Harbor Cleanup News

New Bedford Harbor Super fund Site ~~~ Fall 2006

I o \

U3Ģi

Harbor PCB Dredging Resumes

Vers do Portuguesei, Pdgina 3.
Para Leer La Vers on en Espdnol, Vea la Pdgina 5.

Third Season of Dredging Expected to Last until Late October

In mid-August EPA began the third season of full scale dredging of
PCB-contaminated sediment in New Bedford Harbor. This latest
dredging effort is focusing on an area along and just north of the
former Aerovox facility. Similar to dredging conducted in 2005,
approximately eight acres of sediment will be dredged this year,
resulting in the removal of about 25,000 cubic yards of contaminated
sediment.

What Happens to the Dredged Material?

The dredged material is pumped directly into a floating pipeline
connecting the dredge to EPA's desanding building located at Sawyer
Street, New Bedford, approximately one mile south of the dredged area.
Booster pumps, located along the shoreline, help pump the dredged
sediment through the floating pipeline to the desanding facility.

Raking out

Installing the Pipeline

At the desanding facility, coarse material is separated from the finer
sediment. A submerged pipeline carries the finer sediment another 1.4
miles south to the dewatering facility at Hervey Tichon Ave. and
Herman Melville Blvd, New Bedford. At the dewatering facility,
specialized presses squeeze the excess water out of the dredged
sediment. About 16,000 tons of dewatered sediment will be
transported off-site by train and disposed of in a licensed PCB-landfill
in Michigan. EPA anticipates that approximately 20 million gallons of
water will be treated according to stringent, water-quality based
standards, before being discharged back into the harbor.

What Progress has been Made So Far?

In addition to the two prior seasons of full-scale harbor dredging, many
other areas of PCB contaminated harbor sediment have been cleaned
up to date, including:

~	19 acres capped in 2005 south of the hurricane barrier;

~	seven acres cleaned north of Wood Street in 2002-2003;
~> two acres dredged in 2002 for a business relocation;

~	five acres of the most highly contaminated sediment dredged
in 1994-1995.

-1-


-------
Fish, lobster, Fish Smart... Read This Chart!

quahog and
other seafood
from New
Bedford Harbor
and the Acushnet
River contain
high levels of
PCBs, which can
cause illness if
eaten regularly.

Restrictions on

fishing and
lobstering have
been in place
since 1979.

Don't eal any fish

Don't eat any
lobster

(wfc}0on'1 eat any
shellfish

Don't oa1 any
tiottom fish
[flounder, so.jp,
tauJoo arid eetl

Site History

The New Bedford Harbor Superfund Site is an 18,000 acre urban estuary reaching from the upper
Acushnet River into Buzzards Bay. Its sediment is highly contaminated with PCBs (polychlorinated
biphenyls) used along the harbor from the 1940's until banned in 1978. EPA added the harbor to its
National Priorities List (known as the Superfund list) in 1983, making the site eligible for federal
Superfund cleanup money.

Since 1983, EPA has spent more than $220 million in planning, engineering and construction costs for
the harbor cleanup. The remaining 240 acres of contaminated sediment, including surrounding
wetlands and residential properties, will be processed at the 5-acre dewatering facility in the harbor's
North Terminal. This 55,000 square-foot facility and surrounding marine bulkhead and rail spur
will revert to the city when the harbor cleanup is finished. Around 880,000 cubic yards of sediment
are slated to be removed, roughly equal to 175 football fields each filled 3 feet deep.

For More Information Contact:

U.S. EPA Project Managers:

Dave Dickerson	617-918-1329 or toll free 1-888-372-7341

dickerson. dave@epa. gov

Jim Brown	617-918-1308 or toll free 1-888-372-7341

brown.jim@epa. gov

U.S. EPA Community Involvement:

Stacy Greendlinger	617-918-1403 or toll free 1-888-372-7341

greendlinger. stacy @epa. gov

MA Dept. of Environmental Protection:

Joe Coyne	617-348-4066 joseph.coyne@state.ma.us

www.epa.gov/ne/nbh


-------
Continua^ao da dragagem de PCB no porto

English Version, Page 1
Para Leer La Verson en Espdnol, Vea la Pcigin a 5

A terceira temporada de dragagem
devera durar ate o final de outubro

Em meados de agosto, a EPA (Agenda de Proteqao ao Meio
Ambiente dos EUA) deu inicio a terceira temporada de dragagem
em capacidade plena de sedimentos contaminados com PCBs
(bifenilos policlorados) no Porto de New Bedford. Este ultimo
trabalho de dragagem concentra-se em uma area nas proximidades
da antiga fabrica da Aerovox e na regiao ao norte da mesma.

Semelhante a dragagem realizada em 2005, cerca de oito acres de
sedimentos serao dragados este a no, resultando na retirada de cerca
de 19.000 m3 de sedimentos contaminados.

O que acontece com o material dragado?

