Construction Quality Assurance Plan
Texarkana Wood Preserving Company
Bowie County, Texas

Remedial Action Contract 2
Contract: EP-W-06-004
Task Order: 0058-RDRD-0691

Preparedfor:

U.S. Environmental Protection Agency
Region 6
1445 Ross Avenue
Dallas, Texas 75202-2733

Prepared by :

EA Engineering, Science, and Technology
405 S. Highway 121
Building C, Suite 100
Lewisville, Texas 75067
(972) 315-3922

September 2010
Revision: 00
EA Project 14342.58

000005

lllllllllllllllllllllllllllllllllllllllllllll

9176158


-------
EA Project No.: 14342.58
Revision: 00
Page i of iii

EA Engineering, Science, and Technology, Inc.	September 2010

TABLE OF CONTENTS

Page

1.	GENERAL	 1

1.1.	INTRODUCTION	1

1.2.	DEFINITIONS	2

1.3.	CQA ORGANIZATION PRE-CONSTRUCTION SUBMITTAL REQUIREMENTS 3

1.4.	RESPONSIBILITY AND AUTHORITY	3

1.5.	REFERENCES	4

1.6.	SUBMITTAL REVIEW	5

1.7.	MEETINGS	5

1.7.1.	Pre-Construction Meeting	5

1.7.2.	Weekly Progress Meetings	5

1.7.3.	Contractor Coordination Meetings	5

1.7.4.	Safety Meetings	5

1.8.	CQA SAMPLES	5

1.8.1.	CQA Sample Collection	5

1.8.2.	CQA Sample Testing	6

1.8.3.	Testing Frequency	6

1.8.4.	CQA Test Results	6

2.	SOILS	6

2.1.	GENERAL	6

2.1.1.	CQA Personnel	6

2.1.2.	Equipment	6

2.1.3.	Weather Conditions	7

2.2.	EXECUTION	7

2.2.1.	General	7

2.2.2.	Soils Placement	8

2.2.3.	Compaction	8

2.2.4.	Classification	8

2.2.5.	Tests	8

2.2.6.	Protection	9

2.2.7.	Repairs	9

2.2.8.	Testing of Repaired Areas	9

2.2.9.	Temporary Erosion Control	9

2.2.10.	Maintenance	 10

2.3.	Geotextile	10

3.	PERMANENT EROSION CONTROL	 10

3.1.	GENERAL	10

3.1.1. Delivery, Storage, and Handling	11

3.2.	MATERIAL PROPERTIES	 1 1

3.2.1.	Quality Control Testing	11

3.2.2.	Quality Assurance Testing	11

3.3.	EXECUTION	11

000006


-------
EA Project No.: 14342.58
Revision: 00
Page ii of iii

EA Engineering, Science, and Technology, Inc.	September 2010

3.3.1. Riprap Placement	11

3.4. CHANNELS	12

4.	MONITORING WELL ABANDONMENT	 12

4.1.	GENERAL	 12

4.2.	SUBMITTALS	12

4.3.	EXECUTION	12

5.	MONITORING WELL INSTALLATION	 12

5.1.	GENERAL	 12

5.2.	SUBMITTALS	13

5.3.	EXECUTION	13

6.	CONSTRUCTION QUALITY ASSURANCE DOCUMENTATION	14

6.1.	GENERAL	 14

6.2.	CQA ENGINEER'S DAILY REPORT	14

6.3.	FIELD MOISTURE AND DENSITY TEST RESULT DATA SHEET	15

6.4.	TEST REPORT	15

6.5.	SURVEY RECORDS	15

6.6.	PHOTOGRAPHIC DOCUMENTATION	15

6.7.	FINAL REPORT	15

7.	CONTAMINATED MATERIALS	 16

LIST OF ATTACHMENTS

ATTACHMENT A Quality Assurance Report Daily Log of Construction

ACRONYMS AND ABBREVIATIONS

CM	Construction Manager

CQA	Construction Quality Assurance

CQAP	Construction Quality Assurance Plan

CQC	Construction Quality Control

EA	EA Engineering, Science and Technology, Inc.

