Inspection Report: PQ Corporation, Clean Air Act Stationary Source

Facility Name:	PQ Corporation

Inspection Date(s): September 27, 2023

Facility Address:	4238 Geraldine Avenue, St. Louis, MO 63115

FRS ID #:

110001452703

Federal Facility:	No

NCI:

Creating Cleaner Air for Communities

Facility size:

Major Source

Activity:

PCE

State Referral:

No

NAICS code:

325188 - All Other Basic Inorganic Chemical Manufacturing

Lead Inspector:	Elizabeth Hubbard, ERG Inspector Trainee, (919) 468-7894

Asst. Inspector:	Bryan Lange, ERG Inspector, (919) 622-2374

State Inspector:	Patrick Glass, Missouri Department of Natural Resources (MoDNR)

Facility Contact:	Rich Heisse, Site Manager, (314) 679-8502, rich.heisse@pqcorp.com

1


-------
1. Plant Description:

According to the facility's 2018 operating permit, "PQ Corporation, located within the City of St. Louis,
produces sodium silicate (water glass) and silica gel. Sodium silicate and silica gel are used in a variety of
products including clarifying agent for alcoholic beverages." The installation is a major source for
particulate matter ("PM") and nitrogen oxides.

The operating permit describes the production of sodium silicate as follows: "The production of sodium
silicate begins by unloading railcars of soda ash and sand into storage silos. From the storage silos, a
carefully controlled amount of soda ash and sand are fused and reacted to produce sodium silicate. The
sodium silicate is then solidified and conveyed to the storage silos."

The operating permit describes the production of silica gel as follows: "Silica gel is produced by reacting
sodium silicate with sulfuric acid. Once the silica gel has been produced, it is washed, dried and ground
to the size specified by the customer. The drying and grinding are accomplished in the Mill Heater. From
the Mill Heater, the silica gel is transported by air to the packaging operation."

Figure 1: Satellite image of the PQ Corporation facility in St. Louis, MO.

2


-------
2. Facility Entry:

The representatives of the United States Environmental Protection Agency ("EPA"), Elizabeth Hubbard
and Bryan Lange from Eastern Research Group (ERG), and a representative from MoDNR, Patrick Glass,
arrived at the PQ Corporation facility at 4238 Geraldine Avenue, St. Louis, MO ("PQ Corporation" or "the
facility") at approximately 9:15 am. The MoDNR and ERG representatives ("the inspectors") were met at
the administration building by Rich Heisse, Site Manager; Tom Ferrall, Environment, Health, and Safety
("EHS") Partner; James Kelsey, Gels Plant Unit Manager; and Jeff Zurbriggen, ICD Plant Unit Manager
("the facility representatives"). The inspectors presented their identification credentials and provided an
overview and scope of the inspection. The inspectors explained that ERG worked as contractors to
conduct facility inspections for EPA. They provided a copy of EPA's "Small Business Resources
Information Sheet."

3. Opening Conference/Technical Discussion:

The inspectors explained that they were at the facility to conduct a routine Clean Air Act ("CAA")
inspection that was part of a national initiative to look at facilities close to residential neighborhoods,
including a focus on volatile organic compounds ("VOCs") and hazardous air pollutants ("HAPs"). The
inspectors explained that during the facility walkthrough, they would capture digital images of the
facility's processes and emission points using a digital point and shoot camera, as well as an optical gas
imaging, forward looking infrared ("FUR") video camera, model GF320, that were not intrinsically safe.
Therefore, they requested that the facility representatives inform them of any areas where there could
be a potentially explosive atmosphere. The facility representatives expressed that there were no areas
of the facility where flammability would be a concern.

The inspectors asked for background information about PQ Corporation and the facility. The facility
representatives provided an overview of the facility's history, as well as the general operations that took
place at the facility. The facility representatives explained that the facility operated 24 hours per day, 7
days per week and that 34 people were employed by the facility, with 4 additional corporate employees
that visited regularly. PQ Corporation was a global company and was headquartered in Malvern,
Pennsylvania. The facility representatives said that PQ Corporation had 9 facilities in the U.S. and
estimated it had around 30 facilities globally. The facility was located on 6.2 acres of land, which the
facility representatives said was a medium-sized site for PQ Corporation. The facility was built in 1926 to
serve PQ Corporation customers in the Midwest and originally only included the "ICD Plant", the part of
the facility that produced sodium silicate. The "Gel Plant", where silica gel was produced at the facility,
was added in 1993 to serve Anheuser-Busch and other customers. This facility was one of two facilities
owned by PQ Corporation that produced silica gel. The facility's environmental permits included a Title V
permit, a water discharge permit, and a nuclear gauge permit.

