The EPA Clean School Bus
Program Could Be
Impacted by Utility Delays

December 27, 2023 | Report No. 24-P-0012


-------
Report Contributors

Kevin Collins
Gabriel Porras-Sanchez
Jarrett Rickerds
Kate Robinson
Khadija Walker

Abbreviations

EPA	U.S. Environmental Protection Agency

IIJA	Infrastructure Investment and Jobs Act

OIG	Office of Inspector General

Cover Image

Electric school bus. (EPA photo)

Are you aware of fraud, waste, or abuse in an
EPA program?

EPA Inspector General Hotline

1200 Pennsylvania Avenue, NW (2431T)
Washington, D.C. 20460
(888) 546-8740
(202) 566-2599 (fax)

OIG.Hotline@epa.qov

Learn more about our OIG Hotline.

EPA Office of Inspector General

1200 Pennsylvania Avenue, NW (2410T)
Washington, D.C. 20460
(202) 566-2391
www.epaoiq.gov

Subscribe to our Email Updates.

Follow us on X (formerly Twitter) @EPAoiq.
Send us your Project Suggestions.


-------
At a Gla

24-P-0012
December 27, 2023

The EPA Clean School Bus Program Could Be Impacted by Utility Delays

Why We Did This Audit

To accomplish this objective:

The U.S. Environmental Protection
Agency Office of Inspector General
conducted this audit to determine
whether potential supply chain or
production delays could impact the
EPA's efforts to disburse and manage
Clean School Bus Program funds
pursuant to section 71101 of the
Infrastructure Investment and Jobs Act.

The Infrastructure Investment and Jobs
Act amended the Clean School Bus
Program established by section 741 of
the Energy Policy Act of 2005. It
provides $5 billion over five years, or
through 2026, for the replacement of
existing school buses with clean and
zero-emission school buses. The 2022
Clean School Bus rebate was the first
funding opportunity for the program.

What We Found

We concluded that there were no significant supply chain issues or production delays that
impacted the EPA's efforts to disburse funds through the first round of the Clean School
Bus Program's funding. However, the Agency may be unable to effectively manage and
achieve the program mission unless local utility companies can meet increasing power
supply demands for electric school buses.

The EPA provided utility resources during the rebate application process but did not require
applicants to contact their utility provider to coordinate potential changes needed to connect
charging stations to utilities. While early coordination with utilities is not a requirement, it
could prevent the Agency from achieving its objective to remove older diesel buses and
replace them with clean buses. The increased demand on utility companies may impact the
timeliness of replacing diesel buses.

While utility infrastructure is not funded through the program, we found that there could be
delays in utilities constructing the needed charging stations to make the buses fully
operational in a timely manner. The EPA needs to ensure that utilities have constructed
and connected charging stations in a timely manner so that school districts' school bus
fleets, purchased through the EPA's 2022 Clean School Bus Rebate Program, are
functional. Utility installation delays must be addressed for taxpayers to reap timely health
and environmental benefits of the $5 billion invested in this program through the IIJA.

We did not make any recommendations in this report.

Increased power supply demands could delay electric
school bus deployment.

To support these EPA mission-
related efforts:

•	Improving air quality.

•	Operating efficiently and
effectively.

To address this top EPA
management challenge:

•	Managing grants, contracts, and
data systems.

Address inquiries to our public
affairs office at (202) 566-2391 or
OIG.PublicAffairs@epa.gov.

List of OIG reports.


-------
OFFICE OF INSPECTOR GENERAL

U.S. ENVIRONMENTAL PROTECTION AGENCY

December 27, 2023
MEMORANDUM

SUBJECT: The EPA Clean School Bus Program Could Be Impacted by Utility Delays
Report No. 24-P-0012

FROM: Sean W. O'Donnell, Inspector General

TO:	Joseph Goffman, Principal Deputy Assistant Administrator Performing Delegated Duties

of Assistant Administrator
Office of Air and Radiation

This is our report on the subject audit conducted by the U.S. Environmental Protection Agency Office of
Inspector General. This project number for this audit was QA-FY23-0051. This report contains no
recommendations. If you submit a response, it will be posted on the OIG's website, along with our
memorandum commenting on your response. Your response should be provided as an Adobe PDF file
that complies with the accessibility requirements of section 508 of the Rehabilitation Act of 1973, as
amended. The final response should not contain data that you do not want to be released to the public; if
your response contains such data, you should identify the data for redaction or removal along with
corresponding justification.