EPA	U.S. Environmental Protection Agency

ft	feet

PCP	Pentachlorophenol

QA	Quality Assurance

RA	Remedial Action

SWPPP	Storm Water Pollution Prevention Plan

TCEQ	Texas Commission on Environmental Quality

000007


-------
EA Project No.: 14342.58
Revision: 00
Page 1 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

1. GENERAL

1.1. INTRODUCTION

EA Engineering, Science, and Technology, Inc., (EA) has prepared this Construction Quality
Assurance Plan (CQAP) for the U. S. Environmental Protection Agency (EPA) to describe the
Quality Assurance (QA) tests necessary to ensure the final product meets the design
specifications at the Texarkana Wood Preserving Company Superfund Site (EPA Identification
No. TXD008056152) located in Bowie County, Texas.

The Site is located at 1001 Lubbock Street in Bowie County, Texas near Texarkana, Texas; the
site coordinates are 33°24'29" north latitude and 94°3' 12" west longitude (Figure 1). The Site
spans approximately 26 acres within the 100-year floodplain. It is transected by Lubbock Street,
which splits the Site into eastern and western portions. The Site is bounded to the west by the
Union Pacific (formerly Texas and Pacific) Railroad right-of-way. Days Creek, an interstate
tributary of the Sulphur River, is located approximately 500 feet (ft) east of the Site and flows to
the south-southwest; the Arkansas state line is approximately 2,500 ft east of Days Creek.

Vacant land is located north, east, and south of the Site and the area surrounding the Site is
primarily undeveloped or commercial.

According to past investigations, the Site had been used for lumber-related activities since the
early 1900s. However, in the late 1940s or early 1950s, wood preserving operations were
initiated to treat wood against bacterial and insect damage. Initially, wood preserving operations
utilizing pentachlorophenol (PCP) and creosote occurred on the southwestern portion of the Site.
Facilities included a process building, a pressurized retort, process waste, treatment ponds, and
drying areas for preserved wood. Two ponds (i.e., Ponds 4 and 5) were later added on the
southeast side of Lubbock Street to serve as wastewater evaporation ponds (see Figure 2).

In the latter part of 1971 or early part of 1972, creosoting operations were moved to improved
facilities on the northwest portion of the Site. These facilities included improved wastewater
treatment facilities, which were surrounded by concrete dikes designed to contain potential
spillage and runoff. Following treatment, wastewater from the creosote and PCP operations was
released into a series of three evaporation ponds (i.e., Ponds 1 through 3) on the northeast part of
the Site. The treated wood was allowed to dry in open areas to the south of the treatment
operations and Ponds 1 through 3. The Site ceased operations and closed in August 1984.

This report is a plan for construction quality assurance for the remediation of the Site in
accordance with the treatment remedy put forth in the EPA Record of Decision. This CQAP
provides the Government with a professional responsible for the management and certification of
all construction quality assurance activities on the site, in order to verify compliance with design
specifications and federal regulations.

The Construction Quality Assurance (CQA) Engineer shall be independent from the remedial
construction contractor and the contractor's quality control program. The CQA Engineer shall be
responsible for CQA activities associated with construction of the consolidation area, stabilized

000008


-------
EA Project No.: 14342.58
Revision: 00
Page 2 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

source areas, and related features and shall verify compliance with the specification sections
listed below. The CQA Engineer shall review the following specification sections in preparation
for CQA activities:

01

10

00

Summary of Work

01

20

00

Price and Payment Procedures

01

25

00

Substitution Procedures

01

33

00

Submittal Procedures

01

35

29.13 Health, Safety & Emergency

01

40

00

Quality Requirements

01

50

00

Temporary Facilities and Controls

01

57

23

Temporary Storm Water Pollution Control

01

70

00

Execution and Closeout Requirements

02

55

00

Solidification-Stabilization of Contaminated Material

02

61

13

Excavation and Handling of Contaminated Material

31

10

00

Site Clearing

31

23

16

Excavation of Non-Contaminated Material

31

23

23

Fill

31

25

13

Erosion Controls

32

92

19

Seeding

33

24

00

Monitoring Well Installation

33

29

00

Monitoring Well Abandonment

1.2. DEFINITIONS

The definitions listed in the following paragraphs are relevant to the design, construction and

CQA of the remedial action (RA).

(1)	Construction Quality Assurance: CQA includes observations, audits, and evaluations
of materials and workmanship to determine and document the quality of the
constructed facility. CQA is performed by a party independent from the remediation
contractor.

