EPA HardrockMining Innovative Technology Case Study

ABSTRACT:

The Leviathan Mine is the former site of intermittent
mining operations dating back to the 1860s, and
open pitsuifur mining operations from the 1950s
through the 1960s. A pilot scale bioreactor was first
installed at the Leviathan Creek seep in 1993, and
transferred to the Aspen Creek seep in the late
1990s. In 2003, Atlantic Richfield Company and
researchers from the University of Nevada-Reno
(UNR) and the U.S. Environmental Protection Agency
(EPA) installed a full-scale compost-free sulfate-
reducing bioreactor system to treat acid rock
drainage (ARD). Over an evaluation period of 20
months, from late 2003 to summer 2005, the
bioreactor was able to achieve a target-metal removal
efficiency of 95 percent. All target metals, except
iron, were reduced to concentrations below the EPA
interim discharge standards. The compost-free
bioreactor system also raised the pH of the ARD from
3.0 to 7.0 and treated influent flows up to 30 gallons
per minute (gpm) year-round. This case study looks at
the effectiveness of the sulfate-reducing bioreactor
treating ARD from the Aspen Seep at Leviathan Mine.

Site Background

Leviathan Mine
CERCLIS ID: CAD98067685

The Leviathan Mine is located in Alpine County,
California near the California-Nevada border. The
disturbed land comprises approximately 250 acres
at the 7,000-foot elevation on the eastern slope of
the Sierra Nevada. Mining operations commenced
in the 1860s, but the mine was inactive from 1872 to
1935. The mine operated intermittently until the
Anaconda Company purchased the property in

1951	and extracted sulfur by open pit mining from

1952	to 1962. No significant mining activities have
occurred since Anaconda ceased operations in
1962 and sold the property (U.S. EPA, 2004c).

August 14, 2006


-------
Leviathan Mine Technology Case Study

Compost-Free Sulfate-Reducing Bioreactors at Aspen Seep

Major environmental damage occurred
at the mine, which is surrounded by the
Humboldt-Toiyabe National Forest,
during the period of open pit mining.
Snowmelt, rain, and groundwater
interact with the waste rock, creating
sulfuric acid, which in turn leaches
additional contaminants from the
native minerals such as arsenic, copper,
nickel, zinc, chromium, aluminum and
iron. The resulting acid rock drainage
(ARD) flows into the Leviathan Creek
system at numerous points, eventually
joining the East Fork of the Carson River.
For most of the year, roughly half of the
flow in Leviathan Creek is composed of
ARD (U.S. EPA, 2004c).

When the Leviathan Mine was added
to the National Priorities List (NPL) in May
2000, EPA identified two problems
requiring immediate attention: (1) an
evaporation pond, known as Adit Drain,
collecting highly contaminated acid
drainage, which overflows into the
Leviathan Creek during the spring
snowmelt; and (2) three seeps of acidic
drainage causing contamination to
enter Leviathan Creek and Aspen
Creek (Figure 1) (U.S. EPA, 2004a). One
of these seeps, Aspen Seep, originates
from dumped overburden and flows
into Aspen Creek. A sulfate-reducing
bioreactor (SRB), designed and
operated by Atlantic Richfield
Company and University of Nevada-Reno (UNR) and EPA researchers, treats the drainage from the
Aspen Seep. More traditional lime-based treatment systems are currently being used to treat the
other two contamination sources (Delta Seep/Channel Underdrain and Adit Drain) at the Leviathan
Mine site. The final, long-term remedy for this site has not been selected. This case study focuses on
the effectiveness of the Aspen Seep SRB to date.

Waste Stream Characteristics

Leviathan Mine was added to the NPL in May 2000 to address contamination of surface water from
acid mine drainage (AMD) and ARD. ARD released from the Aspen Seep into Aspen Creek contains
elevated levels of four primary metals: aluminum, copper, iron, and nickel. Each of these metals has
historically exceeded EPA interim discharge standards by over 500 times. Secondary metals of
concern include selenium and zinc. Fish and insect kills in Leviathan Creek, Bryant Creek, and the

Leviathan Mine

Alpine Count/, California

Figure 1: Leviathan Mine Disturbed Area with major known ARD
points including Aspen Seep.

(Source: U.S. EPA, 2004a).