We will post this report to our website at www.epaoig.gov.


-------
Table of Contents

Purpose	1

Background	1

Infrastructure Investment and Jobs Act Provides Funding for the Clean School Bus Program 1

The 2022 Clean School Bus Rebate Program	2

Electric School Bus Market	4

Responsible Offices	4

Scope and Methodology	4

Results	5

No Indication that Supply Chain Delays Have Significantly Impacted the EPA's Ability

to Award and Disburse Funds	5

The EPA Provided Utility Resources During the Rebate Application Process, but Did

Not Require Early Engagement with Utilities	6

Increased Demand on Bus Charger Manufacturers and Utility Companies May Impact
the Timeliness of Replacing Diesel Buses and Achieving Program Environmental
Health Benefits	7

Conclusions	9

A Distribution	10

24-P-0012	i


-------
Purpose

The U.S. Environmental Protection Agency Office of Inspector General initiated this audit to determine
whether potential supply chain or production delays could impact the EPA's efforts to disburse and
manage Clean School Bus Program funds pursuant to section 71101 of the Infrastructure Investment and
Jobs Act.

Top management challenge addressed

This audit addresses the following top management challenge for the Agency, as identified in OIG
Report No. 24-N-0008. The EPA's Fiscal Year 2024 Top Management Challenges, issued
November 15, 2023:

• Managing contracts, grants, and data systems.

Background

Infrastructure Investment and Jobs Act Provides Funding for the Clean School
Bus Program

President Biden signed the Infrastructure Investment and Jobs Act, referred
to as the IIJA, into law on November 15, 2021. The IIJA amended the Clean
School Bus Program established by section 741 of the Energy Policy Act of
2005.1 The IIJA provides $5 billion over five years, or through 2026, to
replace existing school buses, most of which operate on diesel fuel, with
clean and zero-emission school buses.'

The Clean School Bus Program uses several funding mechanisms to replace
school buses, including grants, rebates, and contracts. In 2022, the program
offered rebates to school districts to purchase clean school buses. Under Clean school bus at charging station,
this rebate program, a rebate is a payment from the EPA to an eligible entity	Photo)

to subsidize the purchase of a zero emission or clean school bus, as well as eligible infrastructure, that
meets the Clean School Bus Program's requirements.

Under the IIJA, the U.S. Department of Energy's Renew America's Schools Program was appropriated
$500 million for a grant program for K-12 public schools. These grants may be used for energy
efficiency, renewable energy, and alternative fuel infrastructure investments at K-12 schools. These
grants may also be used for innovative energy technology packages, which cover alternative fueled
vehicle infrastructure on school grounds, as well as the purchase or lease of alternative fueled vehicles,
including clean school buses, for schools.

1	42 U.S.C. § 16091.

2	A zero-emission school bus produces zero exhaust emissions of air pollutants and greenhouse gases. A clean
school bus is either a zero-emission bus or it reduces emissions by operating entirely or in part using an alternative
fuel, such as propane or natural gas.

24-P-0012

1


-------
The 2022 Clean School Bus Rebate Program

In 2022, the EPA offered $500 million in initial funding for the Clean School Bus Program.3 The EPA
solicited rebate applications from school districts through the 2022 Clean School Bus Rebate Program
from May through August 2022. According to the EPA, the Agency received around 2,000 applications
requesting nearly $4 billion for over 12,000 buses. Given the overwhelming demand from school
districts across the country, the EPA prioritized school districts in low-income communities, tribal
nations, and territories. The EPA announced in September 2022 that it will nearly double the amount of
available funding to $965 million for the rebate program.

The maximum rebate amount per bus depended on the bus fuel type and the bus size, as well as
whether the school district receiving the buses met one or more prioritization criteria. For example, as
set forth in Table 1, the Clean School Bus Program will subsidize the cost of a zero-emission school bus,
but only a portion of a clean school bus, such as a compressed natural gas school bus.

