FINDINGS FOR CONSIDERATION IN THE MANAGEMENT OF

CONGRESSIONAL EARMARKS

Drinking water facility. (EPA photo)

Purpose:

We performed this review to highlight
prior audit findings about the
U.S. Environmental Protection Agency's
administration and oversight of
congressional earmarks to inform the
Agency's management of earmarks in
the fiscal year 2022 budget. The project
number for this review is OA-FY22-Q147.

This review supports the following
EPA mission-related efforts:

•	Compliance with the law.

•	Operating efficiently and effectively.

This review addresses these top EPA

management challenges:

•	Managing increased investment in
infrastructure.

•	Managing business operations and
resources.

Report Contributors:

Michael D. Davis
Margaux Hoover
Kristin Pope
Wendy Wierzbicki

Address inquiries to our public affairs
office at (202) 566-2391 or

OIG WEBCOMMENTS@epa.aov.

Full list of EPA OIG reports.

Overview

In the ten years prior to 2022, the U.S. Environmental Protection Agency did
not receive any congressional earmarks, which are appropriated funds
designated by Congress to be spent on a particular project. The EPA's fiscal
year 2022 appropriations included almost $860 million in earmarks. The EPA
Office of Inspector General initiated this review to highlight prior audit findings
about the EPA's administration and oversight of congressional earmarks, also
known as congressionally directed spending, to inform the Agency's
management of earmarks in the fiscal year 2022 budget. Since we initiated our
review, the EPA received additional earmarks of over $1.5 billion in the fiscal
year 2023 appropriations.

This project is not an audit or evaluation but a review of prior OIG reports and
a summary of our findings. The findings highlighted in this report may help the
Agency administer and oversee current and future congressional earmarks.

Background

From 2006 through 2015, the EPA OIG reviewed the EPA's management and
oversight of earmarks in four audit reports and made recommendations for
improvement in three of those four audit reports. In 2011, Congress imposed a
moratorium on earmarks, which it subsequently lifted in 2021.

In the fiscal year 2022 consolidated appropriations law, Congress directed the
EPA to administer and oversee 491 earmarks totaling $859.3 million, as shown
in Figure 1 on the next page. Ninety-eight percent of these earmarks were for
water, wastewater, and storm water infrastructure, and for water quality
protection projects. The remaining earmarks were for feasibility studies, public
health and environmental research, wastewater infrastructure assessment, an
emission study, and remediation and construction projects. Forty-two states
and one U.S. territory received EPA earmarks. The fiscal year 2022
consolidated appropriations law required earmark recipients to contribute no
less than 20 percent of the cost of the project or be approved for a waiver.

Responsible Offices

The Office of Mission Support is one of the offices responsible for the Agency's
monitoring of congressional earmarks. The Office of Grants and Debarment,
which is within the Office of Mission Support, monitors the Agency's grant
awards. This includes grants funded by earmarks, which are generally

23-N-0014

1


-------
Figure 1: Fiscal year 2022
EPA earmarks

•	491 earmarked projects

•	$859.3 million

•	98 percent for water and
wastewater infrastructure
projects

•	For projects in all ten EPA
regions, including 42 states
and one U.S. territory

EPA earmarks (fiscal
year 2022
appropriations)

Source: OIG summary of the EPA's fiscal
year 2022 appropriations. (EPA OIG image)

Figure 2: EPA OIG reports reviewed

Year
issued

Report number and title

2006

2006-P-00037.
EPA Needs to Emphasize
Management of Earmark
Grants

2007

2007-P-00024.
Number of and Cost to
Award and Manage EPA
Earmark Grants, and the
Grants' Impact on the
Agency's Mission

2010

10-P-0081.

EPA Needs Procedures to
Address Delayed Earmark
Projects

2015

15-P-0299.

Unused Earmark Funds for

Water Projects Totaling
$6.2 Million Could Be Put to
Better Use

Source: EPA OIG image.

disbursed like other grants. The Office of Grants and Debarment provides
cradle-to-grave administrative management of all headquarters-administered
grants, loans, cooperative agreements, fellowships, interagency agreements,
and the Agency's Suspension and Debarment program. The EPA regional
offices are responsible for awarding grants and monitoring the projects
receiving these funds.

