QUALITY ASSURANCE PROJECT PLANS

Introduction

This document incorporates the national U.S. EPA Requirements for Quality Assurance
Project Plans (QAPP) and the Region 6 policy requirements into one document for ease of use
by our customers.

It is both a Regulatory requirement and policy of EPA that all projects and tasks
involving environmentally related measurements shall have a QAPP developed and approved
by the Agency prior to any such activities being accomplished. This chapter presents detailed
instructions on what information must be contained in a Quality Assurance Project Plan
(QAPP) for environmental data operations performed by or on behalf of EPA Region 6 and on
the procedures for its review and approval. While there is diversity in the various programs, it
is Region 6 policy that all elements applicable to the QAPP Use Category, to be discussed in
detail further on in this document, will be addressed in each QAPP. To do otherwise would
be to deviate from the national standard and could dilute EPA's goal of national consistency
for Quality Assurance requirements.

The complexity of environmental data operations demands that a systematic process and
structure be established to provide decision makers with the necessary confidence in the quality
of data produced for the decisions to be made, as well as with the means to determine when
the data are not fully usable and what to do about the situation. This process and structure is
provided by the quality system for the organization conducting the environmental data
operations. EPA policy requires that the collection of environmental data by and on behalf of
the Agency be supported by a mandatory Quality System, documented in a Quality
Management Plan (QMP).

An area that must be addressed in each QMP is the systematic planning process used
for each project or task such as the Data Quality Objective process. All projects involving the
generation, acquisition and use of environmental data shall be planned using a systematic plan-
ning process such as the Data Quality Objective process as defined by the current revision of
Guidance for Planning for Data Collection in Support of Environmental Decision Making
Using the Data Quality Objectives Process, EPA QA/G-4, or acceptable alternate. The use of
the Data Quality Objectives process leads to definition of many of the specific elements
required in a QAPP.

It is EPA policy that all decisions and work involving the use of environmental data be
supported by a Quality Assurance Project Plan. The QAPP is the principal product of the

1


-------
planning process inasmuch as it integrates all technical and quality aspects for the life-cycle
of the project, including planning, implementation, and assessment. The QAPP provides a
project or task-specific blueprint of how QA and QC are applied to an environmental data
operation to assure that the results obtained are of the type and quality needed and expected.
Effective implementation of the QAPP should provide the best opportunity to achieve the
technical and quality goals of a project.

The ultimate success of an environmental program or project depends on the quality of
the environmental data collected and used in decision-making, and this may depend
significantly on the adequacy of the QAPP and its effective implementation. Quality planning
is an absolutely essential component of project management and the QAPP provides the
mechanism for documenting the results of the planning process. In the sections to follow, the
elements of the QAPP are discussed in detail. These elements represent the information that
EPA believes to be necessary for data operations involving the characterization of
environmental processes and conditions.

Quality Assurance Project Plan Requirements
QAPP Policy

All work performed by or on behalf of EPA that involves the collection and use of
environmental data1 shall be supported by an Agency-approved Quality Assurance Project Plan
(QAPP). No work performed under contract, work assignment, technical directive, delivery
order, assistance agreement, or inter-agency agreement involving the environmental data
generated from direct measurement activities, collected from other sources, or compiled from
computerized data bases and information systems shall be implemented without an approved
QAPP or without a condition stating that the actual collection of data shall not occur until after
the QAPP is approved. Region 6 has implemented this requirement by establishing a process
that requires a joint certification of the presence and approval status of QMPs and QAPPs by
the Region 6 Quality Assurance Team and the Region 6 Program Office that has management
responsibilities for the particular project.

QAPP Purpose

The QAPP is a critical planning document for any environmental data operation. The
QAPP documents how QA and QC activities will be planned, implemented, and assessed
during the life cycle of a program, project, or task. The QAPP is the "road map" or blueprint
for how a particular project is integrated with the QA program of the organization performing

Environmental data include any information collected, produced, or derived from measurements, analyses,
or models of environmental processes and conditions, or from experimental systems representing such processes
and conditions, including results from laboratory analyses.

2


-------
the work and how the specific QA and QC activities will be applied during a particular project.

Applicability of QAPPs

These QAPP requirements apply to all (intramural and extramural) environmental data
operations that acquire, generate, or compile environmentally-related data and that are per-
formed by or on behalf of EPA. These operations include work performed through contracts,
interagency agreements, and financial assistance agreements (e.g., cooperative agreements,
grants).

Environmental data operations encompass diverse and complex activities, and represent
efforts pertaining to rulemaking, compliance with regulations, and research. Consequently,
any requirements developed to define how QA/QC should be applied to environmental
activities must contain considerable flexibility. This may mean, for example, that some
environmental data operations, perhaps involving research projects, may only require a
qualitative discussion of the experimental process and its objectives, such as a project narrative
statement. Others may require extensive documentation in order to adequately describe a
complex environmental program. This means that the content and level of detail in each
QAPP will vary according to the nature of the work being performed and the intended use of
the data. For QAPPs submitted to EPA Region 6 the decision on the content and level of
detail is to be consistent with national EPA requirements, as defined by the current revision of
EPA Requirements for Quality Assurance Project Plans for Environmental Data Operations,
EPA QA/R-5. It is EPA policy that the type and quality of environmental data needed for
their intended use shall be defined and documented using the EPA Data Quality Objectives
(DQO) Process, or its equivalent, to the extent possible or practicable. The results of the
DQO Process provide key inputs to the QAPP and will largely determine the level of detail
required in the QAPP. These inputs from the DQO Process are identified later.

QAPP Use Categories

Because of the diversity and variability in the mission requirements of the organizations
(e.g., state program offices, EPA regions, research laboratories, municipal organizations)
comprising the environmental community, it is not always possible to define a single checklist
of elements and details needed for all QAPPs. To provide some of the needed flexibility,
several EPA organizations, including Region 6, have been categorizing QAPP requirements
according to the type of work being performed and the intended use of the data. Four
categories have been defined that vary the level of detail and rigor prescribed for particular
QAPPs.

These Use Categories are mandatory for QAPPs prepared and submitted for
approval to U.S. EPA Region 6. They are presented as an aid to determining the level of
detail that may be needed in a QAPP for a particular type of work. This approach recognizes
that not all environmental data operations require QAPPs with the same level of detail. For

3


-------
example, data collected for compliance or enforcement decisions in a Region will require a
more comprehensive QAPP than an exploratory research project conducted for an ORD R&D
laboratory. The categories are:

Category I -	Direct Support to Rulemaking, Enforcement, Regulatory,

or Policy Decisions

These projects include environmental data operations that directly support
rulemaking, enforcement, regulatory, or policy decisions. They also include
research projects of significant national interest, such as those typically
monitored by the Administrator. Category I projects require the most detailed
and rigorous QA and QC for legal and scientific defensibility. Category
Iprojects are typically stand-alone; that is, the results from such projects are sufficient to make
the needed decision without input from other projects.

