[<

SEPA

GREEN

POWER

PARTNERSHIP

RE-Powering America's Land

Project Matching: Facilitating New Renewable Energy Projects
Project Proposal Submittal Form

The EPA Green Power Partnership's (GPP's) Project Matching Initiative works to connect stakeholders
with new, not-yet-built renewable energy projects that may align with their energy, environmental, and
financial objectives. The initiative's goal is to spur the development of new renewable generation by
facilitating the signing of long-term green power contracts between end-users and project developers,
thereby providing a guaranteed stream of revenue that developers can use to secure project financing.

The GPP, in collaboration with EPA's RE-Powering America's Land Initiative, will host a project matching
webinar on Wednesday, June 24, 2015. Project developers are invited to submit project proposals to
GPP for possible inclusion in the webinar. This form includes all anticipated criteria that EPA will use to
select projects for the webinar. All projects submitted for review that meet minimum requirements for
data completeness and basic eligibility will be posted on the GPP website. A renewable energy project's
inclusion in this initiative does not constitute endorsement or recommendation by EPA.

Project proposals are due by June 5, 2015 and must be submitted electronically to James Critchfield,
critchfield.james@epa.gov.

Contact Information

Katya Samoteskul

ksamoteskul(a)invenergvllc.com

312-582-1295

Project Summary

Project name: Beech Ridge II Wind Energy Center

Developer name: Invenergy Wind Development LLC

Renewable energy type: wind

Project city/state: Greenbrier County, WV

Project geographic coordinates (To find, use: www.latlong.net/):

Latitude 38.019848	 Longitude -80.543845	

Total planned megawatt (MW DC) size: 37 MW

1


-------
Are there phases? If so, how many and in what size traunches?

The Project is a phase II of Invenergy's existing 100.5 MW Beech Ridge I project.

What is the expected annual output of the completed project (MWh)? About 129,000 MWh.

Expected date of construction commencement: Q1 2016.

Expected date of commercial operation: Q3 2016.

What is the largest development hurdle and how is it anticipated to be overcome?

No significant development hurdles remain.

Can you provide examples of similar projects you have developed?

Invenergy ranked #2 in terms of new U.S. wind capacity installed in 2014 and is North America's largest
independent wind power generation company. The Company has developed over 50 wind farms across
the United States, Canada and Europe, totaling over 5,822 MW globally. This portfolio consists of over
4,489 MW of operating projects, 1,111 MW of projects in construction, and 222 MW of projects under
contract.

Site Readiness

Has the project received all necessary federal, state, and local permits to proceed with construction
and operation? If not, please outline the key permits required to proceed with project
construction/operation and describe the steps you have taken in order to evaluate and address
permitting risk for this project.

Invenergy has received all state permits required to begin construction, including a siting certificate
from the WV Public Service Commission a Stormwater Pollution Prevention Plan approval from the WV
Department of Environmental Protection. Invenergy expects to attain the remaining federal approval in
Q4 2015.

Have you secured long-term site control? If so, please describe the nature of the agreement (lease,
ownership, etc.)?

Yes, Invenergy has control of all the land needed to build the Project.

Have land leases been filed with the county?

Yes.

Does the project require either an Environmental Impact Statement or Environmental Assessment? If
so, what is the status?

The Project was issued an Incidental Take Permit for potential take of Indiana and Virginia big-eared bats
in December 2013. The U.S. Fish and Wildlife Service completed an EIS as part of its NEPA review for
this permit. Invenergy has completed archaeology and wetlands studies and has identified no significant
resources that would prevent construction of the Project.

2


-------
Is this project sited on a current or formerly contaminated land, landfill or mine site?1 If so, has the
site addressed the related environmental issues?

Portions of the site have been previously mined for coal, and it is now managed by a private owner for
commercial timber production. A Phase 1 environmental site assessment has not identified any
significant issues for the Project.

Interconnection

What is the status of interconnection, and have system impact and facility studies been completed?
(Distribution or transmission level projects are both eligible)

All interconnection studies (including System Impact and Facilities Study) have been completed, and an
interconnection agreement has been signed. The Project will interconnect to PJM at Monongahela
Power Company's 138 kV GrassyFalls substation. The Project will share interconnection with the existing
Beech Ridge Wind Energy Center and an existing 14-mile long 138 kV interconnection line.

When do you expect the interconnection study process will be complete?

The interconnection study process is complete.

Does the transmission owner (TO) or independent system operator (ISO) have a process to study the
project's impact on the local or regional grid and the subsequent cost to interconnect?

Yes. PJM studied these impacts and costs as part of the required interconnection studies.

Operation & Financing

Is any element of the project - technology or systems - experimental or pilot-phase or proven
technology?

Wind turbine technology employed at the Project will not be experimental. Invenergy will use proven
and highly reliable General Electric wind turbines at the Project.

What is the long- and short-term plan for operating and maintaining the project?

Invenergy operates all of its US projects and will maintain the Project through a dedicated O&M facility
near the Project site.

For wind projects, has a meteorological tower been installed? If yes, when was the tower installed
and how much data has been collected?

Meteorological data has been collected from three on-site towers. One was installed for October 2005
and collected 3.5 years of data before being decommissioned. Two other towers were installed in
September 2011 and are still in operation. As of June 2015, Invenergy has collected 3.7 years of data
from these two towers.

1 Examples of such properties could include brownfields, municipal solid waste landfills, abandoned mine lands,
and Superfund sites, among others subject to state or federal authorities or cleanup programs.

3


-------
Provide a short summary of how you view project finance and structure/ownership taking shape for
this project:

Invenergy proficiently structures project financing and maintains strong relationships with banks in the
United States, Canada, Europe and Asia. During the late stages of project development, Invenergy typically
approaches lenders a few months prior to construction to provide construction financing. The
construction loan combined with Sponsor equity will raise sufficient capital for the entire construction
cost of the Project.

Financing for a project is typically structured as non-recourse project financing. The security and collateral
package held by the project financing parties customarily consists of a pledge of the equity in the Project
company, a pledge of all Project assets, and collateral assignments of certain material Project agreements.

On or shortly after COD, the construction financing is replaced by more permanent financing, such as a
term loan or tax equity investment. The security and collateral package during the term loan period is
usually the same as that during the construction period.

Partners

In what ways can organizations participate in the project? (Check all that Apply)
ivf Power purchase agreement for bundled power and RECs
[vf Financial hedge or contract for differences
[vf Long term REC offtake
[vf Financial investment / ownership stake
[vf Other, please specify: PPA with a REC swap	

What are some of the characteristics of your ideal power purchaser, investor, or other partner?

Over the last 10 years, Invenergy has developed a worldwide portfolio of 70 projects totaling 9,000 MW
that are operating or under construction. Invenergy's customers have included utilities, municipalities,
and coops, such as American Electric Power, Commonwealth Edison, Detroit Edison, Los Angeles
Department of Water & Power, Ontario Power Authority, Omaha Public Power District, Pacific Gas &
Electric Company, PacifiCorp, Tennessee Valley Authority, Xcel Energy and others.

We also work with banks (Bank of America, JP Morgan Chase, Citi Group, Credit Suisse and others),
commercial and industrial customers and universities.

We are happy to assist large companies, universities and government agencies with meeting their
sustainability goals, while also providing them with opportunities to invest in well-planned, low risk
renewable energy projects across the US.

4


-------
What marketing opportunities exist at the project?

Invenergy will be happy to assist the future off-taker with crafting any future messaging campaigns to
ensure that the customer receives full credit from the public for supporting renewable energy
development in the US. We are also open to discussions regarding the naming rights for the Project.


-------