Previously, the Office of Wastewater Management under the Office of Water
monitored, oversaw, and reported on water infrastructure grants funded by
congressional earmarks. The Office of Wastewater Management also worked
with the regional offices to manage these grants and was responsible for
implementing some of the OIG recommendations issued in two of the four
prior OIG audit reports that we discuss in this report. The Office of Wastewater
Management supports the Clean Water Act by promoting effective and
responsible water use, wastewater treatment, disposal and management, and
by encouraging the protection and restoration of watersheds.

Scope and Methodolo

As shown in Figure 2, we reviewed four OIG reports related to the EPA's
management of congressional earmarks. The reports cover related EPA
activities from 1998 through 2015, OIG-identified deficiencies, and OIG
recommendations for improvement. Appendix A details our scope and
methodology.

What We Found

From our review of prior OIG reports, we identified three areas for
improvement that the EPA should consider as it administers and oversees
congressional earmarks:

•	Ensure grant work plans adhere to EPA policies and align with strategic
goals.

•	Ensure policies and procedures are in place to address the timely
award and use of earmarked funds.

•	Ensure compliance with grant terms and conditions.

In the following sections, we provide related examples from prior audit
findings.

Ensure Grant Work Plans Adhere to EPA Policies and Align
with Strategic Goals

In two reports, the OIG identified challenges related to work plans. A work
plan identifies how and when a grantee will use its funds and is the basis for
the EPA's grantee performance management and evaluation.

EPA OIG Report No. 2006-P-00037, EPA Needs to Emphasize
Management of Earmark Grants

In the 2006 report, the OIG reviewed 17 prior audit and investigation work
products from 1998 to 2006 to assess whether the EPA should take
additional actions to improve the overall management of earmarked grants.
The OIG found grants with incomplete work plans in four of 17 audits and
investigations. These included grants with work plans that did not

23-N-0014

2


-------
sufficiently outline the work needed to accomplish the project objectives.
Factors that contributed to the EPA's approval of the incomplete work plans
included EPA project officers not performing required duties, such as
conducting cost reviews to determine whether costs were reasonable and
assessing the technical merits of the project.

EPA OIG Report No. 2007-P-00024, Number of and Cost to
Award and Manage EPA Earmark Grants, and the Grants'
Impact on the Agency's Mission

In the 2007 report, the OIG reviewed 86 work plans from 444 earmark
grants issued in 2005 and 2006. The OIG determined that 95 percent of the
earmark grant projects promote the EPA's mission. However, four projects,
totaling $1.29 million in EPA grant funds, did not demonstrate how they
would contribute to the Agency's strategic plan, mission, and goals. For
example, one of the four work plans did not identify specific environmental
problems the grant funds would address. In response to the OIG finding, the
EPA worked with the local government to improve the quality of the work
plan.

Ensure Policies and Procedures are in Place to Address the
Timely Award and Use of Earmarked Funds

In two reports, the OIG identified concerns related to the timely award and use
of earmarked funds.

EPA OIG Report No. 10-P-0081, EPA Needs Procedures to
Address Delayed Earmark Projects

In the 2010 report, the OIG noted that the EPA needed a policy that
specified time limits and procedures for addressing earmarks that remained
unobligated or steps to take when projects were delayed. As shown in
Figure 3, this resulted in unobligated and unspent funds, including:

•	$28.8 million in earmarked funds that were unobligated five years
after congressional appropriation.

•	$122.6 million in earmarked funds that remained unspent five years
after award.

The 2010 report noted that funds were not obligated because, frequently,
earmark recipients either could not provide the matching funds required for
the grant or the projects were complex and required extensive planning. At
the time, the OIG determined that the EPA did not have a policy that clearly
identified when the EPA regions should take action on unobligated
earmarked funds. The OIG also identified instances in which some
designated recipients did not apply for the funds and the funds could have
been considered for other purposes. Of the 22 unobligated earmarks
reviewed in the 2010 report, the EPA only took steps to put the funds to
better use in two cases. The OIG concluded that the EPA needed a policy
outlining what actions EPA staff could take when communities were not able
to start their projects in a timely manner.

The 2010 report also noted that millions of dollars of grant funds were not
spent because of project delays. The OIG identified the following factors that

23-N-0014

3


-------
Figure 4: 2015 OIG report finding:
Earmarked funds that could have
been put to better use*

*Funds were from Regions 4 and 6
Source: EPA OIG image.

