U.S. Environmental Protection Agency

Air Treatment at Grenada
Stamping - Information for Workers

Fact Sheet #13	January 2018

Introduction

On December 29, 2017, a treatment system intended to reduce elevated levels of trichloroethene (TCE) inside the
manufacturing building at the Grenada Stamping facility (Facility) was restarted under an EPA removal action. Removal
actions are short-term responses under the Comprehensive Environmental Response, Compensation, and Liability Act
(CERCLA) intended to protect people from risks or potential risks associated with contaminated sites. The treatment system
will operate with EPA oversight and monitoring.

TCE contamination is present beneath the Facility as a result of spills from prior operations. Sampling indicates TCE vapors
from beneath the concrete floor are rising into the building and there could be a risk to workers. The new treatment system
will replace interim measures taken since January 2017 to increase ventilation. These have decreased TCE concentrations
within the building. The new treatment system is a more reliable, long-term method to ensure TCE concentrations remain
at acceptable levels.

More information about EPA's ongoing work to oversee the cleanup of the site is posted at: www.epa.gov/grenadacleanup.

Pilot Study and Air Permitting

EPA previously directed the Facility to install the treatment system, known as a sub-slab depressurization system or "SSDS"
(refer to Fact Sheet #11 for more detail). The Facility's contractor installed and operated the SSDS from August 12 to
September 11, 2017, as a pilot study. Air sampling results before and after the pilot (summarized on page 2) showed the
treatment system was effective at reducing TCE concentrations inside the building.

As part of the pilot, potential annual emissions of hazardous air pollutants were estimated. Because the treatment system
will operate under EPA's CERCLA authority, a state air permit is not required, however, the Facility will be required to meet
the substantive requirements of such a permit. These include air sampling at multiple points of the air treatment system to
verify effectiveness of the system and ensure emission standards are met.

Summer/Fall 2017 Air Sampling Results

EPA directed the Facility to perform multiple rounds of air sampling in and around the manufacturing building beginning in
October 2016. The results of the most recent air sampling conducted from June to October 2017 are summarized below.
Detailed results from all sampling performed to date are posted online.

EPA


-------
Summer/Fall 2017 Air Sampling Results (continued)

Indoor Air Results

Indoor air samples were collected from six
locations inside the manufacturing building using
traditional Summa canisters and Radiello®
samplers that slowly draw air over a specified
duration (24-hours, 7-days or 28-days). This
yielded 55 samples (summarized in Table 1). Some
results before the treatment system was turned on
exceeded the removal management levels (RMLs)
for sensitive and non-sensitive populations. RMLs
are used by EPA to help determine if any future
actions may be needed. A sample result higher
than a RML by itself does not imply that adverse
health effects will occur.

Outdoor Air Results

Air samples were collected using Radiello®
samplers from outside of the manufacturing
building over several durations (24-hours, 7-days
or 28 days). TCE was detected in all 7 samples at
very low levels below the indoor RML (there is no
RML for outdoor air).

Table 1: Summary of TCE Concentrations in Indoor Air inside of
Manufacturing Building

Sample
Duration

Sampling Date

Removal
Management
Levels (RMLs)41

Range of
Concentrations
Detected

24 hour

6/28/2017

8.8/26

6.2-28

7 day

7/13 - 7/20/2017

8.8/26

6.1-11

28 day

7/13 - 8/10/2017

8.8/26

6.6-26

28 day

8/13 - 9/11/2017

8.8/26

0.93-6.4

24 hour

8/31/2017

8.8/26

<0.98-5.2

7 day

8/31 - 9/7/2017

8.8/26

1.7-2.4

24 hour

9/27/2017

8.8/26

3.1-7.8

28 day

9/11 -10/9/2017

8.8/26

2.0-7.6

Concentrations reported in micrograms per cubic meter ug/m3

*The Removal Management Level (RML) for sensitive

Populations, which includes women of childbearing age, is 8.8 Mg/m3. The RML for
non-sensitive populations is 26.0 ng/m3.

Actions Being Taken

An On-Scene Coordinator (OSC) was assigned to conduct a Removal Site Evaluation (RSE). The RSE consisted of a review of
recent facility indoor air monitoring sample results and current status of the treatment system. The OSC determined that
site conditions met the criteria for conducting a removal action. The OSC conducted a site visit on January 3, 2018, and
verified the treatment system is operational. EPA will require the Facility to submit a sampling plan for the system itself in
order to ensure the system is performing properly and that workers and the surrounding community are protected while
the system operates. EPA continues to work with the MDEQ and the Facility to identify long-term measures to reduce and
eventually eliminate the source of TCE contamination beneath the Facility.

CONTACTS

EPA Community Involvement Coordinator

Abena Ajanaku
404-562-8834
ajanaku. abena (Sepa.gov

EPA On-Scene Coordinator

Steve Spurlin
731-394-8996
spurlin.steveffi epa.gov

FOR MORE INFORMATION

Website

www.epa.gov/grenadacleanup

Information Repository

Elizabeth Jones Library
1050 Fairfield Avenue
Grenada, MS 38902


-------