Community Update #75
Pompton Lakes Study Area
Pompton Lakes, New Jersey

Pompton Lake Dredging

Community Update	April 2018

s

EPA's 75th update is to inform the community of the progress of activities
related the dredging performed on the 36-acre portion of the Pompton Lake
Study Area known as the Acid Brook Delta (ABD).

Activities performed (week of April 2nd):

~	Continued demobilization/disassembly of water treatment equipment.

~	Performed mechanical and hydraulic placement of initial two-inch lift
of ecological layer (i.e. sand) material along shoreline.

~	Two loads of remnant material from demobilization/disassembly of
equipment transported off-site for disposal.

~	Turbidity/dust monitoring in progress for ecological layer placement/
restoration — monitoring data posted at

www.pomptonlakesworks.com/pompton-lake-project/environmental-
monitoring).

Activities scheduled (week of April 9th):

~	Complete demobilization/disassembly of equipment.

~	Continue placement of ecological layer along shoreline of ABD.

~	Receive trucks delivering ecological material on a daily basis.

~	Continue routine inspection of site work areas per approved permits
and for safety purposes.

~	Continue lake turbidity/perimeter air (dust) monitoring.

Note:

THERE WILL BE WORK ON SATURDAY, APRIL 7TH FROM 8
a.m. TILL 5 p.m. WORK ON THE WATER WILL INVOLVE
EQUIPMENT MAINTENANCE AND ON-LAND WORK WILL IN-
VOLVE DISASSEMBLY OF CARBON UNITS UTILIZED DURING
DREDGING. GATES WILL CLOSED WHEN POSSIBLE.

EPA WILL BE A VAILABLE TO THE PUBLIC ON TUESDA Y, APRIL
24THAT THE CARNEVALE CENTER FROM 10AM UNTIL 8PM TO
DISCUSS THE SCOPE OF WORK/ANSWER QUESTIONS REGARD-
ING ACTIVITIES ON POMPTON LAKE FOR 2018 INCLUDING
ECOLOGICAL PLACEMENT AND RESTORATION ACTIVITIES.

THERE WILL BE INCREASED TRUCK TRAFFIC DURING THIS
PHASE DUE TO THE DELIVERY OF ECOLOGICAL MATERIAL
(i.e. SAND). TRAFFIC CONTROLS WILL BE IN PLACE.

PHOTOS: THE FIRST PHOTO SHOWS RECEIPT/UNLOADING
OF ECOLOGICAL MATERIAL. THE SECOND PHOTO SHOWS
LOADING OF THE HOPPER WITH ECOLOGICAL MATERIAL
FOR HYDRAULIC PLACEMENT IN THE ABD.

EPA CLEANUP ACTIVITIES
Basic Site Information—2018

The scope of work in 2018 involves
placement of the eco-layer in the
Island Area and the ABD as well as
site restoration. Hydraulic dredging,
processing and off-site disposal of
sediment containing mainly mercury
and lead in a 36-acre area within
Pompton Lake called the Acid
Brook Delta (ABD) is complete.
The work will be performed by The
Chemours Company FC, LLC.,
through its contractor, Sevenson
Environmental Services with EPA/
NJDEP oversight.

Further information/contacts:

Boroiiph of Pompton Lakes

http: //www .pomptonlake sgov .com

EPA Remedial Project Manager

Perry Katz

(212) 637-4426

katz.ira-perry@epa.gov

EPA Community Involvement
Coordinator

Pat Seppi

(646) 369-0068

seppi .pat@epa.gov

EPA continues presence at Bor-
ough Hall Thursdays from
10 a.m. till 4p.m.


-------