v>EPA
United States
Environmental Protection
Agency
Work Breakdown Structure-Based Cost Model
for Biological Drinking Water Treatment
Office of Water (4607M)
EPA ***_*_*****
June 2019
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Table of Contents
1. Introduction 1
1.1 Background 1
1.2 Objectives 1
1.3 Organization of the Report 2
1.4 List of Abbreviations and Symbols in this Chapter 2
1.5 References 2
2. WBS Model Overview 3
2.1 Model Structure 3
2.2 The WBS Approach 8
2.3 Model Use 10
2.3.1 Input Sheet Structure and Use 10
2.3.2 Common Inputs 13
2.3.3 Input Sheet Examples 16
2.3.4 Output Sheet Structure and Use 18
2.3.5 Critical Design Assumptions Sheet Structure and Use 18
2.3.6 Index Sheet Structure and Use 21
2.4 General Cost Assumptions 22
2.4.1 Building Costs 24
2.4.2 Residuals Management Costs 24
2.4.3 Indirect Capital Costs 25
2.4.4 Add-on Costs 26
2.4.5 Annual O&M Costs 27
2.4.6 Total Annualized Cost 28
2.4.7 Updating and Adjusting Costs 28
2.5 List of Abbreviations and Symbols in this Chapter 29
2.6 References 29
3. Biological Treatment Model 31
3.1 Overview of the Biological Treatment Process 31
3.2 Input Sheet 34
3.3 Model Assumptions Sheets 46
3.4 Bioreactor Constraints Sheet 49
3.5 Chemicals Sheet 49
3.6 Biomass Control Sheet 49
3.7 Post-Treatment Sheet 50
3.8 Pumps, Pipe and Structure Sheet 50
3.9 Instrumentation and Control Sheet 51
3.10 Residuals Management Sheet 51
3.11 O&M and HVAC Sheets 52
3.12 Indirect Sheet 53
3.13 Output Sheet 53
3.14 Ancillary Model Components 54
3.15 List of Abbreviations and Symbols in this Chapter 54
3.16 References 54
Appendix A. Valves, Instrumentation and System Controls 56
Appendix B. Building Construction Costs 62
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Appendix C. Residuals Management Costs 71
Appendix D. Indirect Capital Costs 80
Appendix E. General Assumptions for Operating and Maintenance Costs 103
ii
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
1. Introduction
This report is one of a series of reports describing cost models for drinking water treatment
technologies. Most of these technologies are used in drinking water systems to remove or destroy
pollutants such as arsenic, radon, disinfection byproducts, sulfates, hardness and waterborne
pathogens. In addition, several of these technologies can be used as add-on technologies to
existing treatment systems. For example, some of the technologies can be installed to provide
pre-oxidation to improve contaminant removal efficiency by subsequent treatment processes.
1.1 Background
The Safe Drinking Water Act Amendments of 1996, as well as a number of other statutes and
executive orders, require that the U.S. Environmental Protection Agency (EPA or the Agency)
estimate regulatory compliance cost as part of its rulemaking process. EPA developed the models
described in this document to assist in fulfilling this requirement. In other words, the primary
purpose of these models is to aid EPA in estimating national compliance costs. The models
might be acceptable, however, for other uses (e.g., developing a preliminary site-specific
estimate for a water system) if sufficient care is taken to account for site- or project-specific
factors appropriate to the intended use.
The compliance cost models described in this document differ from the drinking water cost
models previously used by the Agency in that the new models are based on a work breakdown
structure (WBS) approach to developing cost estimates. In general, the WBS approach involves
breaking a process down into discrete components for the purpose of estimating unit costs. EPA
pursued this approach as part of an effort to address recommendations made by the Technology
Design Panel, which convened in 1997 to review the Agency's methods for estimating drinking
water compliance costs (U.S. EPA, 1997).1
1.2 Objectives
In developing WBS-based models for estimating drinking water treatment system costs, EPA
had the following objectives:
• Transparency of process design and cost
• Defensibility of design criteria and assumptions
• Ease of use and updating
• Modularity of components for use with centralized cost database.
The Agency determined that the best way to meet these goals was to develop spreadsheet-based
engineering models drawing from a central database of component unit costs. Each engineering
model contains the work breakdown for a particular treatment process and preprogrammed
engineering criteria and equations that estimate equipment requirements for user-specified design
requirements (e.g., system size and influent water quality). Each model also provides unit and
total cost information by component (e.g., individual items of capital equipment) and totals the
1 The panel consisted of nationally recognized drinking water experts from U.S. EPA, water treatment consulting
companies, public and private water utilities, suppliers, equipment vendors and Federal and state regulators in
addition to cost estimating professionals.
1
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
individual component costs to obtain a direct capital cost. Additionally, the models estimate add-
on costs (permits, pilot study and land acquisition costs for each technology), indirect capital
costs and annual operating and maintenance (O&M) costs, thereby producing a complete
compliance cost estimate.
1.3 Organization of the Report
This report is organized as follows:
• Chapter 2 provides an overview of the general model components and the methods used
in these components to estimate treatment system costs.
• Subsequent chapters describe the individual models, design criteria and assumptions for
the selected treatment technologies.
• Appendices provide additional information on methods EPA used to estimate design
requirements and costs for specific components, such as buildings, system controls,
indirect capital costs and annual O&M costs.
1.4 List of Abbreviations and Symbols in this Chapter
EPA U.S. Environmental Protection Agency
O&M operating and maintenance
WBS work breakdown structure
1.5 References
U.S. Environmental Protection Agency (U.S. EPA). 1997. Discussion Summary: EPA
Technology Design Workshop. Washington, D.C.: U.S. EPA, Office of Groundwater and
Drinking Water.
2
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
2. WBS Model Overview
This chapter includes the following sections:
• An overview of how the models are structured (Section 2.1)
• A description of how this structure was developed using the work breakdown structure
(WBS) approach (Section 2.2)
• A brief users guide describing how to operate the models (Section 2.3), including
documentation of general design assumptions
• Documentation of the general cost assumptions incorporated in all of the models (Section
2.4).
2.1 Model Structure
The WBS-based engineering models integrate the following structural features to generate
treatment cost estimates:
• Treatment component selection, design and cost output based on a WBS approach
• Process design based on state-of-the-art techniques and generally recommended
engineering practices (GREPs)
• A centralized reference database containing unit costs for components and reference
tables for component sizing and chemical properties.
Exhibit 2-1 shows how these features are integrated in a series of spreadsheets that include an
Excel workbook for each technology and a central cost and engineering reference database (the
WBS cost database).2 An input sheet allows the user to define treatment requirements such as
system design and average flows, target contaminant and raw water quality. Exhibit 2-2
provides an example of an input spreadsheet. The information provided via the input sheet
interacts with three critical design assumptions sheets (one each for process design, operating
and maintenance [O&M] and indirect capital costs) to generate inputs to the engineering design
sheets. Although the critical design assumption values are based on GREPs and can be used
without modification, the user can also revise these values to reflect site-specific requirements.
Each model also has a predetermined list of treatment equipment needs (e.g., tanks, vessels and
instrumentation) identified using the WBS approach. The engineering design sheets calculate
equipment quantity and size requirements based on the treatment needs and critical design
assumptions. The technology chapters of this report describe technology-specific content and
function of each sheet. General design and cost assumptions are described in Sections 2.3.5 and
2.4.
2 EPA maintains the central WBS cost database in a separate Excel workbook. The WBS cost database itself is not
provided along with the publicly released WBS models. Instead, for ease of review and to maintain vendor
confidentiality, relevant cost and engineering data have been extracted from the database and included directly in the
WBS model workbooks. Thus, users can review (and adjust, if needed) the information from the central cost
database in the same manner as other WBS model inputs and assumptions.
3
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit 2-1. Structure of the WBS Models
4
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit 2-2. Sample of Input Spreadsheet
MULTI-STAGE BUBBLE AERATION SYSTEM DESIGN AND COST INPUT
STEP 1
Select Contaminant
~I For VOCs, default designs available up to 1 MGD only, because information on using MSBA for these contaminants in larger systems is limited
Select one of the eiqht standard desiqns at right
OR
Select "CLEAR FOR MANUAL ENTRY"
STEP 3:
/Qptiertz! f&r stwtdwd dtfiqrts}
Enter or change values in the and t ¦: cells below,
under "Manual Inputs"
0.030 mgd standard design
<- Usiag this desiga
0.124 mgd standard design
0.305 mgd standard design
0.740 mgd standard design
2.152 mgd standard design
7.365 mgd standard design
22.614 mgd standard design
75.072 mgd standard design
CLEAR FOR MANUAL ENTRY
See model documentation for more information on standard designs
Ikpit Complete — Rtsilti Ready
STEP ~:
Results arc ready (no need to click button"!
Generate Results
iLlii
OUTFIT ihaK for detailf)
MANUAL INPUTS
CcffsM f*Qwr&t tilts iti i '. wi- cptiet&f
Direct Capital Cost: $107,797
Total Capital Cost: {158,397
Annual OScM Cost: $7,292
Annualized Cost: $23.629 f16.9 uears at 7%1
Dtsiqi Flow
Average Flow
I Select units
For iiforaatioi:
Treatment system design flow r
Bypass design flow r
0.030 MGD
0.007 MGD
0.030 TlGD
0.000 llGD
Current bypass percentage is 0%. Go to Critical Design Assumptions to change this value.
Adjust bypass percentage
Optimise Number
of Basins
Deiiqi Tfpe
pre-eaqiaeered packaqe
<— pick on*
Vendor packages include aboveground stainless steel, plastic, or fiberglass basins and typically are used
by small systems
Niabtr of operatiiq basils
Air to water ratio
1
40
3
8
Guidance: For VOCs, typical air to water ratios are between 10:1 and 300:1
MaiiaiH water depth
Guidance: VOCs require no more than 2 to 3 feet water depth, beyond this depth no significant gain is
realised (Lowry peer review comments)
Guidance: for VOCs, minimum of 6 stages, maximum of 12 stages, vendor uses 8 stages for most
applications (Lowry peer review comments)
Niabtr of stiqts
Pilot rale coistatt
0.1T
Umir.
Pilot air iateasit*
2.54
cfm'cubicft
For itforaatioi:
Estimate only, based on pilot rate constant and air intensity. To increase, increase air to water ratio and/or
Theoretical Percent Removal
90.0T%
number of staqes
Number of Basins (including redundancy)
1
units
Basin
.cngth (including quiescent chamber)
4
feet
Basin Width
2.5
feet
Basin height (including freeboard)
5
feet
Adjust freeboard
Diffusers per stage
1
units
Total diffusers
8
units
Adjust basin length constraints
B»i» Itpits OK
Adjust diffuser access space requirements
5
uVL
Pert eat rem o rj/
not required
VOC release at which air pollatioa control 1
sfftta is seeded
ItrMny
For iafor»atioa: Off-gas
oatrol syste* nay
lot be reqaired
fieit reco rer? tppe
Spe*t GAG re
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit 2-3 shows an example of an output spreadsheet. The output sheet summarizes the results
of the calculations performed by the engineering design sheets, listing size and quantity required
for each item of equipment and the corresponding unit cost from the database. The output sheet
multiplies unit cost by quantity to determine total component cost for each WBS component. The
output sheet also lists the estimated useful life of every WBS component. The models use the
component useful lives in estimating total annualized cost (see Section 2.4.6).
For many of the components, there are optional materials, all of which are illustrated on the
output worksheet. For example, pressure vessels can be constructed with different types of body
material (stainless steel or carbon steel) and different types of internal materials (stainless steel or
plastic). Where there are optional materials, the output sheet selects from among these materials.
The specific selections are determined by input values and documented in the "use?" column of
the output worksheet. Direct capital cost is the sum of the selected component costs.
The output sheet also contains sections that calculate add-on costs, indirect capital costs, annual
O&M costs and total annualized cost. Annual O&M costs are based on the annual requirements
calculated on the O&M sheet. Indirect capital costs for certain items (standby power,
geotechnical, site work and yard piping) are based on calculations performed by the indirect
sheet. Other indirect capital costs and add-on costs are based on assumptions described in
Sections 2.4.3 and 2.4.4. Section 2.4.6 describes the calculation of total annualized cost.
The output sheet obtains unit costs (both capital and O&M) either from the central WBS cost
database or from estimated equipment cost curves. All of the treatment technology models use
information from the WBS cost database, which consists of a series of lookup tables that contain
costs by equipment or O&M element type and size. The database also provides useful life
estimates and documents the source of information. The central WBS cost database also contains
several tables that are used by the engineering design sheets of each model. For example, these
tables include information used in selecting pipe diameters, footprint for pumps and chemical
properties.
The WBS cost database itself is not provided along with the publicly released WBS models.
Instead, for ease of review and to maintain vendor confidentiality, relevant cost and engineering
data have been extracted from the database and included directly in the WBS model workbooks.
Thus, users can review (and adjust, if needed) the information from the central cost database in
the same manner as other WBS model inputs and assumptions.
6
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit 2-3. Sample of Output Spreadsheet
OUTPUT SUMMARY
PJY*ufer.w#A«,#«
f/xr t.i j- "i irj-:'' fxuWr-jt, rs-t-rj«t»
U.it Cut
Tit<
Cut Ur»f«
Lif *
1
Ure>
T.1 Curtom De*iqned
it.t
Cbr>crft#
fi imkitr
am
AM
AM
AM
t li-
£\COl'OtfJH>
jm
AM
AM
ASJ*
tis
So eh/iif vs.- l1' Cnmf- o c
AM
AM
AM
Avf
StA/J Cotw
- -r/
AM
AM
AM
AM
U.t
St oMmt StJsis'
t 1w'tr
-W foJ
JW f oi
*
*
fi-V
fi
1.2.1
Pl«rtic
1 »itr
374 ftl
374 Ml
t
2.114
«
2.114
7
1
t.i\i
t imi'
-?JV oof
ST4 to/
*
£$£!&
*
//>
fi
T.3
Beffle*
1.3.1
B«fflu
* »itr
12.5 xffl«ffl*
12.5
1
123
*
4*2
7
1
*4
1.4.1
Diffvtn
* ititr
14 cfB
14 cf.
*
44
*
345
1*
1
2-
13 ir-
13 1»-
4,511
9.432
17
ADDITIONAL WBS COMPONENTS NOT SHOWN
f£i-ot f-wxrf-
am
AM
AM
AM
AM
*_7
2 cr
2 c7
*57
1.314
37
1
Direct -cut cat^iHij
T ¦ t«1 Giidakce
Procexx cartr
$ 101,53$ Excluder alternate c
irt line itemr in itelicr, uithout e
in the "U*e?" column. In<
ludex
retaliation, t
enrportet
on, end O&P
Buildinq cortr
$ 6,259 See indirect e**umpt
onrxheet to exclude buildinq*
Total direct capital cost
~107.797 Totel of procexx end
uildinq coxtx
Add-on Cost Details
vrr.f-1 tjoj-xcfvcb-Sx-
JfivJwofoJif-t
AJI-» Lit* It*.
T>t«l
G«id«kt*
Permit*
t
111
Pilot Study $
No pilot*tudy required for thix techr.oloqy
Lend Cart
*
92«.
For 0.04 ecre*
Total add-on costs
~1.038
Totel of permit*, piloting, end lend
Indirect Capital Cost Details /f*jst*ct arsnow.tfiu^rj-i^j-tta^vofu^xntA'i»juof>r, etfrs-rt>t/-mri
Udir*ct Lib* It*. T¦ t a 1 P*rc»>t G«id«c*
Architecture! Feex for Treetment Building
Qy. Excluded by defeult forxmellxyxtemr
Site Work
t 1,423
Verd Piping
t 1,107
Celculeted bered onxyxtem requirement*.
Stendby Pouer
Celculeted bered onxyxtem requirement*. Excluded by defeult forxmellxyxtemr.
Electricel (including yerd uirinq)
$ 10,154
10:-: Percente-qe ir epplied only to procexx cart. Buildine direct cartr include electricel component*.
Ox
t 21,559
20*
Mixcellcneoux Allouence
$ 10,740
10x
t 2,156
Zy.
Selex Tex
Ox
Finencinq during Conxtruction
Ox
Conrtruction Meneqement end GC Ouerheed
t 2,383
Include* bond end inrurence only far pre-enqineered peckeqer
Total indirect capital cost
~50.162
Tatel af indirect line itemr
TOTAL CAPITAL COST DETAILS
Tala* Gaidaac
*
City Index
Ureredju*
eble.Cen
e u*ed to edjurt e
1t. m.r. -f .
Capitel Cut Ceteqary
T.tal
Totel Direct Cepitel Cart (from eboue)
t
107,737
Totel Add-ar, Cart (from eboue)
i
1,033
Totel Indirect Cart (from above}
t
50.162
Grand total capital cost «;*?»>¦
~ 158.997
Annual Operating and Maintenance Cost Details Afw
vwM'cr, wt&But o A
tls- 'tirs:
r,t oftj-r.'.ots- cartr or- J or J- j\y civ
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
2.2 The WBS Approach
These models represent improvements over past cost estimating methods by increasing
comprehensiveness, flexibility and transparency. By adopting a WBS-based approach to identify
the components that should be included in a cost analysis, the models produce a more
comprehensive assessment of the capital requirements for a treatment system. The models are
flexible in that users can change certain design parameters; warning messages indicate when user
inputs violate GREPs or logical functions. The transparent structure of each model allows users
to see how costs are built up from component unit costs to total treatment costs, which enables
users to identify cost drivers and determine whether the input assumptions generate a cost-
effective treatment design. Users also can perform sensitivity analyses showing how changes in
water quality parameters, chemical feed doses and equipment configuration affect cost.
Unlike prior EPA models, which used a variety of cost build-up methods, the WBS-based
engineering models have been developed using a consistent framework. Exhibit 2-4 shows this
framework. For each technology, the result is an engineering spreadsheet model that combines
user-identified inputs with pre-programmed engineering criteria and equations to generate
appropriate treatment design and equipment requirements. The models also result in a system-
level cost estimate for regulatory cost analysis.
Exhibit 2-4. Framework for Developing the WBS-Based Models
Step
Process
Step 1
Identify the treatment requirements based on the contaminant requiring removal, the flow for which treatment is
required, the influent water quality and treated water quality requirement, and then select a treatment technology
or combination of technologies capable of meeting the requirements.
Step 2
Develop the general design assumptions that apply to all the technologies (e.g., chemical storage capacity).
Step 3
Develop site- and technology-specific design assumptions that might affect treatment performance and, thereby,
design requirements (e.g., assumptions related to influent water constituents such as alkalinity or water quality
parameters such as pH).
Step 4
Construct a typical process flow diagram or P&ID showing the main unit processes for the technology and identify
equipment requirements.
Step 5
Calculate the equipment requirements, including dimensions and quantities, for the core elements of each unit
process. At each component (or group) level, identify choices of material (e.g., stainless steel or PVC pipe
material).
Step 6
Link the treatment equipment requirements to a database that contains unit costs by equipment type, size and
material. Multiplying the unit costs by the dimension and quantity requirements developed in Step 5 provides the
component-level design costs.
Step 7
Tally the costs of the selected components to determine direct capital cost.
Step 8
Develop and add indirect and add-on costs to determine total system capital cost.
Step 9
Develop operation and maintenance cost estimates.
The WBS approach provides EPA with a consistent method for identifying components to
include in a cost estimate. For each technology, the WBS approach develops a process and
instrumentation diagram (P&ID) or a typical schematic layout showing the main unit processes
needed to achieve the contaminant removal goals.
Exhibit 2-5 provides examples of several classes of components that can be included in a P&ID.
The models often include further breakdown for alternative materials of construction for each
component, because costs can differ substantially across materials. For example, most pipes can
8
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
be constructed of stainless steel, steel, polyvinyl chloride (PVC) or chlorinated PVC. Stainless
steel piping can cost twice as much as PVC.
Exhibit 2-5. Component Classes Included in the WBS Inventory
Component Classes
Example Components
Vessels
Pressure vessels
Tanks/basins
Storage
Backwash
Mixing
Contact
Flocculation
Sedimentation
Filtration
Pipes
Process
Backwash
Chemical
Inlet/outlet
Bypass
Valves (see Appendix A for further details)
Check (one-way)
Motor- or air-operated
Manual
Pumps
Booster
Backwash
High-pressure (for membrane systems)
Chemical metering
Mixers
Rapid
Flocculation
Inline static
Instrumentation (see Appendix A for further details)
Pressure gauge
Level switch/alarm
Chlorine residual analyzer
Flow meter
pH meter
Air monitor/alarm
High/low pressure alarm
Gas flow meters—rotameters
Scales
System controls (see Appendix A for further details)
Programmable logic control units
Operator interface equipment
Controls software
Chemicals
Acids
Bases
Coagulants and coagulant aids
Antiscalants
Corrosion control
Oxidants and disinfectants
Treatment media
Activated alumina
Activated carbon
Membranes
Sand
Resins
9
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Component Classes
Example Components
Building (see Appendix B for further details)
Structure
Heating and air conditioning systems
Concrete pad
Indirect Capital Components (see Appendix D for further
details)
Geotechnical investigations
Standby power generators
The level of component detail (and by implication, design detail) in Exhibit 2-5 indicates that
the WBS-based approach is more sophisticated, and potentially more time consuming, than the
factored or parametric cost estimating methods used in earlier efforts. Nevertheless, the
Technology Design Panel considered it the right approach to developing unit costs for policy
analysis. Furthermore, EPA believes that developing unit cost models that are more
comprehensive, flexible and transparent will facilitate the policy analysis process by addressing a
frequent topic of dispute over regulatory cost estimates. Finally, the WBS-based models are
driven by technical scope and selection of suitable equipment and material to achieve a defined
treatment objective. This approach is superior to cost estimating methods that are not defined by
a desired treatment level or that cannot be changed easily to reflect raw water quality.
2.3 Model Use
This section provides basic guidance on operating the WBS technology models. As discussed
above, each model is an Excel workbook comprising a series of spreadsheets. In general, users
need only be concerned with the input sheet and output sheet, although advanced users might
also wish to examine the critical design assumptions spreadsheets.
2.3.1 Input Sheet Structure and Use
The input sheet in each of the technology models is similar to that pictured in Exhibit 2-2. A
step-by-step input process allows the user to quickly generate costs for standard designs built
into the model, modify those designs or construct an alternative design.
Overview of the Input Process
Many models require basic information
from the user before choosing an
appropriate standard design. For example,
contaminant selection is the first choice
that must be made in several of the
models. Such choices are made using a
drop-down list at the top of the input
sheet.
After making any basic, top-level choices,
the user can click on one of the eight
standard design buttons. Each button
corresponds to a system size category in
the flow characterization paradigm
described below in Exhibit 2-6. The
model will populate all inputs with values
10
STEP t
Select Oonta-n.nant
STEP 2:
one of the esght starvlvd designs a: nght OR select
'CLEAR FOR ENTRY
Radon
0 030 VIGO <21 gpm)
0 124 MGD i86 gpm)
0 305 MGD *212 gpm* j
0?40 MGO >'514 gpm' ;
>152 MGD 11494 gp.iV. 1
7 365 MGD 115 gpm) ;
22 614 MGD >15 704 gpmj
75 072 MGO (52 13J gpm; ;
CI EAR FOR MANUAL ENTRY"
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
appropriate for the selected design, then compute all costs. The direct capital cost, total capital
cost and annual O&M cost are displayed on the input sheet; details are available on the output
sheet (see Section 2.3.4). More information on the standard designs is provided below.
Exhibit 2-6. Standard Flow Rate Categories Used in WBS Standard Designs
Size Category
Population Served
Design Flow (MGD)
Average Flow (MGD)
1
25 to 100
0.030
0.007
2
101 to 500
0.124
0.035
3
501 to 1,000
0.305
0.094
4
1,001 to 3,300
0.740
0.251
5
3,301 to 10,000
2.152
0.819
6
10,001 to 50,000
7.365
3.200
7
50,001 to 100,000
22.614
11.087
8
Greater than 100,000
75.072
37.536
The standard designs, with their corresponding buttons, are primarily for EPA's use in estimating
costs for a median sized system in each size category, although some users may find them useful
as a starting point (see the examples in Section 2.3.3). The user can modify the standard designs
after clicking one of the buttons by entering values in the gold and blue input cells, under the
"Manual Inputs" heading on the input sheet. Alternately, many users will want to click the button
marked "CLEAR FOR MANUAL ENTRY" and enter all of the input values by hand. In any
case, the manual inputs section contains several types of cells:
• Required user inputs, highlighted in gold
• Optional user inputs, highlighted in blue
• Greyed-out inputs, which are not required for a given design
• Information and guidance, with text in green.
Some inputs, such as system flows, must contain a numeric value. Others have a drop-down
arrow that appears when the cursor is positioned in the input cell. These cells must contain one of
the drop-down values. Required inputs must be populated; optional inputs can be left blank to
accept model defaults or changed by the user to examine the effect of different assumptions. The
Autosize button, described below, is available in some models to facilitate design.
The input sheet in each model verifies user inputs against certain design constraints that reflect
GREPs. If user inputs result in designs that violate these constraints, a warning message appears
on the input sheet, explaining which input value needs to be corrected. In addition, the message
"Input Incomplete—Check for Error Messages Below" appears at the top of the input sheet.
Once all inputs are complete and the
model has verified that they meet design
constraints, the message at the top of the
input sheet changes to "Input
Complete—Press 'GenerateResults'."
The user must click the "Generate
Results" button to tell the model to
generate costs. Once the user has clicked
STEP 3:
(Optional for standard designs)
Etiter or charge values in the
below, under "Manual Inputs"
STEP 4:
•suits Ready
Generate Results
11
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
the button, the message at the top of the model changes to "Input Complete—Results Ready,"
and total costs are displayed on the input sheet. The output sheet provides more details for the
total costs.
Standard Designs
The input sheet in each of the technology
models contains up to eight buttons,
which correspond to the eight standard
flow sizes in the flow characterization
paradigm for public water systems (see
Exhibit 2-6). These buttons populate all
of the input fields with appropriate values
for the selected design flow. The values in
each standard design meet all relevant
design constraints. Each model includes a
separate sheet, entitled "standard inputs,"
that documents the specific input values
included in each standard design.
Advanced users can adjust the standard
designs by changing the values on the
standard input sheet. For example, a user
could change all the standard designs to use high cost components, rather than the default of low
cost components (see Section 2.3.2 under "Component Level"), by changing values in the
appropriate column on the standard input sheet. The standard input sheet highlights values that
have been changed by the user and includes a button ("Reset to Defaults") that resets the
standard designs back to their original settings. Users that make significant adjustments to the
standard designs should take care to verify that their new designs still meet design constraints by
checking for warning messages on the input sheet after each new design is run.
The Autosize Routine
The models also can be used to estimate
costs for systems with design flows other
than the eight standard sizes. To aid in
developing designs for other flows, some
models include a button labeled
"Autosize." This button activates a
computer-aided design routine that
attempts to find a design meeting all
relevant design constraints for a given design and average flow. For example, the user could
change design flow to 3 million gallons per day (MGD) and average flow to 1 MGD, then click
the autosize button. This would populate some input fields with values that are both appropriate
for a 3 MGD system and that meet all design constraints. More information on the autosize
routines, including details on which inputs are and are not populated, is available in the
technology-specific chapters of this document.
STEP 2:
? •. 01 if *- ~ qli{ t «it a* r li OK select
'CLE^R ^ fJAfhui PITb !
0 030 MGD '.21 gpnu
0 1?4 mi) m gpm't
0 305 N?GD <2)2 gpm»
0 740 MGD ;554gpm\
2 1W MGD >1 434 gpm)
7 305 MGD (5 115 gpm)
614 MGD tl5 704 gptrn
75 072 MGD (62 133 gpm!
CLEAR FOR MANUAL ENTRY
Pressure Vessels
The next four inputs may be ent&ied manually, or calculated with Am
Bed depth
Vessel geometry
Length (straight) •
Diameter. . _
For Information;
Auto Size Pressure Vessels
12
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
In the rare case that the autosize routine cannot find a design meeting all constraints, it will
display a pop-up warning message. This does not mean that it is impossible to design a system
for the selected size. The user might still be able to develop a design by manually adjusting the
input values, paying careful attention to the warning messages on the input sheet. It might be
necessary to relax some of the design constraints by adjusting values on the critical design
assumptions sheet.
Manual Input and "Generate Results"
All of the models allow the user to enter input values by typing them directly into the appropriate
fields on the input sheet. Users can develop complete designs from scratch, populating all the
input fields manually. Users also can adjust designs generated by the standard design or autosize
buttons, by adjusting one or more input fields manually after clicking one of these buttons. In
either case, after completing the manual changes, users should do two things:
• Verify that no warning messages appear to ensure that the design meets all relevant
constraints
• Click the button labeled "Generate Results."
The second step is necessary to tell the
models that the design process is
complete and to select the appropriate
items of equipment for inclusion in total
costs on the output sheet. This step is
particularly important if the system
automation or component level inputs
are adjusted manually, because these
inputs have a significant impact on the selection of equipment. To ensure correct calculation of
costs, however, users should click the "Generate Results" button after completing manual
changes to any of the inputs. It is not necessary to click this button when the input sheet message
reads "Input Complete—Results Ready." This message will appear, for example, when the
standard designs or autosize routine are used without subsequent manual changes to input values.
The standard design buttons and the autosize button automatically incorporate the "Generate
Results" step, telling the models to select the appropriate items of equipment.
2.3.2 Common Inputs
The user inputs in each model are largely technology-specific and are described in detail in the
technology chapters of this document. There are certain inputs, however, that are common to all
of the technology models. These common inputs are described below.
STEP 3: _ __
' t un i
" ff|M ' mt.r ¦¦¦¦ >'ipsti|;s
below, under "Manoaf Inputs" [_
STEP 4:
-i i I'.- Gtmosate Results
13
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Design and Average Flow
MANUAL INPUTS
Cells in are required; cells in blue are optional
Select units
Design Flow
0.74 MGD
Average Flow
0.251
MGD
System size inputs OK
Each model needs the design and average flow to determine the size and number of treatment
components needed. Design flow is the peak instantaneous flow of product water from a
treatment system, while average flow is the annual average flow, taking into account daily and
seasonal variations in demand.
Design flow can be entered in MGD or in gallons per minute (gpm). In either case, the design
flow is meant to represent a maximum instantaneous flow. Average flow can be entered in
MGD, in gpm or as a percentage of design flow.
The standard design functions included in each model (see above) can populate design and
average flow with values based on the flow characterization paradigm for public water systems.
The flow paradigm includes eight model size categories, as shown in Exhibit 2-6. These size
categories represent populations ranging from 25 persons to greater than 100,000 persons. Based
on the values in Exhibit 2-6, the ratio of average flow to design flow ranges from 25 percent for
very small systems to 50 percent for large systems.
Component Level
| Component level
|J ~pick or leave blank
low cost
mid cost
high cost
Each model includes an optional input that determines whether the cost estimate generated is a
low, medium or high cost estimate. This input, labeled "component level" or "cost level," drives
the selection of materials for items of equipment that can be constructed of different materials.
For example, a low cost system might include fiberglass pressure vessels and PVC piping. A
high cost system might include stainless steel pressure vessels and stainless steel piping. The
component level input also drives other model assumptions that can affect the total cost of the
system, including assumptions about system automation (see "System Automation" below),
building quality and heating and cooling (see Appendix B).3 If the component level input is left
blank, the models will generate a low cost estimate. The user can change this input to select a
medium or high cost estimate.
3 In some cases (e.g., the membrane models, which are under development), this input also determines the source
water quality that the model treats. In these models the input is called the "cost level."
14
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
System Automation
System automation
pick or leave blank
manual
semi-automated
fully automated
As described in Appendix A, control of drinking water treatment systems can be manual,
automated or semi-automated. The method of control can have a significant impact on both
capital and O&M costs. Each model includes an optional input that allows the user to select from
among the three control options. If the system automation input is left blank, the control option
selected is determined by the system size and the component level input selected (see above),
using the logic shown in Exhibit 2-7. The user can change the system control input to force the
design of a system with manual, automated or semi-automated control.
Exhibit 2-7. Default Assumptions for System Control
Component Cost Level Selected
System Size (Design Flow)
Less than 1 MGD
System Size (Design Flow)
1 MGD or greater
Low
Manual
Manual
Medium
Manual*
Automated
High
Automated
Automated
* Automated for some models.