(2)	Construction Manager (CM): The CM is responsible for the construction activities
during the RA. Qualifications for this role include a minimum of 4 years of
experience supervising field work and construction activities, including field
investigation activities and the installation, operation, and maintenance of remedial
systems.

(3)	Construction Quality Assurance Engineer: The CQA Engineer shall be a professional
engineer and shall have a minimum of 3 years of experience in design and construction of
earthwork and waste remediation projects. The CQA Engineer shall be responsible for
carrying out the tasks outlined in the CQAP. The CQA Engineer shall be responsible for
hiring CQA personnel to assist in CQA testing, reporting, verification, and
documentation. For the purposes of this document, the term CQA Engineer shall refer to

000009


-------
EA Project No.: 14342.58
Revision: 00
Page 3 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

the CQA Engineer and/or authorized CQA Observation Personnel. Construction Quality
Control (CQC) material testing and documentation will be carried out by the CQA
Engineer's third party laboratory. The CQA Engineer shall oversee and verify that CQC
activities were completed in accordance with the Specifications. The CQA Engineer
shall take independent tests to verify CQC results as described in this CQAP.

(4)	Construction Quality Assurance Observer Personnel: The CQA inspection personnel
shall be under the supervision of the CQA Engineer and shall assist in CQA testing and
observation. These personnel shall have experience as a CQA observer and National
Institute of Certifications in Engineering Technologies certified or shall be individuals with
an engineering (or related field) degree from an accredited university, for the areas in which
they will be performing CQA inspections.

(5)	Construction Quality Assurance Testing Laboratory: The CQA testing laboratory
shall perform CQA conformance tests required by the specifications and CQAP. The
CQA testing laboratory shall be hired by the Government or the CQA Engineer. The
laboratory shall have provided CQA testing of soils used for the construction of
consolidation areas for at least five completed projects.

1.3.	CQA ORGANIZATION PRE-CONSTRUCTION SUBMITTAL
REQUIREMENTS

The CQA organization shall submit a CQA qualifications report listing the names of CQA
personnel which will be onsite and the duties of each. The CQA qualifications report shall show
the lines of authority for the onsite CQA personnel. A resume for the CQA Engineer and each
CQA observer shall also be included in the report. The report shall be submitted for approval a
minimum of 28 days prior to the start of CQA duties. If new CQA personnel are brought
onsite after the start of construction, a resume for each shall be submitted to EPA for approval a
minimum of 7 days prior to the new personnel performing CQA duties.

1.4.	RESPONSIBILITY AND AUTHORITY

The general responsibilities of the CQA Engineer are listed below. Subsequent sections of
this document provide specific CQA requirements during the construction of various
components of the consolidation area.

(1)	Review applicable plans and specifications.

(2)	Review the CQAP.

(3)	Review approved changes to the drawings and specifications.

(4)	Review and recommend approval or disapproval of site-specific documentation,
including contractor submittals, manufacturer's information, installer's
information, and referenced standards.

000010


-------
EA Project No.: 14342.58
Revision: 00
Page 4 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

(5)	Verify construction is performed in accordance with the drawings and specifications.
Observers shall be assigned to every major construction activity being performed. A
minimum of one CQA Engineer or CQA Engineer delegate shall be onsite at all
times during the RA.

(6)	Attend required meetings.

(7)	Educate onsite CQA observers about specific CQA requirements and procedures.

(8)	Assign CQA observers to observe all activities requiring monitoring.

(9)	Confirm that calibrations of CQC and CQA testing equipment are performed and recorded.

(10)	Confirm that CQC and CQA tests are performed and recorded as required and that the results
meet specified requirements.

(11)	Review contractor personnel qualifications to verify conformance with the specifications.

(12)	Review warranty submittals to verify that they comply with the specified warranty
requirements.

(13)	Verify that the contractor is following the CQC requirements of the Specifications.

(14)	Review required submittals and recommend rejection or approval.

(15)	Report any unapproved deviations from the CQAP.

(16)	Note any activities that could result in damage to installed consolidation area
components.

(17)	Prepare and maintain required reports, files, and logs.

(18)	Oversee the collection, marking, packaging, and shipping of CQA conformance samples.

(19)	Review as-built surveys and drawings.

1.5. REFERENCES

The following references were used in preparation of this document:

(1)	Quality Assurance Representatives Guide, EP 415-1-161 Volume 5, United States Army
Corps of Engineers, July 1997.

