Cost-Effectiveness of Oxidation Catalyst
Control of Hazardous Air Pollutant (HAP) Emissions
From Stationary Combustion Turbines
Prepared By the
Combustion Turbine Work Group
Of the Industrial Combustion Coordinated Rulemaking
September 4, 1998

-------
MEMORANDUM:
DATE: 4 September 1998
SUBJECT: Cost-Effectiveness of Oxidation Catalyst Control of Hazardous Air
Pollutant (HAP) Emissions From Stationary Combustion Turbines
FROM: Combustion Turbine Work Group
TO:	ICCR Coordinating Committee
The Combustion Turbine Work Group (CTWG) formed a task group to develop a white
paper on the cost-effectiveness of oxidation catalysts in controlling HAP emissions from
combustion turbines. The attached document is the white paper developed by this task
group.
The CTWG concurs that this information may be valuable to EPA in developing
regulations for combustion turbines and requests that the ICCR Coordinating Committee
pass it to EPA as a Closure Item.
Attachment: Cost-Effectiveness of Oxidation Catalyst Control of Hazardous Air
Pollutant (HAP) Emissions From Stationary Combustion Turbines

-------
Table of Contents
I.	Introduction	1
II.	Summary of Base Case Assumptions	3
III.	Baseline HAP Emissions from Combustion Turbines	4
A.	Source of Baseline HAP Emissions Data	5
B.	Criteria to Include Emission Test Data in Baseline Emissions .... 5
C.	Emission Factors for Baseline HAP Emissions	6
D.	Complicating Factors	9
IV.	Oxidation Catalyst Costs	10
A.	Cost Inputs	11
B.	Costs Estimated by OAQPS Control Cost Manual	16
C.	Summary of Base Case Cost Estimates	17
D.	Complicating Factors	17
V.	Performance of Oxidation Catalysts in
Reducing HAP Emissions	23
A.	HAP Emissions Test Data for Oxidation Catalysts	23
B.	Engineering Estimates of Catalyst Performance on HAPs	26
C.	Summary of Base Case Performance Estimates	27
D.	Complicating Factors	31
VI.	Cost-Effectiveness Results	32
VII.	Conclusions and Recommendations	34
Appendix A	List of Model Turbines
Appendix B	Description of ICCR Emissions Database for Turbines
Appendix C	QA\QC Review Criteria for Emission Tests
Appendix D	List of Emission Tests that do not meet Criteria
Appendix E	Cost Spreadsheets
Appendix F	Description of the SCONOx™ System
Appendix G Cost-Effectiveness Estimates for Individual HAPs
i

-------
I. Introduction
This paper presents the assessment of the Combustion Turbine Work Group (CTWG)
with regard to the potential cost-effectiveness of oxidation catalysts used to control
hazardous air pollutant (HAP) emissions from combustion turbines. This assessment is
made in the context of the Coordinating Committee providing recommendations that
contribute to EPA's evaluation of "above-the-floor" MACT options for existing
combustion turbines. In accordance with Section 112(d) of the Clean Air Act, EPA must
consider costs in evaluating above-the-floor options for MACT, along with any non-air
quality health and environmental impacts and energy requirements.
In previous materials, the Coordinating Committee recommended to EPA, based on
available information, that it is not possible to identify a best performing subset of
existing combustion turbines, and as a result, there is no MACT floor for the existing
population of combustion turbines in the United States. Therefore, to determine MACT,
EPA may evaluate emission reduction technologies above the floor for existing
combustion turbines. The CTWG has reviewed emission reduction technologies for
existing turbines to identify controls that may be considered in the above-the-floor
MACT analysis. Based on the CTWG's review, oxidation catalysts for the reduction of
carbon monoxide (CO) may reduce emissions of organic HAPs from combustion
turbines. The CO oxidation catalyst is an add-on control device that is placed in the
turbine exhaust duct and serves to oxidize CO and hydrocarbons to H20 and CO2. The
catalyst material is usually a precious metal (platinum, palladium, or rhodium). The
oxidation process takes place spontaneously, without the requirement for introducing
reactants (such as ammonia) into the fuel gas stream (EPA, 1993a). Oxidation catalysts
are used on turbines to achieve control of CO emissions, especially turbines that use
steam injection, which can increase the concentrations of CO and unburned hydrocarbons
in the exhaust (EPA 1993a, Chen et al., 1993). Therefore, EPA may evaluate oxidation
catalysts as an "above-the floor" MACT option for existing combustion turbines. This
1

-------
paper addresses the costs and the HAP air emissions reductions that may be achieved
with oxidation catalysts. The CTWG recognizes that EPA may consider other factors,
such as non-air quality environmental impacts, energy requirements, and secondary
pollutants, in assessing above-the-floor MACT
The approach taken in this paper is to present a base case quantitative estimate of the
cost-effectiveness of oxidation catalysts for model combustion turbine units, which range
in size from 1.13 megawatts (MW) to 170 MW. To determine cost-effectiveness for the
base case analysis, the CTWG developed quantitative estimates for the three inputs
required to estimate cost-effectiveness:
1.	the baseline HAP emissions of combustion turbines before emissions control,
2.	the costs of acquiring and operating oxidation catalysts, and,
3.	the performance of oxidation catalysts in reducing HAP emissions.
For each of these inputs this paper presents the key factors that the CTWG considers
important. In assessing these three areas the CTWG presents a base case quantitative
estimate of the cost-effectiveness of oxidation catalysts for each model turbine. The
quantitative cost-effectiveness for each model was calculated by dividing the total annual
cost by the mass of annual HAP emission reductions. Cost-effectiveness is expressed as
dollars per megagram of HAP emission reduction. A megagram (Mg) is one metric ton,
or approximately 1.1 U.S. tons. The paper also presents a qualitative discussion of the
CTWG's views on complicating factors that could cause the estimated cost-effectiveness
base case to be different in real-world situations.
Section II provides a summary of the base case assumptions. Sections III, IV, and V
present the quantitative estimates and complicating factors for each of the three inputs for
cost-effectiveness: baseline HAP emissions, control costs, and emission reduction. The
range of cost-effectiveness values and the base case cost-effectiveness for each model
turbine are presented in Section VI. The CTWG's conclusions and recommendations are
presented in Section VII.
2

-------
II. Summary of Base Case Assumptions
For the base case cost-effectiveness analysis, the CTWG selected seven model turbines
that range in size from 1.13 megawatts (MW) to 170 MW:
•	Model 1 -GEPG7121EA, 85.4 MW
•	Model 2 -- GE PG 723 IF A, 170 MW
•	Model 7- GEPG6561B, 39.6 MW
•	Model 9 - GE LM2500, 27 MW
•	Model 13 — Solar Centaur 40, 3.5 MW
•	Model 15 - Solar Mars T12000, 9 MW
•	Model 17 - Solar Saturn T1500, 1.13 MW
These seven model turbines were selected from the 32 model turbines developed by the
CTWG to provide the basis to estimate the national impacts associated with any future
combustion turbine MACT standard. A complete list of the 32 model turbines is
provided as Appendix A.
As originally developed, the list of model turbines incorporates the fuels used, the typical
hours of operation for a unit, the industry sector that may use a turbine, the presence of a
duct burner, and information about space limitations. For the base case analysis, the
CTWG simplified the model turbines selected. The base case assumes that each turbine
is operated for 8,000 hours annually and operates at 80% rated load or greater.
The CTWG also limited the base case analysis to natural gas-fired model turbines.
Natural gas is the predominant fuel used by combustion turbines in the ICCR database.
54.3% of the turbines in ICCR Inventory Database Version 3 were reported as firing
natural gas exclusively. In addition, 14.5% were reported as being dual fuel units, and it
is expected that these units primarily use natural gas. The CTWG has assembled
quantitative information available on baseline emissions, catalyst costs and catalyst
performance for natural gas-fired turbines. In addition, the CTWG decided to focus the
quantitative analysis on natural gas-fired turbines because fuels other than natural gas
introduce complicating factors. For example, a catalyst vendor indicated that for turbines
3

-------
that operate continuously on fuel oil, it is preferable to use a special catalyst formulation
that is unaffected by sulfur exposure (Chen et al., 1993). The CTWG has no data on the
specially formulated catalysts.
In addition, the CTWG limited the base case quantitative analysis to uncomplicated
retrofit installations. Although the CTWG identified a number of situations that would
complicate a retrofit installation of an oxidation catalyst, especially complications due to
space limitations, time did not permit the CTWG to develop quantitative estimates for
these complications. Therefore, the base case includes only a qualitative description of
retrofit complications, and no costs for retrofit complications are included in the cost-
effectiveness values. Based on the experience of the CTWG members, most retrofit
installations for existing turbines would involve some complicating factors and, therefore,
the costs to retrofit the units with oxidation catalysts would be higher in general, and in
some cases much higher, than the costs presented in this base case analysis.
III. Baseline HAP Emissions from Combustion Turbines
The CTWG used emissions data included in the ICCR Emissions Database to identify
HAPs emitted by natural gas-fired combustion turbines and to estimate baseline emission
rates. Only emissions tests that met the criteria established by the CTWG for this
analysis were considered. Mass emissions for each HAP were calculated using emission
factors (lb/MMBtu) from those emission tests that met the CTWG's criteria. Since the
rate of emissions reported for natural gas-fired combustion turbines varies, the CTWG
used two emission factors to estimate baseline emissions — the highest emission factor
and the average emission factor.
Further discussion of the baseline emissions data used in this analysis and complicating
factors is provided below.
4

-------
A.	Source of Baseline HAP Emissions Data
The information available to the CTWG about the emissions of HAPs from combustion
turbines is included in the ICCR Emissions Database. The CTWG believes that the
emissions database adequately represents the turbine population, and that these source
test data are a sufficient basis for emission factors for a cost-effectiveness analysis.
The current version of the emissions database includes over 70 source tests collected by
EPA, many of which involve replicate sampling and analysis runs. For each test report
EPA has calculated consistent emission factors for measured HAPs based on the
emissions concentration reported. A description of the development of the emissions
database, including assumptions used in the calculations, is provided as Appendix B.
Also, EPA and the CTWG have performed a quality assurance review of each test report
and determined which reports should be considered adequate for general assessment of
HAP emissions from combustion turbines. These review criteria are included in
Appendix C. When possible, pertinent information identified as missing from test
reports was obtained by contacting the tested facilities. Only those source test data
considered appropriate for use in evaluating HAP emissions were used to calculate
emission factors.
B.	Criteria to Include Emission Test Data in Baseline Emissions
The CTWG identified a subset of combustion turbine emission tests from the ICCR
Emissions Database to develop the baseline emission factors for this cost-effectiveness
analysis, based on the following criteria:
1.	Because the baseline emissions estimate is to be done only for natural gas,
emission factors were included only from tests of combustion turbines
firing natural gas. [42 of the 70 test reports in the database are for natural
gas.]
2.	Only test reports that were judged to be complete and to have met quality
assurance criteria were included. [Of the 42 tests for natural gas, 8 reports
were not complete or did not meet QA\QC criteria.]
3.	Because combustion turbines typically operate near full load, emission
factors were extracted only for combustion turbine tests that were
5

-------
conducted at above 80% of rated load. [Of the 42 tests for natural gas, 11
reports were conducted at less than 80% rated load.]
A list of the tests excluded based on the above criteria is provided in Appendix D.
C. Emission Factors for Baseline HAP Emissions
For those test reports in the ICCR Emissions Database that met the criteria discussed
above, emission factors were included in this cost-effectiveness analysis for those HAPs
measured at concentrations above the test method's detection limit in at least one run.
Therefore, none of the emission factors are based solely on non-detects. This criterion is
consistent with the ICCR Testing and Monitoring Work Group's recommendations that
regulatory decisions should not be based solely on non-detects (ICCR Testing and
Monitoring Work Group, 1997).
For natural gas-fired turbines, nine HAPs were measured above the detection limits in at
least one run. Both the highest emission factor and the average emission factor were used
for the base case analysis. The emission factors are presented in Table 1. Baseline
annual emissions for each model turbine were calculated using these emission factors.
The heat input was calculated by converting the model turbine rating (MW) to MMBtu/hr
and dividing by the turbine efficiency, assumed to be 35%. The baseline annual
emissions were then calculated using the heat input (MMBtu/hr), the emission factor
(lb/MMBtu), and the annual operating hours (hr/yr). The baseline emissions
(megagrams/year) for each model turbine are presented in Table 2. [Note: The emission
estimates used in this analysis are presented as emissions at the stack outlet. The
emissions estimates do not address ambient air dispersion of the pollutants, nor ground-
level concentrations.]
6

-------
Table 1. HAPs Emission Factors for the Base Case Analysis
Pollutant
Highest Emission Factor
Average Emission Factor
Test
(Ib/MMBtu)
(Ib/MMBtu)
No. of Tests
Formaldehyde
Test 316.1.1
5.61 E-03
7.13E-04
22 Tests
Toluene
Test 28
7.60E-04
1.42E-04
7 Tests
Acetaldehyde
Test 11
3.50E-04
9.12E-05
7 Tests
Xylenes
Test 18
1.20E-04
4.59E-05
5 Tests
Ethylbenzene
Test 18
4.10E-05
4.10E-05
1 Test
Benzene
Test 315.1
3.91 E-05
1.03E-05
11 Tests
PAHs
Test 7
7.32E-06
2.23E-06
4 Tests
Acrolein
Test 18
6.08E-06
5.49E-06
2 Tests
Naphthalene
Test 7
3.31 E-06
1.46E-06
3 Tests
Source: ICCR Emissions Database for Combustion Turbines
7

-------
Table 2. Baseline Emissions (Mg/yr) for Each Model Turbine
Baseline Emissions (Mg/yr)-- Highest Emission Faetor
Model Turbine
Formsildchvde
Toluene
Aeetsildehvde
Xvlenes
Fthvlbcn/cne
Ben/ene
PAHs
Acrolein
iNsiphthsilcnc
Total IIAl's
2
170 MW
33.810
4.580
2.109
0.723
0.247
0.236
0.044
0.037
0.020
41.806
1
85.4 MW
16.984
2.301
1.060
0.363
0.124
0.118
0.022
0.018
0.010
21.001
7
39.6 MW
7.876
1.067
0.491
0.168
0.058
0.055
0.010
0.009
0.005
9.738
9
27 MW
5.370
0.727
0.335
0.115
0.039
0.037
0.007
0.006
0.003
6.640
15
9 MW
1.790
0.242
0.112
0.038
0.013
0.012
0.002
0.002
0.001
2.213
13
3.5 MW
0.696
0.094
0.043
0.015
0.005
0.005
0.001
0.001
< 0.001
0.861
17
1.13 MW
0.225
0.030
0.014
0.005
0.002
0.002
< 0.001
< 0.001
< 0.001
0.278
Baseline Emissions (Mg/yr) — Average Emission Factor
Model Turbine
Formsildchvde
Toluene
Aeetsildehvde
Xvlenes
Ftlivl benzene
Benzene
PAHs
Acrolein
Niiphthiilene
Totiil IIAl's
2
170 MW
4.297
0.856
0.550
0.277
0.247
0.062
0.013
0.033
0.009
6.344
1
85.4 MW
2.159
0.430
0.276
0.139
0.124
0.031
0.007
0.017
0.004
3.187
7
39.6 MW
1.001
0.199
0.128
0.064
0.058
0.014
0.003
0.008
0.002
1.478
9
27 MW
0.682
0.136
0.087
0.044
0.039
0.010
0.002
0.005
0.001
1.008
15
9 MW
0.227
0.045
0.029
0.015
0.013
0.003
0.001
0.002
< 0.001
0.336
13
3.5 MW
0.088
0.018
0.011
0.006
0.005
0.001
< 0.001
0.001
< 0.001
0.131
17
1.13 MW
0.029
0.006
0.004
0.002
0.002
< 0.001
< 0.001
< 0.001
< 0.001
0.042
8

