2020 RCRA GPRA Corrective Action Work Plan

for

EPA Region 6

Regional Strategy to Complete Corrective Action by 2020

January 30, 2009

Updated: September 9, 2009; April 6, 2010; November 11, 2010; June 29, 2011; August 24, 2011;
November 16, 2011 for FY11 End of Year; December 19, 2011; February 1, 2012; March 21, 2012

Carl E. Edlund, P.E.

Director, Multimedia Planning and Permitting Division


-------
Executive Summary of Regional Strategy to Complete Corrective Action by 2020 from the
Updated 2020 RCRA GPRA Corrective Action Work Plan - EPA Region 6

Goal: Achieve 2020 GPRA Corrective Action goals by September 30, 2020. It is projected that 95% of sites will attain the
Remedy Construction Complete (CA550) milestone.

Baseline/Background: 412 total facilities: Goal is 391 facilities with site-wide CA550-Construction Complete documented
starting with 127 facilities with construction complete at the beginning of 2009 leaving 264 sites to complete in 12 years or
22 sites per year.

Strategy: Region 6 employs a multifaceted approach to address the major challenges of attaining the 2020 goals. The
major elements of the strategy have been used successfully since 1999 allowing the Region to always meet or exceed the
GPRA yearly Annual Commitment System (ACS) targets and achieve the final 2005 and 2008 national OSW goals.
Additions and modifications are made to the strategy as is found convenient or necessary.

Grant Negotiations for 2020: First, Region 6 states were asked to provide 2020 corrective action planning information
and projections and secondly, they were asked to make key commitments for FY09 that if sustained, would result in
achieving the corrective action goals. States responded positively and the initial results indicate that the goals are
achievable as long as conditions remain the same. This approach of has been continued in FY10, FY11 and FY12
showing good progress toward the goals.

Review. Analyze, and Categorize Sites: All planning information provided by the state and Region was reviewed to
determine an individual site's present status and then the 412 total facilities categorized into A, B, and C categories based
on technical and resource requirements. 27 A sites and 45 B sites will require the most EPA and state resources to
address corrective action. 274 C sites are state lead sites that require mainly EPA oversight. A sub-category of state
sites, 35 C-D sites were identified as state lead sites that are having some type of difficulties in the clean-up process.

Also, 31 C-E/C-D-E sites were identified as sites that Region 6 has previously spent time, money, or other resources in
the corrective action process.

For further planning purposes, 13 sites are identified in orange in the work plan as problematic and not likely to achieve
construction complete unless EPA and the states partner to find innovative solutions. These sites are underfunded,
bankrupt, or abandoned, as well as large, complex sites that may not achieve the goal. Another 19 facilities are identified
in yellow in the work plan as requiring extra attention in that they are presently under an EPA order or EPA is partnering


-------
with the state by providing resources to the state. Many times resources are leveraged and innovative approaches to
corrective action are successfully used. Some examples of these case studies are summarized in the work plan.

Provide Resources to Assist or Partner with States: In addition to grant funding, the Region assists in numerous ways
to move sites toward the construction complete goal.

EPA Contract Assistance or EPA Technical Assistance: Help to assess sites with sampling and analysis,
perform ground water surveys, review documents, select remedies, perform modeling, etc.

EPA Training: Numerous trainings have been provided and more are planned to be presented.

Development and Updating of Corrective Action Strategy (CAS): Accelerate cleanups and encourage the use
of risk-based approaches, flexibility, and performance based remedies.

Enforcement Resources: Enforcement staff to perform inspections at some baseline sites and issue new orders
as necessary to expedite site assessment and remediation.

Superfund Resources: Occasionally used for site assessments and removal actions to assist with underfunded
and bankrupt sites.

Increased Communication: A team approach is used in order to solve corrective action issues. State managers,
coordinators, and site project managers are met with in order to obtain more details regarding the individual facilities in
order to develop individual plans for sites where the Region's technical, contractor, or other resources are needed.
Adjustments to the information in this 2020 work plan will be made as new information is obtained.


-------
Updated 2020 RCRA GPRA Work Plan - EPA Region 6
Regional Strategy to Complete Corrective Action by 2020

Goal: Achieve 2020 GPRA goals by September 30, 2020. By the end of FY2020, the cleanup of existing contamination
at RCRA regulated GPRA facilities will be completed, though some long-term remediation work may be ongoing (e.g.
groundwater pump and treat, etc.) The stated goal is that 95% of GPRA baseline sites will attain the Remedy
Construction Completed (CA550) milestone for site-wide RCRA corrective action.

Baseline/Background: The Region 6 2020 Baseline consists of 412 facilities (258 TX, 64 LA, 36
OK, 31 AR and 23 NM). Of those 412 facilities, Region 6 has direct corrective action lead at 62 sites
that are either EPA enforcement lead sites or those facilities where States have requested EPA to
take the lead because of staffing or other issues. EPA is or has provided technical assistance to
States on approximately 41 additional facilities that are BRAC or where they have been determined to
be bankrupt, underfunded or have new ownership with undetermined resources or expertise to
complete corrective action obligations or are large mega-sites.

Strategy: Region 6 has developed a multifaceted approach to address major challenges to
achieving corrective action goals for the GPRA 2020 baseline facilities. The elements of the strategy
have been used successfully since 1999 allowing the Region to always meet or exceed the GPRA yearly and final 2005
and 2008 goals. Additions and modifications are made to the strategy as is found convenient or necessary.

To better track and manage progress at its 2020 baseline facilities the Region has sorted all 412 facilities into three
manageable categories (and two subcategories) based on the expected workload requirement for an EPA project
manager. The classification of each site and can be changed as conditions change. For example as the work is
completed or the milestone is completed by EPA, the category is changed.

State

Facilities

AR

31

LA

64

NM

23

OK

36

TX

258

Total

412


-------
1)	Category A Sites: 24 facilities that are: i) 6PD lead sites that were transferred from the Enforcement Division for
case closure; ii) bankrupt or underfunded facilities; iii) facilities with questionable technical or financial resources; or
iv) EPA lead federal facilities.

2)	Category B Sites: 39 facilities that are: i) State lead sites where the Region is providing the State significant
technical assistance and expects to provide future assistance; ii) sites that Texas identified where they had no project
manager assigned and were given to EPA as project lead; iii) BRAC sites, iv) some large complex sites.

3)	Category C Sites: 276 facilities that are State lead sites where EPA assistance is expected to be minimal. EPA
involvement is expected to be limited to oversight and tracking progress.

4)	Category C-D Sites: 31 facilities that are State lead sites where EPA assistance is expected to be minimal. EPA
involvement is expected to be limited to oversight and tracking progress. However, these are sites that are slow
moving in the corrective action process or present other difficulties to the state. These are sites identified by states in
their individual plans as requiring extra work. These are problematic 'C' Sites that especially need to be monitored for
progress.

5)	Category C-E Sites (or C-D-E): 42 facilities that EPA has either: 1) completed the work, i.e. achieved the
"construction complete" determination or closed the enforcement case, and/or 2) EPA previously contributed
significant technical and/or contractor assistance and/or 3) returned the site to State lead sites. In other words, the
facilities are no longer requiring EPA significant resources but have in the past.

Of the 412 facilities in Region 6, 127 of these sites have construction complete determinations documented at beginning
of FY09. At the end of FY11, 199 had achieved this milestone indicating excellent progress toward the 2020 goal of 95%.
This is 72 sites completed in 3 fiscal years or an average of 24 per year which is slightly ahead of the 22 per year
projected.

Of the sites listed in Table 3., 13 sites are identified as problematic (in orange) as not likely to achieve construction
complete unless EPA and the states partner to find innovative solutions. These sites are underfunded, bankrupt or
abandoned as well as large complex sites that may not achieve the goal. Another 19 facilities are identified in yellow in
Table 3. of the work plan as requiring extra attention in that they are presently under an EPA order or EPA is partnering
with the state by providing resources to the state. Many times resources are leveraged and innovative approaches to




-------
corrective action are successfully used. Some examples of these case studies are summarized in this work plan in
Appendixes 1, 2, and 3.

EPA project managers are assigned, as appropriate, to a subset of the 412 facilities for either direct implementation of
project management, technical assistance to the state as needed, or state oversight responsibilities depending upon the
workload as described in project categories. Project managers will also be responsible for providing and inputting EPA
data into the RCRAInfo national database. Table 4. categorizes the more time consuming or difficult sites in a couple of
ways to depict future challenges which require resources in another way.

Additional Significant Efforts to Achieve 2020 GPRA Goals Including Providing Resources to Assist or Partner
with States:

All Region 6 States are authorized for RCRA corrective actions and are recognized as critical partners in meeting GPRA
goals. The Region is collaborating with States and assisting them in managing many projects. The following is a summary
of other additional resources that have been dedicated to achieving the goals as well as specific activities that the Region
is undertaking to ensure we meet the 2020 goals.

• Understanding The Universe - Where are the facilities in the corrective action process, and what do they have left
to complete? This is very important to further this process. We have done the following in conjunction with our
states:

o All Region 6 States sent letters to each of their facilities requesting information and have received good
responses;

o This information was used to help plan site-specific activities to meet 2020 goals; and
o EPA staff and contractors have also conducted extensive file reviews at Texas and Louisiana State offices
to obtain information to complete CA725/750 forms and CA400/CA550 memorandums where interim
remedies could be considered as final actions,
o As explained below, all five in Region 6 states have submitted plans and projections regarding the 2020
facilities corrective action status.


-------
Improving Data Quality - to help plan and track 2020 milestones:

o EPA Region 6 has been working closely with each of its States on RCRAInfo data cleanups over the past
several years; and

o EPA staff and contractor support has been used to conduct file reviews to assist in data cleanup activities on
hundreds of facilities to date.

GPRA Team Approach To Meeting Corrective Action Goals - EPA staff and government contractors work closely
with State project managers to provide technical assistance on difficult sites (i.e., large and complex, underfunded,
etc). Assistance is in the form of developing conceptual site models, data gap identification, conducting sampling
and analysis, laboratory support, detailed file reviews, Environmental Indicators form completion, and other
relevant tasks.

Grant Restructuring - Region 6 began restructuring performance based grants with each state in 1997 to focus on
corrective action final results over the process and in 1999 focused on achieving GPRA commitments (CA725 and
CA750). Beginning with the RCRA grants in 2006, specific language was added to require state commitments to
obtain the site-wide remedy selection (CA400) and construction complete (CA550) determinations.

Grant Reguirements for 2020 Projections and Plans - Grants also require the states to develop specific 2020 plans
for meeting the 2020 corrective action goals. All five states have provided projections and information regarding
specific sites. Region 6 states indicate that they plan to achieve the targets. The ability to successfully meet the
plan cannot be as certain if resources available to EPA and the states are significantly less than when the initiative
was started. This appears to be the trend in these difficult financial times.

Grant Negotiations for 2020 - New grant commitment numbers were negotiated for FY09 for each of the corrective
action measurements (CA400, CA550, CA725, and CA750). If the states are able to sustain the number of sites
committed to in FY09 for future years, then the 2020 goal will be met. The projections and plans submitted for all of
the states support this approach. See Chart 1 and Table 1 below. Grant progress is tracked through RCRA info
reports as well as monthly calls, mid and end of the year grant reviews.


-------
•	Risk-Based Approach - We are promoting streamlined risk-based performance based corrective action approaches
(Texas Risk Reduction Program (TRRP), Louisiana Risk Evaluation Corrective Action Program (RECAP), Region 6
Corrective Action Strategy (CAS) and use of innovative investigations and cleanup technologies.

•	Performance-Based Remedies - The new edition of Corrective Action Strategy (CAS) emphasizes performance-
based remedies using media-specific corrective action objectives to support the performance standards of source
removal, treatment or containment, achievement of regulatory cleanup values or risk-based values. The emphasis
is on attaining the Corrective Action Objectives (CAOs) - not on choosing a technology. This approach can assist
in negotiating remedies at some sites. An example is Altus Air Force Base.

•	Flexibility - We are promoting programmatic flexibility through the use of alternative authorities and facility lead
agreements to speed up site investigation and cleanups.

•	Training - Region 6 conducts training for States and industry on: RCRA fundamentals, completion of Environmental
Indicator evaluations, development of conceptual site models, vapor intrusion evaluations, use of innovative
technologies for investigation and cleanup, permitting modifications, and moving from interim measures to final
corrective actions. The ORCR training "RCRA Corrective Action Training: Getting to YES! Strategies for Meeting
the 2020 Vision" was presented in Austin, Texas, in April 2009, and was presented by EPA Region 6 staff in Baton
Rouge, Louisiana, in April 2010.

•	Superfund - Superfund staff/resources are utilized where focused site assessments and/or removals are needed
(bankrupt facilities, under-funded sites, or where our recommendations can help prioritize site clean-ups).

