FINAL

Focused Feasibility Study Report

Upper Basin of the Coeur d'Alene River,
Bunker Hill Mining and Metallurgical Complex

Superfund Site

Volume 3

Appendices A through D

&EPA

United States
Environmental Protection
Agency Region 10

AES10 Task Order 49
Architect and Engineering Services
Contract No. 68-S7-04-01

Prepared by

CH2MHILL

August 2012


-------

-------
Contents

Appendix A	Groundwater Modeling Analysis

Appendix B	Predictive Analysis Methodology and Results

Appendix C	Typical Conceptual Design (TCD) Schematics

Appendix D	Cost Analysis Documentation


-------

-------
APPENDIX A

Groundwater Modeling Analysis


-------

-------
Contents

Section	Page

Contents	A-iii

Acronyms and Abbreviations	A-vii

Groundwater Modeling Analysis	A-l

A.l Introduction	A-l

A.2 Model Updates	A-2

A.3 Additional Model Calibrations	A-4

A.3.1 Steady-State Baseflow Calibration	A-4

A.3.2 Steady-State 7Q10 Calibration	A-5

A.3.3 Steady-State 90th Percentile Flow Tier Calibration	A-6

A.3.4 Transient Annual Calibration	A-7

A.4 Methodology for Development of Metals Loading Budget	A-10

A.4.1 Baseline Metals Loadings — SFCDR Model	A-ll

A.4.2 Baseline Metals Loadings — Canyon Creek Model	A-12

A.5 Application of Groundwater Flow Models to Remedial Alternatives

for OUs 2 and 3	A-13

A.5.1 OU 2 Alternative (a)	A-14

A.5.2 OU 2 Alternative (b)	A-14

A.5.3 OU 2 Alternative (c)	A-15

A.5.4 OU 2 Alternative (d)	A-16

A.5.5 OU 2 Alternative (e)	A-17

A.5.6 Groundwater Components of OU 3 Remedial Alternatives for

the Mainstem SFCDR Watershed, Segment 01	A-18

A.5.7 Groundwater Components of OU 3 Remedial Alternatives for

Woodland Park	A-19

A.6 Simulation Results	A-19

A.6.1 Baseflow Conditions	A-20

A.6.2 7Q10 Conditions	A-22

A.6.3 90th Percentile Flow Conditions	A-23

A.6.4 Average Annual Conditions	A-23

A.7 OU 2 Sensitivity Analysis	A-24

A.8 Additional Model Uncertainty	A-26

A.9 References	A-26

A-iii


-------
CONTENTS (CONTINUED)

Figures

A-l Canyon Creek Model Grid
A-2 SFCDR Model Grid

A-3 Upper Aquifer Transmissivity, Bunker Hill Box
A-4 Total Aquifer Transmissivity, Osburn Flats

A-5 Simulated versus Observed Groundwater Elevations - Baseflow Conditions

A-6a Residuals between Measured and Simulated Groundwater Elevations, Western
Bunker Hill Box, Baseflow Conditions

A-6b Residuals between Measured and Simulated Groundwater Elevations, Eastern
Bunker Hill Box, Baseflow Conditions

A-6c Residuals between Measured and Simulated Groundwater Elevations, Osburn Flats,
Baseflow Conditions

A-7 Simulated versus Observed Groundwater Elevations - 7Q10 Conditions

A-8a Residuals between Measured and Simulated Groundwater Elevations, Western
Bunker Hill Box, 7Q10 Conditions

A-8b Residuals between Measured and Simulated Groundwater Elevations, Eastern
Bunker Hill Box, 7Q10 Conditions

A-9 Simulated versus Observed Groundwater Elevations - 90th Percentile Flow Conditions

A-lOa Residuals between Measured and Simulated Groundwater Elevations, Western
Bunker Hill Box, 90th Percentile Flow Conditions

A-lOb Residuals between Measured and Simulated Groundwater Elevations, Eastern
Bunker Hill Box, 90th Percentile Flow Conditions

A-lOc Residuals between Measured and Simulated Groundwater Elevations, Osburn Flats,
90th Percentile Flow Conditions

A-ll Simulated versus Observed Groundwater Elevations - Canyon Creek,
90th Percentile Flow Conditions

A-12 Residuals between Measured and Simulated Groundwater Elevations, Canyon
Creek, 90th Percentile Flow Conditions

A-13a	Simulated versus Measured Groundwater Elevations - Bunker Hill Box

A-13b	Simulated versus Measured Groundwater Elevations - Bunker Hill Box

A-13c	Simulated versus Measured Groundwater Elevations - Bunker Hill Box

A-13d	Simulated versus Measured Groundwater Elevations - Bunker Hill Box

A-13e	Simulated versus Measured Groundwater Elevations - Bunker Hill Box

A-13f	Simulated versus Measured Groundwater Elevations - Bunker Hill Box

A-13g	Simulated versus Measured Groundwater Elevations - Bunker Hill Box

A-13h	Simulated versus Measured Groundwater Elevations - Bunker Hill Box/ Osburn Flats

A-iv


-------
CONTENTS (CONTINUED)

A-13i	Simulated versus Measured Groundwater Elevations - Osburn Flats

A-14	Simulated versus Measured Groundwater Elevations - Canyon Creek Watershed

A-15	OU 2 Mass Loading Reaches

A-16	Woodland Park Mass Loading Reaches

A-17	OU 2 Alternative (a): Minimal Stream Lining

A-18	OU 2 Alternative (b): Extensive Stream Lining

A-19	OU 2 Alternative (c): French Drains

A-20	OU 2 Alternative (d): Stream Lining/French Drain Combination

A-21	OU 2 Alternative (e): Extensive Stream Lining/French Drain Combination

A-22 Groundwater Components of OU 3 Remedial Alternatives for the Mainstem SFCDR
Watershed, Segment 01

A-23 Groundwater Components of Updated Remedial Actions for Woodland Park

A-24 Simulated Upstream Groundwater Flowlines from the SFCDR, No Action, Baseflow
Conditions

A-25 Simulated Upstream Groundwater Flowlines from the SFCDR, OU 2 Alternative (a),
Baseflow Conditions

A-26 Simulated Upstream Groundwater Flowlines from the SFCDR, OU 2 Alternative (b),
Baseflow Conditions

A-27a Simulated Upstream Groundwater Flowlines from the SFCDR, OU 2 Alternative (c),
Baseflow Conditions

A-27b Simulated Upstream Groundwater Flowlines from French Drains, OU 2 Alternative (c),
Baseflow Conditions

A-28a Simulated Upstream Groundwater Flowlines from the SFCDR, OU 2 Alternative (d),
Baseflow Conditions

A-28b Simulated Upstream Groundwater Flowlines from French Drains, OU 2 Alternative (d),
Baseflow Conditions

A-29 Simulated Upstream Groundwater Flowlines from French Drains, OU 2 Alternative (e),
Baseflow Conditions

A-30 Simulated Upstream Groundwater Flowlines from the SFCDR, Mainstem SFCDR
Watershed, Segment 01, No Action, Baseflow Conditions

A-31 Simulated Upstream Groundwater Flowlines from French Drains, Mainstem SFCDR
Watershed, Segment 01, Baseflow Conditions

A-32 Simulated Upstream Groundwater Flowlines from Canyon Creek, No Action,
Baseflow Conditions

A-33 Simulated Upstream Groundwater Flowlines from French Drains, Groundwater

Components of Updated Remedial Actions for Woodland Park, Baseflow Conditions

A-34 Results of the OU 2 Sensitivity Analysis

A-v


-------
CONTENTS (CONTINUED)

Tables

A-l Measured Baseflow Groundwater and Surface Water Elevations in Monitoring Pairs
- Government Gulch

A-2 Final PEST Parameter Multipliers

A-3 Simulated versus Observed Vertical Head Gradients in Well Pairs - Bunker Hill Box

A-4 Simulated versus Observed Vertical Head Gradients in Well Pairs - Osburn Flats

A-5 Comparison of Simulated Stream Gains and Losses to Data Measured During the
2008 Groundwater-Surface Water Interaction Studies

A-6 Simulated Stream Stage Differences for the 90th Percentile Flow Calibration -
SFCDR Model

A-7 Monthly Multipliers for Deep Percolation of Precipitation - SFCDR Model

A-8 Monthly Multipliers for Deep Percolation of Precipitation - Canyon Creek Model

A-9	Average Dissolved Zinc Concentrations in Groundwater in Woodland Park,

Fall 2006

A-10	Net Remedial Effectiveness Factors for Woodland Park Source Control Actions

A-ll	Model-Simulated Flows - Baseflow Conditions

A-12	Simulated Dissolved Zinc Load - Baseflow Conditions

A-13	Model-Simulated Flows - 7Q10 Conditions

A-14	Simulated Dissolved Zinc Load - 7Q10 Conditions

A-15	Model-Simulated Flows - 90th Percentile Flow Conditions

A-l6	Simulated Dissolved Zinc Load - 90th Percentile Flow Conditions

A-l7	Model-Simulated Flows - Average Annual Conditions

A-18	Simulated Dissolved Zinc Load - Average Annual Conditions

A-19	Results of the OU 2 Sensitivity Analysis

A-vi


-------
Acronyms and Abbreviations

bgs

below ground surface

Box

Bunker Hill Box

cfs

cubic feet per second

CIA

Central Impoundment Area

CTP

Central Treatment Plant

feet/ day

feet per day

FFS

Focused Feasibility Study

ft/ft

foot per foot

lb/ day

pound(s) per day

mg/L

milligram(s) per liter

msl

mean sea level

NM

not measured

O&M

operation and maintenance

OU

Operable Unit

PEST

parameter estimation

REF

remedial effectiveness factor

RMS

root mean squared error

ROD

Record of Decision

SFCDR

South Fork of the Coeur d'Alene River

SVNRT

Silver Valley Natural Resource Trust

USEPA

U.S. Environmental Protection Agency

USGS

U.S. Geological Survey

A-vii


-------

-------
APPENDIX A

Groundwater Modeling Analysis

A.1 Introduction

From 2002 to 2005, the National Academy of Sciences (NAS) performed an independent
evaluation of the Record of Decision (ROD) for Operable Unit 3 (OU 3) at the Bunker Hill
Mining and Metallurgical Complex Superfund Site (NAS, 2005). The study concluded that
although adequate characterization of the extent of metals contamination in soil, sediments,
and surface water was presented, the major source of dissolved metals to the surface water
system—groundwater discharge—was not adequately characterized or fully addressed. In
response to these concerns, it was determined by the U.S. Environmental Protection Agency
(USEPA) that it was necessary to develop a quantitative tool that could be used to evaluate
the spatially varying components of the water budget and dissolved metals loading budget.
Two numerical groundwater flow models were developed for the Canyon Creek Watershed
(CH2M HILL, 2007) and the South Fork of the Coeur d'Alene River (SFCDR) Watershed
(CH2M HILL, 2009b) to better characterize the distribution of dissolved metals loading from
the groundwater system under current conditions, and to evaluate various potential
remedial actions. Specific objectives of the groundwater modeling efforts included the
following:

•	Characterize the hydrogeology of the SFCDR and Canyon Creek Watersheds.

•	Develop a quantitative representation of stratigraphy and aquifer properties throughout
the SFCDR and Canyon Creek Watersheds.

•	Quantify the distribution and extent of groundwater-surface water interaction.

•	Develop water budgets for selected areas of the SFCDR and Canyon Creek Watersheds.

•	Develop dissolved metals loading budgets for selected areas of concern within the
SFCDR and Canyon Creek Watersheds.

Development of the Canyon Creek Watershed groundwater flow model (hereafter referred
to as the Canyon Creek Model) began in 2006 as part of the Canyon Creek Hydrologic Study
(CH2M HILL, 2007). The purpose of this study was to better understand the hydrologic
system within the Canyon Creek Watershed, as Canyon Creek represents one of the largest
point discharges of dissolved metals contamination to the greater Coeur d'Alene River
system. The Canyon Creek Model was developed using MicroFEMฎ, an integrated
groundwater modeling software program (Hemker and Nijsten, 2003). The finite-element
grid consists of 42,086 surface nodes and 83,785 elements in each of the five model layers
(Figure A-l). (The figures referenced in the text of this appendix are provided following
Section A.9) Nodal spacing was varied from as little as 2 feet near groundwater monitoring
well clusters and 20 feet in the Woodland Park area to as much as approximately 850 feet
near the model boundary. The lateral extent of the model grid represents the approximate
extent of the Canyon Creek Watershed, roughly 22 square miles, as defined by the
topographic divide (the ridgeline). The five model layers were discretized to simulate

A-1


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

aquifer systems in the alluvium, the weathered bedrock horizon, and the bedrock system.
Full documentation of the Canyon Creek Model development is presented in the Canyon
Creek Hydrologic Study Report (CH2M HILL, 2007).

The grid for the SFCDR Watershed groundwater flow model (hereafter referred to as the
SFCDR Model) consists of 134,535 surface nodes and 268,631 elements in each of the seven
model layers (Figure A-2). Nodal spacing was refined to as little as 25 feet in areas where
analysis of remedial actions was anticipated. The lateral extent of the model grid represents
the approximate extent of the SFCDR Watershed, roughly 300 square miles, as defined by
the topographic divide (the ridgeline). The seven model layers were discretized to simulate
the alluvial aquifer systems of the SFCDR and major tributary valleys, the weathered
bedrock horizon, and the underlying bedrock system. Full groundwater flow model
documentation is presented in South Fork of the Coeur d'Alene River Watershed: Basinwide
Groundwater Flow Model Documentation (CH2M HILL, 2009b).

The purpose of this appendix is to document updates to the SFCDR Model that have taken
place since the documentation was published (no updates have been made to the Canyon
Creek Model), and to describe the application of the two groundwater flow models to the
evaluation of remedial alternatives for OUs 2 and 3 that are developed and described in this
Focused Feasibility Study (FFS) Report for the Upper Basin of the Coeur d'Alene River. The
remedial actions evaluated by the groundwater flow models and documented in this
appendix constitute all substantive groundwater actions evaluated in the FFS. There are
three main alluvial areas in the Upper Basin for which groundwater actions are evaluated:
(1) the Mainstem SFCDR Watershed, Segment 01, which includes the alluvial floodplain of
the SFCDR between Wallace and Elizabeth Park; (2) the Woodland Park area of Canyon
Creek; and (3) the segment of the SFCDR that passes through OU 2 between Elizabeth Park
and Pinehurst.

A.2 Model Updates

The calibrated SFCDR Model, as documented in South Fork of the Coeur d'Alene River
Watershed: Basinwide Groundwater Flow Model Documentation (CH2M HILL, 2009b), was
refined to improve both the characterization of the groundwater-surface water interaction
within Government Gulch and the overall calibration of the model in general.

Table A-l presents measured baseflow surface water and groundwater elevations and
stream discharges from locations within Government Gulch. (The tables referenced in this
appendix are provided after the figures that follow Section A.9.) Although the data obtained
during both the fall 2007 and fall 2008 measurement events are variable from point to point,
there was an overall gain in surface water flow within Government Gulch (between staff
gauging stations BH-GG-0002 and BH-GG-0001). The calibrated model (CH2M HILL, 2009b)
simulated Government Creek as a losing stream throughout the "gulch" portion. To better
evaluate remedial actions within Government Gulch, the following updates were made to
the SFCDR Model:

• The horizontal hydraulic conductivity in model layers 1 and 2 was adjusted from 60 to
20 and 5 feet per day (feet/day), respectively.

A-2


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

•	The thickness of model layer 3 was decreased near the mouth of Government Gulch so
that the total aquifer thickness near monitoring well pairs BH-GG-GW-0005/
BH-GG-GW-0006 and BH-GG-GW-0007/BH-GG-GW-0008 more closely matched
measured data.

•	The horizontal hydraulic conductivity of model layer 3 in the confining unit "window"
at the mouth of Government Gulch was decreased from 28.35 to 2.835 feet/day.

•	The deep percolation of precipitation within Government Gulch was doubled.

These modifications to the model resulted in improved calibration within the Government
Gulch drainage area. The measured stream discharge, as defined by the difference in fall
2008 stream discharge between stream gauging stations BH-GG-0001 and BH-GG-0002
(Table A-l), increased by 0.27 cubic foot per second (cfs) in fall 2008. The revised model
simulation predicts that 0.24 cfs of groundwater discharge to Government Creek occurs
over that same reach. In comparison, the previous version of the SFCDR Model
(CH2M HILL, 2009b) simulated this portion of Government Creek as a losing stream.

As part of the updated baseflow calibration, the SFCDR Model underwent an auto-
calibration process using PEST, a nonlinear parameter estimation software package
(Dougherty, 2004 and 2007). PEST adjusts user-defined model parameters (e.g., hydraulic
conductivity and recharge) to minimize the sum of squared differences between calibration
targets and simulated values (e.g., groundwater elevations and groundwater discharge to
streams). PEST runs a model for each adjustable parameter in which the value of that
parameter is slightly increased or decreased. PEST then identifies how each parameter
change affected each calibration target. These changes are combined in a multidimensional
system of equations that solves for a new set of parameter values that better match the
calibration targets. This is repeated until no further improvement is gained. In the course of
a typical calibration exercise with PEST, thousands to tens of thousands of model runs are
completed. PEST uses a process of parameter modification and calibration target-matching
that is similar to the manual interactive technique used by a groundwater modeler, but
PEST has the advantage of being able to perform and analyze tens (or even hundreds) of
model runs over a short time period. Although PEST cannot exercise professional judgment
on its own, it can be guided by a professional who is familiar with the site and the software.

Targets used in the PEST process included the following:

•	Groundwater elevations measured during fall 2008

•	Vertical head differences measured during fall 2008

•	Groundwater discharge to the SFCDR within the Bunker Hill "Box" (the Box) and
Osburn Flats as measured during the 2008 groundwater-surface water interaction
studies (CH2M HILL, 2009a and 2009c)

•	The total baseflow groundwater discharge to the SFCDR, as measured at the
U.S. Geological Survey (USGS) stream gauge at Pinehurst

A-3


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

•	The total dissolved zinc load from groundwater to the SFCDR within the eastern gaining
stream reach along the northern side of the Central Impoundment Area (CIA)

•	The total dissolved zinc load from groundwater to Government Creek within the
"gulch" portion

During the auto-calibration process, PEST was able to adjust the horizontal and vertical
hydraulic conductivity of model layers 1 though 4 and the streambed conductance
parameters for reaches of the SFCDR in the Box and Osburn Flats. Additionally, because the
PEST process involved numerous model runs, model layer 7 was deleted in order to
decrease the number of nodes in the SFCDR Model and improve simulation run-times.

Table A-2 lists the multiplier factors for these parameters retained in the final calibration.
Figure A-3 presents the updated alluvial transmissivity distribution for the upper aquifer in
the Box, while Figure A-4 presents the updated total alluvial aquifer transmissivity for
Osburn Flats. Results of the auto-calibration process are discussed in Section A.3.

No updates or modifications were made to the Canyon Creek Model.

A.3 Additional Model Calibrations

During development of the remedial alternatives to be evaluated in the FFS, it was
recognized that it would be advantageous to evaluate the effectiveness of potential actions
under a variety of hydrologic conditions, not solely the baseflow conditions that were
assumed for the initial calibrations. To accommodate these additional analyses, both the
SFCDR and Canyon Creek Models were calibrated to four hydrologic conditions:

•	Steady-state calibration to fall baseflow conditions

•	Steady-state calibration to critical low-flow conditions, 7Q10

•	Steady-state calibration to higher flow conditions, 90th percentile flow

•	Transient calibration to an annual hydrologic condition (July 1, 2008 through
June 30, 2009)

These additional model calibrations are discussed in Sections A.3.1 through A.3.4,
respectively.

A.3.1 Steady-State Baseflow Calibration

The fall 2008 flow conditions that correspond to the baseflow calibration represent an
approximately 25th percentile flow condition, as defined by the USGS period of recorded
streamflow at the USGS stream gauge at Pinehurst (SF-271). Targets used in the 2008
baseflow calibration included the following:

•	Groundwater elevations measured in the fall of 2008

•	Vertical head differences measured in the fall of 2008

•	Groundwater discharge to the SFCDR within the Box and Osburn Flats, as measured
during the 2008 groundwater-surface water interaction studies (CH2M HILL, 2009a
and 2009c)

A-4


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

Figure A-5 presents an updated "scattergram" of simulated versus measured groundwater
elevations. Figures A-6a, A-6b, and A-6c present residuals between measured and simulated
groundwater elevations for the Box and Osburn Flats in map view. Tables A-3 and A-4
present the measured and simulated vertical hydraulic gradients for the Box and Osburn
Flats, respectively. Table A-5 presents the measured and simulated groundwater discharge
to the SFCDR in the Box and Osburn Flats.

A.3.2 Steady-State 7Q10 Calibration

To evaluate the effectiveness of potential groundwater remedial actions under critical low-
flow conditions, the Canyon Creek and SFCDR Models were calibrated to a steady-state
7Q10 flow condition. "7Q10" is defined as the lowest 7-day average daily flow that occurs
with a 10-year return period. For the SFCDR at the USGS Pinehurst gauge, the 7Q10 flow
has been estimated at 68 cfs (USEPA, 1999). The most recent 7Q10 at this location was
recorded in mid-September 2001. Data used as targets for the 7Q10 calibration included
groundwater elevations measured in monitoring wells and measured discharge of the
SFCDR at Pinehurst. It was assumed that under extreme low-flow conditions, all surface
water flow was supplied by groundwater discharge.

To calibrate the SFCDR Model to the 7Q10 flow at Pinehurst, several modifications were
made to the boundary conditions to reflect the drier hydrologic conditions. It was assumed
that all smaller streams within the model domain were dry during the 7Q10 flow condition.
These smaller streams (i.e., all streams except the SFCDR, Canyon Creek, Ninemile Creek,
Pine Creek, Government Creek, Milo Creek, Montgomery Creek, Big Creek, Terror Gulch,
Twomile Creek, and Placer Creek) were converted from the two-way head-dependent
boundary condition to a one-way head-dependent boundary condition. As the result of this
conversion, these streams could function as a sink for groundwater, but not a source. The
East and West Page Swamps were also converted to one-way head-dependent boundary
conditions.

The next change was to lower the stream stage elevations consistent with those measured
during fall 2001. The differences in gauge height between mid-September 2001 and fall 2008
(the baseflow calibration period) at the USGS gauges on the SFCDR at Pinehurst and
Elizabeth Park, on Canyon Creek at the mouth, on Ninemile Creek at the mouth, and on
Pine Creek below Amy Gulch were estimated. Of these gauge locations, those along the
tributary streams showed larger gauge heights during the 7Q10 flow condition than during
the fall 2008 flow period. As a result, the baseflow stream elevations were used for the
tributaries. The difference in gauge height between mid-September 2001 and fall 2008 on the
SFCDR was approximately 0.25 foot at Elizabeth Park and 0.50 foot at Pinehurst. The
calibrated baseflow stream stage elevation of the SFCDR was decreased by 0.50 foot
between the western model boundary and Pinehurst and by 0.25 foot from Pinehurst to the
SFCDR headwaters.

The final modification to the SFCDR Model was to adjust the deep percolation of
precipitation to reflect the drier hydrologic conditions. This was accomplished by an
iterative process of applying a multiplier to the deep percolation distribution, running the
model to steady-state solution, and then comparing evaluating the calibration against
measured groundwater elevations (at 28 monitoring wells in the Box) and the total ground-
water discharge to streams at the western model boundary. The final multiplier used in the

A-5


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

7Q10 simulations was 0.37 (i.e., the final deep percolation values were 37 percent of the
baseflow values). Figure A-7 presents a scattergram of simulated versus measured
groundwater elevations, while Figures A-8a and A-8b present the distribution of residuals
between simulated and measured groundwater elevations in map view. The simulated total
groundwater discharge to surface water in the calibrated 7Q10 SFCDR Model was
approximately 67 cfs.

Similar changes were made to calibrate the Canyon Creek Model to 7Q10 conditions. The
calibrated baseflow stage of Canyon Creek was decreased by 0.25 foot because of the
measured gauge height differences between fall 2001 and fall 2006 (the baseflow calibration
period for the Canyon Creek Model). The multiplier on the distribution of deep percolation
of precipitation from the calibrated 7Q10 version of the SFCDR Model (0.37) was applied to
the Canyon Creek Model. No measured groundwater elevations were available in the
Canyon Creek Watershed for the 7Q10 calibration period; therefore, the only calibration
target used was the total groundwater discharge to surface water during fall 2001
(measured at approximately 11 cfs and simulated at approximately 10 cfs).

A.3.3 Steady-State 90th Percentile Flow Tier Calibration

To evaluate the effectiveness of potential groundwater remedial actions under higher flow
conditions, the Canyon Creek and SFCDR Models were calibrated to a steady-state
90th percentile flow condition. The 90th percentile flow at the USGS stream gauge at
Pinehurst (SF-271) has been estimated at 1,290 cfs (USEPA, 1999). The most recently
available data that were obtained during the spring runoff period of Water Year 2009 were
used during the calibration. The first occurrence of a 1,290 cfs flow on the rising limb of the
SFCDR spring runoff hydrograph occurred on April 20, 2009. Calibration targets for the 90th
percentile flow simulations included groundwater elevations measured by transducers in
monitoring wells and piezometers on April 20, 2009. As groundwater discharge to streams
is not the sole component of streamflow during spring runoff, it was not possible to
calculate the quantity of groundwater discharge contributing to surface flow, and therefore
no flow targets were used in these calibration simulations.

To calibrate the SFCDR Model to the 90th percentile flow at Pinehurst, modifications were
made to boundary conditions to reflect the wetter hydrologic conditions. The stream stage
elevations for all streams in the model were modified to be consistent with measured data.
For all streams where data-logging pressure transducers were installed, the difference
between the stage during fall 2008 and the stage on April 20, 2009, was estimated. This
difference was then added to or subtracted from the stream stage in the calibrated baseflow
model. Although many stilling wells on tributary streams are instrumented with
transducers, it was necessary to work in stage differences because reference point elevations
are not available for the stream gauges on the SFCDR. Table A-6 lists the stage changes
implemented for all streams in the SFCDR Model. Where there was more than one stream
gauge on a particular stream, the water-level change was applied to reaches defined by the
half-distance between gauge locations (i.e., there was no interpolation of stream stage
change between gauges). Larger, non-instrumented streams were assigned stream stage
changes observed at the mouth of Government Gulch, while smaller streams were assigned
stage changes consistent with that observed at the mouth of Deadwood Gulch.

A-6


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

Modification of the deep percolation of precipitation to reflect the wetter hydrologic
conditions was accomplished in a similar manner to that used in the 7Q10 calibration. A
multiplier was applied to the baseflow deep percolation distribution, the model was run to
steady-state solution, and the simulated groundwater elevations were compared to the
measured values at 73 monitoring wells and piezometers in the Box and Osburn Flats. This
process was repeated until a reasonable calibration was achieved. The final multiplier used
in the 90th percentile flow simulations was 3 (i.e., the final deep percolation values were
three times greater than the baseflow values). Figure A-9 presents a scattergram of
simulated versus measured groundwater elevations, while Figures A-lOa, A-lOb, and A-lOc
present the distribution of residuals between simulated and measured groundwater
elevations in map view.

Calibration of the Canyon Creek Model to the 90th percentile flow condition involved
modifications to boundary conditions similar to those previously discussed. The stream
stage elevations were modified based on data recorded at stilling wells A2-SSD, A4E-SSD,
and A6-SSD and the USGS stream gauge CC-288. Because the three stilling wells have
surveyed reference point elevations, actual stream stage values measured on April 20, 2009,
were incorporated into the calibration of the Canyon Creek Model, as opposed to the gauge
height differences used in the SFCDR Model calibration. A stream stage value for stream
gauge CC-288 was calculated using the gauge height difference between April 20, 2009, and
the fall of 2006. New stream stage elevations were then applied to all stream nodes in the
model by interpolating stream stage values, as a function of distance, between the four
stilling well/gauge locations. From stilling well A2-SSD to the Canyon Creek headwaters,
the baseflow stream stage elevation was decreased by 0.055 feet, the difference between the
baseflow and 90th percentile stream stages at this stilling well. A multiplier was applied to
the calibrated baseflow distribution of deep percolation of precipitation in order to simulate
the wetter hydrologic conditions. The final multiplier used in the 90th percentile flow
simulations was 5.45 (i.e., the final deep percolation values were 5.45 times greater than the
baseflow values). Figure A-ll presents a scattergram of simulated versus measured
groundwater elevations, and Figure A-12 presents the distribution of residuals between
simulated and measured groundwater elevations in map view.

A.3.4 Transient Annual Calibration

The primary methodology used to evaluate the potential benefit of various remedial actions
on downgradient surface water quality for this FFS was the Predictive Analysis Tool,
discussed in Appendix B of the FFS Report. Because the inputs and outputs to and from this
tool are average annual data, it was necessary to calibrate both the SFCDR and Canyon
Creek Models to a transient annual condition. It was determined that using the most recent
data would provide the largest dataset for these calibrations. At the time of the calibration,
the fall 2009 transducer download had not occurred; therefore, it was not possible to
calibrate to Water Year 2009. Both groundwater flow models were calibrated to the most
recently available data, from July 1, 2008 through June 30, 2009. The output from these
model simulations represent the average flows for the 365-day annual period, so they do not
represent a long-term average or "typical" conditions.

A-7


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

A.3.4.1 SFCDR Model

Similar to the steady-state calibrations previously listed, modifications to the head-
dependent boundary conditions were made to reflect varying hydrologic conditions
observed over the course of the year. Streams included in the SFCDR Model are listed in
Table A-5. For the stream reaches with stage monitoring equipment and a continuous
dataset between July 1, 2008 and June 30, 2009, a new baseline stream state distribution was
calculated. This was accomplished by calculating the gauge height difference between
July 1, 2008 and September 20 through October 20, 2009 (the baseflow calibration period).
This gauge height difference was then applied to the baseflow stream stage distribution for
each reach (reaches are defined as the half-distance between the monitoring locations listed
in Table A-5). Unmonitored streams were assigned changes in baseflow stream stages
consistent with that described for the 90th percentile flow calibration (i.e., small streams
were assigned the values from Deadwood Gulch and large streams were assigned the
values of the mouth of Government Gulch). For each stilling well and stream gauge
location, the average daily deviation from the July 1, 2008 gauge height/ stream stage was
calculated. These daily deviations were applied to the July 1, 2008 baseline stream stage
distribution throughout the transient simulation. Exceptions included the following:

•	The Osburn Flats stilling wells were installed in fall 2008; therefore, continuous
transducer data for these locations prior to November 2, 2008, were not available.
Regressions between available gauge height data at each Osburn Flats stilling wells and
data from the Elizabeth Park gauge (SF-268) were developed. These regressions were
used to populate the missing gauge height data back to July 1, 2008, for the three Osburn
Flats stilling wells. Daily deviations from the July 1, 2008, gauge height were estimated
from the entire dataset.

•	The new USGS stream gauge at Smelterville Flats (at the western end of the Bunker Hill
Box) began recording data on September 23, 2008. A regression was developed between
the available gage height data at this gauge and SF-268. This relationship was used to
populate the missing gauge height data for the Smelterville Flats gauge. Daily deviations
from the July 1, 2008, gauge height were estimated from the entire dataset.

•	Where there were gaps in the daily data, the last estimated deviation from the baseline
stage prior to the missing data was applied to the entire data gap.

•	Transducers in stilling wells BH-BC-0005 and BH-BC-0006 were not submerged over a
large portion of the dataset. The estimated deviations from the baseline stream stage
distribution for BH-BC-0004 were applied to all Bunker Creek stream reaches.

The second modification that was made to boundary conditions within the SFCDR Model
was to vary the quantity of deep percolation of precipitation over the course of the year-long
transient simulation. Developing a recharge runoff relationship for the SFCDR Watershed
was beyond the scope of this effort; therefore, the deep percolation of precipitation was
varied, according to an average unit groundwater hydrograph. Multipliers were applied to
the calibrated baseflow distribution of deep percolation of precipitation on a monthly basis.
Table A-7 lists the monthly factors. Deep percolation was modified so that the total annual
deep percolation within the major alluvial areas equals the average annual deep percolation
of precipitation estimated using the Turner approximation (Turner, 1986).

A-8


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

The transient annual simulation was set up such that the model was first run to steady-state
under baseflow conditions. At the start of the transient simulation, a specific yield of 6
percent was assigned to alluvial areas of model layers 1 and 2, and a specific storage of
2 x 106 x model layer thickness was assigned to bedrock areas of model layers 1 and 2 and
all of model layers 3 through 6. The baseline July 1, 2008 stream elevation distribution was
loaded, and the July 2008 multiplier was applied to the deep percolation distribution. The
transient simulation then proceeded with stream stage varying on daily time steps and deep
percolation of precipitation varying on monthly time steps. Targets for the transient average
annual simulation consisted of average daily measured groundwater elevations at
69 monitoring wells and piezometers within the Box and Osburn Flats. Simulated heads for
each of these locations and simulated groundwater discharge to surface water were output
on a daily basis. At the end of each simulation, the calibration to measured groundwater
elevations was evaluated and additional modifications were made as necessary. During the
calibration process many parameters were varied to test the improvement to the overall
calibration, including: varying the streambed resistance terms, modifying the stream stage
elevations, varying the vertical resistance terms between model layers, decreasing the
specific yield, and globally decreasing the initial heads. Of the parameter variations
previously listed, the following modifications were retained in the final transient calibration:

•	Reduction of the baseline July 1, 2008 stream stage in the SFCDR reach defined by the
Elizabeth Park stream gauge by 1 foot

•	Re-interpolation of the baseline July 1, 2008 stream stage distribution of the SFCDR
reach between monitoring wells BH-SF-E-101-U and BH-SF-E-0314-U

•	Re-interpolation of the baseline July 1, 2008 stream stage distribution of the SFCDR
reach between monitoring locations BH-SF-W-PZ-05 and BH-SF-W-0201-U

Because the groundwater hydrographs in monitoring wells and piezometers near the
SFCDR showed similar magnitude of responses to the SFCDR hydrograph, it was assumed
that the SFCDR was in hydraulic connection with the groundwater system. Although there
were no stream gauges in the reaches listed above, groundwater elevations measured on
July 1, 2008, at monitoring wells adjacent to the SFCDR were used as data points for the
re-interpolation of the baseline stream stage distribution. Plots showing simulated versus
measured groundwater elevations from the final transient calibration targets are presented
on Figures A-13a through A-13i.

A.3.4.2 Canyon Creek Model

The transient average annual calibration for the Canyon Creek Model followed a similar
methodology as described for the SFCDR Model. Rather than establishing a baseline stream
stage for the July 1, 2008 initial condition and then applying changes in stream stage from
this distribution based on gauge height deviations, average daily stream stage distributions
were developed. Daily stream stage distributions were based on linear interpolation, as a
function of distance between gauges, of pressure transducer data recorded at stilling wells
A2-SSD, A4E-SSD, and A6-SSD and the USGS stream gauge at the mouth of Canyon Creek
(CC-288). Because no reference point elevation was available for the USGS stream gauge at
the mouth of Canyon Creek, it was necessary to estimate an initial stream stage for
interpolation based on the difference in gauge height between July 1, 2008 and the fall 2006

A-9


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

baseflow calibration period. Daily stream stages were calculated based on gauge height
deviations from this starting condition. Additionally, it was necessary to develop "soft" data
points for nodes representing the headwaters of Canyon Creek and the southwestern model
boundary at the confluence with the SFCDR. A constant stream stage of 5,856 feet mean sea
level (msl) was used in the daily interpolation of the headwaters node. The node
representing the confluence with the SFCDR was assumed to have a stage 3 feet lower than
that at stream gauge CC-288. Daily stream stages were interpolated between:

•	The southwestern model boundary (confluence with the SFCDR) and gauge CC-288

•	Gauge CC-288 and stilling well A6-SSD

•	Stilling wells A6-SSD and A4E-SSD

•	Stilling wells A4E-SSD and A2-SSD

•	Stilling well A2-SSD and the headwaters of Canyon Creek

An annual average deep percolation of precipitation distribution (based on the Turner
approximation [Turner, 1986]) was developed for the Canyon Creek Watershed. The annual
distribution was apportioned monthly, by applying multipliers to the distribution based on
the approximate trend of an average annual groundwater hydrograph. This approach
differed from the approach used in the SFCDR Model calibration; the multipliers were
applied to an average annual distribution rather than the calibrated baseflow distribution of
deep percolation of precipitation. Table A-8 provides the values of the monthly multipliers
applied to the deep percolation of precipitation distribution. Multipliers were calculated
such that the total deep percolation applied during the average annual simulation was
consistent with that estimated using the Turner approximation (Turner, 1986).

The model simulation consisted of loading an initial set of heads (the calibrated baseflow
heads), assigning the storage values, and applying the changes to the boundary conditions
discussed above. A specific yield of 5 percent was assigned to model layer 1, and a specific
storage of 2 x lO6 x model layer thickness was assigned to model layers 2 through 5. The
transient simulation was calculated with stream stage varying on daily time steps and deep
percolation of precipitation varying on monthly time steps. Targets for the transient average
annual simulation consisted of average daily measured groundwater elevations at eight
monitoring wells within the Woodland Park area of the Canyon Creek Watershed.

Simulated heads for each of these locations and simulated groundwater discharge to surface
water were output on a daily basis. The match between simulated and measured
groundwater elevations from the initial transient simulation was acceptable; therefore, no
model parameters were changed. Plots showing simulated versus measured groundwater
elevations from the final transient calibration are presented on Figure A-14.

A.4 Methodology for Development of Metals Loading Budget

The calibrated groundwater flow models provide improved estimates of the magnitude of
groundwater-surface water interaction within the Box, Osburn Flats, and the Canyon Creek
Watershed. This information was used to identify the location and magnitude of
groundwater discharge to streams within the watershed. By combining the groundwater
discharge estimates with dissolved metals concentrations in groundwater, the groundwater
flow data can be converted into estimates of metals flux from groundwater to surface water.

A-10


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

The SFCDR and Canyon Creek Models are groundwater flow models; therefore, metals
transport and geochemical reactions are not simulated. As an alternative, dissolved metals
loadings to the surface water were estimated by dividing the gaining portions of the SFCDR
and Canyon Creek into reaches, and selecting representative monitoring wells that are
assumed to reflect the dissolved metals concentrations in groundwater entering the stream
over a given reach. The average dissolved metals concentrations within a particular reach
can then be multiplied by the simulated groundwater flow to the stream reach predicted by
the groundwater flow model to yield estimates of metals loadings. These values can then be
compared with more traditional loading calculations, derived from comparing calculated
upstream and downstream loads based on surface water flows and surface water metals
concentrations, to evaluate consistency in the independent loading estimates. If the
estimates agree reasonably well, confidence is gained that the independent predictions of
metals loadings to the stream over certain reaches are reasonably accurate. This
methodology assumes that (a) dissolved zinc can be used as a surrogate for other metals
(i.e., the reaches with the greatest zinc loads are also areas with the highest cadmium loads),
and (b) there is no change in dissolved metals concentrations in groundwater between the
location of the groundwater monitoring well and the discharge area into the stream
(i.e., metals transport in the groundwater system is conservative between the monitoring
well and the stream discharge area). The most recent dissolved zinc concentration data
(collected in fall 2008) were used in this analysis.

A.4.1 Baseline Metals Loadings—SFCDR Model

Dissolved zinc loadings to the SFCDR were estimated by combining the simulated ground-
water discharge rates to the stream with the dissolved zinc concentrations measured in
nearby groundwater monitoring wells. Figure A-15 presents the distribution of dissolved
zinc in the groundwater system measured during the fall 2008 and spring 2009 sampling
events in the Bunker Hill Box. To estimate the metals loadings from groundwater discharge
within the Box, the SFCDR and major tributaries were subdivided into 29 reaches. The
streams were subdivided so that there was one monitoring well or piezometer associated
with each reach. The geographic locations of these reaches are shown on Figure A-15. For a
given simulation, the simulated groundwater discharge to the stream was multiplied by the
dissolved zinc concentration in groundwater measured at the associated monitoring well or
piezometer, and the simulated flow from the stream to the groundwater system was
multiplied by the dissolved zinc concentration in surface water measured during the 2008
OU 2 groundwater-surface water interaction study (CH2M HILL, 2009a). The net dissolved
zinc load for each reach was calculated as the difference between the stream load gained
and lost. The calculated net loads for all 29 reaches were then added together to estimate a
total load gained through the Box under a particular hydrologic condition. Dissolved zinc
concentrations for the hydrologic conditions described in Section A.3.4 were used as
follows:

•	Baseflow — fall 2008 dissolved zinc concentration

•	7Q10 — fall 2008 dissolved zinc concentration

•	90th percentile flow —spring 2009 dissolved zinc concentration

A-11


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

• Transient annual—fall 2008 dissolved zinc concentrations were applied to the time
frame from August 1, 2008 through March 15, 2009; spring 2009 dissolved zinc
concentrations were applied to the time frames from July 1, 2008 through July 31, 2008
and from March 16, 2009 through June 30, 2009.

Dissolved zinc loading for the remedial action simulations followed a similar methodology
as discussed above to estimate total loading to the surface water system. Estimates of
dissolved zinc loading to groundwater collection systems were calculating by multiplying
the simulated load to the French drains included in the remedial alternatives for OU 2 by
the average groundwater concentration in adjacent monitoring wells and piezometers. It
was assumed that the French drain systems simulated in the OU 2 alternatives were set far
enough away from streams that any induced flow from streams would flow through
contaminated sediments before discharging to the drain systems.

For groundwater actions proposed for the Mainstem SFCDR Watershed, Segment 01, the
dissolved zinc load was calculated as previously described. For all hydrologic conditions,
the dissolved zinc concentration was assumed to be equal to the average concentration
measured in Osburn Flats monitoring wells in fall 2008 (1.8 milligram per liter [mg/L]),
and the surface water concentration was assumed to be the average measured during
the 2008 Osburn Flats groundwater-surface water interaction study (0.75 mg/L)
(CH2M HILL, 2009c).

Discussions of how each of the above remedial alternatives was simulated and the results
are provided in Sections A.5 and A.6.

A.4.2 Baseline Metals Loadings—Canyon Creek Model

The zinc loading to Canyon Creek was estimated using a similar methodology as described
above for the SFCDR Model. The model-simulated groundwater discharge rates were
multiplied by the observed zinc concentrations measured in monitoring wells in the
Woodland Park area of the Canyon Creek Watershed. The dissolved zinc loading estimates
focused on this area of the watershed because this is where groundwater components of
various remedial actions were evaluated. To estimate the metals loading from groundwater
discharge, the Woodland Park area was subdivided into 12 reaches. The geographic location
of each reach and the distribution of dissolved zinc in groundwater, as measured during fall
2006, are shown on Figure A-16. For the purposes of this FFS, the average dissolved zinc
concentration within each reach was calculated; these data are provided in Table A-9.
Dissolved zinc loading to the surface water system was estimated by multiplying the
simulated total groundwater discharge to Canyon Creek and to land surface by the average
dissolved zinc concentration within each reach. This methodology assumes that ground-
water discharge to low-lying areas adjacent to Canyon Creek eventually flows into the
stream. The total dissolved zinc load to Canyon Creek through Woodland Park was
estimated as the sum of all 12 reaches. Because the fall 2006 sampling event represents the
most recent synoptic dissolved zinc dataset for the Canyon Creek Watershed, these data
were used for estimating dissolved zinc loading under all hydrologic conditions described
Section A.3.

Remedial actions proposed for the Woodland Park area include various source control and
sediment removal actions. It was assumed that these actions would reduce the dissolved

A-12


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

zinc concentrations in groundwater. The magnitude of these reductions within each of the
12 Woodland Park reaches was assumed to be a function of the percent of material
removed, the remedial effectiveness factor (REF) from the Simplified Tool for Predictive
Analysis1, and the fraction of the total area of each reach represented by a given source. The
estimation of the reduction in dissolved zinc concentrations in groundwater resulting from
source removal actions was as follows:

•	The percentage of total volume of each contaminant source proposed to be removed was
estimated (Table A- l 0, column 3).

•	The REF for each type of source removal action was taken from the Simplified Tool
(Table A-10, column 4).

•	The effective REF for each type of source removal action was calculated by multiplying
the proposed percentage of material to be removed by the REF (Table A-10, column 5).

•	For each Woodland Park reach, the area of contaminant source within the reach was
estimated (Table A-10, column 6).

•	For each Woodland Park reach, the fraction of the total area represented by each
contaminant source was calculated (Table A-10, column 7).

•	For each Woodland Park reach, the fraction of the total area for each contaminant source
was multiplied by effective REF (Table A-10, column 8).

•	The total REF for each reach was the sum of all the fractions of effective REFs for all
contaminant sources within the reach (Table A-10, column 9).

The total REFs for the reaches were used to reduce the average dissolved zinc concentration
in groundwater by assuming that for a given reach, the concentration would be reduced by
a percentage equal to the total REF. For example, for Reach 01, the total REF for the reach
was estimated to be 69 percent; this means that the average dissolved zinc concentration
after the source removal actions are completed would be 31 percent of the initial
concentrations. The pre-removal action and estimated post-source-removal-action dissolved
zinc concentrations in groundwater are presented in Table A-9. A complete discussion of the
simulation results is presented in Section A.6.

A.5 Application of Groundwater Flow Models to Remedial
Alternatives for Oils 2 and 3

This section describes how the groundwater components of each of the remedial actions
included in the applicable remedial alternatives described in Sections 6.0 and 7.0 of the
FFS Report were implemented in the SFCDR and Canyon Creek Models. These components
were consistently implemented in the models for all steady-state and transient hydrologic

1The Simplified Tool was developed in 2008 to provide a simplified version of the Predictive Analysis that was
used in the Remedial Investigation/Feasibility Study for the Coeur d'Alene Basin (USEPA, 2001a, 2001b, and
2007) and is also used in this FFS Report. The Simplified Tool allows for the evaluation of source sites and the
potential benefits of specific remedial actions for smaller segments of a stream, as opposed to the aggregated
source sites and remedial actions evaluated using the Predictive Analysis. The Working Draft Technical
Memorandum: Overview of the Simplified Predictive Analysis for Estimating Post-Remediation Water Quality
(CH2M HILL, 2008) presents the details of how the Simplified Tool was developed.

A-13


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

flow conditions discussed in Section A.3. The results of the simulations are presented in
Section A.6.

A.5.1 OU 2 Alternative (a)

OU 2 Alternative (a) consists of limited stream-lining actions in losing reaches of OU 2
streams to reduce recharge to the shallow alluvial groundwater system. The overall goal of
this alternative is to reduce the mobilization, transport, and mass flux of dissolved metals in
the groundwater system by reducing stream leakage from losing portions of the SFCDR and
tributaries, which would ultimately protect surface water downstream. This alternative was
developed to provide a limited passive action alternative without water treatment. The
locations of stream liners included in this alternative are based on the low operation and
maintenance (O&M) and minimal water management option identified during the OU 2
remedial alternative screening process, and were optimized during this process. Figure A-17
shows the locations of the stream liners that comprise this alternative, which include the
following:

•	Lining the SFCDR from the eastern portion of the Box to the 1-90 underpass at the
northeast corner of the CIA

•	Lining Bunker Creek from the Central Treatment Plant (CTP) to the 1-90 culvert

•	Lining Magnet Gulch from McKinley Avenue to the confluence with Bunker Creek

•	Lining Deadwood Gulch from McKinley Avenue to the confluence with Bunker Creek

For all the steady-state and transient simulations discussed in Section A.3, these stream
liners were simulated in the SFCDR Model by assigning a streambed conductance term of
zero where liners will be installed. This effectively removes the boundary condition from
these nodes, eliminating groundwater and surface water exchange.

A.5.2 OU 2 Alternative (b)

OU 2 Alternative (b) consists of extensive stream lining actions in OU 2 streams to reduce
recharge to the shallow alluvial groundwater system. Groundwater cutoff walls would be
installed at select locations as part of this alternative. The overall goal of OU 2 Alternative
(b) is to (more extensively than OU 2 Alternative (a)) reduce the mobilization, transport, and
mass flux of dissolved metals in the groundwater system to the extent practicable, with no
groundwater treatment, by reducing stream leakage from losing portions of tributaries to
the SFCDR, which would ultimately protect surface water downstream. To achieve this
goal, losing stream reaches were selected for lining. Similar to OU 2 Alternative (a), the
locations of stream liners included in this alternative are based on the objective of low O&M
and minimal water management as identified during the OU 2 remedial alternative
screening process, and were optimized during this process. Figure A-18 shows the locations
of the components of this alternative, which include the following:

•	Lining Bunker Creek from the CTP to the confluence with Bunker Creek

•	Lining Magnet Gulch from the point in the SFCDR Watershed where surface water has
elevated metals concentrations (approximately half the distance to the headwaters) to
the confluence with Bunker Creek

A-14


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

•	Lining Deadwood Gulch from where surface water has elevated metals concentrations
(approximately half the distance to the headwaters) to the confluence with Bunker Creek

•	Lining Government Creek from the upstream point of Government Gulch to the
confluence with Bunker Creek

•	Installing groundwater cut-off walls at the upstream end of all stream liner segments
except those on Bunker Creek

•	Installing clean groundwater collection sumps on the upstream side of the groundwater
cut-off walls

•	Installing sub-liner collection systems below stream liners, except those on Bunker
Creek, to prevent floating the liners in gaining stream reaches

For the steady-state and transient simulations discussed in Section A.3, stream liners were
simulated in the SFCDR Model by assigning a streambed conductance term of zero where
liners will be installed. This effectively removes the boundary condition from these nodes,
eliminating groundwater and surface water exchange. Groundwater cut-off walls were
simulated by assigning anisotropy to the horizontal hydraulic conductivity field.

Anisotropy was assigned to alluvial layers in the location of cut-off walls such that the
hydraulic conductivity in the direction of groundwater flow was 1 percent of the hydraulic
conductivity perpendicular to flow. For example, the horizontal hydraulic conductivity in
the alluvial valley of Deadwood Gulch is 10 feet/day. In the location of the groundwater
cut-off wall, the hydraulic conductivity in the downgradient flow direction is 0.1 foot/day,
while the hydraulic conductivity perpendicular to flow remains at 10 feet/day. This
methodology allowed the assignment of a barrier to flow without having extremely large
contrasts in model properties in adjacent nodes, thereby increasing the numerical stability of
the model simulation. Groundwater sumps on the upstream side of cut-off walls and
sub-liner collection systems were simulated using the MicroFEM drain package. These one-
way head-dependent boundary conditions act as sinks when simulated groundwater
elevations exceed the drain elevations, but do not act as sources of water when the
simulated groundwater elevations are lower than drain elevations. Drain elevations were
set at 2.5 feet below the calibrated baseflow groundwater elevation for all steady-state and
transient model simulations. This means that during simulations of "wetter" and "drier"
hydrologic conditions, the drain elevation did not fluctuate with the simulated water table.

A.5.3 OU 2 Alternative (c)

OU 2 Alternative (c) consists of a French drain system located in the central portion of OU 2
in the area with the highest dissolved metal load gains observed in the SFCDR. This French
drain system would intercept dissolved-metals-contaminated groundwater prior to
discharging to the SFCDR. Figure A-19 shows the locations of the components of this
alternative, which include the following:

•	Piping the CTP effluent directly to the SFCDR along the eastern side of the CIA instead
of conveying the discharge down Bunker Creek.

•	Installing a French drain parallel to the SFCDR in the highest dissolved metals loading
reach between the CIA and 1-90.

A-15


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

•	Installing a French drain perpendicular to the SFCDR alluvial valley in the narrows
between the eastern and western portions of the Box. This drain would be keyed in to
the bedrock on the western side of the mouth of Government Gulch.

The piping of the CTP discharge directly to the SFCDR was simulated in the SFCDR Model
using the same methodology as used for the stream liners discussed in previous sections. A
streambed conductance term of zero was assigned to the entire length of Bunker Creek,
eliminating groundwater and surface water exchange. The French drains were simulated
using the MicroFEM drain package. French drain elevations were set at either the geological
contact between the upper aquifer and the confining unit or at 25 feet below ground surface,
whichever was shallower. Additionally, drain elevations were assigned such that there was
a slope towards the pump station near Bunker Creek. The same drain elevations were used
for model simulations under all hydrologic conditions. A hydraulic conductivity of 1,500
feet/day was assigned along the French drains to simulate coarse backfill material.

A.5.4 OU 2 Alternative (d)

OU 2 Alternative (d) consists of French drains, stream linings, cutoff walls, and extraction
wells located in the central portion of OU 2, primarily in the area with the highest dissolved
metal load gains observed in the SFCDR. Similar to OU 2 Alternatives (a) and (b), the overall
goal of stream lining is to reduce the mobilization, transport, and mass flux of dissolved
metals in the groundwater system to the extent practicable by reducing stream leakage from
Government Creek. This alternative would reduce groundwater recharge and intercept
dissolved-metals-contaminated groundwater for treatment prior to discharging to the
SFCDR. Figure A-20 shows the locations of the components of this alternative, which
include the following:

•	Lining Government Creek from the upstream point of Government Gulch to the
1-90 culvert

•	Installing a groundwater cut-off wall at the upstream end of the stream liner

•	Installing clean groundwater collection sumps on the upstream side of the groundwater
cut-off wall

•	Installing a line of contaminated groundwater collection wells at the mouth of
Government Gulch

•	Installing sub-liner collection systems below stream liners to prevent the liners from
floating where Government Creek is gaining

•	Piping the CTP effluent directly to the SFCDR along the eastern side of the CIA instead
of conveying the discharge down Bunker Creek

•	Installing a French drain parallel to the SFCDR in the highest dissolved metals loading
reach between the CIA and 1-90

•	Installing a French drain perpendicular to the SFCDR alluvial valley in the narrows
between the eastern and western portions of the Box. This drain would be keyed in to
the bedrock on the eastern side of the mouth of Government Gulch

A-16


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

Stream lining and piping the CTP effluent directly to the SFCDR, rather than conveyance via
Bunker Creek, were simulated in the SFCDR Model as discussed above, by assigning a
streambed conductance term of zero to affected stream nodes. The groundwater cut-off wall
at the head of Government Gulch was simulated, as discussed for OU 2 Alternative (b), by
assigning anisotropy to the horizontal hydraulic conductivity field. The groundwater sumps
on the upstream side of the cut-off wall, the sub-liner collection system, the French drains in
the SFCDR valley, and the line of extraction wells at the mouth of Government Gulch were
simulated using the MicroFEM drain package. The drain elevations of the sumps and the
sub-liner collection system were set at 2.5 feet below the calibrated baseflow groundwater
elevation for all steady-state and transient model simulations. The elevations of the French
drains in the SFCDR valley were set at either the geological contact between the upper
aquifer and the confining unit or at 25 feet bgs, whichever was shallower. Additionally,
drain elevations were assigned so that there was a slope towards the pump station near
Bunker Creek. The drain elevation of the line of extraction wells at the mouth of
Government Gulch was set at the geological contact between the alluvium and bedrock. The
same drain elevations were used for model simulations under all hydrologic conditions. A
hydraulic conductivity of 1,500 feet/day was assigned along the French drains and the line
of extraction wells to simulate coarse backfill material.

A.5.5 OU 2 Alternative (e)

OU 2 Alternative (e) is the most extensive water collection and management alternative,
incorporating extensive stream lining of the SFCDR and its tributaries, as well as French
drain systems. The goal of OU 2 Alternative (e) is "no-net gain in dissolved metals through
the Bunker Hill Box". Figure A-21 shows the locations of the components of this alternative,
which include the following:

•	Lining Government Creek from the upstream point of Government Gulch to the
confluence with the SFCDR, the SFCDR throughout the Bunker Hill Box, the entire
length of Bunker Creek, Deadwood Gulch and Magnet Gulch from where surface water
has elevated metals concentrations to the confluence with Bunker Creek, and Humboldt
Creek and Grouse Creek from where they enter the SFCDR valley to the confluence with
the SFCDR

•	Installing groundwater cut-off walls at the upstream end of the stream liners

•	Installing a groundwater cut-off wall at the western end of the Box (installed to the top
of the confining unit)

•	Installing a clean groundwater cut-off wall at the eastern end of the Box (installed to
bedrock)

•	Installing clean groundwater collection sumps on the upstream sides of the
groundwater cut-off walls

•	Installing sub-liner collection systems below stream liners to prevent the liners from
floating where Government Creek, Magnet Gulch, and Deadwood Gulch are gaining

•	Installing a French drain in the eastern portion of the Box (between the CIA and 1-90) to
prevent the liner from floating where the SFCDR is gaining

A-17


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

•	Installing a French drain in the western portion of the Box (in Smelterville Flats) to
prevent the liner from floating where the SFCDR is gaining

•	Removing the weirs in the Page Swamps

Stream liners were simulated in the SFCDR Model as discussed above, by assigning a
streambed conductance term of zero to affected stream nodes. Groundwater cut-off walls
were simulated, as discussed for OU 2 Alternative (b), by assigning anisotropy to the
horizontal hydraulic conductivity field. The groundwater sumps on the upstream sides of
cut-off walls, the sub-liner collection systems, and French drains in the SFCDR valley were
simulated using the MicroFEM drain package. The drain elevations of the sumps and sub-
liner collection systems were set at 2.5 feet below the calibrated baseflow groundwater
elevation for all steady-state and transient model simulations. The elevations of the French
drain north of the CIA were set at either the geological contact between the upper aquifer
and the confining unit or 25 feet below ground surface, whichever was shallower.
Additionally, drain elevations were assigned such that there was a slope towards the pump
station near Bunker Creek. The drain elevation of the French drain in Smelterville Flats was
set at 5 feet below the calibrated baseflow water table. The same drain elevations were used
for model simulations under all hydrologic conditions. A hydraulic conductivity of
1,500 feet/ day was assigned along the French drains north of the CIA and in Smelterville
Flats to simulate coarse backfill materials. Weir removal was simulated by converting the
Page Swamps from a two-way head-dependent boundary condition to a one-way head-
dependent boundary condition. Because ponding no longer occurs within the swamps,
these could function as sinks for groundwater but not as a source of groundwater recharge.

A.5.6 Groundwater Components of OU 3 Remedial Alternatives for the Mainstem
SFCDR Watershed, Segment 01

Figure A-22 shows the groundwater components of all the OU 3 remedial alternatives for
the Mainstem SFCDR Watershed Segment 01. The objective of this remedial alternative was
to hydraulically isolate this reach of the SFCDR via stream lining and collection and
treatment of dissolved-metals-contaminated groundwater that would otherwise discharge
to the SFCDR. The components of this alternative include the following:

•	Lining the SFCDR from approximately Wallace to Elizabeth Park

•	Installing a French drain adjacent to the stream liner to prevent floating the liner in
gaining stream reaches

•	Capping tailings piles at the Silver Dollar Mine (site KLE034), the Silver Crescent Mine
(site KLE011), the Osburn Rock Pit along 1-90 (site WAL035), and the Caladay Mine (site
WAL020). These actions were included in the model simulations as they reduce
groundwater recharge due to deep percolation of precipitation

Lining the SFCDR was simulated in the SFCDR Model, as discussed for the OU 2
alternatives, by assigning a streambed conductance term of zero to lined stream nodes. The
French drain along the SFCDR was simulated using the MicroFEM drain package. The drain
elevation was set at 5 feet below the calibrated baseflow groundwater elevation for all
steady-state and transient model simulations. A hydraulic conductivity of 1,500 feet/ day
was assigned along the French drain to simulate coarse backfill materials. Capping the

A-18


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

tailings piles was simulated by assigning a deep percolation of precipitation of zero to
model nodes representing the capped areas.

A.5.7 Groundwater Components of OU 3 Remedial Alternatives for Woodland
Park

The updated groundwater components of the actions for the Woodland Park area included
in the OU 3 remedial alternatives were simulated using the Canyon Creek Model. These
components include a combination of stream liners and French drains that would be
installed along Canyon Creek to reduce dissolved metals loading to the creek and to collect
metals-contaminated water. The stream liners and French drains would be placed at
locations that would maximize dissolved metals load reduction in the creek and minimize
cost by (a) intercepting metals-contaminated groundwater that would otherwise discharge
to Canyon Creek, and (b) reducing the mobilization, transport, and mass flux of dissolved
metals in the groundwater system by reducing stream leakage from losing portions of
Canyon Creek. The locations of stream liners and French drains included in this alternative
were optimized during the remedial alternative screening process. Figure A-23 shows these
components, which include the following:

•	Lining the losing reach Canyon Creek from approximately Site A2 to Site A4E

•	Installing a French drain adjacent to Canyon Creek from approximately Site A2 to A6

•	Installing a French drain cut-off system perpendicular to the Canyon Creek alluvial
valley near Site A-6

•	Installing a French drain along the base of the Silver Valley Natural Resource Trust
tailings repository

•	Piping the Gem portal discharge directly to Canyon Creek instead of discharging the
effluent to Hecla Star Pond 6

Lining Canyon Creek was simulated, as discussed for the OU 2 alternatives, by assigning a
streambed conductance term of zero to lined stream nodes. All of the French drain systems
were simulated using the MicroFEM drain package. The drain elevations were set at 5 feet
below the calibrated baseflow groundwater elevation for all steady-state and transient
model simulations. Piping of the Gem portal discharge was simulated by removing the
specified flux for all nodes representing Hecla Star Pond 6.

A.6 Simulation Results

Groundwater components of the remedial alternatives described in the previous section
were simulated using the SFCDR and Canyon Creek groundwater flow models. The
modeling simulations were performed to obtain an estimate of the relative effectiveness of
each of the alternatives at reducing the dissolved metals loading to the SFCDR or Canyon
Creek. The effectiveness of each alternative was estimated by running a model simulation
with a remedy-in-place, and comparing the results with a baseline no-action simulation. The
difference in metal loading between the two simulations was assumed to be the benefit of
implementation of that particular alternative. Other information obtained from the model

A-19


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

simulations were estimated drain flows and CTP loads for the various remedial alternatives
evaluated. The sole metric used in this analysis to quantify alternative effectiveness was the
reduction in dissolved metals load to the SFCDR or Canyon Creek. While other benefits,
such as minimizing treatment loading or keeping clean water clean, could also be
considered, the assessment herein uses metal load reduction as the primary differentiator of
remedy effectiveness for the purposes of comparing alternatives.

A.6.1 Baseflow Conditions

Groundwater components of the remedial alternatives were simulated under steady-state
baseflow conditions observed during fall 2008 (the SFCDR Model) and fall 2006 (the Canyon
Creek Model). This time period represents an approximate 25th percentile flow as defined
by the SFCDR flow at the USGS stream gauge at Pinehurst (SF-271). Figure A-24 presents
upstream flowlines from gaining portions of the SFCDR under these conditions. This figure
also presents the simulated gaining and losing reaches of the SFCDR and tributaries for
which stream lining is proposed in the alternatives described above. These flowlines suggest
that under no-action baseline conditions, the primary sources of water to gaining portions of
the SFCDR in the eastern portion of the Box include the losing reaches of the SFCDR and
Bunker Creek, the groundwater underflow from the SFCDR alluvial system upstream of the
Box, and underflow from the Milo Creek Watershed. The primary sources of water to the
gaining reaches of the SFCDR in the western portion of the Box include the Page Swamps
and losing reaches of the SFCDR and Government Creek. (Flowline figures are only
presented for the baseflow conditions; flowlines for other hydrologic conditions show
similar patterns).

Figure A-25 presents upstream flowlines from the same gaining reaches of the SFCDR with
the components of OU 2 Alternative (a) in place. These flowlines are similar to the no-action
baseline conditions, except that they do not track back to losing reaches of the SFCDR and
Bunker Creek, as these stream reaches would be lined. Rather, a larger portion of the
groundwater that discharged to these gaining reaches would originate as groundwater
underflow from the SFCDR alluvial system upstream from the Box and underflow from the
Milo Creek Watershed.

Figure A-26 presents upstream flowlines from the same gaining reaches of the SFCDR with
the components of OU 2 Alternative (b) in place. These flowlines are similar to the no-action
and OU 2 Alternative (a) conditions, except that flowlines do not track back to the tributary
valleys of Bunker Creek due to the more extensive stream lining and groundwater cut-off
walls in these gulches.

Figure A-27a presents upstream flowlines from the same gaining reaches of the SFCDR with
the components of OU 2 Alternative (c) in place. This figure shows that a majority of the
reach of the SFCDR north of the CIA would no longer be gaining. Flowlines from the
portion of this reach that would still be gaining sweep north of the SFCDR under Kellogg.
Figure A-27b presents upstream flowlines from the French drain system. This figure
illustrates that a majority of the contaminated groundwater flowing beneath the CIA that
once discharged to the SFCDR would be captured by the French drains.

Figures A-28a and A-28b present upstream flowlines from the gaining reaches of the SFCDR
and the French drain systems with the components of OU 2 Alternative (d) in place. These

A-20


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

figures indicate that groundwater flow patterns would be similar to those discussed for
OU 2 Alternative (c).

Figure A-29 presents upstream flowlines from French drains with the components of OU 2
Alternative (e) in place. No flowlines from gaining reaches of the SFCDR are presented
because all streams would be lined within the Box under this alternative. This figure shows
that with such extensive stream lining coupled with a cut-off wall at Elizabeth Park, the
majority of water entering the French drains would be from groundwater underflow from
the Milo Creek Watershed.

Figures A-30 and A-31 show upstream flowlines from gaining portions of the SFCDR under
no-action conditions (Figure A-30), and with the French drain system proposed for
Mainstem SFCDR Watershed Segment 01 actions implemented (Figure A-31). These figures
show that the sources of water to either the SFCDR or the French drain system would be the
same: losing portions of the SFCDR, or tributaries and groundwater underflow from the
alluvial system upstream. Under the no-action scenario, this water is discharged to the
SFCDR; when the stream was lined, however, the water would be discharged to the French
drain system.

Figures A-32 and A-33 present upstream flowlines from gaining portions of Canyon Creek
under no-action conditions (Figure A-32), and with the French drain system proposed for
the updated remedial components for Woodland Park (Figure A-33). Figure A-32 also
presents simulated gaining and losing reaches of Canyon Creek under baseflow conditions.
These figures show a similar pattern to the pattern for Mainstem SFCDR Watershed
Segment 01. Under no-action conditions, water discharging to gaining reaches of Canyon
Creek originates from leakage from losing portions of Canyon Creek, groundwater
underflow from upstream portions of the alluvial valley, and groundwater underflow from
beneath the Silver Valley Natural Resource Trust (SVNRT) repository. With the remedial
actions in place, this water would discharge to the French drain systems instead of to
Canyon Creek.

Table A-ll presents summaries of simulated flows for the no-action and remedial
alternative simulations under baseflow conditions. Under no-action baseline conditions, the
SFCDR Model suggests that the SFCDR gain through the Box is approximately 8 cfs, while
the loss is approximately 3 cfs. Model results suggest that the stream-lining-only options
would not significantly reduce the gain to the SFCDR. Because the eastern losing reach of
the SFCDR would be lined, OU 2 Alternative (a) would reduce the leakage from the SFCDR
by approximately 2 cfs. OU 2 Alternative (b) would induce more seepage from the SFCDR
than the no-action baseline conditions, likely the result of the lining of Government Creek.
OU 2 Alternatives (c) and (d) would both reduce the groundwater discharge to the SFCDR
by more than 50 percent; however, the French drains would induce stream leakage doubling
the SFCDR leakage. Additionally, both alternatives would have a treatment flow of
approximately 8.5 cfs. Under OU 2 Alternative (e), the streams would be lined; therefore, no
stream loss or gain is simulated. The simulated treatment flow to the French drain and sub-
liner collection systems is approximately 5.5. cfs. Within the Mainstem SFCDR Watershed
Segment 01, between Wallace and Elizabeth Park in OU 3, the SFCDR Model suggests that
the SFCDR would gain approximately 10 cfs and loses 8 cfs. With the remedial actions in
place, there would be no groundwater-surface water interaction along the SFCDR as a result
of stream lining, and the French drain inflow would be approximately 7.5 cfs. The results of

A-21


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

baseflow simulations from the Canyon Creek Model suggest that under no-action baseline
conditions, Canyon Creek gains approximately 2 cfs and loses approximately 1 cfs. With the
Woodland Park components of the OU 3 remedial alternatives in place, stream gain would
be decreased by 0.5 cfs; however, Canyon Creek stream loss would increase by 0.3 cfs, and
there would be an inflow of 1 cfs to the French drains.

Table A-12 presents summaries of the estimated dissolved zinc loading under baseflow
conditions for the OU 2 and OU 3 baseflow simulations. These data suggest that under
no-action baseline conditions, the total dissolved zinc load to the SFCDR through the Box is
approximately 600 pounds per day (lb/day). This value is consistent with historical
measurements from baseflow groundwater-surface water interaction studies. The stream-
lining-only options would reduce the dissolved zinc load to the SFCDR by approximately
100 lb/ day. OU 2 Alternative (a) would be more effective at reducing direct load to the
SFCDR and the A-4 drain, while OU 2 Alternative (b) would reduce loading to Government
Creek. OU 2 Alternatives (c) and (d) would reduce the direct dissolved zinc loading to the
SFCDR by approximately 460 lb/ day; however, OU 2 Alternative (d) would be more
effective overall because it would reduce dissolved zinc loading to Government Creek. Both
of these alternatives would have a treatment load of more than 1,000 lb/ day. OU 2
Alternative (e) would be 100 percent effective in reducing dissolved zinc loading to the
surface water system and would carry a treatment burden of approximately 550 lb/ day. The
net dissolved zinc loading to Mainstem SFCDR Watershed Segment 01 in OU 3 would be
approximately 65 lb/ day. As shown in Table A-12, the remedial actions would remove this
zinc load from the system; however, the treatment load would be approximately 75 lb/day.
Results from the Canyon Creek Model suggest that under no-action baseline conditions, the
total dissolved zinc load to the Woodland Park reach of Canyon Creek is approximately
125 lb/ day. The Woodland Park components of the remedial alternatives for OU 3 would
reduce this loading by approximately 85 lb/ day and have a treatment load of approximately
80 lb/ day.

A.6.2 7Q10 Conditions

Tables A-13 and A-14 present the model-simulated flows and dissolved zinc load
summaries, respectively, for no-action and remedial alternative simulations from the
SFCDR and Canyon Creek Models under critical low-flow, 7Q10, conditions. A comparison
of Tables A-ll and A-13 shows that the relative trends in simulated flows would be similar
between baseflow and 7Q10 conditions. In general, streams would gain slightly less and lose
slightly more under 7Q10 conditions than under baseflow conditions. This would be the
result of lower groundwater elevations during drier periods.

Table A-14 shows that the estimated dissolved zinc load to the SFCDR under 7Q10 condi-
tions would be approximately 550 lb/day, 50 lb/day less than under baseflow conditions.
The five OU 2 alternatives show similar relative effectiveness under 7Q10 conditions as
under baseflow conditions. Table A-14 shows that of the two stream-lining-only options,
OU 2 Alternative (a) would be more effective under extreme low-flow conditions, probably
because of the inclusion of lining the eastern losing reach of the SFCDR. The lining-only
alternatives would be less effective than the actions involving the installation of French
drains; however, there would be little or no treatment load. The estimated dissolved zinc
load to Mainstem SFCDR Watershed Segment 01 in OU 3 would be approximately

A-22


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

60 lb/day under 7Q10 conditions. This load would be eliminated with the remedial actions
in place; however, the estimated dissolved zinc load to the French drain would be
60 lb/ day. Table A-14 shows that under 7Q10 conditions, the Woodland Park components
of the OU 3 remedial alternatives would reduce the dissolved zinc loading to Canyon Creek
by 75 lb/day and carry a treatment burden of approximately 50 lb/day.

A.6.3 90th Percentile Flow Conditions

Tables A-15 and A-16 present the model-simulated flows and dissolved zinc load
summaries, respectively, for no-action and remedial alternative simulations from the
SFCDR Watershed and Canyon Creek models under 90th percentile flow conditions, as
defined at the USGS stream gauge at Pinehurst (SF-271). Simulated flows presented in
Table A-15 suggest that for the SFCDR and tributaries within OU 2, the stream gains would
be lower and stream losses higher during the higher flow conditions than under baseflow
and 7Q10 conditions. This is likely because the stages in the surface water system would
increase quicker than the groundwater elevations. The larger differential in elevations
between the two systems would result in more stream loss and less stream gain. Simulated
groundwater discharge to Canyon Creek is higher under 90th percentile flow than the drier
hydrologic conditions. Simulated flows also show that in all cases, the French drain inflows
would be higher under the wetter hydrologic conditions than during 7Q10 or baseflow
periods.

Table A-16 presents the estimated dissolved zinc load to the surface water system within
OU 2 and OU 3 under 90th percentile flow conditions. Under the no-action scenario, the
estimated dissolved zinc loading to the SFCDR within the Box is 715 lb/ day. Results from
the SFCDR Model suggest that the relative effectiveness of the OU 2 alternatives would be
similar under the wetter hydrologic conditions as under 7Q10 and baseflow conditions. The
stream-lining-only options would reduce dissolved zinc loading by approximately
100 lb/ day, while the alternatives including French drains would reduce loading by
approximately 550 lb/day. The OU 2 Alternative (e) simulation shows some dissolved ziric
loading to the surface water system, as the A-4 drain would be active under the wetter
hydrologic conditions. The results for Mainstem SFCDR Watershed Segment 01 in OU 3 are
similar to those for the other hydrologic conditions. Table A-16 shows that under 90th
percentile flow conditions, the estimated dissolved zinc loading to Canyon Creek would be
higher under 90th percentile flow conditions than under baseflow and 7Q10 conditions,
approximately 260 lb/day. The Woodland Park components of the OU 3 remedial
alternatives would reduce dissolved zinc loading to Canyon Creek by nearly 150 lb/ day;
however, the treatment load would be approximately 180 lb/ day.

A.6.4 Average Annual Conditions

Tables A-17 and A-18 present the model-simulated flows and dissolved zinc load
summaries, respectively, for the transient annual simulations for the SFCDR and Canyon
Creek Models. A comparison of Tables A-ll and A-17 shows that the simulated flows are
very similar under baseflow and the average annual conditions. Consistent with the
90th percentile simulation results, the simulated flows for the SFCDR and tributaries within
OU 2 show that the stream gains would be lower and stream losses higher during the
average annual conditions than under baseflow conditions. The simulated groundwater
discharge to Canyon Creek is slightly higher under average annual than baseflow

A-23


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

conditions. Simulated flows also show that in all cases, the French drain inflows would be
higher under the average annual hydrologic conditions than during baseflow periods.

Table A-18 presents the estimated dissolved zinc load to the surface water system within
OU 2 and OU 3 under average annual flow conditions. A comparison of Tables A-12 and
A-18 shows that the estimated dissolved zinc loading to the surface water system would be
nearly identical under average annual and baseflow conditions. Although the simulated
flows between the baseflow and annual simulations differ, the use of variable concentration
distributions to estimate the average annual dissolved zinc loading for the transient
simulations yields similar results to the steady-state baseflow simulations. The primary
differences between the two hydrologic conditions are that OU 2 Alternative (a) would be
slightly more effective than OU 2 Alternative (b), and the treatment loads would be slightly
higher under average annual conditions. The results from the average annual simulations
were used as input to the Predictive Analysis Tool, as discussed in Appendix B of the
FFS Report.

A.7 OU 2 Sensitivity Analysis

Numerical models contain inherent uncertainty. Groundwater models are constructed using
available field data and professional judgment to develop an accurate numerical
representation of the physical features of a given site of interest, as well as of the physical
processes that operate at that site. Additionally, the calibration process allows the modeler
to further evaluate and modify the model input parameters in order improve the match
between selected calibration targets and model predictions. The larger the number of
individual calibration targets, and the greater the variety in the types of calibration targets
used (e.g., groundwater elevations, simulated flows, vertical hydraulic gradients, and
transient aquifer test data), the higher the degree of confidence is gained that the model is
able to provide accurate forecasts of future site conditions. There is, however, error
associated with measured field data, and numerical model solutions are non-unique,
meaning that there are a large number of parameter configurations that can provide an
equal level of calibration. To better quantify the potential range of uncertainty in the
estimates of dissolved zinc loading to the SFCDR for the five OU 2 alternatives, an
uncertainty analysis was undertaken using the SFCDR Model.

The sensitivity analysis performed on the SFCDR Model involved varying one model
parameter at a time, within a specified range, and running numerous simulations to yield
independent estimates of zinc loading to the SFCDR. The quality of model calibration was
evaluated for each of these sensitivity simulations to ensure that the parameter change made
in that run did not result in a model that no longer provides acceptable agreement between
simulated and observed calibration targets.

Seven model input parameters were selected for modification during the SFCDR Model
sensitivity analysis. Each parameter was increased and decreased by two factors, resulting
in 28 model simulations for the no-action alternative and each of the five OU 2 alternatives,
resulting in a total of 168 simulations. All of the sensitivity simulations were run using the
steady-state, baseflow condition. It was assumed that the other hydrologic conditions would
result in similar relative uncertainty. The model input parameters that were evaluated

A-24


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

during the sensitivity analysis, along with the range of values tested, are summarized as
follows:

•	Horizontal hydraulic conductivity in the alluvial aquifer system—The horizontal
hydraulic conductivity of the alluvium in model layers 1 through 4 was multiplied and
divided by factors of 5 and 10.

•	Horizontal hydraulic conductivity in the confining unit—The horizontal hydraulic
conductivity of the confining unit in model layer 3 was multiplied and divided by
factors of 10 and 100.

•	Horizontal hydraulic conductivity in the bedrock aquifer system—The horizontal
hydraulic conductivity of the bedrock in model layers 1 through 4 was multiplied and
divided by factors of 10 and 100.

•	Distribution of deep percolation of precipitation—The calibrated baseflow distribution
of deep percolation of precipitation was increased and decreased by 25 and 50 percent
throughout the model domain.

•	The vertical resistance between model layers — The vertical resistance terms at the
interface between model layers 1 and 2, 2 and 3, and 3 and 4 were increased and
decreased by factors of 10 and 100 throughout the model domain.

•	The streambed resistance term—The streambed conductance term for the SFCDR was
increased and decreased by factors of 5 and 10.

•	The wadi elevation term—The baseflow stream stage distribution of the SFCDR was
increased and decreased by 1 and 2 feet.

All of these parameter variations, with the exception of the deep percolation of precipita-
tion, were applied prior to assigning properties for the simulation of the various remedial
actions. Table A-19 summarizes the estimated dissolved zinc loading to the SFCDR within
the Bunker Hill Box for all of the sensitivity analysis simulations. These data are presented
graphically on Figure A-34. The baseflow estimates of residual dissolved zinc loading to the
SFCDR from the calibrated model are shown as yellow triangles, while the black "x"
symbols represent the results of all of the individual sensitivity analysis simulations. These
data show that the simulations of the no-action and liner-only alternatives yielded a wider
range of dissolved zinc loading estimates than did the simulations of the other alternatives.
For example, the alternatives involving French drains show much less overall deviation
from the baseflow dissolved zinc loading estimate obtained from the calibrated model,
while the simulations of OU 2 Alternative (e) show even less.

In all cases, the highest estimates of dissolved zinc loading to the SFCDR for each alternative
are from the simulations with increased horizontal hydraulic conductivity of the alluvial
aquifer system. Increases in the hydraulic conductivity by factors of 5 and 10 over the
currently assumed values result in extremely high values (up to 10,000 feet/ day), greater
than would be expected for the aquifer materials present at the site. Therefore, these results
are not considered representative of site conditions. The lowest estimated values of
dissolved zinc load for each alternative result from a variety of parameter modifications
depending on the alternative being evaluated. But all of the parameter changes that resulted

A-25


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

in these low estimates involve parameters that make it more difficult for groundwater to
discharge upward to the surface water system. These include increases in vertical resistance
between layers (reducing vertical flow), increasing the streambed conductance terms, and
increasing stream stage.

Overall, these results suggest that given the uncertainty in the model input parameters, it is
not possible to predict whether OU 2 Alternative (a) or (b) would be more effective at
reducing metals loading to the SFCDR. However, these results also clearly indicate that
OU 2 Alternatives (c) and (d) would be more effective than the liner-only alternatives, and it
appears that Alternative (d) would be the more effective of the French drain alternatives.
Finally, results suggest that OU 2 Alternative (e) appears to be the most effective under all
of the parameter variations considered in this analysis.

A.8 Additional Model Uncertainty

In addition to uncertainty in model forecasts associated with the assumed model input
parameters, uncertainty is also associated with the methodology used to estimate dissolved
metals loading to streams from groundwater flow model estimates. As discussed in Section
A.4, simulated flow estimates of groundwater discharge to streams, and surface water
leakage to underlying groundwater, are paired with analytical data from surface water
sampling and groundwater monitoring well sampling. This methodology assumes that
(a) dissolved zinc concentrations measured in monitoring wells and piezometers near
streams are representative of the concentrations actually being discharged to the stream,
and (b) a given set of samples collected during a discrete quarterly sampling event are
representative of dissolved zinc concentrations over some range of time (e.g., over the
baseflow or spring runoff period). Insufficient data are available with which to quantify the
magnitude of uncertainty that these assumptions may introduce into model forecasts.

One final area of uncertainty in the modeling results originates from site characteristics that
may be changed by remedial activities that are not explicitly included in the modeling
assumptions. One example is that extensive remedial activities, such as surface water
collection and treatment in the Upper Coeur d'Alene River Basin, may have significant
effects on the magnitude and timing of stream flow in the SFCDR within OU 2. Changes to
surface water flows and associated changes to river stage will affect groundwater conditions
to some degree. These types of changes to site conditions have not been evaluated during
the SFCDR Watershed modeling effort; they would likely have a relatively minor effect on
remedy effectiveness.

A.9 References

CH2M HILL. August 2007. Canyon Creek Hydrologic Study Report. Prepared for
U.S. Environmental Protection Agency Region 10.

CH2M HILL. October 24, 2008. Working Draft Technical Memorandum: Overview of the Simplified
Predictive Analysis for Estimating Post-Remediation Water Quality. Prepared for the
U.S. Environmental Protection Agency Coeur d'Alene Basin Eco-Planning Team.

A-26


-------
APPENDIX A: GROUNDWATER MODELING ANALYSIS

CH2M HILL. March 31, 2009 (2009a). Technical Memorandum: OU2 2008 Groundwater/Surface
Water Interaction Monitoring Data Summary. Prepared for U.S. Environmental Protection
Agency Region 10.

CH2M HILL. April 2009 (2009b). South Fork of the Coeur d'Alene River Watershed: Basinwide
Groundwater Flow Model Documentation. Prepared for U.S. Environmental Protection Agency
Region 10.

CH2M HILL. July 2009 (2009c). Technical Report, Osburn Flats Groundwater-Surface Water
Interaction Study, Upper Coeur d'Alene Basin, Osburn, Idaho. Prepared for U.S. Environmental
Protection Agency Region 10.

Dougherty, J. July 2004. PEST Model-Independent Parameter Estimation User Manual.
5th Edition.

Dougherty, J. January 2007. Addendum to the PEST Manual.

Hemker, C.J., and G.J. Nijsten. 2003. Groundwater Flow Modeling Using MicroFEMฉ.

National Academy of Sciences (NAS). 2005. Superfund and Mining Megasites: Lessons Learned
from the Coeur d'Alene River Basin. National Academies Press. Washington, D.C.

Turner, K.M. May 1986. Water Loss from Forest and Range Lands in California. Presented at the
Chaparral Ecosystems Conference, Santa Barbara, California.

U.S. Environmental Protection Agency (USEPA). April 1999. Total Maximum Daily Load for
Dissolved Cadmium, Dissolved Lead, and Dissolved Zinc in Surface Waters of the Coeur d'Alene
Basin.

U. S. Environmental Protection Agency (USEPA). September 2001 (2001a). Final (Revision 2)
Feasibility Study Report, Coeur d'Alene Basin Remedial Investigation/Feasibility Study. Prepared
by URS Greiner and CH2M HILL for EPA Region 10.

U. S. Environmental Protection Agency (USEPA). October 2001 (2001b). Final (Revision 2)
Feasibility Study Report, Coeur d'Alene Basin Remedial Investigation/Feasibility Study. Prepared
by URS Greiner and CH2M HILL for EPA Region 10.

U. S. Environmental Protection Agency (USEPA). October 1, 2007. A Predictive Analysis of
Post-Remediation Metals Loading.

A-27


-------

-------
Figures


-------

-------
MACE

Woodland Park Inset

South Fork
oeur d'Alene River

WOODLAN
PARK. /

i ypN

ฐ'W ฆ

Model Grid

	 River/Creek

—ฎ*- Major Highway
~ City Limit

0.375 0.75

1.5 Miles

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-1

Canyon Creek Model Grid

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	v>EPA

\\CASTAIC\PROJ\EPA\CDABASIN 382081 \GIS\MAPFiLES\FFS\APPENDIXA\FFS APDXA CCMODELGRID.MXD JCARR3 6/30/2010 10:08:18


-------

-------
/

M?ssa

VILLE

South Fork,
Coeur d'Alene River,
Upper Basin

South Fork
Coeur d'Alene River

WALLACE

Kellogg Inset

South Fork

Coeur d'Alene River	_/

Model Grid

	 River/Creek

Canyon Creek Watershed
City Limit

|	} State Boundary

4 Miles

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-2
SFCDR Model Grid

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	oEPA

\\CASTAIC\PROJ\EPA\CDABASIN 382081 \GIS\MAPFILES\FFS\APPENDIXA\FFS APDXA SFMODELGRID.MXD JCARR3 5/26/2010 09:32:20


-------

-------
The Bunker Hill Box

South Fork
Coeur d'Alene River

SMELTERVII

PINEHURS

— Approximate Extent of Confining Unit

Transmissivity Contour
	 (2000-ft2/day interval)

Transmissivity (feet2/day)

< 2,000
2,000 to 4,000
4,000 to 6,000
6,000 to 8,000
8,000 to 10,000
10,000 to 12,000
12,000 to 14,000
14,000 to 16,000
> 16,000

	 River/Creek

~ City Limit

0 0.125 0.25

0.5 Miles

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-3

Upper Aquifer Transmissivity,
Bunker Hill Box

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	v>EPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_UPPERAQUIFERTRANS.MXD JCARR3 5/24/2010 11:14:11


-------

-------
i15000

Trarismissivity Contour
	 (5000-ft2/day interval)

Transmissivity (feet2/day)

>	5,000

5,000 to 10,000
10,000 to 15,000
15,000 to 20,000
20,000 to 25,000
25,000 to 30,000
30,000 to 35,000
35,000 to 40,000
40,000 to 45,000
45,000 to 50,000
50,000 to 55,000
55,000 to 60,000
60,000 to 65,000
65,000 to 70,000
70,000 to 75,000

>	75,000

	 River/Creek

~ City Limit

500 1,000

2,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-4

Total Aquifer Transmissivity,
Osburn Flats

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	v>EPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_TOTAQUIFERTRANS-OSB.MXD JCARR3 5/24/2010 11:24:07

Upper Basin,
Coeur d'

River, North Fork

Lower Basin
Coeur d'

River

Upper Basin,

d'Alene
River, South Fork


-------

-------
2650

2600

2550

2500

ฃ. 2450

2400

2350

2300

2250

2200

LINE REPRESENTS PERFECT MATCH
BETWEEN OBSERVED AND SIMULATED
GROUNDWATER ELEVATIONS

2150

~

O

OSBURN RMS/RANGE = 1.9%
BOX RMS/RANGE = 1.8%

OSBURN WELLS (MODEL LAYER 1)
OSBURN WELLS (MODEL LAYER 2)
OSBURN WELLS (MODEL LAYER 3)
OSBURN WELLS (MODEL LAYER 4)
BOX WELLS (MODEL LAYER 1)
BOX WELLS (MODEL LAYER 2)
BOX WELLS (MODEL LAYER 4)

2150 2200 2250 2300 2350 2400 2450 2500 2550 2600
OBSERVED GROUNDWATER ELEVATION (feet above mean sea level)

2650

Note:

RMS/Range is a measure of model calibration
and is equal to the root mean squared error
divided by the range in measured groundwater
elevation.

\\Odin\proj\usepa\323031\BunkerHill\Figures\GRAPHER\2009

2__FEFS__ModelingAppendix\FIGURE__A-5__Scattergrarn.grf

Figure A-5

Simulated versus Observed
Groundwater Elevations -
Baseflow Conditions

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

** rnA

m m


-------

-------
BH-SF-W-0207-L

-5.04

-1.63

BH-SF-W-0202-L
-3.30
-4.39

V

BH-SF-W-0206-U

-1.12

-1.20

BH-SF-W-0201-IJ

-0.56

-0.56

BH-SF-W-0203-U
-1.21

-1.18

BH-SF-W-0204-U
-1.15
-1.20

BH-SF-W-0205-L

-4.12

-1.06

"1

BH-SF-W-0121-U

-0.14

-0.10

BH-SF-W-PZ-07

0.01

0.02

BH-SF-W-0118-U
-0.14
-0.08

BH-SF-W-PZ-Q5

0.79

0.76

BH-SF-W-PZ-04
0.80
0.76

BH-SF-W-0104-U

2.50

2.75

BH-SF-W-0122-L
-3.26
-5.34

BH-SF-W-PZ-03

1.97

2.04

BH-SF-W-0119-U

-0.80

-0.74

BH-SF-W-PZ-06
0.17
0.22

PINEHURST

BH-SF-W-0008-U

0.35

0.50

BH-SF-W-0009-U
0.13
0.56

BH-SF-W-0018-U
-1.05
-1.00

BH-SF-W-0021-U

-0.06

0.21

BH-SF-W-0022-U
0.67
1.00

L

BH-SF-W-0023-U
1.20
1.53

BH-SF-W-0111-U

2.88

3.20

BH-SF-W-PZ-01

-19.18
-18.86

BH-SF-W-PZ-02

-21.80

-21.46

BH-SF-W-0010-
-1.06
-0.20

BH-SF-W-0011-L
2.17
0.83

BH-SF-W-0020-U
-0.70
0.36

BH-SF-W-0019-U

-0.92

0.15





%

M

mk

Upper Basin,

Coeur d'Alene—v j
River, North Fork y-OC





c. I a



—\)~

Lower Basin,

Coeur d'Alene—'

River

I Upper Basin,
'—Coeur d'Alene
River, South Fork

Residual (feet)

~

-51 to -25

~

o
o

LO
(N

~

-10 to -5

~

-5 to -1

o

-1 to 1

O

1 to 5

O

5 to 10

O

10 to 25

o

25 to 40



River/Creek

~ City Limit

BH-SF-W-0021-U (Site ID)
-0.06 (Previous Residual)
0.21 (Current Residual1)

AO 500 1,000 2,000 Feet
I	I	I	I	I	I	I	I	I

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Notes:

1.	Residual is equal to simulated groundwater
elevation minus measured groundwater elevation.

2.	The demarcation line represents the area of
overlap between two connected figures such
that data for the previous/subsequent figure
are not displayed on the current figure.

Figure A-6a

Residuals between Measured
and Simulated Groundwater
Elevations, Western Bunker Hill
Box, Baseflow Conditions
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

	&EPA

\\CASTAIC\PROJ\EPA\CDABASIN 382081\GIS\MAPFILES\FFS\APPENDIXA\FFS APDXA OU2WRESIDUALBASEFLOW.MXD JCARR3 5/17/2010 11:55:43


-------

-------
BH-SF-W-0004-L

4.33
3.46

BH-SF-W-0003-U

6.12

5.39

BH-SF-W-00Q6-L

-0.20

ฆ0.93

SMELTERVILLE

BH-SF-W-0007-U /'
-0.62

'1'21 BH-GG-GW-0006
2.89
-4.40

BH-GG-GW-0005 /

-0.43

-7.66

BH-GG-GW-0008 /
3.22

-3.23	,

BH-GG-GW-0007 /
2.21
2! -4.06

WARQ^EI?

Residual (feet)

~

-51 to -25

~

o
o

LO
(N

~

-10 to -5

~

-5 to -1

o

-1 to 1

O

1 to 5

O

5 to 10

O

10 to 25

o

25 to 40



River/Creek

~~ City Limit

BH-SF-E-0101 (Site ID)
-3.05 (Previous Residual)
-0.23 (Current Residual1)

AO 500 1,000 2,000 Feet
I	I	I	I	I	I	I	I	I

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Notes:

1.	Residual is equal to simulated groundwater
elevation minus measured groundwater elevation.

2.	The demarcation line represents the area of
overlap between two connected figures such
that data for the previous/subsequent figure
are not displayed on the current figure.

Figure A-6b

Residuals between Measured
and Simulated Groundwater
Elevations, Eastern Bunker Hill
Box, Baseflow Conditions
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

	&EPA

\\CASTAIC\PROJ\EPA\CDABASIN 382081\GIS\MAPFILES\FFS\APPENDIXA\FFS APDXA OU2ERESIDUALBASEFLOW.MXD JCARR3 5/17/2010 12:12:09


-------

-------
SFOB-MW03D

2.52

2.92

SF-OB-PZ-24
f— 1.71
/ 2.04

/	USBM-MW04

I /— 1.23
/ 1.39

SF-OB-MW02

5.52

6.90

SF-OB-MW07

0.98

1,76

SF-OB-PZ-14
/— 0.63

1 33

SF-QB-PZ-13
ft 0.18
/ 0.45
/	SF-OB-MW09

/ / 0.81
L _4 0.99

SF-OB-MW12
/" 0.63
/ 0.55
v/	SF-OB-MW05

-0.71

N$S<: -0.95

SF-OB-MW08

2.09

3.71

SF-OB-PZ-19

-0.48

0.35

OSBURN

SF-OB-MW01S

-4.22

-3.95

SF-OB-PZ-04
/ rr -2.64
-2.84

SF-OB-MW06

2.43

3.14

SF-OB-PZ-15

1.11

1.38

South Fork
Coeur d'Alene River

Upper Basin,
Coeur d'Alene—
River, North Fork



\ |U|T



s\.

V
/

WA





Lower Basin, j
Coeur d'Alene—'
River



i Upper Basin,
'—Coeur d'Alene
River, South Fork

Residual (feet)

~

-51 to -25

ฆ

o
o

ID
(N

~

-10 to -5

ฆ

-5 to -1

•

-1 to 1

•

1 to 5

•

5 to 10

•

10 to 25

•

25 to 40

		

River/Creek

~ City Limit

SF-OB-PZ-04 (Site ID)
-2.64 (Previous Residual)
-2.84 (Current Residual1)

500 1,000

_j	i	i	I	L

2,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Note:

Residual is equal to simulated groundwater
elevation minus measured groundwater elevation.

Figure A-6c

Residuals between Measured
and Simulated Groundwater
Elevations, Osburn Fiats,
Baseflow Conditions
Focused Feasibility Study
Upper Basin of the Coeur d'Alene River
BUNKER HILL SUPERFUND SITE

	v>EPA

\\CASTAIC\PROJ\EPA\CDABASIN 382081 \GIS\MAPFiLES\FFS\APPENDIXA\FFS APDXA OSBRESIDUALBASEFLOW.MXD JCARR3 6/22/2010 15:42:05


-------

-------
2650

2600

| 2550

ง> 2500

J. 2450

> 2400

2350

O 2300

0ฃ

O
Q
LU

t? 2250

2200

2150

LINE REPRESENTS PERFECT MATCH
BETWEEN OBSERVED AND SIMULATED
GROUNDWATER ELEVATIONS

/

BOX RMS/RANGE = 1.1%

A BOX WELLS (MODEL LAYER 1)
BOX WELLS (MODEL LAYER 2)
O BOX WELLS (MODEL LAYER 4)

2150 2200 2250 2300 2350 2400 2450 2500 2550 2600
OBSERVED GROUNDWATER ELEVATION (feet above mean sea level)

2650

Figure A-7

Simulated versus Observed
Groundwater Elevations -
7Q10 Conditions

Note:	Focused Feasibility Study

RMS/Range is a measure of model calibration	Upper Basin of the Coeur d'Alene River

and is equal to the root mean squared error	BUNKER HILL SUPERFUND SITE

divided by the range in measured groundwater

elevation. g%
	iSr

\\Odin\proj\usepa\323O31\BunkerHill\Figures\GRAPHER\2OO9_12_FEFS_ModelingAppendix\FIGURE_A-7_Scattergram_7Q10.grf


-------

-------
BH-SF-W-0018-U
-0.79

BH-SF-W-0121-U
-0.76

BH-SF-W-0120-U
0.84

BH-SF-W-0104-U
2.82

BH-SF-W-Q111-U

12.03

BH-SF-W-0114-U
1.84

BH-SF-W-0115-L

7.52

PINEHURST

Vฐ'

%

%

CO
o

k-

(C

E

0)

Q

>K

	

Upper Basin,

Coeur d'Alene—v j
River, North Fork y-OC





tiiiy ""i

C. I jj



—\f—

Lower Basin,

Coeur d'Alene—'

River

I Upper Basin,
'—Coeur d'Alene
River, South Fork

Residual (feet)

~

-51 to -25

~

o
o

LO
(N

~

-10 to -5

~

-5 to -1

o

-1 to 1

O

1 to 5

O

5 to 10

O

10 to 25

o

25 to 40



River/Creek

~ City Limit

BH-SF-W-0018-U (Site ID)
-0.79 (7Q10 Residual1)

AO 500 1,000 2,000 Feet
I	l	l	l	I	l	l	l	I

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Notes:

1.	Residual is equal to simulated groundwater
elevation minus measured groundwater elevation.

2.	The demarcation line represents the area of
overlap between two connected figures such
that data for the previous/subsequent figure
are not displayed on the current figure.

Figure A-8a

Residuals between Measured
and Simulated Groundwater
Elevations, Western Bunker Hill
Box, 7Q10 Conditions
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

	&EPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFILES\FFS\APPENDIXA\FFS_APDXA_OU2WRESIDUAL7Q10.MXD JCARR3 5/17/2010 12:52:42


-------

-------
SMELTERVILLE

WARDNER

Residual (feet)

~

-51 to -25

~

o
o

LO
(N

~

-10 to -5

~

-5 to -1

o

-1 to 1

O

1 to 5

O

5 to 10

O

10 to 25

o

25 to 40



River/Creek

~ City Limit

BH-SF-E-0101 (Site ID)
0.03 (7Q10 Residual1)

AO 500 1,000 2,000 Feet
I	I	I	I	I	I	I	I	I

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Notes:

1.	Residual is equal to simulated groundwater
elevation minus measured groundwater elevation.

2.	The demarcation line represents the area of
overlap between two connected figures such
that data for the previous/subsequent figure
are not displayed on the current figure.

