OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX



United States Environmental Protection Agency

Stormwater Management Including Discharges for
Newly Developed and Redeveloped Sites

Industry Questionnaire

Survey ID:

Industry Questionnaire

Page 1 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

General Information

Purpose of the Questionnaire

Stormwater discharges from newly developed and redeveloped land can negatively
impact water quality through increases in stormwater volume and increased pollutant
loads to the receiving waters. This Information Collection Request (ICR) will collect
data to inform decisions regarding how the nation's stormwater regulations should be
strengthened, including additional provisions for stormwater discharges from newly
developed and redeveloped sites.

EPA is issuing the following questionnaire to owners, developers, and contractors of new
and redeveloped sites to provide EPA with information to:

>	Determine current usage, availability, design, and cost of post construction
stormwater controls, BMPs, and retention practices;

>	Assess the compliance costs and pollutant and flow reductions associated with
various regulatory options to control post construction stormwater from newly
and redeveloped sites; and

>	Characterize the economic status of the construction industry that could be
subject to revised regulations and estimate the impact of compliance costs.

The survey is presented in four sections covering the following topic areas:

>	Section A:

>	Section B:

>	Section C:

>	Section D:

General Information
Firm Financial Information

Project Level Information for Owners/General Contractors

Project Level Information for Non-Owners/General
Contractors

> Section E: Certification

Industry Questionnaire

Page 2 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

General Information, Continued

Authority

EPA has authority to administer this questionnaire under section 308 of the Clean Water
Act (Federal Water Pollution Control Act, 22 U.S.C. Section 1318). Participation in this
questionnaire is mandatory, and you are required to respond. You must retain a
copy of the completed questionnaire for your files. EPA may contact you with follow-
up questions to clarify your answers. Late filing of the questionnaire, or failure to
follow any related EPA instruction, may results in civil penalties, criminal fines, or
other sanctions provided by law including the possibility of fines and imprisonment
as explained in Section 308 of the Clean Water Act (33 U.S.C., Section 1318).

When to Complete the Questionnaire

The response to this questionnaire must be received by EPA no more than 60 calendar
days after receiving it.

If you wish to request an extension, you must do so in writing no later than one week of
the due date of this questionnaire. Written requests may be e-mailed to Mr. Brian
D'Amico at damico.brian@epa.gov.

Where to Return the Questionnaire

After completing the questionnaire and certifying the information that it contains, use the
enclosed mailing label to mail the completed questionnaire to:

U.S. Environmental Protection Agency

Stormwater Management Including Discharges from Newly Developed and

Redeveloped Sites Industry Questionnaire

c/o Eastern Research Group, Inc.

14555 Avion Parkway, Suite 200

Chantilly, VA 20151

Certification Statement

The individual responsible for directing or supervising the preparation of the
questionnaire must read and sign the Certification Statement listed below. The certifying
official must be a responsible corporate official or his/her authorized representative.

Where to Get Help

If you have any questions regarding completion of this questionnaire you can request
assistance using EPA's e-mail helpline provided below. Please include the name of the
survey to which you are responding, the question number along with your questions.
Respondents who desire assistance by telephone should send an e-mail with "Please Call

Industry Questionnaire

Page 3 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

Me" in the subject line. Please provide the call-back phone number, contact name, and
desired day and time to call. The return phone call will be free of charge to the
respondent.

E-mail address for help line:	

Confidential Business Information

Regulations governing the confidentiality of business information are contained in the
Code of Federal Regulations (CFR) at Title 40 Part 2, Subpart B. You may assert a
business confidentiality claim covering part or all of the information you submit, other
than effluent data and information or data that is otherwise publicly available, as
described in 40 CFR 2.203(b):

"(b) Method and time of asserting business confidentiality claim. A business which is
submitting information to EPA may assert a business confidentiality claim covering the
information by placing on (or attaching to) the information, at the time it is submitted to
EPA, a cover sheet, stamped or typed legend, or other suitable form of notice complying
language such as 'trade secret,' 'proprietary,' or 'company confidential.' Allegedly
confidential portions of otherwise nonconfidential documents should be clearly identified
by the business, and may be submitted separately to facilitate identification and handling
by EPA. If the business desires confidential treatment only until a certain date or until
the occurrence of a certain event, the notice should so state."

If no business confidentiality claim accompanies the information when it is received
by EPA, EPA may make the information available to the public without further
notice.

You may claim as confidential all information included in the response to a question by
checking the Confidential Business Information (CBI) box next to the question number.

Note that you may be asked to justify any claim of confidentiality at a later time, for
example if someone requests access to your data. Note also that airport effluent data are
not eligible for confidential treatment, pursuant to Section 308(b) of the Clean Water Act.
In addition, information that is publicly available should not be claimed confidential.

Note also that information claimed confidential cannot be accessed or used by the
industry to evaluate data and analyses supporting the national effluent guidelines
regulations.

Information covered by a claim of confidentiality will be disclosed by EPA only to the
extent of, and by means of, the procedures set forth in 40 CFR Part 2, Subpart B. In
general, submitted information protected by a business confidentiality claim may be
disclosed to other employees, officers, or authorized representatives of the United States
concerned with implementing the Clean Water Act. The authorized representatives
include employees of other executive branch agencies, who may review CBI during the
course of reviewing draft regulations.

Industry Questionnaire

Page 4 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

Information covered by a claim of confidentiality will be made available to EPA
contractors to enable the contractors to perform the work required by their contracts with
EPA. All EPA contracts provide that contractor employees use the information only for
the purpose of performing the work required by their contracts and will not disclose any
CBI to anyone other than EPA without prior written approval from each affected business
or from EPA's legal office.

Industry Questionnaire

Page 5 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

Detailed Instructions for Completing the Questionnaire

Complete the questionnaire considering the following instructions:

>	Personnel most knowledgeable about the subject areas covered by a specific section
should complete that section of the questionnaire.

>	For all questions and sections, read all instructions and definitions carefully. Pay
particular attention to the distinction between establishments and firms.

>	Do not leave any entry blank. If the answer is zero, write "0" or "zero". If a question
is not applicable, write "NA "

>	Answer all of the questions in sequence unless you are directed to SKIP forward in
the questionnaire. This is important since some questions and/or sections are only
applicable to some respondents.

>	Use the units specified when responding to questions requesting measurement data
(e.g., acres). If not specified and applicable, include units in your response

>	The period of interest for the survey is fiscal year (FY) 2005-2009 unless indicated
otherwise.

>	Provide the requested information based on data you currently have. EPA is not
requesting or recommending that respondents collect new data to provide information
for this survey.

>	When requested financial information is available in your balance sheets, you may
attach them as opposed to filling out the associated questions. Be sure to identify, in
the appropriate comment section, which questions responses are fulfilled with the
balance sheets.

Industry Questionnaire

Page 6 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

Definitions

These definitions are for the purpose of this questionnaire only.