(2)	Quality Assurance and Quality Control for Waste Containment Facilities, Technical
Guidance, EPA/600/R-93/182, United States Environmental Protection Agency,
September, 1995.

000011


-------
EA Project No.: 14342.58
Revision: 00
Page 5 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

1.6.	SUBMITTAL REVIEW

The CQA Engineer shall review all submittals required by the specifications to ensure that they
comply with the specified requirements. The CQA Engineer shall also review as-built surveys and
drawings to ensure the drawings accurately reflect the construction and that the construction is
in compliance with the drawings and specifications.

1.7.	MEETINGS

The following paragraphs summarize the meetings the CQA Engineer shall attend prior to and
during construction.

1.7.1.	Pre-Construction Meeting

A pre-construction meeting shall be held at the site prior to the beginning of construction. The
meeting shall be attended by the CQA engineer, CQA inspection personnel, CM, general
contractor, and other concerned parties. Specific topics for the preconstruction meeting shall
include the drawings and specifications, the CQAP, areas of confusion, safety, CQC
documentation, and the responsibilities of each party.

1.7.2.	Weekly Progress Meetings

Weekly progress meetings shall be held between the CQA Engineer, CQA inspection personnel,
CM, general contractor, appropriate subcontractors, and other concerned parties. The purpose of
these meetings is to discuss current progress, planned activities for the next week, issues requiring
resolution, and any revisions to the work. The CQA Engineer shall report any deficiencies noted
during the previous week.

1.7.3.	Contractor Coordination Meetings

The CQA Engineer and appropriate CQA inspection personnel shall attend coordination meetings
with each major subcontractor prior to the start of construction activities. Specific topics for the
coordination meetings shall include the plans and specifications, the CQAP, areas of confusion,
safety, and the responsibilities of each party.

1.7.4.	Safety Meetings

The CQA Engineer and CQA inspection personnel shall attend required safety meetings.

1.8.	CQA SAMPLES
1.8.1. CQA Sample Collection

CQA samples shall be collected at locations designated by the CQA Engineer, if determined
necessary. The CQA Engineer or his delegate shall be present during collection of CQA samples
and ensure they are collected, cut, labeled, and packaged in accordance with the specifications

000012


-------
EA Project No.: 14342.58
Revision: 00
Page 6 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

and/or CQAP. The CQA Engineer shall ensure samples are labeled with the following: sample
number, date sampled, project name, soil borrow source, and intended use of soil. The location,
sample number, and purpose of the samples shall be noted on the daily report.

1.8.2.	CQA Sample Testing

The CQA Engineer shall ensure samples are submitted to the CQA laboratory for testing.
Subsequent sections of the CQAP describe the tests to be performed.

1.8.3.	Testing Frequency

Testing frequencies are identified in the specifications.

1.8.4.	CQA Test Results

The CQA Engineer shall verify that test results meet the requirements stated in the specifications.
The following shall be verified when reviewing CQA test results:

(1)	Properties of the borrow soils used for CQA testing are consistent with those of the
materials used for full-scale construction.

(2)	The correct tests were performed and specified test procedures were used.

(3)	Test results are in accordance with the specifications. The CQA Engineer shall
immediately notify the CM of problems with CQA testing procedures or test results.

(4)	The CQA Engineer is to ensure that all testing, by the CQA or CQC, is recorded on an
approved datasheet and filed appropriately.

2. SOILS

2.1. GENERAL

General soils CQA requirements are discussed in this section and in the specifications in the
Contract Documents. Additional requirements for specific types of soils are discussed in
subsequent sections.

2.1.1.	CQA Personnel

All individuals assigned CQA responsibilities for soil layers shall have provided CQC and/or CQA
inspection services on earthmoving and waste remediation projects.

2.1.2.	Equipment

Visually inspect and verify that soil processing, placement, and compaction equipment meet the
requirements described in the specifications.

000013


-------
EA Project No.: 14342.58
Revision: 00
Page 7 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

2.1.3. Weather Conditions

Verify that soil placement or compaction does not occur during periods of freezing temperatures, if
it is raining excessively or if excessive soil moisture is present for other reasons, or if other
detrimental weather conditions exist.

2.2. EXECUTION

2.2.1. General

(1)	Verify that the stockpiles containing contaminated material are bermed, lined, and covered
(as necessary). Covers shall be placed over soil to minimize dust and prevent contact with
storm water in accordance with the specifications.