•	Enforcement and Permitting Coordination including the National Enforcement Strategy for Corrective Action
(NESCA)- In preparation for the 2020 initiative, a 2006 Memorandum of Understanding (MoU) was negotiated
between 6PD (permitting) and 6EN (enforcement). It was agreed that permitting project managers would take over
the corrective action reviews of baseline sites undergoing the corrective action process due to EPA orders
previously issued. This action would in turn free up enforcement staff to perform inspections at baseline sites and




-------
issue new orders as necessary to expedite site assessment and remediation. In 2010, the National Enforcement
Strategy for Corrective Action (NESCA) was finalized which encourages similar initiatives as the 2006 Region 6
Moll, such as the need for robust communication with our state counterparts. Some examples of NESCA ideas
used by Region 6 include: 1) issuance of RCRA 3007 letters to near bankrupt sites to attain financial status of the
corporations (i.e., Benton Creosote) , 2) issuance of 3013 Orders to gather information on closure/NFA status
(International Shoe, Motiva), 3) incorporation of "hard schedules" for corrective action milestones ( Formosa
Plastics 2011 site-wide 3008(h) AOC), 4) inclusion of a financial assurance review as part of our annual Region 6
oversight review of the corrective action and permitting programs, and 5) prioritizing our oversight reviews of state
corrective action and permitting program based on environmental justice ratings used in Region 6.

•	Environmental Justice (EJ) - The Region 6 RCRA Program Environmental Justice (EJ) strategy describes the
goals and methods for incorporating EJ into the day to day operations of our program. The strategy is found in
Appendix 4. This will incorporate EJ into the setting of priorities for oversight reviews of EPA and state lead
corrective action activities at facilities. Coordination with each of our states will occur to ensure that appropriate
actions are taken for all sites and that disproportionately burdened populations are included to the extent
practicable in the decision making process. Staff will be assigned to sites given priority because they are located in
areas of concern. Referrals to enforcement or requests for additional support will be prioritized based impact to the
areas of concern.

•	Increase Communication - In addition to above listed calls and meetings, the Region has increased communication
with states and facilities (conference calls, meetings, site visits) to closely track progress, identify potential
impediments (technical, financial, regulatory, etc), and identify need for support.

•	Continue Planning - As mentioned, close communication with state counterparts is a key factor. A team approach
is used in order to solve corrective action issues. State managers, coordinators, and state site project managers
are met with or conference calls are held to obtain more details regarding the individual facilities in order to develop
individual plans for sites where the Region's technical, contractor, or other resources are needed. Communication,
tracking, and oversight are continuing processes. Adjustments to the information in the 2020 work plan are made
as new information is obtained.




-------
Achievement of the 2020 GPRA Corrective Action Goals

The Achievement of the 2020 GPRA goals for corrective action is dependent on the availability of sufficient resources
to undertake the required tasks. This is true for both the state and EPA regional organizations. At present, state and
Federal budgets are being cut meaning that the number of staff working on the investigation and cleanup of RCRA
facilities on the GPRA baseline are significantly reduced. State and EPA staff have other tasks and non-GPRA sites
that are part of their workload that they must address as well which stretches resources even further. The two largest
Region 6 states, Texas and Louisiana, have both seen drastic reductions in corrective action and other staff in the
recent past. Any reductions in grant money to the states will also hamper the progress of investigations and cleanup
of sites as well as any reduction in EPA staff and/or corrective action contract monies. It is essential that sufficient
funding be available at all levels in order to meet the 2020 GPRA corrective action goals to progress 95% of the
baseline sites to the site-wide construction complete stage.




-------
~ 10 ~


-------
Chart 1: Region 6 Projected Progress for 2020 RCRA Corrective Action

GPRA Construction Complete (CA550) Goal

300

250

™ 200

150

100

50

~ Projected Number of Facilties Remaining at End
of Fiscal Year Required to Complete 95% Goal
by 2020

¦ Actual Number of Facilties Remaining at End of
Fiscal Year Showing Progress to Complete 95%
Goal by 2020



10	11	12	13	14	15	16	17	18	19	20

Fiscal Year

/-V/ ^ ^ /V/


-------
TABLE1A: NUMBER OF FACILITIES PROJECTED TO ACHIEVE RCRA GPRA MEASUREMENTS
AND PERCENT OF 95% (391 FACILITIES) GOAL COMPLETED LISTED BY FISCAL YEAR :

(ORIGINAL TABLE)

MEASUREMENT START FY09 FY09 FY10 FY11 FY12 FY13 FY14

CA725: HUMAN EXPOSURES

246

(63%)

261
(66%)

276
(70%)

291

(74%)

306
(78%)

321
(82%)

336
(86%)

CA750: GROUND WATER

216

(55%)

231
(59%)

246

(63%)

261
(66%)

276
(70%)

291

(74%)

306
(78%)

CA400: REMEDY

145

(37%)

165

(42%)

185

(47%)

205
(52%)

225
(57%)

245
(62%)

265
(67%)

CA550: CONSTRUCTION

127

(32%)

149

(38%)

171

(44%)

19

(49%)

215
(55%)

237
(60%)

259
(66%)

~ 12 ~


-------
TABLE 1B: NUMBER OF FACILITIES PROJECTED TO ACHIEVE RCRA GPRA MEASUREMENTS AND
PERCENT OF 95% (391 FACILITIES) GOAL COMPLETED LISTED BY FISCAL YEAR - UPDATED 09/30/11

START













MEASUREMENT FYQg

FY09

FY10

FY11

FY12

FY13

FY14

CA725: HUMAN EXPOSURES

261 (66%)

276 (70%)

291 (74%)







246 (63%)

ACTUAL

ACTUAL

ACTUAL

309 (79%)

324 (83%)

339 (87%)



262 (67%)

313 (80%)

328 (84%)







CA750: GROUND WATER

231 (59%)

246 (63%)

261 (66%)







216 (55%)

ACTUAL

ACTUAL

ACTUAL

294 (75%)

309 (79%)

324 (83%)



233 (60%)

251 (64%)

266 (68%)







CA400: REMEDY

165 (42%)

185 (47%)

205 (52%)







145 (37%)

ACTUAL

ACTUAL

ACTUAL

248 (63%)

267(68%)

289 (74%)



173 (44%)

199 (51%)

228 (58%)







CA550: CONSTRUCTION

149 (38%)

171 (44%)

193 (49%)







127 (32%)

ACTUAL

ACTUAL

ACTUAL

226 (58%)

248 (63%)

270 (69%)



151 (39%)

177(45%)

199 (51%)







~ 13 ~


-------
TABLE 2: PROJECTED NUMBER OF FACILITIES ACHIEVING RCRA GPRA MEASUREMENTS AND
PERCENT OF UNIVERSE OF 412 FACILITIES COMPLETED BY FISCAL YEAR 2020 VERSUS ACTUAL

Updated 09/30/2011

MEASUREMENT

START
FY09

FY09

FY10

FY11

FY12

FY13

FY14

CA725: HUMAN EXPOSURE

246 (60%)

261 (63%)

ACTUAL

262(64%)

276 (67%)

ACTUAL

313 (76%)

291 (71%)

ACTUAL

328 (80%)

309 (75%)

324 (79%)

339 (82%)

CA750: GROUND WATER

216 (52%)

231 (56%)

ACTUAL

233 (57%)

246 (60%)

ACTUAL

251 (61%)

261 (63%)

ACTUAL

266 (65%)

294 (71%)

309 (75%)

324 (79%)

CA400: REMEDY

145 (35%)

165 (40%)

ACTUAL

173 (42%)

185 (45%)

ACTUAL

199 (48%)

205 (50%)

ACTUAL

228 (55%)

248 (60%)

267(65%)

289 (70%)

CA550: CONSTRUCTION

127 (31%)

149 (36%)

ACTUAL

151 (37%)

171 (42%)

ACTUAL

177(43%)

193 (47%)

ACTUAL

199 (48%)

226 (55%)

248 (60%)

270 (66%)

/-V/ ^ zji /V/


-------
Chart 2: Region 6 Projected versus Actual Progress to Complete
RCRA 2020 Corrective Action Construction Complete (CA550)

Goal - Updated 9/30/2011

w
a>

o
re

a>
.a

E

450
400
350
300
250
200
150
100
50
0

¦ Projected Number of Facilties to be Accomplished at
- End of Fiscal Year to Complete 391 Sites (95%) by 2020

_ ¦ Actual Number of 412 Total Facilities Completed at

End of Fiscal Year Showing Progress toward 2020 Goal





















































































































































































9 10 11 12 13 14 15

Fiscal Year

16

17

18

19

20

~ 15 ~


-------
EXPLANATION OF TABLE 3 BELOW:

1.	Category A Sites: 24 facilities that are: i) 6PD lead sites that were transferred from the Enforcement Division for
case closure; ii) bankrupt or underfunded facilities; iii) facilities with questionable technical or financial resources; or
iv) EPA lead federal facilities. These are the most resource intensive for both technical expertise and EPA contractor
work.

2.	Category B Sites: 39 facilities that are: i) State lead sites where the Region is providing the State significant
technical assistance and expects to provide future assistance; ii) sites that Texas identified where they had no project
manager assigned and were given to EPA as project lead; iii) BRAC sites, iv) some large complex sites. These sites
also require significant EPA resources.

3.	Category C Sites: 276 facilities that are State lead sites where EPA assistance is expected to be minimal. EPA
involvement is expected to be limited to oversight and tracking progress.

4.	Category C-D Sites: 31 facilities that are State lead sites where EPA assistance is expected to be minimal. EPA
involvement is expected to be limited to oversight and tracking progress. However, these are sites that are slow
moving in the corrective action process or present other difficulties to the state. These are sites identified by states in
their individual plans as requiring extra work. These are problematic 'C' Sites that especially need to be monitored for
progress.

5.	Category C-E Sites (or C-D-E): 42 facilities that EPA has either: 1) completed the work, i.e. achieved the
"construction complete" determination or closed the enforcement case, and/or 2) EPA previously contributed
significant technical and/or contractor assistance and/or 3) returned the site to State lead sites. In other words, the
facilities are no longer requiring EPA

6.	Orange is most difficult sites and less likely to achieve the goals.

7.	Yellow is for sites that require extra attention from the Region in that they are being cleaned up under an
order or EPA is assisting the state .

~ 16 ~


-------
TABLE 3: FACILITIES OF CONCERN TO BE ADDRESSED FOR COMPLETION OF THE
REMEDY CONSTRUCTION (CA550): THE A, B, C-D, C-D-E AND C-E SITES

CATEGORY

BASELINE FACILITIES

EPA ID

COMMENTS

A

Elementis Chromium LTP
(American Chrome & Chemicals)

TXD098818339

Corrective action conducted via EPA CONSENT DECREE and state orders. The
CA725 checklist was completed by TCEQ; EPA order covers eastern portion. A
barrier wall was installed in December 2009 to prevent releases to the ship
channel. Statement of Basis for remedy selection projected for 4th quarter 2010.

A

Benton Creosoting Works

LAD008056632

Small site but underfunded. EPA assistance with waste disposal using USACE
contractors.

A

Chalmette Refining, LLC

LAD008179707

EPA LEAD AGENCY; being cleaned up under an EPA order

A

Encycle Texas
(Corpus Christi)

TXD008117186

EPA ORDER-CA400 AND CA550 codes have not been achieved. Some
hurricane preparedness work being completed with financial assurance money.
Long term cleanup to be completed with bankrupt court funding.

A

Ethyl Corp (Baton Rouge)

LAD079460895

Contaminated deep aquifer with DNAPL; slow to progress. EPA is providing
assistance with ground water modeling.

A

Exxon Chemical (Houston)

TXD082684002

EPA LEAD. EPA order - CA400 and CA550 should already been achieved for
big muddy area (area in IHWCA)

A

Formosa Plastics (Point Comfort)

TXT490011293

EPA LEAD under EPA order. Remedy decision effective March 11, 2010. State
is working on newer part of site. All corrective action in now under an EPA order
filed January 18, 2012.

A

Greenway Environmental, Inc.

OKD089761290

Site is abandoned and being cleaned up with limited financial assurance money.
EPA is assisting with contract funds, grant funds, and technical assistance using
EPA staff.

A

Hale Dusting Service, Inc.

TXD057573438

Entity has no funds to support cleanup. EPA staff is using EPA contractor to
delineate the extent of arsenic and pesticide contamination in soil and ground
water.

A

Heat Treatment Services

TXD980624035

EPA providing state with Vapor Intrusion Assistance.

A

Huffman Wood Preserving

OKD053128492

Site is abandoned and being cleaned up with limited financial assurance money
and innovative approaches. EPA assistance provided by staff, contractor, and
EPA laboratories. Construction complete projected for 2011.