O material dragado e bombeado diretamente para urn duto flutuante
que conecta a draga a estaqao de centrifugaqao da EPA, localizada na
Sawyer Street, New Bedford, cerca de 1,5 km ao sul da area drenada.
Bombas auxiliares, localizadas no literal, ajudam a transportar os
sedimentos dragados para as estaqoes de centrifugaqao atraves
do duto flutuante.

Na centrifugaqao, os materials mais grossos separam-se dos
sedimentos mais finos. Dutos submersos transportam os
sedimentos mais finos por cerca de 2,2 km ao sul para as estaqoes
de desaguamento na Hervey Tichon Ave. e no Herman Melville
Blvd, em New Bedford. Nessas estacoes de desaguamento, prensas
especializadas drenam o excesso de agua do sedimento dragado.

Cerca de 16 mil toneladas de sedimentos secos serao transportadas
de trem para outro local e descartadas em um aterro sanitario
licenciado para PCB, em Michigan. A EPA estima que cerca de 20
milhoes de galoes de agua serao tratados de acordo com rigidos
padrOes de qualidade de agua, antes de serem despejados
novamente no porto.

Ate o momento, qual o progresso desse projeto?

Ate o presente momento, alem das duas temporadas anteriores de
dragagem no porto com capacidade plena, varias outras areas do
porto contaminadas por PCB foram limpas, inclusive:

~	19 acres tratados ao sul da barreira para furacoes em 2005;

~	Sete acres limpos ao norte da Wood Street em 2002-2003;

~	Dois acres dragados para a transferencia de uma empresa em 2002;

~> Cinco acres dos sedimentos mais contaminados dragados em 1994-1995.

-3-


-------
Os peixes, lagostas,
mariscos e outros

frutos do mar
provenientes do

Porto de New
Bedford e do Rio
Acushnet contem
altos niveis de PCB,

que podem
provocar doengas se
ingeridos
regularmente.
Desde 1979, ha
restrigoes a pesca de
peixes e de lagostas.

Historia do local

(^) Nao coma peixe
(\^) Nao coma lagosta
(^\) Nao coma mariscos

0

Nao coma peixe de fundo:

•	solha

•	sargo

•	bodiao da ostra

•	enguia

A area do Porto de New Bedford beneficiada pela Superverba e um estuario urbano de 18 mil acres que se estende da regiao
norte do Rio Acushnet ate a Baia de Buzzards. Seus sedimenlos foram a 1 Lamenle contarninados por PCBs (bifenilos policlorados)
utilizados no porto desde a decada de 1940 ate sua proibicao em 1978. Em 1983, a EPA acrescentou o porto a sua Lista de
Prioridades Nacionais (conhecida como lista de Superverba), qualificando assim o local para limpeza com o uso dos fundos
da Superverba do governo federal.

Desde 1983, a EPA ja gastou mais de US$220 milhoes em planejamento, engenharia e construcao para a limpeza do porto. Os
240 acres remanescentes de sedimenlos contarninados, que abrangem os pantanos vizinhos e propriedades residenciais, serao
processados nas estacoes de desaguamento de 5

acres, no Terminal Norte do porto. Estas instalacoes
de 5.000 m2, um anteparo marinho e o ramal
ferroviario vizinhos serao entregues a
responsabilidade e propriedade do muiiicipio apos

o termino da limpeza do

Mudan9a de ^
Filtros das
Esta9oes de

porto. Havera a remocao
de cerca de 673.000 m3 de
sedimentos, o que
equivale a praticamente
175 estadios de futebol,
com 1 metro de altura de
sedimentos.

-4-

Para mais informa9oes, contate:

Gerentes de projetos da EPA nos EUA:

Dave Dickerson	617-918-1329 ou ligagao gratuita 1-888-372-7341

dickerson. dave@epa. gov
Jim Brown	617-918-1308 ou ligagao gratuita 1-888-372-7341

brown.jim@epa. gov
Participagao da Comunidade na EPA nos EUA:

Stacy Greendlinger	617-918-1403 ou ligagao gratuita 1-888-372-7341

greendlinger. stacy@epa. gov
Departamento de Protegao Ambiental de Massachussets:

Joe Coyne	617-348-4066 joseph.coyne@state.ma.us

www.epa.gov/ne/ nbh

ACUSHNET

MATTAPOISETT

hurricane
barrier

(SCONTICtUT
\ neck\

WESl
.IS LAN!

