Community Update #80
Pompton Lakes Study Area
Pompton Lakes, New Jersey

Pompton Lake Dredging

Community Update

May 2018

EPA CLEANUP ACTIVITIES
Basic Site Information—2018

The scope of work in 2018 involves
placement of the eco-layer in the
Island Area and the ABD as well as
site restoration. Hydraulic dredging,
processing and off-site disposal of
sediment containing mainly mercury
and lead in a 36-acre area within
Pompton Lake called the Acid
Brook Delta (ABD) is complete.
The work will be performed by The
Chemours Company FC, LLC.,
through its contractor, Sevenson
Environmental Services with EPA/
NJDEP oversight.

Further information/contacts:

Boroiiph of Pompton Lakes

http: //www .pomptonlake sgov .com

EPA Remedial Project Manager

Perry Katz

(212) 637-4426

katz.ira-perry@epa.gov

EPA Community Involvement
Coordinator

Pat Seppi

(646) 369-0068

seppi .pat@epa.gov

EPA continues its presence at
Borough Hall Thursdays from
10a. nt till 4p.m.

EPA's 80th update is to inform the community of the progress of activities

related to the dredging performed on the 36-acre portion of the Pompton

Lake Study Area known as the Acid Brook Delta (ABD).

Activities performed (week of May 7th):

~	Continued mechanical and hydraulic placement of the eco-layer (i.e.
sand) material in the ABD.

~	2-inch lift of eco-layer material placed via hydraulic and mechanical
means is now complete in ABD.

~	Performed work associated with eco-layer placement and restoration at
Island Area.

~	Lake turbidity/ perimeter air (dust) monitoring continues for eco-layer
placement/restoration — monitoring data posted at
www.pomptonlakesworks.com/pompton-lake-project/environmental-
monitoring.

Activities scheduled (week of May 14th):

~	Continue placement of ecological layer (4-inch lift) within the ABD.

~	Continue eco-layer placement/restoration activities at the Island Area.

~	Receive trucks delivering ecological material on a daily basis.

~	Continue routine inspection of site work areas per approved permits
and for safety purposes.

~	Continue lake turbidity/perimeter air (dust) monitoring.

Notes:

THERE WILL BE WORK ON SATURDAY, MAY 12TH FROM
8 a.m. TILL 5 p.m. WORK WILL INVOLVE EQUIPMENT
MAINTENANCE. GATES WILL BE CLOSED WHEN POSSIBLE.

THE PROGRESS OF THE ECO-LAYER PLACEMENT IS POSTED
ON THE AFOREMENTIONED WEBSITE IN A FORMAT SIMI-
LAR TO THE DEPICTION OF THE DREDGING PROGRESS.

PHOTO: THE PHOTO SHOWS THE MOVING OF THE FEED
PIPE UTILIZED FOR THE HYDRAULIC PLACEMENT OF THE
ECO-LAYER MATERIAL.


-------