Community Update for
I American Cyanamid
Superfund Site

Quarterly Update

Volume III, Summer 2013

Introduction

The U.S. Environmental Protection Agency (EPA) is issuing this quarterly update to inform the
community and local officials about the status of the American Cyanamid Superfund Site (Site) in
Bridgewater Township, New Jersey. The quarterly updates will focus on major tasks completed at the
Site over the previous three (3) months, as well as provide important notice(s) to anticipated future
events. EPA, CRISIS (the recipient of an EPA technical assistance grant), and the Site owner (Wyeth
Holdings Corporation, a wholly-owned subsidiary of Pfizer, Inc.) provide updated information on the
Site at the following web sites:

•	http://www.epa.gov/region02/superfund/npl/american cyanamid/

•	http://www.crisistoxicwatch.org

•	http://www.amcvrestoration.com

•	http://health.bridgewaterni.gov/

Site-wide Remedy Status

EPA issued a Record of Decision in September 2012 to address contaminated soils, ground water, and
impoundments that have not been previously addressed, with the exception of Impoundments 1 and 2.
This remedy, referred to as the site-wide remedy, called for the treatment via in-situ
solidification/stabilization and/or the installation of engineered capping systems to address three highly
contaminated impoundments and all site soils, as well as the collection and treatment of site-related
contaminated groundwater. The remedy also called for the completion of an ecological risk
assessment to determine whether three additional impoundments would require excavation and
relocation. A settlement agreement was executed in March 2013 for the remedial design of the site-
wide remedy, as well as for the completion of a focused feasibility study (FFS) for impoundments 1
and 2. The remedial design of the site-wide remedy is currently underway and is generally being
addressed in two components: (1) impoundments and site-wide soils; and, (2) groundwater. It is
currently anticipated that the design of these two remedial components will be completed in 2015.

Focused Feasibility Study for Impoundments 1 and 2

Due to the unique and highly complex nature of the contaminants within Impoundments 1 and 2 and
their proximity to the Raritan River, these two impoundments were not included in the Site-wide
remedy and are being addressed separately through a FFS. A lab treatability study was completed on
the contents of these impoundments in August 2012 and, based upon the results, it was concluded that
solidification/stabilization, thermal treatment, or a combination of the two technologies could
potentially be implemented for these two impoundments and that field-scale testing is necessary. It is
anticipated that the design of a field-scale pilot study will be completed by Fall 2013, followed by the
construction of the pilot system later in 2013 with the implementation of the actual pilot testing in late


-------
2013 into early 2014. A public information session will be held prior to initiating the pilot test in order
to inform the community of the details of the study, as well as to address all community concerns.

Impoundments 1 and 2 Area Ground Water Removal Action

In May 2012, a ground water collection and treatment system was completed under the oversight of
EPA's Removal Program to address ground water discharges (i.e. seeps) into the Raritan River and
continues to operate. This system includes a collection trench to intercept and capture impacted ground
water, a containment wall to further prevent the migration of impacted ground water to surface water,
and an interim treatment plant to treat collected ground water prior to its discharge. The interim
treatment system, as well as new ground water inputs and bedrock ground water currently conveyed to
the local sewerage authority, will eventually be incorporated into the Site-wide remedy.

Ambient Air Monitoring

The Site owner continues to implement a quarterly monitoring program for ambient air to use as a
baseline during the implementation of the Site-wide remedy. The monitoring program includes eight
locations along the perimeter of the Site and another four locations in the vicinity of impoundments 1
and 2. The results of the recent quarterly monitoring events have exhibited low level concentrations of
constituents consistent with urban background monitoring stations measured by the New Jersey
Department of Environmental Protection.

Surface Water & Sediment Monitoring

The Site owner continues to implement a quarterly surface water and sediment monitoring program,
which includes an expansive analyte list with over 20 surface water and sediment monitoring stations
located throughout the Raritan River, Cuckel's Brook, the Millstone River, and Middle Brook. The
results of the 1st and 2nd quarter monitoring events continue to indicate significant reductions in
benzene concentrations near the previously discovered seep discharge points suggesting that the
groundwater capture system is operating effectively. Contaminant concentrations in Cuckel's Brook
have generally increased in the most recent monitoring events, which is primarily believed to have
occurred due to the re-routing of the local sewerage authority's discharge from Cuckel's Brook to the
Raritan River, resulting in less dilution in the brook. In early May, a discharge was identified in
Cuckel's Brook containing elevated levels of benzene, chlorobenzene, xylene, toluene and acetone. A
reconnaissance of the brook conducted in mid-June resulted in the identification of several other
potential seeps. These potential seeps were sampled in mid-July and the analytical results, which are
expected in August 2013, will be utilized to determine whether further action is required.

Ground Water Monitoring

The Site owner continues to implement a semi-annual groundwater monitoring program, which
includes monitoring of ground water quality and the extraction of bedrock ground water at a minimum
rate of 650,000 gallons per day. The results of the November 2012 monitoring event are currently
available and the results of the May 2013 monitoring event will be available in the next quarter.

If you have any questions about the information in this quarterly update, please contact the EPA
community involvement coordinator, Melissa Dimas at dimas.melissa@epa.gov or 212-637-3677.

http://www.epa.gov/region02/superfund/npl/american_cyanamid/


-------