Table 1: Maximum bus funding amount per replacement school bus



Replacement Bus Fuel Type and Size

Bus type

Zero Emissions
Class 7+

Zero Emissions
Class 3-6

CNG
Class 7+

CNG
Class 3-6

Propane
Class 7+

Propane
Class 3-6

Amount of rebate

$375,000

$285,000

$45,000

$30,000

$30,000

$25,000

Note: This table displays maximum funding levels. The EPA will not disburse rebate funds in excess of the actual
cost of the replacement bus. CNG = compressed natural gas.

Source: 2022 Clean School Bus Rebates Program Guide. (EPA table)

The EPA developed an online system to facilitate the 2022 rebate application process. Applicants could
request funds to replace up to 25 buses. The maximum rebate amount per bus, which could be no more
than $375,000, depended on the replacement bus fuel type, the replacement bus size, and priority
status of the school district as defined in the EPA's 2022 Clean School Bus Rebates Program Guide.

The EPA notified the selectees in October 2022. As of July 17, 2023, the EPA approved rebate
applications for 380 school districts to purchase charging units, which are approximately $20,000 each,
and 2,441 vehicles, including 2,319 electric buses, which are approximately up to $437,000 each;4
116 propane buses, which are approximately $105,000 each; and six compressed natural gas buses,
which are approximately over $125,000 each.5 Selectees had to submit purchase orders for both the
buses and the charging units by April 2023 or request an extension. Table 2 shows the EPA's planned

3	In 2023, the EPA established a Clean School Bus grant program funding opportunity, accepting applications from
April 24 to August 22, 2023, and is implementing another rebate program, accepting applications from
September 28, 2023 to January 31, 2024.

4	Electric School Bus U.S. Market Study and Buyer's Guide, World Resources Institute, issued June 2022.

5	The State of Sustainable Fleets 2022 Market Brief, GNA Clean Transportation and Energy Consultants, issued
May 2022.

24-P-0012

2


-------
timeline for the rebate process as of May 2022. Regardless of extensions, the project completion date
for this rebate program is October 2024, which is when buses are required to be in operation.

Table 2: 2022 Clean School Bus Rebate Program timeline

I Activity

Dates I

The EPA opened the online system and accepted applications submitted via rebate
forms.

May 20-August 19, 2022

The EPA reviewed applications and began the selection process.

September 2022

The EPA notified applicants of selection. Selectees proceeded with purchasing new
buses and eligible charging infrastructure.

October 2022

Selectees submitted payment requests with purchase orders and proof that new buses
and eligible charging infrastructure were ordered.

October 2022-April 2023

Deadline for selectees to receive new buses, install eligible charging infrastructure,
replace old buses, and submit closeout forms

October 2024

Source: EPA Clean School Bus Program timeline. (EPA OIG table)

The EPA can award up to 100 percent of the cost of the replacement bus and charging infrastructure.
According to the 2022 Clean School Bus Rebates Program Guide, selected applicants for replacement
electric school buses would be allocated funding for charging infrastructure installations. The EPA
limited funding for infrastructure to installations between the electrical meter and the charging port, as
shown in Figure 1. This can include charging equipment; design and engineering; and installation costs
such as trenching, wiring and electrical upgrades, labor, and permitting. EPA funds may not be used for
any infrastructure costs associated with work on the utility's side of the electrical meter, but the
Department of Energy's program can fund infrastructure costs that the EPA funds cannot, like
infrastructure on school grounds. Figure 1 illustrates eligible and noneligible utility expenses for EPA
funds.

Figure 1: Noneligible and eligible expenses for the 2022 Clean School Bus Rebate

24-P-0012

3


-------
Electric School Bus Market

The market for electric vehicles has grown rapidly and is expected to continue to grow. Increased
consumer interest, government policies, and buy-in from the automotive industry all contribute to the
growth in the electric vehicle market. The IIJA not only provided funding for clean school buses, but also
to upgrade the nation's power grid and to build a nationwide charging network. The increase in electric
vehicles will bring corresponding demands for supplies for both the buses and the charging
infrastructure to power them. The World Resources Institute, a global nonprofit organization that,
among other things, tracks electric school bus initiatives, has tracked the number of electric school
buses in the United States. According to the World Resources Institute, there were 1,398 electric school
buses that were either ordered, delivered, or operating as of December 2022. There are now
5,612 electric school buses that are ordered, delivered, or operating, almost double the number of
buses since the release of the World Resources Institute's September 2022 dataset. The majority of this
growth is due to the EPA Clean School Bus Rebate Program, which awarded over $900 million for more
than 2,400 electric school buses to 389 school districts, expected to be operational by October 2024.