-------
D. Complicating Factors
The emission factors used for the base case cost-effectiveness analysis, as presented in
Table 1, represent a necessary simplification of actual HAP emissions which could be
expected in the existing population of combustion turbines in the United States. The
following complicating factors would change the baseline emissions of certain
combustion turbines in some cases:
1.	The use of the highest HAP emission factors reported tends to
overestimate HAP baseline emissions.
2.	For the "highest" case, the highest HAP emissions factors for each
pollutant were used. It has not been shown that all these "highs" would
occur simultaneously from a combustion turbine. In fact, it is not likely
that all the "highs" for all pollutants would occur simultaneously.
Therefore, total HAP emissions are overstated in the case where the
highest emission factor from all the tests is used for each HAP.
3.	HAP emissions may be different for combustion turbines using fuels other
than natural gas.
4.	HAP emission factors used in this base case analysis tend to overestimate
HAP emissions for uncontrolled turbines, since a significant portion of the
emissions tests in the ICCR Emissions Database for natural gas-fired
turbines were conducted on units that use steam or water injection to
reduce NOx emissions, and steam or water injection may result in
increased HAP emissions due to the cooling of the combustion process.
5.	For some pollutants there are very few emissions test reports available. In
those cases where emission averages rely on very few tests, it is unclear
whether the resulting emission factor is representative of the turbine
population.
6.	The baseline emissions included in this analysis may underestimate annual
HAP emissions from turbines that operate at less than 80% load, since the
emission factors included in this base case analysis do not include the
higher emission rates that may occur when turbines are operated at low
loads.
9

-------
IV. Oxidation Catalyst Costs
The CTWG obtained information on the costs of acquiring, installing, and operating
oxidation catalysts for HAPs reduction on combustion turbines from the following
sources:
•	Quotes provided to EPA by catalyst vendors
•	Costs gathered by the Gas Research Institute (GRI)
•	Estimates provided by Work Group members
The methodology to estimate the total annual costs for oxidation catalysts was obtained
from the EPA "OAQPS Control Cost Manual" (EPA, 1990). The OAQPS methodology
provides generic cost categories and default assumptions to estimate the installed costs of
control devices. The CTWG relied on the OAQPS methodology to develop the cost-
effectiveness analysis because the Work Group understands that this is the methodology
that EPA has used in the past to assess cost-effectiveness. The GRI study (Ferry et al.,
1998) also relied on the OAQPS methodology.
The OAQPS cost manual requires direct cost inputs for certain key elements, such as
control device capital costs, and then relies on default assumptions (percentages of the
direct cost inputs) to estimate other costs, such as installation. The following sections
describe the direct cost inputs into the OAQPS methodology and the costs estimated
using the OAQPS default assumptions. A printout of the spreadsheet used to estimate
costs is presented as Appendix E.
The OAQPS manual uses five cost categories to describe the annual incremental cost
incurred by installing a control device, such as an oxidation catalyst:
•	Purchased Equipment Costs (PEC) include the capital cost of the
catalyst and auxiliary equipment, and the cost of instrumentation, sales
tax, and freight.
•	Direct Costs for Installation (DCI) are the construction-related costs
associated with installing the catalyst.
10

-------
•	Indirect Costs for Installation (ICI) include expenses related to
engineering and start up.
•	Direct Annual Costs (DAC) include catalyst replacement and disposal
costs and the annual increases in utilities and operating and maintenance
costs.
•	Indirect Annual Costs (IAC) are the annualized cost of the catalyst
system and costs due to tax, overhead, insurance and administrative
burdens.
The cost used in the cost-effectiveness calculation is the total annual cost, which
is the sum of the DAC and IAC.
A.	Cost Inputs
The CTWG developed cost estimates for the following inputs:
•	Capital cost of the oxidation catalysts
•	Capital cost of the catalyst housing
•	Contingency for capital costs
•	Catalyst life and equipment life
•	Catalyst disposal costs
•	Interest rate for capital recovery
•	Direct annual operating & maintenance costs
•	Fuel penalty costs
•	Annual compliance test costs
A description of the each cost input is provided below.
Capital cost of the oxidation catalysts
The CTWG used cost estimates from Engelhard, a catalyst vendor, for six turbine
exhaust flows ranging from 28.4 lb/sec to 984.0 lb/sec to estimate the capital cost
of the oxidation catalysts. The Engelhard costs were based on an oxidation
catalyst that would achieve 90% CO conversion efficiency and 1" pressure drop
across the catalyst panels (not total system pressure drop) and include the cost of
11

-------
an internal support frame and catalyst modules. Regression analysis on these cost
data provided by the vendor suggested that there is a nearly linear relationship
between catalyst cost and exhaust flow rate (r2 = 0.993, when Catalyst
cost=1541.8*(lb/sec)+102370). In estimating catalyst costs for the seven model
turbines, the CTWG relied on the equation based on the Engelhard cost quotes,
where cost is a function of turbine exhaust flow. Additional cost information
reviewed by the CTWG is discussed in complicating factors.
Capital cost of the catalyst housing
The capital cost of the catalyst housing was estimated as 30% of the total cost of
the catalyst system (the catalyst plus housing). This estimate is based on
estimates provided orally by catalyst vendors. The CTWG contacted catalyst
installers to get additional information on the costs for catalyst housings, but the
data was not made available in time to include it in the base case analysis.
Contingency
A contingency of 10% of the sum of the purchased equipment costs, direct costs
of installation, and indirect costs of installation was incorporated in the base case
analysis. The budgeted contingency would cover costs associated with equipment
redesign and modifications, cost escalations, and delays in start-up. The OAQPS
Control Cost Manual recommends a 3% contingency. However, the CTWG
agreed that a contingency of at least 10 percent would be appropriate for the base
case analysis since the analysis is based on a preliminary vendor quote, not a
guaranteed quote. Based on CTWG experience, a contingency factor of 25
percent DCI and ICI (direct and indirect installation costs) is budgeted in the early
planning stages of a project and a contingency factor of at least 10 percent is
budgeted once the project is under contract.
Catalyst life and equipment life
For the base case, the lifetime of purchased equipment was assumed to be fifteen
years, except for the catalyst. Two scenarios were used for the catalyst life: the
12

-------
vendor guaranteed life (three years) and the "typical" life (six years) reported by
catalyst vendors and users. The guaranteed life of the catalyst was used by EPA in
the cost-effectiveness analysis for a passive catalytic device (non-selective
catalytic reduction, NSCR) in the Alternative Control Techniques (ACT)
document for reciprocating internal combustion engines (EPA, 1993b). In the
Turbine ACT document, EPA used 5 years as the catalyst life for Selective
Catalytic Reduction (SCR) (EPA, 1993a). The Turbine ACT did not specify
whether the catalyst life was guaranteed life or "typical" life for SCR. However,
in general, EPA prefers to rely on the useful life of equipment for cost-
effectiveness calculations. The CTWG determined that the base case should
evaluate the costs using both the guaranteed life and the typical life to account for
the uncertainty regarding the long-term performance of oxidation catalysts.
Further discussion of the issues related to catalyst life are discussed as
complicating factors.
The cost of catalyst replacement is annualized by applying a capital recovery
factor based on the catalyst lifetime and interest rate to the cost of the oxidation
catalyst only (based on the Engelhard formula).
Catalyst Disposal Costs
For the base case analysis, costs for catalyst disposal were limited to the freight
charge associated with shipping the spent modules back to the vendor. Based on
the experience of CTWG members, catalyst vendors do not charge for catalyst
disposal since the vendors can recover the noble metals from the spent catalysts.
Interest Rate for Capital Recovery
An interest rate of 7 percent was used in the base case to calculate capital
recovery. The EPA Co-Chair of the ICCR Economics Work Group recommended
this interest rate for the cost-effectiveness analysis.
13

-------
Direct annual operating and maintenance costs
Operating labor costs were estimated using a factor of $25 per hour operating
labor and an estimate of two hours per day incremental labor. The labor costs
cover costs for operator duties likely to result from installing an oxidation catalyst
and complying with MACT. Those duties include 1) inspection of the continuous
parameter monitoring device, 2) collection and review of continuous parameter
monitoring data, 3) inspection of the control device, and 4) recordkeeping and
reporting assumed to be required by the MACT standard. In developing the labor
estimates, the CTWG reviewed the EPA estimates for labor for NSCR for
reciprocating internal combustion engines and for SCR for turbines included in
the Alternative Control Techniques (ACT) documents (EPA, 1993a and 1993b).
The CTWG agreed that the labor estimates for NSCR would more closely
approximate the labor associated with an oxidation catalyst, since NSCR is
essentially a passive catalytic device, like oxidation catalysts. The CTWG agreed
that labor costs for SCR for turbines would be greater than the labor costs for
oxidation catalysts, since SCR may require frequent inspection and adjustment of
the ammonia feed system. Maintenance costs, including labor and materials, were
estimated as 10% of the total purchased equipment cost, based on the ACT
formula for NSCR. Maintenance costs cover catalyst washing (with water),
maintenance of monitoring equipment, and labor for catalyst replacement
(including removal and return of old catalyst and installation of replacement).
Fuel penalty costs
Increased pressure drop in the exhaust of a gas turbine will impact both heat rate
and power output. For the base case analysis, fuel penalty costs are included to
compensate for the increased heat rate as a result of the increased exhaust
backpressure on the turbine that results from installing an oxidation catalyst. The
fuel penalty is assessed as the cost of increased fuel, which is calculated by
assuming a heat rate increase of 0.105% per inch of pressure drop (measured in
inches of water column) and estimates of $2 per MMBtu and a 9,000 Btu/hp-hr
baseline. The heat rate increase of 0.105% was drawn from the GRI study. The
14

-------
CTWG agreed that 0.105% is a very low estimate of the heat rate increase
anticipated and most turbines would have higher increased heat rate due to
backpressure from the catalyst. Other estimates of the heat rate increase are
discussed in the complicating factors portion of this section. The estimate of $2
per MMBtu for natural gas was drawn from the GRI study. The CTWG agreed
that this estimate is low compared to market value of natural gas at this time. The
estimate of increased exhaust backpressure on the turbine from the catalyst was
based on an assumption that the total pressure drop associated with the catalyst
system is solely the pressure drop across the catalyst panels. The CTWG agreed
that the total pressure drop would be higher than the pressure drop across the
catalyst panels due to the pressure drop associated with the inlet and outlet
ductwork for the catalyst system. Therefore, the increase in the exhaust
backpressure and, therefore, the fuel penalty costs resulting from the increase in
exhaust backpressure are understated in the base case analysis.
The Turbine World Handbook indicates that exhaust backpressure may result in a
loss of power. The costs for loss of power were not included in the base case
quantitative analysis. These costs would increase the cost of control beyond the
base case costs presented in this paper. The costs for loss of power are discussed
in the complicating factors portion of this section.
Annual Compliance Test Costs
Costs to perform one annual emissions compliance test are included in the base
case. The costs for this annual test are estimated at $5,000. The costs were
estimated based on an assumption that no continuous emissions monitoring data
would be required in a MACT standard for combustion turbines. Instead, it was
assumed that the MACT would require continuous monitoring for an operating
parameter, such as temperature at the catalyst, along with an annual emissions
test. The costs also were based on an assumption that a surrogate criteria
pollutant can be measured and that HAPs would not be speciated.
15

-------
B. Costs Estimated by OAQPS Control Cost Manual
The methodology outlined in the OAQPS Control Cost manual was used by the CTWG
to estimate costs for the following:
•	Capital cost for instrumentation (continuous parameter monitor)
•	Sales tax for equipment purchases
•	Freight for equipment purchases
•	Direct installation costs (DCI), including foundations & supports, handling
& erection, electrical, piping, insulation for ductwork, and painting.
•	Indirect installation costs (ICI), including engineering, construction and
field expenses, contractor fees, start-up, and performance tests.
•	Indirect annual costs (IAC), including annualized equipment costs,
overhead, administrative costs, property taxes, and insurance.
A description of the methodology to estimate these costs is provided below.
Costs for instrumentation, taxes and freight are estimated by applying factors from the
OAQPS cost manual to the capital cost of the catalyst and auxiliary equipment. These
costs (catalyst capital cost, instrumentation, taxes, and freight) are then summed to
estimate the total Purchased Equipment Costs (PEC). The components of the DCI
(foundations and supports, erection and handling, electrical work, piping, painting and
insulation) are then calculated by applying OAQPS cost manual factors to the PEC.
Likewise, the components of the ICI (engineering, construction and field expenses,
contractor fees, start-up, and initial performance test) are also calculated by applying
factors to the PEC.
Indirect Annual Costs (IAC) are the annualized cost of the catalyst housing and the costs
for overhead, administrative tasks, property taxes, and insurance. The equipment costs
are annualized by applying a capital recovery factor (based on the equipment life, 15
years, and interest rate) to the sum of the direct and the indirect equipment costs,
excluding the cost of the catalyst modules. The cost of the catalyst modules is considered
a direct annual cost (DAC), and is annualized separately. Factors applied to the sum of
16

-------
the direct and indirect equipment costs (including contingency) are used to estimate the
overhead, administrative costs, property taxes, and insurance.
C. Summary of Base Case Cost Estimates
Table 3 presents the range of costs estimated for the seven model turbines included in the
base case cost-effectiveness analysis. The costs for each model turbine are presented in
Appendix E. The highest annual costs are for the largest model turbine and the lowest
annual costs are for the smallest model. The $/MW are lower for the larger model
turbines and higher for the smaller model turbines.
Table 3. Range of Costs Estimated for Seven Model Turbines
Cost Category
Costs for 3-Year Catalyst Life*
Costs for 6-Year Catalyst Life*
Total Capital Cost
$360,000 -
$4,800,000
$360,000 -
$4,800,000
Direct Annual Cost
$96,000 -
$980,000
$74,000 -
$680,000
Indirect Annual Cost
$65,000 -
$700,000
$65,000 -
$700,000
Total Annual Costs
(DAC + IAC)
$160,000 -
$1,700,000
$140,000 -
$1,400,000
*Costs are rounded.
D. Complicating Factors
This section presents the views of the CTWG with regard to factors that complicate the
estimation of the costs of acquisition, installation, and operation of oxidation catalyst on
combustion turbines. For discussion, these complicating factors are divided into five
categories:
•	factors related to the cost of acquiring the oxidation catalyst,
•	costs associated with site installation complications,
•	costs associated with performance testing,
•	complicating factors associated with increased exhaust backpressure, and
•	costs associated with compliance monitoring.
17

-------
Factors Complicating the Estimation of Catalyst Acquisition Costs
The catalyst costs used in this base case analysis are based on a formula that was
derived from one vendor's cost quotes for six different sizes of combustion
turbines. The vendor's cost quotes covered a range of turbine sizes that is similar
to the turbine sizes represented in the seven model turbines used in this cost-
effectiveness analysis. Exhaust flow rates for the vendor's cost quotes ranged
from 28.4 lb/sec to 984 lb/sec, while exhaust flow rates for the seven model
turbines ranged from 14.2 lb/sec to 986 lb/sec. The formula developed by the
CTWG for this cost-effectiveness analysis represents a necessary simplification of
the vendor's cost quotes to facilitate estimating costs for the seven model turbines
used in this analysis.
The CTWG had cost estimates for oxidation catalysts available from two other
sources: 1) cost estimates provided by Mr. Marvin Schorr of General Electric
(Schorr, 1998), and 2) cost estimates included in the GRI cost study (Ferry et al.,
1998). Cost estimates were provided by General Electric for two large turbines
(exhaust flow rates of 400 lb/sec and 1200 lb/sec). The formula calculated using
the General Electric cost estimates is (0.85*(568.75*Exhaust Flow Rate (lb/hr)
+172,500). For small turbines, the costs estimated using the General Electric
formula are higher than the costs used in this base case analysis. For example, the
General Electric formula estimates $153,490 for the catalyst for a 1.13 MW
turbine, while the costs used in this base case analysis are $105,624. For a 3.5
MW turbine, the costs are similar, $166,446 estimated using the General Electric
formula and $165,584 used in this analysis. For larger turbines, the costs
estimated using the General Electric formula are lower than the costs used in this
base case analysis. The differences in the costs estimated using the two different
approaches increase with turbine size. For the 170 MW turbine, the General
Electric formula estimates the cost of the catalyst as $623,294, while $1,622,585
was used in this cost-effectiveness analysis. [Note: the quote provided by
Engelhard for a 170 MW turbine, exhaust flow 984.01b/sec was $1,550,000.] The
CTWG agreed not to use the General Electric cost estimates for this base case
18

