Eastern Diversified Metals Superfiind Site

Hometown, Schuylkill County, Pennsylvania

- Cleanup Construction Completed -

U.S. Environmental Protection Agency Region 3 Community Update

October 27, 2008

Operable Unit 4 Construction Completed

The United States Environmental Protection
Agency (EPA) is overseeing ongoing cleanup
activities at the Eastern Diversified Metals (EDM)
Superfund Site, located near Rush Township, PA.
The Site is categorized into four parts, called
Operable Units (OUs).

•	OU-1: Contamination "Hot Spots," (patches of
areas of a site found to contain a certain
contaminant at levels that are not prevalent
throughout the rest of the site)

•	OU-2: Groundwater Contamination

•	OU-3: Main Fluff Pile (recycling project that
was rejected), and then,

•	OU-4: Main Fluff pile (impermeable cap).

In September 2008, construction activities for OU-4
were completed.

Work Done to Date

The Potential Responsible Party (PRP), with EPA's
oversight, completed construction work of the fluff
pile cap. Work included:

0 Consolidating about 20,000 cubic yards of
impacted perimeter soils into the fluff pile for
containment,

0 Excavating and Restoration of about 625 linear
feet of the unnamed tributary that flows into the
Schuylkill River,

0 Re-shaping, re-grading the pile,

0 Installing a multi-layered impermeable cap, that
i solates and contains the fluff pile onsite,
(equivalent to approximately 12.4 acres in size),

0 Installing surface water and storm water
controls to divert water runoff into designated
drainage ditches,

0 Adding about two feet of clean soil over the
capped area

0 Importing about 75,000 cubic yards of clean
soil for construction purposes,

0 Seeding the capped area with native vegetation,
and,

0 Installing about 4,500 feet of fencing around the
Site's perimeter, to secure the Site and help
eliminate potential trespassing.

EPA is also overseeing the PRP's ongoing cleanup
activities of collecting and treating both shallow
groundwater and leachate from underneath the fluff
pile. The amount of leachate will decrease with
time, now that the cap is completed and the
opportunity for water to trickle through the fluff
pile is eliminated.

A total of approximately 21 acres have been
restored onsite, including about one acre of
floodplain. (See photos on page 2)

Photo to the right: Pre-construction aerial photo of Site.

BERNARD
GORDON

FLUFF PILE


-------
Photo 1: Installing storm water controls December 2006











v„









=

Photo 2: Same view as #1, after cap construction completed September 2008


-------
Next Steps

Background

Now that the construction of the cap is finished,
cleanup activities will include:

~	Continued semi-annual groundwater sampling, to
monitor levels of Site-related contaminants,

~	Continued treatment of collected leachate and
shallow groundwater,

~	Continued routine operations and maintenance
(O&M) of wastewater treatment facility by PRP per-
sonnel,

~	Continued monitoring of treated discharge into
the Little Schuylkill River, and

~	Routine cap inspection and maintenance to moni-
tor for settlement, vegetation progress and erosion
controls,

~	EPA will also continue to conduct Five-Year Re-
views at the Site; an inspection to help ensure that the
remedy in place remains protective of human health
and the environment,

~	Institutional Controls will be necessary, mean-
ing any re-use of the land will be limited in the
sense that it must not interfere with the cap's integ-
rity and wastewater treatment system.

•	The Eastern Diversified Metals (EDM) Superfund
Site is a former wire recycling facility. From
1966 until 1977, the now-bankrupt EDM Corpo-
ration reclaimed copper and aluminum from wire
and cable.

•	During operations, the company disposed of ap-
proximately 350 million pounds of insulation ma-
terial (plastic stripping) commonly called "fluff
in an open pile.

•	The fluff contained elevated levels of lead, bis (2-
ethylhexyl) phthalate (DEHP), and polychlori-
nated biphenyls (PCBs). The fluff may also con-
tain dioxins as a result of past on-site fires. These
contaminants are considered to pose potential
health hazards.

•	The Site was added to the EPA National Priorities
List (NPL), designating it as a Superfund Site,
making it eligible for federal cleanup funding.

•	EPA has entered into a Consent Decree with the
Potential Responsible Parties (PRPs), requiring
the PRPs to conduct the cleanup with EPA over-
sight.

•	EPA has, and will continue to work with Pennsyl-
vania Department of Environmental Protection
(PADEP) and the Army Corps of Engineers
(USACE) on the oversight of Site activities.


-------
For More Information

Please visit the EPA webpage for the Eastern Diversified Metals (EDM)

Superfund Site at:

www.epa.iiov/reii3hwmd/super/sites/PAD980830533/index.htm.

If you have questions about the EDM Site,
please contact:

Frank Klanchar	Trish Taylor

Remedial Project Manager	-or- Community Involvement Coordinator

(215) 814-3218	(215) 814-5539

klanchar. frank@epa. gov	taylor. tri sh@epa. gov

EPA Update for the Eastern Diversified Metals Superfund Site

U.S. Environmental Protection Agency Region 3
(§ A 1650 Arch Street (3HS52)

Philadelphia, PA 19103
Attention: Trish Taylor


-------