Community Update #17
Pompton Lakes Study Area
Pompton Lakes, New Jersey

Upland Soil Areas Excavation/Dredging

Community Update

September 2016

EPA CLEANUP ACTIVITIES

Basic Site Information

The Upland Soil Areas excavation is

complete with the exception of one
small area (Area Al) totaling ap-
proximately 20 cubic yards (CY).
Mechanical dredging of approxi-
mately 19,300 CY of impacted sedi-
ment (containing mercury/lead/other
metals) in Area A and the Island
Area will begin once an access chan-
nel is dredged between the Uplands
Soil Areas and Area A/Island Area.

Work is being performed by Seven-
son Environmental Services, Inc., a
contractor for The Chemours Com-
pany FC, LLC (Chemours) with
EPA/NJDEP oversight.

Boroiiph of Pompton Lakes

http://www.pomptonlakesgov.com

Questions? Please Contact:
EPA Remedial Project Manager

Perry Katz

(212)637-4426
katz.ira-perry@epa.gov

EPA Community Involvement
Coordinator

Pat Seppi

(646)369-0068

This is EPA's seventeenth update to inform the community of the
progress of activities related to the portion of the Pompton Lakes
Study Area known as the Upland Soil Areas and the 3 acres of the
lake (designated Area A and the Island Area) that will be mechani-
cally dredged.

The shallow depth of the Acid Brook Delta between the Upland Soil
Areas and Area A/Island Area necessitated mechanically dredging
an access channel to those two areas. Dredging the access channel is
underway. The project continues to be on schedule.

This update contains a total of three pages including this page, a
page of with some additional notes and a page with photographs.

ACTIVITIES—WEEK OF SEPTEMBER 12TH

~	Transported/disposed of 566 loads of impacted material
(excavated soil/dredged sediment for access channel) a/o Sep-
tember 15th

~	Evaluating most effective method to excavate Uplands Soil Area
Al (small area approx. 20 CY), constrained by a sewer line/tree

~	Continue mobilization of water-based dredging equipment

~	Initiate mechanical dredging of access channel water-side

~	Processing/load-out of dredged sediment for access channel

~	Continued perimeter monitoring—data on website (http://
www.pomptonlakesworks.com/pompton-lake-project/
environmental-monitoring/

~	No exceedances of dust/ mercury vapor/turbidity action levels
during monitoring associated with site activities

UPCOMING ACTIVITIES—WEEK OF SEPTEMBER 19TH

~	Continue dredging of an access channel from water-based me-
chanical dredge

~	Continue processing/loading/off-site disposal of dredged sedi-
ment

~	Continue assessment/testing of water from dredged sediment to
determine treatment modifications

~	Initiate excavation approach for Area Al by removal of trees
atop Area Al

~	Continued perimeter monitoring of dust/mercury/turbidity levels

www3.epa.gov/region02/waste/dupont_pompton/index.html


-------