vvEPA

FACT SHEET

EPA's Final Lead and Copper Rule Improvements.

Technical Fact Sheet for States and Public Water Systems

October 2024

EPA is finalizing the Lead and Copper Rule Improvements (LCRI) to significantly reduce exposure to lead in
drinking water. The final rule builds on the 2021 Lead and Copper Rule Revisions (LCRR), which modified the
previous Lead and Copper Rule (LCR). The final LCRI strengthens five main focus areas: achieving lead pipe
replacement within 10 years, locating legacy lead pipes, improving tap sampling, lowering the lead action level,
and strengthening protections to reduce lead exposure. Key improvements in each of these five main focus
areas are described below.

1. Achieving Lead Pipe Replacements within 10 Years

Where lead service lines (LSLs) are present, they represent the
greatest lead exposure source in drinking water. EPA is requiring water
systems to conduct full replacement of all lead and galvanized
requiring replacement (GRR) service lines that are under the control of
the water system in 10 years or less, with limited exceptions,
regardless of the water system's 90th percentile lead level. The final
rule also:

•	Requires States to set shorter deadlines for individual water
systems where the State determines that it is feasible (e.g., by
taking into account the number of lead and GRR service lines
in a system's inventory).

•	Provides deferred deadlines for water systems with a high
proportion of known lead and GRR service lines in their system (unless the State determines that the
10-year deadline or a shorter deadline is feasible).

•	Prohibits water systems from conducting partial lead or GRR service line replacement unless it is
conducted as part of an emergency repair or in coordination with planned infrastructure work that
impacts service lines. Planned infrastructure work excludes work solely for lead or GRR service line
replacement. In the event of a partial replacement of a lead or GRR service line, the rule requires
water systems to take additional protective measures, including public education and risk mitigation
activities.

•	Requires water systems to provide pitcher filters or point-of-use (POU) devices that are certified to
reduce lead following replacement of lead and GRR service lines and additional types of disturbances
to lead, GRR, and unknown service lines. Examples of service line disturbances include replacement of
a connector, inline water meter, or water meter setter and disturbances that may be caused during
inventorying efforts.

Galvanized Requiring Replacement: A

GRR service line is a galvanized service
line that currently is or ever was
downstream of an LSL or is currently
downstream of a service line of
unknown material.

Control: A service line is under the
control of the water system wherever
it has access (e.g., legal access,
physical access) to conduct full service
line replacement.

EPA 816-F-24-011


-------
2. Locating Legacy Lead Pipes

Knowing where lead pipes are located is critical to replacing them efficiently and equitably and informing
consumers, so they can take actions to reduce their exposure to lead. The LCRI builds upon the 2021 LCRR's
requirement for water systems to create an initial inventory and to regularly update this inventory.

Service Line Inventory

The final LCRI incorporates the 2021 LCRR requirement for systems to develop an initial service line inventory
by October 16, 2024, and also requires water systems to:

•	Develop an updated initial service line inventory, called the LCRI baseline inventory, that includes
updated service line information and connectors. The baseline inventory is due by the LCRI compliance
date.

•	Review specific sources of information for connector materials and include the locations of the
identified connectors in the LCRI baseline inventory.

•	Validate the accuracy of the non-lead service line category in the inventory.

•	Notify customers and persons served by a service line that is known to or may potentially contain lead
(lead, galvanized requiring replacement, or lead status unknown service lines).

•	Annually update the inventory, submit the updates to the State, and include the following:

The total number of lead, GRR, non-lead, and unknown service lines; the total number of lead
connectors and connectors of unknown material; and the total number of lead and GRR service
lines fully and partially replaced in each preceding year.

•	Make the inventory publicly accessible and include the following:

A street address associated with each service line and connector or a
unique locational identifier (e.g., block, GPS coordinates, intersection
or landmark) if a street address is not available.

•	Identify the material of all unknown service lines by the replacement
deadline.

