SEFA

April 3, 1998

Superfund Fact Sheet

Standard Steel and Metals Salvage Yard

Anchorage, Alaska

Cleanup of contaminated soil at the Standard Steel and Metals Salvage Yard Superfund site
is scheduled to begin in mid April. When the cleanup is complete, the Ship Creek channel will
be reestablished, contaminated soil will be treated and contained, and future development by
the property owners will be possible.

Alaska

Region 10	Idaho

1200 Sixth Avenue	Oregon

Seattle WA 98101	Washington

The New Erosion Control Wall

The existing erosion control wall, adjacent
to Ship Creek, will be removed and
replaced with a much stronger wall. The
new erosion wall will not be along the bank
of Ship Creek, but recessed and mostly
buried from view. This design will allow
Ship Creek to reestablish it's preferred
channel adjacent to the site and allow for a
more natural stream corridor. The flood
plain will be revegetated with native plants.

Containment of Contaminated Soil

Soil contaminated primarily with lead and
polychlorinated biphenyls (PCBs) will be
excavated. Higher-level contaminated soil,
above 50 parts per million (ppm) of PCBs
and 1000 ppm of lead, will be mixed with a
solidifying agent like cement and placed in
the on-site containment cell. Soil with PCB
concentrations between 1 and 50 ppm will
also be placed in the containment cell, but
without solidification. The entire
containment cell will be capped with a
liner, which prevents water from entering
the containment cell, and three feet of clean
soil.

Would You Like a Meeting

EPA will have a meeting to discuss the
design for the cleanup and to answer
questions about what will be taking place
during cleanup activities at the site if there
is enough interest. If you would like EPA to
schedule a meeting about the cleanup,
please call Chris Cora or Jean Baker at the
numbers listed below before April 15, 1998.

For More Information

Copies of the RI/FS, ROD, Consent
Decrees, and other documents pertaining to
the Standard Steel and Metals Salvage Yard
site are available for your review at the
following locations:

Alaska Resources Library
U.S. Bureau of Land Management
222 W. 7th #36
Anchorage, AK 99513

EPA Regional Headquarters
1200 Sixth Avenue
Seventh Floor Records Center
Seattle, WA 98101
(206) 553-4494

If you have questions please contact:

Following the cleanup, surface soil on the
site will likely have no PCB contamination
greater than 1 ppm. This will allow for
unrestricted access to the property. There
will be monitoring of the containment cell
for as long as it remains on the site and
groundwater for a minimum of five years.

Chris Cora, Project Manager
(206) 553-1148

Jean Baker
Community Relations Coordinator
(206) 553-2587

or call toll free at 1-800-424-4372.


-------
People with impaired hearing or speech may contact EPA's telecommunications device for the hearing impaired
(TDD) at (206) 553-1698. To ensure effective communication with everyone, additional services can be made
available to persons with disabilities by contacting one of the numbers listed above.

Background

The site, used as a scrap metal yard since the 1950s, is located at 2400 Railroad
Avenue just north of downtown Anchorage. Past activities at the site included salvaging
copper wire from electrical transformers containing polychlorinated biphenyls (PCBs)
and processing and stockpiling lead-acid batteries, drums of liquid, and various types
of equipment.

In 1986, EPA removed all PCB contaminated liquids, 82 barrels of hazardous waste,
780,000 pounds of batteries, and 185 electrical transformers. Contaminated soils were
stockpiled, a security fence and erosion-control wall were built, and an incinerator used
for salvage operations was dismantled and stored.

In August 1990, EPA placed the site on its National Priorities List (NPL) of hazardous
waste sites requiring cleanup. In September 1992, Chugach Electric Association, Inc.,
agreed to conduct the Remedial Investigation and Feasibility Study (RI/FS), two related
studies that determine the type and extent of contamination and identify cleanup
alternatives. In March 1996, various cleanup options were made available for public
comment and the selected cleanup plan was announced in the Record of Decision (ROD)
in July 1996.

During the summer and fall of 1996, the erosion control wall along ship creek was
repaired; old drums and other containers which might leak were removed; the fence was
repaired; and studies were undertaken to select the appropriate solidification material.
A plastic cover was placed over areas with high PCB concentrations to prevent erosion
by the wind and to prevent seepage into the soil due to rain and melting snow.

Under the terms of a Partial Consent Decree approved in December 1996, EPA
recovered past cleanup costs; the Potentially Responsible Parties (PRPs) agreed to share
cost of the RI/FS; and the federal PRPs and the Alaska Railroad Corporation agreed to
pay 64% of all future cleanup costs at the site. A Consent Decree, approved in January
1998, includes an agreement with the PRPs to perform the cleanup of more than six
acres of contaminated soil, and the owner of the property, Alaska Railroad Corporation,
agreed to implement the specific institutional controls contained in the Record of
Decision.


-------