-------
analysis for the following reasons: 1) cost estimates were provided only for two
large turbines, and 2) the costs seemed to underestimate the costs when compared
with the quotes received directly from a catalyst vendor.
The CTWG also reviewed the cost estimates included in the GRI study. In that
case, GRI used cost quotes provided by two catalyst vendors for a 6,000
horsepower turbine. Vendors provided cost quotes for a range of VOC control
estimates: 95 percent, 50 percent, 35 percent, and 22 percent. In comparing the
cost quote in the GRI study for 95 percent VOC control and 98 percent CO
control, the CTWG noted that the costs were similar to the costs for a 6,000 hp
turbine estimated using the formula in this base case (assuming 90 percent CO
control) — $204,500 in the GRI study, and $206,796 using the base case formula.
The CTWG decided not to use the GRI costs for this analysis because there was
insufficient information to develop a reliable cost formula that could be applied to
a wide range of turbine models, ranging in size from 1.13 MW to 170 MW.
The CTWG notes that vendor quotes that have been obtained are essentially for
CO oxidation catalysts. As noted above, available emissions data indicates that
CO/VOC oxidation catalysts should reduce organic HAP compounds. However,
the CTWG is not aware of any actual industry experience in the acquisition of an
oxidation catalyst specified to achieve a percentage reduction of formaldehyde, or
the other HAPs. In the absence of such experience, the cost estimate for an
oxidation catalyst designed to reduce organic HAPs from combustion turbines is
uncertain. Uncertainty about the estimated cost for a HAP reduction catalyst is
increased when considering that oxidation catalysts would be required for fuels
other than natural gas. Oxidation catalysts for oil fired turbines may have to be
formulated differently than for gas fired turbines, and may have different lifetime
and degradation characteristics.
Another key uncertainty in estimating oxidation catalysts costs is the assumption
regarding catalyst life. Clearly, a catalyst that can be relied upon to function for
19

-------
many years will have lower annual costs than a catalyst that must be replaced
more often. The issue of catalyst lifetime includes estimating the probability of
complete failure of the catalyst, and also estimating the degradation of catalyst
performance over time.
The CTWG notes that there may be a difference between the expected useful life
of an oxidation catalyst, and the period of the vendor's performance guarantee.
This raises the question of which period should be used in calculating cost-
effectiveness. As noted in another section, the CTWG has elected to present a
number of cost-effectiveness estimates based on different assumptions about
catalyst life and performance.
Limited information was available to the CTWG on the life of the catalyst.
Information from an emissions test conducted by GRI on a ten-year-old CO
oxidation catalyst indicates that performance can degrade when the catalyst is
used for an extended period of time (10 years in that case). The GRI test is
described under Section V of this paper. Further information is not available that
would allow the CTWG to estimate the expected rate of oxidation catalyst
performance degradation, or the effect of maintenance (such as catalyst washing)
on catalyst life. According to catalyst vendors, the degradation of catalyst
performance over time is not linear. The CTWG has not obtained any
information that would allow the Work Group to estimate the expected rate of
performance degradation over the life of the catalyst.
Costs associated with site installation complications
Costs for retrofit complications were not available for the base case analysis.
Site-specific factors can have a major impact on the cost of retrofitting a catalyst
control system to an existing turbine installation. In general, the heat recovery
unit (if one exists) must be altered, ductwork and piling supports must be added,
and piping, electrical conduits and wiring must be lengthened. Some turbine
installations have enough space between the turbine exhaust and the heat recovery
20

-------
unit to add the catalyst system. In cases where space is very limited, the heat
recovery unit might have to be removed and replaced with a new vertical style
unit. One of the work group members provided retrofit costs for adding a catalyst
system to an ABB Type 11 gas turbine (gas flow = 580 lb/sec) (Allen, 1998a and
1998b). The retrofit costs totaled about $800,000, including $100,000 for
ductwork. The cost of down time is also site specific. In the case described
above, the cost cited by the work group member for down time was about $3.5
million based on a 35 day outage, a power sales price of $35/MWh, and a steam
cost $4.5/thousand pounds of steam (Allen, 1998a).
Costs Associated with Performance Testing
Costs for performance testing were included in the base case quantitative analysis
in accordance with the OAQPS Control Cost Manual. The costs for performance
testing are estimated as 0.01% of the Purchased Equipment Costs (PEC). For the
170 MW turbine, $27,000 was calculated as the performance test costs using the
OAQPS formula. For the 1.13 MW turbine, $2,095 was calculated as the
performance test costs using the OAQPS formula. The CTWG agreed that the
costs for stack emissions testing would be fixed, regardless of turbine size. The
costs estimated for performance testing may have been underestimated for the
base case analysis, especially for the small model turbines.
Complicating Factors Associated with Increased Exhaust Backpressure
For the base case quantitative analysis, fuel penalty costs were estimated
assuming a 0.105% heat rate increase per inch of pressure resulting from
installation of a catalyst system. The CTWG agreed that 0.105% is a very low
estimate of the heat rate increase. The Gas Turbine World 1997 Handbook
provides rough rule of thumb estimates of heat rate increase and power loss per
inch pressure drop (Gas Turbine World 1997). For aeroderivative turbines, the
Handbook indicates that every 4 inches outlet loss will increase heat rate 0.7%
(0.175%) per inch) and reduce power output 0.7%. For heavy frame turbines, the
Handbook indicates that every 4 inches outlet loss will increase heat rate 0.6%
21

-------
(0.15% per inch) and reduce power output 0.6%. Therefore, the heat rate increase
due to increased pressure drop is understated in the base case analysis.
To estimate pressure drop for the base case quantitative analysis, it was assumed
that the total pressure drop associated with the catalyst system is solely the
pressure drop across the panels. The CTWG agreed that the total pressure drop
would be higher than the pressure drop across the catalyst panels alone due to the
inlet and outlet ductwork. Therefore, the operating costs associated with the
increase in exhaust backpressure are understated in the base case analysis. The
fuel penalty costs associated with backpressure may be significantly higher when
a more realistic estimate of the catalyst system pressure drop is used.
In addition, implementing oxidation catalyst control may result in a reduction in
turbine power output caused by increased exhaust backpressure on the engine.
The costs associated with the power loss depend on site-specific factors (e.g.,
value of lost product or capital and annual costs for equipment required to make
up for the power loss). The increase in exhaust backpressure results in a loss of
power sales if the unit is operating at full load. One of the work group members
provided information on the loss in annual sales at different selling prices for
electrical power (Allen, 1998b). For a GE Frame 7 turbine, the annual cost (i.e.,
lost sales) per inch of water pressure drop may be estimated using the following
equation:
Annual Cost ($/inch) = 1,160 * Power Value ($/MWh) +100
For this example turbine unit, if electricity can be sold for $40 per MWh, the
annual cost per each additional inch of water pressure drop caused by the catalyst
would equal $46,500.
These costs were not incorporated into the base case analysis. The cost associated
with power loss would increase the costs for the control system.
22

-------
Costs Associated with Compliance Monitoring
If the MACT would require speciated HAP emissions test data, the costs for the
annual compliance test would increase significantly. Also, if compliance tests
must be conducted more frequently than annually, the costs would increase.
V. Performance of Oxidation Catalysts in Reducing HAP Emissions
Oxidation catalysts have been installed on combustion turbines for the purposes of
controlling emissions of carbon monoxide (CO) and some volatile organic compounds
(VOC). The catalyst is designed to promote the oxidation of hydrocarbon compounds to
carbon dioxide (CO2) and water (H20). It is expected that existing catalysts similar to
those in use for CO and VOC control may oxidize organic HAPs.
In order to estimate the quantitative performance of an oxidation catalyst the CTWG
evaluated two emissions test reports and reviewed engineering estimates of potential
oxidation catalyst performance.
A. HAP Emissions Test Data for Oxidation Catalysts
At present, no HAP emissions tests in the ICCR Emissions Database include before and
after testing of a combustion turbine with an oxidation catalyst. Emissions test data on the
performance of oxidation catalysts should be collected during the CTWG testing
campaign.
The CTWG identified two existing emission test reports that provide some information
on the performance of oxidation catalysts in reducing HAP emissions. The two emission
tests are still being evaluated and may be included in the database after review. One test
was conducted by the Gas Research Institute(GRI), in cooperation with the American
Petroleum Institute (API) and Southern California Gas (SoCal), in March 1998, on a
combustion turbine using a passive oxidation catalyst system, similar to the catalyst used
23

-------
for this base case cost-effectiveness evaluation. A summary of this test has been
provided to the CTWG and the complete test data will be provided to EPA when it is
available (Gundappa, 1998). The complete test report will be required by EPA and the
report will have to undergo review prior to being included in the ICCR Emissions
Database. The oxidation catalyst installed on this turbine is a precious metal catalyst,
similar to the catalyst technology used as the basis for this cost-effectiveness analysis.
This type of oxidation catalyst may be used over a temperature range of 450°F to 1500°F
(Chen et al., 1993).
The second test was submitted to EPA for a new catalytic oxidation control system,
called SCONOx™ (Bell and Finken, 1997). Although the SCONOx™ system relies on
oxidation to reduce hydrocarbons, such as CO, or HAPs, such as formaldehyde, the
SCONOx™ catalyst is a more complicated control system than the oxidation catalyst used
for this base case cost-effectiveness evaluation. SCONOx™ may be operated over a
temperature range of 300°F to 700°F (Goal Line Environmental Technologies, LLC).
The cost and cost-effectiveness values presented in this paper were not based on costs for
the SCONOx™ system. However, the CTWG included a discussion of the source test
results as an indicator of the types of emission reductions that may be achievable for
systems that rely on oxidation to reduce HAP emissions. A description of the SCONOx™
system is provided in Appendix F. The results from these two emissions tests are
discussed below.
GRI/API/SoCal Test
The GRI/API/SoCal testing was conducted in March 1998. GRI, API, and SoCal
added the emissions test to an existing emissions testing program in order to
provide data to the CTWG on the performance of oxidation catalysts. Some
members of the CTWG and EPA representatives witnessed the GRI/API/SoCal
test. The test was performed on a 20 MW GE LM2500 turbine equipped with a
Johnson Matthey CO oxidation catalyst. Three load conditions were tested,
including full load (typical) and part loads (88% and 70% of rated load).
Concentrations of HAPs, including formaldehyde, were measured before and after
24

-------
the oxidation catalyst. HAP and CO measurements were conducted with Fourier
transform infrared (FTIR) sampling upstream and downstream of the oxidation
catalyst. Aldehydes also were measured with the California Air Resources Board
(CARB) Method 430, which relies on an aqueous 2,4-Dinitrophenylhydrazine
solution. Complete results of the test were not available in time to incorporate
them into the ICCR Emissions Database. However, the CTWG has been provided
a summary of the results (Gundappa, 1998). Based on FTIR, formaldehyde
emissions upstream of the catalyst were in the approximate range of 400 to 460
parts per billion by volume (ppbv) and CO emissions upstream of the catalyst
were in the range of 10 to 17 parts per million by volume (ppmv). Both
formaldehyde and CO emissions increased as the load decreased. With FTIR, the
reduction in emissions across the oxidation catalyst was on the order of 10 to 30
percent for formaldehyde and 25 to 33 percent for CO, with the highest reduction
at the lowest load condition. CARB 430 results did not agree with the FTIR data.
In some cases, the CARB 430 results indicated that levels of aldehydes
(formaldehyde and acetaldehyde) increased after the catalyst.
SCONOx™ Test
A unit equipped with a SCONOx™ catalyst system was tested on March 14, 1997,
by Delta Air Quality Services (Bell and Finken, 1997). Samples were collected at
the inlet to the catalyst and at the exhaust from the cogeneration unit (turbine
exhaust stack) and analyzed for the following three HAPs: formaldehyde,
acetaldehyde, and benzene. Formaldehyde and acetaldehyde reportedly were
reduced by 97% and 94%, respectively, based on the catalyst inlet and turbine
exhaust concentrations. No conclusion regarding the control efficiency for
benzene could be drawn since the levels before and after the catalyst were both
very low and within 0.05 parts per billion of each other.
A subgroup of the CTWG reviewed the SCONOx™ report in greater detail to
determine if the data from this test should be included in the emissions database.
The subgroup was concerned with the accuracy of the catalyst inlet concentrations
25

-------
measured during the test since isokinetic sampling was not conducted nor was a
multi-point probe used to collect the samples. However, the catalyst inlet
concentrations were consistent with other source tests involving the same model
turbine (GE LM 2500), using water injection. Also, even if the catalyst inlet
concentrations were one-half to one-third of the average concentration measured
during the source test, the efficiency of the SCONOx™ would still exceed 90% for
formaldehyde. Therefore, the subgroup decided to support inclusion of the data
from this test in the emissions database, with the caveat that EPA may want to
retest this unit to address some of the specific concerns identified during the
subgroup's review.
Based on a review of the two emissions tests available, the CTWG concluded that
organic HAPs, such as formaldehyde and acetaldehyde, may be reduced using after-
treatment controls that rely on catalytic oxidation. The Work Group also concluded that,
in some cases, a high percent reduction may be possible for certain pollutants. However,
the CTWG noted that the limited data available is not sufficient to draw conclusions
about the achievability of high emission reductions over the life of catalytic devices. In
addition, the CTWG noted that although there is some data that suggests catalysts
degrade over time, the rate and the extent of the degradation cannot be determined based
on the limited data.
B. Engineering Estimates of HAP Reduction Performance for
Oxidation Catalysts
The CTWG reviewed information available in the literature on the HAP reduction
performance of oxidation catalysts on organic HAPs, such as formaldehyde. In
particular, the Work Group reviewed an article prepared by Engelhard, the catalyst
vendor that supplied the cost quotes for this base case cost-effectiveness analysis (Chen
et al., 1993). In the article, Engelhard notes that oxidation catalysts for combustion
turbines are typically designed to achieve between 80 and 95 percent CO removal. In
addition, the article indicates the conversion level for each species of hydrocarbon will
26

-------
depend on its diffusion rate in the exhaust gas. In general, larger, heavier molecules will
diffuse more slowly than smaller, lighter molecules. As the size of the hydrocarbon
molecule increases, hydrocarbon conversion decreases due to decreased gas diffusivity.
According to the article, an oxidation catalyst designed for 90 percent CO removal will
achieve 77 percent reduction of formaldehyde, 72 percent reduction of benzene, and 71
percent reduction of toluene. The article notes that the relative conversion rates do not
depend on geometry and that reduction for molecules larger than formaldehyde will be
lower than rates achievable for formaldehyde.
C. Summary of Base Case Performance Estimate
The CTWG has agreed to use two performance values for the base case cost-
effectiveness analysis — 80 percent emissions reduction and 50 percent emissions
reduction. 80 percent emissions reduction is used for both the 3-year and 6-year catalyst
life assumptions. 50 percent emissions reduction is evaluated for a 6-year catalyst life.
The CTWG believes these levels of reduction represent appropriate levels of reduction
for the base case cost-effectiveness analysis, covering both high and moderate levels of
emission reduction. The Work Group relied on the Engelhard engineering estimates for
formaldehyde to select 80% reduction as the catalyst performance in the base case
analysis (77% rounded up to 80%). Although the Engelhard article indicates that
emission reductions for larger molecules, such as PAHs, may be less than the reduction
achieved for formaldehyde, the HAP reduction performance for the base case analysis
was set to 80 percent for all pollutants. The Work Group selected 50% reduction as a
moderate level of emission reduction to examine the sensitivity of the cost-effectiveness
to any significant degradation of the catalyst performance that might occur over time.
Additional emissions test data before and after oxidation catalysts would be necessary to
determine whether the levels of reductions are achievable for combustion turbines,
considering the full range of operating conditions and catalyst degradation.
27

-------
The emission reductions achieved for each model turbine assuming 80 percent reduction
and 50 percent reduction are presented in Tables 4 and 5.
28

