oEPA

United States
Environmental Protection
Agency

Informational meeting

EPA is holding a public meeting
Thursday, Feb. 26, so you can learn
more about the latest developments
in the Kalamazoo River cleanup.

The meeting will be at 6:30 p.m.
at the Comfort Inn and Conference
Center, 622 Allegan St., Plainwell,
Mich.

EPA representatives and other
officials will make a formal
presentation and be available
to discuss site activities with
you individually. If you need
special accommodations, contact
EPA Community Involvement
Coordinator Don de Blasio (see
below) by Feb. 19.

Contact EPA

For more information, or if you have
comments about the Kalamazoo
River cleanup, contact:

Don de Blasio

Community Involvement Coordinator
EPA Region 5 (SI-7J )

77 W. Jackson Blvd.

Chicago, IL 60604-3590
312-886-4360 or 800-621-8431,
Ext. 4360,

weekdays 9:30 a.m. to 5:30 p.m.
deblasio .don@epa.gov

For more information

You can read more information about
the Kalamazoo River cleanup online

at: www.epa.gov/region5/sites/
kalproject

Plainwell PCB Cleanup Progress,
Updates, and Public Meeting

Allied Paper/Portage Creek/Kalamazoo River Superfund Site
Kalamazoo, Michigan	February 2009

Cleanup work to remove PCB-contaminated sediment (mud) from the
Kalamazoo River's Plainwell Impoundment is almost complete. This is
the second year of an estimated 2-year project that has removed nearly
129,000 cubic yards of sediment containing about 4,700 pounds of PCBs.
Contractors hired by the responsible parties, Millennium Holdings LLC and
Georgia-Pacific LLC, are performing the cleanup work.

PCBs, or polychlorinated biphenyls, are chemical compounds with common
industrial uses. At high concentrations and exposures they can cause illness
in humans and wildlife.

In 2007, more than 37,000 cubic yards, or 1,059 truckloads of PCB-
contaminated mud were removed from the river and nearby banks.

In 2008 and 2009, workers removed sediment and restored banks along
6,500 feet of river bank including areas 9A and B, 10A and B, 11A and B,
12A and B, and 13A and B (see map on Page 3). Work has been completed
on mid-channel areas A, B and C, and removal of the Phase 1 and Phase 2
cofferdams. For the year, 89,600 cubic yards, or 2,560 truckloads of PCB-
contaminated mud have been removed. The water control structure, which
was constructed during Phase 1, has been removed, allowing the Kalamazoo
River to flow freely through the new western channel, past what was once
the Plainwell Dam.

PCB-contaminated mud that was removed as part of the cleanup was
sent off-site to commercial landfills for disposal. Prior to disposal, the
contaminated mud was divided into sediment containing 50 parts per
million (ppm) or more of PCBs, and sediment containing lower than 50
ppm concentrations. One ppm can be visualized as four drops of ink mixed
thoroughly in a 5 5-gallon barrel of water. About 17,920 cubic yards of
sediment with PCBs above the 50 ppm level were sent to Environmental
Quality Company's Wayne Disposal Landfill in Belleville, Mich. About
71,680 cubic yards of sediment with PBC concentrations less than 50 ppm,
which is considered non-hazardous waste, were sent to Allied Waste's C
and C Landfill near Marshall, Mich., and the Ottawa Farms Landfill near
Coopersville, Mich.

U.S. Environmental Protection Agency Region 5 and state partner Michigan
Department of Environmental Quality will oversee the remaining restoration
activities for the Plainwell Impoundment, which are scheduled to resume in
the spring. The estimated cost of the project is $30 million. Site information,
including new photos, is posted at www.epa.gov/region5/sites/kalproject.

In addition to the cleanup at the Plainwell Impoundment, cleanups on other
Kalamazoo River site areas are occurring.


-------
Kalamazoo River/Portage Creek
Supplemental cleanup studies

A February 2007 legal agreement required additional
study of other portions of the Kalamazoo River and
Portage Creek site (Phase 2). Planners divided the river
into seven areas for the additional investigation. Area 1
consists of the Kalamazoo River between Morrow Dam
and Plainwell, and Portage Creek between Cork Street
and the Kalamazoo River.

Although previous sampling (Phase 1) occurred in Area
1, Phase 2 focuses on areas where little data exists and/or
where data suggests some previous contamination, but the
extent is not known. Representatives of EPA, MDEQ and
the Kalamazoo River Study Group are working together
to determine what further sampling may be necessary.

Phase 2 investigations are under way and included
collecting 40 sediment cores along Portage Creek, 30
cores along the Kalamazoo River between the former
Georgia-Pacific Mill and Crown Vantage Landfill, and
60 cores along the Kalamazoo River from the Plainwell
Number 2 Dam Area. The cores were segregated and
analyzed for PCBs to determine the extent of any
contamination in these areas.

