Second Five-Year Review Report

Cleburn Street Well Site
Grand Island, Nebraska

August 2008

Prepared by:

U.S. EPA Region 7
Kansas City, Kansas

Approved by:	Date:

.firtBS.

kDu

C ec||fe-^apki;-0(rec to;
SupemiadJDivisis

U.S. EPA Region 7




-------
Table of Contents

List of Abbreviations																			iv

Executive Summary									v

Five-Year Review Summary Form,									vi

Five-Year Review Summary Form, Cont'd									vii

Operable Units I and 2									.	vii

Operable Units 3 and 4																			vii

Operable Unit 5													viii

Overall Protectiveness					viii

I.	Introduction																			1

II.	Site Chronology..																 2

III.	Background			;		 3

Physical Characteristics,...														 3

Land and Resource Use												4

History of Contamination							 4

Initial Response																		 5

Basis for Taking Action......	.													6

IV.	Remedial Actions			7

Remedy Selection																		 7

Remedy Implementation														 8

System Operation and Maintenance						8

V.	Progress Since Last Five-Year Review									11

VI.	Five-Year Review Process..........														 13

Administrative Component					13

Community Involvement															13

Document Review												 13

Data Review					13

Site Inspection....															15

Interviews..........																				 15

VII.	Technical Assessment							16

ii


-------
Question A: Is the remedy functioning as intended by the decision documents?	16

Question B: Are the exposure assumptions, toxicity data, cleanup levels, and remedial

action objectives used at the time of remedy selection still valid?,....						 16

Question C: Has any other information come to light that could call into question the
protectiveness of the remedy?					17

VIII.	Issues																		 18

IX.	Recommendations and Follow-up Actions				19

X.	Protectiveness Statements						20

Operable Units 1 and 2																		 20

Operable Units 3 and 4 												20

Operable Unit 5									20

Overall Protectiveness																		 20

XI.	Next Review											21

Appendix

Appendix 1	OU1 and OU2 Tables and Figures

Appendix 2	Summary of OU3 and OU4 Groundwater Data

Appendix 3-	OU5 Tables and Figures •

Appendix 4	List of Documents Reviewed

Appendix 5	Institutional Control - City Ordinance

m


-------
List of Abbreviations

ARAR	Applicable or Relevant and Appropriate Requirements

AS/SVE	Air Stripper/Soil Vapor Extraction

ATS	Alternative Treatment Study

BTEX	Benzene,Toluene, Ethylbenzene, Xylene

CD	Consent Decree

CERCLA	Comprehensive Environmental Response, Compensation, and Liability Act

cis-1,2-DCE cis-1,2-dichloroethene

EE/CA	Engineering Evaluation/Cost Analysis

EPA	United States Environmental Protection Agency

ESD . Explanation of Significant Differences

EW	Extraction Wells

GET	Groundwater Extraction and Treatment

gpm	gallons per minute

HYAC	Heating, Ventilating, And Air Conditioning

ICs	Institutional Controls

LNAPL	Light Nonaqueous Phase Liquid

LTRA	Long-Term Response Action

MCL	Maximum Contaminant Level

MW	Monitoring Well

NCP	National Contingency Plan

NDEQ	Nebraska Department of Environmental Quality

NDOH	Nebraska Department of Health

NPL	National Priorities List

O&M	Operation and Maintenance

OU	Operable Unit

PCE	Tetrachloroethylene

POTW	Publicly Owned Treatment Works

ppm	parts per million

PRP	Potentially Responsible Parties

RAOs	Remedial Action Objectives

RD/RA	Remedial Design/Remedial Action

RI/FS	Remedial Investigation/Feasibility Study

ROD	Record of Decision

RSE	Remedial System Evaluation

SVE	Soil Vapor Extraction

TCE	Trichloroelhene

TI	Technical Impracticability

UPRR	Union Pacific Railroad

VOC	Volatile Organic Compounds

jig/1	Microgram per liter

iv


-------
Executive Summary

The Cleburn Street Well Site (Site) consists of a former municipal water supply well, the
Cleburn Street well, and surrounding groundwater and soils containing volatile organic
compounds (VOCs), primarily tetrachloroetliylene (PCE). Results of the remedial investigation
completed in 1993 indicate four separate source areas including three dry cleaning facilities and
a former solvents distribution facility.

Because the source areas were separate and distinct and involved varying degrees of
contamination, the United States Environmental Protection Agency (EPA) divided the source
areas into operable units (OUs). OU 1 included source soils at the One Hour Martinizing source
area. Groundwater associated with the One Hour Martinizing source area was addressed by
OU 2, The Liberty Cleaners source area was identified as OU 3, and OU 4 was the Ideal
Cleaners source area. The Nebraska Solvents source area became OU 5.

In 1996, EPA signed a record of decision (ROD) addressing OUs 1-4. The ROD
selected soil vapor extraction (SVE) for OU 1, groundwater extraction and treatment by air
stripping for OU 2, and groundwater monitoring for OUs 3 and 4, No viable potentially
responsible parties (PRPs) were identified for OUs 1-4, so those OUs were addressed as fond-
lead actions. The remedies for OUs 1-4 have been implemented and are functioning as
designed.

The Nebraska Solvents Company had operated on property owned by Union Pacific
Railroad (UPRR), which was notified of its potential liability in February 1997. The remedial
investigation/feasibility study (RI/FS) for OU 5 was completed by UPRR and a final ROD for
OUS was signed in September 2001. The selected remedy included SVE to address source soils
and air sparging to address groundwater and the light hydrocarbons on the surface of the
groundwater. The remedy for OU 5 has been implemented and is functioning as designed.

The first five-year review for the Site was completed in September 2003, That review
found that the remedies for OUs 1-4 were protective. At the time of the first review, the OU 5
remedy had not yet been implemented. Completion of remedial action for OU 5 occurred in
2004 and the Site achieved construction completion on September 14, 2004.

This five-year review concludes that the remedies at all OUs are protective of human
health and the environment, and in the interim, exposure pathways that could result in
unacceptable risks are being controlled. The OU 1 remedy is complete and the associated
remediation system SVE has been combined with OU 2. All remediation systems are operating
as designed. Additional actions will be considered to address high concentration source areas at
OU 2 and OU 5. Exposure pathways are being controlled through plume containment, treatment,
and long-term monitoring. There are no groundwater exposures since all businesses and
residents in the area are connected to city water and city ordinance prohibits the installation of
private water wells in the vicinity of the Site. The vapor intrusion pathway was evaluated in
2007 and determined to be of no concern.


-------
Five-Year Review Summary Form

vi


-------
Five-Year Review Summary Form, Cont'd

Issues, Recommendations, and Follow-up Actions:

Issues

Recommendations and Follow-up Actions

Administrative record for OUs 1-4 is
missing at local library

Generate a new copy and send to the
library in both hard copy and electronic
format on a compact disc.

Sampling ports on air stripper are not
properly labeled.

Label the sampling ports on the air stripper.

Existing OU 2 remediation system may not
be capable of achieving remedial action
objectives in a reasonable time frame.

Evaluate additional technologies to address
source area at OU 2.

Operation and Maintenance (O&M) Plan
and manual for the OU 2 systems need to
be updated.

Update O&M Plans and manuals for the
OU 2 systems.

OU 5 SVE system unable to address
shallow soil.

Consider alternate means to address
shallow soils at OU 5,

Protectiveness Statements:

Operable Units 1 and 2

The remedies at Otis 1 and 2 are protective of human health and the environment, and in
the interim, exposure pathways that could result in unacceptable risks are being controlled. Both
remedial actions are operating as designed. However, the SVE system which began operating as
OU 1 for the purpose of addressing source soils is now being operated as part of the OU 2
remedial action to address groundwater contamination. Exposure pathways are being controlled
through plume containment, treatment, and long-term monitoring. The vapor intrusion pathway
was evaluated in 2007 and determined to be of no concern. There are no groundwater exposures
since all businesses and residents in the area are connected to city water and city ordinance
prohibits the installation of private water wells in the vicinity of the Site.

Operable Units 3 and 4

The remedies at OUs 3 and 4 are protective of human health and the environment, and in
the interim, exposure pathways that could result in unacceptable risks are being controlled. The
OUs 3 and 4 remedies consist of groundwater monitoring events to be conducted at least once
every five years to support five-year reviews. All deep wells continue to show PCE levels well
below the Maximum Contaminant Level (MCL). The two shallow wells at OU 3 recently
showed PCE levels only slightly above the MCL. The shallow well at OU 4 showed a PCE level
slightly below the MCL. There are no groundwater exposures since all businesses and residents
in the area are connected to city water and city ordinance prohibits the installation of private
water wells in the vicinity of the Site.

vii


-------
The remedy at OU 5 currently protects human health and the environment because the
remedies for addressing VOCs in the groundwater and the vadose zone are functioning as
intended and the institutional controls (ICs) are in place. However, in order for the remedy to be
protective in the long-term, additional actions may be necessary to address shallow soils. Long-
term protectiveness will be achieved by modifying the decision document and implementing the
necessary remedy modifications to address shallow soils. Groundwater concentrations have been
significantly reduced since the AS/SVE systems began operating in 2004. Currently, the systems
are operated in pulsed mode to allow periods of rebound to maximize mass removal. In addition,
the presence of light phase hydrocarbons has been reduced to only a few wells. The only
remaining concern relates to shallow soil concentrations which do not appear to be responding to
the SVE system. The UPRR has proposed an alternative for excavating and treating the shallow
soils. The Environmental Protection Agency (EPA) plans to consider this approach and may
modify the decision document in the near future. Groundwater exposures are being controlled
since all businesses and residents in the area are connected to city water supply and city
ordinance prohibits the installation and use of private water wells in the vicinity of the Site. Soil
exposures are controlled by restricted access and the fact that the property is used for limited
industrial purposes.

