*>EPA

United States
Environmental Protection
Agency

For more information

For questions, comments or more
information on the Amphenol
investigation, contact these EPA
team members:

For general information
Ruth Muhtsun

Community Involvement
Coordinator
312-886-6595
Muhtsun.ruth@epa.gov

Rafael P. Gonzalez

Community Involvement
Coordinator
312-886-0269
gonzalez.rafaelp@epa.gov

For technical information
Carolyn Bury
Project Manager
Remediation Branch
EPA Region 5

77 W. Jackson Blvd. (LU-16J)
Chicago, IL 60604-3590
312-886-3020
bury.carolyn@epa.gov.

EPA toll-free at 800-621-8431,
weekdays, 9:30 a.m. to 5:30 p.m.

You may see site-related
documents at EPA's Regional
office, 7th Floor Records Center,
Metcalfe Federal Building, 77 W.
Jackson Blvd., Chicago.

or visit

https://www.epa.gov/in/ampheno
Ifranklin-power-products-
frankli n -i nd#docum ent s

Neighborhood Environmental
Cleanup South of Amphenol

Former Amphenol Facility
Franklin, Indiana

November 2019

Amphenol completed replacing damaged sewers and digging up soil
in the neighborhood south of the Amphenol site on Nov. 9. The sewer
replacement work was completed in cooperation with the city of
Franklin.

•	1,300 linear feet of sewer and six manholes were replaced.

•	6,400 tons of soil were dug out and sent to a landfill.

•	21 homeowners had damaged clay pipe connections to the
sewer lines fully or partially replaced.

The streets will be repaved with bottom and middle asphalt layers by
Nov 27. If the temperatures remain warm enough for asphalt work,
the surface or top coat of asphalt may be placed this year. Otherwise,
the final street restoration will be done in the spring of 2020.

Sewer lining

An additional 1,300 feet of sewers will be lined starting this
December. This work is expected to be completed within two weeks
after it starts. The lining work is not weather-dependent but can't be
done at the same time as the street repaving.

EPA thanks you for your cooperation during the construction period
and apologizes for any inconvenience.

] CCD ~

«

%

~
~

F
Q

Q

A \ V



~ §
Sb dD

a

jn
a

0 ' D Ca

¦ _ . O

~	~ 0?

~	Pa

~	~ a
n=>cD o

O

D°

c»*

& a

~





I ~ ~ O

~
~

C=)



Completed
sewer

replacement

Completed
sewer lining

Sewers will
be lined


-------
Trench where 245 feet of the old sewer line cmd
340 tons of contaminated soil were dug out on the
former Amphenol. site north of Hamilton Avenue
in in October 2019.

On-site cleanup

Until 1983 when the former Bendix plant closed,
contaminated process water was poured into a floor
drain connected to the city's sanitary sewer system.
When the contaminated water flowed through the
sewer line along Hamilton Ave and North Forsythe
St, it leaked out and contaminated the surrounding
soil and groundwater. In 1989, a new sewer was
installed and the old sewer was disconnected from
the city sewer system and left in place. In October,
Amphenol dug out the old sewer and surrounding
soil which was sent to a landfill.

Nearly 7,000 tons of impacted soil were dug up
and sent to a landfill in the blue containers
shown here.

Corrective action process

Corrective action, a component of the federal
Resource Conservation and Recovery Act
(RCRA requires facilities that treat, store, or
dispose of hazardous wastes to investigate and
clean up hazardous releases into soil,
groundwater, surface water and air. In 1984,
Congress passed the Hazardous and Solid Waste
Amendments, which granted EPA expanded
authority to require corrective action at
permitted and non-permitted treatment, storage
and disposal facilities.

The RCRA corrective action cleanup process
focuses on results rather than specific steps, and
is flexible, depending on site-specific
conditions. A typical cleanup may include steps
such as: initial site assessment, site
characterization, interim actions, evaluation of
remedial alternatives, and implementation of the
selected cleanup plan.

See this webpage to learn more about the RCRA
corrective action program

https://www.epa.gov/hw/learn-about-corrective-
action.

2


-------