Any remaining Phase 2 work will be conducted this
winter, and based on those sampling results, Phase 3
sampling will occur in Area 1 in the spring and summer.

Ecological peer review final report

On Dec. 8, the ecological peer review panel issued its final
report. This report addressed the quality and relevance
of environmental studies conducted by Michigan State
University researchers. These studies near the Kalamazoo
River site evaluated risks to wildlife for potential use in
supporting cleanup decisions at the site. The peer review
panel operated independently, reviewing the Michigan
State University studies and evaluating questions developed
by EPA, MDEQ, Kalamazoo River Study Group and the
Natural Resource Trustees.

The results of the peer review panel report and its
implications are being evaluated by EPA, the Kalamazoo
River Study Group and MDEQ.

Expedited cleanup activities

EPA has continued discussions with Georgia Pacific for
a possible cleanup near the Plainwell Number 2 Dam in
Area 1 of the Kalamazoo River. This area was a focus
of recent contamination studies. EPA is evaluating the
study data and determining the scope of work, which
could begin this year. However, the recent Millennium
bankruptcy filing could affect this project (see below).

An expedited cleanup plan developed by the Kalamazoo
River Study Group in August 2008 also proposed
additional cleanup work in other Kalamazoo River
downstream areas during the next 12 years. The recent
Millennium bankruptcy filing could affect this project.
EPA will discuss future plans with Georgia-Pacific,
MDEQ, trustees and the stakeholders as more information
becomes available.

Mill updates

Plainwell Mill

Approximately 4,750 tons of contaminated material,
removed as part of an emergency action, was taken off-
site for disposal. Test pits were also dug between the
mill and the river as part of the investigation into the oily
sheen observed during the emergency action. Shallow
wells were installed and were sampled as part of the first
phase of the investigation at the mill, and EPA is awaiting
the analytical results. Weyerhaeuser, EPA and MDEQ will
discuss the second phase of the mill investigation and
determine a course of action.

Georgia-Pacific Kalamazoo and former
Hawthorne mills

Geoigia-Pacific has submitted its source investigation report
for EPA review. The report asserts the Georgia-Pacific
Kalamazoo and former Hawthorne mills are not a source
of PCBs into the Kalamazoo River, and should not be

An explanation of the recent Millennium bankruptcy filing

On Jan. 6, Lyondell Chemical Company and 79
affiliated debtors filed for bankruptcy under Chapter
11 reorganization. One of the debtors is Millennium
Holdings LLC, one of the responsible parties at the
Kalamazoo River site. The bankruptcy reorganization
process is typically a lengthy process (lasting from
months to possibly years) which allows a company
to restructure its finances through a reorganization
plan and discharge many of its pre-bankruptcy debts.
Under the Bankruptcy Code, claims are prioritized and
organized into classes and paid in accordance with the

bankruptcy priority scheme. Generally, higher priority
claims must be paid in full before any payment is made
to creditors holding lower priority claims. In addition,
reorganized companies may still be responsible for
their environmental liabilities following bankruptcy.
However, bankruptcy is intended to allow a company
a fresh start financially by eliminating many of its
pre-bankruptcy debts and liabilities. EPA is currently
evaluating options under bankruptcy and environmental
law to ensure that the cleanup of the Kalamazoo River
site continues.

2


-------
considered part of the site. EPA is reviewing the report, and
expects to make a decision in the spring.

Update for the landfills

12th Street Landfill

EPA is on schedule in its review of the cleanup plan.
Construction of the landfill cap will begin this summer.

Willow Boulevard/A-Site Landfill

EPA is still in negotiations to start the cleanup. The recent
Millennium bankruptcy may affect the start of this work.
However, EPA is developing a plan to keep the project
moving.

Allied Paper Landfill

EPA is studying cleanup alternatives. EPA has reviewed a
draft report that included a study of the underlying ground
water and a proposed schedule for submission of potential
cleanup alternatives.

Excavating soil in removal area 13A.

Map provided by Arcadis

• SHORELINE
j STAGING AREA
3 STAGING AREA - DEMOBILIZED
J REMOVAL AND REPLANTING COMPLETE
REMOVAL COMPLETE

TRUCK TRAFFIC:

	 REMOVAL AREA TO/FROM DISPOSAL AREA

3


-------
sjsqy. papAosjfo epeui jaded uo psfuud si fssqs pBf s/i/_[

sejepdfi ssejBojd dnueeio god ||3Mu;e|d

:311s QNndyadns yaAia oozviAiviv>i/>G3yo aoviaod/uadvd aamv

t?0909 II 'oBeomo
¦pAia uos>|OBp M LL
(rz-IS) uojSjAjQ puiapedns
g uojBey
AoueBv

ssvio isaid	uojps^ojd |eiu0Luuoj!AU3

S0;e;s pajjun

Vd3^?

Plainwell PCB Cleanup
Progress and Updates

Public Meeting
Thursday, Feb. 26
(details inside)


-------