Term

Definition

Bioretention

A system for controlling runoff using soils and plants. Surface runoff
is directed into shallow, landscaped depressions. These depressions
are designed to incorporate many of the pollutant removal
mechanisms that operate in forested ecosystems. In some cases,
filtered runoff is collected in a perforated underdrain and returned to
the storm drain system or is discharged into another stormwater
management device.

Catch Basin

A chamber or sump, typically at curb level, through which
stormwater runoff enters a conveyance system. Sediment may be
retained in a low area beneath the outlet to the conveyance system.

Commercial/Institutional

Designed for use by retail, wholesale, office, hotel, or service users

Contract Builder

A person who or business who has entered into a contract with
someone to build or construct a structure for them

Constructed Wetland

A constructed wetland is a man-made basin that contains water, a
substrate (soil, gravel, rock, organic materials, etc.), plants (vascular
and non-vascular), and organisms similar to those usually found in
natural wetlands. The number of plants and the biodiversity of a
constructed wetland are greater than that of wet retention pond.
Constructed wetlands usually use a relatively impermeable
subsurface layer to prevent water from seeping into the ground.

Curb and Gutter

A roadside curb with a gutter that provides an improved drainage,
typically along roadways.

Detention Basin (Dry
Pond)

A stormwater control structure into which storm runoff is directed to
control both water quality and quantity. The outlets to the basin are
designed to detain and treat stormwater runoff through settling over
a period of time. The storm runoff storage also decreases peak flow.
Dry ponds are not designed to permanently contain water.

Developer

Owner's agent who is responsible for handling the construction and
development

Establishment

A single physical location where business is conducted, or where
services are performed

Firm

A business organization or entity consisting of one or more domestic
establishment locations under common ownership or control

General/Lead Contractor

A person who or business that performs or supervises the
construction or development of a property pursuant to the terms of a
primary contract with the property owner. The general contractor
may use its own employees to perform the work and/or the services

Industry Questionnaire

Page 7 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX



of other contractors called subcontractors

Green Roofs

Green roofs are vegetated and reduce runoff from the rooftop by
absorbing some stormwater and slowing stormwater flow.

Industrial

Designed for industrial purposes such as factories

Infiltration Basins and
Trenches/Dry Well

A rock-filled trench with no outlet. Typically stormwater first passes
through a swale or other stormwater management application before
reaching the trench. The stormwater filters through the soil.

Linear Projects

A construction project including, roads and pipelines that are
substantially longer than they are wide.

Linear - Transportation

Includes uses such as highways and bridges

Linear - Utility

Includes uses such as water and gas pipelines and powerlines

Manufactured Devices

A manufactured device which is designed to intercept stormwater
runoff and prevent the transfer of pollutants downstream.

Mixed Use

Designed/used for more than one land use category

Multifamily Residential

Housing where multiple separate housing units for residential (ie
non-commercial) inhabitants are contained within one building; also
known as multi-dwelling unit

Municipal Separate Storm
Sewer System (MS4)

A conveyance or system of conveyances that is owned by a state,
city, town, village, or other public entity that discharges to waters of
the United States. The system is designed or used to collect or
convey stormwater (including storm drains, pipes, ditches, etc.) but
is not part of a Publicly Owned Treatment Works (sewage treatment
plant).

Newly Developed/New
Construction

Construction that occurs on previously undeveloped lots including
infill which is new development within existing developed areas

Owner

The firm, individual, or institutions for whom the project is being
built

Permeable Pavement

Pavement composed of a permeable pavement surface, which allows
infiltration into the subsoil. There may also be an underlying stone
reservoir that temporarily stores the surface runoff before it
infiltrates into the subsoil.

Redeveloped

A developed site that has been previously developed and is typically
covered or partially covered with impervious or compacted surface.
Redeveloped areas do not include alterations to the interior of an
existing structure.

Retention Basin (Wet
Pond)

A stormwater control structure with a permanent pool of water into
which storm runoff is directed to control both water quality and
quantity. Runoff from each storm is retained and treated, and
sediment particles and associated pollutants settle out, until the water

Industry Questionnaire

Page 8 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX



is displaced by runoff from a later storm.

Retention Practices

Stormwater techniques which infiltrate, evapotranspirate and reuse
rainfall in order to reduce off-site surface runoff.

Single-Family Residential

Housing unit designed and maintained for occupancy by only one
family.

Stormwater Control
System

The management of stormwater on or off site, including detention,
retention and infiltration.

Subcontractor

A person or company under contract to perform work for a
developer or a general contractor

Swales: Grassed

A broad, shallow channel used for conveying stormwater runoff.
Grass on the side slopes and bottom acts to slow runoff velocity, trap
particulates, and promote infiltration. Grassed swales are often
referred to as bio-swales, enhanced swales, or water quality swales
and can be classified as wet swales, dry swales, and grassed
channels. See Swales: Other Vegetation.

Swales: Other vegetation

A broad, shallow channel used for conveying stormwater runoff.
Vegetation on the side slopes and bottom acts to slow runoff
velocity, trap particulates, and promote infiltration. Vegetated swales
are often referred to as bio-swales, enhanced swales, or water quality
swales and can be classified as wet swales, dry swales, and grassed
channels.

A dry swale (bio-swale) incorporates additional elements with the
vegetated swale design. Water treatment is aided by a soil bed (not
necessarily natural soil) with an underdrain system composed of a
perforated pipe surrounded by gravel. Check dams may be used to
temporarily retain stormwater runoff.

A wet swale is capable of temporarily retaining stormwater runoff,
but, unlike the dry swale, lacks an underdrain system. The wet swale
is marshlike and relies on and supports wetland vegetation.

Tree Box

Tree boxes are usually located in urban areas. Runoff is directed to
the treebox, where it can be filtered by the soil and vegetation. Some
tree boxes may drain to a channel below, which conveys stormwater
to the selected collection system.

Industry Questionnaire

Page 9 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

Section A: General Information

A-l Provide contact information for your establishment.
Establishment's Full Legal Name

Address

Phone/Fax Number

Website

A-2 Provide contact information for the person responsible for completing this
section.

Name

Title

Phone/Fax Number

Email

Best Time to Contact

A-3 Indicate the state(s) where your establishment has completed projects in Fiscal
Year (FY) 2005 through FY 2009.

~

AL

~

FL

~

LA

~

NE

~

OK

~

VT

~

AK

~

GA

~

ME

~

NV

~

OR

~

VA

~

AZ

~

HI

~

MD

~

NH

~

PA

~

WA

~

AR

~

ID

~

MA

~

NJ

~

RI

~

WV

~

CA

~

IL

~

MI

~

NM

~

SC

~

WI

~

CO

~

IN

~

MN

~

NY

~

SD

~

WY

~

CT

~

IA

~

MS

~

NC

~

TN





~

DE

~

KS

~

MO

~

ND

~

TX





~

DC

~

KY

~

MT

~

OH

~

UT





Industry Questionnaire

Page 10 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

A-4 Did your establishment complete at least one project from FY 2005
through FY 2009 that meets both of the following criteria?

