vvEPA

United States
Environmental Protection
Agency

For more information

If you have questions or want to learn
more about the OMC, you can contact
these team members:

Mike Joyce

EPA Community Involvement
Coordinator

312-353-5546 or 800-621-8431,
Ext. 35546

8:30 a.m. - 4:30 p.m., weekdays
j oyce .mike@epa.gov

Tim Drexler

EPA Remedial Project Manager
312-353-4367or 800-621-8431,
Ext. 34367

8:30 a.m. - 4:30 p.m., weekdays
drexler.timothy@epa.gov

Erin Rednour

Illinois EPA Project Manager

217-785-8725

erin. rednour@illinois .gov

Site-related documents

Waukegan Public Library Reference
Desk

128 N. County St.

Waukegan

EPA Record Center

77 W. Jackson Blvd., 7th Floor

Chicago

8:30 a.m. - 4:00 p.m., weekdays

Certain EPA information, including
this fact sheet, can be reviewed
electronically at: www.epa.gov/
region5/cleanup/outboardmarine.

An administrative record, which
contains detailed information upon
which the selection of a cleanup
plan is based, is also available at
the Waukegan Public Library and at
EPA's Chicago offices.

EPA Begins Dredging
HarborThis Fall

Outboard Marine Corp.

Waukegan, Illinois	September 2012

The U.S. Environmental Protection Agency and partner Illinois Environmental
Protection Agency will use two hydraulic dredges to clean up Waukegan
Harbor in a sediment removal project scheduled to begin this fall. Between
153,000 and 182,000 cubic yards of contaminated sediment (mud), with
polychlorinated biphenyl (PCB) concentrations greater than 1 part per million,
will be removed. The cleanup will clear the way for the harbor to be delisted as
a Great Lakes Area of Concern (see detail on page 3) and perhaps stimulate the
lakefront area redevelopment projects envisioned by local officials. Dredging
is planned for two seasons and will begin in late September, be shut down over
the winter, restart in May, and end during the summer of 2013. Dredging will
take a total of about 120 days. The use of the harbor and public beach will not
be affected during any of the dredging operations.

Many of the boat slips in the harbor's North Marina (just north of
"Government Pier") have been removed to better dredge in that area. One
of the two hydraulic dredges will operate there. The sediment that must be
removed is thickest in this location. The second hydraulic dredge will start
working in the entrance channel (near the city water plant) and gradually
move into the harbor. Each dredge will be equipped with an 8-inch, swinging
cutter-head that will carve out sediment from the harbor bottom of the harbor.
The hydraulic dredges will then mix the sediment with harbor water to create
a slurry consisting of both sediment and water. Together, the two dredges will
generate slurry consisting of about 15 percent solids and 85 percent water.
This slurry will be pumped out of the harbor at a rate of about 1,800 gallons
per minute and over to the former Outboard Marine Corporation (OMC)

Plant 2 site for processing. (OMC Plant 2 is considered to have been the
source of the PCB contamination in Waukegan Harbor.) Once pumped over
to the Plant 2 processing area, the dredged sediment will be placed in an
8-acre consolidation facility located on the north end of the site.

Slurry processing

The slurry pumped to the Plant 2 site will first be processed to separate the
water from the sediment. The mixture will initially pass through a rotating
screen, much like a wire basket, to remove material larger than one-eighth of
an inch in diameter. The slurry will then flow into an equalization tank to be
chemically conditioned. Next, it will be pumped into a gravity thickener to
concentrate the sediment solids.

The remaining sediment-slurry will then be pumped into large fabric tubes
at the consolidation facility. These tubes will trap the sediment but allow the
remaining water in the sediment to drain and be collected. Both the large
amount of water that is initially separated from the solids in the gravity
thickener, and the residual water collected in the consolidation facility,
will be treated before it is discharged back to the harbor. As part of the
treatment process, the water will be tested frequently for cleanliness before


-------
Hydraulic
Dredge

Hydraulic
Dredge

Consolidation
Facility

reatment
Facility

-Treated Water
Discharge to
Harbor

OMC Superfund Site Sediment Processing

Harbor Oven'iew Showing Dredging Barges and Sediment Processing Facilities

it is discharged. Harbor water will also be mixed into the
discharge water to lower the concentration of ammonia
being released at the discharge point.

Continuous dredging

Dredging operations will be conducted 24-hours a day,
five days per week. Dredging system maintenance will
be conducted during the other two days of the week.
Floodlights placed around the consolidation facility and in
the harbor will enable dredging to continue at night.

Some contaminated sediment located very near to the
walls of the harbor cannot be removed without damaging
those structures. Therefore, a cap will be installed to cover
this sediment. The cap will consist of a special fabric layer
over the sediment and placing a mat of concrete blocks
011 top of it. These measures will make sure these areas
remain secure even when large boats operate in the harbor.
When the harbor cleanup is finished, the treatment plant
will be dismantled for recycling and the consolidation
facility will be covered with a clean soil layer and seeded.

Background

The OMC Superfund site is located in the northern
Waukegan Harbor area in Waukegan, Illinois. The

100-acre OMC site is the former location of an outboard
boat motor manufacturing plant and a former railroad
tie, coal gasification, and coke plant facility. OMC
declared bankruptcy in December 2000 and abandoned
its manufacturing plant in 2002. The city of Waukegan
purchased the Waukegan Manufactured Gas and Coke
Plant (WCP) site and the OMC Plant 2 property from
the bankruptcy estate as part of its plan to revitalize its
lakefront. Due to its large size, U.S. EPA divided the site
into four cleanup parcels: Waukegan Harbor, the WCP site,
PCB-contamment cells, and OMC Plant 2.