-------
Table 4. Emissions Reductions for Each Model Turbine Assuming 80% HAPs Reduction Performance
Emissions Reductions (Mg/yr)— Highest Emission Factor — 80% HAPs Reduction Performance
Model Turbine
Forniiildchvde
Toluene
Aeetsildehvde
Xvlenes
Ftlivl ben/ene
Ben/ene
PAHs
Acrolein
Nil pli tliii lene
Tohil IIAl's
2
170 MW
27.048
3.664
1.687
0.579
0.198
0.189
0.035
0.029
0.016
33.445
1
85.4 MW
13.587
1.841
0.848
0.291
0.099
0.095
0.018
0.015
0.008
16.801
7
39.6 MW
6.301
0.854
0.393
0.135
0.046
0.044
0.008
0.007
0.004
7.791
9
27 MW
4.296
0.582
0.268
0.092
0.031
0.030
0.006
0.005
0.003
5.312
15
9 MW
1.432
0.194
0.089
0.031
0.010
0.010
0.002
0.002
0.001
1.771
13
3.5 MW
0.557
0.075
0.035
0.012
0.004
0.004
0.001
0.001
< 0.001
0.689
17
1.13 MW
0.180
0.024
0.011
0.004
0.001
0.001
< 0.001
< 0.001
< 0.001
0.222
Emissions Reductions (Mg/yr)— Average Emission Factor — 80% HAPs Reduction Performance
Model Turbine
Formsildchvde
Toluene
Aeetsildehvde
Xvlenes
Ftlivl ben/ene
Ben/ene
PAHs
Acrolein
Nil plitliiilene
Tohil IIAl's
2
170 MW
3.438
0.685
0.440
0.221
0.198
0.050
0.011
0.026
0.007
5.075
1
85.4 MW
1.727
0.344
0.221
0.111
0.099
0.025
0.005
0.013
0.004
2.549
7
39.6 MW
0.801
0.159
0.102
0.052
0.046
0.012
0.003
0.006
0.002
1.182
9
27 MW
0.546
0.109
0.070
0.035
0.031
0.008
0.002
0.004
0.001
0.806
15
9 MW
0.182
0.036
0.023
0.012
0.010
0.003
0.001
0.001
< 0.001
0.269
13
3.5 MW
0.071
0.014
0.009
0.005
0.004
0.001
< 0.001
0.001
< 0.001
0.104
17
1.13 MW
0.023
0.005
0.003
0.001
0.001
< 0.001
< 0.001
< 0.001
< 0.001
0.034
29

-------
Table 5. Emissions Reductions for Each Model Turbine Assuming 50% HAPs Reduction Performance
Emissions Reductions (Mjj/yr)— Highest Emission Factor — 50% Reduction Performance
Model Turbine
Formsildchvde
Toluene
Aeetsildehvde
Xvlenes
Ftlivl benzene
Benzene
PAHs
Acrolein
Nil plitliiilene
Tohil IIAPs
2
170 MW
16.905
2.290
1.055
0.362
0.124
0.118
0.022
0.018
0.010
20.903
1
85.4 MW
8.492
1.150
0.530
0.182
0.062
0.059
0.011
0.009
0.005
10.501
7
39.6 MW
3.938
0.533
0.246
0.084
0.029
0.027
0.005
0.004
0.002
4.869
9
27 MW
2.685
0.364
0.168
0.057
0.020
0.019
0.004
0.003
0.002
3.320
15
9 MW
0.895
0.121
0.056
0.019
0.007
0.006
0.001
0.001
0.001
1.107
13
3.5 MW
0.348
0.047
0.022
0.007
0.003
0.002
< 0.001
< 0.001
< 0.001
0.430
17
1.13 MW
0.112
0.015
0.007
0.002
0.001
0.001
< 0.001
< 0.001
< 0.001
0.139
Emissions Reductions (M^/vr)-- Average Emission Factor — 50% HAPs Reduction Performance
Model Turbine
Formsildchvde
Toluene
Aeetsildehvde
Xvlenes
Ftlivl benzene
Benzene
PAHs
Acrolein
N si plithii lene
Totiil IIAPs
2
170 MW
2.149
0.428
0.275
0.138
0.124
0.031
0.007
0.017
0.004
3.172
1
85.4 MW
1.079
0.215
0.138
0.069
0.062
0.016
0.003
0.008
0.002
1.593
7
39.6 MW
0.500
0.100
0.064
0.032
0.029
0.007
0.002
0.004
0.001
0.739
9
27 MW
0.341
0.068
0.044
0.022
0.020
0.005
0.001
0.003
0.001
0.504
15
9 MW
0.114
0.023
0.015
0.007
0.007
0.002
< 0.001
0.001
< 0.001
0.168
13
3.5 MW
0.044
0.009
0.006
0.003
0.003
0.001
< 0.001
< 0.001
< 0.001
0.065
17
1.13 MW
0.014
0.003
0.002
0.001
0.001
< 0.001
< 0.001
< 0.001
< 0.001
0.021
30

-------
D. Complicating Factors
This section presents the views of the CTWG with regard to factors that complicate the
estimation of the performance of oxidation catalysts in the reduction of organic HAP in
the exhaust of combustion turbines.
Uncertainty About the Real World Performance of Oxidation Catalysts for HAPs
As noted earlier in this paper, although there are oxidation catalysts installed on
existing turbines for control of CO and some VOCs, there are not conclusive
emissions data available regarding the HAP reduction performance of those oxidation
catalysts over time. CO catalysts systems in use operate on far higher levels of CO
than the expected concentration of HAPs. The cost-effectiveness estimates used for
this base case analysis are derived from engineering judgement rather than actual
data. It is possible that it may be more difficult than anticipated to achieve a
consistent 80% reduction of HAPs across a real world population of combustion
turbines running under various ambient conditions and operating points.
Differential Performance for Various HAPs
The assumption used in this base case analysis that oxidation catalysts will have the
same HAP reduction performance for all organic HAPs was necessary because there
was insufficient emissions data to estimate HAP reduction performance for specific
species of HAPs. The CTWG is aware that this assumption is incorrect, based on
engineering estimates performed by Engelhard, a catalyst vendor (Chen et al., 1993).
Engelhard indicates that individual HAPs will be oxidized at different rates due to
differences in the size of the hydrocarbons and that the HAP reduction performance
for each HAP will depend on its diffusion rate. In general, larger, heavier molecules
(like PAHs) will diffuse more slowly than smaller, lighter molecules (like CO).
The CTWG notes that the assumptions used in this base case analysis tend to
overestimate HAP reduction efficiencies for HAPs other than formaldehyde,
especially HAPs like PAHs that are larger, heavier molecules.
31

-------
Decreased Catalyst Performance Over Time
This effect was discussed as a part of the evaluation of catalyst life for costing
purposes. A decline in catalytic activity also would impact the performance side of
the equation in that fewer metric tons of HAPs would be removed from the turbine
exhaust. Again, the CTWG does not have sufficient information to estimate the rate
at which catalytic activity would decline in a real-world installation.
VI. Cost-Effectiveness Results
A breakdown of the total HAP reductions achieved for individual pollutants is provided
in Tables 4 and 5. The cost-effectiveness values based on total HAP reductions are
presented in Table 6 for each model turbine. The cost-effectiveness for total HAPs is
provided to more fully demonstrate the benefit achieved in terms of total reduction of
HAPs for the costs required to install oxidation catalysts. Cost-effectiveness for
individual HAPs, calculated as the total annual costs by the mass emissions for each
individual HAP, is presented in Appendix G. The cost-effectiveness for individual
HAPs is presented to show the cost-effectiveness sensitivity for individual HAPs.
In general, the cost per metric ton of reduced HAP emissions is higher for small turbines,
because capital costs, on a per-megawatt basis, are highest for these units and the annual
HAP emissions are low. The costs per metric ton also would increase for small and large
turbines as operating hours decrease because capital costs remain unchanged while
annual HAP emissions are lower.
32

-------
Table 6. Cost-Effectiveness Estimated for Each Model Turbine ~ Base Case Analysis
Cost Effectiveness ($/Mg Total HAPs Reductions*)
Model Plant
Highest EF
Average EF
3-Year Catalyst Life
80% Emissions
Reduction
6-Year Catalyst Life
80% Emissions
Reduction
6-Year Catalyst Life
50%) Emissions
Reduction
3-Year Catalyst Life
80%o Emissions
Reduction
6-Year Catalyst Life
80%o Emissions
Reduction
6-Year Catalyst Life
50% Emissions
Reduction
Model 1 - 85.4 MW Turbine
$69,000
$57,000
$91,000
$450,000
$380,000
$600,000
Model 2 — 170 MW Turbine
$50,000
$41,000
$66,000
$330,000
$270,000
$440,000
Model 7 - 39.6 MW Turbine
$81,000
$67,000
$110,000
$530,000
$440,000
$710,000
Model 9 — 27 MW Turbine
$78,000
$66,000
$100,000
$520,000
$430,000
$690,000
Model 13 - 3.5 MW Turbine
$290,000
$250,000
$400,000
$1,900,000
$1,700,000
$2,600,000
Model 15 — 9 MW Turbine
$150,000
$130,000
$200,000
$1,000,000
$840,000
$1,400,000
Model 17 - 1.13 MW Turbine
$730,000
$630,000
$1,000,000
$4,800,000
$4,100,000
$6,600,000
*Cost-effectiveness values were rounded. Annual costs estimated for each model turbine are presented in Appendix E. HAPs
reductions estimated for each model turbine are presented in Tables 4 and 5. Cost-effectiveness values for individual HAPs are
presented in Appendix G.
33

-------
VII. Conclusions and Recommendations
The CTWG has assessed the various elements that are relevant to estimation of the cost-
effectiveness of oxidation catalysts for control of organic HAPs emitted by combustion
turbines. Base on this assessment the CTWG has reached the following conclusions.
1.	Using a simplified base case, the annual costs associated with installation
and operation of oxidation catalysts for the model turbines ranged from
$160,000 for a 1.13 MW unit to $1,700,000 for a 170 MW unit, assuming
a three-year catalyst life. Annual costs ranged from $140,000 for a 1.13
MW unit to $1,400,000 for a 170 MW unit, assuming a six-year catalyst
life.
2.	Based on quantified estimates of emissions, cost, and percent reduction for
a simplified base case, the cost-effectiveness of oxidation catalysts for
control of total HAPs from combustion turbines ranges from $41,000 per
metric ton for a 170 MW unit to $1,000,000 per metric ton for a 1.13 MW
unit, assuming emission rates based on the highest reported emission
factors for all HAPs. The cost-effectiveness values range from $270,000
for a 170 MW unit to $6,600,000 for a 1.13 MW unit when the average
emission factor is used.
3.	Because of a variety of complicating factors, it is likely that the base case
cost-effectiveness estimated range is lower than the actual cost-
effectiveness which would be exhibited by actual application of oxidation
catalysts to most combustion turbines in the United States. Key
complicating factors include the catalysts life, problems with retrofitting
ducts and the catalyst housing at existing facilities, differential
effectiveness of the catalysts on various HAP compounds, and fuels that
require pre-treatment to avoid fouling the catalyst. In addition, there is
uncertainty regarding the HAPs reduction performance included in this
base case analysis due to the limited emissions test data available to
predict the performance of oxidation catalyst in reducing organic HAP
emissions from combustion turbines. While experience with CO oxidation
catalysts is useful for evaluating the potential HAP reduction performance,
there may be important differences between the costs and performance of
CO catalysts and the costs and performance of catalysts for reduction or
organic HAPs.
Most of the complicating factors that have not been quantified in the numerical estimates
would tend to increase the catalyst costs, or decrease catalyst performance. Because of
this, the CTWG views the base case quantitative estimate reported in this paper as a
34

-------
lower range estimate of the cost-effectiveness of oxidation catalysts for HAPs control on
combustion turbines.
The CTWG recommends that the Coordinating Committee forward this information to
EPA and recommend that EPA consider the information presented in this paper in the
Agency's assessment of above-the-floor MACT options for combustion turbines. This
paper provides reasonable estimates, based on available information, of the costs and the
HAP air emissions reductions that may be achieved with oxidation catalysts. The CTWG
recognizes that EPA may consider other factors, such as non-air quality environmental
impacts, energy requirements, and secondary pollutants (including possible CO/VOC
control), in assessing above-the-floor MACT options.
35

-------
References Cited
Allen, S. 1998a. E-mail to Sims Roy, U.S. EPA, to transmit retrofit cost information
provided by Vogt, August 10, 1998.
Allen, S. 1998b. Memorandum to transmit information regarding power loss/pressure
drop relationship. Submitted to ICCR Combustion Turbine Work Group on July
30, 1998.
Bell, A., and R. A. Finken. 1997. Formaldehyde and Acetaldehyde and Benzene Control
Efficiency at Federal Cold Storage. Report prepared by Delta Air Quality
Services, Orange, CA, April 2, 1997.
Chen, J. M., B. K. Speronello, and R. M. Heck. 1993. "Catalytic Control of Unburned
Hydrocarbon Emissions in Combustion Turbine Exhausts." Air & Waste
Management Association. Paper prepared by Engelhard Corporation, Iselin, New
Jersey, for presentation at the AWMA 86th Annual Meeting & Exhibition,
Denver, Colorado, June 13-18, 1993.
Engelhard. 1998. Facsimile to U.S. EPA, regarding CO catalysts/HAP control, April 27,
1998.
EPA. 1990. OAQPS Control Cost Manual, Fourth Edition. EPA 450/3-90-006. Office of
Air Quality Planning and Standards, Office of Air and Radiation, Research
Triangle Park, NC, January 1990.
EPA. 1993a. Alternative Control Techniques Document — NOx Emissions from
Stationary Gas Turbines. Office of Air Quality Planning and Standards, Office of
Air and Radiation, Research Triangle Park, NC, January 1993.
EPA. 1993b. Alternative Control Techniques Document — NOx Emissions from
Stationary Reciprocating Internal Combustion Engines. Office of Air Quality
Planning and Standards, Office of Air and Radiation, Research Triangle Park,
NC, July 1993.
Ferry, K. R., W. C. Rutherford, and G. S. Shareef. 1998. Preliminary Study of Oxidation
Catalyst Costs Applied to Gas Turbines for Control of Aldehydes. Gas Research
Institute Topical Report GRI-98/0218. Report prepared by Radian International,
LLC, Austin, TX, June 1998.
Gas Turbine World. 1997. Gas Turbine World 1997 Handbook.
Goal Line Environmental Technologies, LLC. Promotional materials regarding the
SCONOx™ Catalytic Absorption System.