1.	Your establishment was the owner, developer, general or lead contractor, or
contract builder; and

2.	The project was NOT a pipeline or other utility related activity where the
original land cover was replaced at the end of the project.

~	Yes (Skip to Section B)

~	No (You have completed the survey. Sign the certification statement in Section
E and return to address indicated on page 3)

Industry Questionnaire

Page 11 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

Section B: Firm Financial

B-l Is this establishment independently owned and operated (e.g. the establishment is
the business entity)?

~	Yes (skip to Question B-3)

~	No (continue to the next question)

B-2 Provide contact information for the Firm.

Firm's Full Legal Name
Address

Phone/Fax Number
E-mail

B-3 Indicate the firm's type of business organization.

~	Sole proprietorship

~	Partnership

~	Corporation (standard, "C" corporation)

~	Subchapter S Corporation

~	Limited Liability Corporation

~	Other:	

B-4 In what state is your firm organized as a legal entity?

B-5 When was the start of the firm's current fiscal year?

Month (MM) Year (YYYY)

Industry Questionnaire	Page 12 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

B-6 Indicate the number of months in each year listed below for which you have

financial information for your firm. In some cases, such as for new businesses,
financial records may include only part of a year.

Firm Months of Financial Data

Fiscal Year

2005

2006

2007

2008

2009











~ CBI B-7 Complete the following table with information from your firm's balance sheet.
Provide values to the nearest dollar and fill-in all values, indicating not
applicable categories with a "0".

Firm Balance Sheet Data ($)

Item

Fiscal Year

2005

2006

2007

2008

2009

Assets

Cash, cash
equivalents, and
accounts receivable











Inventories











Completed
construction projects











Construction projects
in progress











Landfor current or
future development











Other











Other Current Assets











Net Fixed Assets











Completed
construction projects
held for the firm's
own accounts (e.g.,
commercial
investment property)











Other net fixed assets











Goodwill and Other
Intangibles











Industry Questionnaire

Page 13 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

Other Non-Current
Assets











Total Assets (Sum of
the above)











Liabilities and Net Worth

Total Current
Liabilities











Long-Term Debt











Deferred Taxes











All Other Non-
Current Liabilities











Total Liabilities (Sum
of the above)











Net Worth











~ CBI B-8 Complete the following table with information from your firm's income

statement. Provide values to the nearest dollar and fill-in all values, indicating not
applicable categories with a "0".

Firm Income Statement Data ($)

Item

Fiscal Year

2005

2006

2007

2008

2009

Revenue











Sale of constructed
projects











Sale of land or other
uncompleted
construction projects











Construction (e.g., as
contract builder) and
related services (e.g.,
design, construction
management)











Other revenue;
Please specify











Cost of Revenue











Gross Margin











Operating Expenses











Operating Income











All Other Expenses











Industry Questionnaire

Page 14 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

Income Before
Interest and Tax











Interest Expense











Profit Before Tax











Tax











Net Income After Tax











~ CBI B-9 Complete the following table with information on your firm's cash flow

statement. Provide values to the nearest dollar and fill-in all values, indicating not
applicable categories with a "0".

Firm Cash Flow Statement Data ($)



Fiscal Year

Item

2005

2006

2007

2008

2009

Cash Flows from











Operating Activities











Income from
Operations











Depreciation Non-
Cash Charges











Net Change in
Accounts











Receivable Accounts











Payable











Change in Inventories











Net Change in Other
Current Assets Current











Liabilities











Net Cash Provided by
Operating A ctivities











Cash Flows from











Investing Activities











Capital Expenditures











Investments











Other Cash Flows











from Investing
Activities











Cash Flows from











Financing Activities











Net Increase/Decrease











in Cash











Industry Questionnaire

Page 15 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

~ CBI B-10 How much of your firm's revenue was generated by performing each of the

following roles during the period FY 2005 through FY 2009? Provide values to
the nearest dollar and fill-in all values, indicating not applicable categories with a

"0".

Revenue ($)

Role

Fiscal Year

2005

2006

2007

2008

2009

Owner/ Developer & Builder











Owner/ Developer











General or Lead Contractor or
Contract Builder











Other Contractor/
Subcontractor Role











Other; Please specify











~ CBI B-l 1 How much of your firm's revenue came from the following categories of

construction activities during the period from FY 2005 through FY 2009? Provide
values to the nearest dollar and fill-in all values, indicating not applicable
categories with a "0".

Revenue ($)

Category

Fiscal Year

2005

2006

2007

2008

2009

New Construction











Redevelopment











Other; Please specify:











~ CBI B-12 How much of your firm's revenue came from the following categories of

activities during the period from FY 2005 through FY 2009? Provide values to the
nearest dollar and fill-in all values, indicating not applicable categories with a "0".

Revenue ($)

Category

Fiscal Year

2005

2006

2007

2008

2009

Single-Family Residential











Multifamily Residential











Commercial/Institutional











Industrial











Industry Questionnaire

Page 16 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

Linear Transportation











Linear Utility











Mixed Use











Other; specify











~ CBI B-13 In the table below, indicate how many full-time equivalent employees your firm
employed at the end of each fiscal year requested. Include all full-time and part-time
employees. Do not include contract labor.

Total Number of Firm Employees (Full-Time Equivalent)

Fiscal Year

2005

2006

2007

2008

2009











B-14 Provide contact information for the person responsible for completing this
section.

Name
Title

Phone/Fax Number
Email

Best Time to Contact

Industry Questionnaire

Page 17 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

Section C Project Level Information

C-l How many projects was your establishment engaged in on the last day of FY
2009?

C-2 How many projects did your establishment complete during the period of FY
2005 through FY 2009?

Number of Pro jects

Category

Project Size (acres)

<1

1-

<3

3-

<5

5-

<7.5

7.5-
<10

10-

<15

15-

<20

20-

<30

30-
<40

40-

<60

60-
<80

80-
<100

>100

Single-Family
Residential



























Multifamily
Residential



























Commercial/Institutio
nal



























Industrial



























Linear -
Transportation



























Linear - Utility



























Mixed Use



























Other



























Total



























C-3 Was your establishment the owner/general contractor for any
project completed during FY 2009?

~	Yes (Complete the remainder of this section)

~	No (Skip to Section D)

~	No completed projects in FY 2009 (Skip to Section E)

For the remainder of Section C, respond to the questions for up to ten completed projects
or all completed projects during FY 2009, whichever is less, and which meet both of the
following criteria:

1.	Your establishment was the owner or general/lead contractor, and

2.	The project was NOT a pipeline or other utility related activity where the original
land cover was replaced at the end of the project

Ten copies of the remainder of Section C are provided for a maximum of ten projects. If
applicable, provide information on projects in each of the following size categories:

>	0-1 Acre,

>	1-5 Acres,

>	5-10 Acres, and

>	>10 Acres.

Industry Questionnaire

Page 18 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

General and Technical Information

C-4 Provide the location of the project.

