A.

o

Community Update #34
Pompton Lakes Study Area
Pompton Lakes, New Jersey

Pompton Lake Dredging

Community Update

April 2017

EPA CLEANUP ACTIVITIES
Basic Site Information—2017

The scope of work in 2017 involves
hydraulic dredging, processing and
off-site disposal of sediment con-
taining mainly mercury and lead in a
36-acre area within Pompton Lake
called the Acid Brook Delta (ABD).
Placement of the eco-layer in Area
A, the Island Area and the ABD will
also be completed. The work will
be performed by The Chemours
Company FC, LLC., through its
contractor, Sevenson Environmental
Services with EPA/NJDEP over-
sight.

Further information:

Boron ph of Pompton Lakes

http: //www .pomptonlake sgov .com

Questions? Please Contact:

EPA Remedial Project Manager

Perry Katz

(212) 637-4426
katz.ira-perry@epa.gov

EPA Community Involvement
Coordinator

Pat Seppi

(646) 369-0068

seppi .pat@epa.gov

EPA's 34th update is to inform the community of the progress of
activities related to the upcoming dredging that will be performed on
that 36-acre portion of the Pompton Lake Study Area known as the
Acid Brook Delta (ABD). The dredging work is scheduled to com-
mence in the Spring 2017, but has yet to start.

Preparatory activities underway since January are related to the fact
that the method of dredging to be performed in 2017 (hydraulic
dredging) is different than the dredging performed in 2016
(mechanical dredging).

Preparatory activities currently underway (week of April 3rd):

~	Completion of application of ecological layer in Area A.

~	Turbidity monitoring during placement of eco-layer in Area A.

~	Continued installation of sediment processing and water treat-
ment equipment needed for 2017 work.

~	Continuation of turbidity curtain installation around the ABD.

~	Clearing of debris in/around bridge above Acid Brook.

~	Securing permit modifications addressing changes in the sedi-
ment treatment processes

~	Continue routine inspection of site and work areas per approved
permits and for safety reasons.

Preparatory activities scheduled (week of April 10th):

~	Complete installation of turbidity curtain around ABD.

~	Continue installation of sediment processing and water treatment
equipment needed for 2017 work.

~	Bathymetric surveying.

~	Initiate fish relocation.

~	Continue routine inspection of site and work areas per approved
permits and for safety purposes.

Thank you to those who attended the March 30th Public Availability
session! We are in the process of preparing answers to questions
raised during the Public Availability session and will provide them
in the near future.

Note that EPA has updated its website and we encourage you to fol-
low the link below for additional information about the dredging.


-------