The facility representatives described the sodium silicate production process, which they said had
changed very little since PQ Corporation began producing it in 1851. The facility received both sand and
soda ash (the two raw materials used to produce sodium silicate) by rail, and the final product was
shipped out by rail and truck. In the ICD Plant, sand and soda ash were combined in a natural gas-fired
glass melting and regenerating furnace operated at 2,200 to 2,500°F, which was the facility's main
source of PM emissions. The facility representatives said the last stack test on the furnace was
completed in 2014. Continuous scales controlled the ratio of sand to soda ash fed to the furnace, which
could vary between ratios of 1.6 and 3.2. A product with a lower sand to soda ash ratio would have a
higher alkalinity. From the furnace, the melted material would go to a glass bunker, through pressure
dissolvers, to unfiltered finished product storage, through a filtration process, then to finished lot tanks.

3


-------
The facility used a pressure leaf filter process which involved combining the sodium silicate with a filter
aid in an Admix tank, then the material went to a filter feed tank which fed it to the filter, and finally to
the finished lot tanks. The facility performed quality checks on the product in the finished lot tanks
before shipping it out. The final product was approximately 65% water and could be used in multiple
applications (e.g., as an adhesive or to coat metals for corrosion prevention). Although the final sodium
silicate product was a liquid, the facility representatives said that it was chemically the same as
hardened glass. The site typically shipped 1 to 4 railcars worth of sodium silicate product each day, and
product could also be shipped via truck. A truck would hold 45,000 pounds of sodium silicate, while a
railcar would hold 180,000 pounds.

The facility representatives described the silica gel production process and its applications. Sodium
silicate product from the ICD Plant was combined with sulfuric acid which was sprayed from a nozzle
over a catch pan, then magnesium sulfate was added to the material in an ion exchange extractor. From
there, the material went through a wash water extractor and was then sent to the mill and mill heater,
where it was dried with 1,400°F air and ground to a specified size. The silica gel mill and mill heater
included a baghouse with 244 bags, and the facility representatives said it used high temperature bags
that were changed about once per year. The facility representatives said that 97.5% of the silica gel
produced at the facility was used by Anheuser-Busch for filtering beer, so employees commonly referred
to the silica gel as "beer gel." The silica gel was used to make beer clear and was preferable to
alternative means of filtration because it left no taste behind. The silica gel was also used by other
customers for oil purification. The Gel Plant produced six different products which were sold globally,
including D300 which was a "base set" gel that would set in a fraction of a second. The Gel Plant
produced a larger diameter product called "XLC" and a fine powder product called "L10".

The inspectors asked whether the facility produced any container glass, pressed and blown glass, wool
fiberglass, or flat glass. The facility representatives responded that no hard glass was produced at the
facility; all the glass it produced was liquid sodium silicate or "water glass."

The inspectors asked when the melting furnace was installed at the facility. The facility representatives
said that the furnace was installed in 1926 and was originally coal-powered but now used natural gas. It
was also converted into a regenerating furnace in 2020.

The inspectors explained that they had questions related to the facility's 2018 operating permit, the
associated Statement of Basis ("SOB"), Emission Inventory Questionnaire ("EIQ"), and Annual HAP and
VOC Emissions Reports. The following is a summary of the discussion.

The inspectors noted that the permit limited PM emissions from several sources but did not require
specific monitoring procedures for a lot of said sources. The inspectors asked how the facility ensured
they were meeting those emission limitations. The facility representatives explained that they
conducted opacity readings using EPA Method 22 every month on all sources and EPA Method 9 every
month on the melting furnace. Facility employees, including Mr. Heisse and Mr. Zurbriggen, were
trained on how to conduct Method 9 opacity readings. The inspectors asked to see examples of Method
9 and Method 22 observations, as well as the Method 9 certification for the person who performed the
Method 9 observations. The facility representatives provided a Method 22 observation log for
September 25, 2023, a Method 9 observation log for September 26, 2023, and a Method 9 certification
for Mr. Zurbriggen issued September 19, 2023. See Appendices H, M, and N.