A

International Shoe Co.
(Bryan)/Furniture Brands

TXD008071227

EPA LEAD 04/06/10 update from Tara Hubner with R6 indicated that a 3013
EPA order was issued in November 2009 to address confirmation ground water
sampling at site to re-verify suspected data results from an earlier investigation.
Permanent type wells will be installed and sampled (to replace temporary wells
providing suspect data results due to turbidity issues). COCs to be sampled will
involve arsenic, lead, and bis(2-ethylhexyl) phthalate.

~ 17 ~


-------
CATEGORY

BASELINE FACILITIES

EPA ID

COMMENTS

A

Longview Refining (Longview)

TXD045586187

EPA LEAD; Underfunded site; previously abandoned site purchased for
speculation; a well survey has been completed.

A

MCKINNEY SMELTING INC

TXR000025387

EPA 6PD CASE -EPA LEAD SITE. STATE PM INDICATES THAT ALL CODES
HAVE NOT BEEN ACHIEVED AT THIS TIME AS ASSESSMENT IS NOT
COMPLETE. PREVIOUS OWNERS WENT BANKRUPT AND THE PROPERTY
OWNER HAS NOT COMPLETED THE TASK. CITY OF MCKINNEY WANTS
TO BUY THE PROPERTY BUT NO PURCHASE AGREEMENT WITH THE
OWNER HAS BEEN EXECUTED. ADDITIONAL ENFORCEMENT ACTION IS
POSSIBLE.

A

MicroChemical Company

LAD008181927

EPA IS CURRENTLY LEAD AGENCY; Being cleaned up under an EPA order.
Remedy selection/ Construction complete scheduled for February 2012..

A

Motiva Enterprises (Port Neches)

TXD980626022

EPA LEAD; being cleaned up under enforcement order. In investigation stage.

A

NIBCO, Inc.

TXD008092306

The facility completed the requirements for a facility assessment and response
action plan conducted under a RCRA 3013 Order. They now plan to conduct
remediation through the TCEQ voluntary cleanup program. EPA will continue to
monitor progress to ensure GPRA goals are met at the site.

A

Oklahoma Pole & Lumber

OKD007335524

Underfunded site with EPA assistance. Moving toward remedy selection.

A

Rogers Delinted (Robstown)

TXD980873160

EPA LEAD. Inactive IHWCA case referred to state superfund in 1991; not
currently listed on any state or federal superfund registry; abandoned. No
cleanup funds. EPA undertook a preliminary assessment and stabilization of the
site and is presently using the EPA contractor to further investigate the extent of
the investigation.

A

The Dow Chemical Company

LAD008187080

EPA providing assistance; large complex site with complex issues.

A

U.S. Dept. Of Army-Camp Stanley

TX2210020739

CONTINUING SITE WIDE REMEDIATION, SOURCE REMOVAL OF
CONTAMINATED SOIL, BIOREACTOR AND INVOLVES OFF-SITE GW
CLEANUP.

A

Walker Wood Preserving Co.

TXD026042168

Entity has cleanup funding problems. Currently back in state enforcement. Site
has been abandoned by owner and sold for taxes. EPA is beginning to evaluate
if progress can be made by leveraging resources.

A

Westlake Vinyls (Borden)

LAD003913449

EPA LEAD: Being cleaned up under an EPA order

A

WJ SMITH WOOD PRESERVING
COMPANY

TXD066368879

EPA 6PD CASE- EPA is using contractor to do additional evaluation. City is
interested in purchasing at least part of the property for a sports complex.

B

AK Steel Corporation

TXD000802959

EPA LEAD - On track to achieve goal.

B

Albemarle Catalysts Company, LP

TXD073920399

EPA LEAD - On track to achieve goal.

B

Alpha Omega Recycling, Inc.

TXD981514383

EPA LEAD - On track to achieve goal.

B

Baylor College Of Medicine

TXD988070082

EPA LEAD - On track to achieve goal.

B

BOC Group, Inc.

TXR000052175

EPA LEAD - On track to achieve goal.

B

Chaparral Steel Midlothian, LP

TXD066362559

EPA LEAD - On track to achieve goal.

~ 18 ~


-------
CATEGORY

BASELINE FACILITIES

EPA ID

COMMENTS

B

Clean Harbors Laporte, Lp

TXD982290140

EPA LEAD - On track to achieve goal.

B

Dai-Tile Corporation

TXD988032751

EPA LEAD - On track to achieve goal.

B

Disposal Properties, LLC

TXD052649027

EPA LEAD - On track to achieve goal.

B

Duratherm, Inc.

TXD981053770

EPA LEAD - On track to achieve goal.

B

Eurecat U.S. Incorporated

TXD106829963

EPA LEAD - On track to achieve goal.

B

FMC Corporation

TXD083570051

EPA LEAD - On track to achieve goal.

B

Fort Wingate Depot

NM6213820974

BRAC - Large site; transfer to tribes in future. RFI work ongoing under NMED
closure-post-closure.

B

Gulf Coast Waste Disposal
Authority

TXD000835249

EPA LEAD - On track to achieve goal.

B

Heritage Environmental Services

TXD987995941

EPA LEAD - On track to achieve goal.

B

INEOS

was Total Petrochemicals USA

TXD086981172

EPA LEAD - On track to achieve goal.

B

Neches River Treatment Corp.

TXD074204991

EPA LEAD - On track to achieve goal.

B

P Chem, Inc.

TXD098874308

EPA LEAD - On track to achieve goal.

B

Parkans International, LLC

TXD008105959

EPA LEAD - On track to achieve goal.

B

PPG Industries, Inc.

TXD078552932

EPA LEAD - On track to achieve goal.

B

Rhodia, Inc.

TXD008099079

EPA LEAD - On track to achieve goal.

B

Rogers Delinted Cottonseed Co.

TXD981055486

EPA LEAD - On track to achieve goal.

B

Safety-Kleen Systems, Inc.

TXD000747402

EPA LEAD - On track to achieve goal.

B

Safety-Kleen Systems, Inc.

TXD000747428

EPA LEAD - On track to achieve goal.

B

Safety-Kleen Systems, Inc.

TXD980876015

EPA LEAD - On track to achieve goal.

B

Safety-Kleen Systems, Inc.

TXD981053416

EPA LEAD - On track to achieve goal.

B

Safety-Kleen Systems, Inc.

TXD981056690

EPA LEAD - On track to achieve goal.

B

Sandia National Lab

NM5890110518

Large complex site; mixed waste; public interest

B

Schenectady International, Inc.

TXD010797389

EPA LEAD - On track to achieve goal.

B

Schlumberger Technology Corp.

TXD987988318

EPA LEAD - On track to achieve goal.

B

Set Environmental, Inc.

TXD055135388

EPA LEAD - On track to achieve goal.

B

South Texas Redi-Strip

TXD980879076

EPA LEAD - On track to achieve goal.

B

Southwestern Refining Co.
AKA Kerr Mcgee

TXD000807859

EPA LEAD - On track to achieve goal.

B

Tm Deer Park Services, LLP

TXD000719518

EPA LEAD - On track to achieve goal.

B

TXI Operations LP

TXD007349327

EPA LEAD - On track to achieve goal.

/-V/ ^ Q /V/


-------
CATEGORY

BASELINE FACILITIES

EPA ID

COMMENTS

B

U.S. Dept Of Army- Lone Star
Army Ammunition Depot

TX7213821831

BRAC; CA400 and CA550 pending due to LSAAP preparing for early transfer in
late 2009. This site is still in the RFA stage and still requires the investigation of
about 300 solid waste management units. 12/31/2011 projected date of
achievement for CA400 and CA550 may be very optimistic according to PM .

B

U.S. Naval Weapons Ind. Reserve
(Dallas)

TX6170022770

CA 400 and CA550 codes have not been achieved due to ecological issues
involving NRDA trustee reviews for Cottonwood Bay. Facility also working on
purchasing all of Cottonwood Bay; involving complex real estate issues. 2 PMZS
at the facility; likely to be proposing PRBS for both. Post closure order
application and issuance is needed in order to achieve CA400 and CA550 for
final facility wide remedy implementation.

B

U.S. NNSA

DOE Los Alamos National Lab

NM0890010515

Mega site; mixed waste; public interest

B

UT Southwestern Medical

TXD071378822

EPA LEAD - On track to achieve goal.

C-D

Age Refining

TXD049754047

Site has resumed assessment activities (only) after apparently reaching
resolution on a division of liability dispute. Lawyers for both sides are currently
cooperating, but no sure what future will hold.

C-D

Amarillo Copper Refinery
(Amarillo)

TXD087491973

Updated projected dates as ASARCO is conducting additional delineation and
they also received some cleanup funds from bankruptcy proceedings..

C-D

Arkema, Inc. (Total)

TXD008085185

Arkema is still in the assessment phase for facility wide contamination issues
expect APAR by end of 08.

C-D

Baker Petrolite incl. Cook

TXD000807875

Active Baker Petrolite facility; RFI assessment current phase; need release
determination information.

C-D

Bell Helicopter (Hurst)

TXD980626006

CA400 and CA550 not achieved yet due to Bell trying to resolve eco assessment
issues before finalizing RAP submittal via permit CP mod application.

C-D

BNSF or Burlington Northern
(Sommerville)

TXD000778621

Facility is still conducting assessment activities and working on baseline risk
assessment. Public interest.

C-D

Chevron Oronite Co.

LAD034199802

Still under investigation

C-D

ConocoPhillips Refinery
(Alliance)

LAD056024391

Multiple issues

C-D

Delek Refining was LaGloria Oil

TXD007333800

CP Mod in house for PMZ they are currently in technical nod stage; CA550
achieved date estimated on CP issuance date.

C-D

Detrex Corporation

TXD980626154

Entity experiencing cleanup funding problems. Potential vapor intrusion issues.

C-D

Dow Chemical (Texas City) was
Union Carbide

TXD000461533

Offsite plume still needs to be stabilized for documentation of CA750 and CA550.
Still on track for achievement.

C-D

El DuPont de Nemours

TXD063101794

CA400 and CA550 codes have not been achieved at this facility as the site is still
in the process of assessing discovered releases.

~ 20 ~


-------
CATEGORY

BASELINE FACILITIES

EPA ID

COMMENTS

C-D

El DuPont de Nemours

TXD008079212

The CA400 and CA550 still have not been achieved due to the continued
evaluation of an interim remedy (MNA evaluation ongoing) for and additional
assessment issues associated with TCEQ review and NOD comments to an
APAR submitted by the facility. CP modification process will also be required to
establish final corrective measures for CA400 & CA550.

C-D

Equistar Chemicals, LP

TXD058275769

Equistar still has several releases that required additional groundwater
assessment to complete delineation but they are very close to completion. The
CA400 and CA550 achieved dates are pending submittal of a CP permit mod
application to address RAP implementation.

C-D

Ethyl Corp (Pasadena)

TXD008096158

Ethyl still assessing new releases at the facility.

C-D

Exxon Company (Baytown)

TXD000782698

Facility unable to achieve CA400/550 codes at this time as they are still in the
facility wide FOA assessment stage (step 2) of FOA pre-approval process.

C-D

Flint Hills was Huntsman
Petrochemical Corp (Port Arthur)

TXD000820928

Facility unable to achieve CA400/550 codes at this time as they still have 3 out 4
response action plan submittals completed (still working on the last RAP). The
last RAP will likely propose a PMZ. Progress further complicated by pending
sale to Flint Hills.

C-D

Force

TXD000633453

State Superfund project, currently an inactive IHWCA project. Human exposures
and contamination are under control. Currently completing assessment.

C-D

Fort Bliss

TX4213720101

Project includes the Castner Range Area (munitions cleanup) currently in initial
assessment phase and expected to take several years to complete.
Achievement of CA400/550 will be achieved when final response action plan is
submitted/approved for this area.

C-D

HW Burbank LLC

was Evans Harvey Corp, LLC

LAD008158289

LDEQ is finalizing an order requiring investigation.

C-D

Laughlin AFB

TX2571524105

CA750, CA400 AND CA550 not yet achieved as Laughlin is still assessing (in Rl
phase) for some sites. Also will need to finalize remedies via submittal of an
application to modify the compliance plan.

C-D

Magellan Terminal Holdings

TXD008089021

The Magellan site still has not achieved CA550 due to the construction of a
number of large above ground bulk storage tanks at the site. Due to the
locations of the new tanks, Magellan is revising the existing response action plan
for addressing soil and groundwater contamination at the site. The projected
dates are estimated when the RAP will be approved for implementation.

C-D

Motiva Enterprises (Port Arthur)

TXD008097529

CA400 and CA550 codes have not been achieved yet due to facility expansion
which has also changed final remedies for the facility.