2 of 10

August 14, 2006


-------
Leviathan Mine Technology Case Study

Compost-Free Sulfate-Reducing Bioreactors at Aspen Seep

East Fork of the Carson River have been attributed to the release of metal-laden ARD. ARD, at pH 3,
flows from the Aspen Seep at rates ranging from 8 to 30 gallons per minute (gpm). Table 1 shows
average concentrations of these primary metals and the pH prior to treatment and compares the
concentrations to the EPA Interim Discharge Standard for Leviathan Mine (U.S. EPA, 2006).

Table 1. Concentrations and EPA Interim Discharge Standards for primary metals in

ARD at Aspen Seep

Target Metal

Average Influent Concentration
(mg/L)

EPA Interim Discharge Standard
(Average, mg/L)

Aluminum

37.5

2.0

Copper

0.690

0.016

Iron

117.0

1.0

Nickel

0.487

0.094

Selenium

0.013

0.005

Zinc

0.71

0.21

Treatment Technology

The State of California - site owner and, therefore,
partially responsible for cleanup - had funded a
bioreactor treatment system at the Leviathan
Mine since the early 1990s. The system started as
a simple one-cell, pilot-scale bioreactor with a
manure substrate. The system continued to
evolve throughout the late-90s but did not take its
current form until the site was listed on the NPL.

After the site became final on the NPL, EPA
directed Atlantic Richfield to prevent ARD
discharge from the Aspen Seep and several other
discharge points. The State of California wanted
the bioreactor system to be part of the Atlantic
Richfield responsibility for cleanup. Atlantic
Richfield saw promise in the system but felt it
needed some improvements. The EPA Office of
Research and Development (ORD), Atlantic
Richfield, the State, and UNR researchers
convened for a design session to offer different
approaches and ideas for constructing and
implementing a full-scale bioreactor treatment
system at the site. As a team, they proposed a
system design, and the full-scale, compost-free bioreactor system was constructed in 2003. As
constructed, the system requires 0.75 acres.

ASPEN SEEP SRB CHEMICAL REACTIONS:

Chemical reaction for sulfate-reducing bacteria
using an alcohol carbon source:

4AH2 + S042 + H+ -~ 4A2 + HS + 4H20
H2S + M2+ -~ MS + 2H+

AH2 is the carbon source and SCU2- is the terminal
electron acceptor in the electron transport chain
of the sulfate-reducing bacteria. This causes an
increase in pH. H2S reacts with metals and results
in metal sulfide precipitate (MS).

The reduction of sulfate to sulfide:

H2SO4 + 8H+ + 8e -~ H2S + 4H20

Ethanol contributes 12 electrons per molecule
oxidized.

3H20 + CHsOH -~ 12e + 2CO2 + 12H+

Electron counting enables determination of the
amount of carbon source required to reduce
sulfate.

3 of 10

August 14,2006


-------
Leviathan Mine Technology Case Study

Compost-Free Sulfate-Reducing Bioreactors at Aspen Seep

The bioreactor at the Leviathan Mine Aspen Seep relies on suifate-reducing microbial organisms,
such as Desulfovibrio sp., to reduce sulfate to sulfide. These organisms function at a critical pH 4.0
(Tsukamoto and Miller, 2005). ARD from the Aspen Seep has pH 3.1 and, therefore, requires
pretreatment before entering the compost-free bioreactor treatment system. In order to
accommodate this requirement, a 25 percent sodium hydroxide solution (0.26 ml/L) is added to the
influent in a pretreatment pond (1,000 ft3). The influent is effectively increased to pH 4.0 before it
enters the compost-free bioreactor system. Ethanol (0.43 ml/L) is also added to the system to provide
a carbon source for the suifate-reducing microbes (U.S. EPA, 2004b, 2006a, 2006b).