(2)	Verify waste material is placed so that large void spaces do not exist and that
uncontaminated waste is not disposed of in the consolidation area (i.e., waste from
clearing and grubbing, etc). Material that contains unprocessed DNAPL cannot be placed
in the consolidation area. Material containing DNAPL must be solidified and stabilized
before it can be placed in the consolidation area.

(3)	Compaction of waste is usually specified by requiring several passes of a compactor over
all areas of the waste instead of requiring that a specific density criterion be achieved. At
least three times per 8-hour period, the CQA observer shall spot-check to make sure the
contractor is making the minimum required number of passes for each lift of waste
placed.

(4)	Immediately notify the CM if unexpected hazardous materials (tanks, medical waste, etc.)
are discovered during waste re-grading or placement.

(5)	Notify the CM if odor or volatilization of contaminants becomes a problem.

(6)	Verify that the contractor is maintaining dust control as required.

(7)	When waste is being re-graded, look for leachate seeps that present unsuitable conditions
for fill placement. Report such seeps to the CM.

(8)	Check for areas where additional fill needs to be placed due to settlement.

(9)	Check interim surveys to verify adequate space is available within the consolidation area
to store all contaminated material.

(10) Verify final lines and grades of the re-graded and in-place waste.

000014


-------
EA Project No.: 14342.58
Revision: 00
Page 8 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

2.2.2.	Soils Placement

During soils placement, verify the following:

(1)	Sudden braking or sharp turns are not made.

(2)	Slippage of placement and compaction equipment is not occurring on side slopes. CQA
Engineer shall also verify there are no thin areas of soil which could allow underlying
clay layer to be eroded and potentially release contaminated material.

(3)	Loose lifts are no greater than the specified maximum allowable thickness as listed in the
contractor's approved work plan. A CQA Engineer shall physically measure the loose lift
thickness of each soil layer being placed a minimum of three times per 8-hour shift at
randomly selected locations.

(4)	Soil contains no material prohibited by the specifications. The CQA Engineer shall
physically measure clods and other materials that appear to be too large in size.

(5)	Soil is placed to the lines and grades shown on the drawings by comparing the contract
drawings with as-built surveys and raw data located on known control points and grade
stakes.

2.2.3.	Compaction

(1) Verify that the specified minimum numbers of passes are being made over all areas of

each lift of soil (if applicable). For each soil layer being placed, a CQA Engineer shall spot
check the number of passes over a specific area at least three times per 8-hour shift.

2.2.4.	Classification

(1) Verify that soil classifications and sources meet requirements in specifications.

2.2.5.	Tests

Borrow tests and in-place moisture content and density tests will be conducted.

2.2.5.1. Borrow Tests

(1)	Check CQC borrow third party test results (sieve analysis, Atterberg limits, compaction
tests, classification, etc.) to verify that the borrow material is uniform and matches the
required properties given in the specifications.

(2)	Advise the CM about the need to do additional borrow source assessment testing if the
properties of a borrow source appear to have changed significantly.

000015


-------
EA Project No.: 14342.58
Revision: 00
Page 9 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

2.2.5.2. In-Place Moisture Content and Density Tests
Verify the following during testing of the in-place soil layer:

(1)	CQC moisture content and density tests are performed by the CQA Engineer's third party
testing lab at the required frequency in the specifications.

(2)	Additional CQC tests are taken where density or moisture content test results are not
in compliance with the specifications or the soil is visibly suspect.

(3)	The Contractor performs corrective action as a result of failed tests in compliance with
the specifications and submits documentation describing the corrective measures
taken.

(4)	The Contractor uses nuclear gauges in the direct transmission mode to measure density.

2.2.6.	Protection

(1)	Ensure the contractor removes puddles and excess moisture from the soil surface prior
to placement of additional soil.

(2)	Look for areas of erosion after each rainfall.

(3)	Inspect for damage due to freezing and/or desiccation.

(4)	Ensure the contractor repairs damaged areas and reestablishes grades.

2.2.7.	Repairs

If a soil layer does not conform to the specifications, the CQA Engineer shall assist the CM in
defining the extent of the area requiring repair. This shall be done through the use of additional
testing and/or visual inspection.

