chl oro-diphyny 1 -tri chl oroethane. A
persistent toxic chemical that was used as a
pesticide, particularly for mosquito control.
DDT is banned in U.S. and Canada. DDE and
DDD are metabolites of DDT.
Dieldrin
A persistent toxic chemical that was used
mainly as a soil insecticide.
Dioxins/furans
Dioxin: A family of persistent toxic chemicals
known as dibenzo-p-dioxins. Dioxins can
enter the environment as the by-products of
industrial processes or as a result of
combustion processes in incinerators and
motor vehicles using leaded fuel. The
compound called A2,3,7,8-TCDD@ is the most
toxic member of the dioxin family.
Furans are a class of chemicals similar to
dioxins, which are created at high
temperatures, such as incineration of PCBs and
other organic wastes containing chlorine.
DNAPL (Dense Non-Aqueous Phase Liquid)
An oily, sludge-like mixture of chemicals that
is denser than water. DNAPL flows with
gravity or along geological formations, not
always in the same direction as groundwater.
Downstream
In the direction with the flow of a stream or
river; down river. For Niagara River,
downstream is towards Niagara-on-the-Lake
and Lake Ontario.
E
Embayment
A bay. A part of a waterbody (such as a river
or lake) that makes an indentation into the
adjacent land.
F
Force main
A pipe that carries contaminated groundwater
drawn out of hazardous waste sites by
pumping wells to a treatment plant.
Four Parties
The four agencies who implement the Niagara
River Toxics Management Plan: U.S.
Environmental Protection Agency,
Environment Canada, New York State
Department of Environmental Protection, and
Ontario Ministry of Environment and Energy.
G
Groundwater
The fresh or saline waters found beneath the
Earth:s surface that often supply wells and
springs. Contrast to ASurface water®.
H
Habitat
Place where a particular type of plant or
animal lives. An organisms habitat must
provide all of the basic requirements for its
life.

-------
Hazardous Waste Site
Land disposal site for hazardous wastes.
Hazardous Waste Substance
Any substance that is a by-product of society
classified under U.S. or Canadian law as
potentially harmful to human health or the
environment and are subject to special
handling, shipping, storage, and disposal
requirements under the law.
Heavy metals
Metallic elements with high atomic weights
that tend to be toxic and bioaccumulate.
Examples are mercury, arsenic, lead, etc.
Hexachlorobenzene (HCB)
A persistent toxic chemical that was originally
manufactured as a fungicide for cereal crops.
It is also generated as a by-product in the
manufacture of pesticides and can be formed
during the combustion of substances
containing chlorine.
I
Infiltration
Passing through or filtering through, as in rain
water that filters through soil to join
groundwater.
Inorganic substance
A chemical compound that does not contain
carbon. Inorganic substances are often derived
from minerals.
Insecticide
A chemical used to kill or control the growth
of insects.
L
Landfill
Land disposal site for hazardous (or non-
hazardous) wastes.
Leachate
Liquid derived from rain or snow melt that
percolates through a hazardous waste site.
Load or Loading
The mass amount of a material entering a
system over a given time interval.
M
Medium (plural: Media)
A surrounding substance in the environment:
water, air, or sediment.
Metabolite
A substance that is the product of biological
changes to a chemical.
Mirex
A persistent toxic substance that was used as
an insecticide and a fire retardant.
Multi-media
Involving multiple media, such as water and
air, or air and sediment, or all three.
N
National Priorities List (NPL)
An EPA list of the most serious uncontrolled
or abandoned U.S. hazardous waste sites
identified for long-term remedial action under
Superfund.
Non-Point Source
Diffuse pollution sources (i.e., without a single
point of origin or not introduced into a
waterbody from a specific outlet). Generally
carried off the land by stormwater. Common
sources can be associated with a variety of
land-uses (e.g., agriculture, forestry, and
urban) and activities (e.g., construction,
mining, and land disposal). Contrast to APoint
Source®1.
23