Include Buildings?
Include buildings?
<-
pick or leave blank
Include HVAC?
<~
pick or leave blank
Include land?
pick or leave blank
yes
no
By default, the WBS models include the capital cost of buildings to house the treatment system,
as discussed in Section 2.4.1 and Appendix B. Each model includes an optional input that allows
the user to exclude the capital cost of buildings. If the user excludes the capital cost of buildi ngs,
the model also excludes the O&M cost of building maintenance and lighting.
Include Heating, Ventilating and Air Conditioning (HVAC)?
By default, the WBS models choose whether to include the cost of heating and cooling systems
depending on system size, building structure type and user input for component level, as
discussed in Section 2.4.1 and Appendix B. Each model includes an optional input that allows
the user to override the model's default selection and choose to include or exclude the cost (both
capital and O&M) of HVAC systems.
Include Land?
Regardless of whether a system needs to purchase additional land on which to build the new
treatment train, there is an opportunity cost associated with using land for water treatment rather
15
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
than an alternative use. By default, the WBS models include an add-on cost for land, as
discussed in Section 2.4.4. Each model includes an optional input that allows the user to exclude
the add-on cost for land.
2.3.3 Input Sheet Examples
Several examples are presented here to clarify the use of the WBS model input sheet. The
examples refer to particular technology models. Detailed information about the inputs for these
models can be found in the appropriate technology-specific chapters.
Standard Design
The simplest way to generate a design is by use of the standard design buttons. Suppose that a
user wishes to estimate costs for a system designed to treat trichloroethylene (TCE) using
granular activated carbon (GAC), serving a population of approximately 8,000 people. The
following are step-by-step instructions for using the adsorptive media model to generate such a
cost estimate:
1. Open the Excel workbook named "WBS GAC.xlsm."4 Depending on your settings and
version of Excel, a message might appear regarding "active content" in the workbook.
For the models to function properly, macros must be enabled. Take the appropriate steps
to enable macros (for example, clicking "Options" and selecting "Enable this content,"
depending on your version of Excel).
2. Navigate to the input sheet by clicking on the tab labeled "INPUT" at the bottom of the
Excel window. (It is also possible to page through the sheets by pressing Ctrl-Page Up
and Ctrl-Page Down.) Scroll to the top of the input sheet.
3. The GAC model requires that the user first choose the contaminant. Select "TCE" from
the "Select Contaminant" dropdown list.
4. The GAC model also requires that the user choose between pressure and gravity designs
(see the appropriate technology chapter for discussion of the difference between design
types). Select "Pressure" from the "Select Design Type" dropdown list.
5. The user wishes to use a standard design appropriate for a population of 8,000 people.
Exhibit 2-6 indicates that size category 5, with a design flow of 2.152 MGD, is
appropriate for such a system. Therefore, click on the design button labeled "2.152 MGD
standard design." After a few seconds, the model will display the message "Using this
design" next to the design button and "Input Complete—Results Ready" underneath the
buttons. It displays the direct capital cost, total capital cost and annual O&M cost on the
input sheet.
6. If desired, scroll down on the input sheet to see what inputs are used for the standard
design. For instance, the 2.152 MGD standard design for GAC treating TCE with a
pressure design uses a design flow of 2.152 MGD and an average flow of 0.819 MGD. It
4 Note that your model file name might vary. It likely will include a date following the model title (e.g., "WBS GAC
042514.xlsm" for April 25, 2014).
16
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
assumes a carbon life of 66,600 bed volumes and a total theoretical empty bed contact
time (EBCT) of 7.5 minutes.
Modified Standard Design
Suppose that the user wishes to design a GAC system treating TCE for a population of 1,000,
using source water that entails a different carbon life and EBCT than that assumed in the
standard designs (e.g., because the source water contains a higher initial concentration of TCE).
The user determines that the source water characteristics entail a carbon life of 40,000 bed
volumes and an EBCT of 10 minutes. The following are step-by-step instructions for using the
GAC model to generate such a cost estimate:
1. Open the Excel workbook named "WBS GAC.xlsm"5 and take the appropriate steps to
enable macros (see Step 1 described in the "Standard Design" section above). Navigate to
the input sheet, scroll to the top of that sheet and select "TCE" and "Pressure" from the
appropriate dropdowns (see Steps 2, 3 and 4 described in the "Standard Design" section
above).
2. The user wishes to design a system for a population of 1,000 people. Exhibit 2-6
indicates that size category 3, with design flow 0.305 MGD, is appropriate for this
population, so start by clicking the "0.305 MGD standard design" button.
3. The user wishes to design a system with a carbon life of 40,000 bed volumes. Scrolling
down the input sheet, note that the standard design uses an input carbon life of 66,600
bed volumes. Type the number 40,000 in the gold input cell to change the carbon. Note
that the green informational text below the input cell changes to show the number of
months between regenerations. Note also that the message above the manual inputs
changes to "Input Complete—Press 'Generate Results'" to indicate that costs have not
been updated for your new input.
4. The user wishes to design a system with an EBCT of 10 minutes. Scroll down to the cell
labeled "Theoretical Empty Bed Contact Time" and enter the number 10.
5. Changing the EBCT will change the optimal vessel geometry. To quickly estimate costs
for this new EBCT, click the "Autosize" button next to the inputs for vessel geometry.
The input values will flicker briefly while the model tries several different values and
then settles on a new value. Because the Autosize button was clicked, it is not necessary
to click the "Generate Results" button; the message above the manual inputs reads "Input
Complete—Results Ready," and the total costs are displayed on the input sheet.
Suppose that the user also wishes to estimate a high-end cost for this system. In this case, take
the following additional steps:
5 Again, your model file name might vary. It likely will include a date following the model title (e.g., "WBS GAC
042514.xlsm" for April 25, 2014).
17
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
6. Scroll down and place the cursor in the input cell labeled "Component Level." A
dropdown arrow appears to the right of the cell. Click on the arrow and choose "high
cost."
7. Scroll back to the top of the sheet. Note that the sheet indicates that the user must click
"Generate Results." Click that button. The model displays costs for the high-end system.
To see what components are included, switch to the Output sheet and examine the details.
2.3.4 Output Sheet Structure and Use
The output sheet in each of the technology models is similar to that pictured in Exhibit 2-3. In
addition to the details described in Section 2.1, the output sheet includes several important totals:
• Process cost, which is the sum of the installed capital cost of all equipment required for
the treatment process
• Building cost, which is the sum of the installed capital cost of all buildings and the
concrete pad
• Direct capital cost, which is the sum of the process and building costs
• Total capital cost, which is the total of the direct capital cost, the indirect capital costs and
add-on costs (see Sections 2.4.3 and 2.4.4)
• Annual O&M cost (see Section 2.4.5)
• Total annualized cost (see Section 2.4.6).
The capital equipment section of the output sheet includes a column labeled "Use?" This column
tells the model which line items to include in the direct capital cost. Specifically, items with a
value of 1 in the "Use?" column are included in the total; items with a value of 0 or a blank are
not included in the total. Advanced users can manually adjust this column to include or exclude
certain items of equipment. For example, a user could examine process costs without booster
pumps by changing the "Use?" value to 0 for those pumps. The "Generate Results" button,
which is present on both the input and output sheets, will reset the "Use?" values back to pre-
programmed default values, as driven by system size and input values.
The output sheet also includes a button labeled "Record Output in a New Workbook." This
button generates a complete copy of the output sheet that will not change. Using this button
allows users to record the detailed design output for comparison purposes. For example, a user
could record the output from the standard design for 0.03 MGD, then select the 0.124 MGD
standard design and compare the output results for the two designs.
2.3.5 Critical Design Assumptions Sheet Structure and Use
Each of the technology models includes at least three critical design assumptions sheets:
• One for process and building design assumptions
• One for assumptions used in calculating annual O&M costs
• One for assumptions used in calculating certain indirect capital costs
Some models include additional critical design assumptions sheets (e.g., in the aeration models,
for assumptions associated with off-gas treatment).
18
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
These sheets contain design constraints and structural and chemical engineering assumptions
based on GREPs. Users can review these sheets for details on significant assumptions used in the
models. Advanced users might want to modify certain assumptions, particularly if adapting a
model for use with a source water quality different than assumed in the standard designs or to
reflect site-specific conditions. Most of the assumptions include a comment column explaining
the use of the assumption and/or providing guidance on appropriate values.
Most of the significant design assumptions are technology-specific and discussed in detail in the
technology chapters of this report. However, there are certain assumptions that are common to
many of the models. Exhibit 2-8 summarizes the general design assumptions that are common
across most of the models. As Exhibit 2-8 indicates, these assumptions are based on a
combination of sources, including standard design handbooks, engineering textbooks and
comments of external reviewers. Note that some of the general design assumptions (and some
technology-specific assumptions, as discussed in the relevant technology chapters) differ for
small versus large systems. In general, these differences are because small systems can often be
built as packaged, pre-engineered or skid-mounted systems. In most cases, the different design
and cost assumptions for small systems are based on comparison of model outputs with as-built
designs and costs for actual small treatment systems.
The user can change some of the assumptions shown in Exhibit 2-8 by editing the critical design
assumptions sheet; others can be edited in the data extracted from WBS cost database. The final
column of Exhibit 2-8 provides guidance on how to change each assumption. For example, the
design of pumps for any treatment system is based on the peak flow requirements of the system,
including a safety factor. As specified in Exhibit 2-8, the critical design assumptions sheet
assumes a safety factor of 25 percent. A user could change this factor based on an actual pump
performance curve.
Exhibit 2-8. General Design Assumptions Used in the WBS-based Models
Element
Assumption
Can be changed by:
Influent pumps
Include flooded suction
Replacing unit costs or cost coefficients
extracted from the WBS cost database
All pumps
Design flow incorporates a safety factor of
25 percent
Editing the critical design assumptions
sheet of each technology
Access space for pumps
Provide a minimum of 4 feet of service
space around three sides of each unit,
assuming the fourth side can share access
space with relevant tanks or vessels
Editing the critical design assumptions
sheet of each technology
Pipe size
Based on a maximum of 3 feet of head
loss per 100 feet of pipe
Editing the engineering lookup table
extracted from the WBS cost database
Process pipe size
Based on maximum flow to each unit (not
total system flow)
Cannot be changed
Tank and pressure vessel
capacity
Based on design capacity, freeboard and
standard manufactured sizes
Cannot be changed
Pressure vessel diameter
Based on user input, within limits specified
on a technology-specific basis
Changing user inputs (for diameter) and
editing the critical design assumptions
sheet of each technology (for constraints)
Storage tank diameter
Assumes a cylindrical design, with
diameter equal to one half of the height
Cannot be changed
19
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Element
Assumption
Can be changed by:
Access space for tanks and
pressure vessels
Provide service space around each unit
equal to its diameter (half its diameter for
small systems), to a maximum of 6 feet
Editing the critical design assumptions
sheet of each technology (only maximum
can be changed)
Process vessels and basins, all
pumps and chemical feed
systems
Multiple units required to protect from
single point failure
Editing the critical design assumptions or
input sheet of each technology (depending
on the specific item)
Chemical storage
Storage requirement based on 30-day
delivery frequency
Editing the critical design assumptions
sheet of each technology
Concrete pad under heavy
equipment
1 foot thick for large systems, 6 inches
thick for small systems
Editing the critical design assumptions
sheet of each technology
Office space
100 square feet per employee for large
systems (excluded for small systems)
Editing the critical design assumptions
sheet of each technology
Sources: U.S. EPA (1997); AWWA (1990); AWWA/ASCE (1998); Viessman and Hammer (1993); GREPs; and information from
manufacturers and technology experts who reviewed model critical design assumptions.
Cost Estimation Method
Equipment unit costs can be derived in one of two ways. The first (and recommended) method
uses component-specific cost equations developed from unit costs collected from equipment
vendors. The component cost equations are best-fit equations (developed using statistical
regression analysis across the sizes available for each item) that estimate the unit cost of an item
of equipment as a function of its size. Under the cost equation option, the models will generate
unit costs for each item of equipment by applying the appropriate cost equation to the exact size
determined by the design calculations.
The second method uses unit cost lookup tables extracted from the WBS cost database. These
lookup tables are based on quotes from equipment manufacturers for discrete equipment sizes.
To maintain vendor confidentiality, the tables do not identify the individual vendors associated
with the quotes and the unit costs typically are averages across multiple vendors. Under the
lookup table option, for each item of equipment, the models will search the appropriate lookup
table to locate a unit cost that best meets the design requirements for the component. In general,
this means that the models will select the discrete equipment size for each item of equipment that
is equal to or greater than the size determined by design calculations.
Each model includes a critical design assumption, labeled "cost estimating method," that
determines the method used to derive equipment costs. By default, the assumption is set to 1, to
use the component-specific cost equations. The user can set the assumption to a blank value to
select the lookup table method. EPA believes the cost equations method is most appropriate for
generating national cost estimates and for most user-specified designs. Using the equations,
instead of the price quotes, allows the models to generate unit costs for equipment of the exact
size determined by the design calculations. For example, a WBS model design might require a
250 gallon steel tank, but the available price quotes might be limited to 100 gallon, 500 gallon
and various larger sizes. The cost equation for steel tanks will allow the WBS model to generate
a unit cost for the intermediate sized 250 gallon tank. The lookup table method would use the
cost for the 500 gallon tank. The models retain the lookup table method for users who wish to
examine the specific cost data points on which the component-specific cost equations are based.
20
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
2.3.6 Index Sheet Structure and Use
Each technology model includes an index of all inputs and critical design assumptions, including
hyperlinks to their locations. Exhibit 2-9 shows an example of the index sheet. The sheet
provides an alphabetized list of all inputs and assumptions. Due to the great number of inputs
and assumptions in the WBS models, the Find feature in Excel can be useful in locating a
specific input or assumption.
Next to the description of each input or assumption is a blue, underlined hyperlink. It shows the
internal name of the input or assumption used in the engineering formulas throughout the WBS
model. Clicking on the hyperlink takes the user to the cell where the assumption can be viewed
or adjusted.
21
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit 2-9. Sample of Index Spreadsheet
INDEX
This page provides an index to all user-adjustable inputs and assumptions. Click on a variable name to go directly to the adjustable cells.
User-adjustable Input or Assumption
Variable Name and Link
Access space per pump/blower for custom designed systems
space pumps cust
Access space per pump/blower for pre-engineered packages
space pumps pre
Additional blower head above water depth
add blow head
Additional building after...
add 2nd building
Administrative LOE as a percent of average technical labor
Clerical percent
Air conditioning EER
EER
Air to water ratio
air water ratio
Always include NEPA compliance costs?
include NEPA
Annual cooling degree days
cool DD
Annual heating degree days
heat DD
Average Flow
average flow 1
Basin excavation depth above which deeper boreholes are needed
deep bore need
Bedding depth below pipe
bedding depth
Bedding depth surrounding the pipe
beddinq pet
Blower efficiency
blower effcy
Blower safety factor
blower safety factor
Borehole depth (package systems)
bore depth p
Borehole depth for deep basins
bore depth max
Borehole depth for shallow basins
bore depth min
Borehole needed every x square feet
hole per sf
Boreholes per job
hole perjob
Buffer space around other sides of buildings
non fire buffer
Builder's risk insurance percentage
br ins pet
Building height
Building height
Coefficient of passive pressure
Coeff Kp
Communications hardware
comm hardware
Component level
component level 1
Computer workstations per x operators
workstation ratio
Concrete pad thickness
pad thick
Concrete pad thickness for small systems
pad thick small
Concrete thickness
cone thick
Contaminant-Specific Off-gas Assumptions
contaminant lookup
Cooling table for buildings 500 square feet or greater
coolina table
Cooling table for buildings less than 500 ft2
coolinq table shed
Cooling ventilation/infiltration load
cool viload
Cost for parts & maintenance for pumps and blowers
pump maint rate
Density of air
PA
Design Flow
design flow 1
Design safety factor for standby power
std safety factor
Design Type
desian type 1
Diffuser access space
diffuser access space
Drive controllers per blower
S blower
Drive controllers per booster pump
S booster Dump
Drive controllers per catalytic oxidizer
S CO
Drive controllers per thermal oxidizer
S TO
Efficiency of pumps
pump effcv
Electric resistance heating efficiency
resist eff
Electrical percentage
elect pet
Engineering percentage for large systems
enq pet larae
Engineering percentage for medium systems
enq pet medium
Engineering percentage for small systems
enq pet small
Ethernet modules
pic ethernet
Excess air required
CO ex air
Excess air required
TO ex air
External air piping
air pipe add
Financing percentage
finance pet
2.4 General Cost Assumptions
An important feature of the WBS models is that they build up cost estimates from component-
level data. Each model shows the user the cost build-up, which makes the cost estimates more
transparent, giving the user an opportunity to evaluate the impact of design and unit cost
assumptions on treatment costs. There are several types of costs that need to be aggregated into a
total cost estimate: equipment costs, building cost, residuals discharge cost, indirect capital costs,
add-on costs and annual O&M costs. The sections below describe how each type of cost enters
the WBS models.
22
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
The build-up process for equipment costs is straightforward. The design sheets in the model
generate the required dimensions and quantities for each item in the WBS list of equipment
components and materials. Then, the model obtains unit costs to match the component size and
material (e.g., a 10-inch diameter PVC pipe or a 4,000-gallon steel backwash tank). The model
multiplies unit costs by the quantity estimate (e.g., 30 feet of pipe or 2 tanks) to obtain total
component costs. Direct capital cost equals the sum of these costs across the selected
components, including costs for treatment equipment and buildings.
The models enable equipment unit costs to be derived in one of two ways (using lookup tables or
cost equations, as described in Section 2.3.5 under "Cost Estimation Method"). Regardless of the
method used, the estimates are intended to provide enough information to establish a budgetary
or preliminary cost estimate. Therefore, although the model results are point estimates shown to
the nearest $1, this precision is not meant to imply that the results are accurate to $1. Instead,
EPA's goal is for the resulting costs to be within +30 percent to -15 percent of actual cost. To
validate the engineering design methods used by the models and assess the accuracy of the
resulting cost estimates with this goal, EPA has subjected the individual models to a process of
external peer review by nationally recognized technology experts. The technology-specific
chapters of this document include a discussion of peer reviewer opinions on the accuracy of each
model's results. Users are encouraged to review all documentation, modify inputs and
assumptions as appropriate to their specific purpose, and form their own informed opinions about
the accuracy and suitability of the results.
Consistent with providing a budgetary or preliminary cost estimate, WBS models contain several
cost-related assumptions that allow the models to produce costs for some components without
having detailed site-specific information (e.g., pipe fitting sizes). Exhibit 2-10 summarizes these
assumptions.
23
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit 2-10. General Equipment Cost Assumptions
1. Costs are preliminary estimates based on major components as shown on piping and instrumentation diagrams or typical
layout drawings. Costs include consideration of package plants where relevant (see model-specific chapters for more
details).
2. All equipment costs include costs of transportation and installation.
3. All equipment costs are based on cost quotes from manufacturers or RSMeans database.
4. Long-term storage of chemicals (greater than 30 days) is not taken into account unless specifically mentioned.
5. Cost of waste disposal (residuals) is accounted for using the methods outlined in Section 2.4.2 and Appendix C.
6. Building layout is for the process itself, with room for operation, maintenance and replacing equipment, if needed.
7. Building costs are estimated using unit costs per square foot (see Section 2.4.1 and Appendix B for more details).
8. Costs for a reinforced-concrete pad floor to handle equipment loads are added to building costs. Costs associated with
special unit or site-specific foundation requirements are not included and should be evaluated on a case-by-case basis.
9. To account for the cost of fittings, pipe lengths are determined by applying a multiplier to the overall system building layout
length. The resulting lengths are considered conservative (i.e., erring on the high side), so that the resulting cost covers
the installed cost of the pipe and fittings. The specific multipliers are as follows:
Combined influent and effluent pipe length is 2 times the length of the overall system building layout length.
Process pipe length is 2 times the length of the overall system building layout length.
Backwash pipe length is 2.5 times the overall system layout length.
Chemical piping length is 1 times the overall system layout length.
2.4.1 Building Costs
The WBS model building costs use three sources: RSMeans 2009 Square Foot Costs (RSMeans,
2008), Saylor 2009 Commercial Square Foot Building Costs (Saylor, 2009) and the Craftsman
2009 National Building Cost Estimator software model (described in Craftsman, 2008).
Appendix B provides a detailed description of these sources and the approach to developing
building costs.
In each WBS technology model, there are four possible design configurations for buildings: three
construction design and quality categories (low, medium and high) and small, very low cost,
prefabricated ("shed-type"). The WBS models select from among these configurations based on
system size, structure size and user input for component level (see Section 2.3.2), as shown in
Appendix B. Unit costs (in dollars per square foot) for each configuration vary by structure size.
When appropriate, the WBS models add costs for building heating and cooling systems as line
items separate from the base building costs. Whether the WBS models include these systems also
depends on system size, structure type and user input for component level, as shown in Appendix
B.
As discussed in Section 2.3.2, the input sheet of each model includes optional inputs that allow
the user to choose whether or not to include the costs of buildings and HVAC systems.
2.4.2 Residuals Management Costs
Many of the treatment technologies covered by the WBS-based models generate liquid, semi-
solid (sludge) and/or solid residuals. For these technologies, each model includes a sheet that
estimates the cost of various options for managing these residuals. The residuals management
options available for a given technology vary depending on the types of residuals generated, their
24
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
quantity, the frequency of generation (e.g., intermittent versus continuous) and their
characteristics. Examples of residuals management options include (but are not limited to): direct
discharge to surface water, discharge to a publicly owned treatment works, land disposal of
solids and storage and/or treatment of sludge or liquid waste prior to disposal or discharge. The
individual technology chapters of this document describe the specific residuals management
options available for each technology. Appendix C provides detailed information about the data
and assumptions used to estimate costs for the various residuals handling and disposal options.
2.4.3 Indirect Capital Costs
Indirect capital costs are costs that are not directly related to the treatment technology used or the
amount or quality of the treated water produced, but are associated with the construction and
installation of a treatment process and appurtenant water intake structures. Indirect costs can be
considerable and must be added to cost estimates if they are not included as a line item
component or a factor in the major (cost driver) elements of a technology. They include indirect
material costs (such as yard piping and wiring), indirect labor costs (such as process engineering)
and indirect burden expenses (such as administrative costs).
The WBS models compute the costs of site work, geotechnical investigation, yard piping and
standby power based on the system requirements, as determined during the direct capital cost
buildup. Other indirect costs are computed as a percentage of the installed process cost, building
cost or direct capital cost estimate. The indirect assumptions sheet in each WBS model (see
Section 2.3.5) contains guidance regarding a typical range of percentages for each item and
indicates the base cost to which the percentage will be applied. The guidance also describes
conditions that might require an assumption outside the range of typical values. Finally, guidance
on the output sheet notes that items such as installation costs and contractor overhead and profits
are already included in the direct capital cost estimate, but entries can be made to increase these
cost items should circumstances merit higher costs. Any of these costs can also be excluded by
modifying assumptions on the indirect assumptions sheet. Costs that are computed as a
percentage can be excluded simply by setting the percentage to zero. Those that are computed
based on system requirements can be included or excluded by setting the appropriate flag to one
or zero on the indirect assumptions sheet.
The WBS models report the total capital cost directly below this section of the output sheet so
the user can determine the impact of altering the indirect cost assumptions on total capital costs.
Appendix D provides descriptions of the default assumptions for the following indirect costs:
• Mobilization and demobilization
• Architectural fees for treatment building
• Equipment transportation, installation and contractor overhead and profit
• Construction management and general contractor overhead
• Process engineering
• Site work
• Yard piping
• Geotechnical
• Standby power
25
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
• Yard wiring
• Instrumentation and control
• Contingency
• Financing during construction
• Legal, fiscal and administrative
• Sales tax
• City index
• Miscellaneous allowance.
2.4.4 Add-on Costs
Add-on costs are costs that may be attributed to one or more aspects of the treatment technology.
These add-on costs include permit costs (e.g., for construction and discharge permits), pilot and
bench testing costs and land use costs. Users can include or exclude these costs by setting
appropriate flags on the indirect assumptions sheet (see Section 2.3.5).
Permits
Systems installing new treatment technologies to comply with revised drinking water standards
will often need to build a new structure to house the new treatment train and might need to build
auxiliary structures to store chemicals (e.g., chlorine, which must be stored in a separate
building). In all jurisdictions, such construction activities require a building permit and
inspections to ensure that the structure meets local building codes. New treatment trains can also
create a new waste stream or supplement an existing one. New waste streams such as new point
source discharges to surface water generally require a state or federal permit; additions to
existing flows often require revisions to existing permits. The WBS models include costs for the
following permits:
• Building permits
• Permits under the National Pollutant Discharge Elimination System (when residuals
discharge to surface water is present)
• Storm water permits (for systems requiring one acre of land or greater)
• Risk management plans (when certain chemicals are present in large quantities)
• Compliance with the National Environmental Protection Act (included by default only at
the high cost component level - see Section 2.3.2).
Pilot Study
Site-specific pilot tests are often required by regulatory agencies to better define design
conditions and to ensure that the proposed technology will protect public health. In addition,
pilot tests and bench-scale tests can be run for non-regulatory reasons, e.g., to determine
appropriate loading and chemical feed rates, waste handling requirements or other process
parameters. Options for pre-design and pre-construction testing can include full- or small-scale
pilot studies, bench tests and desktop feasibility studies. Costs for pilot testing vary accordingly.
Pilot studies range from inexpensive small-scale efforts to full-scale tests that might be
warranted by site-specific conditions. Three variables affecting the costs of a pilot study are:
technology requirements, testing protocols and state requirements. Some states determine test
26
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
requirements on a case-by-case basis, particularly where drinking water standards or regulations
such as noise, air emissions, plume abatement or surface water discharges (e.g., the National
Pollutant Discharge Elimination System) are relatively stringent. The diversity of state
requirements, along with the many options for pre-design testing, means that requirements for
pilot- or bench-scale studies are difficult to define. Nevertheless, the WBS models include
default pilot study costs based on vendor quotes and estimated analysis costs. The user can alter
these costs by adjusting the permit cost data extracted from the central WBS cost database if site-
specific conditions warrant.
Land Cost
Regardless of whether a system needs to purchase additional land on which to build the new
treatment train, there is an opportunity cost associated with using land for water treatment rather
than an alternative use. The WBS models capture this cost in a land cost estimate that is based on
the calculated land requirement (in acres) and a unit cost per acre. As discussed in Section 2.3.2,
the input sheet of each model includes an optional input that allows the user to choose whether or
not to include the cost of land.
Each model estimates land required for the treatment system, plus a 40-foot buffer on one side
for emergency vehicle access and 10 feet on the other three sides. The user can change the
assumptions about buffer spacing using the critical design assumptions sheet for each
technology.
The WBS models incorporate land costs based on unit land costs that vary by system size and
land requirements that vary by technology and system size. Average land costs per acre are
estimated as probability-weighted averages using data from the Safe Drinking Water Information
System on system size and location, data for rural land costs for 50 states and data on urban land
costs for approximately 125 cities and metropolitan areas.
2.4.5 Annual O&M Costs
The O&M costs in each WBS model include annual expenses for:
• Labor to operate and maintain the new treatment equipment and buildings
• Chemicals and other expendable items (e.g., replacement media) required by the
treatment technology
• Materials needed to carry out maintenance on equipment and buildings
• Energy to operate all equipment and provide building heating, cooling, lighting and
ventilation
• Residuals discharge fees.
The individual technology chapters of this document describe additional, technology-specific
O&M costs.
O&M costs calculated in the models do not include annual costs for commercial liability
insurance, inspection fees, domestic waste disposal, property insurance and other miscellaneous
expenditures that are not directly related to the operation of the technology. These costs are
27
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
highly site-specific. Users wishing to include them should add the appropriate site-specific
estimates to the model results.
The WBS models calculate annual O&M costs based on the inputs provided by the user in the
input and O&M assumptions sheet. These inputs include system size, raw and finished water
quality parameters and other factors that affect operation requirements. Appendix E contains the
design assumptions used to develop default costs for the O&M sheet.
2.4.6 Total Annualized Cost
The output sheet in each model includes an estimated useful life, in years, for each WBS
component. The models take these component useful lives from the WBS cost database. The
useful lives vary by component type (e.g., buildings generally last longer than mechanical
equipment) and by material (e.g., steel tanks generally last longer than plastic tanks). The models
use the component useful lives to calculate an average useful life for the entire system. The
calculation uses a reciprocal weighted average approach, which is based on the relationship
between a component's cost (C), its useful life (L) and its annual depreciation rate (A) under a
straight-line depreciation method. The formula below shows the reciprocal weighted average
calculation:
N
2X c
Average Useful Life = — = —
IX A
n=l
where:
Cn denotes the cost of component n, n=l to N
C denotes total cost of all N components
An denotes the annual depreciation for component n, which equals Cn/Ln
A denotes total annual depreciation for the N components.
The models use this average useful life for the system, along with a discount rate, to annualize
total capital cost, resulting in capital cost expressed in dollars per year. The models use a default
discount rate of 7 percent, which users can adjust directly on the output sheet. The models add
annual O&M cost to the annualized capital cost to arrive at a total annual cost in dollars per year.
2.4.7 Updating and Adjusting Costs
There are many factors that contribute to the variation in capital and O&M costs for the same
treatment technology. One variable is location, which is captured by the city index indirect cost.
Another is time—over time, the nominal price of materials, labor and land can change due to
inflation. If relative prices do not change over time (i.e., if innovative materials or production
technologies do not affect production cost relative to the price of other goods), then nominal
component prices can be adjusted using standard cost indices. The WBS cost database
incorporates the following indices to adjust prices to values in a common year:
• The Producer Price Index (PPI) consists of a family of indices that measure the average
trends in prices received by producers for their output (BLS, 2010). Within the PPI is the
28
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
family of commodity-based indices. The commodity classification structure of the PPI
organizes products by similarity of end use or material composition. Fifteen major
commodity groupings (at the two-digit level) make up the all-commodities index. Each
major commodity grouping includes (in descending order of aggregation) subgroups
(three-digit level), product classes (four-digit level), subproduct classes (six-digit level)
and individual items (eight-digit level). The WBS cost database assigns components to
the most closely related PPI commodity index. The selected price index for a component
is generally the index with the smallest product space. For example, prices for stainless
steel pressure vessels are escalated using a four-digit level index called BLS1072 Metal
Tanks.
• Building and construction costs are escalated using either the Engineering News-Record
Construction Cost Index or the Building Cost Index (ENR, 2013).
• Labor costs are escalated using the Employment Cost Index for "not seasonally adjusted,
total compensation, private industry and public utilities" (BLS, 2000; SIC series: 252).
The Bureau of Labor Statistics releases this index quarterly. The WBS cost database
utilizes an annual average.
• The Consumer Price Index is used to adjust land costs and components that have not been
assigned a specific PPI (BLS, 2007).
2.6 References
American Water Works Association (AWW A). 1990. Water Quality and Treatment: A
Handbook of Community Water Supplies. Fourth Edition. New York: McGraw Hill.
A WW AJ American Society of Civil Engineers (ASCE). 1998. Water Treatment Plant Design.
Third Edition. New York: McGraw-Hill.
Bureau of Labor Statistics (BLS). 2007. BLS Handbook of Methods: The Consumer Price Index.
Updated June 2007. Online at http://www.bls.gov/opub/hom/pdf/homchl7.pdf
BLS. 2010. BLS Handbook of Methods: The Producer Price Index. Last updated 10 July. Online
at http://www.bls.gov/opub/hom/pdf/homchl4.pdf
2.5
EBCT
EPA
GAC
gpm
GREPs
HVAC
MGD
O&M
P&ID
PPI
TCE
WBS
List of Abbreviations and Symbols in this Chapter
empty bed contact time
U.S. Environmental Protection Agency
granular activated carbon
gallons per minute
generally recommended engineering practices
heating, ventilating and air conditioning
million gallons per day
operating and maintenance
process and instrumentation diagram
Producer Price Index
tri chl oroethy 1 ene
work breakdown structure
29
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
BLS. 2000. Employment Cost Indices, 1976-1999. September. Online at
http://www.bls.gov/ncs/ect/sp/ecbl0014.pdf
Craftsman Book Company. 2008. 2009 National Building Cost Manual. 33rd Edition. October.
