Project Name: Cody Road Wind Farm

Developer Name: Green Power Energy, LLC

Contact Information: David Senehi, davidsenehi@localnet.com

Renewable Energy Type: Wind

Total Planned Megawatt (MW) Size: 10 MW

Project Location: Fenner, NY

Is the project permitted?: Yes

If not, what is the permit status?: NA

What is the status of the project's site?: It is ready for construction

Have land leases been filed with the county?: No but agreements are in place and they can be filed
anytime

What is the status of interconnection, and have system impact and facility studies been completed?
(Distribution or transmission level projects are both eligible): Interconnection study has been signed
and all system studies have been completed

Does the transmission owner (TO) or independent system operator (ISO) have a process to study the
project's impact on the local or regional grid and the subsequent cost to interconnect?: Yes

What is the status of the Environmental Impact Statement?: It has been completed and reviewed
been permitting was established.

Is any element of the project - technology or other - experimental or pilot-phase?: No

What is the long- and short-term operations program of the project? Does the renewable energy
technology manufacturer have a technical support team locally available?: Green Power plans to
operate the facility with one on-site operations manager for an indefinite period including after all tax
incentives and funding payments are completed. There is a near by operations company maintaining
an adjacent facility but at this time there are no plans to contract them.

For wind projects, has a meteorological tower been installed? If yes, when was the tower installed
and how much data has been collected?: A meteorological tower has been on site since 1/15/07.


-------
Who has analyzed the data and what is that person's experience with respect to projects that have
actually been financed?: Global Energy Concepts who has reviewed all of Clipper's projects and
Windguard who has been the advising experts on world wide projects. As a side note although
extensive wind data is available it should be said that this facility will be located next to an existing
facility that has been in operation for 10 years + and has been averaging approximately 30% capacity
continuously.

Can the turbine manufacturer be financed through "traditional" tax equity and debt in the U.S.?: Yes

Provide a short summary of how you view project finance and structure/ownership: A "flip" deal with
a tax equity investor coupled with bank financing.

What are your ideal types of prospective institutions/partners?: A customer that can use all the power
and the New York State RECs and is willing to sign a bilateral agreement through the ISO (they need to
be a market participant in the NYISO to do this)

What is the intended off-take for the renewable power with respect to bundled or unbundled
products and is there a preference? It would be preferred to be a bundled deal but the project will
produce approximately 26,700 MWH annually along with the same number of NYS RECs.


-------