SRI/USEPA-GHG-VR-03
September 1999

Environmental
Technology Verification
Report

France Compressor Products
Emissions Packing

Phase I Report

Prepared by:

Southern Research Institute

Under a Cooperative Agreement with

oEm U.S. Environmental Protection Agency

ElVElVElV


-------
EPA REVIEW NOTICE

This report has been peer and administratively reviewed by the U.S. Environmental Protection Agency, and
approved for publication. Mention of trade names or commercial products does not constitute endorsement or
recommendation for use.


-------
SRI/U SEPA-GHG-VR-03
September 1999

ElV

Greenhouse Gas Technology Verification Center

A U.S. EPA Sponsored Environmental Technology Verification Organization

France Compressor Products
Emissions Packing

Phase I

Technology Verification Report

Prepared By:

Southern Research Institute
Greenhouse Gas Technology Verification Center
PO Box 13825
Research Triangle Park, NC 27709 USA

Under Cooperative Agreement CR 826311-01-0

U.S. Environmental Protection Agency
Office of Research and Development
National Risk Management Research Laboratory
Air Pollution Prevention and Control Division
Research Triangle Park, NC 27711 USA

EPA Project Officer: David A. Kirchgessner

i


-------
TABLE OF CONTENTS

Page

ABSTRACT	iv

ACKNOWLEDGMENTS	vi

1.0 INTRODUCTION	1-1

1.1	BACKGROUND	1-1

1.2	THE EMISSIONS PACKING TECHNOLOGY	1-2

1.3	VERIFICATION GOALS	1-6

2.0 TECHNICAL BACKGROUND AND VERIFICATION APPROACH	2-1

2.1	METHANE EMISSIONS FROM NATURAL GAS COMPRESSORS	2-1

2.2	DESCRIPTION OF THE TEST SITE AND EMISSIONS PACKING
INSTALLATION	2-2

2.3	VHRII CATION APPROACH	2-3

2.3.1	Establishing Baseline Conditions	2-3

2.3.1.1	Case 1	2-4

2.3.1.2	Case 2	2-5

2.3.1.3	Impact on Normal Running Emissions	2-7

2.3.2	Emission Measurements and Calculations	2-7

2.3.2.1	Rod Leak Rate Measurements	2-8

2.3.2.2	Component Leak Rate Measurements	2-10

2.3.2.3	Natural Gas Composition Measurements	2-11

2.3.2.4	Blowdown Volume Determination	2-11

2.3.3	Site Operational Data	2-11

3.0 RESULTS	3-1

3.1	ROD PACKING EMISSIONS	3-1

3.1.1	Emissions During Idle/Shutdown	3-1

3.1.2	Emissions During Compressor Operation	3-2

3.2	OTHER EMISSION SOURCES	3-5

3.2.1	Valve Leaks and Blowdown Volume	3-5

3.2.2	Miscellaneous Fugitive Sources	3-6

3.3	NET GAS SAVINGS	3-7

3.3.1	Compressor Operational Characteristics	3-7

3.3.2	Case 1 and Case 2 Gas Savings	3-7

3.4	INSTALLATION REQUIREMENTS	3-11

4.0 DATA QUALITY	4-1

4.1	BACKGROUND	4-1

4.2	ROD PACKING EMISSION RATE MEASUREMENTS	4-1

4.3	OTHER MEASUREMENTS	4-4

4.3.1	Unit Valve, Blowdown Valve, and Pressure Relief Valve	4-4

4.3.2	Gas Composition	4-6

4.3.3	Blowdown Volume	4-6

4.4	OVERALL UNCERTIANTY IN THE MEASUREMENTS, NET GAS
SAVINGS, AND METHANE EMISSIONS VALUES	4-6

5.0 REFERENCES	5-1

li


-------
LIST OF FIGURES

Figure 1-1	Schematic of a Gas Compressor Engine and Rod Packing	1-3

Figure 1-2	France Emissions Packing - Ring Detail	1-4

Figure 1-3	France Emissions Packing	1-5

Figure 2-1	Simplified Floor Plan of the Test Site	2-3

Figure 2-2	Compressor/Engine Configuration and Emissions Sources	2-6

Figure 2-3	Flow Tube Calibration at Low Flows (7/23/99)	2-9

Figure 3-1	Idle-Mode Emissions	3-3

Figure 3-2	Operating Emissions	3-5

Figure 4-1	Flow Tube Repeatability (6/2/99)	4-3

Figure 4-2	Flow Tube Calibration at High Flows (8/11/99)	4-5

LIST OF TABLES

Table 2-1	Common Shutdown Scenarios and Emissions	2-5

Table 3-1	Rod Seal Emissions ofNatural Gas (Unit Idle & Pressurized	3-2

Table 3-2	Rod Seal Emissions ofNatural Gas (Unit Operating)	3-4

Table 3-3	Component Emissions	3-6

Table 3-4	Engine Operating Schedule for Phase 1	3-8

Table 3-5	Overall Average Emission Factors	3-11

Table 3-6	Case 1 and Case 2 Gas Savings (scf natural gas)	3-12

Table 4-1	Flow Tube Calibration Results (Low Flows)	4-2

Table 4-2	Flow Tube Calibration Results (High Flows)	4-4

Table 4-3	Rotameter Calibration Results	4-5

Table 4-4	Summary of Instrument Performance Data	4-6

in


-------
ABSTRACT

The U. S. Environmental Protection Agency's (EPA) Office of Research and Development has created
the Environmental Technology Verification (ETV) Program to facilitate the deployment of promising
environmental technologies. Under this program, third-party performance testing of environmental
technology is conducted by independent Verification Organizations. Their goal is to objectively and
systematically evaluate technology performance under strict EPA quality assurance guidelines. The
EPA's Air Pollution Prevention and Control Division has selected Southern Research Institute as the
independent Verification Organization to operate the Greenhouse Gas Technology Verification Center
(the Center). With full participation of technology providers and users, the Center develops testing plans
and conducts field and laboratory tests. The test results undergo analysis and peer review, and are then
distributed to industry, regulatory agencies, vendors, and other interested groups.

The Center has completed the verification testing of the Emissions Packing technology. This technology
is offered by France Compressor Products, and is designed to reduce methane leaks from compressor rod
packing when a compressor is in a standby and pressurized state. Performance testing was carried out at a
compressor station operated by ANR Pipeline Company of Detroit, Michigan. The test was carried out on
two separate engines, each with two compressor units. The Emissions Packing was installed on a single
Test Rod of the two engines (Engines 501 and 502). The remaining rod on each engine contained
standard packing, serving as a Control Rod against which Emissions Packing performance could be
compared. The Control Rod packing was outfitted with new seals at the same time the Emissions
Packing was installed, facilitating a more direct comparison of the Test and Control Rods. The evaluation
focused on two shutdown procedures that represent the most common approaches to compressor
shutdown: remain pressurized during idle; and depressurized (blow down) before idle. The goals of the
test were to: verify initial gas savings for primary baseline conditions, and document initial costs and
installation requirements.

This document reports the results of the Phase I test which consisted of short-term performance
evaluation and documentation of initial costs. The Phase I test was executed between July 16 and July 30,
1999. The following performance results were verified:

•	The Emissions Packing did not reduce compressor rod packing leaks during standby idle mode. The
average difference (both engines) between the Control Rod and Test Rod was -0.29 + 0.55 scfin
natural gas. For Engine 501, the Test Rod emitted more gas than the Control Rod (-0.54 + 0.47 scfin
natural gas). For Engine 502, no significant increase in emissions (-0.04 + 0.55 scfin) was detected.

•	Of the 14 samples collected over a 7-day test period, the emission differences between the Control
Rod and the Test Rod were observed to range between -1.35 and +0.55 scfin. Ten measurements
showed a loss in gas savings, and four samples showed a gas savings. It is believed that these savings
are due to the differences in rod material, not the improvements caused by the Emissions Packing (the
Test Rod was ceramic coated while the Control Rod was alloy steel).

•	The Emissions Packing uses spring-loaded pressure plates, along with conventional sealing rings, to
provide static sealing capability during idle periods. To make room for these pressure plates, a seal
had to be removed from the Test Rod, which is not the case with conventional packing. To determine
if the missing seal alters the emission sealing performance of the overall packing system,
measurements were collected on the Test and Control Rods while the engines were running. Based
on 14 samples collected at the doghouse vents, the Emissions Packing was found to slightly increase
rod packing leaks by -0.05 + 0.38 scfin (Control Rod emissions minus Test Rod emissions ranged
from -0.59 to +0.52 scfin).

IV


-------
While the engines were pressurized, fugitive leaks at the blowdown valve were measured to be 0.08
scfm. No leaks were found from the pressure relief valve and other miscellaneous equipment (e.g.,
valves and fittings). The average unit valve leak rate (combined for both compressors) was 12.14
scfm.

For a baseline operating scenario identified with a compressor that normally remains pressurized
during idle periods, the net gas savings for both test engines were determined to be -18,224 + 29,987
scf natural gas. This is based on the compressor operating schedule encountered at the test site (idle
periods equal 908 hours or 53 percent of the total available operating time).

For a baseline operating scenario identified with a compressor that normally blows down to
atmospheric pressure, the net gas savings for both test engines were determined to be 651,261 +
47,775 scf natural gas. The gas savings achieved here are attributable to the change in operating
practice (i.e., elimination of blowdown volume and unit valve leaks), not the Emissions Packing.

Installation of the Emissions Packing was completed in 27 labor hours (per rod), which is the same
amount of time required to install conventional packing. On a per rod basis, the capital cost for the
Emissions Packing was $3,426.42. The cost for the conventional packing is about $3,500.00, which
is the same as for the Emissions Packing. Consequently, no incremental cost increases were observed
with the Emissions Packing.


-------
ACKNOWLEDGMENTS

The Greenhouse Gas Technology Verification Center wishes to thank the staff and employees of ANR
Pipeline Company for their invaluable service in hosting this test. They provided the compressor station
to test this technology, and gave technical support during the installation and shakedown of the
technology. Key individuals who should be recognized include Curtis Pedersen, Dwight Chutz, and Earl
Prince. Thanks are also extended to the Center's Oil and Natural Gas Industry Stakeholder Group for
reviewing this report.

VI


-------
1.0 INTRODUCTION

1.1 BACKGROUND

The U.S. Environmental Protection Agency's Office of Research and Development (EPA-ORD)
has created a program to facilitate the deployment of innovative technologies through
performance verification and information dissemination. The goal of the Environmental
Technology Verification (ETV) program is to further environmental protection by substantially
accelerating the acceptance and use of improved and more cost-effective technologies. The ETV
program is funded by the Congress in response to the belief that there are many viable
environmental technologies which are not being used because of the lack of credible third-party
performance testing. With performance data developed under this program, technology buyers,
financiers, and permitters in the United States and abroad will be better equipped to make
informed decisions regarding environmental technology acquisitions.

The Greenhouse Gas (GHG) Technology Verification Center (the Center) is one of 12
independent verification entities operating under the ETV program. The Center is managed by
EPA's partner verification organization, Southern Research Institute (SRI), and conducts
verification testing of promising GHG mitigation and monitoring technologies. This Center's
verification process consists of developing verification protocols, conducting field tests,
collecting and interpreting field and other data, and reporting findings. Performance evaluations
are conducted according to externally reviewed Verification Test Plans and established protocols
for quality assurance.