Figure A-8b

Residuals between Measured
and Simulated Groundwater
Elevations, Eastern Bunker Hill
Box, 7Q10 Conditions
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

	&EPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFILES\FFS\APPENDIXA\FFS_APDXA_OU2ERESIDUAL7Q10.MXD JCARR3 5/17/2010 12:58:02


-------

-------
2650

2600

2550

2500

ฃ. 2450

2400

2350

2300

2250

2200

2150

LINE REPRESENTS PERFECT MATCH
BETWEEN OBSERVED AND SIMULATED
GROUNDWATER ELEVATIONS

OSBURN RMS/RANGE = 2.8%
BOX RMS/RANGE = 2.5%

+ OSBURN WELLS (MODEL LAYER 1)
O OSBURN WELLS (MODEL LAYER 2)
ฃ3 OSBURN WELLS (MODEL LAYER 3)
~ OSBURN WELLS (MODEL LAYER 4)
A BOX WELLS (MODEL LAYER 1)
BOX WELLS (MODEL LAYER 2)

2150 2200 2250 2300 2350 2400 2450 2500 2550 2600
OBSERVED GROUNDWATER ELEVATION (feet above mean sea level)

2650

Note:

RMS/Range is a measure of model calibration
and is equal to the root mean squared error
divided by the range in measured groundwater
elevation.

Figure A-9

Simulated versus Observed
Groundwater Elevations -
90th Percentile Flow Conditions

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE



>roj\usepa\323031

=igures\GRAPHE

iMV1odelingApperKlix\FIGURE_A-9_Scattergn;

JW.grf


-------

-------
BH-SF-W-0104-U
2.01

BH-SF-W-PZ-04
0.06	\

SMELTERVILL

PINEHURST

Upper Basin,

Coeur d'Alene—v j
River, North Fork y-OC





tiiiy ""i

C. I jj



—\f—

Lower Basin,

Coeur d'Alene—'

River

I Upper Basin,
'—Coeur d'Alene
River, South Fork

Residual (feet)

~

-51 to -25

~

o
o

LO
(N

~

-10 to -5

~

-5 to -1

o

-1 to 1

O

1 to 5

O

5 to 10

O

10 to 25

o

25 to 40



River/Creek

~ City Limit

BH-SF-W-0010-U (Site ID)
-2.13 (90th Percentile Flow Residual1)

AO 500 1,000 2,000 Feet
I	I	I	I	I	I	I	I	I

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Notes:

1.	Residual is equal to simulated groundwater
elevation minus measured groundwater elevation.

2.	The demarcation line represents the area of
overlap between two connected figures such
that data for the previous/subsequent figure
are not displayed on the current figure.

Figure A-10a

Residuals between Measured
and Simulated Groundwater
Elevations, Western Bunker Hill
Box, 90th Percentile Flow
Conditions
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

	&EPA

\\CASTAIC\PROJ\EPA\CDABASI N 382081\GIS\MAPFILES\FFS\APPENDIXA\FFS APDXA OU2WRESIDUAL90FLOWTIER. MXD JCARR3 5/17/2010 12:59:38


-------

-------
SMELTERVILLE

BH-SF-E-01Q1
0.21

BH-SF-E-PZ-01
5.54

WARMER

Residual (feet)

~

-51 to -25

~

o
o

LO
(N

~

-10 to -5

~

-5 to -1

o

-1 to 1

O

1 to 5

O

5 to 10

O

10 to 25

o

25 to 40



River/Creek

~ City Limit

BH-SF-E-0101 (Site ID)

0.21 (90th Percentile Flow Residual1)

AO 500 1,000 2,000 Feet
I	I	I	I	I	I	I	I	I

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Notes:

1.	Residual is equal to simulated groundwater
elevation minus measured groundwater elevation.

2.	The demarcation line represents the area of
overlap between two connected figures such
that data for the previous/subsequent figure
are not displayed on the current figure.

Figure A-10b

Residuals between Measured
and Simulated Groundwater
Elevations, Eastern Bunker Hill
Box, 90th Percentile Flow
Conditions
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

	&EPA

\\CASTAIC\PROJ\EPA\CDABASIN 382081\GIS\MAPFILES\FFS\APPENDIXA\FFS APDXA OU2ERESIDUAL90FLOWTIER.MXD JCARR3 5/17/2010 13:02:25


-------

-------
USBM-MWQ4
0.28

SF-OB-MW03D
1.56

SF-OB-MW02

2.75

OSBURN

SF-OB-MW01S
-4.24

South Fork
Coeur d'Alene River

Residual (feet)

~

-51 to -25

~

o
o

LO
(N

~

-10 to -5

~

-5 to -1

o

-1 to 1

O

1 to 5

O

5 to 10

O

10 to 25

o

25 to 40



River/Creek

LH

City Limit

SF-OB-MW01D (Site ID)

-3.84 (90th Percentile Flow Residual1)

AO 500 1,000 2,000 Feet
I	I	I	I	I	I	I	I	I

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Note:

1. Residual is equal to simulated groundwater
elevation minus measured groundwater elevation.

Figure A-10c

Residuals between Measured
and Simulated Groundwater
Elevations, Osburn Flats, 90th
Percentile Flow Conditions

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	&EPA

\\CASTAIC\PROJ\EPA\CDABASIN 382081\GIS\MAPFILES\FFS\APPENDIXA\FFS APDXA OSBRESIDUAL90FLOWTIER.MXD JCARR3 5/17/2010 13:05:41


-------

-------
3000

LINE REPRESENTS PERFECT MATCH
BETWEEN OBSERVED AND SIMULATED
GROUNDWATER ELEVATIONS

CANYON CREEK RMS/RANGE = 1.4%

CANYON CREEK WELLS (MODEL LAYER 1)
CANYON CREEK WELLS (MODEL LAYER 2)

2800

2800

2825 2850 2875 2900 2925 2950 2975 3000
OBSERVED GROUNDWATER ELEVATION (feet above mean sea level)

Note:

RMS/Range is a measure of model calibration
and is equal to the root mean squared error
divided by the range in measured groundwater
elevation.

Figure A-11

Simulated versus Observed
Groundwater Elevations -
Canyon Creek,

90th Percentile Flow Conditions

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

4%

	ฉ

>roj\usepa\323031\Bunkerl-

rigures\GRAPHER\:;;

jy]o€lelmgAppen€lix\FIGURE_A~J'


-------

-------
A2-MWD2
0.45

A4W-ATWD
1.89

A4W-MWS2
1.46

A2-MWS2
-1.47

WOODI^AND
PARK

A6-MWS2
1.19

A4E-MWS1
-1.08

A6-MWS3
2.30



WALLACE

Residual (feet)

~

-51 to -25

ฆ

o
o

ID
(N

~

-10 to -5

ฆ

-5 to -1

•

-1 to 1

•

1 to 5

•

5 to 10

•

10 to 25

•

25 to 40

		

River/Creek

~ City Limit

A2-MWD2 (Site ID)

0.45 (90th Percentile Flow Residual1)

0	500 1,000

	1	i	i	i	I	L

2,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Note:

Residual is equal to simulated groundwater
elevation minus measured groundwater elevation.

Figure A-12

Residuals between Measured
and Simulated Groundwater
Elevations, Canyon Creek, 90th
Percentile Flow Conditions

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	v>EPA

\\CASTAIC\PROJ\EPA\CDABASIN 382081 \GIS\MAPFiLES\FFS\APPENDIXA\FFS APDXA CCRESIDUAL90FLOWTIER.MXD JCARR3 6/22/2010 15:47:14


-------

-------
2370

2369

2368

2367

2366

2365

2364

2363

2362

2361

2360

2275

2274

2273

2272

2271

2270

2269

2268

2267

2266

2265

BH-GG-GW-0004

BH-SF-E-0101

BH-SF-E-0202-U

BH-SF-E-0301-U



nV\_;

2284
2283

o 2281

| 2280
+-ป

(5

o 2279

LU

ฎ 2278

re

5

"g 2277

3

<5 2276

2275
2274

2275

2274

15 2273
E

| 2272

I 2271

13

o 2270

LU

ซ 2269

re

5

"g 2268

3

o

(5 2267
2266

V\*

/A



7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09

7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09

7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

BH-SF-E-0305-U

BH-SF-E-0309-U

BH-SF-E-0314-U

BH-SF-E-0317-U



2280

2279

^ 2278
E

~ 2277

o

,

0?>

If / \\^





„ V ft

 \

^ I

& i\

I 4 * /

/ V









































2275

2274

^ 2273
E

| 2272

.2 2271
15

0	2270

LU

J" 2269

re

5

1	2268

3

o

(5 2267

2266
2265

2265
2264

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

LEGEND

- SIMULATED
MEASURED

Figure A-13a

Simulated versus Measured
Groundwater Elevations -
Bunker Hill Box

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE


-------

-------
2270

2269

2268

2267

2266

2265

2264

2263

2262

2261

2260

2250

2249

2248

2247

2246

2245

2244

2243

2242

2241

2240

BH-SF-E-0320-U

BH-SF-E-0321-U

BH-SF-E-0402-U

BH-SF-E-0410-U

2260

2259

(0

E

| 2257

re
>
o

LU

a> 2254

(5

5

T3

2
o





2251

2250

2258

2257

(0

E

| 2255

| 2254
"S

o 2253

LU

ฃ 2252

re

5

"g 2251

3

<5 2250

2249

2248

2261

TZ 2260
E

| 2259

re
>
o

LU
0)

"S
ง
T3

O

(5 2254

2257





~\r~











<3>





















7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09

7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09

7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

BH-SF-E-0423-U

BH-SF-E-0425-U

BH-SF-E-0427-U

BH-SF-E-0429-U

2250

2249

TZ 2248
E

| 2247

g 2246
+-ป
rc

0	2245

LU

ฎ 2244

TO

5

1	2243

3

<5 2242

ซ 2251
E

1 2250

J 2249
13

0	2248

LU

ฃ 2247

(5

5

1	2246

3

o

(5 2245

V

-J*—"

2248

2247

^ 2246
E

| 2245

J 2244
13

0	2243

LU

ฃ 2242

(5

5

1	2241

3

o

(5 2240

2241
2240

2244
2243

2239

2238

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

LEGEND

- SIMULATED
MEASURED

Figure A-13b

Simulated versus Measured
Groundwater Elevations -
Bunker Hill Box

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE


-------

-------
BH-SF-E-0502-U

BH-SF-E-0503-U

BH-SF-E-PZ-01

BH-SF-E-PZ-03

2234
2233

re
>
o

LU

ป V

2240

2239

^ 2238
E

| 2237

2236

re
>
o

LU

ฎ 2234

re

5

"g 2233

3

(5 2232

2231
2230

2294

2 2292

| 2291
re

o 2290

LU

ฎ 2289

rc

5

"g 2288

3

<5 2287

2286
2285

A"W\S





2290

2289

15 2288
E

| 2287

| 2286
13

o 2285

LU

ฃ 2284

re

5

"g 2283

3

o

(5 2282
2281
2280

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

BH-SF-E-PZ-04

BH-SF-E-PZ-05

BH-SF-E-PZ-06

BH-SF-E-PZ-08

2290
2289
2288
2287
2286
2285
2284
2283
2282
2281
2280

2284
2283

~ 2282
in

E

2281



0

LU 2278

0)

1	2277

T3

| 2276

2

ฉ 2275
2274
2273

2284

2283

^ 2282
E

1 2281

| 2280
13

0	2279

LU

ฃ 2278

re

5

1	2277

3

o

(5 2276
2275
2274























































% ffn ป

. y











0 V



\jw



AJy

A % f

i ^







\
%











%

%

\

% ปe

0 '

to c

i







N

\

vป*



















7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

LEGEND

- SIMULATED
MEASURED

Figure A-13c

Simulated versus Measured
Groundwater Elevations -
Bunker Hill Box

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

>roj\usepa\323031\Bunkerh

3RAPHER\2009

_MocfelingAppendix\FIGURE__A-13c__BoxHydrogra|:

"Xf


-------

-------
BH-SF-E-PZ-09

BH-SF-E-PZ-10

BH-SF-E-PZ-11

BH-SF-E-PZ-13

2278
2277
2276
2275
2274
2273
2272
2271
2270
2269
2268
2267

%

V



2280
2279
2278
2277
2276
2275
2274
2273
2272
2271
2270
2269

2277
2276

o 2274

| 2273
"S

o 2272

LU

ฎ 2271

re

5

"g 2270

3

<5 2269

2268
2267





2284

2283

„ 2282
to

ฃ 2281
+-ป

0)

ฃ 2280

.1 2279
13

o 2278

LU

5 2277
"S

j> 2276

T3

o

2275
2274
2273
2272

V



7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09

7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09

7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

BH-SF-E-PZ-14

BH-SF-E-PZ-15

BH-SF-E-PZ-16

BH-SF-E-PZ-17

2270

2269

TZ 2268
E

| 2267

g 2266
+-ป

(5

0	2265

LU

ฎ 2264

TO

5

1	2263

3

<5 2262

2261

2260

2275

2274

15 2273
E

| 2272

g 2271
+-ป

(5

0	2270

LU

ฎ 2269

GJ

5

1	2268

3

<5 2267
2266
2265

2268

2267

^ 2266
E

| 2265

J 2264
13

0	2263

LU

ฃ 2262

re

5

1	2261

3

o

(5 2260
2259
2258

A



2262

2261

^ 2260
E

1 2259

rc

o 2257

LU

ฃ 2256
re
5

T3

O

<5 2254

X

r*\

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

LEGEND

- SIMULATED
MEASURED

Figure A-13d

Simulated versus Measured
Groundwater Elevations -
Bunker Hill Box

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE


-------

-------
BH-SF-E-PZ-18

BH-SF-E-PZ-20

BH-SF-E-PZ-21

BH-SF-E-PZ-22

2257

(0

E

| 2255

| 2254
"S

o 2253

LU

ฃ 2252

(5

5

"g 2251

3

<5 2250

2249
2248

2254

(0

E

| 2251

2250

- 2249

o
+-ป

(5
>

0

LU

3> 2248

GJ

"g 2247

3

<5 2246
2245
2244

r-	

2244
2243

o 2241

2240

* 2239

o
+-ป

(5
>

0

LU

S 2238

GJ

5

"g 2237

3

<5 2236

2234



1 0 \

,v\

2245

2244

^ 2243
E

| 2242

| 2241
15

o 2240

LU

ฃ 2239

(5

5

"g 2238

3

o

<5 2237

2236

I

,&w"V	_

vr

& d& ฎ ฎ

JS

i V \



ฐ \ * \\
\ ฐ \
V •



/sr*V

*









7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

BH-SF-E-PZ-23

BH-SF-E-PZ-24

BH-SF-E-PZ-25

BH-SF-E-PZ-26

2254

2251
2250
2249
2248
2247
2246
2245
2244

-Ar

2250
2249
2248
2247
2246
2245
2244
2243
2242
2241
2240

2244

2243

? 2242
E

1 2241

J 2240
13

0	2239

LU

ฃ 2238

re

5

1	2237

3

o

(5 2236

2234





2240

2239

^ 2238
E

1 2237

| 2236
13

0	2235

LU

ฃ 2234

(5

5

1	2233

3

o

<5 2232
2231
2230



' V V*



7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

LEGEND

- SIMULATED
MEASURED

Figure A-13e

Simulated versus Measured
Groundwater Elevations -
Bunker Hill Box

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

i\323031\BunkerHill\Figures\GRAPHER\2009_12_FEFS_ModelingAppendix\FIGURE_A-13e_BoxHydrograf:




-------

-------
2240

2239

2238

2237

2236

2235

2234

2233

2232

2231

2230

2235

2234

2233

2232

2231

2230

2229

2228

2227

2226

2225

BH-SF-E-PZ-27

2240
2239

BH-SF-E-PZ-28

2240
2239

BH-SF-E-PZ-29

2240
2239

ฆJo 2238

E

| 2237
o 2236

re
>
o

LU

a> 2234

re

5

"2 2233

2
o

2231
2230



2 2237

| 2236
+ฆป
re
>


0

LU

ฃ 2234

GJ

"2 2233

O

o

2231
2230

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09

7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09

7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08

BH-SF-E-PZ-31

2235

BH-SF-E-PZ-32

2230

BH-SF-W-0001-U

2215

2234

2214

"Jo 2233
E

| 2232

g 2231
+-ป

(5

o 2230

LU

5 2229

GJ

5

T3

O 2227

2225

(0

E

| 2227

g 2226
"S

o 2225

LU

ฃ 2224
re
5

T3

O

(5 2222
2221
2220

m 2213

$ 2212

J 2211
13

0	2210

LU

ฃ 2209

re

5

1	2208

3

o

(5 2207

2206

2205

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08

LEGEND

- SIMULATED
MEASURED


-------

-------
2215

2214

2213

2212

2211

2210

2209

2208

2207

2206

2205

2200

2199

2198

2197

2196

2195

2194

2193

2192

2191

2190

BH-SF-W-0010-U

BH-SF-W-0018-U

BH-SF-W-0021-U



2214

2213

?2212
E

"S 2211
ฃ

I 2210

"S

j) 2209

LU


o

LU

S 2203

GJ

5

"g 2202

3

o

(5 2201
2200
2199

- 2204

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08

BH-SF-W-0104-U

BH-SF-W-0111-U

BH-SF-W-0118-U

2205
2204
2203
2202
2201
2200
2199
2198
2197
2196
2195

>5

VA

wป

2198

2197

^ 2196
E

1 2195

Hi

J 2194
13

0	2193

LU

ฃ 2192

(5

5

1	2191

3

o

(5 2190
2189
2188

2195

2194

TZ 2193
E

"5 2192

J 2191
13

0	2190

LU

ฃ 2189

(5

5

1	2188

3

o

(5 2187

2186

2185

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08

9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08

LEGEND

- SIMULATED
MEASURED


-------

-------
BH-SF-W-0201 -U

BH-SF-W-PZ-03

BH-SF-W-PZ-04

BH-SF-W-PZ-05

2195

2194

TZ 2193
E

"S 2192
ฃ

I 2191

"S

o 2190

LU

ฃ 2189

re

5

"g 2188

3

<5 2187
2186

2185

KJ*

o o % 0

ฐ %s 1

2200

2199

^ 2198
E

"S 2197
ฃ

2196

- 2195

o
+-ป

(5
>

0

LU

S 2194

GJ

5

"g 2193

3

<5 2192
2191

2190



ฆvV

ic\

2200
2199

o 2197

| 2196
+-ป

(5

o 2195

LU

ฎ 2194

re

5

"g 2193

3

<5 2192

2191
2190

2200

2199

TZ 2198
E

| 2197

| 2196
13

o 2195

LU

ฎ 2194

re

5

"g 2193

3

o

(5 2192
2191
2190

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

BH-SF-W-PZ-06

BH-SF-W-PZ-07

SF-OB-MW01S

SF-OB-MW01D

2198

2197

TZ 2196
E

| 2195

g 2194
+-ป
rc

0	2193

LU

ฃ 2192

GJ

5

1	2191

3

<5 2190
2189
2188

2195

2194

TZ 2193
E

| 2192

g 2191
+-ป

(5

0	2190

LU

ฎ 2189

TO

5

1	2188

3

<5 2187
2186
2185







ฐ

00^

oY *0 a





w























2551

2550

=5 2549
E

1 2548

J 2547
13

0	2546

LU

ฃ 2545

re

5

1	2544

3

o

(5 2543
2542
2541







2550

2549

TZ 2548
E

| 2547

| 2546
13

0	2545

LU

ฎ 2544

re

5

1	2543

3

o

(5 2542
2541
2540

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

LEGEND

- SIMULATED
MEASURED

Figure A-13h

Simulated versus Measured
Groundwater Elevations -
Bunker Hill Box/Osburn Flats

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE


-------

-------
2508

2507

2506

2505

2504

2503

2502

2501

2500

2499

2498

2460

2459

2458

2457

2456

2455

2454

2453

2452

2451

2450

SF-OB-MW02

SF-OB-MW10

SF-OB-PZ-17

SF-OB-PZ-24































ss

y

/V



2505
2504
2503
2502
2501
2500
2499
2498
2497
2496
2495

2505
2504

2 2502

| 2501
+-ป
rc

o 2500

LU

ฃ 2499

(5

5

"g 2498

D

<5 2497

2496
2495

2460

2459

TZ 2458
E

| 2457

| 2456
13

o 2455

LU

ฃ 2454

(5

5

"g 2453

D

o

(5 2452
2451
2450

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

USBM-MW04

Figure A-13i

Simulated versus Measured
Groundwater Elevations -
Osburn Flats

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

LEGEND

- SIMULATED
MEASURED


-------

-------
A2-MWS2

A2-MWD2

A4E-MWS1

A4E-MWD1

2964

2961

n 2960

E

o

a

| 2959

+-ป

(5
>

0

LU

2958

GJ

"O
c

3

o 2957

2956

\
• ฃ

V

V

%

v

y

\

2923

ซ 2922
E

\ I

.2

* -a



. -V





f -A

2922

ฆJo 2921

E
o
ฃ

| 2920

"S
>
o

LU

ฃ 2919

re

5

T3
C
3

o

(5 2918

2917



7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09

7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09

7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

A4W-MWS2

A4W-ATWD

A6-MWS2

A6-MWS3

2928

ฆJo 2927
E
o
ฃ

o 2926

<ง 2924

2923



2929

"Jo 2928
E
o
ฃ

g 2927
+-ป

(5
>

0

LU

5 2926

TO

"O
c

3

o 2925

2924







2866

2865

E
"5
ฃ

| 2864

13
>
o

LU

5 2863

GJ

"O
c

3

o

o 2862







VVV



2862

w 2861

E

"S
.
0

LU
0

"S

-o

o

o 2858

2857

JV;	\



7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

7/1/08 9/1/08 11/1/08 1/1/09 3/1/09 5/1/09 7/1/09

Figure A-14

Simulated versus Measured
Groundwater Elevations -
Canyon Creek Watershed

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

EFฅV



LEGEND

- SIMULATED
MEASURED

i\323031\BunkerHill\Figures\GRAPHER\2009__12__FEFS__ModelingAppendix\FIGURE__A-14__CanyonCreekHydrographs.gti


-------

-------
The Bunker Hill Box

^MELTERVILL
X 0.0022

WARDNER

Dissolved Zinc (mg/L) (4Q0S)



Oto 5



5 to 10

•

10 to 15

•

15 to 25

•

25 to 50

•

50 to 75



Mass Loading Reach



River/Creek

~ City Limit

0.12 (4Q08 Dissolved Zinc Concentration [mg/L])
0.13 (2Q09 Dissolved Zinc Concentration [mg/L])
mg/L = milligrams per liter

0	1,000 2,000

	1	i	i	i	I	i

4,000 Feet



Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-15

OU 2 Mass Loading Reaches
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

	svEPA


-------

-------
CC451
0,48

REACH 12

REACH 11

A4W-ATWD
3.84

A4W-MWS1 _
2.14

A4W-MWS3
1.60

A4W-MWD1
3.01	~~I

A4W-MWS2 _
3.08	~1

REACH9

REACH 10

REACH7
-REACH 8

ฆ "• CC460
\ 9.90

REACH6
REACH5-

CC467
13.40

_ CC463
13.20 CC459

1220 A2-MWS1

13-20 A2-MWD1

—I	15 70 A2-MWS2

^	Z	524 A2-MWD2

' 			16-20 A2-ATWD

_ CC464	16.70

-i^CC1496

	^ CC1505

NS

CC1506

51.60 .. .

-	 Unknown

124.00
MW-CCTW-01D

MW-CCTW-01 S
15.30

A4E-MW-S3
\X\ 28.40
VSC A4E-ATWD
V\ 8.94

A4E-MWS1
26.20

CC1509
49.20

CC1511
2.71

CC468
1.93 \
CC1494 __
12.70
CC1493
5.81

CC1512
5.97

CC1492
8.88

CC469
0.021 s

CC1515
5.24

CC1490
9.71

REACH3—
REACH 2

L_ CC1508

50.60
_ A4E-MWD1

12.10
_ A4E-MWS2

9.36
_ CC462

11.60
. CC1497

21.90
. CC1510
20.9

CC1501
5.86

REACH1

A6-MW2 _
5.39
A6-MW1
2.83

A6-MW3
0.865

/ j1_ CC1498

/ / 29-ฐ
| L_ CC1513
/ 13.00

L CC1514

16.60
CC465
2.33

CC480
0.985

CC481
1.92

CC1499

WALLACE

Upper Basin,

Coeur d'Alene—v j
River, North Fork

\ MT



vTjy





Lower Basin, J
Coeur d'Alene—'
River



, Upper Basin,
'—Coeur d'Alene
River, South Fork

Dissolved Zinc (mg/L)

•

0to 5

•

5 to 10

•

10 to 15

•

15 to 25

•

25 to 50

•

50 to 124

~

Canyon Creek

	

River/Creek

~

City Limit

CC453 (Site ID)

12.30 (Dissolved Zinc Concentration [mg/L])
mg/L = milligrams per liter

0	500 1,000

	1	i	i	i	I	

2,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-16

Woodland Park Mass Loading
Reaches

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	*>EPA

WCASTAlC\PROJ\EPA\CDABASIN 382Q81\GIS\MAPFILES\FFS\APPENDIXA\FFS APDXA WOODREACHES.MXD JCARR3 6/30/2010 07:55:19


-------

-------
The Bunker Hill Box

South Fork
Coeur d'Alene River

SMELTERVILLE

PINEHURST

WARDNE

Install Check Dams Within
— Reed and Russell
Adit Tunnels

Cherry Raise

Upper Basin,
Coeur d'Alene—
River, North Fork

m /



\

\

\ MT





^7

\







Lower Basin, I
Coeur d'Alene—'
River



i Upper Basin,
'—Coeur d'Alene
River, South Fork

ฆ	Central Treatment Plant (CTP)
0 Adit

ฆ	Raise

Conveyance of Reed and Russell adit
discharge through the Bunker Hill Mine
via the Cherry Raise and the Kellogg
Tunnel to the CTP

Stream Liner
River/Creek

~ City Limit

Note: Conveyance and treatment of Reed and Russell
adit discharge is a contingency action that will be
implemented only if check dams do not eliminate the
flow of contaminated water from the adits.

1,000 2,000

4,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-17

OU 2 Alternative (a):

Minimal Stream Lining

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	SEPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_OU2ALTS.MXD JCARR3 5/26/2010 15:37:09


-------

-------
The Bunker Hill Box

South Fork
Coeur d'Alene River

SMELTERVILLE

PINEHURST

WARDNE

Install Check Dams Within
— Reed and Russell
Adit Tunnels

Cherry Raise

Upper Basin,
Coeur d'Alene—
River, North Fork

ID I



\

\

\ MT

1

^7

\







—



Lower Basin, I
Coeur d'Alene—'
River



1 Upper Basin,
'—Coeur d'Alene
River, South Fork

0

Central Treatment Plant (CTP)

Adit

Raise

Conveyance of Reed and Russell adit
discharge through the Bunker Hill Mine
via the Cherry Raise and the Kellogg
Tunnel to the CTP

Slurry Wall

Stream Liner

Extraction Wells

River/Creek

~ City Limit

Note: Conveyance and treatment of Reed and Russell
adit discharge is a contingency action that will be
implemented only if check dams do not eliminate the
flow of contaminated water from the adits.

1,000 2,000

4,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-18

OU 2 Alternative (b):

Extensive Stream Lining

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	SEPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_OU2ALTS.MXD JCARR3 5/27/2010 08:14:31


-------

-------
The Bunker Hill Box

South Fork
Coeur d'Alene River

SMELTERVILLE

PINEHURST

WARDNE

Install Check Dams Within
— Reed and Russell
Adit Tunnels

Cherry Raise

Upper Basin,
Coeur d'Alene—
River, North Fork

m /



\

\

\ MT





^7

\







Lower Basin, I
Coeur d'Alene—'
River



i Upper Basin,
'—Coeur d'Alene
River, South Fork

ฆ	Central Treatment Plant (CTP)

I	Pump Station

0	Adit

~	Raise

Conveyance of Reed and Russell adit
discharge through the Bunker Hill Mine
via the Cherry Raise and the Kellogg
Tunnel to the CTP

Conveyance Pipeline

CTP Effluent Discharge Pipeline

= French Drain

	 River/Creek

~ City Limit

Note: Conveyance and treatment of Reed and Russell
adit discharge is a contingency action that will be
implemented only if check dams do not eliminate the
flow of contaminated water from the adits.

1,000 2,000

4,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-19

OU 2 Alternative (c):

French Drains

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	SEPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_OU2ALTS.MXD JCARR3 5/27/2010 08:14:31


-------

-------
The Bunker Hill Box

South Fork
Coeur d'Alene River

SMELTERVILLE

PINEHURST

WARDNE

Install Check Dams Within
— Reed and Russell
Adit Tunnels

Cherry Raise

Upper Basin,
Coeur d'Alene—
River, North Fork

m /



\

\

\ MT





^7

\







Lower Basin, I
Coeur d'Alene—'
River



i Upper Basin,
'—Coeur d'Alene
River, South Fork

ฆ	Central Treatment Plant (CTP)

I	Pump Station

0	Adit

~	Raise

Conveyance of Reed and Russell adit
discharge through the Bunker Hill Mine
via the Cherry Raise and the Kellogg
Tunnel to the CTP

Conveyance Pipeline

CTP Effluent Discharge Pipeline

= French Drain

= Slurry Wall

' Stream Liner

= Extraction Wells

		 River/Creek

~ City Limit

Note: Conveyance and treatment of Reed and Russell
adit discharge is a contingency action that will be
implemented only if check dams do not eliminate the
flow of contaminated water from the adits.

1,000 2,000

4,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-20
OU 2 Alternative (d):

Stream Lining/French Drain
Combination

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	SEPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_OU2ALTS.MXD JCARR3 5/27/2010 08:14:31


-------

-------
The Bunker Hill Box

South Fork
Coeur d'Alene River

SMELTERVILLE

PINEHURST

WARDNE

Install Check Dams Within
— Reed and Russell
Adit Tunnels

Cherry Raise

Upper Basin,
Coeur d'Alene—
River, North Fork

m /



\

\ MT





^7



















Lower Basin, I
Coeur d'Alene—'
River



i Upper Basin,
'—Coeur d'Alene
River, South Fork

0

~

Central Treatment Plant (CTP)

Pump Station

Adit

Raise

Conveyance of Reed and Russell adit
discharge through the Bunker Hill Mine
via the Cherry Raise and the Kellogg
Tunnel to the CTP

Conveyance Pipeline

French Drain

Slurry Wall

Stream Liner

Extraction Wells

River/Creek

~ City Limit

Note: Conveyance and treatment of Reed and Russell
adit discharge is a contingency action that will be
implemented only if check dams do not eliminate the
flow of contaminated water from the adits.

1,000 2,000

4,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-21
OU 2 Alternative (e):

Extensive Stream Lining/French
Drain Combination

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	SEPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_OU2ALTS.MXD JCARR3 5/27/2010 08:14:31


-------

-------
KLE034

SILVER DOLLAR MINE

OSBURN

WALQ35

OSBURN ROCKPIT
ALONG 1-90

KLE011

SILVER CRESCENT TAILINGS

SILVERTON

WAL020
CALADAY MINE

French Drain
Stream Liner
River/Creek
Capped Tailings Pile

~ City Limit

WAL020 (Site ID)

CALADAY MINE (Site Name)

AO 1,000 2,000 4,000 Feet
!	i	i	i	I	(	(	i	!

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

iDWR (Aerial Imagery, 2006).

Figure A-22

Groundwater Components of
OU 3 Remedial Alternatives for
the Mainstem SFCDR Watershed,
Segment 01

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	SEPA

\\CASTAIC\PROJ\EPA\CDABASIN 382081\GIS\MAPFILES\FFS\APPENDIXA\FFS APDXA SFCDRALT.MXD JCARR3 5/17/2010 14:49:55


-------

-------
French Drain
Stream Liner
River/Creek

~ City Limit

0	500 1,000

	1	I	I	I	I	l_

2,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

\\CASTAIC\PROJ\EPA\CDABASIN 382081 \GIS\MAPFiLES\FFS\APPENDIXA\FFS APDXA WOODALTE.MXD JCARR3 5/24/2010 11:38:14

Figure A-23

Groundwater Components of
Updated Remedial Actions for
Woodland Park
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

	SEPA


-------

-------
The Bunker Hill Box

South Fork
Coeur d'Alene River

SMELTERVILLE

PINEHURST

Upper Basin,
Coeur d'Alene—
River, North Fork

ID I



\

\ MT

I

^7

\











Lower Basin, I
Coeur d'Alene—'
River



i Upper Basin,
'—Coeur d'Alene
River, South Fork

Simulated Groundwater Flowpath
Simulated Gaining Stream Reach
Simulated Losing Stream Reach
•4 Simulated Groundwater Flow Direction

	 River/Creek

~ City Limit

AO 1,000 2,000	4,000 Feet

I	i	i	i	I	i	i	i	I

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-24

Simulated Upstream Groundwater
Flowlines from the SFCDR,
No Action, Baseflow Conditions
Focused Feasibility Study
Upper Basin of the Coeur d'Alene River
BUNKER HILL SUPERFUND SITE

	v>EPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_OU2NOACTION.MXD JCARR3 5/24/2010 12:01:07


-------

-------
The Bunker Hill Box

South Fork
Coeur d'Alene River

SMELTERVILLE

PINEHURST

WARDNER

Install Check Dams Within
Reed and Russell
Adit Tunnels

Cherry Raise

Upper Basin,
Coeur d'Alene—
River, North Fork



\ MT





\

A

\ ^

K

K



v^-





Lower Basin,
Coeur d'Alene—'
River



Upper Basin,
'—Coeur d'Alene
River, South Fork

0

Central Treatment Plant (CTP)

Adit

Raise

Conveyance of Reed and Russell adit
discharge through the Bunker Hill Mine
via the Cherry Raise and the Kellogg
Tunnel to the CTP

Stream Liner

Simulated Groundwater Flowpath
Simulated Groundwater Flow Direction
River/Creek

~ City Limit

Note: Conveyance and treatment of Reed and Russell
adit discharge is a contingency action that will be
implemented only if check dams do not eliminate the
flow of contaminated water from the adits.

1,000 2,000

4,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-25

Simulated Upstream Groundwater
Flowlines from the SFCDR, OU 2
Alternative (a), Baseflow
Conditions

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	*>EPA

\\CASTAIC\PROJ\EPA\CDABASIN 382081 \GIS\MAPFILES\FFS\APPENDIXA\FFS APDXA OU2ALTS.MXD JCARR3 5/26/2010 15:37:09


-------

-------
The Bunker Hill Box

South Fork
Coeur d'Alene River

PINEHURST

WARDNER

Install Check Dams Within
ฆ— Reed and Russell
Adit Tunnels

Cherry Raise

0

Central Treatment Plant (CTP)

Adit

Raise

Conveyance of Reed and Russell adit
discharge through the Bunker Hill Mine
via the Cherry Raise and the Kellogg
Tunnel to the CTP

Slurry Wall

Stream Liner

Extraction Wells

Simulated Groundwater Flowpath
Simulated Groundwater Flow Direction
River/Creek

~ City Limit

Note: Conveyance and treatment of Reed and Russell
adit discharge is a contingency action that will be
implemented only if check dams do not eliminate the
flow of contaminated water from the adits.

1,000 2,000

4,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-26

Simulated Upstream Groundwater
Flowlines from the SFCDR, OU 2
Alternative (b), Baseflow
Conditions

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	v>EPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_OU2ALTS.MXD JCARR3 5/27/2010 08:14:31


-------

-------
/

IS

The Bunker Hill Box

=

South Fork
Coeur d'Alene River

PINEHURST



_

Install Check Dams Within
Reed and Russell
Adit Tunnels

ฆ	Central Treatment Plant (CTP)

I	Pump Station

0	Adit

~	Raise

Conveyance of Reed and Russell adit
discharge through the Bunker Hill Mine
via the Cherry Raise and the Kellogg
Tunnel to the CTP

Conveyance Pipeline

CTP Effluent Discharge Pipeline

= French Drain

Simulated Groundwater Flowpath

<1 Simulated Groundwater Flow Direction

•	 River/Creek

~ City Limit

Note: Conveyance and treatment of Reed and Russell
adit discharge is a contingency action that will be
implemented only if check dams do not eliminate the
flow of contaminated water from the adits.

1,000 2,000

4,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-27a

Simulated Upstream Groundwater
Flowlines from the SFCDR, OU 2
Alternative (c), Baseflow
Conditions

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	c/EPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_OU2ALTS.MXD JCARR3 5/27/2010 08:14:31


-------

-------
The Bunker Hill Box

South Fork
Coeur d'Alene River

SMELTERVILLE

PINEHURST

WARDNE

Install Check Dams Within
•— Reed and Russell
Adit Tunnels

Cherry Raise

ฆ	Central Treatment Plant (CTP)

I	Pump Station

0	Adit

~	Raise

Conveyance of Reed and Russell adit
discharge through the Bunker Hill Mine
via the Cherry Raise and the Kellogg
Tunnel to the CTP

Conveyance Pipeline

CTP Effluent Discharge Pipeline

= French Drain

Simulated Groundwater Flowpath

<1 Simulated Groundwater Flow Direction

•	 River/Creek

~ City Limit

Note: Conveyance and treatment of Reed and Russell
adit discharge is a contingency action that will be
implemented only if check dams do not eliminate the
flow of contaminated water from the adits.

1,000 2,000

4,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-27b

Simulated Upstream Groundwater
Flowlines from French Drains,
OU 2 Alternative (c), Baseflow
Conditions

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	c/EPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_OU2ALTS.MXD JCARR3 5/27/2010 08:14:31


-------

-------
The Bunker Hill Box

South Fork
Coeur d'Alene River

PINEHURST

WARDซi5?

Install Check Dams Within
— Reed and Russell
Adit Tunnels

Cherry Raise

ฆ	Central Treatment Plant (CTP)

I	Pump Station

0	Adit

~	Raise

Conveyance of Reed and Russell adit
discharge through the Bunker Hill Mine
via the Cherry Raise and the Kellogg
Tunnel to the CTP

Conveyance Pipeline

CTP Effluent Discharge Pipeline

= French Drain

= Slurry Wall

' ! Stream Liner

Extraction Wells

Simulated Groundwater Flowpath
<< Simulated Groundwater Flow Direction

*	 River/Creek

~ City Limit

Note: Conveyance and treatment of Reed and Russell
adit discharge is a contingency action that will be
implemented only if check dams do not eliminate the
flow of contaminated water from the adits.

1,000 2,000

4,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-28a

Simulated Upstream Groundwater
Flowlines from the SFCDR, OU 2
Alternative (d), Baseflow
Conditions

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	SEPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_OU2ALTS.MXD JCARR3 5/27/2010 08:14:31


-------

-------
The Bunker Hill Box

South Fork
Coeur d'Alene River

SMELTERVILLE

PINEHURST

WARDNES?

Install Check Dams Within
— Reed and Russell
Adit Tunnels

Cherry Raise

ฆ	Central Treatment Plant (CTP)

I	Pump Station

0	Adit

~	Raise

Conveyance of Reed and Russell adit
discharge through the Bunker Hill Mine
via the Cherry Raise and the Kellogg
Tunnel to the CTP

Conveyance Pipeline

CTP Effluent Discharge Pipeline

= French Drain

= Slurry Wall

' ! Stream Liner

Extraction Wells

Simulated Groundwater Flowpath
<< Simulated Groundwater Flow Direction

*	 River/Creek

~ City Limit

Note: Conveyance and treatment of Reed and Russell
adit discharge is a contingency action that will be
implemented only if check dams do not eliminate the
flow of contaminated water from the adits.

1,000 2,000

4,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-28b

Simulated Upstream Groundwater
Flowlines from French Drains,
OU 2 Alternative (d), Baseflow
Conditions

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	c/EPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_OU2ALTS.MXD JCARR3 5/27/2010 08:14:31


-------

-------
The Bunker Hill Box

South Fork
Coeur d'Alene River

SMELTERVILLE

PINEHURST

Install Check Dams Within
— Reed and Russell
Adit Tunnels

Cherry Raise

ฆ	Central Treatment Plant (CTP)

I	Pump Station

0	Adit

~	Raise

Conveyance of Reed and Russell adit
discharge through the Bunker Hill Mine
via the Cherry Raise and the Kellogg
Tunnel to the CTP

Conveyance Pipeline

= French Drain

: Slurry Wall

8 > Stream Liner

= Extraction Wells

Simulated Groundwater Flowpath

Simulated Groundwater Flow Direction

•	 River/Creek

~~ City Limit

Note: Conveyance and treatment of Reed and Russell
adit discharge is a contingency action that will be
implemented only if check dams do not eliminate the
flow of contaminated water from the adits.

1,000 2,000

4,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-29

Simulated Upstream Groundwater
Flowlines from French Drains,
OU 2 Alternative (e), Baseflow
Conditions

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

	SEPA

\\CASTAIC\PROJ\EPA\CDABASIN_382081\GIS\MAPFiLES\FFS\APPENDIXA\FFS_APDXA_OU2ALTS.MXD JCARR3 5/27/2010 08:14:31


-------

-------
ฆKg. fwMtm l

ง

' m

mm

Simulated Groundwater Flowpath
4 Simulated Groundwater Flow Direction

	 River/Creek

~ City Limit

AO 1,000 2,000 4,000 Feet

I	i	i	i	I	i	i	i	I

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-30

Simulated Upstream Groundwater
Flowlines from the SFCDR,
Mainstem SFCDR Watershed,
Segment 01, No Action,

Baseflow Conditions
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

	v>EPA

\\CASTAIC\PROJ\EPA\CDABASIN 382081 \GIS\MAPFiLES\FFS\APPENDIXA\FFS APDXA SFCDRBASEFLOW.MXD JCARR3 5/24/2010 12:04:48


-------

-------
KLE034

SILVER DOLLAR MINE

OSBURN

WALQ35

OSBURN ROCKPIT
ALONG 1-90

KLE011

SILVER CRESCENT TAILINGS

WAL020
CALADAY MINE

WALLACE

Upper Basin,

Coeur d'Alene—v j
River, North Fork y-OC

		vmF





,



Lower Basin,
Coeur d'Alene—'
River

I Upper Basin,
'—Coeur d'Alene
River, South Fork

Simulated Groundwater Flowpath

Simulated Groundwater Flow Direction

French Drain

Stream Liner

River/Creek

Capped Tailings Pile

~ City Limit

WAL020 (Site ID)

CALADAY MINE (Site Name)

0	1,000 2,000 4,000 Feet

	1	I	I	I	I	I	I	I	I

Source: NHDPIus (Rivers, Waterbodies); ESRI base
data (Interstates 2006, Major Highways 2008); IDWR
(Aerial Imagery 2006).

Figure A-31

Simulated Upstream Groundwater
Flowlines from French Drains,
Mainstem SFCDR Watershed,
Segment 01, Baseflow
Conditions
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

	&EPA

\\CASTAIC\PROJ\EPA\CDABASI N 382081\GIS\MAPFILES\FFS\APPENDIXA\FFS APDXA SFCDRBASEFLOWFD. MXD JCARR3 5/18/2010 08:36:50


-------

-------
WOODUAND
I PARK-/



WALLACE

Upper Basin,
Coeur d'Alene—

"X J

River, North Fork

i n I



\ MT

\













Lower Basin, I
Coeur d'Alene—'
River



I Upper Basin,
'—Coeur d'Alene
River, South Fork

Simulated Groundwater Flowpath
Simulated Gaining Stream Reach
Simulated Losing Stream Reach
•4 Simulated Groundwater Flow Direction

	 River/Creek

~ City Limit

0

	1	L_

500 1,000

	I	I	I	l_

2,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-32

Simulated Upstream Groundwater
Fiowlines from Canyon Creek,
No Action, Baseflow Conditions
Focused Feasibility Study
Upper Basin of the Coeurd'Aiene River
BUNKER HILL SUPERFUND SITE

	SEPA

\\CASTAIC\PROJ\EPA\CDABASIN 382081 \GIS\MAPFiLES\FFS\APPENDIXA\FFS APDXA WOODALTE.MXD JCARR3 5/24/2010 11:38:14


-------

-------
French Drain
Stream Liner

Simulated Groundwater Flowpath
River/Creek

~ City Limit

0	500 1,000

	1	i	i	i	I	

2,000 Feet

Base Map Data:

NHDPIus (Hydrography, 2005);

ESRI (Roads, Jurisdictional Boundaries, 2006);

IDWR (Aerial Imagery, 2006).

Figure A-33

Simulated Upstream Groundwater
Flowlines from French Drains,
Groundwater Components of
Updated Remedial Actions for
Woodland Park, Baseflow
Conditions
Focused Feasibility Study
Upper Basin of the Coeurd'Aiene River
BUNKER HILL SUPERFUND SITE

	SEPA

\\CASTAIC\PROJ\EPA\CDABASIN 382081 \GIS\MAPFiLES\FFS\APPENDIXA\FFS APDXA WOODALTE.MXD JCARR3 6/22/2010 15:50:34


-------

-------
1400

1300
-D 1200

Q/ 1100
Q

ljl 1000

900
800
700

^ 600

"S 500
>
o

w 400

cc 300

=3
"O

'<ฃ> 200

100

No Action

Calibrated Baseflow Value
Sensitivity Analysis Value

Alternative (a)	Alternative (b)	Alternative (c)

OU 2 Remedial Alternative

A

g

	^	

Alternative (d)

Alternative (e)

Notes:

1.	lb/day = pounds per day

2.	SFCDR = South Fork of the Coeur d'Alene River

3.	OU 2 = Operable Unit 2

Figure A-34
Results of the OU 2
SensitivityAnalysis

Focused Feasibility Study

Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE



>roj\usepa\323031\Bunkei+

jy]o€lelmgApperi€lix\Figure_A~34_




-------

-------
Tables


-------

-------
TABLE A-1

Measured Baseflow Groundwater and Surface Water Elevations in Monitoring Pairs - Government Gulch
Focused Feasibility Study, Upper Basin of the Coeurd'Alene River, Bunker Hill Superfund Site	

Monitoring Well and













Stream Gauging Station

Fall 2007 Elevations

Elevation Difference

Fall 2007 Discharge

Fall 2008 Elevations

Elevation Difference

Fall 2008 Discharge

Pair

(feet msl)

(feet)

(ft3/s)

(feet msl)

(feet)

(cfs)

BH-GG-GW-0002

2605.455





2605.645





BH-GG-0002

2604.582

0.873

0.83

2604.622

1.023

1.18

BH-GG-GW-0009

2475.735





2475.615





BH-GG-0005

2476.726

-0.991

2.41

NM



NM

BH-GG-GW-0010

2440.778





2440.498





BH-GG-0006

2436.515

4.263

1.24

2436.465

4.033

1.52

BH-GG-GW-0003

2407.657





2407.427





BH-GG-0007

2409.55

-1.893

1.25

2409.57

-2.143

0.99

BH-GG-GW-0004

2362.222





2362.062





BH-GG-0008

2363.702

-1.48

1.38

2363.742

-1.68

1.29

BH-GG-GW-0005

2243.52





2243.58





BH-GG-GW-0007

2239.8





2239.91





BH-GG-0001

NM



NM

2253.339

-11.594

1.45

Notes:

Monitoring pairs listed from upstream to downstream.

A positive elevation difference indicates an upward hydraulic gradient (gaining stream).

Surface water and groundwater measurements not collected on the same date.

NM = not measured

msl = mean sea level

cfs = cubic feet per second

Pagel of 1


-------

-------
TABLE A-2

Final PEST Parameter Multipliers

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Parameter

Multiplier

Horizontal Hydraulic Conductivity - Layer 1 Alluvium

1.04

Horizontal Hydraulic Conductivity - Layer 1 Bedrock

1.00

Vertical Hydraulic Conductivity - Layer 1 Alluvium

1.00

Vertical Hydraulic Conductivity - Layer 1 Bedrock

1.00

Horizontal Hydraulic Conductivity - Layer 2 Alluvium

0.49

Horizontal Hydraulic Conductivity - Layer 2 Bedrock

1.00

Vertical Hydraulic Conductivity - Layer 2 Alluvium

1.00

Vertical Hydraulic Conductivity - Layer 2 Bedrock

1.00

Horizontal Hydraulic Conductivity - Layer 3 Alluvium

5.53

Horizontal Hydraulic Conductivity - Layer 3 Bedrock

1.00

Vertical Hydraulic Conductivity - Layer 3 Alluvium

1.00

Vertical Hydraulic Conductivity - Layer 3 Bedrock

1.00

Horizontal Hydraulic Conductivity - Layer 4 Alluvium

0.66

Horizontal Hydraulic Conductivity - Layer 4 Bedrock

1.00

Vertical Hydraulic Conductivity - Layer 4 Bedrock

1.00

Wadi Conductance - Osburn Flats Reach 1

0.26

Wadi Conductance - Osburn Flats Reach 2

0.60

Wadi Conductance - Osburn Flats Reach 3

1.14

Wadi Conductance - Osburn Flats Reach 4

0.88

Wadi Conductance - Bunker Hill Box Reach 1

0.30

Wadi Conductance - Bunker Hill Box Reach 2

2.14

Wadi Conductance - Bunker Hill Box Reach 3

0.79

Wadi Conductance - Bunker Hill Box Reach 4

0.84

Wadi Conductance - Bunker Hill Box Reach 5

1.00

Note:

PEST = parameter estimation

Page 1 of 1


-------

-------
TABLE A-3

Simulated versus Observed Vertical Head Gradients in Well Pairs-Bunker Hill Box
Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









Simulated

Simulated Vertical

Simulated

Simulated Vertical



Difference in Well

Observed Groundwater

Observed Vertical

Groundwater Elevation

Gradient

Groundwater Elevation

Gradient



Screen Mid-Points

Elevation

Gradient

Previous Calibration

Previous Calibration

Updated Calibration

Updated Calibration

Well Name

(feet)

(feet msl)

(ft/ft)

(feet msl)

(ft/ft)

(feet msl)

(ft/ft)

BH-SF-E-0002

35

2,341.60

0.012

2,340.03

0.002

2,339.71

0.003

BH-SF-E-0003



2,341.10



2,339.94



2,339.60



BH-SF-E-PZ-03

50.5

2,283.40

0.315

2,287.15

0.08

2,288.30

0.05

BH-SF-E-0104



2,267.50



2,283.11



2,285.95



BH-SF-E-0202-U

50.5

2,275.80

0.175

2,277.97

0.042

2,279.11

0.03

BH-SF-E-0203-L



2,267.00



2,275.87



2,277.63



BH-SF-E-0301-U

53

2,268.30

0.059

2,271.41

0.028

2,273.45

0.04

BH-SF-E-0302-L



2,265.20



2,269.92



2,271.54



BH-SF-E-0306-U

42.5

2,266.20

0.014

2,270.25

0.007

2,271.85

0.008

BH-SF-E-0305-L



2,265.60



2,269.95



2,271.50



BH-SF-E-0309-U

45.5

2,272.40

0.133

2,271.06

0.02

2,271.86

0.008

BH-SF-E-0310-L



2,266.40



2,270.16



2,271.50



BH-SF-E-0314-U

6

2,269.70

0.027

2,268.49

0.037

2,268.88

0.006

BH-SF-E-0315-U



2,269.60



2,268.27



2,268.84



BH-SF-E-0423-U

62

2,243.50

-0.021

2,246.01

-0.079

2,246.87

-0.09

BH-SF-E-0424-L



2,244.80



2,250.91



2,252.25



BH-SF-E-0425-U

51

2,243.10

0.027

2,246.00

-0.049

2,246.70

-0.06

BH-SF-E-0426-L



2,241.70



2,248.52



2,249.62



BH-SF-E-0427-U

58.5

2,246.60

0.1

2,248.31

-0.026

2,248.73

-0.04

BH-SF-E-0428-L



2,240.70



2,249.85



2,250.93



BH-SF-W-0003-U

66.5

2,214.40

-0.014

2,219.39

0.013

2,219.82

0.015

BH-SF-W-0004-L



2,215.40



2,218.53



2,218.83



BH-SF-W-0005-U

75

2,215.60

-0.037

2,217.72

0.01

2,218.22

0.011

BH-SF-W-0006-L



,2218.4



2,216.98



2,217.43



BH-SF-W-0010-U

59

2,210.20

0.012

2,208.91

-0.01

2,209.97

-0.006

BH-SF-W-0011-L



2,209.50



2,209.51



2,210.32



BH-SF-W-0121-U

72.5

2,188.80

-0.077

2,188.57

-0.002

2,188.74

-0.005

BH-SF-W-0122-L



2,194.40



2,188.71



2,189.08



BH-SF-W-0201 -U

92.5

2,187.00

-0.042

2,186.12

0.001

2,186.46

-0.001

BH-SF-W-0202-L



2,190.90



2,186.07



2,186.55



BH-SF-W-0204-U

100.5

2,172.90

0.011

2,171.25

0.008

2,171.65

0.009

BH-SF-W-0205-L



2,171.80



2,170.44



2,170.71



BH-SF-W-0206-U

119

2,171.70

0.006

2,170.07

0.008

2170.496

0.009

BH-SF-W-0207-L



2,171.00



2,169.17



2169.404



Notes:

A positive value indicates a downward vertical gradient,
ft/ft = foot per foot
msl = mean sea level

Page 1 of 1


-------

-------
TABLE A-4

Simulated versus Observed Vertical Head Gradients in Well Pairs - Osburn Flats
Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









Simulated











Observed



Groundwater

Simulated Vertical

Simulated Groundwater

Simulated Vertical



Difference in Well

Groundwater

Observed Vertical

Elevation

Gradient

Elevation

Gradient



Screen Mid-Points

Elevation

Gradient

Previous Calibration

Previous Calibration

Updated Calibration

Updated Calibration

Well Name

(feet)

(feet msl)

(ft/ft)

(feet msl)

(ft/ft)

(feet msl)

(ft/ft)

SF-OB-MW-01S

9.6

2,547.80

0.055

2,543.70

-0.005

2,543.82

0.007

SF-OB-MW-01D



2,547.20



2,543.80



2,543.76



SF-OB-PZ-17

11.3

2,499.50

0.304

2,500.50

-0.067

2,501.13

-0.162

SF-OB-MW-02



2,496.10



2,501.30



2,502.96



SF-OB-PZ-24

17.8

2,451.90

0.041

2,451.80

-0.023

2,453.92

-0.008

SF-OB-MW-03



2,451.10



2,452.30



2,454.06



SF-OB-MW-06

1.8

2,503.20

-0.003

2,505.30

0.12

2,506.29

0.102

SF-OB-PZ-16



2,503.20



2,505.10



2,506.10



SF-OB-PZ-14

15.4

2,504.50

0.023

2,504.90

0.002

2,505.85

-0.006

SF-OB-MW-07



2,504.20



2,504.90



2,505.93



SF-OB-PZ-13

8.1

2,511.30

0.028

2,511.70

-0.042

2,511.77

-0.039

SF-OB-MW-09



2,511.10



2,512.00



2,512.08



SF-OB-PZ-23

5.4

2,452.90

0.015

2,455.10

0.03

2,457.99

0.024

SF-OB-MW-11



2,452.80



2,455.00



2,457.86



Notes:

A positive value indicates a downward vertical gradient,
ft/ft = foot per foot
msl = mean sea level

Page 1 of 1


-------

-------
TABLE A-5

Comparison of Simulated Stream Gains and Losses to Data Measured During the 2008 Groundwater-Surface Water Interaction Studies
Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site	









SFCDR Discharge Gain/Loss (cfs)







Gain/Loss









Model-simulated

Model-simulated

SFCDR Reaches3

Condition

9/23/2008

9/24/2008

9/25/2008

3-day Average

Previous Calibration

Previous Calibration

BH-SF-LF-0001 to BH-SF-LF-0003

Losing

-6

-10

-7

-7.7

-2.7

-1.8

BH-SF-LF-0003 to BH-SF-LF-0006

Gaining

5

-1

6

3.3

4.8

4.5

BH-SF-LF-0006 to BH-SF-LF-0008

Losing

-5

3

-11

-4.3

-0.4

0.1

BH-SF-LF-0008 to BH-SF-LF-0010

Gaining

23

9

15

15.7

3.1

2.2

BH-SF-LF-0010 to BH-SF-LF-0011

Gaining

32

41

28

33.7

NAb

NAb













Model-simulated

Model-simulated





9/9/2008

9/10/2008

9/11/2008

3-day Average

Previous Calibration

Previous Calibration

Site B-1 ALT to Site B-2 ALT

Losing

-12.7

-14.5

-7.9

-11.7

-3.0

-4.1

Site B-2 ALT to Site B-5 ALT

Gaining

9.1

12.1

8.6

9.9

2.4

3.4

Site B-5 ALT to Site B-7

Losing

-5.5

-9.2

-6.2

-7.0

0.25

0.9

Site B-7 to Site B-8

Gaining

14.9

17.9

15.8

16.2

0.5

0.5

aAlthough the reaches are the same approximate geographic location between the field-measured and simulated data, the exact locations of the transitions between
gaining and losing vary slightly.

bThe change in flow for this reach was not evaluated due to anomalous surface water flow measurements in the western portion of the Box, as noted in the Technical
Report, Osburn Flats Groundwater-Surface Water Interaction Study, Upper Coeur d'Alene Basin, Osburn, Idaho (CH2M HILL, 2009c).

Notes:

cfs = cubic feet per second

SFCDR = South Fork Coeur d'Alene River

Page 1 of 1


-------

-------
TABLE A-6

Simulated Stream Stage Differences for the 90th Percentile Flow Calibration - SFCDR Model

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site	

Stream Stage Difference3

Stream

Stream Gauge

(feet)

Boulder Creek

None

0.2

Bear Creek

None

0.2

Big Creek

None

0.3

Blackcloud Creek

None

0.2

Bunker Creek

BH-BC-0004

0

Bunker Creek

BH-BC-0005

0.1

Bunker Creek

BH-BC-0006

0.2

Canyon Creek

None

0.3

Cook Creek

None

0.2

Deadman Gulch

None

0.2

Deadwood Gulch

BH-DW-0001

0.2

Dexter Gulch

None

0.2

East Fork Big Creek

None

0.2

East Fork Deadman Gulch

None

0.2

Notes:

None

0.2

East Fork Ninemile Creek

None

0.2

East Fork Pine Creek

None

0.3

East Fork Twomile Creek

None

0.2

East Fork Willow Creek

None

0.2

Elk Creek

None

0.3

Gold Creek

None

0.2

Government Creek

BH-GG-0001

0.3

Government Creek

BH-GG-0002

0.3

Government Creek

BH-GG-0004

0.3

Grouse Creek

BH-GC-0001

0.15

Grouse Gulch

None

0.2

Humboldt Creek

BH-HC-0001

0.3

Italian Gulch

None

0.2

Jackass Creek

None

0.2

Lake Creek

None

0.2

Little North Fork of the South Fork Coeur d'Alene River

None

0.2

Little Pine Creek

None

0.3

Magnet Gulch

BH-MG-0001

0.15

McFarren Culch

None

0.2

Middle Fork Pine Creek

None

0.2

Mill Creek

None

0.2

Milo Creek

None

0.3

Montgomery Creek

None

0.3

Moon Creek

None

0.3

Ninemile Creek

None

0.3

Nuckols Gulch

None

0.2

Pine Creek

None

0.3

Placer Creek

None

0.3

Portal Gulch

None

0.2

Railroad Gulch

None

0.2

Revenue Gulch

None

0.2

Rock Creek

None

0.2

Rosebud Gulch

None

0.2

Ruddy Gulch

None

0.2

SFCDR

SF-268 (Elizabeth Park)

2.1

SFCDR

SF-271 (Pinehurst)

1.6

SFCDR

SF-OB-SG01

1.7

SFCDR

SF-OB-SG02

1.2

Page 1 of 2


-------
TABLE A-6

Simulated Stream Stage Differences for the 90th Percentile Flow Calibration - SFCDR Model
Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site





Stream Stage Difference3

Stream

Stream Gauge

(feet)

SFCDR

SF-OB-SG03

1.3

SFCDR

Smelterville

1.6

SFCDR

Theater Bridge

1.6

Shields Gulch

None

0.2

St. Joe Creek

None

0.2

Terror Gulch

None

0.3

Trowbridge Gulch

None

0.2

Twomile Creek

None

0.3

Upper SFCDR Unnamed Tributary

None

0.2

West Fork

None

0.2

West Fork Big Creek

None

0.2

West Fork Deadman Gulch

None

0.2

West Fork Elk Creek

None

0.2

West Fork Montgomery Creek

None

0.2

West Fork Moon Creek

None

0.2

West Fork Pine Creek

None

0.2

West Fork Placer Creek

None

0.2

West Fork Wllow Creek

None

0.2

Wllow Creek

None

0.2

aStream stage difference is equal to the value measured on April 20, 2009, minus the average value measured between
September 22 and October 20, 2008 (the baseflow calibration period).

Note:

SFCDR = South Fork Coeur d'Alene River

Page 2 of 2


-------
TABLE A-7

Monthly Multipliers for Deep Percolation of Precipitation - SFCDR Model

Focused Feasibility Study, Upper Basin of the Coeurd'Alene River, Bunker Hill Superfund Site

Simulation Month

Multiplier

July 2008

2.3

August 2008

1.5

September 2008

1.3

October 2008

1

November 2008

1.3

December 2008

1.5

January 2009

1.7

February 2009

1.9

March 2009

2.5

April 2009

2.9

May 2009

3.6

June 2009

2.9

Note:

SFCDR = South Fork Coeur d'Alene River

Page 1 of 1


-------

-------
TABLE A-8

Monthly Multipliers for Deep Percolation of Precipitation - Canyon Creek Model

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Simulation Month

Multiplier

July 2008

0.1

August 2008

0.02

September 2008

0.01

October 2008

0.01

November 2008

0.02

December 2008

0.025

January 2009

0.05

February 2009

0.05

March 2009

0.1

April 2009

0.15

May 2009

0.2

June 2009

0.15

Page 1 of 1


-------

-------
TABLE A-9

Average Dissolved Zinc Concentrations in Groundwater in Woodland Park, Fall 2006
Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Woodland Park Reach

No Action

Average Dissolved Zinc Concentration
(mg/L)

Post-Sou rce-Control
Average Dissolved Zinc Concentration
(mg/L)

Reach 01

1.5

0.4

Reach 02

3.0

2.5

Reach 03

5.2

4.8

Reach 04

19.5

18.3

Reach 05

13.6

13.0

Reach 06

44.3

42.7

Reach 07

14.4

13.9

Reach 08

13.5

13.1

Reach 09

11.1

10.7

Reach 10

12.3

11.3

Reach 11

1.5

1.2

Reach 12

0.5

0.5

SVNRT

124.0

124.0

Notes:

mg/L = milligram(s) per liter

SVNRT = Silver Valley Natural Resource Trust

Page 1 of 1


-------

-------
TABLE A-10

Net Remedial Effectiveness Factors for Woodland Park Source Control Actions

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site







REF from Simplified

Effective REF Based



Fraction of Total









Proposed Percentage of Total

Tool for Complete

on Limited Source

Area of Source within

Source Area within

Fraction of

Total REF for

Woodland Park Reach

Contaminant Source ID

Volume of Material to be Removed

Removal

Removal3

Reach (feet2)

Reach

Effective REF

Reach

Reach 01

WAL040

72%

99%

71%

1,073,000

0.90

71%



Reach 01

WAL081

50%

99%

50%

115,270

0.10

50%

69%

Reach 02

WAL040

72%

99%

71%

67,083

0.17

71%



Reach 02

WAL041

7%

99%

6%

334,300

0.83

6%

17%

Reach 03

WAL041

7%

99%

6%

572,600

1.00

6%

6%

Reach 04

WAL041

7%

99%

6%

450,200

1.00

6%

6%

Reach 05

WAL041

7%

99%

6%

569,400

0.78

6%



Reach 05

WAL009

0%

0%

0%

165,300

0.22

0%

5%

Reach 06

WAL041

7%

99%

6%

784,500

0.57

6%



Reach 06

WAL009

0%

0%

0%

506,900

0.37

0%



Reach 06

WAL042

50%

0%

0%

73,860

0.05

0%

4%

Reach 07

WAL009

0%

0%

0%

332,300

0.45

0%



Reach 07

WAL041

7%

99%

6%

413,100

0.55

6%

4%

Reach 08

WAL009

0%

0%

0%

344,400

0.55

0%



Notes:

WAL041

7%

99%

6%

192,900

0.31

6%



Reach 08

WAL010

7%

99%

7%

92,610

0.15

7%

3%

Reach 09

WAL009

0%

0%

0%

510,900

0.58

0%



Reach 09

WAL010

7%

99%

7%

364,900

0.42

7%

3%

Reach 10

WAL009

0%

0%

0%

822,800

0.48

0%



Reach 10

WAL010

7%

99%

7%

392,500

0.23

7%



Reach 10

OSB047/cc05

21%

99%

20%

411,600

0.24

20%



Reach 10

WAL011

25%

99%

25%

93,650

0.05

25%

8%

Reach 11

OSB047/cc05

21%

99%

20%

411,600

1.00

20%

20%

Reach 12

None

NA

NA

NA

NA

NA

NA

NA

aEffective remedial effectiveness factor (REF) is calculated as the proposed percentage of material to be removed multiplied by the REF from the Simplified Tool.

Page 1 of 1


-------

-------
TABLE A-11

Model-Simulated Flows - Baseflow Conditions

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site







Total Bunker Creek

Total Bunker Creek

Total Government

Total Government

Total A-4 Drain

Total Canyon

Total Canyon

Total Remedial Drain



Total SFCDR Gain

Total SFCDR Loss

Gain

Loss

Creek Gain

Creek Loss

Gain

Creek Gaina b

Creek Lossb

Gain

Simulation

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

OU 2 No Action

7.8

2.9

0.2

0.8

0.2

0.1

0.4

NA

NA

NA

Alternative (a)

6.6

1.0

0.0

0.1

0.2

0.1

0.2

NA

NA

NA

Alternative (b)

6.8

3.3

0.0

0.0

0.0

0.0

0.4

NA

NA

NA

Alternative (c)

3.5

6.9

0.0

0.0

0.2

0.1

0.1

NA

NA

8.4

Alternative (d)

3.5

6.9

0.0

0.0

0.0

0.0

0.1

NA

NA

8.3

Alternative (e)

0.0

0.0

0.0

0.0

0.0

0.0

0.0

NA

NA

5.2

OU 3 Mainstem SFCDR





















Watershed Segment 01 -





















No Action

10.1

8.0

NA

NA

NA

NA

NA

NA

NA

NA

OU 3 Mainstem SFCDR





















Watershed Segment 01 -





















G ro u n dwate r Acti o ns

0.0

0.0

NA

NA

NA

NA

NA

NA

NA

7.6

OU 3 Woodland Park-





















No Action

NA

NA

NA

NA

NA

NA

NA

2.1

0.8

NA

OU 3 Updated Remedial





















Components for Woodland Park

NA

NA

NA

NA

NA

NA

NA

1.6

1.1

1.0

includes groundwater discharge to Canyon Creek and land surface
bWoodland Park Reaches 1 though 12

Notes:

cfs = cubic feet per second
NA = not applicable
OU = Operable Unit

SFCDR = South Fork Coeur d'Alene River

Page 1 of 1


-------

-------
TABLE A-12

Simulated Dissolved Zinc Load - Baseflow Conditions

Focused Feasibility Study, Upper Basin of the Coeurd'Alene River, Bunker Hill Superfund Site





Net Load to

Net Load to

Net Load to A-4

Load to Canyon



Reduction in Load





Net Load to SFCDR

Bunker Creek

Government Creek

Drain

Creek

Total Load

from No Action

Load to RA-Drains

Simulation

lb/day

lb/day

lb/day

lb/day

lb/day

lb/day

lb/day

lb/day

OU 2 No Action

526

15

33

31

NA

605

0

NA

Alternative (a)

462

0

33

18

NA

513

92

NA

Alternative (b)

475

0

0

29

NA

504

101

NA

Alternative (c)

63

0

33

4

NA

100

505

1,073

Alternative (d)

63

0

0

4

NA

67

538

1,065

Alternative (e)

0

0

0

0

NA

0

605

510

OU 3 Mainstem SFCDR

















Watershed Segment 01 -

















No Action

66

NA

NA

NA

NA

66

0

NA

OU 3 Mainstem SFCDR

















Watershed Segment 01 -

















Groundwater Actions

0

NA

NA

NA

NA

0

66

74

OU 3 Woodland Park -

















No Action

NA

NA

NA

NA

125

125

0

NA

OU 3 Updated Remedial

















Components for Woodland Park

NA

NA

NA

NA

41

41

84

82

Notes:

lb/day = pound(s) per day
NA = not applicable
OU = Operable Unit

SFCDR = South Fork Coeur d'Alene River

Page 1 of 1


-------

-------
TABLE A-13

Model-Simulated Flows - 7Q10 Conditions

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site







Total Bunker Creek

Total Bunker Creek

Total Government

Total Government

Total A-4 Drain

Total Canyon

Total Canyon

Total Remedial Drain



Total SFCDR Gain

Total SFCDR Loss

Gain

Loss

Creek Gain

Creek Loss

Gain

Creek Gaina b

Creek Lossb

Gain

Simulation

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

OU 2 No Action

7.1

3.5

0.2

0.9

0.1

0.2

0.3

NA

NA

NA

Alternative (a)

5.7

1.4

0.0

0.1

0.1

0.2

0.1

NA

NA

NA

Alternative (b)

6.7

3.6

0.0

0.0

0.0

0.0

0.3

NA

NA

NA

Alternative (c)

2.8

7.6

0.0

0.0

0.1

0.2

0.0

NA

NA

8.2

Alternative (d)

3.3

6.5

0.0

0.0

0.0

0.0

0.1

NA

NA

8.6

Alternative (e)

0.0

0.0

0.0

0.0

0.0

0.0

0.0

NA

NA

4.0

OU 3 Mainstem SFCDR





















Watershed Segment 01 -





















No Action

9.4

8.4

NA

NA

NA

NA

NA

NA

NA

NA

OU 3 Mainstem SFCDR





















Watershed Segment 01 -





















Groundwater Actions

0.0

0.0

NA

NA

NA

NA

NA

NA

NA

6.3

OU 3 Woodland Park-





















No Action

NA

NA

NA

NA

NA

NA

NA

1.7

1.1

NA

OU 3 Updated Remedial





















Components for Woodland Park

NA

NA

NA

NA

NA

NA

NA

1.1

1.2

0.8

includes groundwater discharge to Canyon Creek and land surface.

bWoodland Park Reaches 1 though 12

Notes:

cfs = cubic feet per second
NA = not applicable
OU = Operable Unit

SFCDR = South Fork Coeur d'Alene River

Page 1 of 1


-------

-------
TABLE A-14

Simulated Dissolved Zinc Load - 7Q10 Conditions

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site







Net Load to















Net Load to

Government

Net Load to A-4

Load to Canyon



Reduction in Load



Net

Load to SFCDR

Bunker Creek

Creek

Drain

Creek

Total Load

from No Action

Load to RA-Drains

Simulation

lb/day

lb/day

lb/day

lb/day

lb/day

lb/day

lb/day

lb/day

OU 2 No Action

502

11

14

25

NA

553

0

NA

Alternative (a)

425

0

14

12

NA

450

103

NA

Alternative (b)

477

0

0

28

NA

505

48

NA

Alternative (c)

43

0

14

1

NA

58

495

1,045

Alternative (d)

61

0

0

11

NA

72

481

1,095

Alternative (e)

0

0

0

0

NA

0

553

398

OU 3 Mainstem SFCDR

















Watershed Segment 01 -

















No Action

58

NA

NA

NA

NA

58

0

NA

OU 3 Mainstem SFCDR

















Watershed Segment 01 -

















Groundwater Actions

0

NA

NA

NA

NA

0

58

61

OU 3 Woodland Park -

















No Action

NA

NA

NA

NA

101

101

0

NA

OU 3 Updated Remedial

















Components for Woodland Park

NA

NA

NA

NA

26

26

75

53

Notes:

lb/day = pound(s) per day
NA = not applicable
OU = Operable Unit

SFCDR = South Fork Coeur d'Alene River

Page 1 of 1


-------

-------
TABLE A-15

Model-Simulated Flows - 90th Percentile Flow Conditions

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site







Total Bunker Creek

Total Bunker Creek

Total Government

Total Government

Total A-4 Drain

Total Canyon

Total Canyon

Total Remedial Drain



Total SFCDR Gain

Total SFCDR Loss

Gain

Loss

Creek Gain

Creek Loss

Gain

Creek Gaina b

Creek Lossb

Gain

Simulation

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

OU 2 No Action

6.0

3.7

0.5

0.4

0.5

0.1

0.5

NA

NA

NA

Alternative (a)

5.6

1.2

0.0

0.1

0.5

0.1

0.5

NA

NA

NA

Alternative (b)

5.7

3.8

0.0

0.0

0.0

0.0

0.5

NA

NA

NA

Alternative (c)

2.6

8.0

0.0

0.0

0.5

0.1

0.2

NA

NA

9.4

Alternative (d)

2.9

7.2

0.0

0.0

0.0

0.0

0.4

NA

NA

9.8

Alternative (e)

0.0

0.0

0.0

0.0

0.0

0.0

0.3

NA

NA

10.8

OU 3 Mainstem SFCDR





















Watershed Segment 01 -





















No Action

9.9

9.5

NA

NA

NA

NA

NA

NA

NA

NA

OU 3 Mainstem SFCDR





















Watershed Segment 01 -





















Groundwater Actions

0.0

0.0

NA

NA

NA

NA

NA

NA

NA

8.0

OU 3 Woodland Park-





















No Action

NA

NA

NA

NA

NA

NA

NA

4.5

0.4

NA

OU 3 Updated Remedial





















Components for Woodland Park

NA

NA

NA

NA

NA

NA

NA

3.7

0.7

1.5

includes groundwater discharge to Canyon Creek and land surface.

bWoodland Park Reaches 1 though 12

Notes:

cfs = cubic feet per second
NA = not applicable
OU = Operable Unit

SFCDR = South Fork Coeur d'Alene River

Page 1 of 1


-------

-------
TABLE A-16

Simulated Dissolved Zinc Load - 90th Percentile Flow Conditions

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site





Net Load to

Net Load to

Net Load to A-4

Load to Canyon



Reduction in Load



Net

Load to SFCDR

Bunker Creek

Government Creek

Drain

Creek

Total Load

from No Action

Load to RA-Drains

Simulation

lb/day

lb/day

lb/day

lb/day

lb/day

lb/day

lb/day

lb/day

OU 2 No Action

561

42

57

54

NA

715

0

NA

Alternative (a)

516

0

57

52

NA

625

90

NA

Alternative (b)

545

0

0

60

NA

605

110

NA

Alternative (c)

86

0

57

22

NA

165

550

1,303

Alternative (d)

123

0

0

40

NA

163

552

1,350

Alternative (e)

0

0

0

30

NA

30

685

1,213

OU 3 Mainstem SFCDR

















Watershed Segment 01 -

















No Action

58

NA

NA

NA

NA

58

0

NA

OU 3 Mainstem SFCDR

















Watershed Segment 01 -

















Groundwater Actions

0

NA

NA

NA

NA

0

58

77

OU 3 Woodland Park -

















No Action

NA

NA

NA

NA

258

258

0

NA

OU 3 Updated Remedial

















Components for Woodland Park

NA

NA

NA

NA

112

112

146

182

Notes:

lb/day = pound(s) per day
NA = not applicable
OU = Operable Unit

SFCDR = South Fork Coeur d'Alene River

Page 1 of 1


-------

-------
TABLE A-17

Model-Simulated Flows - Average Annual Conditions

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site







Total Bunker Creek

Total Bunker Creek

Total Government

Total Government

Total A-4 Drain

Total Canyon

Total Canyon

Total Remedial Drain



Total SFCDR Gain

Total SFCDR Loss

Gain

Loss

Creek Gain

Creek Loss

Gain

Creek Gaina b

Creek Lossb

Gain

Simulation

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

(cfs)

OU 2 No Action

7.2

2.9

0.2

0.9

0.3

0.1

0.4

NA

NA

NA

Alternative (a)

6.0

1.5

0.0

0.1

0.3

0.1

0.3

NA

NA

NA

Alternative (b)

6.4

3.3

0.0

0.0

0.0

0.0

0.4

NA

NA

NA

Alternative (c)

3.2

7.3

0.0

0.0

0.3

0.2

0.1

NA

NA

00
CO

Alternative (d)

3.2

7.3

0.0

0.0

0.0

0.01

0.1

NA

NA

8.7

Alternative (e)

0

0

0

0

0

0

0.0

NA

NA

5.3

OU 3 Mainstem SFCDR





















Watershed Segment 01 -





















No Action

10.8

7.0

NA

NA

NA

NA

NA

NA

NA

NA

OU 3 Mainstem SFCDR





















Watershed Segment 01 -





















Groundwater Actions

0.0

0.0

NA

NA

NA

NA

NA

NA

NA

8.0

OU 3 Woodland Park-





















No Action

NA

NA

NA

NA

NA

NA

NA

2.8

0.6

NA

OU 3 Updated Remedial





















Components for Woodland Park

NA

NA

NA

NA

NA

NA

NA

2.1

0.9

1.2

includes groundwater discharge to Canyon Creek and land surface.

bWoodland Park Reaches 1 though 12

Notes:

cfs = cubic feet per second
NA = not applicable
OU = Operable Unit

SFCDR = South Fork Coeur d'Alene River

Page 1 of 1


-------

-------
TABLE A-18

Simulated Dissolved Zinc Load - Average Annual Conditions

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site





Net Load to Bunker

Net Load to

Net Load to A-4

Load to Canyon



Reduction in Load





Net Load to SFCDR

Creek

Government Creek

Drain

Creek

Total Load

from No Action

Load to RA-Drains

Simulation

lb/day

lb/day

lb/day

lb/day

lb/day

lb/day

lb/day

lb/day

OU 2 No Action

524

14

38

42

NA

617

0

NA

Alternative (a)

447

-0.5

37

26

NA

509

108

NA

Alternative (b)

480

0

0

37

NA

517

100

NA

Alternative (c)

64

0

36

7

NA

107

510

1,163

Alternative (d)

64

0

0

6

NA

70

547

1,146

Alternative (e)

0

0

0

0

NA

0

617

531

OU 3 Mainstem SFCDR

















Watershed Segment 01 -

















No Action

77

NA

NA

NA

NA

77

0

NA

OU 3 Mainstem SFCDR

















Watershed Segment 01 -

















Groundwater Actions

0

NA

NA

NA

NA

0

77

77

OU 3 Woodland Park -

















No Action

NA

NA

NA

NA

141

141

0

NA

OU 3 Updated Remedial

















Components for Woodland Park

NA

NA

NA

NA

53

53

87

117

Notes:

lb/day = pound(s) per day
NA = not applicable
OU = Operable Unit

SFCDR = South Fork Coeur d'Alene River

Page 1 of 1


-------

-------
TABLE A-19

Results of the OU 2 Sensitivity Analysis

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site	

Estimated Dissolved Zinc Load to the Surface Water System within the Bunker Hill Box (lb/day)

Input Parameter Modification	No Action	Alternative (a)	Alternative (b)	Alternative (c)	Alternative (d)	Alternative (e)

Calibrated Baseflow Model

605

513

504

100

67

0

Kx Bedrock x 10

625

541

514

115

70

11

Kx Bedrock x 100

684

628

568

140

93

14

Kx Bedrock10

600

507

502

97

66

11

Kx Bedrock 100

600

506

502

96

66

11

Kx CU x 10

605

513

504

100

67

12

Kx CU x 100

605

511

503

101

67

11

Kx CU - 10

605

513

504

100

67

13

Kx CU - 100

605

513

504

100

67

13

Kx Alluvium x 5

1,026

863

849

278

260

20

Kx Alluvium x 10

1,341

1,120

1,117

498

491

31

Kx Alluvium 5

433

384

371

63

32

8

Kx Alluvium - 10

394

353

336

56

26

7

PPN x 25%

615

527

522

107

69

13

PPN x 50%

624

539

515

114

72

13

PPN - 25%

593

498

498

91

64

12

PPN - 50%

581

481

492

82

61

12

Vertical Resistance x 10

390

341

284

77

44

2

Vertical Resistance x 100

303

245

191

66

31

0

Vertical Resistance 10

726

594

604

115

82

7

Vertical Resistance 100

774

621

636

123

91

11

SFCDR wc1 x 5

358

316.0

274

100

66

13

SFCDR wc1 x 10

277

241

195

101

65

13

SFCDR wc1 5

679

563

562

100

66

11

SFCDR wc1 - 10

688

571

670

101

68

13

SFCDR Stream Stage -1 foot

647

540

530

122

89

13

SFCDR Stream Stage - 2 feet

680

558

537

145

111

13

SFCDR Stream Stage + 1 foot

540

464

448

74

41

13

SFCDR Stream Stage + 2 feet

447

384

364

41

8

13

Notes:

CU = confining unit

Kx = horizontal hydraulic conductivity

PPN = calibrated deep percolation of precipitation distribution
wc1 = streambed conductance term

RDD/100080013 (Draft_Final_FFS_Report_Appendix_A_Tables.xls)

ES010710093751RDD

Page 1 of 1


-------

-------
APPENDIX B

Predictive Analysis Methodology and Results


-------

-------
Contents

Section	Page

Abbreviations and Acronyms	B-iii

Predictive Analysis Methodology and Results	B-l

B.l Predictive Analysis Tool Overview	B-2

B.l.l Model Components	B-2

B.l.2 Model Outputs	B-3

B.l.3 Analytical Steps, Input Values, and Uncertainties	B-3

B.2 FFS Predictive Analysis Tool Model Components	B-5

B.2.1 Pre-Remediation Dissolved Metal Loads	B-5

B.2.2 Pre-Remediation Load Allocation	B-7

B.2.3 Post-Remediation Load Reduction	B-8

B.2.3.1 Non-Groundwater Source Remedial Factors	B-8

B.2.3.2 Groundwater Residual Load	B-8

B.2.4 Post-Remediation Residual Load Aggregation	B-9

B.2.5 Post-Remediation AWQC	B-9

B.3 Model Uncertainty Estimates	B-10

B.4 Predictive Analysis Modeling Results	B-ll

B.5 References	B-ll

Figures

B-l Predictive Analysis Model Schematic

B-2 Elizabeth Park Dissolved Zinc vs. Discharge Over Time

B-3 Pinehurst Dissolved Zinc vs. Discharge Over Time

B-4 Elizabeth Park Loading: Comparison of Pre-Remediation, Remediation, and Post-
Remediation Distribution

B-5 Pinehurst Loading: Comparison of Pre-Remediation, Remediation, and Post-
Remediation Distribution

Tables

B-l Elizabeth Park and Pinehurst Predictive Analysis Tool Modeling Inputs
B-2 Total Source Volumes and Relative Loading Potential by Waste Type
B-3 Elizabeth Park Source Volume Inputs by Waste Type and Remedial Action
B-4 Pinehurst Source Volume Inputs by Waste Type and Remedial Action
B-5 Remediation Factor by Waste Type and Remedial Action


-------
APPENDIX B: PREDICTIVE ANALYSIS METHODOLOGY AND RESULTS

B-6 Groundwater Load Reductions for Treatment Alternatives with Groundwater
Components

B-7 Summary of Predictive Analysis Results
Attachments

B-l Mathematical Updates to Predictive Analysis Implemented in PAT1

B-ii


-------
Abbreviations and Acronyms

ARAR

applicable or relevant and appropriate requirement

AWQC

ambient water quality criterion/criteria

AWQCr

AWQC ratio

BEMP

Basin Environmental Monitoring Program

cfs

cubic foot/feet per second

CV

coefficient of variation

cy

cubic yard(s)

EOF

Error of Fact

FFS

Focused Feasibility Study

lb / day

pound(s) per day

LCL

lower confidence level

Lr

load ratio

^g/L

microgram(s) per liter

mg/L

milligram(s) per liter

NA

not applicable

NAS

National Academy of Sciences

NE

nonexceedance

OU

Operable Unit

PAT

Predictive Analysis Tool

PI

probability interval

RF

remediation factor

RI

Remedial Investigation

RLP

relative loading potential

ROD

Record of Decision

SFCDR

South Fork of the Coeur d'Alene River

UCL

upper confidence level

USEPA

U.S. Environmental Protection Agency

USGS

U.S. Geological Survey


-------

-------
APPENDIX B

Predictive Analysis Methodology and Results

A comparison of the potential relative effectiveness of the remedial alternatives in this
Focused Feasibility Study (FFS) has been developed using an approach called the Predictive
Analysis. The Predictive Analysis, in turn, relies on an analytical model called "the
Predictive Analysis Tool" (PAT). The PAT was initially developed to support the evaluation
of alternatives in the 2001 Feasibility Study (FS) Report for Operable Unit 3 (OU 3) (U.S.
Environmental Protection Agency [USEPA], 2001a) and was subsequently used to support
evaluations in the Proposed Plan (USEPA, 2001b) and the Record of Decision (ROD) for OU
3 (often referred to as "the Interim ROD"; USEPA, 2002). The analyses included two
modeled locations, Pinehurst and Harrison, and did not account for dissolved metals
sources in OU 2, which is located in the Bunker Hill "Box" (often referred to as "the Box").

The theory underlying the PAT, its mathematical and statistical bases, and the parameter
estimates assumed in the 2001 predictive modeling were formally documented in the
Technical Memorandum (Revision 1): Probabilistic Analysis of Post-Remediation Metal Loading
Technical Memorandum (URS Greiner, 2001).1 The PAT was evaluated as part of the program
review conducted by the National Academy of Sciences (NAS) in Superfund and Mining
Megasites: Lessons from the Coeur d'Alene River Basin (NAS, 2005). When the pre-publication
NAS review report was released, a response to both the review and criticism of the PAT
contained in Appendix F of the NAS report was prepared. This response document, NAS
Appendix F Errors of Fact (EOF) (URS, 2005), includes a point-by-point discussion of the
issues raised by the NAS and identifies substantive errors in the NAS review that were not
corrected in the subsequent final NAS report. Further, USEPA sought an independent
review of the PAT by a well-known leader in the field of probabilistic modeling, Dr.

Gregory B. Baecher, University of Maryland, A.J. Clark School of Engineering (College Park,
Maryland). The independent review validated the approach used by USEPA and its use in
the evaluation and comparison of alternatives. This review culminated in a second technical
memorandum, A Predictive Analysis for Post-Remediation Metal Loading, Coeur d'Alene Basin
RI/FS (URS, 2007), which provided clarification and additional documentation of the
approach used by USEPA. The fundamentals of the original analysis have remained
unchanged since its initial development for the 2001 FS. The 2007 technical memorandum
included a cover letter prepared by Dr. Baecher describing the conclusions of his review.

It has been necessary to make a number of modifications to the Predictive Analysis to
support the evaluation of alternatives in this FFS. These modifications have included:

•	Adding Elizabeth Park as a modeled location;

•	Updating current water quality conditions (i.e., pre-remediation loads);

•	Adding pre-remediation loading from the Box (mathematical updates to the PAT to
support this modification are detailed in Attachment B-l);

1 The Predictive Analysis was referred to as the Probabilistic Analysis at that time.

B-1


-------
APPENDIX B: PREDICTIVE ANALYSIS METHODOLOGY AND RESULTS

•	Updating source types, volumes, and remedial actions to reflect the updated remedial
alternatives; and

•	Integrating more accurate estimates of load reduction from the groundwater model
(groundwater modeling is described in Appendix A of this FFS Report, and
mathematical updates to the Predictive Analysis to support the integration of these
results into the PAT are detailed in Attachment B-l to this Appendix B).

This appendix summarizes the methodology and results from the updated Predictive

Analyses for the remedial alternatives described in this FFS Report. The appendix consists

of the following five sections:

•	Section B.l provides an overview of the PAT model, describes the steps in the
probabilistic Predictive Analysis, and identifies uncertainties inherent in the modeling
process;

•	Section B.2 describes the updates to the PAT model specific to the integration of the
groundwater model results, as well as changes in input data that document current
conditions in the watershed;

•	Section B.3 describes how the uncertainty associated with the expected performance of
remedial alternatives was quantified by mathematically propagating the uncertainty of
the input variables;

•	Section B.4 summarizes results from the updated Predictive Analysis modeling
applicable to the alternatives evaluated in this FFS Report; and

•	Section B.5 provides full references for documents cited.

B.1 Predictive Analysis Tool Overview

B.1.1 Model Components

The PAT is a simple analytical tool whose underlying concepts are shown schematically in
Figure B-l. The figure is a generic description of the modeling process that was applied at
two locations within the Upper Basin of the Coeur D'Alene River: Elizabeth Park on the
South Fork of the Coeur d'Alene River (SCFDR), representing water quality in OU 3
upstream from (above) OU 2, and Pinehurst, which is downstream from OU 2, representing
the combined water quality of OU 2 and the rest of the Upper Basin. The surface water
monitoring locations in Elizabeth Park (SF-268) and Pinehurst (SF-271) are depicted in
Figure 3-1 in this FFS Report. The modeling process is the same at the two locations,
differing with respect to input values unique to each location. In both cases, the modeling
process draws upon observed loading of dissolved metals (in this case, dissolved zinc) in
surface water at the modeled location, allocates the observed loading between known
upstream dissolved metal contaminant sources, and then estimates load reductions
resulting from implementation of the remedial actions specific to each of the remedial
alternatives evaluated in this FFS Report.

The PAT also includes a component that can be used to estimate residual post-remediation
loads over time, due to source depletion. The natural source depletion component of the

B-2


-------
APPENDIX B: PREDICTIVE ANALYSIS METHODOLOGY AND RESULTS

PAT has not been used in the FFS analysis because the prediction of long-term water quality
trends and specific water quality in the SFCDR watershed in the distant future is subject to
considerable uncertainty, stemming from the complex weathering rates and the changes in
these rates for the numerous mine waste types and source sites in the watershed. A
description of natural source depletion processes is provided in Section 3.0 of this FFS
Report. Site-specific exposure to seasonal wetting and water flux, as well as variations in
particle surface area, iron sulfide content, trace metal content, air diffusion, and other
factors, control the release of contaminants from mine wastes. The effect of cleanup actions
further complicates these predictions.

Knowledge gained from other heavily contaminated mine sites suggests that water quality
in the SFCDR watershed could be adversely impacted for long periods of time, particularly
when significant waste volumes are left in place. A long-term monitoring program coupled
with adaptively managed cleanup actions is likely the best approach for assessing long-term
water quality and improvements resulting from cleanup. The PAT time-dependent source
depletion estimates will be considered in remedy implementation, including adaptive
management, and updated as new information becomes available from Basin
Environmental Monitoring Program (BEMP) monitoring.

B.1.2 Model Outputs

The primary PAT output estimates residual load. Calculated residual loads can be used to
establish the percent dissolved zinc load reduction by each alternative. Percent load
reduction is defined as the alternative-specific ratio of the predicted dissolved zinc load
reduction to the existing pre-remediation loading. The PAT also provides estimates of the
post-remediation ambient water quality criteria (AWQC) ratios. AWQC ratios are the main
output estimates used for evaluating compliance with applicable or relevant and
appropriate requirements (ARARs), and the effectiveness of the remedial alternatives
presented in this FFS. The AWQC ratios are calculated by comparing the dissolved zinc
loads to loading capacity values that are equal to the AWQC multiplied by discharge.

B.1.3 Analytical Steps, Input Values, and Uncertainties

Each analytical step in the modeling procedure (see Figure B-l) requires model input values
that derive from either available empirical data or engineering estimates based on
experience and expert opinion. All of the input values, regardless of source (empirical data
or engineering-based estimated factors), are subject to uncertainties. The input values and
the uncertainties for each analytical step are as follows:

• Step 1, Estimate Surface Water Loading. This step requires input of the cumulative pre-
remediation loading of dissolved zinc in surface water. The pre-remediation loading
estimates are location-specific and based on empirical environmental monitoring to
estimate flow and concentrations of dissolved metals in surface water within the Upper
Basin. Both flow rate and concentrations of dissolved metals are subject to real variations
over time and space on the scale of "events" (e.g., pre-remediation conditions vs.
conditions during remedial actions vs. conditions following remedy completion) as well
as temporal variations within and across water years.

B-3


-------
APPENDIX B: PREDICTIVE ANALYSIS METHODOLOGY AND RESULTS

•	Step 2, Allocate Loading to Upstream Sources. Step 2 includes quantification of both
the volume of contaminant source materials and estimation of the leaching
characteristics of those materials. The load attributed to direct discharge of adit
drainages, seeps, and groundwater is first subtracted from the total load, and then the
remaining load is apportioned to specific waste types and volumes represented at each
location. During preparation of the 2001 FS Report, an inventory of contaminant sources
was developed based on extensive data accumulated through previous studies
conducted by multiple state and federal agencies. This inventory includes volume
estimates for each source type identified in the Coeur d'Alene Basin. The volume
estimates are considered to carry a significant degree of uncertainty, primarily related to
limitations in knowledge about the extent of both known and unknown contamination
sources. Notwithstanding these uncertainties, the primary objective is to assess the
potential relative effectiveness of the FFS alternatives, and not to quantify specific
predictions of future water quality.

The apportioning of load is based on the total volumes of waste types and their
respective relative load potential (RLP) estimates. Each waste type is assigned a different
RLP based on professional judgment estimates of its proportional "loading strength".
The RLP values used for different waste types were first defined in the 2001 FS Report
and remain unchanged in this analysis. The RLP of a given source type is an index of the
average contribution of metal (zinc) load from that source type to the SFCDR per cubic
yard (cy) of source material per year. The RLP expresses the relative propensity of a
source type to contribute metal load to the river. That source judged to have the highest
propensity is assigned an RLP of 1.0, and other source types are scaled proportionately,
with values ranging from 0.0 to 1.0. At the end of Step 2, the difference in load between
the two points is apportioned to specific waste types and volumes located between those
two points, such that the sum of all waste type-specific loads is equal to the measured
load between the two locations.

•	Step 3, Estimate Residual Loading for Remedial Alternatives. Step 3 applies
remediation factors (RFs) to the source-specific pre-remediation loads to estimate post-
remediation residual loads, depending upon the specific actions identified in the
remedial alternatives. The effectiveness of specific remedial actions is based largely on
engineering experience and expert opinion, which is subject to uncertainty. Inclusion of
groundwater-based actions in this FFS has added another level of uncertainty because
estimates of load reduction resulting from groundwater-based actions are based on
groundwater modeling, a methodology that is also subject to uncertainties due to both
spatial and temporal conditions of groundwater within the watershed and inherent
limitations of empirical data upon which the modeling is based.

•	Step 4, Sum Residual Loading Across Sources. Step 4 aggregates the post-remediation
loadings from each contamination source into a cumulative summation. Estimation
uncertainty in that sum also combines the estimation error propagated at each step of
the modeling process.

Throughout the analytical process, the PAT mathematically assigns uncertainties to the

required model component inputs (empirically-based variables, model-based metrics, and

engineering-based parameters). Input estimates for all input variables and parameters

B-4


-------
APPENDIX B: PREDICTIVE ANALYSIS METHODOLOGY AND RESULTS

applied in the model incorporate both a best estimate and an estimate of the uncertainty in
the best estimate. The best estimate used in the model is the expected value of the variable
or parameter. The uncertainty is measured by the coefficient of variation (CV), which
includes both natural variability and estimation error. By definition, the CV is the ratio of
the standard deviation divided by the expected value, resulting in a unitless estimate. As
such, the CV gives insight into the relative variability of different variables over different
scales. For example, an input variable with a CV of 0.30 is substantively less variable than a
variable with a CV of 0.97, independent of where on the measurement scale the expected
value lies.

Expected values and CVs are the inputs into the PAT for all measures and parameter
estimates described in this appendix.

B.2 FFS Predictive Analysis Tool Model Components

Although the PAT is conceptually simple, its successful implementation requires use of an
involved modeling procedure. As shown in Figure B-l, the modeling consists of five
analytical steps (only Steps 1 through 4 are used in this FFS), beginning with estimation of
pre-remediation input loading of dissolved metals into system surface waters. Those loads
are then allocated to known upstream sources, each of which was assigned a RLP. Source-
specific pre-remediation loads are then reduced based on the remedial actions identified for
each of the remedial alternatives, resulting in source-specific post-remediation residual
loads that would be expected to remain after successful remedy implementation. Source-
specific post-remedial loads are then re-aggregated to a cumulative, location-specific
residual post-remediation load. The analytical steps are the same at Elizabeth Park and
Pinehurst, differing only in terms of input metrics given location-specific conditions and
remedial alternatives.

The remainder of this section details the expected values and CVs used in each of the
analytical steps in the PAT conceptual schematic shown in Figure B-l (with the exception of
the source depletion component). Each model component (empirically-based value or
estimated engineering parameter) is first described, followed by the strategy and methods
used to update specific model components and tailor the model to the FFS alternatives.

B.2.1 Pre-Remediation Dissolved Metal Loads

The development of estimates for pre-remediation surface water loading in pounds per day
(lb/day) of dissolved zinc at Elizabeth Park and Pinehurst is based on monitoring records
from Stations SF-268 and SF-271, respectively, which are stream gauging and water quality
sampling stations maintained by the U.S. Geological Survey (USGS) for USEPA.

Load estimates used in the 2001 FS were developed using data collected from 1987 through
1999. Since the FS, remedial actions have been taken in the Box that were expected to reduce
post-remediation loadings at Pinehurst. For the current FFS, surface water monitoring data
were accessed and updated through August 2009 and evaluated to determine the extent to
which conditions have changed with respect to surface water loadings at Elizabeth Park and
Pinehurst over the period 1987 through 2009.

B-5


-------
APPENDIX B: PREDICTIVE ANALYSIS METHODOLOGY AND RESULTS

Potential changes in loading over time were evaluated by examining the relationships
between dissolved zinc concentration and discharge (the two components used to calculate
load) over three periods: pre-remediation (1987 through September 1995), active
remediation (October 1995 through September 2002), and post-remediation (October 2002
through August 2009). Figures B-2 and B-3 show the relationships at Elizabeth Park and
Pinehurst, respectively, plotting the natural log (In) of the discharge (cfs) on the x-axis and
dissolved zinc concentration (milligrams per liter [mg/L]) on the y-axis. Synoptic
observations from the three periods use different symbols, as noted in the legend.