Overall Protectiveness

Because additional actions are needed to achieve long-term protectiveness at OU 5, the
Site is protective of human health and the environment only in the short term.


-------
I. Introduction

The purpose of the five-year review is to determine whether the remedy at a site is
protective of human health and the environment. The methods, findings, and conclusions of
such reviews are documented in the Five-Year Review Report. In addition, Five-Year Review
Reports identify problems or issues discovered concerning the remedy during the review process,
and recommend actions to resolve them.

The United States Environmental Protection Agency (EPA) is preparing this Five-Year
Review Report pursuant to the Comprehensive Environmental Response, Compensation, and
Liability Act (CERCLA) section 121 and the National Contingency Plan (NCP), CERCLA
section 121 states:

If the President selects a remedial action that results in any hazardous substances,
pollutants, or contaminants remaining at the site, the President shall review such
remedial action no less often than each 5 years after the initiation of such remedial
action to assure that human health and the environment are being protected by the
remedial action being implemented. In addition, if upon such review it is the
judgment of the President that action is appropriate at such site in accordance with
section 104 or 106, the President shall take or require such action. The President
shall report to the Congress a list of facilities for which such review is required,
and the results of all such reviews, and any actions taken as a result of such
reviews.

EPA interpreted this requirement further in the NCP. Specifically, 40 CFR section
300.430(f)(4)(ii) states:

If a remedial action is selected that results in hazardous substances, pollutants, or
contaminants remaining at the site above levels that allow for unlimited use and
unrestricted exposure, the lead agency shall review such action no less often than
every five-years after the initiation of the selected remedial action.

EPA Region 7 conducted the first five-year review for the Cleburn Street Well Site (Site)
in Grand Island, Hall County, Nebraska, in 2003. The triggering action for the first five-year
review was the start of physical on-site construction of the remedial action for operable units
(OUs) 1 and 2. The triggering action for this live-year review is the date of the first five-year
review. This five-year review is a policy review because the selected remedial actions will not
leave hazardous substances on the site above levels that will allow for unlimited use and
unrestricted exposure, but five or more years are required to meet cleanup levels. The Site
consists of five OUs. This report documents the findings of the second five-year review for the
Site.

1


-------
II, Site Chronology

Table 1
Chronology of Site Events

Description of Event

Date

Tetrachloroethylene discovered in city water supply

3/1986

Cleburn Street supply well disconnected from water supply

4/1986

EPA conducts soil gas survey in Grand Island

1988

EPA conducts search for Potentially Responsible Parties

1990-1992

Site proposed for National Priorities List

7/29/1991

Remedial Investigation/Feasibility Study started

9/1991

Final listing on National Priorities List

10/14/1992

Engineering Evaluation/Cost Analysis completed

4/1993

Action Memorandum signed/Removal Action started

8/1993

OUs 1-4 Remedial Investigation completed

1/1994

OUs 1-4 Feasibility Study completed

7/1995

OUs 1-4 signed Record of Decision

6/7/1996

OUs 3 and 4 completed Remedial Design

6/1997

OUs 1 and 2 completed Remedial Design

9/1997

OUs 1 and 2 started Remedial Action

12/1997

Removal Action completed

6/1998

OUs 3 and 4 started Remedial Action

9/15/1997

OUs 1 and 2 Remedial Action physical construction complete

9/18/1998

OUs 3 and 4 Remedial Action complete

7/14/1999

OUs 3 and 4 Operation and Maintenance started

9/10/1999

OUs 1 and 2 determined Operational and Functional

10/29/1999 .

OU 1 enters Operation and Maintenance and turned over to state

2/8/2000

OU 2 enters Long-Term Response Action phase

2/8/2000

OU 5 Remedial Investigation/Feasibility Study started

6/13/1997

OU, 5 Remedial Investigation/Feasibility Study completed

9/10/2001

OU 5 Record of Decision signed

9/10/2001

OU 5 Consent Decree entered

9/20/2002

OU 5 Remedial Design complete

1/7/2004

OU 5 Remedial Action complete

9/28/2004

First five-year review complete

9/30/2003

Site-wide construction complete

9/14/2004

OU 1 Operation and Maintenance complete

2/22/2007

2


-------
Ill, Background

Physical Characteristics

The Site is located in Grand Island, Hall County, Nebraska. The Site is situated in central
Nebraska, approximately two miles north of the Wood River and approximately seven miles
northeast of the Platte River. The Site is comprised of four separate source areas encompassing a
portion of the downtown area and is surrounded by a variety of light industries, commercial
businesses, and residential dwellings.

The Site is located in the Great Plains physiographic province in the middle of the Platte
River Basin. Surface topography is generally flat with natural surface drainage flowing in a
northeasterly direction. Much of the surface water runoff from the Site is controlled by man-
made features such as storm sewers and gutters. The Platte River flows from southwest to
northeast and is situated approximately seven miles south of Grand Island. Groundwater flows
in a northeasterly direction in the vicinity of the Site.

The Site consists of a former municipal
water supply well, the Cleburn Street well, and
surrounding groundwater and soils containing
volatile organic compounds (VOCs), primarily
tetrachloroethylene (PCE). Results of the remedial
investigation completed in 1993 indicate four
separate source areas including three dry cleaning
facilities and a former solvents distribution facility.
Figure 2 shows the location of all four source areas.

The three dry cleaner source areas include
the former One Hour Martinizing facility, the
Liberty Services facility, and the Ideal Cleaners of
Grand Island facility. Results of the RI indicate that
the primary source area responsible for
contamination of the Cleburn Street municipal well
is the former One Hour Martinizing facility.
Extremely high contaminant levels were found in
the shallow groundwater in the vicinity of this
facility. The Liberty Services and Ideal Cleaners
source areas exhibit lesser degrees of contamination
and are not believed to contribute to contamination
of the Cleburn Street well.

The fourth source area is a former solvents distribution company known as Nebraska
Solvents and is located at the intersection of Lincoln Street and North Front Street, a few blocks
west of the Cleburn Street municipal well. Contamination at this source area includes soil and
groundwater containing VOCs.

Grand Island

CLEBURN ST.
WELL SITE

Figure 2

3


-------
Land and Resource Use

Land use surrounding each of the four source areas can best be described as mixed use,
consisting of light industrial operations, commercial businesses, and residential dwellings. The
contaminated shallow aquifer was historically used as the city's main water source. However, all
municipal wells in the vicinity of the Site have been disconnected from the public water supply,
and a new well field has been installed several miles from the Site along the Platte River. In
addition, the city has passed an ordinance prohibiting groundwater use or installation of wells
within the affected area around the Site.

Land use at the Liberty Cleaners and Ideal Cleaners source areas continues to be
commercial dry cleaning operations. The former One Hour Martinizing property had been used
as a pawn shop for a few years and is currently used as a commercial operation for audio and
hydraulic enhancements for automobiles. A portion of the former Nebraska Solvents source area
is now leased by the city street department to store and maintain trucks and equipment and also
contains a small sign shop.

History of Contamination

The presence of PCE in the Cleburn Street Well was first discovered in 1986 by the
Nebraska Department of Health (NDOH). The city quickly disconnected the well from the
public water supply but continued to operate the well to alleviate flooding problems in a nearby
railroad underpass. Water from the well was discharged to the storm sewer for a number of
years and then later diverted to the sanitary sewer for treatment in the city's publicly owned
treatment works (POTW).

EPA became involved with the Site in 1987 and conducted site investigations including a
soil gas survey to locate potential source areas. Based on the findings of the early investigations,
the Site was proposed for listing on the National Priorities List (NPL) on July 29,1991, and was
finalized on the NPL on October 14,1992.

Based on results of a soil gas survey completed in 1989, EPA conducted a search for
potentially responsible parties (PRPs) and issued notice letters to the parties involved with the
various source areas. In 1992, EPA initiated a fund-lead remedial investigation/feasibility study
(RI/FS) for three of the four source areas because the PRPs lacked the financial resources to
conduct the work. The three source areas addressed by the initial RI/FS included the former One
Hour Martinizing dry cleaners, Liberty Cleaners, and Ideal Cleaners of Grand Island.

In the early stages of the RI/FS, it was discovered that the PCE concentrations in
groundwater at the former One Hour Martinizing source area were extremely high (over 170,000
micrograms per liter or |ig/l). In order to contain this highly contaminated groundwater, EPA
initiated a time-critical removal action in 1993. The removal action included the installation of a
single Extraction Well (EW) with the extracted water discharged to the city sanitary sewer for
treatment in the POTW. This action was taken as a gross containment action to prevent further
migration until a permanent remedy could be selected and implemented.