Engineering News-Record (ENR). 2013. Building and Construction Cost Indexes. Online at
http://enr.construction.com/economics/
RSMeans. 2008. 2009 Square Foot Costs. 30th Annual Edition. Kingston, Massachusetts:
RSMeans Company.
Saylor Publications, Inc. 2009. 2009 Commercial Square Foot Building Costs: 19th Annual
Edition.
U.S. Environmental Protection Agency (U.S. EPA). 1997. Discussion Summary: EPA
Technology Design Workshop. Washington, D.C.: U.S. EPA, Office of Groundwater and
Drinking Water.
Viessman, W.J. and M.J. Hammer. 1993. Water Supply and Pollution Control. 5th Edition.
Harper Collins College Publishers, New York, NY.
30
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
3. Biological Treatment Model
Biological treatment uses bacteria to remove contaminants. The process has a vessel or basin
called a bioreactor that contains the bacteria in a media bed. As contaminated water flows
through the bed, the bacteria, in combination with an electron donor and nutrients, react with
contaminants to produce biomass and other non-toxic by-products. In this way, the biological
treatment chemically "reduces" the contaminant in the water.
The work breakdown structure (WBS) model for biological treatment can estimate costs for three
types of bioreactors:
• Pressure vessels with a fixed media bed
• Open concrete basins with a fixed media bed
• Pressure vessels with a fluidized media bed.
For fixed bed reactors, influent water typically is passed under pressure through a static media
bed located in a vessel or concrete basin. Fluidized bed bioreactor designs use vessels where
recycled water is pumped at high rates in an up-flow design to fluidize the media bed, allowing
for more surface area for biomass growth.
The WBS model includes standard designs for perchlorate and nitrate treatment in drinking
water applications. However, the model can also be used to estimate the cost of biological
treatment for the removal of other contaminants as well. Users wishing to simulate the use of
biological treatment for other contaminants will need to adjust default inputs (e.g., electron donor
and nutrient doses) and critical design assumptions (e.g., minimum and maximum loading rates).
This chapter includes discussion of inputs and assumptions that might require adjustment and
these values are highlighted in gold in the model.
3.1 Overview of the Biological Treatment Process
The biological treatment process includes the following components:
• Booster pumps for influent water
• Electron donor addition
• Nutrient addition (optional)
• Bioreactors (either pressure vessels or concrete basins) that contain the media bed
• Post-treatment re-oxygenation (aeration or hydrogen peroxide addition)
• Post-treatment filters (filter basins or pressure vessels)
• Tanks and pumps for backwashing the bioreactors and post-treatment filters
• Associated piping, valves and instrumentation.
Biological treatment of perchlorate is accomplished by bacteria reducing the perchlorate anion,
sequentially producing chlorate, chlorite, chloride and oxygen (Xu et al., 2003). Exhibit 3-1
shows a diagram of the reduction pathway. Similarly, the reduction pathway for nitrate uses an
electron donor to reduce the nitrate anion to nitrogen gas in a process called denitrification.
31
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit 3-1. Biological Perchlorate Reduction Pathway
cio4-
Electron donor
C02, H20, Biomass
CIO3-
Electron donor
C02, H20, Biomass
cio2-
I
Electron donor
C02, H20, Biomass
CI-+O,
2
Aerobic Pathway
The bacteria that perform the reduction are located in the media bed within a bioreactor. Lab
studies have effectively used a variety of media to host the bacteria, including granular activated
carbon (GAC), anthracite, sand and plastic media. Full-scale designs for perchlorate and nitrate
treatment have primarily used GAC. As shown in Exhibit 3-1, an electron donor is necessary to
complete the reduction. Electron donors are injected into the influent water prior to entering the
bioreactor. A wide variety of electron donors have been tested, including acetate, acetic acid,
lactate, ethanol, methanol, carbohydrate by-product, hydrogen and propane. Besides an electron
donor, the bacteria may also require supplemental nutrients to survive and reduce contaminants.
In the reduction pathways discussed above, anions in the water, including perchlorate and nitrate,
act as electron acceptors. Lab studies have shown that these anions have a preferred order in
which they will compete for available electrons (Marqusee, 2001). That order is as follows:
This preferred order means that perchlorate will not be effectively reduced until after nitrate and
dissolved oxygen will undergo reduction before either nitrate or perchlorate. As a result,
biological treatment of perchlorate or nitrate will result in product water with depleted oxygen
levels. Therefore, post-treatment re-oxygenation is common (Harding ESE, 2001). Polishing
filters are also common in post treatment for removal of turbidity and excess biomass from the
reactors.
Exhibit 3-2 and Exhibit 3-3 provide schematic drawings for a fixed bed bioreactor facility and
fluidized bed bioreactor facility, respectively.
dissolved oxygen > nitrate > perchlorate > sulfate
32
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit 3-2. Typical Schematic Layout for Fixed Bed Bioreactor
33
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit 3-3. Typical Schematic Layout for a Fluidized Bed Bioreactor
3.2 Input Sheet
The input sheet accepts the user-defined design parameters that determine fundamental process
requirements. The user can indicate system size and select basic equipment characteristics such
as bed depth and vessel geometry. Key design considerations that the user identifies on this sheet
are described in greater detail below and include the following:
• Target contaminant (e.g., perchlorate, nitrate)
• Design type for bioreactor
• Design and average flow (see Section 2.3)
• Electron donor type and dose
• Biomass generation
• Influent concentrations (optional)
• Nutrient requirements and phosphoric acid/ammonium chloride dose
• Empty bed contact time (EBCT) or hydraulic residence time (HRT)
• Bed depth and bioreactor dimensions
• Post-treatment options
• Interval between backwashes
34
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
• Include air scour
• Residuals management
• Number of booster pumps (optional)
• Number of redundant units (optional)
• Backwash pumping (optional)
• Backwash storage (optional)
• Component level (optional, see Section 2.3)
• System automation (optional, see Section 2.3 and below)
• Include buildings; heating, ventilating and air conditioning (HVAC) and land? (optional,
see Section 2.3).
Exhibit 3-4 summarizes the units and constraints (i.e., Excel validation criteria) for each of these
inputs, along with conditions under which the model generates warnings. The sections below
describe each input in greater detail.
Exhibit 3-4. Biological Treatment Model Input Constraints and Warnings
Input
Units
Constraints
Warning Conditions
Select Target Contaminant
Pick list
Pick list
None
Select Bioreactor Design Type
Pick list
Pick list
None
Design flow
MGDor gpm
Greater than 0
Blank
Average flow
MGDor gpm
Greater than 0
Blank, greater than design flow
or less than 0.1 times design
flow
Electron donor type
Pick list
Pick list
Blank
Electron donor dose
mg/L
Greater than 0
Blank
Biomass generation
mg/L
Greater than or equal to 0
Blank
Influent perchlorate concentration
(optional)
mg/L
Greater than or equal to 0
None
Influent dissolved oxygen
concentration (optional)
mg/L
Greater than or equal to 0
None
Influent nitrate-nitrogen concentration
(optional)
mg/L as nitrogen
Greater than or equal to 0
None
Nutrient requirements
Pick list
Pick list
None
Ammonium chloride dose (if
additional nitrogen required)
mg/L
Greater than 0
Blank
Phosphoric acid dose (if additional
phosphorus required)
mg/L as phosphorus
Greater than 0
Blank
Hydraulic residence time (HRT)
minutes
Greater than 0
Blank
Bioreactor pressure vessel inputs
Additional warnings if vessel
volume is insufficient for bed
expansion or loading rate is
outside of minimum and
maximum constraints
Bed depth (for fixed bed) or static
bed depth (for fluidized bed)
feet
Greater than 0
Blank, outside of minimum and
maximum constraints or
greater than twice vessel
diameter
Vessel geometry (for fixed bed)
Pick list
Pick list
Blank
Height (straight) or Length (straight)
feet
Greater than 0
Blank or outside of minimum
and maximum constraints
35
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Input
Units
Constraints
Warning Conditions
Diameter
feet
Greater than 0
Blank or outside of minimum
and maximum constraints
Bioreactor fixed bed gravity contact
basin inputs
Additional warnings if loading
rate is outside of minimum and
maximum constraints
Basin width
feet
Greater than 0
Blank or outside of minimum
and maximum constraints
Basin length
feet
Greater than 0
Blank or outside of minimum
and maximum constraints
Bed depth
feet
Greater than 0
Blank or outside of minimum
and maximum constraints
Post-treatment oxidation option
Pick list
Pick list
Blank
Include polishing filter
Yes/No
Yes/No
Blank
Polishing filter type (if polishing filter
included)
Pick list
Pick list
Blank
Include coagulant addition before
filtration (if polishing filter included)
Yes/No
Yes/No
Blank
Polishing filter gravity contact basin
inputs
Basin width
feet
Greater than 0
Blank or outside of minimum
and maximum constraints
Basin length
feet
Greater than 0
Blank or outside of minimum
and maximum constraints
Bed depth
feet
Greater than 0
Blank or outside of minimum
and maximum constraints
Polishing filter pressure vessel inputs
Bed depth
feet
Greater than 0
Blank, outside of minimum and
maximum constraints or
greater than twice vessel
diameter
Vessel geometry (for fixed bed)
Pick list
Pick list
Blank
Height (straight) or Length (straight)
feet
Greater than 0
Blank or outside of minimum
and maximum constraints
Diameter
feet
Greater than 0
Blank or outside of minimum
and maximum constraints
Interval between bioreactor
backwashes
hours
Greater than 0
Blank
Interval between polishing filter
backwashes
hours
Greater than 0
Blank
Include air scour
Yes/No
Yes/No
Blank
Discharge option for spent backwash
Pick list
Pick list
Blank
Holding tank for spent backwash
Pick list
Pick list
Blank
Solids treatment/storage
Pick list
Pick list
Blank
Characteristics of holding tank or
evaporation pond solids
Pick list
Pick list
Blank
Number of booster pumps (optional)
pumps
Integer greater than or
equal to 0
Pump flow is greater than
maximum for which prices are
available
Number of redundant contactors to
be added (optional)
units
Integer greater than or
equal to 0
None
Backwash pumping (optional)
Pick list
Pick list
None
Backwash storage (optional)
Pick list
Pick list
None
Component level (optional)
Pick list
Pick list
None
System automation (optional)
Pick list
Pick list
None
36
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Input
Units
Constraints
Warning Conditions
Include buildings? (optional)
Yes/No/Blank
Yes/No/Blank
None
Include HVAC? (optional)
Yes/No/Blank
Yes/No/Blank
None
Include land? (optional)
Yes/No/Blank
Yes/No/Blank
None
gpm = gallons per minute; MGD = million gallons per day; mg/L = milligrams per liter
Target Contaminant
STEP 1
Select Target Contaminant
Perchlorate
Fl
Perchlorate
Nitrate
Other
The WBS model for biological treatment includes a "drop-down" list box that allows the user to
select from the following target contaminants:
• Perchlorate
• Nitrate
• Other.
This box is located at the top of the input sheet, above the standard design buttons. The model
contains default inputs for perchlorate and nitrate designs that are populated by clicking on one
of the standard design buttons. For treatment of other contaminants, the "other" button should be
selected and the user will be required to manually adjust inputs.
Design Type
STEP 2
Select Bioreactor Design Type
Fluidized Bed
•w
Fixed Bed Pressure Vessel
Fixed Bed Gravity Basin
Fluidized Bed
The WBS model for biological treatment includes a "drop-down" list box that allows the user to
select among standard designs for:
• Fixed media bed pressure vessels
• Fixed media bed gravity basin
• Fluidized bed vessels.
This box is located directly under the contaminant dropdown box, above the standard design
buttons. The user should verify that the selections shown in both this box and the target
contaminant box are correct before populating the other design input values. The user can change
the bioreactor design type modeled by picking a different selection from the list. After doing so,
the user should then repopulate the input sheet with values appropriate for the new design type
by either clicking one of the standard design buttons or manually adjusting inputs and clicking
the "Generate Results" button (see Section 2.3 for further discussion of each of these methods).
37
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Electron Donor Type and Dose
Electron donor type
acetic acid
<- pick one
Electron donor dose
10
mg/L
The input sheet prompts the user to select between acetic acid and ethanol as the electron donor
type. These options are included because they are the most common electron donors used in full-
scale biological systems treating perchlorate and nitrate (Harding ESE, 2001; U.S. DoD, 2008;
U.S. DoD, 2009; Greene and Pitre, 2000; Polk et al., 2001).
Determining the correct electron donor dose is critical in the effectiveness of the bioreactor. For
perchlorate reduction, oxygen and nitrates will be reduced prior to perchlorate, so the electron
donor dose must be large enough to fully reduce all three. However, the dose cannot be too large
or sulfides might form and be present in the effluent along with excess organic carbon, requiring
additional post treatment (Harding ESE, 2001).
Electron donor dose is dependent on site-specific conditions including raw water characteristics.
Therefore, determining the dose requirements for the electron donor typically requires pilot study
tests and source water sampling, along with stoichiometric and thermodynamic calculations. The
following site-specific relationships were developed for two full-scale treatment designs using
ethanol (Harding ESE, 2001) and acetic acid (provided in peer review comments on the model):
Ce = 0.903 *(02) + 2.229*(NOs"-N )+ 0.581*(C104")
and
Caa = 2.248*(02) + 0.515*(NO3-N) + 1.447*(C104")
where:
Ce = required ethanol concentration in milligrams per liter (mg/L)
Caa = required acetic acid concentration in mg/L
NO3-N = influent nitrate concentration, measured as nitrogen in mg/L
O2 = influent dissolved oxygen concentration in mg/L
CIO4" = influent perchlorate concentration in mg/L.
As can be seen in these stoichiometric equations, influent concentrations of oxygen, nitrate-
nitrogen and perchlorate need to be available to determine the electron dose. For comparison
purposes, the model includes optional inputs for influent perchlorate, dissolved oxygen and
nitrate (as nitrogen). If the user enters values for these optional inputs, the model will provide
theoretical electron donor dose results calculated using the site-specific equations above.
However, a pilot study is recommended to determine actual electron donor dose values. The
model standard designs use acetic acid as the electron donor at a dose of 10 mg/L.
38
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Biomass Generation
Biomass generation
8 mg/L
Influent perchlorate concentration
Bmg/L
Influent dissolved oxygen concentration
Hmg/L
Influent nitrate-nitrogen concentration
; mg/L as nitrogen
Determining the amount of biomass generated during biological treatment is important in
calculating the amount of residual solids that will need to be removed after treatment. The
amount of biomass generated depends on the raw water characteristics. The following site-
specific relationship was developed using stoichiometric calculations for a full-scale treatment
design:
Biomass = 1.016*(O2)+ 0.155* (NO3-N) + 0.659 *(C104")
where:
Biomass = biomass generated in mg/L
O2 = oxygen concentration in mg/L
NO3-N = nitrate concentration, measured as nitrogen in mg/L
CIO4" = perchlorate concentration in mg/L
As can be seen in the stoichiometric equation, influent concentrations of oxygen, nitrate-nitrogen
and perchlorate need to be available to determine the amount of biomass generated. For
comparison purposes, if the user enters values for the optional influent water characteristic
inputs, the model will provide theoretical biomass generation results using the site-specific
equation above. The model standard designs use 8 milligrams of biomass generated for every
liter of water treated.
Nutrient Requirements
Nutrient requirements
additional phosphorous required
<- pick one
Ammonium chloride dose
Phosphoric acid dose
1
mg/L as phosphorus
Nutrient inputs OK
Bacteria in bioreactors require nutrients to survive and reduce contaminants. Although these
nutrients are often present in source water, some full-scale designs have required addition of
macro-nutrients such as nitrogen and/or phosphorous. While there are a number of methods for
adding nitrogen and phosphorous to the influent, the typical options are addition of ammonium
chloride for supplemental nitrogen and/or addition of phosphoric acid for supplemental
phosphorous (Harding ESE, 2001; U.S. DoD, 2008). The input sheet includes a "drop-down" list
box with the following options:
• No additional nutrients required
• Additional nitrogen required
• Additional phosphorous required
• Both nitrogen and phosphorous required.
For nitrate treatment the nitrogen addition options are inactive. For designs that require
additional nutrients, the model prompts the user to input doses for ammonium chloride and/or
39
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
phosphoric acid. The model standard designs use additional phosphorous in the form of
phosphoric acid at a dose of 1 mg/L as phosphorus.
Empty Bed Contact Time or Hydraulic Residence Time
Theoretical total empty bed contact time (EBCT) 12 minutes
EBCT inputs OK
— or —
Hydraulic residence time (HRT) 12 minutes
HRT inputs OK
EBCT is defined as the volume of support media divided by the flow rate. Minimum EBCT
needed for the contaminant to be fully reduced is the primary design parameter in sizing fixed
bed bioreactor vessels. For fluidized bed bioreactors, HRT is the more accurate term for the
primary design parameter. HRT is the time required for treated water to move through the
fluidized media bed. For larger flows, multiple bioreactors will be operated in parallel. For
perchlorate reduction, full-scale bioreactor designs have an EBCT or HRT in the range of 10 to
12 minutes for both fixed bed reactors (U.S. DoD, 2008) and fluidized bed reactors (Harding
ESE, 2001). The model standard designs use a 12 minute EBCT (for fixed bed designs) or HRT
(for fluidized bed designs). For nitrate treatment, the model uses a default EBCT/HRT value of
10 minutes (Upadhyaya et al., 2010).
Bed Depth and Bioreactor Dimensions
For all design types, the input sheet requires an input for the depth of the media bed in the
bioreactors. For gravity basins, typical bed depths are between 3 and 10 feet. For pressure
vessels, typical bed depths are between 2 and 7 feet. For preliminary design, other sources of a
reasonable bed depth include the designer's past experience, pilot study results and published
literature. The specific input fields for bioreactor dimensions other than bed depth differ among
the three design types, as described below. For all three design types, the model includes a
computer-aided design routine, also described below, to assist users in selecting dimensions.
Fixed Bed Pressure Vessel Dimensions and Geometry
Bioreactor Pressure Vessels
The next four inputs may be entered manually, or calculated with AutoSize button. All other gold inputs must be complete before AutoSizing.
Bed depth
4.9
feet
Auto Size Pressure
Vessel geometry
upright
<-- pick one
Vessels
Height (straight)
8.5
feet
Diameter
12.5
feet
For fixed bed pressure bioreactor designs, the input sheet requires vessel geometry values.
Options are vertical or upright cylinders for small to medium sized systems and horizontally laid
long cylinders for large systems. Inputs include the straight height or length of the vessel and the
diameter of the vessel. Pressure vessels used in this application typically are cylindrical, with a
diameter ranging from 2 to 12 feet. The guidance suggests using horizontally laid vessels 20 to
40 feet long and 10 to 12 feet in diameter for systems with design flows greater than 2,000
gallons per minute.
The input sheet will display warning signs if the dimensions of the selected vessel are outside the
boundaries specified on the critical design assumptions sheet. These boundaries include loading
40
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
rates, which are discussed in more detail in Section 3.3, and transportation limitations. For large
treatment plants, on-site assembly of tanks might be an option to overcome transportation
limitations. To allow this option, the user should increase the maximum dimensions permitted on
the critical design assumptions sheet.
Fluidized Bed Pressure Vessel Dimensions and Geometry
Bioreactor Pressure Vessels
The next four inputs may be entered manually, or calculated with AutoSize button. All other gold inputs must be complete before AutoSizing.
Static bed depth
5.8
feet
Auto Size Pressure
Vessel geometry
<- pick one
Vessels
Height (straight)
17
feet
Diameter
12.5
feet
For fluidized bed pressure bioreactor designs, the design constraints are similar to the packed bed
pressure vessels, except that the model only allows designs for vertical vessels. Fluidized vessels
are typically taller than fixed bed vessels due to space requirements above the fluidized bed, as
discussed in Section 3.3.
Gravity Contact Basin Dimensions
Bioreactor Fixed Bed Gravity Contact Basins
The next three inputs may be entered manually, or calculated with AutoSize button. All other gold inputs must be complete before AutoSizing.
Basin width
11
feet
Auto Size Gravity
Basin length
11
feet
Contactors
Bed depth
5.0
feet
There are challenges involved with designing gravity fed bioreactors, primarily the loss of head
over the treatment system and the fact that downward flow bioreactors lead to biomass
accumulati on on the bottom of the media bed, which can be difficult to clean. For gravity
bioreactor basins, the input sheet requires the user to input the width and length of the basins.
Bioreactor basins typically are square. The input sheet will display warning signs if the
dimensions of the basin are outside the boundaries specified on the critical design assumptions
sheet. These boundaries include loading rates, which are discussed in more detail in Section 3.3,
and reasonable size limitations based on generally recommended engineering practices (GREPs).
The size limitations (which can be modified by the user on the critical design assumptions sheet)
are:
• Bed depth of 3 to 10 feet
• Width and length of 3 to 30 feet.
Autosize Routine
To aid users, the model includes buttons labeled "Autosize" for each of the design types. These
buttons activate a computer-aided design routine that attempts to find a design that meets all
relevant design constraints for a given design and average flow and minimizes annualized cost.
Using the autosize routine, the model will automatically select bed depth, geometry and
dimensions that meet all constraints, thus reducing trial and error by users, particularly for
systems with design flows other than the eight standard sizes provided on the input sheet. Note
that all other inputs must be complete before using the autosize routine. For standard designs, the
41
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
U.S. Environmental Protection Agency (EPA) used the autosize routine to select dimensions that
meet all required constraints.
Post-Treatment Options
Post-treatment oxidation option
aeration
<- pick one
Include polishing filter
yes
<- pick one
Polishing filter type
gravity basin
<- pick one
Incude coagulant addition before filtration
yes
<- pick one
Post-treatment inputs OK
Biological treatment results in soluble microbial organic products that become part of the treated
water. The biological treatment process also depletes the levels of oxygen in the treated water.
Therefore, post-treatment in the form of re-oxygenation, followed by mixed media filtration for
removal of turbidity, sulfide and/or dissolved organic content, typically will be required for
production of drinking water. The input sheet allows the user to select either aeration or
hydrogen peroxide addition for re-oxygenation. It also allows the user to select whether or not to
include post-treatment (polishing) filtration. If filtration is included, it allows the user to select
either gravity basins or pressure vessels and to indicate whether coagulant is added prior to the
mixed media filter. The effluents from the bioreactors contain solids and a coagulant is usually
used in order to assist post-treatment filtration.
The model does not include post-treatment disinfection. To account for the cost of post-treatment
disinfection, EPA has developed separate WBS models that generate costs for this post-treatment
step. For example, the chlorine gas and hypochlorite models described earlier in this document
are capable of estimating the cost of post-treatment disinfection using these technologies. In
generating national costs, EPA would add costs from the separate post-treatment disinfection
models to costs from the biological treatment model for scenarios that require additional post-
treatment disinfection.
The model standard designs include re-oxygenation using aeration and filtration using gravity
basins. The model standard designs also include coagulant addition prior to filtration.
Interval between Backwashes and Include Air Scour
Interval between bioreactor backwashes
24
hours
Interval between filter backwashes
36
hours
Include air scour
yes
<~ pick one
Fixed bed bioreactors require periodic backwashing to remove excess biomass. The backwash
water must not be chlorinated to protect the microbial populations in the filter. Fluidized bed
bioreactors use a continuous biomass separation device consisting of a blower to agitate excess
biomass and send it out of the bioreactor in the effluent. For fixed bed bioreactors, an air scour
followed by a water flush is used to remove biomass from the media. Typical fixed bed
bioreactors have a backwash interval in the range of 24 to 36 hours, which is determined based
on target head across the media bed. The input sheet requires the user to specify backwash
intervals for fixed bed bioreactors. It also requires a backwash interval for post-treatment filters
when they are part of the biological treatment design (see above). When either fixed bed
bioreactors or post-treatment filters are present in the design, the input sheet requires the user to
specify whether or not to include air scour in the backwash process. The model standard designs
42
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
use backwash intervals of 24 hours for fixed bed bioreactors and 36 hours for post-treatment
filters. The model standard designs include air scour.
Residuals Management
Discharge option for spent backwash
recycle
<— pick one
Holding tank for spent backwash
always included
Solids treatment/storage
none
<— pick one
Characteristics of holding tank solids
non-hazardous
pick one
Residual inputs OK
In fixed bed bioreactors, biomass removal typically is accomplished using a backwash process
that generates spent backwash water containing excess biosolids and some lost media. This
backwash water is non-toxic and can be discharged to a sanitary sewer. However, a clarification
and recycle process is more common. Post-treatment filters can also generate residual wastes in
the form of backwash water and separated solids. Exhibit 3-5 shows the management options
available for spent backwash. When both bioreactor backwash and post-treatment filter
backwash are present, the model combines these two streams for management using the same
options and equipment.
Exhibit 3-5. Management Options for Spent Backwash
Options for Stage 1 of Management
Options for Stage 2 of Management
Holding tank with or without coagulant addition (for flow
equalization and suspended solids removal)*
Direct discharge to surface water
Discharge to POTW (via sanitary sewer)
Recycle to head of treatment train
No holding tank
Direct discharge to surface water
Discharge to POTW (via sanitary sewer)
Evaporation pond**
* Results in generation of secondary residuals (holding tank settled solids).
** Results in generation of secondary residuals (evaporation pond solids).
The management options shown in Exhibit 3-5 include the option for a holding tank for flow
equalization. The purpose of the holding tank is to equalize the rate of flow at which residuals
are released or discharged. When averaged over the time between generation events, backwash
flow is relatively low. Instantaneous flow during a generation event, however, is much higher. If
spent backwash is recycled to the head of a treatment plant, recommended engineering practice
is that the recycle stream should be no more than 5 to 10 percent of total system flow (U.S. EPA,
2002; U.S. EPA, 1996). Given the instantaneous backwash flow rates, if recycling is chosen for
stage 2 of management, a holding tank would always be necessary to prevent recycle flow from
exceeding this recommendation. It also may be reasonable to include a holding tank for the other
stage 2 options (e.g., to prevent instantaneous flow from overwhelming the capacity of a publicly
owned treatment works [POTW]).
Exhibit 3-5 includes the option for an evaporation pond. When very large quantities of spent
backwash are generated, an evaporation pond might be appropriate, particularly for facilities in
dry climates. A holding tank would not be necessary with an evaporation pond, because the
design of the pond would provide sufficient capacity to handle instantaneous flow. The required
area for an evaporation pond depends on local climate. After selecting an evaporation pond, the
43
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
user should carefully review the climatic parameters on the critical design assumptions sheet. For
more information, see Appendix C. Furthermore, to ensure that heating, cooling and standby
power costs are computed consistently, the user should review the climatic parameters in the
operating and maintenance (O&M) and indirect assumptions sheets. Appendix E and Appendix
D contain information on these parameters.
The use of a holding tank or evaporation pond results in the generation of a secondary residuals
stream, in the form of solids that settle from the spent backwash during the holding/evaporation
period. When a holding tank is used, the model includes the option to add a polymer to promote
the settling of these solids and reduce suspended solids levels in the holding tank effluent. As a
default, the model includes polymer addition. The user can change this option on the critical
design assumptions sheet. For holding tank solids, the model also includes an input to allow for
additional solids treatment and intermediate storage processes. Options under this input are no
additional treatment or use of a thickener with mechanical or non-mechanical dewatering.
Management options available for secondary solid residuals (i.e., holding tank solids or
evaporation pond solids) include off-site non-hazardous waste landfill disposal6 and off-site
hazardous waste disposal. The management options do not include disposal in an on-site landfill.
This option would be economically viable only for facilities with an existing on-site landfill—a
factor that is highly site-specific. For such facilities, the cost of this option would be less than
that for off-site disposal, because it would involve much lower transportation costs. Therefore,
the off-site disposal options included provide a conservative cost estimate for these facilities.
For all systems, the model standard designs manage spent backwash by recycling to the head of
the treatment train, which means the designs also include holding tanks. The standard designs
include non-hazardous waste landfill disposal for the holding tank solids, without additional
treatment or storage.
Number of Booster Pumps
For information: # of booster pumps
2 pumps
Review of actual as-built designs for small systems using various technologies (U.S. EPA, 2004)
shows that these systems often can operate without additional booster pumps using existing
supply pump pressure. Therefore, the model uses zero booster pumps for small systems (less
than 1 million gallons per day [MGD] design flow). For larger systems, the model calculates the
number of pumps using a method that attempts to minimize the number of pumps, while still
accommodating variations in flow and providing redundancy to account for possible equipment
failure. The model includes an optional input that allows the user to change these default
calculations by specifying the number of pumps required to operate the treatment system. If the
user enters zero, the model excludes booster pumps from the design and cost estimate. The
model standard designs leave this input blank, excluding booster pumps for small systems (less
than 1 MGD design flow) and accepting the default calculations for larger systems.
6 Users can also select land application, instead of landfilling, for non-hazardous secondary residuals by changing an
option on the critical design assumptions sheet. Appendix C discusses this option in more detail.
44
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Number of Redundant Units
Number of redundant units to be added
^ units
For information: Redundant bioreactors
1 units
This optional input controls the model calculation for the number of redundant bioreactors. There
should be a minimum of one redundant bioreactor in a treatment system. An exception would be
small systems designed with multiple bioreactors required to treat the maximum design flow. In
such systems, the average daily flow is low enough, relative to the design flow, that the multiple
bioreactor design provides sufficient redundancy without additional vessels. The system can
operate at reduced, but greater than average, flow, even while one bioreactor is off-line for
backwashing. Thus, the number of redundant bioreactors can be zero for certain small systems
having at least two bioreactors.
The model assumes redundant bioreactors (and other redundant items of equipment) are used
during downtime periods for other bioreactors and are swapped into operation intermittently,
with other vessels then becoming standby. For this reason, the O&M estimate in the model
includes labor for operating valves and reading instruments associated with redundant
bioreactors.
The input sheet allows the user to specify the number of redundant bioreactors. If the user leaves
this optional input blank for a large system (1 MGD or greater design flow), the model calculates
the number of redundant bioreactors based on a redundancy frequency specified on the critical
design assumptions sheet. If the user leaves this optional input blank for a small system (less
than 1 MGD design flow), the model does not add redundant bioreactors, unless the design
selected by the user results in a single operational bioreactor. If the design does use only a single
operational bioreactor, the model adds one redundant bioreactor. The standard designs leave this
input blank, resulting in the following redundancy results:
• No redundant bioreactors for small systems, (less than 1 MGD design flow), except in
cases where the design results in only one operating bioreactor
• One redundant bioreactor every eight treatment trains for larger fixed bed pressure
bioreactor systems (1 MGD or greater design flow)
• One redundant bioreactor total for medium gravity basin systems (1 MGD to less than 10
MGD design flow)
• Two redundant bioreactors total for large gravity basin systems (10 MGD or greater
design flow)
• No redundant bioreactors for larger fluidized bed designs (1 MGD or greater design
flow).
Backwash Pumping
Backwash pumping
existinq pumps
new pumps
The backwash process can require new pumps or use existing pumps (either influent supply
pumps or treated water pumps, assuming these pumps can deliver unchlorinated treated water).
45
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
The practicality of using existing pumps can vary on a site-specific basis, depending on the
performance characteristics of the existing pumps and the differences in head required between
normal operation and during backwash. By default, the model uses existing pumps for backwash
for small systems (less than 1 MGD design flow), but includes the costs of new backwash pumps
for larger systems. The model includes an optional input that allows the user to change these
default assumptions by explicitly selecting "existing pumps" or "new pumps." If the "existing
pumps" option is selected, the costs of backwash pumps will be excluded from the output sheet.
If "new pumps" is selected, these costs will be included. The standard designs leave this input
blank, thereby assuming the use of existing pumps for small systems (less than 1 MGD design
flow), but including the costs of backwash pumps for larger systems.