Regression equations that estimate dissolved zinc concentration using a power equation
relationship (concentration equaling a constant times discharge taken to a power, estimated
from the data by regression) are also noted in the figures. Best-fit curves are indicated as
curved lines passing through the period-specific points.

Dissolved zinc loads calculated from synoptic concentration and discharge data within the
three periods were compared at the two sites, applying a nonparametric analysis of variance
to observed loadings. Load comparisons are graphically displayed in box plots found in the
left panels of Figures B-4 and B-5, for Elizabeth Park and Pinehurst, respectively. Apparent
lack of significant difference across monitoring periods for Elizabeth Park is indicated by the
overlap of box plot loads and corroborated with the insignificant test statistic (p = 0.32).
Although the best fit power functions across years in Figure B-2 suggest a decreasing trend,
differences in load are not sufficient at Elizabeth Park to exceed "noise" within the metric.
Figure B-5 suggests statistically significant differences in the pre-remediation, active
remediation, and post-remediation periods for Pinehurst loads; these differences are
supported by the significant test statistic (p = 0.002). Apparent differences at Pinehurst
indicate that samples from both pre-remediation and active remediation events are
significantly elevated over loads observed following the remedial activities.

Based on the Pinehurst results and in the interest of using data representative of current
conditions within the Basin, monitoring data used to develop estimates for the PAT input
were limited to results from sampling events following October 2002. Although loadings at
Elizabeth Park exhibit no statistically significant differences over pre-remediation, active
remediation, and post-remediation conditions, synoptic observations are needed to estimate
OU 2 loadings; therefore, the data used were limited to the same period. Limiting sampling
events to the post-October 2002 period resulted in approximately 50 observations per
location, which gives sample sizes considered sufficient to develop reasonable expected
values and CVs.

Pre-remediation dissolved zinc load estimates are based on lognormal distributions that are
supported by the probability plots of loading in the right panels of Figures B-4 and B-5.2
Table B-l lists model input estimates of Elizabeth Park and Pinehurst loading (along with
other variable expected values used as input for the current model runs). Results for both
Elizabeth Park and Pinehurst are summarized in the following bullets. In these bullets, the
current estimates at Pinehurst are compared to the 2001 FS input estimates. This comparison
was done only for changes observed at Pinehurst because Predictive Analysis modeling at
Elizabeth Park was not conducted during the 2001 FS, precluding comparison.

2 Pre-remediation load estimates for the 2001 FS modeling effort were also based on lognormal distributions.

B-6


-------
APPENDIX B: PREDICTIVE ANALYSIS METHODOLOGY AND RESULTS

•	Elizabeth Park dissolved zinc load inputs (expected value and coefficients of variation)
for the current Predictive Analysis modeling are 1,260 pounds per day (lb/ day) and
CV=0.94.

•	Dissolved zinc load inputs at Pinehurst for the 2001 FS and the current Predictive
Analysis modeling exhibit statistically significant differences, with expected value and
coefficients of variation of 2,921 lb/day (CV=0.60) and 2,285 (CV = 1.21), respectively.
The comparatively lower expected value with higher CV for the current data indicates
an overall reduction in dissolved metal loading at Pinehurst with a somewhat increased
relative variability. These results are consistent with remedial activities having been
initiated in OU 2 in 1995 and completed in 2002.

B.2.2 Pre-Remediation Load Allocation

As noted above, an inventory of contaminant sources was developed for the 2001 FS Report
based on information accumulated by multiple state and federal agencies. In the
development of that inventory, each source was designated as a specific source type (e.g.,
sediments within the floodplain or upland tailings). On-going source documentation since
the 2001 FS Report was completed has resulted in changes in the original inventory of
contaminant sources within the Upper Basin. The current inventory was developed by
adjusting the original inventory to reflect updated source and volume information. Table B-
2 lists updated total volumes of materials for each source waste type for both Elizabeth Park
and Pinehurst, including sediments; impounded tailings at both inactive and active
facilities; unimpounded tailings; waste rock with loading potential, upland waste rock with
little potential loading, and waste rock with loading potential at active facilities; and adit
drainages.

Allocation of pre-remediation cumulative loads to individual sources draws upon both
empirical data documenting upstream contaminant sources and source volumes as well as
professional judgment as to the RLP associated with individual sources. Table B-2 lists RLPs
for each waste type. For this FFS modeling, the RLP for each source was assigned, based on
professional judgment, as documented in the 2001 FS Predictive Analysis modeling efforts.
The RLPs as originally defined in the 2001 FS Predictive Analysis have been retained
without change. RLPs range between 0 and 1, with 1 meaning that the full source volume is
included in the adjusted volume cumulative sum.

The resulting cumulative pre-remediation load was then allocated among the individual
sources, based on the relative loading potential and volume per source, normalized by the
sum of relative loading and volume products across all sources. The ultimate result of this
step of the modeling is the attribution of the cumulative pre-remediation load to the
individual upstream contaminant sources. In reality, loading will be heavily influenced also
by the concentration of metals in the waste (which can vary considerably by site) and site
characteristics such as drainage (i.e. poorly drained sites yield relatively higher loading).
However, accounting for this variability would require a degree of site characterization that
is not yet available.

B-7


-------
APPENDIX B: PREDICTIVE ANALYSIS METHODOLOGY AND RESULTS

B.2.3 Post-Remediation Load Reduction

Changes in focus between the 2001 FS and the current FFS have required modifications to
the original PAT algorithm. First, the spatial coverage of the remedial alternatives in the two
feasibility studies differs in that the 2001 FS considered sources in the Upper and Lower
Basins, intentionally excluding sources within OU 2. Second, although groundwater
collection and treatment was considered for OU 3 in the 2001 FS, the original PAT did not
account for dissolved metals sources in OU 2, including groundwater. For this FFS,
contaminated groundwater from OU 2 and upstream from Elizabeth Park is being
considered in addition to the source contamination outside OU 2 that was considered in the
2001 FS.

In summary, adaptation of the PAT to account for differences between the 2001 FS and this
FFS represents not only a spatial expansion of where contaminant sources are found (to
include sources both outside and within OU 2), but also changes in the method of
accounting for the sources and their remediation when groundwater is a treatment option
for the remedial alternative. How these changes affect the current modeling effort is
described for non-groundwater sources and groundwater sources in Sections B.2.3.1 and
B.2.3.2., respectively.

B.2.3.1 Non-Groundwater Source Remedial Factors

Post-remediation load reductions of non-groundwater source loads depend upon relative
effectiveness of the remedial treatment proposed. Remediation factors (RFs) have been
developed for each of the remedial technologies in Alternatives 3+ and 4+ described in
Section 7.0 of this FFS Report. RFs for the various treatment technologies in each alternative
to be applied to the different waste types estimate how much of the pre-remediation loading
would remain following successful implementation of the alternative for each waste type.
That quantity, designated the post-remediation or residual load, is specific for each waste
type for each remedial alternative. RFs are, therefore, specific to both waste type and
remedial technology. RFs range in value from zero to one, with higher RFs corresponding to
reduced remedial effectiveness. Thus, for example, a no-action technology for a portion of a
source material volume would carry an RF value of 1.00. RFs for waste types and treatment
technologies that were previously defined as alternative options in the original FS modeling
have been retained in the current application of the PAT to the FFS alternatives.

Tables B-3 and B-4 list the Alternative 3+ and 4+ remedial actions for Elizabeth Park and
Pinehurst, respectively, including the volumes by type of action and alternative. Cumulative
volumes for the individual source types sum to the entries in Table B-2. Table B-5 lists RFs
for each of the remedial actions included in the alternatives. These RFs are applied
consistently across alternatives and modeled locations.

B.2.3.2 Groundwater Residual Load

The PAT algorithm was updated to account for groundwater-based actions in the post-
remediation load calculations in a manner that parallels other treatment technologies. Load
reduction estimates are based on expected value and variability in load reductions from
water-year transient model groundwater results specific to each OU 2 alternative and to the
actions identified for the Woodland Park area of Canyon Creek and the SFCDR French drain
and stream liner system between Wallace and Elizabeth Park.

B-8


-------
APPENDIX B: PREDICTIVE ANALYSIS METHODOLOGY AND RESULTS

Expected values and CVs for the five OU 2 alternatives and the two groundwater actions
upstream from Elizabeth Park (Woodland Park and the SFCDR drain/liner system) are
based on groundwater modeling, and the results are documented in Appendix A of this FFS
Report. Table B-6 summarizes modeled load reductions for these groundwater components,
including summary statistics used for model input estimates.

B.2.4 Post-Remediation Residual Load Aggregation

Re-aggregation of the post-remediation residual loads results in cumulative post-
remediation loads specific to each of the alternatives. The analytical methods used for the
summation are identical to the methods used in the original PAT developed in 2001,
requiring no changes in the original algorithm.

B.2.5 Post-Remediation AWQC

As described in Section B.1.2, Predictive Analysis outputs include post-remediation residual
loads that estimate the extent to which remedial actions are effective. Residual loads
normalized by load capacity are numerically comparable to AWQC ratios, and an AWQC
ratio equal to one means that residual loading equals loading capacity. To develop AWQC
ratios from the modeled residual loads requires an additional model parameter, load
capacity. Load capacity calculations applied in the 2001 Predictive Analysis have changed
based on a new site-wide AWQC values as described in Section B.2.5.1.

As described in Section B.l, load capacities depend on sample-specific AWQC and surface
water discharge. They are, therefore, sample-specific calculated values that are calculated
from empirical data. The AWQC that are applicable to the SFCDR have changed since the
2001 FS Report was completed. Since that time, site-specific AWQC for ecological protection
for the SFCDR basin have been developed by the State of Idaho and adopted by USEPA.
Therefore, the surface water AWQC applicable to the Upper Basin are SFCDR Subbasin-
Specific Criteria (Idaho Administrative Procedures Act [IDAPA] 58.01.02.284). Reference to
AWQC in this appendix refers to these standards.

The SFCDR-specific dissolved-zinc AWQC calculation is based on the following equation:

AWQCsFCDR-spedfic = e(o.6624 * in(hardness) + 2.2235) (micrograms per liter [|Jg/ L] )

The dissolved-zinc AWQC calculation that was applicable to the SFCDR in the 2001 FS
(based on State of Idaho regulations in place at that time)is provided as follows for
comparison:

AWQC2OOI	=	0.986*e (0-8473 * ln(hardness) + 0.7614) (jj,g/L)

For fixed water hardness, the calculated SFCDR-specific AWQC is greater than the Idaho
criterion, resulting in a higher load capacity for the same discharge. For example, the range
of hardness observed at Elizabeth Park over the period 1987-2009 is between 12 and
146 mg/L. The corresponding Idaho AWQC ranges are between 17.3 and 47.9, whereas the
SFCDR AWQC range is between 108 and 200. The relationship between the two calculated
values is not linear, but over the range of hardness observed at Elizabeth Park, the SFCDR
AWQC is between 1.7 and 2.8 times greater than the original AWQC applied in 2001.

B-9


-------
APPENDIX B: PREDICTIVE ANALYSIS METHODOLOGY AND RESULTS

As shown under Load Capacity in Table B-l (bottom row), the dissolved zinc load capacity
expected values and CVs input for the Elizabeth Park and Pinehurst modeling are
287 lb/day (CV = 1.22) and 449 mg/L (CV = 1.08), respectively. As apparent in the table,
differences in loading capacity between the two locations are attributable to the reduced
discharge at Elizabeth Park as opposed to differences in surface water hardness that are
comparable over the post-remediation period.

B.3 Model Uncertainty Estimates

The Predictive Analysis quantified the uncertainty associated with the expected
performance of remedial alternatives in terms of post-remediation dissolved zinc loading,
F(t), and load ratios, Lr(t), which are numerically identical to AWQC ratios. The uncertainty
stems from unavoidably imperfect knowledge and includes both inherent natural variability
(aleatory uncertainty) of basin conditions and limited information (epistemic uncertainty)
on both Coeur d'Alene Basin conditions and future remedial performance.

The uncertainty was quantified by mathematically propagating the uncertainty of the input
variables, as measured by their coefficients of variation, through the Predictive Analysis
model (the PAT) to the output variables, F(t) and Lr(t) (URS Greiner, 2001, and URS, 2007).
The PAT output included both the expected value and coefficients of variation of each F(t)
and Lr(t) estimate (one estimate for each alternative and time step).

Based on statistical analysis and interpretation of historical (pre-remediation) loadings and
load ratios measured at BEMP monitoring locations , the uncertainty in the post-
remediation F(t) and Lr(t) estimates was assumed to following lognormal probability
distributions, consistent with historical BEMP data. A lognormal probability distribution
was thus associated with the expected value and coefficients of variation of each F(t) and
Lr(t) estimate.

For each estimate, its lognormal probability distribution (which includes the expected value
and coefficient of variation) represents a complete quantitative description of the
uncertainty of the estimate. The probability distribution can then be used to quantify the
expected accuracy and precision of the estimate using "probability intervals", or Pis, as
discussed in the following paragraphs. Pis are used for probabilistic estimates in the same
way as confidence intervals are used for estimates of statistical parameters.3

The accuracy of the F(t) and Lr(t) estimates was quantified by Pis, with the precision
quantified by the range of the interval. The higher the probability associated with the PI
(e.g., 80 percent or 90 percent), the more accurate the estimate, but the wider the interval,
meaning less precision. Conversely, higher precision means lower accuracy. For this
analysis, an 80% PI was calculated for each F(t) and Lr(t) estimate, consistent with the range
used for the 2001 FS (URS Greiner, 2001, URS, 2007). Each 80% PI is bounded on the high
end by the 90% nonexceedance (90% NE) estimate, and on the low end by the 10% NE

3 For example, for an 80 percent confidence interval (80% CI) on a statistical estimate for a population average,
the 80% CI would be bounded by the 90 percent upper confidence level (90% UCL) and 90 percent lower
confidence level (90% LCL). Because Predictive Analysis estimates are probabilistic, not statistical, "confidence
intervals" are replaced by "probability intervals" with UCLs and LCLs replaced by "nonexceedance" (NE)
estimates.

B-10


-------
APPENDIX B: PREDICTIVE ANALYSIS METHODOLOGY AND RESULTS

estimate. There is thus a nominal or estimated 80 percent probability (90% - 10%) that the
uncertain true value of the variable being estimated, F(t) or Lr(t), will lie within the 80% PI
of the estimate. There is a 10 percent probability that the true value will not exceed the 10%
NE and a 10 percent probability it will exceed the 90% NE.

B.4 Predictive Analysis Modeling Results

Results from the Predictive Analysis modeling at Elizabeth Park and Pinehurst with
implementation of the remedial alternatives evaluated in this FFS Report are presented in
Table B-7. Elizabeth Park results (found in the upper panel of the table) are limited to the No
Action Alternative, Alternative 3+ including groundwater treatment-based actions at
Woodland Park and along the Mainstem SFCDR segment between Elizabeth Park and
Wallace, and Alternative 4+ with groundwater-based actions limited to the SFCDR segment.
The Pinehurst results include the No Action Alternative and Alternatives 3+ and 4+, both
with and without OU 2 groundwater-based actions, Alternatives (a) through (e).

Table B-7 summarizes, for Alternatives 3+ (a) to (e) and 4+ (a) to (e), the remaining post-
remediation load (lb/day) with 80% PI intervals; the load reduction (lb/day) and percent
load reduction given initial cumulative load; and the resulting AWQC ratio for the residual
load, calculated based on remedy completion. As noted above, the results of the Predictive
Analysis have been used in this FFS Report to assist in the comparison of the potential
relative effectiveness among the remedial alternatives evaluated. Actual post-
implementation performance of remedial alternatives may deviate significantly from
predictions due to the inherent uncertainties in modeling, as reflected in the 80% PI intervals
presented along with the results.

B.5 References

National Academy of Sciences (NAS). 2005. Superfund and Mining Megasites: Lessons from the
Coeur d'Alene River Basin.

URS. July 25, 2005. NAS Appendix F Error of Fact (EOF) Document. Prepared for U.S.
Environmental Protection Agency Region 10.

URS. October 2007. Technical Memorandum: A Predictive Analysis for Post-Remediation Metal
Loading, Coeur d'Alene Basin RJ/FS. Prepared for U.S. Environmental Protection Agency
Region 10.

URS Greiner. September 2001. Technical Memorandum (Revision 1): Probabilistic Analysis of
Post-Remediation Metal Loading. Prepared for U.S. Environmental Protection Agency
Region 10.

U.S. Environmental Protection Agency (USEPA). October 2001 (2001a). Final (Revision 2)
Feasibility Study Report, Coeur d'Alene Basin Remedial Investigation/Feasibility Study. Prepared
by URS Greiner and CH2M HILL for EPA Region 10.

U.S. Environmental Protection Agency (USEPA). October 29, 2001 (2001b). Coeur d'Alene
Basin Proposed Plan.

B-11


-------
APPENDIX B: PREDICTIVE ANALYSIS METHODOLOGY AND RESULTS

U.S. Environmental Protection Agency (USEPA). September 2002. Record of Decision, The
Bunker Hill Mining and Metallurgical Complex Operable Unit 3.

B-12


-------
Figures


-------

-------
MODELING

PROCESS:

SURFACE
WATER
LOADING

ANALYTICAL
STEPS:

1. ESTIMATE

SURFACE WATER
LOADING

DATA

SOURCES:

USGS
EPA STORET\



LOADING

BY SOURCE



SOURCE

SOURCE

RELATIVE

VOLUME

LOADING

(VOL)

POTENTIAL

(RLP)

WASTE

RLP WASTE

ROCK

ROCK

^'ฆTAILINGS
ฆ

ฆ

ฆ

TAILINGS
ฆ

ฆ

I

ฆ

ฆ

ADITS

. I
ฆ

RLP

ADITS

REMEDIAL
ALTERNATIVE 3+

REMEDIATION FACTOR (RF)
BY SOURCE

LOAD

WASTE ROCK

LOAD

TAILINGS

LOAD

ADITS

2. ALLOCATE LOADING
TO UPSTREAM SOURCES





PROFESSIONAL f
JUDGMENT \

( (I

FS SOURCE
VOLUME INVENTORY}

)

<

RF

3+, WASTE ROCK

RF

3+, TAILINGS

RF

3+, ADITS

GW



Note:

The natural source depletion component of the
model is not used in this FFS Report, as discussed
in Section B.1.1.

RESIDUAL

3+, WASTE
ROCK

RESIDUAL

3+, MODELED LOAD
REDUCTION

3. ESTIMATE RESIDUAL LOADING
FOR REMEDIAL ALTERNATIVE

FS DESIGN SPECIFICATIONS
PROFESSIONAL JUDGMENT

DEFINITIONS

LOAD

VOL

RLP

Surface water dissolved metal loading [lb/day] RF
Waste Volume [cy] RESIDUAL
Relative Leaching Potential AWQCr

Remedial Factor

Load Remaining Post-Remedy

Ambient Water Quality Criterion Ratio

)

3+, GW



CUMULATIVE
RESIDUAL
LOADING

4. SUM

~ RESIDUAL
LOADING
ACROSS
SOURCES

at TQm.i

Time to
AWQCr = 1

5. PROJECT NATURAL
RECOVERY DUE TO
SOURCE DEPLETION



382081.F1.06.01,03_BunkerHill_ES042009003SEA . Fig. B-1 PredidiveAnalysis_ModelSchematic_5May10.ai

Figure B-1

Predictive Analysis Model Schematic
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

	SEm

i


-------

-------
Pre-Remediation

ฆ2.2875

ฉ Pre-Remediation: 1987-1995

ฆ	Active Remediation: 1995-2002
A Post-Remediation: 2002-Present

Power (Pre-Remediation: 1987-1995)

ฆ	ฆ Power (Active Remediation: 1995-2002)
™ ^Power (Post-Remediation: 2002-Present)

4.00	4.50	5.00	5.50	6.00	6.50

LN Discharge [cfs]

7.00

7.50

8.00

8.50

Figure B-2

Elizabeth Park Dissolved Zinc vs. Discharge Over Time

Focused Feasibility Study
Upper Basin of the Coeur d'Alene River
BUNKER HILL SUPERFUND SITE


-------

-------
O Pre-Remediation: 1987-1995
ฆ Active Remediation: 1995-2002
A Post-Remediation: 2002-Present

Power (Pre-Remediation: 1987-1995)
Power (Active Remediation: 1995-2002)
Power (Post-Remediation: 2002-Present)

4.00 4.50	5.00	5.50 6.00	6.50

LN Discharge [cfs]

7.00

7.50

8.00

8.50

9.00

Figure B-3

Pinehurst Dissolved Zinc vs. Discharge Over Time

Focused Feasibility Study
Upper Basin of the Coeur d'Alene River
BUNKER HILL SUPERFUND SITE


-------

-------
3 r

0 1000 2000 3000 4000 5000 6000 7000
Dissolved Zinc Load (lb/day)

o>
o

-3

Probability Plot

J	L







Post-Remediation Dissolved Zinc Load (lb/day)

Figure B-4

Elizabeth Park Loading: Comparison of Pre-Remediation,
Remediation, and Post-Remediation Distribution

Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE


-------

-------
5000

10000

J

15000

o>
o

Probability Plot

J	I	I	i i i i



Dissolved Zinc Load (lb/day)

Post-Remediation Dissolved Zinc Load (lb/day)

Figure B-5

Pinehurst Loading: Comparison of Pre-Remediation,
Remediation, and Post-Remediation Distribution

Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE


-------

-------
Tables


-------

-------
TABLE B-1

Elizabeth Park and Pinehurst Predictive Analysis Tool Modeling Inputs

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Elizabeth Park	Pinehurst

Parameter Inputs

Record
Count

Expected
Value

Coefficient
of Variation

Model
Estimation
Error

Record
Count

Expected
Value

Coefficient
of Variation

Model
Estimation
Error

Pre-Remediation Load (lb/day)

50

1,260

0.94

-

51

2,285

1.21

-

OU 3 Upper Basin Load (lb/day)

-

-

-

-

50

1,424

1.50

-

OU 2 Groundwater Load (lb/day)

—

-

-

-

50

1,025

0.78

—

Groundwater Load Reduction (lb/day)

















OU 2(a)

-

-

-

-

365

108

0.27

0.26

OU 2(b)

-

-

-

-

365

100

0.07

0.29

OU 2(c)

-

-

-

-

365

510

0.13

0.71

OU 2(d)

-

-

-

-

365

547

0.12

1.04

OU 2(e)

-

-

-

-

365

617

0.19

0.49

OU 3 (Woodland Park)

365

157

0.33

0.25

365

157

0.33

0.25

OU 3 (SFCDR Mainstem)

365

76

0.42

0.25

365

76

0.42

0.25

Load Capacity (lb/day)

50

287

1.22

—

51

449

1.08

—

Notes:

lb/day = pounds of dissolved zinc per day
OU = Operable Unit

SCFDR = South Fork Coeur d'Alene River

Page 1 of 1


-------

-------
TABLE B-2

Total Source Volumes and Relative Loading Potential by Waste Type

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

Estimated Relative

Pre-Adjusted Source Volume Loading Potential
	(cy)	(RLP)

Waste Type

Elizabeth Park

Pinehurst



Floodplain Sediments

6,500,000

6,800,000

1.000

Tailings, Impounded in Inactive Facilites

3,600,000

3,700,000

0.143

Tailings, Impounded in Active Facilites

6,000,000

6,000,000

0.143

Tailings, Unimpounded

1,100,000

1,300,000

0.404

Waste Rock with Loading Potential

6,400,000

7,100,000

0.059

Waste Rock, Upland (with Little Loading Potential)

3,200,000

4,400,000

0.003

Waste rock, with loading potential at active facilities

1,000,000

1,000,000

--

Adits (Equivalent to Floodplain Sediments)3

108

133

1.000

Notes:

aEstimated adits drainage (pounds of zinc per day) has been adjusted to cubic yards of sediment, based on a common RLP of 1.

cy = cubic yards

RLP = relative loading potential

Page 1 of 1


-------

-------
TABLE B-3

Elizabeth Park Source Volume Inputs by Waste Type and Remedial Action

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Remedial Actions

Units

Alternative 3+

Alternative 4+

Floodplain Sediments

Total Materials

cy

6,500,000

6,500,000

Excavation/Disposal

cy

2,100,000

3,500,000

Hydraulic Isolation at Discrete Facilities

cy

1,200,000

920,000

Hydraulic Isolation of Stream Reaches

cy

0

150,000

No Action

cy

3,200,000

1,930,000

Potential Deeper Affected Sediment

cy

10,081,363

10,081,363

Tailings, Impounded at Inactive Facilities

Total Materials

cy

3,600,000

3,600,000

Cap or Regrade/Consolidate/Revegetate

cy

910,000

0

Excavation/Disposal

cy

13,000

3,600,000

No Action

cy

2,677,000

0

Tailings, Impounded at Active Facilities

Total Materials

cy

6,000,000

6,000,000

Hydraulic Isolation

cy

4,000,000

4,700,000

No Action

cy

2,000,000

1,300,000

No Action (Materials with Loading Potential)

cy

700,000

0

Tailings, Unimpounded

Total Materials

cy

1,100,000

1,100,000

Excavation/Disposal

cy

670,000

700,000

No Action

cy

430,000

400,000

Waste Rock with Loading Potential

Total Materials

cy

6,400,000

6,400,000

Regrade/Consolidate/Revegetate

cy

770,000

290,000

Cap

cy

3,900,000

0

Excavation/Disposal

cy

1,300,000

5,800,000

No Action

cy

430,000

310,000

Waste Rock, Upland (with Little Loading Potential)

Total Materials

cy

3,200,000

3,200,000

Regrade/Consolidate/Revegetate

cy

144,000

2,545,000

No Action

cy

3,056,000

655,000

Waste Rock with Loading Potential (at Active Facilities)

Total Materials

cy

1,000,000

1,000,000

No Action

cy

1,000,000

1,000,000

Adit Drainage

Total Load

lb/day

108

108

Notes:

cy = cubic yards; lb/day = pounds of dissolved zinc per day

Page 1 of 1


-------

-------
TABLE B-4

Pinehurst Source Volume Inputs by Waste Type and Remedial Action

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

Remedial Actions

Units

Alternative 3+

Alternative 4+

Floodplain Sediments

Total Materials

cy

6,800,000

6,800,000

Excavation/Disposal

cy

2,200,000

3,600,000

Hydraulic Isolation at Discrete Facilities

cy

1,200,000

920,000

Hydraulic Isolation of Stream Reaches

cy

0

150,000

No Action

cy

3,400,000

2,130,000

Potential Deeper Affected Sediment

cy

10,081,363

10,081,363

Tailings, Impounded at Inactive Facilities

Total Materials

cy

3,700,000

3,700,000

Cap or Regrade/Consolidate/Revegetate

cy

950,000

0

Hydraulic Isolation

cy

42,000

0

Excavation/Disposal

cy

13,000

3,700,000

No Action

cy

2,695,000

0

Tailings, Impounded at Active facilities

Total Materials

cy

6,000,000

6,000,000

Hydraulic Isolation

cy

4,000,000

4,700,000

No Action

cy

2,000,000

1,300,000

No Action (Materials with Loading Potential)

cy

700,000

0

Tailings, Unimpounded

Total Materials

cy

1,300,000

1,300,000

Cap

cy

56,000

0

Excavation/Disposal

cy

770,000

850,000

No Action

cy

474,000

450,000

Waste Rock with Loading Potential

Total Materials

cy

7,100,000

7,100,000

Regrade/Consolidate/Revegetate

cy

860,000

380,000

Cap

cy

4,000,000

20,000

Excavation/Disposal

cy

1,600,000

6,100,000

No Action

cy

640,000

600,000

Waste Rock, Upland (with Little Loading Potential)

Total Materials

cy

4,400,000

4,400,000

Regrade/Consolidate/Revegetate

cy

667,900

3,680,000

No Action

cy

3,732,100

720,000

Waste Rock with Loading Potential (at Active Facilities)

Total Materials

cy

1,000,000

1,000,000

No Action

cy

1,000,000

1,000,000

Adit Drainage

Total Load

lb/day

133

133

Notes:

cy = cubic yards

lb/day = pounds of dissolved zinc per day

Page 1 of 1


-------

-------
TABLE B-5

Remediation Factor by Waste Type and Remedial Action

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Remedial Action

Estimated Remediation Factor

Floodplain Sediments

Excavation/Disposal

0.01

Hydraulic Isolation at Discrete Facilities

0.18

Hydraulic Isolation of Stream Reaches

0.25

No Action

1.00

No Action (Potential Deeper Affected Sediment)

1.00

Tailings, Impounded at Inactive Facilities

Cap + Hydraulic Isolation

0.03

Cap Only

0.05

Excavation/Disposal

0.01

Hydraulic Isolation

0.05

No Action

1.00

Tailings, Unimpounded

Cap

0.05

Excavation/Disposal

0.01

No Action

1.00

Waste Rock with Loading Potential

Cap

0.05

Excavation/Disposal

0.01

Regrade/Consolidate/Revegetate

0.46

No Action

1.00

Waste Rock, Upland (with Little Loading Potential)

Regrade/Consolidate/Revegetate

0.46

No Action

1.00

Waste Rock with Loading Potential (at Active Facilities)

No Action

1.00

Adit Drainage

Passive Load Treatment

0.11

Active Load Treatment

0.01

Load No Treatment

1.00

Page 1 of 1


-------

-------
TABLE B-6

Groundwater Load Reductions for Treatment Alternatives with Groundwater Components
Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site



Dissolved Zinc Load Reduction (lb/day)





Alternatives

Minimum

Maximum

Expected Value

Coefficient of
Variation

Standard
Deviation

OU 3 Alternatives

OU 3 Woodland Park

62.24

118.55

87

0.23

20

OU 3 SFCDR Drains - Wallace to Elizabeth Park

-24.93

114.78

77

0.42

32

OU 2 Alternatives

OU 2 (a)

62.95

186.96

108

0.27

30

OU 2 (b)

60.77

138.36

100

0.07

7

OU 2 (c)

189.89

633.16

510

0.13

67

OU 2 (d)

219.33

668.78

547

0.12

64

OU 2 (e)

34.39

855.02

617

0.19

117

Notes:

lb/day = pounds of dissolved zinc per day
OU = Operable Unit

SFCDR = South Fork Coeur d'Alene River

Page 1 of 1


-------

-------
TABLE B-7

Summary of Predictive Analysis Results

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

At Remedy Completion



Post-
Remediation
Dissolved
Zinc Load
(lb/day)

80% Probability Interval on
Load Estimate

Dissolved Zinc Load
Reduction

AWQC Ratio

80% Probability Interval on
AWQC Estimate

Modeled Location/Alternative

Expected
Value

Lower

Upper

Pounds/Day

Percent

Expected
Value

Lower

Upper

Elizabeth Park





No Action Alternative3

1,260

330

2,540

5.5

2.9

8.6

Alt. 3+ (OU 3 Only)

513

90

1,120

744

59

1.9

1

3

Alt. 4+ (OU 3 Only)

432

75

940

825

66

1.6

0.8

2.6

Pinehurst





No Action Alternative3

2,290

433

4,910

5.2

2.8

8.1

Alt. 3+ (OU 3 Only)

1,450

267

3,140

833

36

3.3

1.8

5.1

Alt. 3+(a)

1,340

225

2,940

941

41

2.9

1.5

4.7

Alt. 3+(b)

1,350

227

2,960

933

41

3.0

1.5

4.7

Alt. 3+(c)

942

97

2,140

1,340

59

1.8

0.7

3.1

Alt. 3+(d)

905

84

2,060

1,380

60

1.7

0.6

2.9

Alt. 3+(e)

835

71

1,900

1,450

63

1.5

0.5

2.7

Alt. 4+ (OU 3 Only)

1,350

268

2,890

931

41

3.1

1.7

4.9

Alt. 4+(a)

1,250

223

2,700

1,040

45

2.8

1.5

4.4

Alt. 4+(b)

1,250

226

2,720

1,030

45

2.8

1.5

4.4

Alt. 4+(c)

844

90

1,910

1,440

63

1.6

0.7

2.8

Alt. 4+(d)

807

76

1,830

1,480

65

1.5

0.6

2.6

Alt. 4+(e)

737

63

1,680

1,550

68

1.3

0.5

2.4

Notes:

aThe dissolved zinc load and AWQC ratio for the No Action Alternative at each location are reflective of current conditions.

AWQC = ambient water quality criteria
OU = Operable Unit

lb/day = pounds of dissolved zinc per day

Page 1 of 1


-------

-------
Attachment B-l
Mathematical Updates to Predictive Analysis

Implemented in PAT1


-------

-------
MEMORANDUM

Page 1 of 10

Mathematical Updates to Predictive Analysis
Implemented in PAT1

TO:

DATE:

FROM:

Rebecca Maco, PE, and Alta Turner, MS; CH2MHill
Chuck Vita, PhD, PE, GE; URS
March 8, 2010

The mathematical updates to the Predictive Analysis (PA) that were implemented in the Predictive
Analysis Tool spreadsheet PAT1 are documented in this memorandum. PAT1 was used to estimate
the performance of remedial alternatives, as discussed in the Draft FFS Report (CH2MHill 2010).
This memo supplements the FFS Report and builds on previous PA documents (URS 2007, 2002,
2001) that provide the basis and detailed description of the PA. Some opportunities for
improvements to the PA and PAT1 are also noted in this memo.

The PAT1 updates included the addition of pre-remediation loadings in the Box and load reductions
(LR) due to groundwater treatment (GWT) elements that were part of the remedial alternatives.
Also, a source depletion empirical beta calibration factor (beta factor) was added to the PA natural
recovery model. FFS Report Section 7 can be consulted for an overview and discussion of the
PAT1 updates and the analysis results.

The mathematical updates have treated post-remediation loads and AWQC ratios at time t=0 as
occurring immediately after the completion of active remediation and without explicit consideration
of the time associated with remedy implementation and any concurrent source depletion that would
occur during that implementation period. The current pre-remediation load and load capacity inputs
to PAT1 have been based on statistical analysis of historic monitoring data that do not account for
source depletion during a potential future period of remedy implementation. Correction for the
period of implementation would entail including a corresponding element of load reduction (by
source depletion) either as part of the remedy in effect at t=0 or by a corresponding reduction in the
pre-remediation load inputs. Absent correction, PAT1 results will be biased to higher loads and
AWQC ratios at time t=0 than would be expected in consideration of concurrent source depletion
during the period of remedy implementation.

Memo Structure and Organization

This memorandum is structured as follows. Table 1 lists and briefly describes the PA and PAT1
input variables. The input variables are estimated outside the PA and PAT1 based on analysis and
evaluation of available data and professional judgment. Table 2 lists and briefly describes the output
variables calculated by PAT1. The PA mathematical development follows Tables 1 and 2, starting
with post-remediation loading at time t=0, F, followed by the AWQC Ratio, Lr, and non-
exceedance estimates. Natural recovery by source depletion including the empirical calibration beta
factor completes the PA and PAT1 mathematical updates discussed in this memo.

Chuck Vita	Paget of 10	5/5/2010

C:\My Files\CdA 2006-10\2009 CdAYPATs 2009\05Janl0 PATsVPA Math Update - Attach 1 Appen B.doc


-------
MEMORANDUM Math Updates to Predicative Analysis Implemented in PAT1

Page 2 of 10

Table 1.--PAT1 Input Variables

Variables Used in Mathematical Formulation

PAT1 Input Variables

Symbol

Description

Expected Values E[-] and Coefficients of Variation CV[-]

Lungwt

Pre-remediation Load from Upper Basin (SF268+PC) not including GWT.
Estimates based on statistical analysis of available historical monitoring data.

LRugwt

GWT Load Reduction in Upper Basin; varies with remedial alternative.
Estimates are based on GWM output.

Lbx

Pre-remediation Load from Box; independent of remedial alternative. Estimates
based on statistical analysis of available historical monitoring data.

LRbxgwt

GWT Load Reduction in Box; varies with remedial alternative. Estimates are
based on GWM output.

Cl

Loading capacity (CL= AWQC*Q) over water year. Estimates based on
statistical analysis of available historical monitoring data.

GWMEu

Groundwater model random estimation error (error) for LR estimates in the
Upper Basin. Measured by CV[GWMEu] with E[GWMEu]= 1.0. Assumed
independent of remedial alternative. Estimates based on professional judgment.

GWMEbx

Groundwater model random estimation error (error) for LR estimates in the
Box. Measured by CV[GWMEBx] with E[GWMEBx]=10. Assumed
independent of remedial alternative. Estimates based on professional judgment.

BF

Beta Factor used to calibrate P to empirical P estimates from statistical analysis
of available historic monitoring data.

Correlation Coefficients, p

PlnL,lnRo

p between the natural log (In) of Upper Basin pre-remediation loading, InL, and
the natural log of the aggregate remediation factor for upper basin remedial
action, lnR0. In PAT1, PimIjmr0 = "plnL,lnRo (t=0 only)" and is treated
independent of remedial alternative.

Pfu,fbx

p between Upper Basin post-remediation loading Fu and post-remediation Box
loading FBx- In PAT1, Pfu.fbx = "pBox Load, UB Load" (the same as "pUB
Load, Box Load" = Pfbx fu) and is treated independent of remedial alternative.

PFungwt,LRugwt

p between Upper Basin post-remediation loading without (no) groundwater
treatment, F, v,;\yt- and Upper Basin load reduction due to groundwater
treatment, LRUGWT. In PAT1, PFungwt,LRugwt = "pAlt3+ Load, 3+ GW LR" for
Alternative 3+ and "pAlt4+ Load, 4+ GW LR" for Alternative 4+.

PLBX,LRBXgwt

p between pre-remediation Box loading, LBX, and Box load reduction due to
groundwater treatment, LRBXgwt- In PAT1, Plbx,LRBXgwt = "pBox Load, Box GW
LR" and is treated independent of remedial alternative.

PlnF,lnCL

p between natural log of post-remediation loading, F, and load capacity CL. In
PAT1, PinF.inCL = "plnF,lnCL" and is treated independent of remedial alternative.

PlnFo,B

p between the natural log of the post-remediation loading, F0, and decay factor
"beta" p. In PAT1, p^B = "plnFo,exp{-Bt}." PAT1 treats PhFo.B as
independent of remedial alternative. See URS 2002 for further discussion.

Table 1 Notes. LR is used for load reductions due to GWT; the "GWT" and "gwt" subscripts could be deleted, but
are included for clarity. GWT = Groundwater Treatment. GWM = Groundwater Mode. PAT 1 could be modified to
make Pi„u„r„ Pfu.fbx, PLBx,LRBxgwt, or pinFo3 dependent on remedial alternative. In PAT1, PimUmr0 = "plnL,lnRo (t=0
only)"; Pfu.fbx = "pBox Load, UB Load"; PFmgwt,LRugwt = "pAlt3+ Load, 3+ GW LR" and "pAlt4+ Load, 4+ GW LR";
PLBx,LRBXgwt = "pBox Load, Box GW LR"; piM|..iM,;i. = "plnF,lnCL"; and piM|.„.h = "plnFo,exp{-Bt}."

Chuck Vita	Page 2 of 10

C:\My Files\CdA 2006-10\2009 CdAYPATs 2009\05Janl0 PATsVPA Math Update - Attach 1 Appen B.doc

5/5/2010


-------
MEMORANDUM Math Updates to Predicative Analysis Implemented in PAT1

Page 3 of 10

Table 2.--PAT1 Calculated Variables

Variables Used in Mathematical Formulation



Symbol

Description



Expected Values E[-] and Coefficients of Variation CV[-]



Rungwt

Remediation factor of Upper Basin remedial actions. Estimates calculated from
PAT1 inputs for source type remediated volumes (including no action), Vij, and
corresponding remediation factors, Rij.



LR'

CV[LR'] only. CV[LR'] combines LR variability over the water year,
CV[LRugwt] or CV[LRBXgwtL and GWM model error, CV[GWMEu] or
CV[GWMEBx]-



Fu

Post-remediation load into the Box from the Upper Basin at SF268 plus Pine
Creek.

3

.2

Fbx

Post-remediation load from the Box, between SF268 and SF271, not including
Pine Creek.

C8
>
ฆa

F

Post-remediation load at SF271 or at SF268 by not including (1) Box loading or
groundwater treatment, and (2) Pine Creek loading or remedial actions.

—

"s

CJ

Lr

Post-remediation AWQC (Load) Ratio.

u

Non-Exceedance Estimates at Probability of Non-Exceedance "Pn"

H
<
a.

Fpn

Post-remediation loading F having probability of non-exceedance "Pn."
Pn=90% and 10% is used in PAT1.



LRPn

Post-remediation AWQC Ratio LR having probability of non-exceedance "Pn."
Pn=90% and 10% is used in PAT1.



Natural Recovery by Source Depletion: Loading and AWQC Ratio at Times t>0



F(t)

Post-remediation load at times t>0 that include natural recovery by source
depletion.



LR(t)

Post-remediation AWQC (Load) Ratio at times t>0 that include natural
recovery by source depletion.



F(t)pn

Post-remediation loading F(t) having probability of non-exceedance "Pn."
Pn=90% and 10% is used in PAT1.



LR(t)pn

Post-remediation AWQC Ratio having probability of non-exceedance "Pn."
Pn=90% and 10% is used in PAT1.

Chuck Vita	Page 3 of 10

C:\My Files\CdA 2006-10\2009 CdAYPATs 2009\05Janl0 PATsVPA Math Update - Attach 1 Appen B.doc

5/5/2010


-------
MEMORANDUM Math Updates to Predicative Analysis Implemented in PAT1

Page 4 of 10

POST REMEDIATION LOAD AT SF271 AT TIME t=0

In this section all post-remediation loads are at time t=0. Time t=0 occurs immediately after the
completion of active remediation without explicit consideration of the time associated with remedy
implementation. The pre-remediation load inputs to PAT1 have been based on statistical analysis of
historic monitoring data that do not account for source depletion during a future period of remedy
implementation. While this simplification does not directly affect the mathematical development, it
would affect the meaning, and thus interpretation, of numerical results. A relatively simple
correction for the period of implementation would entail including a corresponding element of load
reduction (by source depletion) either as part of the remedy in effect at t=0 or by a corresponding
reduction in the pre-remediation load inputs. Absent correction, PAT1 results will be biased to
higher loads, and thus AWQC ratios, at time t=0 than would be expected in consideration of
concurrent source depletion during the period of remedy implementation.

L represents pre-remediation loads; F represents post-remediation loads. The subscript on F0 for
time t=0 has been suppressed to reduce notational complexity. Subscript "U" represents Upper
Basin (inflow to the Box) at SFCDR station SF268 plus Pine Creek inflow to the Box. Subscript
"BX" represents the Box between SF268 and SF271. Load reductions (LR) due to groundwater
treatment (GWT) were estimated using the groundwater model (GWM) documented in the FFS.
Symbol LR is used for load reductions that are due only to GWT. Subscript "UNGWT" represents
Upper Basin without (no) GWT; "UGWT" represents Upper Basin loadings with GWT.

E[LRugwt] and CV[LRugwt] are from the GWM. CV[LRugwt] represents natural variability of the
load reduction over the water year. CV[GWME] represents GWM model uncertainty. E[LRugwt]
and E[LRBxgwt] vary with each GWT alternative. GWT = Groundwater Treatment; GWM =
Groundwater Model.

Based on the math model for the post-remediation loading F expressed in the following Eq 1, the
expected value E[F] and variance V[F] and coefficient of variation CV[F], of post-remediation
loading were calculated as follows.

MATH MODEL

[1]	F	= Fu + Fbx

= Fu + (Lbx - LRbxgwt)

= (Lungwt*Rungwt - LRugwt) + (Lbx - LRbxgwt)

= (Fungwt - LRugwt) + (Lbx - LRbxgwt)

= Fungwt - LRugwt + Lbx - LRbxgwt

EXPECTED VALUES, E[-]

[2]	E[F]	= E[Fu + Fbx]

= E[Fu + (LBx - LRbxgwt)]

= E[(Lungwt*Rungwt - LRugwt) + (Lbx - LRbxgwt)]

Chuck Vita	Page 4 of 10

C:\My Files\CdA 2006-10\2009 CdAYPATs 2009\05Janl0 PATsYPA Math Update - Attach 1 Appen B.doc

5/5/2010


-------
MEMORANDUM Math Updates to Predicative Analysis Implemented in PAT1

Page 5 of 10

- E[(Fungwt - LRugwt) + (Lbx - LRbxgwt)]

= E[Fungwt ~ LRugwt + Lbx - LRbxgwt]

= E[Fu] + E[Fbx]

= E[Fu] + (E[Lbx] - E[LRbxgwt])

= (E[Lungwt]*E[Rungwt]*^inL,inRo - E[LRugwt]) + (E[LBx] - E[LRBXGWt])
= E[Lungwt] *E[Rungwt] * ฃ2inL,inRo - E[LRugwt] + E[Lbx] - E[LRbxgwt]
= E[Fungwt] - E[LRugwt] + E[Lbx] - E[LRbxgwt]

Where: E[FunGWt] = E[LuNGWT]*E[RuNGWT]*ฃ2lnL,lnRo

^lnL,lnRo = exp{pinL,lnRo*[ln(CV[LuNGWT]2 + l)(ln(CV[RuNGWT]2 + l )] ' J

Note that the variable "exp" in PAT1 is Q2.

^lnL,lnRo exp{2*pinL,lnRo*[ln(CV[LuNGWT]2 + l)(ln(CV[RuNGWT]2 + l)]2};

ฃ2lnL,lnRo = exp{pinLJnRo*[hl(CV[LuNGWT]2 + l)(ln(CV[RuNGWT]2 + l )] '} •

E[F] using only PAT1 Inputs:

E[F] = E[LuNGWT]*E[RuNGWT]*^inL,inRo - E[LRugwt] + E[Lbx] - E[LRbxgwt]

Expected Value for Upper Basin Loading before (no) GWT, Fungwt

E[FuNGWt] = E[LuNGWT]*E[RuNGWT]*^lnL,lnRo

Where: QinL,inRo = exp{pinL,inRo*[ln(CV[LuNGWT]2 + l)(ln(CV[RuNGWT]2+ l)]2}
CV[FuNGWt] = Sqrt{(CV[LuNGWT]2 + 1)(CV[RuNGWt]2+ l)]*^lnL,lnRo2 - 1}

V[Fungwt] = (CV[Fungwt]*E[Fungwt])2

= {(CV[LuNGWt]2 + 1)(CV[RuNGWt]2+ l)]*^lnL,lnRo2 - 1 } *E[FuNGWt]2

Expected Value for Upper Basin Loading, Fu

E[Fu] = E[Fungwt] - E[LRugwt]

Expected Value for Box Loading, FBx

E[Fbx] = E[Lbx] - E[LRbxgwt]

VARIANCE, V[-], AND COEFFICIENT OF VARIATION, CV[-]

[3] V[F]	=V[Fu + FBx]

= V[Fu + (Lbx - LRbxgwt)]

= V[(Lungwt*Rungwt - LRugwt) + (Lbx - LRbxgwt)]
= V[(Fungwt - LRugwt) + (Lbx - LRbxgwt)]
= V[Fungwt - LRugwt + Lbx - LRbxgwt]
= V[Fu] + V[Fbx] + 2pfu,fbx(V[Fu]*V[Fbx])2

Chuck Vita	Page 5 of 10

C:\My Files\CdA 2006-10\2009 CdAVPATs 2009\05Janl0 PATsVPA Math Update - Attach 1 Appen B.doc

5/5/2010


-------
MEMORANDUM Math Updates to Predicative Analysis Implemented in PAT1

Page 6 of 10

[4] CV[F]	=V[F]1/2/E[F]

= Sqrt{V[Fu] + V[FBX] + 2PFUjFBx(V[Fu]*V[Fbx])1/2}/E[F]

Variance for Upper Basin Loading before (no) GWT, Fungwt

V[Fungwt] = (CV[Fungwt]*E[Fungwt])2

= {(CV[LuNGWt]2 + 1)(CV[RuNGWt]2+ l)]*^lnL,lnRo2 - 1 } *E[FuNGWt]2

Where: CV[Fungwt] = Sqrt{(CV[LuNGWT]2 + 1)(CV[Rungwt]2+ l)]*^inL,inR02 - 1}

Variances for Upper Basin Loading, Fu

V[Fu] = V[FuNGWt] + V[LRugWt'] - 2pFungwt,LRugwt(V[FuNGWT]*V[LRuGWT])/2

V[Fungwt] = {(CV[Lungwt]2 + 1)(CV[Rungwt]2+ l)]*^inL,inR02 - 1} *E[Fungwt]2

Where: QinLjnRo = exp{pinL,inRo*[ln(CV[LuNGWT]2 + l)(ln(CV[RuNGWT]2+ l)]2}

V[LRUGwt'] = {(CV[LRugwt]2 + l)(CV[GWMEu]2+ 1) - 1}*E[LRUGwt]2

Where: Q = 1.0 for Upper Basin LR and GWM assumed uncorrected, Plr,gwm = 0.0

CV[LRUGwt'] = {(CV[LRUGwt]2 + l)(CV[GWMEu]2+ 1) - 1}'/2

CV[LRugwt'] combines LR water-year variability, CV[LRugwt],
and GWM model error, CV[GWMEu].

Coefficient of Variation for Upper Basin Loading, Fu

CV[Fu] = Sqrt{V[Fu]}/E[Fu]

= Sqrt{V[FuNGWT] + V[LRugWt] - 2pFungwt,LRugwt(V[FuNGWT]*V[LRuGWT])/2}/E[Fu]

Variances for Box Loading, FBx

V[Fbx] = V[Lbx] + V[LRbxGWt'] - 2pLBX,LRBXgwt(V[LBx]*V[LRBXGWT']) 2

= (CV[Lbx]*E[Lbx])2 + (CV[LRbxgwt']*E[LRbxgwt])2

- 2pLBx,LRBXgwt(C V[Lbx] *E[Lbx] *C V[LRbxgwt' ] *E[LRbxGWt])

Where: Q = 1.0 for Box LR and GWM assumed uncorrected, Plr,gwm = 0.0
CV[LRbxgwt'] = {(CV[LRbxgwt]2 + l)(CV[GWMEBx]2+ 1) - 1}'/2

Chuck Vita	Page 6 of 10	5/5/2010

C:\My Files\CdA 2006-10\2009 CdAVPATs 2009\05Janl0 PATsVPA Math Update - Attach 1 Appen B.doc


-------
MEMORANDUM Math Updates to Predicative Analysis Implemented in PAT1

Page 7 of 10

CV[LRBxgwt'] combines LR water-year variability, CV[LRBxgwt],
and GWM model error, CV[GWMEBx]-

Coefficient of Variation for Box Loading, FBx

CV[Fbx] = Sqrt{V[FBx]}/E[Fbx]

= Sqrt{V[LBx] + V[LRbxgwt'] - 2pLBx,LRBxgwt(V[LBx]*V[LRBXGWT']) 2}/E[FBx]

As stated, the pre-remediation load inputs to PAT1 have been based on statistical analysis of
historic monitoring data that do not account for source depletion during a potential future period of
remedy implementation. A relatively simple to implement correction for the period of
implementation would be to include a corresponding element of load reduction (by source
depletion) either as part of the remedy in effect at t=0 or by a corresponding reduction in the pre-
remediation load inputs. Absent correction, PAT1 results will be biased to higher loads and AWQC
ratios at time t=0 than would be expected in consideration of concurrent source depletion during the
period of remedy implementation.

AWQC (LOAD) RATIO, Lr

Based on the relationship for the AWQC (or load) ratio, Lr, expressed in the following Eq 1, where
Cl is the load capacity, the expected value and coefficient of variation of the load ratio, E[Lr] and
CV[Lr], were calculated as follows:

[1]

Lr

F/Cl

[2]

E[Lr] =

E[F](l+CV[CL]2)QinF,inCL / E[Cl]

[3]

CV[Lr]=

{(CV[F]2+l)(CV[CL]2+l)QinF,inCL2-l}1/2

where: OinF,inCL- exp {- PtaFjnCLj ln(C V[F]2+1 )ln(C V[CL]2+1) }1/2 }

Because F varies with remedial alternative, so does Lr. Load capacity Cl is treated as independent
of remedial alternative and estimated from available historic monitoring data.

NON-EXCEEDANCE ESTIMATES

Non-exceedance estimates are denoted with subscript "Pn" the non-exceedance probability. Pn is
the nominal probability that the uncertain true value of the variable (say, loading F) does not exceed
the non-exceedance estimate (say FPn). Equivalently, Pn is the probability that the non-exceedance
estimate overestimates the true value, and is thus not an underestimate. The complement of the

Chuck Vita	Page 7 of 10

C:\My Files\CdA 2006-10\2009 CdAYPATs 2009\05Janl0 PATsYPA Math Update - Attach 1 Appen B.doc

5/5/2010


-------
MEMORANDUM Math Updates to Predicative Analysis Implemented in PAT1

Page 8 of 10

non-exceedance probability, 1-Pn, is the probability that the uncertain true value of the variable
does exceed the non-exceedance estimate or, equivalently, that non-exceedance estimate is an
underestimate of the true value.

The non-exceedance estimate are given by the following equations, where upn is the standardized
normal variate corresponding to Pn. The values calculated in PAT1 are the 10% and 90% non-
exceedance values, for which upn = 1.28.

Non-Exceedance Estimates of Post-Remediation Loading

[1]

F pn =

E[F]

expjupn ln(CV[F] 2+l)1/2} / (CV[F] 2+l)1/2

[2]

F 90% =

E[F]

exp{1.28 ln(CV[F] 2+l)1/2} / (CV[F] 2+l)1/2

[3]

Fio% =

E[F]

exp{-1.28 ln(CV[F] 2+l)1/2} / (CV[F] 2+l)1/2

Non-Exceedance Estimates of the Load Ratio

[4]

LrPn =

E[Lr]

[5]

Lr9o% =

E[Lr]

[6]

Lrio% =

E[Lr]

vl/2-ป / /^T,rT 2 , inI/2

U/2-> / tT*\ ttt „n 2 , in 1/2

vl/2-ป / ^,,rr 2 , 1 \l/2

LOADS & AWQC RATIO AT TIME t>0
NATURAL RECOVER BY SOURCE DEPLETION

Post-remediation loading at SF271 for time t>0, F(t), was estimated from the post-remediation
loading at t=0, F, by decaying that loading over time using the source depletion model developed in
URS 2001. Two aggregate decay rates "(3" are needed: one for the Upper Basin, (3u, and one for the
Box, Pbx- To simplify the analysis, and to a tractable first approximation, (3bx was set to (3u with
the composite beta symbolized as "(3." The mathematics implemented in PAT1 is as follows.

[1]	F(t)	= Fu(t) + FBX(t)

= Fu*exp{-(3ut} +FBx(t)*exp{-(3Bxt}
= F*exp{-(3t}

[2]	E[F(t)]	= E[F*exp{-(3t}]

= E[F]*E[exp{-(3t}]*QinFo,p

[3] CV[F(t)] = {(CV[F]2 + l)*(CV[exp{-(3t}]2 + 1}*Qi„Fo/ - 1}

1/2

^inFo,p = exp{-pinFo p{ln(CV[F]Z + l)*ln(CV[exp{-(3t}]z + 1}1/2 }

Chuck Vita	Page 8 of 10

C:\My Files\CdA 2006-10\2009 CdAVPATs 2009\05Janl0 PATsVPA Math Update - Attach 1 Appen B.doc

5/5/2010


-------
MEMORANDUM Math Updates to Predicative Analysis Implemented in PAT1

Page 9 of 10

The greatest single source of uncertainty for the composite (3 is (3bx, the "Box beta," which could
also vary with Box GWT alternative. It is recommended that any future update to the PA make the
uncertainty in (3bx explicit and separate from the uncertainty in (3u. Relevant discussion on this
issue can be found in Section B.3.5.2. of URS 2001 and 2007, which should be updated if (3bx is
made explicit from (3u in PAT1. Updating PAT1 for separate (3bx and (3u is an easy modification.

AWQCR at Time t>0, Lr(t)

Mathematically, the AWQC Ratio over time, Lr(t), follows from F(t); that is:

Non-exceedance estimates use the previous equations with F(t) substituted for F and Lr(t)
substituted for Lr.

Source Depletion Factor and Decay Rate

Source depletion factors exp{-(3t}, needed to estimate F(t), were estimated at selected times "t"
based on the following relationships, where PDF[(3] is the (lognormal) probability density function
of the natural recovery decay rate (3. PDF[(3] represents both parameter uncertainty in (3 and model
uncertainty in the source depletion factor exp{-(3t} as they affect F(t), including effects of natural
variability.

For a given time, t, the integrals on the right sides of Eqs 6 and 7 were numerically approximated as
detailed in URS 2001 and 2007. PDF[(3] depends on E[(3] and CV[|3], calculated as follows, where
estimates for E[L\ and CV[Z] and E[TEM'] and CV[TEM'] are detailed in URS 2007 Section
B.2.2.2. The (model-based) decay rate (3 is updated to |3" by the empirical "Beta Factor, BF."

[5] CV[Lr(t)]

[4] E[Lr(t)]

E[F(t)](l+CV[CL]2)QnF,incL / E[Cl]

{ (C V[F(t)]2+1 )(C V[CL]2+1 )OlnF,lnCL2 " 1 }^

[6]	E[exp{-(3t}] = /0toปexp{-Pt}*PDF[P],,'dP

[7]	CV[exp{-pt}] = V[exp{-pt}]1/2/E[exp{-pt}]

{/0toป (exp{-pt})2*PDF[p]*dp-E[exp{-pt}]2}1/2/E[exp{-pt}]

[8] p

BF*(Z/(TEM')

BF*(E[Z](1+CV[TEM']2)Q / E[TEM'])
{(CV[Z]2+1)(CV[TEM']2+1)Q2(CV[M]2+1) - 1}1/2

[9] E[P"]

[10] CV[P"]

Chuck Vita	Page 9 of 10

C:\My Files\CdA 2006-10\2009 CdAVPATs 2009\05Janl0 PATsVPA Math Update - Attach 1 Appen B.doc

5/5/2010


-------
MEMORANDUM Math Updates to Predicative Analysis Implemented in PAT1

10

Page 10 of

CV[p]

exp{-p {ln(CV[Lf+1 )ln(C V[TEM' ]2+1) }1/2 }

=	1.00 for p = pinLJnTEM' = 0.0

= Source Depletion model uncertainty,

CV[M]=0.5 was used in the analysis
= Beta Factor.

Note: In PAT1, BF operates through the "B update factor" which is the
reciprocal of BF, 1/BF, that multiplies TEM' to reduce the "total effective
metal mass available for leaching" and thus increase the effective "updated"
beta, P", as represented in these equations. The PAT1 "B update factor" =
1/BF as represented here. The physical meaning of BF is that it reduces
TEM' by the factor 1/BF, consistent with empirical beta. TEM' is a very
uncertain variable that cannot be measured directly, unlike the yearly average
load L. The BF is therefore meant to modify TEM', not /., to effect an
empirically updated estimate of P, P".

The beta factor "BF" was used to calibrate P, and thus E[P] and PDF[P], to empirical P estimates
from statistical analysis of available historic monitoring data. Empirically, P appears to vary to
some extent with the discharge level and time period, although there is significant measurement
noise and natural variability in the data. Nevertheless, with judgment, the BF can be used (as a tool)
to investigate potential discharge effects and their implications, including natural recovery trends
and projections for load and AWQC ratio at lower and higher discharge levels.

To reiterate, the greatest single source of uncertainty for t>0 projections at SF271 is (3bx, the "Box
beta." It is recommended that any future update to the PA make the uncertainty in (3bx explicit and
separate from the uncertainty in (3u. (Some relevant discussion on this issue can be found in Section
B.3.5.2. of URS 2001 and 2007). Updating PAT1 for separate (3bx and (3u is an easy modification.

CITED REFERENCES

CH2MHill 2010. Focused Feasibility Study Report, Upper Basin of the Coeur d'Alene River,

Bunker Hill Mining and Metallurgical Complex Superfund Site. Draft Report prepared for U. S.
EPA. February 2010.

URS 2007. A Predictive Analysis for Post-Remediation Metal Loading, Coeur d'Alene Basin RI/FS
Technical Memorandum. Prepared for U.S. EPA. October 2007.

URS 2002. "Draft Selected Remedy and Ecological Alternatives 1 through 6, Updated Probabilistic
Estimates for the SFCDR at Pinehurst (SF271) and the CDR at Harrison (LC60)," Memo to Coeur
d'Alene Project File. May 29, 2002.

URS 2001. Probabilistic Analysis of Post-Remediation Metal Loading, Technical Memorandum
(Revision 1). Prepared for U.S. EPA. September 2001.

oOo

Q

CV[M]
BF

Chuck Vita	Page 10 of 10

C:\My Files\CdA 2006-10\2009 CdAYPATs 2009\05Janl0 PATsYPA Math Update - Attach 1 Appen B.doc

5/5/2010


-------
APPENDIX C

Typical Conceptual Design (TCD) Schematics


-------

-------
APPENDIX C

Typical Conceptual Design (TCD) Schematics

This appendix provides schematics of the typical conceptual designs (TCDs) that were used
to develop the remedial alternatives for the Upper Basin of the Coeur d'Alene River during
the Focused Feasibility Study (FFS). Detailed descriptions of each TCD can be found in
Section 5.0 of the FFS Report. The schematics are listed below and organized by Source
Control TCDs (Figures C-l through C-10); Water Collection, Conveyance, and Management
TCDs (Figures C-ll through C-20); Water Treatment TCDs (Figures C-21 through C-24); and
Stream and Riparian Cleanup Action TCDs (Figures C-25 through C-31). No separate
schematics are provided for Human Health TCDs because existing TCD schematics visually
represent these TCDs; details are provided in Section 5.4.1.

Source Control TCDs

C-l	Excavation, TCDs C01 and COlb

C-2	Regrade/Consolidate/Re vegetate, TCDs C02a through C02c

C-3	Low-Permeability Cap, TCD C03

C-4	Low-Permeability Cap with Seepage Collection, TCD C04

C-5	Low-Permeability Cap with Erosion Protection, TCD C05

C-6	Waste Consolidation Area with Erosion Protection, TCD C06

C-7	Waste Consolidation Area Above Flood Level, TCD C07

C-8	Repository, TCD C08a

C-9	Impoundment Closure, TCD C09

C-10	Haul to Repository, TCD HAUL-2

Water Collection, Conveyance, and Management TCDs

C-ll	Adit Drainage Collection, TCD CIO

C-12	Hydraulic Isolation Using Slurry Wall, TCDs Clla through Cllj

C-13	Stream Lining, TCDs C14a through C14c

C-14	French Drain, TCDs C15a through C15d

C-15	Extraction Well, TCDs C17a through C17e

C-16	SFCDR Diversion, TCD C18

C-l7	1-90 Crossing, TCD C19

C-1


-------
APPENDIX C: 1BTYPICAL CONCEPTUAL DESIGN (TCP) SCHEMATICS

C-18 Check Dam, TCD C20

C-19 Gravity Pipeline and Pressurized Pipeline, TCDs PIPE-1 through -4 and PRESSURE-
PIPE-1 through -4

C-20 Pump Station, TCDs PUMP-1 through PUMP-5

Water Treatment TCDs

C-21 Centralized High-Density Sludge (HDS) Treatment at Central Treatment Plant
(CTP), TCD WT01

C-22 Onsite Semi-Passive Water Treatment Using Lime Addition and Settling Pond(s),
TCD WT02

C-23 Onsite Semi-Passive Water Treatment Using Sulfate-Reducing Bioreactor (SRB)
System, TCD WT03

C-24 In Situ Semi-Passive Groundwater Treatment Using Sulfate-Reducing Permeable
Reactive Barrier (SR-PRB), TCDs WT04a and WT04b

Stream and Riparian Cleanup Action TCDs

C-25	Current Deflectors, TCD CD-AVG

C-26	Current Deflectors, Sediment Traps, TCD CD-SED

C-27	Vegetative Bank Stabilization, TCD VBS-AVG

C-28	Bioengineered Revetments, TCD BSBR-AVG

C-29	Floodplain and Riparian Replanting, TCD FP/RP-AVG

C-30	Off-Channel Hydrologic Features, TCD OFFCH-AVG

C-31	Channel Realignment, TCD CH-REAL-1

C-2


-------
Figures


-------

-------
TCD C01. Excavation (Dry)

Waste Pile

TCD C01b. Excavation (60% Dry/40% Wet)

This figure shows the 40% wet excavation (below the water table). The

figure for TCD C01 shows the 60% dry excavation (above the water table).

Material Below Water Table

DEWATERING TRENCH	INFILTRATION TRENCH

Note: These typical conceptual designs (TCDs) were developed for
feasibility-level analysis of remedial alternatives. Actual designs would be
developed during remedial design based on the selected remedy and
site-specific conditions and requirements.

NOT TO SCALE

Figure C-1

Excavation, TCDs C01 and C01b

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

382081.F1.06.01.03_BunkerHill_ES042009003SEA . Fig. C-1 TCDs C01 and C016 Excavation.ai . 4/15/10 . dk . Iw

f/EPA


-------

-------
LEGEND



Existing Slope





Regraded Slope



/ /V

Cut





Fill

Surface Drainage
as Needed

COVER DETAIL

ฆ Topsoil of Manufactured
Growth Medium

Waste
Rock

Regrade/Consolidate Above Flood Plain

Notes:

1.	C02a assumes waste rock piles are on slopes.

2.	C02b assumes waste rock pile has filled stream valley.

3.	C02c assumes slope too steep and requires regrade. Riprap placed
below floodplain to limit erosion.

This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

NOT TO SCALE

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-2 TCDs C02a through C02c.ai . 4/15/10 . dk

Figure C-2

Regrade/Consolidate/Revegetate,
TCDs C02a through C02c

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	


-------

-------
Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

NOT TO SCALE

Figure C-3

Low-Permeability Cap, TCD C03

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-3TCDsC03 Low-Permeability Cap.ai . 4/15/10 . dk . Iw


-------

-------
Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

NOT TO SCALE

382081.F1.06.01.03_BunkerHill_ES042009003SEA . Fig. C-4TCD C04 Low-Permeability Cap.ai . 4/15/10 . dk . Iw

Figure C-4

Low-Permeability Cap with
Seepage Collection, TCD C04

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	oEFft


-------

-------
Note: This typical conceptual design (TCD) was developed for
feasibility-level analysis of remedial alternatives. Actual designs would be

developed during remedial design based on the selected remedy and	Figure C-5

site-specific conditions and requirements.	Low-Permeability Cap with

Erosion Protection, TCD C05
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

NOT TO SCALE

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-5TCD C05 Low-Permeability Cap.ai . 4/15/10 . dk . Iw

HEPA


-------

-------
Topsoil or Manufactured
Growth Medium

16 oz.Geotextile

Drainage Layer

Geosynthetic Clay Liner —

GROUNDWATER
DIVERSION

16 oz.Geotextile
Drainage Layer
16 oz.Geotextile

Low-Permeability Native Soil
(#10-6 cm/sec)

Rock pad - as needed
to elevate waste above
groundwater

Nominal
100-year
flood level

Ordinary

high-water

level

Note: This typical conceptual design (TCD)
was developed for feasibility-level
analysis of remedial alternatives.

Actual designs would be developed during
remedial design based on the remedy
selected in the ROD and site-specific
conditions and requirements.

Cap (see detail above)
Waste

TOE DRAIN DETAIL

As required for
flood protection
(with bioengineering
as needed)

ROCK PAD DETAIL
See Detail Above

Collect and discharge 60mil - FML

NOT TO SCALE

Figure C-6

Waste Consolidation Area with
Erosion Protection, TCD C06

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-6 onsite repository with erosion protection, TCD C06.ai. 4/15/10 . dk . Iw




-------

-------
TOE DRAIN DETAIL

Topsoil or Manufactured
Growth Medium

16 oz. Geotextile -
Drainage Layer
Geosynthetic Clay Liner—

Low-Permeability Native Soil

60mil - FML

GROUNDWATER DIVERSION DETAIL

Free-Draining

I#

N—

bravei dqcktiii

I
I



Silt Barrier

<	60mil FML

Geotextile





Regolith

Perforated

!p



PVC Pipe

1

J Bedrock
Discharge to Surface
Drainage System

ROCK PAD DETAIL

16-oz. Geotextile
Drainage Layer
16-oz. Geotextile

Low-Permeability Native Soil
(#10"6 cm/sec)

Rock Pad - as Needed
to Elevate Waste Above
Groundwater

Waste

,r

Varies

Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

NOT TO SCALE

Figure C-7

Waste Consolidation Area
Above Flood Level, TCD C07

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

382081. F1.06.01.03_Bun kerHill_ES042009003SEA . Fig. C-7 TCD C07 Vtoste Consolidation Area Above Flood Level.ai. 4/15/10 . dk . Iw




-------

-------
Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

NOT TO SCALE

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-8TCDC08 Regional Repository.ai . 4/15/10 . dk

Figure C-8

Repository, TCD C08a

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	HEPA


-------

-------
CAP DETAIL

TOE DRAIN DETAIL



3 S

j	

Cap, see detail



Berm Material

—Free-Draining
Gravel

/ Discharge to



Surface Drainage System

Topsoil or Manufactured
Growth Medium

16-oz. Geotextile -

Drainage Layer

Geosynthetic

Clay Liner

Existing Sideslope
Regrade to 3H:1V
or Flatter and Cap

PERIMETER
GROUNDWATER BARRIER
Provide Hydraulic Isolation (TCD C11)
where Native Soil Consists of
Contaminated Sediments

Low-Permeability Layer

Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

NOT TO SCALE

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-9TCDC09 Impoundment Closure.ai . 4/15/10 . dk . Iw

Figure C-9

Impoundment Closure, TCD C09

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	SEFA


-------

-------
NOT TO SCALE

Figure C-10
Haul to Repository,

TCD HAUL-2

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-10 TCDs Haul-2.ai . 4/15/10 . dk . Iw

ปERA


-------

-------
6' typ

Bat Gate
(Steel Bars)

T

3'typ

Drainage collected and piped to
active treatment plant (high metals
loading sources) or conveyed to
passive treatment system (small
or remote sources)

Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

NOT TO SCALE

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-11 TCD C10 Adit Drainage Collection.ai . 4/15/10 . dk . Iw

Figure C-11

Adit Drainage Collection, TCD C10

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	ปvEFtt


-------

-------
Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

NOT TO SCALE

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-12TCD C11 Hydraulic Isolation Using Slurry Wall.ai . 4/15/10 . dk . Iw

Figure C-12

Hydraulic Isolation Using Slurry Wall,
TCDs C11 a through C11 j

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

iiepa


-------

-------
EXISTING CHANNEL

Notes:	NOT TO SCALE

1.	Remove and stage existing riprap.

2.	Excavate 2 ft below existing channel bottom.

PVC LINER

GRAVEL (1 ft)

SAND (1 ft)

CONSTRUCTED CHANNEL

NOT TO SCALE

Notes:

1.	Sand layer 1 ft placed over native materials.

2.	PVC liner placed over sand and keyed into anchor trench.

3.	Gravel placed over PVC liner.

4.	Geotextile placed over gravel layer and keyed into anchor trench.

5.	Staged riprap placed over geotextile.

6.	Channel width:

C14a: 10 ft
C14b: 20 ft
C14c: 100 ft

This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-13TCD C14Typical Channel Liner.ai . 4/15/10 . dk . Iw

Figure C-13

Stream Lining,

TCDs C14a through C14c

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	#EPA


-------

-------
CLEAN OUT VAULT ON
1,000 FOOT CENTERS

TO PUMP STATION
OR TREATMENT
FACILITY

GRANULAR BEDDING
FILTER

Notes:

1.	TCD assumes drains are installed to a depth of 5 feet below the water table.

2.	Drain depths range from 10-25 ft below ground surface.

This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-14TCD C15Typical French Drain.ai . 4/15/10 . dk . Iw

Figure C-14

French Drain,

TCDs C15a through C15d

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	ซEPA


-------

-------
SO'
UIN

extraction

WELL

TO

TREATMENT

EXTRACTION
WELL

Notes:

1. Well depths range from 20-70 ft.
2.15 ft screen intervals.

This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

Figure C-15
Extraction Well,

TCDs C17a through C17e

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-15 TCD C17 Typical Groundwater Extractioin Wells.ai . 4/15/10 . dk . Iw




-------

-------
Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

NOT TO SCALE

Figure C-16

SFCDR Diversion, TCD C18

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-16 TCD C18_SFCDR Diversion.ai . 4/15/10 . dk . Iw




-------

-------
Hydraulic Isolation Using Slurry
Separate TCD

Notes:

1-90 would be compromised for hydraulic isolation using
slurry wall installation. Two lanes of 1-90 (eastbound or westbound)
would be compromised at one time.

This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

NOT TO SCALE

Figure C-17

I-90 Crossing, TCD C19

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE



382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-17TCD C19J-90 Crossing.ai . 4/15/10 . dk . Iw


-------

-------
Mine
Water
Flow





Tunnel

HT

Check
Dam

PLAN VIEW

Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-18 Tunnel Seal, TCD C20.ai . 4/15/10 . dk . Iw

Mine Water

t "

Check
Dam

SECTION VIEW

Figure C-18
Check Dam, TCD C20

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

SEPA


-------

-------
TCDs PIPE-1 through PIPE-4

Facility

Notes:

Pipe-1: 6-inch diameter pipe
Pipe-2: 12-inch diameter pipe
Pipe-3: 24-inch diameter pipe
Pipe-4: 36-inch diameter pipe

TCDs PRESSURE-PIPE-1 through PRESSURE-PIPE-4

Valve Vault on
1,000 Foot Centers

Notes:

Pressure-Pipe-1: <6-inch diameter pipe
Pressure-Pipe-2: 6-14 inch diameter pipe
Pressure-Pipe-3: >14-inch diameter pipe
Pressure-Pipe-4: 3-inch diameter vertical pipe

These typical conceptual designs (TCDs) were developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

NOT TO SCALE

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-19 TCDs Pipe 1-3 & Pipe 1-4.ai . 5/24/10 . dk

Figure C-19

Gravity Pipeline and Pressurized
Pipeline, TCDs PIPE-1 through -4
and PRESSURE-PIPE-1 through -4

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	#EPA


-------

-------
TCD PUMP-1

Note:

Pump station capacity is 0.14 MGD.

Pump to be submersible pump (constant speed or float controlled).
The pump should be able to handle some grit, sand, and debris

TCDs PUMP-2 through PUMP-5

To Treatment
Facility

French Drain

Confining Unit

Notes:

Pump station capacity ranges from 1.4 to 6.5 MGD.

Lower Aquifer

Stainless-Steel
Pumps

These typical conceptual designs (TCDs) were developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

Pump to be submersible pump (constant speed or float controlled).
The pump should be able to handle some grit, sand, and debris

NOT TO SCALE

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-20 Pump Stations, TCDs PUMP-1 through PUMP-5.ai . 4/15/10 . dk . Iw

Figure C-20

Pump Station, TCDs PUMP-1
through PUMP-5

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	SEPA


-------

-------
*-

Discharge to Sludge Pond at the
Central Impoundment Area

Waste Sludge

Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-21 Central Treatment Plant Flow Schematic.ai . 4/15/10 . dk

-Or



Polymer

Vซ-

Makeup

Polymer Feed Pump
(Flocculant)

Thickener

Thickener Overflow (Supernatant)

Thickener Underflow (Sludge)

Granular Media
Filtration System

Sludge Recycling
& Wasting Pumps

Effluent

Discharge to
Bunker Creek

Figure C-21

Centralized High-Density Sludge
(HDS) Treatment at Central Treatment
Plant (CTP), TCD WT01

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	SEFtt


-------

-------
M = Valve

Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-22 Semi-Passive Lime Flow Schematic.ai . 4/15/10 . dk

Emergency Channel

Optional Bypass

Optional Bypass

Settling Pond 1

100 ft.

Settling Pond 2

Effluent

50 ft. Channel

Figure C-22

Onsite Semi-Passive Water
Treatment Using Lime Addition,
TCD WT02

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

SEPA


-------

-------
Emergency Channel

Optional Bypass

Influent
100 ft. Pipe

100 ft. Pipe

Optional Bypass

SRB-2

Aeration

Aerobic Polishing
Pond

Wetland

Effluent

50 ft. Channel

: Valve

Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-23 Ex Situ Treatment.ai . 5/24/10 . dk

Figure C-23

Onsite Semi-Passive Water Treatment
Using Sulfate-Reducing Bioreactor (SRB)
System, TCD WT03

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	ฎBฅV


-------

-------
7.5'

75% Stable Waste	Low-Permeability Layer

25% Lime

Figure C-24

In Situ Semi-Passive Groundwater
Treatment Using Sulfate-Reducing
Permeable Reactive Barrier (SR-PRB),
TCDs WT04a and WT04b

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

f/EPA

Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-24 In Situ Groundwater Treatment.ai . 5/24/10 . dk . Iw


-------

-------
Cross-Sectional Detail

PLAN VIEW

Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

Figure C-25

Current Deflectors, TCD CD-AVG

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

NOT TO SCALE

&EPA

382081.F1.06.01.03_BunkerHill_ES042009003SEA . Fig. C-25 Current Deflectors, TCD CD-AVG.ai . 4/15/10 . dk . Iw

Whdrc, h
-------

-------
PLAN VIEW

Notes:

CD-SED includes addition of sediment traps.

This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

NOT TO SCALE

Figure C-26

Current Deflectors, Sediment Traps,
TCD CD-SED

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

	SEPA

382081.Fl.06.01.03_BunkerHill_ES042009003SEA . Fig. C-26 Current Deflectors, Sediment Traps, TCD CD-SED.ai . 4/15/10 . dk . Iw


-------

-------
CROSS SECTION

MEAN HIGH WATER
(TOP

TOP OF BANK

RIPRAP

- STATIC

WATER
LEVEL

ENDS REACH
STATIC WATER

JOINT PLANTED FASCINE

LIVE POST

STAKE

MEAN LOW
WATER ELEVATION

BACKFILL WITH SOIL
SUITABLE FOR PLANT GROWTH.

VERTICAL SPACING VARIES
DEPENDENT UPON BANK HEIGHT

TOE TREATVE
NOT SHOWN

p^ 1/4	j

——|varie:s 1-2.5 m|—-

Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

NOT TO SCALE

Figure C-27

Vegetative Bank Stabilization,
TCD VBS-AVG
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

	SERA

382081.F1.06.01.03_BurikerHill_ES042009003SEA . Fig. C-27 Vegetative Bank Stabilization, TCD VBS-AVG.ai. 4/15/10 . dk . Iw


-------

-------
COIR GEOCRID

TOP OF BANK
(PLANT WITH UVE STAKES AND LIVE POSTS)

STAKED FASCINE
UVE STAKE „

UVE CUTTINGS
1.5-2.5 M

5—MAN ROCK
/S NEEDED

FISH BOULDER
(5—MAN ROCK)

TOE OF BANK PRO TEC VON
RIPRAP SIZED FOR
SITE CONDITIONS

EXCAVATE OR DRIVE LOG INTO BANK
(POINT END AS NEEDED)

LONG LOG WITH ROOTS.

TRENCH AND INSTALL UMBED LOG BOLE 3.5-5 M. MINIMUM
DISTANCE INTO BANK BELOW EXISTING MEAN HIGH WATER.
ANCHOR WITH FISH BOULDERS. EPOXY AND WIRE ROPE
CABLE. OR DRIVEABLE ANCHORS.

CROSS-SECTION

Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

Figure C-28

Bioengineered Revetments,
TCD BSBR-AVG
Focused Feasibility Study
Upper Basin of the Coeurd'Alene River
BUNKER HILL SUPERFUND SITE

NOT TO SCALE

SEPA

382081.F1.06.01.03_BurikerHill_ES042009003SEA . Fig. C-28 Bioengineered Revetments, TCD BSBR-AVG.ai . 4/15/10 . dk . iw


-------

-------
'Single or Double Row along Toe of
Eroded Bank with Bioengineered
Bank Protection

Downstream Inclined Rows

Stems placed in trenches
excavated by backlioe

Depth of Plantings close
to expected low water level

Eroded Bank

PLAN VIEW

Cross-Sectional Detail



derive

Figure C-29

Note: This typical conceptual design (TCD) was developed for feasibility-level	Floodplain and^Riparian Replanting,

analysis of remedial alternatives. Actual designs would be developed during	TCD FP/RP-AVG

remedial design based on the selected remedy and site-specific	Focused Feasibility Study

conditions and requirements.	Upper Basin of the Coeur d'Alene River

BUNKER HILL SUPERFUND SITE

NOT TO SCALE

SEPA

382081.FI.06.01.03_BunkerHill_ES042009003SEA . Fig. C-29 Floodplain and Riparian Replanting, TCD FP/RP-AVG.ai. 4/15/10 . dk . Iw


-------

-------
Log curtain wall to
deflect floating debris

Intake structure
and trash rack

Settling pond with T*f
^ wood debris cover B

Cu vert

Valve

OFF-CHANNEL POND

PLAN VIEW

Flood protection dyke using granular
material from channel excavation

Wood debris cover
throughout channel

SIDE CHANNEL

Pool with large wood debris
(minimum 0.5 m water depth)

Notes:

Combination of side channels and off-channel ponds.

This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

Figure C-30

Off-Channel Hydrologic Features,
TCD OFFCH-AVG

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

NOT TO SCALE

&EPA

382081.F1.06.01.03_BunkerHill_ES042009003SEA . Fig. C-30 Off-Channel Hydrologic Features, TCD OFFCH-AVG.ai . 4/15/10 . dk . Iw


-------

-------
Stream Channel

PLAN VIEW

Note: This typical conceptual design (TCD) was developed for feasibility-level
analysis of remedial alternatives. Actual designs would be developed during
remedial design based on the selected remedy and site-specific
conditions and requirements.

Figure C-31
Channel Realignment,
TCD CH-REAL-1

Focused Feasibility Study

Upper Basin of the Coeurd'Alene River

BUNKER HILL SUPERFUND SITE

NOT TO SCALE

SEPA

382081.F1.06.01.03_BunkerHill_ES042009003SEA . Fig. C-31 Channel Realignment, TCD CH-REAL-1 .ai . 4/15/10 . dk . Iw


-------

-------
APPENDIX D

Cost Analysis Documentation


-------

-------
Contents

Section	Page

Acronyms and Abbreviations	D-iii

Cost Analysis Documentation	D-l

D.l TCD Cost Estimation and Application	D-l

D.l.l Source Control TCDs	D-l

D.l.2 Water Collection, Conveyance, and Management TCDs	D-2

D.l.3 Water Treatment TCDs	D-3

D.1.4 Human Health TCDs	D-4

D.1.5 Stream and Riparian Cleanup Action TCDs	D-4

D.2 Remedy Protection Costs	D-4

D.2.1 Alternative RP-1	D-4

D.2.2 Alternative RP-2	D-5

D.3 Site-by-Site Costs for Alternatives 3+ and 4+	D-5

D.4 References	D-6

Tables

D-l Detailed Unit Cost Estimates for Source Control TCDs

D-2a Detailed Unit Cost Estimates for Water Collection, Conveyance, and Management
TCDs

D-2b Detailed Unit Cost Estimates for Pump Station TCDs
D-3 Detailed Unit Cost Estimates for Water Treatment TCDs
D-4 Detailed Unit Cost Estimates for Human Health TCDs

D-5 Detailed Unit Cost Estimates for Stream and Riparian Cleanup Action TCDs

D-6 Summary of Cost Assumptions and Limitations for Source Control TCDs

D-7 Summary of Cost Assumptions and Limitations for Water Collection, Conveyance,
and Management TCDs

D-8 Summary of Cost Assumptions and Limitations for Water Treatment TCDs

D-9 Summary of Cost Assumptions and Limitations for Human Health TCDs

D-10 Summary of Cost Assumptions and Limitations for Stream and Riparian Cleanup
Action TCDs

D-ll	Alternative RP-1: Pinehurst Cost Analysis

D-12	Alternative RP-1: Smelterville Cost Analysis

D-13	Alternative RP-1: Kellogg Cost Analysis

D-14	Alternative RP-1: Wardner Cost Analysis

D-i


-------
CONTENTS (CONTINUED)

D-15	Alternative RP-1: Osburn Cost Analysis

D-16	Alternative RP-1: Silverton Cost Analysis

D-17	Alternative RP-1: Wallace Cost Analysis

D-18	Alternative RP-1: Mullan Cost Analysis

D-19	Alternative RP-1: Approximate Cost for Side Gulches

D-20	Alternative RP-2: Pinehurst Cost Summary

D-21	Alternative RP-2: Pinehurst Detailed Unit Cost

D-22	Alternative RP-2: Smelterville Cost Summary

D-23	Alternative RP-2: Smelterville Detailed Unit Cost

D-24	Alternative RP-2: Kellogg Cost Summary

D-25	Alternative RP-2: Kellogg Detailed Unit Cost

D-26	Alternative RP-2: Wardner Cost Summary

D-27	Alternative RP-2: Wardner Detailed Unit Cost

D-28	Alternative RP-2: Osburn Cost Summary

D-29	Alternative RP-2: Osburn Detailed Unit Cost

D-30	Alternative RP-2: Silverton Cost Summary

D-31	Alternative RP-2: Silverton Detailed Unit Cost

D-32	Alternative RP-2: Wallace Cost Summary

D-33	Alternative RP-2: Wallace Detailed Unit Cost

D-34	Alternative RP-2: Mullan Cost Summary

D-35	Alternative RP-2: Mullan Detailed Unit Cost

D-36	Alternative RP-2: Approximate Cost for Side Gulches

D-37	Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

D-38	Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

D-39	Summary of Total Estimated Costs by Site, Alternative 3+

D-40	Summary of Total Estimated Costs by Site, Alternative 4+

D-41	Summary of Total Estimated Costs by Watershed

Attachment

D-l	Technical Memorandum: CTP Expansion for Treatment of Other OU 2 and OU 3
Waters

D-ii


-------
Acronyms and Abbreviations

bgs

below ground surface

BLM

Bureau of Land Management

cfs

cubic foot/feet per second

CPES

CH2M HILL Parametric Cost Estimating System

CTP

Central Treatment Plant

CY

cubic yards

FML

flexible membrane liner

FS

Feasibility Study

FFS

Focused Feasibility Study

gpm

gallons per minute

NPV

net present value

O&M

operation and maintenance

PVC

polyvinyl chloride

TCD

typical conceptual design

USEPA

U.S. Environmental Protection Agency Region 10


-------

-------
APPENDIX D

Cost Analysis Documentation

This appendix provides a detailed description of the processes used to develop cost estimates
for the Focused Feasibility Study (FFS) for the Coeur d'Alene Basin. The text of this appendix is
organized by typical conceptual design (TCD) costs (Section D. l), remedy protection costs
(Section D.2), and site-by-site costs for Alternatives 3+ and 4+ (Section D.3). References cited in
the text are listed in Section D.4, and are followed by Tables D-l through D-41.

D.1 TCD Cost Estimation and Application

This section presents the methodology and assumptions used to develop the cost estimates for
the TCDs included in Alternatives 3+ and 4+. The development of these TCDs is described in
Section 5.0 of the FFS Report. Costs were developed based upon principles outlined in U.S.
Environmental Protection Agency's (USEPA's) A Guide to Developing and Documenting Cost
Estimates during the Feasibility Study (2000).

Detailed unit cost estimates are summarized by TCD in Tables D-l through D-5. Direct capital
costs were calculated for each individual action, characterized by a TCD, on a source material.
The direct capital cost was calculated using the TCD unit cost and the appropriate
measurement, which is specific to the site and source material. The indirect capital costs were
assumed to be 70 percent of the direct capital costs for all TCDs except for WT01, active
treatment at the Central Treatment Plant (CTP) discussed in Attachment D-l (which follows the
tables in this appendix). This assumption was based on information provided in USEPA's cost
estimating guide (USEPA, 2000). Operation and maintenance (O&M) costs were assumed to be
a percentage of the direct capital costs and varied for each TCD.

The O&M costs were calculated as the net present value (NPV) of 30 years of O&M at a discount
rate of 7 percent (USEPA, 2000). The total cost is the sum of direct capital, indirect capital, and
O&M costs. The nominal accuracy of these estimates is -30 percent to +50 percent. Assumptions
and limitations used in the development of the unit costs are summarized in Tables D-6 through
D-10.

For TCDs retained from the Final (Revision 2) Feasibility Study Report, Coeur d'Alene Basin
Remedial Investigation/Feasibility Study (2001 FS Report; USEPA, 2001), costs were escalated to
2009 values assuming an escalation factor of 1.358. This escalation factor was developed from
the Engineering News Record Construction and Building Cost Index (2008). For new TCDs, costs
were developed by calculating unit costs for materials, labor, and equipment. These values were
then summed to determine the direct capital unit cost for each TCD.

D.1.1 Source Control TCDs

All of the Source Control TCDs were retained from the 2001 FS Report, and the costs were
escalated as described above with the exception of C01, COlb, and C02c. Revegetation was
added to TCDs C01 and COlb for areas disturbed during excavation. TCD C02c was developed
in 2007, and no detailed cost breakdown is available (URS, 2007).

D-1


-------
APPENDIX D: COST ANALYSIS DOCUMENTATION

A number of assumptions were used when applying these TCDs:

•	The unit costs for C02a, C02b, C02c, C03, C04, C05, and C09 are on a per-acre basis. The
acreage used to calculate the cost for a given source was assumed to be the acreage
associated with the source material in the Bureau of Land Management (BLM) polygon.

•	The costs for treatment of leachate (TCDs C04, C06, CO 7, COS a, and C09) were assumed to be
negligible. Infiltration would be minimized with the cap design, and little leachate would be
anticipated. Therefore, the cost of leachate treatment should be negligible in comparison to
the cost of the waste consolidation area or repository.

•	Hauling costs were calculated on a site-by-site basis. For the waste consolidation area above
flood level (TCD C07), hauling costs are included in the TCD and assume a haul distance of
one half-mile. For the repository (TCD C08a), hauling costs are not included in the TCD. A
hauling TCD, H A U L-2, was developed for the 2001 FS and was applied along with TCD
C08a assuming a haul distance of 5 miles for all sites.

•	The costs for the disposal of waste at the repository were developed for various repository
sizes. Based on work conducted by the repository siting team, the costs for the smallest
repository, TCD C08a, of 1 million cubic yards (CY) were used. Costs from the 2001 FS
Report were adjusted to remove the geosynthetic clay liner and increase the drainage layer
flexible membrane liner (FML) from 60 to 80 mils.

•	Road costs were applied as 15 percent of the total direct capital cost for each alternative.

D.1.2 Water Collection, Conveyance, and Management TCDs

TCDs C10, PIPE-1, PIPE-2, and PIPE-3 were retained from the 2001 FS Report, and the costs
were escalated as described above. Additional TCDs were developed for actions that the TCDs
retained from the 2001 FS Report did not address or needed modifications to address site needs.
These included TCDs PIPE-4, Clla through Cllj, PRESSURE-PIPE-1 through PRESSURE-PIPE-
4, C14a through C14c, C15a through C15d, C17a through C17e, C18, C19, C20, and PUMP-1
through PUMP-5. Detailed descriptions of these TCDs can be found in Section 5.2.2 and
Table 5-1 in the FFS Report.

Piping TCD design was based on maximum flow, which increased pipe size from the 2001 FS
Report. In addition, several sites designated for passive water treatment in the 2001 FS Report
were included in active treatment for this FFS Report.

The costs for Hydraulic Isolation Using Slurry Wall TCDs (Clla through Cllj) are based on the
length of the wall required for hydraulic isolation. If the slurry wall is required for both sides of
the river/stream, then the length of the river/stream must be doubled to calculate the cost.

The costs for Stream Lining TCDs (C14a through C14e) are based on the average width of the
river/ stream over the application length of each liner. The costs currently include some
measures to prevent liner lift. These include anchoring the polyvinyl chloride (PVC) liner and
the geotextile into the trench and placing staged riprap over the geotextile. Care should be taken
during the design of the stream liners for the gaining reaches to ensure that the design will
prevent lift given site-specific conditions.

D-2


-------
APPENDIX D: COST ANALYSIS DOCUMENTATION

The costs for French Drain TCDs (C15a through C15d) are based on the flows developed by
groundwater modeling.

Pump station TCD costs were developed based on a CH2M HILL Parametric Cost Estimating
System (CPES) model. Direct unit costs based on varying flow rates are presented in Table D-2b.

D. 1.3 Water Treatment TCDs

Attachment D-l describes the active treatment TCD WT01. The capital costs are based on
maximum flow to the CTP, and O&M costs are based on average flow to the CTP for each
alternative. An additional sludge pond cost was developed to support TCD WT01 and applied
on an alternative basis.

Detailed sludge pond costs were developed based on sludge capacities of Alternatives 3+ (cl)
and (d l), which both have a storage capacity of 414,000 cubic yards. Capital cost, annual O&M,
and 30-year NPV O&M were scaled for the remaining alternatives based the sludge production
rate. The costs were scaled depending on the required size of the sludge pond for each
alternative. The capital cost includes the closure cost of the existing pond once it reaches
capacity and the capital cost of the new sludge pond. Section 5.3 of the FFS Report describes the
pond design.

All of the semi-passive treatment TCDs (VVT02, VVT03, \VT04a, and WT04b) were newly
developed for the FFS.

The costs for WT02 (Onsite Semi-Passive Water Treatment Using Lime Addition and Settling
Pond[s]) and WT03 (Onsite Semi-Passive Water Treatment Using Sulfate-Reducing Bioreactor
[SRB] System) are based on flow (gallons per minute [gpm]). Detailed direct capital and O&M
costs were developed for flows of 5 gpm, 50 gpm, and 1,000 gpm. These costs were then
graphed and linearized. The linear equations were then used to calculate both direct capital and
O&M costs for the site flows.

A bypass and emergency channel system was put in place for WT02 and WT03 to prevent
flooding of the systems.

For WT02, the lime feed storage system cost was based on a quote by Aquafix. There are
multiple options for the size of the lime feed storage and dispenser. The appropriate size of
equipment was chosen based on the lime demand for that size flow. Winter weather was
accounted for by adding a propane tank to heat the building containing the lime feed system. It
is assumed that the settling ponds would be dredged every 10 years.

For WT03, the SRB ponds were assumed to include 75 percent stable waste and 25 percent lime.
It is assumed that the media would be replaced every 15 years.

TCDs WT04a and WT04b (In Situ Semi-Passive Groundwater Treatment Using Sulfate-
Reducing Permeable Reactive Barrier [SR-PRB]) were designed based on the depth of the
media. WT04a assumes a media depth of 10 feet, which begins at 5 feet below ground surface
(bgs). WT04b assumes a media depth of 40 feet, which begins at 5 feet bgs. These depths were
chosen in order to apply these TCDs to different depths of confining layers. The media are
assumed to be 75 percent stable waste and 25 percent lime. It is assumed that the media would
be replaced every 15 years. Both TCDs assume a length of 100 feet and a width of 7.5 feet.

D-3


-------
APPENDIX D: COST ANALYSIS DOCUMENTATION

For both semi-passive and active water treatment, cost calculations for direct capital cost were
based on maximum flow, while the O&M costs were based on average flow. If the average flow
at a site was known, but the maximum flow was unknown, the maximum flow was assumed to
be twice the average flow. In cases where no flow data were available, the average flow was
assumed to be 0.1 cubic foot per second (cfs) and the maximum flow was assumed to be 0.2 cfs.

D.1.4 Human Health TCDs

All of the Human Health TCDs were retained from the 2001 FS Report, and the costs were
escalated to 2009 values as described above.

D.1.5 Stream and Riparian Cleanup Action TCDs

All of the Stream and Riparian Cleanup Action TCDs were retained from the 2001 FS Report,
with the exception of CD-SED. Retained TCD costs were escalated to 2009 values as described
above. TCD CD-SED was developed in 2007, and no detailed cost breakdown is available (URS,
2007).

D.2 Remedy Protection Costs

This section discusses the assumptions used for developing costs for the remedy protection
alternatives evaluated in Section 9.0 of the FFS Report. The remedy protection alternatives
include RP-1: No Further Action (Post-Event Response) and RP-2: Modifications to Selected
Remedies to Enhance Protectiveness (Remedy Protection Projects). The scope of costs that were
developed for these alternatives includes eight communities within the Upper Coeur d'Alene
Basin (Pinehurst, Smelterville, Kellogg, Wardner, Osburn, Silverton, Wallace and Mullan) in
addition to a less detailed estimate developed for the side gulches.

The approach used to develop costs for these alternatives differed from the TCD approach
described above. Detailed hydrologic and hydraulic modeling was conducted, as documented
in Appendix G of the FFS Report, to determine (1) the expected damage to the Selected
Remedies and subsequent post-event costs for Alternative RP-1, and (2) the capital project costs
necessary to mitigate the potential risks posed by flood events for Alternative RP-2. The cost
analyses conducted for Section 9.0 are also more detailed than the TCD approach. This detailed
approach for Alternatives RP-1 and RP-2 was determined to be more appropriate for
developing costs for the remedy protection alternatives because (1) only eight communities
were evaluated in detail, and (2) hydrologic and hydraulic modeling allowed sufficient data to
create more detailed cost estimates.

D.2.1 Alternative RP-1

The costs for Alternative RP-1 were developed based on the methodology described in Section
9.6.1.1 of the FFS Report (CH2M HILL, 2009). This methodology uses the hydrologic and
hydraulic analyses documented in Appendix G to apply costs for the expected annual damage
to the Selected Remedies. The 30-year NPV cost was then calculated as the present value of the
expected annual damage. Tables D-ll through D-18 include the expected annual damage and
30-year NPV costs for each community.

D-4


-------
APPENDIX D: COST ANALYSIS DOCUMENTATION

Although detailed analyses were not conducted for the side gulches, it would be expected that
hydrologic and hydraulic trends within the eight Upper Basin communities would be
applicable to the side gulches. Table D-19 presents the calculations used to determine the
approximate RP-1 costs for the side gulches.

Alternative RP-1 includes costs for post-event response (or "re-remediation") of the protective
barriers. These are considered O&M costs. No capital costs are associated with Alternative RP-1.