The Center is guided by volunteer groups of Stakeholders. These Stakeholders offer advice on
technology areas and specific technologies most appropriate for testing, help disseminate results,
and review test plans and verification reports. The Center's Executive Stakeholder group consists
of national and international experts in the areas of climate science, and environmental policy,
technology, and regulation. It also includes industry trade organizations, environmental
technology finance groups, various governmental organizations, and other interested groups. The
Executive Stakeholder Group helps identify and select technology areas for verification. For
example, the oil and gas industry was one of the first areas recommended by the Executive
Stakeholder Group as having a need for high quality performance verification.

To pursue verification testing in the oil and gas industries, the Center established an Oil and Gas
Industry Stakeholder Group. The group consists of representatives from the production,
transmission, and storage sectors. It also includes technology vendors, technology service
providers, environmental regulatory groups, and other government and non-government
organizations. This group has voiced support for the Center's mission, identified a need for
independent third-party verification, prioritized specific technologies for testing, and identified
broadly acceptable verification strategies. They also indicated that technologies that reduce
methane leaks from compressor rod packings are of great interest to the technology purchasers. In
the natural gas industry, interstate gas pipeline operators use large gas-fired engines to provide
the mechanical energy needed to drive pipeline gas compressors. In the U.S., fugitive natural gas
leaks from these compressors represent a major source of methane emissions, and a loss of
economic and natural resources.

1-1


-------
To pursue verification testing on compressor rod packing technologies, the Center placed formal
announcements in the Commerce Business Daily and industry trade journals to invite vendors of
commercial products to participate in independent testing. France Compressor Products (parent
company: Coltec Industries, Inc.) responded, committing to participate in a medium-term
independent verification of their new rod packing technology. The technology is referred to as
the Emissions Packing, and is designed to reduce methane leaks from compressor rod packing
during periods when the compressor is in a standby and pressurized state.

Performance testing of the Emissions Packing was carried out at a compressor station operated by
ANR Pipeline Company (ANR) of Detroit, Michigan. The verification test was originally
planned to be executed in two phases where: Phase I verified short-term gas savings and
documented installation costs; and Phase II addressed longer-term technical and economic
performance. This report presents the results of the Phase I test, which occurred between June 16
and July 30, 1999.

Details on Phase I and II verification test design, measurement test procedures, and Quality
Assurance/Quality Control (QA/QC) procedures can be found in the report: Testing and Quality
Assurance Plan for the France Compressor Products Emissions Packing (SRI 1999). It can be
downloaded from the Center's Web site at www.sri-rtp.com. The Test Plan describes the
rationale for the experimental design, the testing and instrument calibration procedures planned
for use, and specific QA/QC goals and procedures. The plan was reviewed and revised based on
comments from France Compressor Products, ANR Pipeline, selected members of the Oil and
Gas Industry Stakeholder Group, and the EPA Quality Assurance Team. The plan meets the
requirements of the Center's Quality Management Plan (QMP), and conforms with EPA's quality
standard for environmental testing (ANSI/ASQC E-4 1994). In some cases, deviations from the
Test Plan were required. These deviations, and the alternative procedures selected for use, are
discussed in this report.

This section also provides a description of the Emissions Packing technology and the goals of the
verification tests. Section 2 presents a background discussion of methane emissions from natural
gas compressors and descriptions of the test site, and the measurement system employed at the
test site. Section 3 presents Phase I test results, and Section 4 assesses the quality of the data.

1.2 THE EMISSIONS PACKING TECHNOLOGY

One of the largest sources of fugitive natural gas emissions from compressor operations is the
leakage associated with operating and idle-mode compressor rod packing. During standby
conditions, natural gas leaks into the atmosphere from the packing case and other compressor
emission sources. Based on an EPA/GRI study, reciprocating compressors in the gas
transmission sector were operating 45 percent of the time in 1992 (Hummel et al. 1996). If rod
leaks during standby operations are reduced or eliminated, significant gas savings and emissions
reductions could be realized. France Compressor Emissions Packing is intended to provide this
benefit.

In general, compressor packing provides a seal around the rod shaft, keeping high pressure gas
contained in the compressor from leaking out into the atmosphere. A typical compressor packing
case is shown in Figure 1-1 (see location No. 3). It consists of one or more sealing rings
contained within a case that serves several functions. These functions include: lubrication,
venting, purging, cooling, temperature and pressure measurement, leakage measurement, rod
position detection, and sealing for standby mode operations (GRI 1997). In conventional

1-2


-------
packing, the sealing rings are configured in series to successively restrict the flow of gas into the
distance piece between the compressor and the engine. The sealing rings are held in separate
grooves or "cups" within the packing case, and are free to move laterally along with the rod, and
free to "float" within the grooves. The distance piece, shown between locations 3 and 4 in Figure
1-1, typically vents rod packing leaks to the atmosphere.

Figure 1-1. Schematic of a Gas Compressor Engine and Rod Packing

1	Compressor Valves and Unloaders

2	Piston & Rider Rings

3	Packing Rings & Case

4	Oil Wiper Rings & Cases

A conventional packing case typically contains seven to nine cups. Each cup houses one or more
seal rings, which restrict the flow of natural gas to atmosphere or out into the distance piece.
Each ring seals against the piston rod and also against the face of the packing cup. The first cup
is occupied by the breaker ring (see Figure 1-2) whose designed function is to reduce the pressure
on the packing rings by providing an orifice restriction to flow. A second function of the breaker
ring is to regulate the reverse flow of gas from the packing case into the cylinder. This reverse
flow occurs as the piston begins the intake stroke, and the pressure is rapidly reduced in the
cylinder.

1-3


-------
Figure 1-2. France Emissions Packing - Ring Detail

PRESSURE—>
Cup #1

Breaker Ring

Cuds #2-6

Conventional
Ring Sets

I—Cup #7

o	Spring

o-	Plate

£

Cup #8

Spring
Plate

Compression
Springs (typ.

Conventional
Ring Set

Cups 2 through 6 are occupied by conventional three-ring packing sets which consist of a "radial
cut" ring, a "tangent cut" ring, and a "backup" ring (see Figure 1-2). During the discharge stroke,
while the compressor is operating, pressure is exerted on each ring. This forces the rings to mate
against each other, and reduce leakage laterally along the rod. During this time, the tangent cut
ring constricts against the rod, reducing leakage past the rod surface. During the intake stroke,
pressure is rapidly reduced in the cylinder, and gas flows from around the sealing rings back
toward the cylinder. During this cycle, the rings are free to move back and forth within the cups
(depending on how much differential pressure is experienced between the discharge and intake
strokes and the movement of the rod). The final cup houses a vent control ring which can be used
to transport the leaking gas for subsequent use or discharge into the distance piece. A more
detailed description of rod packing is given in GRI's report documenting existing compressor rod
packing technology and emissions (GRI 1997).

1-4


-------
Figure 1-3. France Emissions Packing

Emissions Packing

Lubrication
Connection

Packing
Cups

GASKET

157-0400-09029-

NECK FLANGE

VENT PLATE

74-0400-07304

PLAIN PLATE

[84 -0400-07330-1

186-0400-07330-1

SASKET CUP

DESCRIPTION

During idle periods the unit remains pressurized, and pressure equalizes around the rings and they
can float within the cups. While they are floating, the pressure breaker rings and other rings
downstream of the packing are not designed to stop gas leakage. As a result, rod packing leaks
continue when the rod motion has stopped. The leakage encountered during idle periods is due to
the loss of lubrication oil which normally fills the leak paths, changes in the shape of the ring as it
cools, and changes in rod alignment as the temperature changes (GRI 1997).

France Compressor Products (France) offers the Emissions Packing system to reduce leakage
during idle periods. The Emissions Packing system is shown in Figure 1-3. The Emissions
Packing appears identical to a conventional rod packing, with the exception that the final two
cups in a conventional packing are replaced with a single France "T-cup". The France "T-Cup".
which is shown as item 6 in Figure 1-3, contains two spring-loaded pressure plates in addition to
the six sealing rings originally contained in the conventional packing. The spring-loaded pressure
plate and the remaining three conventional rings in the "T-cup" are intended to provide a positive
and continuous seal during idle periods. The pressure plate is a two-piece radial cut ring with
several compression springs equally spaced around the ring that exert a force parallel to the rod.
While the compressor is in an idle, pressurized state, the spring-loaded pressure plate exerts a

1-5


-------
force in the direction of the conventional rings (see the direction of the arrows in Figure 1-2). As
a result of this action, the adjacent seals experience a force similar to that encountered during the
discharge stroke while the compressor is operating, causing the rings to mate together and
constrict the tangent cut ring against the rod.

To allow room for the addition of the pressure plates, the France Packing contains one less ring
set than conventional packing. France did not expect this modification to influence running or
idle emissions; however, both of these factors were quantified in the verification test.

1.3 VERIFICATION GOALS

Normal compressor shutdown and standby procedures vary from station to station. Some
operators depressurize and blow down all pressure from a compressor before standby. Others
depressurize the compressor to a lower, but elevated, pressure, while still others maintain full
pressure during standby. Adding the Emissions Packing to a compressor may result in varying
levels of net gas savings and emission reductions depending on the shutdown procedure used.
Evaluation of the Emissions Packing focused on two shutdown procedures that represent the most
common approaches to compressor shutdown: remain pressurized during idle; and depressurize
(blow down) before idle. Shutdown modes are discussed in Section 2.1.

The Phase I and II verification goals and parameters associated with the two compressor
shutdown scenarios are outlined below.

Phase I Evaluation:

Verify initial gas savings for primary baseline conditions
Document installation and shakedown requirements
Document capital and installation costs

Phase II Evaluation:

Document annualized gas savings for primary baseline conditions

Verify annual methane emission reduction

Calculate and document Emissions Packing payback period

Phase I goals were achieved through observation, collection, and analyses of direct gas
measurements, and the use of site logs and vendor-supplied cost and operational data. The
evaluation was completed after about a 4-week period. Initial gas savings were based on three
sets of manual emission measurements conducted at roughly equal intervals (beginning, middle,
and end of the test period). The number and duration of shutdowns were determined from site
records provided by ANR Pipeline Company for the testing period, and for prior years. Measured
emission rates, site operational data, estimated gas savings, and installation requirements are
documented and verified in this report.

A primary goal of the Phase II evaluation is to determine the Emissions Packing payback period.
As a practical matter, the Center cannot conduct testing for the number of years that would be
required to determine payback from direct measurements. Thus, several Phase II goals will be
accomplished through a combination of medium-term measurements (several months) and data
extrapolation techniques. A Phase II report is planned for release in 2000.

1-6


-------
2.0 TECHNICAL BACKGROUND AND VERIFICATION APPROACH

2.1 METHANE EMISSIONS FROM NATURAL GAS COMPRESSORS

Fugitive natural gas emissions from compressor stations account for a significant loss in revenue
for gas companies and increase a company's unaccounted for gas losses. These emissions also
contribute to the release of methane, a potent greenhouse gas, into the atmosphere. Prior EPA
and Gas Research Institute studies estimated that reciprocating compressors emitted
approximately 21 percent of the total gas emissions (314 billion cubic feet) from the natural gas
industry in 1992 (Harrison et al. 1996).

Methane emissions from compressors are liberated from a variety of different sources. These
sources include leaks from the rod packing, unit valves, the blowdown valve, the pressure relief
valve, and miscellaneous valves, fittings, and other devices. Emissions from blowdown
operations are also significant. One source of fugitive natural gas emissions is the leakage
associated with compressor rod packing. Most leaks occur from operating compressors, but
emissions also occur when some compressors are placed into a standby or idle mode while
remaining pressurized.