Contaminants of concern at the OMC site include PCBs,
which the business used in hydraulic fluids at its boat
motor manufacturing plant, and trichloroethene (TCE), a
chlorinated solvent it used to degrease newly made parts.
PCBs are found in Waukegan Harbor and on the OMC
Plant 2 site and TCE is found in the groundwater under
the OMC Plant 2 site. Groundwater is an environmental
term for underground supply of fresh water. The WCP
site has a different set of contaminants caused by the
former manufactured gas plant and coke plant operations.
Pollution at the WCP site includes tars, creosote, arsenic,
ammonia, and phenol found in soil and groundwater and
cleanup is nearly completed there.


-------
Treatment and Consolidation Facilities on the former OMC Plant 2 Site

Land use in the immediate area of the OMC site is marine
recreational and industrial. Several large industries in the
area use Waukegan Harbor to receive raw materials from
cargo ships. The city of Waukegan has a public beach
on Lake Michigan southeast of the WCP site. Once the
WCP and OMC Plant 2 properties are fully cleaned up,
the city plans to use that land to constaict town homes,
condominiums and shops.

Waukegan Harbor

OMC first cleaned up Waukegan Harbor in 1992 by
dredging PCB-contaminated sediment from the northern
harbor extension area. However, EPA determined in 2009
that more dredging was needed to remove residual PCB
contamination. The dredging project that is the subject of
this fact sheet is expected to accomplish this and advance
the cause of delisting Waukegan Harbor as a Great Lakes
Area of Concern.

For more information about the Waukegan AOC, visit
the EPA's website at www.epa.gov/glnpo/aoc/waukegan.

General information about AOCs and the Great Lakes
can be found at the following websites:

www.epa.gov/glnpo/aoc/

www.epa.gov/glnpo/

Great Lakes Areas of Concern

The Great Lakes, the largest system of fresh water lakes
in the world, are shared by the United States and Canada.
They make up 95 percent of the surface freshwater in
the contiguous United States and have 10,000 miles of
coastline (including connecting channels, mainland and
islands) — more than the contiguous United States" Pacific
and Atlantic coastlines combined. The lakes are a system
of transport and shipping, as well as a place of recreation.

Great Lakes Areas of Concern are designated geographic
areas within the Great Lakes basin that show severe
environmental degradation. There are a total of 43 Areas
of Concern - 26 are in the United States, 12 in Canada, and
five shared by the two countries. Waukegan Harbor is the
only Area of Concern in the state of Illinois.

An Area of Concern must have at least "one beneficial use
impairment which means that it has undergone a change
in its chemical, physical, or biological integrity of a water
body." These include:

•	restrictions on eating fish and wildlife

•	tainting of fish and wildlife flavor

•	degradation of fish and wildlife populations

•	fish tumors or other deformities


-------
•	bird or animal deformities or reproduction problems

•	degradation of benthos, the organisms living at the
bottom of body of water

•	restrictions on dredging activities

•	undesirable algae caused by eutrophication, which is
the over enrichment of water by nutrients

•	drinking water restrictions, or taste and odor problems

•	beach closings

•	degradation of the look and feel of the environment
(known as aesthetics)

•	added costs to agriculture or industry

•	degradation of tiny plants (called phytoplankton)
and tiny animals (called zooplankton) that make up
plankton, the microscopic organisms that float freely in
bodies of water

•	loss of fish and wildlife habitat

The beneficial use impairments at Waukegan Harbor
include restrictions on fish consumption and restrictions on
dredging activities. In October 2011, EPA Administrator

Lisa P. Jackson announced that Waukegan Harbor was one
of the nine AOCs in the United States targeted for cleanup
and delisting by 2014 under the Great Lakes Restoration
Initiative. The harbor cleanup will address these beneficial
use impairments and allow Waukegan Harbor to change
from an Area of Concern to an Area in Recovery and
eventually be delisted.

Environmental cleanups can be very costly. Once all
cleanup actions are completed at all the OMC sites in
Waukegan, EPA estimates that at least $140 million will
have been spent by public and private parties to restore
the sites:

OMC Waukegan Harbor site cleanup action (1990-1993)

-	$21 million

EPA cleanup actions at OMC Plant 2 site (2000-2015) -
$44 million

General Motors and North Shore Gas cleanup actions at
WCP site (1992-2012) - $30 million

EPA Waukegan Harbor site cleanup action (2002-2014)

-	$45 million

¦sjdqy papAoaj}o apeui jaded uo paiuud si }aaqs loej. siq±

||Bj smiJoqjBH BinBpejQ sinBeg \/d3

:yaoo 3nihviai auvoaino

a31S3n03U 30IAH3S l\mni3U

CCWT1 I Cm J	06S£-t,0909 "II 'o6eo|L|Q

oov ij ioai3	-pA|g uos>per mll

(pz-IS) uojSjAjo punpsdns
g uojBsy

AousBv

uoiioaiojj |eiu8wuojiAU3
saieis paijun

Vd3'cv


-------