-------
o
Octachlorostyrene (OCS)
A persistent toxic chemical that was released
as a by-product when chlorine was
manufactured using certain processes that are
no longer used.
Organic substance
A chemical compound that contains carbon.
Overburden groundwater
Water flowing through a layer of mixed soil
and loose rock that lies over the rock layer
called bedrock.
P
PAHs
Polycyclic or polynuclear aromatic
hydrocarbons. A class of persistent toxic
compounds that are formed from the
combustion of organic material, such as forest
fires or gasoline in cars.
PCBs
Polychlorinated biphenyls. A group of
persistent toxic chemicals used in electrical
and hydraulic equipment for insulating or
lubricating purposes.
Persistent toxic chemical
Any toxic chemical that is difficult to destroy
or that breaks down slowly in the environment
(i.e., with a half-life in water greater than eight
weeks).
Pesticide
A chemical used for preventing, destroying, or
repelling any pest.
Point source
Any discernible confined and discrete
conveyance, including, but not
limited to, any pipe, ditch, channel, tunnel,
conduit, well, container, landfill, leachate
collection system, vessel or other floating craft
from which pollutants are or may be
discharged from.
Pollution prevention
Any action that reduces or eliminates
pollutants before they enter the environment.
Potentially Responsible Party (PRP)
Any individual or company potentially
responsible for, or contributing to, the
contamination problems at U.S. hazardous
waste sites.
Pretreatment
Processes used to reduce, eliminate, or alter
pollutants from industrial sources before they
are discharged into publicly-owned sewage
treatment systems.
Priority toxic chemicals
Under the NRTMP, 18 toxic chemicals that
exceeded water quality or fish tissue standards
in the Niagara River or Lake Ontario.
R
RCRA
Resource Conservation and Recovery Act. A
U.S. program to remediate active hazardous
waste sites. Sites are remediated by
potentially responsible parties whenever this
can be arranged.
Record of Decision (ROD)
A public document that explains what actions
will be taken to remediate a U.S. hazardous
waste site.
24

-------
Remedial Investigation/Feasibility Study
(RI/FS)
The RI defines the areal and vertical extent of
the hazardous waste problem at a Superfund
site through numerous sampling wells, an
extended environmental sampling program and
a full geophysical survey. Based on the RI, the
FS develops and evaluates alternative
solutions to the problem.
Requisite Remedial Technology (RRT)
An RRT is the equivalent of an FS (see RI/FS
above) for a pre-CERCLA agreement.
Runoff
Water that flows over the land surface into a
waterbody.
S
Slurry wall
Barrier made of a thin, watery mixture of fine,
insoluble material (e.g., clay, cement, soil).
Solid Waste Management Units (SWMUs)
Areas within a hazardous waste site where
hazardous materials are stored or managed.
SWMUs are generally storage areas, treatment
systems, disposal areas, spill areas, or
containment cells.
Superfund
A U.S. program to remediate inactive or
abandoned hazardous waste sites in an
emergency or for the long-term. Sites are
remediated by potentially responsible parties
whenever this can be arranged.
Surface water
All water open to the atmosphere (e.g., rivers,
lakes, reservoirs, seas, etc.). Contrast to
AGroundwater@.
T
Toxaphene
A persistent toxic chemical that was used as an
insecticide.
Toxic substance
Any substance that adversely affects the health
or well-being of a living organism, e.g.,
causing death, disease, birth defects,
behavioral abnormalities, cancer, genetic
mutations, physiological/reproductive
malfunctions, or physical deformities.
U
Upstream
In the direction against the flow of a stream or
river; upriver. For Niagara River, upstream is
towards Fort Erie and Lake Erie.
V
Volatile substance
A substance that evaporates readily.
W
Wetland
An area that is saturated with water or has a
water level at or near the surface. A wetland
has organic soils and plant/animal species that
are adapted to a wet environment.
25

-------
References
The Niagara River Declaration of Intent (DOI). 1987. Environment Canada, the United States
Environmental Protection Agency - Region II, Ontario Ministry of the Environment, and the New
York State Department of Environmental Conservation, February 1987.
Gradient Corp./GeoTrans Inc. 1988. Potential Contaminant Loadings to the Niagara River from U.S.
Hazardous Waste Sites, February 1988.
U.S. Environmental Protection Agency/New York State Department of Environmental Conservation
(EPA/NYSDEC). 1989. Reduction of Toxics Loadings to the Niagara River from Hazardous Waste
Sites in the United States, November 1989.
Niagara River Toxics Management Plan Letter of Support. 1996. Environment Canada, the United
States Environmental Protection Agency - Region II, Ontario Ministry of the Environment, and the
New York State Department of Environmental Conservation,
December 1996
Conestoga-Rovers & Associates (CRA). 1998. Estimates of Pre-Remedial and Post-Remedial
Action Chemical Loading via Groundwater to the Niagara River, Ref. No. 9855(1),
January 1998.
The Niagara River Secretariat. 2007. Niagara River Toxics Management Plan (NRTMP) Progress
Report and Work Plan, October 2007.
USEPA Great Lakes - NRTMP website, 2009.
http ://www. epa. gov/ greatiakes/lakeont/nrtmp
NYSDEC Environmental Site Remediation Database website, 2009.
http://www.dec.nv. gov/cfmx/extapps/derextemal/index.cfm?pageid=3
24