Street Name:

Town/City:

State:

ZIP Code:

C-5 Was your establishment a National Pollutant Discharge Elimination System
Notice of Intent (NOI) permit holder for this project?

~	Yes CONTINUE to the next question.

~	No SKIP to Question C-7.

C-6 Provide the NOI permit number(s) and attach a copy of each NOI.

C-7 What was the project start and end dates?

Start Date	 End Date	

(MM/DD/YYY)	(MM/DD/YYY)

C-8 What was the duration of each phase of the project and the entire project?

Project Duration

Pro ject Phase

Duration (months)

Land Acquisition



Land Development



Design



Building Construction



Total



Industry Questionnaire

Page 19 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX
C-9 Indicate the project type and size for newly developed and redeveloped sites.

Developed Area Type

Area of the Pro ject (acres)

Total



New

Single-Family Residential



Multifamily Residential



Commercial



Industrial



Institutional



Government



Linear/T ransportation



Other



Redeveloped Area

Single-Family Residential



Multifamily Residential



Commercial



Industrial



Institutional



Government



Linear/T ransportation



Other



C-10 PRE-Construction Land Cover

Indicate the area occupied by each of the following site components. Fill in information
for each site component. If not applicable write "NA". If info is not available or
unknown for a particular site component, please provide your best estimate or indicate
"NK" for Not Known.

(a) Indicate the area occupied by each of the following impervious site components. Do
not include the footprint of buildings that have a green roof or disconnected spout leading
to an infiltration best management practice or transportation areas which are constructed
of pervious pavers or other pervious materials. Rather, include these areas in response to
the part b.

Acres Covered by Impervious Site Components

Site Component

Area (Acres)

Building Areas/ Rooftops (house, garage, storage
structure etc.)



Transportation Areas (roads, driveways)



Parking area



Other Impervious Area



Industry Questionnaire

Page 20 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX
(b) Indicate the area occupied by each of the following pervious site components.

Acres Covered by Pervious Site Components

Site Component

Acres

Green or vegetated rooftops



Semi-pervious surfaces (such as pervious
pavement)



Open green space (such as grass lawns)



Infiltration BMPs (such as rain gardens, swales,
and wetlands)



Water bodies including natural ponds and
detention BMPs



Cropland/Pasture



Natural vegetation and undisturbed areas



Forest



Shnibland



Grassland



Barren



Wetlands



Other:



Other pervious area



C-l 1 POST-Construction Land Cover

Indicate the area occupied by each of the following site components. Fill in information
for each site component. If not applicable write "NA". If info is not available or
unknown for a particular site component, please provide your best estimate or indicate
"NK" for Not Known.

Industry Questionnaire

Page 21 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX
(a) Indicate the area occupied by each of the following impervious site components. Do
not include the footprint of buildings that have a green roof or disconnected spout leading
to an infiltration best management practice or transportation areas which are constructed
of pervious pavers or other pervious materials. Rather, include these areas in response to
the part b.

Acres Covered by Impervious Site Components

Site Component

Area (Acres)

Building Areas/ Rooftops (house, garage,
storage structure etc.)



Transportation Areas (roads, driveways)



Parking area



Other Impervious Area



(b) Indicate the area occupied by each of the following pervious site components.

Acres Covered by Pervious Site Components

Site Component

Acres

Green or vegetated rooftops



Semi-pervious surfaces (such as pervious
pavement)



Open green space (such as grass lawns)



Infiltration BMPs (such as rain gardens,
swales, and wetlands)



Water bodies including natural ponds and
detention BMPs



Cropland/Pasture



Natural vegetation and undisturbed areas



Forest



Shntbland



Grassland



Barren



Wetlands



Other:



Other pervious area



Industry Questionnaire

Page 22 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

C-12 Indicate the predominant soil type at this site.

~	Clayey soils (clay, clay loam)

~	Silty soils (silt, silt loam)

~	Loamy soils (loam, sandy loam)

~	Sandy soils (sand, loamy sand)

C-13 Provide the percolation rate at this site.

minutes/inch

C-14 Is this site within the boundaries of a regulated MS4?

~	Yes ~ No

C-15 Does this site discharge to an MS4 system?

~	Yes ~ No

C-16 Indicate which of the following specific or numeric stormwater post construction
performance standards and/or design criteria applied to this project? Check all that apply.

~	Maximum peak runoff
Specify:	

~	Maximum total volume of runoff
Specify:	

~	Minimum size for detention structures
Specify:	

~	Maximum size for retention structures
Specify-.	

~	Maximum discharge velocity of detention structures
Specify-.	

~	Other channel protection measures
Specify-.	

~	Maximum percent impervious surface.

Specify-.	

~	On-site retention requirements for specific storm event:

Specify-.	

~	Maintain predevelopment runoff for a specific storm event.

Specify-.	

~	Infiltration/groundwater preservation requirement

Specify-.	

~	Quality improvement (e.g. solids, nitrogen, phosphorus, etc)

Specify-.	

~	Limits for effluent concentrations

Specify-.	

~	Land grading requirements or other erosion prevention specifications
Specify-.	

~	Clustering or other site design requirements

Specify-.	

Industry Questionnaire

Page 23 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

~	Natural area protection (wetland & upland)

Specify:	

~	Water conservation requirements
Specify:	

~	Other:	

~	None

C-17 Did your firm perform a cost comparison between traditional stormwater practices
and retention or pervious stormwater practices (i.e. green infrastructure
practices) for this project?

~	Yes ~ No

C-18 Were stormwater retention practices planned for this site?

~	Yes ~ No

C-19 Were stormwater retention practices implemented on this site?

~	Yes ~ No

C-20 What, if any, challenges did your establishment encounter in implementing the
stormwater retention practice? Or if the retention practices were planned but not
implemented, what prevented your establishment from implementing the
technique(s)? Check all that apply.

~	No retention practices techniques planned or implemented

~	Zoning ordinances

~	Local stormwater regulations/permit requirements

~	Site limitations

~	Financing requirements

~	Lack of local providers with retention practice experience (site
designers/engineers, architects, subcontractors for parts and installation, etc.)

~	Lack of desirability by site owner or other project participant

~	Other	

~	Not Applicable

~	None

C-21 If on-site stormwater controls had not been implemented at the site, how would
the additionally available land most likely been used? Check all that apply.

~	Larger building footprint

~	Additional connected impervious area such as parking, driveway, or garage

~	Additional disconnected impervious area such as a shed

~	Additional green space such as lawn

~	Additional natural vegetation/undisturbed land

~	Stormwater management technique did not have a footprint

~	Other	

~	Not Applicable

~	Unknown

Industry Questionnaire

Page 24 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX
C-22 Complete the following information for the design criteria for the system of
storm water controls for this project.