Category II - Complementary Support to Rulemaking, Regulatory, or Policy
Decisions

These projects include environmental data operations that complement other
projects in support of rulemaking, regulatory, or policy decisions. Such
projects are of sufficient scope and substance that their results could be
combined with those from other projects of similar scope to provide the
necessary information for decisions. Category II projects may also include
certain high-visibility projects as defined by EPA management.

Category III - Interim Studies

These projects include environmental data operations performed as interim steps
in a larger group of operations. Such projects include testing research
hypotheses, estimating effects, developing methods, and other work producing
results that are used to evaluate and select options for interim decisions or to
perform feasibility studies or preliminary assessments of unexplored areas for
possible future work.

Category IV - Basic Studies

These are projects involving environmental data operations to study basic
phenomena or issues, including proof of concept and qualitative screening for
particular analytical species.

4


-------
The final determination of a project's category is made by the EPA Region 6
Program Office2 responsible for the work. Where no category is defined, the preparer of
the QAPP shall assume that it is a Category I project. It should be noted that projects may
contain specific tasks or subtasks that vary in the level of QA/QC requirements. Such
conditions should be considered when deciding on the Use Category for a particular project.

Special Requirements

In some cases, it may be necessary for special requirements to be added to the QAPP
that are not included in this document. When this occurs, such additional elements must also
be addressed by the QAPP in the same manner as the elements listed in this document. The
EPA Region 6 program office sponsoring the work shall delineate any specific requirements
beyond those listed in this manual. If none are specified, the QAPP shall address all elements
required, as specified by their particular Use Category. Attached documentation, such as an
approved Work Plan, Standard Operating Procedures (SOPs), etc., may be referenced in
response to a particular QAPP element. This is, in fact, encouraged to reduce the time
required to prepare the QAPP. The QAPP shall also address related QA planning documenta-
tion (e.g., Quality Management Plans, QA Project Plans) from subcontractors or suppliers of
services critical to the technical and quality objectives of the project or task. In any case, all
referenced documents must be attached to the QAPP itself or be placed on file with the
appropriate EPA office for routine referencing when needed. Such references must be kept
current by the submitter.

QAPP Process Responsibilities and Approvals

The QAPP may be prepared by different groups. The QAPP may be prepared by the
EPA principal investigator for an in-house project and may be reviewed by the principal
investigator's immediate supervisor before it goes to the QA manager or coordinator for final
approval. The QAPP may be prepared by a contractor or an assistance agreement holder. In
addition, the QAPP may be prepared by another Federal agency under an interagency
agreement. These specific situations must be addressed in the organization's QMP to establish
how, when, and by whom review, approval, and effective oversight of QAPPs occurs.

Except where specifically delegated, all QAPPs prepared by non-EPA organizations must
be approved by EPA for implementation. Region 6 policy allows for the development of a
QAPP to occur only after a QMP has been approved, and specifically precludes approval of a
QAPP until the applicable QMP has been approved.

EPA believes that the necessary flexibility in content and level of detail in the QAPP
may be best achieved by having the QAPP requirements reviewed and confirmed by the EPA

2

Organization refers to the EPA Program Office, Region, or ORD Laboratory having an approved Quality
Management Plan that describes its quality system for planning, implementing, and assessing environmental
programs.

5


-------
project manager (or officer)3 with the assistance and concurrence of the EPA QA Manager. In
the case of Region 6, the authority to review and approve QAPPs has been delegated to the
Region 6 Program Offices, and is covered and defined by the Quality Management Plans of
the various divisions.

None of the environmental work addressed by the QAPP should be started until the
initial QAPP has been approved and distributed to project personnel. It is Region 6 policy that
sixty days prior to the initiation of any environmental measurements or data generation, the
recipient (of any EPA funding) shall submit to the EPA Project Officer, for review and
approval, a written Quality Assurance Project Plan for the project. Any costs for
environmental measurements or data generation incurred prior to approval of the QAPP
by the EPA Project Officer will be ineligible for reimbursement. The Region 6 Policy
does not authorize granting conditional approval to a QAPP. There are only two recognized
statuses of a QAPP are approved, and not approved. It is the responsibility of the organiza-
tion performing the work to assure that no environmental data are acquired before the QAPP is
approved and received by project personnel.

QAPP Implementation and Revision

It is EPA policy that all approved QAPPs shall be implemented for the intended work.
It is the responsibility of the group performing the work to implement the approved QAPP
and to ensure that all personnel involved in the work have copies of the approved QAPP and
all other necessary planning documents and understand their requirements prior to the start of
data generation activities.

Because of the complex and diverse nature of environmental data operations, changes
to original plans are often needed. When such changes occur, it is the responsibility of the
Project Manager for whom the work is being performed to determine if the change signifi-
cantly impacts the technical and quality objectives of the project. This determination should be
done in consultation with the QA Manager. When substantive change is contemplated, the
originator of the QAPP shall modify the QAPP as necessary to document the change and
submit the revision for approval by the same parties as for the original review. Only after the
revision has been approved and receipt of the change (at least verbally with written follow-up)
by the project personnel performing the work, shall the change be implemented.

It is absolutely essential that the QAPP be kept current and that aU personnel involved
in the work effort have a current version of the QAPP available. For programs or projects of
long duration, such as multi-year monitoring programs, the QAPPs shall be reviewed at least
annually by the Project Manager, revised if necessary to reflect current needs, and resubmitted

3

This term refers to the responsible EPA official for the project and includes such descriptors as project
officer, work assignment manager, and principal investigator.

6


-------
for review and approval. If the entire QAPP is current, valid and accurately reflects the
project goals and the organization's policy, at a minimum, each year the organization will
submit to EPA Region 6 a certification that the plan is current, to include a copy of new,
signed approval pages for the QAPP.

QAPP Elements

General Content

All projects involving the generation, acquisition, and use of environmental data shall
be planned and documented. The QAPP is the logical product of the planning process and
must provide sufficient detail to demonstrate that:

the project technical and quality objectives (e.g., DQOs, or equivalent) are
identified and agreed upon;

the intended measurements or data acquisition methods are appropriate for
achieving project objectives;

assessment procedures (including QA and QC) are sufficient for obtaining data
of the type and quality needed and expected; and

any limitations on the use of the data can be identified and documented.

Environmental data operations require the coordinated efforts of many individuals,
including managers, engineers, scientists, chemists, statisticians, and others. The QAPP must
integrate the contributions and requirements of everyone involved into a clear, concise
"blueprint" of what is to be accomplished, how it will be done, and by whom. This means it
must provide understandable instructions to those who must implement all parts of the QAPP,
including the field sampling team, the analytical laboratory, and the data reviewers. In all
aspects of the QAPP, the use of national standards and practices, and inclusion of standard
operating procedures is encouraged.