4


-------
The inspectors explained that low levels of emissions of metal HAPs, such as chromium, lead,
manganese, nickel, and cadmium, had been reported to the National Emissions Inventory ("NEI") for the
facility. The inspectors asked whether any of these emissions came from the ingredients used to
produce sodium silicate and/or silica gel. The facility representatives responded that there were trace
metals present in finished products but only very minimal amounts. They explained that the final
products were tested for trace metals in the facility's research and development lab, and silica gel was
tested for soluble iron and arsenic. The inspectors asked how the facility calculated its metal HAP
emissions, and the facility representatives said that calculations were based on stack testing results and
emission factors from AP-42.

The inspectors noted that the permit limited PM emissions from the silica gel mill and mill heater (EP-
102) to 3.71 pounds per hour and 0.30 grain per standard cubic foot of exhaust gases. The permit
required daily visible emissions monitoring and baghouse pressure drop checks to ensure it stayed
between 0.1 and 7 inches of water. The inspectors asked to see records of pressure drop
measurements. The facility representatives presented daily pressure drop measurements for the
baghouses for both EP-102 and the silica gel product bagging unit (EP-103) for August 2023, which the
inspectors reviewed. The inspectors noted that all the pressure drop measurements they reviewed for
both baghouses appeared to be within the permitted range. See Appendix L.

The inspectors noted that the permit limited the 30-day average oxygen concentration from the melting
furnace to 3.0 percent by volume on a dry basis and required the facility to calculate an average oxygen
concentration for each furnace operating hour and record any deviations in a logbook. The inspectors
asked to see the furnace logbook. The facility representatives presented the logbook, and the inspectors
reviewed a few days' worth of oxygen concentration records, all of which appeared to be within the
permitted range. See Appendix K for an example of a furnace oxygen monitoring log.

The inspectors noted that the permit limited emissions of sulfur compounds when using Fuel Oil No. 2 as
backup fuel for the melting furnace. They asked how frequently Fuel Oil No. 2 was used and how the
facility ensured compliance with the emission limit for sulfur compounds. The facility representatives
explained that Fuel Oil No. 2 was no longer used at the facility, and the facility's Fuel Oil No. 2 tank had
been emptied and cleaned. The facility's furnace could technically still run on Fuel Oil No. 2, but that was
no longer done. Instead, the facility only used natural gas which was received by pipeline.

The inspectors asked how the facility calculated the potential to emit ("PTE") listed for each of the
pollutants in the SOB and from where they derived the emission factors used to calculate the PTE. The
facility representatives responded that all of the calculations and emission factors used to determine
PTE were based on the stack tests performed at the facility.

The inspectors noted that, for the emissions reported to the NEI, the emission calculation methods
listed for many of the pollutants included "USEPA Speciation Profile," "USEPA Emission Factor," or
"Engineering Judgment." They asked the facility representatives if they could elaborate on these
calculation methods or explain what sources were used for USEPA Speciation Profiles or USEPA Emission
Factors. The inspectors noted that a few pollutants had "Stack Test" listed as the calculation method and
asked why stack tests were not used for more pollutants. The facility representatives explained that the
EIQ calculations for the facility were performed by a consultant, so they did not know exactly how the
calculations were performed. They said that stack tests were used as the basis for calculations from
emission points where stack testing had been performed, and AP-42 was used for other emission points.

5


-------
The inspectors asked to see examples of any remaining attachments from the SOB that they had not yet
reviewed, which included the Inspection/Maintenance/Repair/Malfunction Log and the Monthly Fuel
Usage Monitoring Log. The facility representatives provided the Inspection/Maintenance/Repair/
Malfunction Log for August of 2023 and the Monthly Fuel Usage Monitoring Log for January through
August of 2023. See Appendices I and J.

The inspectors asked how the facility determined the capture and control efficiencies of its control
devices as listed in the SOB. The facility representatives responded that the capture and control
efficiencies were determined from manufacturer specifications. The inspectors asked how often the
bags on the baghouses were replaced. The facility representatives said that the bags were replaced
yearly or as needed if any rips were seen, but that rips did not occur frequently.