Backwash Storage
| Backwash storage - Pick or leave blank
existinq storaqe
it rtf harkAAiackU^WStOrage its
Backwash tanks may not be required on most installations, particularly for large systems that
have treated water storage capacity. The model is set up so that systems with design flow less
than 1 MGD do not require backwash tanks because the quantity of backwash water required is
low. The model also is designed so that systems of 10 MGD and larger design flow do not
require backwash tanks because existing storage capacity is sufficient. The model includes
backwash tanks for intermediate-sized systems. The model includes an optional input that allows
the user to change these default assumptions by explicitly selecting "existing storage" or "new
storage." If the "existing storage" option is selected, the costs of backwash tanks will be
excluded from the output sheet. If "new storage" is selected, these costs will be included. The
standard designs leave this input blank, thereby including the costs of backwash tanks for
intermediate-sized systems (1 MGD to less than 10 MGD design flow) only. To maintain the
bacterial populations responsible for contaminant reduction, water used for backwashing
bioreactors should not be chlorinated.
System Automation
| System automation
~
pick or leave blank
manual
semi-automated
fully automated
I
The system automation optional input in the biological treatment model functions as described in
Section 2.3. However, because of the importance of process monitoring and control in biological
treatment, the model standard designs specify fully automated systems, instead of leaving the
system automation input blank.
3.3 Model Assumptions Sheets
There are three sheets that contain assumptions needed to facilitate process design: the critical
design assumptions sheet, the operating and maintenance (O&M) assumptions sheet and the
indirect assumptions sheet. These sheets contain a variety of structural and chemical engineering
46
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
parameters used in the engineering sheets. They also interact with the input sheet to determine if
the user inputs violate good engineering practices. For example, if a user selects bioreactor
dimensions that generate a surface loading rate that is too high or low, a warning message will
appear on the input sheet. The warning message will advise the user to adjust bioreactor
dimensions or bed depth to achieve a surface loading rate within generally recommended
engineering practices.
There are more than 100 critical design assumptions in the model that cover process, O&M and
indirect cost parameters. Key critical design assumptions include surface loading rate, fluidized
bed expansion and freeboard, backwash assumptions, media attrition, bypass percentage and
assumptions applicable to small systems. The following sections provide descriptions and default
values for these assumptions. Any assumption value can be modified, as needed.
Surface Loading Rate
A loading rate is the velocity of flow through the media measured in units of flow rate per unit
area in gallons per minute per square foot (gpm/ft2). The surface area of the bioreactors must be
selected to maintain loading rates within reasonable bounds because water can channel through
the carbon bed if the loading rate is too low and pressure requirements might be excessive if the
loading rate is too high. For biological treatment systems, loading rates usually are between 1
gpm/ft2 and 15 gpm/ft2. Higher loading rates can be used in site-specific situations where
hydraulics and tests allow or in fluidized bed designs where loading rate includes both influent
and recycled water flow. The model includes a maximum loading rate of 10 gpm/ft2 and a
minimum loading rate of 1 gpm/ft2.
Fluidized Bed Expansion and Freeboard (fluidized bed designs only)
For fluidized bed bioreactors, an additional important vessel sizing consideration is bed
expansion. Target bed expansions are used to determine the height of the vessels. Typically, the
vessel is filled with a fixed bed depth of media and initially fluidized to 40 to 50 percent. As the
biomass grows, the fluidized media bed expands further. The model is designed so that this
additional expansion brings the fluidized bed to 70 percent of the initial fixed bed depth.
Biomass separation maintains expansion at this target level. Additional space at the top of the
vessel provides a safety factor to prevent fluidized media from exiting the reactor. The model
uses a freeboard of 7 feet or 4 feet for small systems (less than 1 MGD design flow).
Backwash Assumptions (Fixed Bed Designs and/or Post-Treatment Filters Only)
For fixed bed bioreactors and post-treatment filters, backwash rates should be sufficient to
fluidize the bed and should allow for the expansion of the media during backwash
(AWWA/ASCE, 1998). The model includes a bioreactor bed expansion value during backwash
of 50 percent and accounts for this expansion in sizing the reactor vessels or basins. The
backwash for the bioreactors occurs at a lower rate than the filters because only the excess
biosolids are intended to be removed, not all of them. The model includes a backwash rate of 15
gpm/ft2 and backwash duration of 7 minutes for post-treatment filters, compared to a backwash
rate of 8 gpm/ft2 and backwash duration of 10 minutes for fixed bed bioreactors.
47
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Media Attrition
During the backwash of fixed bed bioreactors and post-treatment filters, some media is carried
off in the backwash water and lost. The model includes a 10 percent loss of media bed per year
for both fixed bed bioreactors and post-treatment filters. The model also includes a 5 percent loss
of media per year for fluidized designs for media lost during the biomass separation process.
Bypass Percentage
Because biological treatment can reduce contaminants to very low levels, systems may choose to
treat only a portion of their production flow, using a smaller treatment system and blending
treated water with raw water while still achieving treatment targets. The bypass percentage is
that portion of production flow that goes untreated. If bypass is used, the model designs the
treatment system to treat a flow equal to (100 percent minus bypass percentage) multiplied by
design flow and adds bypass piping and associated valves to the components included on the
output sheet. The model uses no bypass, but the user can incorporate bypass by entering a
percentage of bypass flow on the critical design assumptions sheet.
Small Systems
Off-the-shelf package systems are not currently available for biological treatment systems.
However, because the equipment required for the process is similar to that for other technologies
utilizing pressure vessels (e.g., adsorptive media, GAC), the model is designed so that small
biological treatment systems can be partially pre-engineered in a similar manner to that used for
the other technologies. That is, many of the primary process components can be mounted on a
skid that is pre-assembled off-site and transported to the treatment location. Accordingly, for
small systems (less than 1 MGD design flow), the model applies a variant set of design inputs
and assumptions that are intended to simulate this practice. Also included are assumptions that
reflect the smaller capacity and reduced complexity of the treatment systems. These design
modifications typically reduce the size and cost of the treatment system. Some are adjustable on
the input sheet or the critical design assumptions sheet, while others are in the engineering design
formulae. Exhibit 3-6 shows the design modifications used in the model for small systems.
Exhibit 3-6. Variant Design Inputs and Assumptions for Small Systems
Small System Design
Modification
Explanation
Model Location
Reduced spacing
between vessels and
other equipment
This assumption simulates skid placement of treatment vessels (and
of pumps, if included in the design), resulting in reduced system
footprint and, therefore, reduced costs for interconnecting piping,
building structures, certain indirect costs and O&M.
Design equations in
the pumps, pipe and
structure sheet
No redundant
bioreactors
Small systems typically do not include redundant bioreactors
because they are designed to operate at reduced capacity during
the brief periods when one bioreactor is not operating (e.g., during
backwash).
Input sheet
Reduced instrumentation
requirements
Instrumentation required for small systems does not include level
switch/alarms on the bioreactors. All other instrumentation remains
the same for small biological treatment systems because of the
importance of process monitoring.
Critical design
assumptions sheet
48
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Small System Design
Modification
Explanation
Model Location
Simplified system
controls for automated
systems
Small systems, when automated, typically are controlled by a single,
pre-programmed operator interface unit mounted on the skid.
Therefore, for small systems, the model uses this type of operator
interface only and excludes multiple programmable logic controllers,
computer workstations, printers, operator interface software and
plant intelligence software included for large, automated, custom-
engineered systems.
Component selection
logic in the output
sheet and WBS cost
database
No booster pumps
Small systems result in limited head loss and typically do not require
additional booster pumps.
Input sheet
No backwash pumps or
tanks
Small systems typically use existing pumps and water supplies and
do not require separate backwash pumps or backwash water
storage.
Input sheet
Reduced concrete pad
thickness
Small capacity systems require less structural support.
Critical design
assumptions sheet
Reduced indirect costs
Small systems require less effort to design and install. Therefore, the
model reduces or eliminates certain indirect costs (e.g.,
mobilization/demobilization, construction management) for small
package plants (see Appendix D for complete details).
Indirect assumptions
sheet
3.4 Bioreactor Constraints Sheet
The bioreactor constraints sheet contains calculations that utilize the user-defined parameters
from the input sheet and the boundary values from the critical design assumption sheet to
determine the validity of the input values. This sheet also determines the number of bioreactors
required and the quantity of media needed, given the input values selected by the user. For
gravity basin designs, this sheet also calculates the total volume of concrete required and,
because bioreactor basins are constructed below grade, determines excavation and backfill
requirements.
3.5 Chemicals Sheet
The chemicals sheet calculates the electron donor and nutrient requirements, based on the input
options chosen by the user, and calculates the number and size of electron donor and nutrient
tanks needed. The model includes separate day tanks, in addition to the primary bulk storage
tanks, are required if daily usage at design flow exceeds the number of gallons specified on the
critical design assumptions sheet. To provide secondary containment for electron donor and
nutrient chemicals, this sheet also includes calculations for concrete curbing around each storage
area and chemical resistant coating for the curbing and the underlying concrete pad.
3.6 Biomass Control Sheet
The biomass control sheet calculates the total backwash volume required to backwash one
bioreactor or post-treatment filter based on the surface area, backwash loading rate and backwash
time. The sheet uses these values to calculate backwash storage requirements. When backwash
storage is included, this storage can use steel, fiberglass or plastic backwash tanks. This sheet
calculates the total volume of each tank. This sheet also calculates the air scour volume used for
biomass separation in fluidized bed designs.
49
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
3.7 Post-Treatment Sheet
The post-treatment sheet calculates the equipment requirements for the various post-treatment
steps to be included in the design based on the input options chosen by the user. For post-
treatment re-oxygenation by aeration, this sheet performs calculations to determine the number
and size of aeration tanks and diffusers. If hydrogen peroxide is used in place of aeration, the
sheet calculates the hydrogen peroxide needed per day and in storage, followed by the number
and size of storage tanks, day tanks, inline static mixers and curbing and chemical resistant
coating for secondary containment. If post-treatment filtration is included, this sheet determines
the number and size of filters required and the quantity of media needed. For gravity basin
designs, it calculates the total volume of concrete required and, because post-filtration basins are
constructed below grade, determines excavation and backfill requirements. This sheet also
calculates the amount of coagulant addition and size of the coagulant mix tank used prior to
filtration.
3.8 Pumps, Pipe and Structure Sheet
Other elements of the technology for which the size and cost need to be determined include
pumps, blowers and piping. The pumps, pipe and structure sheet performs the required
calculations to determine the number and size (in terms of flow capacity) of the following
pumps:
• Booster pumps
• Recycle pumps (fluidized bed designs only)
• Backwash pumps (if required)
• Chemical metering pumps (electron donor, nutrients, post-treatment hydrogen peroxide)
• Blowers for post-treatment aeration (if required)
• Blowers for backwash air scour (if required)
• Blowers for biomass separation (fluidized bed designs only).
This sheet uses the input values for flow and water quality parameters, as well as the pertinent
parameters detailed on the critical design assumption sheet, to determine the number of pumps
needed, including redundant units. Pump sizing depends on the maximum corresponding flow
rate. For example, booster pumps are sized based on the system design flow and backwash
pumps are based on the total backwash flow. The sizes of metering pumps vary based on the
calculations performed on the chemicals sheet (or post-treatment sheet for hydrogen peroxide).
As discussed in Section 2.3, the sizing of all pumps incorporates a safety factor, which is
specified on the critical design assumptions sheet.
This sheet also performs calculations for the following pipes:
• Influent and effluent piping
• Process piping
• Backwash piping
• Chemical piping (electron donor, nutrients, post-treatment hydrogen peroxide)
• Bypass piping (if a bypass percentage is specified).
50
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
The size (diameter) of pipes is determined using a pipe flow look-up table that is part of the
WBS cost database. The pipe diameter selection method incorporates a reasonable head loss and
flow velocity, as documented in Exhibit 2-8. These design assumptions may result in some over
sizing of pipes, which means the resulting cost estimates may be conservative (i.e., err on the
high side).
The flow used to determine influent and effluent pipe size is the design flow. The diameter of
interconnecting process piping uses the same pipe flow chart, after splitting the inflow by the
number of parallel treatment trains. A similar approach is used in determining the size and
capacity of backwash, chemical and bypass piping. The length of these pipes is determined using
the assumptions documented in Exhibit 2-10, which are designed to account for the cost of
fittings.
This sheet also calculates the housing area for this technology based on the footprint of the
technology components and the spacing criteria specified on the critical design assumption sheet.
The space requirements for bioreactors, pumps, tanks and service space are based on
manufacturer specification, "to scale" drawings and the experience of engineers. The amount of
additional concrete needed to support heavy equipment, such as pumps and pressure bioreactors,
is based on the footprint of the equipment.
For smaller space requirements (less than a square footage specified on the critical design
assumptions sheet), the model includes a single building containing all process equipment. For
larger requirements, the model includes two buildings, one containing the bioreactors and post-
treatment filters (if included) and the other containing all other equipment. The number of
buildings affects the total land required and energy costs for heating, ventilating and cooling.
3.9 Instrumentation and Control Sheet
The instrumentation and control sheet calculates requirements for valves, instrumentation (e.g.,
flow meters) and automated system controls. The number of valves and instruments is based on
the number of process components (e.g. number of treatment lines) and assumptions from the
critical design assumptions sheet (e.g., x number of valves per treatment line). The assumptions
correspond to the general schematic layout for this technology shown in Exhibit 3-2 and Exhibit
3-3. Sizing of valves corresponds to the size of the appropriate pipe determined in the pumps,
pipe and structure sheet. Appendix A describes the method used in the WBS models to estimate
the number and type of system control components.
3.10 Residuals Management Sheet
The residuals management sheet estimates the volume and mass of residuals, their characteristics
and the capital and O&M requirements for residuals management based on the management
options selected in the input sheet and the approach outlined in Appendix C. Depending on the
management options chosen, specific items of capital equipment for residuals can include:
• Holding tanks
• Pumps
• Evaporation ponds (including excavation and lining)
• Polymer feed and mixing equipment
51
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
• Valves, piping and instrumentation.
Specific O&M requirements associated with residuals can include:
• Residuals pump labor, materials and energy
• Sanitary sewer discharge fees
• Polymer usage
• Secondary residuals (holding tank solids) transportation and disposal costs.
3.11 O&M and HVAC Sheets
The O&M and HVAC calculations cover two sheets: the O&M sheet (annual labor, materials
and energy usage) and the HVAC sheet (HVAC capacity requirements). The O&M sheet derives
O&M requirements for biological treatment based on the engineering design, O&M critical
design assumptions and input values. It determines the following O&M requirements based on
the approach outlined in Section 2.4 and Appendix E:
• Operator labor for system operation and maintenance
• Managerial and clerical labor
• Booster pump maintenance materials and operating energy
• Facility maintenance materials
• Energy for building lighting and HVAC.
In addition, the O&M sheet adds the following technology-specific O&M requirements:
• Operator labor and materials for backwash pump and air scour blower maintenance (if
backwash occurs weekly or more frequently)
• Operating energy for backwash pumps and air scour blowers
• Operator labor, materials and energy for aeration blowers
• Operator labor, materials and energy for recycle pumps and biomass removal blowers
(for fluidized bed designs)
• Operator labor for managing bioreactor backwash events
• Operator labor for managing post-treatment filter backwash events
• Operator labor and materials for basin maintenance (for fixed bed gravity basin designs)
• Chemical usage (electron donor, nutrients, post-treatment hydrogen peroxide)
• Replacement media to account for attrition loss in the bioreactors and post-treatment
filters.
Because biological systems are backwashed frequently, backwash pumping facilities (including
air scour blowers) consume more energy than for other technologies and can require significant
maintenance. Therefore, when backwash occurs weekly or more often, the model includes these
O&M costs explicitly. The sheet determines materials for backwash pumps and blowers using
the same approach outlined in Appendix E for booster or influent pumps. Backwash pump and
blower maintenance labor also uses the approach described in Appendix E for booster or influent
pumps. Backwash pump and air scour blower energy consumption also follows the approach in
Appendix E, except that, rather than assuming continuous operation, the calculation uses the
number of hours per year during which backwash pumps and blowers operate.
52
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
For manual and semi-automated systems, backwashing requires constant operator attention.
Therefore, the model includes labor equal to twice the actual time to accomplish backwash for
these systems. For automated systems, the model uses one minute per backwash event to verify
that the automated backwash cycle is initiated and operating properly. The user can change this
latter assumption on the O&M assumptions sheet.
For bioreactors with gravity basin designs, the O&M sheet determines labor for basin
maintenance assuming one hour per week for each contact basin. The model also includes the
annual cost of materials for contact basins equal to 1 percent of their pre-installation capital cost.
The user can change these assumptions on the O&M assumptions sheet.
The O&M sheet determines chemical usage based on the electron donor and nutrient
requirements calculated on the chemicals sheet and the hydrogen peroxide requirements
calculated on the post-treatment sheet. It calculates replacement media requirements based on the
attrition loss rate assumptions on the critical design assumptions sheet.
3.12 Indirect Sheet
As stated in Section 2.4, indirect capital costs are costs that are not directly related to the
treatment technology used or the amount or quality of the finished water, but that are associated
with the construction and installation of a treatment technology and water intake structures. The
indirect sheet derives capital costs for the following components of indirect costs:
• Construction management and general contractor overhead
• Standby power
• Geotechnical
• Site work
• Yard piping.
Appendix D contains detailed information on the derivation of these and other indirect costs.
This sheet also contains calculations to estimate permit costs.
3.13 Output Sheet
The output sheet contains the list of components identified for biological treatment based on the
WBS approach. For each component, the output sheet provides information on size (e.g., tank
capacity or pipe diameter) and quantity, as well as estimated capital cost and estimated useful
life. The output sheet also contains cost estimates for indirect capital costs (e.g., mobilization and
demobilization, site work and yard piping), add-on costs (for permitting, pilot testing and land)
and O&M costs. These estimates are described generally in Section 2.4 and in more detail in
Appendix D (indirect costs) and Appendix E (O&M costs). Finally, the output sheet combines
the total capital cost, system useful life and annual O&M cost to estimate total annualized cost,
as discussed in Section 2.4. Sections 2.1 and 2.3 provide further details about the output sheet.
As discussed in Section 2.4, the output sheet shows model results to the nearest $1, but this
precision is not meant to imply that the results are accurate to $1. The biological treatment model
underwent peer review in early 2012. One reviewer thought the model underestimated O&M
costs by 20 to 30 percent (which would be in the range of an order of magnitude estimate), but
53
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
overestimated capital costs by about 25 percent (which would be in the range of a budget
estimate). A second reviewer responded that direct capital costs were at the fringes of a budget
estimate (+30 to -15 percent), while total capital costs were in the order of magnitude range (+50
to -30 percent) or possibly even better, in the budget estimate range. This reviewer's conclusions
about total capital costs were based on comparison to preliminary costs for a plant currently
under construction, for which the model underestimated costs. The final reviewer responded that
costs were budget estimates (+30 to -15 percent). The biological treatment model has since
undergone revision in response to the peer review comments. Users are encouraged to review all
documentation, modify inputs and assumptions as appropriate to their specific purpose, and form
their own informed opinions about the accuracy and suitability of the results shown on the output
sheet.
3.14 Ancillary Model Components
The model contains several ancillary sheets: index, standard inputs, autosize, cost equations and
lookup tables. The index is a hyperlinked list of user-adjustable inputs and assumptions that can
assist the user in finding these inputs and assumptions, should they wish to change them. The
standard inputs worksheet documents the inputs used in the standard designs. Advanced users
can adjust these standard inputs, if desired. The model uses the autosize sheet when performing
the iterative calculations required when the user clicks an "Autosize" button on the input sheet.
The cost equations sheet uses the component-level cost curve equations from the WBS cost
database to generate unit costs on an item-by-item basis. The lookup tables sheet is for internal
model use in populating the drop-down boxes on the model input sheet.
3.16 References
American Water Works Association and American Society of Civil Engineers (AWWA/ASCE).
1998. Water Treatment Plant Design. Third Edition. New York: McGraw-Hill.
Greene, M.R. and M.P. Pitre. 2000. "Treatment of Groundwater Containing Perchlorate Using
Biological Fluidized Bed Reactors with GAC or Sand Media." in E.T. Urbansky (ed)
Perchlorate in the Environment. Cincinnati, OH: U.S. EPA Office of Research and
Development.
3.15
EBCT
EPA
GAC
gpm/ft2
GREPs
HRT
HVAC
MGD
mg/L
O&M
POTW
WBS
List of Abbreviations and Symbols in this Chapter
empty bed contact time
U.S. Environmental Protection Agency
granular activated carbon
gallons per minute per square foot
generally recommended engineering practices
hydraulic residence time
heating, ventilating and air conditioning
million gallons per day
milligrams per liter
operating and maintenance
publicly owned treatment works
work breakdown structure
54
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Harding Engineering and Environmental Services (ESE). 2001. Final: Phase 2 Treatability
Study Report, Aerojet GET E/F Treatment Facility, Sacramento, California. Prepared for U.S.
Environmental Protection Agency Region IX and Baldwin Park Operable Unit Cooperating
Respondents, San Gabriel Basin, California. September.
Marqusee, J. 2001. In Situ Bioremediation ofPerchlorate in Groundwater. Presentation at
Federal Remediation Technologies Roundtable, General Meeting. 30 May.
Polk, J., C. Murray, C. Onewokae, D. E. Tolbert, A. P. Togna, W. J. Guarini, S. Frisch and M.
Del Vecchio. 2001. Case Study ofEx-Situ Biological Treatment of Per chlorate-Contaminated
Groundwater. Presented at the 4th Tri-Services Environmental Technology Symposium, San
Diego, CA. 18-20 June.
Upadhyaya, G.; Jackson, J.; Clancy, T.M.; Hyun, S. P.; Brown, J.; Hayes, K. F.; Raskin, L. 2010.
Simultaneous removal of nitrate and arsenic from drinking water sources utilizing a fixed-bed
bioreactor system. Water Research.
U.S. Department of Defense (U.S. DoD). 2008. Direct Fixed-bed Biological Perchlorate
Destruction Demonstration. ESTCP Final Report (ER-0544). 25 September.
U. S. DoD. 2009. Demonstration of a Full-Scale Fluidized Bed Bioreactor for the Treatment of
Perchlorate at Low Concentrations in Groundwater. Environmental Security Technology
Certification Program (ESTCP) Final Report (ER-0543). 20 January.
U.S. EPA. 1996. Technology Transfer Handbook: Management of Water Treatment Plant
Residuals. United States Environmental Protection Agency, Office of Research and
Development. EPA 625-R-95-008. April.
U.S. EPA. 2002. Filter Backwash Recycling Rule: Technical guidance manual. United States
Environmental Protection Agency, Office of Ground Water and Drinking Water. EPA 816-R-02-
014. December.
U.S. EPA. 2004. Capital Costs of Arsenic Removal Technologies, U.S. EPA Arsenic Removal
Demonstration Project, Round 1. EPA-600-R-04-201. Cincinnati, OH: U.S. EPA, National Risk
Management Research Laboratory.
Xu, J., Y. Song, B. Min, L. Steinberg and B.E. Logan. 2003. "Microbial Degradation of
Perchlorate: Principles and Applications." Environmental Engineering Science 20(5).
55
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Appendix A. Valves, Instrumentation and System Controls
A.1 Valves in the WBS Models
There are many types of valves used to control water and chemical flow rates, pressure and
direction in a water treatment plant. Valves can be distinguished by function, mode of operation,
materials of construction, size (i.e., diameter), design or shape and connection method. For
purposes of estimating valve costs, the most important of these distinctions are function, mode of
operation, size and materials of construction. Therefore, the work breakdown structure (WBS)
models group valves according to these four distinctions. The WBS models identify valve size
explicitly, using the same methodology used to size pipes. The WBS models also explicitly
identify materials of construction. The output sheet of each model includes line item costs for
valves of each material (plastic, stainless steel and cast iron), so that the user can observe
variations in cost among materials.
To distinguish by function and mode of operation, the WBS models use a generic nomenclature.
The WBS models identify valves as one of the following:
• Check valves
• Manual valves
• Motor/air-operated valves.
Check valves are those that serve the function of backflow prevention. They generally do not
vary significantly in mode of operation or design/shape.
The other two categories of valves serve the function of flow control and are distinguished by
their mode of operation (i.e., whether they are manual or automated). An example of a valve that
must be a manual valve is an emergency shut-off valve that, in an extreme event such as
complete power failure, can be shut off by an operator. Manual valves can vary in design
according to their specific opening/closing method (e.g., hand wheel or chain). Automated valves
(identified in the WBS models as motor/air operated) can be motor-operated valves, air-operated
valves or solenoid valves. Solenoid valves are electrically operated on/off control valves. Motor-
operated valves open and close more slowly than solenoid valves. This action reduces likelihood
of a water hammer. While the different opening/closing methods for manual and automated
valves have various advantages and disadvantages, cost differences among designs are relatively
small and the WBS unit costs do not distinguish between them at this level of detail. The key
cost difference is whether the valves are automated or manual, because of the cost of the motor,
air actuator or solenoid.
A.2 Instrumentation for Process Measurements
Each of the models includes the cost of various instruments that perform process measurements.
Most of these measurement devices are categorized into the following groups:
• Hydraulic measurement instruments and control devices. Hydraulic measurement
instruments include: flow meters, pressure gauges, head loss sensors and water level
meters/alarms. Hydraulic control devices include: pump control, motor control and valve
control.
56
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
• Water quality measurement and control devices. These include water quality parameter
measurement devices, such as pH meters, oxidation-reduction potential (ORP) sensors,
temperature meters, turbidity meters and sampling devices and ports.
The WBS models determine instrumentation requirements for each technology based on review
of the schematic flow diagram for the appropriate technology, along with certain general
assumptions that are applied to all of the technologies. Exhibit A-l documents the general
assumptions about instrumentation that are applied in the WBS models. Slightly different
assumptions hold when a model is intended as an add-on to an existing process (e.g., acid feed)
rather than a complete process (e.g., anion exchange).
Exhibit A-1. General Design Assumptions for Instrumentation
Instrument Type
Assumption
Chlorine analyzers
For chlorine and hypochlorite disinfection, 1 per treatment train to monitor residual
Conductivity meters
Varies by technology
Dissolved oxygen analyzers
Varies by technology
Drive controllers
1 per each pump (including booster, backwash and chemical metering pumps) or
other motorized item of equipment (e.g., mixers, blowers) in fully automated systems
Electric enclosures
Only for technologies with significant electric-powered equipment outside a building
structure
Flow meters
1 for the influent or effluent line and 1 for backwash discharge. Some technologies
also include flow meters on process lines.
Head loss sensors
Continuous level sensors. 1 per process vessel for technologies with pressure
vessels. Some technologies omit head loss sensors for systems with design flows
less than 1 million gallons per day.
High/low alarms
1 per backwash tank and 1 per chemical storage tank
Level switch/alarms
1 per process basin; 2 per contact tank for chemical disinfection technologies.
Technologies with chemical cleaning use 1 per chemical tank in the cleaning system.
ORP sensors
Varies by technology
Particle meters
Varies by technology
pH meters
1 each for the influent and effluent lines for systems with pH adjustment, plus others
on a technology-specific basis
Pressure transducers
Included in the cost of flow meter assemblies for venturi and orifice plate meters
Sampling ports
1 per process vessel, plus 1 each for the influent line, effluent line and discharge side
of the backwash line for complete process models. Others are included on a
technology-specific basis.
Total dissolved solids monitors
Varies by technology
Temperature meters
Varies by technology; often 1 for the influent and/or effluent lines, except for add-on
models. Some technologies omit temperature meters for systems with design flows
less than 1 million gallons per day.
Total organic carbon analyzers
Varies by technology
Turbidity meters
Varies by technology
Several types of flow meters can appear in the model output: propeller, venturi, orifice plate and
magnetic flow meters. In general, the choice of meter depends on the cost level and design flow
of the system, although some technologies require particular types of flow meters for specific
purposes. For smaller and/or low-cost systems, the preference order in the models will have
propeller flow meters as a first choice; for intermediate systems, venturi flow meters top the
preference order; and for larger and/or high-cost systems, the top preference is magnetic flow
57
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
meters. In all cases, the component buildup will display the price for all available types of flow
meters at a given size, so that a user can assess the cost impact of different types.
The critical design assumptions sheet of each model incorporates these general assumptions.
Therefore, the user can adjust instrumentation assumptions on a technology-specific basis.
Individual technologies—in particular, aeration technologies and chlorine and hypochlorite
disinfection—have additional or differing instrumentation requirements.
A.3 Control Systems
Automated control systems comprise the hardware and software used to monitor and control a
treatment process. There are two general types of systems: programmable logic controls (PLCs)
and/or remote telemetry units (RTUs). PLCs are stand-alone microprocessor-based control
systems that can be programmed to monitor and control process equipment. RTUs were
originally developed to communicate with systems from remote, outdoor locations. Newer RTU
models can provide full equipment control through remote operator interface (AWW A, 2001).
Because the WBS cost models (except for the nontreatment model) pertain to centralized
treatment facilities, the assumptions reflect the control of all system components using a PLC
system; RTUs are generally more appropriate for remote communications.
PLC hardware consists of a rack-mounted system with plug-in slots for the input and output
(I/O) modules, which provide connections for the instruments and equipment, and one or more
central processing unit (CPU) modules, which process the monitoring data inputs and control
command outputs. The PLC equipment requires a power supply unit to operate the PLC data and
command processing functions. In addition, an uninterruptible power supply (UPS) will protect
the PLC system from undesired features such as outages and surges that can adversely affect the
performance of the PLC unit. A system operator can monitor and operate with the PLC using
either a computer or an operator interface unit, which is a panel mounted on the PLC enclosure.
These units can be as simple as 2-line light-emitting diode text panels or as advanced as full
color touch panels. The WBS models have default assumptions that PLC systems for smaller
drinking water systems will be operated using an advanced, fully-functional operator interface
unit after the control system installer has programmed the PLC. Larger systems will include an
operator interface unit with more limited functionality and use at least one computer workstation
with PLC programming software and printers to accomplish more advanced control functions
from a central location. Large systems also include plant intelligence software to assist operation
of the extensive control system.
The PLC system design in the WBS models depends on the design of the treatment system,
which dictates the total number and type of I/O connections. The PLC system receives input
signals from and transmits output signals to ports on instruments and equipment controllers. The
I/O signals may be discrete or analog, depending on the type of equipment generating or
receiving the signals. Discrete signals indicate which of two conditions apply such as whether a
switch is on or off. Analog signals indicate a value along a predefined range such as temperature
or rate of flow. Exhibit A-2 identifies the assumptions used in the WBS models to determine the
total number of I/O connections required for the PLC system.
58
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit A-2. I/O Port Requirements for Instrumentation and Control
Instrument Type
Inputs to and Outputs from PLC System
Alarm (level switch/alarm, high/low alarm or low alarm)
1 input and 1 output—discrete
Chlorine analyzer
1 input—analog
Conductivity meter
1 input—analog
Dissolved oxygen analyzer
1 input—analog
Drive controller
3 inputs (1 for the auto switch position, 1 for the run status signal
and 1 for overload or fault signal) and 1 output—discrete
Flow meter
1 input—analog
Venturi and orifice plate meters also include inputs and outputs
for the associated pressure transducer (below)
Head loss sensor
1
nput—discrete
Motor/air-operated valve
1
nput and 1 output—analog
ORP sensor
1
nput—analog
Particle meter
1
nput—analog
pH meter
1
nput—analog
Pressure transducer
1
nput—analog
Sampling port
1
nput—discrete
Total dissolved solids monitor
1
nput—discrete
Temperature meter
1
nput—analog
Total organic carbon analyzer
1
nput—analog
Turbidity meter
1
nput—analog
The degree of automated control at a treatment facility can range from none to a fully automated
control system that can monitor and control the hydraulic regime at the plant, the chemicals
addition system, the power system and the communication system. To reflect potential ranges in
treatment costs, the WBS models can provide equipment and operator labor cost outputs for
three degrees of control:
• Fully automated control with safety overrides
• Semi-automated control where instruments provide data and information to the control
station, but operators manually activate valves and mechanical equipment (e.g., this
option removes outputs from the PLC system and removes automated drive controllers
from mechanical equipment)
• Fully manual control where operators collect data directly from the instruments and
manually activate valves and mechanical equipment.
Users can select among these three control schemes using the system automation input in each
WBS model (see Section 2.3). Exhibit A-3 shows the general design assumptions about control
equipment used for each control scheme in the WBS models. The paragraphs below provide
additional information regarding the equipment components and calculations.