Expanded Service Line Replacement Plan Requirements

The final LCRI requires water systems to:

•	Include the following elements in the service line replacement plan: 1) strategy for identifying
unknown service lines; 2) standard operating procedure for full service line replacement; 3)
communication strategy to inform consumers and customers before full or partial replacement; 4)
procedure for consumers and customers to flush service lines and premise plumbing; 5) strategy to
prioritize replacements based on (but not limited to) known lead and GRR service lines and
community-specific factors such as disproportionally impacted and/or sensitive populations; 6) funding
strategy; 7) communication strategy to inform residential and non-residential consumers and
customers about the replacement plan and program; and 8) identification of any State and local laws
and water tariff agreements that affect the water system's ability to gain access to conduct full service
line replacement.

Water systems
serving more than
50,000 persons must
make the publicly
accessible inventory
available online.

EPA 816-F-24-011


-------
•	For systems that identify any lead-lined galvanized service lines in the inventory, the plan must include
a strategy to determine the extent of the use of these lines in the distribution system and categorize
them accordingly.

•	For systems that are eligible for and plan to use a deferred deadline, the plan must include
documentation that the systems meet the eligibility criterion and that the deferred deadline and
associated replacement rate are the fastest feasible.

•	Submit a service line replacement plan to the State by the LCRI compliance date and update it
periodically with new or updated information.

•	Make the service line replacement plan publicly accessible. For water systems serving more than
50,000 people, post it online.

The final LCRI makes key changes to the required protocol for tap sampling informed by best practices already
being deployed at the State and local levels. The rule also revises the requirements for how frequently systems
must conduct tap sampling and requires systems to submit a tap sampling plan to the State.

Sampling Protocol

The final LCRI:

•	Prioritizes collecting samples from sites served by LSLs. All samples must be collected from sites served
by LSLs, if available.

•	Modifies the tiering criteria that indicates where tap samples must be collected to include LSLs and
premise plumbing made of lead (where known) in the highest priority Tier 1 and Tier 2 sites. Also,
revises the Tier 3 criteria to include sites served by a lead connector and sites served by a galvanized
service line or containing galvanized premise plumbing identified as ever having been downstream of
an LSL.

•	Requires water systems with LSLs to collect an additional fifth-liter sample at the same time as the
first-liter sample (i.e., first-and-fifth-liter-paired sample) for lead at LSL sites and use the higher of the
two values to calculate the 90th percentile lead level.

•	Specifies which samples must be included in the 90th percentile calculation.

•	Requires water systems to provide sampling instructions that do not include recommendations for
aerator cleaning/removal and pre-stagnation flushing prior to sample collection.

•	Requires the use of a wide-mouth bottle that is defined as having a mouth with an inner diameter of at
least 40 millimeters.

Sampling Frequency

The final LCRI does not modify the minimum required number of samples but revises the monitoring schedule:

•	Water systems with lead and/or GRR service lines must conduct standard six-month monitoring
beginning January 1, 2028. Water systems that meet the requirements of the LCRI tap sampling
protocols, such as the lower action level, prior to the compliance date can remain on their existing
sampling schedule.

3. Improving Tap Sampling

EPA 816-F-24-011


-------
•	Water systems can qualify for annual monitoring if they do not exceed the lead action level of 0.010
mg/L or copper action level of 1.3 mg/L for two consecutive six-month tap monitoring periods after
the LCRI compliance date. When conducting annual monitoring, systems must sample for lead at the
standard number of sites and for copper at the reduced number of sites.

•	Water systems can qualify for triennial monitoring at the reduced number of sites for both lead and
copper if they serve:

o 50,000 or fewer people and their 90th percentile levels do not exceed the lead action level of
0.010 mg/L or copper action level of 1.3 mg/L for three consecutive years of sampling.

•	Water systems serving any number of people and their 90th percentile levels do not exceed the lead
practical quantitation limit (PQL) of 0.005 mg/L and copper PQL of 0.65 mg/L for two consecutive tap
monitoring periods.

Sampling Plan

By the start of the first lead and copper tap monitoring period, all water systems must submit a site sample
plan to the State. The plan must include:

•	A pool of tap sampling sites from the highest tier(s) based on the materials of service lines and
connectors in their service line inventory.