~ No on-site post-construction stormwater controls at this project (skip to C-23)
(a) Indicate the total watershed area for the system (acres):

(b) Indicate which design specifications for on-site stormwater controls were used
for this project:

~ Containment of storm:

~ 2-yr ~ 5-yr ~ 10-yr

~	Capture and treatment of percentage of stormwater:

~	Other (Please specify):	

(c) Indicate the system design capacity (including units):

C-23 Indicate which of the following post construction stormwater control components
have been installed for this project. Check all that apply.

~	Detention basins

~	Curbs and Gutters/Storm Sewers

~	Catch Basins

~	Swales

~	Constructed Wetlands

~	Underground Detention

~	Underground Infiltration

~	Manufactured Devices

~	Tree Boxes

~	Green Roofs

~	Bioretention

~	Infiltration basins/trenches/dry wells

~	Permeable pavement

~	None (skip to C-25)

C-24 Provide, if available, an estimate of the total cost of the post construction

stormwater management system associated with this project and costs for each
stormwater control component indicated in C-23. If the costs for a specific
applicable component are unknown, enter UNK.

~Number of inches of;
~ rainfall

~ runoff

Total Cost:

~	Detention basins:

~	Curbs and Gutters/Storm Sewers:

$
$
$

Industry Questionnaire

Page 25 of 61


-------
OMB Control No. 20XX-XXXX
Approval expires XX/XX/XX

~ Catch Basins:

$

~ Swales:

$

~ Constructed Wetlands:

$

~ Underground Detention:

$

~ Underground Infiltration:

$

~ Manufactured Devices:

$

~ Tree Boxes:

$

~ Green Roofs:

$

~ Bioretention:

$

~ Infiltration basins/trenches/dry wells:

$

~ Permeable pavement:

$

~ Other:

$

C-25 Fill out one worksheet for each applicable stormwater system components
indicated in C-23. You may make copies of the worksheet for multiple
components for a single project. If you do not have detailed information
requested in the worksheet, write UNK. Leave any worksheet that is not
applicable blank.

Industry Questionnaire

Page 26 of 61


-------
Detention Basin (Dry Pond) Worksheet

Project Name and Unit Description:

	Capital Costs	

Installed Capital Cost: $	

Year of Cost Data: 	

Check all elements included in your capital cost estimate and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Engineering and Overhead Costs:	$	

~	Site Clearing and Excavation Costs:	$	

~	Land Cost or Value:	$	

~	Vegetation and Landscaping Costs:	$	

~	Other Capital Costs:	$	

	Active Construction Usage	

Was this unit installed as part of active construction runoff control?

~ Yes	~ No

If yes, how much did it cost to convert the unit for post construction control?

~ No additional cost ~ $	 ~ Unknown

	Design Basis	

Check and provide information on all applicable design criteria for this unit

~	Capacity (gallons):		

~	Drainage Area (Acres):		

~	Design Storm Return Interval: m2-yr m5-yr mlO-yr mOther:	

~	Design Storm Depth (inches): 		~ Rainfall ~ Runoff

~	Other:	

	Technical Specifications	

Area of Pond (acres):		

Volume of Pond (gallons):		

Other Technical Data (describe): 	

Industry Questionnaire

Page 27 of 61


-------
Detention Basin (Dry Pond) Worksheet
Operation and Maintenance Costs

If you were responsible for maintaining this unit at any time, provide the following information.
If you were not responsible for maintenance please check here ~

Detail of and duration for maintenance activities:

Total Maintenance Costs:



$

Check all elements included in the total maintenance

costs

and provide estimates of their

individual costs if known. If unknown, enter UNK.





~ Revegetation/Maintenance Cost:

$



~ Sediment Removal Costs:

$



~Other Costs:

$









Industry Questionnaire

Page 28 of 61


-------
Curb And Gutter/Storm Sewer Worksheet

Project Name and Unit Description:

	Capital Costs

Installed Capital Cost: $	

Year of Cost Data:

Check all elements included in your capital cost estimate and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Engineering and Overhead Costs:	$

~	Storm Sewer Cost:	$

~	Site Clearing and Excavation Costs:	$

~	Materials Cost:	$

~	Other Capital Costs:	$

Design Basis

Check and provide information on the d

ssign criteria for this unit

~ Capacity (gallons):



~ Drainage Area (Acres):



~ Design Storm Return Interval: m2-yr

~5-yr mlO-yr ~ Other:

~ Design Storm Depth (inches):

~Rainfall ~ Runoff

~ Other:



Technical Specifications

Flow Rate Capacity (gal)



Length (ft):



Other Design Features ~

Curb Cuts ~ Height (in):

Connects To: ~ Combined Storm
Sewer System

~ Separate Storm ~ Bioretention ~ Pond
Sewer System Basin

Other Technical Data (describe):



Industry Questionnaire

Page 29 of 61


-------
Curb And Gutter/Storm Sewer Worksheet

Operation and Maintenance Costs

If you were responsible for maintaining this unit at any time, provide the following information.
If you were not responsible for maintenance please check here ~

Detail of and duration for maintenance activities:

Maintenance Costs:	$

Check all elements included in the total maintenance costs and provide estimates of their
individual costs if known. If unknown, enter UNK.

~ Sediment Removal Costs:	$	

~Other Costs:	$

Industry Questionnaire

Page 30 of 61


-------
Catch Basin Worksheet

Capital Costs

Installed Capital Cost: $
Year of Cost Data:

Check all elements included in your capital cost estimate and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Engineering and Overhead Costs:	$	

~	Construction Costs:	$	

~	Land Cost or Value:	$	

~	Materials Costs:	$	

~	Other Capital Costs:	$	

Active Construction Usage

Was this unit installed as part of active construction runoff control?

~ Yes	~ No

If yes, how much did it cost to convert the unit for post construction control?

~ No additional cost ~ $	~ Unknown

Design Basis

Check and provide information on the c

iesign criteria for this unit



~ Flow Rate Capacity (gpm):





~ Drainage Area (acres):





~ Containment of Storm:

~2-yr n5-yr nlO-yr

~Other:

~ Design Storm Depth (inches):

~Rainfall

~Runoff

~Other:







Technical Specifications

Connects To: ~ Combined Storm ~ Separate Storm ~ Bioretention ~ Pond
Sewer System Sewer System	Basin

Industry Questionnaire

Page 31 of 61


-------
Catch Basin Worksheet

Operation and Maintenance Costs

If you were responsible for maintaining this unit at any time, provide the following information.
If you were not responsible for maintenance please check here ~

Detail of and duration for maintenance activities:

Total Maintenance Costs:	$

Provide detail on the activities included in the total maintenance costs above. If known, provide
costs for the individual activity. If unknown, enter UNK.

~Cost component:		$	

~Cost component:		$	

~Cost component:		$	

Industry Questionnaire

Page 32 of 61


-------
Swale Worksheet

Project Name and Unit Description:

	Capital Costs	

Installed Capital Cost: $	

Year of Cost Data: 	

Check all elements included in your capital cost estimate and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Engineering and Overhead Costs:	$	

~	Construction Costs:	$	

~	Land Cost or Value:	$	

~	Materials Costs:	$	

~	Other Capital Costs:	$	

	Active Construction Usage	

Was this unit installed as part of active construction runoff control?