4


-------
Results of the RI indicated that the various source areas were separate and distinct plumes
and the only source area responsible for contaminating the Cleburn Street municipal well was the
former One Hour Martinizing source area. Because the source areas were clearly separate and .
distinct, and involved varying degrees of contamination, EPA divided the source areas into OUs.
OU 1 included source soils at the One Hour Martinizing source area. Groundwater associated
with the One Hour Martinizing source area was addressed by OU 2. The Liberty Cleaners
source area was identified as OU 3, and OU 4 was the Ideal Cleaners source area. The Nebraska
Solvents source area became OU 5 and would be addressed later in a separate RI/FS to be
performed by PRPs.

In 1996, EPA signed a Record of Decision (ROD) addressing OUs 1-4. The ROD
selected soil vapor extraction for OU 1, groundwater extraction and treatment by air stripping for
OU 2, and for OUs 3 and 4, the selected remedy included groundwater monitoring. The
implementation status of each of these remedies is discussed later in this report.

The Nebraska Solvents Company had operated on property owned by Union Pacific
Railroad (UPRR). The Nebraska Solvents Company was defunct, and UPRR was notified of its
potential liability for the Site in February 1997. In June 1997, EPA signed a consent order with
UPRR for the completion of an RI/FS for OU 5, Between 1997 and 2001, the OU 5 RI/FS was
conducted.

The OU 5 area consists of two parcels of land known as the east parcel and the west
parcel. The west parcel was used for storage and distribution of industrial solvents including
PCE. The solvents were stored in above-ground tanks. Results of the RI indicated significant
levels of VOCs in the soil and groundwater (up to 4100 f.ig/1 PCE) at the west parcel. In
addition, high levels of benzene, toluene, ethylbenzene, and xylene (collectively referred to as
BTEX) were detected in the shallow groundwater at the west parcel. It is believed that these
compounds are associated with a light phase hydrocarbon floating on top of the groundwater
surface. The east parcel was used for warehousing, handling, and loading solvents in drums.
Results of the RI indicate low levels of YOCs in the soils at the east parcel but significant
concentrations of PCE in shallow groundwater (up to 1600 pg/1 PCE).

A final remedy was selected for OU 5 in a ROD signed in September 2001. The selected
remedy included soil vapor extraction to address source soils and air sparging to address
groundwater and the light phase hydrocarbons on the surface of .the groundwater. The remedy
also included institutional controls (ICs) to restrict groundwater use and certain subsurface
construction activities on the UPRR property.

EPA negotiated a Consent Decree (CD) with UPRR for the Remedial Design/Remedial
Action (RD/RA) for OU 5. The CD was entered by the District Court of Nebraska on September
20,2002. The implementation status of the OU 5 remedy is discussed later in this report.

Initial Response

5


-------
In 1993, EPA initiated a time-critical removal action to address the most highly
contaminated groundwater at the One Hour Martinizing source area. Using the information
obtained in the early stages of the RI/FS, EPA prepared an Engineering Evaluation/Cost Analysis
(EE/CA) and an action memorandum to support the time critical removal action. The Action
Memorandum authorized the expenditure of funds for installation of a groundwater EW which
was located near the high concentration source area, and discharge piping, which was connected
to the sanitary sewer. Groundwater was extracted at a rate of approximately 50 gallons per
minute (gpm) and discharged to the sanitary sewer for treatment in the city's POTW. This gross
containment action continued until a permanent groundwater extraction and treatment system
was constructed in 1998 as the OU 2 remedy.

Basis for Taking Action

High concentrations of VOCs detected in the soils and shallow groundwater at facilities
known to have used, the VOCs in their operations served as the basis for taking action at this Site.
Information obtained during the various investigations indicated a release to the environment of
hazardous substances. Contamination of the shallow groundwater had impacted the public water
supply and necessitated the shut down of a municipal supply well known as the Cleburn Street
well.

6


-------
IV, Remedial Actions

Remedy Selection

Remedies for OUs 1-4 were selected in a ROD signed on June 7,1996. The selected
remedy for OU 1 included soil vapor extraction (SVE) to address source soils at the One Hour
Martinizing source area,' Groundwater extraction and treatment by air stripping was the remedy
selected for OU 2 to address contaminated groundwater at the One Hour Martinizing source area.
The selected remedies for OUs 3 and 4 included groundwater monitoring, with soil vapor
extraction as a contingency action, to address shallow groundwater contamination at the Liberty
Cleaners and Ideal Cleaners source areas, respectively. The 1996 ROD also called for ICs to
restrict groundwater use in the vicinity of the Site. Remedial action objectives (RAOs) set forth
in OUs 1-4 ROD included:

•	Prevent or minimize ingestion of groundwater having a carcinogenic risk greater
than 1x10*6 and/or a hazard index for noncarcinogens greater than 1.0

•	Restore groundwater quality to below Maximum Contaminant Levels (MCLs) for
all contaminants that have an MCL

•	Prevent or minimize direct contact with soils having a carcinogenic risk greater
than 1 xl 0"6 and/or a hazard index greater than 1.0

•	Prevent the migration of contaminants that would result in groundwater
contamination at levels above MCLs

A final ROD for OU 5 was signed on September 10,2001. The selected remedy for
OU 5 included SVE to address source soils and air sparging to address groundwater and the light
nonaqueous phase liquid (LNAPL) on the surface of the groundwater. The remedy also included
ICs to restrict groundwater use and certain subsurface construction"activities on the UPRR
property. RAOs for OU 5 include the following:

•	Reduce or eliminate further contamination of the groundwater from the source

•	Restore the aquifer to drinking water standards within a reasonable time frame

•	Prevent future migration of groundwater contamination

•	Reduce or eliminate sporadic polluting of the aquifer surface

Target concentrations for specific compounds in groundwater and a standard for the
LNAPL reduction were set forth in the OU 5 ROD. Those standards include:

•	5 ng/1 PCE

•	5 jig/1 trichloroethene (TCE)

•	70 p.g/1 cis-1,2-dichloroethene (cis-1,2-DCE)

•	10,000 |ig/l xylenes

•	1000 |ig/l toluene

•	700 ug/'l ethylbenzene

•	5 jag/1 benzene

•	Sheen standard for LNAPL

7


-------
Remedy Implementation

The RD for OUs 1 and 2 were completed in September 1997, and the remedies were
constructed and operating by October 1998, Following the first year of operation, a joint
inspection was conducted by EPA and the state, and the remedies were determined to be
operational and functional on October 29,1999. The OU 1 remedy was turned over to the state
for Operation and Maintenance (O&M). The OU 2 remedy entered into the ten year period for'
long-term response action (LTRA) on February 8,2000, marked by approval of the interim RA
report. Refer to Appendix 1 for a diagram of the OUs 1 and 2 remediation systems. The
required ICs were implemented in February 1998 when the city passed Ordinance No. 8363.

This ordinance established a Groundwater Control Area encompassing all OUs of the Site,
restricted the use of groundwater pumped from within this area, and required the registration of
all new wells placed within the area. The ordinance contains a provision that it shall remain in
effect for an initial term of 25 years, with an option of extending it if groundwater contamination
persists beyond that time frame.

The RDs for OUs 3 and 4 were completed in June 1997. The RA included the
installation of two down gradient monitoring wells at each OU and six quarterly monitoring
events. The final RA Report for OUs 3 and 4 was approved on July 14,1999. The OUs 3 and 4
remedies were turned over to the state for O&M on September 10,1999.

For the OU 5 SVE and air sparging systems, the RD was completed in January 2004, and
construction was completed by August of the same year. The RD and RA were performed
pursuant to a CD entered on September 20,2002. A RA report was signed in September 2004
marking the start of O&M for OU 5. Since OU 5 was the final remedy for the Site, a preliminary
close out report was prepared following completion of construction activities for the OU 5
remedy, and the Site achieved construction completion on September 14,2004. Refer to
Appendix 3 for a diagram of the OU 5 area.

System Operation and Maintenance

The state operated the OU 1 SVE system for a period of approximately 4 years between
1998 and 2002. In July 2002, the SVE system was shut down due to equipment failures and low
influent vapor concentrations. In March 2004 the state collected soil borings which indicated
that the remediation goal had not yet been achieved. The state replaced the blower and operated
the system from April 2005 through early 2006. During this period of operation, vapor influent
concentrations dropped dramatically. In April 2006, the state notified EPA of its position that
the OU 1 remedy was complete because soil vapor concentrations had reached asymptotic levels
and no further mass removal was being achieved by the SVE system. In a letter dated February
22,2007, EPA agreed that the OU 1 remedy had achieved its intended purpose of addressing
source soils, and indicated that any further operation of the SVE system would be conducted by
EPA in association with its ongoing LTRA of the OU 2 groundwater remedy. In other words,
further operation of the SVE system may enhance groundwater cleanup and would thus be
considered part of the OU 2 LTRA.

8


-------
During the first year of operation of the OU 1 SVE system, operating costs were about
$80 ,000, mostly due to the high cost of changing out the carbon canisters. However, the need for
offgas treatment from the SVE system quickly ended following state take over of the O&M. The
state has reported annual O&M costs for the SVE system ranged from $34,000 - $41,000 for the
years it operated the SVE system.

The OU 2 groundwater extraction and treatment (GET) system began operating in 1999.
The design extraction rate was 120 gpm. However, the system flow rate was quickly reduced to
about 90 gpm because of excessive pump cycling. Groundwater modeling conducted during the
RD had indicated that this reduced flow rate was sufficient to provide plume capture. The
system has operated continuously except for short periods of shut down for minor repairs.
Operating costs for the first year of operation were approximately $150,000. However, these
costs have been reduced to about $100,000 per year in recent years.