C-D

National Oilwell

TXD057425662

Difficulty assessing site due to off-site access issues and in the area of an
existing superfund site

C-D

Occidental Chemical

TXD007325111

CA400 and CA550 has not been achieved yet due to off-site access issues and
off-site deed recordation problems. Facility is also pursuing an MSD with the
city.

~ 21 ~


-------
CATEGORY

BASELINE FACILITIES

EPA ID

COMMENTS

C-D

Safety-Kleen Systems, Inc.

TXD077603371

Encountering offsite access problems which are hampering assessment
activities.

C-D

TAFT-STAR

was Union Carbide-Taft Plant

LAD041581422

Facility currently undertaking a facility-wide investigation and remediation.

C-D

The Lubrizol

TXD041067638

CA400 and CA550 achieved are pending additional assessment. Lubrizol plans
to use phytoremediation, but assessment is not complete. TCEQ must ensure
they have investigated all the target COC's. Lubrizol has many specialty
chemicals and TCEQ is working with them to determine how to investigate and to
what cleanup levels.

C-D

The Premcor Refining (Port
Arthur)

TXD008090409

CA400 and CA550 have yet to achieve due to ongoing property disputes/legal
issues between Premcor and Chevron.

C-D

Tronox/Kerr McGee(Texarkana)

TXD057111403

CA400 and CA550 codes have not been achieved at this facility due to
ecological issues involving impacted sediments in days creek. Eco PCLs are
lower than human health PCLs and are the cleanup driver for the site. APAR
currently in-house for review with NRDA trustees to evaluate eco assessment.
Facility has an interim remedy system in place. CA400 and CA550 achievement
is also dependant on permit/CP modification application and issuance for final
corrective measures.

C-D

Wood Industries, PA (San
Antonio)

TXD027070655

Difficulty achieving CA400 and CA550 codes as waste is still onsite. Site is
involved with state enforcement program and entity is experiencing financial
difficulty paying for cleanup/possible bankruptcy issues. Some EPA assistance.

C-D

Wright Way Spraying Service

TXD981605868

County is encountering technical issues & cleanup funding problems for this
abandoned crop dusting business site at the airport.

C-D-E

Cedar Chemical Company
(W.Helena)

ARD990660649

Large offsite plume being addressed under a state order with new PRPs. EPA
assistance via a Superfund removal, deep well installation, and technical input.
Will be listed on the NPL.

C-D-E

Marshall Holdings (Monarch Tile)
(Marshall)

TXD008041048

WAS EPA LEAD. Site referred to EPA informally in April 2004. Formerly
Monarch Tile. Underfunded. Sent back to state.

C-D-E

Parker Solvents Company (Little
Rock)

ARD035565068

Large offsite plume; EPA and ADEQ investigated vapor intrusion issues and
found not to exist; underfunded site.

C-D-E

Western - was Giant Refining Co-
Bloomfield

NMD089416416

Presently being cleaned up under orders; slow to progress; release to river was
addressed. Returned to state.

C-E

AEROJET-GENERAL CORP

ARD091688283

STATE/ EPA ASSISTANCE

C-E

Air Force Base Conv-Eaker

AR8571924473

BRAC - CA550 achieved 09/13/2002.

C-E

AMAX METALS RECOVERY, INC

LAD058472721

STATE/EPA ASSISTANCE

C-E

BARKSDALE AIR FORCE BASE,
LOUISIANA

TXD000449397

STATE/EPA ASSISTANCE

C-E

Base Transition Team - Ft Chaffee

AR9210020187

BRAC - CA550 achieved 11/20/2003

~ 22 ~


-------
CATEGORY

BASELINE FACILITIES

EPA ID

COMMENTS

C-E

Bayport Processing-was Houston
Chemical Services,

TXD010791184

The RCRA permit states that EPA/TCEQ co-review of RFI related documents are
required (EPA issued order) EPA transferred to State for corrective action. Still
in investigation stage.

C-E

Big Lake Nash

TXD981150923

EPA evaluated, considered an order, returned to state.

C-E

BP-WAS IN EOS USA
LLCINNOVENE USA LLC
(O & D USA)

TXD000751172

STATE/EPA TX47

C-E

Dixie Metals Corp

LAD055792097

EPA ENFORCEMENT/STATE

C-E

England Air Force Base

LA9572124452

BRAC - Has not achieved CA400/CA550.

C-E

GALVESTON ENVIRONMENTAL
SERVICES INC

TXD980628028

STATE/EPA ASSISTANCE

C-E

General Electric Company
Apparatus Service

NMD047140256

EPA ENFORCEMENT/STATE

C-E

GTX. Inc.

LAD981057706

Large site being cleaned up under a joint order. Should progress. EPA and
DOJ were involved.

C-E

HELENA CHEMICAL COMPANY

ARD030414494

STATE/EPA ASSISTANCE

C-E

ISO-TEX INC

TXD072206311

STATE/EPA ASSISTANCE

C-E

Mixon Brothers Wood Preserving

OKD007336258

EPA assisted permit renewal drafted, awaiting issuance by State. Will include
corrective action to be accomplished.

C-E

Red River Army Depot

TX3213820738

BRAC - CA550 achieved 10/11/2009

C-E

REMINGTON ARMS CO

AR0000064311

STATE/EPA ASSISTANCE

C-E

Safety-Kleen Altair, Inc.

TXD000747410

EPA LEAD - CA550 Achieved

C-E

Safety-Kleen Systems, Inc.

TXD000747394

EPA LEAD - CA550 Achieved

C-E

Safety-Kleen Systems, Inc.

TXD000729400

EPA LEAD - CA550 Achieved

C-E

Safety-Kleen Systems, Inc.

TXD000747378

EPA LEAD - CA550 Achieved.

C-E

SHEFFIELD-GERDAU
AMERISTEEL SAND SPRINGS
WAS SHEFFIELD STEEL CORP.

OKD007219181

STATE/EPA ASSISTANCE

C-E

Sparton Technologies

NMD083212332

EPA6PD CASE-lssues resolved; Remediation systems upgraded and operating
well. GW models show remediation to extend to 2027.

C-E

Texas Instruments Incorporated

TXD982551806

EPA Oversight of VCP Cleanup

C-E

THE COLONEL FACTORY
OUTLET OF AR INC

ARD980621288

STATE/EPA ASS I ST/BAN KRPT

C-E

THE COLONELS FACTORY
OUTLET OF ARK INC

ARD035663301

STATE/EPA ASS I ST/BAN KRPT

~ 23 ~


-------
CATEGORY

BASELINE FACILITIES

EPA ID

COMMENTS

C-E

U.S. Altus Air Force Base

OK9571824045

PREVIOUS EPA LEAD; was being cleaned up under an EPA ORDER; remedy
was selected and site was progressing toward construction complete under the
order. HSWA-only state permit effective January 21, 2010, for remedy
implementation. EPA Order terminated March 23, 2010.

C-E

U.S. Dept Navy - Carswell

TX0571924042

BRAC - CA550 Achieved 7/21/2006.

C-E

U.S. Dept Of AF-DRMO

TX6570024939

BRAC - CA550 Achieved 2/10/2006.

C-E

U.S. Dept Of AF-Reese

TX8571524091

BRAC-COMPLETED TRANSFER

C-E

U.S. DOE Pantex Plant

TX4890110527

Part federal superfund: achievement of CA400 and CA550 dependent on
issuance of ROD and pending permit modification application submittal

C-E

U.S. NASA Michould Space
Systems

LAD800014587

Investigation completed, facility will do thermal desorption pilot study for the TCE
plume. State requested EPA assistance with plan and report..

C-E

US AIR FORCE PLANT #3
MCDONNELL DOUGLAS

OK9570000001

STATE/EPA DELISTING OF WASTE FOR REMOVAL.

C-E

US GOVERNMENT NAVY
FACILITY- MCGREGOR

TX9170024708

STATE/EPA ASSISTANCE

C-E

Vopak Logistics Services USA

TXD097673149

EPA LEAD - CA550 Achieved

C-E

WHITE LION HOLDINGS LLC
(VISION METALS)

TX8571524091

STATE/EPA ASSISTANCE

C-E ??

Kelly AFB (San Antonio)

TX2571724333

BRAC - CA550 has not been achieved yet as Kelly is still constructing final
remedies and need compliance plan renewal issued. Involves public
input/notice.

/-v/ 2 4 ^


-------
TABLE 4: Categorization of More Difficult or Time Consuming Baseline Facilities



DIFFICULT OR TIME
CONSUMING BASELINE
FACILITIES

EPA ID

CATEGORIES

NAICS_DESCRIPTION

A

Elementis Chromium LTP
(American Chrome &
Chemicals)

TXD098818339

ENFORCEMENT CASE

ALL OTHER BASIC INORGANIC
CHEMICAL MANUFACTURING

A

Benton Creosoting Works

LAD008056632

UNDERFUNDED

WOOD PRESERVATION

A

Chalmette Refining, LLC

LAD008179707

ENFORCEMENT CASE

PETROLEUM REFINERIES

A

Encycle Texas
(Corpus Christi)

TXD008117186

ENFORCEMENT CASE

HAZARDOUS WASTE TREATMENT AND
DISPOSAL

A

Ethyl Corp
(Baton Rouge)

LAD079460895

COMINGLED DEEP AQUIFER PLUMES

ALL OTHER BASIC INORGANIC
CHEMICAL MANUFACTURING

A

Exxon Chemical
(Houston)

TXD082684002

ENFORCEMENT CASE

ALL OTHER MISCELLANEOUS
CHEMICAL PRODUCT AND
PREPARATION MANUFACTURING

A

Formosa Plastics
(Point Comfort)

TXT490011293

ENFORCEMENT CASE

PLASTICS MATERIAL AND RESIN
MANUFACTURING

A

Greenway Environmental

OKD089761290

UNDERFUNDED/ABANDONED

HAZARDOUS WASTE TREATMENT AND
DISPOSAL

A

Hale Dusting Service, Inc.

TXD057573438

UNDERFUNDED

SOIL PREPARATION, PLANTING, AND
CULTIVATING (Crop dusting)

A

Heat Treatment Services

TXD980624035

VAPOR INTRUSION ISSUES

HAZARDOUS WASTE TREATMENT AND
DISPOSAL

A

Huffman Wood Preserving

OKD053128492

UNDERFUNDED/ABANDONED

WOOD PRESERVATION

A

International Shoe Co.
(Bryan)/Furniture Brands

TXD008071227

ENFORCEMENT CASE

GENERAL FREIGHT TRUCKING, LOCAL

A

Longview Refining (Longview)

TXD045586187

UNDERFUNDED/ABANDONED

PETROLEUM REFINERIES

A

McKinney Smelting

TXR000025387

ENFORCEMENT CASE

IRON FOUNDRIES

A

Motiva Enterprises
(Port Neches)

TXD980626022

ENFORCEMENT CASE

PETROLEUM REFINERIES

A

NIBCO, Inc.

TXD008092306

ENFORCEMENT CASE

INDUSTRIAL VALVE MANUFACTURING

A

Oklahoma Pole & Lumber

OKD007335524

UNDERFUNDED

WOOD PRESERVATION

~ 25 ~


-------


DIFFICULT OR TIME
CONSUMING BASELINE
FACILITIES

EPA ID

CATEGORIES

NAICS_DESCRIPTION

A

Rogers Delinted (Robstown)

TXD980873160

UNDERFUNDED/ABANDONED

POSTHARVEST CROP ACTIVITIES
(EXCEPT COTTON GINNING)

A

The Dow Chemical Co.

LAD008187080

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP.

ALL OTHER BASIC ORGANIC CHEMICAL
MANUFACTURING

B

Walker Wood Preserving

TXD026042168

UNDERFUNDED/ABANDONED

WOOD PRESERVATION

B

Westlake Vinyls (Borden)

LAD003913449

ENFORCEMENT CASE

PETROCHEMICAL MANUFACTURING

B

Fort Wingate Depot

NM6213820974

FEDERAL FACILITY - BRAC - COMPLEX:
WIDESPREAD CONTAMINATION AND/OR
NUMEROUS SWMUs TO CLEAN UP: TRANSFER
TO NATIVE AMERICANS IN FUTURE.

NATIONAL SECURITY

C-D

Sandia National Lab

NM5890110518

FEDERAL FACILITY -COMLEX LARGE SITE WITH
MIXED WASTE AND PUBLIC INTEREST.

NATIONAL SECURITY

C-D

U.S. NNSA/DOE Los Alamos
National Lab

NM0890010515

FEDERAL FACILITY -COMLEX LARGE SITE WITH
MIXED WASTE AND PUBLIC INTEREST.

NATIONAL SECURITY

C-D

Age Refining

TXD049754047

LIABILITY DISPUTE IN PAST.