The inspectors noted that the permit limited emissions from the facility's natural gas emergency
generators under 40 CFR Part 60 Subpart JJJJ, Standards of Performance for Spark Ignition Internal
Combustion Engines and asked to see records of operating hours for the generators. The facility
representatives provided run time logs for the 60-kW generator located in the Gel Plant and the 80-kW
generator located in the ICD Plant. See Appendices F and G.

The inspectors noted that the permit mentioned 40 CFR Part 60 Subpart CC, Standards of Performance
for Glass Manufacturing Plants and 40 CFR Part 63 Subpart SSSSSS, National Emission Standards for
Hazardous Air Pollutants for Glass Manufacturing Area Sources did not apply to the facility because the
facility was not a glass manufacturing plant. The inspectors asked how these determinations were made.
The facility representatives explained that, in 2002, MoDNR had tried to model the facility as a glass
plant and apply these regulations to the facility. The facility had pushed back because it was not a glass
plant, and these regulations were determined not to be applicable. They explained that their process
was much smaller and less complicated than that of a glass manufacturer's. For example, hard glass
manufacturing would require a melting furnace 4 to 5 times larger than the furnace at the facility.

6


-------
4. Facility Tour/Walkthrough:

At approximately 11:15 am, the facility representatives led the inspectors on a walkthrough of the
facility. They started at the truck loading area, toured the ICD Plant, visited the sodium silicate product
storage tanks, proceeded to the location where the facility regularly performed opacity observations,
then toured the Gel Plant, and walked by the railcar loading area. The list of digital images and FLIR
videos taken during the walkthrough are included in Appendix A.

The facility representatives informed the inspectors that the ICD Plant was making a 3.2 ratio (sand to
soda ash) product that day, while the Gel Plant was making L10.

At the truck loading area, the facility representatives informed the inspectors that all trucks were top
filled for sodium silicate loading.

At the ICD Plant, the facility representatives showed the inspectors the plant's 80-kW emergency
generator and its run time log screen. See photos CBI_DSCN7540.JPG and CBI_DSCN7541.JPG.

The group proceeded to the melting furnace, where the facility representatives pointed out that the
furnace length to width ratio was not optimal, which was causing flames to come out of the furnace
door and waste energy. See photos CBI_DSCN7542.JPG and CBI_DSCN7553.JPG. The facility
representatives informed the inspectors that the conveyor that carried the molten glass to the bunker
was a couple of hundred feet long and had approximately 500 molds.

The group visited the ICD Plant operator room, and the inspectors reviewed several process control
screens. See photos CBI_DSCN7543.JPG through CBI_DSCN7546.JPG. They then proceeded past the feed
water tank, the blow tank, and the dissolver tanks. The inspectors noted all of these tanks had apparent
buildup on their exteriors. See photos CBI_DSCN7547.JPG through CBI_DSCN7549.JPG.

At the outdoor storage tank area, the inspectors saw the tank that was formerly used to store Fuel Oil
No. 2 and had been emptied and cleaned. The facility representatives informed the inspectors that the
tank had not been used since 2018. See photo CBI_DSCN7550.JPG. The inspectors also saw a multitude
of sodium silicate product storage tanks. The facility representatives informed the inspectors that at any
given time, there were generally 27 to 28 sodium silicate tanks in use, which stored between 20 and 22
million pounds of total product. See photos CBI_DSCN7551.JPG and CBI_DSCN7552.JPG. The group was
unable to visit the melting furnace baghouse due to safety concerns regarding its location above the
furnace.

Upon exiting the ICD Plant, the facility representatives showed the inspectors the facility's natural gas
pipeline manifold. See photo CBI_DSCN7554.JPG.

The group proceeded to the location from which the facility employees conducted opacity observations
for the melting furnace. The facility representatives informed the inspectors that visible emissions were
graded between 1 and 100% based on what they saw and that they were typically between 5 and 20%
opacity. The facility representatives told the inspectors that there had been two instances they were
aware of when black smoke was seen coming from the melting furnace, with the most recent
occurrence being in 2019. In both instances, the observations were reported to MoDNR immediately.
The inspectors noted that they could see visible emissions coming from the furnace stack at this
location, but they appeared minimal. The inspectors did not see any apparent VOC emissions coming

7


-------
from the furnace stack while using the FLIR camera and took a video of the stack. See photo
CBI_DSCN7555.JPG and video CBI_MOV_2765.mp4.