~ Yes	~ No

If yes, how much did it cost to convert the unit for post construction control?

~ No additional cost ~ $	 ~ Unknown

	Design Basis	

Check and provide information on the design criteria for this unit

~	Flow Rate Capacity (gpm):		

~	Drainage Area (Acres):		

Check the type of swale (check all that apply):

~	Grassed ~ Rip-Rap/Rock Lined ~ Other Vegetation ~ Other:	

Other:

Technical Specifications

Provide dimensions of swale (or attach drawing: Length(ft)

Width(ft)

Depth(ft)

Type of Vegetation:





Other:





Industry Questionnaire

Page 33 of 61


-------
Swale Worksheet

Operation and Maintenance Costs

If you were responsible for maintaining this unit at any time, provide the following information.
If you were not responsible for maintenance please check here ~

Detail of and duration for maintenance activities:

Total Maintenance Costs:	$

Check all elements included in the total maintenance costs and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Sediment removal	$	

~	Revegetation	$	

~	Other	$

Industry Questionnaire

Page 34 of 61


-------
Constructed Wetland Worksheet

Project Name and Unit Description:

	Capital Costs

Installed Capital Cost: $	

Year of Cost Data:

Check all elements included in your capital cost estimate and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Engineering and Overhead Costs:	$

~	Site Clearing and Excavation Costs:	$

~	Land Cost or Value:	$

~	Vegetation and Landscaping Costs:	$

~	Other Capital Costs:	$

	Design Basis	

Check and provide information on the design criteria for this unit

~	Drainage Area (Acres):		

~	Containment of Storm:	m2-yr m5-yr mlO-yr mOther:
Other:

Technical Specifications

Area of Pond (acres):



Volume of Pond (gal):



Type of Vegetation:



Other Technical Data:



Industry Questionnaire

Page 35 of 61


-------
Constructed Wetland Worksheet
Operation and Maintenance Costs

If you were responsible for maintaining this unit at any time, provide the following information.
If you were not responsible for maintenance please check here ~

Detail of and duration for maintenance activities:

Total Maintenance Costs:

$

Check all elements included in the total maintenance

costs and provide estimates of their

individual costs if known. If unknown, enter UNK.



~ Sediment removal

$

~ Revegetation

$

~ Other

$



Industry Questionnaire

Page 36 of 61


-------
Underground Detention Worksheet

Project Name and Unit Description:

	Capital Costs

Installed Capital Cost: $	

Year of Cost Data:

Check all elements included in your capital cost estimate and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Engineering and Overhead Costs:	$

~	Site Clearing and Excavation Costs:	$

~	Structural Materials Cost:	$

~	Structural Control Devices Costs:	$

~	Other Capital Costs:		$

Design Basis

Check and provide information on the c

iesign criteria for this unit



~ Drainage Area (Acres):





~ Containment of Storm:

~2-yr n5-yr mlO-yr

~Other:

~ Design Storm Depth (inches):

~Rainfall

~Runoff

Other:







Technical Specifications

Detention Volume (gal)



Time to Drain (hours)



Other Technical Data:



Industry Questionnaire

Page 37 of 61


-------
Underground Detention Worksheet

Operation and Maintenance Costs

If you were responsible for maintaining this unit at any time, provide the following information.
If you were not responsible for maintenance please check here ~

Detail of and duration for maintenance activities:

Total Maintenance Costs:	$

Check all elements included in the total maintenance costs and provide estimates of their
individual costs if known. If unknown, enter UNK.

~Cost component:		$	

~Cost component:		$	

~Cost component:		$	

Industry Questionnaire

Page 38 of 61


-------
Underground Infiltration Worksheet

Project Name and Unit Description:

	Capital Costs

Installed Capital Cost: $	

Year of Cost Data:

Check all elements included in your capital cost estimate and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Engineering and Overhead Costs:	$

~	Site Clearing and Excavation Costs:	$

~	Structural Materials Cost:	$

~	Structural Control Devices Costs:	$

~	Other Capital Costs:		$

	Design Basis	

Check and provide information on the design criteria for this unit

~	Drainage Area (Acres):		

~	Containment of Storm:	m2-yr m5-yr mlO-yr mOther:	

~	Design Storm Depth (inches): 		~ Rainfall ~Runoff

Other:

Technical Specifications

Infiltration Rate (unit):



Time to Drain (hours):



Other Technical Data:



Industry Questionnaire

Page 39 of 61


-------
Underground Infiltration Worksheet

Operation and Maintenance Costs

If you were responsible for maintaining this unit at any time, provide the following information.
If you were not responsible for maintenance please check here ~

Detail of and duration for maintenance activities:

Total Maintenance Costs:	$

Check all elements included in the total maintenance costs and provide estimates of their
individual costs if known. If unknown, enter UNK.

~Cost component:		$	

~Cost component:		$	

~Cost component:		$	

Industry Questionnaire

Page 40 of 61


-------
Manufactured Device Worksheet

Project Name and Unit Description:

	Capital Costs

Installed Capital Cost: $	

Year of Cost Data:

Check all elements included in your capital cost estimate and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Engineering and Overhead Costs:	$	

~	Land Cost or Value:	$	

~	Site Clearing and Excavation Costs:	$	

~	Other Capital Costs:		$	

	Design Basis

Please provide as much design detail on the unit as possible

	Technical Specifications

Maximum Treatment capacity (unit):	_

Device Function (check all that apply):

~	Settling

~	Filtration

~	Absorptive/adsorptive materials

~	Vortex separation

~	Other solids removal

~	Other Pollutant removal 	

~	Other	

Other Technical Detail:

Industry Questionnaire

Page 41 of 61


-------
Manufactured Device Worksheet

Operation and Maintenance Costs

If you were responsible for maintaining this unit at any time, provide the following information.
If you were not responsible for maintenance please check here ~

Detail of and duration for maintenance activities:

Total Maintenance Costs:	$

Check all elements included in the total maintenance costs and provide estimates of their
individual costs if known. If unknown, enter UNK.

~Cost component:		$	

~Cost component:		$	

~Cost component:		$	

Industry Questionnaire

Page 42 of 61


-------
Tree Box Worksheet

Project Name and Unit Description:

	Capital Costs

Installed Capital Cost: $	

Year of Cost Data:

Check all elements included in your capital cost estimate and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Site Clearing and Excavation Costs:	$	

~	Other Capital Costs:		$	

	Design Basis	

Provide information on the design criteria for this unit

	Technical Specifications

Infiltration Rate (unit):		

Storage Volume (unit):		

Tree or Shrub Species and Installed Size (unit):		

Other Technical Data:

Operation and Maintenance Costs

If you were responsible for maintaining this unit at any time, provide the following information.
If you were not responsible for maintenance please check here ~

Detail of and duration for maintenance activities:

Total Maintenance Costs:	$

Check all elements included in the total maintenance costs and provide estimates of their
individual costs if known. If unknown, enter UNK.