•	A list of water quality parameter entry point and distribution sampling locations.

90th Percentile Calculation

The final LCRI updates how systems must calculate the 90th percentile for lead and copper. For most systems,
the LCRI requires water systems to include all samples from sites that meet the prioritized site tiering criteria
and compliance sampling protocol.

The final LCRI simplifies and streamlines the calculation for systems with insufficient Tier 1 and Tier 2 sites:

•	Samples from Tiers 1, 2, and the next highest tier(s) (sufficient to supply enough sites to meet the
minimum number of samples required) are eligible. Only when Tier 3 sites are exhausted can systems
include samples from Tier 4, and only when Tier 4 is exhausted can systems include samples from Tier
5.

•	The 90th percentile level is calculated using the highest results from the eligible samples, equal to the
minimum number of samples required.

4. Lowering the Lead Action Level

The final LCRI streamlines and simplifies the rule requirements by eliminating the lead trigger level of 0.010
mg/L and lowering the lead action level from 0.015 mg/L to 0.010 mg/L. When a water system exceeds the
lead action level, it is required to:

•	Conduct Tier 1 Public Notification within 24 hours to inform the public,

•	Take actions associated with corrosion control treatment (CCT), and

•	Employ public education measures to reduce lead exposure.

EPA 816-F-24-011


-------
5. Strengthening Protections to Reduce Exposure

The final LCRI requires water systems with continually high lead levels to conduct additional outreach to
consumers and make filters certified to reduce lead in drinking water available to all consumers.

Actions When a System Has Multiple Lead Action Level Exceedances

The final LCRI requires:

Systems with three action level exceedances in a rolling five-year period
must conduct public education activities and make filters available to
consumers. After two action level exceedances in five years, water systems
must submit a filter plan to the State within 60 days of the second action
level exceedance. The filter plan:

•	Must describe how the water system will make filters and
replacement cartridges available (e.g., operating distribution facilities, delivering filters when
requested) and address any barriers to consumers obtaining filters.

•	Does not need to be resubmitted unless there are updates or requested by the State.

•	Must be approved by the State within 60 days.

Water systems that exceed the lead action level three times during a rolling five-year period:

•	According to their filter plan, must make available pitcher filters or point-of-use devices certified by an
ANSI accredited certifier to reduce lead to all consumers and make available six months of
replacement cartridges and user instructions.

Must be in place within 60 days after the tap monitoring period in which the water system
exceeded the lead action level for the third time.

Must continue to make replacement cartridges available until the water system meets the criteria
to discontinue described below.

•	Must conduct at least one community outreach activity in addition to the outreach required when a
water system has a single lead action level exceedance.

Can choose from: 1) public meeting; 2) participation in a community event; 3) customer contact via
phone call or voice message, text message, email, or door hanger; 4) social media campaign; or 5)
other State approved method.

o Chosen activity must be conducted within six months of the start of the tap monitoring
period after the most recent lead action level exceedance.

A community outreach activity is required every six months until the water system meets the
criteria to discontinue described below.

•	Can discontinue filter and public education requirements:

When the water system no longer has three lead action levels exceedances in a five-year period, or

At the States discretion if the water system no longer exceeds the lead action level for two
consecutive tap monitoring periods and has taken actions to reduce lead levels (e.g., re-optimized
CCT, completed LSLR).

The first rolling five-year period

ends five years after the LCRI
compliance date followed by
assessments every six months
thereafter.

EPA 816-F-24-011


-------
Improved Accessibility and Information about Lead

The final LCRI:

•	Improves requirements for accessibility of public education and outreach materials to consumers
including renters and for communities with a large proportion of individuals with limited English
proficiency.

•	Requires all public education and outreach materials to include improved and simplified lead health
effects language so that it is easier for consumers to understand. The revised language would begin
with a statement that there is no safe level of lead in drinking water.

•	Adds language to highlight risks to pregnant people, infants (both formula-fed and breastfed), and
young children.