A remedial systems evaluation (RSE) was conducted in 2001 as part of the national
optimization pilot project. The RSE recommended various improvements for the system
including combining the operation of the OUs 1 and 2 systems, performing a capture zone study,
and cleaning EW screens, among other things. Most of the recommendations have now been
implemented. Since 2006, EPA Region 7 has been conducting additional optimization activities
in order to prepare the remedy for state take over in 2010.

The GET system has operated continuously since its startup in 1999 except for brief
periods of shut down for mechanical repairs. The system is now operating near design capacity
at 110 gpm. Influent concentrations have declined from over 1,500 p.g/1 PCE in 1999 to
approximately 500 p.g/1 PCE in 2007. Concentrations of PCE in the Cleburn Street well have
declined from over 1,000 pg/I in 1999 to less than 5 jug/1 in 2007. The GET system has been
successful in cleaning up the Cleburn Street well and preventing further migration of highly
contaminated groundwater. However, a significant source area remains in very close proximity
to the former One Hour Martinizing facility. In general, operating costs for the GET system are
approximately $100,000 per year. During the past two years, operating costs have been higher
due to system optimization and rehabilitation efforts.

EPA began operating the SVE system in January 2008 to enhance the OU 2 groundwater
cleanup. Initial monitoring after startup indicated that vapor concentrations decline significantly
after about 48 hours of operation. Therefore, the SVE system is operated on an intermittent
basis. Currently, the system is operated for a few days out of every 2-3 week period.

The O&M program for the GET system currently consists of weekly system inspections
and quarterly groundwater monitoring events, with an expanded annual groundwater monitoring
event. O&M activities for the SVE system include routine system checks when the system is
operating and the collection of field measurements including vapor flow rates and
concentrations. Weekly inspection reports are completed and submitted to EPA on a monthly
basis.

The Nebraska Department of Environmental Quality (NDEQ) began conducting O&M
for the OUs 3 and 4 groundwater monitoring remedies in September 1999. Routine monitoring
was conducted by the state from 1999 until March 2004, and the state reports that monitoring

9


-------
costs ranged from $10,000-$ 12,000 per year. During that time. PCE concentrations remained
below the MCL of 5 jj.g/1 in all deep wells. Groundwater from the shallow wells contained low
concentrations of PCE, with the highest concentration detected in monitoring well (MW)-IC at
OU 3 at a level of approximately 50 j.ig/1. This concentration has remained fairly steady in well
MW-1C since the start of the RA.

Following the March 2004 monitoring event, NDEQ recommended that further
groundwater monitoring be discontinued due to the stability of PCE concentrations in the wells.
EPA agreed that monitoring could be limited to one event every five years to support the five-
year reviews.

O&M for OU 5 is conducted by the Forrester Group, consultant for the Union Pacific
Railroad. Initially, O&M for OU 5 included weekly monitoring of the SVE influent and effluent
concentrations. Monitoring was reduced to monthly and then to quarterly as influent
concentrations dropped. When the SVE system was first started up, a thermal oxidizer was used
to treat extracted vapors. After a few months of operation, vapor treatment was no longer
required, and the thermal oxidizer was removed from service. No major mechanical repairs have
been necessary for system components.

Since the remedy started up in 2004, great strides have been made toward achieving
RAOs. The air sparging system has reduced the maximum PCE concentration in groundwater
from 5,000 ju.g/1 in April 1998 to 9.4 |ig/l in March 2008. Other VOCs have also been
significantly reduced. Some of the reduction in PCE concentration was due to injection of
potassium permanganate into the dissolved PCE plume downgradient from the west parcel. This
alternative treatment study (ATS) was proposed by Forrester Group in November 2006 and
completed in January/February 2007. The injection has resulted in the acceleration of the
degradation of PCE and daughter products in the groundwater to levels below or slightly above
their MCLs. Refer to Appendix 3 for a summary of groundwater data. To address LNAPL, the
Forrester Group injected a proprietary chemical into the subsurface. Subsequent monitoring
events have indicated a significant reduction of LNAPL in many wells. However, the LNAPL
sheen standard has not yet been achieved in all wells.

The O&M program currently consists of quarterly groundwater monitoring events, bi-
weekly LNAPL checks, and quarterly vapor monitoring when the SVE is running. The SVE and
air sparging systems are currently shut down to allow rebound. The Forrester Group does not
submit information regarding operating costs for the OU 5 remedy.

The Forrester Group does not believe that the existing SVE system will be able to meet
RAOs for shallow soils. For that reason, excavation and on-site treatment of shallow soils has '
been proposed, EPA may modify the ROD by issuing an Explanation of Significant Differences
(BSD) to support this remedy

10


-------
Y. Progress Since Last Five-Year Review

The first five-year review was completed in September 2003. At that time, the remedies
were found to be protective of human health and the environment for OUs 1-4, and the RD for
OU 5 was in progress. Recommendations included the continued operation of the OU I SVE
system, continued operation of the OU 2 GET system, continued groundwater monitoring in
OUs 1-4, continue optimization efforts related to OUs 1 and 2, and implement the OU 5 remedy.
Each of these recommendations has been fully implemented.

For the OU 1 remedy, progress since the last five-year review includes soil sampling
conducted by NDEQ and operation of the SVE system from April 2005 through early 2006.
NDEQ shut down the SVE system in early 2006 due to low influent vapor concentrations. In
April 2006, the state notified EPA of its position that the OU 1 remedy was complete because
soil vapor concentrations had reached asymptotic levels and no further mass removal was being
achieved by the SVE system. In a letter dated February 22, 2007, EPA agreed that the OU 1
remedy had achieved its intended purpose of addressing source soils, and indicated that any
further operation of the SVE system would be conducted by EPA in association with its ongoing
LTRA of the OU 2 groundwater remedy.

Since the last five-year review, the OU 2 GET system has operated continuously,"but
extraction rates decreased steadily between 2004 and 2007. In 2006, EPA conducted a source
investigation to determine whether source soils still existed beneath the former One Hour
Martinizing building. During the RI, sampling beneath the building was not possible due to the
dilapidated condition of the building and ownership complications (abandoned facility). By
2006, the property had been purchased and the building had been restored to a condition that
would allow for sampling. With the owner's permission, EPA collected soil, soil gas, and
groundwater samples from temporary boreholes drilled through the concrete floor of the
building. In addition, EPA installed five 2-inch SVE wells, four 1-ineh vapor monitoring points,
and three 1.5-inch groundwater monitoring wells inside the building to expand the capabilities of
the SVE system and improve the monitoring of both the SVE and the GET systems.

The 2006 source investigation and subsequent sampling by EPA has indicated that the
remaining source appears to be an area of highly concentrated groundwater contamination on the
eastern edge of the building. Soil samples have shown very little PCE while soil gas samples
show very high PCE levels. This indicates that the PCE is volatilizing from the groundwater and
filling in the void spaces in the vadose zone and becoming trapped beneath the concrete building.
To address this situation and to enhance groundwater cleanup, EPA began operating the SVE
system in January 2008.

In order to bring the SVE system back into operation and to optimize performance of the
GET system, EPA completed a number of mechanical repairs and improvements during 2007
and 2008. In order to increase the extraction rate from the GET system, all three EWs were
chemically cleaned and new pumps were installed in June 2007. Additionally, the acid
circulation pump was replaced and improvements were made to the acid wash system so that the
tray air stripper can be routinely cleaned. A series of improvements were made for the SVE
system in 2007 including the installation of a new water knock-out tank, reconfiguration of well-
head piping to allow collection of vapor flow measurements, and replacement of all pressure
gages.

11


-------
In May 2008, EPA conducted additional groundwater investigation activities to better
characterize vertical and horizontal plume characteristics and to determine whether
contamination existed at depth. Results of this investigation indicate that deep groundwater
contamination is not a problem, and that there is a zone of low permeability between 25-35 feet.
This area of low permeability is likely preventing the contamination from migrating into deeper
portions of the aquifer. Also, the cleanup of the high concentrations of PCE in the shallow
groundwater is likely being slowed because the EWs have depths and screened intervals below
this siltv zone.

All studies conducted at the Site indicate that there remains a significant, localized source
very near the east edge of the former One Hour Martinizing building. Operation of the existing
SVE and GET systems will not likely reduce groundwater concentrations to cleanup levels
within a reasonable time period. In order to address this high concentration area, EPA plans to
conduct pilot studies of certain technologies and may implement remedy modifications upon
completion of the studies. Technologies being considered include air sparging and chemical
oxidation. Further optimization of the GET system may also be considered.

For OUs 3 and 4, progress since the last five-year review includes the completion of
groundwater monitoring events through March 2004. Following this event, NDEQ discontinued
monitoring due to stabilized contaminant concentrations. In February 2007, EPA agreed that
further groundwater monitoring at OUs 3 and 4 is only necessary to support five-year reviews.
In support of this review, NDEQ conducted a monitoring event at OUs 3 and 4 in April 2008.
Results of this event indicate that PCE concentrations are below the MCL at all wells at OU 4,
and the maximum PCE concentration at OU 3 is 12.7 ug/l. Refer to Appendix 2 for a summary
of the April 2008 groundwater data for OUs 3 and 4.