According to an ongoing multiyear compressor station fugitive emissions study conducted by the
Pipeline Research Committee, very little difference was observed between the overall average
value of running rod packing emissions and pressurized, but idle, rod emissions. The overall
average leak rate was approximately 1.9 cfm per rod (GRI 1997). The study also concluded that
very large differences at a single site can be encountered, and individual measurements can be
highly variable within a single year, particularly among the idle pressurized compressors. These
results are based on data collected from 9 compressor stations, containing 56 reciprocating
compressors and readings taken at 365 individual rod packings.

Fugitive emissions from standby or idle-mode compressors are affected by the compressor
shutdown mode which varies from station to station. In general, the following procedures are
used:

•	Maintain full operating pressure when idle (either with or without the unit
isolation valves open),

•	Depressurize and blow down all pressure when idle (except a small residual
pressure to prevent air in-leakage) and vent the gas, either partially or
completely, to the atmosphere,

•	Depressurize to a lower pressure, venting the gas either to the atmosphere or
to the station fuel system, or

•	A combination of these procedures.

Based on an EPA/GRI study (Harrison et al. 1996), the first two operating procedures represent
the most common approaches to compressor shutdown. The study estimated that about 57
percent of idle transmission compressors are maintained at operating pressures and 3 8 percent are

2-1


-------
blown down to the atmosphere. A smaller percentage (less than 5 percent) is blown down to a
lower pressure, in some cases venting to the station's fuel system.

2.2 DESCRIPTION OF THE TEST SITE AND EMISSIONS PACKING
INSTALLATION

Reciprocating compressors are the type most commonly used within the gas transmission
industry, and are a primary source of compressor-related emissions. Thus, the Emissions Packing
verification was conducted at a transmission station that uses reciprocating compressors. ANR
Pipeline Company expressed interest in hosting the verification, and assisted the Center in
identifying a representative compressor station within their pipeline system. ANR reviewed its
operations and identified facilities where: Emissions Packing was not currently used; at least one
compressor operates in a shutdown mode several times a year; and site operators could cooperate
in support of the short- and long-term evaluations.

The natural gas transmission engine/compressor selected to host the Emissions Packing
evaluation operates six Cooper-Bessemer engines (8 cylinder, 2000 hp), each equipped with two
reciprocating compressors operating in series (4,275 cubic inch displacement, 4-inch rods). The
low-speed engines at the site are typical of many used in the industry, but may not be typical of
newer, high-speed engines in use. The rods and packing cases have the same basic design and
function as most reciprocating compressors currently used and planned for use in the future in the
transmission sector. The rod packing is essentially a dry seal system, using only a few ounces of
lubricant per day. Wet seals, which use high-pressure oil to form a barrier against escaping gas,
have traditionally been employed. According to the natural gas STAR partners, dry seal systems
have recently come into favor because of lower power requirements, improved compressor and
pipeline operating efficiency and performance, enhanced compressor reliability, and reduced
maintenance. The STAR industry partners report that about 50 percent of new seal replacements
consist of dry seal systems.

Two engines, designated 501 and 502, were selected to verify the performance of the Emissions
Packing system (see Figure 2-1 for a simplified floor plan). These two engines are the same age
and have similar operating hours, which is ANR's normal operating practice. Actual operating
hours on each engine are logged continuously. Each engine contains two compressor rods, and
nine cups are contained in each packing case. The Emissions Packing was installed on a single
rod on each engine by removing the final three sealing cups and replacing them with France "T-
cups". All the standard packing was also replaced. This rod is referred to as the Test Rod, and it
contains one less ring set than the original packing because of the addition of the pressure plates.
France did not expect this modification to influence running or idle emissions; but measurements
were made to verify this claim.

The remaining rod on each engine contained standard packing, and served as a Control Rod
against which Emissions Packing performance was compared. The Control Rod packing was
outfitted with new seals at the same time the Emissions Packing was installed, allowing a more
direct comparison between the Test and Control Rods. All rods are made of alloy steel, with the
exception of the Test Rod on Engine 502. The material on this rod is ceramic-coated steel, which
has been used at this site to reduce oil usage in the seals.

2-2


-------
Figure 2-1. Simplified Floor Plan of the Test Site

I n-jii.- =iu
( IVm I nil)

Control Rod with	Test Rod with

Conventional Packing Emissions Packing

I ii'jnii' *n2
(l t>t [ nil)

Control Rod with	Test Rod with

Conventional Packing Emissions Packing

2.3 VERIFCATION APPROACH

2.3.1 Establishing Baseline Conditions

According to France, the Emissions Packing can provide static sealing during idle periods,
provided the compressor remains pressurized. Of course, the gas savings achieved depend on the
emission characteristics of the compressors packing, both before and after installation of the
France Emissions Packing. Gas savings also depend on the shutdown procedures used, and the
number and duration of shutdowns experienced. For example, a station that currently leaves
compressors pressurized during shutdown will achieve net savings from the decrease in rod
packing leaks during idle. Alternatively, if a station currently blows down compressors before
shutdown, installing the Emissions Packing would be associated with a change in operating
practice to a pressurized shutdown condition. A likely scenario for such a change would be that
the station wishes to eliminate blowdown emissions, and employs a static sealing system at the
same time to reduce or eliminate any new emissions from the newly pressurized rod packings. In
this case, gas savings occur by eliminating blowdown emissions and unit valve leaks. However,
there is a potential for increases in emissions from components now exposed to high pressure
during shutdown.

2-3


-------
For the two most commonly used compressor shutdown scenarios described in Section 2.1, Table
2-1 shows the relationship between compressor shutdown procedures and emissions. Since use of
the Emissions Packing system is associated with a pressurized compressor standby operation, the
table indicates how compressor emissions may change from the emissions that occurred during
the original standby mode. Using this table as a guide, a verification plan was developed to
characterize all the emissions changes that may occur with the installation of the Emissions
Packing and the possible adoption of a different shutdown procedure.

The evaluation of the Emissions Packing performance at ANR Pipeline Company focused on the
two shutdown scenarios that collectively represent practices employed by about 95 percent of the
transmission compressors (Shires and Harrison 1996). Case 1 represents compressors that remain
pressurized when idle, and Case 2 represents compressors that completely depressurize and blow
down all gas. The host site was asked to follow these practices during testing, although their
normal practice is to maintain idle pressures of about 120 psig and recover all blowdown gas into
the engine fuel system. The following discussion highlights the verification issues for each case
and outlines measurements and data collection activities implemented in the verification test.

2.3.1.1 Case 1

Case 1 represents a compressor that normally maintains full operating pressure during idle
periods. For this case, a change in emissions was anticipated to occur only at the rod packing due
to the static sealing action of the Emissions Packing. To quantify this potential change in rod
packing leaks, direct methane emission rate measurements were conducted on the distance piece
or doghouse vent pipes associated with the Control Rods and Test Rods for each of the two
engines. Because the unit pressure is essentially unchanged during both operating and idle
periods, leak rates from all other components (pressure relief valve, blowdown valve, unit valves,
and miscellaneous flanges, valves, and fittings) can be assumed to remain constant after
installation of the Emissions Packing. The idle-mode emissions from the two Control Rods are
compared to idle-mode emissions from the two Test Rods. The difference between these two
values are determined, and used to quantify the static sealing abilities of the Emissions Packing.

For Case 1, the savings consist solely of the gas prevented from leaking from the rod packing
during idle periods. This is the difference between the leak rate without the Emissions Packing
(measured for the Control Rods) and the leak rate with the Emissions Packing (measured for the
Test Rods). Equation 1 states how gas savings will be calculated.

G1 = [Qu - Qs] * t	(Eqn 1)

where,

G1 = average gas savings for the Phase I test period (Case 1), scf
Qu = average uncontrolled leak rate during idle (Control Rod), scfm
Qs = average controlled leak rate during idle (Test Rod), scfm
t = total shutdown or idle time during Phase I, minutes

2-4


-------
Table 2-1. Common Shutdown Scenarios and Emissions

Matrix of Shutdown Procedure Changes

Procedure or emission
source

CASE 1

CASE 2

Current shutdown
procedure

Pressurized shutdown with
unit valves open or closed3

Blowdown/100% vent to
atmosphere

Procedure with Emissions
Packing

n/c

Pressurized shutdown

Matrix of Possible Emissions Changes Due to Shutt
Installation of the Emissions P

own Procedure Changes or
acking

Rod seals

Decrease

Little or no increase

Blow-down volume

n/cb

Decrease

Unit valve seat (via open
blow-down line)

n/c

Decrease

Blow-down valve

n/c

Increase

Pressure relief valve

n/c

Increase

Misc. valves, fittings,
flanges, stems etc.

n/c

Increase

a Most sites leave the unit valves closed for safety reasons (i.e., sites may not want problems in the shutdown

engine to affect the integrity of the entire station).
b n/c - no change/effectively no change
Shaded area represents measured parameters.

2.3.1.2 Case 2

Case 2 represents a compressor that normally blows down from operating pressure to a minimum
pressure during idle periods. At such times the pressure on compressor components is reduced to
near atmospheric pressure. Consequently, leaks from rod packing, pressure relief valves, and
blowdown valves cease to exist. However, leaks from the unit valves, which are closed to isolate
the compressor from the pipeline, are liberated into the atmosphere. This gas leaks past the unit
valves, into the compressor system, and out into the atmosphere via the open blowdown valve.
Figure 2-2 illustrates a simplified diagram of these emission sources. Because emissions
associated with leaking unit valves can be substantial, measurements were made to quantify these
emissions after blowdown was completed. When the Emissions Packing is installed, and a
pressurized shutdown eliminates the unit valve leaks, this gas represents a saving associated with
the use of the Emissions Packing. In addition, the compressed gas contained in the compressor
and lines is lost during the blowdown. This gas must also be considered as a savings associated
with the Emissions Packing, and was calculated based on known volumes of compressor
components and the measured operating pressure. All of these emission savings are added to the
savings determined for the rod packing as described above, resulting in a total gas savings value
for the Emissions Packing.

2-5


-------
Figure 2-2. Compressor/Engine Configuration and Emissions Sources

Blowdown Valve and Vent

In contrast, emissions can increase from several components which are now exposed to high
pressure. Ultimately, these leaks decrease the net gas savings associated with the Emissions
Packing. To verify this, methane emission rate measurements were conducted (during
pressurized idle mode) on all components newly exposed to elevated pressures as a result of the
pressurized shutdown. These compounds include the pressure relief valve, the blowdown valve,
and various flanges, connectors, and valves. Emissions from these devices are subtracted from
the total savings above, to yield the net savings associated with the Emissions Packing.

It is assumed that, following installation of the Emissions Packing and after a pressurized
shutdown is adopted, the unit valve would be placed in a closed position during shutdown (this
was the host site's procedure). Compressor pressures were monitored during shutdown to
determine if the pressure slowly dropped due to this closed valve, or if leaks from the closed
valve were sufficient to maintain full compressor pressure.

For Case 2, gas savings consist of the blowdown volume (times the number of idle periods) and
the unit valve leak rate (times the duration of idle periods). In addition, there are gas leakages
from the blowdown valve, pressure relief valves, and miscellaneous components. Additionally,
any gas that escapes past the Emissions Packing is lost (because the baseline for this case is a
blowndown compressor, rod packing leakage would be zero). For Case 2, the gas savings for
each idle period were calculated as follows.