Responsible Offices

The Office of Air and Radiation develops national programs, policies, and regulations for controlling air
pollution and radiation exposure. Within Office of Air and Radiation, the Office of Transportation and Air
Quality's programs address emissions from a range of mobile sources: cars and light trucks, large trucks
and buses, farm and construction equipment, lawn and garden equipment, marine engines, aircraft, and
locomotives. The office's Transportation and Climate Division is responsible for administering the Clean
School Bus Program.

Scope and Methodology

We conducted this audit from March to September 2023 in accordance with generally accepted
government auditing standards. Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on
our audit objectives. We believe that the evidence obtained provides a reasonable basis for our findings
and conclusions based on our audit objectives. For this audit, we answered the objective in relation to
electric or zero emission buses, which account for 95 percent of the clean school buses receiving
rebates. We did not review implementation of low-emission or clean buses, such as propane and
compressed natural gas.

To answer our objective, we interviewed staff from the Office of Transportation and Air Quality, four
electric bus manufacturers, six bus suppliers, two school districts that purchased large volumes of buses,
two utility companies, and two charger companies. We obtained and analyzed data from the Clean
School Bus database maintained by the Office of Transportation and Air Quality.

24-P-0012

4


-------
Results

We concluded that there were no significant supply chain issues or production delays that impacted the
EPA's efforts to disburse funds through the first round of the Clean School Bus Program's funding.
However, the EPA's 2022 rebate application did not require applicants to coordinate with their utility
companies before applying for rebates. As a result, the Agency may be unable to effectively manage and
achieve the program mission unless utility companies can meet increasing power supply demands for
electric school buses.

No Indication that Supply Chain Delays Have Significantly Impacted the EPA's
Ability to Award and Disburse Funds

We did not find indications that supply chain or production delays have impacted the EPA's efforts to
disburse funds through the Clean School Bus Rebate Program. First, Agency market research for the
Clean School Bus Rebate Program concluded that supply chains would not cause delays. The Agency
held 24 meetings with major bus manufacturers from February 9, 2022, through January 30, 2023, when
developing the program. In these meetings, the Agency and stakeholders discussed building the electric
school bus market; manufacturing capacity; delivery timelines; charging infrastructure; utilities; and
domestic preference requirements, which require federal awardees to use domestically sourced
products and materials in certain situations. These manufacturers expressed confidence in meeting
demand since they already began increasing electric bus manufacturing prior to the program.

Second, as part of the program design, the EPA is allowing school districts two years to demonstrate that
they received their new buses and eligible charging infrastructure and have replaced their old buses. The
Agency chose this time frame to accommodate potential supply chain delays or long delivery times, as
well as to allow time for fleet owners to get comfortable with their new buses and related technology
prior to scrapping their existing fleet. The Agency stated that "[a]s with any product, there may be
supply chain issues that impact the broader economy and could result in delays delivering buses."
However, the EPA has planned for this type of potential delay and included in the program guide an
allowance for selectees to request extensions for submitting purchase orders or confirming bus delivery:

Selectees can request extensions to the project period deadline. EPA will review these
requests on a case-by-case basis and may grant extensions if sufficient justification is
provided. For example, EPA may grant an extension if a bus is on order but is
experiencing manufacturing or delivery delays.

The EPA is requiring recipients to provide purchase orders with delivery or completion date
information.6 In addition, the EPA is reviewing all rebate applications to ensure that delivery dates are
within the prescribed timeline. If rebate applicants cannot provide delivery date information, they can

6 As the inspector general explained in his testimony to the House Energy and Commerce Committee on
September 13, 2023, these are not rebates in the traditional sense because once a recipient provides a Payment
Request Form with a copy of a purchase order, the EPA will issue the award to the recipient's bank account before
the bus has been delivered in order to subsidize the purchase of the buses.

24-P-0012

5


-------
request an extension. As of July 31, 2023, the program has processed and paid rebates to 189 out of
approximately 380 recipients, which represents $309 million. The Agency expects to process the rebates
as quickly as possible.