~Cost component:		$	

~Cost component:		$	

~Cost component:		$	

Industry Questionnaire	Page 43 of 61


-------
Green Roof Worksheet

Project Name and Unit Description:

	Capital Costs

Installed Capital Cost: $	

Year of Cost Data:

Check all elements included in your capital cost estimate and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Construction Costs:	$

~	Engineering and Overhead Costs:	$

~	Planting Media Costs:	$

~	Vegetation Costs:	$

~	Irrigation System Costs:	$

~	Additional Structural Support Design Costs: $

~	Other Capital Costs:		$

	Design Basis

Provide information on the design criteria for this unit
Volume Retained:		

Other:

Technical Specifications

Roof Surface Area





% of Roof Vegetated





Type ~ extensive

~ intensive

~ semi-intensive

Depth of soil (inches)





Depth of media (inches)





Roof storage capacity (unit)





Other Technical Data:





Industry Questionnaire

Page 44 of 61


-------
Green Roof Worksheet

Operation and Maintenance Costs

If you were responsible for maintaining this unit at any time, provide the following information.
If you were not responsible for maintenance please check here ~

Detail of and duration for maintenance activities:

Total Maintenance Costs:	$

Check all elements included in the total maintenance costs and provide estimates of their
individual costs if known. If unknown, enter UNK.

~Cost component:		$	

~Cost component:		$	

~Cost component:		$	

Industry Questionnaire

Page 45 of 61


-------
Bioretention Worksheet

Project Name and Unit Description:

	Capital Costs	

Installed Capital Cost: $	

Year of Cost Data: 	

Check all elements included in your capital cost estimate and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Construction Costs:	$	

~	Engineering and Overhead Costs:	$	

~	Site Clearing and Excavation Costs:	$	

~	Land Costs or Value:	$	

~	Soil Amendment Materials Costs:	$	

~	Vegetative and Landscaping Costs:	$	

~	Other Capital Costs:		$	

	Active Construction Usage	

Was this unit installed as part of active construction runoff control?

~ Yes	~ No

If yes, how much did it cost to convert the unit for post construction control?

~ No additional cost	~ Unknown	~ $	

Design Basis

Check and provide information on the de

sign criteria for this unit



~ Capacity (gallons):





~ Drainage Area (Acres):





~ Design Storm: n2-yr n5-yr

~ 10-yr ~ Other:



~ Design Storm Depth (inches):

~Rainfall

~Runoff

~ Other:







Industry Questionnaire

Page 46 of 61


-------
Bioretention Worksheet

	Technical Specifications

Underdrain filter gravel, filter fabric, pipe materials:		

Length and thickness/diameter of underdrain, if used (units): 	

Soil mix added, if native soil excavated and replaced:		

Amendment materials and percentages of native soil amended in place:

Types of Vegetation:	

Other:

Operation and Maintenance Costs

If you were responsible for maintaining this unit at any time, provide the following information.
If you were not responsible for maintenance please check here ~

Detail of and duration for maintenance activities:

Total Maintenance Costs:

$

Check all elements included in the total maintenance

costs and provide estimates of their

individual costs if known. If unknown, enter UNK.



~ Revegetation/Maintenance Cost:

$

~ Sediment Removal Costs:

$

~Other Costs:

$



Industry Questionnaire

Page 47 of 61


-------
Infiltration Basin / Trench / Dry Well Worksheet

Project Name and Unit Description:

	Capital Costs	

Installed Capital Cost: $	

Year of Cost Data: 	

Check all elements included in your capital cost estimate and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Construction Costs:	$	

~	Engineering and Overhead Costs:	$	

~	Site Clearing and Excavation Costs:	$	

~	Structural Materials Cost:	$	

~	Structural Control Devices Costs:	$	

~	Vegetation and Landscaping Cost:	$	

~	Other Capital Costs:		$	

	Active Construction Usage	

Was this unit installed as part of active construction runoff control?

~ Yes	~ No

If yes, how much did it cost to convert the unit for post construction control?

~ No additional cost ~ $	 ~ Unknown

Design Basis

Check and provide information on

the design criteria for this unit

~ Drainage Area (Acres):



~ Containment of Storm:

~2-yr m5-yr mlO-yr mOther:

~ Design Storm Depth (inches):

~Rainfall ~ Runoff

Other:



Technical Specifications

Infiltrating Surface Area:



Infiltration Capacity:



Other Technical Data:



Industry Questionnaire

Page 48 of 61


-------
Infiltration Basin / Trench / Dry Well Worksheet

Operation and Maintenance Costs

If you were responsible for maintaining this unit at any time, provide the following information.
If you were not responsible for maintenance please check here ~

Detail of and duration for maintenance activities:

Total Maintenance Costs:	$

Check all elements included in the total maintenance costs and provide estimates of their
individual costs if known. If unknown, enter UNK.

~ Sediment Removal	$	

~Other	$

Industry Questionnaire

Page 49 of 61


-------
Permeable Pavement Worksheet

Project Name and Unit Description:

	Capital Costs

Installed Capital Cost: $	

Year of Cost Data:

Check all elements included in your capital cost estimate and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Paving Costs:	$	

~	Granular Fill Costs:	$	

~	Engineering and Overhead Costs:	$	

~	Site Clearing and Excavation Cost:	$	

~	Other Capital Costs:		$	

	Active Construction Usage	

Was this unit installed as part of active construction runoff control?

~ Yes ~ No
If yes, how much did it cost to convert the unit for post construction control?
~ No additional cost ~ $	 ~ Unknown

	Design Basis	

Check and provide information on the design criteria for this unit

Pavement Surface Area:

Maximum Absorption (%):
Permeability (mD):
Infiltration rate (in/hr):

Size of underdrain:

Other:

Technical Specifications

Type of Permeable Pavement:



~ Permeable Asphalt

~ Permeable Concrete

~ Permeable Blocks

~ Open Grid Pavement

~ Other:



Other Technical Data:





Industry Questionnaire

Page 50 of 61


-------
Permeable Pavement Worksheet
Operation and Maintenance Costs

If you were responsible for maintaining this unit at any time, provide the following information.
If you were not responsible for maintenance please check here ~

Detail of and duration for maintenance activities:

Total Maintenance Costs:	$

Check all elements included in the total maintenance costs and provide estimates of their
individual costs if known. If unknown, enter UNK.

~	Sediment Removal	$	

~	Other	$

Industry Questionnaire

Page 51 of 61


-------
C-26 Provide contact information for the person responsible for completing the general
and technical info in this section.

Name

Title

Phone/Fax Number

Email

Best Time to Contact

Industry Questionnaire

Page 52 of 61


-------
Financial Information

C-27 Indicate your establishment's percent share of ownership in the project.

	%

C-28 Did your establishment conduct services associated with this project for another
business entity?