The group proceeded to the Gel Plant, starting at the top floor of the plant where nozzles sprayed
sodium silicate and sulfuric acid over a catch pan. The inspectors did not see any apparent VOC
emissions from the nozzles when viewing with the FLIR camera. The facility representatives showed the
inspectors what the silica gel beads looked like immediately after forming as the sodium silicate and
sulfuric acid were combined. The beads could be seen being carried by a flight conveyor. See photos
CBI_DSCN7556.JPG and CBI_DSCN7557.JPG.

In the Gel Plant operator room, the inspectors reviewed several process control screens and the
baghouse pressure drop log for September 2023. The facility representatives informed the inspectors
that the Gel Plant generally operated 7 days per week, but for approximately the past month it had been
operating 5 days per week. See photos CBI_DSCN7558.JPG and CBI_DSCN7559.JPG.

The group then proceeded to the mill and mill heater, the mill baghouse, and the bagging area. See
photo CBI_DSCN7560.JPG.

At approximately 12:30 pm, the group returned to the office for a closing conference.

8


-------
5. Closing Conference

In addition to the personnel who were present at the opening conference, Jennie Houle, EHS Director
for Management Systems, Compliance, and Global Silicas, attended via Microsoft Teams.

The inspectors thanked the facility representatives for their time and cooperation during the inspection.
The inspectors explained to the facility representatives that EPA would provide PQ Corporation with an
inspection report in approximately 60 days. They explained that the report would be available to the
public through the Freedom of Information Act, and therefore, if the company wanted to claim any
notes, documents, or digital images as confidential business information ("CBI"), they could do so today
or within 10 days following the inspection. They provided the facility representatives with the EPA's
confidentiality notice form. Mr. Heisse filled out and signed the form. See Appendix B.

The inspectors summarized questions and concerns raised during the inspection. They noted that during
the facility walkthrough, they observed no VOC emissions while using the FLIR camera. The inspectors
had no concerns about the facility's compliance with its permit requirements based on the
documentation provided during the inspection. The inspectors provided the facility representatives with
a copy of a Notice of Preliminary Findings form and explained that EPA may follow up with additional
questions. See Appendix C.

The inspectors provided a receipt for the copies of the documents they received (see Appendices D
through N).

At approximately 1:15 pm, the inspectors departed from the facility.

9


-------
6. Appendices

A.	Digital Image Log

B.	Confidentiality Notice Form

C.	Notice of Preliminary Findings Form

D.	Document Receipt Form

E.	Opening Conference Attendance Sheet (claimed as CBI)

F.	60-kW Generator Log (claimed as CBI)

G.	80-kW Generator Log (claimed as CBI)

H.	Method 22 Observation Log (claimed as CBI)

I.	Inspection-Maintenance-Repair-Malfunction Log (claimed as CBI)
J.	Monthly Fuel Usage Log (claimed as CBI)

K.	Furnace 02 Monitoring Log (claimed as CBI)

L.	Baghouse Pressure Drop Monitoring Log (claimed as CBI)

M.	Method 9 Certification (claimed as CBI)

N.	Method 9 Observation Sheet (claimed as CBI)


-------
Inspection Report Sign-Off

Lead Inspector's Name: Elizabeth Hubbard, ERG

Pli-7Qhoth	Digitally signed by

X^liz.aut;ui	Elizabeth Hubbard

Hubbard ?0a322406230520005

Lead Inspector

Assisting Inspector's Name: Bryan Lange, ERG

Signed by Jason Sese for Bryan Lanqe

X Jason Sese

Digitally signed by Jason
Sese

Date: 2023.12.05
13:11:57 -05'00'

Assisting Inspector

Supervisor's Name: Tracey Casburn, Air Branch Chief, ECAD

X

Digitally signed by
TRACEY CASBURN £^X!RN
14:22:31 -06'00'

Supervisor

11


-------