PETROLEUM REFINERIES

C-D

Amarillo Copper Refinery
(Amarillo)

TXD087491973

PREVIOUS BANKRUPTCY ISSUES: COMPLEX
WIDESPREAD CONTAMINATION AND/OR
NUMEROUS SWMUs TO CLEAN UP:

PRIMARY SMELTING AND REFINING OF
COPPER

C-D

Arkema, Inc.
(Total)

TXD008085185

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP:
OFFSITE PLUME

ALL OTHER MISCELLANEOUS
CHEMICAL PRODUCT AND
PREPARATION MANUFACTURING

C-D

Baker Petrolite incl. Cook

TXD000807875

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP.

ALL OTHER MISCELLANEOUS
CHEMICAL PRODUCT AND
PREPARATION MANUFACTURING

C-D

Bell Helicopter (Hurst)

TXD980626006

ECOLOGICAL ASSESSMENT ISSUES

AIRCRAFT MANUFACTURING

C-D

BNSF or Burlington Northern
(Sommerville)

TXD000778621

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP.

WOOD PRESERVATION

C-D

Chevron Oronite Co.

LAD034199802

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP.

PETROLEUM REFINERIES

C-D

ConocoPhillips Refinery
(Alliance)

LAD056024391

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP.

PETROLEUM REFINERIES

C-D

Delek Refining
was LaGloria Oil

TXD007333800

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP

ALL OTHER BASIC ORGANIC CHEMICAL
MANUFACTURING

~ 26 ~


-------


DIFFICULT OR TIME
CONSUMING BASELINE
FACILITIES

EPA ID

CATEGORIES

NAICS_DESCRIPTION

C-D

Detrex Corporation

TXD980626154

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN
UP.VAPOR INTRUSION ISSUES

PETROCHEMICAL MANUFACTURING

C-D

Dow Chemical (Texas City) was
Union Carbide

TXD000461533

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP:
OFFSITE PLUME

INDUSTRIAL GAS MANUFACTURING

C-D

El DuPont de Nemours

TXD063101794

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP.
POTENTIAL VAPOR INTRUSION

ALL OTHER BASIC ORGANIC CHEMICAL
MANUFACTURING

C-D

El DuPont de Nemours

TXD008079212

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP

ALL OTHER BASIC ORGANIC CHEMICAL
MANUFACTURING

C-D

Equistar Chemicals, LP

TXD058275769

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP

ALL OTHER BASIC ORGANIC CHEMICAL
MANUFACTURING

C-D

Ethyl Corp
(Pasadena)

TXD008096158

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP

PETROLEUM REFINERIES

C-D

Exxon Company
(Baytown)

TXD000782698

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP:
FOA

ALL OTHER BASIC ORGANIC CHEMICAL
MANUFACTURING

C-D

Flint Hills was Huntsman
Petrochemical Corp
(Port Arthur)

TXD000820928

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP

PETROLEUM REFINERIES

C-D

Fort Bliss

TX4213720101

FEDERAL FACILIITY: COMPLEX: WIDESPREAD
CONTAMINATION AND/OR NUMEROUS SWMUs
TO CLEAN UP. POTENTIAL VAPOR INTRUSION

NATIONAL SECURITY

C-D

HW Burbank LLC was Evans
Harvey Corp, LLC

LAD008158289

UNDERFUNDED

PAINT AND COATING MANUFACTURING

C-D

Laughlin AFB

TX2571524105

FEDERAL FACILIITY: COMPLEX: WIDESPREAD
CONTAMINATION AND/OR NUMEROUS SWMUs
TO CLEAN UP. POTENTIAL VAPOR INTRUSION

NATIONAL SECURITY

C-D

Magellan Terminal Holdings

TXD008089021

PLANT EXPANSION UNCOVERED AND SPREAD
CONTAMINATION.

PETROLEUM BULK STATIONS AND
TERMINALS

C-D

Motiva Enterprises (Port Arthur)

TXD008097529

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP

CYCLIC CRUDE AND INTERMEDIATE
MANUFACTURING

C-D

National Oilwell

TXD057425662

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP:
OFFSITE ACCESS ISSUES

PETROLEUM REFINERIES

~ 27 ~


-------


DIFFICULT OR TIME
CONSUMING BASELINE
FACILITIES

EPA ID

CATEGORIES

NAICS_DESCRIPTION

C-D

Occidental Chemical

TXD007325111

OFFSITE DEED RECORDATION PROBLEMS

ALL OTHER BASIC INORGANIC
CHEMICAL MANUFACTURING

C-D

Safety-Kleen Systems, Inc.

TXD077603371

OFFSITE ACCESS ISSUES TO CHARACTRIZE
PLUME.

HAZARDOUS WASTE TREATMENT AND
DISPOSAL

C-D

TAFT-STAR

was Union Carbide-Taft

LAD041581422

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP

ALL OTHER BASIC ORGANIC CHEMICAL
MANUFACTURING

C-D

The Lubrizol

TXD041067638

COMPLEX: WIDESPREAD CONTAMINATION
AND/OR NUMEROUS SWMUs TO CLEAN UP

ALL OTHER BASIC ORGANIC CHEMICAL
MANUFACTURING

C-D

The Premcor Refining
(Port Arthur)

TXD008090409

ONGOING PROPERTY DISPUTES/LEGAL
ISSUES BETWEEN PREMCOR AND CHEVRON

PETROLEUM REFINERIES

C-D

Tronox/Kerr McGee (Texarkana)

TXD057111403

ECOLOGICAL ISSUES WITH CREEK SEDIMENTS

WOOD PRESERVATION

C-D-E

Wood Industries, PA
(San Antonio)

TXD027070655

UNDERFUNDED -PREVIOUS RECYCLER

GENERAL FREIGHT TRUCKING, LOCAL

C-D-E

Wright Way Spraying Service

TXD981605868

UNDERFUNDED-PESTICIDES

SOIL PREPARATION, PLANTING, AND
CULTIVATING (Crop dusting)

C-D-E

Cedar Chemical Company
(W.Helena)

ARD990660649

COMPLEX SITE: IN PROCESS OF BEING LISTED
ON NPL

OTHER BASIC ORGANIC CHEMICAL
MANUFACTURING

C-D-E

Marshall Holdings (Monarch
Tile) (Marshall)

TXD008041048

UNDERFUNDED

CERAMIC WALL AND FLOOR TILE
MANUFACTURING

C-D-E

Parker Solvents Company
(Little Rock)

ARD035565068

RECALCITRANT

OTHER CHEMICAL AND ALLIED
PRODUCTS MERCHANT WHOLESALERS

C-D-E

Western - was Giant Refining
Co-Bloomfield

NMD089416416

COMPLEX SITE

PETROLEUM REFINERIES

~ 28 ~


-------
ADDENDUM 1

Huffman Wood Preserving and Oklahoma Pole and Lumber Facilities, Broken Bow, Oklahoma

EPA Region 6 RCRA project team took two corrective action sites that were stalled in being cleaned up and used innovation in
finding funds, technology and resources to get the sites cleaned up and back in productive use in the community. Both facilities had
lingered in the corrective action pipeline for over ten years with little or no activity. EPA, ODEQ and the other stakeholders are
working together to creatively leverage resources to complete site investigation and cleanup activities at these facilities and put them
back into productive use.

Huffman Wood Preserving, Inc. (HWP) and Oklahoma Pole and Lumber Company (OPLC) are two wood treating facilities located in
Broken Bow, Oklahoma, and approximately half a mile apart. Both facilities are on the GPRA RCRA 2020 baseline and
bankrupt/underfunded. HWP is a 25-acre facility that treated fence posts and other wood products with creosote and
pentachlorophenol. The facility operated from 1956 until 1984. In 1989, the now-deceased owner closed 5 unlined surface
impoundments under state authority, and set aside approximately $120,000 in financial assurance for future site work. The owner
passed away in 1991 and the facility was purchased by an adjacent property owner to house his small welding shop. Several acres
of the site were use by Oklahoma Pole and Lumber as a laydown yard for untreated poles but this practice will be discontinued. The
facility sits atop a recharge zone for the Antlers Aquifer.

OPLC is a 26-acre site that was initially owned by Thomason Lumber and Timber Company, Inc. The facility operated from the late-
60's to late-90's. Thomason abandoned the site in 1999, leaving behind two closed surface impoundments, 15 wells, and possible
soil contamination. The site was purchased by OPLC, who took over the deed and liability for the property in June of 2000. In June
2002, OPLC abandoned the facility. The facility remained abandoned through 2004. OPLC resumed treatment operations at the
facility in early 2005. Currently, OPLC is operating the facility, but has limited cash flow/resources to conduct site investigation and
any cleanup.

Region 6 project team members were innovative in collaborating with numerous stakeholders to achieve investigation and cleanup at
these financially troubled sites. The culmination of the corrective action process has been the result of partnerships between EPA
Region 6 (Dallas), EPA ORD's lab in Ada, Oklahoma, EPA OSWER's Technology Innovation Office, Region 6's Houston Lab,

~ 29 ~


-------
Oklahoma DEQ, the Army Corps of Engineers, the City of Broken Bow, and the facility owners. All investigation and cleanup
activities are expected to be completed within the next year.

The specific external resources leveraged over the course of the project included the following:

•	Technology Innovation Office provided funding and TRIAD technical assistance to Region 6 and ADA Lab to develop a
site assessment plan.

•	City of Broken Bow provided resources to clear brush in order for sampling to take place. In addition, the City provided
heavy equipment/operators for trenching as part of sampling activities and disposed of purge water via the City's POTW.
The City also provided a water truck for decontamination and other sampling work, and a vacuum tanker truck for purge
and decon water.

•	Region 6 staff and its contractors conducted soil and groundwater sampling at OPLC and HWP.

•	The Houston Lab provided analysis for the soil and groundwater samples collected at HWP.

•	USACE (via an IAG with Region 6) installed groundwater monitoring wells at HWP to characterize the deeper regional
groundwater aquifer.

•	OPLC's contractors conducted groundwater sampling and analysis of HWP's monitoring wells.

•	OPLC provided equipment and manpower to conduct soil removal at both OPLC and HWP. HWP's financial assurance
funds will be used to pay for soil disposal for that site; OPLC will fund disposal of its contaminated soils.

•	The balance of the HWP's financial assurance will be used for long-term monitoring and maintenance at that site

•	Ada Lab personnel provided training to Region 6 and ODEQ Project Managers, and took a lead role in gathering samples
to conduct calibration testing for immunoassay field test kits that will be used during the cleanups at OPLC and HWP.
The Houston Lab provided final calibration standards. Ada Lab also assisted Region 6 in developing a gridded sampling
plan following the TRIAD approach for soil and groundwater sampling. This approach will reduce project costs due to real
time field sampling and use of EPA staff/labs, while increasing technical competency and expediting corrective action.

•	Region 6 and Ada Lab characterized and performed confirmatory sampling of soils using immunoassay field test methods,
along with laboratory confirmation sampling.

•	Region 6 installed four additional groundwater monitoring wells at OPLC.

•	Region 6 and ODEQ will jointly issue Ready for Reuse Determinations to the facilities at the completion of their respective
cleanups in order to promote productive, protective and sustainable reuse of the properties.

•	It should be noted that the revitalization tool was really effective in initiating correction actions at these sites as City of
Broken Bow was interested in using one of these properties for parking city equipment.

~ 30 ~


-------
ADDENDUM 2

Micro Chemical Company, Winnsboro, Louisiana

This GPRA facility has been at a stalemate regarding site investigation and remediation efforts for approximately 10 years due to
limited funding for site work and the inflexibility of the regulatory project manager on how to appropriately deal with this under-funded
facility. Regulatory inflexibility, lead to limited cooperation between the parties and little progress was made after the initial Interim
Measures were completed. During the past year, the regulatory project manager changed and the facility is now participating in the
Region 6 Corrective Action Strategy (CAS) process which focuses on risk-based / performance-based corrective action objectives for
the site. The facility ceased operations in 2008 due to a downturn in the economy and loss of contracts. Investigation and cleanup
activities at the facility were completed in 2009. In September 2010, LDEQ and EPA issued a Ready for Reuse determination for a
portion of the site, which will likely be sold to the adjacent grain elevator operations in 2011. EPA is currently working with the
property owner and consultant on completing the documentation of CA550 construction complete with the expectation of completing
this work by Sept. 2011. At that time, EPA will close out its Order and post closure care will be conducted under a new LDEQ post
closure order.

The Micro Chemical Facility is located in Winnsboro, Louisiana 45 minutes south of Monroe on Hwy 15. It is located on 4.75 acres
and has been formulating, blending and packaging agri-chemicals (pesticides and herbicides) for local use since 1954. The facility
closed in 2008 due to a shrinking competitive market. The owner of the facility has since retired (approximately 80 years of age) but
is willing to use remaining limited resources to complete site investigation and cleanup activities. After the cleanup of the property is
complete, EPA and the State will provide a Region 6 Ready for Reuse comfort letter to aid in the sale of the property to the adjacent
feed mill operation. The proceeds from the sale will be used as financial assurance for long term monitoring and post closure case.