59
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit A-3. General Design Assumptions for System Controls
Small
Medium
Large
Item of Control Equipment
System
(<1 MGD)
System
(1-10 MGD)
System
(>10 MGD)
WBS Assumption
PLC Rack/Power Supply
A,S
A,S
A,S
1 base and expansion bases
as needed for I/O (see text)
CPU
A,S
A,S
A,S
2 per system1
I/O Discrete Output Module
A
A
A
1 for every 32 outputs2
I/O Discrete Input Module
A,S
A,S
A,S
1 for every 32 inputs2
I/O Combination Analog Module
A,S
A,S
A,S
1 for every 12 inputs (for A
and S) and outputs (for A
only)3
Ethernet Module
A,S
A,S
A,S
2 per system1
Base Expansion Module
A,S
A,S
A,S
1 per expansion base
Base Expansion Controller Module
A,S
A,S
A,S
1 per expansion base
UPS
A,S
A,S
A,S
1 per system
Operator Interface Unit - limited
functionality
NA
A,S
A,S
2 per system1 (see text)
Operator Interface Unit - advanced,
fully functional
A,S
NA
NA
2 per system1 (see text)
Computer Workstations
NA
A,S
A,S
1 per operator
Laser Jet Printer
NA
A,S
A,S
1 per 4 workstations
Dot Matrix Printer
NA
A,S
A,S
1 per 4 workstations
PLC Programming Software
NA
A,S
A,S
1 per workstation
Operator Interface Software
A,S
NA
NA
1 per system
PLC Data Collection Software
NA
A,S
A,S
1 per workstation
Plant Intelligence Software
NA
A,S
A,S
1 per workstation
A = included in a fully automated system; S = included in a semi-automated system; NA = not applicable for this design size
Notes: Fully manual systems do not include system controls
1. Includes one to provide redundancy
2. Discrete input and output modules can have fewer I/O connections, but price differences are small. To keep the equipment
requirement calculation tractable, the WBS models use a 32-connection module, which will slightly overstate cost when fewer
connection points are needed on the last module.
3. A combination module accommodates 8 inputs and 4 outputs. This 2-to-1 ratio is generally consistent with the ratio of analog
inputs-to-outputs in the WBS models for a fully automated system.
The primary PLC system is a rack and power supply (i.e., a "base") with nine slots for control
modules.7 The CPU module requires one slot. An ethernet module necessary for PLC
programming requires a second slot, leaving seven for I/O modules. If additional I/O slots are
needed to accommodate instruments and equipment, then up to four additional expansion bases
can be added, giving the single CPU the capacity to run up to 8,192 I/O connections. Each
expansion base has nine module slots and is linked to the CPU module on the primary base.
The total number of PLC racks and power supplies include the primary rack and any expansion
racks. The calculation for the total number of racks must take into account the module slots that
will be occupied by all types of modules including the CPU module, the ethernet module and
expansion base controller modules. Each expansion rack requires a base expansion controller
module, which occupies one of the module slots on the expansion rack, leaving eight slots for
7 Bases with fewer slots are also available, but cost differences across base sizes are small. To keep the equipment
requirement calculation tractable, the WBS models use a 9-slot base, which will slightly overstate cost when fewer
slots are needed.
60
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
I/O modules. Each expansion rack also requires a base expansion module, which is attached to
the outside of the rack and, therefore, does not require a module slot. The following calculations
illustrate how the WBS models calculate total PLC racks:
IF (pic cpu + pic ethernet + pic discrete input + pic discrete output +
pic combination analog) < 9
THEN pic rack = 1, pic base expansion = 0, pic base expansion controller = 0
IF (pic cpu + pic ethernet + pic discrete input + pic discrete output +
pic combination analog) > 9 AND <17
THEN pic rack = 2, pic base expansion = 1, pic base expansion controller = 1
IF (pic cpu + pic ethernet + pic discrete input + pic discrete output +
pic combination analog) >17 AND < 25
THEN pic rack = 3, pic base expansion = 2, pic base expansion controller = 2
IF (pic cpu + pic ethernet + pic discrete input + pic discrete output +
pic combination analog) > 25 AND <33
THEN pic rack = 4, pic base expansion = 3, pic base expansion controller = 3
IF (pic cpu + pic ethernet + pic discrete input + pic discrete output +
pic combination analog) >36 AND <41
THEN pic rack = 5, pic base expansion = 4, pic base expansion controller = 4
A.5 References
American Water Works Association (A WW A). 2001. Instrumentation and Control, Manual of
Water Supply Practices—M2. Third Edition. Denver, Colorado: AWWA.
A.4
CPU
I/O
ORP
PLCs
RTUs
UPS
WBS
List of Abbreviations and Symbols in this Appendix
central processing unit
input and output
oxidation-reduction potential
programmable logic controls
remote telemetry units
uninterruptible power supply
work breakdown structure
61
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Appendix B. Building Construction Costs
B.1 Introduction
The work breakdown structure (WBS) cost database incorporates building costs from three
sources: RSMeans 2009 Square Foot Costs (RSMeans, 2008), Saylor 2009 Commercial Square
Foot Building Costs (Saylor, 2009) and the Craftsman 2009 National Building Cost Estimator
(NCBE) software model (described in Craftsman, 2008). Each of these sources enables a user to
create a cost estimate by combining costs for different elements of a building—for example, the
foundation, exterior walls or light fixtures.
For each source, the WBS cost database includes three sets of options to represent low, medium
and high building design and material qualities. Section B.2 provides descriptions of the relevant
options for each source within these categories, as well as the options selected for each of the
three building types used in the WBS models. The WBS models cost heating and cooling
systems as individual capital cost line items separate from the building construction costs.
Therefore, the building costs discussed here exclude heating and cooling systems.
For each of the three types of building, EPA used the three sources described here to develop
cost buildups for 24 building sizes ranging from 500 to 200,000 square feet and tabulated costs
for each of the models. The resulting costs from each model are included in the WBS cost
database. The database escalates these costs from 2008 dollars using the Engineering News-
Record Building Cost Index (ENR, 2013) and averages them following the same procedure as
for other components, as described in Chapter 2. The WBS models use these costs to estimate
costs per square foot for buildings larger than 500 square feet (ft2).
EPA also developed a fourth building type that applies only to structures smaller than 500 ft2—
essentially a shed with steel walls and a roof. This additional building type allows the WBS
models to use, for very small systems, building costs that reflect very inexpensive building
construction methods and materials. For this type of building, EPA used the Craftsman NCBE
model to estimate costs for a low-profile steel building. However, the WBS models do not use
this building type for chlorine storage buildings because chlorine gas use necessitates a non-
corrodible building material and special ventilation requirements. Thus, for chlorine storage
buildings smaller than 500 ft2, the WBS models use the same unit costs as for larger buildings.
B.2 Buildup Options and Building Quality Selections
EPA developed building cost estimates using comparable assumptions across data sources: the
Craftsman NBCE model, building costs from RSMeans 2009 Square Foot Costs and Saylor 2009
Commercial Square Foot Building Costs. Each source provides unit costs for different building
types and construction qualities.
The Craftsman NBCE model is a software model that generates building cost estimates based on
user input (i.e., building size and quality of building features and fixtures). Given the variation in
unit costs for components by size, it appears to function as a parametric model. The costs in the
NBCE model are based on data obtained from U.S. government building cost surveys.
62
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
The RSMeans and Saylor manuals contain unit costs, usually in dollars per square foot, for
various building components (e.g., exterior walls, floor structure or roof structure). The costs are
based on data obtained from the construction industry and independent research of construction
costs. By combining unit costs across components, one can build up a total building unit cost.
The approach is essentially a WBS cost approach where most components are priced on the basis
of building area, with little or no variation in the cost per unit area as building size increases. For
example, the RSMeans unit cost for a foundation slab varies with the thickness of the slab (EPA
chose thicker slabs for higher quality buildings), but not with the building size. Notable
exceptions are the cost of exterior walls and roof structures. Exterior wall cost in dollars per ft2
declines as building size increases because the ratio of exterior wall linear footage to square
footage declines. For roof structures, EPA chose roof spans based on the length of a side of the
building (assumed square). For building side lengths greater than 70 feet, EPA included support
columns to give a maximum roof span of 70 feet. Larger buildings, therefore, may have
somewhat more expensive superstructures on a per-square-foot basis, since they may have a
wider roof span or support columns.
EPA chose inputs to the NBCE model and chose components from the RSMeans and Saylor
manuals to reflect the different levels of building quality used in the WBS models (high,
medium, low and very small low quality).
Based on the NBCE industrial building quality classifications, EPA determined that the NBCE
Class 1&2 (best/good quality), Class 3 (average quality) and Class 4 (low quality) reflected WBS
high, medium and low quality buildings, respectively. EPA used the NBCE low-profile steel
building for very small low quality buildings.
The RSMeans and Saylor manuals do not contain building types that are closely comparable to
the very small low quality building. Therefore, there are no RSMeans or Saylor costs for this
type of structure. RSMeans and Saylor building cost estimates were "built" by selecting specific
building elements of differing quality for each type of building from the assemblies sections of
their respective manuals.
From each source, EPA obtained cost estimates for the following building areas in square feet:
500; 1,000; 2,000; 3,000; 4,000; 5,000; 7,500; 8,000; 10,000; 12,000; 15,000; 18,000; 20,000;
24,000; 25,000; 30,000; 36,000; 42,000; 48,000; 50,000; 54,000; 60,000; 100,000 and 200,000.
The resulting costs do not include costs for site improvements (e.g., land, landscaping, parking
and utilities), permits, furnishings and production equipment, homeland security responses or
contingency allowance.
The RSMeans and Saylor costs include installation costs as well as overhead and profit for the
contractors installing the building components, but do not include architectural fees or general
contractor markup for general conditions, overhead and profit (RSMeans, 2008; Saylor, 2009).
According to Craftsman (Ogershok, 2009), the NBCE model's costs do not include installing
contractor markup directly, but do include a markup of 30 percent for the general contractor,
which they assume to also cover the installing contractor's markup. Since the Craftsman costs
were generally lower than those from Means or Saylor and since the installing contractor's
markup in Means and Saylor is usually 30 percent or more, EPA assumed that the 30 percent
markup in the Craftsman costs was passed along directly to the installing contractor and further
63
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
markup would be required for the general contractor. Architectural fees and the general
contractor's markup are included in the WBS model indirect cost output, as described in
Appendix D.
Each source has a different set of options. They can be grouped into six categories:
• Substructure
• Superstructure
• Exterior closure
• Interior finish
• Mechanical services, excluding heating and cooling
• Electrical services.
B.2.1 Substructure
Building substructure was selected using application scenarios for each of the three quality
options. For low quality buildings, EPA assumed an average industrial use scenario. For medium
quality buildings, EPA assumed a heavy industrial use scenario. For higher quality buildings,
EPA assumed a heavy industrial with live loads use scenario. EPA assumed light foot traffic for
the very small (less than 500 ft2) buildings (other than those used to store chlorine gas).
Exhibit B-l shows the detailed choices that EPA made for each of the three sources.
Exhibit B-1. Substructure Selections for NBCE, RSMeans and Saylor
Building
Variable
Lower Quality Building
Medium Quality
Building
Higher Quality Building
Very Small Lower
Quality Building
Craftsman
NBCE
Foundation: reinforced
concrete pads under
pilasters.
Floor. 6" rock base, 4"
concrete with reinforcing
mesh.
Foundation: continuous
reinforced concrete.
Floor. 6" rock base, 5"
concrete with reinforcing
mesh or bars.
Foundation: continuous
reinforced concrete.
Floor. 6" rock base, 6"
concrete with reinforcing
mesh or bars.
Foundations as required
for normal soil conditions;
a 4" concrete floor with
reinforcing mesh and a 2"
sand fill.
RSMeans
Foundation: poured
concrete; strip and spread
footings.
Slab: 4" reinforced,
industrial concrete with
vapor barrier and granular
base. Site preparation for
slab and trench for
foundation wall and
footing. 4' foundation wall.
Foundation: poured
concrete; strip and spread
footings.
Slab: 5" reinforced, heavy
industrial concrete with
vapor barrier and granular
base. Site preparation for
slab and trench for
foundation wall and
footing. 4' foundation wall.
Foundation: poured
concrete; strip and spread
footings.
Slab: 6" reinforced, heavy
industrial concrete with
vapor barrier and granular
base. Site preparation for
slab and trench for
foundation wall and
footing. 4' foundation wall.
not applicable
Saylor
Foundation: concrete strip
and spread footings, 4'
foundation wall.
Slab on grade: reinforced
concrete, vapor barrier, 4"
thick, on 4' sand or gravel
base.
Foundation: concrete strip
and spread footings, 4'
foundation wall.
Slab on grade: reinforced
concrete, vapor barrier, 5"
thick, on 4' sand or gravel
base.
Foundation: concrete strip
and spread footings, 4'
foundation wall.
Slab on grade: reinforced
concrete, vapor barrier, 6"
thick, on 4' sand or gravel
base.
not applicable
' = feet;" = inches
64
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
B.2.2 Superstructure
EPA assumed the same quality of superstructure for each of the three quality options—metal
deck and open web steel joists, supported by columns and exterior walls. However, the
superstructure support column spans range up to 70 feet, depending upon building size. To
establish the column span, EPA computed the length of a building side, assuming the building to
be square. For buildings with side lengths larger than 70 feet, EPA included support columns in a
square grid to provide a roof span of 70 feet or less, assuming that the roof would also be
supported on the exterior walls. For instance, a 10,000 ft2 building (100 feet on a side) would
have one support column in the center, with a 50 foot roof span. A 30,000 ft2 building (173 feet
on a side) would have four support columns at 58 foot intervals. Since the sources included roof
spans in increments of 10 feet, EPA rounded up to a 60 foot roof span for this building. EPA
used a steel building quality superstructure for the very small (less than 500 ft2) buildings (other
than those used to store chlorine gas).
Exhibit B-2 displays the superstructure options that EPA selected for each source.
Exhibit B-2. Superstructure Selections for NBCE, RSMeans and Saylor
Building
Variable
Lower Quality Building
Medium Quality Building
Higher Quality Building
Very Small
Lower
Quality
Building
Craftsman
NBCE
Roof structure: glu-lams wood or
steel trusses on steel intermediate
columns, short span. Roof cover.
panel ized roof system, Vz" plywood
sheathing, 4-ply built-up roof. 10 ft2
of skylight per 2,500 ft2 of floor
area (1-2'x 4'skylight 40' to 50'
O.C.).
Roof structure: glu-lams
wood or steel trusses on
steel intermediate columns,
short span. Roof cover.
panelized roof system, Vz"
plywood sheathing, 4-ply
built-up roof. 24 ft2 of skylight
per 2,500 ft2 of floor area (1-
4'x 6' skylight 40' to 50' o.c.).
Roof structure: glu-lams
wood or steel trusses on
steel intermediate columns,
span exceeds 70'.
Roof cover, panelized roof
system, Vz" plywood
sheathing, 4-ply built-up
roof. 32 ft2 of skylight per
2,500 ft2 of floor area (1-4'x
8' skylight 40' to 50' o.c.).
Steel roof
purlins 4!4
to 5Yz feet
on centers,
26-gauge
galvanized
steel on
roof
RSMeans
Roof. 1.5" galvanized metal deck,
open web steel joists, joist girders,
on columns and walls; total load =
60-65 lbs/ft2. Column spacing
chosen to give a maximum span of
70', with the building assumed
square. Steel columns.
Roof cover. Built-up tar and gravel
roof covering with flashing,
perlite/EPS composite insulation.
Roof hatches with curb.
Same as lower quality
Same as lower quality
not
applicable
Saylor
Roof: metal deck, open web steel
joists, on columns and walls. Wide
flange steel columns, steel beams
and girders. Column spacing
chosen to give a maximum span of
70', with the building assumed
square.
Roof cover: built-up tar and gravel.
Same as lower quality
Same as lower quality
not
applicable
' = feet;" = inches; EPS = expanded polystyrene; o.c. = on center
65
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
B.2.3 Exterior Closure
EPA used different building exterior qualities to estimate unit costs that vary by exterior
material. EPA selected reinforced concrete block exteriors for the lower quality buildings,
reinforced tilt-up concrete panel exteriors for the medium quality buildings8 and brick-faced,
reinforced cavity/composition wall exteriors for the higher quality buildings. EPA used
corrugated metal exteriors for the very small lower quality structures (smaller than 500 ft2).
A cavity wall (e.g., masonry) is a wall in which the inner and outer wythes are separated by an
air space, but tied together with wires or metal stays. A composition wall is a wall combining
different materials to work as a single unit. A tilt-up wall is a method of concrete construction in
which wall sections are cast horizontally at a location adjacent to their eventual position and
tilted into place after removal of forms.
Exhibit B-3 shows the exterior closure options that EPA selected for each model.
Exhibit B-3. Exterior Closure Selections for NBCE, RSMeans and Saylor
Building
Variable
Lower Quality Building
Medium Quality
Building
Higher Quality Building
Very Small Lower
Quality Building
Craftsman
NBCE
8" reinforced concrete
block or brick, unpainted.
(Same for both lower and
medium quality.)
8" reinforced concrete
block or brick, unpainted.
(Same for both lower and
medium quality.)
8" reinforced concrete
block or brick with
pilasters 20' on centers,
painted sides and rear
exterior, front wall brick
veneer
Steel frames/bents set 20'
to 24' on centers, steel
wall girts 3/4' to 4/4' on
centers, post and beam
type end wall frames, 26-
gauge galvanized steel
on ends and sides
RSMeans
Concrete block,
reinforced, regular weight,
hollow, 4x8x16', 2,000 psi
Tilt-up concrete panels,
broom finish, 5/4" thick,
3,000 psi
Brick face composite wall-
double wythe: utility brick,
concrete block backup
masonry, 8" thick, perlite
core fill.
not applicable
Saylor
Concrete block, 4x8x16',
reinforced
Tilt-up concrete panel, 6"
thick, no pilasters.
Brick cavity wall,
reinforced, 10" thick.
not applicable
' = feet;" = inches; psi = pounds per square inch
B.2.4 Interior Finish
Choices of interior finish reflect the quality and duty of the interior construction materials such
as floor coverings, wall coverings and ceilings. EPA selected functional, minimally attractive
interior finishes for the lower quality buildings and more functional and attractive interiors for
medium and higher quality buildings. EPA also selected functional, unattractive interior finishes
for the very small (less than 500 ft2) buildings (other than those used to store chlorine gas).
Exhibit B-4 shows the interior finish options that EPA selected for each source.
8 Tilt-up concrete panel exteriors were selected in the RSMeans and Saylor cost estimation buildups. Tilt-up
concrete panels were not an exterior option in the Craftsman NBCE cost estimation model; therefore, reinforced
concrete block exterior was selected in the Craftsman NBCE cost estimation model for medium quality buildings.
66
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit B-4. Interior Finish Selections for NBCE, RSMeans and Saylor
Building
Variable
Lower Quality Building
Medium Quality
Building
Higher Quality Building
Very Small Lower
Quality Building
Craftsman
NBCE
Concrete floors. Rest
rooms: unfinished
wallboard partitions and 2
low cost fixtures.
Concrete floors. Rest
rooms: painted gypsum
wallboard partitions and 2
average fixtures.
Concrete floors. Rest
rooms: enameled gypsum
wallboard partitions, 3
good fixtures, vinyl
asbestos tile floors.
Minimal quality, minimal
duty, functional,
unattractive
RSMeans
One minimal quality 2-
fixture restroom per 5,000
ft2 building area.
Unpainted walls.
Concrete floors.
Fiberglass ceiling board
on exposed grid system
covering 10 percent of
building area.
One minimal quality 2-
fixture restroom per 5,000
ft2 building area. Painted
walls. Vinyl composition
tile floors covering 10
percent of building area.
Fiberglass ceiling board
on exposed grid system
covering 10 percent of
building area.
One high quality 3-fixture
restroom per 5,000 ft2
building area. Acrylic
glazed walls. Vinyl
composition tile floors
covering 10 percent of
building area. Fiberglass
ceiling board on exposed
grid system covering 10
percent of building area.
not applicable
Saylor
One restroom per 5,000
ft2 building area, with 2
economy fixtures, baked
enamel partitions.
Unpainted walls.
Concrete floors. Ceiling:
5/8" gypsum board on
metal frame, covering 10
percent of building area.
One restroom per 5,000
ft2 building area, with 2
standard fixtures, baked
enamel partitions. Painted
walls. Vinyl composition
floor covering 10 percent
of building area. Ceiling:
5/8" gypsum board on
metal frame, covering 10
percent of building area.
One restroom per 5,000
ft2 building area, with 3
standard fixtures, baked
enamel partitions. Painted
walls. Vinyl composition
floor covering 10 percent
of building area. Ceiling:
5/8" gypsum board on
metal frame, covering 10
percent of building area.
not applicable
' = feet;" = inches
B.2.5 Mechanical Services
Mechanical services include fire protection, plumbing, heating, ventilation and cooling. The
WBS models cost heating and cooling systems as individual capital cost line items separate from
the building construction costs, so the mechanical services included in the building costs are
limited to fire protection, plumbing and ventilation. EPA assumed no sprinkler systems for the
lower quality buildings and normal hazard wet sprinkler systems for medium and higher quality
buildings. EPA also assumed no sprinkler systems for the very small (less than 500 ft2) buildings
(other than those used to store chlorine gas).
Exhibit B-5 shows the mechanical services options that EPA selected for each source.
67
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit B-5. Mechanical Services Selections NBCE, RSMeans and Saylor
Building
Variable
Lower Quality Building
Medium Quality
Building
Higher Quality Building
Very Small Lower
Quality Building
Craftsman
NBCE
No sprinklers. 1 small
rotary vent per 2,500 ft2 of
floor area.
Sprinklers. 1 medium
rotary vent per 2,500 ft2 of
floor area. (Same for both
medium and higher
quality.)
Sprinklers. 1 medium
rotary vent per 2,500 ft2 of
floor area. (Same for both
medium and higher
quality.)
Minimal quality, minimal
duty, functional, no
sprinklers
RSMeans
Gas-fired water heater.
No sprinklers.
Gas-fired water heater.
Wet pipe sprinkler
system. (Same for both
medium and higher
quality.)
Gas-fired water heater.
Wet pipe sprinkler
system. (Same for both
medium and higher
quality.)
not applicable
Saylor
Gas-fired water heater (1
per 5,000 ft2), 50 gallon,
100 GPH. No sprinklers.
Gas-fired water heater (1
per 5,000 ft2), 50 gallon,
100 GPH. Exposed wet
sprinkler system, normal
hazard. (Same for both
medium and higher
quality.)
Gas-fired water heater (1
per 5,000 ft2), 50 gallon,
100 GPH. Exposed wet
sprinkler system, normal
hazard. (Same for both
medium and higher
quality.)
not applicable
' = feet;" = inches; GPH = gallons per hour
B.2.6 Electrical Services
EPA included the cost of light fixtures and convenience power, along with associated wiring and
conduits. EPA selected inexpensive lighting fixtures that provide minimal lighting and a minimal
number of wall switches and receptacles for the lower quality buildings and selected increasingly
expensive lighting fixtures that provide bright lighting and an increased number of wall switches
and receptacles for the medium and higher quality buildings. EPA also selected minimal lighting
fixtures for the very small (less than 500 ft2) buildings (other than those used to store chlorine
gas).
EPA did not include electrical feed, switchgear, motor control centers, etc. in building costs.
These costs are likely to vary significantly by technology for buildings of the same size and
quality; for example, a mid-sized reverse osmosis system and a small packaged conventional
filtration system might occupy roughly the same footprint in similar buildings, but the reverse
osmosis system will likely have much greater power requirements. It is therefore not appropriate
to base these costs on the building's area or quality. These costs are included in the indirect cost
buildup based on a percentage of process cost, as described in Appendix D.
Exhibit B-6 shows the electrical services options that EPA selected for each source.
68
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit B-6. Electrical Services Selections for NBCE, RSMeans and Saylor
Building
Variable
Lower Quality Building
Medium Quality
Building
Higher Quality Building
Very Small Lower
Quality Building
Craftsman
NBCE
Lighting: low cost
incandescent fixtures,
20'x30' spacing
Lighting: low cost single
tube fluorescent fixtures
20'x20' spacing
Lighting: 4" single tube
fluorescent fixtures
10'x12' spacing
Minimal quality, minimal
duty, basic wiring and
minimal lighting fixtures
RSMeans
Lighting: Incandescent
fixtures recess mounted,
type A: 1 W/ft2, 8 FC. 6
lighting fixtures, 1 wall
switch and 2.5
receptacles per 1,000 ft2.
1 W miscellaneous
power.
Lighting: Fluorescent
fixtures recess mounted
in ceiling: T-12, 40 W
lamps, 2 W/ft2, 40 FC. 10
lighting fixtures, 2.5 wall
switches and 5
receptacles per 1,000 ft2.
1.5 W miscellaneous
power.
Lighting: Fluorescent
fixtures recess mounted
in ceiling: T-12, 40 W
lamps, 4 W/ft2, 80 FC. 20
lighting fixtures, 5 wall
switches and 10
receptacles per 1,000 ft2.
3 W miscellaneous
power.
not applicable
Saylor
Lighting: Incandescent
fixtures, surface mounted,
100 W, commercial
grade, 10 per 1,000 ft2 for
1 W/ft2 total. 1
commercial grade single-
pole switch and 2.5
commercial-grade duplex
receptacles per 1,000 ft2.
In slab/PVC conduit and
wire for 60 A current,
length assumed equal to
building perimeter for a
square building.
Lighting: Fluorescent
fixtures, recessed, 2 13 W
bulbs each, 16 per 1,000
ft2 for 2 W/ft2 total. 2.5
commercial grade single-
pole switches and 5
commercial-grade duplex
receptacles per 1,000 ft2.
EMT conduit and wire for
60 A current, length
assumed equal to
building perimeter for a
square building.
Lighting: Fluorescent
fixtures, recessed, 2 13 W
bulbs each, 31 per 1,000
ft2 for 4 W/ft2 total. 5
commercial grade single-
pole switches and 10
commercial-grade duplex
receptacles per 1,000 ft2.
RGS conduit and wire for
60 A current, length
assumed equal to
building perimeter for a
square building.
not applicable
' = feet;" = inches; A = amp; EMT = electrical metallic tubing; FC = foot candles; PVC = polyvinyl chloride; RGS = rigid
galvanized steel; W = watt
B.3 List of Abbreviations and Symbols in this Appendix
EPA U.S. Environmental Protection Agency
ft2 square feet
NBCE National Building Cost Estimator
WBS work breakdown structure
B.4 References
Craftsman Book Company. 2008. 2009 National Building Cost Manual: 33rd Edition. October.
Engineering News-Record (ENR). 2013. Building and Construction Cost Indexes. Online at
http://enr.construction.com/economics/
Ogershok, Dave, Craftsman Book Company. 2009. Personal communication with Danielle Glitz,
SAIC. 6 March.
RSMeans. 2008. 2009 Square Foot Costs. 30th Annual Edition. Kingston, Massachusetts:
RSMeans Company.
69
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Saylor Publications, Inc. 2009. 2009 Commercial Square Foot Building Costs: 19th Annual
Edition.
70
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Appendix C. Residuals Management Costs
C.1 Introduction
The purpose of this appendix is to outline the approach used to estimate costs for managing the
residuals generated by different drinking water treatment technologies. The work breakdown
structure (WBS) model for each treatment technology includes its own residuals cost estimate.
Each model allows the user to choose from different residual management options that reflect the
methods most likely to be used for the drinking water treatment technology being modeled.
Based on the residuals management option selected, each model identifies the specific
component equipment and operating and maintenance (O&M) requirements and generates costs
using the WBS approach based on engineering design. Costs for residuals management
equipment appear as line items in the model output, as is the case for other WBS elements. The
residuals management design also affects indirect costs, land costs and building costs.
The residuals management options available in each model are specific to the technology being
modeled, driven by the types of residuals generated, their quantity, the frequency of generation
(e.g., intermittent versus continuous) and their characteristics. There are, however, similarities
among groups of technologies that generate similar residuals. Exhibit C-l, below, lists the
technology groups, the residuals generated and the frequency of generation.
The technology-specific chapters of this report identify the residuals management options
available in each model. Because many of the options are similar within (or even across)
technology groups, this appendix describes the methodology and assumptions used for each
option in a single location, rather than repeating the information in each technology chapter. The
residuals management options that may be included in a given model include the following:
• Holding tanks (with or without coagulant addition)
• Direct discharge to surface water
• Discharge to a publicly owned treatment works (POTW)
• Recycle to treatment plant headworks
• Evaporation ponds
• Septic system
• Off-site disposal (non-hazardous, hazardous, radioactive or hazardous and radioactive)
• Land application
• Liquid hazardous waste disposal
• Deep well injection
• Off-gas treatment.
Section C.2, below, describes general design methods and assumptions common across residuals
management options. With two exceptions, subsequent sections describe each of the above
options. Deep well injection is included as an option only in the reverse osmosis/nanofiltration
model and, therefore, is discussed in detail in the chapter relating to that model. Off-gas
treatment is relevant only to aeration technologies and, therefore, is discussed in detail in
chapters relating to aeration models (e.g., packed tower aeration, multi-stage bubble aeration).
71
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit C-1. Technologies and Residuals Generated
Residuals Generated
Type of
residual
Generation
Frequency
Technologies
Spent regenerant or brine1
Liquid
Intermittent or
continuous
Adsorptive Media, Anion Exchange, Cation
Exchange
Spent backwash
Liquid
Intermittent
Adsorptive Media, Anion Exchange, Biologically
Active Filtration, Biological Treatment, Cation
Exchange, Greensand Filtration, Granular
Activated Carbon
Spent media or resin
Solid
Intermittent
Adsorptive Media, Anion Exchange, Biologically
Active Filtration, Biological Treatment, Cation
Exchange, Greensand Filtration, Granular
Activated Carbon
Membrane concentrate
Liquid
Continuous
Reverse Osmosis/Nanofiltration
Spent backwash/tank drain and
crossflow
Liquid
Intermittent
Low-pressure Membranes
(Microfiltration/Ultrafiltration)
Cleaning waste
Liquid
Intermittent
Reverse Osmosis/Nanofiltration, Low-pressure
Membranes (M icrof i I trati on/U I traf i I tration)
Spent membrane modules/elements
Solid
Intermittent
Reverse Osmosis/Nanofiltration, Low-pressure
Membranes (M icrof i I trati on/U I traf i I tration)
Used cartridge filters
Solid
Intermittent
Reverse Osmosis/Nanofiltration
Off-gas
Gas
Continuous
Packed Tower Aeration, Multi-stage Bubble
Aeration, Diffuse Aeration, Tray Aeration
Spent lamps, ballasts and intensity
sensors
Solid
Intermittent
Ultraviolet Disinfection, Ultraviolet Advanced
Oxidation
The chlorine gas, hypochlorite, chlorine dioxide, chloramine, nontreatment, ozone, permanganate addition, phosphate feed,
caustic feed and acid feed models are not shown because no process residuals are generated.
Note:
1. Generated when the technology is used with media regeneration, rather than on a throw away basis.
C.2 General Assumptions
Some of the general assumptions used in developing the costs for management of residuals are
listed below:
• For intermittently generated liquid residuals (e.g., filter backwash), the models calculate
residuals quantities based on the volume of a single generation event (e.g., backwashing
one vessel) and assuming a staggered schedule between generation events (e.g., if vessels
must be backwashed every 48 hours and there are two vessels in operation, the facility
will backwash vessel one at 0 and 48 hours and backwash vessel two at 24 and 72 hours).
• For intermittently generated liquid residuals, flow rates depend on whether flow
equalization is used (e.g., through the use of holding tanks, as described in Section C.3).
• Without flow equalization, the maximum residuals flow rate for intermittently generated
liquid residuals is single generation event volume/event duration.
• With flow equalization, the models assume residuals are released continuously during the
time between generation events. Therefore, the maximum residuals flow rate for
intermittently generated liquid residuals is (single generation event volume/time between
events) x capacity factor. The variable, capacity factor, is present to account for less than
perfect staggering between generation events. The models assume capacity factor equals
72
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
2, but the user can change this assumption on the critical design assumptions sheet of
each model.
• The models size residuals piping, valves and other downstream equipment based on the
maximum flow rates calculated as described above for intermittently generated liquid
residuals and on the maximum continuous flow rate determined by the engineering
models for continuously generated liquid residuals.
