Community Update #72
Pompton Lakes Study Area
Pompton Lakes, New Jersey

Pompton Lake Dredging

Community Update

March 2018

EPA CLEANUP ACTIVITIES
Basic Site Information—2018

The scope of work in 2018 involves
placement of the eco-layer in the
Island Area and the ABD as well as
site restoration. Hydraulic dredging,
processing and off-site disposal of
sediment containing mainly mercury
and lead in a 36-acre area within
Pompton Lake called the Acid
Brook Delta (ABD) is complete.
The work will be performed by The
Chemours Company FC, LLC.,
through its contractor, Sevenson
Environmental Services with EPA/
NJDEP oversight.

Further information:

Boroiiph of Pompton Lakes

http: //www .pomptonlake sgov .com

Questions? Please Contact:

EPA Remedial Project Manager

Perry Katz

(212) 637-4426

katz.ira-perry@epa.gov

EPA Community Involvement
Coordinator

Pat Seppi

(646) 369-0068

seppi .pat@epa.gov

EPA's 72nd update is to inform the community of the progress of activities
related to the dredging performed on the 36-acre portion of the Pompton
Lake Study Area known as the Acid Brook Delta (ABD). EPA is resum-
ing the use of this format for providing a status update as the level of
activity for this season '.s work is about to increase.

Activities performed (week of March 12th):

~	Continued demobilization/disassembly of equipment.

~	Continued mobilization of equipment associated with the next phase of
work—ecological layer placement.

~	Turbidity/dust/mercury monitoring completed— data on website:
(www.pomptonlakesworks.com/pompton-lake-project/environmental-
monitoring).

Activities scheduled (week of March 19th):

~	Complete demobilization/disassembly of equipment.

~	Complete mobilization of equipment and materials to initiate placement
of ecological layer.

~	Continue routine inspection of site work areas per approved permits
and for safety purposes.

Note:

HYDRAULIC AND MECHANICAL DREDGING ARE COMPLETE.

THIS PHASE OF WORK IS "CLEAN" WORK MEANING THAT
THE PLACEMENT OF THE ECOLOGICAL LAYER AND SITE
RESTORATION DO NOT INVOLVE THE HANDLING OR
TRANSPORT OF CONTAMINATED SEDIMENT.

THERE WILL BE INCREASED TRUCK TRAFFIC DURING THIS
PHASE DUE TO THE DELIVERY OF ECOLOGICAL MATERIAL
(i.e. SAND). TRAFFIC CONTROLS WILL BE IN PLACE.

EPA WILL CONTINUE ITS PRESENCE AT BOROUGH HALL ON
THURSDAYS FROM 10AM UNTIL 4PM. ALTERNATIVELY, DO
NOT HESITATE TO CONTACT US USING THE CONTACT IN-