2-6


-------
G2 — BDV + Quv * t — [Qprv + Qbdv + Qmisc + Qs] * t

(Eqn. 2)

where,

G2 = gas savings for each idle period (Case 2), scf

BDV = blowdown volume times the number of blowdowns during the Phase I period, scf

Quv = unit valve leak rate, scfim

t = idle time over the Phase I test period, minutes

Qprv = pressure relief valve leak rate, scfim

Qbdv = blowdown valve leak rate, scfm

Qmisc = aggregate leak rate for miscellaneous components, scfm
Qs = test rod leak rate, scfm

2.3.1.3 Impact on Normal Running Emissions

With the Emissions Packing technology, several standard sealing rings are replaced with special
France rings and pressure plates. With this change, there is a potential to alter the emission
sealing performance of the overall packing system (i.e., cause an increase or decrease in packing
emissions compared to the standard packing). To address this, measurements were conducted on
the test and control rods, with the compressors in a normal operating state. It is assumed that,
after installation of the Emissions Packing, the unit valve position (i.e., closed or open) would
remain the same as before the Emissions Packing was installed. Any implied running emission
changes were integrated into the assessment of net gas savings for the Emissions Packing system.

For example, if it was determined that the Emissions Packing caused any increase in emissions
during normal compressor operation (see later discussion on running emissions), these emissions
were subtracted from the gas savings. The following equation states how the total gas savings
will be calculated for each case. The total gas savings, G1t and G2T, for Case 1 and Case 2,
respectively, are given in Equations 3a and 3b.

G1j — G1 - Vm	(Eqn. 3a)

G2j = G2 - Vm	(Eqn. 3b)

Where, Vm is any increase in operating emissions that occurred over the test period due to the
Emissions Packing. Vm is the difference in operating emissions (i.e., non-idle periods) between
the Test and Control Rods, times the number of minutes the compressor operated during the
Phase I test period.

2.3.2 Emission Measurements and Calculations

The following discussion provides an overview of the measurements made, instruments used,
field procedures followed, and key calculations made in the Phase I tests. For more detail on
these topics, the reader should consult the Test Plan titled Testing and Quality Assurance Plan for
the France Compressor Products Emissions Packing (SRI 1999). It can be downloaded from the
Center's Web site at www.sri-rtp.com.

2-7


-------
To characterize the running emissions and Case 1/Case 2 emissions, manual emission
measurements were collected on the following sources: doghouse vent, unit valve seat (via the
open blowdown line), pressure relief valve vent, blowdown valve vent, and miscellaneous
components (e.g., fittings, connections, valve stems). Tests were performed when the engine was
pressurized and running, pressurized and idle, and depressurized and idle. For the rod packing
leaks, tests were performed when the engine was pressurized and running, and pressurized and
idle. Measurements of the leak rate for the blowdown valve, pressure relief valve, and
miscellaneous other components were made when the unit was pressurized and idle. The unit
valve leak rate measurement was made with the unit blowndown and the blowdown valve closed.

The measurements made and operating conditions under which testing was performed are listed
below. One full day was required to conduct this suite of measurements on both engines.

•	With both units shut down and pressurized: natural gas leak rates for the
pressure relief valve, blow down valve, miscellaneous components, and rod
packing vents (test rod and control rod)

•	With both units blown down: natural gas leak rates for the unit valve and unit
valve stem

•	With both units running: natural gas leak rates for the doghouse vents (Test
Rod and Control Rod)

Measured natural gas leak rates were converted to methane leak rates using natural gas
compositional measurements (about 97 percent methane) provided by ANR Pipeline.

The station agreed to a limited number of scheduled shutdowns for the purpose of conducting the
measurements described above. Results from these tests were used to characterize emission rates
at the time of testing, and to characterize emissions differences between Case 1 and 2 above. Net
gas savings were calculated based on the number and duration of idle periods encountered at the
site for the test period.

2.3.2.1 Rod Leak Rate Measurements

Emissions from the packing case vent and leaking rod seals are both vented into the distance
piece or doghouse described in Section 1.2. Both emission sources vent gas that has escaped the
sealing action of the packing, and are included together when measuring emissions. After
emissions are discharged into the doghouse, they are vented to the atmosphere through the
doghouse vent. After soap screening all doghouse seals and connections and monitoring the
long-term compositional trends of the gas exiting the doghouse, it was determined that no other
gas was entering the doghouse. The doghouse vent and oil drain were the only paths by which
emissions escaped into the atmosphere. For the test, the doghouse oil drain was sealed using a
liquid trap (ball valves closed during testing), which forced all emissions to exit through the
doghouse vent.

To measure these emissions, a Flow Tube was used to measure vent gas velocity, and a
hydrocarbon analyzer was used to measure vent gas total hydrocarbon concentration (THC)
before flow measurement started. In the original Test Plan, sensitive, low-pressure-drop
continuous flow meters were planned for use, but after their installation, it was determined that

2-8


-------
the pressure in the doghouse vents was so low that reliable flow detection could not be
established. With this discovery, the decision was made to proceed with testing, and to use
sensitive manual methods to conduct the measurements.

The Flow Tube consists of a sensitive 1-inch vane anemometer mounted on the inside walls of a
polyvinyl chloride (PVC) tube that measures 30 inches in length and 1 inch in diameter. Just
before taking velocity readings, the hydrocarbon concentration in the doghouse vent was
measured using a portable hydrocarbon analyzer. The analyzer used was a Bascom-Turner CGI-
201, with a 4-100 percent total hydrocarbon range, and an instrument rated accuracy of 2 percent
(per manufacturer specifications) of the measured concentration. The CGI-201 measures all
primary hydrocarbon compounds found in natural gas including methane, ethane, propane, and
butane.

Before each trip to the site for on-site measurements, the Flow Tube was laboratory-calibrated
using a National Institute of Standards and Technology (NIST) traceable Laminar Flow Element
and a wide range of simulated natural gas flow rates (99 percent methane, 0.3 to 4 scfm). These
calibrations were used to generate a calibration curve which spanned the range of flow rates
anticipated for the site. This curve was used to select a natural gas flow rate based on the
indicated velocity from the flow tube. An example calibration chart is shown in Figure 2-3.

Figure 2-3. Flow Tube Calibration at Low Flows (6/2/99)

Gas Velocity (fpm)

2-9


-------
For each doghouse vent, a minimum of 10 separate gas velocity readings were recorded with the
Flow Tube. These measurements were made after the doghouse emissions were observed to
stabilize (15 to 20 minutes after the vents were opened). The standard deviation of the doghouse
emissions ranged between 0.0042 and 0.0680 scftn natural gas. The standard deviation over 70
percent of the samples collected was within the average standard deviation of 0.0042 scfm. In
most cases, the 10 readings showed stable emissions. More readings were collected if the
standard deviation was greater than 5 percent of the average emission rate of the entire data set.
Each measurement represents a 16-second average value and, after completion, all values were
averaged to yield an overall average total gas flow rate in feet per minute. Using this value, a
natural gas flow rate was selected from the flow tube calibration curve.

It should be noted that, after opening the doghouse vent for measurement, air typically enters and
mixes with the natural gas leaking from the rod packing. The average THC content in the gas
flows measured at the Control Rod was 85 percent, and at the Test Rod was 91 percent (during
running and idle periods). Based on the Center's experience with characterizing doghouse vent
emissions at several compressor facilities, it is believed that the rod packing leak is the driving
force which results in gas escaping through the vents (i.e., only one outlet stream is present for
the gas to escape and no other gas can enter the doghouse). As such, it is assumed that the flow
rate measured during testing is representative of the flow rate of pure natural gas. Also, given a
sufficient amount of time, the rod leaks would eventually completely purge all air from the
doghouse, allowing direct measurement of pure natural gas with the flow tube. As a practical
matter, this could not be done routinely. This assumption was verified by monitoring composition
on two vents over time (about 1 hour), and verifying that the composition eventually reached 92
to 94 percent THC.

2.3.2.2 Component Leak Rate Measurements

Manual measurements were made for the pressure relief valves, unit valves, blowdown valves,
and miscellaneous components. The leak rates for the blowdown valve and pressure relief valve
were measured with the unit shut down and pressurized. Measurements for miscellaneous
components were also made with the unit pressurized. Leak rates for the unit valves were
determined with the unit depressurized and the valve closed.

The pressure relief valves vent through a 6-inch standpipe extending to the roof of the compressor
building. Access to the roof was limited, and posed a hazard to the testing personnel. Thus, a
hydrocarbon analyzer was first used to determine if leaks were present. If hydrocarbons were
detected, the Flow Tube was to be used to quantify gas flow rates. With the exception of making
a direct connection to the 6-inch standpipe outlet, the sampling and calibration procedures
described in the previous section apply to this emission source as well.

Flow measurements were conducted at an existing port, located immediately downstream of the
unit valves in the suction line of each compressor. During compressor shutdown, any leaks from
the seats of the unit valves will exit through this opened port. The leak rate for the unit valves
was the highest flow measured at the host site. The leak rate was measured using the same Flow
Tube applied to the rod packing vents. The anemometer mounted within the tube has the capacity
to measure the high flows that occurred (e.g., a maximum of 6,500 fpm or about 20 cfm of natural
gas could be measured). However, a different calibration chart from the one presented in Figure
2-3 was used to determine emission rates at the higher flows encountered with unit valves leaks
(see Section 4 for more information on calibration).

2-10


-------
The leak rate for the blowdown valve was measured at the flange located at the exit of the valve.
To make this measurement, it was necessary to unbolt the flange, separate the two sides by about
1 inch, and then insert a disk. The disk contained channels that allowed the leak to be captured
and directed into a small, sensitive low-flow-rate rotameter (Dwyer VB Series, 0 to 1000
mL/min, with a published accuracy and precision +3 percent). The Flow Tube was originally
planned for use on the blowdown valve emissions, but early field results indicated relatively low
flow rates existed at this location. The low-flow-rate rotameter was used because of the poor
performance of the Flow Tube at these low flows.

The miscellaneous components at the test site consist of pressure and temperature metering taps,
fittings that connect the taps to data transmitters, and valves used to recover gas for the fuel
recovery system. The host station normally vents to a specially designed gas recovery system
during shutdown, but performed the blowdown procedure for this verification, allowing an
assessment of the Case 1 and Case 2 shutdown scenarios described above. Significant leaks were
not expected at these locations; however, all components were soap screened and any leaks
identified were to be quantified using the EPA protocol tent/bag method.

2.3.2.3	Natural Gas Composition Measurements

Natural gas compositional analysis for the test site is performed at an adjacent compressor station
operated by ANR Pipeline Company (about 70 miles downstream). At this site ANR operators
use a gas chromatograph (Daniel Model #2251) to determine the concentration of methane,
hydrocarbons, and inert gas species present in the pipeline gas. The gas chromatograph is
capable of measuring 0 to 100 percent methane, with a published accuracy and precision of +0.02
percent of full range. The instrument is calibrated each month using 97.0 percent certified
methane.

The Center obtained copies of the fuel gas analyses results and their calibration records which
correspond to the Phase I measurements. An average methane concentration was calculated for
those days when sampling was conducted. This value was multiplied by the natural gas savings
measured for each case to calculate the standard cubic feet of methane saved.

2.3.2.4	Blowdown Volume Determination

The blowdown volume represents gas contained in the test compressor, engine, auxiliary piping,
and all components located downstream of the unit valves. Based on records obtained from ANR,
the total gas volume present in this equipment is 176 cu ft. ANR engineers determined that at
600 psig pressure, 7,900 scf natural gas occupies this volume (corrected for the compressibility
factor). Because it is not feasible to directly measure the blowdown volume, 7,900 scf was used
to represent the total gas that would be released into the atmosphere each time the test compressor
was depressurized from 600 to 0 psig.