Third, the major electric bus manufacturers we interviewed indicated that supply chain issues would not
impact the EPA's ability to award funds because suppliers were already ramping up to meet the
increased demand, and delivery times would take between six to 12 months, which is within the time
the EPA allotted. Another manufacturer had already started deliveries under the program in June 2023.
This manufacturer stated that delivery times would depend on the type of school bus; vehicle
specifications; destination, as all states have different requirements; and when the order is placed, but
that all the program-funded buses were scheduled to be delivered before the October 2024 deadline.

To properly handle any possible increase in demand for the electric buses, one manufacturer stated that
it has added a new plant, while another is hoping to open a new manufacturing facility. Two
manufacturers have hired additional employees. The remaining three manufacturers stated that they
did not have any immediate plans to hire new staff but may do so depending on increased market
demand. In addition, four of the manufacturers stated that they always hire staff that are trained to
work on all types of school buses they build, including diesel, electric, and propane. While the
manufacturers we interviewed were confident that they could meet the increased demand driven by
the Clean School Bus Program, recent public reporting has indicated that some of those manufacturers
are experiencing significant supply chain issues resulting in delayed delivery of new school buses. This
might represent a broader supply chain issue; however, we did not find indications that it has impacted
the EPA's efforts to disburse funds.

Agency staff is monitoring clean school bus delivery dates. The Office of the Administrator has contacted
all the major electric school bus manufactures to request a delivery forecasting document from each
one. This document identifies the school district, applicant type of bus they are purchasing, and
estimated delivery dates. The manufacturers are in the process of completing and returning these
documents to the Agency.

The EPA Provided Utility Resources During the Rebate Application Process, but
Did Not Require Early Engagement with Utilities

Although the EPA's 2022 rebate application did not require applicants to coordinate with their utility
companies before applying for rebates, the Agency stated that it encouraged applicants to do so during
program webinars. Due to some applicants facing challenges in utility coordination, among other things,
many applicants requested extensions to submit their purchase order documentation to allow time to
conduct such coordination.

Obtaining detailed project review and buy-in from utilities to establish the necessary infrastructure to
support the electric panel, charging, and electric bus was also not a requirement for the 2022 rebate
program. The impact of utility issues on the program will not be fully known until the 2022 selectees
close out their rebates, which is not scheduled until October 2024. According to the program guide:

24-P-0012

6


-------
To facilitate coordination between applicants and utilities, the EPA has partnered
with Edison Electric Institute and the Beneficial Electrification League on an "Electric
Utility Pledge." This pledge includes a set of commitments electric utility companies
can take to proactively help school districts with the deployment of electric school
buses, including providing technical support and guidance on existing rate structures,
interconnection requirements, costs, and timelines, as well as identifying the right
type of charging infrastructure to meet their needs.

On September 28, 2023, the Agency announced the second Clean School Bus rebate program.7 Under
this new rebate program, all applicants must submit a Utility Partnership Agreement to verify that the
school district's electric utility provider is aware of the school district's rebate application. Proactive and
ongoing communication between the school district and its local electricity providers is critical to
successful infrastructure deployment.

Increased Demand on Bus Charger Manufacturers and Utility Companies May
Impact the Timeliness of Replacing Diesel Buses and Achieving Program
Environmental Health Benefits

We identified concerns with delays related to the infrastructure needed to support the bus charger
manufacturers and the increased demand on utilities. Entities we interviewed identified concerns about
possible delays with utility providers bringing the necessary power lines and transformers to the school
districts for charging the buses. One utility company we interviewed stated while it had experience with
electric vehicles and buses, it did not have experience at the projected scale. One utility company
explained that it could take nine months to two years to complete construction. The most common
infrastructure upgrades needed to support the bus chargers are transformers, electrical lines, and
switch changers. This utility noted that early communication between the companies and school
districts, such as prior to applying for funding, is important for the execution of this program.

The process for establishing charging stations and connecting them to power lines could take
approximately 12 to 24 months, according to the World Resources Institute's Electric School Bus Buyers
Guide. The process, illustrated in Figure 2, is as follows:

•	The utility conducts a site assessment, which could take up to a month, to determine the
location of the chargers.

•	Utility engineers conduct a design review and set-up, which could take a couple of months.

•	The utility must contract the construction of the charging station, which could take up to two
years.

