Situation Photo Log

Wednesday, September 5, 2012
Kalamazoo River / Enbridge Spill

Prepared by:

Larry Rader
START-USEPA
Situation Unit Leader


-------
Wednesday, September 5, 2012 Photo Log

1. Source Area, no sheen observed.

2. Frac Tank City decontamination pad, containment boom staged in decon

pad.


-------
Wednesday, September 5, 2012 Photo Log

4. Sheen and tar globules observed at trestle above Ceresco Dam.


-------
Wednesday, September 5, 2012 Photo Log

5. MP 5.75 river channel, rainbow sheen and tar globs observed
downstream from trestle above Ceresco Dam.

6. Sheen sweeper boat operating at MP 5.75 LDB above Ceresco Dam.


-------
Wednesday, September 5, 2012 Photo Log

7. Ceresco Dam, observed sheen and crew removing debris from the control

point.

8. MP 5.75 LDB, sheen observed downstream from peninsula.


-------
Wednesday, September 5, 2012 Photo Log

9. Ceresco Dam, observed sheen sweeper observed collecting sheen within

containment.

10. MP10.75 no sheen observed.


-------
Wednesday, September 5, 2012 Photo Log

11. Shoreline restoration work observed along west side of Raymond Road.

12. South Mill Pond, no sheen observed.


-------
Wednesday, September 5, 2012 Photo Log

13. MP15.75 north Mill Pond, no sheen observed.

14. Observed sweeper boat heading upstream at MP 22.0.


-------
Wednesday, September 5, 2012 Photo Log

15. MP33.0 A, observed sediment trap survey crew and sweeper boat.

16. Sediment trap poling crew observed at MP 33.0 A.


-------
Wednesday, September 5, 2012 Photo Log

17. E 4.0 containment structure, some sheen and debris observed within

containment.

18. Sheen sweeper pontoon heading to south cove of Morrow Lake.


-------
Wednesday, September 5, 2012 Photo Log

19. Sweeper boat operating in north cove on Morrow Lake

20. Close up of Morrow Lake Dam


-------