Project Matching: Facilitating New Renewable Energy Projects
Project Proposal Submittal Form

Opportunity Overview

Apex is pleased to discuss power offtake and investment opportunities for the North Rim Wind Project
with interested parties. For power offtake contracts we are open to consider contract sizes from 5 MW
up to the full 250 MW capacity and we are open to contract lengths of 5 years to 20 years. On the
investment/ownership side there are opportunities for partial or 100% stakes in the sponsor equity and
tax equity financing of the project.

This project is PTC-qualified and in an advanced stage of development with no significant development
hurdles anticipated to reach the scheduled Q4 2016 commercial operation date. We are actively
discussing power offtake and finance opportunities for this project with interested parties and
encourage those interested in additional information to contact us immediately following the webinar.

Contact Information

Ellen Gilman

ellen.gilman@apexcleanenergy.com
434-220-6342

Project Summary
Project name:

North Rim

Developer name:

Apex Clean Energy

Renewable energy type:

Wind

Project city/state:

Beckham County, Oklahoma

Project geographic coordinates (To find, use: www.latlong.net/):

Latitude 35.175935 Longitude -99.811853

1	Apex Clean Energy - North Rim Project


-------
Total planned megawatt (MW DC) size:

Contracts available for 5 MW up to the entire 250 MW project capacity

Are there phases? If so, how many and in what size traunches?

The project can be apportioned out in segments to interested buyers but the project will be

constructed in one phase.

What is the expected annual output of the completed project (MWh)?

Contract portions available for anywhere from 22,324 MWh (5 MW) annual production up to

entire project output of 1,116,210 MWh (250 MW).

Expected date of construction commencement:

On site construction is expected to start in Q2 2016.

Expected date of commercial operation:

Q4 2016. This project is qualified to receive the federal production tax credit ("PTC").

What is the largest development hurdle and how is it anticipated to be overcome?

No major development hurdles are anticipated as this project is completed.

Can you provide examples of similar projects you have developed?

•	December 2012, Apex completed the development and construction of the 300 MW Canadian
Hills Wind project outside Oklahoma City. At the time of its construction, Canadian Hills was
the largest single-phase wind farm in Oklahoma. The project, which utilizes both Repower
and Mitsubishi turbines, sells all of its power through long-term PPAs with three utility off-
takers.

•	In April 2014, Apex executed a transaction for the development, financing, construction and
sale of the 98 MW Hoopeston Wind project in Illinois to IKEA. In March 2015, Apex completed
the construction and transferred ownership of the completed project to IKEA.

•	In October 2014, Apex executed a similar transaction for the development, financing,
construction, and sale of the 165 MW Cameron Wind project to IKEA. Apex is managing
construction of the project and will transfer ownership to IKEA upon commercial operation,
which is scheduled for Q4 2015.

•	Apex developed the 300 MW Balko Wind project in Beaver County, OK and sold the project
to D.E. Shaw in in December 2014. The Balko project, which utilizes GE turbines, will sell all
of its power through long-term PPAs with two utility off-takers. It is expected to begin
commercial operation in Q3 2015.

•	In January 2015, Apex completed the sale of its 300 MW Kingfisher Wind project in Canadian
county, OK to First Reserve. Apex is currently managing construction of the project.
Kingfisher, which will utilize Vestas turbines, is expected to begin commercial operation in Q4
2015.

2

Apex Clean Energy - North Rim Project


-------
•	In February 2015, Apex executed a transaction for the sale of the 300 MW Kay Wind project
in Kay County, OK to Southern Power Company. Apex will complete development, finance
and construct the project, and transfer ownership to Southern upon commercial operation,
which is anticipated in Q4 2015. The Kay Wind project will utilize Siemens turbines and sell its
power through long-term PPAs with two utility off-takers.

Site Readiness

Has the project received all necessary federal, state, and local permits to proceed with construction
and operation? If not, please outline the key permits required to proceed with project construction/
operation and describe the steps you have taken in order to evaluate and address permitting risk for
this project.

With the exception of non-discretionary construction-related permits and local zoning, North Rim
is not subject to any other federal, state, or local permitting requirements in order to build the
Project. North Rim has completed recommended studies and consultations with key federal, state
and local officials.

•	Beckham County has minimal local zoning, which has been changed to accommodate the
Project.

•	Only standard administrative permits are required prior to commencement of construction
activities (e.g., Road Use Agreement).

•	Tier 3 bird and bat studies will continue until late 2015 in coordination with the United
States Fish and Wildlife Service (USFWS) and the Oklahoma Department of Wildlife
Conservation (ODWC). Study results, to date, confirm the site as low risk to birds and bats,
with no threatened or endangered species identified. No permits for special-status species
were recommended or required.

•	The Project is not expected to impact any historic properties listed or eligible for listing on
the National Register of Historic Places. North Rim is not expected to disturb or impact any
culturally or archaeologically significant sites.

Have you secured long-term site control? If so, please describe the nature of the agreement (lease,
ownership, etc.)?

68% site control is secured for the project and no issues are anticipated to complete site control
in Q3 2015. Approximately 37,825 acres of farm land are under long-term lease with 52
landowners.

Have land leases been filed with the county?

Yes.