D.2.2 Alternative RP-2

Alternative RP-2 was developed to enhance the protectiveness of existing Selected Remedies
within the eight communities. These enhancements were developed from the list of
technologies and process options applicable to remedy protection included in Table 9-4
accompanying Section 9.0 in the FFS Report. Multiple technologies and/or process options were
combined and applied to expected impact areas in each of the communities. The impact areas
were developed based on the results of the hydrologic and hydraulic analyses documented in
Appendix G. These analyses were also used to determine approximate sizes, lengths, and other
quantity measurements to apply to the process options to mitigate the existing risks posed to
Selected Remedies during flood and storm events. Detailed descriptions (including figures) of
the process options applied for each community are included in Attachment G-3 of Appendix
G.

Based on the information included in Attachment G-3, cost estimates were developed for each
community. Tables D-20 through D-35 present the detailed unit costs for the process options
applied to each community, and a summary by community of the costs to mitigate damage to
the Selected Remedies. Based on existing conditions, assumptions were made to support
development of the detailed unit costs. It was assumed that the remedy protection projects
would be implemented during the dry season and minimal dewatering would be necessary
during construction. Unit costs assume that all excavated material would be disposed of at a
repository (similar to TCD C08a).

O&M costs were also included for Alternative RP-2 on a community basis. Costs for O&M
include inspections, repairs, and documentation. These costs were assumed to be 2 percent of
the capital costs for Alternative RP-2 annually.

As discussed in Section 9.0, an approximate cost for Upper Basin side gulches was developed
for Alternative RP-2. This cost is approximate because detailed hydrologic and hydraulic
modeling was not conducted for the side gulches. This cost is based on a typical side gulch,
which assumes average characteristics based on the side gulches included in Table 9 in
Appendix G. Table D-36 presents the methods used to develop the total approximate
Alternative RP-2 cost for the side gulches.

D.3 Site-by-Site Costs for Alternatives 3+ and 4+

Because of the large number of sites involved, a relational database was developed to compile
quantity and unit cost data, identify TCDs, and calculate costs on a site-by-site and alternative-
by-alternative basis. For each waste type at each source, quantity data including the volume,
acreage, linear feet, volumetric flow rate, and metals concentration, were input into the
database. The TCD(s) identified to remediate each waste type at each source were input for each

D-5


-------
APPENDIX D: COST ANALYSIS DOCUMENTATION

alternative. The unit cost data for the TCDs were input into the database. The quantity and unit
cost data were used by the database to calculate the direct capital, indirect capital, and net
present value costs.

Costs were calculated for Alternative 3+ and Alternative 4+. Tables D-37 and D-38 present the
estimated costs for each site included in Alternatives 3+ and 4+, respectively, broken out by
waste type (trait) and TCD. Tables D-39 and D-40 present the total estimated costs by site for
Alternatives 3+ and 4+, respectively. Table D-41 presents the total estimated costs for each
watershed under the two alternatives. Rolled-up costs for each alternative are presented in
Table 8-3 in the FFS Report.

D.4 References

Engineering News Record. December 2008. Construction and Building Cost Index.

CH2M HILL. September 16, 2009. Memorandum: Methodology for Estimating Expected Loss from
Damage to Remedies. Prepared for U.S. Environmental Protection Agency Region 10.

CH2M HILL. March 21, 2010. Technical Memorandum: Side Gulch Costs for Remedy Protection
Alternatives. Prepared for U.S. Environmental Protection Agency Region 10.

TerraGraphics Environmental Engineering. March 30, 2010. Side Gulch Costing Memorandum.
Prepared for U.S. Environmental Protection Agency Region 10.

URS. June 8, 2007. Memorandum: Estimated Cleanup Costs for the Coeur d'Alene Basin, Costs
Escalated to December 2006 and Pine Creek Costs Excluded. Prepared for U.S. Environmental
Protection Agency Region 10.

U.S. Environmental Protection Agency (USEPA). July 2000. A Guide to Developing and
Documenting Cost Estimates during the Feasibility Study.

U.S. Environmental Protection Agency (USEPA). October 2001. Final (Revision 2) Feasibility Study
Report, Coeur d'Alene Basin Remedial Investigation/Feasibility Study. Prepared by URS Greiner and
CH2M HILL for USEPA Region 10.

D-6


-------
Tables


-------

-------
TABLE D-1

Detailed Unit Cost Estimates for Source Control TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









2009



TCD







Direct Capital



Code

Description

Quantity

Unit

Unit Cost

Comments

C01

Excavation

1

CY

$4.28





Excavate

1

CY

$4.20

hydraulic excavator @ 100cy/hr



Hydroseed

2%

LS

$0.08

assume 2% of direct unit cost

C01b

Excavation (60% Dry/40% Wet)

1

CY

$13.49

Assumes 60% excavation above and 40% below water table, backfill 25% of
excavated sediment; NEW



Excavate in dry

1

CY

$2.19

60%; cost by others



Excavate below water table

1

CY

$5.99

40%; cost by others, with excavator or dredge?



Replace excavated sediment

1

CY

$5.05

25%; cost by others



Hydroseed

2%

LS

$0.26

assume 2% of direct unit cost

C02a

Regrade/Consolidate/Revegetate

1

AC

$84,281.47

per Draft Tech Memo 1 dated 1/00



Regrade Waste Rock

8,067

CY

$5.98

assume 5' deep



Vegetative Cover

1,613

CY

$16.66

based on CIA estimate



Grade Surface Drainage Ditch

400

CY

$4.15

assume 400' & 1 cy/LF



Hydroseed

4,840

SY

$0.41

from Bunker Hill estimates



Miscellaneous

1

LS

$5,513.74

slope protection, erosion control, etc

C02b

Regrade/Consolidate/Revegetate

1

AC

$166,906.76

per Draft Tech Memo 1 dated 1/00



Regrade Waste Rock

20,973

CY

$5.98

assume 13' deep



Vegetative Cover

1,613

CY

$16.66

based on CIA estimate



Grade Surface Drainage Ditch

400

CY

$4.15

assume 400' & 1 cy/LF



Hydroseed

4,840

SY

$0.41

from Bunker Hill estimates



Miscellaneous

1

LS

$10,919.13

slope protection, erosion control, etc

C02c

Regrade/Consolidate/Revegetate

1

AC

$14,900.00

per 2007 Cost Update Memo; No detail available

C03

Low-Permeability Cap

1

AC

$224,826.10

per Draft Tech Memo 1 dated 1/00



Regrade Waste Rock

8,067

CY

$5.98

assume 5' deep



Vegetative Cover

2,420

CY

$19.55

over geotextile



Grade Surface Drainage Ditch

400

CY

$4.15

assume 400' & 1 cy/LF



Hydroseed

4,840

SY

$0.41

from Bunker Hill estimates



Native Soil Leveling Layer Placement

807

CY

$11.59

50cy/hr production, depth of 0.5'; description & quantity change only, same cost



Drainage Layer Placement

1,613

CY

$11.59

50cy/hr production



Haul Above Material

2,420

CY

$13.73

this & following item, Sue Alvarez information, based on 10mi one way



Develop & Close Pit for Material Above

2,420

CY

$3.43

allowance per CY for mining development & closure



GCL

4,840

SY

$5.86

Bunker Hill estimates; added line item, previous cost



16oz Geotextile

4,840

SY

$2.68

quote for CIA plus installation



Miscellaneous

1

LS

$14,708.25

slope protection, erosion control, etc

C04

Low-Permeability Cap w/Seepage Collection

1

AC

$254,029.64

per Draft Tech Memo 1 dated 1/00



Regrade Waste Rock

8,067

CY

$5.98

assume 5' deep



Vegetative Cover

2,420

CY

$19.55

over geotextile



Grade Surface Drainage Ditch

400

CY

$4.15

assume 400' & 1 cy/LF

Page 1 of 6


-------
TABLE D-1

Detailed Unit Cost Estimates for Source Control TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









2009



TCD







Direct Capital



Code

Description

Quantity

Unit

Unit Cost

Comments



Hydroseed

4,840

SY

$0.41

from Bunker Hill estimates



Native Soil Leveling Layer Placement

807

CY

$11.59

50cy/hr production, depth of 0.5'



Drainage Layer Placement

1,613

CY

$11.59

50cy/hr production



Haul Above Material

2,420

CY

$13.73

this & following item, Sue Alvarez information, based on 10mi one way



Develop & Close Pit for Material Above

2,420

CY

$3.43

allowance per CY for mining development & closure



GCL

4,840

SY

$5.86

Bunker Hill estimates



16oz Geotextile

4,840

SY

$2.68

quote for CIA plus installation



Groundwater Collection & Diversion Trench

2,500

SF

$10.92

Size: 3'wx10'd Length Variable=



Soil Excavation

241

CY

$8.40

boulders, cobbles, etc



Rock Excavation

56

CY

$41.99

earthwork crew @ 10cy/hr-assume can be excavated w/backhoe



Shoring (trench box)

250

LF

$2.72

trench box



Waste

296

CY

$6.86

dispose on tailings pile



Dewatering

250

LF

$6.79

allowance for sumps & pumps



4" CPE Pipe

250

LF

$4.15





Drain Rock

296

CY

$44.67

quote for Bunker Hill projects, 20cy/hour



Geotextile

333

SY

$2.68

quote for CIA plus installation



60mil FML

333

SY

$10.08

10Osy/hr



Miscellaneous

1

LS

$16,618.76

slope protection, erosion control, etc

C05

Low-Permeability Cap w/Erosion Protection

1

AC

$252,170.08

per Draft Tech Memo 1 dated 1/00



Site Preparation

1

AC

$3,324.79

clearing, grubbing



Regrade Waste Rock

8,067

CY

$5.98

assume 5' deep



Vegetative Cover

2,420

CY

$19.55

over geotextile



Grade Surface Drainage Ditch

400

CY

$4.15

assume 400' & 1 cy/LF



Hydroseed

4,840

SY

$0.41

from Bunker Hill estimates



Native Soil Leveling Layer Placement

807

CY

$11.59

50cy/hr production, depth of 0.5'



Drainage Layer Placement

1,613

CY

$11.59

50cy/hr production



Haul Above Material

2,420

CY

$13.73

this & following item, Sue Alvarez information, based on 10mi one way



Develop & Close Pit for Material Above

2,420

CY

$3.43

allowance per CY for mining development & closure



GCL

4,840

SY

$5.86

Bunker Hill estimates



16oz Geotextile

4,840

SY

$2.41





Riprap Toe

296

CY

$43.96

assume 10'w x 2'd



Miscellaneous

1

LS

$27,018.22

slope protection, erosion control, etc

C06

Waste Consolidation Area w/Erosion Protection

40,333

CY

$15.72

per Draft Tech Memo 1 dated 1/00



Haul to On-site Containment

40,333

CY

$1.56

loader to nearby repository, assume 25' deep



Site Preparation

1

AC

$3,324.79

clearing, grubbing



Grade at Repository

40,333

CY

$2.07

1-dozer @ 100cy/hr



Grade Surface Drainage Ditch

400

CY

$4.15

assume 400' & 1 cy/LF



Groundwater Collection & Diversion Trench

3,000

SF



Size: 3'wx 10'd Variable=

Page 2 of 6


-------
TABLE D-1

Detailed Unit Cost Estimates for Source Control TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site







2009









Direct Capital



Description

Quantity

Unit

Unit Cost

Comments

Soil Excavation

289

CY

$8.40

boulders, cobbles, etc

Rock Excavation

67

CY

$41.99

earthwork crew @ 10cy/hr-assume can be excavated w/backhoe

Shoring (trench box)

300

LF

$2.72

trench box

Waste

356

CY

$6.86

dispose on tailings pile

Dewatering

300

LF

$6.79

allowance for sumps & pumps

4" CPE Pipe

300

LF

$4.15



Drain Rock

356

CY

$44.67

quote for Bunker Hill projects, 20cy/hour

Geotextile

400

SY

$2.68

quote for CIA plus installation

60miI FML

400

SY

$10.08

100sy/hr

Rock Pad

0.8

AC



assume 80% of cap area

Geotextile

7,744

SY

$2.41



Low Permeability Native Soil Placement

1,291

CY

$11.59

50cy/hr production

Drainage Layer Placement

2,581

CY

$11.59

50cy/hr production

Haul Above Material

3,872

CY

$13.73

this & following item, Sue Alvarez information, based on 10mi one way

Develop & Close Pit for Material Above

3,872

CY

$3.43

allowance per CY for mining development & closure

Toe Drain for Rock Pad

300

LF





Excavation

267

CY

$4.20

earthwork crew @ 100cy/hr

Waste

4,172

CY

$6.86

dispose on tailings pile

4" CPE Pipe

300

LF

$4.15



Drain Rock

267

CY

$44.67

quote for Bunker Hill projects, 20cy/hour

60mil FML

333

SY

$10.08

10Osy/hr

Cap

1.20

AC



assumed acreage=

GCL Liner

5,808

SY

$5.97

Bunker Hill estimates

Vegetative Cover

2,904

CY

$19.55

over geotextile

Hydroseed

5,808

SY

$0.41

from Bunker Hill estimates

Low Permeability Native Soil Placement

968

CY

$11.59

50cy/hr production

Drainage Layer Placement

1,936

CY

$11.59

50cy/hr production

Haul Above Material

2,904

CY

$13.73

this & following item, Sue Alvarez information, based on 10mi one way

Develop & Close Pit for Material Above

2,904

CY

$3.43

allowance per CY for mining development & closure

16oz Geotextile

5,808

SY

$2.68

quote for CIA plus installation

Riprap Toe

296

CY

$43.96

assume 10'w x 2'd

Miscellaneous

1

LS

$67,953.46

anchor trenches, slope protection, erosion control, etc

Waste Consolidation Area Above Flood Level

40,333

CY

$14.68

per Draft Tech Memo 1 dated 1/00

Haul to On-site Containment

40,333

CY

$1.56

loader to nearby repository, assume 25' deep

Site Preparation

1

AC

$3,324.79

clearing, grubbing

Grade at Repository

40,333

CY

$2.07

1-dozer @ 100cy/hr

Grade Surface Drainage Ditch

400

CY

$4.15

assume 400' & 1 cy/LF

Groundwater Collection & Diversion Trench

3,000

SF

$10.92

Size: 3'wx 10'd Variable=

Page 3 of 6


-------
TABLE D-1

Detailed Unit Cost Estimates for Source Control TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









2009



TCD







Direct Capital



Code

Description

Quantity

Unit

Unit Cost

Comments



Soil Excavation

289

CY

$8.40

boulders, cobbles, etc



Rock Excavation

67

CY

$41.99

earthwork crew @ 10cy/hr-assume can be excavated w/backhoe



Shoring (trench box)

300

LF

$2.72

trench box



Waste

356

CY

$6.86

dispose on tailings pile



Dewatering

300

LF

$6.79

allowance for sumps & pumps



4" CPE Pipe

300

LF

$4.15





Drain Rock

356

CY

$44.67

quote for Bunker Hill projects, 20cy/hour



Geotextile

400

SY

$2.68

quote for CIA plus installation



60miI FML

400

SY

$10.08

100sy/hr



Rock Pad

0.8

AC



assume 80% of cap area



Geotextile

7,744

SY

$2.68

quote for CIA plus installation



Low Permeability Native Soil Placement

1,291

CY

$11.59

50cy/hr production



Drainage Layer Placement

2,581

CY

$11.59

50cy/hr production



Haul Above Material

3,872

CY

$13.73

this & following item, Sue Alvarez information, based on 10mi one way



Develop & Close Pit for Material Above

3,872

CY

$3.43

allowance per CY for mining development & closure



Toe Drain for Rock Pad

300

LF







Excavation

266.67

CY

$4.20

earthwork crew @ 100cy/hr



Haul Above Material

266.67

CY

$6.86

assume 5 mile one way - 5 trucks



4" CPE Pipe

300

LF

$4.15





Drain Rock

266.67

CY

$44.67

quote for Bunker Hill projects, 20cy/hour



60mil FML

333.33

SY

$10.08

10Osy/hr



Cap

1.2

AC

$160,721.13

assumed size w/area adjustment for slopes



GCL Liner

5,808

SY

$5.97

Bunker Hill estimates



Vegetative Cover

2,904

CY

$19.55

over geotextile



Hydroseed

5,808

SY

$0.41

from Bunker Hill estimates



Low Permeability Native Soil Placement

968

CY

$11.59

50cy/hr production



Drainage Layer Placement

1,936

CY

$11.59

50cy/hr production



Haul Above Material

2,904

CY

$13.73

this & following item, Sue Alvarez information, based on 10mi one way



Develop & Close Pit for Material Above

2,904

CY

$3.43

allowance per CY for mining development & closure



16oz Geotextile

5,808

SY

$2.68

quote for CIA plus installation



Miscellaneous

1

LS

$63,426.69

anchor trenches, slope protection, erosion control, etc

C08a

Repository, 1 million cy

1,000,000

CY

$17.68

assume 900' sq & 75' high



Transfer at Repository

1,000,000



$1.36





Grade & Compact at Repository

1,000,000

CY

$2.07

1-dozer @ 100cy/hr



Access Road

1

Ml

$679,000.00





Liner

19

AC

$3,618,745.71





Site Preparation

19

AC

$3,324.79

clearing, grubbing



Grade base for drainage (CNS)

45,093

CY

$5.08











Page 4 of 6




-------
TABLE D-1

Detailed Unit Cost Estimates for Source Control TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site







2009









Direct Capital



Description

Quantity

Unit

Unit Cost

Comments

Drainage Layer

60,000

CY

$11.59

hauled in from elsewhere, over geotextile

Haul Above Material

60,000

CY

$13.73

recent site information, based on 10 mi one way

Develop & Close Pit for Material Above

60,000

CY

$3.43

allowance per CY for mining development & closure

80miI FML

90,000

SY

$8.63

CHANGED ON 12/01/09

Geotextile

90,000

SY

$2.68

quote for CIA plus installation

Drain Rock

1,100

CY

$44.67

Every 300 ft

Drain Pipe

3,600

LF

$4.15



Strip drains

810,000

SF

$0.48

100% of area

Leachage Collection System

1

LS

$100,000.00

ALLOWANCE ADDED ON 12/01/09

Perimeter Drain & Rock Berm

3,600

LF





Drain Pipe

3,600

LF

$4.15



Drain Rock

5,333

CY

$44.67

quote for Bunker Hill projects, 20cy/hour

Trench Liner

5,200

SY

$7.42

Bunker Hill estimates

Rock Berm

43,333

CY

$43.96

assume full perimeter, 10' high x 32.5' average width

Collection Sump & Gravity Pipeline

1

LS

$45,516.42

ALLOWANCE ADDED ON 12/01/09, ASSUMES 1000' OF 6" HDPE

Cap

22.31

AC

$6,082,768.64

slope area increase factor of 1.2

Subgrade Preparation

108,000

SY

$0.21

top of existing pile or site of new pile

80miI FML

108,000

SY

$8.63

CHANGED ON 12/01/09

Geotextile

108,000

SY

$2.68

quote for CIA plus installation

Strip drains

81,000

SF

$0.48

10% of area

Drainage Layer

36,000

CY

$11.59

hauled in from elsewhere, over geotextile

Compacted Native Soil

36,000

CY

$5.79



Interim cover

100,000

CY

$5.79

10% of volume

Haul Above Material

172,000

CY

$13.73

this & following item, Sue Alvarez information, based on 10mi one way

Develop & Close Pit for Material Above

172,000

CY

$3.43

allowance per CY for mining development & closure

Vegetative Cover

36,000

CY

$16.66

based on CIA estimate, REVISED TO 1' ON 12/01/09

Hydroseed

108,000

SY

$0.41

from Bunker Hill estimates

Misc Work

1

LS

$1,607,085.73

anchor trenches, slope protection, erosion control, etc

Impoundment Closure

67

AC

$245,945.54

based on Hecla-Star 5800'x 500' x 35' high

Perimeter Drain

12,600

LF

$32.25



Excavation

16,333

CY

$8.40

assume added volume for boulders, cobbles, etc

Waste

16,333

CY

$6.86

assume 20% volume of bentonite

Trench Liner

16,800

SY

$5.97

Bunker Hill estimates

Drain Pipe

12,600

LF

$4.15



Drain Rock

2,800

CY

$44.67

quote for Bunker Hill projects, 20cy/hour

Cap

73.23

AC

$216,393.23

x 1.1 area increase factor for slopes

Regrade Tailings Pile Top

107,407

CY

$2.07

1-dozer @ 100cy/hr, assume 1' average depth

Regrade Tailings Side Slopes

425,000

CY

$2.07

1-dozer @ 100cy/hr, from 1.5:1 slope to 3:1 slopes

Page 5 of 6


-------
TABLE D-1

Detailed Unit Cost Estimates for Source Control TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

2009

TCD	Direct Capital

Code

Description

Quantity

Unit

Unit Cost

Comments



GCL Liner

354,444

SY

$5.97

Bunker Hill estimates



Geotextile

354,444

SY

$2.68

quote for CIA plus installation



Drainage Layer

118,148

CY

$11.59

hauled in from elsewhere, over geotextile



Compacted Native Soil

118,148

CY

$5.79





Haul Above Material

236,296

CY

$13.73

this & following item, Sue Alvarez information, based on 10mi one way



Develop & Close Pit for Material Above

236,296

CY

$3.43

allowance per CY for mining development & closure



Vegetative Cover

236,296

CY

$16.66

based on CIA estimate



Hydroseed

354,444

SY

$0.41

Bunker Hill estimates



Misc Work

1

LS

$1,488,525.89

anchor trenches, slope protection, erosion control, etc

HAUL-2

Haul to Repository

1

CY-MI

$1.10

1 - 10cy truck, at 25mph average, plus return trip



Haul to Repository

1

CY

$1.10

25x10=250, 1/250=004x2=008

Notes:

AC = acre(s)

CIA = Central Impoundment Area

CPE = polyethylene

CY = cubic yards

FML = flexible membrane liner

GCL = geosynthetic clay liner

HDPE = high density polyethylene

LF = linear feet

LS = lump sum

SY = square yards

TCD = typical conceptual design

NOTE: The above costs are presented rounded to three significant figures

NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of -30 percent to +50
percent (-30/+50%).

NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-magnitude cost
opinion shown has been prepared for guidance in project evaluation from the information available at the time of
preparation. The final costs of the project will depend on actual labor and material costs, actual site conditions,
productivity, competitive market conditions, the final project scope, the final project schedule, and other variable
factors. As a result, the final project costs will vary from those presented above. Because of these factors, funding
needs must be carefully reviewed prior to making specific financial decisions or establishing final budgets.

Page 6 of 6


-------
TABLE D-2a

Detailed Unit Cost Estimates for Water Collection, Conveyance, and Management TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009











Direct Capital



TCD Code

Description

Quantity

Unit

Unit Cost

Comments

C10

Adit Drainage Collection

1

LS

$9,684.18

per DTM 1 dated 1/00, conveyance pipe included elsewhere



Steel Bars

12

EA

$414.74

assume 6" spacing & 1" dia x 7'long drilled & grouted



Concrete Wall

1

CY

$1,872.29

incl forms, rebar & concrete



Drain pipe, stainless

5

LF

$119.94

4" diameter



Misc Work

1

LS

$2,235.27

flanges, grout, waste, pipe penetration, temporary drainage, etc

C11a

Hydraulic Isolation Using Slurry Wall, 15'd x 3'w

1

LF

$195.60





Soil Bentonite Mix (10%), 20'd x 3'w

15

SF

$144.60

for 1 slurry wall only from C11 retained TCD cost



Waste all Excavated Material to Repository

15

SF

$51.00



C11b

Hydraulic Isolation Using Slurry Wall, 20'd x 3'w

1

LF

$260.80





Soil Bentonite Mix (10%), 20'd x 3'w

20

SF

$192.80

for 1 slurry wall only from C11 retained TCD cost



Waste all Excavated Material to Repository

20

SF

$68.00



C11c

Hydraulic Isolation Using Slurry Wall, 30'd x 3'w

1

LF

$391.20





Soil Bentonite Mix (10%), 20'd x 3'w

30

SF

$289.20

for 1 slurry wall only from C11 retained TCD cost



Waste all Excavated Material to Repository

30

SF

$102.00



C11d

Hydraulic Isolation Using Slurry Wall, 40'd x 3'w

1

LF

$521.60





Soil Bentonite Mix (10%), 20'd x 3'w

40

SF

$385.60

for 1 slurry wall only from C11 retained TCD cost



Waste all Excavated Material to Repository

40

SF

$136.00



C11e

Hydraulic Isolation Using Slurry Wall, 45'd x 3'w

1

LF

$594.90





Soil Bentonite Mix (10%), 45'd x 3'w

45

SF

$441.90

for 1 slurry wall only from C11 retained TCD cost



Waste all Excavated Material to Repository

45

SF

$153.00



C11f

Hydraulic Isolation Using Slurry Wall, 50'd x 3'w

1

LF

$652.00





Soil Bentonite Mix (10%), 50'd x 3'w

50

SF

$482.00

for 1 slurry wall only from C11 retained TCD cost



Waste all Excavated Material to Repository

50

SF

$170.00



C11g

Hydraulic Isolation Using Slurry Wall, 50'd x 10'wide

1

LF

$4,175.00





Soil Cement Mix (10%), 50'd x 10'wide

50

SF

$4,005.00

revised to cement w/clamshell, 8/11/09 - revised to 10' thick 9/23/09



Waste all Excavated Material to Repository

50

SF

$170.00



C11h

Hydraulic Isolation Using Slurry Wall, w/Drain

1

LF

$1,116.29

per Draft Tech Memo 1 dated 1/00



GW Barrier (Soil/Bentonite Slurry)

1

LF

$173.86







15

SF

$11.59

per Draft Tech Memo #1 dated 1/17/00 - 30'd x 3'thick x variable=



Excavation

2.22

CY

$8.40

assume added volume for boulders, cobbles, etc



Rock Excavation

0.22

CY

$41.99

rock will be waste



Haul & Dispose at Repository

2.22

CY

$5.49

assume all wasted, 5 mile, use HAUL-2 cost



Repository Cost

2.22

CY

$17.70

use C8a cost



Bentonite Material

0.24

TN

$203.70

1 ton/cy



Mix & Place Bentonite/Soil

2.44

CY

$11.11

add $2 for mixing



Miscellaneous

1

LS

$17.37





French Drain

1

LF







15' Deep French Drain

1

LF

$942.43

see detail for C15b

C11 i

Hydraulic Isolation Using Slurry Wall, w/Drain

GW Barrier (Soil/Bentonite Slurry)

1
1

LF
LF

$1,210.81

$225.70

per Draft Tech Memo 1 dated 1/00





20

SF

$11.29

per Draft Tech Memo #1 dated 1/17/00 - 30'd x 3'thick x variable=



Excavation

2.96

CY

$8.40

assume added volume for boulders, cobbles, etc



Rock Excavation

0.22

CY

$41.99

rock will be waste



Haul & Dispose at Repository

2.96

CY

$5.49

assume all wasted, 5 mile, use HAUL-2 cost

Page 1 of 11


-------
TABLE D-2a

Detailed Unit Cost Estimates for Water Collection, Conveyance, and Management TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009











Direct Capital



TCD Code

Description

Quantity

Unit

Unit Cost

Comments



Repository Cost

2.96

CY

$17.70

use C8a cost



Bentonite Material

0.32

TN

$203.70

1 ton/cy



Mix & Place Bentonite/Soil

3.19

CY

$11.11

add $2 for mixing



Miscellaneous

1

LS

$22.51





French Drain

1

LF







20' Deep French Drain

1

LF

$985.10

see detail for C15c

C11j

Hydraulic Isolation Using Slurry Wall, w/Drain

GW Barrier (Soil/Bentonite Slurry)

1
1

LF
LF

$1,586.14

$329.41

per Draft Tech Memo 1 dated 1/00





30

SF

$10.98

per Draft Tech Memo #1 dated 1/17/00 - 30'd x 3'thick x variable=



Excavation

4.44

CY

$8.40

assume added volume for boulders, cobbles, etc



Rock Excavation

0.22

CY

$41.99

rock will be waste



Haul & Dispose at Repository

4.44

CY

$5.49

assume all wasted, 5 mile, use HAUL-2 cost



Repository Cost

4.44

CY

$17.70

use C8a cost



Bentonite Material

0.47

TN

$203.70

1 ton/cy



Mix & Place Bentonite/Soil

4.67

CY

$11.11

add $2 for mixing



Miscellaneous

1

LS

$32.79





French Drain











30' Deep French Drain

1

LF

$1,256.73

see detail for C15d

C14a

Stream Lining -10' wide

1

LF

$318.46

10' wide bottom width channel



Diversion/Care of Water

1

LF

$20.00

allowance for temp dikes/facilities & bypass pumping



Diversion Piping - Temporary: 36" dia Equiv

1

LF

$37.41

Temporary piping allowance; may be in segments



Excavate & Prep Channel

2

CY

$20.49

50cy/hr



Haul & Dispose at Repository

2

CY

$13.42

assume all but rock is wasted, 5 mile, use HAUL-2 cost



Repository Cost

2

CY

$43.27

use C8a cost



12" Quarry Spalls

1

CY

$29.95

native, include loading & hauling



Pea Gravel

1

CY

$45.15

imported



Sand

1

CY

$45.15

imported



Liner/Geotextile System

5

SY

$39.82

incl anchor trench



Misc Detail Allowance

10%

LS

$23.80

road maint & repair, testing, detection tape, etc

C14b

Stream Lining - 20' wide

1

LF

$505.10

20' wide bottom width channel



Diversion/Care of Water

1

LF

$10.00

allowance for temp dikes/facilities & bypass pumping



Diversion Piping - Temporary: 36" dia Equiv

1

LF

$26.73

Temporary piping allowance; may be in segments



Excavate & Stockpile Riprap

3

CY

$49.67

25cy/hr



Excavate & Prep Channel

3

CY

$24.84

50cy/hr



Haul & Dispose at Repository

3

CY

$16.27

assume all but rock is wasted, 5 mile, use HAUL-2 cost



Repository Cost

3

CY

$52.44

use C8a cost



Replace Stockpiled Riprap

3

CY

$73.87

native, include loading & hauling



Pea Gravel

1

CY

$82.10

imported



Sand

1

CY

$82.10

imported



Liner/Geotextile System

6

SY

$47.41

incl anchor trench



Misc Detail Allowance

10%

LS

$39.67

road maint & repair, testing, detection tape, etc

C14c

Stream Lining -100' wide

1

LF

$2,969.53

100' wide bottom width channel



Diversion/Care of Water

1

LF

$50.00

allowance for temp dikes/facilities & bypass pumping



Diversion Piping

1

LF

$58.58

Temporary piping allowance; may be in segments

Page 2 of 11


-------
TABLE D-2a

Detailed Unit Cost Estimates for Water Collection, Conveyance, and Management TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009
Direct Capital

TCD Code Description

Quantity

Unit

Unit Cost

Comments

Excavate & Prep Channel

24

CY

$198.68

50cy/hr, 6' deep

Excavate & Sort Existing Rock

9

CY

$99.86

50cy/hr + screening allowance

Haul & Dispose at Repository

19

CY

$104.11

assume all but rock is wasted, 5 mile, use HAUL-2 cost

Repository Cost

19

CY

$335.64

use C8a cost

Riprap

19

CY

$778.53

48" thick

Pea Gravel

5

CY

$262.72

imported

Sand

5

CY

$262.72

imported

Native Rock, Screened

5

CY

$94.56

excavated material

Liner/Geotextile System

15

SY

$261.69

incl anchor trench, 80mil PVC & 16oz geotex, allowance

Additional Mob & Demob Required

5

EA

$250.71



Misc Detail Allowance

10%

LS

$211.75

TESC etc.

C15a French Drain, 10'bgs

1

LF

$545.41

10' deep avg depth, valve vault @1000'

Clear, Grub & Dispose

0.001

AC

$0.65



Excavate Trench

2

CY

$6.31



Bed & Zone

0.3

CY

$14.87

1/2 mile one way average

Locally Obtained Backfill Material

1

CY

$17.38

allow for material loading & preparation

Imported Backfill - Drain Rock Material (Cobble)

0

CY

$7.18



Haul & Dispose at Repository

2

CY

$8.27

assume all wasted, 5 mile, use HAUL-2 cost

Repository Cost

2

CY

$26.66

use C8a cost

Filter Fabric Wrap

21

SF

$24.76



Trench Shoring - 25' avg depth

20

SF

$288.50

Solid shoring

Dewatering: Two Sump Pmps

0.1

HR

$2.08

24 hr operation plus redundantt pump, pump to PS drain & to CTP

Temporary Pipeline to PS Drain & Removal

1

LF

$41.82

allow for 8" above grade HDPE pipe & appurtenances

Pipe, 14" HDPE, SDR 26 - Perforated

1

LF

$54.39

200'/day

Cleanouts

0.002

EA

$4.37

allowance

Restoration - Seeding

0.001

AC

$1.75

subcontract

Misc Detail Allowance

10%

LS

$46.41

road maint & repair, testing, detection tape, etc

C15b French Drain, 15'bgs

1

LF

$907.04

10' deep avg depth, valve vault @1000'

Clear, Grub & Dispose

0.001

AC

$0.65



Excavate Trench

2

CY

$9.31



Bed & Zone

0.3

CY

$16.01

1/2 mile one way average

Locally Obtained Backfill Material

1

CY

$27.37

allow for material loading & preparation

Imported Backfill - Drain Rock Material (Cobble)

0.46

CY

$11.31



Haul & Dispose at Repository

2

CY

$12.20

assume all wasted, 5 mile, use HAUL-2 cost

Repository Cost

2

CY

$39.33

use C8a cost

Filter Fabric Wrap

24

SF

$27.60



Trench Shoring - 25' avg depth

40

SF

$567.55

Solid shoring

Dewatering: Two Sump Pmps

0.1

HR

$3.07

24 hr operation plus redundantt pump, pump to PS drain & to CTP

Temporary Pipeline to PS Drain & Removal

1

LF

$41.82

allow for 8" above grade HDPE pipe & appurtenances

Pipe, 18" HDPE, SDR 26 - Perforated

1

LF

$66.92

180'/day

Cleanouts

0.002

EA

$4.37

allowance

Restoration - Seeding

0.001

AC

$1.75

subcontract

Misc Detail Allowance

10%

LS

$77.77

road maint & repair, testing, detection tape, etc

Page 3 of 11


-------
TABLE D-2a

Detailed Unit Cost Estimates for Water Collection, Conveyance, and Management TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009
Direct Capital

TCD Code

Description

Quantity

Unit

Unit Cost

Comments

C15c

French Drain, 20' bgs

1

LF

$949.24

10' deep avg depth, valve vault @1000'



Clear, Grub & Dispose

0.001

AC

$0.65





Excavate Trench

3

CY

$12.42





Bed & Zone

0.3

CY

$16.01

1/2 mile one way average



Locally Obtained Backfill Material

2

CY

$38.47

allow for material loading & preparation



Imported Backfill - Drain Rock Material (Cobble)

1

CY

$15.89





Haul & Dispose at Repository

3

CY

$16.27

assume all wasted, 5 mile, use HAUL-2 cost



Repository Cost

3

CY

$52.44

use C8a cost



Filter Fabric Wrap

26

SF

$30.54





Trench Shoring - 25' avg depth

40

SF

$567.55

Solid shoring



Dewatering: Two Sump Pmps

0.2

HR

$4.09

24 hr operation plus redundantt pump, pump to PS drain & to CTP



Temporary Pipeline to PS Drain & Removal

1

LF

$41.82

allow for 8" above grade HDPE pipe & appurtenances



Pipe, 18" HDPE, SDR 26 - Perforated

1

LF

$66.92

180'/day



Cleanouts

0.002

EA

$4.37

allowance



Restoration - Seeding

0.001

AC

$1.75

subcontract



Misc Detail Allowance

10%

LS

$80.05

road maint & repair, testing, detection tape, etc

C15d

French Drain, 25' bgs

1

LF

$1,210.16

25' deep avg depth, valve vault @1000'



Clear, Grub & Dispose

0.001

AC

$0.65





Excavate Trench

4

CY

$16.14





Bed & Zone

0.4

CY

$17.14

1/2 mile one way average



Locally Obtained Backfill Material

3

CY

$50.67

allow for material loading & preparation



Imported Backfill - Drain Rock Material (Cobble)

1

CY

$20.93





Haul & Dispose at Repository

4

CY

$21.15

assume all wasted, 5 mile, use HAUL-2 cost



Repository Cost

4

CY

$68.18

use C8a cost



Filter Fabric Wrap

29

SF

$34.06





Trench Shoring - 25' avg depth

52

SF

$737.81

Solid shoring



Dewatering: Two Sump Pmps

0.2

HR

$5.32

24 hr operation plus redundantt pump, pump to PS drain & to CTP



Temporary Pipeline to PS Drain & Removal

1

LF

$41.82

allow for 8" above grade HDPE pipe & appurtenances



Pipe, 24" HDPE, SDR 26 - Perforated

1

LF

$88.27

150'/day,



Cleanouts

0.002

EA

$4.37

allowance



Restoration - Seeding

0.001

AC

$1.75

subcontract



Misc Detail Allowance

10%

LS

$101.89

road maint & repair, testing, detection tape, etc

C17a

Extraction Well - 20' deep

1

EA

$65,722.66

6" dia, 20' deep, sst screen 15', sch 80 pvc casing
Quote plus mark-up



Well Drilling and Development - Subcontract

1

EA

$4,729.56



Pumps - Subcontracted

1

EA

$3,547.17

allow



Discharge Piping











Pipe at Pump











Pipe-2" SDR 11 HDPE

30

LF

$251.52





Bend- 90 deg

2

EA

$214.11





Check Valve

1

EA

$463.97





Globe Valve

1

EA

$617.68





Gate Valve

1

EA

$411.94





Insulation Allowance

1

LS

$17,276.03





Clear & Grub Disposal Site

0.15

AC

$127.00



Page 4 of 11


-------
TABLE D-2a

Detailed Unit Cost Estimates for Water Collection, Conveyance, and Management TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site







2009









Direct Capital



TCD Code Description

Quantity

Unit

Unit Cost

Comments

Pipe-6" SDR 21 HDPE

200

LF

$7,080.05



Tee - Reducing

1

EA

$628.55



Bend- 45 deg - allow

2.0

EA

$1,322.85



Excavate Trench

89

CY

$372.53



Bed & Zone

36

CY

$1,728.58



Native Backfill

52

CY

$517.10



Haul Waste Material

37

CY

$203.70

within 5 mile radius, clean material

Restoration - Seeding

0.15

AC

$339.58

subcontract

Electrical Service & Controls Allowance

50%

LS

$19,915.96

allow

Misc Detail Allowance

10%

LS

$5,974.79

road maint & repair, testing, detection tape, etc

C17b Extraction Well - 40' deep

1

EA

$68,649.07

6" dia, 40' deep, sst screen 15', sch 80 pvc casing
Quote plus mark-up

Well Drilling and Development - Subcontract

1

EA

$6,503.15

Pumps - Subcontracted

1

EA

$3,547.17

allow

Discharge Piping









Pipe at Pump









Pipe-2" SDR 11 HDPE

30

LF

$251.52



Bend- 90 deg

2

EA

$214.11



Check Valve

1

EA

$463.97



Globe Valve

1

EA

$617.68



Gate Valve

1

EA

$411.94



Insulation Allowance

1

LS

$17,276.03



Clear & Grub Disposal Site

0.15

AC

$127.00



Pipe -6" SDR 21 HDPE

200

LF

$7,080.05



Tee - Reducing

1

EA

$628.55



Bend- 45 deg - allow

2.0

EA

$1,322.85



Excavate Trench

89

CY

$372.53



Bed & Zone

36

CY

$1,728.58



Native Backfill

52

CY

$517.10



Haul Waste Material

37

CY

$203.70

within 5 mile radius, clean material

Restoration - Seeding

0.15

AC

$339.58

subcontract

Electrical Service & Controls Allowance

50%

LS

$20,802.75

allow

Misc Detail Allowance

10%

LS

$6,240.82

road maint & repair, testing, detection tape, etc

C17c Extraction Well - 50'deep

1

EA

$72,876.48

6" dia, 50' deep, sst screen 15', sch 80 pvc casing
Quote plus mark-up

Well Drilling and Development - Subcontract

1

EA

$8,276.73

Pumps - Subcontracted

1

EA

$5,911.95

allow

Discharge Piping









Pipe at Pump









Pipe-2" SDR 11 HDPE

30

LF

$251.52



Bend- 90 deg

2

EA

$214.11



Check Valve

1

EA

$463.97



Globe Valve

1

EA

$617.68



Gate Valve

1

EA

$411.94



Insulation Allowance

1

LS

$17,276.03



Clear & Grub Disposal Site

0.15

AC

$127.00



Page 5 of 11


-------
TABLE D-2a

Detailed Unit Cost Estimates for Water Collection, Conveyance, and Management TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site







2009









Direct Capital



TCD Code Description

Quantity

Unit

Unit Cost

Comments

Pipe-6" SDR 21 HDPE

200

LF

$5,738.51



Tee - Reducing

1

EA

$527.94



Bend- 45 deg - allow

2.0

EA

$1,188.69



Excavate Trench

89

CY

$372.53



Bed & Zone

36

CY

$1,728.58



Native Backfill

52

CY

$517.10



Haul Waste Material

37

CY

$203.70

within 5 mile radius, clean material

Restoration - Seeding

0.15

AC

$339.58

subcontract

Electrical Service & Controls Allowance

50%

LS

$22,083.78

allow

Misc Detail Allowance

10%

LS

$6,625.13

road maint & repair, testing, detection tape, etc

C17d Extraction Well - 50'deep

1

EA

$80,354.73

10" dia, 55' deep, sst screen 15', sch 80 pvc casing (Note while this was
developed for 55' foot deep well it is being applied in a 50' deep scenario as the
values are similar)

Well Drilling and Development - Subcontract

1

EA

$11,232.71

Quote plus mark-up

Pumps - Subcontracted

1

EA

$5,911.95

allow

Discharge Piping









Pipe at Pump









Pipe-2" SDR 11 HDPE

30

LF

$251.52



Bend- 90 deg

2

EA

$214.11



Check Valve

1

EA

$463.97



Globe Valve

1

EA

$617.68



Gate Valve

1

EA

$411.94



Insulation Allowance

1

LS

$17,276.03



Clear & Grub Disposal Site

0.15

AC

$127.00



Pipe -6" SDR 21 HDPE

200

LF

$7,080.05



Tee - Reducing

1

EA

$628.55



Bend- 45 deg - allow

2.0

EA

$1,322.85



Excavate Trench

89

CY

$372.53



Bed & Zone

36

CY

$1,728.58



Native Backfill

52

CY

$517.10



Haul Waste Material

37

CY

$203.70

within 5 mile radius, clean material

Restoration - Seeding

0.15

AC

$339.58

subcontract

Electrical Service & Controls Allowance

50%

LS

$24,349.92

allow

Misc Detail Allowance

10%

LS

$7,304.98

road maint & repair, testing, detection tape, etc

C17e Extraction Well - 70' deep

1

EA

$83,281.15

10" dia, 70' deep, sst screen 15', sch 80 pvc casing
interp from above

Well Drilling and Development - Subcontract

1

EA

$13,006.29

Pumps - Subcontracted

1

EA

$5,911.95

allow

Discharge Piping









Pipe at Pump









Pipe-2" SDR 11 HDPE

30

LF

$251.52



Bend- 90 deg

2

EA

$214.11



Check Valve

1

EA

$463.97



Globe Valve

1

EA

$617.68



Gate Valve

1

EA

$411.94



Page 6 of 11


-------
TABLE D-2a

Detailed Unit Cost Estimates for Water Collection, Conveyance, and Management TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009
Direct Capital

TCD Code

Description

Quantity

Unit

Unit Cost

Comments



Insulation Allowance

1

LS

$17,276.03





Clear & Grub Disposal Site

0.15

AC

$127.00





Pipe-6" SDR 21 HDPE

200

LF

$7,080.05





Tee - Reducing

1

EA

$628.55





Bend- 45 deg - allow

2.0

EA

$1,322.85





Excavate Trench

89

CY

$372.53





Bed & Zone

36

CY

$1,728.58





Native Backfill

52

CY

$517.10





Haul Waste Material

37

CY

$203.70

within 5 mile radius, clean material



Restoration - Seeding

0.15

AC

$339.58

subcontract



Electrical Service & Controls Allowance

50%

LS

$25,236.71

allow



Misc Detail Allowance

10%

LS

$7,571.01

road maint & repair, testing, detection tape, etc

C18

SFCDR Diversion

1

EA

$881,812.79





Cofferdam Both Sides of Cutoff Wall Excavation

300

LF

$270,000.00





Pump Intake Structure

2

EA

$50,000.00

allowance



Diversion Pump

4

EA

$243,748.27

2 active, 2 standby



30" HDPE Pipe

200

LF

$24,126.93

asm SDR 17



Misc Detail Allowance

50%

LS

$293,937.60

TESC, maintenance, etc

C19

I-90 Crossing

1

EA

$276,096.45





Remove Pavement

433

SY

$9,080.37

sawct, remove, dispose



Night Work Premium

1

LS

$52,000.00

assume 10%



Production Loss Adjustment

1

LS

$104,000.00

130LF, % of cutoff wall cost



Replace Pavement, Striping, etc

433

SY

$21,666.67

assume concrete/ACP



Traffic Control

1

LS

$52,000.00





Misc Detail Allowance

20%

LS

$37,349.41

road maint & repair, lights, plates, patch, etc

C20

Check Dam

1

EA

$47,897.66

assume pyramid 10ft base and 5 ft tall



Prepare Location for Check Dam Structure

1

LS

$14,601.84

potential shoring & bracing replacements, etc



Prep & Clean Surfaces for Mix

1

LS

$5,840.73

remove dirt & debris



Controlled Density Fill (CDF)

11

CY

$2,251.85

allow for special mix in small quantity, transport, 1:1 slope



Transport, Setup, Prep Operation

1

LS

$9,000.00

RSM 07/21/29.10, assume $3000/day & 3 days for bulkhead



Setup & Install CDF

11

CY

$8,220.29

assume hand mix at site



Misc Detail Allowance

20%

LS

$7,982.94

lighting, ventilation, etc

PIPE-1

Gravity Pipeline - 6"

1

LF

$58.74





Clear & Grub

3.6

SY

$0.84





Excavation

0.43

CY

$20.99





Bed & Zone

0.14

CY

$43.31





Native Backfill

0.28

CY

$11.59





Waste

0.15

CY

$6.86





HDPE Pipe

1

LF

$24.12

assume SDR 26 HDPE, 400'/day



Restoration

3.6

SY

$0.68

road gravel/seeding



Misc Work

1

LS

$9.79

fittings, valves, testing, startup

Page 7 of 11


-------
TABLE D-2a

Detailed Unit Cost Estimates for Water Collection, Conveyance, and Management TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009
Direct Capital

TCD Code

Description

Quantity

Unit

Unit Cost

Comments

PIPE-2

Gravity Pipeline -12"

1

LF

$86.16





Clear & Grub

3.8

SY

$0.84





Excavation

0.59

CY

$20.99





Bed & Zone

0.23

CY

$43.31





Native Backfill

0.33

CY

$11.59





Waste

0.26

CY

$6.86





HDPE Pipe

1

LF

$38.07

assume SDR 26 HDPE, 350'/day



Restoration

3.8

SY

$0.68

road gravel/seeding



Misc Work

1

LS

$14.36

fittings, valves, testing, startup

PIPE-3

Gravity Pipeline - 24"

1

LF

$138.85





Clear & Grub

4.2

SY

$0.84





Excavation

1

CY

$20.99





Bed & Zone

0.38

CY

$43.31





Native Backfill

0.5

CY

$11.59





Waste

0.5

CY

$6.86





HDPE Pipe

1

LF

$62.65

assume SDR 26 HDPE, 300'/day



Restoration

4.2

SY

$0.68

road gravel/seeding



Misc Work

1

LS

$23.14

fittings, valves, testing, startup

PIPE-4

Gravity Pipeline - 36"

1

LF

$180.00

Assume 6/10ths rule based on PIPE-3

PRESSURE-PIPE-1

Pressurized Pipeline - 3"

1

LF

$44.06

3' cover



Clear, Grub & Dispose

0.001

AC

$2.96





Excavate Trench

0.52

CY

$2.17





Bed & Zone

0.16

CY

$7.77





Native Backfill

0.36

CY

$3.56





Haul Waste Material

0.16

CY

$0.89

within 5 mile radius, clean material



Trench Safety

1.00

LF

$5.00

trench box



Dewatering: Two Sump Pmps

0.00

HR

$0.00

NA



Pipe, 3" HDPE, SDR 17

1.00

LF

$15.80

500'/day



Restoration - Seeding

0.0009

AC

$1.98

subcontract



Misc Detail Allowance

10%

LS

$3.92

fittings, valves, location detection, etc

PRESSURE-PIPE-2

Pressurized Pipeline - 6"

1

LF

$82.03

single pipe, 30' deep avg depth, valve vault @1000'



Clear, Grub & Dispose

0.001

AC

$2.54





Excavate Trench

0.444

CY

$1.86





Bed & Zone

0.178

CY

$8.64





Native Backfill

0.259

CY

$2.59





Haul Waste Material

0.185

CY

$1.02

within 5 mile radius, clean material



Trench Safety

1.000

LF

$5.00

trench box



Dewatering: Two Sump Pmps

0.027

HR

$0.32

24 hr operaton x 4 for in stream



Pipe, 6" HDPE, SDR 17

1.000

LF

$34.07

300'/day



Pipe, 6" Tee Assembly

0.001

EA

$1.31





Pipe, 6" Flange Adapter

0.001

EA

$1.64





Pipe, 6" Valve w/ Stem/Box

0.001

EA

$7.12





Pipe, 8" Cap

0.001

EA

$0.53



Page 8 of 11


-------
TABLE D-2a

Detailed Unit Cost Estimates for Water Collection, Conveyance, and Management TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009
Direct Capital

TCD Code

Description

Quantity

Unit

Unit Cost

Comments



Valve Vault Structure

0.001

EA

$6.33





Restoration - Seeding

0.001

AC

$1.70

subcontract



Misc Detail Allowance

10%

LS

$7.37

road maint & repair, testing, detection tape, etc

PRESSURE-PIPE-2

Pressurized Pipeline - 8"

1

LF

$86.72

single pipe, 30' deep avg depth, valve vault @1000'



Clear, Grub & Dispose

0.001

AC

$2.55





Excavate Trench

0.463

CY

$1.94





Bed & Zone

0.191

CY

$9.27





Native Backfill

0.260

CY

$2.59





Haul Waste Material

0.204

CY

$1.12

within 5 mile radius, clean material



Trench Safety

1.000

LF

$5.00

trench box



Dewatering: Two Sump Pmps

0.028

HR

$0.33

24 hr operaton x 4 for in stream



Pipe, 8" HDPE, SDR 17

1.000

LF

$36.44

300'/day



Pipe, 8" Tee Assembly

0.001

EA

$1.28





Pipe, 8" Flange Adapter

0.001

EA

$1.73





Pipe, 8" Valve w/ Stem/Box

0.001

EA

$8.06





Pipe, 8" Cap

0.001

EA

$0.59





Valve Vault Structure

0.001

EA

$6.33





Restoration - Seeding

0.001

AC

$1.71

subcontract



Misc Detail Allowance

10%

LS

$7.78

road maint & repair, testing, detection tape, etc

PRESSURE-PIPE-2

Pressurized Pipeline -12"

1

LF

$91.46

single pipe, 30' deep avg depth, valve vault @1000'



Clear, Grub & Dispose

0.001

AC

$2.58





Excavate Trench

0.505

CY

$2.11





Bed & Zone

0.212

CY

$10.28





Native Backfill

0.264

CY

$2.63





Haul Waste Material

0.241

CY

$1.32

within 5 mile radius, clean material



Trench Safety

1.000

LF

$5.00

trench box



Dewatering: Two Sump Pmps

0.030

HR

$0.36

24 hr operaton x 4 for in stream



Pipe, 12" HDPE, SDR 17

1.000

LF

$38.21

300'/day



Pipe, 12" Tee Assembly

0.001

EA

$1.37





Pipe, 12" Flange Adapter

0.001

EA

$1.80





Pipe, 12" Valve w/ Stem/Box

0.001

EA

$8.89





Pipe, 12" Cap

0.001

EA

$0.65





Valve Vault Structure

0.001

EA

$6.33





Restoration - Seeding

0.001

AC

$1.72

subcontract



Misc Detail Allowance

10%

LS

$8.19

road maint & repair, testing, detection tape, etc

PRESSURE-PIPE-2

Pressurized Pipeline -14"

1

LF

$105.48

single pipe, 30' deep avg depth, valve vault @1000'



Clear, Grub & Dispose

0.001

AC

$2.60





Excavate Trench

0.556

CY

$2.33





Bed & Zone

0.234

CY

$11.37





Native Backfill

0.282

CY

$2.81





Haul Waste Material

0.274

CY

$1.51

within 5 mile radius, clean material

Page 9 of 11


-------
TABLE D-2a

Detailed Unit Cost Estimates for Water Collection, Conveyance, and Management TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009
Direct Capital

TCD Code

Description

Quantity

Unit

Unit Cost

Comments



Trench Safety

1.000

LF

$5.00

trench box



Dewatering: Two Sump Pmps

0.033

HR

$0.40

24 hr operaton x 4 for in stream



Pipe, 14" HDPE, SDR 17

1.000

LF

$47.56

250'/day



Pipe, 14" Tee Assembly

0.001

EA

$1.52





Pipe, 14" Flange Adapter

0.001

EA

$1.92





Pipe, 14" Valve w/ Stem/Box

0.001

EA

$10.19





Pipe, 14" Cap

0.001

EA

$0.74





Valve Vault Structure

0.001

EA

$6.33

Seventeen structures assumed



Restoration - Seeding

0.001

AC

$1.74

subcontract



Misc Detail Allowance

10%

LS

$9.45

road maint & repair, testing, detection tape, etc

PRESSURE-PIPE-3

Pressurized Pipeline -18"

1

LF

$176.44

single pipe, 30' deep avg depth, valve vault @1000'



Clear, Grub & Dispose

0.001

AC

$2.66





Excavate Trench

0.667

CY

$2.79





Bed & Zone

0.280

CY

$13.61





Native Backfill

0.321

CY

$3.20





Haul Waste Material

0.346

CY

$1.90

within 5 mile radius, clean material



Trench Safety

1.000

LF

$5.00

trench box



Dewatering: Two Sump Pmps

0.040

HR

$0.92

24 hr operation plus redundantt pump, pump to PS drain & to CTP



Temporary Pipeline to PS Drain & Removal

1.000

LF

$42.57

allow for 8" above grade HDPE pipe & appurtenances



Pipe, 18" HDPE, SDR 17

1.000

LF

$62.47

factored from 20"



Pipe, 18" Tee Assembly

0.001

EA

$1.85

factored from 20"



Pipe, 18" Flange Adapter

0.001

EA

$2.42

factored from 20"



Pipe, 18" Valve w/ Stem/Box

0.001

EA

$12.11

factored from 20"



Pipe, 18" Cap

0.001

EA

$0.97

factored from 20"



Valve Vault Structure

0.001

EA

$6.33

Seventeen structures assumed



Restoration - Seeding

0.001

AC

$1.78

subcontract



Misc Detail Allowance

10%

LS

$15.87

road maint & repair, testing, detection tape, etc

PRESSURE-PIPE-3

Pressurized Pipeline - 21"

1

LF

$183.12

5' cover, valve vault @1000'



Clear, Grub & Dispose

0.001

AC

$2.85





Excavate Trench

1.203

CY

$5.04





Bed & Zone

0.316

CY

$15.35





Native Backfill

0.797

CY

$7.95





Haul Waste Material

0.405

CY

$2.23

within 5 mile radius, clean material



Trench Safety

1.000

LF

$5.00

trench box



Dewatering: Two Sump Pmps

0.072

HR

$1.66

24 hr operation plus redundantt pump, pump to PS drain & to CTP



Temporary Pipeline to PS Drain & Removal

1.000

LF

$42.57

allow for 8" above grade HDPE pipe & appurtenances



Pipe, 21" HDPE, SDR 17

1.000

LF

$58.86

300'/day



Pipe, 21" Tee Assembly

0.001

EA

$1.76





Pipe, 21" Flange Adapter

0.001

EA

$2.10





Pipe, 21" Valve w/ Stem/Box

0.001

EA

$12.21





Pipe, 21" Cap

0.001

EA

$0.86





Valve Vault Structure

0.001

EA

$6.33

Seventeen structures assumed

Page 10 of 11


-------
TABLE D-2a

Detailed Unit Cost Estimates for Water Collection, Conveyance, and Management TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009











Direct Capital



TCD Code

Description

Quantity

Unit

Unit Cost

Comments



Restoration - Seeding

0.001

AC

$1.90

subcontract



Misc Detail Allowance

10%

LS

$16.44

road maint & repair, testing, detection tape, etc

PRESSURE-PIPE-4

Pressurized Pipeline - 3"

1

LF

$154.69





3" HDPE Vertical in Cherry Raise

1

LF

$85.62

SDR 15.5, 80'/day



Supports & Hangers

1

LF

$5.00

asm 1/5', installation above



Pipe Chase Improvements

1

LF

$50.00

allowance to replace rotted timbers, etc



Misc Work

1

LS

$14,062.32

lights, acess, fittings, valves, etc

NOTE: The above costs are presented rounded to three significant figures

NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of -30 percent to
+50 percent (-30/+50%).

NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-magnitude
cost opinion shown has been prepared for guidance in project evaluation from the information available at the
time of preparation. The final costs of the project will depend on actual labor and material costs, actual site
conditions, productivity, competitive market conditions, the final project scope, the final project schedule, and
other variable factors. As a result, the final project costs will vary from those presented above. Because of these
factors, funding needs must be carefully reviewed prior to making specific financial decisions or establishing final
budgets.

Page 11 of 11

Notes:

AC = acre(s)

ACP = asphalt concrete paving
CDF = control density fill
CTP = central treatment plant
CY = cubic yards
EA = each

HDPE = high density polyethylene

HR = hour

LF = linear feet

LS = lump sum

PVC = polyvinyl chloride

SDR = standard dimension ratio

SF = square foot

SST = stainless steel

SY = square yards

TCD = typical conceptual design


-------

-------
TABLE D-2b

Detailed Unit Cost Estimates for Pump Station TCDs

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

TCD Code

Description

Unit

2009
Direct Capital
Unit Cost

O&M %

PUMP-1

Pump Station - 0.14 MGD

EA

$29,300.00

100%

PUMP-2

Pump Station -1.4 MGD

EA

$959,000.00

100%

PUMP-3

Pump Station - 3.9 MGD

EA

$1,025,000.00

100%

PUMP-4

Pump Station - 6.3 MGD

EA

$1,188,000.00

100%

PUMP-5

Pump Station - 6.5 MGD

EA

$1,208,000.00

100%

Notes:

EA = each

MGD = million gallons per day
TCD = typical conceptual design

NOTE: The above costs are presented rounded to three significant figures

NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of-30 percent
to +50 percent (-30/+50%).

NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-
magnitude cost opinion shown has been prepared for guidance in project evaluation from the information
available at the time of preparation. The final costs of the project will depend on actual labor and material
costs, actual site conditions, productivity, competitive market conditions, the final project scope, the final
project schedule, and other variable factors. As a result, the final project costs will vary from those
presented above. Because of these factors, funding needs must be carefully reviewed prior to making
specific financial decisions or establishing final budgets.

Page 1 of 1


-------

-------
TABLE D-3

Detailed Unit Cost Estimates for Water Treatment TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009



TCD







Direct Capital



Code

Description

Quantity

Unit

Unit Cost

Comments

WT01

Centralized High-Denisty Sludge Treatment at CTP







Costs for WT01 are included in Attachment D-1

WT02

Semi-Passive Lime Treatment (Lineraized Cost)



gpm

y = 2613x +

O&M %:









258722

y = (4254.9x + 997357)/(2613x + 258722)

WT02

Semi-Passive Lime Treatment

5

GPM

$233,951





5 Lime Feed System











Clear & Grub

0.50

AC

$2,748

entire area allowance



Lime Feed/Storage System

1

LS

$21,133

quote + frt & markup [Aquafix]



Lime

0.25

Ton

$109

quote + frt & markup [Aquafix] This system holds 500 lbs of lime.



Concrete Pad

6

CY

$3,972

assume 10' sq



Building over Equipment

100

SF

$20,000

3-sided metal shed, foundation, no lighting



500-gallon propane tank for heating

1

LS

$2,200

lump sum estimate by Aquafix



Conveyance Channel

100

LF







Excavation

122

CY

$2,080

assume 100' long, 2'w@ bottom, 3:1 slopes, 3'd



Waste

122

CY

$293

2 trucks, dispose nearby



Riprap

85

CY

$4,255

assume 12" thick



Settling Ponds and Bypass

2

EA







Cut & Fill

1,180

CY

$24,318

assume balance cut & fill, From design spreadsheet: Volume pond =











2612 cf, Liquid depth = 10 ft., Area (avg) = 261 sf



Liner Fill

380

CY

$18,042

6" under & over, prorated quantity



Lining

1,120

SY

$12,661

single 60mil HDPE, prorated quantity



Site Fencing, Gates & Signage

480

LF

$12,000

subcontract



Bird Deterrent

1,120

SY

$5,600

subcontract



6" HDPE Pipeline

230

LF

$15,901

5' cover; This assumes 100 ft of pipe to the ponds, 100 ft. of pipe











between the 2 ponds, and 30 ft of pipe for the bypass. The bypass











was determined to be 150% of the diameter of the two ponds.



6" Knife Gate Valve & Vault

4

EA

$24,727





Effluent and Emergency Channel

310

LF



This assumes a 50' effluent channel and a 260' (100' conveyance, 60'











diameter of ponds, 100' in between ponds - see figure) emergency











channel to protect the ponds.



Excavation

379

CY

$6,449

assume 310' long, 2'w @ bottom, 3:1 slopes, 3'd



Waste

379

CY

$908

2 trucks, dispose nearby



Riprap

264

CY

$13,189

assume 12" thick



Misc Detail Allowance

20%

LS

$38,117

testing, startup, other TESC, etc

Page 1 of 7


-------
TABLE D-3

Detailed Unit Cost Estimates for Water Treatment TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009



TCD







Direct Capital



Code

Description

Quantity

Unit

Unit Cost

Comments

WT02

Semi-Passive Lime Treatment

50

GPM

$428,994



50

Lime Feed System











Clear & Grub

0.50

AC

$2,748

entire area allowance



Lime Feed/Storage System

1

LS

$29,933

quote + frt & markup



Lime

2

Ton

$875

quote + frt & markup; This system holds 2 tons of lime.



Concrete Pad

6

CY

$3,972

assume 10' sq



Building over Equipment

100

SF

$20,000

3-sided metal shed, foundation, no lighting



500-gallon propane tank for heating

1

LS

$2,200

lump sum estimate by Aquafix



Conveyance Channel

100

LF







Excavation

122

CY

$2,080

assume 100' long, 2'w@ bottom, 3:1 slopes, 3'd



Waste

122

CY

$293

2 trucks, dispose nearby



Riprap

85

CY

$4,255

assume 12" thick



Settling Ponds and Bypass

2

EA







Cut & Fill

4,960

CY

$102,220

assume balance cut & fill



Liner Fill

840

CY

$39,882

6" under & over



Lining

2,520

SY

$28,487

single 60mil HDPE



Site Fencing, Gates & Signage

1,120

LF

$28,000

subcontract



Bird Deterrent

2,520

SY

$12,600

subcontract



6" HDPE Pipeline

290

LF

$20,049

5' cover; This assumes 100 ft of pipe to the ponds, 100 ft. of pipe











between the 2 ponds, and 90 ft of pipe for the bypass. The bypass











was determined to be 150% of the diameter of the two ponds.



6" Knife Gate Valve & Vault

4

EA

$24,727





Effluent and Emergency Channel

430

LF



This assumes a 50' effluent channel and a 380' (100' conveyance,











180' diameter of ponds, 100' in between ponds - see figure)











emergency channel to protect the ponds.



Excavation

526

CY

$8,953

assume 380' long, 2'w @ bottom, 3:1 slopes, 3'd



Waste

526

CY

$1,261

2 trucks, dispose nearby



Riprap

366

CY

$18,280

assume 12" thick



Misc Detail Allowance

20%

LS

$70,163

testing, startup, other TESC, etc

WT02

Semi-Passive Lime Treatment

1,000

GPM

$2,869,940



1000

Lime Feed System











Clear & Grub

1.00

AC

$5,496

entire area allowance



Lime Feed/Storage System

1

LS

$117,933

quote + frt & markup



Lime

18

Ton

$7,878

quote + frt & markup

Page 2 of 7


-------
TABLE D-3

Detailed Unit Cost Estimates for Water Treatment TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009



TCD







Direct Capital



Code

Description

Quantity

Unit

Unit Cost

Comments



Concrete Pad

13

CY

$8,938

assume 15' sq



Building over Equipment

100

SF

$20,000

3-sided metal shed, foundation, no lighting



500-gallon propane tank for heating

1

LS

$2,200

lump sum estimate by Aquafix



Conveyance Channel

100

LF







Excavation

122

CY

$2,080

assume 100' long, 2'w@ bottom, 3:1 slopes, 3'd



Waste

122

CY

$293

2 trucks, dispose nearby



Riprap

85

CY

$4,255

assume 12" thick



Settling Ponds and Bypass

2

EA







Cut & Fill

63,000

CY

$1,298,359

assume balance cut &fill; Volume pond = 522,413 cf, Liquid depth =











10 ft., Area (avg) = 52,241 sf



Liner Fill

6,000

CY

$284,871

6" under & over



Lining

17,900

SY

$202,349

single 60mil HDPE



Site Fencing, Gates & Signage

4,320

LF

$108,000

subcontract



Bird Deterrent

17,900

SY

$89,500

subcontract



12" HDPE Pipeline

590

LF

$86,299

5' cover; This assumes 100 ft of pipe to the ponds, 100 ft. of pipe











between the 2 ponds, and 390 ft of pipe for the bypass. The bypass











was determined to be 150% of the diameter of the two ponds.



12" Knife Gate Valve & Vault

4

EA

$43,090

allowance



Bypass System

1

LS

$14,727

pipe, fittings, valves, vaults, etc



Effluent and Emergency Channel

1,030

LF



This assumes a 50' effluent channel and a 980' (100' conveyance,











780' diameter of ponds, 100' in between ponds) emergency channel











to protect the ponds.



Excavation

1,259

CY

$21,428

assume 1030' long, 2'w@ bottom, 3:1 slopes, 3'd



Waste

1,259

CY

$3,017

2 trucks, dispose nearby



Riprap

877

CY

$43,822

assume 12" thick



Misc Detail Allowance

20%

LS

$472,907

testing, startup, other TESC, etc

WT03

Semi-Passive SRB Treatment (Linearized Cost)



gpm

y = 6482.4x +

O&M %:









132414

y = (3012.9x + 526116)/(6482.4x + 132414)

WT03

Semi-Passive SRB Treatment

5

GPM

$164,753





5 SRB Ponds

2

EA







Clear & Grub

0.25

AC

$1,374

entire area allowance



Cut & Fill

264

CY

$5,441

assume balance earthwork;SRB depth = 10 ft, SRB Area = 361 sf



Liner Fill

170

CY

$8,071

6" under & over

Page 3 of 7


-------
TABLE D-3

Detailed Unit Cost Estimates for Water Treatment TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009



TCD







Direct Capital



Code

Description

Quantity

Unit

Unit Cost

Comments



Lining

560

SY

$6,330

60mil HDPE



Stable Waste

203

CY

$7,953

75% of excavation, 0.5TN/CY, quote + markup



Lime

68

CY

$5,479

25% of excavation, 1.25TN/CY, quote + markup, mix in-place



Flow Distribution Piping

2

EA

$7,496

allowance



Passive Aeration Channel

100

LF







Excavation

122

CY

$2,080

assume 100' long, 2'w@ bottom, 3:1 slopes, 3'd



Waste

122

CY

$293

2 trucks, dispose nearby



Riprap

85

CY

$4,255

assume 12" thick



Aerobic Polishing Pond

1

EA







Cut & Fill

60

CY

$1,237

assume balance earthwork



Wetland

1

EA







Cut & Fill

10

CY

$2,748

assume balance earthwork



Wetland Planting

11

SY

$111

cattails, allowance



Other including bypass











Site Fencing, Gates & Signage

600

LF

$15,000

subcontract, assume 1/2 acre



Bird Deterrent

1,200

SY

$6,000

subcontract, assume 1/4 acre



6" HDPE Pipeline

270

LF

$18,666

5' cover; This assumes 100 ft of pipe to the ponds, 100 ft. of pipe











between the 2 ponds, and 70 ft of pipe for the bypass. The bypass











was determined to be 150% of the diameter of the two SRB ponds.



6" Knife Gate Valve & Vault

4

EA

$24,727





Effluent and Emergency Channel

370

LF



assumes a 50' effluent and 320' emergency channel



Excavation

452

CY

$7,698

assume 320' long, 2'w @ bottom, 3:1 slopes, 3'd



Waste

452

CY

$1,084

2 trucks, dispose nearby



Riprap

315

CY

$15,742

assume 12" thick



Misc Detail Allowance

20%

LS

$19,362

testing, startup, other TESC, etc

WT03

Semi-Passive SRB Treatment

50

GPM

$456,608





50 SRB Ponds

2

EA







Clear & Grub

0.50

AC

$2,748

entire area allowance



Cut & Fill

1,970

CY

$40,599

assume balance earthwork



Liner Fill

400

CY

$18,991

6" under & over



Lining

2,200

SY

$24,870

60mil HDPE



Stable Waste

2,006

CY

$78,767

75% of excavation, 0.5TN/CY, quote + markup



Lime

669

CY

$54,264

25% of excavation, 1.25TN/CY, quote + markup, mix in-place



Flow Distribution Piping

2

EA

$7,496

allowance

Page 4 of 7


-------
TABLE D-3

Detailed Unit Cost Estimates for Water Treatment TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009



TCD







Direct Capital



Code

Description

Quantity

Unit

Unit Cost

Comments



Passive Aeration Channel

100

LF







Excavation

122

CY

$2,080

assume 100' long, 2'w@ bottom, 3:1 slopes, 3'd



Waste

122

CY

$293

2 trucks, dispose nearby



Riprap

85

CY

$4,255

assume 12" thick



Aerobic Polishing Pond

1

EA







Cut & Fill

400

CY

$8,244

assume balance earthwork



Wetland

1

EA







Cut & Fill

50

CY

$13,739

assume balance earthwork



Wetland Planting

278

SY

$2,778

cattails, allowance



Other including bypass











Site Fencing, Gates & Signage

800

LF

$20,000

subcontract, assume 1 acre



Bird Deterrent

2,400

SY

$12,000

subcontract, assume 1/2 acre



6" HDPE Pipeline

410

LF

$28,345

5' cover; This assumes 100 ft of pipe to the ponds, 100 ft. of pipe











between the 2 ponds, and 210 ft of pipe for the bypass. The bypass











was determined to be 150% of the diameter of the two SRB ponds,











polishing pond, and wetland.



6" Knife Gate Valve & Vault

4

EA

$24,727





Effluent and Emergency Channel

590

LF



assumes a 50' effluent and a 540' emergency channel



Excavation

721

CY

$12,275

assume 590' long, 2'w @ bottom, 3:1 slopes, 3'd



Waste

721

CY

$1,728

2 trucks, dispose nearby



Riprap

503

CY

$25,102

assume 12" thick



Misc Detail Allowance

20%

LS

$64,091

testing, startup, other TESC, etc

WT03

Semi-Passive SRB Treatment

1,000

GPM

$6,614,763



1000

SRB Ponds

2

EA







Clear & Grub

4.55

AC

$24,980

entire area allowance



Cut & Fill

60,000

CY

$1,236,532

assume balance earthwork



Liner Fill

8,000

CY

$379,828

6" under & over



Lining

22,000

SY

$248,698

60mil HDPE



Stable Waste

40,101

CY

$1,574,990

75% of excavation, 0.5TN/CY, quote + markup



Lime

13,367

CY

$1,085,046

25% of excavation, 1.25TN/CY, quote + markup, mix in-place



Flow Distribution Piping

2

EA

$7,496

allowance



Passive Aeration Channel

100

LF







Excavation

122

CY

$2,080

assume 100' long, 2'w@ bottom, 3:1 slopes, 3'd



Waste

122

CY

$293

2 trucks, dispose nearby



Riprap

85

CY

$4,255

assume 12" thick







Page 5 of 7




-------
TABLE D-3

Detailed Unit Cost Estimates for Water Treatment TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009



TCD







Direct Capital



Code

Description

Quantity

Unit

Unit Cost

Comments



Aerobic Polishing Pond

1

EA







Cut & Fill

10,800

CY

$222,576

assume balance earthwork



Wetland

1

EA







Cut & Fill

600

CY

$164,871

assume balance earthwork



Wetland Planting

1,202

SY

$12,018

cattails, allowance



Other including bypass











Site Fencing, Gates & Signage

2,000

LF

$50,000

subcontract, assume 6 acre



Bird Deterrent

24,000

SY

$120,000

subcontract, assume 5 acre



12" HDPE Pipeline

1,110

LF

$162,359

5' cover; This assumes 100 ft of pipe to the ponds, 100 ft. of pipe











between the 2 ponds, and 910 ft of pipe for the bypass. The bypass











was determined to be 150% of the diameter of the two SRB ponds.



12" Knife Gate Valve & Vault

4

EA

$43,090

allowance



Effluent and Emergency Channel

1,720

LF



assumes a 50' effluent and a 1670' emergency channel



Excavation

2,102

CY

$35,784

assume 1720' long, 2'w@ bottom, 3:1 slopes, 3'd



Waste

2,102

CY

$5,038

2 trucks, dispose nearby



Riprap

1,465

CY

$73,179

assume 12" thick



Misc Detail Allowance

20%

LS

$1,044,542

testing, startup, other TESC, etc

WT04a

Semi-Passive SR-PRB Treatment

11,250

CF

$19,522



10' Deep

Clear & Grub

0.07

AC

$378

150'x20'



Excavation

417

CY

$3,546

100'Lx7.5'Wx15'D;PRB will be 10'deep, 5'of excavation on top



Waste

278

CY

$666

2 trucks, dispose nearby



Stable Waste

208

CY

$5,066

75% of excavation, 0.5TN/CY, quote + markup



Lime

69

CY

$6,931

25% of excavation, 1.25TN/CY, quote + markup, mix in-place



Misc Detail Allowance

15%

LS

$2,488

testing, startup, other TESC, etc





7,500





100'Lx7.5'Wx10'D This accounts for only the PRB. See 'P11" for











entire excavation.

Page 6 of 7


-------
TABLE D-3

Detailed Unit Cost Estimates for Water Treatment TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009



TCD







Direct Capital



Code

Description

Quantity

Unit

Unit Cost

Comments

WT04b

Semi-Passive SR-PRB Treatment

33,750

CF

$117,985



40' Deep

Clear & Grub

0.17

AC

$946

150'x50'



Excavation

1,250

CY

$24,300

100'Lx7.5'Wx45'D; PRB will be 40' deep, 5' of excavation on top



Waste

1,111

CY

$2,663

2 trucks, dispose nearby



Stable Waste

833

CY

$28,574

75% of excavation, 0.5TN/CY, quote + markup



Lime

278

CY

$36,352

25% of excavation, 1.25TN/CY, quote + markup, mix in-place



Misc Detail Allowance

25%
30,000

LS

$23,209

testing, startup, other TESC, safety, dewatering, rockissure etc
100'Lx7.5'Wx40'D This accounts for only the PRB. See 'P11" for
entire excavation.

Notes:

AC = acre(s)

CTP = central treatment plant
CY = cubic yards
EA = each

HDPE = high density polyethylene
LS = lump sum

SRB = sulfate reducing bioreactor

SR-PRB = sulfate reducing permeable reactive barrier

SY = square yards

TESC = temporary erosion and sediment control

NOTE: The above costs are presented rounded to three significant figures
NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal
accuracy of-30 percent to +50 percent (-30/+50%).

NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-
magnitude cost opinion shown has been prepared for guidance in project evaluation from the information
available at the time of preparation. The final costs of the project will depend on actual labor and material
costs, actual site conditions, productivity, competitive market conditions, the final project scope, the final
project schedule, and other variable factors. As a result, the final project costs will vary from those
presented above. Because of these factors, funding needs must be carefully reviewed prior to making
specific financial decisions or establishing final budgets.

Page 7 of 7


-------

-------
TABLE D-4

Detailed Unit Cost Estimates for Human Health TCDs

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Direct

TCD	Capital Unit

Code

Description

Quantity

Unit

Cost

Comments

HH-2

Upland Waste Pile Soil Cover

1

AC

$58,443.08





Regrade Waste Rock

4,840

CY

$5.25

assume 5' deep



Vegetative Cover

1,613

CY

$15.94

based on CIA estimate



Grade Surface Drainage Ditch

400

CY

$3.78

assume 400' & 1cy/LF



Hydroseed

4840

SY

$0.41

Bunker Hill estimates



Miscellaneous

1

LS

$3,823.73



HH-3

Millsite Decontamination

1

EA

$135,800.00



HH-4

Millsite Demolition/Disposal

100

CY

$168.60





Demolish and Dispose in Solid Waste Landfill

75

CY

$67.90





Disposal of Hazardous Waste

25

TN

$407.40





Miscellaneous

1

LS

$1,582.07



Notes:

AC = acre(s)

CIA = central impoundment area

CY = cubic yards

EA = each

LS = lump sum

SY = square yards

TCD = typical conceptual design

NOTE: The above costs are presented rounded to three significant figures

NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of-30 percent to +50 percent (-30/+50%).

NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-magnitude cost opinion shown has
been prepared for guidance in project evaluation from the information available at the time of preparation. The final costs of the project will
depend on actual labor and material costs, actual site conditions, productivity, competitive market conditions, the final project scope, the final
project schedule, and other variable factors. As a result, the final project costs will vary from those presented above. Because of these
factors, funding needs must be carefully reviewed prior to making specific financial decisions or establishing final budgets.

Page 1 of 1


-------

-------
TABLE D-5

Detailed Unit Cost Estimates for Stream and Riparian Cleanup Action TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









2009











Direct Capital



TCD Code

Description

Quantity

Unit

Unit Cost

Comments

CD-1

Current Deflector-Groynes (Spur Dikes, Spurs)

1

EA

$2,005.22

high end of cost range



Rock

3

EA

$135.80





Log

3

EA

$108.64





Installation

1

LS

$1,089.61

assume 2 hours



Misc Work

1

LS

$182.29

stream diversion, eros/sed control, etc

CD-2

Current Deflector-Bank Deflector with Root Wad

1

EA

$1,674.82





Riprap

20

CY

$27.16

allow 20cy



Orientation Log

4

EA

$108.64





Installation

1

LS

$544.80

assume 1 hour



Misc Work

1

LS

$152.26

stream diversion, eros/sed control, etc

CD-3

Current Deflector-Riprap Groynes & Orientation Effect

1

EA

$1,915.59





Riprap

20

CY

$27.16

allow 20cy



Log

1

EA

$108.64





Installation

1

LS

$1,089.61

assume 2 hours



Misc Work

1

LS

$174.14

stream diversion, eros/sed control, etc

CD-4

Current Deflector-Log Weir & Dam Structure

1

EA

$2,806.17





Riprap

10

CY

$27.16

allow 10cy



Streambed Gravel

10

CY

$33.95

allow 10cy



Logs, Posts & Braces

1

LS

$271.60





Filter Cloth

1

LS

$33.95





Installation

1

LS

$1,634.41

assume 3 hours



Misc Work

1

LS

$255.11

stream diversion, eros/sed control, etc

CD-5

Current Deflector-Angled Vortex Rock Weir w/Rootwads

1

EA

$1,915.59





Riprap

20

CY

$27.16

allow 10cy



Rootwad & Anchor

1

EA

$108.64





Installation

1

LS

$1,089.61

assume 2 hours



Misc Work

1

LS

$174.14

stream diversion, eros/sed control, etc

CD-6

Current Deflector-Riprap Turning Rock Wall

1

EA

$2,093.09





Riprap

50

CY

$27.16

allow 50cy



Installation

1

LS

$544.80

assume 1 hour



Misc Work

1

LS

$190.28

stream diversion, eros/sed control, etc

CD-7

Current Deflector-Riprap Tieback

1

EA

$2,035.10





Riprap

20

CY

$27.16

allow 20cy



Log

2

EA

$108.64





Installation

1

LS

$1,089.61

assume 2 hours



Misc Work

1

LS

$185.01

stream diversion, eros/sed control, etc

CD-AVG

Current Deflector, Average Cost

1

EA

$2,063.65

average cost from above

CD-SED

Current Deflectors, Sediment Traps

1

EA

$1,870.00

from 2007 URS Cost Update Memo

Page 1 of 5


-------
TABLE D-5

Detailed Unit Cost Estimates for Stream and Riparian Cleanup Action TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

2009
Direct Capital

TCD Code

Description

Quantity

Unit

Unit Cost

Comments

VBS-1

Brush Mattress w/Rock Toe

1

LF

$52.05





Rock Toe

0.5

CY

$38.06

excavate & place



Wire or Jute Rope & Stakes

10

SF

$1.36





Topsoil

0.2

CY

$16.66

6"th



Fascines

1

LS

$6.79

allowance



Installation

1

LF

$4.59

assume 500'/day



Misc Work

1

LS

$4.73

stream diversion, eros/sed control, etc

VBS-2

Brush Layer

1

LF

$27.69





Wire or Jute Rope & Stakes

10

SF

$1.36





Topsoil

0.1

CY

$16.66





Fascines

1

LS

$6.79

allowance



Installation

1

LF

$4.59

assume 500'/day



Misc Work

1

LS

$1.07

eros/sed control, etc

VBS-3

Live Stake, Live Post & Joint Planted Fascines

1

LF

$76.25





Riprap

1

CY

$27.16





Joint Planted Fascine

2

EA

$2.72





Live Stake

5

EA

$1.36

6"th



Live Post

3

EA

$2.72





Installation

1

LS

$21.79

assume 200'/day



Misc Work

1

LS

$6.93

stream diversion, eros/sed control, etc

VBS-AVG

Vegetative Bank Stabilization, Average Cost

1

LF

$52.00

average cost from above

BSBR-1

Vegetated Geogrid

1

LF

$112.24





Soil Excavation

2

CY

$5.45

assume 2cy/LF



Waste

2

CY

$2.72

dispose on tailings pile



Filter Layer

0.09

CY

$1.36

assume 5' x 6"th



Rock Blanket

0.44

CY

$44.67

quote for Bunker Hill projects, 20cy/hour



Topsoil

1.11

CY

$16.66

assume 6' x 5'th



Coir Geotextile

3

SY

$1.36

assume 3sy/LF



Live Branches

5

EA

$0.68





Live Stakes

5

EA

$1.36





Straw Matting

2

SY

$2.04

assume 2sy/LF



Installation

1

LS

$28.87

assume 150'/day



Misc Work

1

LS

$10.20

stream diversion, eros/sed control, etc

BSBR-2

Live Cribwall

1

LF

$206.54





Soil Excavation

2

CY

$5.45

assume 2cy/LF



Waste

2

CY

$2.72

dispose on tailings pile



Timbers

36

BF

$1.36

assume 6x6 timbers & 36BF/LF



Rock Fill

0.44

CY

$26.32

quote for Bunker Hill projects



Topsoil

1.11

CY

$16.66

assume 6' x 5'th



Anchor

0.01

EA

$67.90

assume 100'oc allow cost



Live Branches

5

EA

$0.68





Drain Rock

1

CY

$44.67

quote for Bunker Hill projects, 20cy/hour

Page 2 of 5


-------
TABLE D-5

Detailed Unit Cost Estimates for Stream and Riparian Cleanup Action TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









2009











Direct Capital



TCD Code

Description

Quantity

Unit

Unit Cost

Comments



Installation

1

LS

$43.58

assume 100'/day



Misc Work

1

LS

$18.78

stream diversion, eros/sed control, etc

BSBR-3

Low Energy Tree Revetment

1

LF

$61.35





Soil Excavation

1

CY

$5.45

assume 1cy/LF



Backfill

1

CY

$5.45

assume excavated material backfill & compact around
logs



Logs

0.20

EA

$108.64

assume 5' spacing, allow cost



Revegetate Bank

1.00

SY

$1.36

1 sy/LF



Installation

1

LS

$21.79

assume 200'/day



Misc Work

1

LS

$5.58

stream diversion, eros/sed control, etc

BSBR-4

Moderate Energy Tree Revetment

1

LF

$104.27





Soil Excavation

2

CY

$5.45

assume 1cy/LF



Waste

1

CY

$2.72

dispose on tailings pile



Backfill

1

CY

$5.45

assume excavated material backfill & compact around
logs



Logs

0.20

EA

$108.64

assume 10' spacing, allow cost for footer, header &
rootwad



5-man Rock

0.07

EA

$135.80

assume 15' spacing, allow cost



Deadman

0.01

EA

$67.90

assume 100' spacing, allow cost



Live Stakes & Posts

10.00

EA

$1.36

assume 10/LF



Revegetate Bank

1.00

SY

$1.36

1 sy/LF



Installation

1

LS

$28.87

assume 150'/day



Misc Work

1

LS

$9.48

stream diversion, eros/sed control, etc

BSBR-5

Tree Deflector

1

LF

$90.48





Soil Excavation

1

CY

$5.45

assume 1cy/LF



Backfill

1

CY

$5.45

assume excavated material backfill & compact around
logs



Trees

0.10

EA

$108.64

assume 10' spacing, allow cost



Connector Cable

1.00

LF

$2.72





Deadman & Cable

0.03

EA

$67.90

assume 40' spacing, allow cost



Rock Anchor & Leash

0.10

EA

$203.70

assume 10' spacing, allow cost



Live Stakes & Posts

10.00

EA

$1.36

assume 10/LF



Installation

1

LS

$21.79

assume 200'/day



Misc Work

1

LS

$8.23

stream diversion, eros/sed control, etc

BSBR-6

Woody Debris & Vegetated Geogrid System

1

LF

$156.70





Soil Excavation

1

CY

$5.45

assume 2cy/LF



Backfill

1

CY

$5.45

assume excavated material backfill & compact around
logs



Logs

0.10

EA

$108.64

assume 10' spacing, allow cost



Rock Filter Layer

0.09

CY

$21.73

assume 5' x 6"th



Riprap

1.00

CY

$27.16

assume 1cy/LF



Rock Anchor & Leash

0.10

EA

$203.70

assume 10' spacing, allow cost

Page 3 of 5


-------
TABLE D-5

Detailed Unit Cost Estimates for Stream and Riparian Cleanup Action TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









2009











Direct Capital



TCD Code

Description

Quantity

Unit

Unit Cost

Comments



5-man Rock

0.07

EA

$135.80

assume 15' spacing, allow cost



Topsoil

1.11

CY

$16.66

assume 6' x 5'th



Coir Geotextile

3

SY

$1.36

assume 3sy/LF



Live Branches

5

EA

$0.68





Live Stakes & Posts

5

EA

$1.36





Installation Cost

1

LS

$28.87

assume 150'/day



Misc Work

1

LS

$14.25

stream diversion, eros/sed control, etc

BSBR-Avg

Bioengineered Revetments, Averaqe Cost

1

LF

$121.93

average cost from above

FP/RP-1a

Floodplain and Riparian Planting

1

SF

$0.54

bank width/LF of river variable



Site Prep

0.01

CY

$2.72

assume 4" deep average grading



Soil Ammendments

0.01

CY

$1.73





Live Planting

0.1

EA

$1.36

assume 1cy/LF



Tree Planting

0.1

EA

$2.72

allow cost



Hydroseeding

0.1

SY

$0.41

Bunker Hill estimates



Misc Work

1

LS

$0.05

stream diversion, eros/sed control, etc

FP/RP-1b

Floodplain Planting

1

SF

$2.14





Soil Excavation

0.01

CY

$5.45

assume trenches 5' apart & 10'long each side, 1cy/LF



Backfill

0.01

CY

$5.45

assume excavated material backfill & compact around
logs



Riprap

0.01

CY

$54.40

assume 1cy/LF



Live Branches

2

EA

$0.70

allow cost



Installation Cost

0.01

LS

$9.19

assume 500'/day



Misc Work

0.01

LS

$0.21

stream diversion, eros/sed control, etc

FP/RP-Avg

Floodplain and Riparian Planting, Average Cost

1

SF

$1.34



OFFCH-1

Groundwater-Fed Side Channel

6,050

SY

$23.76

assume 1/2 hectare as typical size = approx 1.25 acre



Cut & Fill

2,017

CY

$5.45

assume 1' deep over entire area



Stream Gravel

2,017

CY

$39.40

assume 1' deep



Riprap

100

CY

$54.40

allow quantity



LWD etc

50

EA

$135.80

assume 2' spacing, allow cost



Misc Work

1

LS

$41,067.86

stream diversion, eros/sed control, etc

OFFCH2-3

Surface-Fed Side Channel

167

SY

$41.64

assume 15'w, sloped 3h:1v, 5'd



Cut & Fill

56

CY

$5.45

assume 1' deep over entire area



Stream Gravel

56

CY

$39.40

assume 1' deep



Riprap

20

CY

$54.40

assume quantity



LWD etc

10

EA

$135.80

assume quantity



Misc Work

1

LS

$1,982.95

stream diversion, eros/sed control, etc

Page 4 of 5


-------
TABLE D-5

Detailed Unit Cost Estimates for Stream and Riparian Cleanup Action TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

2009
Direct Capital

TCD Code Description

Quantity

Unit

Unit Cost

Comments

OFFCH-3 Off-Channel Pond

556

SY

$62.56

assume 50'w, sloped 3h:1v, 5'd

Soil Excavation

1,204

CY

$5.45

assume 5' deep & slope allowance

Waste

1,204

CY

$6.86



Stream Gravel

185

CY

$39.40

assume 1' deep

LWD etc

20

EA

$135.80

assume quantity

Misc Work

1

LS

$9,930.88



OFFCH-Avg Off-Channel Hydroloqic Features, Average Cost

2,257

SY

$42.65



CH REAL-1 Channel Realignment

100

SY

$42.19



Soil Excavation

133

CY

$5.45

assume 3' deep including slope allowance

Waste

133

CY

$6.86



Stream Gravel

44

CY

$39.40

assume 1' deep

Misc Work

1

LS

$843.75

bank stabilization & restoration

Notes:

BF = board foot
CY = cubic yards
EA = each
LF = linear feet
LS = lump sum
SF = square foot
SY = square yards
TCD = typical conceptual design

NOTE: The above costs are presented rounded to three significant figures

NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of-30 percent to +50 percent (-30/+50%).
NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-magnitude cost opinion shown has
been prepared for guidance in project evaluation from the information available at the time of preparation. The final costs of the project will
depend on actual labor and material costs, actual site conditions, productivity, competitive market conditions, the final project scope, the
final project schedule, and other variable factors. As a result, the final project costs will vary from those presented above. Because of these
factors, funding needs must be carefully reviewed prior to making specific financial decisions or establishing final budgets.

Page 5 of 5


-------

-------
TABLE D-6

Summary of Cost Assumptions and Limitations for Source Control TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

TCD



Assumptions/Limitations

Code

Description

2009 Direct Capital Unit Cost

O&M Costs

C01

Excavation

Assumes excavator (trackhoe),
excavation above water table. Does not
include hauling and dewatering, if
needed.

Assumes complete removal.

C01b

Sediment Excavation

Assumes 60% excavation above water
table, 40% below water table, with
replacement of 25% of excavated
sediment with imported backfill.

Assumes complete removal.

C02a

Regrade/Consolidate/Revegetate

Waste pile on hillside. Assumes average
regrading depth of 5 ft.

Repair of damaged cap components potentially largest
O&M element: assumed 5% of cap area repaired at
ฆyear 2, 2.5% at year 5, and 1 % every 5 years
thereafter. O&M would also include inspections and
ฆmonitoring.

C02b

Regrade/Consolidate/Revegetate

Waste pile in drainage. Assumes
average regrading depth of 13 ft.

C02c

Regrade/Consolidate/Revegetate

For slopes steeper than 1.51-1:1 V. Riprap
used for erosion protection below
nominal 100-year flood elevation.

C03

Low-Permeability Cap

Uses GCL for low permeability layer.
Low-permeability native soil or native soil
amended with bentonite are other
options.



C04

Low-Permeability Cap with Seepage
Collection

Same as C03, with groundwater
collection and diversion trench.



C05 Low-Permeability Cap with Erosion
Protection

C06

C07

Same as C03, with addition of riprap toe.

Waste Consolidation Area with
Erosion Protection

Assumes 25 ft waste thickness.
Assumes GCL and 1 acre cap.

Waste Consolidation Area Above
Flood Level

Cost does include a 1/2 mile haul.
Assumes 25 ft waste thickness.
Assumes GCL and 1 acre cap.

C08a

Repository, 1 million cy

Cost does not include hauling.

Assumes bottom liner and leachate
collection system.

Land acquisition costs are not included.

Includes two 16 hr inspections/year (1 spring and 1
winter) and two storm event inspections/year;
Assumes 2% of capital cost for annual repairs and
maintenance;

Quarterly sampling and analysis

C09

Impoundment Closure

Includes regrading to 31-1:1 V sideslope
and placement of GCL cap.

Repair of damaged cap components potentially largest
O&M element: assumed 5% of cap area repaired at
year 2, 2.5% at year 5, and 1 % every 5 years
thereafter. O&M would also include inspections and
monitoring.

HAUL-2 Haul to Repository

Cost is in units of CY-MI.

No O&M costs.

Notes:

CY = cubic yards
GCL = geosynthetic clay liner
O&M = operation and maintenance
TCD = typical conceptual design

Page 1 of 1


-------

-------
TABLE D-7

Summary of Cost Assumptions and Limitations for Water Collection, Conveyance, and Management TCDs

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Assumptions/Limitations

TCD Code

Description

2009 Direct Capital Unit Cost

O&M Costs

C10

Adit Drainage Collection

Costs for water treatment not
included. Does not incorporate full
adit seal, infiltration control, or
management of water levels inside
mine.

Inspections
and sediment
removal.

C11a

Slurry Wall (no drain) -15 feet deep

Used for hydraulic isolation of stream No O&M costs.

C11b

Slurry Wall (no drain) - 20 feet deep

reaches or discrete facilities. When



C11c

Slurry Wall (no drain) - 30 feet deep

used for stream reaches, cost is per



C11d

Slurry Wall (no drain) - 40 feet deep

linear foot of stream, one side of



C11e

Slurry Wall (no drain) - 45 feet deep

stream. Assumes excavated with



C11f

Slurry Wall (no drain) - 50 feet deep

excavator (track hoe). Assumed no



C11g

Slurry Wall (no drain, soil cement) - 50 feet deep

excavated material reusable as



C11h

Slurry Wall (with drain) -15 feet deep

backfill.

Inspections

C11i

Slurry Wall (with drain) - 20 feet deep



and drain

C11 j

Slurry Wall (with drain) - 30 feet deep



cleanout.

C14a

Stream Lining -10 feet wide

Assumes average bottom width of

Routine

C14b

Stream Lining - 20 feet wide

channel over entire length of

inspection and

C14c

Stream Lining -100 feet wide

application.

maintenance.

C15a

French Drain -10 feet deep

Water treatment not included in drain Inspections

C15b

French Drain -15 feet deep

cost.

and drain

C15c

French Drain - 20 feet deep



cleanout.

C15d

French Drain - 25 feet deep





C17a

Extraction Well - 20 feet deep (6" wide)

Costs do not include effluent piping.

Inspection,

C17b

Extraction Well - 40 feet deep (6" wide)



maintenance.

C17c

Extraction Well - 50 feet deep (6" wide)



Replacement

C17d

Extraction Well - 50 feet deep (10" wide)



of pumps.

C17e

Extraction Well - 70 feet deep (10" wide)





C18

SFCDR Diversion

Includes coffer dam on both sides of
cutoff wall.

No O&M costs.

C19

I-90 Crossing

Assumes 130' cutoff wall beneath
I-90.

No O&M costs.

C20

Check Dam

Dam height and material dependent
upon water flowrate and chemistry.

No O&M costs.

PIPE-1

Gravity Pipeline - 6"

All pipelines trenched and buried. No Assumed 2%

PIPE-2

Gravity Pipeline -12"

unusual geographic, soils, or

replacement

PIPE-3

Gravity Pipeline - 24"

groundwater conditions. Land

every 5 years.

PIPE-4

Gravity Pipeline - 36"

acquisition costs not included.



PRESSURE-PI PE-1

Pressurized Pipeline - < 6" diameter

All pipelines trenched and buried. No Assumed 2%

PRESSURE-PI PE-2

Pressurized Pipeline - < 6"-14" diameter

unusual geographic, soils, or

replacement

PRESSURE-PI PE-3

Pressurized Pipeline - >14" diameter

groundwater conditions. Land

every 5 years.

PRESSURE-PI PE-4

Pressurized Pipeline - 3" diameter

acquisition costs not included.



PUMP-1

Pump Station - 0.14 MGD

Costs developed using CPES

Inspection,

PUMP-2

Pump Station -1.4 MGD

assuming maximum flow.

maintenance.

PUMP-3

Pump Station - 3.9 MGD



Replacement

PUMP-4

Pump Station - 6.3 MGD



of pumps.

PUMP-5

Pump Station - 6.5 MGD





Notes:

MGD = million gallons per day
O&M = operation and maintenance
TCD = typical conceptual design

Page 1 of 1


-------

-------
TABLE D-8

Summary of Cost Assumptions and Limitations for Water Treatment TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

Assu mptions/Li mitations

TCD Code

Description

2009 Direct Capital Unit Cost

O&M Costs

WT02	Onsite Semi-Passive Water Treatment

Using Lime Addition and Settling Pond(s)

Includes a Lime feed system,	Includes cleaning of ponds (with a 50% liner

conveyance channel, 2 settling ponds replacement) at years 10 and 20.
with bypass functionality, and an effluent Includes lime replacement based on usage
and emergency channel	determined by design criteria.

Includes monitoring 4 times/year
Includes miscellaneous O&M at 8% of direct
capital cost

WT03	Onsite Semi-Passive Water Treatment

Using SRB System

Includes 2 SRB ponds, a passive
aeration channel, an aerobic polishing
pond, a wetland, and an effluent and
emergency channel

Includes media replacement every 15 years
Includes monitoring 4 times/year
Includes miscellaneous O&M at 4% of direct
capital cost

WT04a In Situ Onsite Semi-Passive Groundwater
Treatment Using SR-PRB

Includes a 10 ft. deep PRB with 5 feet
excavation on top of that. Therefore the
total excavation is 15 ft bgs.