•	Requires additional information in all public education materials about steps that consumers can take
to reduce their exposure to lead in drinking water (e.g., using a filter certified to reduce lead, cleaning
faucet aerators).

Enhanced Service Line-Related Outreach

The final LCRI:

•	Requires additional outreach activities for water systems that do not meet their service line
replacement rate.

•	Requires annual notification to customers and persons served by a lead, GRR, or unknown service line.
Adds instructions for how consumers can notify the water system if they think the material
classification is incorrect and a statement that the consumer can request to have their tap water
sampled for lead.

•	Requires water systems that cause a disturbance to a lead, GRR, or unknown service line to notify
persons at the service connection and provide them with 1) information to reduce their exposure,
including instructions for a flushing procedure to remove particulate lead; and, for some disturbances,
2) a pitcher filter or POU device certified to reduce lead and replacement cartridges to last six months.
Clarifies that service line disturbances could also result from physical action or vibration. Clarifies that
notification must be delivered within 24 hours of the disturbance if the service line was not shut off or
bypassed.

Better Informing Consumers of Tap Sample Results

The final LCRI:

•	Requires all notices of lead and copper tap sampling results to be delivered to consumers served at the
sampled tap within 3 business days after the system learns of the results, regardless of the lead or
copper concentration. Applies to samples from compliance monitoring and supplemental monitoring
(e.g., sampling requested by consumers).

•	Requires water systems to deliver the consumer notice of tap sample results either electronically (e.g.,
email or text message), by phone call or voice message, hand delivery, by mail (postmarked within
three days of the system learning of the results), or by another method approved by the State. Notices
by phone call or voice message must have a written follow-up notice within 30 days of the system
learning of the results.

EPA 816-F-24-011


-------
Improved Public Education Following a Lead Action Level Exceedance

The final LCRI:

•	Requires delivery of public education materials to every service connection address, in addition to the
bill-paying customer, so that consumers such as renters are informed of the exceedance and steps
they can take to reduce their risk of exposure to lead in drinking water.

•	Requires community water systems (CWSs) serving a population greater than 50,000 persons (lowered
from 100,000) to post the public education materials online to increase consumer accessibility.

•	Improves the timeframe of public education after a lead action level exceedance by requiring water
systems to conduct public education activities within 60 days after the end of every tap sampling
period until the system no longer exceeds the lead action level.

•	Expands public education requirements for water systems with LSLs to systems with lead, GRR, and/or
unknown service lines. Includes specific content requirements.

•	Retains the 2021 public notification requirement for water systems to provide 24-hour Tier 1 public
notification after exceeding the lead action level of 0.015 mg/L, starting October 16, 2024. Beginning
on the LCRI compliance date, Tier 1 public notification is triggered by the revised lead action level of
0.010 mg/L.

Revised Consumer Confidence Report Information

The final LCRI:

•	Revises the Consumer Confidence Report Rule requirements to:

Include an updated informational statement about lead to improve risk communication, updated lead
health effects language, information about the requirement for systems to sample in schools and child
care facilities, and how to access the water system's service line replacement plan.

Additional Resources

EPA has developed additional fact sheets and frequently asked questions on the final LCRI that are available on
EPA's website at https://www.epa.gov/ground-water-and-drinking-water/lead-and-copper-rule-
improvements.

Disclaimer: This document is being provided for informational purposes only to assist members of the public, States, Tribes, and/or public water systems
in understanding the Lead and Copper Rule Improvements (LCRI). It includes descriptions of regulatory requirements. In the event that there are any
differences, conflicts, or errors between this document and the LCRI, States, Tribes, and/or public water systems should refer to the LCRI. This document
does not impose any legally binding requirements on the EPA, States, Tribes, or the regulated community. Further, this document does not confer legal
rights or impose legal obligations on any member of the public. In the event of a conflict between the discussion in this fact sheet and any statute or
promulgated regulation, the statute and any promulgated regulations are controlling.

EPA 816-F-24-011


-------