Since the OU 5 remedy was started up in 2004, great strides have been made toward
achieving RAOs, The air sparging system has reduced the maximum PCE concentration in
groundwater from 5000 (ig/1 in April 1998 to 9.4 \ig!\ in March 2008. Other YOCs have also
been significantly reduced. Injection of potassium permanganate into the dissolved PCE plume
downgradient from the west parcel was conducted during January and February 2007.
Subsequent monitoring of groundwater has shown an accelerated decline in plume VOC
concentrations to levels near or below their MCLs. To address LNAPL, the Forrester Group
injected a proprietary chemical into the subsurface. This effort seems to have resulted in a
reduction of the LNAPL, However, LNAPL continues to be monitored in a few wells and is
removed whenever possible.

To achieve RAOs for shallow soil, the Forrester Group has proposed excavation and on-
site thermal treatment because they do not believe the existing SVE system will be able to
address shallow soils. EPA is considering modifying the decision document to support this
remedy change.

12


-------
VI. Five-Year Review Process

Administrative Component

The state was notified of the start of the five-year review in April 2008 when it was asked
to participate by conducting a monitoring event for OUs 3 and 4. The city was notified of the
start of the five-year review in a meeting in January 2008, Members of the review team include
the EPA project managers, the state project manager, and risk assessors for human health and
ecological risk.

Community Involvement

A fact sheet announcing the start of the five-year review was mailed to Congressional
offices and on November 20,2007, was published on the EPA Region 7 Website. In addition, an
ad was placed in the local newspaper on December 2,2007, and the EPA project manager met
with local officials in January 2008. Following completion of the Five-Year Review Report,
another fact sheet and ad will be prepared to announce the availability of the report for public
viewing. Additionally, the report will be published on the EPA Website.

Document Review

Due to the multiple OUs on this Site and the number of years of operation of the various
remedies, many Site documents were reviewed for this report. Documents reviewed include
RODs, O&M reports, RI reports and risk assessments, and the first Five-Year Review Report. A
complete list of Site documents reviewed is included as Appendix 4.

Data Review

For the OU 1 SVE system, PCE vapor concentrations dropped from over 1500 ppm to
approximately 10 ppm over the period from 1998 to 2002. The NDEQ operated the system
again between April 2005 and early 2006, during which time the PCE vapor concentrations
dropped from around 300 ppm to less than 1 ppm. At that time, NDEQ shut down the SVE
system and declared that it had fulfilled its purpose of addressing source soils.

In February 2007, EPA elected to take over the SVE system for the purpose of enhancing
the OU 2 groundwater remedy. After completing additional source characterization and system
rehabilitation, EPA restored the SVE system to operation in January 2008. Initial PCE vapor
concentrations were about 40 ppm. Start-up monitoring indicated that the vapor concentrations
decreased to about 2 ppm within the first 48 hours of operation. For this reason, the SVE system
is now being operated in a pulsed mode to maximize mass removal and minimize operating
costs. Operation of the SVE system in this manner also promotes diffusion from groundwater
thereby enhancing groundwater cleanup by evacuating accumulated vapors from the vadose zone
beneath the building. Refer to Appendix 1 for a graph of the PCE vapor concentrations during
the first 48 hours of operation of the SVE system. Under current operating conditions,
approximately 1 lb per day of PCE can be removed. Additional data is being gathered to
evaluate optimum operating conditions to make the best use of the existing SVE system.

13


-------
For the OU 2 GET system, influent PCE concentrations have dropped from over 2,000
j.tg/1 to approximately 500 (j.g/1 since the system was started up in 1998, Refer to Figure 3,1 from
the 2007 Annual Performance Report included as Appendix 1, Concentrations of PCE in the
Cleburn Street well have dropped from over 1,200 jjtg/1 in 1998 to 6.8 p.g/1 in 2007. Refer to
Figure 3.2 from the 2007 Annual Performance Report included as Appendix 1. With regard to
the EWs, PCE concentrations remain highest in EW-1, which is the closest EW to MW-2A (the
area of highest PCE contamination). Since start-up of the system in 1998, PCE concentrations in
MW-2A. show a generally declining trend but remain extremely high at approximately 70,000
Hg/1. Figure 3,10 from the 2007 Annual Performance Report included as Appendix 1 shows that
there continues to be a small, localized area of high PCE concentration very near the east edge of
the former One Hour Martini zing building. It is not likely that the GET system alone will be
able to achieve RAOs within a reasonable time frame. For this reason, EPA plans to conduct
pilot studies to evaluate the ability of various technologies to address this area of high
concentration. If supplemental technologies can not achieve RAOs within a reasonable time
frame, it is possible that a technical impracticability (TI) waiver will be sought pursuant to
section 121(d) of CERCLA at some point within the next five years.

Due to fouling of the EWs and pumps over time, the extraction rate had declined to about
60 gpm during 2006. EPA completed rehabilitation of the wells and replaced all the well pumps
in June 2007. As a result of these actions, the extraction rate was restored to 110 gpm, near
design capacity of 120 gpm. Under current operating conditions, approximately 1 lb PCE per
day is being removed. The air stripper continues to remove PCE at a calculated efficiency of 99
percent.

Since 2000, all deep monitoring wells at OUs 3 and 4 have been below 5 pg/1 PCE.
NDEQ continued groundwater monitoring at OUs 3 and 4 through March 2004. Shallow
groundwater concentrations at OU 3 remained fairly steady over time and in March 2004, the
maximum PCE concentration was 49 ng/L The maximum PCE concentration detected at OU 4
during the March 2004 event was 6.6 p.g/1.

In support of this five-year review, NDEQ conducted groundwater monitoring at OUs 3
and 4 in April 2008. The PCE concentrations in shallow groundwater at OU 3 have declined to a
maximum of 12.7 |xg/L The concentration of PCE in the shallow groundwater at OU 4 has also
declined to 4.7 fig/1 PCE. All deep wells at OUs 3 and 4 continue to show nondeteetable levels
of PCE, Refer to Appendix 2 for a summary of the April 2008 groundwater data from OUs 3
and 4.

Groundwater concentrations have been significantly reduced for all contaminants of
concern at OU 5 since the remediation systems began operating in 2004. The table included as
Appendix 3 demonstrates the reductions of each contaminant in groundwater.

14


-------
Site Inspection

The site inspection was conducted on May 13, 2008, by the EPA project manager.
Activities included a visual inspection of all mechanical equipment associated with the OUs 1
and 2 SVE and GET systems, review of on-site documents such as the O&M manuals,
completion of the five-year review site inspection checklist, and review of the administrative
record at the local public library.

The site inspection revealed that all mechanical equipment for the SVE and GET systems
is operating properly and most equipment is clearly labeled. However, the blower for the SVE
system was awaiting a minor electrical repair to prevent the blower from shutting down due to
high amp draw. The repair has been completed and the blower restored to service. Sampling
ports on the air stripper need to be labeled.

Operating manuals and health and safety materials were stored in a file cabinet on-site.
One spare extraction pump is stored in the treatment building, The heating, ventilating, and air
conditioning (HVAC) system and other facility support equipment is operating properly.
However, the water service has been disconnected for some time due to a frozen water pipe that
burst and flooded the building a few years back. The building owner does not heat his portion of
the building enough to protect the line, so no water service is currently available in the treatment
building. This is a potential health and safety concern for the operator, especially during
periodic cleanouts of the air stripper. EPA directed the LTRA contractor to provide a temporary
water source, and EPA is currently evaluating more permanent solutions.

A visit to the local public library revealed that the administrative record for OUs 1-4 is
missing, except for the 2003 Five-Year Review Report. The administrative,record for OU 5
appeared to be in tact. The EPA project manager met with the manager of the library, who asked
that EPA provide another copy of the record, EPA plans to reproduce the administrative record
in both hard copy and on compact disc as requested by the library manager.

Interviews

Given the active status" of the various remedies at the Site, formal interviews were not
conducted, EPA met with city officials in January 2008 at the start of the review and no specific
concerns or issues were identified. EPA maintains routine communication with the LTRA
contractor for OUs 1 and 2 and the UPRR's contractor for OU 5. Regarding OUs 3 and 4, EPA
coordinated with NDEQ for completion of the monitoring needed to support this review. The
EPA project manager met with the manager of the local public library concerning the
administrative record.

15


-------
VII. Technical Assessment

Question A: Is the remedy functioning as intended bv the decision documents?

The OU 1 SVE remedy for addressing source soils was operated by NDEQ for a few
years and was shut down in early 2006 due to declining influent concentrations and low mass
removal. The SVE system had operated as intended. In February 2007, EPA notified NDEQ
that the OU 1 remedy was complete and that EPA may elect to operate the SVE system in
conjunction with the OU 2 GET system to enhance groundwater cleanup. Further operation of
the SVE system will be considered part of the OU 2 remedy.

Overall, the OU 2 GET system is functioning as intended. The PCE concentrations in the
Cleburn Street well have teen reduced to below 5 pg/1. The air stripper continues to remove
PCE at an efficiency of 99 percent, and the extraction system is containing the plume. However,
contaminant concentrations remain extremely high near the source area. It is not likely that the
GET system alone can achieve RAOs within a reasonable time frame. For this reason, EPA
plans to conduct pilot studies of various technologies to more aggressively address the localized
hot spot.

The OUs 3 and 4 groundwater monitoring remedies are functioning as intended, in that
shallow groundwater concentrations continue to decline. Monitoring at OUs 3 and 4 has been
reduced to once every five years.