Includes media replacement every 15 years
Includes monitoring 4 times/year
Includes miscellaneous O&M at a lump sum
of $3500/year

WT04b In Situ Onsite Semi-Passive Groundwater
Treatment Using SR-PRB

Includes a 40 ft. deep PRB with 5 feet
excavation on top of that. Therefore the
total excavation is 45 ft bgs.

Includes media replacement every 15 years
Includes monitoring 4 times/year
Includes miscellaneous O&M at a lump sum
of $10,000/year

Notes:

O&M = operation and maintenance
SRB = sulfate reducing bioreactor
PRB = permeable reactive barrier
TCD = typical conceptual design

Page 1 of 1


-------

-------
TABLE D-9

Summary of Cost Assumptions and Limitations for Human Health TCDs

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site





Assumptions/Limitations

TCD Code

Description

2009 Direct Capital Unit Cost

O&M Costs

HH-2

Upland Waste Pile Soil Cover

Assumed depth of regrading = 5 ft.

Routine inspection and
maintenance.

HH-3

Millsite Decontamination

Removal and offsite disposal of
hazardous substances,
decontamination of building
surfaces.

Routine inspection and
maintenance.

HH-4

Millsite Demolition/Disposal

Assume 25% of material to
hazardous waste landfill; 75% to
solid waste landfill or disposed of
onsite.

Routine inspection and
maintenance.

Notes:

O&M = operation and maintenance
TCD = typical conceptual design

Page 1 of 1


-------

-------
TABLE D-10

Summary of Cost Assumptions and Limitations for Stream and Riparian Cleanup Action TCDs

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

TCD Code

Description

2009 Direct Capital Unit Cost

Assumptions/Limitations

O&M Costs

CD-AVG

CD-SED

Current Deflector, Average Cost

Placement requires use of heavy
machinery, riprap toe protection. Site
access may also be a significant cost
consideration in some cases. However,
most streams in the project are
paralleled by roads on one or both sides,
minimizing access difficulties.

Current Deflectors, Sediment Traps

Detailed cost breakdown unavailable.

Assumes periodic (annual) inspection for
evidence of outflanking or undermining.
Repair or redesign and replacement may
be required if damaged by high flow
events or channel migration.

VBS-AVG Vegetative Bank Stabilization, Average Cost	Site preparation with heavy machinery All plantings are vulnerable to high

and toe protection with riprap, live	stream flows and desiccation until roots

facines, or other material required.	are established. Frequent monitoring

Banks may be stabilized with live cuttings may be required initially until the root
or rooted stock, rooted stock being mass is established, followed by
generally more expensive.	seasonal and then annual monitoring.

Protection from browsing animals,
irrigation, and some replanting may be
required.

BSBR-AVG Bioengineered Revetments, Average Cost	Assumes site preparation and toe	Requires annual monitoring for evidence

protection with heavy machinery.	of undermining or outflanking at head.

Placement of rocks, crib, logs, and other Repair or additional reinforcement may
large heavy materials also require heavy be required to prevent structure failure,
machinery.	Occasional repair or redesign and

replacement of some areas may be
required if large scale failure occurs.

FP/RP-AVG Floodplain/Riparian Planting, Average Cost

Assumes areas subject to regular
overbank flows during high flow events
require use of heavy machinery to create
trenches for protection of live plantings.
Areas less subject to overbank flow will
not require heavy machinery and may
follow the "dig and drop" approach to
planting.

Live plantings are vulnerable to
desiccation, overbank flows, and
browsing animals. Protection from
browsing animals and irrigation may be
required initially. Assumes regular
monitoring will be conducted until root
mass is established, and seasonal
monitoring thereafter, with site
preparation and replanting conducted as
required.

OFFCH-AVG Off-Channel Hydrologic Feature, Average Cost

Off-channel hydrologic features will be
sited in areas where excavation of
contaminants is planned. Unit cost
estimates do not include site excavation

O&M rates for off-channel hydrologic
features can vary considerably. Properly
constructed groundwater fed features will
require minimal maintenance, whereas

requirements assumed to be represented surface water fed features may require
by the costs of contaminant removal, but an active O&M plan to maintain
do include "cut and fill" costs using heavy connectivity to the mainstem, hydrologic

machinery for additional site preparation
as needed.

performance, and ensuring fish access
and other habitat considerations as
desired. Accordingly, monitoring
requirements will vary with the type of
feature.

CH REAL-1

Channel Realignment

Channel realignment may be required as Assuming proper design and

part of an integrated approach to
streambank and substrate stabilization.
This approach assumes use of heavy
machinery and possibly temporary flow
diversion.

implementation, channel realignment is
directed towards creating a self-
maintaining structural change requiring
minimal O&M. However, realignment
failure and subsequent channel migration
can result in failure of bank stabilization
and other remedial measures, requiring
extensive replacement.

Notes:

O&M = operation and maintenance
TCD = typical conceptual design

Page 1 of 1


-------

-------
TABLE D-11

Alternative RP-1 - Pinehurst Cost Analysis

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Calculation of Expected Annual Damage7

30-Year Life Cycle Cost	

Average

Storm Damage for Expected
Event Probability of Estimated Frequency Frequency Annual
(Years)	Occurrence Damage2	Interval	Interval	Damage

50	2.00% $11,127,000

2.00% $8,958,000 $179,200

25	4.00% $6,788,000

16.00% $5,166,000 $826,600

5	20.00% $3,544,000

Total	$1,005,800

Real Discount Rate	7%

Target Number of Years for Remedy Protection	30

^resent^/alue_of_Exฃected^nnual_Damac(e_Over30^ear_ฃenod^^_^^^12J480J000

Notes:

1	Calculation of expected annual damage based on method described in Memorandum: Methodology for Estimating Expected Loss from
Damage to Remedies (CH2M HILL, September 16, 2009).

2	Estimated damage values are from Appendix G in this Focused Feasibility Study Report. Based on modeling results and remediation
costs of $5.17 per square foot.

Page 1 of 1


-------

-------
TABLE D-12

Alternative RP-1: Smelterville Cost Analysis

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Calculation of Expected Annual Damage1

30-Year Life Cycle Cost

Average

Storm Damage for Expected
Event Probability of Estimated Frequency Frequency Annual
(Years)	Occurrence	Damage2	Interval	Interval	Damage

50	2.00%	$6,468,000

2.00%	$4,887,000	$97,700

25	4.00%	$3,306,000

16.00%	$2,071,000	$331,400

5	20.00%	$835,000

Total	$429,100

Real Discount Rate	7%

Target Number of Years for Remedy Protection	30

Present Value of Expected Annual Damage Over 30-year period	$5,320,000

Notes:

1	Calculation of expected annual damage based on method described in Memorandum: Methodology for Estimating Expected Loss
from Damage to Remedies (CH2M HILL, September 16, 2009).

2	Estimated damage values are from Appendix G in this Focused Feasibility Study Report. Based on modeling results and
remediation costs of $5.17 per square foot.

Page 1 of 1


-------

-------
TABLE D-13

Alternative RP-1: Kellogg Cost Analysis

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Calculation of Expected Annual Damage1

30-Year Life Cycle Cost

Storm
Event
(Years)

50

25

Probability of
Occurrence

2.00%
4.00%
20.00%

Estimated
Damage2

Frequency
Interval

Average
Damage for
Frequency
Interval

$867,000
$745,000
$474,000

2.00%
16.00%

$806,000
$610,000

Expected
Annual
Damage

$16,100
$97,600

Total

$113,700

Real Discount Rate

Target Number of Years for Remedy Protection

Present Value of Expected Annual Damage Over 30-year period

7%

30

$1,410,000

Notes:

1	Calculation of expected annual damage based on method described in Memorandum: Methodology for Estimating Expected
Loss from Damage to Remedies (CH2M HILL, September 16, 2009).

2	Estimated damage values are from Appendix G in this Focused Feasibility Study Report. Based on modeling results and
remediation costs of $5.17 per square foot.

Page 1 of 1


-------

-------
TABLE D-14

Alternative RP-1: Wardner Cost Analysis

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site
Calculation of Expected Annual Damage1

30-Year Life Cycle Cost	

Average

Storm Damage for Expected
Event Probability of Estimated Frequency Frequency Annual
(Years)	Occurrence	Damage2	Interval	Interval	Damage

50	2.00%	$696,000

2.00%	$696,000	$13,900

25	4.00%	$696,000

16.00%	$696,000	$111,400

5	20.00%	$696,000

Total	$125,300

Real Discount Rate	7%

Target Number of Years for Remedy Protection	30

Present Value of Expected Annual Damage Over 30-year period	$1,550,000

Notes:

1	Calculation of expected annual damage based on method described in Memorandum: Methodology for Estimating Expected
Loss from Damage to Remedies (CH2M HILL, September 16, 2009).

2	Estimated damage values are from Appendix G in this Focused Feasibility Study Report. Based on modeling results and
remediation costs of $5.17 per square foot.

Page 1 of 1


-------

-------
TABLE D-15

Alternative RP-1: Osburn Cost Analysis

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site
Calculation of Expected Annual Damage1

30-Year Life Cycle Cost	

Average

Storm Damage for Expected
Event Probability of Estimated Frequency Frequency Annual
(Years)	Occurrence	Damage2	Interval	Interval	Damage

50	2.00%	$4,440,000

2.00%	$4,032,000	$80,600

25	4.00%	$3,623,000

16.00%	$2,473,000	$395,700

5	20.00%	$1,322,000

Total	$476,300

Real Discount Rate	7%

Target Number of Years for Remedy Protection	30

Present Value of Expected Annual Damage Over 30-year period	$5,910,000

Notes:

1	Calculation of expected annual damage based on method described in Memorandum: Methodology for Estimating Expected Loss
from Damage to Remedies (CH2M HILL, September 16, 2009).

2	Estimated damage values are from Appendix G in this Focused Feasibility Study Report. Based on modeling results and
remediation costs of $5.17 per square foot.

Page 1 of 1


-------

-------
TABLE D-16

Alternative RP-1: Silverton Cost Analysis

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site
Calculation of Expected Annual Damage1

30-Year Life Cycle Cost	

Average

Storm	Damage for	Expected

Event	Probability of Estimated Frequency Frequency	Annual

(Years)	Occurrence	Damage2	Interval	Interval	Damage

50	2.00%	$3,192,000

2.00%	$2,401,000	$48,000

25	4.00%	$1,610,000

16.00%	$1,282,000	$205,100

5	20.00%	$954,000

Total	$253,100

Real Discount Rate	7%

Target Number of Years for Remedy Protection	30

Present Value of Expected Annual Damage Over 30-year period	$3,140,000

Notes:

1	Calculation of expected annual damage based on method described in Memorandum: Methodology for Estimating Expected Loss
from Damage to Remedies (CH2M HILL, September 16, 2009).

2	Estimated damage values are from Appendix G in this Focused Feasibility Study Report. Based on modeling results and
remediation costs of $5.17 per square foot.

Page 1 of 1


-------

-------
TABLE D-17

Alternative RP-1: Wallace Cost Analysis

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site
Calculation of Expected Annual Damage1

30-Year Life Cycle Cost	

Average

Storm Damage for Expected
Event Probability of Estimated Frequency Frequency Annual
(Years)	Occurrence	Damage2	Interval	Interval	Damage

50	2.00%	$534,000

2.00%	$392,000	$7,800

25	4.00%	$249,000

16.00%	$169,000	$27,000

5	20.00%	$88,000

Total	$34,800

Real Discount Rate	7%

Target Number of Years for Remedy Protection	30

Present Value of Expected Annual Damage Over 30-year period	$430,000

Notes:

1	Calculation of expected annual damage based on method described in Memorandum: Methodology for Estimating Expected
Loss from Damage to Remedies (CH2M HILL, September 16, 2009).

2	Estimated damage values are from Appendix G in this Focused Feasibility Study Report. Based on modeling results and
remediation costs of $5.17 per square foot.

Page 1 of 1


-------

-------
TABLE D-18

Alternative RP-1: Mullan Cost Analysis

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site
Calculation of Expected Annual Damage1

30-Year Life Cycle Cost	

Average

Storm Damage for Expected
Event Probability of Estimated Frequency Frequency Annual
(Years)	Occurrence	Damage2	Interval	Interval	Damage

50	2.00%	$2,889,000

2.00%	$2,477,000	$49,500

25	4.00%	$2,065,000

16.00%	$1,457,000	$233,100

5	20.00%	$848,000

Total	$282,600

Real Discount Rate	7%

Target Number of Years for Remedy Protection	30

Present Value of Expected Annual Damage Over 30-year period	$3,510,000

Notes:

1	Calculation of expected annual damage based on method described in Memorandum: Methodology for Estimating Expected
Loss from Damage to Remedies (CH2M HILL, September 16, 2009).

2	Estimated damage values are from Appendix G in this Focused Feasibility Study Report. Based on modeling results and
remediation costs of $5.17 per square foot.

Page 1 of 1


-------

-------
TABLE D-19

Alternative RP-1: Approximate Cost for Side Gulches

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

Total Area of Existing Selected Remedies in Side Gulches1
Unit Cost to Re-remediate (or Repair) Selected Remedies2 $
Estimated Area of Remedy at Risk for 5-, 25-, and 50-year Storm Events

11,320,000 SF
5.17 per SF

Estimated Estimated Area
Percent of of Remedy at Estimated Cost to
Storm Event Remedy at Risk3 Risk4 Re-Remediate5
(Years)	(%)	(SF)	($)

50
25
5

25%	2,830,000 $ 14,600,000

16%	1,810,000 $ 9,400,000

7%	790,000 $ 4,080,000

Calculation of Expected Annual Damage
30-Year Life Cycle Cost	

Average Damage

Storm Event Probability of Estimated Frequency for Frequency Expected Annual
(Years)	Occurrence7	Damage8	Interval9	Interval	Damage

50
25
5

2.00%
4.00%
20.00%

14,600,000
9,400,000
4,080,000

2.00%
16.00%

$12,000,000	$240,000

$6,700,000	$1,070,000

Total

$1,310,000

Real Discount Rate

Target Number of Years for Remedy Protection

Present Value of Expected Annual Damage Over 30-year period

7%
30

$16,300,000

TOTAL APPROXIMATE COST (30-year NPV) for Side Gulches

$16,300,000

Notes:

SF = square feet
NPV = net present value

1	Total area of existing Selected Remedies in side gulches calculated by GIS analysis as documented in
Side Gulch Costing Memorandum (TerraGraphics, 2010).

2	This cost was developed by TerraGraphics and is documented in Appendix G of the FFS Report.

3	The estimated percent of remedy at risk is based on the average remedy at risk for the eight
communities where hydrologic and hydraulic modeling analyses were conducted. This is documented in
Table 9-3 in the FFS Report.

4	The estimated area of remedy at risk multiplies the estimated percent of remedy at risk by the total
existing remedy in the side gulches.

5	The estimated cost to re-remediate multiplies the estimated area of remedy at risk by the unit costs to re-
remediate (or repair) Selected Remedies

6	Calculation of expected annual damage based on method described in Methodology for Estimating Expected Loss
from Damage to Remedies Memorandum (CH2M HILL, 2009).

7	Probability of occurrence calculated based on the percent chance that the storm event will happen in any given
year. For example in a single year, there is a 2% probability of experiencing the damage from a 50-year storm event.

Estimated damage values are from modeling outputs and unit cost assumptions discussed in Section 9.6.1.1 and
documented in Appendix G of the FFS Report.

9 The frequency interval is the difference between the probability of occurrence for two storm events.

Page 1 of 1


-------

-------
TABLE D-20

Alternative RP-2: Pinehurst Cost Summary

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009 Total









2009 Direct

2009 Total

Direct and









Capital Unit

Direct Capital

Indirect Capital



Description

Quantity

Unit

Cost

Cost

Cost

Little Pine Creek











1

Channel Modification-Increase Left Bank Height To 4 ft With A 1 ft Tall Berm (XS 1)

165

LF

$110

$18,150

$30,855

2

Reconstruct Existing Earthen Channel To 10' X 3' Channel W/ 3' Vert Concrete Wall Along

80

LF

$340

$27,200

$46,240



Left Side Of Channel (XS 2)











3

Reconstruct Existing Earthen Channel To 12' X 3' (L) X61 (R) Concrete Channel (XS 3A)

50

LF

$928

$46,400

$78,880

4

Reconstruct Existing Earthen Channel To 12' X 3' (L) X61 (R) Concrete Channel (XS 3B)

100

LF

$933

$93,300

$158,610

5

Reconstruct Existing Earthen Channel To 12' X 3.5' (L) X 4' (R) Concrete Channel (XS 4)

125

LF

$780

$97,500

$165,750

6

Reconstruct Existing Earthen Channel To 12' X3' (L) Concrete Channel (XS 6A)

105

LF

$697

$73,185

$124,415

7

Reconstruct Existing Earthen Channel To 12' X3' (L) Concrete Channel (XS 6B)

105

LF

$697

$73,185

$124,415

8

Reconstruct Existing Earthen Channel To 12' X3' (L) Concrete Channel (XS 6C)

180

LF

$711

$127,980

$217,566

9

Channel Modification-Increase Left Bank Height To 3 ft With A 1.4 ft Tall Berm (XS 10)

330

LF

$37

$12,210

$20,757

10

Reconstruct Existing Channel By Widening To 28'X18'X2.5' Earthen Channel W/ 0.8 ft Tall

270

LF

$56

$15,120

$25,704



Berm On Right And Left Bank (XS 11)











11

Channel Modifications-Construct 0.5 ft Tall Berm On Left Bank And Increase Channel

170

LF

$22

$3,740

$6,358



Bottom By 0.1 ft To Account For Slope Alterations (XS 13)











12

Channel Modifications-Construct 0.5 ft Tall Berm On Left Bank And Decrease Channel

120

LF

$28

$3,360

$5,712



Bottom By 0.5 ft To Account For Slope Alterations (XS 14)











13

Channel Modifications-Decrease Channel Depth By 0.7 ft To Account For Slope

55

LF

$28

$1,540

$2,618



Alterations (XS 15)











14

Reconstruct Existing Channel To 25.2'X11'X3.1' (L) X4' (R) Earthen Channel And

55

LF

$65

$3,575

$6,078



Decrease Channel Depth By 0.7 ft To Account For Slope Alterations (XS 16)











15

Replace Existing Wood Driveway Bridge With 14'X26' Single Span Bridge W/ A Clear

1

EA

$169,000

$169,000

$287,300



Height Of 2.5 ft (Bridge 1, Xs 5)











16

Replace Existing Steel Driveway Bridge With 14'X15" Single Span Bridge W/ A Clear

1

EA

$103,000

$103,000

$175,100



Height Of 2.5 ft (Bridge 2, Xs 7)











17

Replace Existing Wood Driveway Bridge With 14'X18' Single Span Bridge W/ A Clear

1

EA

$118,000

$118,000

$200,600



Height Of 2.5 ft (Bridge 3, Xs 8)











18

Replace Existing Driveway Bridge With 14'X16' Single Span Bridge W/ A Clear Height Of

1

EA

$110,000

$110,000

$187,000



2.5 ft (Bridge 4, Xs 9)











19

Replace Existing Concrete Box Culvert (3'X8'X28') With 18'X28' Single Span Bridge W/ A

1

EA

$224,000

$224,000

$380,800



Clear Height Of 3 ft (Bridge 5, Xs 12)











20

Replace Existing Wood Bridge (12'X4') With 14'X4' Single Span Bridge W/ A Clear Height

1

EA

$34,000

$34,000

$57,800



Of 3.6 ft (Bridge 6)



















Subtotal Rounded

$2,300,000

NPV for 30-year O&M Cost
Total NPV cost at 30 years

$844,000
$3,144,000

Notes:

NPV = Net Present Value
EA = each
LF = linear feet

O&M = operation and maintenance
Assumptions:

All excavated material is hauled to repository and replaced with imported material.
Pipe cover is 3' over pipe

All work will be performed in the summer and therefore no water issues exist.

See estimate details for additional assumptions

Total indirect cost assumes 70% of Total Direct Capital Cost

Page 1 of 1


-------

-------
TABLE D-21

Alternative RP-2: Pinehurst Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

	Description	Quantity Unit Capital Unit Cost	Cost	Comments

Little Pine Creek

Increase Left Bank Height to 4 ft w/1 ft Berm (1)

165

LF





see detail

Prep Channel Bank

165

LF

$86.03

$14,194

difficult operation, assume 10 dys

Imported Fill Material

34.8

CY

$62.91

$2,191

imported, difficult operation

Misc Detail Allowance

10%

LS

$0.00

$1,639

access.TESC, restoration, etc

Sales Tax on Materials

5%





$29





Total Direct Unit Cost



$110.00

$18,053



Reconstruct Existing Channel to 10' wide/ 3' Wall (2)

80

LF







Clear, Grub & Dispose

0.1

AC

$6,514.75

$479



Diversion/Care of Water

0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0



Excavate Channel

26.7

CY

$14.80

$395



Prep & Grade Channel

80

LF

$7.84

$627



Haul & Dispose at Repository

26.7

CY

$5.49

$146

assume all but rock is wasted, 5 mile 1

Repository Cost

26.7

CY

$11.38

$303

use C08a cost

Imported Fill Material

17.8

CY

$53.33

$948

imported, difficult operation

CIP Wall, 12" thk, 3' tall + 1 foot below grade

11.9

CY

$737.64

$8,742



Wall Rebar @ 200 #/cy

2370.4

LB

$1.79

$4,231



CIP Wall Footing, 2.5 wide x 1.5' tall

11.1

CY

$496.76

$5,520



Footing Rebar @ 150 #/cy

1666.7

LB

$1.79

$2,975



Misc Detail Allowance

10%

LS

$0.00

$2,392

access.TESC, restoration, etc

Sales Tax on Materials

5%





$375



Total Direct Unit Cost





$340.00

$27,134



Reconstruct Channel w/ 3' L wall, 6' R wall, 12' Channel (3A)

50

LF





Clear, Grub & Dispose

0.0

AC

$6,514.75

$299

Diversion/Care of Water

0

LF

$10.00

$0

Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0

Demo existing RR Tie and Debris

50

LF

$62.74

$3,137

Excavate Channel

55.6

CY

$14.80

$822

Prep & Grade Channel

50

LF

$7.84

$392

Haul & Dispose at Repository

55.6

CY

$5.49

$305

Repository Cost

55.6

CY

$11.38

$632

Imported Fill Material

20.4

CY

$53.33

$1,086

CIP Wall, 12" thk, 3' tall

5.6

CY

$737.64

$4,098

Wall Rebar @ 200 #/cy

1111.1

LB

$1.79

$1,983

CIP Wall, 12" thk, 6' tall

11.1

CY

$737.64

$8,196

assume all but rock is wasted, 5 mile 1 way

use C08a cost

imported, difficult operation

Page 1 of 10


-------
TABLE D-21

Alternative RP-2: Pinehurst Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site













2009 Total















2009 Direct

Direct Capital







Description



Quantity

Unit

Capital Unit Cost

Cost

Comments





Wall Rebar @ 200 #/cy



2222.2

LB

$1.79

$3,967







CIPSlab, 12" thk, 16' wide



30

CY

$295.88

$8,767







Footing Rebar @ 150 #/cy



4,444

LB

$1.79

$7,934







Misc Detail Allowance



10%

LS

$0.00

$4,068

access.TESC, restoration, etc





Sales Tax on Materials



5%





$682









Total Direct Unit Cost





$928.00

$46,369





4

Reconstruct Channel w/ 3' L wall, 6' R wall, 12' Channel (3B)

100

LF











Clear, Grub & Dispose



0.1

AC

$6,514.75

$598







Diversion/Care of Water



0

LF

$10.00

$0







Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0







Demo existing RR Tie and Debris



100

LF

$62.74

$6,274







Excavate Channel



127.8

CY

$14.80

$1,891







Prep & Grade Channel



100

LF

$7.84

$784







Haul & Dispose at Repository



127.8

CY

$5.49

$702

assume all but rock is wasted, 5 mile 1

way



Repository Cost



127.8

CY

$11.38

$1,454

use C08a cost





Imported Fill Material



40.7

CY

$53.33

$2,173

imported, difficult operation





CIP Wall, 12" thk, 3' tall



11.1

CY

$737.64

$8,196







Wall Rebar @ 200 #/cy



2222.2

LB

$1.79

$3,967







CIP Wall, 12" thk, 6' tall



22.2

CY

$737.64

$16,392







Wall Rebar @ 200 #/cy



4444.4

LB

$1.79

$7,934







CIPSlab, 12" thk, 16' wide



59

CY

$295.88

$17,534







Footing Rebar @ 150 #/cy



8,889

LB

$1.79

$15,868







Misc Detail Allowance



10%

LS

$0.00

$8,161

access.TESC, restoration, etc





Sales Tax on Materials



5%





$1,364









Total Direct Unit Cost





$933.00

$93,290





5

Reconstruct Channel w/ 3.5' L wall, 4' R wall, 12' Channel (4)

125

LF











Clear, Grub & Dispose



0.1

AC

$6,514.75

$748







Diversion/Care of Water



0

LF

$10.00

$0







Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0







Excavate Channel



125.0

CY

$14.80

$1,850







Prep & Grade Channel



125

LF

$7.84

$980







Haul & Dispose at Repository



125.0

CY

$5.49

$686

assume all but rock is wasted, 5 mile 1

way



Repository Cost



125.0

CY

$11.38

$1,423

use C08a cost





Imported Fill Material



34.7

CY

$53.33

$1,852

imported, difficult operation





CIP Wall, 12" thk, 3.5' tall



16.2

CY

$737.64

$11,953







Wall Rebar @ 200 #/cy



3240.7

LB

$1.79

$5,785





Page 2 of 10


-------
TABLE D-21

Alternative RP-2: Pinehurst Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site











2009 Total











2009 Direct

Direct Capital



Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

CIP Wall, 12" thk, 4' tall



18.5

CY

$737.64

$13,660



Wall Rebar @ 200 #/cy



3703.7

LB

$1.79

$6,611



CIP Slab, 12" thk, 16' wide



74

CY

$295.88

$21,917



Footing Rebar @ 150 #/cy



11,111

LB

$1.79

$19,834



Misc Detail Allowance



10%

LS

$0.00

$8,519

access.TESC, restoration, etc

Sales Tax on Materials



5%





$1,565





Total Direct Unit Cost





$780.00

$97,383



6 Reconstruct Channel w/ 3' L & R wall, 12' Channel (6A)

105

LF







Clear, Grub & Dispose



0.1

AC

$6,514.75

$628



Diversion/Care of Water



0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0



Excavate Channel



68.4

CY

$14.80

$1,013



Prep & Grade Channel



105

LF

$7.84

$823



Haul & Dispose at Repository



68.4

CY

$5.49

$376

assume all but rock is wasted, 5 mile 1 way

Repository Cost



68.4

CY

$11.38

$779

use C08a cost

Imported Fill Material



23.3

CY

$53.33

$1,244

imported, difficult operation

CIP Wall, 12" thk, 3' tall



11.7

CY

$737.64

$8,606



Wall Rebar @ 200 #/cy



2333.3

LB

$1.79

$4,165



CIP Wall, 12" thk, 3' tall



11.7

CY

$737.64

$8,606



Wall Rebar @ 200 #/cy



2333.3

LB

$1.79

$4,165



CIP Slab, 12" thk, 16' wide



62

CY

$295.88

$18,410



Footing Rebar @ 150 #/cy



9,333

LB

$1.79

$16,661



Misc Detail Allowance



10%

LS

$0.00

$6,432

access.TESC, restoration, etc

Sales Tax on Materials



5%





$1,204





Total Direct Unit Cost





$697.00

$73,113



Reconstruct Channel w/ 3' L & R wall, 12' Channel (6B)

105

LF







Clear, Grub & Dispose

0.1

AC

$6,514.75

$628



Diversion/Care of Water

0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0



Excavate Channel

70.0

CY

$14.80

$1,036



Prep & Grade Channel

105

LF

$7.84

$823



Haul & Dispose at Repository

70.0

CY

$5.49

$384

assume all but rock is wasted, 5 mile 1

Repository Cost

70.0

CY

$11.38

$797

use C08a cost

Imported Fill Material

23.3

CY

$53.33

$1,244

imported, difficult operation

CIP Wall, 12" thk, 3' tall

11.7

CY

$737.64

$8,606



Wall Rebar @ 200 #/cy

2333.3

LB

$1.79

$4,165



Page 3 of 10


-------
TABLE D-21

Alternative RP-2: Pinehurst Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site











2009 Total













2009 Direct

Direct Capital





Description



Quantity

Unit

Capital Unit Cost

Cost

Comments



CIP Wall, 12" thk, 3' tall



11.7

CY

$737.64

$8,606





Wall Rebar @ 200 #/cy



2333.3

LB

$1.79

$4,165





CIP Slab, 12" thk, 16' wide



62

CY

$295.88

$18,410





Footing Rebar @ 150 #/cy



9,333

LB

$1.79

$16,661





Misc Detail Allowance



10%

LS

$0.00

$6,435

access.TESC, restoration, etc



Sales Tax on Materials



5%





$1,204







Total Direct Unit Cost





$697.00

$73,165





8 Reconstruct Channel w/ 3' L & R wall, 12' Channel (6C)

180

LF









Clear, Grub & Dispose



0.2

AC

$6,514.75

$1,077





Diversion/Care of Water



0

LF

$10.00

$0





Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0





Excavate Channel



53.3

CY

$14.80

$789





Prep & Grade Channel



180

LF

$7.84

$1,412





Haul & Dispose at Repository



53.3

CY

$5.49

$293

assume all but rock is wasted, 5 mile 1

way

Repository Cost



53.3

CY

$11.38

$607

use C08a cost



Imported Fill Material



120.0

CY

$53.33

$6,399

imported, difficult operation



CIP Wall, 12" thk, 3' tall



20.0

CY

$737.64

$14,753





Wall Rebar @ 200 #/cy



4000.0

LB

$1.79

$7,140





CIP Wall, 12" thk, 3' tall



20.0

CY

$737.64

$14,753





Wall Rebar @ 200 #/cy



4000.0

LB

$1.79

$7,140





CIP Slab, 12" thk, 16' wide



107

CY

$295.88

$31,561





Footing Rebar @ 150 #/cy



16,000

LB

$1.79

$28,562





Misc Detail Allowance



10%

LS

$0.00

$11,359

access.TESC, restoration, etc



Sales Tax on Materials



5%





$2,130







Total Direct Unit Cost





$711.00

$127,974





9 Increase L Bank to 3' with 1.4' Berm (10)



330

LF









Clear, Grub & Dispose



0.3

AC

$6,514.75

$1,974





Diversion/Care of Water



0

LF

$10.00

$0





Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0





Excavate Channel



58.7

CY

$14.80

$868





Prep & Grade Channel



330

LF

$7.84

$2,588





Haul & Dispose at Repository



58.7

CY

$5.49

$322

assume all but rock is wasted, 5 mile 1

way

Repository Cost



58.7

CY

$11.38

$668

use C8a cost



Imported Fill Material



85.6

CY

$53.33

$4,563

imported, difficult operation



Misc Detail Allowance



10%

LS

$0.00

$999

access.TESC, restoration, etc



Page 4 of 10


-------
TABLE D-21

Alternative RP-2: Pinehurst Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site













2009 Total















2009 Direct

Direct Capital







Description



Quantity

Unit

Capital Unit Cost

Cost

Comments





Sales Tax on Materials



5%





$71









Total Direct Unit Cost





$37.00

$12,052





10

Increase Channel Height to 2.5' and 18' wide (11)



270

LF











Clear, Grub & Dispose



0.2

AC

$6,514.75

$1,615







Diversion/Care of Water



0

LF

$10.00

$0







Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0







Excavate Channel



229.5

CY

$14.80

$3,396







Prep & Grade Channel



270

LF

$7.84

$2,117







Haul & Dispose at Repository



229.5

CY

$5.49

$1,260

assume all but rock is wasted, 5 mile 1

way



Repository Cost



229.5

CY

$11.38

$2,612

use C08a cost





Imported Fill Material



52.8

CY

$53.33

$2,816

imported, difficult operation





Misc Detail Allowance



10%

LS

$0.00

$994

access.TESC, restoration, etc





Sales Tax on Materials



5%





$44









Total Direct Unit Cost





$56.00

$14,854





11

Construct 6" Berm on Left Bank, Increase Bottom 0.1' (13)

170

LF











Clear, Grub & Dispose



0.2

AC

$6,514.75

$1,017







Diversion/Care of Water



0

LF

$10.00

$0







Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0







Excavate Channel



0.0

CY

$14.80

$0







Prep & Grade Channel



170

LF

$7.84

$1,333







Haul & Dispose at Repository



0.0

CY

$5.49

$0

assume all but rock is wasted, 5 mile 1

way



Repository Cost



0.0

CY

$11.38

$0

use C08a cost





Imported Fill Material



18.6

CY

$53.33

$994

imported, difficult operation





Misc Detail Allowance



10%

LS

$0.00

$334

access.TESC, restoration, etc





Sales Tax on Materials



5%





$15









Total Direct Unit Cost





$22.00

$3,694





12

Construct 6" Berm on Left Bank, Lower Bottom 0.5' (14)

120

LF











Clear, Grub & Dispose



0.1

AC

$6,514.75

$718







Diversion/Care of Water



0

LF

$10.00

$0







Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0







Excavate Channel



31.1

CY

$14.80

$460







Prep & Grade Channel



120

LF

$7.84

$941







Haul & Dispose at Repository



31.1

CY

$5.49

$171

assume all but rock is wasted, 5 mile 1

way



Repository Cost



31.1

CY

$11.38

$354

use C08a cost



Page 5 of 10


-------
TABLE D-21

Alternative RP-2: Pinehurst Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site











2009 Total











2009 Direct

Direct Capital





Description

Quantity

Unit

Capital Unit Cost

Cost

Comments



Imported Fill Material

6.7

CY

$53.33

$356

imported, difficult operation



Misc Detail Allowance

10%

LS

$0.00

$247

access.TESC, restoration, etc



Sales Tax on Materials

5%





$6





Total Direct Unit Cost





$28.00

$3,253



13

Lower Channel Bottom By 0.7' (15)

55

LF









Clear, Grub & Dispose

0.1

AC

$6,514.75

$329





Diversion/Care of Water

0

LF

$10.00

$0





Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0





Excavate Channel

20.0

CY

$14.80

$295





Prep & Grade Channel

55

LF

$7.84

$431





Haul & Dispose at Repository

20.0

CY

$5.49

$110

assume all but rock is wasted, 5 mile 1 way



Repository Cost

20.0

CY

$11.38

$227

use C08a cost



Imported Fill Material

0.0

CY

$53.33

$0

imported, difficult operation



Misc Detail Allowance

10%

LS

$0.00

$106

access.TESC, restoration, etc



Sales Tax on Materials

5%





$0





Total Direct Unit Cost





$28.00

$1,498



14

Reconstruct Channel: 25.2'x11,x3.1,(L)x4,(R), Lower Bottom 0.7'

55

LF









Clear, Grub & Dispose

0.1

AC

$6,514.75

$329





Diversion/Care of Water

0

LF

$10.00

$0





Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0





Excavate Channel

81.1

CY

$14.80

$1,200





Prep & Grade Channel

55

LF

$7.84

$431





Haul & Dispose at Repository

81.1

CY

$5.49

$445

assume all but rock is wasted, 5 mile 1 way



Repository Cost

81.1

CY

$11.38

$923

use C08a cost



Imported Fill Material

0.0

CY

$53.33

$0

imported, difficult operation



Misc Detail Allowance

10%

LS

$0.00

$196

access.TESC, restoration, etc



Sales Tax on Materials

5%





$0





Total Direct Unit Cost





$65.00

$3,525



15

Replace Existing Bridge w/ New 14'x26' Span Bridge

1

EA





3' cover, done in summer, no dewatering needed,













keep one lane open



Sawcut & Remove Pavement

77.8

SY

$12.55

$976





Remove & Dispose Existing Wooden Bridge, 14'x26'

364

SF

$30.00

$10,920





Excavate Trench

0.0

CY

$7.84

$0

account for pipe removal & loading, less pipe

Page 6 of 10


-------
TABLE D-21

Alternative RP-2: Pinehurst Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009 Total









2009 Direct

Direct Capital



Description

Quantity

Unit

Capital Unit Cost

Cost

Comments

Bed & Zone

0.0

CY

$46.86

$0

1/2 mile one way average

Imported Backfill

0.0

CY

$9.94

$0

assume all wasted to repository

Haul & Dispose at Repository

0.0

CY

$5.49

$0

assume all but rock is wasted, 5 mile 1 way

Repository Cost

0.0

CY

$11.38

$0

use C08a cost

Trench Safety

0

LF

$5.00

$0

trench box

CIP Wall, 12" thk, 2.5' tall

2.4

CY

$737.64

$1,776



Wall Rebar @ 200 #/cy

481.5

LB

$1.79

$859



CIP Wall, 12" thk, 2.5' tall

2.4

CY

$737.64

$1,776



Wall Rebar @ 200 #/cy

481.5

LB

$1.79

$859



CIP Slab, 12" thk, 16' wide

15

CY

$295.88

$4,559



Footing Rebar @ 150 #/cy

2,311

LB

$1.79

$4,126



New Bridge & Abutments - Steel

364

SF

$300.00

$109,200

based on road & bridge file

Misc Detail Allowance

20%

LS

$0.00

$27,010

minor traffic control, TESC, etc

SUBTOTAL







$162,061



Total Direct Unit Cost





$169,000.00

$168,914



16 Replace Existing Bridge w/ New 14'x15' Span Bridge

1

EA





3' cover, done in summer, no dewatering needed,











keep one lane open

Sawcut & Remove Pavement

77.8

SY

$12.55

$976



Remove & Dispose Existing Steel Bridge, 14'x15'

210

SF

$50.00

$10,500



Excavate Trench

0.0

CY

$7.84

$0

account for pipe removal & loading, less pipe

Bed & Zone

0.0

CY

$46.86

$0

1/2 mile one way average

Imported Backfill

0.0

CY

$9.94

$0

assume all wasted to repository

Haul & Dispose at Repository

0.0

CY

$5.49

$0

assume all but rock is wasted, 5 mile 1 way

Repository Cost

0.0

CY

$11.38

$0

use C08a cost

Trench Safety

0

LF

$5.00

$0

trench box

CIP Wall, 12" thk, 2.5' tall

1.4

CY

$737.64

$1,025



Wall Rebar @ 200 #/cy

277.8

LB

$1.79

$496



CIP Wall, 12" thk, 2.5' tall

1.4

CY

$737.64

$1,025



Wall Rebar @ 200 #/cy

277.8

LB

$1.79

$496



CIP Slab, 12" thk, 16' wide

9

CY

$295.88

$2,630



Footing Rebar @ 150 #/cy

1,333

LB

$1.79

$2,380



New Bridge & Abutments - Steel

210

SF

$300.00

$63,000

based on road & bridge file

Misc Detail Allowance

20%

LS

$0.00

$16,505

minor traffic control, TESC, etc

Sales Tax on Materials

5%





$3,954



Total Direct Unit Cost





$103,000.00

$102,986



Page 7 of 10


-------
TABLE D-21

Alternative RP-2: Pinehurst Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009 Total









2009 Direct

Direct Capital



Description

Quantity

Unit

Capital Unit Cost

Cost

Comments

17 Replace Existing Bridge w/ New 14'x18' Span Bridge

1

EA





3' cover, done in summer, no dewatering needed,











keep one lane open

Sawcut & Remove Pavement

77.8

SY

$12.55

$976



Remove & Dispose Existing Wooden Bridge, 14'x 18'

252

SF

$30.00

$7,560



Excavate Trench

0.0

CY

$7.84

$0

account for pipe removal & loading, less pipe

Bed & Zone

0.0

CY

$46.86

$0

1/2 mile one way average

Imported Backfill

0.0

CY

$9.94

$0

assume all wasted to repository

Haul & Dispose at Repository

0.0

CY

$5.49

$0

assume all but rock is wasted, 5 mile 1 way

Repository Cost

0.0

CY

$11.38

$0

use C08a cost

Trench Safety

0

LF

$5.00

$0

trench box

CIP Wall, 12" thk, 2.5' tall

1.7

CY

$737.64

$1,229



Wall Rebar @ 200 #/cy

333.3

LB

$1.79

$595



CIP Wall, 12" thk, 2.5' tall

1.7

CY

$737.64

$1,229



Wall Rebar @ 200 #/cy

333.3

LB

$1.79

$595



CIP Slab, 12" thk, 16' wide

11

CY

$295.88

$3,156



Footing Rebar @ 150 #/cy

1,600

LB

$1.79

$2,856



New Bridge & Abutments - Steel

252

SF

$300.00

$75,600

based on road & bridge file

Misc Detail Allowance

20%

LS

$0.00

$18,759

minor traffic control, TESC, etc

Sales Tax on Materials

5%





$4,744



Total Direct Unit Cost





$118,000.00

$117,301



18 Replace Existing Bridge w/ New 14'x16' Span Bridge

1

EA





3' cover, done in summer, no dewatering needed,











keep one lane open

Sawcut & Remove Pavement

77.8

SY

$12.55

$976



Remove & Dispose Existing Wooden Bridge, 14'x 18'

224

SF

$50.00

$11,200



Excavate Trench

0.0

CY

$7.84

$0

account for pipe removal & loading, less pipe

Bed & Zone

0.0

CY

$46.86

$0

1/2 mile one way average

Imported Backfill

0.0

CY

$9.94

$0

assume all wasted to repository

Haul & Dispose at Repository

0.0

CY

$5.49

$0

assume all but rock is wasted, 5 mile 1 way

Repository Cost

0.0

CY

$11.38

$0

use C08a cost

Trench Safety

0

LF

$5.00

$0

trench box

CIP Wall, 12" thk, 2.5' tall

1.5

CY

$737.64

$1,093



Wall Rebar @ 200 #/cy

296.3

LB

$1.79

$529



CIP Wall, 12" thk, 2.5' tall

1.5

CY

$737.64

$1,093



Wall Rebar @ 200 #/cy

296.3

LB

$1.79

$529



CIP Slab, 12" thk, 16' wide

9

CY

$295.88

$2,805



Footing Rebar @ 150 #/cy

1,422

LB

$1.79

$2,539



New Bridge & Abutments - Steel

224

SF

$300.00

$67,200

based on road & bridge file

Page 8 of 10


-------
TABLE D-21

Alternative RP-2: Pinehurst Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009 Total









2009 Direct

Direct Capital



Description

Quantity

Unit

Capital Unit Cost

Cost

Comments

Misc Detail Allowance

20%

LS

$0.00

$17,593

minor traffic control, TESC, etc

Sales Tax on Materials

5%





$4,217



Total Direct Unit Cost





$110,000.00

$109,773



19 Replace Existing Culvert w/ New 18'x28' Span Bridge

1

EA





3' cover, done in summer, no dewatering needed,











keep one lane open

Sawcut & Remove Pavement

77.8

SY

$12.55

$976



Remove & Dispose Exist Culvert, 8'x28'

224

SF

$50.00

$11,200



Excavate Trench

8.3

CY

$7.84

$65

account for pipe removal & loading, less pipe

Bed & Zone

0.0

CY

$46.86

$0

1/2 mile one way average

Imported Backfill

20.7

CY

$9.94

$206

assume all wasted to repository

Haul & Dispose at Repository

8.3

CY

$5.49

$46

assume all but rock is wasted, 5 mile 1 way

Repository Cost

8.3

CY

$11.38

$94

use C08a cost

Trench Safety

0

LF

$5.00

$0

trench box

CIP Wall, 12" thk, 3.0'tall +1 bury

4.1

CY

$737.64

$3,060



Wall Rebar @ 200 #/cy

829.6

LB

$1.79

$1,481



CIP Wall, 12" thk, 3.0'tall +1 bury

4.1

CY

$737.64

$3,060



Wall Rebar @ 200 #/cy

829.6

LB

$1.79

$1,481



CIP Wall Footing, 2.5 wide x 1.5' tall

7.8

CY

$496.76

$3,864



Footing Rebar @ 150 #/cy

1166.7

LB

$1.79

$2,083



New Bridge & Abutments - Steel

504

SF

$300.00

$151,200

based on road & bridge file

Misc Detail Allowance

20%

LS

$0.00

$35,735

minor traffic control, TESC, etc

Sales Tax on Materials

5%





$9,347



Total Direct Unit Cost





$224,000.00

$223,897



20 Replace Existing Bridge w/ New 14'x4' Span Bridge

1

EA





3' cover, done in summer, no dewatering needed,











keep one lane open

Sawcut & Remove Pavement

77.8

SY

$12.55

$976



Remove & Dispose Existing Wooden Bridge, 12'x14'

48

SF

$50.00

$2,400



Excavate Trench

0.0

CY

$7.84

$0

account for pipe removal & loading, less pipe

Bed & Zone

0.0

CY

$46.86

$0

1/2 mile one way average

Imported Backfill

0.0

CY

$9.94

$0

assume all wasted to repository

Haul & Dispose at Repository

0.0

CY

$5.49

$0

assume all but rock is wasted, 5 mile 1 way

Repository Cost

0.0

CY

$11.38

$0

use C08a cost

Trench Safety

0

LF

$5.00

$0

trench box

CIP Wall, 12" thk, 3.6' tall

1.9

CY

$737.64

$1,377



Wall Rebar @ 200 #/cy

373.3

LB

$1.79

$666



Page 9 of 10


-------
TABLE D-21

Alternative RP-2: Pinehurst Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

Description

Quantity

Unit

2009 Direct
Capital Unit Cost

2009 Total
Direct Capital
Cost

Comments

CIP Wall, 12" thk, 3.6' tall

1.9

CY

$737.64

$1,377



Wall Rebar @ 200 #/cy

373.3

LB

$1.79

$666



CIP Slab, 12" thk, 16' wide

4

CY

$295.88

$1,227



Footing Rebar @ 150 #/cy

622

LB

$1.79

$1,111



New Bridge & Abutments - Steel

56

SF

$300.00

$16,800

based on road & bridge file

Misc Detail Allowance

20%

LS

$0.00

$5,320

minor traffic control, TESC, etc

Sales Tax on Materials

5%





$1,137





Total Direct Unit Cost



$34,000.00

$33,058



Notes:

CIP = cast-in-place
CY = cubic yards
EA = each
LB = pound(s)

LS = lump sum
SF = square feet
SY = square yards

TESC = temporary erosion and sediment control

NOTE: The above costs are presented rounded to three significant figures

NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of-30

percent to +50 percent (-30/+50%).

NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-
magnitude cost opinion shown has been prepared for guidance in project evaluation from the
information available at the time of preparation. The final costs of the project will depend on actual
labor and material costs, actual site conditions, productivity, competitive market conditions, the final
project scope, the final project schedule, and other variable factors. As a result, the final project costs
will vary from those presented above. Because of these factors, funding needs must be carefully
reviewed prior to making specific financial decisions or establishing final budgets.

Page 10 of 10


-------
TABLE D-22

Alternative RP-2: Smelterville Cost Summary

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Direct 2009 Total Direct and
Capital Unit Direct Capital Indirect Capital

	Description	Quantity Unit	Cost	Cost	Cost

Grouse Creek

1	Abandon Existing 36" Dia Concrete Culvert (Culvert 1)

2	Abandon Existing 36" Dia Concrete Culvert (Culvert 2)

3	Install/Construct New 4.5' X 8' Concrete Box Culvert (Culvert 3)

4	Reconstruct Existing Channel - Install 4.5' Tall Vertical Concrete Wall Along N Side
Of Creek (Xs 1)

5	Reconstruct Existing Channel - Install 4.5' Tall Vertical Concrete Wall Along N Side
Of Creek (Xs 2)

6	Reconstruct Existing Channel - Install 4.5' Tall Vertical Concrete Wall Along N Side
Of Creek (Xs 3)

7	Reconstruct Existing Channel - Install 4.5' Tall Vertical Concrete Wall Along N Side
Of Creek And 0.7' Berm On S Side Of Creek (Xs 4)

Subtotal Rounded $1,700,000
$620,000

	$2,320,000

Notes:

NPV = Net Present Value
LF = linear feet

O&M = operation and maintenance
Assumptions:

All excavated material is hauled to repository and replaced with imported material.

Pipe cover is 3' over pipe

All work will be performed in the summer and therefore no water issues exist.

See estimate details for additional assumptions

Total indirect cost assumes 70% of Total Direct Capital Cost

60

LF

$59

$3,540

$6,018

50

LF

$59

$2,950

$5,015

105

LF

$1,359

$142,695

$242,582

335

LF

$433

$145,055

$246,594

620

LF

$433

$268,460

$456,382

880

LF

$420

$369,600

$628,320

160

LF

$432

$69,120

$117,504

NPV for 30-year OaM Cost
Total NPV cost at 30 years

Page 1 of 1


-------

-------
TABLE D-23

Alternative RP-2: Smelterville Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Description

Quantity Unit

2009 Direct
Capital Unit Cost

2009 Total
Direct Capital
Cost

Comments

Grouse Creek
1,2

Abandon Existing 36" Dia Concrete Culvert

50

LF





Fill with CDF

13

CY

$100.00

$1,309

Pumping Costs

13

CY

$80.82

$1,058

Misc Detail Allowance

20%

LS

$0.00

$473

Sales Tax on Materials

5%





$79

Total Direct Unit Cost

$59.00

$2,919

leave open, use as overflow storage

Construct New 4.5'x8" Concrete Box Culvert

105

LF







Total Direct Unit Cost

180.0

SY

$12.55

$2,258



Excavate Channel

368.5

CY

$5.92

$2,181

25cy/hr to remove & load

Imported Fill Material

177.4

CY

$24.94

$4,426

imported

Haul & Dispose at Repository

368.5

CY

$5.57

$2,054

assume all but rock is wasted, 5 mile 1

Repository Cost

368.5

CY

$11.38

$4,193

use C08a cost

CIP Wall, 8"thk, 105 If x 4.5 ft tall

23.5

CY

$737.64

$17,298



Wall Rebar @ 200 #/cy

4690.0

LB

$1.79

$8,372



CIP ElvSlab, 8' wide x 8" Thk

41.7

CY

$664.70

$27,711



Elv Slab Rebar @ 200 #/cy

8337.8

LB

$1.79

$14,884



CIP Slab, 8' wide x 8" thk

41.7

CY

$295.88

$12,335



Footing Rebar @150 #/cy

6253.3

LB

$1.79

$11,163



ACP Pavement, 4" thk

41

TON

$70.00

$2,873



CSBC, 6" thk

30

CY

$31.26

$938



Flagger

200

HR

$60.14

$12,028



Misc Detail Allowance

15%

LS

$0.00

$17,778

access.TESC, restoration, etc

Sales Tax on Materials

5%





$2,167





Total Direct Unit Cost



$1,359.00

$142,657



Reconstruct Exist Channel w/ 4.5' wall, 15' bottom, XS1&2

335

LF







Clear, Grub & Dispose

0.3

AC

$6,514.75

$2,004



Diversion/Care of Water

0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0



Excavate Channel

375.3

CY

$14.80

$5,554



Prep & Grade Channel

335

LF

$7.84

$2,627



Haul & Dispose at Repository

375.3

CY

$5.49

$2,061

assume all but rock is wasted, 5 mile 1

Repository Cost

375.3

CY

$11.38

$4,271

use C08a cost

Imported Fill Material

68.2

CY

$53.33

$3,639

imported, difficult operation

CIP Wall, 12" thk, 4.5' tall + 1 foot below grade

68.2

CY

$737.64

$50,337



Wall Rebar @ 200 #/cy

13648.1

LB

$1.79

$24,363



Page 1 of 3


-------
TABLE D-23

Alternative RP-2: Smelterville Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site













2009 Total













2009 Direct

Direct Capital





Description



Quantity

Unit

Capital Unit Cost

Cost

Comments



CIP Wall Footing, 2.5 wide x 1.5' tall



46.5

CY

$496.76

$23,113





Footing Rebar @150 #/cy



6979.2

LB

$1.79

$12,459





Misc Detail Allowance



10%

LS

$0.00

$12,410

access.TESC, restoration, etc



Sales Tax on Materials



5%





$1,903







Total Direct Unit Cost





$433.00

$144,741



6

Reconstruct Exist Channel w/ 4.5' wall, 13.7' bottom, XS3



880

LF









Clear, Grub & Dispose



0.8

AC

$6,514.75

$5,264





Diversion/Care of Water



0

LF

$10.00

$0





Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0





Excavate Channel



490.5

CY

$14.80

$7,259





Prep & Grade Channel



880

LF

$7.84

$6,901





Haul & Dispose at Repository



490.5

CY

$5.49

$2,693

assume all but rock is wasted, 5 mile 1 way



Repository Cost



490.5

CY

$11.38

$5,582

use C08a cost



Imported Fill Material



268.9

CY

$53.33

$14,340

imported, difficult operation



CIP Wall, 12" thk, 4.5' tall + 1 foot below grade



179.3

CY

$737.64

$132,229





Wall Rebar @ 200 #/cy



35851.9

LB

$1.79

$63,999





CIP Wall Footing, 2.5 wide x 1.5' tall



122.2

CY

$496.76

$60,715





Footing Rebar @150 #/cy



18333.3

LB

$1.79

$32,727





Misc Detail Allowance



10%

LS

$0.00

$32,343

access.TESC, restoration, etc



Sales Tax on Materials



5%





$5,072







Total Direct Unit Cost





$420.00

$369,124



7

Reconstr Exist Channel w/ 4.5' wall, 10.5' bottom, & berm, XS4

880

LF









Clear, Grub & Dispose



0.8

AC

$6,514.75

$5,264





Diversion/Care of Water



0

LF

$10.00

$0





Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0





Excavate Channel



824.6

CY

$14.80

$12,202





Prep & Grade Channel



880

LF

$7.84

$6,901





Haul & Dispose at Repository



824.6

CY

$5.49

$4,527

assume all but rock is wasted, 5 mile 1 way



Repository Cost



824.6

CY

$11.38

$9,384

use C08a cost



Imported Fill Material behind wall



179.3

CY

$53.33

$9,560

imported, difficult operation



Imported Fill Material for berm



88.0

CY

$53.33

$4,693

imported, difficult operation



CIP Wall, 12" thk, 4.5' tall + 1 foot below grade



179.3

CY

$737.64

$132,229





Wall Rebar @ 200 #/cy



35851.9

LB

$1.79

$63,999





CIP Wall Footing, 2.5 wide x 1.5' tall



122.2

CY

$496.76

$60,715





Footing Rebar @150 #/cy



18333.3

LB

$1.79

$32,727





Misc Detail Allowance



10%

LS

$0.00

$32,829

access.TESC, restoration, etc

Page 2 of 3


-------
TABLE D-23

Alternative RP-2: Smelterville Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site



Description

Quantity

2009 Direct
Unit Capital Unit Cost

2009 Total
Direct Capital
Cost

Comments

Sales Tax on Materials



5%

Total Direct Unit Cost

$432.00

$5,071
$380,101



Notes:

ACP = asphalt concrete paving

CIP = cast-in-place

CY = cubic yards

EA = each

LB = pound(s)

LS = lump sum

SF = square feet

SY = square yards

TESC = temporary erosion and sediment control
NOTE: The above costs are presented rounded to three significant figures

NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of-30
percent to +50 percent (-30/+50%).

NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-
magnitude cost opinion shown has been prepared for guidance in project evaluation from the information
available at the time of preparation. The final costs of the project will depend on actual labor and material
costs, actual site conditions, productivity, competitive market conditions, the final project scope, the final
project schedule, and other variable factors. As a result, the final project costs will vary from those
presented above. Because of these factors, funding needs must be carefully reviewed prior to making
specific financial decisions or establishing final budgets.

Page 3 of 3


-------

-------
TABLE D-24

Alternative RP- 2: Kellogg Cost Summary

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009 Direct 2009 Total 2009 Total Direct
Capital Unit Direct Capital and Indirect Capital

	Description	Quantity Unit	Cost	Cost	Cost	

Jackass Creek

1

Reconstruct Existing Channel To 15' X12' X 5' Channel (Xs 1)

260

LF

$34

$8,840

$15,028

2

Line Side Of Channel With Riprap (5.00 Cf/Lf)

260

LF

$25

$6,500

$11,050

3

Line Culvert Entrance With 15 Cy Of Rip Rap

2

EA

$830

$1,660

$2,822

Portland Road











1

Construct 4'X0.5'X2' Rock-Lined Ditch Along South Side Of Portland Road. Must First

1070

LF

$50

$53,500

$90,950



Remove Existing Wooden 1'X1'X1' Flume











2

Install 300 Lf Of 36" Dia Cpe Pipe In Place Of Existing Pipe

300

LF

$240

$72,000

$122,400

3

Remove And Replace Existing Concrete Vault With 4'X4'X4' Concrete Inlet

1

EA

$6,004

$6,004

$10,207

4

Install 2'WX1'HX12'L Rock Water Bars At 250 Lf Spacings Along Portland Road

1

LS

$325

$325

$553



(4 To 5 Rock Bars Total)











5

Re-Grade Gravel Road (Portland Road) To Drain South Towards New Ditch

1070

LF

$13

$13,910

$23,647

	Subtotal Rounded	$280,000

NPV for 30-year O&M Cost	$149,000

Total NPV cost at 30 years	$429,000

Notes:

NPV = Net Present Value
EA =each
LF = linear feet
LS = lump sum

O&M = operation and maintenance
Assumptions:

All excavated material is hauled to repository and replaced with imported material.

Pipe cover is 3' over pipe

All work will be performed in the summer and therefore no water issues exist.

See estimate details for additional assumptions

Total indirect cost assumes 70% of Total Direct Capital Cost

Page 1 of 1


-------

-------
TABLE D-25

Alternative RP-2: Kellogg Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









2009 Total









2009 Direct

Direct Capital



Description

Quantity

Unit

Capital Unit Cost

Cost

Comments

Jackass Creek











1 Reconstruct Existing Channel to 15'x12'x5' -XS1

260

LF







Clear, Grub & Dispose

50.0

AC

$6,514.75

$1,555



Excavate Channel

145.6

CY

$14.80

$2,155



Prep & Grade Channel

260

LF

$7.84

$2,039



Haul & Dispose at Repository

145.6

CY

$5.49

$799

assume all but rock is wasted, 5 mile 1 way

Repository Cost

145.6

CY

$11.38

$1,657

use C08a cost

Misc Detail Allowance

10%

LS

$0.00

$575

access.TESC, restoration, etc

Sales Tax on Materials

5%





$0



Total Direct Unit Cost





$34.00

$8,780



2 Line Side of Channel with Riprap

260

LF







Riprap

52

CY

$72.91

$3,791

imported, difficult operation

Prep & Grade Channel

260

LF

$7.84

$2,039



Misc Detail Allowance

10%

LS

$0.00

$583

access.TESC, restoration, etc

Sales Tax on Materials

5%





$72



Total Direct Unit Cost





$25.00

$6,485



3 Line Culvert Entrance with Riprap

1

EA







Riprap

15

CY

$48.96

$734

imported, difficult operation

Misc Detail Allowance

10%

LS

$0.00

$73

access.TESC, restoration, etc

Sales Tax on Materials

5%





$21



Total Direct Unit Cost





$830.00

$828



Portland Road











1 Construct 4'x0.5'x2' rock lined ditch

1,070

LF







Clear, Grub & Dispose

0.7

AC

$6,514.75

$4,801



Diversion/Care of Water

0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0



Excavate Channel

713.3

CY

$14.80

$10,556



Prep & Grade Channel

1,070

LF

$7.84

$8,391



Haul & Dispose at Repository

713.3

CY

$5.49

$3,916

assume all but rock is wasted, 5 mile 1 way

Repository Cost

713.3

CY

$11.38

$8,118

use C08a cost

Imported Fill Material

257.6

CY

$53.33

$13,737

imported, difficult operation

Misc Detail Allowance

10%

LS

$0.00

$3,748

access.TESC, restoration, etc

Sales Tax on Materials

5%





$213



Total Direct Unit Cost





$50.00

$53,480



Page 1 of 3


-------
TABLE D-25

Alternative RP-2: Kellogg Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

Pipeline - 36" CHDPE, 6' to Invert



1

LF





3' cover

Demo ACP Roadway



1.6

SY

$12.55

$20



Excavate T rench



1.4

CY

$3.92

$6



Bed & Zone



0.5

CY

$46.86

$24

1/2 mile one way average

Imported Backfill



0.7

CY

$29.94

$20



Haul & Dispose at Repository



1.4

CY

$5.49

$8

assume all but rock is wasted, 5 mile 1 way

Repository Cost



1.4

CY

$11.38

$16

use C08a cost

Trench Safety



1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA

Pipe, 36" CPE Pipe



1

LF

$80.83

$81

200'/day

ACP Pavement, 4" thk



0.4

TON

$70.00

$25



CSBC, 6" thk



0.3

CY

$31.26

$8



Flagger



0.08

HR

$60.14

$5



Misc Detail Allowance



10%

LS

$0.00

$19

road maint & repair, testing, detection tape, etc

Sales Tax on Materials



5%





$6





Total Direct Unit Cost





$240.00

$242



Install new 4' x 4' x 4' concrete inlet



1

EA







Sawcut & Remove Pavement



16.0

SY

$12.55

$201



Diversion/Care of Water



0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0



Excavate Catch Basin



26.7

CY

$14.80

$395



Prep & Grade Channel



0

LF

$7.84

$0



Haul & Dispose at Repository



26.7

CY

$5.49

$146

assume all but rock is wasted, 5 mile 1 way

Repository Cost



26.7

CY

$11.38

$303

use C08a cost

Imported Fill Material



22.0

CY

$53.33

$1,175

imported, difficult operation

Grate



1.0

EA

$250.00

$250



CIP Wall, 6" thk, 4'tall



1.2

CY

$737.64

$874



Wall Rebar @ 200 #/cy



237.0

LB

$1.79

$423



CIP Elevated Slab, 10" thk



0.8

CY

$737.64

$567



Wall Rebar @ 200 #/cy



153.7

LB

$1.79

$274



CIP Slab, 10" thk, 7'x 7' wide



0.8

CY

$295.88

$227



Footing Rebar @150 #/cy



115.3

LB

$1.79

$206



Misc Detail Allowance



10%

LS

$0.00

$459

access.TESC, restoration, etc

Sales Tax on Materials



5%





$502





Total Direct Unit Cost





$6,004.00

$6,003



Page 2 of 3


-------
TABLE D-25

Alternative RP-2: Kellogg Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site















2009 Total















2009 Direct

Direct Capital







Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

4

Install 2' w x 1' h x 12' 1 rock water bars



5

EA





4'w x 1 'th



Prep Channel Bank





0

LF

$86.03

$0

assume 2 days



Imported Fill Material





4.44

CY

$62.91

$280

imported, difficult operation



Misc Detail Allowance





15%

LS

$0.00

$42

access.TESC, restoration, etc



Sales Tax on Materials





5%





$4









Total Direct Unit Cost





$65.00

$325



5

Regrade Gravel Road





1,070

LS





5' cover



Re-Grade Roadway





1426.7

SY

$3.10

$4,416





CSBC, 6" thk





237.8

CY

$31.26

$7,432





Flagger





8.00

HR

$60.14

$481





Misc Detail Allowance





10%

LS

$0.00

$1,233

road maint & repair, testing, detection tape, etc



Sales Tax on Materials





5%





$235









Total Direct Unit Cost





$13.00

$13,797



Notes:

ACP = asphalt concrete paving

CIP = cast-in-place

CPE = polyethylene

CY = cubic yards

EA = each

LB = pound(s)

LS = lump sum

SF = square feet

SY = square yards

TESC = temporary erosion and sediment control

NOTE: The above costs are presented rounded to three significant figures

NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of-30 percent
to +50 percent (-30/+50%).

NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-
magnitude cost opinion shown has been prepared for guidance in project evaluation from the information
available at the time of preparation. The final costs of the project will depend on actual labor and material
costs, actual site conditions, productivity, competitive market conditions, the final project scope, the final
project schedule, and other variable factors. As a result, the final project costs will vary from those
presented above. Because of these factors, funding needs must be carefully reviewed prior to making
specific financial decisions or establishing final budgets.

Page 3 of 3


-------

-------
TABLE D-26

Alternative RP-2: Wardner Cost Summary

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

2009 Direct 2009 Total 2009 Total Direct
Capital Unit Direct Capital and Indirect Capital

Description

Quantity Unit

Cost

Cost

Cost

Wardner/Sierra Nevada Road

1	Construct 40' Of 36 Dia Cpe Pipe With 1' Of Cover

2	Construct 50' Of 36 Dia Cpe Pipe With 1' Of Cover

3	Install 12'X6.5' Cattle Guard W/ 10'X6'X4' Cast-ln-Place Concrete Vault

40
50
2

LF
EA
EA

$150
$150
$25,100

$6,000
$7,500
$50,200

$10,200
$12,750
$85,340

Subtotal Rounded $110,000

Npv For 30-Year O&M Cost
Total NPV cost at 30 years

$99,000
$209,000

Notes:

NPV = Net Present Value
CPE = polyethylene
EA = each
LF = linear feet

O&M = operation and maintenance
Assumptions:

All excavated material is hauled to repository and replaced with imported material.
Pipe cover is 3' over pipe

All work will be performed in the summer and therefore no water issues exist.
See estimate details for additional assumptions

Page 1 of 1


-------

-------
TABLE D-27

Alternative RP-2: Wardner Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

	Description	Quantity Unit Capital Unit Cost	Cost	Comments

Wardner/Sierra Nevada Road

Pipeline - 36" CHDPE, 1' Cover



1

LF





3' cover

Clear, Grub & Dispose



50.0

AC

$6,514.75

$1



Excavate T rench



0.8

CY

$3.92

$3



Bed & Zone



0.5

CY

$46.86

$24

1/2 mile one way average

Imported Backfill



0.1

CY

$29.94

$2



Haul & Dispose at Repository



0.8

CY

$5.49

$5

assume all but rock is wasted, 5 mile 1 way

Repository Cost



0.8

CY

$11.38

$10

use C08a cost

Trench Safety



1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA

Pipe, 36" CPE Pipe



1

LF

$80.83

$81

200'/day

Misc Detail Allowance



10%

LS

$0.00

$12

road maint & repair, testing, detection tape, etc

Sales Tax on Materials



5%





$3





Total Direct Unit Cost





$150.00

$146



12'X6' Cattle Guard with CIP Vault



1

EA







10'x6' Cattle Guard



1.0

EA

$10,305.31

$10,305

Use $100/SF cost

Grade existing pond bottom



140.0

SF

$3.14

$439



Excavate for walls



25.9

CY

$3.92

$102



Imported Backfill



8.1

CY

$29.94

$244



Haul & Dispose at Repository



25.9

CY

$5.49

$142

assume all but rock is wasted, 5 mile 1 way

Repository Cost



25.9

CY

$11.38

$295

use C08a cost

CIP Wall, 12" thk, 4 ft tall



5.3

CY

$737.64

$3,934



Wall Rebar @ 200 #/cy



1066.7

LB

$1.79

$1,904



CIP Slab, 12" thk, 14'x10' including 1 foot beyond wall



5.2

CY

$295.88

$1,534



Footing Rebar @150 #/cy



777.8

LB

$1.79

$1,388



Misc Detail Allowance



20%

LS

$0.00

$4,058



Sales Tax on Materials



5%





$717





Total Direct Unit Cost





$25,100.00

$25,063



Page 1 of 2


-------
TABLE D-27

Alternative RP-2: Wardner Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

	Description	Quantity Unit Capital Unit Cost	Cost	Comments

Notes:

CPE = polyethylene
CIP = cast-in-place
CY = cubic yards
EA = each
LB = pound(s)

LS = lump sum
SF = square feet

TESC = temporary erosion and sediment control

NOTE: The above costs are presented rounded to three significant figures
NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal
accuracy of-30 percent to +50 percent (-30/+50%).

NOTE: The above cost opinion is in 2009 dollars and does not include future
escalation. The order-of-magnitude cost opinion shown has been prepared for
guidance in project evaluation from the information available at the time of
preparation. The final costs of the project will depend on actual labor and material
costs, actual site conditions, productivity, competitive market conditions, the final
project scope, the final project schedule, and other variable factors. As a result, the
final project costs will vary from those presented above. Because of these factors,
funding needs must be carefully reviewed prior to making specific financial decisions
or establishing final budgets.

Page 2 of 2


-------
TABLE D-28

Alternative RP-2: Osburn Cost Summary

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

Description

Quantity

Unit

2009 Direct
Capital Unit
Cost

2009 Total
Direct Capital
Cost

2009 Total Direct
and Indirect
Capital Cost

Shields Gulch











1 Replace Existing 32" 0 Cmp Culvert With 4'X6' Cmp Arch (Culvert 1)

14

LF

$780

$10,920

$18,564

2 Replace Existing 36" 0 Concrete Culvert With 4'X6' Cmp Arch (Culvert 2)

25

LF

$780

$19,500

$33,150

3 Replace Existing 36" 0 Cmp Culvert With 4'X6' Cmp Arch (Culvert 3)

50

LF

$780

$39,000

$66,300

4 Install New 4'X6' Cmp Arch Culvert (Culvert 4)

35

LF

$570

$19,950

$33,915

5 Reconstruct Right Channel Bank With 1' Berm (Xs 1)

65

LF

$411

$26,715

$45,416

6 Construct 12' X 4' X 4' Earthen Channel (Xs 2)

1890

LF

$57

$107,730

$183,141

7 Construct 25' X 15' X 5' Earthen Channel (Xs 3)

155

LF

$260

$40,300

$68,510

Rosebud Gulch











1 Replace Existing Culverts (One 24" 0 Cmp And Two 20" 0 Cmp) With One 48" 0

130

LF

$620

$80,600

$137,020

Cmp (Culvert 1)











2 Replace Existing Park Culvert With A 10.5' X 16' Single Span Bridge With A

1

EA

$95,000

$95,000

$161,500

Clear Height Of 2' (Bridge 1)











3 Reconstruct Right Channel Bank With 1' Berm (Xs 1)

310

LF

$110

$34,100

$57,970

4 Reconstruct Existing Channel To 11' X 4' X 4' Earthen Channel (Xs 2 - A & B)

90

LF

$32

$2,880

$4,896

5 Reconstruct Existing Channel To 8.5' X 5.5' X 2' Earthen Channel (Xs 4)

1330

LF

$21

$27,930

$47,481

Meyer Creek











1-10 Construct 24"0 hdpe Pipe At An Average Depth Of 7 Ft

2835

LF

$210

$595,350

$1,012,095

11 Furnish And Install New48"0 Manhole

9

EA

$4,600

$41,400

$70,380

12 Abandon 360 Lf Of Existing Meyer Creek Pipe-Leave Open For Storage

1

LS

$0

$0

$0

13 Modify Inlet Structure

1

LS

$97,874

$97,874

$166,386







Subtotal Rounded

$2,110,000

NPV for 30-year O&M Cost
Total NPV cost at 30 years









$745,000
$2,855,000

Notes:

NPV = Net Present Value
EA = each
LF = linear feet
LS = lump sum

O&M = operation and maintenance
Assumptions:

All excavated material is hauled to repository and replaced with imported material.
Pipe cover is 3' over pipe

All work will be performed in the summer and therefore no water issues exist.

See estimate details for additional assumptions

Total indirect cost assumes 70% of Total Direct Capital Cost

Page 1 of 1


-------

-------
TABLE D-29

Alternative RP-2: Osburn Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009 Total









2009 Direct

Direct Capital



Description

Quantity

Unit

Capital Unit Cost

Cost

Comments

Shields Gulch











1,2,3 Replace Culvert with 4'X6' CMP Arch

50

LF





3' cover, done in summer, no dewatering needed,
keep one lane open

Sawcut & Remove Pavement

40

SY

$12.55

$502



Remove & Dispose Existing Culvert

30

LF

$7.84

$235

32 to 36" CMP or RCP

Excavate Trench

83.2

CY

$7.84

$653

account for pipe removal & loading, less pipe

Bed & Zone

44.2

CY

$46.86

$2,071

1/2 mile one way average

Imported Backfill

32.0

CY

$24.94

$798

assume all wasted to repository

Haul & Dispose at Repository

83.2

CY

$5.49

$457

assume all but rock is wasted, 5 mile 1 way

Repository Cost

83.2

CY

$11.38

$947

use C08a cost

Trench Safety

30

LF

$5.00

$150

trench box

Dewatering: Two Sump Pmps



HR

$12.00

$0

none requred

4'x6' CMP Arch

30

LF

$360.72

$10,822

75'/day

Headwall/Miter

1

EA

$1,500.00

$1,500

allowance

Restoration - Base Course & Pavement Patch

40

SY

$22.00

$880

subcontract

Misc Detail Allowance

20%

LS

$0.00

$3,522

minor traffic control, TESC, etc

Sales Tax on Materials

5%

Total Direct Unit Cost

$780.00

$672
$23,208

New4'X6' CMP Arch Culvert

35

LF





3' cover

Sawcut & Remove Pavement

46.7

SY

$12.55

$586



Remove & Dispose Existing Culvert

0

LF

$7.84

$0

not required

Excavate Trench

105.2

CY

$3.92

$412

account for pipe removal & loading

Bed & Zone

51.6

CY

$46.86

$2,416

1/2 mile one way average

Imported Backfill

37.3

CY

$24.94

$930

assume all wasted to repository

Haul & Dispose at Repository

105.2

CY

$5.49

$577

assume all but rock is wasted, 5 mile

Repository Cost

105.2

CY

$11.38

$1,197

use C08a cost

Trench Safety

35

LF

$5.00

$175

trench box

Dewatering: Two Sump Pmps



HR

$12.00

$0

none requred

4'x6' CMP Arch

35

LF

$215.32

$7,536

75'/day, Material cost per The Guide

Headwall/Miter

1

EA

$1,500.00

$1,500

allowance

Restoration - Base Course & Pavement Patch

46.7

SY

$22.00

$1,027

subcontract

Misc Detail Allowance

20%

LS

$0.00

$2,916

minor traffic control, TESC, etc

Sales Tax on Materials

5%





$464





Total Direct Unit Cost



$570.00

$19,737



Page 1 of 6


-------
TABLE D-29

Alternative RP-2: Osburn Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Direct

Direct Capital





Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

5

Reconstruct Right Channel Bank with 1' Berm



65

LF





4'w x 1 'th



Prep Channel Bank



65

LF

$86.03

$5,592

assume 2 days



Imported Fill Material



9.63

CY

$62.91

$606

imported, difficult operation



Misc Detail Allowance



15%

LS

$0.00

$20,255

access.TESC, restoration, etc



Sales Tax on Materials



5%





$231







Total Direct Unit Cost





$411.00

$26,683



6

Construct 12'x4'x4' Earthen Channel



1,890

LF









Clear, Grub & Dispose



1.7

AC

$6,514.75

$11,307





Diversion/Care of Water



0

LF

$10.00

$0

allowance for temp dikes/facilities & bypass















pumping



Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0





Excavate Channel



2268

CY

$14.80

$33,562

25cy/hrto remove & load, small area



Prep & Grade Channel



1890

LF

$7.84

$14,821





Haul & Dispose at Repository



2268

CY

$5.49

$12,451

assume all but rock is wasted, 5 mile 1 way



Repository Cost



2268

CY

$11.38

$25,810

use C08a cost



Pea Gravel



0

CY

$19.88

$0





Sand



0

CY

$19.88

$0





Liner/Geotextile System



0

SY

$4.97

$0





Misc Detail Allowance



15%

LS

$0.00

$8,954

access.TESC, restoration, etc



Sales Tax on Materials



5%





$0







Total Direct Unit Cost





$57.00

$106,905



7

Construct 25'x15'x5' Earthen Channel



155

LF









Clear, Grub & Dispose



0.1

AC

$6,514.75

$927





Diversion/Care of Water



0

LF

$10.00

$0

allowance for temp dikes/facilities & bypass















pumping



Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0





Excavate Channel



655.7

CY

$15.68

$10,283

25cy/hrto remove & load



Prep & Grade Channel



155

LF

$7.84

$1,216





Haul & Dispose at Repository



655.7

CY

$5.49

$3,600

assume all but rock is wasted, 5 mile 1 way



Repository Cost



655.7

CY

$11.38

$7,461

use C08a cost



Imported Fill Material



52.7

CY

$62.91

$3,312

imported, difficult operation



Sand



0

CY

$19.88

$0





Liner/Geotextile System



0

SY

$4.97

$0





Imported Fill Material



181.35

CY

$49.41

$8,961

imported, small operation



Misc Detail Allowance



15%

LS

$0.00

$3,705

access.TESC, restoration, etc



Sales Tax on Materials



5%





$202







Total Direct Unit Cost





$260.00

$39,666



Page 2 of 6


-------
TABLE D-29

Alternative RP-2: Osburn Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

Description

Quantity Unit

2009 Total
2009 Direct Direct Capital
Capital Unit Cost	Cost

Comments

Rosebud Gulch

1

Replace Multiple Culverts w/1-48" CMP Culvert

130

LF





3' cover, done in summer, no dewatering needed,
keep one lane open

Sawcut & Remove Pavement

642.8

SY

$12.55

$8,065



Remove & Dispose Existing Culvert, 1-24" & 2-20" CMP

390

LF

$3.92

$1,529



Excavate Trench

294.8

CY

$7.84

$2,312

account for pipe removal & loading, less pipe

Bed & Zone

132.6

CY

$46.86

$6,214

1/2 mile one way average

Imported Backfill

136.7

CY

$24.94

$3,409

assume all wasted to repository

Haul & Dispose at Repository

294.8

CY

$5.49

$1,619

assume all but rock is wasted, 5 mile 1 way

Repository Cost

294.8

CY

$11.38

$3,355

use C08a cost

Trench Safety

130

LF

$5.00

$650

trench box

Dewatering: Two Sump Pmps

0

HR

$12.00

$0

none requred

48" CMP Pipe

130

LF

$182.34

$23,704

10O'/day

Headwall/Miter

1

EA

$1,500.00

$1,500

allowance

Restoration - Base Course & Pavement Patch

642.8

SY

$22.00

$14,141

subcontract

Misc Detail Allowance

20%

LS

$0.00

$12,305

minor traffic control, TESC, etc

Sales Tax on Materials

5%

Total Direct Unit Cost

$620.00

$1,324
$80,127

Replace Multiple Culverts w/Single Span Bridge

LF

3' cover, done in summer, no dewatering needed,
keep one lane open

Sawcut & Remove Pavement

642.8

SY

$12.55

$8,065



Remove & Dispose Existing Culvert, 1-24" & 2-20" CMP

390

LF

$3.92

$1,529



Excavate Trench

294.8

CY

$7.84

$2,312

account for pipe removal & loading, less pipe

Bed & Zone

132.6

CY

$46.86

$6,214

1/2 mile one way average

Imported Backfill

136.7

CY

$24.94

$3,409

assume all wasted to repository

Haul & Dispose at Repository

294.8

CY

$5.49

$1,619

assume all but rock is wasted, 5 mile 1 way

Repository Cost

294.8

CY

$11.38

$3,355

use C08a cost

Trench Safety

1

LF

$5.00

$5

trench box

New Bridge & Abutments - Steel

168

SF

$300.00

$50,400

based on road & bridge file

Misc Detail Allowance

20%

LS

$0.00

$14,387

minor traffic control, TESC, etc

Sales Tax on Materials

5%

Total Direct Unit Cost

$95,000.00

$3,322
$94,617

3 Reconstruct Right Channel Bank

310

LF





see detail

Prep Channel Bank

310

LF

$86.03

$26,668

difficult operation, assume 10 dys

Imported Fill Material

62

CY

$62.91

$3,900

imported, difficult operation

Misc Detail Allowance

10%

LS

$0.00

$3,057

access.TESC, restoration, etc

Sales Tax on Materials

5%





$51





Total Direct Unit Cost



$110.00

$33,676



Page 3 of 6


-------
TABLE D-29

Alternative RP-2: Osburn Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

Description

Quantity

Unit

Capital Unit Cost

Cost

Comments

Reconstruct Existing Channel to 11'x4,x4' Earthen Channel

90

LF







Clear, Grub & Dispose

0.1

AC

$6,514.75

$538



Diversion/Care of Water

0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0



Excavate Channel

4.5

CY

$15.68

$71

25cy/hr to remove & load

Prep & Grade Channel

90

LF

$7.84

$706



Haul & Dispose at Repository

4.5

CY

$5.49

$25

assume all but rock is wasted, 5 mile

Repository Cost

4.5

CY

$11.38

$51

use C08a cost

Imported Fill Material

19.4

CY

$62.91

$1,217

imported, difficult operation

Sand

0

CY

$19.88

$0



Liner/Geotextile System

0

SY

$4.97

$0



Misc Detail Allowance

10%

LS

$0.00

$253

access.TESC, restoration, etc

Sales Tax on Materials

5%





$16



Total Direct Unit Cost





$32.00

$2,877



5 Reconstruct Existing Channel to 8.5'x5

Clear, Grub & Dispose

Diversion/Care of Water

Diversion Piping - Temporary: 36" dia Eq

Excavate Channel

Prep & Grade Channel

Haul & Dispose at Repository

Repository Cost

Imported Fill Material

Sand

Liner/Geotextile System
Misc Detail Allowance

Sales Tax on Materials

.5'x2' Earthen Channel

Total Direct Unit Cost

1,330

LF





1.2

AC

$6,514.75

$7,956

0

LF

$10.00

$0

0

LF

$10.39

$0

199.5

CY

$14.80

$2,952

1330

LF

$7.84

$10,430

199.5

CY

$5.49

$1,095

199.5

CY

$11.38

$2,270

0

CY

$62.91

$0

0

CY

$19.88

$0

0

SY

$4.97

$0

10%

LS

$0.00

$2,134

5%	$0

$21.00	$26,838

assume all but rock is wasted, 5 mile 1 way

use C08a cost

imported, difficult operation

access.TESC, restoration, etc

Meyer Creek

Pipeline - 24"

1

LF





5' cover

Sawcut & Remove Pavement

1.3

SY

$12.55

$17



Excavate Trench

1.6

CY

$3.92

$6



Bed & Zone

0.4

CY

$46.86

$17

1/2 mile one way average

Imported Backfill

1.1

CY

$29.94

$33



Haul & Dispose at Repository

1.6

CY

$5.49

$9

assume all but rock is wasted,

Repository Cost

1.6

CY

$11.38

$18

use C08a cost

Trench Safety

1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps

0

HR

$12.00

$0

NA

Page 4 of 6


-------
TABLE D-29

Alternative RP-2: Osburn Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Direct

Direct Capital





Description



Quantity

Unit

Capital Unit Cost

Cost

Comments



Pipe, 24" Corrugated HDPE



1

LF

$58.67

$59

200'/day



Restoration - Base Course & Pavement Patch



1.3

SY

$22.00

$29

subcontract



Misc Detail Allowance



10%

LS

$0.00

$17

road maint & repair, testing, detection tape, etc



Sales Tax on Materials



5%





$3







Total Direct Unit Cost





$210.00

$211



11

Manhole, 48" Dia X 8'



1

EA









Purchase & Install Manhole, Frame, Ring, Cover



1

EA

$4,068.40

$4,068





Misc Detail Allowance



10%

LS

$0.00

$407

invert



Sales Tax on Materials



5%





$138







Total Direct Unit Cost





$4,600.00

$4,613



12

Abandon Meyer Creek Pipe



360

LF









Plug Ends with Concrete



0

EA

$250.00

$0

leave open, use as overflow storage



Misc Detail Allowance



20%

LS

$0.00

$0





Sales Tax on Materials



5%





$0







Total Direct Unit Cost





$0.00

$0



13

Modify Inlet Structure



1

EA





$95,214



Riprap



40

CY

$72.91

$2,916

imported, difficult operation



12'x15' Steel Trash Rack at outlet



1

EA

$21,105.31

$21,105

Use $100/SF cost



Grade existing pond bottom



2000

SF

$3.14

$6,274





CIP Wall, 8" thk, 50 If x 6 ft tall



7.4

CY

$737.64

$5,491





Wall Rebar @ 200 #/cy



1488.9

LB

$1.79

$2,658





CIP Wall Footing, 2.5 wide x 1.5' tall



6.9

CY

$496.76

$3,450





Footing Rebar @ 150 #/cy



1041.7

LB

$1.79

$1,859





CIP Slab and sump, 10" thk



61.5

CY

$295.88

$18,191





Footing Rebar @ 150 #/cy



9222.2

LB

$1.79

$16,463





Crushed Gravel Driveway



30

CY

$31.26

$938





Misc Detail Allowance



20%

LS

$0.00

$15,869





Sales Tax on Materials



5%





$2,660







Total Direct Unit Cost







$97,874



Page 5 of 6


-------
TABLE D-29

Alternative RP-2: Osburn Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

	Description	Quantity Unit Capital Unit Cost	Cost	Comments

Notes:

CIP = cast-in-place
CMP = corrugated metal pipe
CY = cubic yards
EA = each

HDPE = high density polyethylene

HR = hour

LB = pound(s)

LS = lump sum

SF = square feet

SY = square yards

TESC = temporary erosion and sediment control

NOTE: The above costs are presented rounded to three significant figures
NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal
NOTE: The above cost opinion is in 2009 dollars and does not include future
escalation. The order-of-magnitude cost opinion shown has been prepared for
guidance in project evaluation from the information available at the time of preparation.

The final costs of the project will depend on actual labor and material costs, actual site
conditions, productivity, competitive market conditions, the final project scope, the final
project schedule, and other variable factors. As a result, the final project costs will vary
from those presented above. Because of these factors, funding needs must be
carefully reviewed prior to making specific financial decisions or establishing final
budgets.

Page 6 of 6


-------
TABLE D-30

Alternative RP-2: Silverton Cost Summary

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site



Description

Quantity

Unit

2009 Direct
Capital Unit
Cost

2009 Total
Direct Capital
Cost

2009 Total
Direct and
Indirect Capil
Cost

Revenue Gultch Alternative 2











1

Replace Existing Culvert (48" Dia Cmp) With 56" Dia Cmp (Culvert 1)

38

LF

$540

$20,520

$34,884

2

Replace Existing Culvert (15 Lf Of 48" Dia Cmp) With 15'X32' Single Span Bridge W/

1

LS

$184,000

$184,000

$312,800



A Clear Height Of 5' (Bridge 1)











3

Replace Existing Culvert (48" Dia Cmp) W/ One 5.6'X7.9' Pipe Arch Cmp (Culvert 2)

32

LF

$810

$25,920

$44,064

4

Replace Existing Culvert (48" Dia Cmp) W/ One 6.1'X8.8' Pipe Arch Cmp (Culvert 3)

22

LF

$1,350

$29,700

$50,490

5

Replace Existing Culvert (Box Culvert) With One 3'X7.5' Box Culvert (Culvert 4)

550

LF

$1,054

$579,700

$985,490

6

Install/Construct Overflow Structure

1

LS

$72,500

$72,500

$123,250

7

Construct 235 Lf Of 18" Dia Chdpe At An Avg Depth Of 6' To Invert (Pipe 1)

235

LF

$160

$37,600

$63,920

8

Construct 210 Lf Of 18" Dia Chdpe At An Avg Depth Of 6' To Invert (Pipe 2)

210

LF

$160

$33,600

$57,120

9

Construct 210 Lf Of 18" Dia Chdpe At An Avg Depth Of 6' To Invert (Pipe 3)

210

LF

$160

$33,600

$57,120

10

Construct 200 Lf Of 18" Dia Chdpe At An Avg Depth Of 6' To Invert (Pipe 4)

200

LF

$160

$32,000

$54,400

11

Construct 80 Lf Of 36" Dia Chdpe At An Avg Depth Of 6' To Invert (Pipe 5)

80

LF

$240

$19,200

$32,640

12

Construct 290 Lf Of 36" Dia Chdpe At An Avg Depth Of 7.5' To Invert (Pipe 6)

290

LF

$290

$84,100

$142,970

13

Construct 225 Lf Of 36" Dia Chdpe At An Avg Depth Of 7.5' To Invert (Pipe 7)

225

LF

$290

$65,250

$110,925

14

Construct 190 Lf Of 36" Dia Chdpe At An Avg Depth Of 7.5' To Invert (Pipe 8)

190

LF

$290

$55,100

$93,670

15

Construct 190 Lf Of 36" Dia Chdpe At An Avg Depth Of 7.5' To Invert (Pipe 9)

190

LF

$290

$55,100

$93,670

16

Construct 205 Lf Of 36" Dia Chdpe At An Avg Depth Of 7.5' To Invert (Pipe 10)

205

LF

$290

$59,450

$101,065

17

Construct 185 Lf Of 36" Dia Chdpe At An Avg Depth Of 7.5' To Invert (Pipe 11)

185

LF

$290

$53,650

$91,205

18

Construct 190 Lf Of 36" Dia Chdpe At An Avg Depth Of 7.5' To Invert (Pipe 12)

190

LF

$290

$55,100

$93,670

19

Construct 265 Lf Of 36" Dia Chdpe At An Avg Depth Of 6' To Invert (Pipe 13)

265

LF

$240

$63,600

$108,120

20

Construct 265 Lf Of 36" Dia Chdpe At An Avg Depth Of 6' To Invert (Pipe 14)

265

LF

$240

$63,600

$108,120

21

Construct 70 Lf Of 42" Dia Chdpe At An Avg Depth Of 5.5' To Invert (Pipe 15)

70

LF

$280

$19,600

$33,320

22

Furnish And Install New 48" Dia Manhole At A Depth Of 6' To 8'

14

EA

$4,890

$68,460

$116,382

23

Furnish And Install New Storm Drain

8

EA

$6,130

$49,040

$83,368

West

of Western Avenue











1

Construct 206 Lf Of 16" Dia Chdpe At An Avg Depth Of 6' To Invert (Pipe 1)

206

LF

$150

$30,900

$52,530

2

Construct 220 Lf Of 16" Dia Chdpe At An Avg Depth Of 6' To Invert (Pipe 2)

220

LF

$150

$33,000

$56,100

3

Construct 229 Lf Of 16" Dia Chdpe At An Avg Depth Of 6' To Invert (Pipe 3)

229

LF

$150

$34,350

$58,395

4

Construct 192 Lf Of 18" Dia Chdpe At An Avg Depth Of 6' To Invert (Pipe 4)

192

LF

$160

$30,720

$52,224

5

Construct 196 Lf Of 20" Dia Chdpe At An Avg Depth Of 6.5' To Invert (Pipe 5)

196

LF

$180

$35,280

$59,976

6

Construct 183 Lf Of 20" Dia Chdpe At An Avg Depth Of 6.5' To Invert (Pipe 6)

183

LF

$180

$32,940

$55,998

7

Construct 192 Lf Of 20" Dia Chdpe At An Avg Depth Of 6.5' To Invert (Pipe 7)

192

LF

$180

$34,560

$58,752

8

Construct 181 Lf Of 20" Dia Chdpe At An Avg Depth Of 6.5' To Invert (Pipe 8)

181

LF

$180

$32,580

$55,386

9

Construct 200 Lf Of 22" Dia Chdpe At An Avg Depth Of 6.5' To Invert (Pipe 9)

200

LF

$200

$40,000

$68,000

10

Construct 544 Lf Of 22" Dia Chdpe At An Avg Depth Of 5' To Invert (Pipe 10)

544

LF

$150

$81,600

$138,720

11

Furnish And Install New 48" Dia Manhole At A Depth Of 6' To 8'

10

EA

$4,890

$48,900

$83,130

12

Furnish And Install New Storm Drain

20

EA

$6,130

$122,600

$208,420

Unnamed Creek











1

Replace Existing Culvert (12" Cmp) With 22" Dia Cmp (Culvert 1)

24

LF

$290

$6,960

$11,832

2

Reconstruct Existing Channel To 12'X3'X3' Earthen Channel (Xs 1)

1115

LS

$43

$47,945

$81,507

Subtotal Rounded $4,030,000
$1,340,000

	$5,370,000

Notes:

NPV = Net Present Value
CMP = corrugated metal pipe
EA =each
LF = linear feet
LS = lump sum

O&M = operation and maintenance
Assumptions:

All excavated material is hauled to repository and replaced with imported material.

Pipe cover is 3' over pipe

All work will be performed in the summer and therefore no water issues exist.