-------
Gundappa. M. 1998. "Preliminary Results from Natural Gas-Fired Combustion Turbine
Testing." American Petroleum Institute, Southern California Gas Company, and
Gas Research Institute. Report prepared by Radian International, LLC, Austin,
TX, August 1998.
ICCR Testing & Monitoring Work Group. 1997. "September 1997 TMPWG Guidance
on Interpreting and Using Emissions Database Containing Non-detection Values."
MacDonald, R. J. and L. Debbage. 1997. "The SCONOx™ Catalytic Absorption System
for Natural Gas Fired Power Plants: The Path to Ultra-Low Emissions." Power-
Gen International '97, Dallas, TX, December 9-11, 1997.
Schorr, M. E-mail to U.S. EPA, to provide catalyst costs, May 15, 1998

-------
Appendix A - List of Model Turbines
Model
Plant
No.
Unit
Size
Operating
Hours
Per Year
Heat
Recovery
(YIN)
Existing
Application
(YIN)
Clean
Fuel
(YIN)
Typical Applications
Surrogate
Turbine
Output
MW(ISO)
Ex. Flow
(lbs/sec)
1
Large
8000
Y
Y
Y
existing utility/IPP generating station
GE PG 7121EA
85.4
658
1A
Large
8000
Y
Y
N
existing unit with residual oil fuel
GE PG 7121 EA
85.4
658
1B
Large
8000
Y
Y
Y
existing utility/IPP generating station (duct burner)
GE PG 7121 EA
85.4
658
2
Large
8000
Y
N
Y
new utility/IPP generating station
GE PG 7231 FA
170
986
2A
Large
8000
Y
N
N
new unit with residual oil fuel
GE PG 7231 FA
170
986
2B
Large
8000
Y
N
Y
new utility/IPP generating station (duct burner)
GE PG 7231 FA
170
986
3
Large
2000
N
Y
Y
existing utility/IPP generating station
GE PG 7231 FA
170
986
3A
Large
2000
N
Y
Y
existing utility/IPP station (space constrained)
GE PG 7231 FA
170
986
4
Large
2000
N
N
Y
new utility/IPP generating station
GE PG 7231 FA
170
986
5
Large
500
N
Y
Y
existing utility/IPP peaking unit
GE PG 7121 EA
85.4
658
6
Large
500
N
N
Y
new utility/IPP peaking unit
GE PG 7121 EA
85.4
658
7
Medium
8000
Y
Y
Y
existing industrial power production
GE PG 6561B
39.6
318
7A
Medium
8000
Y
Y
N
existing unit with residual oil fuel
GE PG 6561B
39.6
318
7B
Medium
8000
Y
Y
Y
existing industrial power production (duct burner)
GE PG 6561B
39.6
318
8
Medium
8000
Y
N
Y
new industrial power production
GE PG 6561B
39.6
318
8A
Medium
8000
Y
N
N
new unit with residual oil fuel
GE PG 6561B
39.6
318
8B
Medium
8000
Y
N
Y
new industrial power production (duct burner)
GE PG 6561B
39.6
318
9
Medium
8000
N
Y
Y
existing pipeline compressor/ ind.- mech. drive
GE LM2500
27
178
10
Medium
8000
N
N
Y
new pipeline compressor/ ind. mech. drive
GE LM2500
27
178
11
Medium
500
N
Y
Y
existing utility/IPP peaking unit
GE PG 6561B
39.6
318
12
Medium
500
N
N
Y
new utility/IPP peaking unit
GE PG 6561B
39.6
318
13
Small
8000
Y
Y
Y
existing industrial process plant (food, nat'l gas)
Solar Centaur 40
3.5
41
13A
Small
8000
Y
Y
N
existing landfill operation or residual oil fuel
Solar Centaur 40
3.5
41
13B
Small
8000
Y
Y
Y
existing ind. process plant (duct burner)
Solar Centaur 40
3.5
41
14
Small
8000
Y
N
Y
new industrial process plant (food, nat'l gas)
Solar Centaur 40
3.5
41
14A
Small
8000
Y
N
N
new landfill operation or residual oil fuel
Solar Centaur 40
3.5
41
14B
Small
8000
Y
N
Y
new ind. process plant (duct burner)
Solar Centaur 40
3.5
41
15
Small
8000
N
Y
Y
existing pipeline compressor
Solar Mars T12000
9
83.6
15A
Small
8000
N
Y
Y
existing offshore platform (space constrained)
Solar Mars T12000
9
83.6
16
Small
8000
N
N
Y
new pipeline compressor/offshore platform
Solar Mars T12000
9
83.6
17
Small
200
N
Y
Y
existing emergency power (hospital,university,etc)
Solar Saturn T1500
1.13
14.2
18
Small
200
N
N
Y
new emergency power (hospital, university, etc)
Solar Saturn T1500
1.13
14.2
A-l

-------
Appendix B - Description of ICCR Emissions Database
MEMORANDUM
DATE :
SUBJECT:
TO :
FROM :
March 6, 1998
Documentation on the Combustion Turbines Emissions Database
Combustion Turbines Project File
Ana Rosa Alvarez and Dan Herndon
This memorandum provides a short description of the development of the emissions database for turbines,
including assumptions used in the underlying calculations.
Development of the Emissions Database
The emission test reports were first carefully reviewed and summarized. Facility name, location, testing
company, date of testing, make and model of turbine, manufacturer rating (and units), load, fuel type, application
and control device (for emissions) were entered in a table named "Facilities." Pollutant name, sampling method,
concentrations and units, detection limits and units, % oxygen, fuel factors, exhaust gas flow rates, stack
temperature, fuel heating value and flow rate, % humidity, standard temperature, and pollutant molecular weight
were entered in a table named "Test Data." Emission rates (lb/hr) and emission factors (lb/MMBtu) were also
entered in that table for comparison with the emissions calculated in the database using the pollutant concentrations
for each test run.
Test reports included in the database were identified using the following scheme: numbers from 1 to 99 were
assigned to tests containing only hazardous air pollutants (HAPs), and numbers greater than 100 were allocated for
tests with only criteria pollutants or with both HAPs and criteria pollutants. Exceptions are the reports numbered 10
and 15. These test reports contain both HAPs and criteria pollutant test results. They are numbered as HAPs-only
type reports because criteria pollutant data were identified in these reports after the first version of the database was
posted on the TTN. Test reports containing more than one turbine, multiple load conditions, different fuels, control
device inlet and outlet samples (criteria pollutant data only), or more than three sampling runs were assigned the
same initial number followed by an extension (for example, 1.1 or 1.1.1).
Some of the test reports in the database include an "x" symbol at the end of the test report number (e.g., test
report 8x). The "x" symbol indicates that the test report does not meet the acceptance criteria developed by the
CTWG. The data from these test reports are included in the database for informational purposes only.
B-l

-------
Construction of database reports (i.e., summaries of relevant data) required the complete separation of tests with
HAPs-only data from tests with only criteria pollutant data and tests with both HAPs and criteria pollutant data. The
"Test Data" table was consequently divided into three tables: "Test Data - HAPs," containing all HAP data in the
Test Data table; "Test Data - Criteria Pollutants," containing all criteria pollutant data in the Test Data table, and
"Test Data - HAPs + Criteria," containing the tests that include data for both HAPs and criteria pollutants.
In the report section, a set of 6 different reports was built for each of the test data tables discussed above. These
reports provide information about pollutant concentrations (corrected to 15% 02) and emissions in units of lb/hr,
lb/MMBtu, and lb/MW-hr. Individual sets of reports were also developed for test summaries and pollutant
summaries.
Treatment of non-detected or non-reported concentrations
Many pollutants, especially HAPs, were not detected in some or all of the sampling runs collected during a test.
In these cases, concentrations were entered in the database as "ND." Although the test reports identified those
pollutants not detected for a given testing run, the detection limit (DL) values were not always provided (i.e., ND
was reported rather than a detection limit concentration). Often, review of the lab report and some additional
calculations were necessary to determine the DL concentration. For example, in the case of formaldehyde, detection
limits were usually given in micrograms or micrograms per milliliter in the lab report. Estimation of the DL in the
same units as the test data (e.g., ppb) involved the use of the sample volume collected during the test and additional
unit conversions (for example, micrograms/cubic meter to ppb).
Unfortunately, the DL could not always be found or calculated based on the laboratory report. Whenever a
pollutant was not detected in all three runs and the DL could not be determined, the pollutant was removed from the
database. This procedure was used for report ID #1 for benzene and chromium (VI). Also, due to the calculations
discussed above, two or three different DLs (one per testing run) were determined for the same pollutant in some
tests. The protocol followed in these cases was to take the highest DL value.
In some tests, only one or two runs were conducted, or runs were eliminated during test report preparation due to
sampling problems encountered during the test. Missing runs were entered as NR (not reported) in the database.
Other parameters missing from the test reports, such as exhaust gas flow rates, were also entered in the database as
NR.
The acronym NA sometimes appears in the DL field. This acronym is used in those cases when a pollutant was
measured above the detection limit in all of the testing runs but a detection limit value was not reported in the test
report.
Equations
Using raw test data (i.e., lab-reported pollutant concentrations and stack test parameters), calculations were
performed to estimate emissions in lb/hr, lb/MW-hr and lb/MMBtu. Modules, small programs written in Visual
Basic code, were built to perform the calculations. There are various modules in the emissions database that perform
different tasks, but only the main modules are described in this memorandum.
The equations used in the modules were taken from EPA sampling methods 19 and 20 in 40 CFR Part 60,
„ 20.9-15
Cad] Cd 20.9-%O2
Appendix A. For example, for the correction of the dry pollutant concentration to 15% 02, Equation 20-4 from EPA
method 20 is used:
where %02 refers to the reported oxygen level during the testing and Cd to the pollutant dry concentration in ppb.
B-2

-------
For the calculation of emission rates in lb/hr, lb/MW-hr, and lb/MMBtu, the following equations were used :
1. Pounds per hour:
When the concentration of pollutant is given in ppb :
MW
M(lb/hr) = Cvvb*Q* 60*		— * 1.369x io"
T std + 460
where Cppb is the dry concentration of pollutant in ppb; Q is the exhaust gas flow rate in dry standard cubic feet
per minute; 60 is the conversion factor from minutes to hours; MW is the pollutant molecular weight (in lb/lb-mol);
Tstd is the standard temperature in degrees Fahrenheit used in the test report; 460 is the conversion factor from
degrees Fahrenheit to degrees Rankine; and 1.369xl0"9 is the conversion factor from ppb to pounds per cubic feet.
The conversion factor from ppb to pounds per cubic feet was derived from 40 CFR, App. A, Meth. 20, page 1026.
When the concentration of a pollutant is given in units other than ppb or ppm, the equation is :
M(lb/hr) = CP*Q*60* A
where Cp is the concentration of pollutant in micrograms per dry cubic feet (ug/dscf), micrograms per dry cubic
meter (ug/dscm), grams per dry cubic feet (g/dscf) or grams per dry cubic meter (g/dscm). For particulate matter,
concentrations are in grains per dry cubic feet (gr/dscf), grains per dry cubic meter (gr/dscm), micrograms per dry
cubic feet (ugr/dscf) and micrograms per dry cubic meter (ugr/dscm). Q is the exhaust gas flow rate in dry standard
cubic feet per minute; 60 is the conversion factor from minutes to hours; and A is a conversion factor from the given
units to lb/dscf.
The values for A for the different units are:
1.1	For ug/dscf, A = 2.205xl0-8
1.2	For ug/dscm, A = 6.24xlO"10
1.3	For g/dscf and g/dscm, multiplying 1.1 and 1.2 by lxlO"6
1.4	For ugr/dscf, A= 1.43xlO"10.
1.5	For ugr/dscm, A = 4.043xl0"12.
1.6	For gr/dscf and gr/dscm, multiplying 1.4 and 1.5 by lxlO"6
2. Pounds per megawatt-hour:
The emission factor is calculated by dividing the emissions rate in lb/hr by the turbine rating during the test. The
manufacturer rating and the test load are necessary data for this calculation. When load was not available, it was
assumed to be 100%. The equation is :
B-3

-------
Mflb/MW-hr)-^^
R*L
100
where M(lb/hr) is the emission rate in lb/hr; R is the manufacturer rating for the turbine in MW; and L is the
turbine testing load in %.
The equation is :
20 9	MW
M(lbfMMBtu) = CV* F*	—	—)
20.9-%O2 T std + 460
3. Pounds per million Btu:
where Cp is the dry concentration of pollutant in any of the units already described for the calculation of
emission factors (1.1 - 1.6); F is the fuel factor in dry standard cubic feet per minute per million Btu; the fraction
20.9/(20.9-%02) is an oxygen correction factor; and B is the conversion factor corresponding to the units in which
the pollutant concentration is reported (see the units described in 1.1 - 1.6). The fraction MW/(Tstd+460) is a
conversion factor used only when the pollutant concentration was provided in ppb.
When the fuel factor or standard temperature was not available, defaults were used. These defaults are discussed
in next section.
A sample of the modules used for the calculations is provided in Appendix C-l.
Defaults and Assumptions
For the estimation of emission factors from the concentrations given in ppb, gaseous pollutants were assumed to
have ideal gas behavior, so that the volume occupied by an ideal gas (22.4 liters/mol) could be used for calculation
of a conversion factor.
Not all of the reports contained the necessary information required for the calculation of emission factors.
Important parameters are concentrations, units, detection limits, oxygen levels, exhaust gas flow rates, fuel factors,
standard temperatures and molecular weights. In most cases, fuel factors and standard temperatures were missing.
In some cases, exhaust gas flow rates were not provided in the report. Lack of gas flow rates still allows for the
calculation of emission factors in pounds per million Btu. Consequently, tests lacking exhaust gas flow rates were
kept in the database, but the emissions in pound per hour are shown as NR.
For non-methane hydrocarbons (NMHC) and total hydrocarbons (THC), a molecular weight of 16 (as methane)
was assumed. Test reports in the database indicated a molecular weight of 16 for THC and, in most cases, for
NMHC. However, in some test reports, the molecular weight chosen to report emission factors for NMHC was the
molecular weight of hexane.
Fields with NR for fuel factors and standard temperatures were filled with default values based on Table 19-1 in
40 CFR Part 60, Appendix A. A default standard temperature of 68°F was used. This standard temperature was
selected because EPA sampling methods rely on this value.
As discussed earlier, some pollutants were not detected in one or more of the sampling runs conducted during a
test. In these cases, the detection limit was used in the emission calculations. Reports generated in the emissions
B-4

-------
database use a "<" sign in front of the sampling ran concentration, as well as the average concentration calculated for
the three runs, to indicate when a pollutant was not detected in one or more of the runs. When a pollutant was not
detected in all three runs, a"«" sign is shown in front of the average concentration presented in the database
reports. The DL value was used in calculating the average concentration when a pollutant was not detected in one or
more of the runs.
B-5

-------
Appendix C-l
Sample of modules used in the database
The modules shown here are the modules for the calculation of emission factors in pounds per million Btu
(Module Convert) and the module that handles the criteria for the use of detection limits (Module NonDetect).
1. Module for the calculation of emission factors in pounds per million Btu
1.1	Declaring the function that will perform the calculations and return the result to the query. The parameters
r, s, t, u, v, w, z refer to concentration units (r), fuel factor (s), molecular weight (t), standard temperature
(u), % oxygen (v), concentration (w), and a parameter (z, set to three in the database) used to limit the
number of significant digits (utilizing another module) in the result.
Function IbMMBtu (r, s, t, u, v, w, x, y, z)
1.2	Estimating the emission factor to return to the query that is calling this module. First the module identifies
the units (r=ppb), then it makes sure that there are values in all necessary fields and finally performs the
calculation. SigDig_ is calling another module that will perform the reduction of the result to a given
number (z) of significant digits. Val calls for the numerical value of the field being processed.
If(& = "ppb") And Not (s = "NR" Or t = "NR" Orv = "NR" Orw = "NR")) Then
IbMMBtu = CStr(SigDig_((Val(s) * Val(t) * (00000000137/ (Val(u) + 460)) * (20.9/(20.9 - Val(v))) * Val(w)), z))
Elself ((r = "ug/dscm ") And Not (s = "NR" Orv= "NR" Orw = "NR")) Then
IbMMBtu = CStr(SigDig_((Val(s) * Val(w) * .0283 * .000000002204 * (20.9/(20.9 - Val(v)))), z))
Elself ((r = "ug/dscf) And Not (s = "NR" Orv= "NR" Orw = "NR")) Then
IbMMBtu = CStr(SigDig_((Val(s) * Val(w) * .000000002204 * (20.9/(20.9 - Val(v)))), z))
Elself ((r = "gr/dscf) And Not (s = "NR" Orv= "NR" Orw = "NR")) Then
IbMMBtu = CStr(SigDig_((Val(s) * Val(w) * (20.9/(20.9 - Val(v¦))) / 7000), z))
Elself ((r = "ugr/dscm ") And Not (s = "NR" Orv= "NR" Orw = "NR")) Then
IbMMBtu = CStr(SigDig_((Val(s) * Val(w) * .0283 * (20.9/(20.9 - Val(v))) * 0.000001/7000), z))
B-6

-------
Elself ((r = "gr/dscm") And Not (s = "NR" Orv= "NR" Orw = "NR")) Then
IbMMBtu = CStr(SigDig_((Val(s) * Valfw) * .0283 * (20.9/(20.9 - Val(v))) / 7000), z))
1.3 In any other case (units not recognized or necessary parameters were not reported) the function is
returned with the value "NR"
Else
IbMMBtu = "NR"
End If
End Function
2. Module Handling the use of non-detected values
2.1	Declaring the function that will return the values to the query. The parameters x and y refer
respectively to concentration and detection limit.
Function Correction (x, y)
2.2	Identifying the concentration. If it is not reported, return the value "NR;" if it is not detected, take
the value of the detection limit as the value for the concentration to be returned. Otherwise leave
the value as it is.
If(x = "NR") Then
Correction = "NR"
Elself
If (x= "ND") Then
Correction =y
Else
Correction = x
End If
End Function
B-7

