Community Update for
^^7 I American Cyanamid
Superfund Site

Quarterly Update

Volume V, Winter 2013-2014

Introduction

The U.S. Environmental Protection Agency (EPA) is issuing this quarterly update to inform the community and
local officials about the status of the American Cyanamid Superfund Site (site) in Bridgewater Township, New
Jersey. This update will focus on major tasks completed at the site over the previous three (3) months, as well as
provide important notice(s) to anticipated future events. EPA, CRISIS (the recipient of an EPA technical
assistance grant) and the site owner (Wyeth Holdings LLC, a wholly-owned subsidiary of Pfizer, Inc.) provide
updated information on the site at the following web sites:

•	http://www.epa.gov/region02/superfund/npl/american cyanamid/

•	http://www.crisistoxicwatch.org

•	http://www.amcvrestoration.com

•	http://health.bridgewaterni.gov/

Site-wide Remedy Status

EPA issued a Record of Decision (ROD) in September 2012 to address contaminated soils, groundwater and
impoundments that have not been previously addressed, with the exception of impoundments 1 and 2. This
remedy, referred to as the site-wide remedy, called for the treatment via in-situ solidification/stabilization and/or
the installation of engineered capping systems to address three highly contaminated impoundments and all site
soils, as well as the collection and treatment of site-related contaminated groundwater. The remedy also called
for the completion of an ecological risk assessment to determine whether three additional impoundments would
require excavation and relocation. The remedial design of the site-wide remedy is currently underway and is
generally being addressed in two components: (1) impoundments and site-wide soils, and (2) groundwater. The
investigation of impoundments 13, 17 and 24 was completed in November 2013 and the results of the soil
sampling will be used to complete an ecological risk assessment for the three impoundments. Additional
treatability studies are currently being performed in support of the design of the site-wide groundwater
treatment facility to further evaluate technologies to achieve compliance with discharge limitations. It is
currently anticipated that the detailed design of these two remedial components will be completed by 2016.

Focused Feasibility Study for Impoundments 1 and 2

Due to the unique and highly complex nature of the contaminants within impoundments 1 and 2 and their
proximity to the Raritan River, these two impoundments were not included in the site-wide remedy and are
being addressed separately through a focused feasibility study (FFS). As part of the FFS, a pilot study is being
conducted on impoundments 1 and 2 to evaluate whether solidification/stabilization, thermal treatment, or a
combination of the two technologies can effectively treat the impoundment material. An information session
was held at the Bridgewater Township Municipal Complex in October 2013 to inform the community of the
details of the study and address community concerns. The operation of the pilot study is expected to begin in
February 2014 with the thermal treatment component and will be followed by the solidification/stabilization
component of the study. Continuous real-time air monitoring will be conducted throughout the 3-4 month
duration of the pilot study.


-------
Impoundments 1 and 2 Area Groundwater Removal Action

In May 2012, a groundwater collection and treatment system was completed under the oversight of EPA's
Removal Program to address groundwater discharges (i.e. seeps) into the Raritan River. This system includes a
collection trench to intercept and capture impacted groundwater, a containment wall to further prevent the
migration of impacted groundwater to surface water and an interim treatment plant to treat collected
groundwater prior to its discharge. Since the completion of the system, benzene concentrations in the Raritan
River have significantly decreased and have remained below the New Jersey surface water quality standard in
recent events, suggesting that the system is operating effectively. The interim treatment system, as well as new
groundwater inputs and bedrock groundwater currently conveyed to the local sewerage authority, will
eventually be incorporated into the site-wide remedy.

Ambient Air Monitoring

The site owner continues to implement a quarterly monitoring program for ambient air to use as a baseline
during the implementation of the site-wide remedy. The monitoring program includes eight locations along the
perimeter of the site and another four locations in the vicinity of impoundments 1 and 2. The results of the
recent quarterly monitoring events continued to exhibit concentrations consistent with urban background
monitoring stations measured by the New Jersey Department of Environmental Protection.

Surface Water and Sediment Monitoring

The site owner continues to implement a quarterly surface water and sediment monitoring program, which
includes an expansive analyte list with over 20 surface water and sediment monitoring stations located
throughout the Raritan River, Cuckel's Brook, the Millstone River, and Middle Brook. Benzene concentrations
in the Raritan River have continued to exhibit decreasing trends since the completion of a groundwater
collection and treatment system in May 2012. In the three most recent events, benzene has not been detected
above the New Jersey surface water quality standard in the Raritan River. Following the discovery of two seeps
in Cuckel's Brook containing elevated levels of volatile organic compounds, carbon bags were installed at the
discharge points to mitigate impacts to the brook. This interim measure was completed in August 2013 and will
remain in-place until the implementation of the groundwater component of the site-wide remedy. Surface water
and sediment monitoring will continue to be conducted on a quarterly basis.

Groundwater Monitoring

The site owner continues to implement a semi-annual groundwater monitoring program, which includes
monitoring of groundwater quality and the extraction of bedrock groundwater at a minimum rate of 650,000
gallons per day. The results of recent monitoring events are currently under EPA review and it is anticipated
that the results will be available in the next quarter.

Community Assessment

In November and December 2013, a site-wide community assessment was conducted by SKEO solutions, an
EPA contractor. The summary of this assessment can be found on EPA web site:
• http://www.epa.gov/region02/superfund/npl/american_cyanamid/

If you have any questions about the information in this quarterly update, please contact the EPA
community involvement coordinator, Melissa Dimas at dimas.melissa@epa.gov or 212-637-3677.

http://www.epa.gov/region02/superfund/npl/american_cyanamid/


-------