See estimate details for additional assumptions

NPV for 30-year OaM Cost
Total NPV cost at 30 years

Page 1 of 1


-------

-------
TABLE D-31

Alternative RP- 2: Silverton Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site









2009 Total









2009 Direct

Direct Capital



Description

Quantity

Unit

Capital Unit Cost

Cost

Comments

Revenue Gulch











1 Replace 48" Culverst w/ 56" CMP Culvert

38

LF





3' cover, done in summer, no dewatering needed,
keep one lane open

Sawcut & Remove Pavement

50.0

SY

$12.55

$0



Remove & Dispose Existing Culvert, 1-48" CMP

38

LF

$15.68

$596



Excavate Trench

101.1

CY

$7.84

$793

account for pipe removal & loading, less pipe

Bed & Zone

35.4

CY

$46.86

$1,658

1/2 mile one way average

Imported Backfill

41.6

CY

$24.94

$1,038

assume all wasted to repository

Haul & Dispose at Repository

101.1

CY

$5.49

$555

assume all but rock is wasted, 5 mile 1 way

Repository Cost

101.1

CY

$11.38

$1,150

use C08a cost

Trench Safety

38

LF

$5.00

$190

trench box

Dewatering: Two Sump Pmps

0

HR

$12.00

$0

none requred

56" CMP Pipe

38

LF

$241.52

$9,178

75'/day

Headwall/Miter

1

EA

$1,500.00

$1,500

allowance

Restoration - Base Course & Pavement Patch

0.0

SY

$22.00

$0

subcontract

Misc Detail Allowance

20%

LS

$0.00

$2,990

minor traffic control, TESC, etc

Sales Tax on Materials

5%

Total Direct Unit Cost

$540.00

$535
$20,183

2	Replace Multiple Culverts w/ 15'x32' Single Span Bridge	1	EA	3'cover, done in summer, no dewatering needed,

keep one lane open

Sawcut & Remove Pavement

53.3

SY

$12.55

$669



Remove & Dispose Existing Culvert, 1-48" CMP

15

LF

$15.68

$235



Excavate Trench

45.1

CY

$7.84

$353

account for pipe removal & loading, less pipe

Bed & Zone

0.0

CY

$46.86

$0

1/2 mile one way average

Imported Backfill

0.0

CY

$9.94

$0

assume all wasted to repository

Haul & Dispose at Repository

45.1

CY

$5.49

$247

assume all but rock is wasted, 5 mile 1 way

Repository Cost

45.1

CY

$11.38

$513

use C08a cost

Trench Safety

0

LF

$5.00

$0

trench box

New Bridge & Abutments - Steel

480

SF

$300.00

$144,000

based on road & bridge file

Misc Detail Allowance

20%

LS

$0.00

$29,052

minor traffic control, TESC, etc

Sales Tax on Materials

5%





$8,640





Total Direct Unit Cost



$184,000.00

$183,710



Page 1 of 11


-------
TABLE D-31

Alternative RP- 2: Silverton Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site











2009 Total











2009 Direct

Direct Capital





Description

Quantity

Unit

Capital Unit Cost

Cost

Comments

3

Replace 48" Culverts w/ 5.6'x7.9' Arch Culvert

32

LF





3' cover, done in summer, no dewatering needed,













keep one lane open



Sawcut & Remove Pavement

0.0

SY

$12.55

$0





Remove & Dispose Existing Culvert, 1-48" CMP

32

LF

$15.68

$502





Excavate Trench

147.2

CY

$7.84

$1,154

account for pipe removal & loading, less pipe



Bed & Zone

62.1

CY

$46.86

$2,909

1/2 mile one way average



Imported Backfill

54.4

CY

$24.94

$1,357

assume all wasted to repository



Haul & Dispose at Repository

147.2

CY

$5.49

$808

assume all but rock is wasted, 5 mile 1 way



Repository Cost

147.2

CY

$11.38

$1,675

use C08a cost



Trench Safety

32

LF

$5.00

$160

trench box



Dewatering: Two Sump Pmps

0

HR

$12.00

$0

none requred



95"x67" Arch CMP Culert

32

LF

$335.88

$10,748

50'/day, Material cost per The Guide



Headwall/Miter

1

EA

$2,000.00

$2,000

allowance



Restoration - Base Course & Pavement Patch

0.0

SY

$22.00

$0

subcontract



Misc Detail Allowance

20%

LS

$0.00

$3,766

minor traffic control, TESC, etc



Sales Tax on Materials

5%





$656







Total Direct Unit Cost



$810.00

$25,735



4

Replace 48" Culverts/ 6.1'x8.8' Arch Culvert

22

LF





3' cover, done in summer, no dewatering needed,













keep one lane open



Sawcut & Remove Pavement

0.0

SY

$12.55

$0





Remove & Dispose Existing Culvert, 1-48" CMP

22

LF

$15.68

$345





Excavate Trench

214.9

CY

$7.84

$1,686

account for pipe removal & loading, less pipe



Bed & Zone

91.1

CY

$46.86

$4,269

1/2 mile one way average



Imported Backfill

66.8

CY

$24.94

$1,667

assume all wasted to repository



Haul & Dispose at Repository

214.9

CY

$5.49

$1,180

assume all but rock is wasted, 5 mile 1 way



Repository Cost

214.9

CY

$11.38

$2,446

use C08a cost



Trench Safety

22

LF

$5.00

$110

trench box



Dewatering: Two Sump Pmps

0

HR

$12.00

$0

none requred



112"x75" Arch CMP Culert

22

LF

$497.76

$10,951

25'/day, Material cost per The Guide



Headwall/Miter

1

EA

$2,000.00

$2,000

allowance



Restoration - Base Course & Pavement Patch

0.0

SY

$22.00

$0

subcontract



Misc Detail Allowance

20%

LS

$0.00

$4,205

minor traffic control, TESC, etc



Sales Tax on Materials

5%





$628







Total Direct Unit Cost



$1,350.00

$29,487



Page 2 of 11


-------
TABLE D-31

Alternative RP- 2: Silverton Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Direct

Direct Capital







Description

Quantity

Unit

Capital Unit Cost

Cost

Comments

5

Replace Existing Box Culvert w/3'x7.5' Box Culvert

550

LF









Demo ACP Roadway



305.6

SY

$12.55

$3,834

275' of length under roadway



Remove & Dispose Existing Box Culvert

550

LF

$31.37

$17,252





Excavate Channel



1161.1

CY

$5.92

$6,873





Imported Fill Material



702.8

CY

$24.94

$17,529

imported



Haul & Dispose at Repository



1161.1

CY

$5.57

$6,472

assume all but rock is wasted, 5 mile 1 way



Repository Cost



1161.1

CY

$11.38

$13,213

use C08a cost



CIP Wall, 8" thk, 3 ft tall



81.9

CY

$737.64

$60,405





Wall Rebar @ 200 #/cy



16378

LB

$1.79

$29,236





CIP Elv Slab, 7.5' wide x 8" Thk



204.7

CY

$664.70

$136,079





Elv Slab Rebar @ 200 #/cy



40944

LB

$1.79

$73,090





CIP Slab, 7.5' wide x 10" thk



204.7

CY

$295.88

$60,573





Footing Rebar @ 150 #/cy



30708

LB

$1.79

$54,818





ACP Pavement, 4" thk



70

TON

$70.00

$4,877





CSBC, 6" thk



51

CY

$31.26

$1,592





Flagger



200

HR

$60.14

$12,028





Misc Detail Allowance



15%

LS

$0.00

$72,698

access.TESC, restoration, etc



Sales Tax on Materials



5%





$9,232









Total Direct Unit Cost



$1,054.00

$579,801



6

Overflow Structure



1

EA





$70,211



Riprap



18.5

CY

$72.91

$1,350

imported, difficult operation



20'x6' Steel Trash Rack at outlet



1.0

EA

$15,105.31

$15,105

Use $100/SF cost



Grade existing pond bottom



950.0

SF

$3.14

$2,980





Excavate for walls



44.6

CY

$3.92

$175





Imported Backfill



25.5

CY

$29.94

$763





Haul & Dispose at Repository



44.6

CY

$5.49

$245

assume all but rock is wasted, 5 mile 1 way



Repository Cost



44.6

CY

$11.38

$507

use C08a cost



Sluice Gate, 36"x36"



1.0

EA

$17,217.04

$17,217





CIP Wall, 12" thk, 6 ft tall



9.6

CY

$737.64

$7,049





Wall Rebar @ 200 #/cy



1911.1

LB

$1.79

$3,412





CIP Wall Footing, 3 wide x 2' tall



9.6

CY

$496.76

$4,747





Footing Rebar @ 150 #/cy



1433.3

LB

$1.79

$2,559





CIP Slab, 12" thk



4.3

CY

$295.88

$1,260





Footing Rebar @ 150 #/cy



638.9

LB

$1.79

$1,140





Misc Detail Allowance



20%

LS

$0.00

$11,702





Sales Tax on Materials



5%





$2,339









Total Direct Unit Cost



$72,500.00

$72,549



Page 3 of 11


-------
TABLE D-31

Alternative RP- 2: Silverton Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site











2009 Total











2009 Direct

Direct Capital



Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

7-10 Pipeline -18" CHDPE, 6' to Invert



1

LF





4.5' cover

Demo ACP Roadway



1.4

SY

$12.55

$17



Excavate Trench



1.1

CY

$3.92

$4



Bed & Zone



0.3

CY

$46.86

$13

1/2 mile one way average

Imported Backfill



0.7

CY

$29.94

$22



Haul & Dispose at Repository



1.1

CY

$5.49

$6

assume all but rock is wasted, 5 mile 1 way

Repository Cost



1.1

CY

$11.38

$12

use C08a cost

Trench Safety



1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA

Pipe, 18" CPE Pipe



1

LF

$30.71

$31

350'/day

ACP Pavement, 4" thk



0.3

TON

$70.00

$22



CSBC, 6" thk



0.2

CY

$31.26

$7



Flagger



0.05

HR

$60.14

$3



Misc Detail Allowance



10%

LS

$0.00

$12

road maint & repair, testing, detection tape, etc

Sales Tax on Materials



5%





$3





Total Direct Unit Cost





$160.00

$158



11,19,20 Pipeline -36" CHDPE, 6' to Invert



1

LF





3' cover

Demo ACP Roadway



1.6

SY

$12.55

$20



Excavate Trench



1.4

CY

$3.92

$6



Bed & Zone



0.5

CY

$46.86

$24

1/2 mile one way average

Imported Backfill



0.7

CY

$29.94

$20



Haul & Dispose at Repository



1.4

CY

$5.49

$8

assume all but rock is wasted, 5 mile 1 way

Repository Cost



1.4

CY

$11.38

$16

use C08a cost

Trench Safety



1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA

Pipe, 36" CPE Pipe



1

LF

$80.83

$81

200'/day

ACP Pavement, 4" thk



0.4

TON

$70.00

$25



CSBC, 6" thk



0.3

CY

$31.26

$8



Flagger



0.08

HR

$60.14

$5



Misc Detail Allowance



10%

LS

$0.00

$19

road maint & repair, testing, detection tape, etc

Sales Tax on Materials



5%





$6





Total Direct Unit Cost





$240.00

$242



Page 4 of 11


-------
TABLE D-31

Alternative RP- 2: Silverton Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site











2009 Total











2009 Direct

Direct Capital



Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

12-18 Pipeline - 36" CHDPE, 7.5' to Invert



1

LF





4.5' cover

Demo ACP Roadway



1.9

SY

$12.55

$24



Excavate Trench



2.1

CY

$3.92

$8



Bed & Zone



0.5

CY

$46.86

$24

1/2 mile one way average

Imported Backfill



1.3

CY

$29.94

$39



Haul & Dispose at Repository



2.1

CY

$5.49

$11

assume all but rock is wasted, 5 mile 1 way

Repository Cost



2.1

CY

$11.38

$24

use C08a cost

Trench Safety



1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA

Pipe, 36" CPE Pipe



1

LF

$80.83

$81

200'/day

ACP Pavement, 4" thk



0.4

TON

$70.00

$30



CSBC, 6" thk



0.3

CY

$31.26

$10



Flagger



0.08

HR

$60.14

$5



Misc Detail Allowance



10%

LS

$0.00

$23

road maint & repair, testing, detection tape, etc

Sales Tax on Materials



5%





$7





Total Direct Unit Cost





$290.00

$290



21 Pipeline - 42" CHDPE, 5.5' to Invert



1

LF





2' cover

Demo ACP Roadway



1.5

SY

$12.55

$19



Excavate Trench



1.4

CY

$3.92

$5



Bed & Zone



0.6

CY

$46.86

$29

1/2 mile one way average

Imported Backfill



0.4

CY

$29.94

$12



Haul & Dispose at Repository



1.4

CY

$5.49

$8

assume all but rock is wasted, 5 mile 1 way

Repository Cost



1.4

CY

$11.38

$16

use C08a cost

Trench Safety



1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA

Pipe, 42" CPE Pipe



1

LF

$118.68

$119

150'/day

ACP Pavement, 4" thk



0.3

TON

$70.00

$24



CSBC, 6" thk



0.3

CY

$31.26

$8



Flagger



0.11

HR

$60.14

$6



Misc Detail Allowance



10%

LS

$0.00

$23

road maint & repair, testing, detection tape, etc

Sales Tax on Materials



5%





$7





Total Direct Unit Cost





$280.00

$280



Page 5 of 11


-------
TABLE D-31

Alternative RP- 2: Silverton Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site















2009 Total















2009 Direct

Direct Capital







Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

22

Manhole 48" 6 to 8 ft Depth





1

EA









Demo ACP Roadway





7.1

SY

$12.55

$89





Excavate Trench





19.0

CY

$3.92

$74





Bed & Zone





0.0

CY

$46.86

$0

1/2 mile one way average



Imported Backfill





15.2

CY

$29.94

$456





Haul & Dispose at Repository





19.0

CY

$5.49

$104

assume all but rock is wasted, 5 mile 1 way



Repository Cost





19.0

CY

$11.38

$216

use C08a cost



Trench Safety





1

EA

$25.00

$25

trench box



Dewatering: Two Sump Pmps





0

HR

$12.00

$0

NA



48" Manhole





1

EA

$2,776.78

$2,777





ACP Pavement, 4" thk





1.6

TON

$70.00

$113





CSBC, 6" thk





1.2

CY

$31.26

$37





Flagger





8.00

HR

$60.14

$481





Misc Detail Allowance





10%

LS

$0.00

$405

road maint & repair, testing, detection tape, etc



Sales Tax on Materials





5%





$112









Total Direct Unit Cost





$4,890.00

$4,890



23

Furnish and Install Storm Drain and Inlet



1

EA





3' cover, 25 ft long



Demo ACP Roadway





26.4

SY

$12.55

$331





Excavate Trench





17.1

CY

$3.92

$67





Bed & Zone





7.0

CY

$46.86

$328

1/2 mile one way average



Imported Backfill





8.5

CY

$29.94

$254





Haul & Dispose at Repository





17.1

CY

$5.49

$94

assume all but rock is wasted, 5 mile 1 way



Repository Cost





17.1

CY

$11.38

$195

use C08a cost



Trench Safety





25

LF

$5.00

$125

trench box



Dewatering: Two Sump Pmps





0

HR

$12.00

$0

NA



Pipe, 18" CPE Pipe





25

LF

$30.71

$768

350'/day



Grated concrete inlet structure





1

EA

$2,758.50

$2,759





ACP Pavement, 4" thk





6.0

TON

$70.00

$421





CSBC, 6" thk





4.4

CY

$31.26

$137





Flagger





0.05

HR

$60.14

$3





Misc Detail Allowance





10%

LS

$0.00

$519

road maint & repair, testing, detection tape, etc



Sales Tax on Materials





5%





$129









Total Direct Unit Cost





$6,130.00

$6,131



Page 6 of 11


-------
TABLE D-31

Alternative RP- 2: Silverton Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

West of Western Avenue













1-3 Pipeline -16" CHDPE, 6' to Invert



1

LF





4.5' cover

Demo ACP Roadway



1.4

SY

$12.55

$17



Excavate Trench



1.0

CY

$3.92

$4



Bed & Zone



0.3

CY

$46.86

$12

1/2 mile one way average

Imported Backfill



0.7

CY

$29.94

$22



Haul & Dispose at Repository



1.0

CY

$5.49

$6

assume all but rock is wasted, 5 mile 1 way

Repository Cost



1.0

CY

$11.38

$12

use C08a cost

Trench Safety



1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA

Pipe, 16" CPE Pipe (Price as 15" CPE)



1

LF

$26.63

$27

350'/day

ACP Pavement, 4" thk



0.3

TON

$70.00

$22



CSBC, 6" thk



0.2

CY

$31.26

$7



Flagger



0.05

HR

$60.14

$3



Misc Detail Allowance



10%

LS

$0.00

$12

road maint & repair, testing, detection tape, etc

Sales Tax on Materials



5%





$3





Total Direct Unit Cost





$150.00

$151



4 Pipeline-18" CHDPE, 6' to Invert



1

LF





4.5' cover

Demo ACP Roadway



1.4

SY

$12.55

$17



Excavate Trench



1.1

CY

$3.92

$4



Bed & Zone



0.3

CY

$46.86

$13

1/2 mile one way average

Imported Backfill



0.7

CY

$29.94

$22



Haul & Dispose at Repository



1.1

CY

$5.49

$6

assume all but rock is wasted, 5 mile 1 way

Repository Cost



1.1

CY

$11.38

$12

use C08a cost

Trench Safety



1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA

Pipe, 18" CPE Pipe



1

LF

$30.71

$31

350'/day

ACP Pavement, 4" thk



0.3

TON

$70.00

$22



CSBC, 6" thk



0.2

CY

$31.26

$7



Flagger



0.05

HR

$60.14

$3



Misc Detail Allowance



10%

LS

$0.00

$12

road maint & repair, testing, detection tape, etc

Sales Tax on Materials



5%





$3





Total Direct Unit Cost





$160.00

$158



Page 7 of 11


-------
TABLE D-31

Alternative RP- 2: Silverton Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site











2009 Total











2009 Direct

Direct Capital



Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

5-9 Pipeline - 20" CHDPE, 6.5' to Invert



1

LF





4.83' cover

Demo ACP Roadway



1.5

SY

$12.55

$19



Excavate Trench



1.3

CY

$3.92

$5



Bed & Zone



0.3

CY

$46.86

$14

1/2 mile one way average

Imported Backfill



0.9

CY

$29.94

$27



Haul & Dispose at Repository



1.3

CY

$5.49

$7

assume all but rock is wasted, 5 mile 1 way

Repository Cost



1.3

CY

$11.38

$15

use C08a cost

Trench Safety



1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA

Pipe, 20" CPE Pipe



1

LF

$36.41

$36

330'/day

ACP Pavement, 4" thk



0.3

TON

$70.00

$24



CSBC, 6" thk



0.3

CY

$31.26

$8



Flagger



0.05

HR

$60.14

$3



Misc Detail Allowance



10%

LS

$0.00

$14

road maint & repair, testing, detection tape, etc

Sales Tax on Materials



5%





$4





Total Direct Unit Cost





$180.00

$181



10 Pipeline - 22" CHDPE, 5' to Invert



1

LF





4.83' cover

Demo ACP Roadway



1.1

SY

$12.55

$14



Excavate Trench



0.8

CY

$3.92

$3



Bed & Zone



0.3

CY

$46.86

$14

1/2 mile one way average

Imported Backfill



0.4

CY

$29.94

$11



Haul & Dispose at Repository



0.8

CY

$5.49

$4

assume all but rock is wasted, 5 mile 1 way

Repository Cost



0.8

CY

$11.38

$9

use C08a cost

Trench Safety



1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA

Pipe, 22" CPE Pipe (Price as 24" CPE)



1

LF

$45.65

$46

330'/day

ACP Pavement, 4" thk



0.3

TON

$70.00

$18



CSBC, 6" thk



0.2

CY

$31.26

$6



Flagger



0.05

HR

$60.14

$3



Misc Detail Allowance



10%

LS

$0.00

$12

road maint & repair, testing, detection tape, etc

Sales Tax on Materials



5%





$3





Total Direct Unit Cost





$150.00

$147



Page 8 of 11


-------
TABLE D-31

Alternative RP- 2: Silverton Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site















2009 Total















2009 Direct

Direct Capital







Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

11

Manhole 48" 6 to 8 ft Depth





1

EA









Demo ACP Roadway





7.1

SY

$12.55

$89





Excavate Trench





19.0

CY

$3.92

$74





Bed & Zone





0.0

CY

$46.86

$0

1/2 mile one way average



Imported Backfill





15.2

CY

$29.94

$456





Haul & Dispose at Repository





19.0

CY

$5.49

$104

assume all but rock is wasted, 5 mile 1 way



Repository Cost





19.0

CY

$11.38

$216

use C08a cost



Trench Safety





1

EA

$25.00

$25

trench box



Dewatering: Two Sump Pmps





0

HR

$12.00

$0

NA



48" Manhole





1

EA

$2,776.78

$2,777





ACP Pavement, 4" thk





1.6

TON

$70.00

$113





CSBC, 6" thk





1.2

CY

$31.26

$37





Flagger





8.00

HR

$60.14

$481





Misc Detail Allowance





10%

LS

$0.00

$405

road maint & repair, testing, detection tape, etc



Sales Tax on Materials





5%





$112









Total Direct Unit Cost





$4,890.00

$4,890



12

Furnish and Install Storm Drain and Inlet



1

EA





3' cover, 25 ft long



Demo ACP Roadway





26.4

SY

$12.55

$331





Excavate Trench





17.1

CY

$3.92

$67





Bed & Zone





7.0

CY

$46.86

$328

1/2 mile one way average



Imported Backfill





8.5

CY

$29.94

$254





Haul & Dispose at Repository





17.1

CY

$5.49

$94

assume all but rock is wasted, 5 mile 1 way



Repository Cost





17.1

CY

$11.38

$195

use C08a cost



Trench Safety





25

LF

$5.00

$125

trench box



Dewatering: Two Sump Pmps





0

HR

$12.00

$0

NA



Pipe, 18" CPE Pipe





25

LF

$30.71

$768

350'/day



Grated concrete inlet structure





1

EA

$2,758.50

$2,759





ACP Pavement, 4" thk





6.0

TON

$70.00

$421





CSBC, 6" thk





4.4

CY

$31.26

$137





Flagger





0.05

HR

$60.14

$3





Misc Detail Allowance





10%

LS

$0.00

$519

road maint & repair, testing, detection tape, etc



Sales Tax on Materials





5%





$129









Total Direct Unit Cost





$6,130.00

$6,131



Page 9 of 11


-------
TABLE D-31

Alternative RP- 2: Silverton Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

	Description	Quantity Unit Capital Unit Cost	Cost	Comments

Unnamed Creek

Replace 12" Culverts w/ 22" CMP Culvert



24

LF





3' cover, done in summer, no dewatering needed,













keep one lane open

Sawcut & Remove Pavement



0.0

SY

$12.55

$0



Remove & Dispose Existing Culvert, 1-18" CMP



24

LF

$10.46

$251



Excavate Trench



19.8

CY

$7.84

$155

account for pipe removal & loading, less pipe

Bed & Zone



7.9

CY

$46.86

$369

1/2 mile one way average

Imported Backfill



9.5

CY

$24.94

$238

assume all wasted to repository

Haul & Dispose at Repository



19.8

CY

$5.49

$108

assume all but rock is wasted, 5 mile 1 way

Repository Cost



19.8

CY

$11.38

$225

use C08a cost

Trench Safety



24

LF

$5.00

$120

trench box

Dewatering: Two Sump Pmps



0

HR

$12.00

$0

none requred

56" CMP Pipe



24

LF

$124.52

$2,988

75'/day

Headwall/Miter



1

EA

$1,200.00

$1,200

allowance

Restoration - Base Course & Pavement Patch



0.0

SY

$22.00

$0

subcontract

Misc Detail Allowance



20%

LS

$0.00

$1,064

minor traffic control, TESC, etc

Sales Tax on Materials



5%





$151





Total Direct Unit Cost





$290.00

$6,869



Reconstruct Exist Channel w/12' wx 3'd, XS 1



1,115

LF







Clear, Grub & Dispose



1.0

AC

$6,514.75

$6,670



Diversion/Care of Water



0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0



Excavate Channel



929.2

CY

$14.80

$13,750



Prep & Grade Channel



1,115

LF

$7.84

$8,744



Haul & Dispose at Repository



929.2

CY

$5.49

$5,101

assume all but rock is wasted, 5 mile 1 way

Repository Cost



929.2

CY

$11.38

$10,574

use C08a cost

Imported Fill Material



0.0

CY

$53.33

$0

imported, difficult operation

Misc Detail Allowance



10%

LS

$0.00

$2,916

access.TESC, restoration, etc

Sales Tax on Materials



5%





$0





Total Direct Unit Cost





$43.00

$47,755



Page 10 of 11


-------
TABLE D-31

Alternative RP- 2: Silverton Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

	Description	Quantity Unit Capital Unit Cost	Cost	Comments

Notes:

ACP = asphalt concrete paving

CIP = cast-in-place

CMP = corrugated metal pipe

CPE = polyethylene

CY = cubic yards

EA = each

HR = hour

LB = pound(s)

LS = lump sum

SF = square feet

SY = square yards

TESC = temporary erosion and sediment control

NOTE: The above costs are presented rounded to three significant figures
NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal
NOTE: The above cost opinion is in 2009 dollars and does not include future
escalation. The order-of-magnitude cost opinion shown has been prepared for
guidance in project evaluation from the information available at the time of preparation.

The final costs of the project will depend on actual labor and material costs, actual site
conditions, productivity, competitive market conditions, the final project scope, the final
project schedule, and other variable factors. As a result, the final project costs will vary
from those presented above. Because of these factors, funding needs must be
carefully reviewed prior to making specific financial decisions or establishing final
budgets.

Page 11 of 11


-------

-------
TABLE D-32

Alternative RP-2: Wallace Cost Summary

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Description

Quantity Unit

2009 Direct
Capital Unit
Cost

2009 Total
Direct Capital
Cost

2009 Total
Direct and
Indirect Capital
Cost

Printer's Creek

1	Furnish And Install New 10' Deep, 5' Diameter Precast Manhole

2	Remove Existing Inlet Structure

3	Construct New Inlet Structure

EA
LS
LS

$7,630
$9,900
$41,000

$7,630
$9,900
$41,000

$12,971
$16,830
$69,700

Subtotal Rounded $100,000

Npv For 30-Year O&M Cost
Total NPV cost at 30 years

$99,000
$199,000

Notes:

NPV= Net Present Value
EA = each
LS = lump sum

O&M = operation and maintenance

Assumptions:

All excavated material is hauled to repository and replaced with imported material.
Pipe cover is 3' over pipe

All work will be performed in the summer and therefore no water issues exist.

See estimate details for additional assumptions

Total indirect cost assumes 70% of Total Direct Capital Cost

Page 1 of 1


-------

-------
TABLE D-33

Alternative RP-2: Wallace Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

Description

Quantity

Unit

Capital Unit Cost

Cost

Comments

Printer's Creek











1 Manhole 5' Diameter, 10' Depth

50

EA







Demo ACP Roadway

9.0

SY

$12.55

$113



Excavate T rench

30.0

CY

$3.92

$118



Bed & Zone

0.0

CY

$46.86

$0

1/2 mile one way average

Imported Backfill

22.7

CY

$29.94

$681



Haul & Dispose at Repository

30.0

CY

$5.49

$165

assume all but rock is wasted, 5 mile 1 way

Repository Cost

30.0

CY

$11.38

$341

use C08a cost

Trench Safety

1

EA

$25.00

$25

trench box

Dewatering: Two Sump Pmps

0

HR

$12.00

$0

NA

60" Manhole, 10 feet deep

1

EA

$4,718.35

$4,718



ACP Pavement, 4" thk

2.1

TON

$70.00

$144



CSBC, 6" thk

1.5

CY

$31.26

$47



Flagger

8.00

HR

$60.14

$481



Misc Detail Allowance

10%

LS

$0.00

$633

road maint & repair, testing, detection tape, etc

Sales Tax on Materials

5%





$163





Total Direct Unit Cost



$7,630.00

$7,628



2 Remove Existing Inlet Structure

1

EA







Demo Existing inlet structure

1

LS

$6,273.60

$6,274



Haul & Dispose

1

LS

$1,891.84

$1,892

assume all is wasted, 5 mile 1 way

Misc Detail Allowance

20%

LS

$0.00

$1,633



Sales Tax on Materials

5%





$132





Total Direct Unit Cost



$9,900.00

$9,930



3 New Inlet Structure at Printer's Creek

1

EA







Riprap

15

CY

$72.91

$1,080

imported, difficult operation

20'x6' Steel Trash Rack at outlet

1

EA

$15,105.31

$15,105

Use $100/SF cost

Grade existing pond bottom

400

SF

$3.14

$1,255



Excavate for walls

30

CY

$3.92

$116



Imported Backfill

16

CY

$29.94

$466



Haul & Dispose at Repository

30

CY

$5.49

$163

assume all but rock is wasted, 5 mile 1 way

Repository Cost

30

CY

$11.38

$337

use C08a cost

CIP Wall, 12" thk, 8 ft tall

7

CY

$737.64

$5,464



Wall Rebar @ 200 #/cy

1481

LB

$1.79

$2,645



CIP Wall Footing, 2' wide x 2' tall

7

CY

$496.76

$3,312



Footing Rebar @150 #/cy

1000

LB

$1.79

$1,785



Page 1 of 2


-------
TABLE D-33

Alternative RP-2: Wallace Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site



Description

Quantity

Unit

2009 Direct
Capital Unit Cost

2009 Total
Direct Capital
Cost

Comments

CIP Slab, 12" thk
Footing Rebar @150 #/cy
Misc Detail Allowance



3
389
20%

CY
LB
LS

$295.88
$1.79
$0.00

$767
$694
$6,638



Sales Tax on Materials



5%

Total Direct Unit Cost



$41,000.00

$1,196
$41,023



Notes:

ACP = asphalt concrete paving

CIP = cast-in-place

CY = cubic yards

EA = each

LB = pound(s)

LS = lump sum

SY = square yards

NOTE: The above costs are presented rounded to three significant figures

NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of-30
percent to +50 percent (-30/+50%).

NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-
magnitude cost opinion shown has been prepared for guidance in project evaluation from the information
available at the time of preparation. The final costs of the project will depend on actual labor and material
costs, actual site conditions, productivity, competitive market conditions, the final project scope, the final
project schedule, and other variable factors. As a result, the final project costs will vary from those
presented above. Because of these factors, funding needs must be carefully reviewed prior to making
specific financial decisions or establishing final budgets.

Page 2 of 2


-------
TABLE D-34

Alternative RP-2: Mullan Cost Summary

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site

Description

Quantity Unit

2009 Direct
Capital Unit
Cost

2009 Total
Direct Capital
Cost

2009 Total
Direct and
Indirect Capital
Cost

3rd Street Neighborhood

1	Construct Asphalt Lined Ditch (2.5' Deep With 1:1 Side Slopes)

2	Install 55 Lf Of 24" Dia Rep Pipe, 2' Cover With Asphalt Reconstruction

3	Remove Existing Culvert And Install 40 Lf Of 24" Dia Rep (Culvert 1), 1 Ft Cover
With Pavement Restoration

4	Remove Existing Culvert And Install 40 Lf Of 24" Dia Rep (Culvert 2), 1 Ft Cover
With Pavement Restoration

5	Remove Existing Culvert And Install 25 Lf Of 24" Dia Rep (Culvert 3), 1 Ft Cover
With Pavement Restoration

6	Remove Existing Culvert And Install 40 Lf Of 24" Dia Rep (Culvert 4), 1 Ft Cover
With Pavement Restoration

7	Furnish And Install New 48" Dia Manhole At 6 Ft Depth

8	Furnish And Install New 48" Catch Basin With Sump

Tiger Creek

1	Construct Concrete Inlet Structure (See Plan 316-1, Case A With 8' Long X 4'

Tall Wingwalls And 3' Long X 4' Tall Headwalls)

2	Install 175 Lf Of 24" Cmp. 1 Ft Cover With Sod Surface Restoration

3	Construct Asphalt Lined Ditch (2.5' Deep With 1:1 Side Slopes)

4	Install 30 Lf Of 24" Rep (Culvert 1). 1 Ft Cover With Pavement Restoration

5	Install 30 Lf Of 24" Rep (Culvert 2). 1 Ft Cover With Pavement Restoration

6	Install Rip Rap At Outfall

Miii Creek

1	Regrade And Vegetate 140 Lf Of Stream Banks

2	Construct 4' High X 4' Long Concrete Wingwalls At Culvert Enterance

3	Reconstruct Existing Concrete Open Channel (2.5' H X 4.33' W) To 3' H X 6' W
Concrete Channel

4	Construct 325 Lf Of 3.5' H X 6' W Concrete Box Culvert Along New Alignment
(Culvert 1). Remove 80 Lf Of Existing 3' H X 6' W Concrete Box

5	Plug And Fill Existing Culvert (80 Lf Of 3' X 6' Concrete Box Culvert And 100 Lf
Of 58" Dia Cmp) With Cdf

6	Install Rip Rap At Culvert 1 Outfall

7	Replace Two Existing 32" Cpe Culvert In Parallel With 15' WX 25' L Precast
Concrete Bridge With Footings And Clear Hieght Of 2.5 Ft (Bridge 1)

8	Replace Two Existing 36" Cpe Culvert In Parallel With 15' WX 20' L Precast
Concrete Bridge With Footings And Clear Hieght Of 2.5 Ft (Bridge 2)

9	Excavate And Regrade 50 Lf Of Existing Gravel Road To Provide 1.5 Ft Rolling
Dip

Mill Street

1	Construct Asphalt Lined Ditch (2.5 Ft Deep With 1:1 Side Slopes) Along South
Side Of Mill Street

2	Construct Asphalt Lined Ditch (2.5 Ft Deep With 1:1 Side Slopes) Along North
Side Of Mill Street

3	Construct 10' X 2' X 3 Rock Lined Ditch (Xs 1)

4	Install 60 Lf Of 15" Dia Rep Pipe With 2 Ft Of Cover (Culvert 1)

5	Install 80 Lf Of 15" Dia Rep Pipe With 2 Ft Of Cover (Culvert 2)

6	Install 30 Lf Of 15" Dia Rep Pipe With 2 Ft Of Cover (Culvert 3)

7	Install 50 Lf Of 15" Dia Rep Pipe With 2 Ft Of Cover (Culvert 4)

8	Install Two (2) 25 Lf 15" Rep Culverts With 2 Ft Of Cover (Culvert 5 & 6)

9	Install Two (2) 50 Lf 18" Rep Culverts With 1.5 Ft Of Cover (Culvert 7 & 9)

10	Install 25 Lf Of 18" Dia Cpe Culvert With 1.5 Ft Cover (Culvert 8)

11	Install 25 Lf Of 30" Dia Cpe Culvert Under Trail Of Coeur D'Alenes (Culvert 10). 3
Ft Cover With Pavement Surface Restoration

12	Install New Dual Inlet Catch Basin (ltd Catch Basin Type 6) With 4' Sump

13	Install 15 Cy Rip Rap At Outfall To South Fork Coeur D'Aiene River

Dewey Street Area

Construct Asphalt Lined Ditch (2.5' Deep With 1:1 Side Slopes) Along N Side Of
Lower Dewey St

Construct Asphalt Lined Ditch (2.5' Deep With 1:1 Side Slopes) Along E Side Of
Lower Dewey St (Daylight To Hunter St)

Construct Asphalt Lined Ditch (2.5' Deep With 1:1 Side Slopes) Along E Side Of
Lower Dewey St (Daylight To Mill St)

3400

LF

$25

$85,000

$144,500

55

LF

$160

$8,800

$14,960

40

LF

$150

$6,000

$10,200

40

LF

$150

$6,000

$10,200

25

LF

$150

$3,750

$6,375

40

LF

$150

$6,000

$10,200

1

LF

$4,890

$4,890

$8,313

2

LF

$4,890

$9,780

$16,626

1

EA

$24,600

$24,600

$41,820

175

LF

$130

$22,750

$38,675

750

LF

$25

$18,750

$31,875

30

LF

$150

$4,500

$7,650

30

LF

$150

$4,500

$7,650

10

CY

$82

$820

$1,394

140

LF

$33

$4,620

$7,854

2

EA

$4,510

$9,020

$15,334

175

LF

$574

$100,450

$170,765

325

LF

$624

$202,800

$344,760

1

LS

$27,025

$27,025

$45,943

10

CY

$82

$820

$1,394

1

EA

$160,000

$160,000

$272,000

2

EA

$128,000

$256,000

$435,200

1

LS

$1,880

$1,880

$3,196

960

LF

$25

$24,000

$40,800

925

LF

$25

$23,125

$39,313

390

LF

$101

$39,390

$66,963

60

LF

$110

$6,600

$11,220

80

LF

$110

$8,800

$14,960

30

CY

$110

$3,300

$5,610

50

EA

$110

$5,500

$9,350

1

LS

$5,500

$5,500

$9,350

1

LS

$12,000

$12,000

$20,400

25

LF

$120

$3,000

$5,100

25

LF

$210

$5,250

$8,925

1

EA

$5,367

$5,367

$9,124

15

CY

$82

$1,230

$2,091

100

LF

$25

$2,500

$4,250

280

LF

$25

$7,000

$11,900

365

LF

$25

$9,125

$15,513

Page 1 of 2


-------
TABLE D-34

Alternative RP-2: Mullan Cost Summary

Focused Feasibility Study, Upper Basin of the Coeur d'Aiene River, Bunker Hill Superfund Site



Description

Quantity

Unit

2009 Direct
Capital Unit
Cost

2009 Total
Direct Capital
Cost

2009 Total
Direct and
Indirect Capital
Cost

4

Install 25 Lf Of 18" Rep (Culvert 1). 1.5 Ft Cover With Pavement Restoration

25

LF

$120

$3,000

$5,100

5

Install 25 Lf Of 18" Rep (Culvert 2). 1.5 Ft Cover With Pavement Restoration

25

LF

$120

$3,000

$5,100

6

Install 25 Lf Of 18" Rep (Culvert 3). 1.5 Ft Cover With Gravel Restoration

25

LF

$100

$2,500

$4,250

7

Replace Existing Catch Basin New 4' Deep Inlet With Sump

6

EA

$4,890

$29,340

$49,878

8

Replace 12" Dia Storm Sewer With 18" Dia Cpe Pipe With 3 Ft Of Cover

650

LF

$120

$78,000

$132,600

Copper Street Neighborhood











1

Construct Asphalt Lined Ditch (2.5 Ft Deep With 1:1 Side Slopes) Along South

400

LF

$25

$10,000

$17,000



Side Of Idaho Street











2

Construct Asphalt Lined Ditch (2.5 Ft Deep With 1:1 Side Slopes) Along Idaho

1100

LF

$25

$27,500

$46,750



Street East And West Sides Of Eighth Street











3

Construct Asphalt Lined Ditch (2.5 Ft Deep With 1:1 Side Slopes) Along North

205

LF

$25

$5,125

$8,713



Side Of Oregon Street











4

Construct Asphalt Lined Ditch (2.5 Ft Deep With 1:1 Side Slopes) Along

305

LF

$25

$7,625

$12,963



Montana Street











5

Install Six (6) 25 Lf 18" Rep Culverts With 1.5 Ft Of Cover (Culvert 1 Through 6)

1

LS

$18,000

$18,000

$30,600

6

Install Seven (7) 20 Lf 18" Rep Culverts With 1.5 Ft Of Cover (Culvert 7 Through
1*^

1

LS

$16,800

$16,800

$28,560

7

lo;

Install 310 Lf Of 48" Cmp Culvert With 3.5 Ft Of Cover (Culvert 14 And 15)

310

LF

$400

$124,000

$210,800

8

Install 915 Lf Of New 24" Cpe Storm Pipe With 4 Ft Of Cover

915

LF

$210

$192,150

$326,655

9

Remove Existing Drywell, 4 Exsiting Catch Basins, And 285 Lf Of Existing Storm

1

LS

$17,680

$17,680

$30,056



Drain Pipe Along Idaho Street











10

Furnish And Install New 6' X 6' Concrete Manhole At A Depth Of 8 Ft

1

EA

$11,676

$11,676

$19,849

11

Furnish And Install New 48" Dia Storm Manhole At A Depth Of 6 Ft

4

EA

$4,890

$19,560

$33,252

12

Furnish And Install New Catch Basin With 4' Sump

6

EA

$4,890

$29,340

$49,878

13

Install 15 Cy Rip Rap At Culvert/Pipe Outfall

30

CY

$82

$2,460

$4,182

South End Of 2nd Street











1

Construct 10'X4'X3' Rock Lined Ditch Along West Side Of Second Street (Xs 1)

110

LF

$108

$11,880

$20,196

2

Construct 10'X4'X3' Rock Lined Ditch Along South Side Of The Trail Of The

655

LF

$108

$70,740

$120,258



Coeur D'Alenes (Xs 1)











3

Install 60 Lf Of New 18" Dia Cpe Pipe With 3 Ft Of Cover

60

LF

$120

$7,200

$12,240

4

Install 20 Lf Of New 18" Dia Cpe Pipe Under Trail Of Coeur D'Alenes (Culvert 1).

20

LF

$120

$2,400

$4,080



3 Ft Of Cover With Pavement Surface Restoration.











5

Install New Dual Inlet Catch Basin (ltd Cathc Basin Type 6) With 4 Ft Sump.

1

EA

$5,367

$5,367

$9,124

6

Install Rip Rap At Outfall To Mill Creek

15

CY

$82

$1,230

$2,091









Subtotal Rounded

$3,110,000



NPV for 30-year O&M Cost
Total NPV cost at 30 years









$1,080,000
$4,190,000

Notes:

NPV = Net Present Value
CY = cubic yards
EA = each
LF = linear feet
LS = lump sum

O&M = operation and maintenance
Assumptions:

All excavated material is hauled to repository and replaced with imported material.
Pipe cover is 3' over pipe

All work will be performed in the summer and therefore no water issues exist.

See estimate details for additional assumptions

Total indirect cost assumes 70% of Total Direct Capital Cost

Page 2 of 2


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

	Description	Quantity Unit Capital Unit Cost	Cost	Comments

3rd Street Neighborhood

Construct Asphalt Lined Ditch (2.5 deep w/1:1 slopes)

3,400

LF







Clear, Grub & Dispose

50.0

AC

$6,514.75

$15,255



Diversion/Care of Water

0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0



Excavate Channel

787.0

CY

$14.80

$11,647



Prep & Grade Ditch

3,400

LF

$3.92

$13,331



Haul & Dispose at Repository

787.0

CY

$5.49

$4,321

assume all but rock is wasted, 5 mile 1

Repository Cost

787.0

CY

$11.38

$8,956

use C08a cost

ACP Pavement, 2" thk

301.5

TON

$70.00

$21,103



Imported Fill Material

0.0

CY

$53.33

$0

imported, difficult operation

Misc Detail Allowance

10%

LS

$0.00

$6,134

access.TESC, restoration, etc

Sales Tax on Materials

5%





$1,161





Total Direct Unit Cost



$25.00

$81,907



Pipeline - 24" RCP, 2' Cover Pavement Restoration

1

LF





2' cover

Demo ACP Roadway

1.0

SY

$12.55

$13



Excavate T rench

0.7

CY

$3.92

$3



Bed & Zone

0.4

CY

$46.86

$17

1/2 mile one way average

Imported Backfill

0.2

CY

$29.94

$6



Haul & Dispose at Repository

0.7

CY

$5.49

$4

assume all but rock is wasted, 5 mile 1 way

Repository Cost

0.7

CY

$11.38

$8

use C08a cost

Trench Safety

1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps

0

HR

$12.00

$0

NA

Pipe, 24" RCP Pipe

1

LF

$65.97

$66

RS Means 334113502040

ACP Pavement, 4" thk

0.2

TON

$70.00

$16



CSBC, 6" thk

0.2

CY

$31.26

$5



Flagger

0.08

HR

$60.14

$5



Misc Detail Allowance

10%

LS

$0.00

$13

road maint & repair, testing, detection tape, etc

Sales Tax on Materials

5%





$4





Total Direct Unit Cost



$160.00

$163



Page 1 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site















2009 Total















2009 Direct

Direct Capital







Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

3-6

Pipeline - 24" RCP, 1' Cover Pavement Restoration



1

LF





1' cover



Demo ACP Roadway





0.8

SY

$12.55

$10





Excavate T rench





0.5

CY

$3.92

$2





Bed & Zone





0.4

CY

$46.86

$17

1/2 mile one way average



Imported Backfill





0.1

CY

$29.94

$2





Haul & Dispose at Repository





0.5

CY

$5.49

$3

assume all but rock is wasted, 5 mile 1 way



Repository Cost





0.5

CY

$11.38

$6

use C08a cost



Trench Safety





1

LF

$5.00

$5

trench box



Dewatering: Two Sump Pmps





0

HR

$12.00

$0

NA



Pipe, 24" RCP Pipe





1

LF

$65.97

$66

RS Means 334113502040



ACP Pavement, 4" thk





0.2

TON

$70.00

$12





CSBC, 6" thk





0.1

CY

$31.26

$4





Flagger





0.08

HR

$60.14

$5





Misc Detail Allowance





10%

LS

$0.00

$12

road maint & repair, testing, detection tape, etc



Sales Tax on Materials





5%





$3









Total Direct Unit Cost





$150.00

$147



7,8

Manhole 48" 6 to 8 ft Depth





1

EA









Demo ACP Roadway





7.1

SY

$12.55

$89





Excavate T rench





19.0

CY

$3.92

$74





Bed & Zone





0.0

CY

$46.86

$0

1/2 mile one way average



Imported Backfill





15.2

CY

$29.94

$456





Haul & Dispose at Repository





19.0

CY

$5.49

$104

assume all but rock is wasted, 5 mile 1 way



Repository Cost





19.0

CY

$11.38

$216

use C08a cost



Trench Safety





1

EA

$25.00

$25

trench box



Dewatering: Two Sump Pmps





0

HR

$12.00

$0

NA



48" Manhole





1

EA

$2,776.78

$2,777





ACP Pavement, 4" thk





1.6

TON

$70.00

$113





CSBC, 6" thk





1.2

CY

$31.26

$37





Flagger





8.00

HR

$60.14

$481





Misc Detail Allowance





10%

LS

$0.00

$405

road maint & repair, testing, detection tape, etc



Sales Tax on Materials





5%





$112









Total Direct Unit Cost





$4,890.00

$4,890



Page 2 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

	Description	Quantity Unit Capital Unit Cost	Cost	Comments

Tiger Creek

New Inlet Structure at Tiger Creek

1

EA







Riprap

14.8

CY

$72.91

$1,080

imported, difficult operation

20'x6' Steel Trash Rack at outlet

1.0

EA

$9,105.31

$9,105

Use $100/SF cost

Grade existing pond bottom

400.0

SF

$3.14

$1,255



Excavate for walls

14.1

CY

$3.92

$55



Imported Backfill

6.2

CY

$29.94

$186



Haul & Dispose at Repository

14.1

CY

$5.49

$77

assume all but rock is wasted, 5 mile 1

Repository Cost

14.1

CY

$11.38

$160

use C08a cost

CIP Wall, 12" thk, 4 ft tall

2.8

CY

$737.64

$2,076



Wall Rebar @ 200 #/cy

563.0

LB

$1.79

$1,005



CIP Wall Footing, 2' wide x 2' tall

5.0

CY

$496.76

$2,502



Footing Rebar @150 #/cy

755.6

LB

$1.79

$1,349



CIP Slab, 12" thk

2.0

CY

$295.88

$592



Footing Rebar @150 #/cy

300.0

LB

$1.79

$536



Misc Detail Allowance

20%

LS

$0.00

$3,996



Sales Tax on Materials

5%





$653





Total Direct Unit Cost



$24,600.00

$24,627



Pipeline - 24" RCP, 1' Cover Sod Restoration

1

LF





1' cover

Clear, Grub & Dispose

0.0

AC

$6,514.75

$4



Excavate T rench

0.5

CY

$3.92

$2



Bed & Zone

0.4

CY

$46.86

$17

1/2 mile one way average

Imported Backfill

0.1

CY

$29.94

$2



Haul & Dispose at Repository

0.5

CY

$5.49

$3

assume all but rock is wasted, 5 mile 1 way

Repository Cost

0.5

CY

$11.38

$6

use C08a cost

Trench Safety

1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps

0

HR

$12.00

$0

NA

Pipe, 24" RCP Pipe

1

LF

$65.97

$66

RS Means 334113502040

SOD

1.6

SY

$4.50

$7



Topsoil, 6" thk

0.3

CY

$27.94

$7



Flagger

0.00

HR

$60.14

$0



Misc Detail Allowance

10%

LS

$0.00

$11

road maint & repair, testing, detection tape, etc

Sales Tax on Materials

5%





$3





Total Direct Unit Cost



$130.00

$133



Page 3 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site













2009 Total













2009 Direct

Direct Capital





Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

3

Construct Asphalt Lined Ditch (2.5 deep w/1:1 slopes)



3,400

LF









Clear, Grub & Dispose



2.3

AC

$6,514.75

$15,255





Diversion/Care of Water



0

LF

$10.00

$0





Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0





Excavate Channel



787.0

CY

$14.80

$11,647





Prep & Grade Ditch



3,400

LF

$3.92

$13,331





Haul & Dispose at Repository



787.0

CY

$5.49

$4,321

assume all but rock is wasted, 5 mile 1 way



Repository Cost



787.0

CY

$11.38

$8,956

use C08a cost



ACP Pavement, 2" thk



301.5

TON

$70.00

$21,103





Imported Fill Material



0.0

CY

$53.33

$0

imported, difficult operation



Misc Detail Allowance



10%

LS

$0.00

$6,134

access.TESC, restoration, etc



Sales Tax on Materials



5%





$1,161







Total Direct Unit Cost





$25.00

$81,907



4,5

Pipeline - 24" RCP, 1' Cover Pavement Restoration



1

LF





1' cover



Demo ACP Roadway



0.8

SY

$12.55

$10





Excavate T rench



0.5

CY

$3.92

$2





Bed & Zone



0.4

CY

$46.86

$17

1/2 mile one way average



Imported Backfill



0.1

CY

$29.94

$2





Haul & Dispose at Repository



0.5

CY

$5.49

$3

assume all but rock is wasted, 5 mile 1 way



Repository Cost



0.5

CY

$11.38

$6

use C08a cost



Trench Safety



1

LF

$5.00

$5

trench box



Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA



Pipe, 24" RCP Pipe



1

LF

$65.97

$66

RS Means 334113502040



ACP Pavement, 4" thk



0.2

TON

$70.00

$12





CSBC, 6" thk



0.1

CY

$31.26

$4





Flagger



0.08

HR

$60.14

$5





Misc Detail Allowance



10%

LS

$0.00

$12

road maint & repair, testing, detection tape, etc



Sales Tax on Materials



5%





$3







Total Direct Unit Cost





$150.00

$147



6

Rip Rap



1

EA









Riprap



1

CY

$72.91

$73

imported, difficult operation



Misc Detail Allowance



10%

LS

$0.00

$7





Sales Tax on Materials



5%





$2







Total Direct Unit Cost





$82.00

$82



Page 4 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Description

Quantity

Unit

2009 Direct
Capital Unit Cost

2009 Total
Direct Capital
Cost

Comments

Mill Creek











1 Regrade and Revegetate Stream Banks

140

LF







Clear, Grub & Dispose

0.1

AC

$6,514.75

$838



Diversion/Care of Water

0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0



Excavate Channel

0.0

CY

$14.80

$0



Prep & Grade Channel

140

LF

$7.84

$1,098



Haul & Dispose at Repository

0.0

CY

$5.49

$0

assume all but rock is wasted, 5 mile 1

Repository Cost

0.0

CY

$11.38

$0

use C08a cost

Planting along stream banks

140

LF

$15.00

$2,100

allowance

Misc Detail Allowance

10%

LS

$0.00

$404

access.TESC, restoration, etc

Sales Tax on Materials

5%

Total Direct Unit Cost

$33.00

$116
$4,554

Construct 4' H x 4' L Wingwalls at Culvert

1

EA







Riprap

8

CY

$72.91

$608

imported, difficult operation

Grade existing pond bottom

225

SF

$3.14

$706



Excavate for walls

5

CY

$3.92

$19



Imported Backfill

2

CY

$29.94

$71



Haul & Dispose at Repository

5

CY

$5.49

$26

assume all but rock is wasted, 5 mile 1

Repository Cost

5

CY

$11.38

$54

use C08a cost

CIP Wall, 12" thk, 4 ft tall

1

CY

$737.64

$874



Wall Rebar @ 200 #/cy

237

LB

$1.79

$423



CIP Wall Footing, 2' wide x 2' tall

1

CY

$496.76

$589



Footing Rebar @150 #/cy

178

LB

$1.79

$317



Misc Detail Allowance

20%

LS

$0.00

$737



Sales Tax on Materials

5%





$83





Total Direct Unit Cost



$4,510.00

$4,507



Page 5 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site











2009 Total











2009 Direct

Direct Capital





Description

Quantity

Unit

Capital Unit Cost

Cost

Comments

3

Reconstruct Channel w/ 3' H Wall, 6' W Concrete Channel

175

LF









Clear, Grub & Dispose

0.2

AC

$6,514.75

$1,047





Diversion/Care of Water

0

LF

$10.00

$0





Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0





Demo existing 2.5' H x 4.33' W

175

LF

$11.84

$2,072





Excavate Channel

137.2

CY

$14.80

$2,031





Prep & Grade Channel

175

LF

$7.84

$1,372





Haul & Dispose at Repository

137.2

CY

$5.49

$753

assume all but rock is wasted, 5 mile 1 way



Repository Cost

137.2

CY

$11.38

$1,562

use C08a cost



Imported Fill Material

38.9

CY

$53.33

$2,074

imported, difficult operation



CIP Wall, 12" thk, 3' tall

38.9

CY

$737.64

$28,686





Wall Rebar @ 200 #/cy

7777.8

LB

$1.79

$13,884





CIP Slab, 12" thk, 10' wide

65

CY

$295.88

$19,177





Footing Rebar @150 #/cy

9,722

LB

$1.79

$17,355





Misc Detail Allowance

10%

LS

$0.00

$8,770

access.TESC, restoration, etc



Sales Tax on Materials

5%





$1,531





Total Direct Unit Cost





$574.00

$100,315



4

Construct 3.5' H x 6' W Concrete Box Culvert

325

LF









Clear, Grub & Dispose

0.3

AC

$6,514.75

$1,944





Diversion/Care of Water

0

LF

$10.00

$0





Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0





Demo existing 3' H x 6' W

80

LF

$11.84

$947





Excavate Channel

379.2

CY

$14.80

$5,611





Prep & Grade Channel

325

LF

$7.84

$2,549





Haul & Dispose at Repository

379.2

CY

$5.49

$2,082

assume all but rock is wasted, 5 mile 1 way



Repository Cost

379.2

CY

$11.38

$4,315

use C08a cost



Imported Fill Material

84.3

CY

$53.33

$4,493

imported, difficult operation



CIP Wall, 12" thk, 3' tall

84.3

CY

$737.64

$62,153





Wall Rebar @ 200 #/cy

16851.9

LB

$1.79

$30,082





CIP Slab, 12" thk, 10' wide

120

CY

$295.88

$35,615





Footing Rebar @150 #/cy

18,056

LB

$1.79

$32,231





Misc Detail Allowance

10%

LS

$0.00

$17,563

access.TESC, restoration, etc



Sales Tax on Materials

5%





$3,072





Total Direct Unit Cost





$624.00

$202,657



Page 6 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site













2009 Total













2009 Direct

Direct Capital





Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

5

Plug and Fill Existing Culvert



1

LS









Fill 3'x6' culvert with CDF



53

CY

$100.00

$5,333

leave open, use as overflow storage



Pumping Costs



53

CY

$80.82

$4,310





Fill 58" Dia CMP with CDF



68

CY

$100.00

$6,786

leave open, use as overflow storage



Pumping Costs



68

CY

$80.82

$5,485





Misc Detail Allowance



20%

LS

$0.00

$4,383





Sales Tax on Materials



5%





$727







Total Direct Unit Cost





$27,025.00

$27,024



6

Rip Rap



1

EA









Riprap



1

CY

$72.91

$73

imported, difficult operation



Misc Detail Allowance



10%

LS

$0.00

$7





Sales Tax on Materials



5%





$2







Total Direct Unit Cost





$82.00

$82



7

Replace Existing Culvert w/ New 15'x25' Span Bridge



1

EA





3' cover, done in summer, no dewatering needed,















keep one lane open



Sawcut & Remove Pavement



41.7

SY

$12.55

$523





Remove & Dispose Exist Culverts



1

LS

$591.92

$592





Excavate T rench



48.6

CY

$7.84

$381

account for pipe removal & loading, less pipe



Bed & Zone



0.0

CY

$46.86

$0

1/2 mile one way average



Imported Backfill



0.0

CY

$9.94

$0

assume all wasted to repository



Haul & Dispose at Repository



48.6

CY

$5.49

$267

assume all but rock is wasted, 5 mile 1 way



Repository Cost



48.6

CY

$11.38

$553

use C08a cost



Trench Safety



0

LF

$5.00

$0

trench box



CIP Wall, 12" thk, 2.5' tall +1 bury



3.2

CY

$737.64

$2,391





Wall Rebar @ 200 #/cy



648.1

LB

$1.79

$1,157





CIP Wall, 12" thk, 2.5' tall +1 bury



3.2

CY

$737.64

$2,391





Wall Rebar @ 200 #/cy



648.1

LB

$1.79

$1,157





CIP Wall Footing, 2.5 wide x 1.5' tall



6.9

CY

$496.76

$3,450





Footing Rebar @150 #/cy



1041.7

LB

$1.79

$1,859





New Bridge & Abutments - Concrete



375

SF

$300.00

$112,500

based on road & bridge file



Misc Detail Allowance



20%

LS

$0.00

$25,280

minor traffic control, TESC, etc



Sales Tax on Materials



5%





$6,977







Total Direct Unit Cost





$160,000.00

$159,478



Page 7 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









2009 Total









2009 Direct

Direct Capital



Description

Quantity

Unit

Capital Unit Cost

Cost

Comments

Replace Existing Culvert w/ New 15'x20' Span Bridge

1

EA





3' cover, done in summer, no dewatering needed,
keep one lane open

Sawcut & Remove Pavement

33.3

SY

$12.55

$418



Remove & Dispose Exist Culverts

1

LS

$591.92

$592



Excavate T rench

38.9

CY

$7.84

$305

account for pipe removal & loading, less pipe

Bed & Zone

0.0

CY

$46.86

$0

1/2 mile one way average

Imported Backfill

0.0

CY

$9.94

$0

assume all wasted to repository

Haul & Dispose at Repository

38.9

CY

$5.49

$214

assume all but rock is wasted, 5 mile 1 way

Repository Cost

38.9

CY

$11.38

$443

use C08a cost

Trench Safety

0

LF

$5.00

$0

trench box

CIP Wall, 12" thk, 2.5' tall +1 bury

2.6

CY

$737.64

$1,912



Wall Rebar @ 200 #/cy

518.5

LB

$1.79

$926



CIP Wall, 12" thk, 2.5' tall +1 bury

2.6

CY

$737.64

$1,912



Wall Rebar @ 200 #/cy

518.5

LB

$1.79

$926



CIP Wall Footing, 2.5 wide x 1.5' tall

5.6

CY

$496.76

$2,760



Footing Rebar @150 #/cy

833.3

LB

$1.79

$1,488



New Bridge & Abutments - Concrete

300

SF

$300.00

$90,000

based on road & bridge file

Misc Detail Allowance

20%

LS

$0.00

$20,248

minor traffic control, TESC, etc

Sales Tax on Materials	5%	$5,582

Total Direct Unit Cost	$128,000.00 $127,724

Excavate and Regrade Gravel Road

1

LS





5' cover

Excavate Roadway

34.7

CY

$3.92

$136



Place Excavated Material Backfill

34.7

CY

$9.94

$345



Trench Safety

0

LF

$5.00

$0

trench box

CSBC, 6" thk

23.1

CY

$31.26

$724



Flagger

8.00

HR

$60.14

$481



Misc Detail Allowance

10%

LS

$0.00

$169

road maint &

Sales Tax on Materials

5%





$23





Total Direct Unit Cost



$1,880.00

$1,878



Page 8 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

	Description	Quantity Unit Capital Unit Cost	Cost	Comments

Mill Street

Construct Asphalt Lined Ditch (2.5 deep w/1:1 slopes)

3,400

LF







Clear, Grub & Dispose

2.3

AC

$6,514.75

$15,255



Diversion/Care of Water

0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0



Excavate Channel

787.0

CY

$14.80

$11,647



Prep & Grade Ditch

3,400

LF

$3.92

$13,331



Haul & Dispose at Repository

787.0

CY

$5.49

$4,321

assume all but rock is wasted, 5 mile 1

Repository Cost

787.0

CY

$11.38

$8,956

use C08a cost

ACP Pavement, 2" thk

301.5

TON

$70.00

$21,103



Imported Fill Material

0.0

CY

$53.33

$0

imported, difficult operation

Misc Detail Allowance

10%

LS

$0.00

$6,134

access.TESC, restoration, etc

Sales Tax on Materials

5%





$1,161





Total Direct Unit Cost



$25.00

$81,907



Construct 10'x2'x3' Rock Lined Ditch

390

LF







Clear, Grub & Dispose

0.4

AC

$6,514.75

$2,333



Diversion/Care of Water

0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0



Excavate Channel

693.3

CY

$14.80

$10,260



Prep & Grade Channel

390

LF

$7.84

$3,058



Haul & Dispose at Repository

693.3

CY

$5.49

$3,806

assume all but rock is wasted, 5 mile 1

Repository Cost

693.3

CY

$11.38

$7,890

use C08a cost

Imported Fill Material

173.3

CY

$53.33

$9,244

imported, difficult operation

Misc Detail Allowance

10%

LS

$0.00

$2,490

access.TESC, restoration, etc

Sales Tax on Materials

5%





$143





Total Direct Unit Cost



$101.00

$39,224



Page 9 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site















2009 Total















2009 Direct

Direct Capital







Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

4-9

Pipeline -15" RCP, 2' Cover





1

LF





2' cover



Demo ACP Roadway





0.8

SY

$12.55

$9





Excavate T rench





0.5

CY

$3.92

$2





Bed & Zone





0.2

CY

$46.86

$12

1/2 mile one way average



Imported Backfill





0.2

CY

$29.94

$5





Haul & Dispose at Repository





0.5

CY

$5.49

$2

assume all but rock is wasted, 5 mile 1 way



Repository Cost





0.5

CY

$11.38

$5

use C08a cost



Trench Safety





1

LF

$5.00

$5

trench box



Dewatering: Two Sump Pmps





0

HR

$12.00

$0

NA



Pipe, 15" RCP Pipe





1

LF

$35.75

$36

350'/day



ACP Pavement, 4" thk





0.2

TON

$70.00

$12





CSBC, 6" thk





0.1

CY

$31.26

$4





Flagger





0.05

HR

$60.14

$3





Misc Detail Allowance





10%

LS

$0.00

$9

road maint & repair, testing, detection tape, etc



Sales Tax on Materials





5%





$2









Total Direct Unit Cost





$110.00

$106



10

Pipeline -18" RCP, 1.5' Cover Pavement Restoration



1

LF





1' cover



Demo ACP Roadway





0.7

SY

$12.55

$9





Excavate T rench





0.5

CY

$3.92

$2





Bed & Zone





0.3

CY

$46.86

$13

1/2 mile one way average



Imported Backfill





0.1

CY

$29.94

$4





Haul & Dispose at Repository





0.5

CY

$5.49

$3

assume all but rock is wasted, 5 mile 1 way



Repository Cost





0.5

CY

$11.38

$5

use C08a cost



Trench Safety





1

LF

$5.00

$5

trench box



Dewatering: Two Sump Pmps





0

HR

$12.00

$0

NA



Pipe, 18" RCP Pipe





1

LF

$44.92

$45

RS Means 334113502040



ACP Pavement, 4" thk





0.2

TON

$70.00

$12





CSBC, 6" thk





0.1

CY

$31.26

$4





Flagger





0.06

HR

$60.14

$4





Misc Detail Allowance





10%

LS

$0.00

$10

road maint & repair, testing, detection tape, etc



Sales Tax on Materials





5%





$2









Total Direct Unit Cost





$120.00

$116



Page 10 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site













2009 Total













2009 Direct

Direct Capital





Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

11

Pipeline - 30" CPE, 3' Cover Pavement Restoration



1

LF





2' cover



Demo ACP Roadway



1.4

SY

$12.55

$17





Excavate T rench



1.1

CY

$3.92

$5





Bed & Zone



0.4

CY

$46.86

$20

1/2 mile one way average



Imported Backfill



0.5

CY

$29.94

$16





Haul & Dispose at Repository



1.1

CY

$5.49

$6

assume all but rock is wasted, 5 mile 1 way



Repository Cost



1.1

CY

$11.38

$13

use C08a cost



Trench Safety



1

LF

$5.00

$5

trench box



Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA



Pipe, 30" CPE Pipe



1

LF

$74.25

$74

RS Means 334113502040



ACP Pavement, 4" thk



0.3

TON

$70.00

$22





CSBC, 6" thk



0.2

CY

$31.26

$7





Flagger



0.08

HR

$60.14

$5





Misc Detail Allowance



10%

LS

$0.00

$17

road maint & repair, testing, detection tape, etc



Sales Tax on Materials



5%





$5







Total Direct Unit Cost





$210.00

$213



12

Install New Dual Inlet Catch Basin with 4' Sump



1

EA









Sawcut & Remove Pavement



8.3

SY

$12.55

$105





Diversion/Care of Water



0

LF

$10.00

$0





Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0





Excavate Catch Basin



20.8

CY

$14.80

$308





Prep & Grade Channel



0

LF

$7.84

$0





Haul & Dispose at Repository



20.8

CY

$5.49

$114

assume all but rock is wasted, 5 mile 1 way



Repository Cost



20.8

CY

$11.38

$237

use C08a cost



Imported Fill Material



17.0

CY

$53.33

$907

imported, difficult operation



Grate



1

EA

$250.00

$250





CIP Wall, 6" thk, 7'tall



2.1

CY

$737.64

$1,530





Wall Rebar @ 200 #/cy



414.8

LB

$1.79

$740





CIP Slab, 6" thk, 5.5' x 2.5' wide



0.5

CY

$295.88

$151





Footing Rebar @150 #/cy



76.4

LB

$1.79

$136





CIP Gutter Slab, 6" thk



0.2

CY

$295.88

$55





Footing Rebar @150 #/cy



27.8

LB

$1.79

$50





Misc Detail Allowance



10%

LS

$0.00

$423

access.TESC, restoration, etc



Sales Tax on Materials



5%





$360







Total Direct Unit Cost





$5,367.00

$5,367



Page 11 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site











2009 Total











2009 Direct

Direct Capital



Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

13 Rip Rap



1

EA







Riprap



1

CY

$72.91

$73

imported, difficult operation

Misc Detail Allowance



10%

LS

$0.00

$7



Sales Tax on Materials



5%





$2





Total Direct Unit Cost





$82.00

$82



Dewey Street Area













1-3 Construct Asphalt Lined Ditch (2.5 deep w/1:1 slopes)



3,400

LF







Clear, Grub & Dispose



2.3

AC

$6,514.75

$15,255



Diversion/Care of Water



0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0



Excavate Channel



787.0

CY

$14.80

$11,647



Prep & Grade Ditch



3,400

LF

$3.92

$13,331



Haul & Dispose at Repository



787.0

CY

$5.49

$4,321

assume all but rock is wasted, 5 mile 1 way

Repository Cost



787.0

CY

$11.38

$8,956

use C08a cost

ACP Pavement, 2" thk



301.5

TON

$70.00

$21,103



Imported Fill Material



0.0

CY

$53.33

$0

imported, difficult operation

Misc Detail Allowance



10%

LS

$0.00

$6,134

access.TESC, restoration, etc

Sales Tax on Materials



5%





$1,161





Total Direct Unit Cost





$25.00

$81,907



4,5 Pipeline -18" RCP, 1.5' Cover Pavement Restoration



1

LF





1' cover

Demo ACP Roadway



0.7

SY

$12.55

$9



Excavate T rench



0.5

CY

$3.92

$2



Bed & Zone



0.3

CY

$46.86

$13

1/2 mile one way average

Imported Backfill



0.1

CY

$29.94

$4



Haul & Dispose at Repository



0.5

CY

$5.49

$3

assume all but rock is wasted, 5 mile 1 way

Repository Cost



0.5

CY

$11.38

$5

use C08a cost

Trench Safety



1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA

Pipe, 18" RCP Pipe



1

LF

$44.92

$45

RS Means 334113502040

ACP Pavement, 4" thk



0.2

TON

$70.00

$12



CSBC, 6" thk



0.1

CY

$31.26

$4



Flagger



0.06

HR

$60.14

$4



Misc Detail Allowance



10%

LS

$0.00

$10

road maint & repair, testing, detection tape, etc

Sales Tax on Materials



5%





$2





Total Direct Unit Cost





$120.00

$116



Page 12 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital



Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

Pipeline -18" RCP, 1.5' Cover Gravel Restoration



1

LF





1' cover

Demo ACP Roadway





0.7

SY

$12.55

$9



Excavate T rench





0.5

CY

$3.92

$2



Bed & Zone





0.3

CY

$46.86

$13

1/2 mile one way average

Imported Backfill





0.1

CY

$29.94

$4



Haul & Dispose at Repository





0.5

CY

$5.49

$3

assume all but rock is wasted, 5 mile 1 way

Repository Cost





0.5

CY

$11.38

$5

use C08a cost

Trench Safety





1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps





0

HR

$12.00

$0

NA

Pipe, 18" RCP Pipe





1

LF

$44.92

$45

RS Means 334113502040

CSBC, 6" thk





0.1

CY

$31.26

$4



Flagger





0.03

HR

$60.14

$2



Misc Detail Allowance





10%

LS

$0.00

$8

road maint & repair, testing, detection tape, etc

Sales Tax on Materials





5%





$2







Total Direct Unit Cost





$100.00

$101



Manhole 48" 6 to 8 ft Depth





1

EA







Demo ACP Roadway





7.1

SY

$12.55

$89



Excavate T rench





19.0

CY

$3.92

$74



Bed & Zone





0.0

CY

$46.86

$0

1/2 mile one way average

Imported Backfill





15.2

CY

$29.94

$456



Haul & Dispose at Repository





19.0

CY

$5.49

$104

assume all but rock is wasted, 5 mile 1 way

Repository Cost





19.0

CY

$11.38

$216

use C08a cost

Trench Safety





1

EA

$25.00

$25

trench box

Dewatering: Two Sump Pmps





0

HR

$12.00

$0

NA

48" Manhole





1

EA

$2,776.78

$2,777



ACP Pavement, 4" thk





1.6

TON

$70.00

$113



CSBC, 6" thk





1.2

CY

$31.26

$37



Flagger





8.00

HR

$60.14

$481



Misc Detail Allowance





10%

LS

$0.00

$405

road maint & repair, testing, detection tape, etc

Sales Tax on Materials





5%





$112







Total Direct Unit Cost





$4,890.00

$4,890



Page 13 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









2009 Total









2009 Direct

Direct Capital



Description

Quantity

Unit

Capital Unit Cost

Cost

Comments

8 Pipeline -18" CHDPE, 3'Cover

1

LF





3' cover

Demo ACP Roadway

1.1

SY

$12.55

$13



Excavate T rench

0.7

CY

$3.92

$3



Bed & Zone

0.3

CY

$46.86

$13

1/2 mile one way average

Imported Backfill

0.3

CY

$29.94

$10



Haul & Dispose at Repository

0.7

CY

$5.49

$4

assume all but rock is wasted, 5 mile 1 way

Repository Cost

0.7

CY

$11.38

$8

use C08a cost

Trench Safety

1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps

0

HR

$12.00

$0

NA

Pipe, 18" CPE Pipe

1

LF

$30.71

$31

350'/day

ACP Pavement, 4" thk

0.2

TON

$70.00

$17



CSBC, 6" thk

0.2

CY

$31.26

$5



Flagger

0.05

HR

$60.14

$3



Misc Detail Allowance

10%

LS

$0.00

$10

road maint & repair, testing, detection tape, etc

Sales Tax on Materials

5%





$3





Total Direct Unit Cost



$120.00

$124



Copper Street Neighborhood











1-4 Construct Asphalt Lined Ditch (2.5 deep w/1:1 slopes)

3,400

LF







Clear, Grub & Dispose

2.3

AC

$6,514.75

$15,255



Diversion/Care of Water

0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0



Excavate Channel

787.0

CY

$14.80

$11,647



Prep & Grade Ditch

3,400

LF

$3.92

$13,331



Haul & Dispose at Repository

787.0

CY

$5.49

$4,321

assume all but rock is wasted, 5 mile 1 way

Repository Cost

787.0

CY

$11.38

$8,956

use C08a cost

ACP Pavement, 2" thk

301.5

TON

$70.00

$21,103



Imported Fill Material

0.0

CY

$53.33

$0

imported, difficult operation

Misc Detail Allowance

10%

LS

$0.00

$6,134

access.TESC, restoration, etc

Sales Tax on Materials

5%





$1,161





Total Direct Unit Cost



$25.00

$81,907



Page 14 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site















2009 Total















2009 Direct

Direct Capital







Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

5,6

Pipeline -18" RCP, 1.5' Cover Pavement Restoration



1

LF





1' cover



Demo ACP Roadway





0.7

SY

$12.55

$9





Excavate T rench





0.5

CY

$3.92

$2





Bed & Zone





0.3

CY

$46.86

$13

1/2 mile one way average



Imported Backfill





0.1

CY

$29.94

$4





Haul & Dispose at Repository





0.5

CY

$5.49

$3

assume all but rock is wasted, 5 mile 1 way



Repository Cost





0.5

CY

$11.38

$5

use C08a cost



Trench Safety





1

LF

$5.00

$5

trench box



Dewatering: Two Sump Pmps





0

HR

$12.00

$0

NA



Pipe, 18" RCP Pipe





1

LF

$44.92

$45

RS Means 334113502040



ACP Pavement, 4" thk





0.2

TON

$70.00

$12





CSBC, 6" thk





0.1

CY

$31.26

$4





Flagger





0.06

HR

$60.14

$4





Misc Detail Allowance





10%

LS

$0.00

$10

road maint & repair, testing, detection tape, etc



Sales Tax on Materials





5%





$2









Total Direct Unit Cost





$120.00

$116



7

Pipeline - 48" CMP, 3.5' Cover Pavement Restoration



1

LF





2' cover



Demo ACP Roadway





2.0

SY

$12.55

$25





Excavate T rench





2.4

CY

$3.92

$9





Bed & Zone





0.7

CY

$46.86

$34

1/2 mile one way average



Imported Backfill





1.2

CY

$29.94

$35





Haul & Dispose at Repository





2.4

CY

$5.49

$13

assume all but rock is wasted, 5 mile 1 way



Repository Cost





2.4

CY

$11.38

$27

use C08a cost



Trench Safety





1

LF

$5.00

$5

trench box



Dewatering: Two Sump Pmps





0

HR

$12.00

$0

NA



Pipe, 48" CMP Pipe





1

LF

$161.36

$161

RS Means 334113402200



ACP Pavement, 4" thk





0.5

TON

$70.00

$32





CSBC, 6" thk





0.3

CY

$31.26

$10





Flagger





0.10

HR

$60.14

$6





Misc Detail Allowance





10%

LS

$0.00

$32

road maint & repair, testing, detection tape, etc



Sales Tax on Materials





5%





$11









Total Direct Unit Cost





$400.00

$401



Page 15 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site













2009 Total













2009 Direct

Direct Capital





Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

8

Pipeline - 24" CPE, 4' Cover Pavement Restoration



1

LF





4' cover



Demo ACP Roadway



1.6

SY

$12.55

$20





Excavate T rench



1.5

CY

$3.92

$6





Bed & Zone



0.4

CY

$46.86

$20

1/2 mile one way average



Imported Backfill



0.9

CY

$29.94

$27





Haul & Dispose at Repository



1.5

CY

$5.49

$8

assume all but rock is wasted, 5 mile 1 way



Repository Cost



1.5

CY

$11.38

$17

use C08a cost



Trench Safety



1

LF

$5.00

$5

trench box



Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA



Pipe, 24" CPE Pipe



1

LF

$47.54

$48

RS Means 334113502040



ACP Pavement, 4" thk



0.4

TON

$70.00

$26





CSBC, 6" thk



0.3

CY

$31.26

$8





Flagger



0.05

HR

$60.14

$3





Misc Detail Allowance



10%

LS

$0.00

$16

road maint & repair, testing, detection tape, etc



Sales Tax on Materials



5%





$5







Total Direct Unit Cost





$210.00

$209



9

Remove Drywell, CB's, and Storm Drain along Idaho St.



1

LF





2' cover



Demo Drywell



1

EA

$392.10

$392





Demo Catchbasin



4

EA

$784.20

$3,137





Demo Existing Storm Drain



285

EA

$9.94

$2,834





Imported Backfill to fill in removals



190

CY

$29.94

$5,689





Trench Safety



285

LF

$5.00

$1,425

trench box



Flagger



40

HR

$60.14

$2,406





Misc Detail Allowance



10%

LS

$0.00

$1,588

road maint & repair, testing, detection tape, etc



Sales Tax on Materials



5%





$209







Total Direct Unit Cost





$17,680.00

$17,679



Page 16 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

10

Description

Quantity

Unit

2009 Direct
Capital Unit Cost

2009 Total
Direct Capital
Cost

Comments

Install New 6' x 6' Concrete Manhole, 8' Depth

1

EA







Sawcut & Remove Pavement

16.0

SY

$12.55

$201



Diversion/Care of Water

0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv

0

LF

$10.39

$0



Excavate Catch Basin

48.0

CY

$14.80

$710



Prep & Grade Channel

0

LF

$7.84

$0



Haul & Dispose at Repository

48.0

CY

$5.49

$264

assume all but rock is wasted, 5 mile 1

Repository Cost

48.0

CY

$11.38

$546

use C08a cost

Imported Fill Material

33.9

CY

$53.33

$1,809

imported, difficult operation

Grate

1.0

EA

$250.00

$250



CIP Wall, 6" thk, 8'tall

3.6

CY

$737.64

$2,623



Wall Rebar @ 200 #/cy

711.1

LB

$1.79

$1,269



CIP Elevated Slab, 10" thk

1.5

CY

$737.64

$1,111



Wall Rebar @ 200 #/cy

301.3

LB

$1.79

$538



CIP Slab, 10" thk, 7'x 7' wide

1.5

CY

$295.88

$446



Footing Rebar @150 #/cy

225.9

LB

$1.79

$403



Misc Detail Allowance

10%

LS

$0.00

$936

access.TESC, restoration, etc

Sales Tax on Materials

5%

Total Direct Unit Cost

$11,676.00

$570
$11,676

11,12 Manhole 48" 6 to 8 ft Depth

1

EA







Demo ACP Roadway

7.1

SY

$12.55

$89



Excavate T rench

19.0

CY

$3.92

$74



Bed & Zone

0.0

CY

$46.86

$0

1/2 mile one way average

Imported Backfill

15.2

CY

$29.94

$456



Haul & Dispose at Repository

19.0

CY

$5.49

$104

assume all but rock is wasted, 5 mile 1 way

Repository Cost

19.0

CY

$11.38

$216

use C08a cost

Trench Safety

1

EA

$25.00

$25

trench box

Dewatering: Two Sump Pmps

0

HR

$12.00

$0

NA

48" Manhole

1

EA

$2,776.78

$2,777



ACP Pavement, 4" thk

1.6

TON

$70.00

$113



CSBC, 6" thk

1.2

CY

$31.26

$37



Flagger

8.00

HR

$60.14

$481



Misc Detail Allowance

10%

LS

$0.00

$405

road maint & repair, testing, detection tape, etc

Sales Tax on Materials

5%





$112





Total Direct Unit Cost



$4,890.00

$4,890



Page 17 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site











2009 Total











2009 Direct

Direct Capital



Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

13 Rip Rap



1

EA







Riprap



1

CY

$72.91

$73

imported, difficult operation

Misc Detail Allowance



10%

LS

$0.00

$7



Sales Tax on Materials



5%





$2





Total Direct Unit Cost





$82.00

$82



South End of 2nd Street













1,2 Construct 10'x4'x3' Rock Lined Ditch



110

LF







Clear, Grub & Dispose



0.1

AC

$6,514.75

$658



Diversion/Care of Water



0

LF

$10.00

$0



Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0



Excavate Channel



195.6

CY

$14.80

$2,894



Prep & Grade Channel



110

LF

$7.84

$863



Haul & Dispose at Repository



195.6

CY

$5.49

$1,074

assume all but rock is wasted, 5 mile 1 way

Repository Cost



195.6

CY

$11.38

$2,225

use C08a cost

Imported Fill Material



61.1

CY

$53.33

$3,259

imported, difficult operation

Misc Detail Allowance



10%

LS

$0.00

$767

access.TESC, restoration, etc

Sales Tax on Materials



5%





$50





Total Direct Unit Cost





$108.00

$11,790



3,4 Pipeline -18" CHDPE, 3'Cover



1

LF





3' cover

Demo ACP Roadway



1.1

SY

$12.55

$13



Excavate T rench



0.7

CY

$3.92

$3



Bed & Zone



0.3

CY

$46.86

$13

1/2 mile one way average

Imported Backfill



0.3

CY

$29.94

$10



Haul & Dispose at Repository



0.7

CY

$5.49

$4

assume all but rock is wasted, 5 mile 1 way

Repository Cost



0.7

CY

$11.38

$8

use C08a cost

Trench Safety



1

LF

$5.00

$5

trench box

Dewatering: Two Sump Pmps



0

HR

$12.00

$0

NA

Pipe, 18" CPE Pipe



1

LF

$30.71

$31

350'/day

ACP Pavement, 4" thk



0.2

TON

$70.00

$17



CSBC, 6" thk



0.2

CY

$31.26

$5



Flagger



0.05

HR

$60.14

$3



Misc Detail Allowance



10%

LS

$0.00

$10

road maint & repair, testing, detection tape, etc

Sales Tax on Materials



5%





$3





Total Direct Unit Cost





$120.00

$124



Page 18 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site













2009 Total













2009 Direct

Direct Capital





Description



Quantity

Unit

Capital Unit Cost

Cost

Comments

5

Install New Dual Inlet Catch Basin with 4' Sump



1

EA









Sawcut & Remove Pavement



8.3

SY

$12.55

$105





Diversion/Care of Water



0

LF

$10.00

$0





Diversion Piping - Temporary: 36" dia Equiv



0

LF

$10.39

$0





Excavate Catch Basin



20.8

CY

$14.80

$308





Prep & Grade Channel



0

LF

$7.84

$0





Haul & Dispose at Repository



20.8

CY

$5.49

$114

assume all but rock is wasted, 5 mile 1 way



Repository Cost



20.8

CY

$11.38

$237

use C08a cost



Imported Fill Material



17.0

CY

$53.33

$907

imported, difficult operation



Grate



1.0

EA

$250.00

$250





CIP Wall, 6" thk, 7'tall



2.1

CY

$737.64

$1,530





Wall Rebar @ 200 #/cy



414.8

LB

$1.79

$740





CIP Slab, 6" thk, 5.5' x 2.5' wide



0.5

CY

$295.88

$151





Footing Rebar @150 #/cy



76.4

LB

$1.79

$136





CIP Gutter Slab, 6" thk



0.2

CY

$295.88

$55





Footing Rebar @150 #/cy



27.8

LB

$1.79

$50





Misc Detail Allowance



10%

LS

$0.00

$423

access.TESC, restoration, etc



Sales Tax on Materials



5%





$360







Total Direct Unit Cost





$5,367.00

$5,367



6

Rip Rap



1

EA









Riprap



1.0

CY

$72.91

$73

imported, difficult operation



Misc Detail Allowance



10%

LS

$0.00

$7





Sales Tax on Materials



5%





$2







Total Direct Unit Cost





$82.00

$82



Notes:

CIP = cast-in-place
CPE = polyethylene
CY = cubic yards
EA = each
LB = pound(s)

LS = lump sum
SF = square feet
SY = square yards

TESC = temporary erosion and sediment control

NOTE: The above costs are presented rounded to three significant figures
NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal

Page 19 of 20


-------
TABLE D-35

Alternative RP-2: Mullan Detailed Unit Cost

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

2009 Total
2009 Direct Direct Capital

Description	Quantity Unit Capital Unit Cost	Cost	Comments

NOTE: The above cost opinion is in 2009 dollars and does not include future
escalation. The order-of-magnitude cost opinion shown has been prepared for
guidance in project evaluation from the information available at the time of
preparation. The final costs of the project will depend on actual labor and material
costs, actual site conditions, productivity, competitive market conditions, the final
project scope, the final project schedule, and other variable factors. As a result, the
final project costs will vary from those presented above. Because of these factors,
funding needs must be carefully reviewed prior to making specific financial decisions
or establishing final budgets.

Page 20 of 20


-------
TABLE D-36

Alternative RP-2: Approximate Cost for Side Gulches

Typical Side Gulch Cost

Length of Stream that Fronts or
Flows Through Remediate
Areas1
(LF)

Length of
Channel
Improvements2
(LF)

Direct Capital
Unit Cost3

Direct Capital
Cost

Indirect
Capital Cost4

O&M Cost Total Cost
(30-Year NPV)5 (30-Year NPV)

2,700

1,200

$ 291

$ 349,000

$ 244,000

$ 228,000 $ 821,000

Approximate Number of
Crossings8

Length of Culvert
Replacement7
(LF)

Direct Capital
Unit Cost8

Direct Capital
Cost

Indirect
Capital Cost

O&M Cost Total Cost
(30-Year NPV)5 (30-Year NPV)

4

104

$ 682

$ 71,000

$ 50,000

$ 46,000 $ 167,000

Surface Water Improvements9

Qty

Direct Capital
Unit Cost10

Direct Capital
Cost

Indirect
Capital Cost

O&M Cost Total Cost
(30-Year NPV)5 (30-Year NPV)

Assume 1 per typcial side gulch

1

$ 181,000

$ 181,000

$ 127,000

$ 118,000 $ 426,000

Total for Typical Side Gulch





$ 601,000

$ 421,000

$ 392,000 $ 1,414,000



TOTAL APPROXIMATE COST for Side Gulches11



$ 6,410,000

$ 4,490,000

$ 4,180,000 $ 15,100,000

Notes:	

LF = linear feet

NPV = net present value

1	Length of stream that fronts or flows through remediated areas is based on GIS analysis. This value (2,700 LF) is an average length for all
side gulches (see Table 9, Appendix G).

2	Length of expected channel improvements for a typical side gulch assumes 45% of length of stream fronting or flowing through remediated
areas would require improvements. This assumption is based on the development of remedy protection projects using hydrologic and
hydraulic modeling for Alternative RP-2 in the eight Upper Basin communities. (TerraGraphics, 2010)

3	Direct unit capital cost for channel improvements is based on average direct capital unit cost for channel hydraulic capacity improvements
included in Alternative RP-2 for the eight Upper Basin communities. (CH2M HILL, 2010)

4	Indirect capital cost assumes 70% of direct capital costs.

5	O&M Cost (30 Year NPV) assumes 38% of total capital cost. This assumption is based on O&M costs calculated in development of
remedy protection projects in eight Upper Basin communities. (CH2M HILL, 2010)

6	Approximate number of crossing is based on average for side gulches (see Table 9, Appendix G). Assumes all crosssings are culverts.

7	Typical culvert (or crossing) assumes a two-lane road (24-ft) with shoulders (20-ft) and rip-rap headwalls (8-ft). Assumes 50% of crossings
would require culvert replacement. This assumption is based on the development of Alternative RP-2 projects using hydrologic and hydraulic
modeling for the eight Upper Basin communities. (TerraGraphics, 2010)

8	Direct unit cost for culvert replacement is based on average unit cost for culvert replacement technologies included in Alternative RP-2 for
the eight Upper Basin communities. (CH2M HILL, 2010)

9	Surface water improvements assumes that a typical side gulch would need some degree of drainage improvements to reduce scour
potential. The typical side gulch cost assumes one surface water improvement project for each side gulch.

10	Direct unit cost is based on average unit cost for surface water improvement projects included in Alternative RP-2 for the eight Upper
Basin communities. These projects include multiple neighborhoods in Mullan, Printer's Creek (Wallace), Portland Road (Kellogg), and
Sierra Nevada Road (Wardner). (CH2M HILL, 2010)

11	The total approximate cost for side gulches assumes 67% of side gulches will actually require remedy protection actions. This
assumption is based on the analyses conducted during the characterization of the risk posed to the Selected Remedies in the eight Upper
Basin communities. Bunker Creek and Government Creek are not included. (TerraGraphics, 2010)

Page 1 of 1


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site















2009 Total















2009 Total



Direct and











Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

BigCrkSegOl

POL044

BLM Polygon

Upland waste rock (erosion potential)

C02c

$4,470

$3,130

$7,600

$1,030

$8,630



POL052

BLM Polygon

Floodplain waste rock

C01

$19,700

$13,800

$33,500

$0

$33,500









C07

$67,600

$47,300

$114,900

$14,900

$129,800

BigCrkSeg03

POL001

BLM Polygon

Floodplain waste rock

C02c

$5,070

$3,550

$8,620

$1,170

$9,790



POL002

BLM Polygon

Floodplain waste rock

C01

$7,280

$5,090

$12,370

$0

$12,370









C07

$25,000

$17,500

$42,500

$5,500

$48,000



POL067

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200









WT02

$521,000

$365,000

$886,000

$1,210,000

$2,096,000



POL068

BLM Polygon

Upland waste rock (erosion potential)

C02a

$16,900

$11,800

$28,700

$2,190

$30,890

BigCrkSeg04

BIG04-2

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$140,000

$97,800

$237,800

$41,900

$279,700









CD-AVG

$35,000

$24,500

$59,500

$10,500

$70,000









CD-SED

$3,740

$2,620

$6,360

$22,400

$28,760









VBS-AVG

$59,500

$41,700

$101,200

$17,900

$119,100



BIG04-3

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$573,000

$401,000

$974,000

$172,000

$1,146,000









CD-AVG

$247,000

$173,000

$420,000

$74,200

$494,200









CD-SED

$26,200

$18,300

$44,500

$157,000

$201,500









FP/RP-AVG

$432,000

$302,000

$734,000

$77,700

$811,700









OFFCH-AVG

$832,000

$582,000

$1,414,000

$150,000

$1,564,000









VBS-AVG

$244,000

$171,000

$415,000

$73,300

$488,300



KLE025

BLM Polygon

Floodplain tailings - inactive Facilities

C09

$5,930,000

$4,150,000

$10,080,000

$1,190,000

$11,270,000



KLE026

BLM Polygon

Floodplain waste rock

C02c

$182,000

$127,000

$309,000

$41,800

$350,800



KLE027

BLM Polygon

Upland waste rock (erosion potential)

C01

$399,000

$279,000

$678,000

$0

$678,000









C07

$1,370,000

$958,000

$2,328,000

$301,000

$2,629,000



KLE047

BLM Polygon

Floodplain sediments

C01b

$44,900

$31,400

$76,300

$0

$76,300









C08a

$58,800

$41,200

$100,000

$8,230

$108,230









HAUL-2

$18,200

$12,800

$31,000

$0

$31,000



KLE053

BLM Polygon

Floodplain waste rock

C01

$842,000

$589,000

$1,431,000

$0

$1,431,000









C07

$2,890,000

$2,020,000

$4,910,000

$636,000

$5,546,000



KLE054

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200









WT03

$714,000

$500,000

$1,214,000

$661,000

$1,875,000







Upland waste rock (erosion potential)

C01

$685,000

$480,000

$1,165,000

$0

$1,165,000









C07

$2,350,000

$1,650,000

$4,000,000

$518,000

$4,518,000



KLE071

BLM Polygon

Floodplain sediments

C01b

$529,000

$370,000

$899,000

$0

$899,000









C08a

$694,000

$486,000

$1,180,000

$97,100

$1,277,100









HAUL-2

$215,000

$151,000

$366,000

$0

$366,000



KLE073

BLM Polygon

Floodplain sediments

C01b

$1,350,000

$945,000

$2,295,000

$0

$2,295,000









C08a

$1,770,000

$1,240,000

$3,010,000

$248,000

$3,258,000









HAUL-2

$549,000

$384,000

$933,000

$0

$933,000



POL008

BLM Polygon

Floodplain waste rock

C01

$34,900

$24,400

$59,300

$0

$59,300









C07

$120,000

$84,000

$204,000

$26,400

$230,400



POL010

BLM Polygon

Upland waste rock (erosion potential)

C01

$19,500

$13,700

$33,200

$0

$33,200









C07

$67,000

$46,900

$113,900

$14,700

$128,600

Page 1 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

POL011

BLM Polygon

Floodplain waste rock

C01

$13,400

$9,350

$22,750

$0

$22,750







C07

$45,900

$32,100

$78,000

$10,100

$88,100

POL022

BLM Polygon

Floodplain waste rock

C02c

$12,700

$8,870

$21,570

$2,910

$24,480

POL066

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

CCSeg PIPECC

General Feature

Source General Information

PIPE-1

$1,050,000

$735,000

$1,785,000

$84,000

$1,869,000







PIPE-2

$54,100

$37,900

$92,000

$4,330

$96,330







PIPE-3

$2,380,000

$1,670,000

$4,050,000

$191,000

$4,241,000







PIPE-4

$3,330,000

$2,330,000

$5,660,000

$267,000

$5,927,000

CCSegOl BUR105

BLM Polygon

Upland waste rock (erosion potential)

C01

$27,800

$19,500

$47,300

$0

$47,300







C03

$60,800

$42,500

$103,300

$7,290

$110,590

BUR109

BLM Polygon

Upland waste rock (erosion potential)

C01

$23,500

$16,400

$39,900

$0

$39,900







C03

$257,000

$180,000

$437,000

$30,800

$467,800

BUR185

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$69,800

$48,800

$118,600

$8,370

$126,970

BUR187

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$56,300

$39,400

$95,700

$6,750

$102,450

THO023

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$42,800

$29,900

$72,700

$5,130

$77,830

CCSeg02 BUR107

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Upland waste rock (erosion potential)

C01

$119,000

$83,300

$202,300

$0

$202,300







C04

$594,000

$416,000

$1,010,000

$137,000

$1,147,000

BUR130

BLM Polygon

Upland waste rock (erosion potential)

C01

$2,570

$1,800

$4,370

$0

$4,370







C03

$536,000

$375,000

$911,000

$64,300

$975,300

BUR132

BLM Polygon

Upland waste rock (erosion potential)

C01

$78,800

$55,100

$133,900

$0

$133,900







C03

$376,000

$263,000

$639,000

$45,100

$684,100

BUR133

BLM Polygon

Upland waste rock (erosion potential)

C01

$22,700

$15,900

$38,600

$0

$38,600







C07

$77,900

$54,500

$132,400

$17,100

$149,500

BUR134

BLM Polygon

Upland waste rock (erosion potential)

C01

$61,600

$43,100

$104,700

$0

$104,700







C07

$212,000

$148,000

$360,000

$46,600

$406,600

BUR135

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$131,000

$91,400

$222,400

$15,700

$238,100

BUR145

BLM Polygon

Upland waste rock (erosion potential)

C01

$240,000

$168,000

$408,000

$0

$408,000







C07

$823,000

$576,000

$1,399,000

$181,000

$1,580,000

BUR150

BLM Polygon

Floodplain waste rock

C01

$27,900

$19,500

$47,400

$0

$47,400







C03

$306,000

$214,000

$520,000

$36,700

$556,700

BUR153

BLM Polygon

Floodplain sediments

C01b

$236,000

$165,000

$401,000

$0

$401,000







C08a

$310,000

$217,000

$527,000

$43,400

$570,400







HAUL-2

$96,100

$67,300

$163,400

$0

$163,400

CC02-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$243,000

$170,000

$413,000

$72,800

$485,800







CD-AVG

$123,000

$86,100

$209,100

$36,900

$246,000

Page 2 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Segment ID Source ID

Source Type Description

Trait Description
(Waste Types)

TCD

2009 Total
Direct Capital
Cost

2009 Indirect
Capital Cost

2009 Total
Direct and
Indirect Capital
Cost

O&M Cost (30-
Year NPV)

Total Cost (30-
Year NPV)







CD-SED

FP/RP-AVG

VBS-AVG

$12,300
$889,000
$172,000

$8,640
$622,000
$121,000

$20,940
$1,511,000
$293,000

$74,100
$160,000
$51,700

$95,040
$1,671,000
$344,700

CCSeg03 BUR087

BLM Polygon

Upland waste rock (erosion potential)

C01
C03

$53,500
$873,000

$37,500
$611,000

$91,000
$1,484,000

$0
$105,000

$91,000
$1,589,000

BUR088

BLM Polygon

Adit drainage

C10
WT01

$9,680
$60,300

$6,780
$64,500

$16,460
$124,800

$1,740
$45,700

$18,200
$170,500

BUR089

BLM Polygon

Upland waste rock (erosion potential)

C01
C03

$171
$45,000

$120
$31,500

$291
$76,500

$0
$5,400

$291
$81,900

BUR090

BLM Polygon

Upland tailings

C01
C07

$128,000
$441,000

$89,900
$309,000

$217,900
$750,000

$0
$97,000

$217,900
$847,000





Upland waste rock (erosion potential)

C01
C03

$47,100
$2,360,000

$33,000
$1,650,000

$80,100
$4,010,000

$0
$283,000

$80,100
$4,293,000

BUR099

BLM Polygon

Adit drainage

C10
WT01

$9,680
$60,300

$6,780
$64,500

$16,460
$124,800

$1,740
$45,700

$18,200
$170,500

BUR146

BLM Polygon

Floodplain sediments

C01b
C08a
HAUL-2

$344,000
$451,000
$140,000

$241,000
$316,000
$98,000

$585,000
$767,000
$238,000

$0
$63,200
$0

$585,000
$830,200
$238,000

BUR149

BLM Polygon

Upland waste rock (erosion potential)

C01
C03

$8,900
$115,000

$6,230
$80,300

$15,130
$195,300

$0
$13,800

$15,130
$209,100

BUR166

BLM Polygon

Upland waste rock (erosion potential)

C01
C03

$171
$74,300

$120
$52,000

$291
$126,300

$0
$8,910

$291
$135,210

BUR180

BLM Polygon

Upland waste rock (erosion potential)

C01
C03

$4,710
$51,800

$3,300
$36,200

$8,010
$88,000

$0
$6,210

$8,010
$94,210

CCSeg04 BUR066

BLM Polygon

Upland waste rock (erosion potential)

C01
C03

$5,990
$67,500

$4,190
$47,300

$10,180
$114,800

$0
$8,100

$10,180
$122,900

BUR067

BLM Polygon

Adit drainage

C10
WT01

$9,680
$950,000

$6,780
$1,020,000

$16,460
$1,970,000

$1,740
$723,000

$18,200
$2,693,000





Upland tailings

C01
C07

$10,700
$36,800

$7,490
$25,700

$18,190
$62,500

$0
$8,090

$18,190
$70,590





Upland waste rock (potential intermixed tailings)

C01
C03
C07

$749,000
$1,070,000
$2,570,000

$524,000
$748,000
$1,800,000

$1,273,000
$1,818,000
$4,370,000

$0
$128,000
$566,000

$1,273,000
$1,946,000
$4,936,000

BUR068

BLM Polygon

Upland waste rock (erosion potential)

C01
C07

$51,400
$176,000

$36,000
$123,000

$87,400
$299,000

$0
$38,800

$87,400
$337,800

BUR072

BLM Polygon

Upland waste rock (erosion potential)

C03

$392,000

$274,000

$666,000

$47,000

$713,000

BUR073

BLM Polygon

Upland waste rock (erosion potential)

C01
C03

$108,000
$1,190,000

$75,500
$830,000

$183,500
$2,020,000

$0
$142,000

$183,500
$2,162,000

BUR075

BLM Polygon

Upland tailings

C01
C07

$15,000
$51,500

$10,500
$36,000

$25,500
$87,500

$0
$11,300

$25,500
$98,800

BUR094

BLM Polygon

Upland waste rock (erosion potential)

C02a

$118,000

$82,600

$200,600

$15,300

$215,900

BUR096

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







Page 3 of 28










-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Segment ID

Trait Description

2009 Total
Direct Capital

2009 Indirect

2009 Total
Direct and
Indirect Capital

O&M Cost (30- Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







WT01

$4,890

$5,230

$10,120

$3,700

$13,820





Upland waste rock

C02a

$120,000

$83,800

$203,800

$15,600

$219,400

BUR097

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$869,000

$929,000

$1,798,000

$659,000

$2,457,000





Upland waste rock

C02a

$73,300

$51,300

$124,600

$9,530

$134,130

BUR098

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$905,000

$968,000

$1,873,000

$896,000

$2,769,000





Upland waste rock (potential intermixed tailings)

C01

$235,000

$165,000

$400,000

$0

$400,000







C07

$809,000

$566,000

$1,375,000

$178,000

$1,553,000

BUR112

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500

BUR117

BLM Polygon

Upland tailings

C01

$7,700

$5,390

$13,090

$0

$13,090







C07

$26,500

$18,500

$45,000

$5,820

$50,820





Upland waste rock (potential intermixed tailings)

C03

$250,000

$175,000

$425,000

$30,000

$455,000

BUR118

BLM Polygon

Upland waste rock (erosion potential)

C01

$141,000

$98,900

$239,900

$0

$239,900







C07

$485,000

$340,000

$825,000

$107,000

$932,000

BUR119

BLM Polygon

Upland waste rock

C02a

$175,000

$123,000

$298,000

$22,800

$320,800

BUR120

BLM Polygon

Upland waste rock (erosion potential)

C02a

$78,400

$54,900

$133,300

$10,200

$143,500

BUR121

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$682,000

$729,000

$1,411,000

$517,000

$1,928,000





Upland waste rock (erosion potential)

C01

$88,200

$61,700

$149,900

$0

$149,900







C03

$452,000

$317,000

$769,000

$54,300

$823,300

BUR122

BLM Polygon

Upland waste rock (erosion potential)

C01

$23,100

$16,200

$39,300

$0

$39,300







C03

$252,000

$176,000

$428,000

$30,200

$458,200

BUR124

BLM Polygon

Upland waste rock (erosion potential)

C02a

$84,300

$59,000

$143,300

$11,000

$154,300

BUR125

BLM Polygon

Upland waste rock (erosion potential)

C02a

$27,000

$18,900

$45,900

$3,510

$49,410

BUR128

BLM Polygon

Buildings & structures

HH-3

$136,000

$95,100

$231,100

$6,790

$237,890





Upland tailings

C01

$186,000

$130,000

$316,000

$0

$316,000







C07

$638,000

$447,000

$1,085,000

$140,000

$1,225,000

BUR129

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Upland tailings

C01

$22,500

$15,700

$38,200

$0

$38,200







C07

$77,200

$54,000

$131,200

$17,000

$148,200

BUR141

BLM Polygon

Floodplain sediments

C01b

$297,000

$208,000

$505,000

$0

$505,000







C08a

$389,000

$273,000

$662,000

$54,500

$716,500







HAUL-2

$121,000

$84,500

$205,500

$0

$205,500

BUR142

BLM Polygon

Upland tailings

C01

$10,500

$7,340

$17,840

$0

$17,840







C07

$36,000

$25,200

$61,200

$7,920

$69,120





Upland waste rock (potential intermixed tailings)

C03

$680,000

$476,000

$1,156,000

$81,500

$1,237,500

BUR143

BLM Polygon

Floodplain sediments

C01b

$432,000

$302,000

$734,000

$0

$734,000







C08a

$566,000

$396,000

$962,000

$79,300

$1,041,300







HAUL-2

$176,000

$123,000

$299,000

$0

$299,000

Page 4 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

BUR144

BLM Polygon

Upland waste rock (erosion potential)

C01

$33,400

$23,400

$56,800

$0

$56,800







C03

$572,000

$400,000

$972,000

$68,600

$1,040,600

BUR176

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$126,000

$88,200

$214,200

$15,100

$229,300

BUR177

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$153,000

$107,000

$260,000

$18,400

$278,400

BUR178

BLM Polygon

Upland waste rock (erosion potential)