-------
Appendix C ~ QA\QC Review Criteria for Emissions Tests
HAPS and Criteria Pollutant Source Test Checklist Source Test	Source Test
Report #		Report #	
Date		Date	
BASIC TURBINE INFORMATION
Manufacturer				
Model #				
Rating (BHP or MW)				
Operating Cycle (Simple, Regenerative, etc.)				
FUEL DESCRIPTION
Fuel Name(s)				
Fuel Analysis Summary				
Flowrate (or BTU/H, if available)				
OPERATING CONDITIONS
Load (during test)				
Water or Steam Injection and/or Ammonia Mass Flowrate				
Firing Temperature or Turbine Inlet Temperature				
AMBIENT CONDITIONS
Temperature				
Relative Humidity				
Barometric Pressure				
Altitude
EXHAUST INFORMATION
Temperature
Flowrate (F-Factor or Measured)
EMISSIONS TEST
* Criteria Pollutants
HAPS
Oxygen or C02
Moisture
Averaging Time
METHODS USED
CARB
EPA
Other
QUALITY CONTROL DOCUMENTATION
Calibration of Instruments
Specialty Gases
CEMs
Dry Gas Meters
MISCELLANEOUS
Limits of Detection Reporting
Supplemental Firing Details
C-l

-------
Appendix D
Development of Emission Factors (lb/MMBtu) for Natural Gas Fired Turbines
The emission factors (lb/MMBtu) presented in Table 1 were calculated for natural gas-
fired turbines from 23 source test reports in the emissions database. Emission factors
from test reports that did not meet acceptance criteria established by the CTWG were not
used in the calculations (4.1.2x, 8x, lOx, 29.1, 29.2, and 29.3). In addition, only test
reports where the testing was conducted at high loads (greater than 80%) were included
in the analysis. Test reports in which the load was not specified in the test report or could
not be estimated from fuel use data were excluded.
The following test reports were used for the emission factor calculations: 2, 3.1, 4.2, 6.2,
7, 9, 11, 12.1, 13.1, 15.1, 17, 18, 22, 26, 27, 28, 313.1.1x, 313.2.1x, 314.1x, 315.lx,
316.1.1x, 316.2.1x, and 317. lx. Listed below are the source test reports that were
excluded from the emission factor calculation with the reason for exclusion.
Test Report ID#
Reason for Exclusion
4.1.2x
Formaldehyde data point appears to be an outlier. Retest of the
same turbine generated formaldehyde data more consistent with
other formaldehyde data in the database.
8x
Report deemed inadequate by state and federal regulators
according to telephone contact with the turbine operator.
lOx
Missing load and fuel usage data.
29.1, 29.2, 29.3
Only summary data provided; no raw data sheets, laboratory
results, etc.
16, 21, 313.1.2x, 313.2.2x,
314.2x, 314.3x, 314.4x,
315.2x, 316.1.2x,
316.2.2x, 317.2x
Testing occurred only at operating loads less than 80%.
23, 25
Load information not available.
Test data for individual HAPs that were not detected in any of the sampling runs for a
source test (i.e., where the concentration was ND in all three runs) were excluded from
the emission factor calculation for that HAP. This exclusion was made on a pollutant
basis such that data for a subset of the HAPs analyzed for in a particular source test may
have been used.
D-l

-------
Appendix E — Cost Spreadsheets
INPUTS AND CALCULATIONS
Model Turbine Number
Turbine Exhaust Flow (lb/sec)
Turbine Rating (MW)
Turbine Rating (hp)
Heat Input, MMBtu/hr, including
efficiency
Hours of operation/yr
Life of equipment
Life of catalyst
Interest rate (fraction)
Capital Recovery Factor,
Equipment, 15-yr Life
Capital Recovery Factor, 3-yr
Catalyst Life
Capital Recovery Factor, 6-yr
Catalyst Life
Destruction Efficiency - 3-yr & 6-
yr Catalyst Life
Destruction Efficiency - 6-yr
Catalyst Life w/Degradation
VAPCCI Escalator
Fuel Type (CLEAN OR DIRTY)
Turbine Assumed Efficiency
(fraction)
Turbine Exhaust Temp (OF)
1
658
85.4
114523.1
832.5656 (Rating in MW/ .29307 MW/MMBTU/hr)/ Efficiency
8000
15
3 or 6 Years
0.07
0.109795
0.381052
0.209796
80 for emission reduction calculation
50 for emission reduction calculation
CLEAN
0.35 for emission reduction calculation
1000
Catalyst Calculations:
Vendor Estimate - Based on 80 Percent Reduction of Formaldehyde
Catalyst, Frame & 1595574 Per Catalyst Vendors, assume housing is 30 percent of Total Catalyst Costs
Housing
Catalyst only	1116874 EPA formula based on Vendor Quotes
Ductwork (No quantitative estimates available)
E-l

-------
COSTS (Patterned after the OAQPS Cost Manual (1S90) Thermal and Catalytic Incinerators Section)
Direct Costs
Purchased Equipment Costs (PEC)
Catalyst + auxiliary equipment* (EC)
Instrumentation**
Sales Tax
Freight
1 EC
0.1 EC
0.03 EC
0.05 EC
3-Year
Costs
1595574
159557.4
47867.23
79778.72
6-Year Costs
1595574
159557.4
47867.23
79778.72
Total Purchased Equipment
Cost, PEC
1.18 EC
1882778 1882778
Direct Installation Costs
Foundations & supports
0.08
PEC
150622.2
150622.2
Handling & erection
0.14
PEC
263588.9
263588.9
Electrical
0.04
PEC
75311.11
75311.11
Piping
0.02
PEC
37655.56
37655.56
Insulation for ductwork
0.01
PEC
18827.78
18827.78
Painting
0.01
PEC
18827.78
18827.78
Direct Installation Cost
0.3 PEC
564833.3 564833.3
Site preparation
Buildings
Total Direct Cost, DC
As required, SP
As required, Bldg.
0
0
0
0
1.30 PEC + SP +
Bldg.
2447611 2447611
Indirect Costs (installation)
Engineering
0.1
PEC
188277.8
188277.8
Construction and Field Expenses
0.05
PEC
94138.89
94138.89
Contractor Fees
0.1
PEC
188277.8
188277.8
Start-up
0.02
PEC
37655.56
37655.56
Performance test
0.01
PEC
18827.78
18827.78
Total Indirect Cost, IC
0.28
PEC
527177.8
527177.8
Contingencies
0.1
DC+IC
297478.9
297478.9
Total Capital Cost (TCC) = DC + IC +	^ .61 PEC + SP + 3272268 3272268
Contingencies	Bldg.+0.1 (DC+IC)
E-2

-------
Direct Annual Cost (DAC)
Fuel Fuel Penalty due to
Penalty Pressure Drop
Assume 1"
backpressure
Perf. Test Performance Test
Not speciated HAPs
Cat. Costs Freight to return
catalyst for disposal
Catalyst replacement
Freight=.05*Catalyst only cost*[i/[(1+i)An
i=interest rate, n=catalyst lifetime
Catalyst only cost * CRFcat
Operating Labor
Operator 2 hours
per day
Supervisor ,15*OL
Maintenance
Labor & .10 PEC
Materials
Per Engine ACT-NSCR
Per Engine ACT-
NSCR
0.15 OL
0.1 PEC
Total Direct Annual Cost (DAC)
Indirect Annual Cost (IAC)
Overhead	0.6 O&M
costs
Administrative	0.02 TCC
Property Taxes	0.01 TCC
Insurance	0.01 TCC
Capital for catalyst: CRFequip(TCC -1,08(Cat only))
Recovery
Total Indirect Annual Cost (IAC)
Total Annual Cost (TAC)
E-3
17320 17320
5000	5000
17370.28 7806.717
425586.9 234315.6
18250 18250
2737.5 2737.5
188277.8 188277.8
674542.4	473707.6
125559.2	125559.2
65445.36 65445.36
32722.68 32722.68
32722.68 32722.68
226840.5	226840.5
483290.3	483290.3
1157833 956997.9

-------
INPUTS AND CALCU .ATIONS
Model Turbine Number
Turbine Exhaust Flow (lb/sec)
Turbine Rating (MW)
Turbine Rating (hp)
Heat Input, MMBtu/hr, including
efficiency
Hours of operation/yr
Life of equipment
Life of catalyst
Interest rate (fraction)
Capital Recovery Factor,
Equipment, 15-yr Life
Capital Recovery Factor, 3-yr
Catalyst Life
Capital Recovery Factor, 6-yr
Catalyst Life
Destruction Efficiency - 3-yr & 6-
yr Catalyst Life
Destruction Efficiency - 6-yr
Catalyst Life w/Degradation
VAPCCI Escalator
Fuel Type (CLEAN OR DIRTY)
Turbine Assumed Efficiency
(fraction)
Turbine Exhaust Temp (OF)
2
986
170
227973.4
1657.332 (Rating in MW/ .29307 MW/MMBTU/hr)/ Efficiency
8000
15
3 or 6 Years
0.07
0.109795
0.381052
0.209796
80 for emission reduction calculation
50 for emission reduction calculation
CLEAN
0.35 for emission reduction calculation
1000
Catalyst Calculations:
Vendor Estimate - Based on 80 Percent Reduction of Formaldehyde
Catalyst, Frame & 2317985 Per Catalyst Vendors, assume housing is 30 percent of Total Catalyst Costs
Housing
Catalyst only	1622585 EPA formula based on Vendor Quotes
Ductwork (No quantitative estimates available)
E-4

-------
COSTS (Patterned after the OAQPS Cost Manual (1S90) Thermal and Catalytic Incinerators Section)
Direct Costs
Purchased Equipment Costs (PEC)
Catalyst + auxiliary equipment* (EC)
Instrumentation**
Sales Tax
Freight
1 EC
0.1 EC
0.03 EC
0.05 EC
3-Year
Costs
2317985
231798.5
69539.54
115899.2
6-Year Costs
2317985
231798.5
69539.54
115899.2
Total Purchased Equipment
Cost, PEC
1.18 EC
2735222 2735222
Direct Installation Costs
Foundations & supports
0.08
PEC
218817.8
218817.8
Handling & erection
0.14
PEC
382931.1
382931.1
Electrical
0.04
PEC
109408.9
109408.9
Piping
0.02
PEC
54704.44
54704.44
Insulation for ductwork
0.01
PEC
27352.22
27352.22
Painting
0.01
PEC
27352.22
27352.22
Direct Installation Cost
0.3 PEC
820566.6 820566.6
Site preparation
Buildings
Total Direct Cost, DC
As required, SP
As required, Bldg.
0
0
0
0
1.30 PEC + SP +
Bldg.
3555789 3555789
Indirect Costs (installation)
Engineering
0.1
PEC
273522.2
273522.2
Construction and Field Expenses
0.05
PEC
136761.1
136761.1
Contractor Fees
0.1
PEC
273522.2
273522.2
Start-up
0.02
PEC
54704.44
54704.44
Performance test
0.01
PEC
27352.22
27352.22
Total Indirect Cost, IC
0.28
PEC
765862.2
765862.2
Contingencies
0.1
DC+IC
432165.1
432165.1
Total Capital Cost (TCC) = DC + IC +	^ .61 PEC + SP + 4753816 4753816
Contingencies	Bldg.+0.1 (DC+IC)
E-5

-------
Direct Annual Cost (DAC)
Fuel Fuel Penalty due to
Penalty Pressure Drop
Assume 1"
backpressure
Perf. Test Performance Test
Not speciated HAPs
Cat. Costs Freight to return
catalyst for disposal
Catalyst replacement
Freight=.05*Catalyst only cost*[i/[(1+i)An
i=interest rate, n=catalyst lifetime
Catalyst only cost * CRFcat
Operating Labor
Operator
2 hours
per day
.15 *OL
Superviso
r
Maintenance
Labor & .10 PEC
Materials
Per Engine ACT-NSCR
Per Engine ACT-
NSCR
0.15 OL
0.1 PEC
Total Direct Annual Cost (DAC)
Indirect Annual Cost (IAC)
Overhead	0.6 O&M
costs
Administrative	0.02 TCC
Property Taxes	0.01 TCC
Insurance	0.01 TCC
Capital for catalyst: CRFequip(TCC -1,08(Cat only))
Recovery
Total Indirect Annual Cost (IAC)
Total Annual Cost (TAC)
E-6
34470 34470
5000	5000
25235.39 11341.53
618288.6	340411.5
18250 18250
2737.5 2737.5
273522.2	273522.2
977503.7	685732.7
176705.8	176705.8
95076.32 95076.32
47538.16 47538.16
47538.16 47538.16
329540.3	329540.3
696398.7 696398.7
1673902 1382131

-------
INPUTS AND CALCULATIONS
Model Turbine Number
Turbine Exhaust Flow (lb/sec)
Turbine Rating (MW)
Turbine Rating (hp)
Heat Input, MMBtu/hr, including
efficiency
Hours of operation/yr
Life of equipment
Life of catalyst
Interest rate (fraction)
Capital Recovery Factor,
Equipment, 15-yr Life
Capital Recovery Factor, 3-yr
Catalyst Life
Capital Recovery Factor, 6-yr
Catalyst Life
Destruction Efficiency - 3-yr & 6-
yr Catalyst Life
Destruction Efficiency - 6-yr
Catalyst Life w/Degradation
VAPCCI Escalator
Fuel Type (CLEAN OR DIRTY)
Turbine Assumed Efficiency
(fraction)
Turbine Exhaust Temp (OF)
7
318
39.6
53104.39
386.0609 (Rating in MW/ .29307 MW/MMBTU/hr)/ Efficiency
8000
15
3 or 6 Years
0.07
0.109795
0.381052
0.209796
80 for emission reduction calculation
50 for emission reduction calculation
CLEAN
0.35 for emission reduction calculation
1000
Catalyst Calculations:
Vendor Estimate - Based on 80 Percent Reduction of Formaldehyde
Catalyst, Frame & 846662.4 Per Catalyst Vendors, assume housing is 30 percent of Total Catalyst Costs
Housing
Catalyst only	592662.4 EPA formula based on Vendor Quotes
Ductwork (No quantitative estimates available)
E-7

-------
COSTS (Patterned after the OAQPS Cost Manual (1S90) Thermal and Catalytic Incinerators Section)
Direct Costs
Purchased Equipment Costs (PEC)
Catalyst + auxiliary equipment* (EC)
Instrumentation**
Sales Tax
Freight
1 EC
0.1 EC
0.03 EC
0.05 EC
3-Year
Costs
846662.4
84666.24
25399.87
42333.12
6-Year Costs
846662.4
84666.24
25399.87
42333.12
Total Purchased Equipment
Cost, PEC
1.18 EC
999061.6 999061.6
Direct Installation Costs
Foundations & supports
0.08
PEC
79924.93
79924.93
Handling & erection
0.14
PEC
139868.6
139868.6
Electrical
0.04
PEC
39962.47
39962.47
Piping
0.02
PEC
19981.23
19981.23
Insulation for ductwork
0.01
PEC
9990.616
9990.616
Painting
0.01
PEC
9990.616
9990.616
Direct Installation Cost
0.3 PEC
299718.5 299718.5
Site preparation
Buildings
Total Direct Cost, DC
As required, SP
As required, Bldg.
0
0
0
0
1.30 PEC + SP +
Bldg.
1298780 1298780
Indirect Costs (installation)
Engineering
Construction and Field Expenses
Contractor Fees
Start-up
Performance test
Total Indirect Cost, IC
Contingencies
Total Capital Cost (TCC) = DC + I
Contingencies
0.1
PEC
99906.16
99906.16
0.05
PEC
49953.08
49953.08
0.1
PEC
99906.16
99906.16
0.02
PEC
19981.23
19981.23
0.01
PEC
9990.616
9990.616
0.28
PEC
279737.3
279737.3
0.1
DC+IC
157851.7
157851.7
+	1.61 PEC+ SP+ 1736369 1736369
Bldg.+0.1 (DC+IC)
E-8

-------
Direct Annual Cost (DAC)
Fuel Fuel Penalty due to
Penalty Pressure Drop
Assume 1"
backpressure
Perf. Test Performance Test
Not speciated HAPs
Cat. Costs Freight to return
catalyst for disposal
Catalyst replacement
Freight=.05*Catalyst only cost*[i/[(1+i)An-1],
i=interest rate, n=catalyst lifetime
Catalyst only cost * CRFcat
Operating Labor
Operator
2 hours
per day
.15 *OL
Superviso
r
Maintenance
Labor & .10 PEC
Materials
Per Engine ACT-NSCR
Per Engine ACT-
NSCR
0.15 OL
0.1 PEC
Total Direct Annual Cost (DAC)
Indirect Annual Cost (IAC)
Overhead	0.6 O&M
costs
Administrative	0.02 TCC
Property Taxes	0.01 TCC
Insurance	0.01 TCC
Capital for catalyst: CRFequip(TCC -1,08(Cat only))
Recovery
Total Indirect Annual Cost (IAC)
Total Annual Cost (TAC)
E-9
8030
8030
5000	5000
9217.431	4142.586
225835 124338.1
18250 18250
2737.5 2737.5
99906.16 99906.16
368976.1	262404.3
72536.2 72536.2
34727.38 34727.38
17363.69 17363.69
17363.69 17363.69
120367.2	120367.2
262358.1	262358.1
631334.2	524762.5