• The models assume the length of interconnecting piping between treatment process
equipment and residuals management equipment is equal to 1 times the overall system
building layout length. Like the pipe length assumptions documented in Exhibit 2-10,
this assumption is designed to account for the cost of fittings.
• With a few exceptions (noted in the individual model chapters), the models assume an
additional 40 feet of piping is required for liquid residuals to reach their ultimate
destination (e.g., the discharge point, head of the treatment plant or evaporation pond).
Except when this piping is used to recycle the residual, the models assume this piping is
buried and, therefore, include the cost of excavation, bedding, thrust blocks, backfill and
compaction for the additional pipe length. The user can change the assumption about the
length of the additional residuals piping on critical design assumptions sheet of each
model.
• The models generally assume that total suspended solids (TSS) in the influent water are
completely removed during treatment and accumulate in the residuals generated. This
assumption provides a conservative (high) estimate of the TSS concentration in the
residuals. Assumptions about the concentration of TSS in the influent water vary on a
technology-by-technology basis, but the user can change the assumption on the critical
design assumptions sheet of each model.
C.3 Holding Tanks
The purpose of a holding tank is to equalize the rate of flow at which residuals are released or
discharged. A holding tank may be desirable for intermittently generated liquid residuals that
ultimately are recycled to the treatment plant headworks or discharged to a POTW. The
instantaneous flow of intermittently generated liquid residuals (e.g., filter backwash) during a
generation event can be quite high. The use of a holding tank allows the discharge of these
residuals over the time between generation events, so that the ultimate flow is lower, but more
continuous. When residuals such as filter backwash are recycled to the head of a treatment plant,
recommended engineering practice is that the recycle stream should be no more than 5 percent to
10 percent of total system flow (U.S. EPA, 2002; U.S. EPA, 1996). Flow equalization through
the use of a holding tank may be necessary to meet this generally recommended engineering
practice. It also may be reasonable to include a holding tank for other discharge options (e.g., to
prevent instantaneous flow from overwhelming the capacity of a POTW).
When holding tanks are used for intermittently generated liquid residuals, the models determine
the capacity required as follows: single generation event volume x capacity factor. This capacity
factor is the same variable discussed in Section C.2 and is intended to account for less than
perfect staggering between generation events.
Holding tanks can also be desirable for certain continuously generated liquid residuals (e.g.,
membrane reject) to accommodate variations in flow that occur as influent flow varies. In this
73
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
case, the models determine the capacity required based on a desired detention time. The user can
change this detention time on the critical design assumptions sheet of the appropriate models.
When holding tanks are included, residuals pumps are required to move residuals from the
holding tank to their ultimate destination. The models size these pumps based on maximum
residuals flow rate, as discussed in Section C.2. The models also include maintenance labor,
materials and energy for these pumps in the O&M calculations using the same approach
described for booster pumps in Appendix E.
When holding tanks are used, they can result in the generation of secondary residuals in the form
of solids that settle in the holding tank. The models also allow for the addition of coagulant to the
holding tank to increase the percentage of TSS removed. Users can model this option by
changing the appropriate triggering variable on the critical design assumptions sheet of each
model. When the coagulant addition option is chosen, users also can choose the coagulant used.
Options available (specified on the critical design assumptions sheet) are polymers, ferric
chloride or both ferric chloride and polymers.
By default, holding tanks can be constructed of plastic, fiberglass or steel or they can be open
concrete basins. When the coagulant addition option is chosen, however, the models
automatically assume the tanks will be open concrete basins, to allow for easier solids cleanout.
The models also size the tanks so that a minimum settling time is achieved. When coagulant
addition is chosen, the models also add other required equipment, specifically mixers and dry
feeders or metering pumps.
The following are the model assumptions relevant to solids generation and coagulant addition:
• Without coagulant addition, most models assume that 25 percent of the TSS present in
the residuals is removed in a holding tank9
• With coagulant addition, this assumption increases to 50 percent
• With coagulant addition, the holding tanks must provide a minimum settling time of 90
minutes
• Coagulant dose is 10 milligrams per liter
• Coagulant sludge production factor is 1 pounds of sludge per pound of polymers added
and 0.99 pounds of sludge per pound of ferric chloride added
• Holding tank solid density is 25 pounds per cubic foot
• Holding tank solids are removed when the solids accumulation reaches 10 percent of tank
capacity.
The user can change each of these assumptions on the critical design assumptions sheet of the
individual models.
9 Exceptions are models, such as anion exchange, that assume low influent solids or include pretreatment filtration
to remove influent solids. These models assume no settling in the holding tank without coagulant addition, because
of the low solids content present (or remaining) in the water being treated.
74
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
C.4 Direct Discharge to Surface Water
Some liquid residuals may be amenable to direct discharge to surface water. Such discharges
require a National Pollutant Discharge Elimination System permit, the costs of which are
included in the add-on costs line item for permits. The only items of capital equipment required
for direct discharges are piping and valves, although the models will include pumps if holding
tanks are used in conjunction with direct discharge (see Section C.3, above).
C.5 Discharge to POTW
Discharge to a POTW is another possible management option for liquid residuals. The discharge
should meet certain pretreatment requirements and must not overwhelm the capacity of the
POTW. The only items of capital equipment required for POTW discharges are piping and
valves, although the models will include pumps if holding tanks are used in conjunction with
POTW discharge (see Section C.3, above).
Discharge to a POTW, however, entails certain charges that are included in the O&M costs of
each model when this discharge option is included. POTW rate structures vary nationwide, but
the most common types of charges are the following:
• Flat fees (e.g., dollars per month).
• Volume-based fees (e.g., dollars per 1,000 gallons discharged).
• TSS-based fees (e.g., dollars per pound of TSS in the discharge if over a certain TSS
concentration). For this fee type, the models assume that the POTW TSS discharge limit
over which a fee is imposed to be 250 parts per million (which is the most common limit
for cities with a limit on TSS).
Individual POTW rate structures can reflect a combination of one or more of these fee types. To
model POTW charges in a way that is nationally representative, the models include all three fee
types and calculate them based on unit charges that represent the average for each fee type based
on data from AWWA (2013). The user can change these average unit charges in the data
extracted from the central WBS cost database. Alternatively, the user can model a specific type
of POTW rate structure by selecting the appropriate option on the critical design assumptions
sheet of each model. The user can indicate which fee types to include (e.g., flat fee only). The
model will then use "typical" unit charges for the selected fee type(s). These "typical" unit
charges, which can be changed in the data extracted from the WBS cost database, reflect the
average including only cities that use that specific fee type (i.e., the average not counting zeros).
C.6 Recycle to Treatment Plant Headworks
Certain liquid residuals can be recycled to the treatment plant headworks provided the system
complies with the backwash recycling rule and the practice does not negatively impact finished
water quality. The recommended engineering practice is that the recycle stream should be no
more than 5 to 10 percent of total system flow (U.S. EPA, 2002; U.S. EPA, 1996). The only
items of capital equipment required for recycling are piping and valves, although a holding tank
(and, therefore, pumps) also would be necessary in most cases to meet the recommendation.
75
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
C.7 Evaporation Ponds
When large quantities of liquid residuals are generated (e.g., spent brine from ion exchange), an
evaporation pond can be an appropriate management method, particularly for facilities in dry
climates. Holding tanks are never necessary with an evaporation pond, even for designs with
intermittent generation frequency, because the design of the pond would provide sufficient
capacity to handle instantaneous flow. A minimum of two cells is recommended to ensure
availability of storage space during cleaning, maintenance or emergency conditions (U.S. EPA,
1987).
When evaporation ponds are selected, the models include the following evaporation pond capital
expenses: excavation, backfill, lining and dike construction. Also, when evaporation ponds are
selected, the models always include the cost of a geotechnical investigation (see Appendix D).
These items are in addition to the pipes and valves required to deliver residuals to the pond. The
models make the following assumptions to design evaporation ponds:
• Arid climate with annual average precipitation of 70 centimeters per year (cm/yr)
• Average annual pan evaporation rate is 180 cm/yr
• Evaporation ratio (which takes into account conversion of pan to lake evaporation rate
and the effect of salinity) of 0.7
• 180 days of storage with no net evaporation
• Evaporation pond safety factor (which accounts for years with below average
evaporation) of 1.1
• Maximum evaporation pond cell area of 5 acres.
The user can change each of these assumptions on the critical design assumptions sheet in each
model that includes the evaporation pond option. If evaporation ponds are selected, the user
should also review the other climate-based assumptions included in the model (e.g., the heating
and cooling requirements on the O&M assumptions sheet) to determine that they are sufficiently
consistent with the assumption of an arid climate that is implicit in the selection of evaporation
ponds as a residuals management method.
The use of an evaporation pond results in the generation of a secondary residual stream in the
form of evaporation pond solids. The models calculate the accumulation of evaporation pond
solids by including all suspended and dissolved solids present in the residuals. The models
assume evaporation pond solids removal frequency of once per year. Users can change this latter
assumption on the critical design assumption sheet of the appropriate models.
C.8 Septic System
Based on comments from peer reviewers, discharge to an in-ground septic tank and drain field (a
septic system) might be an option for some liquid residuals with intermittent generation in small
systems using certain technologies (e.g., adsorptive media, anion exchange). Users selecting this
option should evaluate whether the characteristics of the residuals are appropriate for this type of
discharge. Holding tanks are never necessary with septic systems because the design of the septic
tank would provide sufficient capacity to handle instantaneous flow.
When a septic system is selected, the models include the following capital expenses:
76
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
• Septic tanks
• Excavation for septic tanks
• Di stributi on b oxe s
• Distribution pipe (perforated polyvinyl chloride)
• Drain field trench excavation
• Drain field gravel.
These items are in addition to the pipes and valves required to deliver residuals to the septic tank.
Also, when a septic system is selected, the models always include the cost of a geotechnical
investigation (see Appendix D). The models make the following assumptions to design septic
systems:
• Minimum septic tank discharge time of 2 days
• Minimum septic tank volume of 1,000 gallons
• Maximum septic tank volume of 100,000 gallons
• Septic tank volume safety factor of 150 percent
• Long-term acceptance rate (a value, based on soil type, used by states/localities to
determine the minimum drain field infiltration area) of 0.5 gallons per day per square foot
• Septic drain field trench width of 4 feet
• Septic drain field trench depth of 4 feet
• Septic drain field trench gravel depth below distribution pipe of 1 foot
• A minimum of two septic drain field trenches
• A maximum septic drain field trench length of 100 feet
• 8 feet between drain field trenches
• Septic drain field trench total gravel depth of 28 inches, based on 1 foot below and 1 foot
above the distribution pipe and a 4 inch pipe diameter
• Septic drain field buffer distance of 10 feet
• Septic tank overexcavation depth of 1 foot above and to each side of the tank
• A maximum of 7 distribution pipe connections per distribution box
• Septic system distribution pipe diameter of 4 inches.
These assumptions are based on values typically found in state and local regulations for septic
systems. The user can change each of these assumptions on the critical design assumptions sheet
of each model that includes the septic system option. The use of a septic system results in the
generation of a secondary residual stream in the form of septic tank solids. The models calculate
the accumulation and disposal cost for these solids using the same assumptions used for holding
tank solids (except that addition of coagulant is not included for septic systems).
C.9 Off-Site Disposal
For solid residuals, including secondary residuals like holding tank solids or evaporation pond
solids, most of the models offer two options: disposal in a hazardous or non-hazardous off-site
landfill. The models do not include disposal in an on-site landfill as an option. This option would
be economically viable only for facilities with an existing on-site landfill—a factor that is highly
site-specific. For these facilities, the cost of this option would be less than that for off-site
77
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
disposal, because it would involve much lower transportation costs. Therefore, the off-site
disposal options available in the models provide a conservative cost estimate for these facilities.
For certain solid residuals, many of the models also offer two additional options: off-site disposal
as a radioactive waste or off-site disposal as a hazardous and radioactive waste. The radioactive
waste disposal options assume that the residuals are classified as low-level radioactive wastes
(LLRW), instead of technologically-enhanced, naturally-occurring radioactive materials
(TENORM). In some cases, TENORM is accepted at traditional non-hazardous or hazardous
waste disposal facility. In such cases, disposal costs would be lower than those at specialized
radioactive waste disposal sites. Therefore, the LLRW disposal costs assumed in the models
provide a conservative cost estimate for cases where residuals might be classified instead as
TENORM.
The models calculate annual disposal costs for non-hazardous solid residuals as follows:
Annual disposal costs = Disposal costs + Transportation costs
where:
Disposal costs = quantity of solids per disposal event (in tons per event) x disposal
frequency (in events per year) x unit cost for non-hazardous waste disposal (in dollars
per ton)
Transportation costs = quantity of solids per disposal event (in tons per event) x disposal
frequency (in events per year) x distance to disposal site (in miles) x unit cost for non-
hazardous waste transportation (in dollars per ton per mile).
The disposal costs for hazardous, radioactive and hazardous radioactive solid residuals are
calculated in a similar fashion. For transportation costs, however, there is a minimum charge per
shipment applied. If transportation costs calculated based on dollars per ton per mile are less than
this minimum, the models calculate transportation costs based on this minimum.
The following are the model assumptions relevant to off-site landfill disposal:
• 10 miles to the nearest non-hazardous waste disposal site
• 200 miles to the nearest hazardous waste disposal site
• 700 miles to the nearest radioactive or hazardous radioactive waste disposal site
• Maximum waste shipment size of 18 tons.
The user can change each of these assumptions on the critical design assumptions sheet of each
model.
C.10 Land Application
When secondary solids (e.g., holding tank solids, evaporation pond solids) are non-hazardous,
most models provide the option of assuming land application instead of landfill disposal. Users
can select this option on the critical design assumptions sheet. When land application is chosen,
the models assume that transportation and disposal costs for the secondary solids are zero,
78
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
although they still include the operator labor costs associated with managing the secondary
solids.
C.11 Liquid Hazardous Waste Disposal
In some site-specific cases, the only viable option for certain liquid residuals (e.g., anion
exchange brine) might be off-site disposal as a hazardous waste. When this option is chosen, the
models automatically include a holding tank, which is required to store the residuals for
shipment. Any solids that settle in the holding tank also are assumed to require hazardous waste
disposal.
The models calculate costs for the liquid hazardous waste disposal option similarly to the off-site
hazardous waste landfill option (e.g., disposal cost + transportation cost, with a minimum charge
per shipment), except that unit costs are different. These unit costs are specific to off-site liquid
hazardous waste disposal, instead of off-site hazardous waste solids landfilling, and expressed in
dollars per gallon or dollars per gallon per mile. The models assume the maximum liquid
hazardous waste shipment size is 6,000 gallons.
C.12 List of Abbreviations and Symbols in this Appendix
cm/yr centimeters per year
LLRW low-level radioactive waste
O&M operating and maintenance
POTW publicly owned treatment works
TENORM technologically-enhanced, naturally-occurring radioactive materials
TSS total suspended solids
WBS work breakdown structure
C.13 References
American Water Works Association (AWW A). 2013. 2012 Water and Wastewater Rate Survey.
Denver, Colorado: AWWA. February.
U.S. Environmental Protection Agency (U.S. EPA). 1987. DewateringMunicipal Wastewater
Sludge. EPA Design Manual. EPA/625/1-87/014. September.
U.S. EPA. 1996. Technology Transfer Handbook: Management of Water Treatment Plant
Residuals. United States Environmental Protection Agency, Office of Research and
Development. EPA 625-R-95-008. April.
U.S. EPA. 2002. Filter Backwash Recycling Rule: Technical Guidance Manual. United States
Environmental Protection Agency, Office of Groundwater and Drinking Water. EPA 816-R-02-
014. December.
79
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Appendix D. Indirect Capital Costs
D.1 Introduction
Indirect capital costs are costs that are not directly related to the treatment technology used or the
amount or quality of the treated water produced, but are associated with the construction and
installation of a treatment technology and appurtenant water intake structures. These costs
represent some of the expenditures required in order to get a technology or the treated water
production process up and running. They include indirect material costs (such as yard piping and
wiring), indirect labor costs (such as process engineering) and indirect burden expenses (such as
administrative costs).
Indirect capital costs included in the work breakdown structure (WBS) models include the
following:
• Mobilization and demobilization
• Architectural fees for treatment building
• Equipment delivery, equipment installation and contractor overhead and profit
• Site work
• Yard piping
• Geotechnical
• Standby power
• Electrical infrastructure
• Instrumentation and control
• Process engineering
• Contingency
• Miscellaneous allowance
• Legal, fiscal and administrative
• Sales tax
• Financing during construction
• Construction management and general contractor overhead
• City index.
The following sections describe each of these indirect cost elements in more detail, address their
effect on capital costs and explain the reasoning behind including them as an additional indirect
capital cost allowance or contingency.
D.2 Mobilization and Demobilization
Mobilization and demobilization costs are costs incurred by the contractor to assemble crews and
equipment onsite and to dismantle semi-permanent and temporary construction facilities once the
job is completed. The types of equipment that may be needed include: backhoes, bulldozers,
front-end loaders, self-propelled scrapers, pavers, pavement rollers, sheeps-foot rollers, rubber
tire rollers, cranes, temporary generators, trucks (e.g., water and fuel trucks) and trailers. In some
construction contracts, mobilization costs also include performance bonds and insurance.
80
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
To estimate mobilization and demobilization costs in the absence of site-specific data, the WBS
models use a multiplication factor of 2 to 5 percent. The models apply this multiplication factor
to direct process costs, building costs and the physical portions of indirect capital costs (site
work, yard piping, geotechnical, standby power, electrical, instrumentation and control and
miscellaneous). Examples of mobilization and demobilization percentages include:
• Buckeye, Arizona Water System Infrastructure Improvements (multiple projects)
Mobilization/Demobilization/Bonds/Insurance = 5 percent (Scoutten, Inc., 2009)
• City of New Port Richey Maytum Water Treatment Plant Modifications,
Mobilization/Demobilization (limit included in bid instructions) = 4 percent (Tampa Bay
Water, 2006)
• Alton Water Works Mobilization = 1 percent (AWWC, 1999)
• Fairfax Water Authority New Intake, Mobilization = 4.6 percent, Demobilization =1.8
percent, Total = 6.4 percent (FWA, 2003)
• Fairfax Water Authority Trunk Sewer Project Mobilization = 5 percent (FWA, 2003)
• Forest Park Water Treatment Plant, Chalfont, PA = 0.26 percent (Allis, 2005).
The last example, for the Forest Park treatment plant, applied to a retrofit of an existing
conventional filtration facility with a membrane system. The project involved modifications to
existing buildings and treatment basins and the construction of one new building. Since the
project involved less new construction than a greenfield project, the mobilization cost may be
lower than it otherwise would be.
Mobilization/demobilization costs tend to be proportionately higher for smaller projects because
of fixed costs that are the same regardless of project size. For example, if construction requires
use of a large crane, then the mobilization/demobilization cost will be the same regardless of
whether it is onsite for a long time to complete a large construction project or a short time to
complete a small project. Therefore, small projects will most likely have
mobilization/demobilization percentages in the higher end of the range and larger projects will
tend to have values in the lower end of the range. The default values in the WBS models reflect
this type of variation. For small systems with a design flow less than 1 million gallons per day
(MGD), the default mobilization/demobilization factor is 5 percent. For medium systems (design
flows between 1 MGD and 10 MGD), the default factor is 4 percent and for large systems
(design flows above 10 MGD), the default factor is 2 percent. The models make an exception in
the case of small systems that use pre-engineered package treatment plants. Because these
package plants typically are skid-mounted, they require only a short time to install onsite and
should use a minimum of heavy equipment in the process. Therefore, the models assume a
mobilization/demobilization factor of 0 percent for small, pre-engineered package systems. The
user can change this assumption on the indirect assumptions sheet of each model.
Because the installation costs in the models include rental of equipment for installation (see
Section D.4.2), there may be some redundancy between the default mobilization and
demobilization costs and the installation costs (which are included in the model unit costs). The
extent of this redundancy is difficult to determine, but is a potential source of conservatism in
model cost estimates (i.e., the potential redundancy would tend to make model cost results
higher).
81
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
D-3 Architectural Fees for Treatment Building
The architectural fees for the treatment building include the costs of designing the structure and
preparing technical drawings. By convention, the architectural fee also includes the fees for
structural, electrical and mechanical engineering associated with the treatment building
(RSMeans, 2013). Furthermore, the architectural fees include the costs of preparing final
drawings and the tender document package. The building costs in the WBS cost database (see
Appendix B) do not include architectural fees, so the fees are added as an indirect cost. The
models apply the architectural percentage only to treatment building costs, not to other process
costs.
The WBS models use architectural fees from RSMeans (2013), based upon the direct cost of the
building, as shown in Exhibit D-l. The models make an exception in the case of small systems
with a design flow of less than 1 MGD. Because they are typically housed in small, prefabricated
buildings that require a minimum of design and engineering, the models assume no architectural
fee for these small systems. The user can change this assumption on the indirect assumptions
sheet of each model.
Exhibit D-1. Architectural Fees
Building Direct Cost Range
Architectural Feea
<$250,000
9.0%
$250,000 to $500,000
8.0%
$500,000 to $1,000,000
7.0%
$1,000,000 to $5,000,000
6.2%
$5,000,000 to $10,000,000
5.3%
$10,000,000 to $50,000,000
4.9%
>$50,000,000
4.5%
a. The architectural fee is a percentage of the direct cost for buildings. It includes a structural engineering fee, as well as
mechanical and electrical engineering fees that are associated with the building.
Source: RSMeans (2013), reference table R011110-10.
D.4 Equipment Delivery, Equipment Installation and Contractor
Overhead and Profit
The equipment unit cost estimates in the WBS database include the cost of equipment delivery,
equipment installation and contractor overhead and profit (O&P). Because these costs are
included in the direct or process costs, the default value of this multiplier in the WBS models is 0
percent. If the user has site-specific or technology-specific data that show delivery, installation or
O&P costs outside of typical ranges, the user can change this factor on the indirect assumptions
sheet of each model to better account for actual installation costs.
The sources of unit cost quotes include manufacturers, vendors, published construction cost data
reference books and peer-reviewed literature. Price quotes for an item vary across sources
because of inherent price variability or product quality differences that are not relevant to overall
performance. The U.S. Environmental Protection Agency (EPA) addressed this source of price
variability by including quotes from multiple vendors in the WBS cost database; the unit costs
82
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
used in the WBS models are simple averages across vendor quotes. Differences also arise
because vendors include different information in price quotes. For example, prices obtained from
RSMeans (2013) include all components needed for installed process costs (i.e., delivered
equipment, installation and O&P costs). Quotes from other sources may not include installation
costs, contractor O&P or transportation costs. Thus, before EPA calculated average costs, all
prices needed to be adjusted to the same installed cost basis. EPA converted costs to this basis by
adding transportation, installation and O&P costs where they were missing from the original unit
price estimates.
D.4.1 Equipment Delivery
Incorporating delivery costs in unit costs that will be used for a national cost analysis is
challenging because of variability in the methods used to assess transportation costs. For
example, transportation costs can be based on a cost per mile, a cost per unit of weight, a cost per
unit of volume, a cost per region or within a radius or a proportion of sales price. EPA developed
standardized transportation cost multipliers that vary by equipment type and size. The type of
multiplier selected for each equipment category is based on a likely method of transportation.
For tanks, vessels and towers, EPA applied a transportation cost based on equipment volume
units (e.g., gallons). For iron and steel tanks, the cost is based on a vendor quote of shipping
costs of $1,000 per 10,000 gallons of tank volume. For fiberglass tanks, the cost is based on a
vendor quote of shipping costs of $600 per 10,000 gallons of tank volume. EPA included
minimum and maximum transportation costs for tanks, vessels and towers. For steel equipment,
the minimum transportation cost is $500, which applies to all items with volumes below 5,000
gallons, and the maximum transportation cost is $5,000, which applies to all items with volumes
over 50,000 gallons. For plastic/fiberglass equipment, the minimum transportation cost is $500,
which applies to all items with volumes less than 10,000 gallons, and the maximum
transportation cost is $3,000, which applies to all items with volumes over 50,000 gallons. For
very small plastic/fiberglass equipment, EPA used an alternative minimum shipping charge of
$100, which applies to all items with volumes less than 100 gallons.
To estimate transportation costs for pipe, EPA calculated delivery costs per linear foot of pipe
using vendor delivery cost estimates and linear feet/truck load estimates. EPA averaged two
vendor delivery estimates for 30-inch and 48-inch American Water Works Association C200
steel pipe to obtain an estimate of $197.75 for a truckload of pipe. Information obtained from
vendors was used to estimate the number of linear feet of each size pipe that could fit in a
truckload.
For valves, pumps, blowers and mixers, EPA developed transportation cost estimates based on
equipment weight and costs for "less than a load" (LTL) shipments obtained from vendors. The
estimates assume an average delivery distance of 100 miles. For shipping cost estimation
purposes, average weights were assumed for the small, medium and large sizes of valves, pumps,
blowers and mixers. The assigned weights (which are based on the actual weights of valves,
pumps, blowers and mixers for which EPA received vendor quotes) are as follows:
• Small steel valves -30 pounds
• Medium steel valves ~ 80 pounds
• Large steel valves ~ 400 pounds
83
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
• Small pumps / blowers -100 pounds
• Medium pumps /blowers ~ 300 pounds
• Large pumps / blowers ~ 600 pounds
• Small mixers -50 pounds
• Medium mixers - 100 pounds
• Large mixers - 400 pounds.
Since the density of 304 stainless steel is approximately 5.6 times greater than the density of
polyvinyl chloride, the following weights were assigned to plastic valves:
• Small plastic valve - 5 pounds
• Medium plastic valves - 15 pounds
• Large plastic valves - 70 pounds.
EPA rounded shipping costs to the closest $10 increment. Exhibit D-2 provides the weight
categories and LTL costs for valves, pumps, blowers and mixers, along with a complete
summary of transportation cost methods for all categories of equipment.
EPA assumed a 5 percent markup on miscellaneous equipment and filter components for
membrane systems. For system control components, EPA assumed no transportation costs,
because the vendors contacted did not charge for shipping on large orders (i.e., greater than
$300). Transportation costs for chemicals, resins and filter media are averages of delivery costs
obtained from vendors. EPA used shipping rates for standard service from a vendor for
instrumentation transportation costs; the vendor uses fixed shipping rates that vary according to
the equipment price.
D.4.2 Installation, Overhead and Profit
EPA incorporated installation and O&P costs using multipliers derived from RSMeans (2013)
cost data. RSMeans provides complete installed cost estimates for the unit costs in its database.
The following cost components are reported for each unit cost:
• Bare material costs, including delivery
• Installation labor, materials and any rental cost for installation equipment
• Overhead for installing contractor (i.e., labor and business overhead costs)
• Profit for installing contractor (i.e., a 10 percent rate of profit charged on materials,
installation and overhead costs).
84
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit D-2. Transportation Cost Estimation Methods
Equipment Category
Transportation Costs
Vessels, Tanks, Towers - steel
$1,000 per 10,000 gallons of volume for each tank. There is a minimum shipping
charge of $500 and a maximum of $5,000.
Vessels, Tanks, Towers -
plastic/fiberglass
$600 per 10,000 gallons of volume for each tank. There is a minimum shipping charge
of $500 and a maximum of $3,000. Very small tanks (less than 100 gallons) have an
alternate minimum shipping charge of $100.
Pipes
Varies by pipe diameter and material of construction.
Plastic pipes: range is $0.07—$41.20 per 100 linear feet.
Iron and steel pipes: range is $6.46—$494 per 100 linear feet.
Valves-steel/iron
Weight Class 60
LTL rate = $101.45/100 lb
Small valves: $30.00 (1"—4" diameter)
Medium valves: $80.00 (5"—9" diameter)
Large valves: $400.00 (10"+ diameter)
Valves-plastic
Weight Class 70 - plastics
LTL rate = $115.41/100 lb
Small valves: $10.00 (1"—3" diameter)
Medium valves: $20.00 (4"—6" diameter)
Large valves: $80.00 (>6" diameter)
Pumps and blowers
Weight Class 85
LTL rate = $132.08/100 lb
Small units: $130.00 (0-50 gpm)
Medium units: $400.00 (51—300 gpm)
Large units: $790.00 (>300 gpm)
Mixers
Weight Class 85
LTL rate = $132.08/100 lb
Small mixers: $70.00 (includes mounted and portable mixers)
Medium mixers: $130.00 (includes inline and static mixers)
Large mixers: $400.00 (includes turbine, rapid, flocculant, impeller mixers)
Miscellaneous Equipment
5% of equipment cost
System Controls
None
Chemicals, Resins and Filter Media
$0.22/lb for hazardous materials
$0. 27/lb for filter media and resins
$0.18/lb for 150 lb chlorine cylinders
$0.24/lb for 1 ton chlorine cylinders
$0.06/lb for all other chemicals
RO/NF and MF/UF Skids and
Equipment
5% of equipment cost
Instrumentation
Varies with cost of equipment. Range is $9.95 to $104.35 per unit of equipment.
lb = pound; gpm = gallons per minute;" = inch; RO/NF = reverse osmosis/nanofiltration; MF/UF = microfiItration/uItrafiItration
These component cost data provide enough information to calculate adjustment factors that can
be applied to price quotes that exclude installation and O&P costs. By dividing total unit cost,
which includes all components, by bare material cost including delivery, EPA obtained
adjustment factors for several types of equipment in the WBS cost database. For example, if the
bare material cost, including delivery, for an item of equipment is $1.00 and the total unit cost is
$1.78, then the adjustment factor is 1.78. When unit costs obtained for the database did not
include installation, overhead and profit (as is typical when obtaining costs from manufacturers),
EPA applied these adjustment factors to escalate the unit costs so that they represented the full
installed cost. For example, if a manufacturer's price for a 20,000 gallon steel tank was $25,000,
EPA would first add delivery cost ($1,000 per 10,000 gallons capacity, as described in Section
D.4.1), resulting in a cost with delivery of $27,000. EPA would then multiply that cost by the
85
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
appropriate adjustment factor (for instance, 1.17) to obtain a complete unit cost—that is, the total
unit cost in this example would be ($25,000 + $2,000) x 1.17 = $31,500.
Most of the installation and O&P multipliers in the WBS cost database fall between 1.03 and
1.73, with an average around 1.36.
D.5 Site Work
Every construction site requires a certain amount of site preparation and finish work. Site work
costs include site preparation, excavation and backfilling, temporary and permanent road
construction, retaining wall construction, final grading, landscaping, parking lots, fencing, storm
water control structures, yard structures, site cleanup, waste disposal and utilities.
Estimating the site work cost based on a factor applied to the direct capital cost is an approach
commonly used when detailed information about the site plan is not known. Under this approach,
site work costs are typically estimated between 5 and 15 percent of the direct capital costs,
depending on project size and scope.
Site work costs vary directly with the land area requirement. The WBS models generate land
area estimates, which allows the models to use an alternative cost estimation approach based on
total project land area instead of total project costs. RSMeans (2013) provides an analysis of
actual reported project and component costs for different types of construction. Of the many
building categories reported in the summary database, the "factory" category best fits the scope
of construction associated with drinking water treatment plants. Therefore, the models use the
national average median project cost for site work at factories from RSMeans (2013). The WBS
cost database automatically updates this unit cost to current year dollars using the Engineering
News-Record (ENR) Building Cost Index (see Chapter 2). The models compute a site work cost
based on this unit cost and the total project land area, excluding land used for residuals holding
lagoons and evaporation ponds. Since the models include the cost of excavation and backfill for
these facilities, there is no need to include them in the site work calculations.
EPA believes that using an approach based on land area instead of direct process costs provides a
better estimate of site work costs because the unit costs from RSMeans (2013) are primarily
based on quantities of area and earthwork volume. Furthermore, this approach is less sensitive to
cost fluctuations caused by high cost equipment—the site work cost for a 0.5-acre project site
will be the same regardless of whether the treatment building houses chemical addition or a
membrane filtration process. This is particularly important because expensive, advanced
treatment technologies often have smaller footprints than lower-cost, conventional technologies
such as conventional filtration. Basing site work costs on process costs will tend to overstate site
work costs for such advanced technologies.