The QAPP elements that follow are presented in an order corresponding to planning,
implementation, and assessment. They have been grouped for convenience into four types of
elements. The individual QAPP elements are numbered sequentially within each group. The
four types of elements and their intent are summarized as follows:

A Project Management - This group of QAPP elements covers the basic area of
project management, including the project history and objectives, roles and
responsibilities of the participants, etc. These elements ensure that the project
has a goal, that the participants understand the goal and the approach to be used,
and that project planning is documented.

7


-------
B Measurement/Data Acquisition - This group of QAPP elements covers all of
aspects of measurement systems design and implementation, ensuring that
appropriate methods for sampling , analysis, data handling, and QC are
employed and will be thoroughly documented.

C Assessment/Oversight - This group of QAPP elements addresses the activities
for assessing the effectiveness of the implementation of the project and associ-
ated QA/QC. The purpose of assessment is to ensure that the QAPP is
implemented as prescribed.

D Data Validation and Usability - This group of QAPP elements covers the QA
activities that occur after the data collection phase of the project is completed.
They ensure that the individual data elements conform to the specified criteria,
thus enabling reconciliation with the project objectives.

The Use Categories and elements are summarized in Table 4-1. As stated earlier, the
decision to use this approach and the determination of a project's category and the actual
QAPP elements required is made by the EPA organization. Region 6 requires the Use
Category Codes be utilized in QAPPs. The term DQO after the QAPP Element title indicates
that the information needed to address this element in the QAPP is usually identified in the
DQO process.

TABLE 4-1 USE CATEGORY CHART

CATEGORY ELEMENT DESCRIPTION

PROJECT MANAGEMENT

, II, HI

II, IV
II

II, IV
II, IV
II, IV
II

II

IV

A1	Title and Approval Sheet

A2	Table of Contents

A3	Distribution List

A4	(DQO) Project/Task Organization

A5	(DQO) Problem Definition/Background

A6	(DQO) Project/Task Description

A7	(DQO) Data Quality Objectives for Measurement Data

A8	Project Narrative (ORD Only)

A9	Special Training Requirements/Certification

A10	Documentation and Records

8


-------
TABLE 4-1 USE CATEGORY CHART

(CONTINUED)

CATEGORY ELEMENT DESCRIPTION
MEASUREMENT/DATA ACQUISITION

I, II, III

B1

(DQO)

Sampling Process Design (Experimental Design)

I, II, III

B2



Sampling Methods Requirements

I, II, III

B3



Sample Handling and Custody Requirements

I, II, III

B4

(DQO)

Analytical Methods Requirements

I, II, III

B5



Quality Control Requirements

I, II

B6



Instrument/Equipment Testing, Inspection, and
Maintenance Requirements

I, II, III

B7



Instrument Calibration and Frequency

I

B8



Inspection/Acceptance Requirements for Supplies
and Consumables

I, II, III

B9



Data Acquisition Requirements (Non-direct Mea-
surements)

I, II

BIO



Data Management

ASSESSMENT/OVERSIGHT

I, II, III	CI	Assessments and Response Actions

I, II, III	C2	Reports to Management

DATA VALIDATION AND USABILITY

I, II, III

D1

Data Review, Validation, and Verification Re





quirements

I, II

D2

Validation and Verification Methods

I, II, III

D3

Reconciliation with Data Quality Objectives

9


-------
Group A, Project Management

A1	Title and Approval Sheet

Include:

Title of the plan

Name of the organization(s) implementing the project
Names, titles, signatures of appropriate approving officials and
approval dates for:

Organization's Project Manager (Required)
Organization's Quality Assurance Manager (Required)
Project Subordinate Supervisors Concurrence (Optional)
Region 6 EPA Project Manager (Required)

Region 6 EPA Approving Official (Required)4
Others, as needed (e.g., State, other Federal Agency)

Title and Region 6 QTRAK number of the approved Quality
Management Plan applicable to submitted QAPP

Submission of at least two original approval pages is recommended.

A2	Table of Contents

List the sections, figures, tables, references, and appendices. Document control
format may be required at the option of the Project Manager and QA Manager,
and is encouraged by EPA Region 6. When required, use document control
format in the upper right-hand corner of each page following the Title and
Approval Sheet. For example:

Section No. .
Revision No.

Date	

Page	of.

4

"EPA Approving Official" is the Region 6 Program Office Manager or staff person designated and
authorized by Certification of the Region 6 QA Officer to approve QAPPs. If the EPA Project Manager/Officer
is unable to determine the approving official, contact the Office of Quality Assurance.

10


-------
A3	Distribution List

List the individuals and their organizations who will receive copies of the
approved QAPP and any subsequent revisions. Include all managers who are
responsible for implementing the plan, as well as the QA managers and
representatives of all groups involved.

A4	Project/Task Organization	(DQO)

Identify the individuals or organizations participating in the project and discuss
their specific roles and responsibilities. Include the principal data users and the
decision-makers. The project quality assurance manager shall be independent
of the unit generating the data. This does not include senior officials, such as
corporate managers or agency administrators, who are nominally but not
functionally involved in data generation, data use, or decision-making. The
QAPP should also identify the person (s) responsible for approving and
accepting final products and deliverables.

Provide a concise organization chart showing the relationships and the lines of
communication among all project participants. Include other data users who are
outside of the organization generating the data, but for whom the data are
nevertheless intended; e.g., modelers, risk assessors, design engineers, toxicolo-
gists, etc. Where direct contact between project managers and data users does
not occur, such as, between a project consultant for a Potentially Responsible
Party and EPA risk assessment staff, the organization chart should show the
route by which information is exchanged. The organization chart should also
identify any subcontractor relationships relevant to environmental data
operations. This chart should be realistic and practical, and should reflect only
actual lines of authority and communication for the project described. Names
of current incumbent occupying a position is essential, as is the identification of
vacant positions.

A5	Problem Definition/Background	(DQO)

State the specific problem to be solved or decision to be made. Include
sufficient background information to provide a historical perspective for this
particular project. For example, this would include the regulatory or alleged
toxic exposure situation that led to the need for this project. The discussion
must include enough information about the problem, the past history, any
previous work or data, and any regulatory or legal context to allow a techni-
cally-trained reader to make sense of the project objectives and activities.

11


-------
This discussion also identifies the decision maker (s) and the principal customer (s)
for the results. (When the Data Quality Objectives [DQO] process has been
used, this information should be readily available.)