-------
[This Page Intentionally Left Blank]

-------
APPENDIX A	
PRIORITY NIAGARA RIVER HAZARDOUS WASTE SITES:
Site Remediation Status Summaries

-------
[This Page Intentionally Left Blank]

-------
Silo Niimo:
( (ink-ills
Komodi
l-'u mi ;il
Posl-
Tolill
Addilioiiiil Comments
I SCS Silo # :
/I'lllllllillllS of
ill
Komodiiil
Komodiiil
Komodiii

WSM'.C Silo#:
( onoorn
Aolions
( oinpliiiiioo
Action
lion



( nmplo
iiiul/or
O&M
Cosis lo



10(1
l.nforceiiK'ii
Sliilus
Diilo




1 Actions



Occidental Chemical C
Chlororganics
Decemb
NYS Part
Bedrock &
Not
Implementation of the Bedrock
# 41b-49
, cell brine
er1998
373 and EPA
Overburde
available
& Overburden
#932019
sludges,

RCRA
n
at this
Stabilization Programs will
RCRA (State & Feden
phosphorus

permits
Groundwat
time
effectively eliminate future off-

sludges

issued
er

site loadings from the Main




Monitoring

Plant Site.




Collection
kr






Oi
Treatment


Niagara Co. Refuse Di
Phenolic
Decemb
EPA Consent
Groundwat
Fed:
The site is still monitored by
#81
resins, plating
er 1999;
Order and
er
$1,490,7
EPA/State and data supports
#932026
tank sludges,
NPL
ROD issued
Monitoring
00PRP:
that the remedy is effective and
Federal Superfund
brine sludge
deletion

Program
$13,872,
operating as designed.


in July

on-going
000



2004




Dupont Necco Park
Brine sludge,
Septem
EPA Consent
Groundwat
Fed:
Site is in OM&M phase.
# 14
barium salts,
ber
Orders and
er
$2,155,0
Ground water pump and treat
#932047
chlorinated
2007
ROD issued
Monitoring
00
performing satisfactorily.
Federal Superfund
organic



State:
Upgrades underway to improve

chemicals


Collection
$141,000
pumping efficiency at PW-10.




&
PRP:
Quarterly and annual reports




Treatment
42,500,0
submitted to USEPA and




on-going
00
NYSDEC.
CECOS International /
Acetone, 2-
Februar
EPA RCRA
Groundwat
Not
Corrective Measure
#78/
butanone,
y 1995
HSWA and
er
available
Implementation including
#NA
benzene,

NYS Part
Extraction
at this
Aquifer pumping test program
RCRA (State & Feden
chloroform,

373 permits
&
time.
to control

toluene,

issued
Treatment;

contaminant migration

chlorobenzen


landfill cap

continues to operate

e, methylene


maintenan

satisfactorily.

chloride,


ce; site



tetrachloretha


access



ne


restrictions


Occidental Chemical -
Brine sludge,
June
EPA/NYSDE
Overburde
Fed:
It is estimated that
Hyde Park
organic
2003
c/occ
n
$12,100,
$2,000,000/year will be spent
#39
phosphates,

Stipulation
Groundwat
000
on the O&M of the site for
#932021
dechlorane,

and
er
PRP:
approximately the next 30
Federal/State Superfun
chlorotoluene

Judgment
Monitoring
$78,000,
years.
Co-lead
s, TCP,

Approving

000


benzoyl

Settlement
Collection



chloride,

Agreement
&



chlorobenzen


Treatment



es, acid






chlorides






-------
Silo Niimo:
( (ink-ills
Itemed i
l-'u mi ;il
Posi-
loliil
Addilioiiiil Comments
I SCS Silo # :
/PolllllillllS of
ill
Komodiiil
tioned iiil
Komodiii

WSM'.C Silo#:
Concern
Actions
Compliance
Action
lion

Pro^mm:

(0111 pic
iind/or
O&M
Cosis lo



10(1
l.llloiCOIlH'll
Sliilns
Diilc




1 Actions



102nd Street
Benzenes,
Decemb
EPA ROD
Long-term
Fed/State
Long-term leachate pump and
# 40, 56, 85, and 94
chlorobenzen
er1998
completed
leachate

treat system operating
#932922 & #932031
es,

1990 &
pump and
$9,900,0
optimally. It is estimated that
Federal Superfund
chlorophenols

Administrati
treat
00
future O&M costs to be paid by

, hexa-

ve Order
system
PRP:
the PRP will be approximately

chlorocyclohe

issued
installed
$26,000,
$100,000/year.

xanes,

September
and
000


mercury

1991
optimized






in March






1999.