The OU 5 remedy has performed as intended and has reduced groundwater PCE
concentrations from 700 ug/1 in 2004 to 9.4 ng/1 in March 2008. LNAPL continues to be
monitored and removed when possible. The only issue remaining to be resolved is residual PCE
in very shallow soils, which the existing technologies may not be able to address. For this
reason, UPRR has proposed excavation and on-site treatment of shallow soils in order to fully
meet the cleanup criteria established in the ROD. EPA may modify the decision document to
support implementation of this supplemental remedy.

ICs required by both RODs have been fully implemented and remain in effect. Refer to
Appendix 5 for a copy of the city ordinance.

Question B: Are the exposure assumptions, toxicity data, cleanup levels, and remedial action
objectives used at the time of remedy selection still valid?

To answer this question, a risk assessment review was completed by EPA Region 7.
Relevant Site documents for all OUs were reviewed and a memorandum report was prepared.
The risk assessment review concluded that there have been no changes.in applicable or relevant
and appropriate requirements (ARARs) since the RODs were signed. Similarly, there have been
no newly promulgated standards that would call into question the protectiveness of the remedies.

With regard to changes in exposure pathways, there have been no changes in land use at
the Site. The vapor intrusion pathway has been evaluated at the former One Hour Maximizing
source area due to the high VOC concentrations in shallow groundwater and in subsurface

16


-------
vapors beneath the building. Indoor air monitoring was conducted in 2007 and showed no
concerns related to vapor intrusion. Low levels of VOCs were detected but could not be
attributed to vapor intrusion because of the use of solvents in a business being conducted in the
building above the source area. No residential properties are within the plume area.

There have been no newly identified contaminants or sources. There have been no
unanticipated by-products due to remediation activities. Physical Site conditions have not
changed in any way that would impact the remedies.

Toxicity factors have not changed for Site related contaminants in a way that would
impact the protect!veness of the remedy, nor have there been changes in contaminant
characteristics. EPA has revised its dermal risk assessment guidance since the 1993 risk
assessment for the Site. In addition, EPA Region 7 now uses a different approach for estimating
health risks from inhalation of VOCs during household activities. These changes in risk
assessment procedure may alter some of the input parameters used in the 1993 risk assessment,
but would not significantly alter the conclusions.

Question C: Has anv other information come to light that could call into question the
protectiveness of the remedy?

A review of ecological risks was performed for this five-year review and concludes that
the ecological risks at this Site are low. Contaminated soil is the only potentially complete
exposure pathway since the groundwater plume does not extend to surface water features.
However, the soil pathway is not a concern given that the entire area around the main source area
is covered with concrete.

There have been no natural disasters at the Site, and no other information has come to
light that would call into question the protectiveness of the remedies.

17


-------
VIII. Issues

Table 8-1 below summarizes the major issues identified during the review and whether
those issues affect the protectiveness of the remedy.

Table 8-1

Issues Identified During the Five-Year Review

Issues Identified

Affects Current
Protectiveness?
(Y/N)

Affects Future

Protectiveness?

(Y/N)

AR for OUs 1-4 missing at library

N

N

Sampling ports on air stripper not clearly labeled

N

N

GET system not enough to meet RAOs in reasonable
time frame

N

N

O&M Plan and Manual for GET and SVE systems
need to be updated to reflect system modifications
made during optimization

N

N

OU 5 SVE system unable to address shallow soils

N

Y« if land use
changes

18


-------
IX. Recommendations and Follow-up Actions

Table 9-1 below identifies the recommendations and follow-up actions identified during
the five-year review.

Table 9-1

Recommendations and Follow-up Actions

Issue

Recommendation or
Follow-up Action

Party

Responsible

Oversight
Agency

Milestone
Date

Affects
Proteetiveness
(Y/N) '

Current

Future

AR for OUS 1-4
missing at library

Generate copy of AR
and send both hard
copy and CD to
library

EPA

None

9/30/08

N

N

Sampling ports on
air stripper not
labeled

Label sampling ports
on air stripper

LTRA
contractor

EPA

9/30/08

N

N

GET system not
enough to meet
RAOs in
reasonable time
frame

Evaluate additional
technologies to
address source area

LTRA
Contractor

EPA

6/30/09

N

N

O&M Plan and
manual for GET
and SVE system
need to be updated

Update O&M Plan
and manual for GET
and SVE system

LTRA
contractor

EPA

Following
completion
of pilot
studies and
remedy
modifications

N

N

OU 5 SVE system
unable t o address
shallow soils

Consider alternate
means to address
shallow soils in OU 5

UPRR

EPA

6/30/09

N

Y, if

land
use

changes

19


-------
X. Protectiveness Statements

Operable Units 1 and 2

The remedies at OUs 1 and 2 are protective of human health and the environment, and in the
interim, exposure pathways that could result in unacceptable risks are being controlled. Both RAs
are operating as designed. However, the SVE system which began operating as OU 1 for the purpose
of addressing source soils is now being operated as part of the OU 2 RA to address groundwater
contamination. Exposure pathways are being controlled through plume containment, treatment, and
long-term monitoring. The vapor intrusion pathway was evaluated in 2007 and determined to be of
no concern. There are no groundwater exposures since all businesses and residents in the area are
connected to city water and city ordinance prohibits the installation of private water wells in the
vicinity of the Site.

Operable Units 3 and 4

The remedies at OUs 3 and 4 are protective of human health and the environment, and in the
interim, exposure pathways that could result in unacceptable risks are being controlled. The OUs 3
and 4 remedies consist of groundwater monitoring events to be conducted at least once every five
years to support five-year reviews. All deep wells continue to show PCE levels well below the MCL.
The two shallow wells at OU 3 recently showed PCE levels only slightly above the. MCL. The
shallow well at OU 4 showed a PCE level slightly below the MCL. There are no groundwater
exposures since all businesses and residents in the area are connected to city water and city ordinance
prohibits the installation of private water wells in the vicinity of the Site.

Operable Unit 5

The remedy at OU 5 currently protects human health and the environment because the
remedies for addressing VOCs in the groundwater and the vadose zone are functioning as intended
and the ICs are in place. However, in order for the remedy to be protective in the long-term,
additional actions may be necessary to address shallow soils. Long-term protectiveness will be
achieved by modifying the decision document and implementing the necessary remedy modifications
to address shallow soils. Groundwater concentrations have been significantly reduced since the
AS/SVE systems began operating in 2004. Currently, the systems are operated in pulsed mode to
allow periods of rebound to maximize mass removal. In addition, the presence of LNAPL has been
reduced to only a few wells. The only remaining concern relates to shallow soil concentrations
which do not appear to be responding to the SVE system. The UPRR has proposed an alternative for
excavating and treating the shallow soils, EPA plans to consider this approach and may modify the
decision document in the near future. Groundwater exposures are being controlled since all
businesses and residents in the area are connected to city water supply and city ordinance prohibits
the installation and use of private water wells in the vicinity of the Site. Soil exposures are controlled
by restricted access and the fact that the property is used for limited industrial purposes.

Overall Protectiveness

Because additional actions are needed to achieve long-term protectiveness at OU 5, the Site
is protective of human health and the environment in the short-term.

20


-------
XI. Next Review

The next five-year review for the Site is required by August 2013, five years from the
date of this review. Prior to the next five-year review, O&M of OU 2 will be turned over to the
state, and completion of the OU 5 remedy is likely.

21


-------
Appendix 1

OU 1 and OU 2 Tables and Fi


-------
\

SVE-4	%

\ % \

\

EW-2

\ \\
/ MW-12A \ \\

"N\^ <
SVE-3—V^y'NW

TjpQnneE'One

Hour Martinizing
'•©raiding

\ ^

\\ \\ \
¦ \ \xX \

\ V\ \
MW-2A\\ V\\ \

^ vv*vi \

-'MW-2B

SVE-2 \ \ V

\\

EW-L

ERT-16

Existing

Building

\V®'\

v\\\ \

\

\t" \

ERT-14

\ \ X\ ^ t
a\ A \\

sve-i —r'f \ \%

5 \ i'-

ERT-151—® \ \ \ \

\\ ' \ \
¦ \ \ \ \
\ \ \ \
\ \ \ \ EW-3
Remediation System \ \ \ • \ /

Building	V \ Y

^ :

¦ \

w

\

&

V

%

%

%

\

Xi

MW-13A

\\

w

w

HGL—Annual Report—Cleburn Street Well Site OU2

Figure 1,2
OU2 Soil and Groundwater
Treatment Well Locations



U.S. EPA Region 7



Legend

®	Extraction Well

~	Monitoring Weil

®	Soil Vapor Extraction Well

©	Storm Sewer Manhole

®	ERT Groundwater Weil

		Groundwater Extraction Line

		Soil Vapor Extraction Line

		Treated Water Discharge Line

N

0 5 10 20 30

Feet

Filename.- XsfEPAQQZ/Oebiirn/MAFSfQPR
SoilGr&mdmterJtfeli Loc.mxd
Project: EPAQOfbl9-U~42-04
Revised; 02/26/08 CV
Source: Jacobs Federal Operations

Interim Xaxedial Action Report
Cleburn Street Site Operable
Units I & 2; 12/23/99

V HGL'

¦2T HydtaGtrqlogk. lr>c


-------
HOL—Annual Report Qeburn Street Well Site
Grand Island, Nebraska

Figure 3.10
PCE in Groundwater
Isoconccntration Map

U.S. EPA Region T

4-

A
7.6

/V

ND .