A6	Project/Task Description	(DQO)

Provide a description of the work to be performed. This discussion may
notneed to be lengthy or overly detailed, but it should give a overall picture of
how the project will resolve the problem or question described in A5. Describe
in general terms the following, as needed:

Measurements that are expected during the course of the project and the
approach that will be used.

Applicable technical, regulatory, or program-specific quality standards,
criteria, or objectives.

Any special personnel and equipment requirements that may indicate the
complexity of the project.

The assessment tools needed (i.e., program technical reviews, peer
reviews, surveillances, and technical audits as needed and/or specified
by the QMP) for the project.

A schedule for the work to be performed.

Project and quality records required, including the types of reports
needed.

A7	Quality Objectives and Criteria for Measurement Data (DQO)

Any QAPP must include a statement of the project quality objectives and
measurement performance criteria. EPA recommends that a graded approach be
used in planning, such as the Data Quality Objectives (DQO) Process. Even in
those cases in which the formal DQO Process is not needed, a statement of the
project quality objectives and measurement performance criteria is needed. The
DQO process provides quality objectives based on several factors chosen by the
user of the data. For details on the DQO Process and when it should be used,
please see the EPA guidance document (QA/G-4)5.

5 EPA QA/G-4 is Guidance for Planning for Data Collection in Support of Environmental Decision
Making Using the Data Quality Objectives Process.

12


-------
The project quality objectives should be stated in quantitative terms to the extent
possible:

Example: UV Treatment of Contaminated Groundwater. "The purpose
of this project is to demonstrate whether or not the residual
trichloroethane concentration in the treated water is less than 0.5 (ig/L
at a confidence level of 95 percent."

Without such quantitative goals, it is difficult to know whether the selected
analytical method is sufficiently sensitive or precise, or whether a sufficient
number of samples are being collected. Sometimes, of course, project objec-
tives must be stated somewhat less quantitatively, particularly in those situations
when the use of the formal DQO Process is not needed.

Example: Oil Spill Remediation. "One objective of this project is to
determine whether the populations of clams, mussels, and sand fleas
recover more rapidly in the treated than the untreated area."

Example: Epidemiology Study. "The purpose of this project is to
determine whether the concentrations of indoor NO2 and soot are greater
in the residences of lung cancer patients than in the residences of healthy
persons."

The section on project quality objectives and measurement performance criteria
should address, as appropriate, the following:

the scope of the project; that is, the domain (geographical locale and
boundaries, environmental medium, time period, etc.) over which
conclusions and decisions will apply:

the time, resource, or other constraints on the measurement project;

the intended uses of the data, in order of importance and the expected
users of the data;

the specific data needed: type, quantity, matrices involved;

the action levels or standards upon which decisions will be made,
including the detection limits and data reporting units, and the source(s)
of this information;

the population parameter(s) of interest; e.g., mean, maximum, or range,
which specify the form the data will be in when compared against action

13


-------
levels or standards;

the acceptable level of confidence in the data needed for the stated
purposes or the acceptable amount of uncertainty;

the quantitative sensitivity, precision, bias, and completeness criteria
for each major measurement planned (including all pollutant and process
measurements) for each sample matrix, based on the DQO statements;

the units of expression of the precision and bias goals, which should
correspond to the methods selected to assess data precision and bias;
and

the goals for achieving data representativeness and comparability, and
the planning considerations for attaining these goals (unlike precision,
bias, and completeness, these objectives are not usually expressed or
assessed quantitatively);

Data quality or measurement performance criteria may be typically specified in
terms of detection or quantitation limits, precision, bias, and comparability.
However, simply listing requirements for precision, bias, and completeness
without further discussion is not sufficient. Even statements such as "bias will
be measured as percent recovery of a matrix spike sample" are of marginal
help. In specifying data quality, it is thus essential to specify exactly how such
quality will be measured and interpreted.

Example: A possible statement of bias requirement. "Bias will be mea-
sured a minimum of five times throughout this project by the analysis of
standard reference materials No. 956B. Recovery of TCE from this
SRM should average 85 percent or greater, with a relative standard
deviation of no more than 20 percent."

Data specifications should also be distinguished from the specific QC proce-
dures that are routinely carried out as part of each measurement. QC proce-
dures are used while carrying out specific procedures; data specifications are
used for selecting the appropriate methods and QC criteria.

The QAPP may need to define different types of sensitivity (i.e., qualitative,
quantitative, screening, etc.) that may be appropriate for different parts of the
project.

The quantitative goals should reflect the total measurement, if possible, or

14


-------
address the field, laboratory, and data handling components separately. In the
event there is no basis for defining data quality goals for the project, goals

may be estimated based on prior knowledge of the measurement system,
and on method validation studies (using replicates, spikes, standards, recovery,
studies, etc.) Explain the circumstances under which these goals were estab-
lished.

If defining quantitative goals is not relevant for certain measurements, indicate
this and state the reason.

Data representativeness is the degree to which the environmental samples truly
reflect the population or material in the real world. It can be affected by the
time, place, and manner by which the samples are collected.

Data comparability is dependent upon consistency in sampling condi-
tions, selection of sampling procedures, sample preservation methods, analytical
methods, and data reporting units, throughout the project, and with previous
projects with which these results will be compared.

The DQO Process for compliance and/or enforcement projects in the Regions
may not be within the control of the EPA project manager and QA manager.
The measurement performance criteria are specified in regulations, permits, or
orders. Whether or not those criteria satisfy the requirements of this document,
they are absolutely required. Often the results of the DQO Process are not
expressible in the terms stated here, such as precision, bias, or comparability.
The affected source is simply required to follow a specified method. In such
cases, it is sufficient for the portion of the QAPP addressing the DQO Process
to state that the testing will satisfy the regulatory requirements specified. This
does not, however, relieve the project manager or QA manager from their
responsibility to comply with all other applicable QAPP requirements in this
document.

Project Narrative

Discuss in a narrative form the following issues as they pertain to the project or
task, as needed:

work to be performed or hypothesis to be tested,
anticipated use of the data,

how (quantitatively or qualitatively) the success of the project or task

will be determined (A7, D3),

survey design requirements and description (Bl),

15


-------
sample type and sampling location requirements (B2),
sample handling and custody requirements (B3),
selection of analytical methods (B4),

calibration and performance evaluation samples for sampling and
analytical methods used (B5),

sampling or analytical instrumentation requirements (B6),

plans for peer or readiness reviews prior to data collection (CI), and

any on-going assessments during actual operation (oversight) (CI).

QAPP elements corresponding to the items to be addressed in the narrative are
given in parentheses. The narrative should allow technical or QA readers to
relate the project or task to the DQOs and to the Problem Definition stated
earlier in the QAPP. (The use of the Project Narrative is consistent with the
Use Category scheme described in Appendix A. Since this element addresses in
narrative form many other QAPP elements, it is not necessary to specifically
include those elements in a Category IV QAPP. Moreover, because the
elements listed above would be addressed in more detail in Category I, II, and
III QAPPs, it is not necessary to include this element for those categories.)

