A.

o

Community Update #52
Pompton Lakes Study Area
Pompton Lakes, New Jersey

Pompton Lake Dredging

Community Update

August 2017

EPA CLEANUP ACTIVITIES
Basic Site Information—2017

The scope of work in 2017 involves
hydraulic dredging, processing and
off-site disposal of sediment con-
taining mainly mercury and lead in a
36-acre area within Pompton Lake
called the Acid Brook Delta (ABD).
Placement of the eco-layer in Area
A, the Island Area and the ABD will
also be completed. The work will
be performed by The Chemours
Company FC, LLC., through its
contractor, Sevenson Environmental
Services with EPA/NJDEP over-
sight.

Further information:

Boronph of Pompton Lakes

http: //www .pomptonlakesgov. com

Questions? Please Contact:

EPA Remedial Project Manager

Perry Katz

(212) 637-4426

katz.ira-perry@epa.gov

EPA Community Involvement
Coordinator

Pat Seppi
(646) 369-0068
seppi .pat@epa.gov

EPA's 52nd update is to inform the community of the progress of activi-
ties related to the dredging that is being performed on the 36-acre portion
of the Pompton Lake Study Area known as the Acid Brook Delta (ABD).

Activities performed (week of August 7th):

~	Continue hydraulic dredge operation including sediment dewatering
and material handling.

~	Continue trucking of dredged material to the off-site landfill facility.

~	149 trucks of material sent to landfill between August 4th and August
10th with a total of 1325 truckloads to date.

~	Continued perimeter monitoring—data on website (http://
www.pomptonlakesworks.com/pompton-lake-project/environmental-
monitoring/

~	No exceedances of dust/ mercury vapor/turbidity action levels during
monitoring associated with site activities

Activities scheduled (week of August 14th):

~	Continue hydraulic dredging operation.

~	Continue sediment dewatering and material handling.

~	Continue load-out and off-site disposal of dredged sediment.

~	Continue perimeter air monitoring and lake turbidity monitoring in
accordance with approved Work Plan.

~	Continue routine inspection of site /work areas per approved permits
and for safety purposes.

Note:

On Saturday, August 12th, there WILL BE maintenance work per-
formed from 8AM until 5PM. There WILL NOT BE dredging/water
processing activities or sediment loading/trucking.

Additional information has been added to the aforementioned website
including analytical results from treated water discharged to Pompton
Lake under the NJDEP permit as well as a figure depicting dredging
progress.

Two photos are provided: one shows a view including the hydraulic
dredge and the sediment processing equipment.

The second photo shows coarse material that has been separated from
the dredged sediment that will undergo further processing/treatment.


-------