Although the default site work cost in the WBS models reflects a median value, the user can
enter a different rate in the data extracted from the WBS cost database based on site-specific
conditions. A higher cost factor should be entered for projects where the site conditions may
require higher-than-average site work costs (e.g., a site with steep terrain that may require
retaining walls). Conversely, a lower rate should be entered for projects where the site conditions
may require lower-than-average site work costs (e.g., a site where little grading is needed and
86
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
where requirements for infrastructure and other site improvement are minimal or where portions
are already in-place).
D.6 Yard Piping
Yard piping costs reflect the costs to install piping for untreated, partially treated and treated
water to and from the site, between new treatment plant buildings or between existing and new
treatment units. It does not include piping of treatment residuals to a residuals treatment system,
to disposal in a sewer or to a direct discharge connection; those costs are included as explicit
capital cost line items in the relevant WBS technology models, as discussed in Appendix C.
Yard piping costs include the following components:
• Trench excavation, backfill and pipe bedding
• Piping from the boundary of the building buffer zone to and from the building inlet and
building outlet and in between buildings that house water treatment components
• Optionally, piping from the water source to the property boundary and piping from the
property boundary to the distribution system connection
• Thrust blocks.
The sections below describe each of these components.
D.6.1 Trench Excavation, Backfill and Pipe Bedding
Costs of pipe contained in the WBS cost database are installed costs for aboveground pipes
within the treatment facility. Yard piping generally is installed below ground. Therefore, yard
piping entails additional costs. These costs include trench excavation costs, bedding costs,
backfill costs and thrust block costs (discussed in Section D.6.3).
Technology land area requirements are calculated on a basis of starting with a square building
with the required footprint and adding a non-fire buffer (10 feet) on three sides of each building
and a fire buffer (40 feet) on the fourth side. The general configuration assumption is that the fire
buffer will be located along the front side and the distance between buildings will be two times
the non-fire buffer distance (20 feet) and, therefore, yard piping will not cross the fire buffer
area. Thus, the minimum initial trench length is 20 feet (10 feet at inlet and 10 feet at outlet) for a
system with one building or 30 feet (20 feet inlet and outlet and 10 feet between buildings) for a
system with two buildings. Since the inlet and outlet piping may not always line up and may
extend inside the building perimeter, an offset distance is added to the 10 foot buffer distance
based on the building size. The offset distance is assumed to be Vi the length of one side of the
building footprint (based on square root of total building footprint).
The models assume yard piping will be buried with the top of the pipe set at or below the local
frost depth. Where frost depth is less than 30 inches, a minimum depth of 30 inches is assumed
to provide a protective cover. The default frost depth is 38 inches and corresponds to the frost
depth in St. Louis. Users can change the frost depth on the indirect assumptions sheet of each
model based, for example, on the climate data for a selected city in the climate database
(AFCCC, 2000). Trench depth also incorporates the pipe diameter and the bedding depth, which
the models assume to be 6 inches below the bottom of the pipe. This default value is sufficient to
87
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
approximate bedding requirements for large size pipes laid in soils where bedding is necessary.
The user has the option of changing the default value on the indirect assumptions sheet of each
model.
Trench width is equal to the pipe diameter plus 1 foot on either side. Trench volume is based on
the calculated trench length times the trench cross-sectional area, which incorporates trench
width and depth and assumes sloped trench sides, with an angle of 45 degrees (expressed in
radians on the indirect assumptions sheet). Excavation and backfill costs are based on total
trench volume plus thrust block volume and the unit cost for excavation and backfill. Although
backfill quantities are generally smaller than excavation quantities, they are assumed to be the
same in the WBS models. This approach is assumed to cover to the cost of backfill and the cost
of spreading or hauling excess soil off site. Pipe bedding volume accounts for the bedding depth,
incorporating additional volume to account for the sloped sides of the trench and the assumption
that the bedding covers 25 percent of the pipe diameter. The user can change this latter
assumption on the indirect assumptions sheet of each model.
D.6.2 Piping
The basic assumptions for yard piping from the boundary of building buffer zone to and from the
building inlet and building outlet and in between buildings are:
• Pipe length will be equal to trench length plus two times the trench depth.
• Pipe costs will be based on an equivalent pipe length, which will include an additional
length to account for cost of fittings (e.g., elbows). The equivalent length will be equal to
two times the pipe length, using the same factor used for process piping within the
buildings (see Section 2.4).
• Yard piping costs do not include valves.
• Piping materials, diameter and unit cost are the same as those selected in the treatment
model for inlet and outlet piping within the building.
In addition, the indirect assumptions sheet in each model contains an optional assumption for the
length of yard piping from the water source and another optional assumption for the desired
length of yard piping to the distribution system. Therefore, if the technology is not the initial step
in the treatment train, the default value length of pipe from the water source should be 0 feet,
because there is already a pipe from the water source to the existing facility. Similarly, if the
technology is not the last technology in the treatment train, then the default value should be 0
feet. As a default, these assumptions are set to zero.
D.6.3 Thrust Blocks
Yard piping costs include concrete thrust blocks to hold small pipe elbows and other fittings in
place. The basis of the thrust block volume calculation is thrust force in pounds. The models
derive thrust force using a lookup table based on pipe diameter. Users can modify the thrust
force assumptions by editing the engineering lookup table extracted from the WBS cost database.
The values in the lookup table assume a pipe test pressure of 150 pounds per square inch and a
pipe elbow angle of 90 degrees and account for block weight. Although both vertical and
horizontal elbows are expected in every pipe-laying job, the thrust block calculations assume
horizontal thrust blocks.
88
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Using the data from the thrust force lookup table, the models calculate bearing surface area based
on a conservative approach found in U.S. Army Corps of Engineers guidance (U.S. ACOE,
1992). The calculation is:
Area = 1.5*T/(Soil Density*Kp*Depth*R)
where:
1.5 is a safety factor, which is typical for thrust block design
T is the thrust force required, derived as discussed above
Soil Density is the minimum soil bulk density, which the models assume is 1.55 grams
per cubic centimeter (97 pounds per cubic foot) consistent with loamy sand, which is also
on the lower end of the range for sandy soils (1.5-1.8) and the upper end of the range for
silty clay (1.4-1.5) (MNNRSC, 2003)
Kp is the coefficient of passive pressure, which the models assume to be 3, based on an
internal angle of friction of the soil (phi) of 30 degrees
Depth is the depth to bottom of the block, which the models calculate based on trench
depth and pipe diameter
R is a reduction factor of 0.467, based on phi of 30 degrees and a vertical bearing surface
(CADOT, 2001, Figure 8).
Users can adjust soil density, Kp and R on the indirect assumption sheet of each model. Note that
this approach is conservative in that it considers only the bearing force of the vertical surface,
which is perpendicular to the thrust force, and ignores the frictional force exerted on the bottom
surface of the block. Use of deeper trench depths will result in lower thrust block costs.
D.7 Geotechnical Investigation
Construction cost estimates generally include a geotechnical allowance to provide for
investigation of subsurface conditions. Subsurface conditions can affect the foundation design
and construction technique. For example, a high groundwater table or soft substrate may require
special construction techniques such as piles and dewatering. Thus, the actual costs of addressing
subsurface conditions are site specific and can vary considerably. In addition, where a system is
adding treatment technology to a site with existing structures and, therefore, the site already has
an existing geotechnical investigation, additional geotechnical investigation may not be required.
To account for these variations, the models include assumptions that allow the user to select
whether geotechnical investigation costs should be included for low, medium and high cost
estimates. The default values for these assumptions include geotechnical costs only for high-cost
systems. However, the models always include geotechnical costs (regardless of the value
selected for these assumptions) when certain components are included in the technology design,
such as septic systems, evaporation ponds or below-grade structures like basins.
Geotechnical investigations can be as simple as digging trenches or test pits to determine the soil
conditions underlying small, lightweight structures. For larger, heavier structures, site
investigations generally involve drilling boreholes to extract samples of rock or soil for further
study. Cost estimates in the WBS models reflect either test pit costs or borehole costs, depending
on the building footprint size. For footprints of 2,000 ft2 or smaller, the WBS models have costs
89
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
based on hand digging test pits. All larger structures have costs based on the costs of drilling
boreholes. The following sections describe the method for estimating costs for each approach.
D.7.1 Borehole Cost Analysis
The cost analysis for drilling boreholes includes preparation activities (e.g., staking the field) and
actual drilling. Thus, a key cost driver is the number of boreholes needed. An additional factor is
the required drilling depth.
For a large industrial building, a borehole should be drilled at the expected location for each
column foundation and at locations where concentrated loads are expected to occur such as under
tanks and heavy equipment. The models assume four boreholes is reasonable for structures in the
range of 2,000 to 4,000 ft2. For larger structures, the models assume an additional borehole for
every 1,000 ft2 in additional space. Thus, the requirement for structures in the range of 4,001 to
5,000 ft2 is five boreholes. This approach is based on the assumption that column footings are
spaced approximately 32 feet apart.
Drilling depth depends on a structure's weight and existing knowledge of subsurface conditions.
Nevertheless, a rough criterion used to develop WBS cost estimates is that boreholes should
penetrate at least 1.5 times the width of the footings below the lowest portion of the footing
(Krynine and Judd, 1957). The lowest portion of the footing must be below the frost line, which
ranges from almost 0 feet to more than 5 feet in the continental United States. The WBS models
assume a frost line depth of 38 inches, an additional safety depth of 22 inches and a footing
width of 3 feet to obtain a minimum borehole depth of approximately 10 feet (5 feet + 1.5 x 3
feet).
EPA selected three different boring depths to represent a range of geologic conditions and
building bearing loads. A boring depth of 10 feet applies to relatively light structures in areas
where the soil conditions are predictable without any expectation of deeper strata that exhibit
poor shear strength. A boring depth of 25 feet applies to moderately heavy structures in areas
where subsurface conditions are less well defined, but no severe conditions are expected and
where underground structures, such as basins, as deep as 20 feet need to be constructed.
Similarly, a boring depth of 50 feet deep applies to heavy structures in areas where extreme or
unknown subsurface conditions (such as strata with poor shear strength) may exist.
EPA developed cost estimates based on cost data for drilling activities that use a truck-mounted,
2.5-inch auger with casing and sampling from RSMeans (2013). Exhibit D-3 identifies the cost
elements included in borehole drilling. The WBS cost database automatically updates the unit
costs for these elements to current year dollars using the ENR Construction Cost Index (see
Chapter 2). Costs are applied based on the selected borehole depth and total structure area
rounded up to the nearest thousand ft2.
90
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit D-3. Cost Elements Included in Borehole Drilling
Item
• Borings, initial field stake out and determination of elevations
• Borings, drawings showing boring details
• Borings, report and recommendations from professional engineer
• Borings, mobilization and demobilization, minimum
• Borings, drill rig and crew with truck mounted auger (output 55 feet/day)
• Borings, cased borings in earth, with samples, 2.5-inch diameter.
Source: RSMeans, 2013, 02 32 13.10-0200.
D.7.2 Test Pit Cost Analysis
For smaller, less expensive buildings, boreholes are less cost effective compared to test pits or
trenches that can be dug by hand or by using earth moving equipment if it is already available at
the site. Because geotechnical investigations may precede site work, excavating equipment may
be available to dig test pits. Therefore, for small buildings, the models use hand-dug test pits as
the basis for costs. The models assume one pit for buildings up to 1,000 ft2 and two pits for
buildings of 1,001 to 2,000 ft2.
Pit widths range from 4 feet by 4 feet to 6 feet by 8 feet (Krynine and Judd, 1957). Because this
test method is limited to small buildings, the models assume pits that are 4 feet by 4 feet wide.
Pit depth of 7 feet is based on a footing width of 2 feet and a frost depth of 5 feet (5 feet + 1.5x2
feet). The unit excavation and backfill costs are based on data from RSMeans (2013) for hand
dug pits in heavy soil. The cost of surveying and the soil sample evaluation report and
recommendation from a Professional Engineer are assumed to be the same as for borings.
D.8 Standby Power
A new treatment facility sometimes requires a standby power source that can produce enough
energy to operate the facility in the event of an electricity outage. Thus, the power rating or
capacity of the standby generator should be sufficient to power critical operating components at
the rated maximum flow capacity of the equipment (i.e., the design flow). Critical components in
a treatment plant include pumps, lighting and ventilation. In addition, standby power can be
required to provide space heating (if an electrical resistance heater or heat pump is used) and/or
cooling in the event of a power outage. As a default, the WBS models do not include heating or
cooling in their estimate of standby power requirements. The user can change the assumptions
about inclusion of heating and/or cooling in standby power on the indirect assumptions sheet of
each model.10
Also as a default, the models do not include standby power at all for small systems with a design
flow of less than 1 MGD. These small systems typically operate for only a few hours each day,
placing water in storage for use during the rest of the day. This operating procedure means small
systems can handle short term power outages simply by postponing their operating hours,
10 Note that if the assumption about including heating in standby power is changed, heating requirements will only
be included in standby power if an electrical resistance heater or heat pump is used, because the other heating
options (e.g., natural gas heat) do not use electricity.
91
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
without the need for standby power systems. The user can change the assumption about
including standby power for small systems on the indirect assumptions sheet of each model.
The generation capacity requirement for critical systems is based on the maximum daily load,
which is the potential energy demand to meet production at the design flow rate. Since the
energy requirements calculated in the models are based on continuous operation (24 hours/day
and 365 days/year), the maximum power requirement in kilowatts (KW) can be estimated using
the following equation:
Power requirement for critical operating components (KW) =
[annual power use by critical operating components (MWh/yr) / 365 (day/yr) / 24 (hr/day)] *
1,000 (KW/MW)
where:
hr = hours
MW = megawatt
MWh/yr = megawatt hours per year
yr = years
Standby power costs primarily comprise equipment purchase (e.g., a generator) and installation.
Additional costs include fuel purchase and storage. Annual fuel costs for standby power
generation are hard to estimate or predict, given the unpredictable nature of using the standby
power generator. Typical standby generators consist of diesel engine powered generators
(NREL, 2003). Installation costs include provisions for a foundation, fuel storage and louvered
housings for larger systems. For the diesel generators typically used for standby power, EPA
used installed unit costs from RSMeans (2009a). The WBS cost database automatically updates
these unit costs to current year dollars using the Producer Price Index from the Bureau of Labor
Statistics for motors, generators and motor generator sets (see Chapter 2). The models multiply
the appropriate unit cost, which users can change by modifying the data extracted from the WBS
cost database, by the calculated standby power requirement in KW, after applying a minimum
requirement of 1.5 KW (based on the smallest available standby power generator).
D-9 Electrical
The electrical cost allowance in a construction cost estimate will primarily account for electric
wiring inside structures, such as wiring for motors, duct banks, motor control centers, relays and
lighting. The unit costs for buildings in the WBS models (see Appendix B) already incorporate
general building electrical, such as building wiring and lighting fixtures and electrical
engineering associated with those components. In addition, certain electrical costs (motor/drive
controllers, variable frequency drives and switches) are included in direct costs for system
controls and pumps. Technologies with significant process equipment located outside include an
electrical enclosure as an explicit line item. Thus, the indirect cost electrical allowance only
accounts for additional electrical equipment associated with the treatment facility, including
outdoor lighting, yard wiring, switchgear, transformers and miscellaneous wiring. Yard wiring
consists primarily of the infrastructure that connects a new treatment facility to the power grid
and, if necessary, converts voltage.
92
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Typical electrical percentages include:
• Building electrical as a percentage of building cost = 7.7 to 13.0 percent, depending on
building size and quality (Association for the Advancement of Cost Engineering
International [AACEI] building cost model results)
• Seymour, Indiana electrical costs as a percentage of non-electrical process costs = 12.1
percent (AWWC, 2001a)
• St. Joseph, Missouri electrical costs as a percentage of non-electrical process costs = 8.7
percent (AWWC, 2001b).
Based on these data, the electrical percentage in the WBS models is 10 percent as a default.
Users can change this assumption on the indirect assumptions sheet of each model.
D-10 Instrumentation and Control
Instrumentation and control (I&C) costs include a facility control system and software to operate
the system. The WBS models include detailed process cost estimates for instrumentation and
control, as described in Appendix A. Therefore, the default value for I&C on the indirect
assumptions sheet is 0 percent. This line item remains among the indirect costs on the output
sheet of each model, however, to allow the user to incorporate any site-specific or technology-
specific data that cannot be accommodated by altering the I&C design assumptions in the WBS
models.
D.11 Process Engineering
Process engineering costs include treatment process engineering, unit operation construction
supervision, travel, system start-up engineering, operating and maintenance manual development
and production of record drawings. Process engineering as a percent of installed process capital
cost ranges from 5 to 20 percent. For example, Brayton Point Power Plant Water Works process
engineering costs were estimated at 8 percent of installed capital costs (Stone and Webster,
2001).
The ratio of process engineering to installed process capital cost varies based on system size and
the complexity of the treatment process. In particular, engineering cost as a percentage of process
cost tends to decrease as the size of the treatment plant increases. The default values in the WBS
models reflect this pattern: 8, 12 and 20 percent for large, medium and small systems,
respectively. The WBS models apply these percentages to installed process costs, but not
building costs, because structural, mechanical and electrical engineering fees are included in the
architectural fee (Section D.3).
The process engineering percentages at 13 EPA demonstration sites for low-flow packaged
systems ranged from 20 to 80 percent, with a mean of 36 percent (U.S. EPA, 2004). These
percentages, however, also include permitting and administrative costs. Because these costs are
separate line items in the WBS models, these percentages overstate stand-alone process
engineering costs. Furthermore, engineering costs can be higher for technologies in the
demonstration phase than for those in wide use. Therefore, EPA retained its assumption of 20
percent process engineering cost for small systems.
93
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
D.12 Contingency Cost
Contingency cost reflects the degree of risk that management assigns to a project. This cost
should reflect the statistical probability of additional project costs because of uncertainties and
unlikely or unforeseen events (AACEI, 1996). These unforeseeable additional costs to the project
occur because of changes in design, materials, construction methods and/or project schedule.
Contingency reflects a judgment by project management or bidders to account for unforeseeable
costs, thereby avoiding cost overruns. Contingency costs are included as part of a construction
contract allowing the contractor to be paid extra upon authorization of design and construction
changes by the project engineer (AACEI, 1996).
The risk of additional unforeseen costs associated with construction projects tends to vary with
project size and complexity. Therefore, EPA developed contingency factors using both project
size (i.e., total direct cost) and complexity (i.e., the technology being modeled) as input
variables. Ideally, a contingency cost estimate is based on statistical data or experience from
similar projects. By their nature, however, contingency costs are site specific and difficult to
predict; two estimators may recommend different contingency budgets for the same project
(Burger, 2003). EPA examined recommended contingency values, tabulated by project size,
from an economic analysis of water services (GeoEconomics Associates Inc., 2002). The
recommendations are presented in Exhibit D-4. These contingency rates, which range from 2 to
10 percent, are applied to the base costs (i.e., direct costs) to derive contingency cost. These rates
apply to projects of low to average complexity. Water treatment construction projects typically
fall into this category, depending on the technology being installed.
Exhibit D-4. Recommended Contingency Rates from an Economic Analysis of
Water Services
Project Base (Direct) Cost
Contingency as a Percent of Base Costs
Up to $100,000
10%
$100,000 to $500,000
8%
$500,000 to $1,500,000
6%
$1,500,000 to $3,000,000
4%
Over $3,000,000
2%
Source: GeoEconomics Associates Inc. (2002)
The WBS models would ideally include only the part of a contingency budget that is actually
spent, rather than the total amount budgeted. EPA therefore considered a Construction Industry
Institute (2001) study, which included both budget estimates and actual spending for contingency
in a series of heavy construction projects. Exhibit D-5 presents the relevant results. The factors
are expressed as a percentage of the total budget, rather than direct costs. These projects are not
limited to water treatment systems and include a variety of heavy construction projects. The data
in Exhibit D-5 show that, with the exception of very large projects (those with total project costs
of over $100 million), the contingency cost tends to decrease as project size increased. The
average contingency factor decreases from 6 to 4 percent before increasing to 7 percent for very
large projects. Such very large projects are generally beyond the size of projects that can be
modeled using the WBS models. Exhibit D-5 also shows that unforeseen problems during
94
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
construction tend to account for a higher share of contingency cost than design or procurement
problems.
Exhibit D-5. Average Contingency Costs in Budgets for Heavy Industrial Projects
Project
Size
Total
Cost
Budget
Contingency
Budget
Estimate
Contingency
(% of
budget)
Final
Project
Cost
Contingency Costs
Incurred by Project Phase
(Design / Procurement /
Construction)
Contingency
Incurred /
Budgeted
<$15
8.09
0.46
6%
$7.76
0.34 (0.04/0.10/0.20)
74%
$15—$50
30.22
1.55
5%
$29.51
1.15 (0.20/0.30/0.65)
74%
$50-$100
70.70
3.09
4%
$68.19
2.24 (0.25/0.83/ 1.16)
72%
>$100
214.02
15.56
7%
$206.50
13.63 (2.00/4.24/7.39)
87%
All costs are in millions of dollars. Incurred contingency costs exclude excludes three phases: Project Planning Phase,
Demolition and Start Up.
Source: Cll (2001)
The contingency factors in Exhibit D-5 are higher than the recommended values in Exhibit D-4.
Because Exhibit D-5 data is empirical and the basis for the estimates in Exhibit D-4 is not clear,
EPA based its contingency factors in the WBS models primarily on the values in Exhibit D-5,
but incorporated additional price categories below $15 million with contingency factors above 6
percent. To create the contingency factors, EPA first converted the figures in Exhibit D-5, which
are expressed as percentages of a total budget, to markups. For instance, if the contingency
budget is 7 percent of a total budget, it represents a markup of 7 / (100 - 7) percent = 7.5 percent.
EPA modified the markups by a factor of 0.77, which is the average ratio of incurred to budgeted
contingency costs in Exhibit D-5. Exhibit D-6 presents the resulting base contingency factors.
These represent the contingency or risk prior to consideration of technology complexity.
Exhibit D-6. WBS Model Contingency Factors Prior to Consideration of
Technology Complexity
Project Direct Cost Range
Base Contingency Factor
<$500,000
6.7%
$500,000 to $3,000,000
5.8%
$3,000,000 to $15,000,000
4.9%*
$15,000,000 to $50,000,000
4.1%*
$50,000,000 to $100,000,000
3.2%*
>$100,000,000
5.8%*
* Percentages based on Cll-Benchmarking & Metrics Analysis Results (Cll, 2001).
While there are techniques and computer programs designed to estimate contingency factors for
large projects based on construction activity risk simulation, the engineering costing literature
and the example projects EPA reviewed do not provide specific quantitative guidance regarding
the effect of project complexity on contingency costs. Nevertheless, the anecdotal evidence
suggests that risks (and, therefore, contingency costs) increase when project complexity
increases.
Among the WBS technologies, project complexity depends on the type of technology employed
and the general degree of experience with the technology as it will be applied. Well-established
95
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
technologies, which have a depth of construction and technology installation and operational
history under a variety of conditions, are expected to have low risk with respect to unforeseen
problems during construction and installation. Recently developed technologies or ones that have
had limited application to a variety of water quality conditions and project sizes (or to the
conditions at the project in question) are expected to have a higher degree of risk.
To account for differences in contingency values associated with technology type and project
complexity, EPA identified four categories of project complexity and assigned multipliers that
the models use to adjust the contingency factors (up or down) from Exhibit D-6:
• Low complexity = base contingency factor x 0.5
• Average complexity = base contingency factor x 1.0
• High complexity = base contingency factor x 1.5
• Very high complexity = base contingency factor x 2.0.
Thus, for each technology, the applied contingency factor combines the effects of project size
and technology complexity to obtain the project specific contingency factor. EPA assigned a
project complexity category to each WBS technology based on general knowledge and the
application history of the technology to drinking water treatment. Exhibit D-7 shows this default
complexity category assignment. The user can change these values on the indirect assumptions
sheet of each model if specific knowledge of the technology and its expected performance under
the site-specific conditions warrant such a change.
The WBS models assume that contingency costs are incurred only in high cost scenarios (see
Section 2.3). For low and medium cost estimates, the models assume construction is completed
with a minimum of unforeseen site-specific costs and, therefore, that none of the contingency
budget is incurred. Users can change this assumption on the indirect assumptions sheet of each
model.
96
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit D-7. WBS Default Complexity Factors by Technology
Technology
Risk Level Assigned to
Technology
Default Complexity
Factor
Acid Feed
Low
0.5
Cation Exchange
Low
0.5
Caustic Feed
Low
0.5
Chloramine
Low
0.5
Nontreatment Options
Low
0.5
Phosphate Feed
Low
0.5
Permanganate Addition
Low
0.5
Granular Activated Carbon
Average
1
Chlorine Gas
Average
1
Diffuse Aeration
Average
1
Packed Tower Aeration
Average
1
Adsorptive Media
High
1.5
Anion Exchange
High
1.5
Biological Treatment
High
1.5
Biologically Active Filtration
High
1.5
Chlorine Dioxide
High
1.5
Low-pressure Membranes (MicrofiItration/UItrafiItration)
High
1.5
Greensand Filtration
High
1.5
Hypochlorite
High
1.5
Multi-stage Bubble Aeration
High
1.5
Ozone
High
1.5
Reverse Osmosis/Nanofiltration
High
1.5
Tray Aeration
High
1.5
Ultraviolet Advanced Oxidation Processes
Very high
2
Ultraviolet Disinfection
Very high
2
D.13 Miscellaneous Allowance
In a cost estimate for a construction project, an allowance may be included for conditions or
events that the estimator can anticipate, but whose cost is not known with any degree of
certainty. If, for example, the site is expected to have contaminated soil that may require
remediation, the allowance will incorporate the resulting costs. An allowance differs from a
contingency cost, which provides contract coverage for unpredictable conditions. The allowance
funds account for anticipated additional costs that should become apparent at a later stage of the
project (for example, upon completion of the site investigation activities and the detailed
engineering design). Much of this cost is associated with knowledge of site-related conditions.
In a national average cost estimate such as the one that the WBS models generate, it is not
possible to allow for the specific conditions associated with any given site. However, the models
include an allowance line item to simulate an average effect due to such conditions. The line also
97
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
accounts for the level of detail in the WBS design, since the models do not include all minor
process components.
The WBS models assume a miscellaneous allowance of 10 percent as a default. Since the
allowance addresses a modeling uncertainty, there is little guidance available from the cost
estimation literature. Instead, the assumption must be validated by comparing WBS output to
actual water treatment facility construction costs. Users can change the miscellaneous allowance
on the indirect assumptions sheet of each model.
D.14 Legal, Fiscal and Administrative
This category includes project management, accounting and administrative activities related to
the project, excluding permitting. The cost can range from 2 to 5 percent of the process cost. In
the WBS models, this category is considered to account for administrative costs that the
purchaser incurs in the course of procurement. These costs are distinct from the construction
management fee, which is included as a separate indirect cost (Section D.17). The WBS models
use a default value of 2 percent. Users can change this assumption on the indirect assumptions
sheet of each model.
D.15 Sales Tax
Water treatment plant projects may be exempt from the sales tax, particularly those constructed
with public funds. The default value in the WBS models is 0 percent, which reflects the status of
taxes in social cost analysis. Taxes are considered a transfer payment and not an actual social
cost, which is based on the concept of opportunity cost. Transfer payments are not included in
social cost analysis, so a default value of 0 percent is appropriate for social cost analysis. The
WBS models include a sales tax line item among indirect costs because the models can also be
used for private cost analysis (e.g., for a specific utility), which includes transfer payments.
Users can enter a sales tax percentage on the indirect assumptions sheet of each model in cases
where consideration of transfer payments is appropriate.
D.16 Financing During Construction
Engineering cost estimates include interest for financing of the project. Drinking water systems
can obtain financing through various sources including Drinking Water State Revolving Funds
(DWSRF), public-sector financing, private-sector borrowing or equity instruments. Exhibit D-8
shows interest rates for drinking water treatment projects derived from the EPA 2006
Community Water Systems Survey. The default value in the WBS models is 5 percent, which is
toward the higher end of the range of financing costs for public and private systems, and
implicitly assumes 1 year of financing during construction. For small systems with design flow
less than 1 MGD, the models assume 0 percent financing during construction, implicitly
accounting for the very short construction time required for these systems. Users can change the
assumptions for both large and small systems on the indirect assumptions sheet of each model.
98
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit D-8. Average Interest Rates for Capital Funds
System Ownership Type
Lender
Average Interest Rate
(All System Sizes)
Range of Average Interest
Rates
Public
DWSRF
2.3
LO
CO
I
O
Public
Other Public Sector
3.5
"st
I
LO
O
Public
Private Sector
4.6
o
LO
I
CsJ
"st
Public
Other
3.9
O
O
I
Private
DWSRF
5.6
0.8-6.2
Private
Other Public Sector
4.4
LO
LO
I
CO
Private
Private Sector
6.5
4.3-7.7
Private
Other
5.9
O
o
I
o
o
All Systems
DWSRF
2.6
CO
"st
I
o
All Systems
Other Public Sector
3.8
1.9-4.5
All Systems
Private Sector
5.2
LO
LO
I
CO
"st
All Systems
Other
4.3
O
o
I
o
o
All Systems
All Lenders
Data not available
0.0-10.0
DWSRF = Drinking Water State Revolving Funds
D.17 Construction Management and General Contractor Overhead
As discussed in Section D.4.2, the component costs in the WBS cost database include the cost of
installation, including O&P for the installing contractor. However, the installation cost does not
cover the cost of insurance, performance bonds, job supervision or other costs associated with
the general contractor. The WBS models account for these costs by combining costs and fees for
the following items:
• Builder's risk insurance
• Performance bonds
• Construction management.
Builder's risk insurance is casualty insurance for the project during construction and may cover
various risks, such as vandalism, fire, theft or natural disasters. According to RSMeans (2009c),
a national average rate is 0.34 percent of the project cost. EPA adopted this assumption for the
WBS models. Users can adjust this rate on the indirect assumptions sheet of each model.
Performance bonds compensate the owner for losses due to contractor failure to complete work
according to specifications. RSMeans (2006) estimates the costs based on the total direct cost of
the project, as described in Exhibit D-9.
99
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit D-9. Cost of Performance Bonds
Project Direct Cost Range
Performance Bond Cost
<$100,000
2.5%
$100,000 to $500,000
$2,500 plus 1.5% of the amount over $100,000
$500,000 to $2,500,000
$8,500 plus 1.0% of the amount over $500,000
$2,500,000 to $5,000,000
$28,500 plus 0.75% of the amount over $2,500,000
$5,000,000 to $7,500,000
$47,250 plus 0.70% of the amount over $5,000,000
>$7,500,000
$64,750 plus 0.60% of the amount over $7,500,000
Source: RSMeans (2006), reference table R013113-80.
The construction management fee covers the cost of job supervision, an on-site office, main
office overhead and profit. Various sources provide individual estimates for these items, but the
WBS models roll them into a construction management fee to reflect a cost structure that the
owner might see. RSMeans (2009c) provides a table of typical construction management rates
for jobs of various sizes. EPA adapted those rates to develop those shown in Exhibit D-10.
Exhibit D-10. Construction Management Fees
Project Direct Cost Range
Construction Management Fee
<$100,000
10%
$100,000 to $250,000
9%
$250,000 to $1,000,000
6%
$1,000,000 to $5,000,000
5%
$5,000,000 to $10,000,000
4%
>$10,000,000
3.2%a
a. The reference quotes a fee range of 2.5% to 4% for a $50 million project. The WBS models assume an intermediate rate for
projects over $10 million.
Source: RSMeans (2009c), division 01 11 31.20.
The indirect line item for construction management and general contractor overhead sums all of
these costs. The costs can be omitted individually on the indirect assumptions sheet of each
model, either by an assumption that directly controls inclusion or exclusion or by setting the
appropriate percentage to zero. For example, in the case of small systems that use pre-engineered
package treatment plants, the models exclude the construction management fee portion by
default and include only the performance bond and builder's risk insurance. Because package
plants typically are skid-mounted and assembled offsite, they typically do not require a general
contractor to supervise their installation. Instead, their installation is managed by a single entity,
often the vendor that supplied the package.
