RE-Powering America's Land

Project Matching: Facilitating New Renewable Energy Projects
Project Proposal Submittal Form

The EPA Green Power Partnership's (GPP's) Project Matching Initiative works to connect stakeholders
with new, not-yet-built renewable energy projects that may align with their energy, environmental, and
financial objectives. The initiative's goal is to spur the development of new renewable generation by
facilitating the signing of long-term green power contracts between end-users and project developers,
thereby providing a guaranteed stream of revenue that developers can use to secure project financing.

The GPP, in collaboration with EPA's RE-Powering America's Land Initiative, will host a project matching
webinar on Wednesday, June 24, 2015. Project developers are invited to submit project proposals to
GPP for possible inclusion in the webinar. This form includes all anticipated criteria that EPA will use to
select projects for the webinar. All projects submitted for review that meet minimum requirements for
data completeness and basic eligibility will be posted on the GPP website. A renewable energy project's
inclusion in this initiative does not constitute endorsement or recommendation by EPA.

Project proposals are due by June 5, 2015 and must be submitted electronically to James Critchfield,
critchfield.james@epa.gov.

Contact Information

Matthew Martin
mmartin(a) capitalpower.com
617-274-7700

Project Summary
Project name: Bloom Wind

Developer name: CP Bloom Wind LLC

Renewable energy type: Wind

Project city/state: Bloom and Minneola, Kansas

Project geographic coordinates (To find, use: www.latlong.net/):

Latitude: 37.494635	 Longitude: -99.926464	

Total planned megawatt (MW DC) size: 180MW

Are there phases? If so, how many and in what size traunches? The project prefers to construct as 1
phase (180MW) but is willing to transact in smaller increments (e.g., 2 x 90MW).


-------
What is the expected annual output of the completed project (MWh)? Estimated 800,000 MWh
Expected date of construction commencement: Q.4 2015
Expected date of commercial operation: Q4 2016

What is the largest development hurdle and how is it anticipated to be overcome? The major
development hurdle remaining is obtaining an off-take agreement. The Project has qualified for the
Production Tax Credit and has an executed Generator Interconnection Agreement (GIA) so it is prepared
to move toward construction as soon as off-take is secured.

Can you provide examples of similar projects you have developed? Capital Power has developed and
constructed 5 wind projects:

•	K2 Wind-270MW in Ontario-COD 2015

•	Port Dover Nanticoke Wind - 105MW in Ontario - COD in 2013

•	Halkirk Wind - 150MW in Alberta - COD in 2012

•	Quality Wind - 142MW in British Columbia - COD in 2012

•	Kingsbridge I Wind - 40 MW in Ontario - COD in 2006

Site Readiness

Has the project received all necessary federal, state, and local permits to proceed with construction
and operation? If not, please outline the key permits required to proceed with project
construction/operation and describe the steps you have taken in order to evaluate and address
permitting risk for this project.

The Bloom Wind project has obtained its Conditional Use Permit from Ford County; Federal Aviation
Administration clearances for 64 locations; has a signed Generator Interconnection Agreement with SPP
and ITC Great Plains; has coordinated with the requisite state and federal agencies in regards to species,
cultural resources, waters and wetlands; and has qualified for the Federal Production Tax Credit.

Remaining permits required to commence construction include road access and utility permits from
Kansas Department of Transportation; Culvert and excavation permits from Ford County; and a
Nationwide Permit 12 for construction activities. Many of these will be obtained by the selected EPC
contractor and all can be obtained prior to the planned construction start date.

Have you secured long-term site control? If so, please describe the nature of the agreement (lease,
ownership, etc.)? The Project has long-term site control via Lease & Easement Agreements recorded
with Ford and Clark County Registers of Deeds.

Have land leases been filed with the county? Yes.

Does the project require either an Environmental Impact Statement or Environmental Assessment? If
so, what is the status? No. There is no federal nexus for the Project; an EIS / EA is not required.
However, extension environmental studies have been conducted at the site and project design has been
structured to ensure there will be no adverse effects on species, waters, wetlands or cultural resources.


-------
Is this project sited on a current or formerly contaminated land, landfill or mine site?1 If so, has the
site addressed the related environmental issues? No.

Interconnection

What is the status of interconnection, and have system impact and facility studies been completed?
(Distribution or transmission level projects are both eligible). The Project has an executed Generator
Interconnection Agreement with ITC Great Plains and Southwest Power Pool. System Impact and
Facility Studies are completed.

When do you expect the interconnection study process will be complete? Process is complete. GIA
was executed in March 2015.

Does the transmission owner (TO) or independent system operator (ISO) have a process to study the
project's impact on the local or regional grid and the subsequent cost to interconnect? Yes. Study
process is complete.

Operation & Financing

Is any element of the project - technology or systems - experimental or pilot-phase or proven
technology? The Project will use proven technologies.

What is the long- and short-term plan for operating and maintaining the project? Capital Power
intends to own and operate the facility long-term, as it does with its six other wind facilities in the U.S.
and Canada.

For wind projects, has a meteorological tower been installed? If yes, when was the tower installed
and how much data has been collected? Two wind monitoring towers have been installed and continue
to collect data: 80m tower installed in September 2011; 60m tower installed in November 2012.

Provide a short summary of how you view project finance and structure/ownership taking shape for
this project: Capital Power intends to finance construction on balance-sheet and bring in a tax equity
investor at COD. The structure is expected to be approximately 70% tax equity and 30% sponsor equity
based on Production Tax Credit projections.

Partners

In what ways can organizations participate in the project? (Check all that Apply)

X Power purchase agreement for bundled power and RECs
X Financial hedge or contract for differences
X Long term REC offtake

~	Financial investment / ownership stake

~	Other, please specify:	

What are some of the characteristics of your ideal power purchaser, investor, or other partner?

1 Examples of such properties could include brownfields, municipal solid waste landfills, abandoned mine lands,
and Superfund sites, among others subject to state or federal authorities or cleanup programs.


-------
The project is seeking a purchaser or purchasers of 800,000 MWh of clean energy and associated RECs
and environmental attributes. The ideal counterparty would be investment grade rated and willing to
pursue a long-term (10+ year) contract.

What marketing opportunities exist at the project?

The project is able to market within SPP and is pursuing transmission rights to market its power in
surrounding RTOs and regional markets to the east.


-------