2.2.8.	Testing of Repaired Areas

After repairs have been made, ens ure CQA and CQ C retests are performed to check the repaired
areas. In general, CQA tes ts shall be perform ed at the sam e frequency as the rest of the project.
Additional CQA testing shall be performed in suspect areas.

2.2.9.	Temporary Erosion Control

The CQA Engineer shall verify the following:

(1) Soil erosion control fences (i.e., silt fences), berms, and other structures are installed
at the locations indicated on the Engineer-approved Storm Water Pollution
Prevention Plan (SWPPP).

000016


-------
EA Project No.: 14342.58
Revision: 00
Page 10 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

(2)	The bottoms of silt fences are installed in accordance with specifications and
manufacturers recommendations.

(3)	Hay bales are tied firmly with wire or plastic ties, secured by wood stakes, and are partially
buried.

2.2.10. Maintenance

The CQA Engineer shall inspect vegetation and erosion control material monthly and after storm

events (during construction) to verify the following:

(1)	Silt fences and erosion control blankets are adequately maintained.

(2)	Eroded areas are repaired.

(3)	Reseeding is performed as required.

(4)	Excessive amounts of silt are removed from behind silt fences and hay bales.

(5)	Areas are protected from traffic through the use of appropriate barricades and signs.

2.3. GEOTEXTILE

(1)	Verify sewn, heat bonded, and overlapped seams are constructed in the specified
locations.

(2)	Verify sewn seams are constructed using the correct overlap, thread type, and stitch type.

(3)	Inspect for skipped stitches in stitch bonded seams.

(4)	Inspect for discontinuities in heat bonded seams.

(5)	Ensure the geotextile is not being burned through during the fabrication of heat bonded
seams.

(6)	Check the specifications to determine the maximum allowable exposure time for the
deployed geotextile. If the allowable exposure time has been exceeded, determine
whether the geotextile has been damaged. If needed, request the performance of
additional CQA tests to verify that the physical properties of the textile have not
diminished due to exposure.

(7)	Inspect the geotextile for evidence of clogging from eroded or windblown soil.

3. PERMANENT EROSION CONTROL

3.1. GENERAL

CQA requirements for riprap and other runoff control features are discussed in this section as

well as the drawings in the Contract Documents.

000017


-------
EA Project No.: 14342.58
Revision: 00
Page 11 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

3.1.1. Delivery, Storage, and Handling

The CQA Engineer shall be present during delivery and unloading and shall verify the following:

(1)	Individual pieces of stone protection are free from cracks, seams, and other defects that will
cause rapid deterioration during service.

(2)	Riprap consists of stones which are approximately rectangular in cross section and free
from thin-slabbed pieces, dirt clods, mud, and other deleterious materials.

(3)	No rock is furnished from any source which has not been sampled, tested, and approved for
use.

3.2.	MATERIAL PROPERTIES

3.2.1.	Quality Control Testing

The CQA Engineer shall review certified test results from the quarry.

3.2.2.	Quality Assurance Testing

The CQA Engineer shall visually inspect and measure riprap delivered to the site. No formal
CQA conformance testing for riprap shall be performed unless deemed necessary by the CM. The
CQA Engineer shall advise the CM on the need for CQA testing. If CQA testing is performed,
the CQA Engineer shall verify representative samples are used for this testing.

3.3.	EXECUTION

By visual inspection, the CQA Engineer shall verify that placement of stone protections are in
compliance with the following paragraphs.

3.3.1. Riprap Placement

Verify the following during riprap placement:

(1)	Stone protection is placed in a manner to produce a reasonably well-graded mass of stone
with the minimum practicable percentage of voids.

(2)	Damage to nonwoven geotextile does not occur.

(3)	The entire mass of stone in their final position is roughly graded to conform to the gradation
specified.

(4)	Dumping stone at the top of slopes and rolling or pushing into place does not occur.

000018


-------
EA Project No.: 14342.58
Revision: 00
Page 12 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

3.4. CHANNELS

(1)	Visually inspect for dips and reverse grades along channel bottoms.

(2)	For channels at the toe of cover, verify the outlet pipes for the cover drainage layer are
not obstructed or damaged during construction of the toe channel.

4.	MONITORING WELL ABANDONMENT

4.1.	GENERAL

CQA requirements for monitoring well abandonment are discussed in this section.

4.2.	SUBMITTALS

(1)	Verify that the contractor's registration as a Texas Water Well Contractor is current.