A9	Special Training Requirements/Certification

Identify and describe any specialized training or certification requirements for
personnel in order to successfully complete the project or task. Discuss how
such training will be provided and how the necessary skills will be assured and
documented.

A10	Documentation and Records

Itemize the information and records which must be included in a data report
package for the project or task, and specify the reporting format, if desired.
Documentation can include raw data, filed logs, instrument printouts, and
results of calibration and QC checks. Specify the laboratory data reporting
turnaround time. Specify whether a field sampling and/or laboratory analysis
"case narrative"6 is required to provide a complete description of any difficulties
encountered during sampling or analysis.

Specify any requirements for the final disposition of records and documents
from the project, including location and length of retention period.

6

"Case Narrative" refers to an annotated summary of the analytical work performed by a laboratory that
describes in narrative form what activities were performed and identifies any problems encountered. The case
narrative provides additional information to user in interpreting the data received.

16


-------
Group B, Measurement/Data Acquisition

The following QAPP elements describe the requirements related to the actual methods
to be used for the:

collection, handling, and analysis of samples;

direct measurement of parameters that do not require the actual collec-
tion of a sample; and

the management (i.e., compiling, handling) of the data.

The methods described in these elements may have been cited earlier in element A6;
however, the purpose here is to include sufficient detailed information to ensure that the
methods are verified and documented. As long as the designated methods are well docu-
mented and are readily available to all project participants, specific citations are adequate. If
these methods are not readily available, detailed copies of the methods and/or SOPs must
accompany the QAPP as attachments.

B1	Sampling Process Design (Experimental Design) (DQO)

Outline in general terms the experimental design of the project and the antici-
pated project activities, including the types of samples required, sampling
network design, sampling frequencies, sample matrices, measurement parame-
ters of interest, and the rationale for the design. If individual sampling plans
will be developed for discrete project phases, include their preparation schedule.

Describe techniques or guidelines to be followed in selecting sampling points
and frequencies, well installation design (when applicable), field decontamina-
tion procedures and materials needed, and sampling equipment. When field
screening techniques will be used to identify samples for laboratory analysis,
describe the criteria for sample selection. Similarly, when locational data are to
be collected, stored, and transmitted, the method (s) used must be specified and
described (or referenced). Key elements to be addressed include how locations
and their bias are determined.

All measurements should be classified as critical (i.e., required to achieve
project objectives) or non-critical (informational purposes only). Critical
measurements will undergo closer scrutiny during the review and data gathering
process, and will have first-claim on limited budget resources.

For non-standard methods or unusual sample matrices and situations, appropri-
ate method validation study information is needed to confirm the performance

17


-------
of the method for the particular matrix. Such validation studies may included
round-robin studies performed by other organizations. If previous validation
studies are not available, they must be developed during the project and
included as part of the project results. It is very important for this element to
include complete documentation and validation of both the sampling and
analytical methodologies. Identifying standard methods by number, date, and
regulatory citation (as appropriate) is often sufficient. However, many
published (and even regulatory) methods allow the user to select from various
options. The method citations should state exactly which options are being
selected.

Measurement of process conditions is often essential to a project (e.g., indus-
trial plant or control equipment operation associated with a compliance test,
meteorological parameters associated with impoundment volatization). In such
cases, the experimental design must include the design and validation techniques
as described above.

B2	Sampling Methods Requirements

Describe the procedures for collecting samples. Identify the required sampling
methods (and/or equipment, if automated), including any implementation
requirements, decontamination procedures and materials needed, and any
specific performance requirements for the method. For each sampling method,
identify any support facilities needed. The discussion should also address what
to do if there is a failure in the sampling or measurement system and who is
responsible for corrective action.

Describe the preparation and decontamination of sampling equipment, including
disposal of decontamination by-products; the selection and preparation of
sample containers, sample volumes, preservation methods, and maximum
holding times to sample extraction and/or analysis. A tabular presentation
format is strongly recommended, particularly when two or more sample
matrices are involved.

B3	Sample Handling and Custody Requirements

Describe the provisions for sample handling and shipment, taking into account
the nature of the samples and the maximum allowable sample holding times
before extraction or analysis. Describes the following provisions for sample

18


-------
custody, in both the field and the laboratory:

Forms, notebooks and procedures to record the exact location and
ambient conditions associated with sample collection, possession and
analysis. In the laboratory, a sample custody log should be maintained.

Examples of sample documentation forms, such as sample labels,
custody seals, and chain-of-custody forms.

Labeling procedures and information entered on the forms, including
sample preservation, if any, and dates and times of sample transfer and
analysis.

Procedures for transferring and maintaining custody of samples.

B4	Analytical Methods Requirements (DQO)

Identify the analytical methods and/or equipment required, including any
extraction methods needed, laboratory decontamination procedures and materi-
als needed (such as in the case of hazardous or radioactive samples), waste
disposal requirements (if any), and any specific performance requirements for
the method. The QAPP should also address what to do if there is a failure in
the analytical system and who is responsible for corrective action.

B5	Quality Control Requirements

Discuss QC procedures that should be associated with each sampling, analysis,
or measurement technique. Such specific procedures are performed routinely
during the measurement process, and the results are required to be evaluated
immediately by the technician upon completion of the test. Results must fall
within certain acceptance criteria, or specific corrective action is required. For
projects at or beyond the "proof-of-concept" stage, or for projects employing
well-characterized methods, this section should list each required QC procedure,
along with the associated acceptance criteria and corrective action. Because
standard methods are often vague or incomplete in specifying QC requirements,
simply relying on the cited method to provide this information is usually
insufficient. In any case, QC procedures must frequently be modified on a
project-specific basis in order to meet data specifications.

QC procedures must be compatible with the data specifications discussed above.

This means, if a measurement must be precise within +20 percent, the stability
of calibration checks must be somewhat better than +20 percent. For some

19


-------
research-oriented projects, the analytical technique may not be available until
well into the project. In such instances, detailed QC requirements may
not need to be specified in the initial QAPP. More appropriately, the initial
document might specify general requirements for precision, bias, and detection
limits, and the means of achieving these goals would be developed by the
principal investigator during the course of the project.

List the required QC checks, such as matrix spikes, duplicates, blanks,
laboratory control samples, surrogates, or second column confirmation. State
the frequency of analysis for each type of QC check, and the spike compounds
and levels. State or reference the required control limits for each QC check
and corrective action required when control limits are exceeded.

Describe the procedures to be used to calculate each of the QC statistics,
including the QC checks described in the preceding paragraph as well as
precision and bias. Copies of the formulas are acceptable as long as the
accompanying narrative or explanation specifies clearly how the calculations
will address difficult situations such as missing data values and "less than" or
"greater than" values.