Clark's
Point

Wilbur
Point

Ricketson's
Point

Pesqwe esperto...Use este map a			

\ MARION J

\ NEW BEDFORD II ^	—

\	\ r"Jcoggeshall Street	\

i	C 7j Bridge	\

r?> Đ FAIRHAVEN \

DARTMOUTH

Mishaum
Point


-------
Continua el dragado de PCB del puerto

English Version, Page 1
Versdo Portuguese^ Pdgina 3

Se Espera que la Tercera Sesion de Dragado Continue Hasta
Finales de Octubre

Rastrillando Desperdicios

A mediados de agosto, la EPA comenzo la tercera sesion del dragado a
gran escala del sedimento contaminado con PCB (bifenilos policlorados)
en el puerto de New Bedford. Este ultimo esfuerzo de dragado se
concentra en un area a lo largo y justo al norte de la antigua instalacion
de Aerovox. Similar al dragado que se llevo a cabo en 2005, este ano se
dragaran aproximadamente ocho acres de sedimento, resultando en el
traslado de unas 25.000 yardas cubicas de sedimento contaminado.

jjQue sucede con el material dragado?

El material dragado es bombeado directamente a una tuberia flotante que
conecta la draga a la planta de desarenado de la EPA situada en Sawyer Street,
New Bedford, aproximadamente una milla al sur de la zona dragada. Bombas
impulsoras, situadas a lo largo de la costa, ayudan a bombear el sedimento
dragado a traves de la tuberia flotante a la planta de desarenado.

Instalacion de la Tuberia

En la planta de desarenado, el material grueso es separado del sedimento
mas fino. Una tuberia sumergida lleva el sedimento mas fino otras 1,4
millas mas al sur, a la planta de extraccion de agua en Hervey Tic lion
Ave. y Herman Melville Blvd, New Bedford. En la planta de extraccion
de agua, prensas especializadas escurren el exceso de agua del sedimento
dragado. Unas 16.000 toneladas de sedimento sin agua seran sacadas de
la planta por ferrocarril y vertidas en un relleno autorizado para basura
con PCB en Michigan. La EPA anticipa que aproximadamente 20 millones
de galones de agua seran tratados de acuerdo con normas estrictas de
calidad del agua, antes de ser vertidas en el puerto.



S5i=:



jtli il

Ķ].,r Ķ





!Ķ ma



Ķ**1 J

jQue progreso se ha hecho hasta la fecha?

Ademas de las dos sesiones anteriores de dragado a gran escala del puerto,
se han limpiado hasta la fecha muchas otras areas de sedimento
contaminado con PCB, por ejemplo :

~	19 acres recubiertos en 2005 al sur de la barrera contra huracanes;

~	siete acres limpiados al norte de Wood Street en 2002-2003;

~	dos acres dragados en 2002 para la reubicacion de un negocio;

~	cinco acres del sedimento mas contaminado dragado en 1994-1995.

-5-


-------
Los peces, langostas,
quahog y otros mariscos
del puerto de New
Bedford y del rio
Acushnet contienen altos
niveles de PCB, y pueden
causar enfermedades si

se consumen
regularmente. Se han
implementado
restricciones a la pesca y
captura de langostas
desde 1979.

jPesque con cabeza! Utilice esta graflca

\MARION <

MATTAPOISETT

/tishaum
Point

Historia del lugar

(^) No coma pescado
0) No coma langosta
0 No coma mariscos

No coma pescado de fondo:

•	lenguado

•	sargo

•	tautoga

•	anguila

El sitio del Superfondo del puerto de New Bedford es un estuario urbano de 18.000 acres que se extiende desde la
parte alta del no Acushnet hasta Buzzards Bay. Su sedimento esta altamente contaminado con PCB (bifenilos
policlorados) usados a lo largo del puerto desde la decada de 1940 hasta que se prohibieron en 1978. La EPA anadio
el puerto a su Lista de Prioridades Nacionales (conocida como la lista del Superfondo) en 1983, haciendo que el
lugar fuera elegible para el dinero del Superfondo federal de limpieza.

Desde 1983, la EPA ha gastado mas de $220 millones en costos de planificacion, ingenieria y construccion para la
limpieza del puerto. Los restantes 240 acres de sedimento contaminado, incluso los pantanos circundantes y las
propiedades residenciales, seran procesados en la planta de extraccion de agua de 5 acres de extension en la
terminal norte del puerto. Esta instalacion de 55.000 pies

cuadrados, la presa marina circundante y el ramal corto
de ferrocarril se devolveran a la ciudad cuando la limpieza

del puerto se haya
completado. Unas
880.000 yardas cubicas de
sedimento	estan

programadas para su
retirada, casi equivalentes
a 175 campos de futbol
con un espesor de 3 pies.

Para mas informacion contactese con:

Gerentes de proyecto de la EPA en Estados Unidos:

Dave Dickerson	617-918-1329 o gratis al 1-888-372-7341

dickerson. dave@epa. gov
Jim Brown	617-918-1308 o gratis al 1-888-372-7341

brown.jim@epa. gov
Compromiso comunitario de la EPA en Estados Unidos :

Stacy Greendlinger	617-918-1403 o gratis al 1-888-372-7341

greendlinger. stacy@epa. gov
Departamento de Protection Ambiental de MA:

Joe Coyne	617-348-4066 joseph.coyne@state.ma.us

www.epa.gov/ne/ nbh


-------