C01

$9,420

$6,590

$16,010

$0

$16,010







C03

$104,000

$72,500

$176,500

$12,400

$188,900

BUR189

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$45,000

$31,500

$76,500

$5,400

$81,900

BUR190

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$302,000

$323,000

$625,000

$165,000

$790,000

BUR191

BLM Polygon

Upland waste rock

C02a

$131,000

$91,500

$222,500

$17,000

$239,500

BUR192

BLM Polygon

Floodplain tailings (discrete site)

C01

$13,300

$9,290

$22,590

$0

$22,590







C07

$45,600

$31,900

$77,500

$10,000

$87,500





Upland waste rock (erosion potential)

C01

$23,100

$16,200

$39,300

$0

$39,300







C03

$252,000

$176,000

$428,000

$30,200

$458,200

BUR204

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$42,800

$29,900

$72,700

$5,130

$77,830

CC04-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$732,000

$512,000

$1,244,000

$220,000

$1,464,000







CD-AVG

$371,000

$260,000

$631,000

$111,000

$742,000







CD-SED

$37,400

$26,200

$63,600

$224,000

$287,600







FP/RP-AVG

$510,000

$357,000

$867,000

$91,900

$958,900







VBS-AVG

$520,000

$364,000

$884,000

$156,000

$1,040,000

HHWPCC04-1

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

HHWPCC04-2

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

HHWPCC04-3

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

CCSeg05 CC05-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$81,400

$57,000

$138,400

$24,400

$162,800







CD-AVG

$20,600

$14,400

$35,000

$6,180

$41,180







CD-SED

$1,870

$1,310

$3,180

$11,200

$14,380







FP/RP-AVG

$916,000

$641,000

$1,557,000

$165,000

$1,722,000







VBS-AVG

$57,800

$40,400

$98,200

$17,300

$115,500

CC05-2

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$492,000

$344,000

$836,000

$148,000

$984,000







CD-AVG

$124,000

$86,500

$210,500

$37,100

$247,600







CD-SED

$13,100

$9,160

$22,260

$78,500

$100,760







CH REAL-1

$3,780,000

$2,650,000

$6,430,000

$643,000

$7,073,000







FP/RP-AVG

$1,800,000

$1,260,000

$3,060,000

$324,000

$3,384,000







VBS-AVG

$350,000

$245,000

$595,000

$105,000

$700,000

OSB047

BLM Polygon

Floodplain sediments

C01b

$47,000

$32,900

$79,900

$0

$79,900







C08a

$61,700

$43,200

$104,900

$8,640

$113,540







HAUL-2

$19,100

$13,400

$32,500

$0

$32,500

WAL010

BLM Polygon

Floodplain sediments

C01b

$13,800

$9,640

$23,440

$0

$23,440

Page 5 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







C08a

$18,100

$12,600

$30,700

$2,530

$33,230







HAUL-2

$5,600

$3,920

$9,520

$0

$9,520

WAL011

BLM Polygon

Adit drainage

WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Floodplain sediments

C01b

$29,700

$20,800

$50,500

$0

$50,500







C08a

$38,900

$27,300

$66,200

$5,450

$71,650







HAUL-2

$12,100

$8,450

$20,550

$0

$20,550

WAL039

BLM Polygon

Upland tailings

C01

$53,500

$37,500

$91,000

$0

$91,000







C08a

$221,000

$155,000

$376,000

$31,000

$407,000







HAUL-2

$68,600

$48,000

$116,600

$0

$116,600

WAL040

BLM Polygon

Floodplain sediments

C01b

$175,000

$122,000

$297,000

$0

$297,000







C08a

$229,000

$161,000

$390,000

$32,100

$422,100







HAUL-2

$71,200

$49,800

$121,000

$0

$121,000

WAL041

BLM Polygon

Floodplain sediments

C01b

$53,500

$37,500

$91,000

$0

$91,000







C08a

$70,200

$49,100

$119,300

$9,830

$129,130







HAUL-2

$21,800

$15,200

$37,000

$0

$37,000

WAL042

BLM Polygon

Floodplain tailings - inactive Facilities

C03

$579,000

$406,000

$985,000

$69,500

$1,054,500

WAL081

BLM Polygon

Floodplain artificial fill

C01

$12,200

$8,540

$20,740

$0

$20,740







C08a

$50,400

$35,300

$85,700

$7,060

$92,760







HAUL-2

$15,600

$11,000

$26,600

$0

$26,600

WP-OPTIONC

BLM Polygon

Floodplain sediments

C14b

$1,360,000

$954,000

$2,314,000

$54,500

$2,368,500







C15b

$7,070,000

$4,950,000

$12,020,000

$141,000

$12,161,000





Groundwater

WT01

$453,000

$485,000

$938,000

$549,000

$1,487,000





Source General Information

PIPE-2

$388,000

$272,000

$660,000

$31,000

$691,000

MIDGradSeg PIPEMG

General Feature

Source General Information

PIPE-1

$417,000

$292,000

$709,000

$33,300

$742,300







PIPE-2

$40,400

$28,300

$68,700

$3,230

$71,930







PIPE-4

$12,100,000

$8,480,000

$20,580,000

$969,000

$21,549,000

MIDGradSegOl HHWPMG01-1

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

HHWPMG01-2

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

HHWPMG01-3

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

HHWPMG01-4

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

HHWPMG01-5

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

KLE011

BLM Polygon

Upland tailings - inactive facilities

C09

$1,940,000

$1,360,000

$3,300,000

$388,000

$3,688,000

KLE016

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$140,000

$97,700

$237,700

$16,700

$254,400

KLE020

BLM Polygon

Upland waste rock (erosion potential)

C01

$30,800

$21,600

$52,400

$0

$52,400







C03

$333,000

$233,000

$566,000

$40,000

$606,000

KLE021

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$146,000

$102,000

$248,000

$17,600

$265,600

KLE023

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$259,000

$181,000

$440,000

$31,100

$471,100

KLE033

BLM Polygon

Upland waste rock (erosion potential)

C01

$21,400

$15,000

$36,400

$0

$36,400







C03

$360,000

$252,000

$612,000

$43,200

$655,200

Page 6 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Segment ID

Trait Description

2009 Total
Direct Capital

2009 Indirect

2009 Total
Direct and
Indirect Capital

O&M Cost (30- Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

KLE034

BLM Polygon

Floodplain waste rock

C01

$18,800

$13,200

$32,000

$0

$32,000







C03

$515,000

$361,000

$876,000

$61,800

$937,800

KLE035

BLM Polygon

Buildings & structures

HH-3

$136,000

$95,100

$231,100

$6,790

$237,890







C01

$257,000

$180,000

$437,000

$0

$437,000







C03

$3,030,000

$2,120,000

$5,150,000

$363,000

$5,513,000

KLE040

BLM Polygon

Floodplain sediments

C14c

$10,400,000

$7,280,000

$17,680,000

$312,000

$17,992,000







C15b

$3,170,000

$2,220,000

$5,390,000

$63,500

$5,453,500





Groundwater

WT01

$402,000

$430,000

$832,000

$609,000

$1,441,000

KLE042

BLM Polygon

Floodplain sediments

C01b

$675,000

$473,000

$1,148,000

$0

$1,148,000







C08a

$885,000

$620,000

$1,505,000

$124,000

$1,629,000







HAUL-2

$275,000

$192,000

$467,000

$0

$467,000





Floodplain tailings

C01

$55,600

$38,900

$94,500

$0

$94,500







C07

$191,000

$134,000

$325,000

$42,000

$367,000

KLE048

BLM Polygon

Floodplain sediments

C01b

$744,000

$521,000

$1,265,000

$0

$1,265,000







C08a

$975,000

$683,000

$1,658,000

$137,000

$1,795,000







C14c

$8,910,000

$6,240,000

$15,150,000

$267,000

$15,417,000







C15b

$2,720,000

$1,900,000

$4,620,000

$54,400

$4,674,400







HAUL-2

$302,000

$212,000

$514,000

$0

$514,000





Groundwater

WT01

$402,000

$430,000

$832,000

$609,000

$1,441,000





Floodplain sediments

C01b

$1,760,000

$1,230,000

$2,990,000

$0

$2,990,000







C08a

$2,300,000

$1,610,000

$3,910,000

$322,000

$4,232,000







C14c

$7,430,000

$5,200,000

$12,630,000

$223,000

$12,853,000







C15b

$2,270,000

$1,590,000

$3,860,000

$45,400

$3,905,400







HAUL-2

$714,000

$500,000

$1,214,000

$0

$1,214,000





Groundwater

WT01

$402,000

$430,000

$832,000

$609,000

$1,441,000

KLE051

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$74,300

$52,000

$126,300

$8,910

$135,210

KLE062

BLM Polygon

Floodplain sediments

C01b

$351,000

$246,000

$597,000

$0

$597,000







C08a

$460,000

$322,000

$782,000

$64,400

$846,400







HAUL-2

$143,000

$99,900

$242,900

$0

$242,900

KLE066

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$85,500

$59,900

$145,400

$10,300

$155,700

KLE067

BLM Polygon

Upland waste rock (erosion potential)

C01

$23,500

$16,500

$40,000

$0

$40,000







C03

$45,000

$31,500

$76,500

$5,400

$81,900

KLE068

BLM Polygon

Upland waste rock (erosion potential)

C01

$59,900

$41,900

$101,800

$0

$101,800







C07

$206,000

$144,000

$350,000

$45,300

$395,300

KLE069

BLM Polygon

Upland waste rock (erosion potential)

C01

$2,780

$1,950

$4,730

$0

$4,730







C03

$94,500

$66,200

$160,700

$11,300

$172,000

KLE070

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$94,500

$66,200

$160,700

$11,300

$172,000

KLE074

BLM Polygon

Buildings & structures

HH-3

$136,000

$95,100

$231,100

$6,790

$237,890





Upland tailings

C01

$59,900

$41,900

$101,800

$0

$101,800

Page 7 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







C07

$206,000

$144,000

$350,000

$45,300

$395,300

KLE075

BLM Polygon

Upland tailings

C01

$17,100

$12,000

$29,100

$0

$29,100







C07

$58,800

$41,200

$100,000

$12,900

$112,900

MG01-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$110,000

$76,900

$186,900

$32,900

$219,800







CD-AVG

$53,600

$37,500

$91,100

$16,100

$107,200







CD-SED

$5,610

$3,930

$9,540

$33,700

$43,240







FP/RP-AVG

$46,800

$32,800

$79,600

$8,430

$88,030

MG01-2

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$97,600

$68,300

$165,900

$29,300

$195,200







CD-AVG

$28,800

$20,200

$49,000

$8,650

$57,650







CD-SED

$3,740

$2,620

$6,360

$22,400

$28,760







FP/RP-AVG

$131,000

$91,500

$222,500

$23,500

$246,000

MG01-3

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$134,000

$93,900

$227,900

$40,300

$268,200







CD-AVG

$18,500

$13,000

$31,500

$5,560

$37,060







CD-SED

$1,870

$1,310

$3,180

$11,200

$14,380







FP/RP-AVG

$199,000

$140,000

$339,000

$35,900

$374,900







VBS-AVG

$57,200

$40,000

$97,200

$17,200

$114,400

MG01-4

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$305,000

$214,000

$519,000

$91,500

$610,500







CD-AVG

$53,600

$37,500

$91,100

$16,100

$107,200







CD-SED

$5,610

$3,930

$9,540

$33,700

$43,240







FP/RP-AVG

$1,560,000

$1,100,000

$2,660,000

$282,000

$2,942,000







VBS-AVG

$130,000

$91,000

$221,000

$39,000

$260,000

MG01-5

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$97,600

$68,300

$165,900

$29,300

$195,200







CD-AVG

$12,400

$8,650

$21,050

$3,710

$24,760







CD-SED

$1,870

$1,310

$3,180

$11,200

$14,380







FP/RP-AVG

$35,000

$24,500

$59,500

$6,310

$65,810







VBS-AVG

$41,600

$29,100

$70,700

$12,500

$83,200

MG01-6

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$384,000

$269,000

$653,000

$115,000

$768,000







CD-AVG

$70,000

$49,000

$119,000

$21,000

$140,000







CD-SED

$7,480

$5,240

$12,720

$44,900

$57,620







FP/RP-AVG

$518,000

$363,000

$881,000

$93,300

$974,300







OFFCH-AVG

$956,000

$669,000

$1,625,000

$172,000

$1,797,000







VBS-AVG

$164,000

$115,000

$279,000

$49,100

$328,100

MG01-7

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$433,000

$303,000

$736,000

$130,000

$866,000







CD-AVG

$18,500

$13,000

$31,500

$5,560

$37,060







CD-SED

$1,870

$1,310

$3,180

$11,200

$14,380







FP/RP-AVG

$443,000

$310,000

$753,000

$79,700

$832,700







OFFCH-AVG

$998,000

$699,000

$1,697,000

$180,000

$1,877,000







VBS-AVG

$185,000

$129,000

$314,000

$55,400

$369,400

MG01-8

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$286,000

$200,000

$486,000

$85,900

$571,900







CD-AVG

$43,300

$30,300

$73,600

$13,000

$86,600







CD-SED

$3,740

$2,620

$6,360

$22,400

$28,760







CH REAL-1

$1,320,000

$924,000

$2,244,000

$225,000

$2,469,000

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)

Page 8 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







FP/RP-AVG

$17,900

$12,600

$30,500

$3,230

$33,730







OFFCH-AVG

$3,640,000

$2,550,000

$6,190,000

$655,000

$6,845,000







VBS-AVG

$122,000

$85,400

$207,400

$36,600

$244,000

MG01-9

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$68,000

$47,600

$115,600

$20,400

$136,000







CD-AVG

$10,300

$7,210

$17,510

$3,090

$20,600







CD-SED

$1,870

$1,310

$3,180

$11,200

$14,380







CH REAL-1

$314,000

$219,000

$533,000

$53,300

$586,300







FP/RP-AVG

$305,000

$214,000

$519,000

$55,000

$574,000







VBS-AVG

$29,000

$20,300

$49,300

$8,690

$57,990

MG01-10

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$48,800

$34,200

$83,000

$14,600

$97,600







CD-AVG

$8,240

$5,770

$14,010

$2,470

$16,480







CD-SED

$1,870

$1,310

$3,180

$11,200

$14,380







FP/RP-AVG

$68,700

$48,100

$116,800

$12,400

$129,200







VBS-AVG

$20,800

$14,600

$35,400

$6,240

$41,640

MG01-11

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$140,000

$98,200

$238,200

$42,100

$280,300







CD-AVG

$14,400

$10,100

$24,500

$4,330

$28,830







CD-SED

$1,870

$1,310

$3,180

$11,200

$14,380







FP/RP-AVG

$384,000

$269,000

$653,000

$69,100

$722,100







VBS-AVG

$59,800

$41,900

$101,700

$17,900

$119,600

MG01-12

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$134,000

$93,900

$227,900

$40,300

$268,200







CD-AVG

$26,800

$18,700

$45,500

$8,030

$53,530







CD-SED

$3,740

$2,620

$6,360

$22,400

$28,760







FP/RP-AVG

$554,000

$388,000

$942,000

$99,700

$1,041,700







OFFCH-AVG

$2,320,000

$1,620,000

$3,940,000

$417,000

$4,357,000







VBS-AVG

$57,200

$40,000

$97,200

$17,200

$114,400

MG01-13

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$305,000

$214,000

$519,000

$91,500

$610,500







CD-AVG

$43,300

$30,300

$73,600

$13,000

$86,600







CD-SED

$3,740

$2,620

$6,360

$22,400

$28,760







CH REAL-1

$1,270,000

$892,000

$2,162,000

$217,000

$2,379,000







FP/RP-AVG

$342,000

$239,000

$581,000

$61,500

$642,500







OFFCH-AVG

$3,570,000

$2,500,000

$6,070,000

$642,000

$6,712,000







VBS-AVG

$130,000

$91,000

$221,000

$39,000

$260,000

MG01-14

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$92,500

$64,700

$157,200

$27,700

$184,900







CD-AVG

$14,400

$10,100

$24,500

$4,330

$28,830







CD-SED

$1,870

$1,310

$3,180

$11,200

$14,380







CH REAL-1

$426,000

$298,000

$724,000

$72,500

$796,500







FP/RP-AVG

$203,000

$142,000

$345,000

$36,600

$381,600







OFFCH-AVG

$179,000

$125,000

$304,000

$32,300

$336,300







VBS-AVG

$39,400

$27,600

$67,000

$11,800

$78,800

MG01-15

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$47,100

$33,000

$80,100

$14,100

$94,200







CD-AVG

$35,000

$24,500

$59,500

$10,500

$70,000







CD-SED

$3,740

$2,620

$6,360

$22,400

$28,760

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)

Page 9 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







FP/RP-AVG

$51,800

$36,200

$88,000

$9,320

$97,320







OFFCH-AVG

$2,650,000

$1,850,000

$4,500,000

$476,000

$4,976,000







VBS-AVG

$20,100

$14,100

$34,200

$6,020

$40,220

MG01-16

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$13,100

$9,140

$22,240

$3,920

$26,160







CD-AVG

$20,600

$14,400

$35,000

$6,180

$41,180







CD-SED

$1,870

$1,310

$3,180

$11,200

$14,380







FP/RP-AVG

$19,400

$13,600

$33,000

$3,500

$36,500







OFFCH-AVG

$444,000

$311,000

$755,000

$80,000

$835,000







VBS-AVG

$5,560

$3,890

$9,450

$1,670

$11,120

MG01-17

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$334,000

$234,000

$568,000

$100,000

$668,000







CD-AVG

$49,400

$34,600

$84,000

$14,800

$98,800







CD-SED

$5,610

$3,930

$9,540

$33,700

$43,240







CH REAL-1

$1,540,000

$1,080,000

$2,620,000

$262,000

$2,882,000







FP/RP-AVG

$523,000

$366,000

$889,000

$94,100

$983,100







OFFCH-AVG

$659,000

$462,000

$1,121,000

$119,000

$1,240,000







VBS-AVG

$142,000

$99,700

$241,700

$42,700

$284,400

MG01-18

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$167,000

$117,000

$284,000

$50,000

$334,000







CD-AVG

$24,700

$17,300

$42,000

$7,420

$49,420







CD-SED

$3,740

$2,620

$6,360

$22,400

$28,760







CH REAL-1

$768,000

$538,000

$1,306,000

$131,000

$1,437,000







FP/RP-AVG

$537,000

$376,000

$913,000

$96,600

$1,009,600







OFFCH-AVG

$231,000

$162,000

$393,000

$41,500

$434,500







VBS-AVG

$71,000

$49,700

$120,700

$21,300

$142,000

MUL085

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C04

$94,000

$65,800

$159,800

$21,600

$181,400

MUL086

BLM Polygon

Upland waste rock (erosion potential)

C01

$25,700

$18,000

$43,700

$0

$43,700







C03

$284,000

$198,000

$482,000

$34,000

$516,000

OSB025

BLM Polygon

Upland waste rock (erosion potential)

C01

$10,300

$7,190

$17,490

$0

$17,490







C03

$113,000

$78,800

$191,800

$13,500

$205,300

OSB030

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$101,000

$70,900

$171,900

$12,200

$184,100

OSB065

BLM Polygon

Floodplain sediments

C01b

$5,860,000

$4,100,000

$9,960,000

$0

$9,960,000







C08a

$7,680,000

$5,380,000

$13,060,000

$1,080,000

$14,140,000







C14c

$65,300,000

$45,700,000

$111,000,000

$1,960,000

$112,960,000







C15b

$20,000,000

$14,000,000

$34,000,000

$399,000

$34,399,000







HAUL-2

$2,380,000

$1,670,000

$4,050,000

$0

$4,050,000





Groundwater

WT01

$402,000

$430,000

$832,000

$609,000

$1,441,000

OSB070

BLM Polygon

Upland waste rock (erosion potential)

C01

$26,500

$18,600

$45,100

$0

$45,100







C03

$293,000

$205,000

$498,000

$35,100

$533,100

OSB072

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$51,800

$36,200

$88,000

$6,210

$94,210

OSB073

BLM Polygon

Upland waste rock (erosion potential)

C01

$18,800

$13,200

$32,000

$0

$32,000

Page 10 of 28

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







C03

$131,000

$91,400

$222,400

$15,700

$238,100

OSB074

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000

OSB075

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$63,000

$44,100

$107,100

$7,560

$114,660

OSB076

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$45,000

$31,500

$76,500

$5,400

$81,900

OSB078

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$18,000

$12,600

$30,600

$2,160

$32,760

OSB117

BLM Polygon

Floodplain tailings

C01

$59,900

$41,900

$101,800

$0

$101,800







C07

$206,000

$144,000

$350,000

$45,300

$395,300

OSB118

BLM Polygon

Floodplain sediments

C01b

$810,000

$567,000

$1,377,000

$0

$1,377,000







C08a

$1,060,000

$743,000

$1,803,000

$149,000

$1,952,000







HAUL-2

$329,000

$231,000

$560,000

$0

$560,000

OSB119

BLM Polygon

Floodplain sediments (underlying tailings pond)

C11j

$11,100,000

$7,790,000

$18,890,000

$223,000

$19,113,000





Groundwater

WT01

$30,200

$32,300

$62,500

$22,900

$85,400

OSB120

BLM Polygon

Floodplain sediments

C01b

$3,890,000

$2,720,000

$6,610,000

$0

$6,610,000







C08a

$5,100,000

$3,570,000

$8,670,000

$714,000

$9,384,000







C14c

$41,600,000

$29,100,000

$70,700,000

$1,250,000

$71,950,000







C15b

$12,700,000

$8,890,000

$21,590,000

$254,000

$21,844,000







HAUL-2

$1,580,000

$1,110,000

$2,690,000

$0

$2,690,000





Groundwater

WT01

$402,000

$430,000

$832,000

$609,000

$1,441,000

POL018

BLM Polygon

Upland waste rock (erosion potential)

C01

$18,800

$13,200

$32,000

$0

$32,000







C03

$205,000

$143,000

$348,000

$24,600

$372,600

POL019

BLM Polygon

Upland waste rock (erosion potential)

C05

$1,880,000

$1,320,000

$3,200,000

$434,000

$3,634,000

POL021

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$149,000

$104,000

$253,000

$17,800

$270,800

POL064

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$45,000

$31,500

$76,500

$5,400

$81,900

WAL001

BLM Polygon

Floodplain sediments (underlying tailings pond)

C11j

$13,400,000

$9,350,000

$22,750,000

$267,000

$23,017,000





Groundwater

WT01

$60,300

$64,500

$124,800

$18,300

$143,100





Upland tailings - active facilities

C09

$16,300,000

$11,400,000

$27,700,000

$3,260,000

$30,960,000

WAL002

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$603

$645

$1,248

$366

$1,614





Floodplain waste rock

C01

$171

$120

$291

$0

$291







C03

$196,000

$137,000

$333,000

$23,500

$356,500

WAL004

BLM Polygon

Floodplain sediments

C01b

$1,470,000

$1,030,000

$2,500,000

$0

$2,500,000







C08a

$1,930,000

$1,350,000

$3,280,000

$270,000

$3,550,000







C14c

$25,200,000

$17,700,000

$42,900,000

$757,000

$43,657,000







C15b

$7,710,000

$5,400,000

$13,110,000

$154,000

$13,264,000







HAUL-2

$597,000

$418,000

$1,015,000

$0

$1,015,000





Groundwater

WT01

$402,000

$430,000

$832,000

$609,000

$1,441,000

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)

Page 11 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

WAL014

BLM Polygon

Upland waste rock (erosion potential)

C01

$33,400

$23,400

$56,800

$0

$56,800







C03

$362,000

$254,000

$616,000

$43,500

$659,500

WAL016

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

WAL020

BLM Polygon

Upland waste rock (erosion potential)

C01

$297,000

$208,000

$505,000

$0

$505,000







C03

$1,310,000

$914,000

$2,224,000

$157,000

$2,381,000

WAL024

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$96,800

$67,700

$164,500

$11,600

$176,100

WAL034

BLM Polygon

Floodplain sediments

C01b

$527,000

$369,000

$896,000

$0

$896,000







C08a

$690,000

$483,000

$1,173,000

$96,600

$1,269,600







HAUL-2

$214,000

$150,000

$364,000

$0

$364,000

WAL035

BLM Polygon

Floodplain waste rock

C01

$120,000

$83,900

$203,900

$0

$203,900







C03

$1,330,000

$928,000

$2,258,000

$159,000

$2,417,000

WAL036

BLM Polygon

Floodplain sediments

C01b

$304,000

$213,000

$517,000

$0

$517,000







C07

$331,000

$232,000

$563,000

$72,800

$635,800

WAL037

BLM Polygon

Upland tailings

C01

$51,400

$36,000

$87,400

$0

$87,400







C07

$176,000

$123,000

$299,000

$38,800

$337,800

WAL046

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$58,500

$41,000

$99,500

$7,020

$106,520

WAL055

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$38,300

$26,800

$65,100

$4,590

$69,690

WAL056

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$54,000

$37,800

$91,800

$6,480

$98,280

WAL057

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$22,500

$15,800

$38,300

$2,700

$41,000

WAL058

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$20,300

$14,200

$34,500

$2,430

$36,930

WAL062

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$42,800

$29,900

$72,700

$5,130

$77,830

WAL064

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$78,800

$55,100

$133,900

$9,450

$143,350

WAL072

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$18,000

$12,600

$30,600

$2,160

$32,760

WAL073

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$22,500

$15,800

$38,300

$2,700

$41,000

MIDGradSeg02 KLW061

BLM Polygon

Upland waste rock

C02b

$2,320,000

$1,620,000

$3,940,000

$301,000

$4,241,000

KLW062

BLM Polygon

Upland waste rock

C02b

$356,000

$249,000

$605,000

$46,200

$651,200

KLW070

BLM Polygon

Floodplain sediments

C01b

$126,000

$88,400

$214,400

$0

$214,400







C08a

$165,000

$116,000

$281,000

$23,200

$304,200







HAUL-2

$51,300

$35,900

$87,200

$0

$87,200

KLW095

BLM Polygon

Upland waste rock

C02b

$137,000

$95,900

$232,900

$17,800

$250,700

MG02-10

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$7,540

$5,270

$12,810

$2,260

$15,070

Page 12 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site















2009 Total















2009 Total



Direct and











Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)









CD-AVG

$22,700

$15,900

$38,600

$6,800

$45,400









CD-SED

$1,870

$1,310

$3,180

$11,200

$14,380









VBS-AVG

$6,420

$4,500

$10,920

$1,930

$12,850



MG02-11

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$6,660

$4,660

$11,320

$2,000

$13,320









CD-AVG

$8,240

$5,770

$14,010

$2,470

$16,480









CD-SED

$1,870

$1,310

$3,180

$11,200

$14,380









VBS-AVG

$5,680

$3,980

$9,660

$1,700

$11,360



MG02-12

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$1,830

$1,280

$3,110

$549

$3,659









CD-AVG

$2,060

$1,440

$3,500

$618

$4,118









FP/RP-AVG

$2,070

$1,450

$3,520

$372

$3,892









VBS-AVG

$401

$281

$682

$120

$802

MoonCrkSegOl

KLE061

BLM Polygon

Floodplain waste rock

C01

$856

$599

$1,455

$0

$1,455









C08a

$3,540

$2,480

$6,020

$496

$6,516









HAUL-2

$1,100

$769

$1,869

$0

$1,869



MC01-2

Bioengineering Reach

BioReach Current Deflector Frequency

CD-SED

$7,480

$5,240

$12,720

$44,900

$57,620







BioReach General Characteristics

BSBR-AVG

$187,000

$131,000

$318,000

$56,000

$374,000









CD-AVG

$70,000

$49,000

$119,000

$21,000

$140,000









FP/RP-AVG

$154,000

$108,000

$262,000

$27,700

$289,700









VBS-AVG

$79,600

$55,700

$135,300

$23,900

$159,200

MoonCrkSeg02

KLE008

BLM Polygon

Upland waste rock (erosion potential)

C02b

$109,000

$76,000

$185,000

$14,100

$199,100



KLE014

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455









C08a

$3,540

$2,480

$6,020

$496

$6,516









HAUL-2

$1,100

$769

$1,869

$0

$1,869



KLE041

BLM Polygon

Floodplain sediments

C01b

$44,600

$31,200

$75,800

$0

$75,800









C08a

$58,400

$40,900

$99,300

$8,180

$107,480









HAUL-2

$18,100

$12,700

$30,800

$0

$30,800



KLE063

BLM Polygon

Upland waste rock (erosion potential)

C02b

$25,100

$17,500

$42,600

$3,260

$45,860



KLE064

BLM Polygon

Upland waste rock (erosion potential)

C02b

$21,700

$15,200

$36,900

$2,820

$39,720



KLE065

BLM Polygon

Upland waste rock (erosion potential)

C02b

$38,400

$26,900

$65,300

$4,990

$70,290



MC02-2

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$163,000

$114,000

$277,000

$48,800

$325,800









CD-AVG

$124,000

$86,500

$210,500

$37,100

$247,600









CD-SED

$13,100

$9,160

$22,260

$78,500

$100,760









FP/RP-AVG

$447,000

$313,000

$760,000

$80,500

$840,500









VBS-AVG

$69,400

$48,600

$118,000

$20,800

$138,800



MC02-3

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$136,000

$95,400

$231,400

$40,900

$272,300









CD-AVG

$51,500

$36,100

$87,600

$15,500

$103,100









CD-SED

$5,610

$3,930

$9,540

$33,700

$43,240









FP/RP-AVG

$225,000

$157,000

$382,000

$40,400

$422,400









VBS-AVG

$58,100

$40,700

$98,800

$17,400

$116,200



MC02-4

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$70,800

$49,500

$120,300

$21,200

$141,500









CD-AVG

$53,600

$37,500

$91,100

$16,100

$107,200









CD-SED

$5,610

$3,930

$9,540

$33,700

$43,240

Page 13 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







FP/RP-AVG

$194,000

$136,000

$330,000

$34,900

$364,900







VBS-AVG

$45,200

$31,600

$76,800

$13,600

$90,400

NMSeg PIPENM

General Feature

Source General Information

PIPE-1

$1,560,000

$1,090,000

$2,650,000

$125,000

$2,775,000

NMSegOl BUR051

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000

BUR052

BLM Polygon

Upland waste rock

C01

$3,420

$2,400

$5,820

$0

$5,820







C03

$36,000

$25,200

$61,200

$4,320

$65,520

BUR053

BLM Polygon

Upland waste rock (erosion potential)

C01

$2,960,000

$2,070,000

$5,030,000

$0

$5,030,000







C04

$2,150,000

$1,500,000

$3,650,000

$494,000

$4,144,000

BUR140

BLM Polygon

Floodplain sediments

C01b

$135,000

$94,500

$229,500

$0

$229,500







C08a

$177,000

$124,000

$301,000

$24,800

$325,800







HAUL-2

$54,900

$38,400

$93,300

$0

$93,300

BUR160

BLM Polygon

Upland waste rock (erosion potential)

C04

$1,070,000

$747,000

$1,817,000

$245,000

$2,062,000

NM01-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$489,000

$343,000

$832,000

$147,000

$979,000







CD-AVG

$98,900

$69,200

$168,100

$29,700

$197,800







CD-SED

$9,350

$6,550

$15,900

$56,100

$72,000







FP/RP-AVG

$269,000

$188,000

$457,000

$48,400

$505,400







VBS-AVG

$209,000

$146,000

$355,000

$62,600

$417,600

NMSeg02 BUR054

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$211,000

$148,000

$359,000

$549,000

$908,000





Upland tailings - inactive facilities

C09

$615,000

$431,000

$1,046,000

$123,000

$1,169,000





Upland waste rock (potential intermixed tailings)

C03

$4,820,000

$3,370,000

$8,190,000

$578,000

$8,768,000

BUR055

BLM Polygon

Floodplain sediments

C01b

$74,300

$52,000

$126,300

$0

$126,300







C08a

$97,400

$68,100

$165,500

$13,600

$179,100







HAUL-2

$30,200

$21,100

$51,300

$0

$51,300





Upland tailings

C07

$206,000

$144,000

$350,000

$45,300

$395,300







C01

$59,900

$41,900

$101,800

$0

$101,800

BUR056

BLM Polygon

Upland waste rock (potential intermixed tailings)

C02b

$2,230,000

$1,560,000

$3,790,000

$290,000

$4,080,000

BUR058

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000

BUR139

BLM Polygon

Upland waste rock

C03

$295,000

$206,000

$501,000

$35,400

$536,400

BUR170

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$453,000

$317,000

$770,000

$1,160,000

$1,930,000





Upland waste rock (potential intermixed tailings)

C03

$214,000

$150,000

$364,000

$25,700

$389,700

BUR171

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$330,000

$231,000

$561,000

$1,060,000

$1,621,000





Upland waste rock (potential intermixed tailings)

C03

$149,000

$104,000

$253,000

$17,800

$270,800

BUR172

BLM Polygon

Upland waste rock

C03

$96,800

$67,700

$164,500

$11,600

$176,100

NM02-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$921,000

$645,000

$1,566,000

$276,000

$1,842,000







CD-AVG

$185,000

$130,000

$315,000

$55,600

$370,600







CD-SED

$18,700

$13,100

$31,800

$112,000

$143,800







FP/RP-AVG

$506,000

$354,000

$860,000

$91,100

$951,100

Page 14 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







OFFCH-AVG

$14,800

$10,300

$25,100

$2,660

$27,760







VBS-AVG

$393,000

$275,000

$668,000

$118,000

$786,000

OSB040

BLM Polygon

Floodplain sediments

C01b

$228,000

$160,000

$388,000

$0

$388,000







C08a

$299,000

$210,000

$509,000

$41,900

$550,900







HAUL-2

$92,800

$65,000

$157,800

$0

$157,800

OSB044

BLM Polygon

Floodplain sediments

C01b

$135,000

$94,500

$229,500

$0

$229,500







C08a

$177,000

$124,000

$301,000

$24,800

$325,800







HAUL-2

$54,900

$38,400

$93,300

$0

$93,300





Upland tailings (jig tailings)

C01

$1,540,000

$1,080,000

$2,620,000

$0

$2,620,000







C08a

$6,370,000

$4,460,000

$10,830,000

$892,000

$11,722,000







HAUL-2

$1,980,000

$1,380,000

$3,360,000

$0

$3,360,000





Upland waste rock

C02a

$37,900

$26,600

$64,500

$4,930

$69,430

OSB048

BLM Polygon

Upland waste rock

C02a

$12,600

$8,850

$21,450

$1,640

$23,090

OSB056

BLM Polygon

Floodplain sediments

C01b

$21,600

$15,100

$36,700

$0

$36,700







C08a

$28,300

$19,800

$48,100

$3,960

$52,060







HAUL-2

$8,780

$6,150

$14,930

$0

$14,930

OSB057

BLM Polygon

Floodplain sediments

C01b

$176,000

$123,000

$299,000

$0

$299,000







C08a

$230,000

$161,000

$391,000

$32,200

$423,200







HAUL-2

$71,400

$50,000

$121,400

$0

$121,400

OSB058

BLM Polygon

Floodplain sediments

C01b

$21,600

$15,100

$36,700

$0

$36,700







C08a

$28,300

$19,800

$48,100

$3,960

$52,060







HAUL-2

$8,780

$6,150

$14,930

$0

$14,930

OSB088

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$3,920

$4,200

$8,120

$2,970

$11,090

OSB089

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$10,600

$11,300

$21,900

$8,690

$30,590

NMSeg03 NM03-1

Bioengineering Reach

BioReach General Characteristics

CD-AVG

$68,000

$47,600

$115,600

$20,400

$136,000







CD-SED

$7,480

$5,240

$12,720

$44,900

$57,620







FP/RP-AVG

$621,000

$434,000

$1,055,000

$112,000

$1,167,000







OFFCH-AVG

$56,000

$39,200

$95,200

$10,100

$105,300







VBS-AVG

$169,000

$118,000

$287,000

$50,600

$337,600

NMSeg04 NM04-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$252,000

$177,000

$429,000

$75,700

$504,700







CD-AVG

$51,500

$36,100

$87,600

$15,500

$103,100







CD-SED

$5,610

$3,930

$9,540

$33,700

$43,240







CH REAL-1

$1,160,000

$815,000

$1,975,000

$198,000

$2,173,000







FP/RP-AVG

$194,000

$136,000

$330,000

$34,900

$364,900







OFFCH-AVG

$84,000

$58,800

$142,800

$15,100

$157,900







VBS-AVG

$108,000

$75,300

$183,300

$32,300

$215,600

NM04-2

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$87,500

$61,200

$148,700

$26,200

$174,900







CD-AVG

$18,500

$13,000

$31,500

$5,560

$37,060







CD-SED

$1,870

$1,310

$3,180

$11,200

$14,380







CH REAL-1

$404,000

$282,000

$686,000

$68,600

$754,600

Page 15 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







FP/RP-AVG

$192,000

$135,000

$327,000

$34,600

$361,600







VBS-AVG

$37,300

$26,100

$63,400

$11,200

$74,600

NM04-3

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$677,000

$474,000

$1,151,000

$203,000

$1,354,000







CD-AVG

$138,000

$96,600

$234,600

$41,400

$276,000







CD-SED

$13,100

$9,160

$22,260

$78,500

$100,760







CH REAL-1

$3,120,000

$2,190,000

$5,310,000

$531,000

$5,841,000







FP/RP-AVG

$893,000

$625,000

$1,518,000

$161,000

$1,679,000







VBS-AVG

$289,000

$202,000

$491,000

$86,600

$577,600

OSB032

BLM Polygon

Floodplain waste rock

C01

$17,100

$12,000

$29,100

$0

$29,100







C03

$189,000

$132,000

$321,000

$22,700

$343,700

OSB033

BLM Polygon

Upland waste rock (erosion potential)

C01

$13,700

$9,590

$23,290

$0

$23,290







C03

$153,000

$107,000

$260,000

$18,400

$278,400

OSB038

BLM Polygon

Floodplain waste rock

C01

$26,500

$18,600

$45,100

$0

$45,100







C03

$288,000

$202,000

$490,000

$34,600

$524,600

OSB039

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$4,100

$4,390

$8,490

$3,110

$11,600





Buildings & structures

HH-3

$136,000

$95,100

$231,100

$6,790

$237,890





Floodplain sediments

C01b

$149,000

$104,000

$253,000

$0

$253,000







C08a

$195,000

$136,000

$331,000

$27,300

$358,300







HAUL-2

$60,400

$42,300

$102,700

$0

$102,700





Upland tailings

C01

$47,100

$33,000

$80,100

$0

$80,100







C07

$162,000

$113,000

$275,000

$35,600

$310,600

OSB052

BLM Polygon

Upland tailings - inactive facilities

C09

$1,370,000

$956,000

$2,326,000

$273,000

$2,599,000

OSB059

BLM Polygon

Floodplain sediments

C01b

$446,000

$312,000

$758,000

$0

$758,000







C08a

$584,000

$409,000

$993,000

$81,800

$1,074,800







HAUL-2

$181,000

$127,000

$308,000

$0

$308,000

OSB060

BLM Polygon

Floodplain sediments

C01b

$10,800

$7,560

$18,360

$0

$18,360







C07

$11,800

$8,230

$20,030

$2,590

$22,620

OSB061

BLM Polygon

Upland tailings

C01

$30,000

$21,000

$51,000

$0

$51,000







C07

$103,000

$72,000

$175,000

$22,600

$197,600

OSB082

BLM Polygon

Floodplain waste rock

C01

$11,100

$7,790

$18,890

$0

$18,890







C03

$122,000

$85,100

$207,100

$14,600

$221,700

OSB115

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$76,500

$53,600

$130,100

$9,180

$139,280

WAL006

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$56,300

$39,400

$95,700

$6,750

$102,450

WAL033

BLM Polygon

Floodplain sediments

C01b

$445,000

$312,000

$757,000

$0

$757,000







C07

$485,000

$339,000

$824,000

$107,000

$931,000

PineCrkSegOl HHWPPC01-1

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

HHWPPC01-2

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

MAS006

BLM Polygon

Floodplain tailings - inactive Facilities

C09

$1,010,000

$706,000

$1,716,000

$202,000

$1,918,000







C11j

$3,180,000

$2,230,000

$5,410,000

$63,600

$5,473,600

Page 16 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Segment ID

Trait Description

2009 Total
Direct Capital

2009 Indirect

2009 Total
Direct and
Indirect Capital

O&M Cost (30- Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

MAS007

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$348,000

$243,000

$591,000

$595,000

$1,186,000





Upland waste rock

C01

$205,000

$144,000

$349,000

$0

$349,000







C03

$410,000

$287,000

$697,000

$49,100

$746,100

MAS008

BLM Polygon

Upland waste rock (erosion potential)

C01

$107,000

$74,900

$181,900

$0

$181,900







C07

$368,000

$257,000

$625,000

$80,900

$705,900

MAS009

BLM Polygon

Upland waste rock (erosion potential)

C01

$31,800

$22,300

$54,100

$0

$54,100







C07

$109,000

$76,600

$185,600

$24,100

$209,700

MAS011

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$136,000

$95,300

$231,300

$527,000

$758,300

MAS012

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000





Upland waste rock (erosion potential)

C01

$2,140

$1,500

$3,640

$0

$3,640







C07

$7,350

$5,150

$12,500

$1,620

$14,120

MAS013

BLM Polygon

Upland waste rock (erosion potential)

C01

$20,100

$14,100

$34,200

$0

$34,200







C07

$69,100

$48,400

$117,500

$15,200

$132,700

MAS014

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000





Seep

WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000





Upland tailings

C01

$342

$240

$582

$0

$582







C08a

$1,420

$991

$2,411

$198

$2,609







HAUL-2

$439

$307

$746

$0

$746





Upland waste rock

C01

$131,000

$92,000

$223,000

$0

$223,000







C03

$288,000

$202,000

$490,000

$34,600

$524,600

MAS015

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$152,000

$106,000

$258,000

$528,000

$786,000





Upland waste rock (erosion potential)

C01

$4,280

$3,000

$7,280

$0

$7,280







C07

$14,700

$10,300

$25,000

$3,230

$28,230

MAS016

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$135,000

$94,400

$229,400

$527,000

$756,400





Upland waste rock (erosion potential)

C01

$99,600

$69,700

$169,300

$0

$169,300







C07

$342,000

$240,000

$582,000

$75,300

$657,300

MAS017

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000





Upland waste rock (erosion potential)

C01

$268,000

$188,000

$456,000

$0

$456,000







C07

$921,000

$645,000

$1,566,000

$203,000

$1,769,000

MAS018

BLM Polygon

Upland waste rock (erosion potential)

C01

$11,600

$8,090

$19,690

$0

$19,690







C07

$39,700

$27,800

$67,500

$8,730

$76,230

MAS019

BLM Polygon

Floodplain waste rock

C01

$4,280

$3,000

$7,280

$0

$7,280







C07

$14,700

$10,300

$25,000

$3,230

$28,230

MAS020

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$391,000

$274,000

$665,000

$550,000

$1,215,000

Page 17 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Segment ID

Trait Description

2009 Total
Direct Capital

2009 Indirect

2009 Total
Direct and
Indirect Capital

O&M Cost (30- Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

MAS021

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$389,000

$272,000

$661,000

$1,140,000

$1,801,000





Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C04

$160,000

$112,000

$272,000

$36,800

$308,800

MAS022

BLM Polygon

Floodplain waste rock

C01

$205,000

$144,000

$349,000

$0

$349,000







C07

$706,000

$494,000

$1,200,000

$155,000

$1,355,000

MAS023

BLM Polygon

Upland waste rock (erosion potential)

C01

$4,280

$3,000

$7,280

$0

$7,280







C07

$14,700

$10,300

$25,000

$3,230

$28,230

MAS025

BLM Polygon

Floodplain waste rock (intermixed tailings)

C01

$150,000

$105,000

$255,000

$0

$255,000

MAS027

BLM Polygon

Floodplain waste rock

C01

$30,000

$21,000

$51,000

$0

$51,000







C03

$545,000

$381,000

$926,000

$65,300

$991,300

MAS028

BLM Polygon

Upland waste rock (erosion potential)

C01

$46,200

$32,400

$78,600

$0

$78,600







C07

$159,000

$111,000

$270,000

$34,900

$304,900

MAS029

BLM Polygon

Upland waste rock (intermixed tailings)

C01

$3,000

$2,100

$5,100

$0

$5,100







C07

$10,300

$7,200

$17,500

$2,260

$19,760

MAS030

BLM Polygon

Upland waste rock (erosion potential)

C01

$5,750

$4,030

$9,780

$0

$9,780







C03

$63,000

$44,100

$107,100

$7,560

$114,660

MAS031

BLM Polygon

Upland waste rock (erosion potential)

C01

$18,500

$12,900

$31,400

$0

$31,400







C07

$63,500

$44,500

$108,000

$14,000

$122,000

MAS032

BLM Polygon

Upland waste rock (erosion potential)

C01

$342

$240

$582

$0

$582







C07

$1,180

$823

$2,003

$259

$2,262

MAS033

BLM Polygon

Upland waste rock (erosion potential)

C01

$20,500

$14,400

$34,900

$0

$34,900







C07

$70,600

$49,400

$120,000

$15,500

$135,500

MAS035

BLM Polygon

Upland waste rock (erosion potential)

C01

$34,200

$24,000

$58,200

$0

$58,200







C07

$118,000

$82,300

$200,300

$25,900

$226,200

MAS036

BLM Polygon

Floodplain tailings

C01

$11,600

$8,090

$19,690

$0

$19,690







C07

$39,700

$27,800

$67,500

$8,730

$76,230

MAS040

BLM Polygon

Floodplain sediments

C01b

$18,600

$13,000

$31,600

$0

$31,600







C08a

$24,400

$17,100

$41,500

$3,420

$44,920







HAUL-2

$7,580

$5,300

$12,880

$0

$12,880

MAS041

BLM Polygon

Floodplain sediments

C01b

$31,600

$22,100

$53,700

$0

$53,700







C08a

$41,400

$29,000

$70,400

$5,800

$76,200







HAUL-2

$12,800

$8,990

$21,790

$0

$21,790

MAS042

BLM Polygon

Floodplain sediments

C01b

$14,600

$10,200

$24,800

$0

$24,800







C08a

$19,100

$13,400

$32,500

$2,680

$35,180







HAUL-2

$5,930

$4,150

$10,080

$0

$10,080

MAS043

BLM Polygon

Floodplain sediments

C01b

$40,500

$28,400

$68,900

$0

$68,900







C08a

$53,100

$37,200

$90,300

$7,430

$97,730







HAUL-2

$16,500

$11,500

$28,000

$0

$28,000

MAS045

BLM Polygon

Floodplain sediments

C01b

$40,500

$28,400

$68,900

$0

$68,900







C08a

$53,100

$37,200

$90,300

$7,430

$97,730







HAUL-2

$16,500

$11,500

$28,000

$0

$28,000

Page 18 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Segment ID

Trait Description

2009 Total
Direct Capital

2009 Indirect

2009 Total
Direct and
Indirect Capital

O&M Cost (30- Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

MAS046

BLM Polygon

Floodplain sediments

C01b

$322,000

$225,000

$547,000

$0

$547,000







C08a

$422,000

$296,000

$718,000

$59,100

$777,100







HAUL-2

$131,000

$91,700

$222,700

$0

$222,700

MAS048

BLM Polygon

Floodplain tailings

C01

$21,200

$14,800

$36,000

$0

$36,000







C07

$72,800

$50,900

$123,700

$16,000

$139,700





Upland tailings

C01

$69,800

$48,900

$118,700

$0

$118,700







C07

$240,000

$168,000

$408,000

$52,800

$460,800

MAS049

BLM Polygon

Floodplain tailings

C01

$154,000

$108,000

$262,000

$0

$262,000







C07

$529,000

$370,000

$899,000

$116,000

$1,015,000

MAS050

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$374,000

$261,000

$635,000

$1,150,000

$1,785,000





Floodplain waste rock (intermixed tailings)

C01

$91,600

$64,100

$155,700

$0

$155,700







C03

$338,000

$236,000

$574,000

$40,500

$614,500

MAS052

BLM Polygon

Upland waste rock (erosion potential)

C01

$4,520

$3,160

$7,680

$0

$7,680







C03

$49,500

$34,700

$84,200

$5,940

$90,140

MAS053

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

MAS054

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$184,000

$129,000

$313,000

$538,000

$851,000





Floodplain waste rock

C01

$45,200

$31,600

$76,800

$0

$76,800







C07

$155,000

$109,000

$264,000

$34,200

$298,200

MAS055

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

MAS057

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

MAS065

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

MAS068

BLM Polygon

Upland waste rock (erosion potential)

C01

$171

$120

$291

$0

$291







C03

$36,000

$25,200

$61,200

$4,320

$65,520

MAS072

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

MAS078

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$354,000

$247,000

$601,000

$578,000

$1,179,000

MAS079

BLM Polygon

Floodplain waste rock

C01

$160,000

$112,000

$272,000

$0

$272,000







C03

$428,000

$299,000

$727,000

$51,300

$778,300

MAS081

BLM Polygon

Floodplain waste rock

C02a

$177,000

$124,000

$301,000

$23,000

$324,000

MAS083

BLM Polygon

Upland tailings

C01

$34,900

$24,400

$59,300

$0

$59,300







C07

$120,000

$83,900

$203,900

$26,400

$230,300





Upland waste rock

C01

$124,000

$86,900

$210,900

$0

$210,900







C03

$632,000

$443,000

$1,075,000

$75,900

$1,150,900

MAS084

BLM Polygon

Floodplain tailings

C01

$128,000

$89,900

$217,900

$0

$217,900







C07

$441,000

$309,000

$750,000

$97,000

$847,000

Page 19 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Segment ID

Trait Description

2009 Total
Direct Capital

2009 Indirect

2009 Total
Direct and
Indirect Capital

O&M Cost (30- Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

TWI002

BLM Polygon

Floodplain waste rock

C01

$24,700

$17,300

$42,000

$0

$42,000







C07

$84,700

$59,300

$144,000

$18,600

$162,600

TWI006

BLM Polygon

Upland waste rock (erosion potential)

C01

$20,500

$14,400

$34,900

$0

$34,900







C07

$70,600

$49,400

$120,000

$15,500

$135,500

TWI008

BLM Polygon

Floodplain waste rock

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

TWI009

BLM Polygon

Floodplain waste rock

C01

$27,700

$19,400

$47,100

$0

$47,100







C07

$95,300

$66,700

$162,000

$21,000

$183,000

TWI011

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

TWI012

BLM Polygon

Floodplain waste rock

C01

$16,400

$11,500

$27,900

$0

$27,900







C07

$56,400

$39,500

$95,900

$12,400

$108,300

TWI013

BLM Polygon

Upland waste rock

C01

$32,900

$23,000

$55,900

$0

$55,900







C07

$113,000

$79,000

$192,000

$24,800

$216,800

TWI014

BLM Polygon

Floodplain waste rock

C01

$25,700

$18,000

$43,700

$0

$43,700







C07

$88,200

$61,700

$149,900

$19,400

$169,300

TWI018

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

TWI020

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

TWI027

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

TWI029

BLM Polygon

Upland waste rock

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

TWI 030

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

KLW075

BLM Polygon

Floodplain waste rock

C01

$72,900

$51,100

$124,000

$0

$124,000







C07

$250,000

$175,000

$425,000

$55,100

$480,100

KLW077

BLM Polygon

Floodplain waste rock

C01

$47,300

$33,100

$80,400

$0

$80,400







C07

$162,000

$114,000

$276,000

$35,700

$311,700

KLW079

BLM Polygon

Floodplain waste rock

C01

$41,100

$28,800

$69,900

$0

$69,900







C07

$141,000

$98,800

$239,800

$31,000

$270,800

KLW080

BLM Polygon

Upland waste rock

C01

$30,800

$21,600

$52,400

$0

$52,400







C03

$67,500

$47,300

$114,800

$8,100

$122,900

KLW082

BLM Polygon

Floodplain waste rock

C01

$34,900

$24,400

$59,300

$0

$59,300







C07

$120,000

$84,000

$204,000

$26,400

$230,400

KLW083

BLM Polygon

Floodplain waste rock

C01

$59,600

$41,700

$101,300

$0

$101,300







C07

$205,000

$143,000

$348,000

$45,000

$393,000

KLW085

BLM Polygon

Floodplain waste rock

C01

$61,600

$43,100

$104,700

$0

$104,700







C07

$212,000

$148,000

$360,000

$46,600

$406,600

MAS003

BLM Polygon

Upland waste rock (intermixed tailings)

C04

$980,000

$686,000

$1,666,000

$226,000

$1,892,000

PC03-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$248,000

$174,000

$422,000

$74,400

$496,400

PineCrkSeg02

PineCrkSeg03

Page 20 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







CD-AVG

$76,200

$53,400

$129,600

$22,900

$152,500







CD-SED

$7,480

$5,240

$12,720

$44,900

$57,620







FP/RP-AVG

$312,000

$218,000

$530,000

$56,100

$586,100







OFFCH-AVG

$790,000

$553,000

$1,343,000

$142,000

$1,485,000







VBS-AVG

$106,000

$74,000

$180,000

$31,700

$211,700

PC03-2

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$201,000

$141,000

$342,000

$60,400

$402,400







CD-AVG

$41,200

$28,800

$70,000

$12,400

$82,400







CD-SED

$3,740

$2,620

$6,360

$22,400

$28,760







FP/RP-AVG

$243,000

$170,000

$413,000

$43,700

$456,700







OFFCH-AVG

$763,000

$534,000

$1,297,000

$137,000

$1,434,000







VBS-AVG

$85,700

$60,000

$145,700

$25,700

$171,400

PC03-3

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$122,000

$85,400

$207,400

$36,600

$244,000







CD-AVG

$16,500

$11,500

$28,000

$4,940

$32,940







CD-SED

$3,740

$2,620

$6,360

$22,400

$28,760







FP/RP-AVG

$381,000

$267,000

$648,000

$68,600

$716,600







VBS-AVG

$52,000

$36,400

$88,400

$15,600

$104,000

UpperSFCDRSeg PIPEUG

General Feature

Source General Information

PIPE-1

$245,000

$172,000

$417,000

$19,600

$436,600







PIPE-2

$12,900

$9,050

$21,950

$1,030

$22,980







PIPE-3

$6,420,000

$4,490,000

$10,910,000

$513,000

$11,423,000







PIPE-4

$5,080,000

$3,560,000

$8,640,000

$406,000

$9,046,000

UpperSFCDRSegOl HHWPUG01-1

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

HHWPUG01-2

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

HHWPUG01-3

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

HHWPUG01-4

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

HHWPUG01-5

General Feature

Upland waste rock

HH-2

$58,400

$40,900

$99,300

$7,600

$106,900

LOK001

BLM Polygon

Upland waste rock (erosion potential)

C02a

$109,000

$76,100

$185,100

$14,100

$199,200

LOK002

BLM Polygon

Upland waste rock (erosion potential)

C02a

$107,000

$74,900

$181,900

$13,900

$195,800

LOK004

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$521,000

$365,000

$886,000

$1,210,000

$2,096,000





Floodplain waste rock

C01

$262,000

$183,000

$445,000

$0

$445,000







C07

$900,000

$630,000

$1,530,000

$198,000

$1,728,000





Upland waste rock (erosion potential)

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

LOK006

BLM Polygon

Floodplain waste rock

C01

$5,340

$3,740

$9,080

$0

$9,080







C03

$58,500

$41,000

$99,500

$7,020

$106,520

LOK007

BLM Polygon

Upland waste rock (erosion potential)

C02a

$22,800

$15,900

$38,700

$2,960

$41,660

LOK008

BLM Polygon

Floodplain waste rock

C01

$7,810

$5,460

$13,270

$0

$13,270







C03

$85,500

$59,900

$145,400

$10,300

$155,700

LOK009

BLM Polygon

Floodplain waste rock

C01

$94,500

$66,200

$160,700

$0

$160,700







C07

$325,000

$227,000

$552,000

$71,400

$623,400

LOK010

BLM Polygon

Floodplain waste rock

C01

$2,880

$2,010

$4,890

$0

$4,890







C03

$31,500

$22,100

$53,600

$3,780

$57,380

LOK011

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







Page 21 of 28










-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







WT01

$3,620,000

$3,870,000

$7,490,000

$2,630,000

$10,120,000





Floodplain waste rock

C01

$235,000

$165,000

$400,000

$0

$400,000







C07

$809,000

$566,000

$1,375,000

$178,000

$1,553,000

LOK017

BLM Polygon

Floodplain waste rock

C01

$26,500

$18,600

$45,100

$0

$45,100







C03

$817,000

$572,000

$1,389,000

$98,000

$1,487,000

LOK024

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000

LOK048

BLM Polygon

Floodplain waste rock

C02a

$22,800

$15,900

$38,700

$2,960

$41,660

LOK050

BLM Polygon

Upland tailings - inactive facilities

C01

$55,600

$38,900

$94,500

$0

$94,500







C07

$191,000

$134,000

$325,000

$42,000

$367,000

LOK051

BLM Polygon

Floodplain artificial fill

C02a

$161,000

$113,000

$274,000

$20,900

$294,900

LOK053

BLM Polygon

Upland waste rock (erosion potential)

C02a

$26,100

$18,300

$44,400

$3,400

$47,800

MUL001

BLM Polygon

Floodplain waste rock

C01

$323,000

$226,000

$549,000

$0

$549,000







C07

$1,110,000

$775,000

$1,885,000

$244,000

$2,129,000

MUL002

BLM Polygon

Upland tailings

C01

$98,400

$68,900

$167,300

$0

$167,300







C07

$338,000

$237,000

$575,000

$74,400

$649,400

MUL004

BLM Polygon

Floodplain waste rock

C01

$16,800

$11,800

$28,600

$0

$28,600







C03

$185,000

$129,000

$314,000

$22,100

$336,100

MUL006

BLM Polygon

Floodplain waste rock

C01

$15,000

$10,500

$25,500

$0

$25,500







C03

$164,000

$115,000

$279,000

$19,700

$298,700

MUL007

BLM Polygon

Upland waste rock (erosion potential)

C02a

$80,100

$56,100

$136,200

$10,400

$146,600

MUL008

BLM Polygon

Floodplain waste rock

C01

$28,200

$19,800

$48,000

$0

$48,000







C03

$302,000

$211,000

$513,000

$36,200

$549,200

MUL009

BLM Polygon

Upland waste rock (erosion potential)

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

MUL012

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$210,000

$224,000

$434,000

$197,000

$631,000





Floodplain waste rock

C01

$462,000

$324,000

$786,000

$0

$786,000







C03

$1,520,000

$1,060,000

$2,580,000

$182,000

$2,762,000

MUL013

BLM Polygon

Upland waste rock (erosion potential)

C02a

$44,700

$31,300

$76,000

$5,810

$81,810

MUL014

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$1,100,000

$1,170,000

$2,270,000

$832,000

$3,102,000





Upland waste rock (erosion potential)

C01

$6,780

$4,750

$11,530

$0

$11,530







C03

$74,300

$52,000

$126,300

$8,910

$135,210

MUL015

BLM Polygon

Upland waste rock (erosion potential)

C02a

$787,000

$551,000

$1,338,000

$102,000

$1,440,000

MUL018

BLM Polygon

Floodplain waste rock

C01

$61,600

$43,100

$104,700

$0

$104,700







C07

$212,000

$148,000

$360,000

$46,600

$406,600

MUL019

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$558,000

$597,000

$1,155,000

$540,000

$1,695,000





Buildings & structures

HH-3

$136,000

$95,100

$231,100

$6,790

$237,890





Floodplain tailings

C01

$364,000

$255,000

$619,000

$0

$619,000







C07

$1,250,000

$875,000

$2,125,000

$275,000

$2,400,000





Floodplain waste rock

C01

$288,000

$202,000

$490,000

$0

$490,000

Page 22 of 28

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







C03

$3,970,000

$2,780,000

$6,750,000

$477,000

$7,227,000

MUL020

BLM Polygon

Floodplain sediments (underlying tailings pond)

C11j

$5,090,000

$3,560,000

$8,650,000

$102,000

$8,752,000





Floodplain tailings - active facilities

C09

$2,710,000

$1,900,000

$4,610,000

$543,000

$5,153,000





Groundwater

WT01

$30,200

$32,300

$62,500

$9,150

$71,650

MUL021

BLM Polygon

Floodplain waste rock

C01

$24,900

$17,400

$42,300

$0

$42,300







C03

$272,000

$191,000

$463,000

$32,700

$495,700

MUL022

BLM Polygon

Upland waste rock (erosion potential)

C02a

$29,500

$20,700

$50,200

$3,840

$54,040

MUL023

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000





Floodplain waste rock

C01

$134,000

$93,500

$227,500

$0

$227,500







C07

$459,000

$321,000

$780,000

$101,000

$881,000

MUL027

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$221,000

$155,000

$376,000

$547,000

$923,000





Upland waste rock

C02b

$165,000

$116,000

$281,000

$21,500

$302,500

MUL028

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$388,000

$272,000

$660,000

$600,000

$1,260,000





Floodplain waste rock

C01

$87,300

$61,100

$148,400

$0

$148,400







C03

$956,000

$669,000

$1,625,000

$115,000

$1,740,000

MUL029

BLM Polygon

Floodplain waste rock

C01

$87,300

$61,100

$148,400

$0

$148,400







C07

$300,000

$210,000

$510,000

$66,000

$576,000

MUL030

BLM Polygon

Floodplain waste rock

C01

$7,400

$5,180

$12,580

$0

$12,580







C03

$81,000

$56,700

$137,700

$9,720

$147,420

MUL031

BLM Polygon

Upland waste rock (erosion potential)

C02a

$28,700

$20,100

$48,800

$3,730

$52,530

MUL033

BLM Polygon

Floodplain waste rock

C01

$67,800

$47,500

$115,300

$0

$115,300







C07

$233,000

$163,000

$396,000

$51,200

$447,200

MUL037

BLM Polygon

Floodplain sediments

C01b

$583,000

$408,000

$991,000

$0

$991,000







C08a

$765,000

$535,000

$1,300,000

$107,000

$1,407,000







HAUL-2

$237,000

$166,000

$403,000

$0

$403,000





Floodplain sediments (underlying tailings pond)

C11j

$5,410,000

$3,780,000

$9,190,000

$108,000

$9,298,000





Floodplain tailings - active facilities

C09

$2,470,000

$1,730,000

$4,200,000

$494,000

$4,694,000





Groundwater

WT01

$30,200

$32,300

$62,500

$9,150

$71,650

MUL038

BLM Polygon

Floodplain tailings

C01

$55,600

$38,900

$94,500

$0

$94,500







C07

$191,000

$134,000

$325,000

$42,000

$367,000





Floodplain waste rock

C01

$56,900

$39,800

$96,700

$0

$96,700







C03

$623,000

$436,000

$1,059,000

$74,800

$1,133,800

MUL042

BLM Polygon

Floodplain waste rock

C01

$59,600

$41,700

$101,300

$0

$101,300







C07

$205,000

$143,000

$348,000

$45,000

$393,000

MUL043

BLM Polygon

Floodplain waste rock

C01

$75,000

$52,500

$127,500

$0

$127,500







C07

$258,000

$180,000

$438,000

$56,700

$494,700

MUL045

BLM Polygon

Floodplain waste rock

C01

$118,000

$82,700

$200,700

$0

$200,700







C07

$406,000

$284,000

$690,000

$89,300

$779,300

MUL047

BLM Polygon

Floodplain waste rock

C01

$4,730

$3,310

$8,040

$0

$8,040

Page 23 of 28

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







C03

$51,800

$36,200

$88,000

$6,210

$94,210

MUL048

BLM Polygon

Floodplain waste rock

C01

$91,400

$64,000

$155,400

$0

$155,400







C07

$314,000

$220,000

$534,000

$69,100

$603,100

MUL049

BLM Polygon

Upland waste rock (erosion potential)

C02a

$25,300

$17,700

$43,000

$3,290

$46,290

MUL051

BLM Polygon

Floodplain waste rock

C01

$24,700

$17,300

$42,000

$0

$42,000







C03

$270,000

$189,000

$459,000

$32,400

$491,400

MUL052

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$390,000

$273,000

$663,000

$1,160,000

$1,823,000





Floodplain waste rock

C01

$12,800

$8,990

$21,790

$0

$21,790







C03

$299,000

$209,000

$508,000

$35,900

$543,900

MUL053

BLM Polygon

Upland waste rock (erosion potential)

C02a

$266,000

$186,000

$452,000

$34,600

$486,600

MUL054

BLM Polygon

Upland waste rock (erosion potential)

C02a

$79,200

$55,500

$134,700

$10,300

$145,000

MUL056

BLM Polygon

Upland waste rock (erosion potential)

C02a

$29,500

$20,700

$50,200

$3,840

$54,040

MUL057

BLM Polygon

Upland waste rock (erosion potential)

C02a

$66,600

$46,600

$113,200

$8,660

$121,860

MUL058

BLM Polygon

Floodplain sediments

C01b

$1,890,000

$1,320,000

$3,210,000

$0

$3,210,000







C08a

$2,480,000

$1,730,000

$4,210,000

$347,000

$4,557,000







HAUL-2

$769,000

$538,000

$1,307,000

$0

$1,307,000





Floodplain sediments (underlying tailings pond)

C11j

$9,700,000

$6,790,000

$16,490,000

$194,000

$16,684,000





Floodplain tailings - active facilities

C09

$8,540,000

$5,980,000

$14,520,000

$1,710,000

$16,230,000





Groundwater

WT01

$30,200

$32,300

$62,500

$9,150

$71,650

MUL059

BLM Polygon

Floodplain waste rock

C01

$96,600

$67,600

$164,200

$0

$164,200







C07

$332,000

$232,000

$564,000

$73,000

$637,000

MUL060

BLM Polygon

Floodplain waste rock

C01

$4,310

$3,020

$7,330

$0

$7,330







C03

$47,300

$33,100

$80,400

$5,670

$86,070

MUL063

BLM Polygon

Floodplain waste rock

C01

$4,310

$3,020

$7,330

$0

$7,330







C03

$47,300

$33,100

$80,400

$5,670

$86,070

MUL065

BLM Polygon

Floodplain waste rock

C01

$6,370

$4,460

$10,830

$0

$10,830







C03

$69,800

$48,800

$118,600

$8,370

$126,970

MUL071

BLM Polygon

Floodplain waste rock

C01

$2,140

$1,500

$3,640

$0

$3,640







C03

$1,830,000

$1,280,000

$3,110,000

$220,000

$3,330,000

MUL073

BLM Polygon

Upland waste rock

C02a

$174,000

$122,000

$296,000

$22,600

$318,600

MUL081

BLM Polygon

Floodplain waste rock

C01

$6,850

$4,790

$11,640

$0

$11,640







C03

$171,000

$120,000

$291,000

$20,500

$311,500

MUL083

BLM Polygon

Floodplain waste rock

C01

$13,100

$9,200

$22,300

$0

$22,300







C03

$144,000

$101,000

$245,000

$17,300

$262,300

MUL103

BLM Polygon

Floodplain waste rock

C01

$5,390

$3,770

$9,160

$0

$9,160







C03

$212,000

$148,000

$360,000

$25,400

$385,400

MUL119

BLM Polygon

Upland waste rock (erosion potential)

C02a

$23,600

$16,500

$40,100

$3,070

$43,170

MUL120

BLM Polygon

Floodplain waste rock

C01

$479

$336

$815

$0

$815







C03

$76,500

$53,600

$130,100

$9,180

$139,280

MUL129

BLM Polygon

Floodplain waste rock

C01

$22,800

$16,000

$38,800

$0

$38,800







C03

$250,000

$175,000

$425,000

$30,000

$455,000

Page 24 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Segment ID

Trait Description

2009 Total
Direct Capital

2009 Indirect

2009 Total
Direct and
Indirect Capital

O&M Cost (30- Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

MUL131

BLM Polygon

Upland tailings

C01

$28,200

$19,800

$48,000

$0

$48,000







C07

$97,000

$67,900

$164,900

$21,300

$186,200

MUL132

BLM Polygon

Upland tailings

C01

$7,700

$5,390

$13,090

$0

$13,090







C07

$26,500

$18,500

$45,000

$5,820

$50,820

MUL135

BLM Polygon

Upland waste rock (erosion potential)

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

MUL136

BLM Polygon

Upland waste rock (erosion potential)

C02a

$10,100

$7,080

$17,180

$1,320

$18,500

MUL139

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

MUL141

BLM Polygon

Floodplain sediments

C01b

$65,100

$45,600

$110,700

$0

$110,700







C07

$70,900

$49,600

$120,500

$15,600

$136,100

MUL142

BLM Polygon

Floodplain sediments

C01b

$232,000

$162,000

$394,000

$0

$394,000







C07

$252,000

$176,000

$428,000

$55,500

$483,500

MUL145

BLM Polygon

Floodplain sediments

C01b

$28,400

$19,800

$48,200

$0

$48,200







C07

$30,900

$21,600

$52,500

$6,790

$59,290

MUL146

BLM Polygon

Upland waste rock (erosion potential)

C01

$135,000

$94,200

$229,200

$0

$229,200







C03

$295,000

$206,000

$501,000

$35,400

$536,400

MUL149

BLM Polygon

Floodplain sediments

C01b

$38,100

$26,700

$64,800

$0

$64,800







C07

$41,500

$29,100

$70,600

$9,140

$79,740

MUL150

BLM Polygon

Floodplain sediments

C01b

$102,000

$71,300

$173,300

$0

$173,300







C07

$111,000

$77,700

$188,700

$24,400

$213,100

MUL153

BLM Polygon

Floodplain sediments

C01b

$51,300

$35,900

$87,200

$0

$87,200







C07

$55,900

$39,100

$95,000

$12,300

$107,300

THO020

BLM Polygon

Floodplain waste rock

C01

$5,960

$4,170

$10,130

$0

$10,130







C03

$65,300

$45,700

$111,000

$7,830

$118,830

UG01-4

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$6,220

$4,360

$10,580

$1,870

$12,450







VBS-AVG

$5,360

$3,750

$9,110

$1,610

$10,720

UG01-5

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$133,000

$93,100

$226,100

$39,900

$266,000







CD-AVG

$57,700

$40,400

$98,100

$17,300

$115,400







CD-SED

$5,800

$4,060

$9,860

$34,800

$44,660







FP/RP-AVG

$124,000

$87,100

$211,100

$22,400

$233,500







VBS-AVG

$56,700

$39,700

$96,400

$17,000

$113,400

UG01-6

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$171,000

$120,000

$291,000

$51,200

$342,200







CD-AVG

$56,400

$39,500

$95,900

$16,900

$112,800







CD-SED

$5,610

$3,930

$9,540

$33,700

$43,240







FP/RP-AVG

$906,000

$634,000

$1,540,000

$163,000

$1,703,000







OFFCH-AVG

$97,600

$68,300

$165,900

$17,600

$183,500







VBS-AVG

$135,000

$94,600

$229,600

$40,600

$270,200

UG01-7

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$98,200

$68,700

$166,900

$29,500

$196,400







CD-AVG

$48,400

$33,900

$82,300

$14,500

$96,800







CD-SED

$4,860

$3,400

$8,260

$29,200

$37,460







FP/RP-AVG

$281,000

$197,000

$478,000

$50,600

$528,600







VBS-AVG

$77,700

$54,400

$132,100

$23,300

$155,400

Page 25 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Segment ID













2009 Total













2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

UG01-8

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$39,800

$27,800

$67,600

$11,900

$79,500







CD-AVG

$15,000

$10,500

$25,500

$4,510

$30,010







CD-SED

$1,500

$1,050

$2,550

$8,980

$11,530







VBS-AVG

$14,800

$10,400

$25,200

$4,450

$29,650

UG01-9

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$175,000

$123,000

$298,000

$52,500

$350,500







CD-AVG

$73,500

$51,500

$125,000

$22,100

$147,100







CD-SED

$7,480

$5,240

$12,720

$44,900

$57,620







FP/RP-AVG

$206,000

$144,000

$350,000

$37,000

$387,000







VBS-AVG

$139,000

$97,000

$236,000

$41,600

$277,600

UG01-10

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$150,000

$105,000

$255,000

$45,100

$300,100







CD-AVG

$57,100

$39,900

$97,000

$17,100

$114,100







CD-SED

$5,800

$4,060

$9,860

$34,800

$44,660







FP/RP-AVG

$152,000

$106,000

$258,000

$27,300

$285,300







VBS-AVG

$80,000

$56,000

$136,000

$24,000

$160,000

UG01-11

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$42,700

$29,900

$72,600

$12,800

$85,400







CD-AVG

$17,300

$12,100

$29,400

$5,190

$34,590







CD-SED

$1,680

$1,180

$2,860

$10,100

$12,960







FP/RP-AVG

$143,000

$100,000

$243,000

$25,800

$268,800







VBS-AVG

$33,800

$23,700

$57,500

$10,100

$67,600

UG01-12

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$541,000

$379,000

$920,000

$162,000

$1,082,000







CD-AVG

$165,000

$115,000

$280,000

$49,400

$329,400







CD-SED

$16,800

$11,800

$28,600

$101,000

$129,600







FP/RP-AVG

$702,000

$491,000

$1,193,000

$126,000

$1,319,000







VBS-AVG

$231,000

$161,000

$392,000

$69,200

$461,200

UG01-13

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$297,000

$208,000

$505,000

$89,100

$594,100







CD-AVG

$90,200

$63,200

$153,400

$27,100

$180,500







CD-SED

$9,160

$6,410

$15,570

$55,000

$70,570







FP/RP-AVG

$128,000

$89,900

$217,900

$23,100

$241,000







VBS-AVG

$127,000

$88,600

$215,600

$38,000

$253,600

UG01-14

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$57,600

$40,300

$97,900

$17,300

$115,200







CD-AVG

$17,500

$12,300

$29,800

$5,250

$35,050







CD-SED

$1,680

$1,180

$2,860

$10,100

$12,960







FP/RP-AVG

$21,900

$15,400

$37,300

$3,950

$41,250







VBS-AVG

$24,500

$17,200

$41,700

$7,360

$49,060

UG01-15

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$207,000

$145,000

$352,000

$62,000

$414,000







CD-AVG

$62,800

$44,000

$106,800

$18,800

$125,600







CD-SED

$6,360

$4,450

$10,810

$38,100

$48,910







FP/RP-AVG

$6,850

$4,800

$11,650

$1,230

$12,880







VBS-AVG

$88,100

$61,700

$149,800

$26,400

$176,200

UG01-16

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$190,000

$133,000

$323,000

$57,000

$380,000







CD-AVG

$55,600

$38,900

$94,500

$16,700

$111,200







CD-SED

$5,610

$3,930

$9,540

$33,700

$43,240

Page 26 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







FP/RP-AVG

$510,000

$357,000

$867,000

$91,800

$958,800







VBS-AVG

$150,000

$105,000

$255,000

$45,100

$300,100

UG01-17

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$451,000

$316,000

$767,000

$135,000

$902,000







CD-AVG

$137,000

$96,000

$233,000

$41,200

$274,200







CD-SED

$13,800

$9,690

$23,490

$83,000

$106,490







FP/RP-AVG

$657,000

$460,000

$1,117,000

$118,000

$1,235,000







OFFCH-AVG

$744,000

$521,000

$1,265,000

$134,000

$1,399,000







VBS-AVG

$192,000

$135,000

$327,000

$57,700

$384,700

UG01-18

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$364,000

$255,000

$619,000

$109,000

$728,000







CD-AVG

$111,000

$77,400

$188,400

$33,200

$221,600







CD-SED

$11,200

$7,850

$19,050

$67,300

$86,350







VBS-AVG

$155,000

$109,000

$264,000

$46,500

$310,500

UG01-19

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$38,400

$26,900

$65,300

$11,500

$76,800







CD-AVG

$13,400

$9,370

$22,770

$4,020

$26,790







CD-SED

$1,310

$916

$2,226

$7,850

$10,076







FP/RP-AVG

$36,800

$25,800

$62,600

$6,630

$69,230







OFFCH-AVG

$46,300

$32,400

$78,700

$8,340

$87,040







VBS-AVG

$30,400

$21,300

$51,700

$9,130

$60,830

WAL013

BLM Polygon

Floodplain waste rock

C01

$6,980

$4,890

$11,870

$0

$11,870







C03

$76,500

$53,600

$130,100

$9,180

$139,280

WAL038

BLM Polygon

Floodplain sediments

C01b

$3,760,000

$2,630,000

$6,390,000

$0

$6,390,000







C08a

$4,930,000

$3,450,000

$8,380,000

$690,000

$9,070,000







HAUL-2

$1,530,000

$1,070,000

$2,600,000

$0

$2,600,000

WAL076

BLM Polygon

Floodplain waste rock

C01

$175,000

$122,000

$297,000

$0

$297,000







C07

$600,000

$420,000

$1,020,000

$132,000

$1,152,000

WAL077

BLM Polygon

Floodplain sediments

C01b

$567,000

$397,000

$964,000

$0

$964,000







C08a

$743,000

$520,000

$1,263,000

$104,000

$1,367,000







HAUL-2

$231,000

$161,000

$392,000

$0

$392,000

Notes:

This Table does not include Central Treatment Plant (CTP) Sludge Pond Closure costs, these costs will be applied to the Total Alternative Cost.
This Table does not include Roads and Bridges costs, these costs will be applied to the Total Alternative Cost.

O&M = Operations and Maintenance
NPV = Net Present Value

Typical Conceptual Design (TCD) Codes

BSBR-AVG = Bank Stabilization via Revetments - Average Cost

C01 = Excavation (dry)

C01 b = Excavation (60% dry/40% wet)

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)

Page 27 of 28


-------

-------
TABLE D-37

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)

C02a = Regrade/Consolidate/Vegetative Cover: Lower Part of Pile in 100-Year Floodplain
C02b = Regrade/Consolidate/Vegetative Cover: Waste Rock Pile in Stream Valley
C02c = Regrade/Consolidate/Vegetative Cover: Stabilize Using Erosion Protection
C03 = Low-Permeability Cap

C04 = Low-Permeability Cap with Seepage Collection
C05 = Low-Permeability Cap with Erosion Protection
C07 = Waste Consolidation Area Above Flood Level
C08a = Repository, 1 million cy
C09 = Impoundment Closure
C10 = Adit Drainage Collection

C11j = Hydraulic Isolation Using Slurry Wall (with drain, 30 ft deep)

C14b = Stream Lining (20 feet wide)

C14c = Stream Lining (100 feet wide)

C15b = French Drain (15 feet bgs)

CD-AVG = Current Deflector Average Cost
CD-SED = Current Deflector Sediment Traps
CH REAL-1 = Channel Realignment

FP/RP-AVG = Floodplain and Riparian Replanting - Average Cost
HAUL-2 = Haul to Repository
HH-2 = Upland Waste Pile Soil Cover
HH-3 = Millsite Decontamination

OFFCH-AVG = Off-Channel Hydrologic Feature Average Cost
PIPE-1 = Conveyance Pipeline (6-inch)

PIPE-2 = Conveyance Pipeline (12-inch)

PIPE-3 = Conveyance Pipeline (24-inch)

VBS-AVG = Vegetative Bank Stabilization - Average Cost

WT01 = Centralized High-Density Sludge (HDS) Treatment at Central Treatment Plant (CTP)

WT02 = Onsite Semi-Passive Water Treatment Using Lime Addition and Settling Pond(s)

WT03 = Onsite Semi-Passive Water Treatment Using Sulfate-Reducing Bioreactor (SRB) System

NOTE: The above costs are presented rounded to three significant figures
NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of -30 percent to +50 percent (—30/+50%).
NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-magnitude cost opinion shown has
been prepared for guidance in project evaluation from the information available at the time of preparation. The final costs of the project will
depend on actual labor and material costs, actual site conditions, productivity, competitive market conditions, the final project scope, the
final project schedule, and other variable factors. As a result, the final project costs will vary from those presented above. Because of these
factors, funding needs must be carefully reviewed prior to making specific financial decisions or establishing final budgets.

2009 Total

2009 Total	Direct and

Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)

Page 28 of 28


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

POL044

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

POL045

BLM Polygon

Upland waste rock

C02a

$16,000

$11,200

$27,200

$2,080

$29,280

POL046

BLM Polygon

Upland waste rock

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

POL047

BLM Polygon

Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

POL048

BLM Polygon

Upland waste rock

C02a

$14,300

$10,000

$24,300

$1,860

$26,160

POL049

BLM Polygon

Upland waste rock

C02a

$11,000

$7,670

$18,670

$1,420

$20,090

POL050

BLM Polygon

Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

POL051

BLM Polygon

Upland waste rock

C02b

$33,400

$23,400

$56,800

$4,340

$61,140

POL052

BLM Polygon

Floodplain waste rock

C01

$19,700

$13,800

$33,500

$0

$33,500







C08a

$81,400

$57,000

$138,400

$11,400

$149,800







HAUL-2

$25,300

$17,700

$43,000

$0

$43,000

POL024

BLM Polygon

Upland waste rock

C02a

$16,900

$11,800

$28,700

$2,190

$30,890

POL025

BLM Polygon

Upland waste rock

C02a

$22,800

$15,900

$38,700

$2,960

$41,660

POL026

BLM Polygon

Upland waste rock

C02a

$19,400

$13,600

$33,000

$2,520

$35,520

POL027

BLM Polygon

Upland waste rock

C02a

$39,600

$27,700

$67,300

$5,150

$72,450

POL028

BLM Polygon

Upland waste rock

C02a

$11,000

$7,670

$18,670

$1,420

$20,090

POL036

BLM Polygon

Upland waste rock

C02a

$43,000

$30,100

$73,100

$5,590

$78,690

POL037

BLM Polygon

Upland waste rock

C02a

$23,600

$16,500

$40,100

$3,070

$43,170

POL038

BLM Polygon

Upland waste rock

C02a

$14,300

$10,000

$24,300

$1,860

$26,160

POL039

BLM Polygon

Upland waste rock

C02a

$17,700

$12,400

$30,100

$2,300

$32,400

POL040

BLM Polygon

Upland waste rock

C02b

$78,500

$54,900

$133,400

$10,200

$143,600

POL041

BLM Polygon

Upland waste rock

C02a

$31,200

$21,800

$53,000

$4,050

$57,050

POL042

BLM Polygon

Upland waste rock

C02a

$28,700

$20,100

$48,800

$3,730

$52,530

POL043

BLM Polygon

Upland waste rock

C02a

$29,500

$20,700

$50,200

$3,840

$54,040

POL053

BLM Polygon

Upland waste rock

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

POL054

BLM Polygon

Upland waste rock

C02a

$25,300

$17,700

$43,000

$3,290

$46,290

POL056

BLM Polygon

Upland waste rock

C02a

$35,400

$24,800

$60,200

$4,600

$64,800

POL062

BLM Polygon

Upland waste rock

C02a

$27,000

$18,900

$45,900

$3,510

$49,410

POL063

BLM Polygon

Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

POL001

BLM Polygon

Floodplain waste rock

C01

$34,900

$24,400

$59,300

$0

$59,300







C08a

$144,000

$101,000

$245,000

$20,200

$265,200







HAUL-2

$44,800

$31,400

$76,200

$0

$76,200

POL002

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$223,000

$156,000

$379,000

$547,000

$926,000





Floodplain waste rock

C01

$7,280

$5,090

$12,370

$0

$12,370







C08a

$30,100

$21,100

$51,200

$4,210

$55,410







HAUL-2

$9,330

$6,530

$15,860

$0

$15,860

POL004

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$285,000

$199,000

$484,000

$1,020,000

$1,504,000





Upland waste rock

C02b

$35,100

$24,500

$59,600

$4,560

$64,160

BigCrkSegOl

BigCrkSeg02

BigCrkSeg03

Page 1 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID

BigCrkSeg04









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

POL067

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$521,000

$365,000

$886,000

$1,210,000

$2,096,000





Upland waste rock

C02a

$41,300

$28,900

$70,200

$5,370

$75,570

POL068

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

POL069

BLM Polygon

Upland waste rock

C02a

$24,400

$17,100

$41,500

$3,180

$44,680

POL070

BLM Polygon

Upland waste rock

C02b

$35,100

$24,500

$59,600

$4,560

$64,160

POL071

BLM Polygon

Upland waste rock

C02b

$23,400

$16,400

$39,800

$3,040

$42,840

BIG04-2

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$140,000

$97,800

$237,800

$41,900

$279,700







CD-AVG

$39,100

$27,400

$66,500

$11,700

$78,200







VBS-AVG

$59,500

$41,700

$101,200

$17,900

$119,100

BIG04-3

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$573,000

$401,000

$974,000

$172,000

$1,146,000







CD-AVG

$276,000

$193,000

$469,000

$82,800

$551,800







FP/RP-AVG

$504,000

$353,000

$857,000

$90,700

$947,700







OFFCH-AVG

$849,000

$595,000

$1,444,000

$153,000

$1,597,000







VBS-AVG

$244,000

$171,000

$415,000

$73,300

$488,300

KLE024

BLM Polygon

Floodplain sediments (underlying tailings pond)

C11j

$8,750,000

$6,120,000

$14,870,000

$175,000

$15,045,000





Floodplain tailings - active facilities

C09

$10,400,000

$7,280,000

$17,680,000

$2,080,000

$19,760,000





Groundwater

WT03

$423,000

$296,000

$719,000

$553,000

$1,272,000

KLE025

BLM Polygon

Floodplain sediments

C01b

$135,000

$94,500

$229,500

$0

$229,500







C08a

$177,000

$124,000

$301,000

$24,800

$325,800







HAUL-2

$54,900

$38,400

$93,300

$0

$93,300





Floodplain tailings - inactive Facilities

C01

$1,730,000

$1,210,000

$2,940,000

$0

$2,940,000







C08a

$7,150,000

$5,010,000

$12,160,000

$1,000,000

$13,160,000







HAUL-2

$2,220,000

$1,550,000

$3,770,000

$0

$3,770,000

KLE026

BLM Polygon

Floodplain waste rock

C01

$377,000

$264,000

$641,000

$0

$641,000







C08a

$1,560,000

$1,090,000

$2,650,000

$218,000

$2,868,000







HAUL-2

$483,000

$338,000

$821,000

$0

$821,000

KLE027

BLM Polygon

Upland waste rock (erosion potential)

C01

$399,000

$279,000

$678,000

$0

$678,000







C08a

$1,650,000

$1,150,000

$2,800,000

$231,000

$3,031,000







HAUL-2

$511,000

$358,000

$869,000

$0

$869,000

KLE029

BLM Polygon

Upland waste rock

C02a

$187,000

$131,000

$318,000

$24,300

$342,300

KLE047

BLM Polygon

Floodplain sediments

C01b

$44,900

$31,400

$76,300

$0

$76,300







C08a

$58,800

$41,200

$100,000

$8,230

$108,230







HAUL-2

$18,200

$12,800

$31,000

$0

$31,000

KLE053

BLM Polygon

Floodplain waste rock

C01

$842,000

$589,000

$1,431,000

$0

$1,431,000







C08a

$3,480,000

$2,440,000

$5,920,000

$487,000

$6,407,000







HAUL-2

$1,080,000

$756,000

$1,836,000

$0

$1,836,000

KLE054

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$714,000

$500,000

$1,214,000

$661,000

$1,875,000





Upland waste rock (erosion potential)

C01

$685,000

$480,000

$1,165,000

$0

$1,165,000

Page 2 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







C08a

$2,830,000

$1,980,000

$4,810,000

$397,000

$5,207,000







HAUL-2

$879,000

$615,000

$1,494,000

$0

$1,494,000

KLE071

BLM Polygon

Floodplain sediments

C01b

$662,000

$463,000

$1,125,000

$0

$1,125,000







C08a

$867,000

$607,000

$1,474,000

$121,000

$1,595,000







HAUL-2

$269,000

$188,000

$457,000

$0

$457,000

KLE073

BLM Polygon

Floodplain sediments

C01b

$1,350,000

$945,000

$2,295,000

$0

$2,295,000







C08a

$1,770,000

$1,240,000

$3,010,000

$248,000

$3,258,000







HAUL-2

$549,000

$384,000

$933,000

$0

$933,000

POL005

BLM Polygon

Upland waste rock

C02b

$56,800

$39,700

$96,500

$7,380

$103,880

POL006

BLM Polygon

Upland waste rock

C02b

$31,700

$22,200

$53,900

$4,120

$58,020

POL008

BLM Polygon

Floodplain waste rock

C01

$34,900

$24,400

$59,300

$0

$59,300







C08a

$144,000

$101,000

$245,000

$20,200

$265,200







HAUL-2

$44,800

$31,400

$76,200

$0

$76,200

POL010

BLM Polygon

Upland waste rock (erosion potential)

C01

$19,500

$13,700

$33,200

$0

$33,200







C08a

$80,700

$56,500

$137,200

$11,300

$148,500







HAUL-2

$25,000

$17,500

$42,500

$0

$42,500

POL011

BLM Polygon

Floodplain waste rock

C01

$13,400

$9,350

$22,750

$0

$22,750







C08a

$55,200

$38,700

$93,900

$7,730

$101,630







HAUL-2

$17,100

$12,000

$29,100

$0

$29,100

POL022

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$138,000

$96,800

$234,800

$527,000

$761,800





Floodplain waste rock

C01

$19,700

$13,800

$33,500

$0

$33,500







C08a

$81,400

$57,000

$138,400

$11,400

$149,800







HAUL-2

$25,300

$17,700

$43,000

$0

$43,000

POL023

BLM Polygon

Upland waste rock

C02b

$50,100

$35,100

$85,200

$6,510

$91,710

POL066

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

POL075

BLM Polygon

Upland waste rock

C02b

$33,400

$23,400

$56,800

$4,340

$61,140

CCSeg PIPECC

General Feature

Source General Information

PIPE-1

$1,430,000

$1,000,000

$2,430,000

$115,000

$2,545,000







PIPE-2

$76,900

$53,800

$130,700

$6,150

$136,850







PIPE-3

$1,800,000

$1,260,000

$3,060,000

$144,000

$3,204,000







PIPE-4

$4,090,000

$2,870,000

$6,960,000

$327,000

$7,287,000

CCSegOl BUR102

BLM Polygon

Upland waste rock

C02a

$120,000

$83,800

$203,800

$15,600

$219,400

BUR105

BLM Polygon

Upland waste rock (erosion potential)

C01

$27,800

$19,500

$47,300

$0

$47,300







C07

$95,600

$66,900

$162,500

$21,000

$183,500

BUR109

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Upland waste rock (erosion potential)

C01

$117,000

$82,100

$199,100

$0

$199,100







C07

$403,000

$282,000

$685,000

$88,600

$773,600

BUR110

BLM Polygon

Upland waste rock

C02a

$24,400

$17,100

$41,500

$3,180

$44,680

BUR182

BLM Polygon

Upland waste rock

C02a

$13,500

$9,440

$22,940

$1,750

$24,690

Page 3 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID

CCSeg02









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

BUR183

BLM Polygon

Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

BUR184

BLM Polygon

Upland waste rock

C02a

$17,700

$12,400

$30,100

$2,300

$32,400

BUR185

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

BUR186

BLM Polygon

Upland waste rock

C02a

$20,200

$14,200

$34,400

$2,630

$37,030

BUR187

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

BUR188

BLM Polygon

Upland waste rock

C02a

$36,200

$25,400

$61,600

$4,710

$66,310

THO012

BLM Polygon

Upland waste rock

C02a

$27,800

$19,500

$47,300

$3,620

$50,920

THO013

BLM Polygon

Upland waste rock

C02a

$29,500

$20,700

$50,200

$3,840

$54,040

THO014

BLM Polygon

Upland waste rock

C02a

$23,600

$16,500

$40,100

$3,070

$43,170

THO015

BLM Polygon

Upland waste rock

C02a

$34,600

$24,200

$58,800

$4,490

$63,290

THO016

BLM Polygon

Upland waste rock

C02a

$11,000

$7,670

$18,670

$1,420

$20,090

THO017

BLM Polygon

Upland waste rock

C02a

$45,500

$31,900

$77,400

$5,920

$83,320

THO018

BLM Polygon

Upland waste rock

C02a

$16,900

$11,800

$28,700

$2,190

$30,890

THO023

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

BUR100

BLM Polygon

Upland waste rock

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

BUR106

BLM Polygon

Upland waste rock

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

BUR107

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Upland waste rock (erosion potential)

C01

$595,000

$416,000

$1,011,000

$0

$1,011,000







C07

$2,040,000

$1,430,000

$3,470,000

$450,000

$3,920,000

BUR130

BLM Polygon

Upland waste rock (erosion potential)

C01

$12,800

$8,990

$21,790

$0

$21,790







C07

$44,100

$30,900

$75,000

$9,700

$84,700

BUR131

BLM Polygon

Upland waste rock

C02a

$37,900

$26,600

$64,500

$4,930

$69,430

BUR132

BLM Polygon

Upland waste rock (erosion potential)

C01

$394,000

$276,000

$670,000

$0

$670,000







C07

$1,350,000

$947,000

$2,297,000

$298,000

$2,595,000

BUR133

BLM Polygon

Upland waste rock (erosion potential)

C01

$22,700

$15,900

$38,600

$0

$38,600







C07

$77,900

$54,500

$132,400

$17,100

$149,500

BUR134

BLM Polygon

Upland waste rock (erosion potential)

C01

$61,600

$43,100

$104,700

$0

$104,700







C07

$212,000

$148,000

$360,000

$46,600

$406,600

BUR135

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

BUR138

BLM Polygon

Upland waste rock

C02a

$48,900

$34,200

$83,100

$6,360

$89,460

BUR145

BLM Polygon

Upland waste rock (erosion potential)

C01

$240,000

$168,000

$408,000

$0

$408,000







C07

$823,000

$576,000

$1,399,000

$181,000

$1,580,000

BUR150

BLM Polygon

Floodplain waste rock

C01

$140,000

$97,700

$237,700

$0

$237,700







C08a

$577,000

$404,000

$981,000

$80,800

$1,061,800







HAUL-2

$179,000

$125,000

$304,000

$0

$304,000

BUR151

BLM Polygon

Upland waste rock

C02a

$148,000

$104,000

$252,000

$19,300

$271,300

BUR153

BLM Polygon

Floodplain sediments

C01b

$473,000

$331,000

$804,000

$0

$804,000

Page 4 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







C08a

$620,000

$434,000

$1,054,000

$86,700

$1,140,700







HAUL-2

$192,000

$135,000

$327,000

$0

$327,000

CC02-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$405,000

$283,000

$688,000

$121,000

$809,000







CD-AVG

$136,000

$95,200

$231,200

$40,800

$272,000







FP/RP-AVG

$889,000

$622,000

$1,511,000

$160,000

$1,671,000







VBS-AVG

$172,000

$121,000

$293,000

$51,700

$344,700

BUR085

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000





Upland waste rock

C02a

$34,600

$24,200

$58,800

$4,490

$63,290

BUR086

BLM Polygon

Upland waste rock

C02a

$141,000

$98,500

$239,500

$18,300

$257,800

BUR087

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Upland waste rock (erosion potential)

C01

$107,000

$74,900

$181,900

$0

$181,900







C07

$368,000

$257,000

$625,000

$80,900

$705,900

BUR088

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500

BUR089

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

BUR090

BLM Polygon

Upland tailings

C01

$128,000

$89,900

$217,900

$0

$217,900







C08a

$531,000

$372,000

$903,000

$74,300

$977,300







HAUL-2

$165,000

$115,000

$280,000

$0

$280,000





Upland waste rock (erosion potential)

C01

$235,000

$165,000

$400,000

$0

$400,000







C07

$809,000

$566,000

$1,375,000

$178,000

$1,553,000

BUR091

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Upland waste rock

C02a

$24,400

$17,100

$41,500

$3,180

$44,680

BUR092

BLM Polygon

Upland waste rock

C02a

$16,000

$11,200

$27,200

$2,080

$29,280

BUR099

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Upland waste rock

C02a

$17,700

$12,400

$30,100

$2,300

$32,400

BUR101

BLM Polygon

Upland waste rock

C02a

$20,200

$14,200

$34,400

$2,630

$37,030

BUR146

BLM Polygon

Floodplain sediments

C01b

$689,000

$482,000

$1,171,000

$0

$1,171,000







C08a

$903,000

$632,000

$1,535,000

$126,000

$1,661,000







HAUL-2

$280,000

$196,000

$476,000

$0

$476,000

BUR149

BLM Polygon

Upland waste rock (erosion potential)

C01

$44,500

$31,200

$75,700

$0

$75,700







C07

$153,000

$107,000

$260,000

$33,600

$293,600

BUR165

BLM Polygon

Upland waste rock

C02a

$17,700

$12,400

$30,100

$2,300

$32,400

BUR166

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

BUR167

BLM Polygon

Upland waste rock

C02a

$35,400

$24,800

$60,200

$4,600

$64,800

BUR179

BLM Polygon

Upland waste rock

C02a

$20,200

$14,200

$34,400

$2,630

$37,030

BUR180

BLM Polygon

Upland waste rock (erosion potential)

C01

$23,500

$16,500

$40,000

$0

$40,000

CCSeg03

Page 5 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







C07

$80,900

$56,600

$137,500

$17,800

$155,300

CCSeg04 BUR063

BLM Polygon

Upland waste rock

C02a

$159,000

$112,000

$271,000

$20,700

$291,700

BUR064

BLM Polygon

Upland waste rock

C02a

$34,600

$24,200

$58,800

$4,490

$63,290

BUR065

BLM Polygon

Upland waste rock

C02a

$85,100

$59,600

$144,700

$11,100

$155,800

BUR066

BLM Polygon

Upland waste rock (erosion potential)

C01

$30,000

$21,000

$51,000

$0

$51,000







C08a

$124,000

$86,700

$210,700

$17,300

$228,000







HAUL-2

$38,400

$26,900

$65,300

$0

$65,300

BUR067

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$950,000

$1,020,000

$1,970,000

$723,000

$2,693,000





Upland tailings

C01

$10,700

$7,490

$18,190

$0

$18,190







C08a

$44,300

$31,000

$75,300

$6,200

$81,500







HAUL-2

$13,700

$9,610

$23,310

$0

$23,310





Upland waste rock (potential intermixed tailings)

C01

$1,500,000

$1,050,000

$2,550,000

$0

$2,550,000







C08a

$6,200,000

$4,340,000

$10,540,000

$867,000

$11,407,000







HAUL-2

$1,920,000

$1,350,000

$3,270,000

$0

$3,270,000

BUR068

BLM Polygon

Upland waste rock (erosion potential)