Legend

Existing Building

Curb Line
Railroad Line -
ERT Groundwater Well
Monitoring Well
EW Weil

Municipal Water Well

SVB Weil

PCE Concentration
October 2007 (pg/L)

PCE Isoconcentration Contour
Line in jtg/L {dashed where inferred)

Not Detected

Note:

B wells were not used for contours.

¦0 23 50

100

150

Feet

¦fVenmt: XMPAOW/aebumMAPS/.
PCEJsoconcentration Map.mxd
Project: BPAQQ$Ql9-ll
Revised: 02/25/08 CY
Source: Grand Island Utilities Depf
fGI5 Bosermp) 2807

Hydro GgoLogfe. Snc


-------
Figure 3.1

PCE Concentrations in GET System Influent and Effluent

3500

3000

2500

2000

1500

1000

500

-Influent
Effluent
MCL

.5? ^ ^ .S»N ^ ^ .5? ^ ^ <£ ^ ^ ^
O V9 0° / Oc ^ O *9 O / o ^ O Vs O 0° ^ O

Date


-------
Figure 3.2

PCE Concentrations - Cleburn Street Well











r

'

-~—PCE
—— MCL
	Trend













1



A . *-A,

			 		|		¦ ' y		 			y	~Safcl^Tr.~$-^--«ISSy.Jg^

<§> # ^ & & & <& & # # $ <§

*+ ** ^	fc/' >*v t'V J'V k'	W / ~	k/w *** te#v	k^v

,8 o ^ o »s o ^ o° ** o »s o V» o ^ o / o ^ o

f O f

Date


-------
Figure 3: PCE Concentrations In Combined SVE Influent Line

Time (hr)


-------
Appendix 2

Summary of OU 3 and OU 4 Ground Water Data


-------
Appendix 2.0
Summary of April 2008 Groundwater Data

OU3 and OU4

Well kknlifieation

Screen Interval

PC1: < oncciitimion





WtKKKKKKKMKtM

Maximum ('ontamirrui^ 1 c\cl <\1CL)

¦¦¦¦¦¦MIMl

iiiilMliS^Bi^^Miaisaisls



MW-IA

14.4- ,l>"

i I-

MW-1A (Duplicate)

14.4 - 29.6

12.6

MW-1B

76.7 - 86.4

ND (1.0)

MW-1C

13 -28

6.04

MW-1D

_x:_ XS.-

ND (1.0)

MW-I \

IS 1 V> 0

4.76

MW-4C

17.5-32.5

ND (1.0)

MW-4D

85-95

ND (1.0)

Trip Blank

n/a

ND (1.0)

FB-01

n/a

ND(l.O)

RB-01

n/a

ND (1.0)

Notes:

1.	ft bgs = feet below ground surface.

2.	ND = Compound not detected at or above the detection limit provided in
parentheses.


-------
£XY\ i\ 1 V ^

ppCIlulX J

OU 5 Tables and Figures


-------

-------
Groundwater Analytical Data Summary
Clebum Street OU5
Grand Island, Nebraska







MWN-1A

MWN-1B

MWN-2

MWN-3A

MWN-3B

Contaminant -

Goal

Unit

Apr-98

Mar-08

Apr-98

Mar-08

Apr-98

Mar-08

Apr-98

Mar-08

Apr-98

Mar-08



























cis-1,2-Dichloroethene

70

M9/L

<5.0

<1.0

<5.0

< 1.0

810

1.69 '

<5.0

< 1.0

390

1.69

Ethylbenzene

700

MS/L

<5.0

<1.0

<5.0

< 1.0

<5.0

<1.0

<5.0

< 1.0

<5.0

<1.0

Tetrachioroethene (PCE)

5

miL

52

7.15

<5,0

< 1.0

58

2.32

<5.0

< 1.0

1,600

3.31

Toluene

1,000

mil

<5.0

<1.0

<5.0

< 1.0

<5.0

< 1.0

< 5.0

< 1.0

<5.0

< 1.0

Trichloroethene (TCE)

5

mil

<5.0

45.2

<5.0

< 1.0

11

< 1.0

<5.0

< 1,0

100

<1.0

Total Xylenes

10,000

ms/l

<5.0

<3.0

<5.0

<3.0

25

<3.0

<5.0

<3.0

<5.0

<3.0


-------
Groundwater Analytical Data Summary
Cleburn Street OU5
Grand Island, Nebraska







MWN-4

MWN-5

MWN-6A

MWN-6B

MWN-7

Contaminant

Goal

Unit

Apr-98

Mar-08

Apr-98

Mar-08

Apr-98

Mar-08

Apr-98

Mar-08

Apr-98

Mar-08





-





















cis-1,2-Dichloroethene

70

ug/L

<5.0

< 1.0

<5.0

< 1.0

¦ <5.0

< 1.0

<5.0

< 1.0

<5.0

<1.0

Ethylbenzene

700

Mg/L

<5.0

<1.0

<5.0

<1.0

<5.0

< 1.0

<5.0

< 1.0

<5.0

<1.0

Tetrachloroethene (PCE)

5

Mg/L

6.9

< 1.0

<5.0

< 1.0

< 5.0

< 1.0

<5.0

< 1.0

13

6.95

Toluene

1,000

Mg/L

<5.0

< 1.0

<5.0

<1.0

<5.0

< 1.0

<5.0

< 1.0

<5.0

< 1.0

Trichloroethene (TCE)

5

ug/L

<5.0

< 1.0

< 5.0

< 1.0

<5.0

< 1.0

<5.0

< 1.0

<5.0

< 1.0

Total Xylenes

10,000

M9/L

<5.0

< 3.0

<5.0

<3.0

< 5.0

<3.0

<5.0

<3.0

<5.0

<3,0


-------
Groundwater Analytical Data Summary
Cleburn Street OU5
Grand Island, Nebraska







MWN-8

MWN-8R

MWN-9

MWN-10A

MWN-10B

MWN-11

Contaminant

Goal

Unit

Apr-98

Mar-08

Apr-98

Mar-08

Apr-98

Mar-08

Apr-98

Mar-08

Aug-00

Mar-08



























cis-1,2-Dichloroethene

70

M9/L

<5.0

< 1.0

<5.0

< 1.0

11,000

127

<5.0

< 1.0

< 1.0

< 1.0

Ethylbenzene

700

M9/L

<5.0

- <1.0

<5.0

< 1.0

5,000

< 1.0

7.6

< 1.0

< 1.0

< 1.0

Tetrachloroethene (PCE)

5

MQ/L

<5.0

1.37

3

1.28

5,000

9.4

13

< 1.0

< 1.0

< 1.0

Toluene

1,000

pg/L

<5.0

< 1.0

<5.0

< 1.0

8,200

< 1.0

3

< 1.0

< 1.0

< 1.0

T richloroethene (TCE)

5

mil

<5.0

< 1.0

<5.0

< 1.0

76

< 1.0

<5.0

< 1.0

< 1.0

< 1.0

Total Xylenes

10,000

ms/l

<5.0

<3.0

<5.0

<3,0

19,000

<3.0

26

<3.0

<3.0

<3.0


-------
Groundwater Analytical Data Summary
Cleburn Street OU5 .

Grand. Island, Nebraska







MWN-12

MWN-13

MWN-14

MWN-15

Contaminant

Goal

Unit

Aug-00

Mar-08

Aug-00

Mar-08

Aug-00

Mar-08 .

Aug-00

Mar-08























cis-1,2-Dichloroethene

70

pg/i

< 1.0

<1.0

< 1.0

<1.0

< 1.0

< 1.0

< 1.0

1.02

Ethylbenzene

700

pg/L

< 1.0

<1.0

<1.0

¦ <1.0

<1.0

<1.0

< 1.0 ;

<1.0

Tetrachloroethene (PCE)

5

pg/L

< 1.0

<1.0

< 1.0

<1.0

< 1.0

< 1.0

< 1.0

< 1.0

Toluene

1,000 •

pg/L

< 1.0

<1.0

< 1.0

< 1.0

<1.0

< 1.0

< 1.0

< 1.0

Trichloroethene (ICE)

5

Mg/L

< 1.0

<1.0

<1.0

< 1.0

<1.0

< 1.0

< 1.0

< 1.0

Total Xylenes

10,000

pg/L

<3.0

<3.0

<3.0

<3.0

<3.0

<3.0

<3.0

<3.0


-------
;6$l4Ki
-------
Appendix 4

List of Documents Reviewed


-------
List of Documents Reviewed

Second Five Year Review for the Cleburn Street Well Site

First Five Year Review

EPA

Vptember 30,2003

OU1-4 Record of Decision

FPA

June 7,1996

OU5 Record of Decision

FPA

J**/ A * V

September 10,2001

Technical Assessment for

EPA

May 27, 2008

Ecological Risk





Technical Assessment for

EPA

June 19,2008

Human Health Risk





Preliminary Closeout

EPA

August 2004

Report





Groundwater Sampling

Tetra Tech

June 4,2008

Report for OU3 and OU4





Letter Regarding OU1 SVE
• System, OU3 and OU4

NDEQ

April 4,2006

Remediation System
Evaluation Report

EPA '

July 30,2001

Source Investigation Report

Hydrogeologic, Inc.