2.3.3 Site Operational Data

The number and duration of shutdown/idle periods must be specified to calculate the gas savings
that occurred during the 4-week Phase I evaluation. Site records, provided by ANR pipeline, were
used to determine the number and duration of shutdowns for the Phase I period. The ANR
records identify daily compressor operating hours and the total hours the compressor was
available (i.e., scheduled shutdown for maintenance is not included in the available hour values).
Subtraction of the total available hours from the total operating hours yields the number of hours

2-11


-------
each unit was on idle. Because the number and duration of shutdowns were manipulated by the
Center to ensure collection of the necessary measurements, those shutdowns that occurred at the
Center's request were also subtracted.

The number of blowdowns was determined by accounting for each occurrence of an idle period.
(It should be noted that this is an estimated value because the test site does not normally blow
down, but rather, maintains a minimum pressure of 120 psig operating pressures during idle
periods.) The number of blowdown occurrences assigned for the Case 2 evaluation is a synthetic
value which represents sites that follow blowdown procedures.

2-12


-------
3.0 RESULTS

3.1 ROD PACKING EMISSIONS

3.1.1 Emissions During Idle/Shutdown

Doghouse leak rate measurements data were collected over a 7- day sampling period. These data
span the range of time from when both the Emissions Packing and the conventional packing were
new until they had logged about 1100 hours of wear. Table 3-1 presents the measured packing
vent emissions for Engines 501 and 502 during pressurized idle states. The results are
summarized as differences. A 95 percent confidence interval about the mean of the differences
was computed based on a Student's t distribution. Measurements were generally started 20
minutes after shutdown occurred, unless the engine had been shut down overnight. It generally
required about 30 minutes to complete the data collection. For 80 percent of the samples, the
engine was in the idle mode for at least 24 hours (see footnote d in Table 3-1). No changes in rod
emission rates were observed between measurements made shortly after shutdown and after a
minimum of 24 hours had transpired.

Table 3-1 shows that the France packing did not reduce compressor rod packing leaks during the
standby idle mode. The average difference (both engines) between the Control Rod and Test Rod
was -0.29 +0.55 scfm natural gas. Thus, at the 95 percent confidence level, there is a slight
negative difference between sealing performance with and without the emissions packing. The
errors calculated using the Student's t distribution are greater than the errors expected from the
measurement instruments, showing process variability between the two rods.

Of the 14 samples collected, 10 measurements showed a loss in gas savings between the
Emissions Packing and the conventional packing, although the differences were small in some
cases. Averaging the data from both engines, the overall average emission rate for the France
Packing Rod was 1.23 + 0.54 scfm while the Control Rod overall average emissions rate was 0.94
+ 0.39 scfm.

For Engine 501, the Test Rod emitted slightly more gas than the Control Rod (-0.54 + 0.47 scfm
natural gas). For Engine 502, the France packing emissions were initially lower than the
conventional packing, but halfway through the Phase I test period, they increased and remained
higher than the conventional packing (see Figure 3-1). On average, no reduction in rod emissions
was detected on Engine 502 (-0.04 + 0.55 scfm), indicating that the Emissions Packing did not
reduce idle emissions as expected.

Although not confirmed, the differences between Engines 501 and 502 emissions may be the
result of different rod materials (see footnote a to Table 3-1). As Figure 3-1 illustrates, it appears
that emissions from Engine 502 are slightly higher than from Engine 501. The figure also
suggests that the France packing emissions were more variable, while the emissions for the
conventional packing were relatively stable. No clear emission trends are apparent, but it can be
concluded that the France Packing does not perform significantly better (as expected) than the
conventional packing during idle periods.

3-1


-------


Table 3-1. Rod Seal Emissions of Natural Gas







(Unit Idle & Pressurized)



Date

Approx.

Engine Idle,

Difference



Run Time

Pressurized

(a)y 600 psi

Between Control



on New

Control Rod With

Test Rod With

Rod and Test Rod"



Seals

Conventional Packing

Emissions Packing3

(scfm natural gas)



(hrs)

(scfm natural gas)

(scfm natural gas)



ENGINE 501

6/16/99d

3

0.69

0.73

-0.04

6/17/99 d

20

0.72

0.93

-0.21

7/7/99

510

0.44

0.71

-0.27

7/8/99

530

0.38

1.05

-0.67

7/28/99 d

1030

0.64

1.99

-1.35

7/29/99 d

1075

0.42

0.59

-0.17

7/30/99 d

1100

0.67

1.77

-1.10

Average

0.57

1.11

-0.54

Confidence Coefficient0

+0.13

+0.51

+0.47

ENGINE 502"

6/16/99 d

19

1.33

0.78

+0.55

6/17/99 d

37

1.26

0.89

+0.37

7/7/99 d

540

1.17

0.71

+0.46

7/8/99

560

1.59

1.37

+0.22

7/28/99 d

1065

1.38

2.30

-0.92

7/29/99 d

1090

1.43

2.13

-0.70

7/30/99 d

1115

1.04

1.32

-0.28

Average

1.31

1.36

-0.04

Confidence Coefficient0

+0.17

+0.59

+0.55

Both Engines Combined

Average

0.94

1.23

-0.29

Confidence Coefficient0

+0.39

+0.54

+0.55

a The Test Rod on Engine 502 is ceramic coated. The remaining rods are alloy steel.



Difference = (Control Rod Emissions - Test Rod Emissions), positive values indicate gas savings was achieved.

c Student's t distribution statistical analysis was used. Results are reported at 95% confidence level.

d The test engines were on idle standby mode for at least 24 hours prior to sampling.



3.1.2 Emissions During Compressor Operation

Table 3-2 presents the measured packing vent emissions for Engines 501 and 502 during
compressor operation. As before, seven daily average natural gas emission rates are reported for
each vent, and these data span the range of time from when the packing was new, until the
packing had logged about 1100 hours of wear. Measurements were collected after emissions had
stabilized (generally within 5 to 15 minutes after the engine was loaded).

3-2


-------
Figure 3-1. Idle-Mode Emissions

2.5

3 20 510 530 1030 1075 1100	19 37 540 560 1065 1090 1115

Packing Age (hours)

Control Rod —¦—Test Rod

As was the case with the idle-mode emissions, the France packing generally had emissions that
were slightly higher than the conventional packing during operation, although the differences
were not as great. For Engine 501, the France packing had emissions that were 0.03 to 0.59 scfm
higher than the conventional packing (an average increase of 0.25 + 0.21 scfm). On Engine 502,
the France packing emissions were initially lower, but halfway through the Phase I period, they
became higher for a time and then decreased again. For Engine 502, the differences between the
France packing and the conventional packing ranged from 0.54 to +0.54 scfm, with an average
savings of 0.15 + 0.44 scfm.

Averaging the data from both engines, the France packing produced overall average emissions
that were 1.04 + 0.41 scfm while the Control Rod emissions were 0.99 + 0.40 scfm. Running
emissions were 0.05 + 0.38 scfm higher than the conventional packing (about 3 percent higher
than the Control Rods). Based on these data, it can be concluded that the removal of the seal
required to install the France packing may result in slightly higher emissions while the
compressor is operating, although the differences are relatively insignificant compared to the rod
emission rates.

Figure 3-2 presents a plot of the running emissions for both engines. As the figure suggests,
emissions from the France packing are less variable than the conventional packing when the
compressor is in the operating mode, and the difference between the conventional and France
packing is also reduced. The figure also suggests that no clear emission trends are apparent.

3-3


-------
Table 3-2. Rod Seal Emissions of Natural Gas
(Unit Operating)

Date

Approx.
Run Time
on New
Seals, hrs

Engine Running @ 600 psi

Difference
Between Control
Rod and Test
Rod", scfm
natural gas

Control Rod With
Conventional
Packing, scfm natural
gas

Test Rod With
Emissions Packing3
scfm natural gas

ENGINE 501

6/16/99

3

0.69

1.28

-0.59

6/17/99

20

0.55

0.90

-0.35

7/7/99

510

0.62

0.65

-0.03

7/8/99

530

0.61

0.58

+0.03

7/28/99

1030

0.62

1.04

-0.42

7/29/99

1075

0.54

0.63

-0.09

7/30/99

1100

0.51

0.84

-0.33

Average

0.59

0.85

-0.25

Confidence Coefficient0

+0.06

+0.23

+0.21

ENGINE 502"

6/16/99

19

1.68

1.16

+0.52

6/17/99

37

1.28

0.90

+0.38

7/7/99

540

1.43

0.97

+0.46

7/8/99

560

1.32

0.91

+0.41

7/28/99

1065

1.44

1.97

-0.53

7/29/99

1090

1.46

2.00

-0.54

7/30/99

1115

1.08

0.70

+0.38

Average

1.38

1.23

0.15

Confidence Coefficient0

+0.17

+0.49

+0.44

Both Engines Combined

Average

0.99

1.04

-0.05

Confidence Coefficient0

+0.40

+0.41

+0.38

a The Test Rod on Engine 502 is ceramic coated. The remaining rods are alloy steel.

b Difference = (Control Rod Emissions - Test Rod Emissions), positive values indicate gas savings are achieved.
c Student's t distribution statistical analysis was used. Results are reported at 95% confidence level.

3-4


-------
Figure 3-2. Operating Emissions

Packing Age (hours)

Control Rod —¦—Test Rod

3.2 OTHER EMISSION SOURCES

3.2.1 Valve Leaks and Blowdown Volume

Measurements were conducted to quantify emissions associated with the closed and pressurized
blowdown valve, pressure relief valve, and unit valves. These measurements represent the
emissions leaking past the valve seats on each device. Estimates of the emissions associated with
compressor blowdown operations are also presented, and are based on ANR-supplied gas
pressures and equipment volumes. The sources addressed in this section are among the most
significant fugitive emission sources associated with compressor operations. Measurements
associated with the remaining minor sources (e.g., valve stems, fittings, and other minor fugitive
sources) are addressed in Section 3.2.2.

Measurement results are presented in Table 3-3. As the table shows, screening with the
hydrocarbon analyzer showed that no gas was leaking from the pressure relief valve. Thus, a
flow rate of 0 scfm is assigned here. Emissions from the unit valve were high and relatively
variable. The overall average emission rate was 12.14 scfm, which excludes three low emission
rates that occurred when operators took action to reduce emissions in response to the
measurements data collected (see footnote b in Table 3-3). The blowdown volume is constant
because the operating pressure and equipment volume remained the same.

3-5


-------
Table 3-3. Component Emissions

Date

Blowdown

Pressure Relief

Unit Valve



Blowdown Volume3



Valve
(scfm gas)

Valve
(scfm gas)

(scfm gas)



(scf gas/event)

ENGINE 501

6/16/99

0.16

0d

0.00b

7,900

6/17/99

0.16

0d

1.46b

7,900

7/7/99

0.07

od

12.05

7,900

7/8/99

0.07

od

12.51

7,900

7/28/99

0.06

od

17.50

7,900

7/29/99

C

od

16.55

7,900

7/30/99

0.03

od

19.44

7,900

ENGINE 502

6/16/99

0.14

od

10.00

7,900

6/17/99

0.14

od

3.09b

7,900

7/7/99

0.04

od

6.21

7,900

7/8/99

0.04

od

6.61

7,900

7/28/99

0.04

od

12.70

7,900

7/29/99

C

od

10.96

7,900

7/30/99

0.01

od

9.06

7,900

a Based on calculations performed by ANR engineers. This value represents the total volume of gas present in

the test compressor, piping, and all equipment located downstream of the unit valves (at 600 psig).
b The station operator greased the unit valve to reduce emissions. This process temporarily reduced the leakage,

and is not considered representative.
c The Center field operator mistakenly measured the blowdown valve emissions while the unit was pressurized at

120 psig, instead of 600 psig. Blowdown valve emissions are not reported for this day.
d A hydrocarbon analyzer was first used as a screening method to identify if leaks were present. If THC levels
were found to be greater than 50 percent, the Flow Tube was required to be used to quantify the leak rate. For
these samples, THC levels were nearly 0 percent. Thus, the Flow Tube was not used.

