V
SEPA
GREEN
POWER
PARTNERSHIP9
Aligning Green Power Partners with New Renewable Energy Projects
Pilot Project Summary
Project Name
Apple Blossom Wind Farm
Developer Name:
Geronimo Energy
Contact:
Drew Terwilliger, drewffigeronimoenergy.com
Renewable Energy Type:
Wind Farm
Total Planned Megawatt Size:
100 MW
Project Location:
Huron County, Michigan
Is the project permitted?:
Yes, all portions of the public permitting have been completed. Project is ready to move into final
permitting stages.
If no, what is the permit status?:
Yes, all portions of the public permitting have been completed and the project has a commercial
operation date of 12/31/2014.
What is the status of the project's site?:
The Apple Blossom Wind Farm Project is located in Michigan's Thumb region, the area with the highest-
quality wind resource in the state. The Apple Blossom project is situated on approximately 10,275 acres
of farmland and will consist of between 43 and 66 wind turbines.

-------
Have land leases been filed with the county?:
Yes, Geronimo currently has 10,275 acres under full lease, representing 100% of the land needed to site
the 100 MW Apple Blossom project. The local team is working on an additional 1800 acres that could
potentially enhance the project. Geronimo has entered into signed agreements with landowners in the
form of Land Lease and Wind Easement. Land leases have been filed with the county.
What is the status of interconnection, and have system impact and facility studies been completed?
(Distribution or transmission level projects are both eligible):
Apple Blossom will connect to the new Thumb loop 345kV double circuit transmission line that is
currently under construction in Michigan. A system Impact Study and Facilities Study has been
completed for the Apple Blossom Project.
Apple Blossom will receive 100MW of Network Resource Interconnection Service (NRIS) and will have a
non-provisional generator agreement.
Due to a $510 Million project designed to fulfill an order of the Michigan Public Service Commission to
plan transmission to deliver up to 4,236 MW of wind from the thumb area, it is anticipated that there
will be ample capacity in the thumb area resulting in very low congestion costs, losses, and curtailment
risks for the Apple Blossom location.
Does the transmission owner (TO) or independent system operator (ISO) have a process to study the
project's impact on the local or regional grid and the subsequent cost to interconnect?:
Yes, the Midwest Independent System Operation (MISO) performs a Feasibility Study, System Impact
Study, and Facilities Study before executing an Interconnection Agreement. All of the studies and the
Interconnection Agreement have been completed for the Apple Blossom Wind Farm.
Environmental Impact Statement status:
Apple Blossom has been designed to have low environmental risk. The Project is located on
predominately agricultural land which is compatible with wind energy development. This design is
based on detailed environmental review of the site for wetlands, avian activity, bat activity and the
regional infrastructure system. These studies have been underway since February 2011. Geronimo is
currently developing operational plans to ensure that this low environmental impact continues through
the life of the project.
Is any element of the project - technology or other - experimental or pilot-phase?:
No, the project will use existing, proven technology. No part of the project will be experimental or pilot-
phase.
What is the long- and short-term operations program of the project? Does the renewable energy
technology manufacturer have a technical support team locally available?:
The project will have a 5 to 10 year operations and maintenance agreement with the turbine supplier.
The turbine supplier's maintenance team will be located near the project. Discussions with multiple
turbine suppliers are currently underway, no turbine supplier has been chosen as of yet, so exact details

-------
are still subject to change. After the O&M agreement with the vendor expires, the operations and
maintenance work will be provided by a third party vendor, the turbine vendor under an extended or
new O&M agreement, or internal staff of Geronimo or our strategic partner Enel Green Power.
For wind projects, has a meteorological tower been installed, and when was the tower installed/how
much data has been collected?:
Two meteorological towers have been installed on the Apple Blossom Wind Project. In all,
approximately 120 months worth of data have been collected at the Apple Blossom site.
Analysis of the on-site data indicates an expected annual average wind speed across the site of 7.3 m/s
at a hub height of 100 meters.
Who has analyzed the data and what is that person's experience with respect to projects that have
actually been financed?:
Geronimo Wind Energy has worked with leading international renewable energy consultant GL-Garrad
Hassan (GH) to analyze the wind resource of the project. GH has nearly three decades of experience
analyzing renewable energy projects, from initial design to investment-grade due diligence. GH has
acted as the technical advisor for more wind energy financial arrangements than any other company
worldwide.
Internal analysis of Energy's projects is performed by Michael Morris. He has analyzed approximately
2,000 MW of proposed wind capacity and over 600 MW of operating wind capacity. Of the proposed
capacity, approximately 350 MW have received or are in the process of obtaining third-party financing.
Mr. Morris holds Bachelor's and Master's degrees in Meteorology from the University of Oklahoma.
Can the turbine manufacturer be financed through "traditional" tax equity and debt in the U.S.?:
The majority of turbine manufacturers we are currently negotiating with are considered "Tier 1" vendors
and can be financed through traditional tax equity and debt in the United States. The other turbine
vendors under consideration can be financed through other means (i.e. self-financing or credit
enhancement to entice traditional financing) and that is taken into account when selecting a turbine
vendor.
Provide a short summary of how the project views project finance and structure/ownership:
We expect the project to be built, owned and operated by our strategic partner Enel Green Power North
America "EGPNA," the second largest renewable energy generator in the world. Though EGPNA has
employed tax partnership structures from time to time to monetize tax benefits for its wind project,
EGPNA typically self-finances construction of its project as opposed to partnering with third party
financiers and intends to do the same with the Apple Blossom Project although it reserves the right to
consider other financing options.
What are your ideal types of prospective institutions/partners?:
We would like to partner with institutions that are willing and capable of entering into contracts of at
least five years in duration for at least 25,000 megawatt hours (MWh) per year of renewable energy and
affiliated renewable energy credits (RECs), equal to approximately 7 MW of nameplate capacity from
this project. It is preferable if the partner has an investment grade credit rating.

-------
About Geronimo Energy
Geronimo Energy (Geronimo) is a utility-scale wind energy developer based in Edina, Minnesota.
Geronimo has developed three operating wind farms in Minnesota. Geronimo has a development
pipeline of wind farms in various stages of development throughout the Midwest with an aggregate
nameplate capacity exceeding 4,000 megawatts of clean energy -roughly enough to power 1.5 million
American homes. Geronimo also has a strategic partnership with Enel Green Power, the second largest
renewable energy generator in the world. This partnership gives Geronimo all of the capabilities and
financial strength necessary to bring its projects to fruition.
More information is available on Geronimo is available at www.geronimoenergy.com.

-------