Community Update #15
Pompton Lakes Study Area
Pompton Lakes, New Jersey

Upland Soil Areas Excavation/Dredging

Community Update	August /September 2016

This is EPA's fifteenth update to inform the community of the pro-
gress of activities related to that portion of the Pompton Lakes Study
Area known as the Upland Soil Areas. (Fig. U-l) as well as the are-
as of the lake designated Area A and the Island Area, approximately
3 acres that will be subject to mechanical dredging (Fig. 1). The
project site for this phase includes Rotary Park, the woodlands adja-
cent to and west of Rotary Park that includes Acid Brook (south of
Lakeside Ave) and, the area along the south side of Lakeside Ave-
nue moving east to Lakeside Ave. Park as well as Area A and the
Island Area (see figures). The project continues to be on schedule.

ACTIVITIES—WEEK OF AUGUST 29TH

~	Transported/disposed of 489 loads of impacted material as of
September 1st—unchanged from the prior week

~	Evaluation to determine most effective method to excavate Up-
lands Soil Area A1 (a small area of approx. 20 cubic yards),
which is constrained by a sewer line

~	Fish relocation in scow access channel area completed

~	Mechanical dredging of scow access channel has begun

~	Initiate processing of dredged sediment

~	Continued perimeter monitoring—data on website (http://
www.pomptonlakesworks.com/pompton-lake-project/
environmental-monitoring/

~	No exceedances of dust/ mercury vapor/turbidity action levels
during monitoring associated with site activities

UPCOMING ACTIVITIES—WEEK OF SEPTEMBER 5TH

~	Continue mechanical dredging of scow access channel and pro-
cessing/loading/off-site disposal of dredged sediment

~	Complete load-out/off-site disposal of impacted soil except for
Area A1—awaiting disposal facility approval

~	Continued perimeter monitoring of dust/mercury/turbidity levels

ADDITIONAL NOTES:

~	With the upcoming start of the school year and the initiation of
processing/load-out/off-site disposal of impacted dredged sedi-
ment; traffic control measures will continue including no truck
traffic entering/leaving the site at the start and end of the school
day

~	Enjoy Pompton Day! Have a happy and safe holiday weekend!

www3.epa.gov/region02/waste/dupont_pompton/index.html

EPA CLEANUP ACTIVITIES

Basic Site Information

This phase of work includes excava-
tion of approximately 3,160 cubic
yards (CY) of impacted soil contain-
ing mercury, lead and other metals
as well as the mechanical dredging
of approximately 19,300 CY of
impacted sediment in Area A and
the Island Area.

Work is being performed by Seven-
son Environmental Services, Inc., a
contractor for The Chemours Com-
pany FC, LLC (Chemours) with
EPA/NJDEP oversight.

Boroiiph of Pompton Lakes

http: //www .pomptonlake sgov .com

Questions? Please Contact:
EPA Remedial Project Manager

Perry Katz

(212) 637-4426
katz.ira-perry@epa.gov

EPA Community Involvement
Coordinator

Pat Seppi

(646) 369-0068

seppi .pat@epa.gov


-------