3.2.2 Miscellaneous Fugitive Sources

Once each day, miscellaneous fugitive emission sources were soap-screened to identify
components that were leaking significantly and in need of emission rate measurement. The types
of components screened are identified below.

•	Flanges - Valve, meter, pipe, and other flanges

•	Miscellaneous fittings (tees, elbows, couplings, drains, ports, small valves)

•	Blowdown gas recovery system components

•	Temperature and pressure metering ports

The soap-screening revealed no leaking components. This is not surprising, because most of
these components are located in confined working areas, and any leaks could result in a
significant safety hazard or triggering of the gas detection alarm system located at the site.

3-6


-------
3.3 NET GAS SAVINGS

The primary verification parameter determined for the Phase I evaluation is net gas savings. The
Phase I test period began after the packings were installed and the engines were started (June 16,
1999), and ended on the last day of sampling (July 30, 1999). Net gas savings for the Phase I
period were calculated for the Case 1 and Case 2 baseline shutdown scenarios based on the
overall average emission rates presented in Sections 3.1 and 3.2 and engine operational data
presented in the next section. For Case 1, the use of Emissions Packing resulted in a gas loss of
-18,224 + 29,987 scf for the two test engines. For Case 2, the net gas savings for both test
engines were determined to be 651,261 + 47,775 scf. The gas savings achieved here are due to
the change in operating practice, not the Emissions Packing. The following subsections discuss
these results in detail.

3.3.1	Compressor Operational Characteristics

To calculate net gas savings, the operational characteristics of both engines were defined on a
daily basis. The operating characteristics of interest include the number of shutdowns, the
number of hours in the idle mode, the number of hours in the running or operating mode, and the
number of hours in the out-of-service mode (i.e., non-idle mode such as maintenance and repair).
These operating characteristics, presented in Table 3-4, were defined for Engines 501 and 502
using data supplied by ANR Pipeline. The gray areas in the table correspond with sampling
conducted by the Center. Although several idle-mode shutdowns occurred on these days, they are
not included in the determination of gas savings because these shutdowns were performed at the
request of the Center.

3.3.2	Case 1 and Case 2 Gas Savings

This section presents calculated gas savings associated with the France packing for Engines 501
and 502. Savings are computed by comparing compressor emissions when the France packing is
installed with compressor emissions without the France packing. The France packing requires a
pressurized shutdown/idle mode be used, and the gas savings achieved will depend on how
shutdown and idle mode operations were managed prior to installing the France packing.

Two base-case shutdown/idle modes are assumed. Case 1 represents the original use of a
pressurized shutdown (same as the Emissions Packing requires) and Case 2 represents the
original use of compressor depressurization and blowdown. As a result of changing the packing,
and possibly the shutdown/idle mode, a variety of emission changes will occur in both cases.
Each change is quantified here, and the bullets below describe how each value is calculated. The
emission factors referred to below were described in Sections 3.1 and 3.2, and are summarized in
Table 3-5.

3-7


-------
Table 3-4. Engine Operating Schedule for Phase I

Engine

Date

Number of
Shutdowns

Operational Data (Hrs)

Running

Scheduled
Downtime for
Maintenance, etc.

Idle

501

1 (>-.l Mil

r-.iun













18-Jun



9.9

0

14.1



19-Jun



24

0

0



20-Jun



24

0

0



21-Jun



24

0

0



22-Jun



24

0

0



23-Jun



24

0

0



24-Jun



24

0

0



25-Jun



24

0

0



26-Jun



24

0

0



27-Jun



24

0

0



28-Jun



20.3

3.7

0



29-Jun



24

0

0



30-Jun



24

0

0



1-Jul



24

0

0



2-Jul



24

0

0



3-Jul



24

0

0



4-Jul

1

7.4

0.1

16.5



5-Jul



4.2

0.2

19.6



6-Jul



24

0

0



"-Jul
S-.lul













9-Jul



24

0

0



10-Jul



15.7

8.3

0



11-Jul

1

0

17

7



12-Jul



0

0

24



13-Jul



0

0

24



14-Jul



0

0

24



15-Jul



0

0

24



16-Jul



6.4

6.8

10.8



17-Jul



0

24

0



18-Jul



0

24

0



19-Jul

1

0

7.7

16.3



20-Jul



0

0

24



21-Jul



0

0

24



22-Jul



0

0

24



23-Jul



0

0

24



24-Jul



0

0

24



25-Jul



0

0

24



26-Jul



0

0

24



27-Jul



0

0

24

(continued)

3-8


-------
Table 3-4 (continued)

Engine

Date

Number of
Shutdowns

Operational Data (Hrs)

Running

Scheduled
Downtime for
Maintenance, etc.

Idle



2S-.I ii 1
2<>-.lul
'ii-.liil













TOTAL

•)

44"

1 s

;

502

1 (>-.l III!

r-.iuii













18-Jun

1

0.7

0

23.3



19-Jun



0

0

24



20-Jun



0

0

24



21-Jun



0

1.2

22.8



22-Jun



9.4

5.9

8.7



23-Jun

1

18.5

0.1

5.4



24-Jun



0

0

24



25-Jun



0

0

24



26-Jun



0

0

24



27-Jun



0

0

24



28-Jun



0

9.1

14.9



29-Jun



10.4

0.3

13.3



30-Jun



24

0

0



1-Jul



24

0

0



2-Jul



24

0

0



3-Jul



24

0

0



4-Jul

1

10.4

0.1

13.5



5-Jul



0

0

24



6-Jul



0

0.4

23.6



"-Jul
S-.lul













9-Jul



21.8

0.1

2.1



10-Jul



0

0

24



11-Jul



0

0

24



12-Jul



0

0

24



13-Jul



8.3

0.2

15.5



14-Jul



24

0

0



15-Jul

1

10.8

0.1

13.1



16-Jul



13

1.8

9.2



17-Jul



24

0

0



18-Jul



24

0

0



19-Jul



24

0

0



20-Jul



24

0

0



21-Jul



24

0

0



22-Jul

1

12.9

0.1

11



23-Jul



0

0

24



24-Jul



0

0

24

(continued)

3-9


-------
Table 3-4 (continued)

Engine

Date

Number of

Operational Data (Hrs)





Shutdowns

Running

Scheduled
Downtime for
Maintenance, etc.

Idle



25-Jul



0

0

24



26-Jul



0

0

24



27-Jul



0

0

24



2S-.I ii 1











2<>-.lul











'ii-.liil









TOTAL

5

356.2

19.4

536.4

Note: Gray areas represent sampling conducted by the Center.

CASE 1 (no change in shutdown/idle mode; i.e., pressurized shutdown/idle continues):

•	Rod seal savings while idle:

Description: Rod packing emissions that are reduced by the France packing during idle periods
Calculation: Idle hours*(Control Rod emission factor - Test Rod emission factor)

•	Rod seal losses due to emissions increases while running:

Description: Rod packing emissions increases caused by the France packing during operation
Calculation: Running hours *(Control Rod emission factor - Test Rod emission factor)

CASE 2 (change from depressurize/blowdown mode to a pressurized mode):

•	Rod seal increases while idle:

Description: Idle-mode rod packing emissions from France packing (with new pressurized
shutdown/idle mode, these emissions must now be added)

Calculation: Idle hours* (Test Rod emission factor)

•	Rod seal losses due to emissions increases while running: same as in Case 1

•	Blowdown volume savings:

Description: Gas contained in the compressor and piping released during shutdown (with new
pressurized shutdown/idle mode, these emissions are no longer released)

Calculation: Number of shutdowns* (blow down volume emission factor)

•	Blowdown valve leak losses:

Description: Gas released from the closed blowdown valve (with new pressurized shutdown/idle mode,
these emissions must now be added)

Calculation: Idle hours* (blow down valve emission factor)

•	Unit valve leak savings:

Description: Gas released from the closed unit valves (with new pressurized shutdown/idle mode, these

emissions are no longer released)

Calculation: Idle hours *(unit valve emission factor)

•	PRV and miscellaneous component losses

Description: Gas released from the pressure relief valve and miscellaneous fugitive sources (with new

pressurized shutdown/idle mode, these emissions must now be added)

Calculation: Idle hours*(PRV + Miscellaneous components' emission factors = 0)

3-10


-------
Table 3-5. Overall Average Emission Factors (scfm gas)

Control Rod aie

0.94

Test Rod idle

1.23

Control Rod running

0.99

Test Rod running

1.04

Blowdown Volume

7,900 / shutdown

Blowdown Valve

0.08

Unit Valve

12.14

PRV and Misc. Components

0

Table 3-6 presents the gas savings measured and calculated for Case 1 and Case 2. The
definitions presented above correspond to specific columns in the table. There are significant
differences in gas savings between Engines 501 and 502, but these differences are driven
primarily by differences in the number of idle hours that occurred during Phase I. Total natural
gas savings for both engines under Case 1 were calculated to be -18,224 +29,987 scf of natural
gas (an overall loss). These gas losses occurred because the France packing did not reduce
emissions during idle mode. Total gas savings for both engines under Case 2 were calculated to
be 651,261 + 47,775 scf of natural gas. It should be noted that these savings are not due to the
Emissions Packing; rather, the change in operating characteristics provided the added savings.
Elimination of the unit valve emissions was the primary factor contributing to the gas savings that
occurred in Case 2.

From a greenhouse gas emissions standpoint, the natural gas savings and losses cited above were
converted into methane emissions/losses. This was done using natural gas compositional data
routinely measured by ANR pipeline (see Section 2.3.2.3). An average 97.09 percent methane
composition was measured during the Phase I test period by ANR and, based on this value, total
methane reductions (savings) and increases were calculated as follows

Case 1: 7,594 and 10,099 scf methane increase for Engines 501 and 502, respectively
Case 2: 256,587 and 375,723 scf methane decrease for Engines 501 and 502, respectively

Again, the methane reductions for Case 2 occurred as a result of the shutdown/idle process
change assumed there; not the performance of the France packing.

3.4 INSTALLATION REQUIREMENTS

Installation of the France packing system was completed in 2 days. Based on interviews
conducted with site operators, this is the same amount of time required to install conventional
packing. Thus, the incremental installation costs for the France packing is zero. On a per-rod
basis, the capital cost was $3,426.42, and the installation required 27 labor-hours.

3-11


-------
Table 3-6. Case 1 and Case 2 Gas Savings (scf natural gas)

Engine

Date

CASE 1

CASE 2





Rod Seal

Rod Seal Loss

Total

Rod Seal

Rod Seal Loss

Blowdown

Blowdown

Unit Valve

PRV and

Total





Savings While

Due to Increase

Savings

Increase

Due to Increase

Valve

Valve Leak

Leak Savings

Misc. Comp.