(2)	At the completion of well plugging and abandonment, verify that the water well plugging and
abandonment forms have been properly filled out and submitted to the State for all
monitoring wells plugged and abandoned.

4.3.	EXECUTION

(1)	Verify that the contractor plugs the correct wells.

(2)	Observe the contractor pulling or attempting to pull the casing from the wells.

(3)	Verify that the contractor fills the well bore with heavyweight grout from the total depth
of the well to either the surface or 1 foot above the proposed excavation depth for that
area.

(4)	Verify that all well equipment, including piping, bollards, screens, and other
appurtenances are removed from the site for disposal.

(5)	Verify that the contractor decontaminates all drilling equipment prior to
demobilization.

5.	MONITORING WELL INSTALLATION

5.1. GENERAL

CQA requirements for monitoring well installation are discussed in this section. Monitoring well

installation CQC requirements can be found in Specification Section 33 24 00 Monitoring Well

Installation.

000019


-------
EA Project No.: 14342.58
Revision: 00
Page 13 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

5.2.	SUBMITTALS

(1)	Verify that the contractor's registration as a Texas Water Well Contractor is current.

(2)	Verify that the contractor submits daily drilling logs within 7 days of well installation.

(3)	At the completion of well installation, verify that the contractor registers the wells with the
Texas Commission on Environmental Quality (TCEQ) and that copies of the registration are
provided.

5.3.	EXECUTION

(1)	Verify that the well locations are staked in the correct location.

(2)	Verify that all downhole drilling equipment is decontaminated before the beginning
of field activities, between individual borings, and prior to demobilization.

(3)	Verify that the contractor drills each well to the specified depth or stratum.

(4)	Verify that that well sump, screen, and casing are installed in the hole plumb and true.

(5)	Well screen interval may be adjusted in the field based on the lithology encountered
by the well installer. Record the actual depth of screen installation.

(6)	Verify that the contractor sounds continuously during filter pack placement to
measure its rate of rise and to determine if bridging is occurring.

(7)	Verify that the filter pack is placed in accordance with the design.

(8)	Verify that a minimum of 1 foot of fine sand is placed over the filter pack.

(9)	Verify that 1 foot of bentonite pellets are placed on top of the fine sand using a tremie
pipe.

(10)	Verify that the bentonite is hydrated a minimum of 8 hours prior to grouting.

(11)	Verify that bentonite grout is placed from the top of the bentonite to the surface using a
tremie pipe. Verify that the grouting is done in one continuous operation.

(12)	Verify that well development occurs no sooner than 48 hours after grouting is completed.

(13)	Verify that measurements are taken of the depth to water and total depth of the well prior
to development and there are readings of pH, conductivity, temperature, and turbidity
during development.

(14)	Verify that development continues until the water is clear and appears to be free of
sediment.

000020


-------
EA Project No.: 14342.58
Revision: 00
Page 14 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

(15) Verify that all drill cuttings and decontamination water are placed in drums and
stored onsite.

6. CONSTRUCTION QUALITY ASSURANCE DOCUMENTATION

6.1.	GENERAL

The CQA Engineer shall document all construction inspection and testing activities with logs,
reports, and photographs. The data sheets to be used for CQA documentation shall be as
presented at the end of this section. With the approval of the CM, data sheets presented in this
CQAP may be revised as necessary by the CQA Engineer. Additional data sheets needed to
record test results and observations shall be submitted to the CM for approval.

6.2.	CQA ENGINEER'S DAILY REPORT

The CQA Engineer's Daily Report shall be prepared by the CQA Engineer and submitted weekly
to the CM. At a minimum, the Daily Report shall include the following information:

(1)	Date, project name, location, and other identifying information

(2)	Weather conditions

(3)	A narrative describing construction activities underway

(4)	CQA activities performed

(5)	Summary of CQA and CQC tests performed and test methods used.

(7)	Summary of CQA and CQC test results, including corrective actions taken for all
construction materials not in compliance with project specifications

(8)	A list of items requiring the CM's attention

(9)	Documentation of borrow sources used and placement activities for all soils. Note any visual
changes in borrow soils.

(10)	Corrective actions taken to repair damage

(11)	Visual observations noted on all construction activities, including any concerns noted

(12)	Summary of results for CQA lift thickness, density, and moisture content measurements

(13)	Record of significant discussions or conferences with the CM, subcontractors, CQC
personnel, and others.