After addition of the sodium hydroxide solution and ethanol, ARD flows to Bioreactor No. 1 to reduce
sulfate to sulfide. Bioreactor No. 1 measures 12,500 ft3 in total volume and 5,300 ft3 in active volume,
with a 22-hour hydraulic residence time (HRT) at 30 gpm. The bioreactor is lined in 60 mil high-density
polyethylene (HDPE) and is filled with 6- to 24-inch river rock. Along with supplying a substrate for the
bacteria to grow on, the river rock also provides stabile flow paths and allows precipitates to be
flushed through the matrix. Sulfide generated in the first bioreactor is passed to the second
bioreactor for additional metals removal. With a 13-hour HRT at 30 gpm, Bioreactor No. 2 measures
7,000 ft3 in total volume and 3,000 ft3 in active volume (Figure 2). Each bioreactor has three influent
distribution lines and three effluent collection lines at different elevations to allow variable flow
operations.

After passing through the
bioreactors, a 25 percent
sodium hydroxide solution
is once again added to
the effluent to increase
the pH to a neutral
condition. A continuous-
flow pond, measuring
16,400 ft3 with a 68-hour
HRT at 30 gpm, collects
the effluent from the
second bioreactor for
extended settling of
metal sulfide precipitates.
The effluent from this
settling pond flows over a
rock-lined	aeration

channel, measuring 150
feet long and two feet
wide, to promote
Figure 2: Aspen Seep Bioreactor No. 2 lined with HDPE and filled with river rock. degassing of residua

(Source: The photo is courtesy of J. Bauman) hydrogen sulfide prior to

discharge.

To prevent plugging of the rock matrix, precipitate slurry is flushed occasionally from the bioreactors.
The slurry is settled in a flushing pond (18,000 ft3, 75-hour HRT at 30 gpm). Occasionally, solids are
pumped out of the settling and flushing ponds and dewatered using a 10- to 15- foot spun-fabric bag
filter. Under California and Federal standards, the bag filter solids are not hazardous.

The total system HRT is 107 hours at maximum design flow of 30 gpm.

4 of 10

August 14, 2006


-------
Leviathan Mine Technology Case Study

Compost-Free Sulfate-Reducing Bioreactors at Aspen Seep

Modifications to Initial Design

System Design

Although the system has experienced nearly constant tweaking, the following is a description of the
three major bioreactor treatment system designs: manure substrate pilot-scale; two-cell bioreactor,
and full-scale compost-free.

The original pilot-scale bioreactor developed by the UNR research team in the early 1990s was a
simple system consisting of a manure substrate in a small, shallow pond (Tsukamoto and Miller, 2005).
This organic substrate served as both the physical structure and the sole carbon source for the
sulfate-reducing bacteria. However, once the carbon source was depleted, ARD treatment slowed
down. Additionally, ARD from the Leviathan Seep proved too acidic for the sulfate-reducing
bacteria to function optimally, further reducing the efficiency of waste stream treatment. The
drainage at Leviathan Creek was from waste rock, described as material containing less than 20
percent sulfur by mass. After the first year of operation, the researchers determined the bioreactor
was ineffective in treating ARD from the Leviathan Seep.

In order to address problems with the initial bioreactor design, the system experienced a facelift in
1998 (Tsukamoto and Miller, 2005). A new two-cell bioreactor was constructed at the Leviathan
Mine Aspen Seep. The ARD from the Aspen Seep, originating from dumped overburden, is a less
acidic waste stream and enabled the microbes to have a better chance of survival. In addition to
the location, key modifications implemented in the 1998 bioreactor included:

•	Developing a two-cell system utilizing wood chips and an inert rock matrix,

•	Employing alcohol as a carbon source,

•	Adding base to further increase the alkalinity of the ARD, and

•	Allowing precipitates to be flushed from the bioreactor cells.

The use of alcohol as a carbon source provides an advantage over other organic substrates.
Alcohol can be used for treatment over extended time periods, and it also maintains a liquid state
under varying environmental temperatures. Finally, the addition of alcohol to a treatment system
can be varied according to optimal operating conditions. Alcohol, specifically ethanol, is an ideal
substrate for use at the Leviathan Mine Aspen Seep due to the remote nature of the site as it is only
accessible for a few months out of the year.

Again in 2003, the system was redesigned and the compost-free bioreactor treatment system was
constructed. The most recent design of the bioreactor uses a rock matrix in both bioreactor cells,
includes a pretreatment pond, and has improved flow distribution and advanced sludge capture
capability.