In 1994 Micro Chemical Company entered into an Administrative Order on Consent with EPA to identify, investigate and prevent the
further release and/or migration of hazardous constituents to the environment and to perform corrective actions necessary to protect
human health and the environment.

In 1996 interim measures were performed which consisted of:

•	14,000 cu/yards of contaminated soils being consolidated, stabilized and capped onsite

•	13 nested pairs of groundwater wells were installed and semi-annual groundwater monitoring was initiated

~ 31 ~


-------
•	Sediments in a near-by abandoned oxbow were sampled and tested

In 1997 a draft RFI work plan was submitted but the final was never approved
In 1999 a draft RFI report was submitted but was never approved
No additional site investigation or cleanup activities took place until 2008

In 2008 the Facility, under new regulatory project management initiated corrective action streamlining activities using the Region 6
Corrective Action Strategy

Since that time the following has been accomplished:

•	conducted 4 separate rounds of groundwater delineation step-out sampling the define the extent of the plume

•	conducted soil sampling in the MSMA process and tank storage area

•	conducted soil sampling along the abandoned Toxaphene delivery line and tank storage area

•	conducted additional sediment sampling in the Turkey Creek oxbow

•	Excavated, stabilized and consolidated an additional 1,500 cu/yards of contaminated soils (all surface soils were excavated to
a minimum of 2 feet and replaced with clean top soil)

•	Installed 4 new wells to groundwater monitoring well network

•	Financial assurance will be provided by the facility via the sale of the property for long term monitoring and maintenance.

•	Currently working on CA550 documentation, where Interim Measures will serve as the final remedy at the facility.

~ 32 ~


-------
ADDENDUM 3

Rogers Delinted Cottonseed Co, Site, Robstown, TX

This former cottonseed delinting facility in South Texas was recently purchased by the Robstown Industrial Development Corporation
(RIDC) from Nueces County. The County had originally obtained the property on back taxes from the deceased property owner,
Koshiro Yazaki (Yazaki USA Corporation). The RIDC would like to complete whatever cleanup is required at the facility and promote
the property for use that would complement the new Nueces County Fairground and Convention Center that is located across the
highway from the RDCC facility. A new retail outlet mall is also proposed for development this year next to the fairgrounds. During
the summer of 2011, EPA Region 6 Superfund performed some removal actions at the facility which included cleaning out a
collapsed aboveground storage tank, cleaning up/removing the pesticide application room, removing containers of pesticides left at
the facility, sweeping and pressure washing the facility buildings to remove pesticide residues, and performing lead-based paint and
asbestos inspections in the facility buildings. EPA Region 6 RCRA has used REPA contract funds to install groundwater monitoring
wells at the facility, perform groundwater monitoring, and perform soil sampling. EPA Region 6 RCRA will work with the TCEQ to
determine what further corrective actions are required at the facility based on its potential future reuse. The facility has achieved the
CA725 human exposure under control goal. The EPA will determine the status of meeting CA750, CA400, and CA550 milestones
after discussions and resolutions with the TCEQ.

The former Rogers Delinted Cottonseed Co. facility is located just northeast of Robstown, TX, in Nueces County, on the east side of
U.S. Hwy 77 (Business). It produced cottonseed for sale by using a wet acid cottonseed delinting process, in which highly
concentrated sulfuric acid was used on cottonseeds to remove cotton fibers from the seed. The spent sulfuric acid and rinsewaters
were discharged from a sump into a series of evaporation ponds. The seed was then dried and treated with fungicides and
insecticides. The plant operated from about 1962 to 1983 and has been abandoned since 1984.

The facility is on EPA's GPRA baseline list for corrective action, and as such must meet El determinations and corrective action
completion.

August 2003 groundwater sampling by TCEQ found arsenic, benzene and organochlorine pesticides above MCLs. EPA conducted a
site reconnaissance trip on August 4, 2004, and found that part of the site was actively being used for playing paintball games, as
noted by paintball equipment left on site, paintball debris, and paintball splatters on wooden pallets in the warehouse building.

In March 2005, EPA returned to the site to conduct sampling and to post signs to warn trespassers that the site was under
investigation. Sampling results indicated that the fungicide and pesticides wastes left on site in the process building had elevated

~ 33 ~


-------
levels of lead, chromium and thiram. This waste was bagged. Floor sweep samples from the warehouse building indicated elevated
levels of arsenic, lead and chromium. Surface soil samples indicated elevated levels of lead.

EPA returned to the site in July 2005 and conducted the following measures:

•	the bagged waste in the process building was drummed and removed from the site,

•	the warehouse building was swept and wastes were drummed and removed,

•	surface soils outside the warehouse that had elevated levels of lead were covered with a clay-gravel mixture to prevent
exposure to surface soils,

•	All openings to the process building were fenced off and marked with KEEP OUT signs.

The property owner passed away in 1997 with a significant accumulated property tax levy. The City of Robstown has an interest in
securing the property through tax resale. Therefore, the EPA has been collaborating with the City of Robstown to move the site
forward. The fencing and most of the warning signs that EPA installed in 2005 have been removed by trespassers. The City of
Robstown initiated a trash cleanup day at the site to remove the tires and wood pallets that trespassers had been using to build
paintball courses. The City of Robstown also cleared brush so that EPA could access the site for an investigation. In June 2010,
EPA contractors installed groundwater monitoring wells at the site and groundwater was sampled. Soil borings were installed within
the unclosed ponds and subsurface soil samples were collected. Surface soil samples were also collected throughout the site.

EPA Region 6 RCRA Multimedia Planning and Permitting Division (PD) requested assistance from Region 6 Superfund Division to
perform some waste removal work at the site. During 2011, EPA Superfund is planning to remove a 13,000 gallon collapsed sulfuric
acid tank and surrounding acidic soils and a 55 gallon drum of unknown liquid at the site. Superfund is also planning to sample and
potentially cleanup the pesticide application room. Through a REPA IV contract, PD is planning to perform another round of
groundwater monitoring, a water well survey, and an aquifer test at the site during 2011.

EPA intends to work with the local government and City officials to achieve CA750, CA400 and CA550; and encourage the beneficial
reuse of the property by recycling onsite materials including metal equipment and building components.

^ 2 4 ^


-------
ADDENDUM 4

The Region 6 RCRA Hazardous Waste Program Environmental Justice Strategy

Introduction

The Agency has made "Expanding the Conversation on Environmentaiism and Working for Environmental Justice" a priority. To
implement this priority, EPA launched Plan EJ 2014 as the Agency's strategy for integrating environmental justice (EJ) in its
programs, policies and activities. This four-year plan will help EPA move forward to develop a stronger relationship with communities
and increase the Agency's effort to improve the environmental conditions and public health in overburdened communities. The plan
seeks to protect the environment and health in overburdened communities; empower communities to take action to improve their
health and environment and establish partnerships with local, state, tribal and federal governments and organizations to achieve
healthy and sustainable communities.

The Region 6 EJ office has identified five areas of concern for EJ consideration. A map showing the locations is shown in Appendix
A. These areas will be used as initial assessment areas by the RCRA program to focus our efforts.

The Region 6 RCRA Hazardous Waste Program evaluated three EJ assessment tools. These were available for use to prioritize
sensitive areas for consideration. See Appendix B for a comparison table of the three tools. EPA Region 6 uses the Potential EJ
Index (PEJI) ranking tool which has high resolution because it is based on the Census block level, but there are a low number of
social demographic indicators used in the ranking. (Social demographic indicators include: percent minority, per capita income,
population density and others.) The Social Vulnerability Index (SVI) ranking tool utilized by Region 9 makes assessments at the
Census block group level, which is a lower resolution than the PEJI, but considers a higher number of social demographic indicators,
including: percent minority, per capita income, percent population over 18, percent population over 64, percent population without
high school diploma, and percent households with limited English proficiency. OECA's Environmental Justice Strategic Enforcement
Assessment Tool (EJSEAT) assesses at a Census tract level, the highest resolution of the three indices. EJSEAT evaluates the
same social demographic indicators as the SVI, but also includes various environmental, human health, and compliance indicators.
In order to eliminate the diverse assessment of tools, the EPA Headquarters is working to create a national EJ ranking tool,
anticipated to be released in 2014. For the purposes of this strategy, the RCRA Hazardous Waste oversight program will evaluate
factors from the various rankings until the national tool is available, and will designate identified areas as areas of concern.

The Region 6 RCRA Hazardous Waste Program strategy describes the goals and methods for incorporating EJ into the day to day
operations of our program. This strategy defines three focus areas for the RCRA Hazardous Waste State Program oversight process:

1. Program oversight review of state-issued permits and GPRA corrective action reviews

~ 35 ~


-------
2.	Program oversight review of state public participation activities associated with permit renewals and RCRA corrective action,
and

3.	In other program areas, we will consider areas of concern in our decision-making process for EPA assistance to the states.
This would involve RCRA underfunded/near bankrupt sites and the various state voluntary cleanup programs.

Focus Area 1: Oversight Review of Permits and GPRA Corrective Action

There are several areas in our oversight of state- implemented RCRA hazardous waste programs where we can more effectively
protect human health and the environment for disproportionately burdened populations by incorporating EJ considerations into our
reviews.

•	Complete an initial review of the five areas of concern identified by the Region 6 EJ office. Using GIS layer treatment storage
and disposal (TSD) and permit data along with GPRA 2020 data for corrective action sites within a 5 mile radius of the areas
of concern.

•	Expand the list of facilities by incorporating information on voluntary cleanup program (VCP) sites. For Texas this will include
facilities located in municipal settings designated (MSD) areas.

•	Prioritize the facilities within an area of concern by narrowing the focus to facilities with an identified off-site release. In
addition to the above we will prioritize our reviews and oversight based upon the ORCR Corrective Action EJ Analysis. This
analysis places GPRA 2020 corrective action sites into one of three categories.

•	Expand the number of areas of concern by using other screening tools to look at areas that may be disproportionately
burdened by RCRA facilities. There are numerous pockets of that have large numbers of 2020 Corrective Action sites. See
Appendix C.

•	To further prioritize the identified areas of concern, the concentration of RCRA facilities within an area will be used for
screening.

•	Prioritize our annual permit and corrective action reviews for each state by ensuring that facilities located in the areas of
concern are given priority.

•	Prioritize GPRA corrective action status updates (via monthly conference calls) based on areas of concern or sensitive areas.

•	Based on facility-specific information on corrective action progress and agreement with state partners, referrals to the
Hazardous Waste Enforcement Branch of the Region 6 Compliance Assurance and Enforcement Division may be
appropriate.

~ 36 ~


-------
Focus Area 2: Oversight Review of State Public Participation

In February 1996, EPA finalized the RCRA Expanded Public Participation Rule (EPA530-F-95-030) to empower communities to
become involved earlier and more often in the process of permitting hazardous waste management facilities. The Rule supports 1)
involving the public earlier in the permitting process, 2) providing more opportunities for public involvement, 3) expands access to
public information, and 4) provides guidance on how facilities can improve public participation.

•	During our RCRA Permit Program and Corrective Action Program reviews for a state, EJ considerations will be incorporated
into the review. This includes documenting how each state supports the RCRA Expanded Public Participation Rule into their
permitting and corrective action processes. For example see Appendix D, Summary of Region 6 States RCRA Public
Participation.

Focus Area 3: EPA Assistance to the States

Facilities that are identified within areas of concern through the use of the various EJ prioritization tools will be prioritized for EPA
assistance which may include:

•	Use of contract dollars for additional sampling at facilities located in areas of concern.

•	Coordination with each of our states to ensure that appropriate actions are taken for all sites and that disproportionately
burdened populations are included to the extent practicable in the decision making process.

•	Referrals to enforcement or requests for additional support will be prioritized based impact to the areas of concern.

•	Special consideration for sites in the VCP with potential Indoor Air Exposures.

Pali Forward

The RCRA Hazardous Waste Program will concentrate on the five areas of concern to perform an initial screen of RCRA sites and
2020 GPRA corrective action sites. The Grants Mining District in New Mexico does not have any RCRA sites or 2020 GPRA
corrective action sites within the 5 mile radius we are using for the screen. The initial mapping effort for Manchester and Port Arthur,
Texas along with Mossville, Louisiana will be completed by the end of September 2011. The Corpus Christi, Texas area is dependent
upon receiving parcel boundary data, but should be completed by December 2011.

In addition to mapping the 2020 GPRA corrective action sites located within the areas of concern, we will prioritize them to prepare
for discussions with the states. This should be completed by December 2011. See Appendix E for a list.