Instrument/Equipment Testing, Inspection, and Maintenance Re-
quirements

Discuss how inspections and acceptance testing, including the use of QC
standards and reference materials, of environmental sampling and measurement
systems and their components must be performed and documented to assure
their intended use as specified by the design. Identify and discuss how final
acceptance shall be performed by independent personnel (e.g., personnel other
than those performing the work). Discuss how deficiencies are to be resolved
when acceptance criteria are not met, and how and when re-inspection will be
performed as necessary.

Discuss how periodic preventive and corrective maintenance of measurement or
test equipment shall be performed to ensure availability and satisfactory
performance of the systems. Identify the equipment and/or systems requiring
periodic maintenance. Discuss how the availability of critical spare parts,
identified in the operating guidance and/or design specifications of the systems,
will be assured and maintained.

20


-------
B7	Instrument Calibration and Frequency

Identify all tools, gauges, instruments, and other sampling, measuring, and test
equipment used for data collection activities affecting quality that must be
controlled and, at specified periods, calibrated to maintain bias within specified
limits. Discuss how calibration shall be conducted using certified equipment
and/or standards with known valid relationships to nationally recognized
performance standards. If no such nationally recognized standards exist,
document the basis for the calibration. Identify the certified equipment and/or
standards used for calibration. Indicate how documentation of calibration shall
be maintained and be traceable to the instrument.

B8	Inspection/Acceptance Requirements for Supplies and Consumables

Discuss how and by whom supplies and consumables shall be inspected and
accepted for use in the project. Supplies and consumables are those items
necessary to support the sampling and analytical operation. They include, but
are not limited to: sample bottles, calibration gases, reagents, hoses, materials
for decontamination of sampling equipment, deionized water, and potable
water. Identify acceptance criteria for such supplies and consumables in order
to satisfy the technical and quality objectives of the project or task.

B9	Data Acquisition Requirements (Non-direct Measurements)

Identify the type of data acquired from non-measurement sources such as
computer data bases, spreadsheets, and programs, and literature files. Define
acceptance criteria for the use of the data in this project. Discuss any limita-
tions on the use of the data based on uncertainty in the quality of the data and
discuss the nature of that uncertainty.

BIO	Data Management

Outline the project data management scheme, tracing the path of the data,
beginning from receipt from the field or laboratory, to the use or storage of the
final reported form. Describe the standard record-keeping procedures,
document control system, and the approach used for data storage and retrieval
on electronic media. Discuss the control mechanism for detecting and correct-
ing paperwork errors and for preventing loss of data during data reduction (i.e.,
calculations), data reporting, and data entry to forms, reports, and databases.

21


-------
Provide examples of any forms or checklists to be used.

Identify and describe all data handling equipment and procedures that will be
used to process, compile, and analyze the data. This includes procedures for
addressing data generated as part of this project as well as data from other
sources. The specifications should include any required computer hardware and
software and should address any specific performance requirements for the
hardware/software configuration used. Describe the procedures that will be
followed to demonstrate acceptability of the hardware/software configuration
required.

Group C, Assessment/Oversight

Assessments and Response Actions

Identify the number, frequency, and type of assessment activities needed for this
project. Assessments include, but are not limited to, the following:

surveillance,
peer review,

management systems review,
readiness review,
technical systems audit,
performance evaluation,
audit of data quality, and
data quality assessment.

Discuss the information expected from the assessment and success criteria (i.e.,
goals, performance objectives, acceptance criteria specifications, etc.) for each
assessment proposed. For each proposed assessment, list the approximate
schedule of activities, and discuss the information expected from the assessment
and the criteria for success. For any planned self-assessments (utilizing
personnel from within the project groups), identify the participants and their
exact relationship within the project organization. For independent assessments,
identify the organization and person(s) that will perform the assessments.

Discuss how and to whom the results of the assessments will be reported.

Define the authorities of the assessors. For example, if the assessors should
order a work suspension upon finding a significant condition, this section
delineates clearly their authority to do so. Define explicitly the unsatisfactory
conditions under which the assessors are authorized to act. Recognizing that
assessments may be needed at any time during the project, provide a schedule
for the assessments to be performed.

22


-------
Discuss how response actions to non-conforming conditions will be addressed
and by whom. Identify who is responsible for implementing the response
action. Describe how response actions will be verified, validated, and docu-
mented.

C2	Reports to Management

Identify the frequency, content, and distribution of reports issued to inform
management of the following:

status of the project;

results of performance evaluations and system audits;

results of periodic data quality assessments; and

significant quality assurance problems and recommended solutions.

Identify the responsible organization(s) that will prepare the reports, and the
recipients of the reports. Identify any other status reports to management as
well as their content and frequency.

Group D, Data Validation and Usability

D1	Data Review, Validation, and Verification Requirements

State the criteria used to review and validate - that is, accept, reject, or qualify -
data, in an objective and consistent manner. Provide examples of any forms or
checklists to be used.

Project-specific calculations or algorithms should be discussed. Some projects
may require special calculation during or after data generation:

Example: Indoor Air Pollution. Consider a project that is meant to
estimate the number of residences within the greater Washington, D. C.,
area exhibiting NO concentrations greater than 100 |_ig/m; at a
frequency of 30 of more days per year. Once NO measurements are
available, one would attempt to extrapolate the limited information to the
greater metropolitan area. The QAPP should explain the statistical
techniques that will be employed, including how uncertainties will be
assessed.

For other projects, one may only need to calculate a mass balance of ade-

23


-------
struction/removal efficiency. While these are much simpler requirements,

the specific formulas and data inputs should be listed. This approach
helps assure that at least the minimum necessary data are collected for the
intended interpretation (even if additional interpretation schemes are eventually
employed).

D2	Validation and Verification Methods

Describe the process to be used for validating and verifying data, including the
chain of custody for data throughout the life cycle of the project or task.
Discuss how issues shall be resolved and the authorities for resolving such
issues. Describe how the results are conveyed to data users. The review of
data can include checks of the following: transmittal errors, field and labora-
tory QC data, detection limits, instrument calibration, special sampling or
analysis conditions, performance evaluations, technical systems audits, contract
compliance issues (e.g., holding times), and statistical data treatments, such as
tests for identification of potential outliers.

D3	Reconciliation with Data Quality Objectives

Describe how the results obtained from the project or task will be reconciled
with the results of the DQO Process. Describe how issues will be resolved.
Discuss how limitations on the use of the data will be reported to decision
makers. Identify the procedures used to assess precision, bias, and complete-
ness for the project data.