Operation Mode: Gravity-flow vs. Recirculation

Over the first six months of evaluation, the 2003 bioreactor design operated under gravity-flow mode
(Attachment A). Gravity-flow mode allowed metal precipitates to accumulate in both the
bioreactors and the settling pond. This required the system operators to flush the system frequently, in
turn disturbing the bacteria in the bioreactors. In order to avoid the need to flush the system so
frequently, the researchers transferred the system into recirculation mode for the remaining 14
months of the evaluation period (Attachment B). In recirculation mode, untreated ARD is mixed with
a 25 percent sodium hydroxide solution and sulfide-rich water from Bioreactor No. 2. The mixture then

5 of 10

August 14,2006


-------
Leviathan Mine Technology Case Study

Compost-Free Sulfate-Reducing Bioreactors at Aspen Seep

flows into the settling pond where the high pH and high sulfide concentrations encourage
precipitation of metal sulfides. This prevents the metals sulfides from precipitating in the bioreactors.
The pH of the water moving through the bioreactors is nearly neutral, presenting ideal conditions for
the sulfate-reducing bacteria. The system required 17 percent less sodium hydroxide while operating
under recirculation mode (U.S. EPA, 2006b).

Performance of System

Compost-free Bioreactor

The 2003 compost-free bioreactor was evaluated between November 2003 and July 2005 as part of
the Superfund Innovative Technology Evaluation (SITE) program. This effort was possible through the
cooperation of the U.S. EPA National Risk Management Research Laboratory (NRMRL), EPA Region IX,
the State of California, Atlantic Richfield, and UNR (U.S. EPA, 2006b).

Table 2. Bioreactor Treatment System Removal (U.S. EPA, 2006b)

Full-scale Compost-free Bioreactor

Gravity-flow Mode	Recirculation Mode

(11 /2003 - 4/2004)	(5/2004 - 7/2005)

PH

Influent (mg/L)

Effluent (mg/L)

Influent (mg/L)

Effluent (mg/L)

EPA Interim Discharge
Standard (mg/L)

3.1

7.2

2.9

7.6

—

Al

37.5

0.1

40

0.05

2.0

Fe

117

4.9

116

2.7

1.0

Ni

0.49

0.07

0.53

0.07

0.094

Cu

0.69

0.005

0.79

0.005

0.016

Sulfate

1502

1222

1530

1170

-

The system achieved an increase in waste stream pH from 3.0 to over 7.0 during treatment (Table 2).
Additionally, although the influent concentrations of the target metals were up to 580 -fold greater
than EPA interim standards, effluent concentrations were up to 43 fold below the standards. The
system was also able to reduce the sulfate concentration in ARD by more than 17 percent.

During the first six months of evaluation, while the system operated in gravity-flow mode, 2.44 million
gallons of ARD was treated. The system utilized 2,440 gallons of sodium hydroxide solution and 1,180
gallons of ethanol. Removal efficiency of target metals exceeded 94 percent.

Over the following 14 months, while the system functioned in recirculation mode, over 5.8 million
gallons of ARD was treated achieving a removal efficiency of target metals exceeding 96 percent.
During this time, 5,280 gallons of sodium hydroxide and 2,805 gallons of ethanol were pumped into
the system.

The system operates year-round and treats up to 30 gpm in either mode.

6 of 10

August 14,2006


-------
Leviathan Mine Technology Case Study

Compost-Free Sulfate-Reducing Bioreactors at Aspen Seep

Lessons Learned

A bioreactor treatment system, ranging from pilot-scale to full-scale implementation, has been
operating at the Leviathan Mine since 1993. The technology has experienced many changes since
its inception. In its current form, this treatment technology operates year-round and is compliant with
EPA discharge standards for all target metals except iron.

As the site remedial project manager explains, initially designed with simplicity in mind, the Aspen
Seep SRB has required more operator involvement than originally anticipated because pumping is
required to keep the system operating properly. Although the system has proven to be both
effective and reliable, it has also required more maintenance than originally planned.

The remote nature of the site and the surrounding environment are impacting system operations. The
climate is also influencing the system with slower biological activity during the winter months. Winter
snowpack limits access to the site for eight months out of the year requiring operating materials such
as sodium hydroxide, ethanol, and diesel fuel to be stored in bulk before the winter. Similarly,
equipment replacement, sludge dewatering, and sludge transfer are all performed during the
summer months (U.S. EPA, 2006a).

