COSDEN CHEMICAL
COATINGS
CORPORATION
NEW JERSEY
EPA ID# NJD000565531
EPA REGION 2
CONGRESSIONAL DIST. 03
Burlington County
Beverly
Other Names:
Cosden Paint Company
Cosden Industrial Coatings
Corporation
Moleta-Cosden Industrial Coatings
Site Description 	
The 6 1/2-acre Cosden Chemical Coatings Corp. site operated under several names from 1945 until
1989, when it permanently closed. The facility produced paints for industrial applications that
involved the use of solvents, which were stored in tanks and drums on site. Prior to 1974, solvents
and wastes were recycled by a contractor who regularly removed the drums. In 1974, the recycling
ceased and the drums accumulated on the site. The owner abandoned the site in 1985. The site first
came to the attention of the New Jersey Department of Environmental Protection (NJDEP) following
a grass fire at the facility. An inspection by the NJDEP in 1980 revealed surface spills and several
hundred unsecured drums stored on site. EPA conducted sampling in 1988 and found the soil to be
contaminated primarily with heavy metals and the groundwater contaminated with volatile organic
compounds (VOCs). Approximately 3,000 people live in the City of Beverly with a residential
development bordering the site. There are two public water supply wells one mile from the site that
provide 1.2 million gallons of drinking water per day to Beverly and eight other adjacent townships.
These wells are located near the Delaware River which is used for recreational activities.
Site Responsibility: This site is being addressed through
Federal and State actions.
NPL LISTING HISTORY
Proposed Date: 01/01/87
Final Date: 07/01/87
Threats and Contaminants 	
^¦sool The soil was and groundwater is contaminated with VOCs, including toluene, xylene, and
' / \> ethyl benzene. The soil was also contaminated with heavy metals, including chromium,
/ \ I lead, zinc, and copper, as well as polychlorinated biphenyls (PCBs). Although private
wells had been the source of drinking water in the past, all of the homes in the area are
now connected to a public water supply system.
COSDEN CHEMICAL CORP.
1
May 2002

-------
Clean
up Approach 	
This site is being addressed in two stages: immediate actions and a long-term remedial phase
focusing on cleanup of the entire site.
Response Action Status 	
Immediate Actions: The company initiated the cleanup of the site in early 1985,
under a court order, segregating and containerizing waste solvents, paints and spills into
drums. This effort was abandoned in late 1985, leaving the removal of over 500 drums
of hazardous waste to be completed by the State. After the site was put on the NPL, EPA undertook
another major removal action in 1989; hundreds of production and laboratory samples were
consolidated and transported off site for incineration at a federally approved facility, as were the
contents of one of the underground storage tanks. In July 1989, EPA constructed a fence to secure
the site.
Entire Site: In September 1992, EPA chose the following remedy to clean up the site:
(1) decontamination and demolition of the former manufacturing plant; (2) in-situ
stabilization of soils contaminated with PCBs and metals; and (3) extraction, treatment of
contaminated groundwater, and reinjection of the treated water. A remedial action construction
contract for decontamination, demolition and disposal of all on-site structures, equipment and debris
at an appropriate off-site facility, was awarded in May 1995. That work was completed in spring
1996. A pre-design investigation related to the soil remedy revealed that the contamination was
widely scattered throughout the site which would make in-situ treatment more costly and less
effective than localized excavation with off-site treatment and disposal. An Explanation of
Significant Differences (ESD) was issued in September 1998 to change the soil remedy to excavation
with off-site treatment and disposal. The design of the soil remedy was completed in June 1999.
Field work for the soil cleanup began in June and was progressing well when the period of
performance for that contractor expired in December 1999. Work resumed under a new contract
with the last of the excavation/off-site disposal effort taking place in January 2002 and the final
backfilling/landscaping effort completed in March 2002. The design of the groundwater remedy,
which includes an extensive hydrogeologic investigation, is ongoing. It is expected that the design
will be completed next year.
Site Facts: The State ordered Cosden to clean up on-site spills and to remove and dispose of the
drums three different times (1981, 1984, and 1985). The company began to comply with the 1985
order but later abandoned the effort. The plant continued to operate on a small scale intermittently
until EPA began removal activities in spring 1989. The owner of the site died in 1992, and the small
amount of money in his estate did not warrant a cost recovery action.
Cleanup Progress	(Actual Cleanup Underway)	
After the site was put on the NPL in 1987, the EPA undertook a removal action. The first action was
the construction of a fence to secure the site from trespassers. This was followed by the removal and
COSDEN CHEMICAL CORP.
2
May 2002

-------
offsite disposal of 75 lab pack drums, 300 fifty-five gallon drums, 2,000 gallons of bulk liquids, and
350 empty containers ranging in size from 5 gallon pails to fifty-five gallon drums.
In the September 1992 Record of Decision, EPA chose three specific remedies to deal with the
contamination that existed (1) above ground, (2) in the soil, and (3) in the groundwater. These
activities are now being addressed as 3 separate, operable units. The remedial action for OU-1,
decontamination, demolition and disposal of all on-site structures, equipment and debris, was
initiated in May 1995 and completed 7 months later, ahead of schedule and below budget. The
quantities removed were as follows: 776 tons of contaminated building debris, 310 cubic yards of
asbestos-containing material and 1.4 tons of PCB-contaminated material.
Actual on-site remedial activities for the operable unit addressing soil took place from June 21 to
December 16, 1999. During that six-month time frame 9,000 tons of soil, 1,800 tons of debris and
3,000 gallons of liquid waste were safely removed from the site. Under a second remedial contract,
which spanned the period January 2000 to March 2002, an additional 987 tons of contaminated soil
was removed, along with 724 tons of PCB contaminated soil and one buried drum of liquid waste.
After the excavation/removal work was completed, clean fill, top soil, regrading, vegetation and
young trees were added to give the site a park-like appearance.
Site Repository
Beverly Municipal Building, Broad Street, Beverly, NJ 08010
COSDEN CHEMICAL CORP.
3
May 2002

-------