A methodology has been developed to assist users in reconciling data results
with the DQOs. The Data Quality Assessment (DQA) Process is used to
assess the scientific and statistical quality of data collected for a specific
purpose. In the DQA Process, the data will be analyzed scientifically to inspect
for technical anomalies and to judge that the context of the data is correct. At
the same time, the data will be evaluated statistically to confirm that the
statistical model was correct by selecting a statistical test and validating the test
by verifying assumptions, such as for distribution and independence. The
outcome of the DQA process will indicate whether a decision can be made using
the existing data or additional data must be collected.

24


-------
APPENDIX A
TERMS AND DEFINITIONS

Activity - an all-inclusive term describing a specific set of operations or related tasks to be
performed, either serially or in parallel (e.g., research and development, field sampling,
analytical operations, equipment fabrication), that in total result in a product or service.

Assessment - the evaluation process used to measure the performance or effectiveness of a
system and its elements. In this Standard, assessment is an all-inclusive term used to denote
any of the following: audit, performance evaluation, management systems review, peer
review, inspection or surveillance.

Audit - a planned and documented investigative evaluation of an item or process to determine
the adequacy and effectiveness as well as compliance with established procedures, instructions,
drawings, QAPPs, and other applicable documents.

Characteristic - any property or attribute of a datum, item, process, or service that is distinct,
describable, and measurable.

Computer Program - a sequence of instructions suitable for processing by a computer.
Processing may include the use of an assembler, a compiler, an interpreter, or a translator to
prepare the program for execution. A computer program may be stored on magnetic media,
and be referred to as "software", or may be stored permanently on computer chips, and be
referred to as "firmware". Computer programs covered by this Standard are those used for
design analysis, data acquisition, data reduction, data storage (data bases), operation or
control, and data base or document control registers when used as the controlled source of
quality information.

Contractor - any organization or individual that contracts to furnish services or items or
perform work.

Corrective Action - measures taken to rectify conditions adverse to quality and, where
necessary, to preclude their recurrence.

Customer - any individual or organization for whom items or services are furnished or work
performed in response to defined requirements and expectations.

Data Quality Assessment (DQA) - a process of statistical and scientific evaluation that is used
to assess the validity and performance of the data collection design and statistical test, and to
establish whether a data set is adequate for its intended use.

25


-------
Data Quality Objectives (DQOs) - a statement of the precise data, the manner in which such
data may be combined, and the acceptable uncertainty in those data in order to resolve an
environmental problem or condition. This may also include the criteria or specifications
needed to design a study that resolves the question or decision addressed by the DQO process.

Data Quality Objectives Process - a Total Quality Management (TQM) tool, based on the
Scientific Method and developed by the U.S. Environmental Protection Agency to facilitate the
planning of environmental data collection activities. The DQO process enables planners to
focus their planning efforts by specifying the use of the data (the decision), the decision
criteria (action level), and the decision maker's acceptable decision error rates. The products
of the DQO process are the DQOs (See also Graded Approach).

Data Usability - the process of ensuring or determining whether the quality of the data
produced meets the intended use of the data.

Design Review - a documented evaluation by a team, including personnel other than the
original designers, the responsible designers, the customer for the work or product being
designed, and a QA representative to determine if a proposed design will meet the established
design criteria and perform as expected when implemented.

Engineered Environmental Systems - an all-inclusive term used to describe pollution control
devices and systems, waste treatment processes and storage facilities, and site remediation
technologies and their components that may be utilized to remove pollutants or contaminants
from the environment. Examples include wet scrubbers (air), soil washing (soil), granulated
activated carbon unit (water), and filtration (air, water). Usually, this term will apply to
hardware-based systems; however, it will also apply to methods or techniques used for
pollutant reduction or containment of contamination to prevent further movement of the
contaminants, such as capping, solidification or vitrification, and biological treatment.

Environmental Conditions - the description of a physical medium (e.g., air, water, soil,
sediment) or biological system expressed in terms of its physical, chemical, radiological, or
biological characteristics.

Environmental Data - any measurements or information that describe environmental
processes or conditions, or the performance of engineered environmental systems.

Environmental Data Operations - work performed to obtain, use, or report information
pertaining to environmental processes and conditions.

Environmental Monitoring - the process of measuring or collecting environmental data.
Environmental Processes - manufactured or natural processes that produce discharges to or

26


-------
impact the ambient environment.

Environmental Programs - an all-inclusive term pertaining to any work or activities involving
the environment, including but not limited to: characterization of environmental processes and
conditions; environmental monitoring; environmental research and development; the design,
construction, and operation of engineered environmental systems; and laboratory operations on
environmental samples.

Environmentally Related Measurements - the data collection activity or investigation
involving the assessment of chemical, physical or biological factors in the environment which
affect human health or the quality of life.

Financial Assistance - the process by which funds are provided by one organization (usually
government) to another organization for the purpose of performing work or furnishing services
or items. Financial assistance mechanisms include grants, cooperative agreements, and
government interagency agreements.

Graded Approach - the process of basing the level of application of managerial controls
applied to an item or work according to the intended use of results and the degree of
confidence needed in the quality of the results. (See Data Quality Objectives Process).

Hazardous Waste - any waste materials that satisfies the definition of "hazardous waste" as
given in 40 CFR Part 261, "Identification and Listing of Hazardous Waste."

Independent Assessment - an assessment performed by a qualified individual, group, or
organization that is not a part of the organization directly performing and accountable for the
work being assessed.

Inspection - examination or measurement of an item or activity to verify conformance to
specific requirements.

Item - an all-inclusive term used in place of the following: appurtenance, facility, sample
assembly, component, equipment, material, module, part, product, structure, subassembly,
subsystem, system, unit, documented concepts, or data.

Management - those individuals directly responsible and accountable for planning,
implementing, and assessing work.

Management System - a structured non-technical system describing the policies, objectives,
principles, organizational authority, responsibilities, accountability, and implementation plan
of an organization for conducting work and producing items and services.

Management System Review (MSR) - the qualitative assessment of a data collection

27


-------
operation and/or organization(s) to establish whether the prevailing quality management
structure, policies, practices, and procedures are adequate for ensuring that the type and
quality of data needed are obtained.

May - denotes permission but not a requirement.

Method - a body of procedures and techniques for performing an activity (e.g., sampling,
chemical analysis, quantification) systematically presented in the order in which they are to be
executed.

Mixed Waste - hazardous waste material, as defined by 40 CFR part 261 (RCRA), mixed
with radioactive constituents.

Must - denotes a requirement that has to be met.

Peer Review - a documented critical review of work generally beyond the state of the art or
characterized by the existence of potential uncertainty. The peer review is conducted by
qualified individuals (or organization) who are independent of those who performed the work,
but are collectively equivalent in technical expertise (i.e., peers) to those who performed the
original work. The peer review is conducted to ensure that activities are technically adequate,
competently performed, properly documented, and satisfy established technical and quality
requirements. The peer review is an in-depth assessment of the assumptions, calculations,
extrapolations, alternate interpretations, methodology, acceptance criteria, and conclusions
pertaining to specific work and of the documentation that supports them. Peer reviews provide
an evaluation of a subject where quantitative methods of analysis or measures of success are
unavailable or undefined, such as in research and development.

