EPA Inspection Report - Page 1 of 3

v/CrM

Region 6 - Enforcement & Compliance Assurance Division
INSPECTION REPORT

Inspection Date(s):

04/23/2022

Media Program:

Air

Regulatory Program(s)

Title V

Company Name:

Nucor Steel Louisiana LLC

Facility Name:

Direct Reduced Iron Facility

Facility Physical Location:

9101 HWY3125

(city, state, zip code)

Convent, LA 70723

Mailing address:

9101 HWY3125

(city, state, zip code)

Convent, LA 70723

County/Parish:

St. James

Facility Phone Number

225-331-4000



Facility Contact:

Marshall Crawford

Environmental Manager

Marshall.Crawford@Nucor.com

FRS Number:

110056317677

Identification/Permit Number:

3086-V9

Media Identifier Number:

22-09300281

NAICS:

331110

SIC:

3312

Personnel participating in inspection:

Sarah Frey

EPA ECD-AT

Inspector

Richard Helmich

EPA NEIC

Chemist

David Mahoney

EPA NEIC

Technical Coordinator

Ali Gitipour

EPAORD

Engineer

Sophia Ong

LDEQ

Environmental Scientist

Marshall Crawford

Nucor Steel

Environmental Manager

Erika Caruso

Nucor Steel

Environmental Engineer

Lane Grant

Nucor Steel

Technical Manager



EPA Lead Inspector
Signature/Date



6/24/2022

//

Sarah Frey

Date

Supervisor
Signature/Date

1 A M CC 1 C ATU CDC Digitally signed by JAMES LEATHERS

JMIVIlj LLn 1 nLnj Date: 2022.07.15 16:30:30 -05'00'



James Leathers

Date

6ENFORM-019-R8.2 (02/12/2020)

1


-------
EPA Inspection Report - Page 2 of 3

Nucor Steel Louisiana LLC / Direct Reduced Iron Facility

Inspection Date 4/23/2022

Section I - INTRODUCTION
PURPOSE OF THE INSPECTION

EPA inspector Sarah Frey, accompanied by Richard Helmich (National Enforcement Investigations
Center, "NEIC"), David Mahoney (NEIC), and Ali Gitipour (Office of Research and Development), arrived
at Nucor Steel Louisiana LLC - Direct Reduced Iron Facility at 8:35 am on April 23, 2022 for an
announced inspection. Notification of the inspection occurred on Friday, April 22, 2022. We were
accompanied by Louisiana Department of Environmental Quality inspector Sophia Ong. We checked in
at the security gate and then met with Marshall Crawford/Environmental Manager, Lane
Grant/Technical Manager, and Erika Caruso/Environmental Engineer. Credentials were presented to Mr.
Crawford, and we informed him that this was an EPA inspection to evaluate potential sources of excess
emissions using EPA's Geospatial Measurement of Air Pollution ("GMAP") vehicle and evaluate
compliance with the facility's Title V Permit and the Clean Air Act. The scope of the inspection is a partial
compliance evaluation ("PCE"). This inspection occurred as part of the Administrator's Multi-Scale
Monitoring Project called the Pollution Accountability Team (PAT).

FACILITY DESCRIPTION

The Nucor Steel Louisiana LLC - Direct Reduced Iron Facility processes iron oxide pellets into iron to be
shipped to offsite steel mills. The facility began operations in 2013 and operates under Permit Number
3086-V9 issued June 23, 2020.

Section II - OBSERVATIONS

The NEIC GMAP was driven by Mr. Mahoney and the instruments were operated by Mr. Helmich and
Mr. Gitipour. A facility representative, Ms. Caruso, was present in the GMAP. Inspectors Dr. Frey and
Ms. Ong were escorted in a facility vehicle by Mr. Crawford. Ms. Caruso led the GMAP throughout and
around the facility, where air pollution data was collected and recorded. A full report from the GMAP
will be issued by NEIC at a later date.

When driving past the ore yard, low concentrations of sulfur dioxide were detected above
background/baseline ambient concentrations. Downwind of the cooling tower, concentrations of
methane were detected above background. No photos or videos were taken during the inspection.

Section III-AREAS OF CONCERN

Richard Helmich and Sarah Frey conducted a closing conference at Nucor Steel Louisiana LLC - Direct
Reduced Iron Facility at 10:10 am on April 23, 2022 for the inspection. Davie Lartigue, Operations
Manager, Mr. Crawford, Ms Caruso, and Mr. Grant were in attendance. During the closing conference,
Mr. Helmich reviewed the emissions detected by the GMAP during the inspection. We observed no
areas of concern at the time of the inspection and departed at 10:30 am.

2


-------
EPA Inspection Report - Page 3 of 3

Nucor Steel Louisiana LLC / Direct Reduced Iron Facility

Inspection Date 4/23/2022

Section IV-FOLLOW UP

No additional information was received by EPA after exiting the Facility on April 23, 2022.

Section V - LIST OF APPENDICES

No appendices.

3


-------