Figure 5: 2015 OIG report finding:
Explanations for delayed grant
progression

Land Purchase
Delays

Matching
Funds Issues

Hurricane
Disasters

Congressional
Technical
Corrections

Environmental
Reviews

Note: As of 2015, funds were awarded in
fiscal year 2009 and earlier.

Source: EPA OIG image.

contributed to delayed projects: recipient changes to the original work plans
and problems complying with non-EPA regulatory requirements. The OIG
determined that at the time, the EPA had limited guidance on how to deal
with delays in spending earmarked grant funds, and lacked the policies and
procedures needed to provide reasonable assurance that funds would be
spent in a timely manner. The Agency agreed with all the recommendations
in the 2010 report, which resulted in the creation of the Management Plan
for the Timely Award and Completion of Special Appropriations Act Project
Grants in October 2011. Following the issuance of the management plan,
unobligated funds and unliquidated obligations significantly declined in both
number and dollar amount. For example, the number of unobligated grants
decreased from 866 totaling $375 million in 2010, to 76 totaling
$32.2 million in 2015.

EPA OIG Report No. 15-P-0299, Unused Earmark Funds for
Water Projects Totaling $6.2 Million Could Be Put to Better Use

In the 2015 report, the OIG noted that 76 grants worth $32.2 million
remained unobligated and all missed the programmatic goal to award grants
within three years of appropriation. The report focused on Regions 4 and 6,
which had 41 of the 76 grants totaling $14 million. These regions had the
largest amount of unliquidated obligations and the greatest number of
unobligated funds. As outlined in Figure 4, these funds included $3.4 million
that remained unobligated and missed the programmatic goal to award
grants within three years of appropriation.

The OIG found that, per the management plan, regions classified
unobligated funds as no-progress when they did not receive a grant
application—or received an unacceptable grant application—and an
unreasonable amount of time had passed. Once classified as no-progress,
the regions could start the process to return the funds to the
U.S. Department of the Treasury. Since only Congress can rescind or reassign
earmarked funds, the regions have the option to return funds associated
with no-progress grants to EPA headquarters and request congressional
rescission of the earmarked funds.

The OIG found that taking actions on unobligated earmarks was not a
priority for the regions at the time. Staff hesitated to send no-progress
letters to recipients and instead waited for recipients to say funds were not
needed. The OIG determined that, had the regions been more proactive in
the management of funds and sent no-progress letters to recipients,
$3.4 million in unobligated funds could have been—with congressional
rescission—returned to the Treasury Department and put to better use. The
OIG recommended the development and implementation of a plan to
expedite the reduction of unobligated funds.

Further, the OIG found that 12 grants totaling $6.68 million had been
obligated more than five years prior but had no financial activity. These
grants were from Regions 2, 4, 6, 8, and 9. The OIG reviewed six of the
12 grants, totaling $4.1 million, from Regions 4 and 6 to determine whether
the grants could have been identified as no-progress grants. The regions
were considering identifying two of the six grants as no-progress. As shown
in Figure 5, the other four grants were delayed for various reasons.

23-N-0014

4


-------
The OIG found that if a recipient had indicated that it was interested in a
grant, Regions 4 and 6 hesitated to identify the grant as no-progress. The
regions would consider the grant as making progress if the recipient had
communicated with the region, identified a project, or developed a plan,
even if there was no financial activity. Therefore, the OIG determined that
the Region 4 and Region 6 standards for when a grant was making
reasonable or sufficient progress allowed grant funds to remain
unliquidated. As a result, the OIG determined that nearly $2.8 million could
have been put to better use if grants that had no financial activity were
deobligated and—with congressional rescission—returned to the
U.S. Treasury, as shown in Figure 4. In the 2015 report, the OIG
recommended that the EPA develop guidance for, and communicate
guidance to, the EPA regions to clarify how to determine whether a grant is
making sufficient progress and the time period for a grant to have no
financial activity before it is identified as no-progress.

Ensure Compliance with Grant Terms and Conditions

EPA OIG Report No. 2006-P-00037, EPA Needs to Emphasize
Management of Earmark Grants

In the 2006 report, which covered audits and investigations from 1998
through 2006, the OIG identified several instances in which grant recipients
did not comply with grant terms and conditions. The OIG concluded that the
EPA's insufficient oversight of earmark grants contributed to grant recipient
mismanagement. This resulted in the OIG questioning nearly $73 million in
federal grant funding. Further, the report indicated that Agency policies did
not give specific steps for EPA staff to address concerns with award and
project oversight. The OIG found that:

•	In four of 17 audits and investigations, there was noncompliance with
applicable laws and regulations. For example, one grant recipient did
not meet federal matching requirements and another improperly used
grants and earmarked funds.