Bell Aerospace Textro
Chlorinated
1987
NYS Part
Hydraulic
PRP:
Recent maintenance and
#5
solvents,

373 and EPA
groundwat
$1,898,8
upgrades in 2007 to the
#932052
rocket fuel,

RCRA
er
91
treatment system has increased
RCRA (State and Fede
misc.

permits
containme
(Capital
operational efficiency.

chemicals

issued
nt pump
and





and treat
O&M)





system in






place
Future






O&M






estimated






$400,000






/year

OCC- Durez Corp. -
Phenolic
1995
NYS Part
Groundwat
Not
EPA and NYSDEC have
Packard Road
wastes

373 and EPA
er pump
available
determined that the existing
# 66


RCRA
and treat
at this
groundwater pump and treat
#932040


permits
program;
time.
program is capable of serving
RCRA (State and Fede


issued
maintenan

as the final groundwater




ce of

remedy for the site.




landfill






cap; site






access






restrictions



-------
Silo Niimo:
( (ink-ills
Komodi
l-'u mi ;il
Posl-
Tolill
Addilioiiiil ( oiniiionls
I SCS Silo # :
/I'lllllllillllS of
ill
Komodiiil
Komodiiil
Komodiii

WSM'.C Silo#:
( onoorn
Aolions
( oinpliiiiioo
Action
lion



(imiplo
iiiul/or
O&M
Cosis lo



10(1
l.nforceiiK'ii
Sliilus
Diilo




1 Actions



Occidental Chemical
CaF2 sludge,
August
EPA/NYSDE
Operation
Fed/State
Continued optimization of the
S-Area
organic
2002
C lead
and
$10,500,
performance of
# 41A
phosphates,

responsibility
maintenan
000
groundwater pump and treat
#932019A
chlororganics,

under 1985
ce of S-
PRP:
system effective.
Federal/State Superfun
sulfides

judicial
Area
$45,000,

Co-lead


settlement
landfill
000




agreement
cap;
Future





groundwat
O&M





er
estimated





collection
Fed:





and
$1,000,0





treatment.
00; PRP:






$5,000,0






00






capital






and up to






$3,000,0






00 /year






for 30






years.

Stauffer Chemical
Carbon
Decemb
NYSDEC
Bedrock
State:
Groundwater treatment system
#255
tetrachloride,
er1995
Consent
groundwat
$180,000
has been modified to include
#932053
various

Order
er pump
PRP:
granular activated carbon prior
NYSDEC Superfund
metallic


and treat
$5,100,0
to discharge to the NYPA

chlorides,


system;
00 State
Forebay.

methylene


soil vapor
O&M:


chloride,


extraction
$10,000


tetrachloroeth


and
PRP:


ylene


dewatering
$1,300,0





system.
00/year






for 30






years.

Solvent Chemical
Chlorobenzen
May
ROD issued
Bedrock
State:
Continued operation and
#251
es, zinc
2001
December
groundwat
$1,170,0
maintenance of bedrock
#932096


1994; U.S.
er pump
00 PRP:
groundwater pump and treat
NYSDEC Superfund


District
and treat
$7,374,0
system.



Court
system.
00 PRP




Judgement

O&M:




issued

$4,600,0




October

00




1997.




-------
Silo Niimo:
( (ink-ills
Komodi
l-'u mi ;il
Posl-
Tolill
Addilioiiiil Comments
I SCS Silo # :
/I'lllllllillllS of
ill
Komodiiil
Komodiiil
Komodiii

WSM'.C Silo#:
( onoorn
Aolions
( oinpliiiiioo
Action
lion



( nmplo
iiiul/or
O&M
Cosis lo



10(1
l.nforceiiK'ii
Sliilus
Diilo




1 Actions



Vanadium Corp.
Chromium,
Projecte
ROD issued
OU#l -
State:
Remedial Design for OU#3
# 1
caustic waste
d
March 2006:
Containme
$454,000
was completed in in 2007 The
#932001

complet
OU#l - No
nt and
PRP:
Remedial Action is expected to
NYSDEC Superfund

ion
Further
storm
$9,900,0
start in early 2010 pending


October
Action
water
00
execution of a Consent Decree.