This technology can now be
implemented at other sites. Initiating
the technology on a pilot scale, the
2006 Technology News and Trends
explains, is no longer necessary. The
bioreactor system at Leviathan Mine
successfully addressed problems
related to carbon availability and
sulfate reduction. However, due to the
unique characteristics of each site, the
dose for base and ethanol would need
to be determined through a simple
bench test (U.S. EPA, 2006b).

Cost

The capitol costs for construction of the
gravity-flow operation amounted to
$836,600 and changing to the
recirculation mode added nearly
$30,000, for a total of $864,100.
Operating at an average flow rate of
10 gpm, the operation and
maintenance costs of the system are
$15.73 per 1,000 gallons of treated ARD
(U.S. EPA, 2006b).

Key Dates

(U.S. EPA 2001; 2004a, b, c; 2006a, b)

Early 1960s

The California Regional Water Quality control
Board, Lahontan Region (Regional Board)
become involved at the site.

Early 1980s

The California Regional Water Quality control
Board, Lahontan Region (Regional Board)
negotiate a settlement with Atlantic Richfield
Company (corporate successor to Anaconda).

1984

The State of California purchases the property to
address the contamination.

1993

Pilot-scale Bioreactor begins to treat AMD at
Leviathan Creek Seep.

1997

Washoe Tribe in Nevada and California requests
EPA's involvement at the site.

1998

Researchers from the University of Nevada-Reno
install a two-cell bioreactor at Aspen Seep.

2000

Leviathan Mine is listed on the NPL.

2001

Aspen Seep bioreactor treats over 2.5 million
gallons of ARD.

2003

Atlantic Richfield and UNR install a full-scale,
compost-free bioreactor system at Aspen Seep.
The bioreactor treats over 5.0 million gallons of
ARD.

NRMRL initiates long-term evaluation of the
bioreactor.

2005

NRMRL completes long-term evaluation of SRB
system.

7 of 10

August 14,2006


-------
Leviathan Mine Technology Case Study

Compost-Free Sulfate-Reducing Bioreactors at Aspen Seep

The compost-free sulfate-reducing bioreactor at the Aspen Seep is the first of its kind. The project was
labor intensive because the operating conditions at the site were continually altered to stress and
test the system. The system also included many optional features, such as controlling and routing
flows, that would not normally be used in most systems. Because of these factors, the final costs are
likely to be higher at Leviathan than the cost of operating and maintaining the system at other sites.

EPA Contacts

Kevin Mayer

Remedial Project Manager

U.S. Environmental Protection Agency Region IX

Phone: (415) 972-3176

Email: Maver.Kevin@epa.gov

Edward Bates

Project Manager

U.S. Environmental Protection Agency
National Risk Management Research Laboratory
Office of Research and Development
Phone: (513) 569-7774
Email: Bgtes.Edwgrd@epg.gov

References

Tsukamoto, T.K. and Miller, G.C.. 2005. "Semi-Passive Bioreactors at the Leviathan Mine." URL:
http://www.unr.edu/mines/mlc/presentgtions pub/presentgtions/Tiim%20Ts.%20Semi-
Pgssive%20Bioregctors%2Qgt%20the%20Levigthgn%20Mine.PPT#353,2,Slide 2

U.S. Environmental Protection Agency (U.S. EPA). 2001. "Leviathan Mine Superfund Site: Update on
Cleanup Activities." San Francisco, CA. URL:

http://vosemite.epg.gov/r9/sfund/r9sfdocw.nsf/91 f8ceee903fc0f088256f0000092934/0bdfb95fe5g4b9b788
2570070063c2f9/$FILE/levi11 01 .pdf.

U.S. Environmental Protection Agency (U.S. EPA). 2004a. "Leviathan Mine Superfund Site: Proposal for Year-
Round Treatment System." San Francisco, CA. URL:

http://vosemite.epg.gov/r9/sfund/fsheet.nsf/024bc4d43f9gg0f48825650f005g714e/469733799e2ce6gQ882
56e8400686547/$FILE/Levigthgn%20Mine gpr 04.pdf.

