^tosrx

:&z) NONPIINTSlURCi SUCCESS STSRV

W J"

PRO^

p\(\sY'Vj I'lX'WCl

Baltimore County Project Restores Stream Channel on Roland Run

Waterbody Improved historical mapping indicates that Roland Run and Thornton Road

Tributary follow similar flow paths from Lutherville to Lake Roland.
However, most of the channel was likely altered in the 1950s to accommodate development,
including housing, infrastructure, utilities, and a ballfield. These historic alterations were considered
the primary contributors to this stream's instability. Restoration and stabilization efforts in the
mainstem helped improve the integrity and function of the stream and extended bank protection in
critical areas. Community outreach efforts educated landowners about the historical degradation of
the stream channel and the project plans designed to stabilize and restore Roland Run. The project
produced a stabilized stream channel with better baseflow and floodplain connection. Monitoring
will be required by the U.S. Army Corps of Engineers (USACE) and the Maryland Department of the
Environment (MDE).

Problem

Roland Run is a tributary of Jones Falls, with head-
waters in Timonium, Maryland. Roland Run flows
south through Lutherville, where it joins Jones Falls in
Lake Roland (Figure 1). The Thornton Road tributary
to Roland Run originates north of Timonium Road,
flowing south and crossing Seminary Road, Interstate
695, and Thornton Road. Historical mapping indicates
that Roland Run and the Thornton Road Tributary
have followed similar flow paths from Lutherville to
Lake Roland as they do today. As a result of develop-
ment during the 1950s, most of the channel was likely
altered to accommodate housing, infrastructure,
utilities, and a baiifieid. Roland Run was listed on
Maryland's CWA section 303(d) list of impaired waters
for nutrients, sediment, and other pollutants.

Story Highlights

In 2001, the design firm, Century Engineering, com-
pleted site surveys, an environmental constraints
analysis, a geomorphic assessment, engineering models,
permitting, plans, and cost estimates for a project
to stabilize and restore the mainstem of Roland Run.
The Thornton Road Tributary's nested channel design
provided multiple grade control structures and bank
protection for higher-flow events. Cross-vane structures
drop flow over a shorter distance, creating larger, low-
stress areas where intermittently submerging vegetated
banks improve baseflow and floodplain connection.

Figure 1. Roland Run is in Baltimore County, MD.

The maintenance of the 2001 mainstem project helped
the integrity and function of the stream and extended
bank protection in critical areas. Installing 120 linear feet
of imbricated riprap bank protection beyond the origi-
nal 2001 project addressed a high vertical streambank

Subwatersheds
I I Roland Run
Ruxton Run
C3 Towson Run

I	J Lake Roland Drainage

Other Layers

| | Lake Roland


-------


Pre- and Post-construction Bank Stream Scoring at Roland Run

Overall



Bank Area







Kiltie & Bend



Channel Broadness



Regular Flow















Flaw Velocity « Dejilli







Sediment Quality



Submerged



Habitat & Cover



POOR OPTIMA!,



¦ Post-contraction ¦ Pre-contruction

Figure 2. Iwo areas of Roland Run, before (left) and
after (right) restoration was completed

adjacent to the ballfield within Essex Farm Park. These
practices reduced sediment and nutrient inputs and
addressed an ongoing safety issue for park users.

Costs of the maintenance and new imbricated riprap
bank protection were not paid for by matching funds.

This project was entirely within a Baltimore County-
owned area, except for two parcels on jeffers Road
along Roland Run. A signed permission was issued for
work to occur on these properties. Certified letters
notifying adjacent property owners of the planned
stream restoration project were sent. A community
meeting was held in May 2019 to inform landowners
of construction plans and answer questions. A link
to Baltimore County's community outreach video
describing stream restoration, including several
educational components, such as trash and watershed
connections, was provided to the community.

Results

This project stabilized the stream channel and estab-
lished better baseflow and floodplain connection
(Figure 2). The project restored the eroding streambed
and channel banks, reducing sediment and nutrient
input. The hyporheic zone (defined as the porous layer
beneath a stream bed where groundwater and surface
water mix) and substantial floodplain wetlands provide
additional nutrient reduction and improved stream
ecology. Landscape adjustments shifted the eroding
channel off private property and provided on-site
coverage of sanitary sewer lines.

Figure 3. Pre-and post-construction bank stream
scores at Roland Run.

Vegetation stabilization has been achieved since con-
struction was completed. Storm flows in the tributary
now frequently overtop the floodplain in a lower
energy and non-erosive manner. The new retrofitted
channel performed as designed in mul tiple significant
storm events. The invasive plants treated before
construction continue to be treated throughout the
area. A more robust native riparian buffer has been
established, along with an aesthetically pleasing park
area for the community and surrounding landowners.

Monitoring is required as part of the USACE™ and MDE-
issued permits. The monitoring requires ongoing physi-
cal surveys of channel stability, vegetation diversity/
viability, invasive species management, and stream
habitat quality over a three- to five-year period.

Results will be presented with annual reports submit-
ted to the overseeing agencies. Stream scores col-
lected before and after construction show improved
stream bank scores at Roland Run (Figure 3).

Partners and Funding

Expenses to date totaled $988,253 for design, construc-
tion, and monitoring. Funding included state grants
($525,944) and EPA section 319 grant funds ($462,309).
A contractor, Stormwater Maintenance and Consulting,
performed the construction services. Many federal,
state, and local agencies were involved throughout the
project, including the Baltimore County Department of
Environmental Protection and Sustainability, Baltimore
County Soil Conservation District, and MDE.

^tDSr<%

* Q '

35

%
\

% /
PRC**

2

o

U.S. Environmental Protection Agency
Office of Water
Washington, DC

EPA 841-F-23-0Q1I
September 2023

For additional information contact:

Robert R. Ryan

Baltimore County EPS Restoration
410-887-2904 • rryan@baltimorecountymd.gov


-------