2009
OU#2 - No
control,
(OU#l &




Further
approved
OU#2)




Action
OM&M





OU#3 -
plan;
Projected




Consolidatio
OU#2-
future




nand
landfill
OU#3




capping
cap,
PRP cost





groundwat
to





er
completi





collection
on





and treat
$12,000,





system,
000





approved






OM&M






plan


Olin Corporation
Mercury brine
October
NYSDEC
Groundwat
Not
Remedial system close to
# 58, 59
sludges,
1997
Consent
er pump
available
meeting optimum
#932051
chlororganics,

Order
and treat.
at this
effectiveness; recent
State and Federal RCR
fly ash



time.
performance reports indicate






system improvements.
Dupont - Buffalo Ave.
Carbon
January
NYSDEC
Groundwat
State:
Periodic post monitoring
# 15-19
tetrachloride,
1992
Consent
er
$75,000
reports indicate effective
#932013
chloroform,

Order
remediatio
PRP: $
groundwater pump and treat
NYSDEC Superfund
dichloroethyle

ROD issued
n system
74,000,0
system. Blast fractured

ne, methylene

January 1990
(pump and
00
bedrock trenches installed in

chloride,


treat)
(includes
SW plant area have greatly

trichloroethyl



Gill
increased hydraulic

ene,



Creek
containment and pump rates.

tetrachloroeth



cleanup)
GWRS system upgrades

ylene, vinyl



Projected
replaced steam stripper and

chloride,



future
added therm-ox unit to treat

PCBs,



O&Mby
off-gasses to handle additional

barium, and



PRP:
flow from trenches.

other organic



$1,100,0
Approximately 133,000 pounds

and inorganic



00 / year.
of organic contaminants

compounds




removed from groundwater






since startup thru 1st Quarter






2008 by the GWRS and Olin






pumping well.

-------
Silo Niimo:
( onionls
Reined i
l-'di'iiiiil
Posl-
Idlill
Addilioiiiil ( n in men (s
I SCS Silo # :
/Pulliiliinls of
ill
Komodhil
Komodiiil
Komodiii

WSM'.C Silo#:
( onoorn
Aolions
( oiiipliiiiioo
Action
lion



( (llliplo
iind/or
O&M
Cosls In



10(1
l.llloiCOIlH'll
1 Actions
Sliilus
Diilo

Buffalo Color Corp.
Aniline, N-
IRM
NYS Part
Groundwat
Not
Draft Remedial
Plant Site
methylaniline,
pump
373 and EPA
er pump
available
Investigation/Feasibility Study
# 120, 122
N-
and
RCRA
and treat
at this
completed in March 2008.
#C915230, C915231,
dimethylanilin
treat
permits
system
time.
As a result of the RI/FS, a
C915232
e, N-
system
issued;
operational

Brownfield Cleanup Plan
State and Federal RCR
diethylaniline,
installe
NYSDEC
12/2007.

application was submitted and
State Brownfield Progi
cyanide,
d
Consent


was approved by the NYSDEC

methanol,
12/2007
Orders issued


in April 2009. The Remedial

nickel,

3/12/2005


Work Plan was approved in

chromium

and
6/30/2006.


May 2009. Demolition of the
plant buildings began in late
2009 and will continue through
early 2010. Design activities
will continue into 2010.
Remedial Action work is
expected to be performed in
2010/11.
Buffalo Color - Area I
Iron oxide
Septem
NYSDEC
Slurry
State:
Groundwater pump and treat
# 120-122
sludges
ber
Consent
wall;
$200,000
system operating
#915012
containing
1998
Order
sediment
PRP:
satisfactorily.
NYSDEC Superfund
organics


dredging;
lanfill cap;
groundwat
er pump &
treat
system
$14,000,
000


-------
Silo Niimo:
( (ink-ills
Itemed i
l-'u mi ;il
Posi-
loliil
Addilioiiiil Comments
I SCS Silo # :
/PolllllillllS of
ill
Komodiiil
tioned iiil
Komodiii

WSM'.C Silo#:
Concern
Actions
Compliance
Action
lion

Pro^mm:

(0111 pic
iind/or
O&M
Cosis lo



10(1
l.nforceiiK'ii
Sliilns
Diilc




1 Actions



Bethlehem Steel Corp.
Tar decanter
C91519
NYSDEC
Proposed
Not
915009 - Consists of RCRA
# 118
sludge,
7
Consent
Groundwat
available
regulated portion of property
#915009, C915197,
ammonia still
Projecte
Order
er
at this
C915197 - Tecumseh Phase I
C915198, C915199,
lime, sludge,
d
C915197 -
collection
time.
Business Park -IRM completed
C915205, C915216,
pickling
October
Brownfield
and

2009, RI/AAR (NFA) expected
C915217, & C915218
liquor
2008
Clean-up
treatment

in 2010
State and Federal RCR

C91520
Agreement
for

C915198 - Tecumseh Phase II
State Brownfield Progi

5 -
(BCA)
brownfield

Business Park - RI/AAR WP


complet
C915198 -
s

submitted 2009, RD field in


ed 2006
BCA
redevelop

2010, RA implementation in



C915199 -
ment.

2011



BCA


C915199 - Tecumseh Phase III



C915205 -
C915205-

Business Park - Site change -



BCA
Protective

C915217 removed from the



C915216 -
cover,

site, RI/AAR WP submitted, RI



Denied entry
passive

to be completed in 2010.



into BCP
groundwat

C915205 - Tecumseh



C915217 -
er

Redevelopment, Inc.-Steel



BCA
treatment,

winds - Completed



C915218 -
Easement

C915216 - Steel Winds IA -



Eligibility


Denied entry into BCP.



Pending


C915217 - Steel Winds II -






Submitted RI/AAR WP but






never implemented Site






included in C915199






C915218 - Tecumseh Phase IA






Business Park - Submitted






RI/AAR WP, RI anticipated in






2010.
River Road (INS Equi|
Foundry sand,
January
NYSDEC
OM&M
State:
Remedial action completed in
# 136
cutting oils,
2000
Consent
activities
$546,000
January 2000 for the Cherry
#915031
industrial

Order. ROD
underway.
PRP:
Farm and River Rd sites.
NYSDEC Superfund
sludges, PCBs

issued March

$15,000,
OM&M activities underway.



1994

000
Periodic reports submitted to






the NYSDEC.
Niagara Mohawk -
Foundry sand,
See Site
ROD issued
OM&M
See Site
See Site 915031 above.
Cherry Farm
cutting oils,
915031
Feb 1991
activities
915031

# NA
industrial
above.
Amended
underway.
above.

#915063
sludges, PCBs

ROD Oct



NYSDEC Superfund


1993




-------
Silo Niimo:
( (ink-ills
Reined i
l-'u mi ;il
Posl-
Tolill
Addilioiiiil Comments
I SCS Silo # :
/I'lllllllillllS of
ill
Komodiiil
Komodiiil
Komodiii

WSM'.C Silo#:
( onoorn
Aolions
( oinpliiiiioo
Action
lion



( nmplo
iiiul/or
O&M
Cosis lo



10(1
l.nforceiiK'ii
Sliilus
Diilo




1 Actions



Frontier Chemical -
Solvents, oils,
March
NYSDEC
Landfill
State:
Long-term O&M includes
Pendleton
acids, dyes,
1997
ROD issued
cap and
$1,430,0
landfill cap maintenance and
#67
paint wastes,

March 1992;
leachate
00
pump and treat of leachate
#932043
heavy metal

NYSDEC
collection
PRP:
from the site.
NYSDEC Superfund
sludges, metal

Consent
and
$14,120,


salt sludges,

Order
treatment
000


pickling



Future


liquors



O&M






costs






State:






PRP:






$50,000






annually

Frontier Chemical,
Monochloroto
Projecte
NYSDEC
Remediati
Fed:
A DEC RI/FS Order for OU#2
Royal Avenue
luene,
d
ROD - OU#l
on on-
$3,690,0
with PRP group was signed in
#
methylene
complet
issued March
going
00 State:
2008. Investigative work was
#932110
chloride,
ion date
2006

$400,000
completed in 2009 and a draft
EPA and NYSDEC
chloroform,
to be


PRP:
report was submitted in late
Superfund
dichlorobenze
determi


$3,600,0
2009 which is under review.

ne,
ned.