U.S. Environmental Protection Agency (U.S. EPA). 2004b. "NRMRL Evaluates Active and Semi-Passive
Technologies for Treating Acid Mine Drainage." Technology News and Trends. Issue 12. URL: http://clu-
in.org/down logd/newsltrs/tng ndt0504.pdf

U.S. Environmental Protection Agency (U.S. EPA). 2004c "Leviathan Mine, California." ID# CAD980673685.
URL: http://www.epg.gov/superfund/sites/nplfs/fs0901943.pdf. (Accessed on 1 7 April 2006).

U.S. Environmental Protection Agency (U.S. EPA). 2006a. "Compost-Free Bioreactors Remove Metals from
Acid Rock Drainage." Technology News and Trends.

U.S. Environmental Protection Agency (U.S. EPA). 2006b. "Compost-Free Bioreactor Treatment of Acid
Rock Drainage." SITE Technology Capsule. URL:
http://www.epg.gov/QRD/SITE/reports/540r06009/540r06009g.pdf

8 of 10

August 14,2006


-------
Leviathan Mine Technology Case Study

Compost-Free Sulfate-Reducing Bioreactors at Aspen Seep

Attachment A: SRB System Operations in Gravity-Flow Mode (U.S. era, 2006b)

ASFffl Hff
ANAEF.OE'JC
CAPTURE AflEA

IrtfLwri QCrtHbulion Loin Efftiam Coltdjert L-acpa
«'Tsp, Mtddla, Etotic-m ofCdh (Tcp.lfiiUk, fattnn of CaQl

FLOW CONTROL WEJH

PIPE
VAULT

JPFETHA31MEHT ND-I
POND
lljKBtij

HOL
FEED

CHJ5TK
FEED

OVEPfLOWTO
A5PW CREEK

hfkiinl DiBjibuticfi Loop
GOrril HGPELnr

rE"-J-ri

hfliarc Dbtaribuben Loop Effort Cdkciian Lc-jpc
|TiplMiicflBlBGffiimofCil| (hptMithMrtumeFUl

BOREAODRNO.I
(U,S»*3|

3it- ItirrJi diHTrr* ttpw rode

/	1—V

TYPICAL CKK&-2CT10N CF HDflEACTQK



BIOflEAJCTCfi HO. 2
17,000 ft 3l

:^==/

		

EfiurtCdbriHn Loop
RudvTJnin Loop

FLUSHCflAh ID CPS

CDNTHU0USFU3W
STIC FEED SETTING POND

(IMOOfc3!

FLUSHHG FOND AMD
CDNTHJOUS FLOW
5ETTUHG PCND |u rwMl

O

Mmih

RCCK4JNED
AEFH710N QUNHEL

jHjdl h t aivpdi I

a

DRAFT

9 Of 10

July 18, 2006


-------
Leviathan Mine Technology Case Study

Compost-Free Sulfate-Reducing Bioreactors at Aspen Seep

Attachment B: SRB System Operating in Recirculation Mode (U.S. era, 2006b)

r

1ERM

GWHHDWTD
ASPENCHEB

Irfluart DUrbittan l£op
iDlilHCfELIiw

WanurtBhrfcil

Irfluanc [tori bud on Loops Efluart CollKtbn Loot
C^MlEMta.BciiomtfCdt iTcflMttlta, fetiDmofCUO

_ _i	i- .

BBREACTORHO. 1

3-co It hchdUrrwlif rt^rnxt

/ i \

InflLHri [toritudon Lofd Etluart Ldbcttn Lxps
ffcflHiHto.BaitomrfCflG flap, MM* Bottom of Cd&

>	-f-	1 FLUSHDHAH LOOPS

RECflCUUmOHUNE

FUU5H i1 DflAW LOOPS

CAUSTIC FEED .

r-zp-.-c

CCMNJOU3FLCW
SETTlMiPOND

BBREACTOR HO.2
(7JK»fl3|

nPtMLCflGSi -SKTBH OF BBREOOR

¥¦

EfflJHTtColfiCtlooLcap
FLfih'Mn Loop

-a

FUU5HIHGPGNDAND
CONTINUOUS FLOW
SETTLWGPIWiainflrfsdi

¦ h/BDn3|

lU0(KJIt3|

a

_

ABKllONCHMWL
0»y«ls h IhicHxi

DRAFT

10 Of 10

July 18, 2006


-------