-------
INPUTS AND CALCU .ATIONS
Model Turbine Number
Turbine Exhaust Flow (lb/sec)
Turbine Rating (MW)
Turbine Rating (hp)
Heat Input, MMBtu/hr, including
efficiency
Hours of operation/yr
Life of equipment
Life of catalyst
Interest rate (fraction)
Capital Recovery Factor,
Equipment, 15-yr Life
Capital Recovery Factor, 3-yr
Catalyst Life
Capital Recovery Factor, 6-yr
Catalyst Life
Destruction Efficiency - 3-yr & 6-
yr Catalyst Life
Destruction Efficiency - 6-yr
Catalyst Life w/Degradation
VAPCCI Escalator
Fuel Type (CLEAN OR DIRTY)
Turbine Assumed Efficiency
(fraction)
Turbine Exhaust Temp (OF)
9
178
27
36207.54
263.2233 (Rating in MW/ .29307 MW/MMBTU/hr)/ Efficiency
8000
15
3 or 6 Years
0.07
0.109795
0.381052
0.209796
80 for emission reduction calculation
50 for emission reduction calculation
CLEAN
0.35 for emission reduction calculation
1000
Catalyst Calculations:
Vendor Estimate - Based on 80 Percent Reduction of Formaldehyde
Catalyst, Frame & 538310.4 Per Catalyst Vendors, assume housing is 30 percent of Total Catalyst Costs
Housing
Catalyst only	376810.4 EPA formula based on Vendor Quotes
Ductwork (No quantitative estimates available)
E-10

-------
COSTS (Patterned after the OAQPS Cost Manual (1S90) Thermal and Catalytic Incinerators Section)
Cost Item
Direct Costs
Purchased Equipment Costs (PEC)
Catalyst + auxiliary equipment* (EC)
Instrumentation**
Sales Tax
Freight
1 EC
0.1 EC
0.03 EC
0.05 EC
3-Year
Costs
538310.4
53831.04
16149.31
26915.52
6-Year Costs
538310.4
53831.04
16149.31
26915.52
Total Purchased Equipment
Cost, PEC
1.18 EC
635206.3 635206.3
Direct Installation Costs
Foundations & supports
0.08
PEC
50816.5
50816.5
Handling & erection
0.14
PEC
88928.88
88928.88
Electrical
0.04
PEC
25408.25
25408.25
Piping
0.02
PEC
12704.13
12704.13
Insulation for ductwork
0.01
PEC
6352.063
6352.063
Painting
0.01
PEC
6352.063
6352.063
Direct Installation Cost
0.3 PEC
190561.9 190561.9
Site preparation
Buildings
Total Direct Cost, DC
As required, SP
As required, Bldg.
0
0
0
0
1.30 PEC + SP +
Bldg.
825768.2 825768.2
Indirect Costs (installation)
Engineering
Construction and Field Expenses
Contractor Fees
Start-up
Performance test
Total Indirect Cost, IC
Contingencies
Total Capital Cost (TCC) = DC + I
Contingencies
0.1
PEC
63520.63
63520.63
0.05
PEC
31760.31
31760.31
0.1
PEC
63520.63
63520.63
0.02
PEC
12704.13
12704.13
0.01
PEC
6352.063
6352.063
0.28
PEC
177857.8
177857.8
0.1
DC+IC
100362.6
100362.6
+	1.61 PEC+ SP+ 1103989 1103989
Bldg.+0.1 (DC+IC)
E-ll

-------
Direct Annual Cost (DAC)
Fuel Fuel Penalty due to
Penalty Pressure Drop
Assume 1"
backpressure
Perf. Test Performance Test
Not speciated HAPs
Cat. Costs Freight to return
catalyst for disposal
Catalyst replacement
Freight=.05*Catalyst only cost*[i/[(1+i)An
i=interest rate, n=catalyst lifetime
Catalyst only cost * CRFcat
Operating Labor
Operator
2 hours
per day
.15 *OL
Superviso
r
Maintenance
Labor & .10 PEC
Materials
Per Engine ACT-NSCR
Per Engine ACT-
NSCR
0.15 OL
0.1 PEC
Total Direct Annual Cost (DAC)
Indirect Annual Cost (IAC)
Overhead	0.6 O&M
costs
Administrative	0.02 TCC
Property Taxes	0.01 TCC
Insurance	0.01 TCC
Capital for catalyst: CRFequip(TCC -1,08(Cat only))
Recovery
Total Indirect Annual Cost (IAC)
Total Annual Cost (TAC)
E-12
5470	5470
5000	5000
5860.375 2633.826
143584.2 79053.24
18250 18250
2737.5 2737.5
63520.63 63520.63
244422.7 176665.2
50704.88	50704.88
22079.77 22079.77
11039.89	11039.89
11039.89 11039.89
76530.51	76530.51
171394.9 171394.9
415817.7 348060.1

-------
INPUTS AND CALCU .ATIONS
Model Turbine Number
Turbine Exhaust Flow (lb/sec)
Turbine Rating (MW)
Turbine Rating (hp)
Heat Input, MMBtu/hr, including
efficiency
Hours of operation/yr
Life of equipment
Life of catalyst
Interest rate (fraction)
Capital Recovery Factor,
Equipment, 15-yr Life
Capital Recovery Factor, 3-yr
Catalyst Life
Capital Recovery Factor, 6-yr
Catalyst Life
Destruction Efficiency - 3-yr & 6-
yr Catalyst Life
Destruction Efficiency - 6-yr
Catalyst Life w/Degradation
VAPCCI Escalator
Fuel Type (CLEAN OR DIRTY)
Turbine Assumed Efficiency
(fraction)
Turbine Exhaust Temp (OF)
15
83.6
9
12069.18
87.74111 (Rating in MW/ .29307 MW/MMBTU/hr)/ Efficiency
8000
15
3 or 6 Years
0.07
0.109795
0.381052
0.209796
80 for emission reduction calculation
50 for emission reduction calculation
CLEAN
0.35 for emission reduction calculation
1000
Catalyst Calculations:
Vendor Estimate - Based on 80 Percent Reduction of Formaldehyde
Catalyst, Frame & 330364.5 Per Catalyst Vendors, assume housing is 30 percent of Total Catalyst Costs
Housing
Catalyst only	231264.5 EPA formula based on Vendor Quotes
Ductwork (No quantitative estimates available)
E-13

-------
COSTS (Patterned after the OAQPS Cost Manual (1S90) Thermal and Catalytic Incinerators Section)
Direct Costs
Purchased Equipment Costs (PEC)
Catalyst + auxiliary equipment* (EC)
Instrumentation**
Sales Tax
Freight
1 EC
0.1 EC
0.03 EC
0.05 EC
3-Year
Costs
$236,584
$23,658
$7,098
$11,829
6-Year Costs
$236,584
$23,658
$7,098
$11,829
Total Purchased Equipment
1.18 EC
$279,169
$279,169
Cost, PEC



Direct Installation Costs



Foundations & supports
0.08 PEC
$22,334
$22,334
Handling & erection
0.14 PEC
$39,084
$39,084
Electrical
0.04 PEC
$11,167
$11,167
Piping
0.02 PEC
$5,583
$5,583
Insulation for ductwork
0.01 PEC
$2,792
$2,792
Painting
0.01 PEC
$2,792
$2,792
Direct Installation Cost
0.3 PEC
$83,751
$83,751
Site preparation
As required, SP
$0
$0
Buildings
As required, Bldg.
$0
$0
Total Direct Cost, DC
1.30 PEC + SP +
$362,920
$362,920

Bldg.


Indirect Costs (installation)



Engineering
0.1 PEC
$27,917
$27,917
Construction and Field Expenses
0.05 PEC
$13,958
$13,958
Contractor Fees
0.1 PEC
$27,917
$27,917
Start-up
0.02 PEC
$5,583
$5,583
Performance test
0.01 PEC
$2,792
$2,792
Total Indirect Cost, IC
0.28 PEC
$78,167
$78,167
Contingencies
0.1 DC+IC
$44,109
$44,109
Total Capital Cost (TCC) = DC + IC +
1.61 PEC + SP +
$485,196
$485,196
Contingencies
Bldg.+0.1 (DC+IC)


E-14

-------
Direct Annual Cost (DAC1
Direct Costs
Purchased Equipment Costs (PEC)
Catalyst + auxiliary equipment* (EC)	1 EC
Instrumentation**	0.1 EC
Sales Tax	0.03 EC
Freight	0.05 EC
Total Purchased	Equipment 1.18 EC
Cost, PEC
Direct Installation Costs
Foundations & supports	0.08 PEC
Handling & erection	0.14 PEC
Electrical	0.04 PEC
Piping	0.02 PEC
Insulation for ductwork	0.01 PEC
Painting	0.01 PEC
Direct Installation Cost	0.3 PEC
Site preparation
Buildings
As required, SP
As required, Bldg.
Total Direct Cost, DC
Indirect Costs (installation)
Engineering
Construction and Field Expenses
Contractor Fees
Start-up
Performance test
Total Indirect Cost, IC
Contingencies
1.30 PEC + SP +
Bldg.
0.1 PEC
0.05 PEC
0.1 PEC
0.02 PEC
0.01 PEC
0.28 PEC
0.1 DC+IC
Total Capital Cost (TCC) = DC + IC +
Contingencies
1.61 PEC + SP +
Bldg.+0.1 (DC+IC)
E-15
3-Year 6-Year Costs
Costs
330364.5	330364.5
33036.45	33036.45
9910.934	9910.934
16518.22	16518.22
389830.1	389830.1
31186.41	31186.41
54576.21	54576.21
15593.2	15593.2
7796.602	7796.602
3898.301	3898.301
3898.301	3898.301
116949	116949
0	0
0	0
506779.1 506779.1
38983.01	38983.01
19491.5	19491.5
38983.01	38983.01
7796.602	7796.602
3898.301	3898.301
109152.4	109152.4
61593.15	61593.15
677524.7
677524.7

-------
Direct Annual Cost (DAC)
Fuel Fuel	Assume
Penalty Penalty	1"
due to	backpress
Pressure	ure
Drop
Perf. Test Performan	Not speciated HAPs
ce Test
1
Cat. Costs Freight to return
catalyst for disposal
Catalyst replacement
Freight=.05*Catalyst only cost*[i/[(1+i)An-
i=interest rate, n=catalyst lifetime
Catalyst only cost * CRFcat
Operating Labor
Operator
2 hours
per day
.15 *OL
Superviso
r
Maintenance
Labor & .10 PEC
Materials
Per Engine ACT-NSCR
Per Engine ACT-
NSCR
0.15 OL
0.1 PEC
Total Direct Annual Cost (DAC)
Indirect Annual Cost (IAC)
Overhead	0.6 O&M
costs
Administrative	0.02 TCC
Property Taxes	0.01 TCC
Insurance	0.01 TCC
Capital for catalyst: CRFequip(TCC -1,08(Cat only))
Recovery
Total Indirect Annual Cost (IAC)
Total Annual Cost (TAC)
E-16
1820
1820
5000	5000
3596.76	1616.49
88123.72	48518.32
18250	18250
2737.5	2737.5
38983.01	38983.01
158511	116925.3
35982.31	35982.31
13550.49	13550.49
6775.247	6775.247
6775.247	6775.247
46965.64	46965.64
110048.9	110048.9
268559.9	226974.3

-------
INPUTS AND CALCULATIONS
Model Turbine Number
13

Turbine Exhaust Flow (lb/sec)
41

Turbine Rating (MW)
3.5

Turbine Rating (hp)
4,694

Heat Input, MMBtu/hr, including
34
(Rating in MW/ .29307 MW/MMBTU/hr)/
efficiency


Hours of operation/yr
8000

Life of equipment
15

Life of catalyst
3 or 6 Years
Interest rate (fraction)
0.07

Capital Recovery Factor,
0.1098
Equipment, 15-yr Life

Capital Recovery Factor, 3-yr
0.3811
Catalyst Life

Capital Recovery Factor, 6-yr
0.2098
Catalyst Life

Destruction Efficiency - 3-yr & 6-
80
for emission reduction calculation
yr Catalyst Life


Destruction Efficiency - 6-yr
50
for emission reduction calculation
Catalyst Life w/Degradation


VAPCCI Escalator

Fuel Type (CLEAN OR DIRTY)
CLEAN

Turbine Assumed Efficiency
0.35
for emission reduction calculation
(fraction)


Turbine Exhaust Temp (OF)
1000

Catalyst Calculations:
Vendor Estimate - Based on 80 Percent Reduction of Formaldehyde
Catalyst, Frame & $236,584 Per Catalyst Vendors, assume housing is 30 percent of Total Catalyst Costs
Housing
Catalyst only	$165,584 EPA formula based on Vendor Quotes
Other catalyst - associated costs
Ductwork (No quantitative estimates available)
E-17

-------
COSTS (Patterned after the OAQPS Cost Manual (1S90) Thermal and Catalytic Incinerators Section)
Direct Costs
Purchased Equipment Costs (PEC)
Catalyst + auxiliary equipment* (EC)
Instrumentation**
Sales Tax
Freight
1 EC
0.1 EC
0.03 EC
0.05 EC
3-Year
Costs
$236,584
$23,658
$7,098
$11,829
6-Year Costs
$236,584
$23,658
$7,098
$11,829
Total Purchased Equipment
1.18 EC
$279,169
$279,169
Cost, PEC



Direct Installation Costs



Foundations & supports
0.08 PEC
$22,334
$22,334
Handling & erection
0.14 PEC
$39,084
$39,084
Electrical
0.04 PEC
$11,167
$11,167
Piping
0.02 PEC
$5,583
$5,583
Insulation for ductwork
0.01 PEC
$2,792
$2,792
Painting
0.01 PEC
$2,792
$2,792
Direct Installation Cost
0.3 PEC
$83,751
$83,751
Site preparation
As required, SP
$0
$0
Buildings
As required, Bldg.
$0
$0
Total Direct Cost, DC
1.30 PEC + SP +
$362,920
$362,920

Bldg.