D.18 City Index
This indirect cost accounts for city-specific and regional variability in materials and construction
costs. The city index factor included in the WBS models is expressed as a decimal number,
assuming a national average of 1.0. The default value in the WBS models is set to the national
average of 1.0, which is appropriate for estimating national compliance costs. Users wishing to
adjust estimated costs to be more reflective of potential costs in specific geographic locations can
100
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
change the city index value on the output sheet. For example, to estimate costs for a city where
construction costs are 90 percent of the national average, the user would change the city index to
0.9. One source for region- or location-specific adjustment factors is RSMeans (2013), which
publishes average construction cost indices for various three-digit zip code locations.
D.19 List of Abbreviations and Symbols in this Appendix
DWSRF
Drinking Water State Revolving Funds
EPA
U.S. Environmental Protection Agency
ENR
Engineering News-Record
ft2
square feet
I&C
instrumentation and control
KW
kilowatt
LTL
less than a load
MGD
million gallons per day
O&P
overhead and profit
WBS
work breakdown structure
D.20 References
Association for the Advancement of Cost Engineering International (AACEI). 1996.
Certification Study Guide. Morgantown, West Virginia.
Allis, William A. 2005. Personal communication with L. Petruzzi, SAIC. April.
Air Force Combat Climatology Center (AFCCC). 2000. Engineering Weather Data: 2000
International Edition. Published by the National Climatic Data Center.
American Water Works Corporation (AWWC). 1999. Preliminary Cost Estimate Summary:
Alton Water Treatment Plant, H&S no. 1862. 7 January.
AWWC. 2001a. Seymour, Indiana Process Cost Estimate.
AWWC. 2001b. St. Joseph, Missouri Cost Estimate.
Burger, Riaan. 2003. "Contingency, Quantifying the Uncertainty." Cost Engineering 45, no. 8. 8
August.
California Department of Transportation (CADOT). 2001. Earth Pressure Theory and
Application.
Construction Industry Institute (CII). 2001. Benchmarking & Metrics Analysis Results. Austin,
Texas. May.
Fairfax Water Authority (FWA). 2003. New Construction Works Brochures. Virginia.
GeoEconomics Associates Incorporated. 2002. An Economic Analysis of Water Services. Chapter
5.
101
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Krynine, D.P. and W.R. Judd. 1957. Principles of Engineering Geology and Geotechnics.
McGraw-Hill. New York.
Minnesota Natural Resources Conservation Services (MNNRSC). 2003. General Guide for
Estimating Moist Soil Density. 10 May.
National Renewable Energy Laboratory (NREL). 2003. Gas-Fired Distributed Energy Resource
Technology Characterizations. U.S. Department of Energy.
RSMeans. 2006. Facilities Construction Cost Data. 21st Annual Edition. Kingston,
Massachusetts: RSMeans Company.
RSMeans. 2009a. Assemblies Cost Data. 34th Annual Edition. Kingston, Massachusetts:
RSMeans Company.
RSMeans. 2009b. Building Construction Cost Data. 67th Annual Edition. Kingston,
Massachusetts: RSMeans Company.
RSMeans. 2009c. Facilities Construction Cost Data. 24th Annual Edition. Kingston,
Massachusetts: RSMeans Company.
RSMeans. 2013. Facilities Construction Cost Data 2014. 29th Annual Edition. Norwell,
Massachusetts: Reed Construction Data LLC.
Scoutten, Inc. 2009. Opinion of Probable Cost for Town Of Buckeye Water And Wastewater
Infrastructure and Water Resources Improvements Associated with 2009 Development Fees.
Revised 11 May. Online at http://www.buckeyeaz.gov/DocumentView.aspx?DID=640
Stone and Webster. 2001. Brayton Point Station Permit Renewal Application. Five Volumes.
Tampa Bay Water. 2006. West Pasco Infrastructure Project, Maytum WTP Modifications,
Project No. 05903. Memorandum from Kenneth R. Herd, Director of Operations and Facilities,
to Jerry L. Maxwell, General Manager. 1 December.
United States Army Corp of Engineers (U.S. ACOE). 1992. Revision of Thrust Block Criteria in
TM5-813-5/AFM88-10 VOL. 5 Appendix C. Publication Number: ETL 1110-3-446. 20 August.
U.S. Environmental Protection Agency (U.S. EPA). 2004. Capital Costs of Arsenic Removal
Technologies, U.S. EPA Arsenic Removal Demonstration Project, Round 1. EPA-600-R-04-201.
Cincinnati, OH: U.S. EPA, National Risk Management Research Laboratory.
102
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Appendix E. General Assumptions for Operating and
Maintenance Costs
E.1 Introduction
The work breakdown structure (WBS) models calculate operating and maintenance (O&M) costs
independently for each treatment technology. Nevertheless, there are several general assumptions
and estimation functions that are common to the O&M estimates across the treatment models.
This appendix describes those assumptions and functions. Any O&M cost element that is
technology-specific is included in the chapter describing that technology in the main document.
The O&M costs estimated in the WBS models primarily include annual expenses for:
• Labor to operate and maintain the new treatment equipment
• Chemicals required by the treatment
• Materials needed to carry out maintenance (including small tools)
• Energy.
Costs for commercial liability insurance, inspection fees, domestic waste disposal, property
insurance and other miscellaneous expenditures that are not directly related to the operation of
the technology are included in the WBS models by applying a miscellaneous allowance to the
total annual O&M costs. This calculation uses the same miscellaneous allowance percentage that
is applied to capital costs as an indirect line item (see Appendix D). Users can change this
percentage on the indirect assumptions sheet of each model.
The WBS models calculate O&M costs based on the inputs provided by the user on the input
sheet and values specified on the O&M assumptions sheet. These inputs include system size, raw
and finished water quality parameters and other factors that affect operation requirements such as
an option in the activated alumina model to regenerate media or operate on a throw away basis.
The design equations and assumptions incorporated in the O&M sheets are described below.
Despite provisions for user inputs, there are several factors that can affect site-specific O&M
costs in ways that are not readily reflected in the WBS outputs. These include:
• Operator expertise
• Equipment quality, design, installation and degree of automation
• Environmental conditions (e.g., changes in raw water quality over time).
Some O&M costs components, such as energy for pumping water or chemicals for treatment, are
well defined and readily estimated using an engineering cost approach. Other O&M cost drivers,
however, depend on multiple factors that are difficult to quantify and, therefore, represent a
challenge for estimating costs. For example, the required level of effort to operate or maintain a
technology depends on the level of complexity and sophistication of the installed technology, the
size of the treatment system, the professional level or education and training of the operator and
state and local regulations for process staffing.
103
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
To complicate matters further, there are trade-offs between system capital costs and O&M costs.
Higher cost equipment may require less intensive maintenance or less hands-on operation. For
example, using mixers and tanks to prepare brine solution for regenerating an anion exchanger
might reduce equipment costs compared to using salt saturators. However, salt saturators require
less labor to use and potentially reduce the need for a salt storage facility. Also high quality,
highly automated systems can significantly reduce labor requirements, but increase capital costs.
The U.S. Environmental Protection Agency (EPA) included some adjustments to O&M costs in
the WBS models to account for some types of savings, which are described below.
E.2 Labor Costs
The WBS models calculate the annual hours of O&M labor in the following categories:
• Operator labor for operation and maintenance of process equipment
• Operator labor for building maintenance
• Managerial and clerical labor.
The WBS model labor hour estimates are intended to be incremental. That is, they only include
labor associated with the new treatment system components.
E.2.1 Operator Labor for Operation and Maintenance of Process Equipment
System operation includes the following primary tasks:
• Collecting data from process instruments and recording system operating parameters
• Preventative maintenance and calibration of process instruments
• Verifying the proper operation of pumps, valves and other equipment and controlling the
treatment process by adjusting this equipment
• Preventative maintenance of pumps, valves and other equipment
• Inspection and maintenance of chemical supplies
• Visual inspection of the treatment facility and system components
• Other, technology-specific tasks (e.g., managing regeneration, backwash or media
replacement).
Labor required for these tasks is sensitive to the level of system automation. As discussed in
Section 2.3 and Appendix A, the user has the option to choose from three levels of automation:
manual, semi-automated and fully automated. The assumptions about labor required for each
task vary depending on the level of automation selected, as shown in Exhibit E-l and discussed
below. Users can change these assumptions, if desired, on the O&M assumptions sheet of each
model.
EPA compared model results using these assumptions with annual labor hours reported for 12
different water treatment facilities. Most of the resulting model estimates were within +50
percent to -30 percent of the annual labor hours reported for the sample facilities.
104
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Exhibit E-1. Operator Labor Assumptions for Three Levels of Automation
Task
Manual
Semi-automated
Automated
Record system operating parameters from process
instruments (includes routine sampling)
5 minutes per day
per instrument
5 minutes per day
5 minutes per day
Preventative maintenance and calibration of process
instruments
10 minutes per
month per
instrument
10 minutes per
month per
instrument
10 minutes per month
per instrument
Verify and adjust pump operating parameters
5 minutes per day
per pump
5 minutes per day
per pump
None
Preventative maintenance of pumps
30.25 hours per
year per pump
30.25 hours per
year per pump
30.25 hours per year
per pump
Verify and adjust valve positions
5 minutes per
week per valve
5 minutes per
week per valve
None
Preventative maintenance and inspection of valves
5 minutes per year
per valve
5 minutes per year
per valve
5 minutes per year per
valve
Visual inspection of facility
1 minute per day
per 100 square
feet of facility
1 minute per day
per 100 square
feet of facility
1 minute per day per
100 square feet of
facility
Inspect and maintain chemical supplies
120 minutes per
month per
chemical supply
tank
120 minutes per
month per
chemical supply
tank
120 minutes per month
per chemical supply
tank
Collecting Data from Process Instruments and Recording System Operating
Parameters
For manual systems, the models assume 5 minutes per day per instrument associated with day-
to-day operation of the treatment process (e.g., flow meter, head loss sensor). Instruments
associated with intermittent processes (e.g., backwash flow meters) are not included in this
estimate, because observation of these instruments is included the operator labor associated with
managing the intermittent process. In semi-automated and automated systems, the control system
handles the task of collecting information from the various process instruments, so operator labor
is reduced to 5 minutes per day to keep a record of operating parameters.
Preventative Maintenance and Calibration of Process Instruments
Regardless of the level of automation, the models assume 5 minutes per month for each
instrument, including those associated with intermittent processes. While some instruments (e.g.,
chlorine residual analyzers) may require calibration more frequently than monthly, others (e.g.,
head loss sensors) will require limited, less frequent maintenance. Therefore, the models use 10
minutes per month as an average across the various types of instruments.
Verify and Adjust Pump Operating Parameters
For manual and semi-automated systems, the models assume 5 minutes per day per pump,
including metering pumps associated with continuous chemical feed processes. Pumps
associated with intermittent processes (e.g., backwash pumps) are not included in this estimate,
105
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
because operation of these pumps is included the operator labor associated with managing the
intermittent process. In automated systems, the control system handles this task, so no additional
operator labor is required.
Preventative Maintenance of Pumps
Regardless of level of automation, the models assume 30.25 hours per year for large, frequently
operated pumps (e.g., booster pumps). This estimate does not include small chemical metering
pumps, but does include backwash pumps when these are operated more frequently than weekly.
The estimate of 30.25 hours per year is based on a list of recommended pump maintenance
activities from a vendor, combined with an independent engineering estimate of hours required
for each activity, as shown in Exhibit E-2.
Exhibit E-2. Pump Maintenance Activities
Task
Interval
Estimated
Minutes/Task
Estimated Hours/Year
Check bearing temperature
Monthly
5
1
Changing lubricant/ adjusting power level
Monthly
30
6
Disassemble for inspection, reassemble
Monthly
60
12
Check oil
Quarterly
10
0.67
Check lubricated bearings for saponification
Quarterly
10
0.67
Removal of bearings and replace, reassemble
Quarterly
60
4
Check packing and replace if necessary, reassemble
6 months
60
2
Vibration readings
6 months
10
0.33
Remove casing and inspect pump
Annual
120
2
If parts are worn, replace
Annual
varies
covered by pump materials
percentage and pump
useful life
Clean deposits and/ or scaling
Annual
60
1
Clean out stuffing box piping
Annual
30
0.5
Measure and record suction and discharge pipe head
Annual
5
0.08
Total All Tasks
Annual
1,815
30.25
Verify and Adjust Valve Positions
For manual and semi-automated systems, the models assume 5 minutes per week per valve on
the main process line. In automated systems, the control system handles this task, so no
additional operator labor is required.
Preventative Maintenance and Inspection of Valves
Regardless of level of automation, the models assume 5 minutes per year per valve on the main
process line.
106
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Visual Inspection of Facility
Regardless of level of automation, the models assume 1 minute per week per 100 square feet (ft2)
of treatment system floor plan to conduct visual inspection of the overall process. This daily
inspection is in addition to inspection conducted as part of routine operation and maintenance of
major operational components (instruments, pumps and valves), as discussed above.
Inspect and Maintain Chemical Supplies
The models assume that chemical supplies, whether they are associated with continuous addition
or intermittent use, require additional attention beyond that included in daily visual inspection. In
particular, they also require labor associated with receiving chemical shipments. Regardless of
level of automation, the models assume 120 minutes per month for each chemical storage tank.
Although counted on the basis of the number of tanks, this estimate is intended to cover all
components associated with the chemical supply system (e.g., checking pipes and valves for
leaks and inspecting and maintaining small metering pumps).
Technology-Specific Tasks
Many of the technologies include activities in addition to day-to-day operation that may require
operator attention, depending on the level of automation (e.g., intermittent regeneration,
backwash or media replacement). Where this is the case, the technology chapters in the main
document describe the specific assumptions required to calculate operator labor.
E.2.2 Labor for Building Maintenance
The WBS models include a building maintenance cost based on the building area (i.e., using a
unit cost in dollars per square foot per year). EPA developed this cost based on two sources:
Whitestone Research (2009) and RSMeans (2013). Specifically, EPA selected a list of
appropriate building maintenance repair and repair tasks from those listed in the two sources.
The selected tasks include those associated with preventative maintenance, small repairs and
major repairs. EPA estimated a frequency for each task by averaging the frequency
recommended in each of the two sources. Exhibit E-3 identifies the tasks included in the
maintenance and repair buildup. The models include maintenance and repair tasks for heating
and cooling systems only for buildings with the relevant systems. To avoid double-counting, the
task list does include tasks in the following categories:
• Maintenance of treatment system components that are already explicitly considered in the
models' maintenance labor and materials costs (e.g., pumps, valves, instruments)
• Full replacement of items that are explicitly given a useful life in the models (e.g., piping,
heating and cooling systems)
• Repair tasks with a lower frequency than the useful life assumed in the models for the
related WBS line item (e.g., skylight replacement has a recommended frequency of 40
years, whereas the models assume a useful life for the entire building of 37 to 40 years).
For the buildup, EPA assumed a baseline building area of 4,000 ft2 and building components
corresponding to a medium-quality building (see the assumptions in Appendix B). EPA
estimated costs for each task using data from RSMeans (2013) and assuming that preventative
maintenance and minor repairs would be conducted using in-house labor, while major repairs
would be conducted using outside contractors. These costs include both labor and materials.
107
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Because repair needs do not follow a strict schedule, EPA annualized costs with no discount
rate—that is, a $100 task with a typical frequency of 5 years is assigned an annual cost of $20.
Labor accounts for most of the cost for the maintenance and repair tasks. Further, the Building
Cost Index and Construction Cost Index, the only two cost indices in the WBS cost database that
combine labor and material costs, do not include the costs of materials that are likely to be used
in building maintenance. The WBS cost database therefore uses the Employment Cost Index to
escalate the building maintenance costs to current year dollars.
Exhibit E-3. Building Maintenance and Repair Tasks
• Minor repairs and refinishing for concrete floors
• Repairs and waterproofing for exterior concrete block walls
• Repairs and refinishing for doors
• Roofing debris removal and inspections
• Minor repairs and replacement for roofing membranes and flashing
• Repairs to skylights
• Repairs and refinishing for interior concrete block walls
• Repairs and refinishing for drywall
• Office painting
• Vinyl tile flooring replacement
• Repairs, refinishing and replacement for acoustic tile ceilings
• Preventive maintenance, repairs and replacement for lavatories and lavatory fixtures
• Water heater preventive maintenance, cleaning and servicing, overhauls and replacement
• Repairs to pipe joints and fittings
• Cleaning of drains
• Maintenance, repair and replacement of gutters
• Repai r and replacement of fans
• Inspection and replacement of sprinkler systems
• Maintenance, inspection, repair and replacement of electrical systems including switchgear, receptacles, wiring devices,
voice/data outlets and structure ground
• Replacement of lamps, ballasts and lighting fixtures
• Standby generator maintenance and inspection
• Preventive maintenance of computers
E.2.3 Managerial and Administrative Labor
The models contain an assumption that managerial and administrative support levels for a new
treatment plant are equal to 10 percent of the total operator hours for system operation and
maintenance. This estimate is not intended to represent total administrative and managerial time
at a drinking water system, because total time includes many tasks unrelated to operating a new
treatment train. It only represents incremental time needed to provide administrative support for
the new treatment plant, e.g., processing supply orders. It also does not include labor time
associated with recordkeeping and reporting burden estimates that EPA must estimate and report
independently to comply with Paperwork Reduction Act requirements. Users can change the 10
108
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
percent assumption for either or both of managerial and administrative labor on the O&M
assumptions sheet of each model.
E.2.4 Labor Unit Costs
To estimate the cost of the labor calculated in each of the categories above, the models multiply
labor hours by unit costs from the WBS cost database. These unit costs reflect average loaded
wage rates for applicable labor categories (i.e. technical, managerial and administrative) and vary
across system size. The WBS cost database uses the Employment Cost Index to escalate the rates
to current year dollars. Users can change the wage rates, if desired, in the data extracted from the
WBS cost database.
E.3 Chemicals
Each of the WBS models calculates annual chemical usage (in pounds or gallons per year) on a
technology-specific basis. The technology chapters in the main document describe these
calculations. In some models, these calculations also reflect the selected option for regeneration
or disposal of spent chemicals. Annual chemical costs equal the product of the annual chemical
requirements and the unit chemical costs in the WBS cost database.
E.4 Materials
The WBS models calculate the annual cost of materials in the following categories:
• Materials for maintenance of booster or influent pumps
• Materials for maintenance and operation of other, technology-specific equipment
• Replacement of technology-specific equipment that occurs on an annual basis
• Materials for building maintenance.
Pumps are operated continuously (or nearly continuously) and require preventive and routine
maintenance. Pumps are common to all the technologies. Each of the models assumes the annual
cost of materials for pumps is equal to 1 percent of their pre-installation capital cost to account
for consumable supplies and small parts requiring frequent replacement. This assumption is
based on input from the technology experts who reviewed the WBS models and commented that
the initial assumption of 5 percent was too high. Users can change this assumption on the O&M
assumptions sheet of each model. Although accidents or improper operation can result in a need
for major repairs that increase maintenance materials costs beyond 1 percent, the models do not
include these types of costs.
Some of the technologies include other equipment that may require significant maintenance (e.g.,
the blowers in the packed tower aeration and multi-stage bubble aeration technologies). The
models for these technologies include annual costs for maintenance materials. The technology
chapters in this document describe the specific calculations. In general, these calculations are
based a percentage of the pre-installation capital cost of the equipment.
Some of the technologies also include equipment components (e.g., membrane filter cartridges)
that require frequent replacement. Rather than treat these components as frequently replaced
capital items, the models handle the replacement costs in the O&M sheet. The replacement cost
calculations are based on assumptions about replacement frequency and unit costs from the WBS
109
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
component cost database. The specific calculations are in the technology sections of the main
document.
The WBS models compute a cost for building maintenance that combines labor and materials.
The cost is discussed in Section E.2.2.
E.5 Energy
All of the WBS models calculate the annual cost of energy in the following categories:
• Energy for operation of booster or influent pumps
• Energy for operation of other, technology-specific items of equipment
• Energy for lighting
• Energy for ventilation
• Energy for cooling
• Energy for heating.
E.5.1 Energy for Pumps and Other Equipment
Booster or influent pumps are equipment common to all the technologies. Because these pumps
are operated continuously (or nearly continuously), they can represent significant energy
consumption. Therefore, each of the WBS models calculates pump operating horsepower based
on average flow, pump head and pump efficiency. The models then convert this operating
horsepower to megawatt-hours/year assuming continuous operation. To calculate annual cost, the
models then multiply the annual power requirement by the unit cost for electricity contained in
the WBS component cost database.
Some of the technologies include other equipment that consumes significant quantities of energy
(e.g., blowers, backwash pumps, mixers). For those technologies, the model also calculates the
energy for such equipment explicitly. The technology chapters in the main document describe
the specific energy calculations. In general, those calculations are similar to the energy
calculation for pumps.
E.5.2 Energy for Lighting
The models calculate annual lighting requirements based on the building square footage estimate
and the quality level of the building (see Appendix B). The building capital costs in the WBS
cost database include the cost of light fixtures for the following light requirements:
• Sheds and low quality buildings, 1 watt/hour/ft2 of building area
• Mid quality buildings, 2 watts/hour/ft2 of building area
• High quality buildings, 4 watts/hour/ft2 of building area.
Multiplying the appropriate light requirement by 8.8 results in an energy usage rate in kilowatt
hours per ft2 per year. This conversion is based on operation of the lights 24 hours per day, 365
days per year. EPA evaluated these assumptions by calculating the granular activated carbon
contactor, pipe gallery and furnace area lighting requirements at the Richard Miller Water
Treatment Plant in Cincinnati, Ohio. For this facility, the lighting requirements are 1.5, 1.0 and
0.8 watts per hour per ft2 for the contactor, pipe gallery and regeneration areas, respectively, with
110
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
a weighted average of 1.0 watt per hour per ft2, which is at the low end of the range that EPA
uses in the models. Technologies with different types of process equipment that require more
frequent access may require more lighting. Users can change the lighting requirement for each
level of building quality on the O&M assumptions sheet of each model.
Because many systems are not lit during times an operator is not present, the models reduce
lighting energy requirements when a full-time operator presence is not required (possible for
small systems for many technologies) using the following factor (with a maximum of 1 to
account for large systems that might require more than one full-time operator):
Operator hours per year/ (24*365).
E.5.3 Energy for Ventilation
The models calculate ventilation requirements based on the assumptions shown in Exhibit E-4.
The technology experts who reviewed the assumptions for the WBS models confirmed the
reasonableness of these assumptions, although one expert commented that the air change rate for
pumps could be lower for systems in a northern climate. The WBS models continue to use the
value shown, however, because it is believed to be more reasonable for a national average
estimate and results in a more conservative (i.e., higher) estimate of ventilation energy
consumption. All of the models use these same assumptions with the exception of chlorination,
which has special ventilation requirements as described in that technology section. Users can
change the ventilation assumptions, if desired, on the O&M assumptions sheet of each WBS
technology model.
Exhibit E-4. Assumptions for Calculating Ventilation Requirements
Variable
Value used
Ventilation air change rate for contactor areas
3 air changes/hour
Ventilation air change rate for pump areas
20 air changes/hour
Ventilation air change rate for chemical storage areas
2 air changes/hour
Ventilation air change rate for offices
2 air changes/hour
Pressure drop across ventilation fans
0.25 pounds/ft2
Number of days with mechanical ventilation for small systems (less than 1 MGD)
90 days/year
Number of days with mechanical ventilation for medium systems (1 to 10 MGD)
120 days/year
Number of days with mechanical ventilation for large systems (greater than 10 MGD)
185 days/year
Building height
20 feet
MGD = million gallons per day
The models first use the air change rate assumptions to calculate an overall weighted average air
change rate for each building based on the equipment present in that building. The models then
use this weighted average air change rate for each building in the following formula:
Ventilation energy (MWh/yr) = DAYS x 24 x 0.746 x Pdrop x FP x H x Achanges / 33,000,000
where:
111
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
DAYS = days per year with mechanical ventilation
Pdrop = pressure drop across ventilation fans (pounds/ft2)
FP = building footprint (ft2)
H = building height (feet)
Achanges = weighted average air change rate for the building (air changes/hour)
E.5.4 Energy for Heating and Cooling
The models calculate heating and cooling requirements based on the assumptions shown in
Exhibit E-5. Users can change these assumptions, if desired, on the O&M assumptions sheet of
each WBS technology model. These assumptions are described in greater detail below.
R-values are a measure of the effective resistance to heat flow of an insulating barrier such as a
building envelope. The R-values assumed in the models (13 for walls, 38 for ceilings) are based
on the use of standard building materials. The user can change these values to reflect higher
efficiency construction materials. In doing so, however, the user should also examine the unit
building costs extracted from the WBS cost database (see Appendix B) to determine if they are
consistent with the use of such construction materials.
Exhibit E-5. Assumptions for Calculating Heating and Cooling Requirements
Variable
Value used
R-value for walls
13 hour- ft2 -°F /BTU
R-value for ceilings
38 hour - ft2 -°F /BTU
Annual heating degree days
4,923 degree days
Annual cooling degree days
1,697 degree days
Heating ventilation/infiltration load
168,679 BTU/cfm
Cooling ventilation/infiltration load
51,771 BTU/cfm
Electric resistance heating efficiency
98%
Heat pump heating coefficient of performance
3.2
Natural gas non-condensing furnace efficiency
80%
Natural gas condensing furnace efficiency
95%
Diesel non-condensing furnace efficiency
78%
Diesel condensing furnace efficiency
85%
Air conditioning energy efficiency ratio
11 Whr/BTU
Heat pump cooling energy efficiency ratio
10.1 Whr/BTU
Maximum capacity for heat pump heating
200 thousand BTU per hour
Maximum capacity for other heating options
6,148 thousand BTU per hour
Maximum capacity for heat pump cooling
50 tons
Maximum capacity for other cooling options
113.32 tons
BTU = British thermal unit; cfm = cubic feet per minute; Whr = watt hour
112
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
The next four values in the exhibit (annual heating and cooling degree days and heating and
cooling ventilation/infiltration loads) are climate-related. EPA derived these values from data in
the Air Force Combat Climatology Center Engineering Weather Data Version 1.0 (U.S. Air
Force, 2000). Specifically, EPA selected climate data for 21 cities distributed geographically
throughout the United States and calculated total annual heating and cooling losses. The values
used in the WBS models are those for the city (St. Louis) that represents the median total annual
heating and cooling loss from among the 21 cities. Therefore, the values used are intended to
represent a climate that produces a national median total heating and cooling requirement. The
user can change these values to represent a specific different climate. In doing so, however, the
user should select values for the heating and cooling measures, respectively, that are consistent
with one another (i.e., reflective of a realistic climate).
The remaining values in the exhibit are related to the efficiency and performance of heating and
air conditioning equipment. These values are based on data from the following sources:
• 10 CFR 430.32
• Canadian Office of Energy Efficiency (2009)
• ACEEE (2012).
The user can modify these values, as desired, to reflect the use of more or less efficient
equipment.
The WBS models use the assumptions in Exhibit E-5, along with estimated building
dimensions, to calculate total annual heating and cooling losses. The models consider both
conductance losses and ventilation/infiltration losses. The models calculate conductance losses
for each building using the following formulae:
Conductance heating loss = 4 x S x H x Hdd x 24 / Rwaii + FP x Hdd x 24 / Rceiiing
Conductance cooling loss = 4 x S x H x Cdd x 24 / Rwaii + FP x Cdd x 24 / Rceiiing
where:
S = length of building side in feet (assumed to equal the square root of the building
footprint)
H = building height (feet)
Hdd = annual heating degree-days
Cdd = annual cooling degree-days
FP = building footprint (ft2)
Rwaii = R-value for walls
Rceiiing = R-value for ceiling.
The equations above represent the total heat transfer in British thermal units (BTU)/year through
all four walls and the ceiling of each building. The models assume heat transfer through the
building floor is negligible.
To calculate ventilation and infiltration losses, the models first calculate the air exchange rate in
cubic feet per minute (cfm) for each building using the following formula:
113
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
Air exchange rate (cfm) = FP x H x Achanges / 60
where:
H = building height (feet)
FP = building footprint (ft2)
Achanges = weighted average air change rate for the building (air changes/hour, as
described above in the section on ventilation)
Note that, unlike the calculation for ventilation energy use, this calculation does not incorporate
assumptions about the frequency of mechanical ventilation. This is because heating and cooling
losses occur regardless of whether ventilation is achieved by mechanical or natural means.
The models then apply the air exchange rate calculated above to determine ventilation and
infiltration losses (in BTU/year) for each building using the following formulae:
Heating ventilation and infiltration heat loss = CFM x Hviioad
Cooling ventilation and infiltration heat loss = CFM x Cviioad
where:
CFM = air exchange rate (cfm, as calculated above)
Hviioad = heating ventilation/infiltration load (in BTU/cfm)
Cviioad = cooling ventilation/infiltration load (in BTU/cfm)
The models then sum conductance losses and ventilation/infiltration losses to determine total
annual heating and cooling requirements for each building. For cooling, the models add cooling
required to compensate for the waste heat generated by pumps (and other technology-specific
mechanical equipment).
The models then calculate heating and cooling energy consumption for each of several options
using these requirements, BTU values for the appropriate fuel (i.e., electricity, natural gas or oil)
and the efficiency factors shown in Exhibit E-5. For heating, the options are electric resistance
heating, electric heat pump, natural gas condensing or non-condensing furnace and diesel
condensing or non-condensing furnace. For cooling, the options are conventional air
conditioning and electric heat pump. As indicated by the final two assumptions in Exhibit E-5,
some of these options are not applicable for systems requiring large heating or cooling capacity
(i.e., large systems with large buildings). Specifically, electric resistance heating and heat pumps
are not useable for heating beyond a maximum capacity of 240,000 BTU/hour and heat pumps
are not useable for cooling beyond this same maximum capacity. When total annual heating or
cooling losses are greater than these maximum capacities, the models do not include these
options among those displayed on the output sheet.
The models determine whether to include heating and cooling costs (both capital and O&M)
based on building size, system design flow and user input for component level (see Section 2.3),
as shown in Exhibit E-6. Users can change these assumptions on the indirect assumptions sheet
of each model. When heating and/or cooling are included, the models choose among the heating
and cooling system options based on the total annualized cost of each option (annual energy cost,
plus capital cost of the system annualized as discussed in Section 2.4). The models select the
114
-------
WBS-Based Cost Model for Biological Drinking Water Treatment
option with the lowest annualized cost for inclusion in the system capital costs and add the
corresponding annual energy cost to O&M costs.
Exhibit E-6. WBS Model Assumptions Regarding Inclusion of Heating and Cooling
Building Square
Footage
Component Cost
Level Selected
System Design Flow:
Less than 1 MGD
System Design Flow:
1 to 10 MGD
System Design Flow:
10 MGD or greater
500 or greater
Low
Neither
Heating Only
Heating and Cooling
500 or greater
Medium
Heating Only
Heating and Cooling
Heating and Cooling
500 or greater
High
Heating and Cooling
Heating and Cooling
Heating and Cooling
Less than 500
Low or Medium
Neither
Neither
Heating Only
Less than 500
High
Heating Only
Heating Only
Heating Only
MGD = million gallons per day
E.5.5 Energy Unit Costs
To estimate the cost of the energy consumption calculated in each of the categories above, the
models use unit costs from the WBS component cost database. These unit costs represent
national averages for each fuel (electricity, natural gas and diesel) obtained from the U.S.
Department of Energy's Energy Information Administration. Because energy costs are highly
variable, users can change these energy unit costs, if desired, in the data extracted from the WBS
cost database.
E.6 List of Abbreviations and Symbols in this Appendix
BTU British thermal unit
cfm cubic feet per minute
EPA U.S. Environmental Protection Agency
ft2 square feet
O&M operating and maintenance
WBS work breakdown structure
E.7 References
American Council for an Energy Efficient Economy (ACEEE). 2012. Heating. Last updated
December. Online at http://www.aceee.org/consumerguide/heating.htm.
Canadian Office of Energy Efficiency. 2009. Heating with Gas - Comparing Annual Heating
Costs.
RSMeans. 2013. Facilities Maintenance and Repair Cost Data 2014. 21st Annual Edition.
Norwell, Massachusetts: Reed Construction Data.
U.S. Air Force. 2000. Air Force Combat Climatology Center Engineering Weather Data.
Version 1.0.
Whitestone Research. 2009. The Whitestone Facility Maintenance and Repair Cost Reference
2009-2010. Fourteenth Annual Edition. October.
115
------- |