00


tetrachloroeth






ylene and






other organic






contaminants





Occidental Chemical -
Phenol tars
Plant
NYSDEC
Plant site
State:
In May 2000, additional
Durez Division,
containing
site: 199
ROD
includes
$510,00
contaminated sediment from
North Tonawanda
chlorobenzen
0
OU#l/2 -Feb
cover
PRP:
the bottom of the cove were
# 24-37
es and
City
1989; ROD
system and
$39,000,
removed. The most recent
#932018
chlorophenols
sewer
OU#3 -
groundwat
000
report (-2006), indicates
NYSDEC Superfund

cleanin
March 1992.
er

elevated concentrations of


g:1992

control/tre

dioxins and furans. A work


Inlet/Co

atment.

plan for source investigation


ve:

Inlet and

and additional sediment


1992

cove &

removal as needed has been


&2000

north lobe

approved. This work was




removal

begun in 2008.




and






containme






nt work is






being






monitored.



-------
Silo Niimo:
( onionls
Komodi
l-'di'iiiiil
Posl-
Tolill
Addilioiiiil (n in men (s
I SCS Silo # :
/PulllllillllS of
ill
Komodhil
Komodiiil
Komodiii

WSM'.C Silo#:
( onoorn
Aolions
( oiiipliiiiioo
Action
lion



( (llliplo
iind/or
O&M
Cosis lo



10(1
r.iiforoomon
Sliilus
Diilo




1 Actions



Gratwick Riverside Pa
Phenolic
Decemb
NYSDEC
Landfill
State:
The Site was reclassified by
#68
resins, PCBs
er 2005
ROD- Feb.
cap and
$2,550,0
DEC from a Class 2
#932060


1991;
leachate
00PRP:
(significant threat) to a Class 4
NYSDEC Superfund


Amended
collection
$5,000,0
(Site remediated and in long



ROD - Jan.
and
00
term OM&M) site in June 2008



1999
treatment







Future






O&M






costs






estimated






to be






$1,140,0






00 over






10 years.

Mobile Oil
Tetraethyl
Projecte
NYSDEC
Remediati
Not
Site segregated into (5)
# 141
lead and lube
d
Consent
on on-
available
operable units. Remediation of
#915040 &C915201
sludges, spent
Decemb
Order issued
going
at this
OU-1 complete to commercial
NYSDEC Brownfield
catalysts, Air
er2011
in 1985.

time.
standards via excavation of

floatation unit

NYS


contaminated fill with no

and gravity

Brownfield


required monitoring. Removal

oil/water

Cleanup


of Pipelines in OU-2 complete

separator

Agreement


with further Investigation of

sludges

executed


OU-2 on going.



April 3, 2006


OU-3 - RI/AAR submitted and






under review






OU-4 - RI/AAR submitted and






under review






OU-5 - Work scheduled for






future years
Iroquois Gas - Westwc
PAHs
Main
NYSDEC
915141A:
State: $
915141 A: hydraulic control,
Pharmaceutical
(Polynuclear
plant
ROD issued
hydraulic
250,000
and groundwater pump and
# NA
Aromatic
site in
March 1994
control;
PRP: $
treat are effective.
# 915141A & B
Hydrocarbons
1997
for both sites.
groundwat
7,000,00

NYSDEC Superfund
) BTEX
and

er pump
0
915141B: DNAPL from under

(Benzene,
Scajaqu

and treat

the creek continues to be

Toluene,
ada

915141B:

collected

Ethyl
Creek

DNAPL



benzene,
sedimen

extraction



Xylene), lead,
ts in





and cyanide
March






1999.






915141






A:1997






915141






B:2001





-------
Silo Niimo:
( onionls
Reined i
l-'oi'iiiiil
Posl-
Idlill
Addilioiiiil ( (mi men (s
I SCS Silo # :
/PulllllillllS of
ill
Komodhil
Komodiiil
Komodiii

WSM'.C Silo#:
( onoorn
Aolions
( oiiipliiiiioo
Action
lion



( (llliplo
iind/or
O&M
Cosls Ht



10(1
Inloicoiiu'ii
1 Aclions
Sliilus
Diilo

Booth Oil
Waste oils,
Novem
NYSDEC
Haz waste
State:
Remedial action completed
# NA
PCBs, VOCs,
ber
ROD issued
removed,
$1,318,9
Nov 1994. Additional remedial
#932100
semi-VOCs,
2004
March 1992
residual
00
work to address gasoline vapor
NYSDEC Superfund
andPAHs

and March
PAH
PRP:
impacts to adjacent home



1993, ROD
contaminat
$6,000,0
continued through 2005.



amendments
ion.
00
Previously unknown USTs



in August
OM&M

removed with soil disposal and



2002
plan for
site cover
maintenan
ce. Deed
restrictions
in place

vapor extraction. Monitoring
wells installed to monitor
groundwater for gasoline
impacts.
Deed restrictions filed for site.