Does the project require either an Environmental Impact Statement or Environmental Assessment? If
so, what is the status?

Not required.

3

Apex Clean Energy - North Rim Project


-------
Is this project sited on a current or formerly contaminated land, landfill or mine site?1 If so, has the
site addressed the related environmental issues?

Project is located on farmland. Not on contaminated land, landfill or mine site.

Interconnection

What is the status of interconnection, and have system impact and facility studies been completed?
(Distribution or transmission level projects are both eligible)

North Rim will interconnect with the OG&E Woodward-to-Tuco 345 kV transmission line which
runs through the site going from the Tuco Substation in Lubbock, IX to the Woodward Substation
in Woodward, OK.

A generator interconnection request was filed for the project with SPP in 2011 (queue position
GEN-2011-049). The System Impact Study (DISIS-2011-002) was issued in January 2012, and the
Facilities Study was completed in June of the same year. SPP and North Rim Wind entered into
an Interconnection Facilities Study Agreement on February 28, 2014.

The scheduled in-service date for the interconnection facilities ("Energization Date") will be in
August 2016.

•	GIA executed with SPP and OG&E in February 2014 (GEN-2011-049)

•	Interconnection at 345 kV Border Substation and connecting to the Woodward-to-Tuco 345
kV line owned by Oklahoma Gas and Electric

•	Energization of North Rim interconnection facilities at Border substation scheduled for
August 2016

When do you expect the interconnection study process will be complete?

The interconnection study process is complete.

Does the transmission owner (TO) or independent system operator (ISO) have a process to study the
project's impact on the local or regional grid and the subsequent cost to interconnect?

Yes, process completed.

Operation & Financing

Is any element of the project - technology or systems - experimental or pilot-phase or proven
technology?

No. All technology and systems used for the project are proven.

1 Examples of such properties could include brownfields, municipal solid waste landfills, abandoned mine lands,
and Superfund sites, among others subject to state or federal authorities or cleanup programs.

4	Apex Clean Energy - North Rim Project


-------
What is the long- and short-term plan for operating and maintaining the project?

Apex will serve as the long-term operator of the project subject to agreement with the Project's
sponsor equity investor. Apex is currently contracted to serve this role on 1 MW of assets that
are online or scheduled for completion in 2015.

The Apex asset management team provides oversight, management, and optimization of the
Project:

•	Site Services: safety, stakeholder relationship management, operations and maintenance

•	Market Services: performance monitoring and forecasting, scheduling, market participation,
NERC compliance

•	Administrative Services: compliance, accounting, insurance, tax, legal, reporting & analysis

•	Asset Optimization: research, analysis, and implementation of new technologies,
optimization to changes in market conditions

The Project's turbine supplier is anticipated to be the initial primary subcontractor for the
operations and maintenance of the project's turbines, and will provide all required scheduled and
unscheduled service, maintenance and repair work (including all parts, consumables, tools /
cranes) under a fixed fee service agreement that will include an annual availability warranty.

For wind projects, has a meteorological tower been installed? If yes, when was the tower installed
and how much data has been collected?

A robust wind measurement campaign was initiated in April 2008 with the installation of a 60-
meter meteorological tower in the Project area followed by four additional towers, which
captured data for a cumulative collection period of 234 months, and three more towers were
installed in May 2015.

Provide a short summary of how you view project finance and structure/ownership taking shape for
this project:

Apex is actively discussing investment and ownership opportunities for the project with
potential investors and is open to new discussions for partial or full sponsor equity and tax
equity positions.

In anticipation of a 2016 COD for the Project, the proposed capital structure will include the
following:

•	Construction Period. During the construction period, Apex assumes that 85-90% of the
capital required to construct the Project will be provided by a construction loan and 10-15%
from the long-term equity sponsors, which will be Apex and its equity partners.

•	Operational Period. Upon or shortly after COD, Apex anticipates the Project's capital
structure to be as follows: (i) 60% will be supported by tax equity investors; and (ii) 40% will
be supported by our sponsor equity investors, which will be Apex and its equity partners.

This structure is identical to the structure Apex has used to finance many of their projects. For
example, for the 300 MW Balko Wind Farm, the tax equity investors are GE, Bank of America, Citi

5	Apex Clean Energy - North Rim Project


-------
Group, and Google. For the 298 MW Kingfisher Wind Farm, the tax equity investors is a Strategic
investor owned utility. Additional counterparties we have worked with for tax equity include JP
Morgan, Union Bank, State Street and MetLife. For construction lenders, we have worked with
Morgan Stanley, Key Bank, and Santander. With current market knowledge of needs of financing
counterparties from recent large financings such as these, Apex is confident that it will close a
successful financing for Grant Plains on time to support a November 2016 COD.

Partners

In what ways can organizations participate in the project? (Check all that Apply)

X Power purchase agreement for bundled power and RECs
X Financial hedge or contract for differences
X Long term REC offtake
X Financial investment / ownership stake
~ Other, please specify:	

What are some of the characteristics of your ideal power purchaser, investor, or other partner?

Power purchasers, investors or other partners should have investment grade credit.

What marketing opportunities exist at the project?

Apex is open to discussing marketing opportunities such as naming rights with project partners.