Savings





Idle

While Running



While Idle

While Running

Savings

Loss



Loss



501

16-.I	mi

17-J	nil

i i

()

I 1

I 1

()

()

()

()

()

()



I i

()

I 1

I 1

()

()

()

()

()

()



18-Jun

-245

-30

-275

-1,041

-30

0

-68

10,270

0

9,132



19-Jun

0

-72

-72

0

-72

0

0

0

0

-72



20-Jun

0

-72

-72

0

-72

0

0

0

0

-72



21-Jim

0

-72

-72

0

-72

0

0

0

0

-72



22-Jun

0

-72

-72

0

-72

0

0

0

0

-72



23-Jim

0

-72

-72

0

-72

0

0

0

0

-72



24-Jun

0

-72

-72

0

-72

0

0

0

0

-72



25-Jim

0

-72

-72

0

-72

0

0

0

0

-72



26-Jun

0

-72

-72

0

-72

0

0

0

0

-72



27-Jun

0

-72

-72

0

-72

0

0

0

0

-72



28-Jun

0

-61

-61

0

-61

0

0

0

0

-61



29-Jun

0

-72

-72

0

-72

0

0

0

0

-72



30-Jun

0

-72

-72

0

-72

0

0

0

0

-72



1-Jul

0

-72

-72

0

-72

0

0

0

0

-72



2-Jul

0

-72

-72

0

-72

0

0

0

0

-72



3-Jul

0

-72

-72

0

-72

0

0

0

0

-72



4-Jul

-287

-22

-309

-1,218

-22

7,900

-79

12,019

0

18,600



5-Jul

-341

-13

-354

-1,446

-13

0

-94

14,277

0

12,723



6-Jul

0

-72

-72

0

-72

0

0

0

0

-72



7-J nl

I 1

()

i i

i i

()

()

()

()

()

()

(continued)

3-12


-------
Table 3-6 (continued)

Engine

Date

CASE 1

CASE 2





Rod Seal

Rod Seal Loss

Total

Rod Seal

Rod Seal Loss

Blowdown

Blowdown

Unit Valve

PRV and

Total





Savings While

Due to Increase

Savings

Increase

Due to Increase

Valve

Valve Leak

Leak Savings

Misc. Comp.

Savings





Idle

While Running



While Idle

While Running

Savings

Loss



Loss





8-Jul

()

()

i i

()

()

()

()

()

()

()



9-Jul

0

-72

-72

0

-72

0

0

0

0

-72



10-Jul

0

-47

-47

0

-47

0

0

0

0

-47



11-Jul

-122

0

-122

-517

0

7,900

-34

5,099

0

12,449



12-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



13-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



14-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



15-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



16-Jul

-188

-19

-207

-797

-19

0

-52

7,867

0

6,999



17-Jul

0

0

0

0

0

0

0

0

0

0



18-Jul

0

0

0

0

0

0

0

0

0

0



19-Jul

-284

0

-284

-1,203

0

7,900

-78

11,873

0

18,492



20-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



21-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



22-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



23-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



24-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



25-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



26-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



27-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



2 8-Jul
20-Jul
30-J ul

()

()

I 1

()

()

()

()

()

()

()



()

()

I 1

()

()

()

()

()

()

()



()

()

i i

()

()

o

()

()

()

()

TOTAL

rs

-1,344





-1,344

23 ~MM

-l,"s"

271,183

1 1

264,277

(continued)

3-13


-------
Table 3-6 (continued)

Engine

Date

CASE 1

CASE 2





Rod Seal

Rod Seal Loss

Total

Rod Seal

Rod Seal Loss

Blowdown

Blowdown

Unit Valve

PRV and

Total





Savings While

Due to Increase

Savings

Increase

Due to Increase

Valve

Valve Leak

Leak Savings

Misc. Comp.

Savings





Idle

While Running



While Idle

While Running

Savings

Loss



Loss



502

16-.I	un

17-J	un

I 1

()

"

i i

()

()

()

()

()

()



I 1

()

i i

i i

()

()

()

()

()

()



18-Jun

-405

-2

-408

-1,720

-2

7,900

-112

16,972

0

23,038



19-Jun

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



20-Jun

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



21-Jun

-397

0

-397

-1,683

0

0

-109

16,608

0

14,815



22-Jun

-151

-28

-180

-642

-28

0

-42

6,337

0

5,625



23-Jun

-94

-56

-149

-399

-56

7,900

-26

3,933

0

11,353



24-Jun

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



25-Jun

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



26-Jun

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



27-Jun

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



28-Jun

-259

0

-259

-1,100

0

0

-72

10,853

0

9,682



29-Jun

-231

-31

-263

-982

-31

0

-64

9,688

0

8,611



30-Jun

0

-72

-72

0

-72

0

0

0

0

-72



1-Jul

0

-72

-72

0

-72

0

0

0

0

-72



2-Jul

0

-72

-72

0

-72

0

0

0

0

-72



3-Jul

0

-72

-72

0

-72

0

0

0

0

-72



4-Jul

-235

-31

-266

-996

-31

7,900

-65

9,833

0

16,641



5-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



6-Jnl

7-J	nl

8-J	nl

-411

o

-411

-1.742

o

o

-113

17.190

o

15.335



I 1

()

i i

i i

()

o

()

()

()

()



I 1

()

i i

i i

()

o

()

()

()

()



9-Jul

-37

-65

-102

-155

-65

0

-10

1,530

0

1,299



10-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



11-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595

(continued)

3-14


-------
Table 3-6 (continued)

Engine

Date

CASE 1

CASE 2

Rod Seal
Savings While
Idle

Rod Seal Loss
Due to Increase
While Running

Total
Savings

Rod Seal
Increase
While Idle

Rod Seal Loss
Due to Increase
While Running

Blowdown
Valve
Savings

Blowdown
Valve Leak
Loss

Unit Valve
Leak Savings

PRV and
Misc. Comp.
Loss

Total
Savings



12-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



13-Jul

-270

-25

-295

-1,144

-25

0

-74

11,290

0

10,047



14-Jul

0

-72

-72

0

-72

0

0

0

0

-72



15-Jul

-228

-32

-260

-967

-32

7,900

-63

9,542

0

16,380



16-Jul

-160

-39

-199

-679

-39

0

-44

6,701

0

5,939



17-Jul

0

-72

-72

0

-72

0

0

0

0

-72



18-Jul

0

-72

-72

0

-72

0

0

0

0

-72



19-Jul

0

-72

-72

0

-72

0

0

0

0

-72



20-Jul

0

-72

-72

0

-72

0

0

0

0

-72



21-Jul

0

-72

-72

0

-72

0

0

0

0

-72



22-Jul

-191

-39

-230

-812

-39

7,900

-53

8,012

0

15,009



23-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



24-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



25-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



26-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



27-Jul

-418

0

-418

-1,771

0

0

-115

17,482

0

15,595



28-.I	ul

29-Jul

30-Jul

i i

o

I 1

I 1

o

0

()

o

o

()



i i

()

I 1

I 1

()

()

()

()

()

()



i i

()

i i

i i

()

o

()

()

()

()

TOTAL



-1 069

-10,402

-3^',5S'j

-1,069

39,500

-? -S7S

390,714

0

386,984

Note: Gray areas represent sampling conducted by the Center.

3-15


-------
4.0 DATA QUALITY

4.1	BACKGROUND

Information on data quality is used to characterize the level of uncertainty in measured values and
verification parameters. The process of establishing data quality objectives starts with
determining the desired level of confidence in the primary verification parameters. A primary
parameter for Phase I was the establishment of idle-mode gas savings for the France packing.
These gas savings are used to help quantify the primary Phase II verification parameter, the
France packing payback period. The data quality objective that was established for the payback
period defines the quality goals for all measured parameters. It is based on input from gas
industry and other Stakeholder Group members, and allows for an error in payback values of
about +3 to 4 months. This goal was used to set data quality goals for the following key
measured values: rod packing emissions, valve emissions (unit, blowdown, and pressure relief
valves), miscellaneous source emissions, and natural gas quality measurements. This section
identifies these goals and discusses how they affect the Phase I verification results.

During the Phase I evaluation, field and laboratory measurements were collected in an effort to
quantify uncertainty in the measured values identified above. For example, the accuracy and
precision of the flow tube measurement was quantified with frequent calibrations and replicate
samples, and these data were used to quantify uncertainty in the packing emissions rates
presented in Section 3. These calibrations and replicate samples, along with accuracy and
precision data provided by instrument vendors, were used to quantify uncertainty in the key Phase
I verification parameter, natural gas savings. As a practical matter, one limitation on the quality
and representativeness of the measurements collected is their relative infrequency. Although the
level of uncertainty is associated with measurement frequency, it was addressed by repeating all
measurements on three separate occasions. On each occasion, measurements were collected at
least twice, and each result represented numerous individual quantifications.

4.2	ROD PACKING EMISSION RATE MEASUREMENTS

The MEM Rangemaster flow meters originally planned for use on the doghouse vents did not
function properly in the field. As a result, a decision was made to replace these meters with the
manual Flow Tube measurements. Based on manufacturer supplied performance data for the
MEM meters, the maximum error anticipated was +2 percent of the instrument's full-scale
reading. An error of 5 percent would have allowed the achievement of the data quality objectives
set for the payback period and, considering the magnitude of the average emission rates measured
at the site, the MEM meter may have resulted in an error of about 6 percent. Calibration data
collected on the Flow Tube suggest that the error associated emission rates measured at the site
were low, exceeding the original performance goal for the MEM meters.

Table 4-1 presents Phase I calibration results for the Flow Tube, and shows the accuracy values
developed from these data. The Flow Tube was calibrated against a laminar flow element (LFE),
which itself was calibrated against a NIST-traceable primary standard (r2 values ranged between
0.9975 and 0.9995). The run-average Flow Tube accuracy values presented were calculated by
averaging the accuracy values for each individual measurement in a run. Individual measurement
accuracy values were calculated by determining the differences between the Flow Tube and LFE

4-1


-------
flow rates (flow tube minus LFE), dividing this value by the LFE flow rate, and then
multiplying by 100. As the table shows, the

Table 4-1. Flow Tube Calibration Results (Low Flows)

Date

Run

Flow Tube

Flow Tube Methane

LFE Pressure

LFE Methane

Flow Tube





Velocity, fpm

Flow Rate, scfm

Drop, in. HjO

Flow Rate, scfm

Accuracy," %

6/2/99

1

102

0.29

0.98

0.34







238

0.70

2.00

0.69







484

1.44

4.05

1.41







711

2.12

6.05

2.10







905

2.70

8.00

2.78













Run Average

-2.5

6/2/99

2

101

0.30

0.98

0.34







236

0.70

2.00

0.69







486

1.45

4.05

1.41







712

2.13

6.05

2.10







908

2.72

8.00

2.78













Run Average

-1.9

7/2/99

1

113

0.32

1.02

0.35







202

0.70

2.03

0.71







368

1.41

4.03

1.40







528

2.10

6.02

2.09







683

2.77

8.05

2.80







843

3.45

10.1

3.52













Run Average

-2.3

7/2/99

2

103

0.30

1.04

0.36







203

0.72

2.05

0.71







370

1.42

3.98

1.38







535

2.11

6.01

2.09







694

2.78

8.04

2.81







850

3.44

10.05

3.51













Run Average

-2.7

7/23/99

1

110

0.27

0.92

0.32







230

0.72

2.00

0.70







427

1.45

4.01

1.41







608

2.12

6.01

2.12







784

2.77

7.98

2.82













Run Average

-2.5

7/23/99

2

107

0.30

1.02

0.36







225

0.72

1.99

0.70







427

1.45

4.01

1.41







612

2.12

5.99

2.12







791

2.76

7.96

2.83













Run Average

-2.7

a Rounding errors may prevent the reader from calculating the exact run average percentages using the concentration

data presented in the table.