~ 37 ~


-------
We will use the screening information to prioritize our permit and corrective action reviews for FY 2012.

We currently host monthly calls with Louisiana to discuss issues with corrective action sites. If the need arises we will implement a
similar strategy in other states.

The Region 6 RCRA program will incorporate an Environmental Justice element into the RCRA state grant program for each of the
five states. This would occur during the negotiations for the 2013 fiscal grant year for each state and would require the consideration
of EJ facility rankings as a factor in the setting of priorities for review of state lead corrective action activities.

Once the initial review of potential oversight areas is complete we will continue to screen additional facilities in these areas of
concern, such as voluntary cleanups to ensure that our oversight program is adequate. This task would start in FY 2013. Additional
areas of concern could be identified based upon screening criteria the Region decides to implement in the interim until an Agency
wide screening tool is developed hopefully in FY 2014.

~ 38 ~


-------
APPENDIX A

~ 39 ~


-------
APPENDIX B

Oklahoma.:
City"'

OKLAHOMA

TEXAS

Mossville, LA

Beau moil! -4r

San

Antonto-

Manchester, TX

Port Arthur, TX

Laredo

Corpus
'Christi

Region 6 Environmental Justice
Areas of Concern

Location of 5 Areas of Concern

Abilene

Shrevepori «

¦*»

Corpus Christi, TX

P

~	Albuquerque \

e	--- - i _

Grants Mining District, NM

9 NEW

\ MEXICO

)

-0_

kittle
Rock

ARKANSAS^

^ ^ Q ZN/


-------
OECA - Environmental Justice Strategic Region 9 - Social Vulnerability Index Region 6 - Potential Environmental Justice Index
Enforcement Assessment Tool (EJSEAT) (SVI) (PEJI)

~	Assessed at Census Tract Level (multiple tracts
make up a county)

~	Designed for enforcement/compliance programs to
rank census tracts and regulated facilities

~	Project started in 2005 - draft tool still in
development

~	Score: 1 (Highest Potential EJ Concern) - 10
(Lowest Potential EJ Concern)

Tool pulls data for 4 indicator categories from 18 select

federally-recognized or managed databases:

~	Assessed at Census Block Group Level
(multiple block groups make up a tract)

~	Designed for ranking both census block
groups and Corrective Action sites

~	Developed by Region 9's Environmental
Justice Program

~	Score: 0 (Least Socially Vulnerable) -18
(Most Socially Vulnerable)

Tool pulls data for 1 indicator category from 6

select federally-recognized or managed databases:

~	Assessed at Census Block Level (multiple blocks make uo a
block group)

~	Designed for all Region 6 programs to identify potential EJ
areas of concern

~	Methodology derived in the mid-1990s (from Human Health
Risk Index)

~	Score: 0 (Low EJ Sensitivity) - 100 (High EJ Sensitivity)

Tool pulls data for 1 indicator category from 3 select federally-
recognized or managed databases:

> Social Demoaraohic Indicators

(2000 Census Data)
o Percent minority
o Percent in poverty
o Percent population under 5
o Percent population over 64
o Percent population without high school diploma
o Percent households with limited English
proficiency

> Social Demoaraohic Indicators

(2000 Census Data)
o Percent minority
o Per capita income
o Percent population under 18
o Percent population over 64
o Percent population without high school
diploma

o Percent households with limited English
proficiency

> Social Demoaraohic Indicators

(2000 Census Data)
o Percent minority

o Percent in poverty/economically stressed (percent of
households with income under $20,000 - adjusted to
present day)
o Population density (pop. per sq mi)

> Environmental Indicators

o NA TA cancer and non-cancer risk from air
emissions

o Toxic chemical emissions and transfers from

industrial facilities-TRI
o Population weighted ozone and PM 2.5
monitoring data





> Human Health Indicators

o Percent infant mortality
o Percent low birth weight





> Compliance Indicators

o Inspections, violations, and formal actions at

major facilities
o Facility density (no. of permitted facilities per q
mi)





/-V	^ /V/


-------
OECA- Environmental Justice Strategic
Enforcement Assessment Tool (EJSEAT)

How community vulnerability is scored:

•	Each indicator is scaled from 0-100 within each
state by Census tract

•	The scaled indicator values are averaged within
each category (e.g., demographic, health)

•	The four category values are averaged into an
overall value

•	This value is again rescaled from 0-100 within
each state, and the final summary value is
represented as a decile (1 -10) for the Census tract

How facility ranking is scored:

•	Facilities are ranked based on their proximity
(currently, considered within 2/3 mile) to Census
tracts with high EJSEAT scores

Advantages:

•	Considers multiple indicators and datasets

•	Calculates a score not just for a demographic
area, but also for a regulated facility

Disadvantages:

•	Static: limited ability to customize output

•	Census tract scale is not detailed enough to pick
up all EJ communities

•	Environmental indicators are focused on outdoor
air risk and toxics; do not take into account indoor
air quality, drinking water, groundwater, pesticide,
and other concerns

Not all indicators have data available at the Census
tract level (e.g., health indicators are at the County
level)

Region 9 - Social Vulnerability Index (SVI)

How community vulnerability is scored:

Each dataset for each block group is assigned an index score of
0-3, based on whether the value in that dataset falls in the top
quartile (score=3), second quartile (score=2), third quartile
(score=1), or bottom quartile (score=0)

•	Top quartile represents most vulnerable (i.e., block group
with the highest percent minority)

•	The datasets are then all added together to assign a
comprehensive score to each block group (0-18)

How site ranking is scored:

•	A one-mile radius is drawn around each site

•	If a site's radius falls within one block group, then the SVI
score for that block group is assigned

•	If a site's radius covers multiple block groups, then the
percentage of each block group that falls within the radius is
calculated, and then multiplied by the total population within
each block group

•	Each value is then multiplied by that block group's SVI
score, and then summed

•	This value is then divided by the total population that falls
within the one-mile radius to come up with a weighted SVI
score for the site

Advantages:

•	Flexible: easy to customize output

•	Block group scale can pick up more EJ communities than
Census tract

•	Calculates a score not just for a demographic area (i.e.,
block group), but also for a site location

Disadvantages:

Doesn't consider multiple indicators (e.g., environmental, human

health)

Region 6 - Potential Environmental
Justice Index (PEJI)

How community vulnerability is scored:

•	Population density (population per 1 square mile)
is scaled 0-4 (0 = 0, 4 = >5,000)

•	Economically stressed and percent minority are
scaled 1-5 (based on comparison to State Avg.)

•	Population density and percent minority are
calculated at the block level; economically
stressed calculated at the block group level, and
then applied to the block level

•	The 3 factors are multiplied together to assign a
comprehensive EJ score to each block (0-100)

How site ranking is scored:

•	N/A - there is no site ranking component to this
methodology

Advantages:

•	Flexible: easy to customize output

•	Block scale can pick up more EJ communities
than Census tract or block group

Disadvantages:

• Doesn't consider multiple indicators (e.g.,

environmental, human health)

Current methodology doesn't take into account
calculating a score for a regulated facility or Corrective
Action site




-------



-------
APPENDIX C

Oklahoma
. City_ r

ARKANSAS

Shrevepcrt t

Austin £

Beaumont

;New \
Orleans

Housloril,

San Antonio

Laredo

[Corpus
Chrissi

Region 6 RCRA Corrective Action
Baseline

® Location of CA2020 site

Albuquerque,^.. .	F

( NEW
iMEXICO

9

AR = 31
LA = 64
NM = 23
OK = 36
TX = 258
Total = 412

y

Amanita

Lubbock
to

'OKLAHOMA

• Abilene

• TEXAS

vvonn

f'—	*-j!

^	Dallas

ie	• s

/v/


-------



-------



-------
APPENDIX D

Summary of Region 6 States RCRA Public Participation

All of the states in Region 6 are authorized to implement the RCRA permitting corrective action programs. As such EPA does not
issue RCRA permits in Region 6. We rely on the state programs to follow at minimum EPA guidelines for public participation. As our
role of oversight has expanded we continue to look all parts of the RCRA permitting and corrective action programs, including public
participation.

In general the states follow the RCRA public participation requirements with some enhancements that are unique for each state.
Several of the states provide the public access to draft permits on-line. States also have documents related to corrective action
activities on-line. This allows the public easy access to documents for review and in some cases to leave comments. Included is a
brief description of each states program and how environmental justice factors into decisions.

Arkansas

The Arkansas Department of Environmental Quality (ADEQ) follows the basic required steps for public notices/participation during
the permitting process for all Class 1/2/3 Permit Modifications as well as Permits (both initial and renewals). This involves both
administrative completeness as well as technical completeness. For Commercial facilities, they always hold a public meeting/hearing
for all Class 3 modifications/renewals. For Non-Commercial facilities a public notice of the decisions is made and they await final
decisions after the close of the public comment period, etc. Public meetings/hearings are not required to be held for Non-Commercial
facilities, but there have been an occasion in which ADEQ has felt it was prudent based upon public concerns, etc. In all public
notices, ADEQ offers the public the opportunity to request a public hearing (if not originally required or scheduled).

All comments (both verbal and written) are addressed in a Responsiveness Summary and are sent to all parties that are on the
mailing list for the respective facility or to those that provided comments. This Responsiveness Summary becomes part of the final
approval/notice of issuance. All final decisions are discussed in Responsiveness Summary and Fact Sheet on each respective
decision.

The current State Administrative Regulation (APC&EC Reg. No. 8) allows for any party to request a hearing/meeting if one is not
initially offered. Based upon discussions with program managers they could not recall a time in which someone requested a
meeting/hearing that the Director did not grant such request.




-------
The point where the local community has input into the process is from the point the facility submits a request to ADEQ for a Permit
Modification or a Renewal (or initial issuance) since (1) the facilities are required regulatory to do a public notice when applications
are submitted to ADEQ for consideration and (2) ADEQ issues notices of intent to either deny or grant. This later notice has a 30 to
45 day public comment period built into the process. Administrative Repositories are established for all Permitting decisions and the
locations of these are placed in the initial public notice Fact Sheets.

There is also a public participation process in RCRA corrective action. A RCRA final remedy for a site is described in a Remedial
Action Decision document (RADD), which has a 45-day (or 30-day) public comment period. Once public comments are collected,
the authorized agency writes a Response to Comments/Final Decision document.

Louisiana

The Louisiana Department of Environmental Quality (LDEQ) follows the required steps for public notices/participation during the
permitting process. LDEQ also has a Public Participation Group that is part of the Permit Support Services Division. They are
responsible for issuing public notices and conducting public hearing and meetings associated with permitting activities.

One additional enhancement is noted in the requirements to hold an evidentiary hearing in LAC 33:V.709, Evidentiary Hearings on
Operating Permit Applications for Commercial Hazardous Waste Treatment, Storage, Disposal, or Recycling Facilities. This applies
to a company applying for a RCRA permit as a commercial TSD. The department must hold an evidentiary hearing after the technical
review of the permit. There is a public notice and hearing at which extra information regarding the application can be submitted by
the public to the LDEQ. LDEQ can't issue the draft permit until it has received and reviewed the record of the evidentiary hearing.

The state maintains an on-line method for the public to access permits (both draft and final), correspondence, public notices and
applications.

There is also a public participation process in RCRA corrective action. A RCRA final remedy for a site is described in a Basis of
Decision document which has a 45-day (or 30-day) public comment period. Once public comments are collected, the authorized
agency writes a Response to Comments/Final Decision document.

Oklahoma

The Oklahoma Department of Environmental Quality (ODEQ) follows the required steps for public notices/participation during the
permitting process. ODEQ has a Customer Assistance Program which provides a point of access for agency information. Among
other things they provide risk communication and citizen assistance. This allows citizens and public interest groups to obtain copies
of permits and other documents.




-------
Another enhancement over and above the basic public participation requirement is how they post all draft permits on the ODEQ web
site. The permits can be viewed and comments can be provided on-line by interested parties. ODEQ plans to have all active permits
available on line for viewing.

There is also a public participation process in RCRA corrective action. A RCRA final remedy for a site is described in a Statement of
Basis which has a 45-day (or 30-day) public comment period. Once public comments are collected, the authorized agency writes a
Response to Comments/Final Decision document.

Mem Mexico

The New Mexico Environment Department (NMED) follows the required steps for public notices/public participation during the
permitting process. The New Mexico Hazardous Waste Management Regulations, 20.4.1 NMAC provides for a robust public
participation process. Through involvement of the public in the permitting process the hazardous waste permits in New Mexico are
improved.

Through negotiations with the applicants and the public, comments received during the comment period the final permits are greatly
enhanced to provide the public with more awareness, such as e-mail notifications of various activities that occur at the facility through
the term of the permit. NMED will also extend the public comment period on some of the more complex permits.