000021


-------
EA Project No.: 14342.58
Revision: 00
Page 15 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

6.3.	FIELD MOISTURE AND DENSITY TEST RESULT DATA SHEET

The CQA shall ensure that the contractor records moisture content and density tests, and they shall
be recorded on an approved datasheet.

6.4.	TEST REPORT

An approved data sheet shall be used to record all other testing.

6.5.	SURVEY RECORDS

Record drawings resulting from the topographic surveys shall be reviewed by the CQA Engineer.
Record drawings shall be included as part of the Final CQA Report issued by the CQA Engineer.

6.6.	PHOTOGRAPHIC DOCUMENTATION

Photographic documentation shall serve as a record of work progress, problems, and repairs and
shall be taken of every phase of construction being performed. It is recommended the CQA use a
digital camera with at least 3 megapixels resolution quality for these photographs and that
photographs be taken daily of the construction process. Additional photographs shall be taken to
document potential contractual or regulatory problems. The basic file shall contain color prints
in electronic format saved in order of date. These photographs shall be available for review by
the CM, the CQA Engineer, and other interested parties authorized to view them. Selected
photographs shall be reproduced as part of the final report. The remaining photographs shall be
transmitted to the CM for archive as part of the permanent records.

6.7.	FINAL REPORT

At the completion of work, the CQA Engineer shall be responsible for writing a final report on
CQA activities performed at the site. The draft final report shall be completed and submitted to the
CM no more than 60 days after completion of construction and shall include, at a minimum, the
following information:

(1)	Brief description of the project including type of facility, name of site, location, altitude,
name of owner, design engineer, general contractor, and all major subcontractors

(2)	Detailed description of the cover and lining systems, including surface area, cross
sections, and a summary of all materials used

(3)	Chronological summary of construction activities

(4)	Photographic documentation, including photographs of the site at different phases of
construction, photographs of construction details, and photographs of all CQA operations

(5)	General record of activities, such as dates of performance of CQA operations, and number
and names of CQA observers

000022


-------
EA Project No.: 14342.58
Revision: 00
Page 16 of 16

EA Engineering, Science, and Technology, Inc.	September 2010

(6)	Sampling and testing locations

(7)	Copies of all CQA data sheets and records completed during construction of the
consolidation area

(8)	All CQA field and laboratory test results as well as a summary of these results

(9)	Discussion of special problems encountered and their solutions

(10)	Discussion of significant changes from design and material specifications

(11)	As-built survey records

(12)	A summary statement sealed and signed by the CQA Engineer documenting that CQA was
conducted in accordance with the CQAP and, based on visual observations and data
generated in accordance with the CQAP, the consolidation area, stabilized areas, and
related features shown on the construction drawings were constructed in accordance with
project construction drawings and specifications except as properly authorized and
documented in the CQA Final Report.

7. CONTAMINATED MATERIALS

CM shall monitor Contractor's work to verify compliance with the Contractor's approved

Contaminated Materials Handling Plan. Any deficiencies shall be immediately reported to the

CQA Engineer.

000023


-------
Attachment A

Quality Assurance Report
Daily Log of Construction

000024


-------
QUALITY ASSURANCE REPORT (QAR)
DAILY LOG OF CONSTRUCTION

THE OCR WILL BE ATTACHED TO OR FILED WITH THE QAR.

REPORT NUMBER

DATE

PROJECT CONTR

ACT NUMBER

CONTRACTOR (Or hired labor)

WEATHER

CQC control phases attended and instruction given:

Results of QA activities and tests, deficiencies observed, actions taken and corrective action of Contractor:
(Include comment pertaining to Contractors CQC activities.)

Verbal instruction given to Contractor: (Include names, reactions and remarks.)

Has anything developed on the work which might lead to a change order or finding of fact?	No	Yes

000025


-------
Information on progress of work, causes for delays and extent of delays, weather, plant, material, etc.:

Information, instructions, or actions taken not covered on QCR report or disagreements:

Safety: (Include any infractions of approved safety plan or safety manual Specify corrective action taken.)

Remarks: (Include visitors to project and miscellaneous remarks pertinent to work.)

QA Representative's Signature

Date Supervisor's

Initials

Date

Page 2 of 2 Pages

000026


-------