4-2


-------
average accuracy of the Flow Tube ranged from -1.9 to -2.7 percent of the value measured by the
LFE (overall average of -2.4 percent). The instrument provided acceptable readings across the
flow range represented in Table 4-1, but a relatively consistent negative bias was observed at low
flow rates. Specifically, at flows less than about 0.3 scfm, a negative bias (between -11 and -17
percent) was observed for all calibration runs. Fortunately, there were no field measurements
collected in this flow regime. In the regime where most measurements were collected (between
0.5 and 3 scfm), the overall average Flow Tube accuracy was 0.4 percent. This value is used to
determine the level of actual uncertainty in the net gas savings values described in Section 4.4.

Precision and/or repeatability were assessed by conducting replicate calibrations. The calibrations
conducted on 6/2/99 represent the only set of calibration replicates where the reference flow rates
(i.e., the LFE flow rates) were precisely duplicated for both runs. In the other calibrations, the
duplication of flow conditions was close, but not exact. Figure 4-1 presents a plot of the
calibration results collected on 6/2/99. The two lines plot the difference between the Flow Tube
flow rates and LFE rates divided by the LFE rates. These values are plotted for each of the five
flow rate conditions examined, so if the Flow Tube values were 100 percent repeatable at all flow
conditions, only one line would be visible. In this case, repeatability is not exact but is acceptable
at all calibration flow conditions. Overall Flow Tube repeatability was calculated for 6/2/99 by:
calculating the average difference between the two Flow Tube rates measured for each of two
runs at the five flow conditions; dividing this value by the average reference concentration across
all flow conditions; and multiplying by 100. This value, calculated to be -0.54 percent, is a
measure of the degree of Flow Tube variability observed relative to the actual or reference flow.
The trends observed in the 6/2/99 data were apparent in plots of all calibration results collected.

Figure 4-1. Flow Tube Repeatability (6/2/99)

LLI
U_

—I

LU

LL. —~

-> E

0) o
¦° 

5
o

0.05

0.00

-0.05

-0.10

-0.15

Flow Condition (1 = lowest flow)

Gas savings for the rod packing are determined as the difference between the packing emission
rates measured on the Test and Control Rods. Thus, the total error in the difference is the sum of
the absolute errors in each measurement. This principle, along with the average accuracy value
of 0.4 percent described earlier, is used to determine potential levels of error in net gas savings
values presented in Section 3. This overall error is presented in Section 4.4.

4-3


-------
Finally, the original completeness goal for rod packing emissions measurements required the
completion of 15 sets of measurements. As discussed in Section 3, 14 complete sets of
measurements were collected.

4.3 OTHER MEASUREMENTS

4.3.1 Unit Valve, Blowdown Valve, and Pressure Relief Valve

Measurement of the leak rates for the blowdown valve, pressure relief valve, and unit valves were
made using different calibrated instruments. QA results associated with each of these
measurements are described below. Data quality considerations for the estimated blowdown
volume are also discussed.

The pressure relief and unit valves were measured using the Flow Tube discussed earlier.
Because flow was not detected for any pressure relief valves, QA and calibration data are not
presented for them. For the unit valve, the Flow Tube calibration data presented in Section 4.2
are applicable to the few low flow rate measurements collected on this device. In most cases,
flow rates were higher, and a high flow calibration chart was developed and used after the field
study was completed to convert measured gas velocities into natural gas flow rates. The same
Flow Tube calibration procedure described for the rod packing vent measurements was followed
here, and the calibration data developed are presented in Table 4-2 (Note: it was not feasible to
simulate gas flows greater than 8 scfm in the laboratory). A calibration chart, similar to the Flow
Tube calibration chart presented in Section 2 for the rod packing vent measurements, is shown in
Figure 4-2. The Flow Tube accuracy at high flow rate regimes was found to perform as good as
or better than the accuracy observed at lower flow regimes. Figure 4-2 clearly shows that the
natural gas flow rate is linearly proportional to the gas velocity measured with the Flow Tube (at
both high and low flow rate regimes). For this reason, the equation shown in the figure was used
to extrapolate the calibration data, and estimate gas flow rates at higher velocity readings. The
accuracy and precision of the Flow Tube in high flow rate regimes approximated those at lower
flow rate regimes.

Table 4-2. Flow Tube Calibration Results (High Flows)

Date

Run

Flow Tube

Flow Tube Methane

LFE Pressure

LFE Methane

Flow Tube





Velocity, fpm

Flow Rate, scfm

Drop, in. HjO

Flow Rate, scfm

Accuracy, %

8/11/99

l

674

2.08

0.25

2.14







1150

3.55

0.41

3.55







1433

4.43

0.50

4.36







1881

5.82

0.65

5.72







2351

7.28

0.81

7.23







2416

7.48

0.85

7.39













Run Average

-0.1

8/11/99

2

179

0.06

0.07

0.60







725

2.19

0.25

2.15







1207

3.58

0.41

3.54







1458

4.31

0.50

4.34







1928

5.67

0.65

5.70







2286

6.71

0.75

6.61













Run Average

0.7

4-4


-------
Figure 4-2. Flow Tube Calibration at High Flows (8/11/99)

Gas Velocity (fpm)

The Flow Tube was originally planned for use on the blowdown valve as well. However, early
field results suggested that the flow rates from the blowdown valve were very low, and Flow
Tube calibrations suggested that performance was poor in this regime (i.e., there is no response).
Therefore, a low flow rate rotameter was used to conduct measurements on the blowdown valve.
The calibration results for this device are presented in Table 4-3. The original accuracy goals for
this measured parameter are also shown for comparison.



Table 4-3.

Rotameter Calibration Results





Measurement

Calibration



Range

Accuracy

Precision

Instrument Used

Date



Goal

Actual

Goal

Actual

Rotameter
(Dwyer VB Series)

8/9

0 to 1000
mL/min

3

1.38

3

-0.73

For the miscellaneous components such as flanges and valve stems, it was not possible to
effectively channel the leaking gas to the flow tube. For these types of fugitive sources, soap-
screening was used to identify significant leaks, and when flow rate determination was needed,
EPA's protocol tent/bag method was planned for use. Because significant leaks were not found,

4-5


-------
the tent/bag method was not applied. The data quality information for this method is not
presented.

The average accuracy values presented here are used later in Section 4.4 to assess how these
measured values may contribute to overall uncertainty in the natural gas savings estimated for
Case 1 and Case 2.

4.3.2	Gas Composition

Based on average gas compositional data supplied by ANR, the average methane concentration in
the natural gas was determined to be 97.09 percent. The accuracy of these readings was
determined to be 0.12 percent

4.3.3	Blowdown Volume

Blowdown volume was quantified based on the volume of piping and manifolds in the
compressor system, and is accurate to within the piping specifications (assumed to be 100 percent
accurate). The unit pressure, which was measured at the station by ANR engine monitors, was
used to convert the calculated volume into a volume of natural gas at standard conditions.
Generally, the host site operated at about 600 psig suction pressure. Unfortunately, calibration
records for the pressure monitor were not made available by ANR, so accuracy estimates for this
measured parameter could not be determined. However, the accuracy of the pressure sensor was
not required because blowdown volume was calculated based on a typical suction pressure of 600
psig.

4.4 OVERALL UNCERTIANTY IN THE MEASUREMENTS, NET GAS SAVINGS,
AND METHANE EMISSIONS VALUES

Calibrations were conducted by the Center on most of the instruments used in this verification.
These data are summarized in Table 4-4. In a few cases, performance data supplied by either the
instrument vendor or ANR Pipeline were used. These data are also presented in Table 4-4.

Table 4-4. Summary of Instrument Performance Data

Measurement
Instrument Used

Applicable Source

Source of
Performance Data

Accuracy
(%)

Precision
(%)

Flow Tube

Doghouse Vents

The Center

-2.4 (0.4)a

-0.54

Pressure Relief Valve Leaks

The Center

-2.4

-0.54

Unit Valve Leaks

The Center

+ 0.31

+ 1.37

Rotameter

Blowdown Valve Leaks

The Center

+ 1.38

-0.73

Gas Chromatograph

All (convert natural gas
emissions into methane
emissions)

ANR Pipeline

0.12

not
available

Hydrocarbon
Analyzer

Pressure Relief Valve Misc.
Components

The Center

1.5

0.5

a The value in parentheses represents the accuracy at flow regimes encountered in the field. It was used to assess
uncertainty in net gas savings values as described below.

4-6


-------
The measurement accuracy values presented above were used to calculate how measurement
error might propagate through the calculation process used to determine net gas savings and
methane emissions for the France packing. Based on these calculations, uncertainty or potential
error in the net gas savings and methane emissions values due to instrumentation is estimated to
be +5 percent for Case 1. For Case 2, more individual measurements were collected, and a
greater opportunity for error existed. In this case, the overall uncertainty or potential error due to
measurements instruments is estimated to be +8 percent.

It should be noted that the estimated errors above represent uncertainty introduced by the
measurements methods used. They do not include uncertainty or bias that could be introduced
into the results attributable to: differences in the host sites design or operating characteristics
relative to other sites; the frequency of measurements conducted; and environmental, diurnal,
geographic, or other potential biasing factors. The Center conducted this evaluation over a 4-
week period, and collected several separate measurements data sets, in an effort to address some
of these potentially biasing factors. Based on the Student's t distribution analysis shown earlier in
Section 3, it is clear that process variability is introducing errors that are greater than the
instrument errors. The Center is investigating more sensitive instruments that may be able to
detect some of this variability. It is expected that some level of process variability may still exist
and may not be addressed with the measurement scheme used in this verification.

4-7


-------
5.0 REFERENCES

ANSI/ASQC E4-1994. Specifications and Guidelines for Quality Systems for Environmental
Data Collection and Environmental Technology Programs, American Society for Quality,
Milwaukee, WI.

GRI 1997. Documentation of Existing Rod Packing Technology and Emissions. GRI-97/0393,
Gas Research Institute, Chicago, IL, December 1997.

Harrison, Matthew R., Lisa M. Campbell, Theresa M. Shires, and R. Michael Cowgill 1996.
Methane Emissions from the Natural Gas Industry, Volume 2: Technical Report, EPA-600/R-96-
080b (NTIS PB97-142939). U.S. Environmental Protection Agency, National Risk Management
Research Laboratory, Research Triangle Park, NC, June 1996.

Hummel, Kirk E., Lisa M. Campbell, and Matthew R. Harrison 1996. Methane Emissions from
the Natural Gas Industry, Volume 8: Equipment Leaks, EPA-600/R-96-080h (NTIS PB97-
142996). U.S. Environmental Protection Agency, National Risk Management Research
Laboratory, Research Triangle Park, NC. June 1996.

Shires, Theresa M. and Matthew R. Harrison 1996. Methane Emissions from the Natural Gas
Industry, Volume 7: Blow and Purge Activities. EPA-600/R-96-080g (NTIS PB97-142988). U.S.
Environmental Protection Agency, National Risk Management Research Laboratory, Research
Triangle Park, NC. June 1996.

SRI 1999. Testing and Quality Assurance Plan for the France Compressor Products Emissions
Packing, SRI/USEPA-QAP03, Greenhouse Gas Technology Verification Center, Southern
Research Institute, Research Triangle Park, NC, July 1999.

5-1


-------