-------
[This Page Intentionally Left Blank]

-------
APPENDIX B	
REMEDIATION of ADDITIONAL POLLUTANT SOURCES:
Site Remediation Status Summaries

-------
[This Page Intentionally Left Blank]

-------
Silo Niimo:
( (ink-ills
Komodiiil
I'llI'lllill
Posl-
llllill
Addilioiiiil
I SCS Silo # :
/PolllltillltS
Actions
Reined i;il
Kcmcdhil
Kcmcdi
Comments
WSM'.C Silo#:
ol' Concern
Completed
(oni|)li;inc
Action
iilion




o iiiid/oi'
O&M
Cosls lo




r.nforccnic
Sliilus
l);Kc




ill Actions



Fourth Street Site
benzene,
Completed
State
Environment
State:
Remedial Action
NA
toluene,
in 2006
Superfund
al Easement
$10,000
included excavation
915167
xylenes,

Program

,000
and off-site disposal
NYS Superfund
phenolic




of all contaminated

compounds,




media above clean-up

PAHs




goals.
Former Buffalo Service
benzene,
Completed
Brownfield
Groundwate
PRP:
Remedial Action
Center
toluene,
in 2006
Clean-up
r monitoring
$16,500
included excavation
NA
ethylbenzene,

Agreement
and
,000
and off-site disposal
C915194
xylenes,


Environment

of all contaminated
NYS Brownfield Clean-up Pro
poly cyclic


al Easement

media above clean-up

aromatic




goals.

hydrocarbons






, total






cyanides





Alltift Landfill
miscellaneou
Completed
SSF
Groundwate
PRP:
Remedial Action
NA
s organic
in 2005
Consent
r monitoring
$14,000
included
915054
chemicals,

Order
and
,000
consolidation and
NYS Superfund
chrome


Environment

capping of waste and

sludge,


al Easement

restoration of

copper




adjacent wetlands

sulfate,




areas.

nitrobenzene,






monochlorob






enzene,






naphthalene,






automobile






shredder






wastes,






demolition






debris, fly-






ash and sand






wastes





Steelfields Site
waste slag
Completed
Voluntary
Groundwate
PRP:
On-site Landfill and
NA
and coke,
in 2007
Clean-up
r monitoring
$16,500
groundwater
V00619/C915204
significant

Agreement
and
,000
containment system
NYS Voluntary Clean-up Prog
quantities of


Declaration

of non-hazardous

chemically


of

waste, Groundwater

contaminated


Covenants

monitoring, Remedial

fill soils


and

Action included




Restrictions

excavation and off-






site disposal of all






contaminated media






above clean-up goals.

-------
Silo Niimo:
( onionls
Komodiiil
l-OI'lllill
Posi-
Idlill
Addilioiiiil
I SCS Silo # :
/I'olllllillllS
Actions
Itemed i;d
tioned i;d
Reined i
( (mi men (s
WSM'.C Silo#:
nf Concern
Completed
Compli;inc
Action
iilion




o ;ind/or
I'.ii lore cine
¦ll Actions
O&M
Sliilus
( (ISlS lo
Diilo

Niacet Corporation
mercury/
Not
Voluntary
Remedial
Not
Project design
NA
acetaldehyde,
completed.
Clean-up
Design
availabl
activities are on-
V00334
sodium

Agreement
Underway
e at this
going and are
NYS Voluntary Clean-up
acetate,



time.
expected to be
Program
paraldehyde,
aldol,
crotonaldehy
de,
aluminum
sludge, 2-
ethylexoate,
zincacetate,
acetic acid,
acetate salts




complete by early
2010.
Spaulding Fiber
PCBs,
Not
State
Remedial
State:
Demolition of plant
NA
Metals,
completed.
Superfund
Actions
$6,000,
structures ongoing
915050/E915050
phenolic

Program
Underway
000
through efforts by
NYS
compounds

State


City of Tonawanda
Superfund/Environmental


Assistance


and Erie County. A
Restoration program


Contract


No further Action -
Record of Decision
for the ERP project
(OU7) was issued in
March 2009.
Remediation of the
Superfund areas
(OU1, OU2, OU3, &
OU4) and the
Environmental
Restoration Grant
areas (OU5 & OU6)
began in late 2009
and should be
completed by summer
2010.

-------