~	Yes

~	No (skip to Question 30)

C-29 Indicate the role of the business (your client) in the project for which you
provided services?

~	Owner/Developer

~	Owner/Developer & Builder

~	General or Lead Contractor, Construction Manager or Contract Builder

~	Other Contractor/Sub contract or Role

~	Other: Please specify:	

~ CBI C-30 Provide the following financial information for each phase of the project.

Land Acquisition and Initial Project Planning and Design

Item

Cost ($)

Raw Land Cost



Fees - Legal, Accounting, Financing, and Permitting incurred during
land acquisition phase



Project Design, Architectural Services, etc.



Interest or other financing costs incurred during this phase



Establishment's Overhead



Other Costs





Industry Questionnaire

Page 53 of 61


-------
Land Development

Item

Cost ($)

Land Development (includes site preparation, site improvements such
as paving, water and sewer connections, erosion and sediment
control, land preservation and planting etc.)



Fees - Legal, Accounting, Impact Analysis, Other



Interest or other financing costs incurred during this phase



Establishment's Overhead



Other Costs





Project Construction

Item

Cost ($)

Fees - Legal, Accounting, Building Permit and Inspection, Other



Cost of Construction - Materials, Labor, Services, Construction
Contracts, etc.



Fees/Costs



Interest or other financing costs Incurred during this phase



Establishment's Overhead



Other Costs





Completion - Sale or Other Completion Disposition

Item

Cost ($)

Fees - Legal, Accounting, Marketing, Other



Interest or other financing costs incurred during this phase



Establishment's Overhead



Other Costs



Industry Questionnaire

Page 54 of 61


-------
~ CBI C-31 Provide information on the financial structure and financing terms for each phase
of the project.

Financing Information for Each Project Phase

Item

Land Acquisition

Land Development

Construction

Primary Debt Financing (first or senior debt)

Fraction Financed (%):







Interest Rate, if a fixed rate
(%):







Interest Ferms, if not fixed:







Base Rate (checkbox):

~	Prime Rate

~	LIBOR

~	Other:

~	Prime Rate

~	LIBOR

~	Other:

~	Prime Rate

~	LIBOR

~	Other:

Increment to Base Rate (%):







Secondary Debt or Other Fixed Repayment Ferm Financing

Description:







Fraction Financed (%):







Interest Rate, if a fixed rate
(%):







Interest Ferms, if not fixed:







Base Rate (checkbox):

~	Prime Rate

~	LIBOR

~	Other:

~	Prime Rate

~	LIBOR

~	Other:

~	Prime Rate

~	LIBOR

~	Other:

Increment to Base Rate (%):







Equity Financing (Owner's Financing or other Non-Debt, Non-Fixed Repayment Ferm Financing)

Fraction Financed (%):







Equity Financing (Owner's Financing or other Non-Debt, Non-Fixed Repayment Ferm Financing)

Description:







Fraction Financed (%):







~ CBI C-32 Indicate the final value of the project?

(For example, the final project sales value or recorded asset value of completed project
when transferred from under-construction status to completed construction status)

$

Industry Questionnaire

Page 55 of 61


-------
C-33 Does your establishments plan to retain ownership of this project now that it is
complete?

~	Yes

~	No

~	Not Applicable

C-34 Provide contact information for the person responsible for providing the financial
information in this section.

Name

Title

Phone/Fax Number

Email

Best Time to Contact

You have completed the questionnaire. Sign the certification statement in Section E and
refer to instructions for mailing the questionnaire back to the United States
Environmental Protection Agency. Thank you.

Industry Questionnaire

Page 56 of 61


-------
Section D Project Level Information for Non-
Owners/General Contractors

This Section should only be completed by establishments that were required to respond to
Section C and that responded "no" to Question C-3.

For Section D, respond to the questions for up to ten completed projects or all completed
projects during FY2009, whichever is less. Do not report on pipeline or other utility
related activities where the original land cover was replaced at the end of the project

Ten copies of the remainder of Section D are provided for a maximum of ten projects. If
applicable, provide information on projects in each of the following size categories:

>	0-1 Acre,

>	1-5 Acres,

>	5-10 Acres, and

>	>10 Acres.

Industry Questionnaire

Page 57 of 61


-------
D-l Provide the location of the project.
Street Name:

Town/City:

State:

ZIP Code:

D-2 Provide contact information for the business or entity for which your

establishment provided services for this project. EPA may need to seek additional
financial information regarding the project that will help the development of a
more accurate estimate of the impact of any potential regulation on all potentially
affected entities.

Name

Title

Establishment

Phone/Fax Number

Email

D-3 Indicate the role of the business (your client) in the project for which you
provided services?

~	Owner/Developer

~	Owner/Developer & Builder

~	General or Lead Contractor, Construction Manager or Contract
Builder

~	Other Contractor/Subcontractor Role

~	Other; Please specify:	

Industry Questionnaire

Page 58 of 61


-------
D-4 If the business or entity identified in D-l was not the project owner,

provide the contact information for the owner of the project, if known.

Check here if unknown ~

Name

Title

Establishment

Phone/Fax Number

Email

D-5 What services did your establishment provide? Check all that apply.

~	Responsible for construction on part of the total project's area
Acreage:	

~	Responsible for specific construction activities, but not overall project
management

Specific Activity:	

Acreage:	

~	Other; Please specify :	

Acreage:	

~ CBI D-6 How much revenue did your establishment receive for the provided services?

$	

D-7 What was the duration of your establishment's part of the project?
	months

D-8 Provide contact information for the person responsible for completing this
section.

Name

Title

Phone/Fax Number

Industry Questionnaire

Page 59 of 61


-------
Email

Best Time to Contact

You have completed the questionnaire. Sign the certification statement in Section E and
refer to instructions for mailing the questionnaire back to the United States
Environmental Protection Agency. Thank you.

Industry Questionnaire

Page 60 of 61


-------
Section E: Certification Statement

The individual responsible for directing or supervising the preparation of the enclosed
Stormwater Discharges from New Developed and Redeveloped Sites Industry
Questionnaire must read and sign the Certification Statement below before returning both
documents to the U.S. Environmental Protection Agency. The certifying official must be
an official duly authorized representative. The Certification Statement must be completed
and submitted in accordance with the requirements contained in the Code of Federal
Regulations at 40. CFR 122.22.

I certify under penalty of law that the attached questionnaire was prepared under
my direction or supervision in accordance with a system designed to ensure that qualified
personnel properly gathered and evaluated the information submitted. The information
submitted is, to the best of my knowledge and belief accurate and complete. In those
cases where we did not possess the requested information, we have provided best
engineering and/or financial estimates or judgment. I am aware that there are significant
penalties for submitting false information, including the possibility offines and
imprisonment as explained in Section 308 of the Clean Water Act (33 U.S.C., Section

1318).

Signature of Certifying Official

Date

(	).

Printed Name of Certifying Official

Telephone Number

Title of Certifying Official

Industry Questionnaire

Page 61 of 61


-------