Performance Evaluation (PE) - a type of audit in which the quantitative data generated in a
measurement system are obtained independently and compared with routinely obtained data to
evaluate the proficiency of an analyst or laboratory.

Procedure - a documented set of steps or actions that systematically specifies or describes how
an activity is to be performed.

Process - an orderly system of actions that are intended to achieve a desired end or result.
Examples of processes include analysis, design, data collection, operation, fabrication, and
calculation.

QTRAK - is a Computer Program that contains database information on Quality
Management Plans and Quality Assurance Project Plans to the Program Managers, Project
Officers, and the OQA for planning and assessment of the status of regional Quality
Management Plans and the associated Project Plans.

28


-------
Qualified Data - any data that have been modified or adjusted as part of statistical or
mathematical evaluation, data validation, or data verification operations.

Quality - the sum of features and properties/characteristics of a process, item, or service that
bears on its ability to meet the stated needs and expectations of the user.

Quality Assurance (QA) - an integrated system of management activities involving planning,
implementation, assessment, reporting, and quality improvement to ensure that a process,
item, or service is of the type and quality needed and expected by the customer.

Quality Assurance Division (QAD) - the U.S. EPA's headquarters staff element that
establishes and promulgates Quality Assurance Policy, formerly Quality Assurance
Management Staff (QAMS).

Quality Assurance Officer (QAO) - the designated Region 6 staff member that has the
delegated authority for approval of all Quality Management Plans in Region 6, Chief of the
Quality Assurance Team.

Quality Assurance Program Description/Plan see Quality Management Plan.

Quality Assurance Project Plan (QAPP) - a formal document describing in comprehensive
detail the necessary QA, QC, and other technical activities that must be implemented to ensure
that the results of the work performed will satisfy the stated performance criteria.

Quality Control (QC) - the overall system of technical activities that measures the attributes
and performance of a process, item, or service against defined standards to verify that they
meet the stated requirements established by the customer.

Quality Improvement - a management program for improving the quality of operations. Such
management programs generally entail a formal mechanism for encouraging worker
recommendations with timely management evaluation and feedback or implementation.

Quality Indicators - measurable attributes of the attainment of the necessary quality for a
particular environmental decision. Indicators of quality include precision, bias, completeness,
representativeness, reproducibility, comparability, and statistical confidence.

Quality Management - that aspect of the overall management system of the organization that
determines and implements the quality policy. Quality management includes strategic planning,
allocation of resources, and other systematic activities (e.g., planning, implementation, and
assessment) pertaining to the quality system.

Quality Management Plan (QMP) - a formal document that describes the quality system in

29


-------
terms of the organizational structure, functional responsibilities of management and staff, lines
of authority, and required interfaces for those planning, implementing, and assessing all
activities conducted.

Quality System - a structured and documented management system describing the policies,
objectives, principles, organizational authority, responsibilities accountability, and
implementation plan of an organization for ensuring quality in its work processes, products
(items), and services. The quality system provides the framework for planning, implementing,
and assessing work performed by the organization and for carrying out required QA and QC.

Radioactive Waste - waste material containing radionuclides, or contaminated by
radionuclides.

Readiness Review - a systematic, documented review of the readiness for the startup or
continued use of a facility, process, or activity. Readiness reviews are typically conducted
before proceeding beyond project milestones and prior to initiation of a major phase of work.

Remediation - the process of reducing the concentration of a contaminant (or contaminants) in
air, water, or soil media to a level that poses an acceptable risk to human health.

Research (Applied) - a process, the objective of which is to gain knowledge or understanding
necessary for determining the means by which a recognized and specific need may be met.

Research (Basic) - a process, the objective of which is to gain knowledge or understanding of
the fundamental aspect of phenomena and of observable facts without specific applications
toward processes or products in mind.

Research Development/Demonstration - Systematic use of the knowledge and understanding
gained from research and directed toward the production of useful materials, devices, systems,
or methods, including prototypes and processes.

Self-Assessment - Assessments of work conducting by individuals, groups, or organizations
directly responsible for overseeing and/or performing the work.

Service - the category of economic activity that does not produce manufactured items. In
environmental data operations or engineering projects, such activities include design,
inspection, laboratory and/or field analysis, repair, and installation.

Shall - denotes a requirement that is mandatory and has to be met.

Should - denotes a guideline or recommendation.

30


-------
Significant Condition - any state, status, incident, or situation of an environmental process or
condition of an engineered environmental system in which the work being performed will be
adversely affected in a manner sufficiently serious to require corrective action to satisfy quality
objectives or specifications and safety requirements.

Software Life Cycle - the period of time that starts when a software product is conceived and
ends when the software product is no longer available for routine use. The software life cycle
typically includes a requirements phase, a design phase, an implementation phase, a test phase,
an installation and check-out phase, an operation and maintenance phase, and sometimes a
retirement phase.

Standard Operating Procedure (SOP) - a written document that details the method for an
operation, analysis, or action with thoroughly prescribed techniques and steps, and that is
Officially approved as the method for performing certain routine or repetitive tasks.

Supplier - any individual or organization furnishing items or services or performing work
according to a procurement document or financial assistance agreement. This is an all-
inclusive term used in place of any of the following: vendor, seller, contractor, subcontractor,
fabricator, or consultant.

Surveillance - the act of monitoring or observing a process or activity to verify conformance
to specified requirements.

Technical Review - a documented critical review of work that has been performed within the
state of the art. The review is accomplished by one or more qualified reviewers who are
independent of those who performed the work, but are collectively equivalent in technical
expertise to those who performed the original work. The reviews are an in-depth analysis and
evaluation of documents, activities, material, data, or items that require technical verification
or validation for applicability, correctness, adequacy, completeness, and assurance that
established requirements are satisfied.

Technical Systems Audit (TSA) - a thorough, systematic, on-site qualitative audit of
facilities, equipment, personnel, training procedures, record keeping, data validation, data
management, and reporting aspects of a system.

Total Quality Management (TQM) - the process of applying quality management to all
activities of the organization, including technical and administrative operations. See Quality
Management and Quality System.

Validation - an activity that demonstrates or confirms that a process, item, data set, or service
satisfies the requirements defined by the user.

Verification - the act of authenticating or formally asserting the truth that a process, item, data

31


-------
set, or service is, in fact, that which is claimed.

Work - the process of performing a defined task or activity (e.g., research and development,
field sampling, analytical operations, equipment fabrication).