Indirect Costs (installation)



Engineering
0.1 PEC
$27,917
$27,917
Construction and Field Expenses
0.05 PEC
$13,958
$13,958
Contractor Fees
0.1 PEC
$27,917
$27,917
Start-up
0.02 PEC
$5,583
$5,583
Performance test
0.01 PEC
$2,792
$2,792
Total Indirect Cost, IC
0.28 PEC
$78,167
$78,167
Contingencies
0.1 DC+IC
$44,109
$44,109
Total Capital Cost (TCC) = DC + IC +
1.61 PEC + SP +
$485,196
$485,196
Contingencies
Bldg.+0.1 (DC+IC)


E-18

-------
Direct Annual Cost (DAC1
Fuel Fuel Penalty due to	1.0
Penalty Pressure Drop
Assume 1"
backpressure
Perf. Test Performance Test
Not speciated HAPs
Cat. Costs Freight to return Freight=.05*Catalyst only cost*[i/[(1+i)An-
catalyst for disposal i=interest rate, n=catalyst lifetime
Catalyst replacement Catalyst only cost * CRFcat
Operating Labor
Operator 2 hours Per Engine ACT-NSCR
per day
Supervisor ,15*OL	0.15 OL
Maintenance
Labor & .10 PEC Per Engine ACT-	0.1 PEC
Materials	NSCR
Total Direct Annual Cost (DAC)
Indirect Annual Cost (IAC1
Overhead	0.6 O&M
costs
Administrative	0.02 TCC
Property Taxes	0.01 TCC
Insurance	0.01 TCC
Capital for catalyst: CRFequip(TCC -1,08(Cat only))
Recovery
Total Indirect Annual Cost (IAC)
Total Annual Cost (TAC)
E-19
$710	$710
$5,000	$5,000
$2,575	$1,157
$63,096	$34,739
$18,250	$18,250
$2,738	$2,738
$27,917	$27,917
$120,286	$90,511
$29,343	$29,343
$9,704	$9,704
$4,852	$4,852
$4,852	$4,852
$33,637	$33,637
$82,388	$82,388
$202,673	$172,898

-------
INPUTS AND CALCULATIONS
Model Turbine Number
17

Turbine Exhaust Flow (lb/sec)
14.2

Turbine Rating (MW)
1.13

Turbine Rating (hp)
1,515

Heat Input, MMBtu/hr, including
11
(Rating in MW/ .29307 MW/MMBTU/hr)/
efficiency


Hours of operation/yr
8000

Life of equipment
15

Life of catalyst
3 or 6 Years
Interest rate (fraction)
0.07

Capital Recovery Factor,
0.1098
Equipment, 15-yr Life

Capital Recovery Factor, 3-yr
0.3811
Catalyst Life

Capital Recovery Factor, 6-yr
0.2098
Catalyst Life

Destruction Efficiency - 3-yr & 6-
80
for emission reduction calculation
yr Catalyst Life


Destruction Efficiency - 6-yr
50
for emission reduction calculation
Catalyst Life w/Degradation


VAPCCI Escalator

Fuel Type (CLEAN OR DIRTY)
CLEAN

Turbine Assumed Efficiency
0.35
for emission reduction calculation
(fraction)


Turbine Exhaust Temp (OF)
1000

Catalyst Calculations:
Vendor Estimate - Based on 80 Percent Reduction of Formaldehyde
Catalyst, Frame & $177,564 Per Catalyst Vendors, assume housing is 30 percent of Total Catalyst Costs
Housing
Catalyst only	$124,264 EPA formula based on Vendor Quotes
Other catalyst - associated costs
Ductwork (No quantitative estimates available)
E-20

-------
COSTS (Patterned after the OAQPS Cost Manual (1S90) Thermal and Catalytic Incinerators Section)
Direct Costs
Purchased Equipment Costs (PEC)
Catalyst + auxiliary equipment* (EC)
Instrumentation**
Sales Tax
Freight
1 EC
0.1 EC
0.03 EC
0.05 EC
3-Year
Costs
$177,564
$17,756
$5,327
$8,878
6-Year Costs
$177,564
$17,756
$5,327
$8,878
Total Purchased Equipment
1.18 EC
$209,525
$209,525
Cost, PEC



Direct Installation Costs



Foundations & supports
0.08 PEC
$16,762
$16,762
Handling & erection
0.14 PEC
$29,334
$29,334
Electrical
0.04 PEC
$8,381
$8,381
Piping
0.02 PEC
$4,191
$4,191
Insulation for ductwork
0.01 PEC
$2,095
$2,095
Painting
0.01 PEC
$2,095
$2,095
Direct Installation Cost
0.3 PEC
$62,858
$62,858
Site preparation
As required, SP
$0
$0
Buildings
As required, Bldg.
$0
$0
Total Direct Cost, DC
1.30 PEC + SP +
$272,383
$272,383

Bldg.


Indirect Costs (installation)



Engineering
0.1 PEC
$20,953
$20,953
Construction and Field Expenses
0.05 PEC
$10,476
$10,476
Contractor Fees
0.1 PEC
$20,953
$20,953
Start-up
0.02 PEC
$4,191
$4,191
Performance test
0.01 PEC
$2,095
$2,095
Total Indirect Cost, IC
0.28 PEC
$58,667
$58,667
Contingencies
0.1 DC+IC
$33,105
$33,105
Total Capital Cost (TCC) = DC + IC +
1.61 PEC + SP +
$364,154
$364,154
Contingencies
Bldg.+0.1 (DC+IC)


E-21

-------
Direct Annual Cost (DAC1
Fuel Fuel Penalty due to
Penalty Pressure Drop -
Assume 1"
backpressure
Perf. Test Performance Test
Not speciated HAPs
Cat. Costs Freight to return Freight=.05*Catalyst only cost*[i/[(1+i)An-
catalyst for disposal i=interest rate, n=catalyst lifetime
Catalyst replacement Catalyst only cost * CRFcat
Operating Labor
Operator 2 hours Per Engine ACT-NSCR
per day
Supervisor ,15*OL	0.15 OL
Maintenance
Labor & .10 PEC Per Engine ACT-	0.1 PEC
Materials	NSCR
Total Direct Annual Cost (DAC)
Indirect Annual Cost (IAC1
Overhead	0.6 O&M
costs
Administrative	0.02 TCC
Property Taxes	0.01 TCC
Insurance	0.01 TCC
Capital for catalyst: CRFequip(TCC -1,08(Cat only))
Recovery
Total Indirect Annual Cost (IAC)
Total Annual Cost (TAC)
E-22
$230	$230
$5,000	$5,000
$1,933	$869
$47,351	$26,070
$18,250	$18,250
$2,738	$2,738
$20,953	$20,953
$96,453	$74,109
$25,164	$25,164
$7,283	$7,283
$3,642	$3,642
$3,642	$3,642
$25,247	$25,247
$64,977	$64,977
$161,431	$139,086

-------
Appendix F ~ Description of SCONOx™ System
The SCONOx™ catalytic absorption system was described in a paper presented at the Power-Gen
International '97 conference as follows:
The SCONOx™ system uses a single catalyst for both CO & NOx control. It oxidizes CO
to C02 and NO to N02, and the N02 is then absorbed onto the surface of the catalyst.
Just as a sponge absorbs water and must be wrung out periodically, the SCONOx™
catalyst must be periodically regenerated. This is accomplished by passing a dilute
hydrogen gas across the surface of the catalyst in the absence of oxygen. Nitrogen oxides
are broken down into nitrogen and water, and this is exhausted up the stack instead of
NOx.
Source: "The SCONOx™ Catalytic Absorption system for Natural Gas Fired Power Plants: The
Path to Ultra-Low Emissions," Robert J. MacDonald, P.E., and Lawrence Debbage, presented to
Power-Gen International '97, December 9-11, 1997.
F-l

-------
Appendix G ~ Cost-Effectiveness for Individual HAPs
Model 1 - 85.4 MW Turbine
Pollutant
80% Reduction &
3-Yr Catalyst Life
80% Reduction &
6-Yr Catalyst Life
50% Reduction &
6-Yr Catalyst Life
Highest EF
Average EF
Highest EF
Average EF
Highest EF
Average EF
Formaldehyde
$85,213
$670,472
$70,432
$554,173
$112,692
$886,677
Toluene
$629,008
$3,366,524
$519,902
$2,782,575
$831,843
$4,452,120
Acetaldehyde
$1,365,847
$5,241,737
$1,128,930
$4,332,518
$1,806,289
$6,932,029
Xylenes
$3,983,720
$10,414,955
$3,292,714
$8,608,402
$5,268,342
$13,773,443
Ethylbenzene
$11,659,669
$11,659,669
$9,637,211
$9,637,211
$15,419,538
$15,419,538
Benzene
$12,226,251
$46,412,275
$10,105,515
$38,361,714
$16,168,825
$61,378,743
PAHs
$65,306,889
$214,370,595
$53,978,915
$177,186,393
$86,366,264
$283,498,228
Acrolein
$78,626,057
$87,075,852
$64,987,772
$71,971,886
$103,980,436
$115,155,018
Naphthalene
$144,424,903
$327,429,060
$119,373,310
$270,634,011
$190,997,296
$433,014,417
Total HAPs
$68,914
$454,166
$56,961
$375,388
$91,137
$600,620
Model 2 — 170 MW Turbine
Pollutant
80% Reduction &
3-Yr Catalyst Life
Highest EF Average EF
80% Reduction &
6-Yr Catalyst Life
Highest EF Average EF
50% Reduction &
6-Yr Catalyst Life
Highest EF Average EF
Formaldehyde
$61,887 $486,938
$51,100 $402,062
$81,760 $643,299
Toluene
$456,825 $2,444,978
$377,198 $2,018,804
$603,516 $3,230,087
Acetaldehyde
$991,963 $3,806,874
$819,058 $3,143,314
$1,310,492 $5,029,302
Xylenes
$2,893,224 $7,563,985
$2,388,918 $6,245,538
$3,822,269 $9,992,861
Ethylbenzene
$8,467,973 $8,467,973
$6,991,956 $6,991,956
$11,187,129 $11,187,129
Benzene
$8,879,461 $33,707,467
$7,331,718 $27,832,058
$11,730,750 $44,531,292
PAHs
$47,429,906 $155,689,197
$39,162,595 $128,551,656
$62,660,151 $205,682,649
Acrolein
$57,103,110 $63,239,874
$47,149,703 $52,216,793
$75,439,524 $83,546,868
Naphthalene
$104,890,305 $237,799,252
$86,607,309 $196,349,447
$138,571,694 $314,159,115
Total HAPs
$50,050 $329,844
$41,326 $272,350
$66,122 $435,760
G-l

-------
Model 7 - 39.6 MW Turbine
Pollutant
80% Reduction &
3-Yr Catalyst Life
Highest EF Average EF
80% Reduction &
6-Yr Catalyst Life
Highest EF Average EF
50% Reduction &
6-Yr Catalyst Life
Highest EF Average EF
Formaldehyde
$100,204 $788,418
$83,289 $655,330
$133,262 $1,048,528
Toluene
$739,661 $3,958,748
$614,803 $3,290,496
$983,685 $5,264,793
Acetaldehyde
$1,606,121 $6,163,841
$1,335,001 $5,123,360
$2,136,002 $8,197,375
Xylenes
$4,684,519 $12,247,109
$3,893,753 $10,179,747
$6,230,005 $16,287,596
Ethylbenzene
$13,710,787 $13,710,787
$11,396,351 $11,396,351
$18,234,162 $18,234,162
Benzene
$14,377,040 $54,576,921
$11,950,138 $45,364,117
$19,120,221 $72,582,586
PAHs
$76,795,394 $252,081,741
$63,832,022 $209,529,327
$102,131,235 $335,246,924
Acrolein
$92,457,612 $102,393,858
$76,850,395 $85,109,363
$122,960,632 $136,174,980
Naphthalene
$169,831,505 $385,028,960
$141,163,263 $320,034,521
$225,861,221 $512,055,233
Total HAPs
$81,038 $534,061
$67,358 $443,910
$107,773 $710,255
Model 9 — 27 MW Turbine
Pollutant
80% Reduction &
3-Yr Catalyst Life
Highest EF Average EF
80% Reduction &
6-Yr Catalyst Life
Highest EF Average EF
50% Reduction &
6-Yr Catalyst Life
Highest EF Average EF
Formaldehyde
$96,796 $761,608
$81,023 $637,504
$129,637 $1,020,007
Toluene
$714,509 $3,824,133
$598,080 $3,200,990
$956,927 $5,121,583
Acetaldehyde
$1,551,505 $5,954,241
$1,298,687 $4,983,997
$2,077,900 $7,974,395
Xylenes
$4,525,223 $11,830,650
$3,787,838 $9,902,844
$6,060,540 $15,844,550
Ethylbenzene
$13,244,556 $13,244,556
$11,086,354 $11,086,354
$17,738,167 $17,738,167
Benzene
$13,888,154 $52,721,050
$11,625,077 $44,130,148
$18,600,124 $70,608,237
PAHs
$74,183,991 $243,509,783
$62,095,700 $203,829,832
$99,353,120 $326,127,732
Acrolein
$89,313,621 $98,911,988
$74,759,955 $82,794,267
$119,615,928 $132,470,827
Naphthalene
$164,056,440 $371,936,175
$137,323,422 $311,329,127
$219,717,475 $498,126,604
Total HAPs
$78,282 $515,901
$65,526 $431,835
$104,841 $690,935
G-2

-------
Model 13 - 3.5 MW Turbine
Pollutant
80% Reduction &
3-Yr Catalyst Life
Highest EF Average EF
80% Reduction &
6-Yr Catalyst Life
Highest EF Average EF
50% Reduction &
6-Yr Catalyst Life
Highest EF Average EF
Formaldehyde
$363,955 $2,863,658
$310,486 $2,442,953
$496,777 $3,908,725
Toluene
$2,686,563 $14,378,788
$2,291,876 $12,266,378
$3,667,001 $19,626,205
Acetaldehyde
$5,833,680 $22,388,026
$4,976,645 $19,098,966
$7,962,632 $30,558,345
Xylenes
$17,014,900 $44,483,398
$14,515,214 $37,948,271
$23,224,342 $60,717,234
Ethylbenzene
$49,799,706 $49,799,706
$42,483,553 $42,483,553
$67,973,684 $67,973,684
Benzene
$52,219,641 $198,231,840
$44,547,971 $169,109,287
$71,276,753 $270,574,860
PAHs
$278,932,781 $915,599,980
$237,954,325 $781,087,739
$380,726,920 $1,249,740,383
Acrolein
$335,820,387 $371,910,374
$286,484,483 $317,272,433
$458,375,173 $507,635,893
Naphthalene
$616,854,367 $1,398,484,901
$526,231,317 $1,193,031,273
$841,970,107 $1,908,850,037
Total HAPs
$294,341 $1,939,794
$251,099 $1,654,815
$401,758 $2,647,705
Model 15 — 9 MW Turbine
Pollutant
80% Reduction &
3-Yr Catalyst Life
Highest EF Average EF
80% Reduction &
6-Yr Catalyst Life
Highest EF Average EF
50% Reduction &
6-Yr Catalyst Life
Highest EF Average EF
Formaldehyde
$187,550 $1,475,677
$158,509 $1,247,173
$253,614 $1,995,477
Toluene
$1,384,418 $7,409,561
$1,170,045 $6,262,213
$1,872,072 $10,019,541
Acetaldehyde
$3,006,165 $11,536,816
$2,540,669 $9,750,376
$4,065,071 $15,600,602
Xylenes
$8,767,980 $22,922,824
$7,410,286 $19,373,296
$11,856,457 $30,997,274
Ethylbenzene
$25,662,381 $25,662,381
$21,688,641 $21,688,641
$34,701,826 $34,701,826
Benzene
$26,909,402 $102,151,226
$22,742,565 $86,333,426
$36,388,104 $138,133,482
PAHs
$143,737,381 $471,819,563
$121,480,094 $398,759,771
$194,368,151 $638,015,633
Acrolein
$173,052,241 $191,649,841
$146,255,640 $161,973,459
$234,009,023 $259,157,534
Naphthalene
$317,872,394 $720,655,908
$268,650,843 $609,064,582
$429,841,348 $974,503,331
Total HAPs
$151,677 $999,599
$128,191 $844,814
$205,105 $1,351,702
G-3

-------
Model 17 - 1.13 MW Turbine
Pollutant
80% Reduction &
3-Yr Catalyst Life
Highest EF Average EF
80% Reduction &
6-Yr Catalyst Life
Highest EF Average EF
50% Reduction &
6-Yr Catalyst Life
Highest EF Average EF
Formaldehyde
$897,899 $7,064,815
$773,614 $6,086,919
$1,237,782 $9,739,070
Toluene
$6,627,912 $35,473,330
$5,710,491 $30,563,190
$9,136,785 $48,901,104
Acetaldehyde
$14,392,037 $55,232,597
$12,399,923 $47,587,423
$19,839,877 $76,139,877
Xylenes
$41,976,774 $109,743,200
$36,166,442 $94,552,789
$57,866,307 $151,284,462
Ethylbenzene
$122,858,851 $122,858,851
$105,853,000 $105,853,000
$169,364,800 $169,364,800
Benzene
$128,828,974 $489,049,793
$110,996,752 $421,356,601
$177,594,803 $674,170,562
PAHs
$688,143,835 $2,258,839,853
$592,892,485 $1,946,176,230
$948,627,977 $3,113,881,969
Acrolein
$828,488,959 $917,525,113
$713,811,348 $790,523,314
$1,142,098,156 $1,264,837,302
Naphthalene
$1,521,816,578 $3,450,145,803
$1,311,170,089 $2,972,584,242
$2,097,872,142 $4,756,134,788
Total HAPs
$726,157 $4,785,587
$625,644 $4,123,176
$1,001,030 $6,597,082
G-4

-------