The New Mexico Hazardous Waste Management Regulations, at 20.4.1.901.A(4) NMAC, states: "If the Secretary issues a Draft
Permit, and a timely written notice of opposition to the Draft Permit and a request for a public hearing is received, the Department,
acting in conjunction with the applicant, will respond to the request in an attempt to resolve the issues giving rise to the opposition. If
such issues are resolved to the satisfaction of the opponent, the opponent may withdraw the request for a public hearing." NMED has
interpreted this rule to allow face-to-face discussions with commenter's and the applicant. NMED has successfully conducted such
meetings, which have led to withdrawal of hearing requests. While avoiding a hearing can save months of time and considerable
resources preparing for an administrative hearing, conducting multiple meetings can also add to the delay in issuing permits.

Commenter's that did not request a hearing are not invited to the meetings with NMED and the applicant. The intent is to resolve as
many issues as possible during these meetings. The meetings provide a beneficial interaction and understanding of each party
position and in many instances, through detailed discussion of the specific issue, ends in a mutual resolution or compromise.
Concerns being discussed may include environmental justice issues. The resolution or compromise must be consistent with and not
conflict with the regulations and statute.

At the end of these meetings there are several procedures that may occur. If the withdrawal of hearing requests is made then NMED
could issue a final permit. If hearing requests are not withdrawn NMED could then reissue the draft permit for public comment if




-------
significant changes have been made. NMED could schedule a public hearing which would be limited to those issues that were not
resolved during the meetings. Other iterations could be considered in the process.

NMED has employed all of these strategies at various times, depending on the circumstances peculiar to each permitting action.

In addition LANL and WIPP have e-mail notification when certain actions occur. These are required in their respective hazardous
waste permits. Also, WIPP held pre-submittal meetings when they applied for their permit renewal and they also hold them for Class
2 and Class 3 permit modification proposals. LANL has held pre-submittal meetings on permit modifications, and recently, a new unit
they are proposing to add to the current permit. NMED has and continues to encourage the facilities to hold pre-submittal meetings
on major modifications and renewal applications. New Mexico public notices permit applications as required by 40 CFR 124.32.

Many of our federal facilities also have established physical information repositories. LANL has recently employed an electronic
repository in addition to a physical repository as was negotiated during the permit process and required under the current permit.
WIPP also has an electronic repository and a physical repository. In addition, many of our facilities are required to put in place a
community relations plan (CRP) that engages the public, and in some instance tribes, on how to inform the communities and
interested public of permit and corrective action related activities. The CRPs are required to be updated annually with input from
communities, tribes and interested persons.

NMED has established a Border Liaison and a Tribal Liaison to work on EJ concerns and issues. The liaisons were established in
response to a public participation process to ascertain the extent and nature of unique and differing EJ issues and concerns in
NMED's five state-wide districts. The goal of the liaisons is to be the main point of contact for border or tribal EJ issues focusing on
reducing air pollution, providing safe drinking water, reducing the risk of exposure to hazardous waste, training and outreach.

Other enhancements that allow easy access to documents include the NMED website which has all of the current RCRA permits on-
line for viewing or download. The site also includes public notices.

There is also a public participation process in RCRA corrective action. A RCRA final remedy for a site is described in a Statement of
Basis which has a 45-day (or 30-day) public comment period. Once public comments are collected, the authorized agency writes a
Response to Comments/Final Decision document

Texas

The Texas Commission on Environmental Quality (TCEQ) follows the required steps for public notices/public participation during the
permitting process. Enhancements include publishing notices in an alternate language. After a preliminary decision is reached (Final
Draft Permit is sent the Office of Chief Clerk (OCC)): a) OCC sends notice of preliminary decision to all persons listed in 30 TAC

~ 50 ~


-------
39.413; b) Applicant publishes notice in English in local newspaper (in some areas also in an alternate language...i.e. Spanish); c) for
new, renewal, and major amendments (not Class 3 modifications) the company will also do a radio broadcast.

Comments and hearing requests will be accepted and considered from the first notice through the final comment period. Also, for
major permitting actions and new facilities, the Commission may hold a public meeting as per 30 TAC 39 if public interest is shown.

TCEQ provides easy to find public participation information on-line. In addition the state maintains an Environmental Equity office to
address EJ issues. Some of the goals of the program are to help citizens and neighborhood groups participate in regulatory
processes; serve as the agency contact to address allegations of environmental injustice; serve as a link for communications
between the community, industries, and the government; and to thoroughly consider all citizens' concerns and handle them fairly.

There is also a public participation process in RCRA corrective action. A RCRA final remedy for a site is described in a Statement of
Basis which has a 45-day (or 30-day) public comment period. Once public comments are collected, the authorized agency writes a
Response to Comments/Final Decision document.

~ 51 ~


-------
~ 52 ~


-------
APPENDIX E

2020 CPRA Corrective Action Sites within 5 Miies of Communities of Concern

EPA ID NO.

FACILITY

PARCEL
OWNER

LEAD
AGENCY

RANK
CA075

HUMAN
HEALTH
CA725

GROUNDWATER
CONTROLLED
CA750

REMEDY
SELECTED
CA400

REMEDY
CONSTRUCTED
CA550

PROJECTED
REMEDY
CONSTRUCTED
CA 550

EJ SEAT
RANKING

Manchester, Texas

TXD000802959

Ak Steel
Corporation

Armco Inc

EPA TX47

ME

YE 10/09

OK

OK

OK

2017

1

TXD008089021

Koppers
Company Inc

Magellan
Terminal
Holdings

STATE

HI

YE 07/04

YE 07/04

08/06



2011

1

TXD008098725

Chevron
Phillips
Chemical
Company Lp

Chevron
Phillips
Chemical

STATE

HI

YE 02/09

YE 02/09

02/09

NR 02/09



1

TXD008099079

Rhodia Inc

Rhodia /
Texas Ultra
Pure (joint

parcel
ownership)

EPA TX47

ME

YE 03/07

OK

OK

OK

2018

1

TXD008105959

Parkans
International
Lie

Seafood
Internationale
LLC

EPA TX47

LO

YE 10/09

OK

OK

OK

2018

2

TXD026481523

Kinder Morgan

Liquids
Terminals Lp

GATX
Terminals
Corp

STATE

HI

YE 12/04

YE 12/04

08/08

RC 08/08





TXD053624193

Valero

Valero
Refining Co
Texas

STATE

LO

YE
11/10

YE 11/10

10/10

10/10



1

TXD055135388

Set

Environmental
Inc

Set

Environmental
Inc

EPA TX47

LO

YE
9/10

OK

OK

OK



1

~ 53 ~


-------
EPA ID NO.

FACILITY

PARCEL
OWNER

LEAD
AGENCY

RANK
CA075

HUMAN
HEALTH
CA725

GROUNDWATER
CONTROLLED
CA750

REMEDY
SELECTED
CA400

REMEDY
CONSTRUCTED
CA550

PROJECTED
REMEDY
CONSTRUCTED
CA 550

EJ SEAT
RANKING

TXD082684002

Exxon
Chemical
Americas
Baytown
Chemical

Exxon Corp

EPA6PD
CASE

HI

YE
8/07

IN 8/07





2016



TXD082688979

Lyondell Citgo
Refining Lp

Houston
Refining

STATE

HI

YE 08/02

YE 08/02

07/06

RC 08/07



5

TXD084972777

Bayer Corp

John E Frantz

STATE

HI

YE 10/01

YE 08/02

02/08

NR 02/08



1

TXD982560294

Nuclear
Sources And
Services Inc

Robert D
Gallagher

STATE

HI

YE 10/00

YE 10/00

02/06

NR 02/06



1

TXD990757486

Air Products Lp

Air Products
Incorporated

STATE

ME

IN 07/97

IN 07/97

01/09

RC 01/09



1

Corpus Christi, Texas

TXD008117186

Encycle Texas
Inc

Still waiting on
data

EPA6PD
CASE

HI

YE 12/04

YE 04/04

11/10



2013

3

TXD008132268

Valero Energy
Corp

Still waiting on
data

STATE

ME

YE 01/09

YE 01/09





2012

1

TXD051161990

Citgo
Petroleum
Corporation

Still waiting on
data

STATE

LO

YE 01/09

YE 01/09





2012

1

TXD066447376

Flint Hills
Resources Lp

Still waiting on
data

STATE

HI

YE 02/00

YE 12/03

08/07

RC 08/07



1

TXD981153711

Citgo Refining
And Chemicals
Company Lp

Still waiting on
data

STATE

ME

YE 09/09

YE 06/09

02/09

NR 02/09



3

TXD981157530

Citgo Refining
And Chemicals
Inc

Still waiting on
data

STATE

LO

IN 03/07

IN 03/07

3/11

3/11





Port Arthur, Texas

TXD000820928

Huntsman
Petrochemical
Corporation

Huntsman
Petrochemical
Corp

STATE

LO

YE 03/05

YE 03/05

02/06

RC 02/06



3

TXD008076846

Huntsman
Petrochemical
Corporation

Huntsman
Petrochemical
Corp

STATE

ME

YE 09/09

YE 09/09

09/09

NR 09/09



2

TXD008090409

The Premcor

Golden

STATE

HI

YE 02/03

YE 02/03





2012

4

/-N^ ^	/V/


-------
EPA ID NO.

FACILITY

PARCEL
OWNER

LEAD
AGENCY

RANK
CA075

HUMAN
HEALTH
CA725

GROUNDWATER
CONTROLLED
CA750

REMEDY
SELECTED
CA400

REMEDY
CONSTRUCTED
CA550

PROJECTED
REMEDY
CONSTRUCTED
CA 550

EJ SEAT
RANKING



Refining Group
Inc

Triangle
Properties
LLC

















TXD008097529

Motiva
Enterprises Lie

Motiva
Refinery

STATE

HI

YE 04/04

YE 04/04

02/09



2015

3

TXD980626022

Motiva
Enterprises Lie

Motiva
Refinery

EPA6PD
CASE

HI

YE 12/04

YE 12/04





2015

2

Mossville, Louisiana

LAD000618256

Cecos Intl, Inc.
Calcasieu
Facility

Cecos
International
Inc

STATE

HI

YE 05/03

YE 05/03

06/08

2/11



9

LAD008080350

Citgo
Petroleum
Corporation

Citgo
Petroleum
Corporation

STATE

HI

YE 04/05

IN 08/99





2018

3

LAD008080681

Olin
Corporation,
Lake Charles

Olin
Corporation

STATE

HI

YE 06/03

YE 06/03





2014

3

LAD008086506

PPG Industries
Inc

PPG
Industries Inc

STATE

HI

YE 06/04

YE 06/04

6/10



2012

3

LAD086478047

Georgia Gulf
Lake Charles,
Lie

Georgia Gulf
Lake Charles
LLC

STATE

HI

YE 03/03

YE 03/03

02/10

NR 02/10



3

LAD981514441

Ppg Industries
No 5
Incinerator

PPG
Industries Inc

STATE

HI

YE 06/00

YE 06/00

12/05

12/05





LAD990683716

ConocoPhillips
Company

Conoco Inc

STATE

HI

YE 10/05

YE 10/05





2020

3

LAR000018333

Lyondell
Chemical
Company

Lyondell
Chemical
Company

STATE

LO





6/10



2014

3

LAR000041087

Sasol North
America Inc.

Sasol North
America Inc

STATE

LO









2014

3

Grants, New Mexico - no RCRA 2020 sites within 40 miles

~ 55 ~


-------
~ 56 ~


-------
Table of Contents

Page

Original Corrective Action Strategy to Meet GPRA 2020 Goals	1

Updated Regional Corrective Action Strategy	3

Chart 1: Projected Progress to CA550	11

Table 1A: Projected % Facilities Reaching GPRA Goals	12

Table 1B: Actual vilifies Reaching GPRA Goals	13

Table 2: Projected and Actual % Facilities in Total Universe Reaching GPRA Goals	14

Chart 2: Projected versus Actual Progress to CA550	15

Table 3: Facilities of Concern	17

Tabl ategorization of Difficult Baseline Facilities	25

Addendum 1: Huffman Wood Preserving and Oklahoma Pole and Lumber Facilities	29

Addendum 2: MicroChemical Company	31

Addendum 3: Rogers Delinted Cottonseed Company	33

Addendum 4: Region 6 RCRA Hazardous Waste Program Environmental Justice Strategy	35

Appendix A: Map EJ Areas of Concern	39

Appendix B: Environmental Justice Strategic Enforcement Assessment Tool	40

Appenc \ „ Map Regi $ „ ective Action Baseline Facilities Location	43

Appendix D: Summ > i V ig/"o- Spates RCRA Pub ^ •• "licipation	45

Appendix E: 2020 GPRA CA Sites witl e Miles of Communities of Concern	51

~ 57 ~


-------