7 This represents the EPA's third round of funding under the Clean School Bus Program. The EPA had previously
announced the second round of Clean School Bus Program funding on April 24, 2023, in the form of grants.

24-P-0012

7


-------
Figure 2: Illustration of timeline for utility construction to
support electric bus charging stations.

Source: EPAOIG image.

Additionally, according to the stakeholders we interviewed, infrastructure to support fleets of 25 buses
or more require a more challenging electrical set-up, which can lead to more delays. Clean bus charging
sites that need to support 25 buses or more often require a different transformer and switch gear,
which take a year to construct. A utility provider we interviewed explained that it is hard to find
transformers in the United States and it has backlogged orders because of the high demand. The EPA's
2022 rebate program issued rebates to 39 school districts to purchase 21-25 buses each. These large
bus purchases constituted about 36 percent of rebate funds. Figure 3 illustrates the percentage of funds
and number of rebates issued for the 2022 program.

Figure 3: Distribution of the 2022 Clean School Bus Rebate
Program awards

50

42%



40







36%

30





23%





20













10













Small (1-10 buses)	Medium (11-20 buses)	Large (21-25 buses)

Number of Electric Buses Awarded per District

Note: Percentages are rounded.

Source: EPA Clean School Bus Program, Second Report to Congress, Fiscal
Year 2022. (EPA image)

24-P-0012

8


-------
The EPA stated that it was aware that school districts working with utilities and installing charging
infrastructure may be challenging, particularly for those school districts looking to add more than ten
clean buses to their fleet. Infrastructure needs are less of an issue for applicants looking to add a small
number of buses. School bus manufacturers highlighted that, in their experience, installation could take
months for customers purchasing clean buses. According to the EPA, a project period of two years was
implemented for the rebate process to allow for bus delivery delays as well as charging equipment
installation.

Conclusions

In our discussions with the EPA and various stakeholders, we concluded that there were no significant
supply chain issues or production delays that impacted the EPA's efforts to disburse funds through the
first round of funding for the Clean School Bus Rebate Program. However, the Agency may be unable to
effectively achieve program goals unless it can ensure that school districts will be able to establish the
infrastructure necessary to support clean bus and charging purchases. There could be delays in utilities
constructing the needed charging stations to make the buses fully operational in a timely manner. While
early coordination with utilities is not a requirement, it could prevent the Agency from achieving its
objective to remove older diesel buses and replace them with clean buses. The increased demand on
manufacturers and utility companies may impact the timeliness of replacing diesel buses and ultimately
may delay program health and environmental benefits.

We issued no recommendations in this report.

24-P-0012

9


-------
Distribution

The Administrator

Deputy Administrator

Chief of Staff, Office of the Administrator

Agency Follow-Up Official (the CFO)

Assistant Administrator for Air and Radiation

Agency Follow-Up Coordinator

General Counsel

Principal Deputy Assistant Administrator for Air and Radiation
Deputy Assistant Administrator for Stationary Sources, Office of Air and Radiation
Deputy Assistant Administrator for Mobile Sources, Office of Air and Radiation
Deputy Assistant Administrator for Air and Radiation

Associate Administrator for Congressional and Intergovernmental Relations
Associate Administrator for Public Affairs

Director, Office of Transportation and Air Quality, Office of Air and Radiation
Director, Office of Continuous Improvement, Office of the Chief Financial Officer
Office of Policy OIG Liaison
Office of Policy GAO Liaison

Audit Follow-Up Coordinator, Office of the Administrator
Audit Follow-Up Coordinator, Office of Air and Radiation

24-P-0012


-------
Whistleblower Protection

U.S. Environmental Protection Agency
The whistleblower protection coordinator's role
is to educate Agency employees about
prohibitions against retaliation for protected
disclosures and the rights and remedies against
retaliation. For more information, please visit
the OIG's whistleblower protection webpage.

Contact us:

Congressional Inquiries: OIG.CongressionalAffairs(5)epa.gov

Media Inquiries: OIG.PublicAffairs@epa.gov
line EPA OIG Hotline: OIG.Hotline@epa.gov

-§Tg Web: epaoig.gov

Follow us:

X (formerly Twitter): (5)epaoig

Linkedln: linkedin.com/company/epa-oig
YouTube: voutube.com/epaoig
[01 Instagram: @epa.ig.on.ig


-------