•	In five of 17 audits and investigations, grant recipients were not in
compliance with their terms and conditions. The OIG gave examples of
noncompliance issues from two grantees. They did not:

o Competitively procure contractual services.

o Require cost or pricing analyses.

o Separately identify and accumulate the costs for all direct activities.

o Account for program income generated by the activities funded by
the EPA agreements.

o Maintain an adequate labor distribution system.

o Submit the project's final report.

•	In ten of 17 audits and investigations, recipients did not properly
account for federal funds. The OIG noted issues with improper billing,
incomplete accounting records, and improper federal reimbursements
to the recipients.


-------
• In four of the 17 audits and investigations, there were conflicts of
interest between the grantee and the subcontracted entity. For
example, after the grant award, an officer of the organization
participated in the selection, award, and administration of a
noncompetitive contract to a company in which a relative had a
financial or other interest.

Conclusions

In the fiscal years 2022 and 2023 consolidated appropriations law, Congress
directed the EPA to administer and oversee 1,224 earmarks totaling nearly
$2.36 billion. As the Agency awards these and future earmarks, it should
consider the findings identified in prior EPA OIG reports regarding earmarks
management to ensure that it efficiently and effectively administers earmarks,
meets the earmarks' intended purpose, improves the environment, protects
taxpayer dollars, and ensures public trust. Specifically, the Agency should
ensure grant work plans adhere to EPA policies and align with strategic goals,
ensure policies and procedures are in place to address the timely award and
use of earmarked funds, and ensure grantee compliance with grant terms and
conditions.

23-N-0014

6


-------
Appendix A

Scope and Methodology

We conducted this project from October 2022 to March 2023. We did not follow generally accepted government
auditing standards or the Council of the Inspectors General on Integrity and Efficiency's Quality Standards for Inspection
and Evaluation. However, we did follow the OIG's quality control procedures for ensuring that the information in this
report is accurate and supported. Additionally, the Quality Standards for Federal Offices of Inspector General require
that our work adheres to the highest ethical principles of integrity, objectivity, confidentiality, independence, and
professional judgement, and we adhered to these principles in performing our work.

To answer our objective, we reviewed four OIG audit reports related to the EPA's management of congressional
earmarks. The reports were issued from fiscal year 2006 through fiscal year 2015, as shown in Figure 2, and covered
related EPA activities from 1998 through 2015. We reviewed the findings and recommendations in the four reports. We
also reviewed the status of the issued recommendations in the Agency's audit tracking system. We summarized the
reported findings and areas for improvement. We also collected earmark-specific data from the 2022 Consolidated
Appropriations Act and the December 2022 Congressional Record (Senate) for the FY 2023 earmarks.

To obtain an understanding of the applicable criteria for grant management and oversight, we reviewed the following:

•	Office of Management and Budget Circular No. A-123, Management's Responsibility for Enterprise Risk
Management and Internal Control, dated July 15, 2016.

•	U.S. Government Accountability Office's Standards for Internal Control in the Federal Government, dated
September 2014.

23-N-0014

7


-------
Distribution

Appendix B

The Administrator

Deputy Administrator

Chief of Staff, Office of the Administrator

Deputy Chief of Staff, Office of the Administrator

Agency Follow-Up Official (the CFO)

Assistant Administrator for Mission Support

Principal Deputy Assistant Administrator for Mission Support

Agency Follow-Up Coordinator

General Counsel

Associate Administrator for Congressional and Intergovernmental Relations

Associate Administrator for Public Affairs

Deputy Assistant Administrator for Mission Support

Deputy Assistant Administrator for Administration and Resources Management, Office of Mission Support

Director, Office of Continuous Improvement, Office of the Chief Financial Officer

Director, Office of Resources and Business Operations, Office of Mission Support

Director, Office of Grants and Debarment, Office of Mission Support

Audit Follow-Up Coordinator, Office of the Administrator

Audit Follow-Up Coordinator, Office of Mission Support

Audit Liaison, Office of Grants and Debarment, Office of Mission Support

Audit Follow-Up Coordinators, Regions 1-10

23-N-0014

8


-------