February 22, 2007

2007 Annual Performance

Hydrogeologic, Inc.

March 2008

Report, OU2





Start-up/Semi-annual
Performance Report, OU1
and OU2

Sverdrup

September 15,1999

Second Semi-annual'
. Performance Report, OU 1
and OU2

Sverdrup

September 29, 1999

Interim Remedial Action

Sverdrup

December 29,1999

Report, OU1 and OU2





Final Remedial Action ¦

EPA

July 14,1999

Report, OU3 and OU4





Technical Memorandum on

Hydrogeologic, Inc.

April 16,2008

SVE System Operation .





Operations Reports, OU2

Hydrogeologic, Inc.

Multiple reports


-------
Appendix 5

Institutional Control - City Ordinance


-------
Grand Island City Code

Chapter 35

Article VI. Groundwater Control Area No. 1

835 -60, Purpose

The United States Environmental Protection Agency issued a Record of Decision (ROD) for the Clefaum
¦ Street Well Superfund Site on June 7, 1996. which identified three sources.of subsurface soil and groundwater
contamination. These sources included the former One Hour Martinizing facility. Liberty Cleaners and Shirt
Launderers, and Ideal Cleaners, The former Nebraska Solvent Company was identified as a possible fourth
contamination source subject to subsequent evaluation and testing. The ROD described selected remedies for the
three source areas, an element of which required the City of Grand Island to enact and enforce.institutional control
ordinances designating a Groundwater Control Area No. 1 in which groundwater use would be restricted to prevent
human exposure and consumption of potentially contaminated groundwater, requiring registration of existing wells
and requiring approval and registration of new wells. The institutional control ordinances are to remain in full force
and effect until the groundwater contamination identified in the ROD is reduced to a level making the groundwater
safe to be used as a source of drinking water'pursuant to 42 USC §300g, et seq.. the Safe Drinking Water Act, or its
successor legislation.	.

§35-61. Definitions

As used in this Article, the following terms mean: •

Groundwater means water pumped from a well located within the Groundwater Control Area No. 1 described
in Section 35-62.

Groundwater Con lam i nation means the chemicals of concern (COC) described in the United Slates
Environmental Protection Agency Record of Decision (ROD) for the Clebum Street Well Superfund Site date
June 7, 1996, which was received and accepted by the Mayor and City Council pursuant to Resolution 98-28.

Groundwater Control Area No. 1 means a defined area-within the corporate limits of the City of Grand Island
subject to the institutional controls.provided in this Article which are intended to prohibit human consumption
of potentially contaminated groundwater from wells.

Well means a hole or shaft sunk into the earth in order to obtain water from a natural subterranean supply or
aquifer.

The definitions found in Neb. Rev. Stat., Chapter 46 - Irrigation and Regulation of Water are adopted by reference,
except where such definitions arc in conflict with those provided in this section above.

§35-62. Groundwater Control Area Boundaries

The outer boundaries of the Groundwater Control Area No. 1 are described as follows: Commencing at the
southeasterly comer of the intersection of 9ft Street and Adams Street; thence running northeasterly along the south
boundary of 9* Street to the southwesterly comer of the intersection of 9th Street and Sycamore Street; thence running
southeasterly along the west boundary of Sycamore Street to the northwesterly corner of the intersection of Sycamore
Street "and 1st Street; thence running southwesterly along the north boundary of 1st Street to the northwesterly corner
of the intersection of 1st Street and Locust Street; thence running southerly along the west boundary of Locust Street

33


-------
to the intersection of Locust Street and Division Street; thence, running southwesterly along the north boundary of
Division Street 10 the northeasterly corner of the intersection of Division Street and Adams Street; thence running
northwesterly along the east boundary of Adams Street lo the point of beginning.

§35-63. Duration of Institutional Control Ordinance

, (A) This Article shall remain in full force and effect for an initial term of twenty-live (25) years from the
effective date following approval and adoption by the Mayor and City Council.¦

(B) The term of this Article may be extended by the Mayor and City Council if at the end of the initial term
there remains groundwater contamination identified in the ROD described in Section 35-60 making the
groundwater unsafe to be used as a source-of drinking water pursuant to the Safe Drinking Water Act or its ,
successor legislation.

' (C) in the event the City of Grand Island is notified during the initial term by the Environmental Protection
Agency that groundwater contamination within the Groundwater Control Area No. 1 has been reduced to a
• level making the groundwater safe to be used as a source of drinking water pursuant to the Safe Drinking

Water Act or its successor'legislation, the Mayor and City Council may proceed to repeal this Article
¦ forthwith.

§35-64. Prohibited Groundwater Uses	'

(A) Groundwater pumped from wells within the Groundwater Control Area No. 1 shall not be used for any .
human consumption including drinking water, cooking, washing or other household uses. Because
groundwater from wells within the groundwater control area may be contaminated and present a hazard to the
health, safety and welfare of persons exposed to said water, any known human consumption of groundwater
from wells within the Groundwater Control Area No. 1 is a violation of this Article and is declared a public
nuisance subject to abatement as provided hereafter.

' ¦ (B) This Article shall not apply to uses of groundwater pumped from wells within the Groundwater Control
Area No, I which do not involve human consumption, including, but not limited to, non-contact cooling wate
for industrial, commercial or residential uses and watering of vegetation other than gardens, plants and trees
producing food for human consumption.

§35-65. Well Registration

(A)	All wells for which drilling has commenced or existing within the Groundwater Control Area No, 1 as of

the effective date of this Article shall be registered with the Building Department by the person owning the .
real estate on which the well is located. There shall be no fee for registering an existing well.

(B)	No person shall drill or install a well within the Groundwater Control Area No. 1 prior to applying for and
obtaining a well permit from the Building Department. There shall be a nonrefundable fee in accordance with
the City of Grand Island Fee Schedule paid to the Building Department contemporaneously with making an
application for a well permit.

34


-------
§35-66. Existing Well Registration, Information Required

The following information shall be submitted to the Building Department in connection with registering a wel
in existence as of the effective dale of this Article;

(A)	The name and address of the person owning the real estate on which the well is located.

(B)	The address and legal description of the property on which the well is located.

(C)	The address of all properties being served by groundwater pumped from the well.

(D)	A description of the uses of the water pumped from the well, including specifically whether such
groundwater is used for human consumption including, but not limited to drinking, cooking, washing, or othei
household uses,

(E)	Whether City water is available to the property currently served by the well.

(F)	The depth of the well, if known.

¦(G) A diagram showing the location of the well.

§35-67. New Well Registration, Application for Well Permit

The following information shall be submitted to the Building Department in connection with applying for a well
permit for a new well in the Groundwater Control Area No. 1;

(A)	The name and address of the person owning the real estate on which the proposed well is to be located.

(B)	The address and legal description of the property on which the proposed well is to be located.

(C)	The address of all properties to be served by groundwater pumped from the proposed well.

(D)	A description of the uses to be made of water pumped from the proposed well, including a certification
that said groundwater will not be used for human consumption, including but not limited to drinking, cooking,
washing, or other household uses,

(E)	Whether City water is available to the property to be served by the proposed well.

(F)	The depth of the proposed well,

(G)	A diagram showing the location of the proposed well.

§35-68. Violations of Institutional Control Ordinance, Abatement of Public Nuisance

Whenever the Building Department Director, or his/her designee has inspected any well within the
Groundwater Control Area No. 1 and determined that groundwater pumped from the well is being used in violation of
this Article, he/she shall send a written notice to the owner of record or owner's duly authorized agent, or person in

35


-------
possession, charge or control, or to' the, occupant by ordinary first-class mail and by certified mail, return receipt
requested, notifying the addressee of the violation, The written notice shall contain the following information;

(A)	The street address and a legal description sufficient for identification of the premises on which the well is
located.

(B)	A brief and concise description of the acts or circumstances constituting a violation of this Article,

(C)	A brief and concise description of the corrective action required to be taken to render the well and
groundwater uses in compliance with this code.

(D)	A brief and concise statement advising the addressee that if the well and groundwater uses are not broughi
into compliance with this Article within the time specified, that the Building Department Director, or his/her
designee may order electrical power to the well disconnected and may request the City Attorney, with the
consent of the Mayor, to file an action to abate the public nuisance and charge the costs thereof against the rea
estate, the owner of record and the addressee. . ¦	¦

§35-69. Procedure for Abatement of Public Nuisance

If the addressee of the written notice described in Section 35-68 fails to abate said nuisance within the time
specified, the City of Grand Island, at the written request of the Building Department Director, or his/her designee
di rected to the City Attorney, and with the consent of the Mayor, may proceed to abate said public nuisance pursuant
to Section 20-15 of the Grand Island City Code, and charge the costs thereof against the real estate on which the well
is located and the addressee of the written notice.

In the event the use of the groundwater in violation of this Article might cause irreparable harm or poses a threat to'
public health, safety or welfare, or the health, safety or welfare of the persons using the groundwater, the written
notice to abate pursuant to Section 20-15 shall not be required as a condition precedent to commencing a legal action
to obtain abatement of the nuisance. The City of Grand Island, with the consent .of the Mayor, may immediately file
an action requesting such temporary and permanent orders as are appropriate to expeditiously and permanently abate
said public nuisances and protect the public health,, safety or welfare or the health, safety or welfare of persons using
the groundwater in violation of this Article.

36


-------