C01

$51,400

$36,000

$87,400

$0

$87,400







C08a

$212,000

$149,000

$361,000

$29,700

$390,700







HAUL-2

$65,900

$46,100

$112,000

$0

$112,000

BUR069

BLM Polygon

Upland waste rock

C02a

$88,500

$62,000

$150,500

$11,500

$162,000

BUR070

BLM Polygon

Upland waste rock

C02a

$237,000

$166,000

$403,000

$30,800

$433,800

BUR071

BLM Polygon

Upland waste rock

C02a

$166,000

$116,000

$282,000

$21,600

$303,600

BUR072

BLM Polygon

Upland waste rock (erosion potential)

C01

$61,200

$42,800

$104,000

$0

$104,000







C08a

$253,000

$177,000

$430,000

$35,400

$465,400







HAUL-2

$78,500

$55,000

$133,500

$0

$133,500

BUR073

BLM Polygon

Upland waste rock (erosion potential)

C01

$539,000

$377,000

$916,000

$0

$916,000







C08a

$2,230,000

$1,560,000

$3,790,000

$312,000

$4,102,000







HAUL-2

$692,000

$484,000

$1,176,000

$0

$1,176,000

BUR074

BLM Polygon

Upland waste rock

C02a

$145,000

$101,000

$246,000

$18,800

$264,800

BUR075

BLM Polygon

Upland tailings

C01

$15,000

$10,500

$25,500

$0

$25,500







C08a

$62,000

$43,400

$105,400

$8,670

$114,070







HAUL-2

$19,200

$13,500

$32,700

$0

$32,700





Upland waste rock

C02a

$148,000

$103,000

$251,000

$19,200

$270,200

BUR076

BLM Polygon

Upland waste rock

C02a

$9,270

$6,490

$15,760

$1,210

$16,970

BUR093

BLM Polygon

Upland waste rock

C02a

$11,800

$8,260

$20,060

$1,530

$21,590

BUR094

BLM Polygon

Upland waste rock (erosion potential)

C02a

$118,000

$82,600

$200,600

$15,300

$215,900

BUR095

BLM Polygon

Upland waste rock (erosion potential)

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

BUR096

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$4,890

$5,230

$10,120

$3,700

$13,820





Upland waste rock

C02a

$120,000

$83,800

$203,800

$15,600

$219,400

BUR097

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$869,000

$929,000

$1,798,000

$659,000

$2,457,000





Upland waste rock

C02a

$73,300

$51,300

$124,600

$9,530

$134,130

Page 6 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

BUR098

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$905,000

$968,000

$1,873,000

$896,000

$2,769,000





Upland waste rock (potential intermixed tailings)

C01

$235,000

$165,000

$400,000

$0

$400,000







C08a

$974,000

$681,000

$1,655,000

$136,000

$1,791,000







HAUL-2

$302,000

$211,000

$513,000

$0

$513,000

BUR111

BLM Polygon

Upland waste rock

C02a

$20,200

$14,200

$34,400

$2,630

$37,030

BUR112

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Upland waste rock

C02a

$111,000

$77,900

$188,900

$14,500

$203,400

BUR113

BLM Polygon

Upland waste rock

C02a

$22,800

$15,900

$38,700

$2,960

$41,660

BUR114

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Upland waste rock (erosion potential)

C02a

$98,600

$69,000

$167,600

$12,800

$180,400

BUR115

BLM Polygon

Upland waste rock

C02a

$49,700

$34,800

$84,500

$6,470

$90,970

BUR116

BLM Polygon

Upland waste rock (erosion potential)

C02a

$27,800

$19,500

$47,300

$3,620

$50,920

BUR117

BLM Polygon

Upland tailings

C01

$7,700

$5,390

$13,090

$0

$13,090







C08a

$31,900

$22,300

$54,200

$4,460

$58,660







HAUL-2

$9,880

$6,920

$16,800

$0

$16,800





Upland waste rock (potential intermixed tailings)

C01

$621,000

$434,000

$1,055,000

$0

$1,055,000







C08a

$2,570,000

$1,800,000

$4,370,000

$359,000

$4,729,000







HAUL-2

$796,000

$557,000

$1,353,000

$0

$1,353,000

BUR118

BLM Polygon

Upland waste rock (erosion potential)

C01

$141,000

$98,900

$239,900

$0

$239,900







C08a

$584,000

$409,000

$993,000

$81,800

$1,074,800







HAUL-2

$181,000

$127,000

$308,000

$0

$308,000

BUR119

BLM Polygon

Upland waste rock

C02a

$175,000

$123,000

$298,000

$22,800

$320,800

BUR120

BLM Polygon

Upland waste rock (erosion potential)

C02a

$78,400

$54,900

$133,300

$10,200

$143,500

BUR121

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$682,000

$729,000

$1,411,000

$517,000

$1,928,000





Upland waste rock (erosion potential)

C01

$441,000

$309,000

$750,000

$0

$750,000







C08a

$1,820,000

$1,280,000

$3,100,000

$255,000

$3,355,000







HAUL-2

$565,000

$396,000

$961,000

$0

$961,000

BUR122

BLM Polygon

Upland waste rock (erosion potential)

C01

$116,000

$80,900

$196,900

$0

$196,900







C08a

$478,000

$335,000

$813,000

$66,900

$879,900







HAUL-2

$148,000

$104,000

$252,000

$0

$252,000

BUR123

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Upland waste rock (erosion potential)

C02a

$13,500

$9,440

$22,940

$1,750

$24,690

BUR124

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Upland waste rock (erosion potential)

C02a

$84,300

$59,000

$143,300

$11,000

$154,300

BUR125

BLM Polygon

Upland waste rock (erosion potential)

C02a

$27,000

$18,900

$45,900

$3,510

$49,410

BUR126

BLM Polygon

Upland waste rock

C02a

$39,600

$27,700

$67,300

$5,150

$72,450

Page 7 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

BUR127

BLM Polygon

Upland waste rock

C02a

$14,300

$10,000

$24,300

$1,860

$26,160

BUR128

BLM Polygon

Buildings & structures

HH-4

$1,690,000

$1,180,000

$2,870,000

$219,000

$3,089,000





Upland tailings

C01

$186,000

$130,000

$316,000

$0

$316,000







C08a

$768,000

$538,000

$1,306,000

$108,000

$1,414,000







HAUL-2

$238,000

$167,000

$405,000

$0

$405,000

BUR129

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Upland tailings

C01

$22,500

$15,700

$38,200

$0

$38,200







C08a

$92,900

$65,000

$157,900

$13,000

$170,900







HAUL-2

$28,800

$20,200

$49,000

$0

$49,000

BUR141

BLM Polygon

Floodplain sediments

C01b

$297,000

$208,000

$505,000

$0

$505,000







C08a

$389,000

$273,000

$662,000

$54,500

$716,500







HAUL-2

$121,000

$84,500

$205,500

$0

$205,500

BUR142

BLM Polygon

Upland tailings

C01

$21,000

$14,700

$35,700

$0

$35,700







C08a

$86,700

$60,700

$147,400

$12,100

$159,500







HAUL-2

$26,900

$18,800

$45,700

$0

$45,700





Upland waste rock (potential intermixed tailings)

C01

$310,000

$217,000

$527,000

$0

$527,000







C08a

$1,280,000

$898,000

$2,178,000

$180,000

$2,358,000







HAUL-2

$398,000

$279,000

$677,000

$0

$677,000

BUR143

BLM Polygon

Floodplain sediments

C01b

$432,000

$302,000

$734,000

$0

$734,000







C08a

$566,000

$396,000

$962,000

$79,300

$1,041,300







HAUL-2

$176,000

$123,000

$299,000

$0

$299,000

BUR144

BLM Polygon

Upland waste rock (erosion potential)

C01

$167,000

$117,000

$284,000

$0

$284,000







C08a

$690,000

$483,000

$1,173,000

$96,600

$1,269,600







HAUL-2

$214,000

$150,000

$364,000

$0

$364,000

BUR174

BLM Polygon

Upland waste rock

C02a

$427,000

$299,000

$726,000

$55,500

$781,500

BUR175

BLM Polygon

Upland waste rock

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

BUR176

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

BUR177

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

BUR178

BLM Polygon

Upland waste rock (erosion potential)

C01

$47,100

$33,000

$80,100

$0

$80,100







C08a

$195,000

$136,000

$331,000

$27,300

$358,300







HAUL-2

$60,400

$42,300

$102,700

$0

$102,700

BUR189

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

BUR190

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$302,000

$323,000

$625,000

$165,000

$790,000

BUR191

BLM Polygon

Upland waste rock

C02a

$131,000

$91,500

$222,500

$17,000

$239,500

Page 8 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

BUR192

BLM Polygon

Floodplain tailings (discrete site)

C01

$13,300

$9,290

$22,590

$0

$22,590







C08a

$54,900

$38,400

$93,300

$7,680

$100,980







HAUL-2

$17,000

$11,900

$28,900

$0

$28,900





Upland waste rock (erosion potential)

C01

$116,000

$80,900

$196,900

$0

$196,900







C08a

$478,000

$335,000

$813,000

$66,900

$879,900







HAUL-2

$148,000

$104,000

$252,000

$0

$252,000

BUR193

BLM Polygon

Upland waste rock

C02a

$63,200

$44,300

$107,500

$8,220

$115,720

BUR194

BLM Polygon

Upland waste rock

C02a

$58,200

$40,700

$98,900

$7,560

$106,460

BUR195

BLM Polygon

Upland waste rock

C02a

$35,400

$24,800

$60,200

$4,600

$64,800

BUR198

BLM Polygon

Upland waste rock

C02a

$114,000

$79,700

$193,700

$14,800

$208,500

BUR199

BLM Polygon

Upland waste rock

C02a

$27,000

$18,900

$45,900

$3,510

$49,410

BUR200

BLM Polygon

Upland waste rock

C02a

$19,400

$13,600

$33,000

$2,520

$35,520

BUR202

BLM Polygon

Upland waste rock

C02a

$9,270

$6,490

$15,760

$1,210

$16,970

BUR203

BLM Polygon

Upland waste rock

C02a

$10,100

$7,080

$17,180

$1,320

$18,500

BUR204

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

CC04-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$1,220,000

$854,000

$2,074,000

$366,000

$2,440,000







CD-AVG

$412,000

$288,000

$700,000

$124,000

$824,000







FP/RP-AVG

$3,190,000

$2,230,000

$5,420,000

$574,000

$5,994,000







OFFCH-AVG

$1,800,000

$1,260,000

$3,060,000

$324,000

$3,384,000







VBS-AVG

$520,000

$364,000

$884,000

$156,000

$1,040,000

CC05-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$136,000

$94,900

$230,900

$40,700

$271,600







CD-AVG

$22,700

$15,900

$38,600

$6,800

$45,400







FP/RP-AVG

$4,810,000

$3,370,000

$8,180,000

$865,000

$9,045,000







OFFCH-AVG

$16,000,000

$11,200,000

$27,200,000

$2,890,000

$30,090,000







VBS-AVG

$57,800

$40,400

$98,200

$17,300

$115,500

CC05-2

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$820,000

$574,000

$1,394,000

$246,000

$1,640,000







CD-AVG

$138,000

$96,600

$234,600

$41,400

$276,000







CH REAL-1

$3,780,000

$2,650,000

$6,430,000

$643,000

$7,073,000







FP/RP-AVG

$1,800,000

$1,260,000

$3,060,000

$324,000

$3,384,000







VBS-AVG

$350,000

$245,000

$595,000

$105,000

$700,000

OSB047

BLM Polygon

Floodplain sediments

C01B

$230,000

$161,000

$391,000

$0

$391,000







C08a

$301,000

$211,000

$512,000

$42,100

$554,100







HAUL-2

$93,300

$65,300

$158,600

$0

$158,600

WAL009

BLM Polygon

Floodplain sediments (underlying tailings pond)

C01B

$4,360,000

$3,050,000

$7,410,000

$0

$7,410,000







C08a

$5,720,000

$4,000,000

$9,720,000

$800,000

$10,520,000







HAUL-2

$1,770,000

$1,240,000

$3,010,000

$0

$3,010,000





Floodplain tailings - inactive Facilities

C01

$8,990,000

$6,290,000

$15,280,000

$0

$15,280,000







C08a

$37,200,000

$26,000,000

$63,200,000

$5,200,000

$68,400,000







HAUL-2

$11,500,000

$8,070,000

$19,570,000

$0

$19,570,000

WAL010

BLM Polygon

Floodplain sediments

C01B

$203,000

$142,000

$345,000

$0

$345,000

CCSeg05

Page 9 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID

MIDGradSeg









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







C08a

$266,000

$186,000

$452,000

$37,200

$489,200







HAUL-2

$82,400

$57,600

$140,000

$0

$140,000

WAL011

BLM Polygon

Adit drainage

WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Floodplain sediments

C01B

$119,000

$83,200

$202,200

$0

$202,200







C08a

$156,000

$109,000

$265,000

$21,800

$286,800







HAUL-2

$48,300

$33,800

$82,100

$0

$82,100





Upland tailings

C01

$49,600

$34,800

$84,400

$0

$84,400







C08a

$205,000

$144,000

$349,000

$28,700

$377,700







HAUL-2

$63,700

$44,600

$108,300

$0

$108,300

WAL039

BLM Polygon

Upland tailings

C01

$53,500

$37,500

$91,000

$0

$91,000







C08a

$221,000

$155,000

$376,000

$31,000

$407,000







HAUL-2

$68,600

$48,000

$116,600

$0

$116,600

WAL040

BLM Polygon

Floodplain sediments

C01B

$243,000

$170,000

$413,000

$0

$413,000







C08a

$319,000

$223,000

$542,000

$44,600

$586,600







HAUL-2

$98,800

$69,200

$168,000

$0

$168,000

WAL041

BLM Polygon

Floodplain sediments

C01B

$486,000

$340,000

$826,000

$0

$826,000







C08a

$637,000

$446,000

$1,083,000

$89,200

$1,172,200







HAUL-2

$198,000

$138,000

$336,000

$0

$336,000

WAL042

BLM Polygon

Floodplain sediments

C01B

$109,000

$76,500

$185,500

$0

$185,500







C08a

$143,000

$100,000

$243,000

$20,100

$263,100







HAUL-2

$44,500

$31,100

$75,600

$0

$75,600





Floodplain tailings - inactive Facilities

C01

$2,570,000

$1,800,000

$4,370,000

$0

$4,370,000







C08a

$10,600,000

$7,430,000

$18,030,000

$1,490,000

$19,520,000







HAUL-2

$3,290,000

$2,310,000

$5,600,000

$0

$5,600,000

WAL081

BLM Polygon

Floodplain artificial fill

C01

$24,400

$17,100

$41,500

$0

$41,500







C08a

$101,000

$70,600

$171,600

$14,100

$185,700







HAUL-2

$31,300

$21,900

$53,200

$0

$53,200

PIPEMG

General Feature

Source General Information

PIPE-1

$417,000

$292,000

$709,000

$33,300

$742,300







PIPE-2

$40,400

$28,300

$68,700

$3,230

$71,930







PIPE-4

$12,100,000

$8,480,000

$20,580,000

$969,000

$21,549,000

KLE004

BLM Polygon

Upland waste rock

C02a

$29,500

$20,700

$50,200

$3,840

$54,040

KLE005

BLM Polygon

Upland waste rock

C02a

$54,000

$37,800

$91,800

$7,010

$98,810

KLE006

BLM Polygon

Upland waste rock

C02a

$115,000

$80,800

$195,800

$15,000

$210,800

KLE011

BLM Polygon

Upland tailings - inactive facilities

C01

$351,000

$246,000

$597,000

$0

$597,000







C08a

$1,450,000

$1,020,000

$2,470,000

$203,000

$2,673,000







HAUL-2

$450,000

$315,000

$765,000

$0

$765,000

KLE016

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

KLE020

BLM Polygon

Upland waste rock (erosion potential)

C01

$154,000

$108,000

$262,000

$0

$262,000







C08a

$637,000

$446,000

$1,083,000

$89,200

$1,172,200







HAUL-2

$198,000

$138,000

$336,000

$0

$336,000

MIDGradSegOl

Page 10 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

KLE021

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

KLE022

BLM Polygon

Upland waste rock

C02a

$88,500

$62,000

$150,500

$11,500

$162,000

KLE023

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

KLE032

BLM Polygon

Upland waste rock

C02a

$23,600

$16,500

$40,100

$3,070

$43,170

KLE033

BLM Polygon

Upland waste rock (erosion potential)

C01

$107,000

$74,900

$181,900

$0

$181,900







C08a

$443,000

$310,000

$753,000

$62,000

$815,000







HAUL-2

$137,000

$96,100

$233,100

$0

$233,100

KLE034

BLM Polygon

Floodplain waste rock

C01

$94,200

$65,900

$160,100

$0

$160,100







C08a

$389,000

$273,000

$662,000

$54,500

$716,500







HAUL-2

$121,000

$84,500

$205,500

$0

$205,500

KLE035

BLM Polygon

Buildings & structures

HH-4

$1,690,000

$1,180,000

$2,870,000

$219,000

$3,089,000





Floodplain waste rock

C01

$514,000

$360,000

$874,000

$0

$874,000







C08a

$2,120,000

$1,490,000

$3,610,000

$297,000

$3,907,000







HAUL-2

$659,000

$461,000

$1,120,000

$0

$1,120,000

KLE036

BLM Polygon

Upland waste rock

C02a

$58,200

$40,700

$98,900

$7,560

$106,460

KLE038

BLM Polygon

Upland waste rock

C02a

$307,000

$215,000

$522,000

$39,900

$561,900

KLE039

BLM Polygon

Upland waste rock (erosion potential)

C01

$150,000

$105,000

$255,000

$0

$255,000







C08a

$620,000

$434,000

$1,054,000

$86,700

$1,140,700







HAUL-2

$192,000

$135,000

$327,000

$0

$327,000

KLE040

BLM Polygon

Floodplain sediments

C01b

$1,510,000

$1,060,000

$2,570,000

$0

$2,570,000







C08a

$1,980,000

$1,390,000

$3,370,000

$278,000

$3,648,000







HAUL-2

$615,000

$430,000

$1,045,000

$0

$1,045,000





Groundwater

WT01

$402,000

$430,000

$832,000

$609,000

$1,441,000

KLE042

BLM Polygon

Floodplain sediments

C01b

$675,000

$473,000

$1,148,000

$0

$1,148,000







C08a

$885,000

$620,000

$1,505,000

$124,000

$1,629,000







HAUL-2

$275,000

$192,000

$467,000

$0

$467,000





Floodplain tailings

C01

$55,600

$38,900

$94,500

$0

$94,500







C08a

$230,000

$161,000

$391,000

$32,200

$423,200







HAUL-2

$71,400

$50,000

$121,400

$0

$121,400

KLE048

BLM Polygon

Floodplain sediments

C01b

$1,620,000

$1,130,000

$2,750,000

$0

$2,750,000







C08a

$2,120,000

$1,480,000

$3,600,000

$297,000

$3,897,000







C14c

$8,910,000

$6,240,000

$15,150,000

$267,000

$15,417,000







C15b

$2,720,000

$1,900,000

$4,620,000

$54,400

$4,674,400







HAUL-2

$657,000

$460,000

$1,117,000

$0

$1,117,000





Groundwater

WT01

$402,000

$430,000

$832,000

$609,000

$1,441,000

KLE049

BLM Polygon

Floodplain sediments

C01b

$1,760,000

$1,230,000

$2,990,000

$0

$2,990,000







C08a

$2,300,000

$1,610,000

$3,910,000

$322,000

$4,232,000







C14c

$7,430,000

$5,200,000

$12,630,000

$223,000

$12,853,000

Page 11 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







C15b

$2,270,000

$1,590,000

$3,860,000

$45,400

$3,905,400







HAUL-2

$714,000

$500,000

$1,214,000

$0

$1,214,000





Groundwater

WT01

$402,000

$430,000

$832,000

$609,000

$1,441,000

KLE051

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

KLE056

BLM Polygon

Upland waste rock

C02a

$30,300

$21,200

$51,500

$3,950

$55,450

KLE057

BLM Polygon

Upland waste rock

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

KLE058

BLM Polygon

Upland waste rock

C02a

$19,400

$13,600

$33,000

$2,520

$35,520

KLE059

BLM Polygon

Upland waste rock

C02a

$11,800

$8,260

$20,060

$1,530

$21,590

KLE060

BLM Polygon

Upland waste rock

C02a

$20,200

$14,200

$34,400

$2,630

$37,030

KLE062

BLM Polygon

Floodplain sediments

C01b

$351,000

$246,000

$597,000

$0

$597,000







C08a

$460,000

$322,000

$782,000

$64,400

$846,400







HAUL-2

$143,000

$99,900

$242,900

$0

$242,900





Upland waste rock

C02a

$278,000

$195,000

$473,000

$36,200

$509,200

KLE066

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

KLE067

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$267,000

$187,000

$454,000

$1,010,000

$1,464,000





Upland waste rock (erosion potential)

C01

$118,000

$82,400

$200,400

$0

$200,400







C08a

$487,000

$341,000

$828,000

$68,100

$896,100







HAUL-2

$151,000

$106,000

$257,000

$0

$257,000

KLE068

BLM Polygon

Upland waste rock (erosion potential)

C01

$59,900

$41,900

$101,800

$0

$101,800







C08a

$248,000

$173,000

$421,000

$34,700

$455,700







HAUL-2

$76,900

$53,800

$130,700

$0

$130,700

KLE069

BLM Polygon

Upland waste rock (erosion potential)

C01

$5,560

$3,890

$9,450

$0

$9,450







C08a

$23,000

$16,100

$39,100

$3,220

$42,320







HAUL-2

$7,140

$5,000

$12,140

$0

$12,140

KLE070

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

KLE074

BLM Polygon

Buildings & structures

HH-4

$1,690,000

$1,180,000

$2,870,000

$219,000

$3,089,000





Upland tailings

C01

$59,900

$41,900

$101,800

$0

$101,800







C08a

$248,000

$173,000

$421,000

$34,700

$455,700







HAUL-2

$76,900

$53,800

$130,700

$0

$130,700

KLE075

BLM Polygon

Upland tailings

C01

$17,100

$12,000

$29,100

$0

$29,100







C08a

$70,800

$49,600

$120,400

$9,910

$130,310







HAUL-2

$22,000

$15,400

$37,400

$0

$37,400

MG01-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$110,000

$76,900

$186,900

$32,900

$219,800







CD-AVG

$59,700

$41,800

$101,500

$17,900

$119,400







FP/RP-AVG

$47,000

$32,900

$79,900

$8,460

$88,360

Page 12 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID







2009 Total



Direct and







Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description (Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

MG01-10

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$104,000

$72,600

$176,600

$31,100

$207,700





CD-AVG

$10,300

$7,210

$17,510

$3,090

$20,600





FP/RP-AVG

$409,000

$286,000

$695,000

$73,600

$768,600





OFFCH-AVG

$2,990,000

$2,090,000

$5,080,000

$538,000

$5,618,000





VBS-AVG

$44,200

$30,900

$75,100

$13,300

$88,400

MG01-11

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$140,000

$98,200

$238,200

$42,100

$280,300





CD-AVG

$16,500

$11,500

$28,000

$4,940

$32,940





FP/RP-AVG

$173,000

$121,000

$294,000

$31,200

$325,200





VBS-AVG

$59,800

$41,900

$101,700

$17,900

$119,600

MG01-12

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$134,000

$93,900

$227,900

$40,300

$268,200





CD-AVG

$30,900

$21,600

$52,500

$9,270

$61,770





FP/RP-AVG

$238,000

$166,000

$404,000

$42,800

$446,800





VBS-AVG

$57,200

$40,000

$97,200

$17,200

$114,400

MG01-13

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$305,000

$214,000

$519,000

$91,500

$610,500





CD-AVG

$47,400

$33,200

$80,600

$14,200

$94,800





CH REAL-1

$1,270,000

$892,000

$2,162,000

$217,000

$2,379,000





FP/RP-AVG

$715,000

$500,000

$1,215,000

$129,000

$1,344,000





OFFCH-AVG

$2,710,000

$1,900,000

$4,610,000

$488,000

$5,098,000





VBS-AVG

$130,000

$91,000

$221,000

$39,000

$260,000

MG01-14

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$92,500

$64,700

$157,200

$27,700

$184,900





CD-AVG

$16,500

$11,500

$28,000

$4,940

$32,940





CH REAL-1

$426,000

$298,000

$724,000

$72,500

$796,500





FP/RP-AVG

$61,900

$43,300

$105,200

$11,100

$116,300





OFFCH-AVG

$55,700

$39,000

$94,700

$10,000

$104,700





VBS-AVG

$39,400

$27,600

$67,000

$11,800

$78,800

MG01-15

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$236,000

$165,000

$401,000

$70,700

$471,700





CD-AVG

$39,100

$27,400

$66,500

$11,700

$78,200





FP/RP-AVG

$966,000

$676,000

$1,642,000

$174,000

$1,816,000





OFFCH-AVG

$1,800,000

$1,260,000

$3,060,000

$324,000

$3,384,000





VBS-AVG

$30,200

$21,100

$51,300

$9,050

$60,350

MG01-16

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$131,000

$91,500

$222,500

$39,200

$261,700





CD-AVG

$22,700

$15,900

$38,600

$6,800

$45,400





FP/RP-AVG

$60,300

$42,200

$102,500

$10,900

$113,400





OFFCH-AVG

$1,400,000

$979,000

$2,379,000

$252,000

$2,631,000





VBS-AVG

$16,700

$11,700

$28,400

$5,010

$33,410

MG01-17

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$334,000

$234,000

$568,000

$100,000

$668,000





CD-AVG

$55,600

$38,900

$94,500

$16,700

$111,200





CH REAL-1

$1,540,000

$1,080,000

$2,620,000

$262,000

$2,882,000





FP/RP-AVG

$1,400,000

$981,000

$2,381,000

$252,000

$2,633,000





OFFCH-AVG

$1,100,000

$772,000

$1,872,000

$198,000

$2,070,000





VBS-AVG

$142,000

$99,700

$241,700

$42,700

$284,400

MG01-18

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$167,000

$117,000

$284,000

$50,000

$334,000

Page 13 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







CD-AVG

$28,800

$20,200

$49,000

$8,650

$57,650







CH REAL-1

$768,000

$538,000

$1,306,000

$131,000

$1,437,000







FP/RP-AVG

$545,000

$381,000

$926,000

$98,000

$1,024,000







OFFCH-AVG

$231,000

$162,000

$393,000

$41,500

$434,500







VBS-AVG

$71,000

$49,700

$120,700

$21,300

$142,000

MG01-2

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$97,600

$68,300

$165,900

$29,300

$195,200







CD-AVG

$33,000

$23,100

$56,100

$9,890

$65,990







FP/RP-AVG

$133,000

$92,900

$225,900

$23,900

$249,800

MG01-3

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$189,000

$132,000

$321,000

$56,700

$377,700







CD-AVG

$20,600

$14,400

$35,000

$6,180

$41,180







FP/RP-AVG

$557,000

$390,000

$947,000

$100,000

$1,047,000







VBS-AVG

$80,600

$56,400

$137,000

$24,200

$161,200

MG01-4

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$305,000

$214,000

$519,000

$91,500

$610,500







CD-AVG

$119,000

$83,600

$202,600

$35,800

$238,400







FP/RP-AVG

$874,000

$612,000

$1,486,000

$157,000

$1,643,000







VBS-AVG

$130,000

$91,000

$221,000

$39,000

$260,000

MG01-5

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$97,600

$68,300

$165,900

$29,300

$195,200







CD-AVG

$14,400

$10,100

$24,500

$4,330

$28,830







FP/RP-AVG

$833,000

$583,000

$1,416,000

$150,000

$1,566,000







VBS-AVG

$41,600

$29,100

$70,700

$12,500

$83,200

MG01-6

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$384,000

$269,000

$653,000

$115,000

$768,000







CD-AVG

$78,300

$54,800

$133,100

$23,500

$156,600







FP/RP-AVG

$1,900,000

$1,330,000

$3,230,000

$342,000

$3,572,000







OFFCH-AVG

$3,240,000

$2,270,000

$5,510,000

$583,000

$6,093,000







VBS-AVG

$164,000

$115,000

$279,000

$49,100

$328,100

MG01-7

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$433,000

$303,000

$736,000

$130,000

$866,000







CD-AVG

$20,600

$14,400

$35,000

$6,180

$41,180







FP/RP-AVG

$487,000

$341,000

$828,000

$87,700

$915,700







OFFCH-AVG

$440,000

$308,000

$748,000

$79,100

$827,100







VBS-AVG

$185,000

$129,000

$314,000

$55,400

$369,400

MG01-8

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$286,000

$200,000

$486,000

$85,900

$571,900







CD-AVG

$47,400

$33,200

$80,600

$14,200

$94,800







CH REAL-1

$1,320,000

$924,000

$2,244,000

$225,000

$2,469,000







FP/RP-AVG

$3,150,000

$2,200,000

$5,350,000

$566,000

$5,916,000







OFFCH-AVG

$2,620,000

$1,830,000

$4,450,000

$471,000

$4,921,000







VBS-AVG

$122,000

$85,400

$207,400

$36,600

$244,000

MG01-9

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$68,000

$47,600

$115,600

$20,400

$136,000







CD-AVG

$12,400

$8,650

$21,050

$3,710

$24,760







CH REAL-1

$314,000

$219,000

$533,000

$53,300

$586,300







FP/RP-AVG

$30,600

$21,400

$52,000

$5,520

$57,520







VBS-AVG

$29,000

$20,300

$49,300

$8,690

$57,990

MUL085

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200

Page 14 of 43

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







WT02

$1,090,000

$766,000

$1,856,000

$1,680,000

$3,536,000





Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

MUL086

BLM Polygon

Upland waste rock (erosion potential)

C01

$128,000

$89,900

$217,900

$0

$217,900







C08a

$531,000

$372,000

$903,000

$74,300

$977,300







HAUL-2

$165,000

$115,000

$280,000

$0

$280,000

MUL087

BLM Polygon

Upland waste rock

C02a

$31,200

$21,800

$53,000

$4,050

$57,050

OSB024

BLM Polygon

Upland waste rock

C02a

$54,800

$38,400

$93,200

$7,120

$100,320

OSB025

BLM Polygon

Upland waste rock (erosion potential)

C01

$51,400

$36,000

$87,400

$0

$87,400







C08a

$212,000

$149,000

$361,000

$29,700

$390,700







HAUL-2

$65,900

$46,100

$112,000

$0

$112,000

OSB026

BLM Polygon

Upland waste rock

C02a

$65,800

$46,000

$111,800

$8,550

$120,350

OSB027

BLM Polygon

Upland waste rock

C02a

$100,000

$70,200

$170,200

$13,000

$183,200

OSB028

BLM Polygon

Upland waste rock

C02a

$9,270

$6,490

$15,760

$1,210

$16,970

OSB030

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

OSB065

BLM Polygon

Floodplain sediments

C01b

$6,240,000

$4,370,000

$10,610,000

$0

$10,610,000







C08a

$8,180,000

$5,720,000

$13,900,000

$1,140,000

$15,040,000







C14c

$65,300,000

$45,700,000

$111,000,000

$1,960,000

$112,960,000







C15b

$20,000,000

$14,000,000

$34,000,000

$399,000

$34,399,000







HAUL-2

$2,540,000

$1,780,000

$4,320,000

$0

$4,320,000





Groundwater

WT01

$402,000

$430,000

$832,000

$609,000

$1,441,000

OSB070

BLM Polygon

Upland waste rock (erosion potential)

C01

$133,000

$92,900

$225,900

$0

$225,900







C08a

$549,000

$384,000

$933,000

$76,800

$1,009,800







HAUL-2

$170,000

$119,000

$289,000

$0

$289,000

OSB071

BLM Polygon

Upland waste rock

C02a

$27,000

$18,900

$45,900

$3,510

$49,410

OSB072

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

OSB073

BLM Polygon

Upland waste rock (erosion potential)

C01

$94,200

$65,900

$160,100

$0

$160,100







C08a

$389,000

$273,000

$662,000

$54,500

$716,500







HAUL-2

$121,000

$84,500

$205,500

$0

$205,500

OSB074

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000





Upland waste rock

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

OSB075

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

OSB076

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$139,000

$97,200

$236,200

$528,000

$764,200

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)

Page 15 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)





Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

OSB078

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

OSB079

BLM Polygon

Upland waste rock

C02a

$13,500

$9,440

$22,940

$1,750

$24,690

OSB080

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$145,000

$102,000

$247,000

$529,000

$776,000





Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

OSB117

BLM Polygon

Floodplain tailings

C01

$59,900

$41,900

$101,800

$0

$101,800







C08a

$248,000

$173,000

$421,000

$34,700

$455,700







HAUL-2

$76,900

$53,800

$130,700

$0

$130,700

OSB118

BLM Polygon

Floodplain sediments

C01b

$810,000

$567,000

$1,377,000

$0

$1,377,000







C08a

$1,060,000

$743,000

$1,803,000

$149,000

$1,952,000







HAUL-2

$329,000

$231,000

$560,000

$0

$560,000

OSB119

BLM Polygon

Floodplain sediments (underlying tailings pond)

C01b

$4,320,000

$3,020,000

$7,340,000

$0

$7,340,000







C08a

$5,660,000

$3,960,000

$9,620,000

$792,000

$10,412,000







C11j

$11,100,000

$7,790,000

$18,890,000

$223,000

$19,113,000







HAUL-2

$1,760,000

$1,230,000

$2,990,000

$0

$2,990,000





Groundwater

WT01

$30,200

$32,300

$62,500

$22,900

$85,400

OSB120

BLM Polygon

Floodplain sediments

C01b

$6,480,000

$4,540,000

$11,020,000

$0

$11,020,000







C08a

$8,500,000

$5,950,000

$14,450,000

$1,190,000

$15,640,000







C14c

$41,600,000

$29,100,000

$70,700,000

$1,250,000

$71,950,000







C15b

$12,700,000

$8,890,000

$21,590,000

$254,000

$21,844,000







HAUL-2

$2,640,000

$1,840,000

$4,480,000

$0

$4,480,000





Groundwater

WT01

$402,000

$430,000

$832,000

$609,000

$1,441,000

POL015

BLM Polygon

Upland waste rock

C02a

$27,000

$18,900

$45,900

$3,510

$49,410

POL016

BLM Polygon

Upland waste rock

C02a

$25,300

$17,700

$43,000

$3,290

$46,290

POL017

BLM Polygon

Upland waste rock

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

POL018

BLM Polygon

Upland waste rock (erosion potential)

C01

$94,200

$65,900

$160,100

$0

$160,100







C08a

$389,000

$273,000

$662,000

$54,500

$716,500







HAUL-2

$121,000

$84,500

$205,500

$0

$205,500

POL019

BLM Polygon

Upland waste rock (erosion potential)

C01

$856,000

$599,000

$1,455,000

$0

$1,455,000







C08a

$3,540,000

$2,480,000

$6,020,000

$496,000

$6,516,000







HAUL-2

$1,100,000

$769,000

$1,869,000

$0

$1,869,000

POL020

BLM Polygon

Upland waste rock

C02a

$16,000

$11,200

$27,200

$2,080

$29,280

POL021

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

POL029

BLM Polygon

Upland waste rock

C02a

$13,500

$9,440

$22,940

$1,750

$24,690

POL030

BLM Polygon

Upland waste rock

C02a

$40,500

$28,300

$68,800

$5,260

$74,060

Page 16 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

POL031

BLM Polygon

Upland waste rock

C02a

$36,200

$25,400

$61,600

$4,710

$66,310

POL032

BLM Polygon

Upland waste rock

C02a

$19,400

$13,600

$33,000

$2,520

$35,520

POL033

BLM Polygon

Upland waste rock

C02a

$19,400

$13,600

$33,000

$2,520

$35,520

POL034

BLM Polygon

Upland waste rock

C02a

$69,100

$48,400

$117,500

$8,990

$126,490

POL035

BLM Polygon

Upland waste rock

C02a

$165,000

$116,000

$281,000

$21,500

$302,500

POL055

BLM Polygon

Upland waste rock

C02a

$37,900

$26,600

$64,500

$4,930

$69,430

POL057

BLM Polygon

Upland waste rock

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

POL058

BLM Polygon

Upland waste rock

C02a

$19,400

$13,600

$33,000

$2,520

$35,520

POL059

BLM Polygon

Upland waste rock

C02a

$22,800

$15,900

$38,700

$2,960

$41,660

POL060

BLM Polygon

Upland waste rock

C02a

$17,700

$12,400

$30,100

$2,300

$32,400

POL061

BLM Polygon

Upland waste rock

C02a

$32,000

$22,400

$54,400

$4,160

$58,560

POL064

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

POL065

BLM Polygon

Upland waste rock

C02a

$17,700

$12,400

$30,100

$2,300

$32,400

POL077

BLM Polygon

Upland waste rock

C02a

$16,900

$11,800

$28,700

$2,190

$30,890

POL078

BLM Polygon

Upland waste rock

C02a

$13,500

$9,440

$22,940

$1,750

$24,690

POL079

BLM Polygon

Upland waste rock

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

POL080

BLM Polygon

Upland waste rock

C02a

$13,500

$9,440

$22,940

$1,750

$24,690

POL081

BLM Polygon

Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

POL082

BLM Polygon

Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

POL083

BLM Polygon

Upland waste rock

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

POL084

BLM Polygon

Upland waste rock

C02a

$13,500

$9,440

$22,940

$1,750

$24,690

POL085

BLM Polygon

Upland waste rock

C02a

$11,800

$8,260

$20,060

$1,530

$21,590

POL086

BLM Polygon

Upland waste rock

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

POL087

BLM Polygon

Upland waste rock

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

POL088

BLM Polygon

Upland waste rock

C02a

$27,000

$18,900

$45,900

$3,510

$49,410

POL089

BLM Polygon

Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

POL090

BLM Polygon

Upland waste rock

C02a

$9,270

$6,490

$15,760

$1,210

$16,970

POL091

BLM Polygon

Upland waste rock

C02a

$16,000

$11,200

$27,200

$2,080

$29,280

POL092

BLM Polygon

Upland waste rock

C02a

$23,600

$16,500

$40,100

$3,070

$43,170

WAL001

BLM Polygon

Floodplain sediments (underlying tailings pond)

C11j

$13,400,000

$9,350,000

$22,750,000

$267,000

$23,017,000





Groundwater

WT01

$60,300

$64,500

$124,800

$18,300

$143,100





Upland tailings - active facilities

C09

$16,300,000

$11,400,000

$27,700,000

$3,260,000

$30,960,000

WAL002

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$603

$645

$1,248

$366

$1,614





Floodplain waste rock

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

WAL003

BLM Polygon

Upland waste rock

C02a

$277,000

$194,000

$471,000

$36,100

$507,100

WAL004

BLM Polygon

Floodplain sediments

C01b

$1,600,000

$1,120,000

$2,720,000

$0

$2,720,000







C08a

$2,100,000

$1,470,000

$3,570,000

$293,000

$3,863,000

Page 17 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







C14c

$25,200,000

$17,700,000

$42,900,000

$757,000

$43,657,000







C15b

$7,710,000

$5,400,000

$13,110,000

$154,000

$13,264,000







HAUL-2

$650,000

$455,000

$1,105,000

$0

$1,105,000





Groundwater

WT01

$402,000

$430,000

$832,000

$609,000

$1,441,000

WAL005

BLM Polygon

Upland waste rock

C02a

$28,700

$20,100

$48,800

$3,730

$52,530

WAL014

BLM Polygon

Upland waste rock (erosion potential)

C01

$167,000

$117,000

$284,000

$0

$284,000







C08a

$690,000

$483,000

$1,173,000

$96,600

$1,269,600







HAUL-2

$214,000

$150,000

$364,000

$0

$364,000

WAL016

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

WAL017

BLM Polygon

Upland waste rock

C02a

$175,000

$122,000

$297,000

$22,700

$319,700

WAL019

BLM Polygon

Upland waste rock

C02a

$24,400

$17,100

$41,500

$3,180

$44,680

WAL020

BLM Polygon

Upland waste rock (erosion potential)

C01

$595,000

$416,000

$1,011,000

$0

$1,011,000







C08a

$2,460,000

$1,720,000

$4,180,000

$344,000

$4,524,000







HAUL-2

$763,000

$534,000

$1,297,000

$0

$1,297,000

WAL021

BLM Polygon

Upland waste rock

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

WAL022

BLM Polygon

Upland waste rock

C02a

$11,000

$7,670

$18,670

$1,420

$20,090

WAL023

BLM Polygon

Upland waste rock

C02a

$13,500

$9,440

$22,940

$1,750

$24,690

WAL024

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

WAL025

BLM Polygon

Upland waste rock

C02a

$16,900

$11,800

$28,700

$2,190

$30,890

WAL026

BLM Polygon

Upland waste rock

C02a

$7,590

$5,310

$12,900

$986

$13,886

WAL027

BLM Polygon

Upland waste rock

C02a

$76,700

$53,700

$130,400

$9,970

$140,370

WAL028

BLM Polygon

Upland waste rock

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

WAL029

BLM Polygon

Upland waste rock

C02a

$30,300

$21,200

$51,500

$3,950

$55,450

WAL034

BLM Polygon

Floodplain sediments

C01b

$1,050,000

$737,000

$1,787,000

$0

$1,787,000







C08a

$1,380,000

$966,000

$2,346,000

$193,000

$2,539,000







HAUL-2

$428,000

$300,000

$728,000

$0

$728,000

WAL035

BLM Polygon

Floodplain waste rock

C01

$599,000

$419,000

$1,018,000

$0

$1,018,000







C08a

$2,480,000

$1,730,000

$4,210,000

$347,000

$4,557,000







HAUL-2

$769,000

$538,000

$1,307,000

$0

$1,307,000

WAL036

BLM Polygon

Floodplain sediments

C01b

$608,000

$425,000

$1,033,000

$0

$1,033,000







C08a

$797,000

$558,000

$1,355,000

$112,000

$1,467,000







HAUL-2

$247,000

$173,000

$420,000

$0

$420,000

WAL037

BLM Polygon

Upland tailings

C01

$51,400

$36,000

$87,400

$0

$87,400







C08a

$212,000

$149,000

$361,000

$29,700

$390,700







HAUL-2

$65,900

$46,100

$112,000

$0

$112,000

WAL046

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)

Page 18 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

WAL047

BLM Polygon

Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

WAL048

BLM Polygon

Upland waste rock

C02a

$102,000

$71,400

$173,400

$13,300

$186,700

WAL049

BLM Polygon

Upland waste rock

C02a

$95,300

$66,700

$162,000

$12,400

$174,400

WAL050

BLM Polygon

Upland waste rock

C02a

$70,800

$49,600

$120,400

$9,210

$129,610

WAL051

BLM Polygon

Upland waste rock

C02a

$54,000

$37,800

$91,800

$7,010

$98,810

WAL052

BLM Polygon

Upland waste rock

C02a

$70,800

$49,600

$120,400

$9,210

$129,610

WAL053

BLM Polygon

Upland waste rock

C02a

$27,000

$18,900

$45,900

$3,510

$49,410

WAL054

BLM Polygon

Upland waste rock

C02a

$58,200

$40,700

$98,900

$7,560

$106,460

WAL055

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

WAL056

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

WAL057

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

WAL058

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

WAL059

BLM Polygon

Upland waste rock

C02a

$35,400

$24,800

$60,200

$4,600

$64,800

WAL060

BLM Polygon

Upland waste rock

C02a

$20,200

$14,200

$34,400

$2,630

$37,030

WAL061

BLM Polygon

Upland waste rock

C02a

$32,000

$22,400

$54,400

$4,160

$58,560

WAL062

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

WAL063

BLM Polygon

Upland waste rock

C02a

$24,400

$17,100

$41,500

$3,180

$44,680

WAL064

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

WAL065

BLM Polygon

Upland waste rock

C02a

$31,200

$21,800

$53,000

$4,050

$57,050

WAL066

BLM Polygon

Upland waste rock

C02a

$27,800

$19,500

$47,300

$3,620

$50,920

WAL067

BLM Polygon

Upland waste rock

C02a

$58,200

$40,700

$98,900

$7,560

$106,460

WAL070

BLM Polygon

Upland waste rock

C02a

$59,900

$41,900

$101,800

$7,780

$109,580

WAL071

BLM Polygon

Upland waste rock

C02a

$16,900

$11,800

$28,700

$2,190

$30,890

WAL072

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

WAL073

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

WAL074

BLM Polygon

Upland waste rock

C02a

$21,900

$15,300

$37,200

$2,850

$40,050

Page 19 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

KLW061

BLM Polygon

Upland waste rock

C02b

$2,320,000

$1,620,000

$3,940,000

$301,000

$4,241,000

KLW062

BLM Polygon

Upland waste rock

C02b

$356,000

$249,000

$605,000

$46,200

$651,200

KLW070

BLM Polygon

Floodplain sediments

C01b

$126,000

$88,400

$214,400

$0

$214,400







C08a

$165,000

$116,000

$281,000

$23,200

$304,200







HAUL-2

$51,300

$35,900

$87,200

$0

$87,200

KLW071

BLM Polygon

Upland waste rock

C02b

$576,000

$403,000

$979,000

$74,900

$1,053,900

KLW095

BLM Polygon

Upland waste rock

C02b

$137,000

$95,900

$232,900

$17,800

$250,700

KLW123

BLM Polygon

Upland waste rock

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

KLW124

BLM Polygon

Upland waste rock

C02b

$61,800

$43,300

$105,100

$8,030

$113,130

KLW125

BLM Polygon

Upland waste rock

C02b

$38,400

$26,900

$65,300

$4,990

$70,290

KLW126

BLM Polygon

Upland waste rock

C02a

$21,900

$15,300

$37,200

$2,850

$40,050

KLW127

BLM Polygon

Upland waste rock

C02b

$21,700

$15,200

$36,900

$2,820

$39,720

KLW128

BLM Polygon

Upland waste rock

C02b

$212,000

$148,000

$360,000

$27,600

$387,600

MAS070

BLM Polygon

Upland waste rock

C02a

$33,700

$23,600

$57,300

$4,380

$61,680

MG02-10

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$15,100

$10,500

$25,600

$4,520

$30,120







CD-AVG

$12,400

$8,650

$21,050

$3,710

$24,760







FP/RP-AVG

$16,600

$11,600

$28,200

$2,980

$31,180







VBS-AVG

$6,420

$4,500

$10,920

$1,930

$12,850

MG02-11

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$13,300

$9,330

$22,630

$4,000

$26,630







CD-AVG

$10,300

$7,210

$17,510

$3,090

$20,600







FP/RP-AVG

$14,600

$10,200

$24,800

$2,630

$27,430







VBS-AVG

$5,680

$3,980

$9,660

$1,700

$11,360

MG02-12

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$9,410

$6,590

$16,000

$2,820

$18,820







CD-AVG

$2,060

$1,440

$3,500

$618

$4,118







FP/RP-AVG

$6,200

$4,340

$10,540

$1,120

$11,660







VBS-AVG

$1,200

$842

$2,042

$361

$2,403

KLE007

BLM Polygon

Upland waste rock

C02b

$104,000

$72,500

$176,500

$13,500

$190,000

KLE061

BLM Polygon

Floodplain waste rock

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

MC01-2

Bioengineering Reach

BioReach Current Deflector Frequency

CD-SED

$7,480

$5,240

$12,720

$44,900

$57,620





BioReach General Characteristics

BSBR-AVG

$187,000

$131,000

$318,000

$56,000

$374,000







CD-AVG

$70,000

$49,000

$119,000

$21,000

$140,000







FP/RP-AVG

$154,000

$108,000

$262,000

$27,700

$289,700







VBS-AVG

$79,600

$55,700

$135,300

$23,900

$159,200

KLE008

BLM Polygon

Upland waste rock (erosion potential)

C02b

$109,000

$76,000

$185,000

$14,100

$199,100

KLE009

BLM Polygon

Upland waste rock

C02a

$116,000

$81,400

$197,400

$15,100

$212,500

KLE013

BLM Polygon

Upland waste rock

C02b

$88,500

$62,000

$150,500

$11,500

$162,000

KLE014

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

KLE041

BLM Polygon

Floodplain sediments

C01b

$44,600

$31,200

$75,800

$0

$75,800

MIDGradSeg02

MoonCrkSegOl

MoonCrkSeg02

Page 20 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

TCD

2009 Total
Direct Capital
Cost

2009 Indirect
Capital Cost

2009 Total
Direct and
Indirect Capital
Cost

O&M Cost (30-
Year NPV)

Total Cost (30-
Year NPV)

C08a
HAUL-2

$58,400
$18,100

$40,900
$12,700

$99,300
$30,800

$8,180
$0

C02b

$25,100

$17,500

$42,600

$3,260

C02b

$21,700

$15,200

$36,900

$2,820

C02b

$38,400

$26,900

$65,300

$4,990

BSBR-AVG
CD-AVG
FP/RP-AVG
VBS-AVG

$163,000
$138,000
$447,000
$69,400

$114,000
$96,600
$313,000
$48,600

$277,000
$234,600
$760,000
$118,000

$48,800
$41,400
$80,500
$20,800

BSBR-AVG
CD-AVG
FP/RP-AVG
VBS-AVG

$136,000
$57,700
$225,000
$58,100

$95,400
$40,400
$157,000
$40,700

$231,400
$98,100
$382,000
$98,800

$40,900
$17,300
$40,400
$17,400

BSBR-AVG
CD-AVG
FP/RP-AVG
VBS-AVG

$70,800
$59,700
$194,000
$45,200

$49,500
$41,800
$136,000
$31,600

$120,300
$101,500
$330,000
$76,800

$21,200
$17,900
$34,900
$13,600

$107,480
$30,800

$45,860

$39,720

$70,290

$325,800
$276,000
$840,500
$138,800

$272,300
$115,400
$422,400
$116,200

$141,500
$119,400
$364,900
$90,400

PIPE-1

$1,560,000

$1,090,000

$2,650,000

$125,000

$2,775,000

C10
WT02

$9,680
$493,000

$6,780
$345,000

$16,460
$838,000

$1,740
$1,190,000

C02a

$153,000

$107,000

$260,000

$19,800

C01
C07

$17,100
$58,800

$12,000
$41,200

$29,100
$100,000

$0
$12,900

C01
C07

$2,960,000
$10,200,000

$2,070,000
$7,120,000

$5,030,000
$17,320,000

$0

$2,240,000

C02a

$96,100

$67,300

$163,400

$12,500

C10
WT02

$9,680
$493,000

$6,780
$345,000

$16,460
$838,000

$1,740
$1,190,000

C02a

$51,400

$36,000

$87,400

$6,680

C02a

$35,400

$24,800

$60,200

$4,600

C02a

$27,000

$18,900

$45,900

$3,510

C02a

$22,800

$15,900

$38,700

$2,960

C01b
C08a
HAUL-2

$135,000
$177,000
$54,900

$94,500
$124,000
$38,400

$229,500
$301,000
$93,300

$0
$24,800
$0

BSBR-AVG
CD-AVG
FP/RP-AVG
VBS-AVG

$489,000
$82,400
$269,000
$209,000

$343,000
$57,700
$188,000
$146,000

$832,000
$140,100
$457,000
$355,000

$147,000
$24,700
$48,400
$62,600

$18,200
$2,028,000

$279,800

$29,100
$112,900

$5,030,000
$19,560,000

$175,900

$18,200
$2,028,000

$94,080

$64,800

$49,410

$41,660

$229,500
$325,800
$93,300

$979,000
$164,800
$505,400
$417,600

C10
WT03

$9,680
$211,000

$6,780
$148,000

$16,460
$359,000

$1,740
$549,000

C01

$963,000

$674,000

$1,637,000

$0

$18,200
$908,000

$1,637,000

Segment ID

Trait Description
Source ID Source Type Description (Waste Types)

KLE063

MC02-2

BLM Polygon

KLE064 BLM Polygon

KLE065 BLM Polygon

Bioengineering Reach

Upland waste rock (erosion potential)

Upland waste rock (erosion potential)

Upland waste rock (erosion potential)

BioReach General Characteristics

MC02-3

Bioengineering Reach

BioReach General Characteristics

MC02-4

Bioengineering Reach

BioReach General Characteristics

NMSeg

NMSegOl

PIPENM

General Feature

BUR051 BLM Polygon

Source General Information

Adit drainage

BUR052 BLM Polygon

Upland waste rock

Upland waste rock

BUR053 BLM Polygon

Upland waste rock (erosion potential)

BUR077 BLM Polygon

BUR081 BLM Polygon

Upland waste rock

Adit drainage

BUR082 BLM Polygon

BUR083 BLM Polygon

BUR084 BLM Polygon

BUR140 BLM Polygon

Upland waste rock

Upland waste rock

Upland waste rock

Upland waste rock

Floodplain sediments

NM01-1

Bioengineering Reach

BioReach General Characteristics

NMSeg02

BUR054 BLM Polygon

Adit drainage

Upland tailings - inactive facilities

Page 21 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







C08a

$3,980,000

$2,790,000

$6,770,000

$558,000

$7,328,000







HAUL-2

$1,240,000

$865,000

$2,105,000

$0

$2,105,000





Upland waste rock (potential intermixed tailings)

C01

$321,000

$225,000

$546,000

$0

$546,000







C08a

$1,330,000

$929,000

$2,259,000

$186,000

$2,445,000







HAUL-2

$412,000

$288,000

$700,000

$0

$700,000

BUR055

BLM Polygon

Floodplain sediments

C01b

$74,300

$52,000

$126,300

$0

$126,300







C08a

$97,400

$68,100

$165,500

$13,600

$179,100







HAUL-2

$30,200

$21,100

$51,300

$0

$51,300





Upland tailings

C01

$59,900

$41,900

$101,800

$0

$101,800







C08a

$248,000

$173,000

$421,000

$34,700

$455,700







HAUL-2

$76,900

$53,800

$130,700

$0

$130,700

BUR056

BLM Polygon

Upland waste rock (potential intermixed tailings)

C01

$1,250,000

$878,000

$2,128,000

$0

$2,128,000







C08a

$5,190,000

$3,630,000

$8,820,000

$726,000

$9,546,000







HAUL-2

$1,610,000

$1,130,000

$2,740,000

$0

$2,740,000

BUR057

BLM Polygon

Upland waste rock

C02a

$76,700

$53,700

$130,400

$9,970

$140,370

BUR058

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000





Upland waste rock

C02a

$81,800

$57,200

$139,000

$10,600

$149,600

BUR059

BLM Polygon

Upland waste rock

C02a

$147,000

$103,000

$250,000

$19,100

$269,100

BUR060

BLM Polygon

Upland waste rock

C02a

$180,000

$126,000

$306,000

$23,500

$329,500

BUR061

BLM Polygon

Upland waste rock

C02a

$120,000

$83,800

$203,800

$15,600

$219,400

BUR062

BLM Polygon

Upland waste rock

C02a

$57,300

$40,100

$97,400

$7,450

$104,850

BUR170

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$453,000

$317,000

$770,000

$1,160,000

$1,930,000





Upland waste rock (potential intermixed tailings)

C01

$47,100

$33,000

$80,100

$0

$80,100







C08a

$195,000

$136,000

$331,000

$27,300

$358,300







HAUL-2

$60,400

$42,300

$102,700

$0

$102,700

BUR171

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$330,000

$231,000

$561,000

$1,060,000

$1,621,000

BUR196

BLM Polygon

Upland waste rock

C02a

$26,100

$18,300

$44,400

$3,400

$47,800

BUR197

BLM Polygon

Upland waste rock

C02a

$38,800

$27,100

$65,900

$5,040

$70,940

BUR205

BLM Polygon

Upland waste rock

C02a

$54,800

$38,400

$93,200

$7,120

$100,320

NM02-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$921,000

$645,000

$1,566,000

$276,000

$1,842,000







CD-AVG

$157,000

$110,000

$267,000

$47,000

$314,000







FP/RP-AVG

$506,000

$354,000

$860,000

$91,100

$951,100







OFFCH-AVG

$15,600

$10,900

$26,500

$2,810

$29,310







VBS-AVG

$393,000

$275,000

$668,000

$118,000

$786,000

OSB040

BLM Polygon

Floodplain sediments

C01b

$257,000

$180,000

$437,000

$0

$437,000







C08a

$336,000

$235,000

$571,000

$47,100

$618,100







HAUL-2

$104,000

$73,000

$177,000

$0

$177,000

OSB044

BLM Polygon

Floodplain sediments

C01b

$135,000

$94,500

$229,500

$0

$229,500







C08a

$177,000

$124,000

$301,000

$24,800

$325,800

Page 22 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID

NMSeg03

NMSeg04









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







HAUL-2

$54,900

$38,400

$93,300

$0

$93,300





Upland tailings (jig tailings)

C01

$1,540,000

$1,080,000

$2,620,000

$0

$2,620,000







C08a

$6,370,000

$4,460,000

$10,830,000

$892,000

$11,722,000







HAUL-2

$1,980,000

$1,380,000

$3,360,000

$0

$3,360,000





Upland waste rock

C01

$72,800

$50,900

$123,700

$0

$123,700







C08a

$301,000

$211,000

$512,000

$42,100

$554,100







HAUL-2

$93,300

$65,300

$158,600

$0

$158,600

OSB045

BLM Polygon

Upland waste rock

C02a

$70,800

$49,600

$120,400

$9,210

$129,610

OSB046

BLM Polygon

Upland waste rock

C02a

$29,500

$20,700

$50,200

$3,840

$54,040

OSB048

BLM Polygon

Upland waste rock

C02a

$12,600

$8,850

$21,450

$1,640

$23,090

OSB056

BLM Polygon

Floodplain sediments

C01b

$21,600

$15,100

$36,700

$0

$36,700







C08a

$28,300

$19,800

$48,100

$3,960

$52,060







HAUL-2

$8,780

$6,150

$14,930

$0

$14,930

OSB057

BLM Polygon

Floodplain sediments

C01b

$176,000

$123,000

$299,000

$0

$299,000







C08a

$230,000

$161,000

$391,000

$32,200

$423,200







HAUL-2

$71,400

$50,000

$121,400

$0

$121,400

OSB058

BLM Polygon

Floodplain sediments

C01b

$21,600

$15,100

$36,700

$0

$36,700







C08a

$28,300

$19,800

$48,100

$3,960

$52,060







HAUL-2

$8,780

$6,150

$14,930

$0

$14,930

OSB088

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$3,920

$4,200

$8,120

$2,970

$11,090

OSB089

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$10,600

$11,300

$21,900

$8,690

$30,590

NM03-1

Bioengineering Reach

BioReach General Characteristics

CD-AVG

$76,200

$53,400

$129,600

$22,900

$152,500







FP/RP-AVG

$621,000

$434,000

$1,055,000

$112,000

$1,167,000







OFFCH-AVG

$56,000

$39,200

$95,200

$10,100

$105,300







VBS-AVG

$241,000

$169,000

$410,000

$72,300

$482,300

OSB041

BLM Polygon

Upland waste rock

C02a

$69,100

$48,400

$117,500

$8,990

$126,490

OSB042

BLM Polygon

Upland waste rock

C02a

$16,000

$11,200

$27,200

$2,080

$29,280

OSB043

BLM Polygon

Upland waste rock

C02a

$113,000

$79,100

$192,100

$14,700

$206,800

OSB049

BLM Polygon

Upland waste rock

C02a

$46,400

$32,500

$78,900

$6,030

$84,930

OSB081

BLM Polygon

Upland waste rock

C02a

$11,800

$8,260

$20,060

$1,530

$21,590

OSB087

BLM Polygon

Upland waste rock

C02a

$8,430

$5,900

$14,330

$1,100

$15,430

NM04-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$252,000

$177,000

$429,000

$75,700

$504,700







CD-AVG

$43,300

$30,300

$73,600

$13,000

$86,600







CH REAL-1

$1,160,000

$815,000

$1,975,000

$198,000

$2,173,000







FP/RP-AVG

$194,000

$136,000

$330,000

$34,900

$364,900







OFFCH-AVG

$101,000

$70,800

$171,800

$18,200

$190,000







VBS-AVG

$108,000

$75,300

$183,300

$32,300

$215,600

NM04-2

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$87,500

$61,200

$148,700

$26,200

$174,900







CD-AVG

$14,400

$10,100

$24,500

$4,330

$28,830







CH REAL-1

$404,000

$282,000

$686,000

$68,600

$754,600

Page 23 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







FP/RP-AVG

$192,000

$135,000

$327,000

$34,600

$361,600







VBS-AVG

$37,300

$26,100

$63,400

$11,200

$74,600

NM04-3

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$677,000

$474,000

$1,151,000

$203,000

$1,354,000







CD-AVG

$115,000

$80,800

$195,800

$34,600

$230,400







CH REAL-1

$3,120,000

$2,190,000

$5,310,000

$531,000

$5,841,000







FP/RP-AVG

$893,000

$625,000

$1,518,000

$161,000

$1,679,000







VBS-AVG

$289,000

$202,000

$491,000

$86,600

$577,600

OSB031

BLM Polygon

Upland waste rock

C02a

$47,200

$33,000

$80,200

$6,140

$86,340

OSB032

BLM Polygon

Floodplain waste rock

C01

$85,600

$59,900

$145,500

$0

$145,500







C08a

$354,000

$248,000

$602,000

$49,600

$651,600







HAUL-2

$110,000

$76,900

$186,900

$0

$186,900

OSB033

BLM Polygon

Upland waste rock (erosion potential)

C01

$68,500

$47,900

$116,400

$0

$116,400







C08a

$283,000

$198,000

$481,000

$39,600

$520,600







HAUL-2

$87,800

$61,500

$149,300

$0

$149,300

OSB034

BLM Polygon

Upland waste rock

C02a

$25,300

$17,700

$43,000

$3,290

$46,290

OSB035

BLM Polygon

Upland waste rock

C02a

$41,300

$28,900

$70,200

$5,370

$75,570

OSB036

BLM Polygon

Upland waste rock

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

OSB037

BLM Polygon

Upland waste rock

C02a

$59,900

$41,900

$101,800

$7,780

$109,580

OSB038

BLM Polygon

Floodplain waste rock

C01

$133,000

$92,900

$225,900

$0

$225,900







C08a

$549,000

$384,000

$933,000

$76,800

$1,009,800







HAUL-2

$170,000

$119,000

$289,000

$0

$289,000

OSB039

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$4,100

$4,390

$8,490

$3,110

$11,600





Buildings & structures

HH-4

$1,690,000

$1,180,000

$2,870,000

$219,000

$3,089,000





Floodplain sediments

C01b

$297,000

$208,000

$505,000

$0

$505,000







C08a

$389,000

$273,000

$662,000

$54,500

$716,500







HAUL-2

$121,000

$84,500

$205,500

$0

$205,500





Upland tailings

C01

$47,100

$33,000

$80,100

$0

$80,100







C08a

$195,000

$136,000

$331,000

$27,300

$358,300







HAUL-2

$60,400

$42,300

$102,700

$0

$102,700





Upland waste rock

C02a

$991,000

$694,000

$1,685,000

$129,000

$1,814,000

OSB052

BLM Polygon

Upland tailings - inactive facilities

C01

$856,000

$599,000

$1,455,000

$0

$1,455,000







C08a

$3,540,000

$2,480,000

$6,020,000

$496,000

$6,516,000







HAUL-2

$1,100,000

$769,000

$1,869,000

$0

$1,869,000

OSB055

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$4,040

$4,320

$8,360

$3,060

$11,420





Upland waste rock

C02a

$30,300

$21,200

$51,500

$3,950

$55,450

OSB059

BLM Polygon

Floodplain sediments

C01b

$446,000

$312,000

$758,000

$0

$758,000







C08a

$584,000

$409,000

$993,000

$81,800

$1,074,800







HAUL-2

$181,000

$127,000

$308,000

$0

$308,000

OSB060

BLM Polygon

Floodplain sediments

C01b

$10,800

$7,560

$18,360

$0

$18,360







C08a

$14,200

$9,910

$24,110

$1,980

$26,090

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)

Page 24 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID

PineCrkSegOl









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







HAUL-2

$4,390

$3,070

$7,460

$0

$7,460

OSB061

BLM Polygon

Upland tailings

C01

$30,000

$21,000

$51,000

$0

$51,000







C08a

$124,000

$86,700

$210,700

$17,300

$228,000







HAUL-2

$38,400

$26,900

$65,300

$0

$65,300

OSB082

BLM Polygon

Floodplain waste rock

C01

$55,600

$38,900

$94,500

$0

$94,500







C08a

$230,000

$161,000

$391,000

$32,200

$423,200







HAUL-2

$71,400

$50,000

$121,400

$0

$121,400

OSB083

BLM Polygon

Upland waste rock

C02a

$64,900

$45,400

$110,300

$8,440

$118,740

OSB114

BLM Polygon

Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

OSB115

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

OSB116

BLM Polygon

Upland waste rock

C02a

$26,100

$18,300

$44,400

$3,400

$47,800

WAL006

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

WAL033

BLM Polygon

Floodplain sediments

C01b

$459,000

$321,000

$780,000

$0

$780,000







C08a

$602,000

$421,000

$1,023,000

$84,300

$1,107,300







HAUL-2

$187,000

$131,000

$318,000

$0

$318,000

WAL069

BLM Polygon

Upland waste rock

C02a

$20,200

$14,200

$34,400

$2,630

$37,030

WAL075

BLM Polygon

Upland waste rock

C02a

$7,590

$5,310

$12,900

$986

$13,886

WAL078

BLM Polygon

Upland waste rock

C02a

$22,800

$15,900

$38,700

$2,960

$41,660

MAS004

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$322,000

$225,000

$547,000

$1,050,000

$1,597,000





Upland waste rock

C02a

$71,700

$50,200

$121,900

$9,320

$131,220

MAS005

BLM Polygon

Upland waste rock

C02a

$24,400

$17,100

$41,500

$3,180

$44,680

MAS006

BLM Polygon

Floodplain tailings - inactive Facilities

C01

$180,000

$126,000

$306,000

$0

$306,000







C08a

$743,000

$520,000

$1,263,000

$104,000

$1,367,000







HAUL-2

$231,000

$161,000

$392,000

$0

$392,000

MAS007

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$348,000

$243,000

$591,000

$595,000

$1,186,000





Upland waste rock

C01

$205,000

$144,000

$349,000

$0

$349,000







C08a

$850,000

$595,000

$1,445,000

$119,000

$1,564,000







HAUL-2

$264,000

$184,000

$448,000

$0

$448,000

MAS008

BLM Polygon

Upland waste rock (erosion potential)

C01

$107,000

$74,900

$181,900

$0

$181,900







C08a

$443,000

$310,000

$753,000

$62,000

$815,000







HAUL-2

$137,000

$96,100

$233,100

$0

$233,100

MAS009

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$135,000

$94,400

$229,400

$527,000

$756,400





Upland waste rock (erosion potential)

C01

$31,800

$22,300

$54,100

$0

$54,100







C08a

$132,000

$92,200

$224,200

$18,400

$242,600







HAUL-2

$40,800

$28,600

$69,400

$0

$69,400

Page 25 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID







2009 Total



Direct and







Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

MAS011 BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200





WT03

$136,000

$95,300

$231,300

$527,000

$758,300

MAS012 BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200





WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000



Upland waste rock (erosion potential)

C01

$2,140

$1,500

$3,640

$0

$3,640





C08a

$8,850

$6,200

$15,050

$1,240

$16,290





HAUL-2

$2,750

$1,920

$4,670

$0

$4,670

MAS013 BLM Polygon

Upland waste rock (erosion potential)

C01

$20,100

$14,100

$34,200

$0

$34,200





C08a

$83,200

$58,200

$141,400

$11,600

$153,000





HAUL-2

$25,800

$18,100

$43,900

$0

$43,900

MAS014 BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200





WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000



Seep

WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000



Upland tailings

C01

$342

$240

$582

$0

$582





C08a

$1,420

$991

$2,411

$198

$2,609





HAUL-2

$439

$307

$746

$0

$746



Upland waste rock

C01

$131,000

$92,000

$223,000

$0

$223,000





C07

$452,000

$316,000

$768,000

$99,300

$867,300

MAS015 BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200





WT03

$152,000

$106,000

$258,000

$528,000

$786,000



Upland waste rock (erosion potential)

C01

$4,280

$3,000

$7,280

$0

$7,280





C08a

$17,700

$12,400

$30,100

$2,480

$32,580





HAUL-2

$5,490

$3,840

$9,330

$0

$9,330

MAS016 BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200





WT03

$135,000

$94,400

$229,400

$527,000

$756,400



Upland waste rock (erosion potential)

C01

$99,600

$69,700

$169,300

$0

$169,300





C08a

$412,000

$288,000

$700,000

$57,700

$757,700





HAUL-2

$128,000

$89,500

$217,500

$0

$217,500

MAS017 BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200





WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000



Upland waste rock (erosion potential)

C01

$268,000

$188,000

$456,000

$0

$456,000





C08a

$1,110,000

$776,000

$1,886,000

$155,000

$2,041,000





HAUL-2

$344,000

$241,000

$585,000

$0

$585,000

MAS018 BLM Polygon

Upland waste rock (erosion potential)

C01

$11,600

$8,090

$19,690

$0

$19,690





C08a

$47,800

$33,500

$81,300

$6,690

$87,990





HAUL-2

$14,800

$10,400

$25,200

$0

$25,200

MAS019 BLM Polygon

Floodplain waste rock

C01

$4,280

$3,000

$7,280

$0

$7,280





C08a

$17,700

$12,400

$30,100

$2,480

$32,580





HAUL-2

$5,490

$3,840

$9,330

$0

$9,330

MAS020 BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200





WT03

$391,000

$274,000

$665,000

$550,000

$1,215,000

MAS021 BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200

Page 26 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







WT02

$389,000

$272,000

$661,000

$1,140,000

$1,801,000





Upland waste rock (erosion potential)

C01

$4,280

$3,000

$7,280

$0

$7,280







C08a

$17,700

$12,400

$30,100

$2,480

$32,580







HAUL-2

$5,490

$3,840

$9,330

$0

$9,330

MAS022

BLM Polygon

Floodplain waste rock

C01

$205,000

$144,000

$349,000

$0

$349,000







C08a

$850,000

$595,000

$1,445,000

$119,000

$1,564,000







HAUL-2

$264,000

$184,000

$448,000

$0

$448,000

MAS023

BLM Polygon

Upland waste rock (erosion potential)

C01

$4,280

$3,000

$7,280

$0

$7,280







C08a

$17,700

$12,400

$30,100

$2,480

$32,580







HAUL-2

$5,490

$3,840

$9,330

$0

$9,330

MAS025

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$714,000

$500,000

$1,214,000

$661,000

$1,875,000

MAS025

BLM Polygon

Floodplain waste rock (intermixed tailings)

C01

$150,000

$105,000

$255,000

$0

$255,000







C08a

$620,000

$434,000

$1,054,000

$86,700

$1,140,700







HAUL-2

$192,000

$135,000

$327,000

$0

$327,000

MAS027

BLM Polygon

Floodplain waste rock

C01

$30,000

$21,000

$51,000

$0

$51,000







C08a

$124,000

$86,700

$210,700

$17,300

$228,000







HAUL-2

$38,400

$26,900

$65,300

$0

$65,300

MAS028

BLM Polygon

Upland waste rock (erosion potential)

C01

$46,200

$32,400

$78,600

$0

$78,600







C08a

$191,000

$134,000

$325,000

$26,800

$351,800







HAUL-2

$59,300

$41,500

$100,800

$0

$100,800





Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$139,000

$97,000

$236,000

$528,000

$764,000

MAS029

BLM Polygon

Upland waste rock (intermixed tailings)

C01

$3,000

$2,100

$5,100

$0

$5,100







C08a

$12,400

$8,670

$21,070

$1,730

$22,800







HAUL-2

$3,840

$2,690

$6,530

$0

$6,530

MAS030

BLM Polygon

Upland waste rock (erosion potential)

C01

$28,800

$20,100

$48,900

$0

$48,900







C08a

$119,000

$83,300

$202,300

$16,700

$219,000







HAUL-2

$36,900

$25,800

$62,700

$0

$62,700

MAS031

BLM Polygon

Upland waste rock (erosion potential)

C01

$18,500

$12,900

$31,400

$0

$31,400







C08a

$76,500

$53,500

$130,000

$10,700

$140,700







HAUL-2

$23,700

$16,600

$40,300

$0

$40,300

MAS032

BLM Polygon

Upland waste rock (erosion potential)

C01

$342

$240

$582

$0

$582







C08a

$1,420

$991

$2,411

$198

$2,609







HAUL-2

$439

$307

$746

$0

$746

MAS033

BLM Polygon

Upland waste rock (erosion potential)

C01

$20,500

$14,400

$34,900

$0

$34,900







C08a

$85,000

$59,500

$144,500

$11,900

$156,400







HAUL-2

$26,400

$18,400

$44,800

$0

$44,800

MAS034

BLM Polygon

Upland waste rock

C02a

$12,600

$8,850

$21,450

$1,640

$23,090

MAS035

BLM Polygon

Upland waste rock (erosion potential)

C01

$34,200

$24,000

$58,200

$0

$58,200







C08a

$142,000

$99,100

$241,100

$19,800

$260,900







HAUL-2

$43,900

$30,700

$74,600

$0

$74,600

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)

Page 27 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

MAS036

BLM Polygon

Floodplain tailings

C01

$11,600

$8,090

$19,690

$0

$19,690







C08a

$47,800

$33,500

$81,300

$6,690

$87,990







HAUL-2

$14,800

$10,400

$25,200

$0

$25,200

MAS040

BLM Polygon

Floodplain sediments

C01b

$18,600

$13,000

$31,600

$0

$31,600







C08a

$24,400

$17,100

$41,500

$3,420

$44,920







HAUL-2

$7,580

$5,300

$12,880

$0

$12,880

MAS041

BLM Polygon

Floodplain sediments

C01b

$31,600

$22,100

$53,700

$0

$53,700







C08a

$41,400

$29,000

$70,400

$5,800

$76,200







HAUL-2

$12,800

$8,990

$21,790

$0

$21,790

MAS042

BLM Polygon

Floodplain sediments

C01b

$14,600

$10,200

$24,800

$0

$24,800







C08a

$19,100

$13,400

$32,500

$2,680

$35,180







HAUL-2

$5,930

$4,150

$10,080

$0

$10,080

MAS043

BLM Polygon

Floodplain sediments

C01b

$40,500

$28,400

$68,900

$0

$68,900







C08a

$53,100

$37,200

$90,300

$7,430

$97,730







HAUL-2

$16,500

$11,500

$28,000

$0

$28,000

MAS045

BLM Polygon

Floodplain sediments

C01b

$40,500

$28,400

$68,900

$0

$68,900







C08a

$53,100

$37,200

$90,300

$7,430

$97,730







HAUL-2

$16,500

$11,500

$28,000

$0

$28,000

MAS046

BLM Polygon

Floodplain sediments

C01b

$322,000

$225,000

$547,000

$0

$547,000







C08a

$422,000

$296,000

$718,000

$59,100

$777,100







HAUL-2

$131,000

$91,700

$222,700

$0

$222,700

MAS048

BLM Polygon

Floodplain tailings

C01

$21,200

$14,800

$36,000

$0

$36,000







C08a

$87,600

$61,300

$148,900

$12,300

$161,200







HAUL-2

$27,200

$19,000

$46,200

$0

$46,200





Upland tailings

C01

$69,800

$48,900

$118,700

$0

$118,700







C08a

$289,000

$202,000

$491,000

$40,400

$531,400







HAUL-2

$89,600

$62,700

$152,300

$0

$152,300

MAS049

BLM Polygon

Floodplain tailings

C01

$154,000

$108,000

$262,000

$0

$262,000







C08a

$637,000

$446,000

$1,083,000

$89,200

$1,172,200







HAUL-2

$198,000

$138,000

$336,000

$0

$336,000

MAS050

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$374,000

$261,000

$635,000

$1,150,000

$1,785,000





Floodplain waste rock (intermixed tailings)

C01

$91,600

$64,100

$155,700

$0

$155,700







C08a

$379,000

$265,000

$644,000

$53,000

$697,000







HAUL-2

$117,000

$82,200

$199,200

$0

$199,200

MAS051

BLM Polygon

Upland waste rock

C02b

$38,400

$26,900

$65,300

$4,990

$70,290

MAS052

BLM Polygon

Upland waste rock (erosion potential)

C01

$22,600

$15,800

$38,400

$0

$38,400







C08a

$93,500

$65,400

$158,900

$13,100

$172,000







HAUL-2

$29,000

$20,300

$49,300

$0

$49,300

MAS053

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

Page 28 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

MAS054

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$184,000

$129,000

$313,000

$538,000

$851,000





Floodplain waste rock

C01

$45,200

$31,600

$76,800

$0

$76,800







C08a

$187,000

$131,000

$318,000

$26,200

$344,200







HAUL-2

$58,000

$40,600

$98,600

$0

$98,600

MAS055

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

MAS056

BLM Polygon

Upland waste rock

C02b

$31,700

$22,200

$53,900

$4,120

$58,020

MAS057

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

MAS058

BLM Polygon

Upland waste rock

C02a

$25,300

$17,700

$43,000

$3,290

$46,290

MAS059

BLM Polygon

Upland waste rock

C02a

$23,600

$16,500

$40,100

$3,070

$43,170

MAS060

BLM Polygon

Upland waste rock

C02b

$45,100

$31,600

$76,700

$5,860

$82,560

MAS061

BLM Polygon

Upland waste rock

C02a

$26,100

$18,300

$44,400

$3,400

$47,800

MAS062

BLM Polygon

Upland waste rock

C02b

$38,400

$26,900

$65,300

$4,990

$70,290

MAS063

BLM Polygon

Upland waste rock

C02a

$12,600

$8,850

$21,450

$1,640

$23,090

MAS065

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

MAS067

BLM Polygon

Upland waste rock

C02a

$30,300

$21,200

$51,500

$3,950

$55,450

MAS068

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

MAS069

BLM Polygon

Upland waste rock

C02a

$159,000

$112,000

$271,000

$20,700

$291,700

MAS072

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

MAS075

BLM Polygon

Upland waste rock

C02a

$16,000

$11,200

$27,200

$2,080

$29,280

MAS076

BLM Polygon

Upland waste rock

C02a

$37,900

$26,600

$64,500

$4,930

$69,430

MAS077

BLM Polygon

Upland waste rock

C02a

$91,900

$64,300

$156,200

$11,900

$168,100

MAS078

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$354,000

$247,000

$601,000

$578,000

$1,179,000

MAS079

BLM Polygon

Floodplain waste rock

C01

$160,000

$112,000

$272,000

$0

$272,000

MAS079

BLM Polygon

Floodplain waste rock

C08a

$660,000

$462,000

$1,122,000

$92,400

$1,214,400







HAUL-2

$205,000

$143,000

$348,000

$0

$348,000

MAS080

BLM Polygon

Upland waste rock

C02a

$36,200

$25,400

$61,600

$4,710

$66,310

MAS081

BLM Polygon

Floodplain waste rock

C02a

$177,000

$124,000

$301,000

$23,000

$324,000

MAS082

BLM Polygon

Upland waste rock

C02b

$104,000

$72,500

$176,500

$13,500

$190,000

MAS083

BLM Polygon

Upland tailings

C01

$34,900

$24,400

$59,300

$0

$59,300







C08a

$144,000

$101,000

$245,000

$20,200

$265,200

Page 29 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID

PineCrkSeg02









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







HAUL-2

$44,700

$31,300

$76,000

$0

$76,000





Upland waste rock

C01

$124,000

$86,900

$210,900

$0

$210,900







C08a

$513,000

$359,000

$872,000

$71,900

$943,900







HAUL-2

$159,000

$111,000

$270,000

$0

$270,000

MAS084

BLM Polygon

Floodplain tailings

C01

$128,000

$89,900

$217,900

$0

$217,900







C08a

$531,000

$372,000

$903,000

$74,300

$977,300







HAUL-2

$165,000

$115,000

$280,000

$0

$280,000

TWI001

BLM Polygon

Upland waste rock

C02a

$47,200

$33,000

$80,200

$6,140

$86,340

TWI002

BLM Polygon

Floodplain waste rock

C01

$24,700

$17,300

$42,000

$0

$42,000







C08a

$102,000

$71,400

$173,400

$14,300

$187,700







HAUL-2

$31,600

$22,100

$53,700

$0

$53,700

TWI003

BLM Polygon

Upland waste rock

C02a

$13,500

$9,440

$22,940

$1,750

$24,690

TWI004

BLM Polygon

Upland waste rock

C02a

$19,400

$13,600

$33,000

$2,520

$35,520

TWI005

BLM Polygon

Upland waste rock

C02a

$25,300

$17,700

$43,000

$3,290

$46,290

TWI006

BLM Polygon

Upland waste rock (erosion potential)

C01

$20,500

$14,400

$34,900

$0

$34,900







C08a

$85,000

$59,500

$144,500

$11,900

$156,400







HAUL-2

$26,400

$18,400

$44,800

$0

$44,800

TWI007

BLM Polygon

Upland waste rock

C02b

$41,800

$29,200

$71,000

$5,430

$76,430

TWI008

BLM Polygon

Floodplain waste rock

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

TWI009

BLM Polygon

Floodplain waste rock

C01

$27,700

$19,400

$47,100

$0

$47,100







C08a

$115,000

$80,300

$195,300

$16,100

$211,400







HAUL-2

$35,600

$24,900

$60,500

$0

$60,500

TWI010

BLM Polygon

Upland waste rock

C02b

$55,100

$38,600

$93,700

$7,160

$100,860

TWI011

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

TWI012

BLM Polygon

Floodplain waste rock

C01

$16,400

$11,500

$27,900

$0

$27,900







C08a

$68,000

$47,600

$115,600

$9,520

$125,120







HAUL-2

$21,100

$14,800

$35,900

$0

$35,900

TWI013

BLM Polygon

Upland waste rock

C01

$32,900

$23,000

$55,900

$0

$55,900







C08a

$136,000

$95,200

$231,200

$19,000

$250,200







HAUL-2

$42,200

$29,500

$71,700

$0

$71,700

TWI014

BLM Polygon

Floodplain waste rock

C01

$25,700

$18,000

$43,700

$0

$43,700







C08a

$106,000

$74,300

$180,300

$14,900

$195,200







HAUL-2

$32,900

$23,100

$56,000

$0

$56,000

TWI015

BLM Polygon

Upland waste rock

C02b

$53,400

$37,400

$90,800

$6,950

$97,750

TWI016

BLM Polygon

Upland waste rock

C02b

$41,800

$29,200

$71,000

$5,430

$76,430

TWI017

BLM Polygon

Upland waste rock

C02a

$22,800

$15,900

$38,700

$2,960

$41,660

TWI018

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516

Page 30 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







HAUL-2

$1,100

$769

$1,869

$0

$1,869

TWI019

BLM Polygon

Upland waste rock

C02b

$55,100

$38,600

$93,700

$7,160

$100,860

TWI020

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

TWI021

BLM Polygon

Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

TWI022

BLM Polygon

Upland waste rock

C02a

$61,500

$43,100

$104,600

$8,000

$112,600

TWI023

BLM Polygon

Upland waste rock

C02a

$42,200

$29,500

$71,700

$5,480

$77,180

TWI024

BLM Polygon

Upland waste rock

C02a

$35,400

$24,800

$60,200

$4,600

$64,800

TWI025

BLM Polygon

Upland waste rock

C02a

$25,300

$17,700

$43,000

$3,290

$46,290

TWI026

BLM Polygon

Upland waste rock

C02a

$116,000

$81,400

$197,400

$15,100

$212,500

TWI027

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

TWI028

BLM Polygon

Upland waste rock

C02b

$30,100

$21,000

$51,100

$3,910

$55,010

TWI029

BLM Polygon

Upland waste rock

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

TWI030

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

KLW072

BLM Polygon

Upland waste rock

C02a

$87,700

$61,400

$149,100

$11,400

$160,500

KLW073

BLM Polygon

Upland waste rock

C01

$36,000

$25,200

$61,200

$0

$61,200







C08a

$149,000

$104,000

$253,000

$20,800

$273,800







HAUL-2

$46,100

$32,300

$78,400

$0

$78,400

KLW075

BLM Polygon

Floodplain waste rock

C01

$72,900

$51,100

$124,000

$0

$124,000







C08a

$302,000

$211,000

$513,000

$42,200

$555,200







HAUL-2

$93,500

$65,500

$159,000

$0

$159,000

KLW077

BLM Polygon

Floodplain waste rock

C01

$47,300

$33,100

$80,400

$0

$80,400







C08a

$195,000

$137,000

$332,000

$27,400

$359,400







HAUL-2

$60,600

$42,400

$103,000

$0

$103,000

KLW079

BLM Polygon

Floodplain waste rock

C01

$41,100

$28,800

$69,900

$0

$69,900







C08a

$170,000

$119,000

$289,000

$23,800

$312,800







HAUL-2

$52,700

$36,900

$89,600

$0

$89,600

KLW080

BLM Polygon

Upland waste rock

C01

$30,800

$21,600

$52,400

$0

$52,400







C07

$106,000

$74,100

$180,100

$23,300

$203,400

KLW081

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$156,000

$109,000

$265,000

$532,000

$797,000

KLW082

BLM Polygon

Floodplain waste rock

C01

$34,900

$24,400

$59,300

$0

$59,300







C08a

$144,000

$101,000

$245,000

$20,200

$265,200







HAUL-2

$44,800

$31,400

$76,200

$0

$76,200

KLW083

BLM Polygon

Floodplain waste rock

C01

$59,600

$41,700

$101,300

$0

$101,300

PineCrkSeg03

Page 31 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site













2009 Total













2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







C08a

$246,000

$172,000

$418,000

$34,500

$452,500







HAUL-2

$76,400

$53,500

$129,900

$0

$129,900

KLW084

BLM Polygon

Upland waste rock

C02a

$28,700

$20,100

$48,800

$3,730

$52,530

KLW085

BLM Polygon

Floodplain waste rock

C01

$61,600

$43,100

$104,700

$0

$104,700







C08a

$255,000

$178,000

$433,000

$35,700

$468,700







HAUL-2

$79,100

$55,300

$134,400

$0

$134,400

MAS001

BLM Polygon

Upland waste rock

C02a

$91,000

$63,700

$154,700

$11,800

$166,500

MAS003

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$152,000

$106,000

$258,000

$532,000

$790,000





Upland waste rock (intermixed tailings)

C06

$314,000

$220,000

$534,000

$72,200

$606,200

MAS064

BLM Polygon

Upland waste rock

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

MAS066

BLM Polygon

Upland waste rock

C01

$856

$599

$1,455

$0

$1,455







C08a

$3,540

$2,480

$6,020

$496

$6,516







HAUL-2

$1,100

$769

$1,869

$0

$1,869

PC03-1

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$248,000

$174,000

$422,000

$74,400

$496,400







CD-AVG

$84,500

$59,100

$143,600

$25,300

$168,900







FP/RP-AVG

$313,000

$219,000

$532,000

$56,300

$588,300







OFFCH-AVG

$792,000

$554,000

$1,346,000

$143,000

$1,489,000







VBS-AVG

$106,000

$74,000

$180,000

$31,700

$211,700

PC03-2

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$201,000

$141,000

$342,000

$60,400

$402,400







CD-AVG

$45,300

$31,700

$77,000

$13,600

$90,600







FP/RP-AVG

$265,000

$186,000

$451,000

$47,800

$498,800







OFFCH-AVG

$679,000

$475,000

$1,154,000

$122,000

$1,276,000







VBS-AVG

$85,700

$60,000

$145,700

$25,700

$171,400

PC03-3

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$122,000

$85,400

$207,400

$36,600

$244,000







CD-AVG

$20,600

$14,400

$35,000

$6,180

$41,180







FP/RP-AVG

$381,000

$267,000

$648,000

$68,600

$716,600







VBS-AVG

$52,000

$36,400

$88,400

$15,600

$104,000

UpperSFCDRSeg PIPEUG

General Feature

Source General Information

PIPE-1

$332,000

$232,000

$564,000

$26,600

$590,600







PIPE-2

$12,900

$9,050

$21,950

$1,030

$22,980







PIPE-3

$6,420,000

$4,490,000

$10,910,000

$513,000

$11,423,000







PIPE-4

$5,080,000

$3,560,000

$8,640,000

$406,000

$9,046,000

UpperSFCDRSegOl BUR136

BLM Polygon

Upland waste rock

C02a

$25,300

$17,700

$43,000

$3,290

$46,290

BUR137

BLM Polygon

Upland waste rock

C02a

$27,000

$18,900

$45,900

$3,510

$49,410

LOK001

BLM Polygon

Upland waste rock (erosion potential)

C02a

$109,000

$76,100

$185,100

$14,100

$199,200

LOK002

BLM Polygon

Upland waste rock (erosion potential)

C02a

$107,000

$74,900

$181,900

$13,900

$195,800

LOK003

BLM Polygon

Upland waste rock

C02a

$20,200

$14,200

$34,400

$2,630

$37,030

LOK004

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$521,000

$365,000

$886,000

$1,210,000

$2,096,000





Floodplain waste rock

C01

$262,000

$183,000

$445,000

$0

$445,000







C08a

$1,080,000

$758,000

$1,838,000

$152,000

$1,990,000







HAUL-2

$336,000

$235,000

$571,000

$0

$571,000

Page 32 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

LOK005

BLM Polygon

Upland waste rock (erosion potential)

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

LOK006

BLM Polygon

Floodplain waste rock

C01

$26,700

$18,700

$45,400

$0

$45,400







C08a

$110,000

$77,300

$187,300

$15,500

$202,800







HAUL-2

$34,300

$24,000

$58,300

$0

$58,300

LOK007

BLM Polygon

Upland waste rock (erosion potential)

C01

$27,700

$19,400

$47,100

$0

$47,100







C07

$95,300

$66,700

$162,000

$21,000

$183,000

LOK008

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Floodplain waste rock

C01

$39,000

$27,300

$66,300

$0

$66,300







C07

$134,000

$93,800

$227,800

$29,500

$257,300

LOK009

BLM Polygon

Floodplain waste rock

C01

$94,500

$66,200

$160,700

$0

$160,700







C07

$325,000

$227,000

$552,000

$71,400

$623,400

LOK010

BLM Polygon

Floodplain waste rock

C01

$14,400

$10,100

$24,500

$0

$24,500







C08a

$59,500

$41,600

$101,100

$8,330

$109,430







HAUL-2

$18,400

$12,900

$31,300

$0

$31,300

LOK011

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$3,620,000

$3,870,000

$7,490,000

$2,630,000

$10,120,000





Floodplain waste rock

C01

$235,000

$165,000

$400,000

$0

$400,000







C07

$809,000

$566,000

$1,375,000

$178,000

$1,553,000

LOK012

BLM Polygon

Upland waste rock

C02a

$122,000

$85,600

$207,600

$15,900

$223,500

LOK013

BLM Polygon

Upland waste rock

C02a

$108,000

$75,500

$183,500

$14,000

$197,500

LOK014

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000





Upland waste rock

C02a

$40,500

$28,300

$68,800

$5,260

$74,060

LOK015

BLM Polygon

Upland waste rock

C02a

$10,100

$7,080

$17,180

$1,320

$18,500

LOK016

BLM Polygon

Upland waste rock

C02a

$69,100

$48,400

$117,500

$8,990

$126,490

LOK017

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$159,000

$111,000

$270,000

$532,000

$802,000





Floodplain waste rock

C01

$133,000

$92,900

$225,900

$0

$225,900







C08a

$549,000

$384,000

$933,000

$76,800

$1,009,800







HAUL-2

$170,000

$119,000

$289,000

$0

$289,000

LOK018

BLM Polygon

Upland waste rock

C02a

$47,200

$33,000

$80,200

$6,140

$86,340

LOK019

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$134,000

$93,900

$227,900

$527,000

$754,900





Upland waste rock

C02b

$110,000

$77,200

$187,200

$14,300

$201,500

LOK020

BLM Polygon

Upland waste rock

C02a

$45,500

$31,900

$77,400

$5,920

$83,320

LOK021

BLM Polygon

Upland waste rock

C02a

$96,100

$67,300

$163,400

$12,500

$175,900

LOK022

BLM Polygon

Upland waste rock

C02a

$124,000

$86,700

$210,700

$16,100

$226,800

LOK024

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000





Upland waste rock

C02a

$111,000

$77,900

$188,900

$14,500

$203,400

LOK025

BLM Polygon

Upland waste rock

C02a

$32,000

$22,400

$54,400

$4,160

$58,560

Page 33 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

LOK026

BLM Polygon

Upland waste rock

C02a

$28,700

$20,100

$48,800

$3,730

$52,530

LOK027

BLM Polygon

Upland waste rock

C02a

$16,000

$11,200

$27,200

$2,080

$29,280

LOK028

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000





Upland waste rock

C02a

$38,800

$27,100

$65,900

$5,040

$70,940

LOK041

BLM Polygon

Upland waste rock

C02a

$79,200

$55,500

$134,700

$10,300

$145,000

LOK044

BLM Polygon

Upland waste rock

C02b

$127,000

$88,800

$215,800

$16,500

$232,300

LOK045

BLM Polygon

Upland waste rock

C02a

$31,200

$21,800

$53,000

$4,050

$57,050

LOK047

BLM Polygon

Upland waste rock

C02a

$191,000

$133,000

$324,000

$24,800

$348,800

LOK048

BLM Polygon

Floodplain waste rock

C01

$27,700

$19,400

$47,100

$0

$47,100







C07

$95,300

$66,700

$162,000

$21,000

$183,000

LOK050

BLM Polygon

Upland tailings - inactive facilities

C01

$55,600

$38,900

$94,500

$0

$94,500







C08a

$230,000

$161,000

$391,000

$32,200

$423,200







HAUL-2

$71,400

$50,000

$121,400

$0

$121,400

LOK051

BLM Polygon

Floodplain artificial fill

C01

$196,000

$137,000

$333,000

$0

$333,000







C08a

$811,000

$568,000

$1,379,000

$114,000

$1,493,000







HAUL-2

$252,000

$176,000

$428,000

$0

$428,000

LOK052

BLM Polygon

Upland waste rock

C02a

$26,100

$18,300

$44,400

$3,400

$47,800

LOK053

BLM Polygon

Upland waste rock (erosion potential)

C02a

$26,100

$18,300

$44,400

$3,400

$47,800

LOK054

BLM Polygon

Upland waste rock

C02a

$11,000

$7,670

$18,670

$1,420

$20,090

MUL001

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$18,300

$19,600

$37,900

$13,900

$51,800





Floodplain waste rock

C01

$323,000

$226,000

$549,000

$0

$549,000







C08a

$1,330,000

$934,000

$2,264,000

$187,000

$2,451,000







HAUL-2

$414,000

$290,000

$704,000

$0

$704,000

MUL002

BLM Polygon

Upland tailings

C01

$98,400

$68,900

$167,300

$0

$167,300







C08a

$407,000

$285,000

$692,000

$57,000

$749,000







HAUL-2

$126,000

$88,400

$214,400

$0

$214,400

MUL003

BLM Polygon

Upland waste rock

C02a

$231,000

$162,000

$393,000

$30,000

$423,000

MUL004

BLM Polygon

Floodplain waste rock

C01

$84,200

$59,000

$143,200

$0

$143,200







C08a

$348,000

$244,000

$592,000

$48,800

$640,800







HAUL-2

$108,000

$75,600

$183,600

$0

$183,600

MUL005

BLM Polygon

Upland waste rock

C02a

$28,700

$20,100

$48,800

$3,730

$52,530

MUL006

BLM Polygon

Floodplain waste rock

C01

$75,000

$52,500

$127,500

$0

$127,500







C08a

$310,000

$217,000

$527,000

$43,400

$570,400







HAUL-2

$96,200

$67,300

$163,500

$0

$163,500

MUL007

BLM Polygon

Upland waste rock (erosion potential)

C02a

$80,100

$56,100

$136,200

$10,400

$146,600

MUL008

BLM Polygon

Floodplain waste rock

C01

$141,000

$98,900

$239,900

$0

$239,900







C08a

$584,000

$409,000

$993,000

$81,800

$1,074,800







HAUL-2

$181,000

$127,000

$308,000

$0

$308,000

MUL009

BLM Polygon

Upland waste rock (erosion potential)

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

MUL010

BLM Polygon

Upland waste rock

C02a

$27,000

$18,900

$45,900

$3,510

$49,410

Page 34 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

MUL011

BLM Polygon

Upland waste rock

C02a

$12,600

$8,850

$21,450

$1,640

$23,090

MUL012

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$210,000

$224,000

$434,000

$197,000

$631,000





Floodplain waste rock

C01

$924,000

$647,000

$1,571,000

$0

$1,571,000







C07

$3,180,000

$2,220,000

$5,400,000

$699,000

$6,099,000

MUL013

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$60,300

$64,500

$124,800

$45,700

$170,500





Upland waste rock (erosion potential)

C02a

$44,700

$31,300

$76,000

$5,810

$81,810

MUL014

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$1,100,000

$1,170,000

$2,270,000

$832,000

$3,102,000





Upland waste rock (erosion potential)

C01

$33,900

$23,700

$57,600

$0

$57,600







C07

$116,000

$81,500

$197,500

$25,600

$223,100

MUL015

BLM Polygon

Upland waste rock (erosion potential)

C01

$98,400

$68,900

$167,300

$0

$167,300







C07

$338,000

$237,000

$575,000

$74,400

$649,400

MUL016

BLM Polygon

Upland waste rock

C02a

$46,400

$32,500

$78,900

$6,030

$84,930

MUL017

BLM Polygon

Upland waste rock

C02a

$45,500

$31,900

$77,400

$5,920

$83,320

MUL018

BLM Polygon

Floodplain waste rock

C01

$61,600

$43,100

$104,700

$0

$104,700







C08a

$255,000

$178,000

$433,000

$35,700

$468,700







HAUL-2

$79,100

$55,300

$134,400

$0

$134,400

MUL019

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT01

$558,000

$597,000

$1,155,000

$540,000

$1,695,000





Buildings & structures

HH-4

$1,690,000

$1,180,000

$2,870,000

$219,000

$3,089,000





Floodplain tailings

C01

$364,000

$255,000

$619,000

$0

$619,000







C08a

$1,500,000

$1,050,000

$2,550,000

$211,000

$2,761,000







HAUL-2

$467,000

$327,000

$794,000

$0

$794,000





Floodplain waste rock

C01

$1,440,000

$1,010,000

$2,450,000

$0

$2,450,000







C08a

$5,950,000

$4,170,000

$10,120,000

$833,000

$10,953,000







HAUL-2

$1,850,000

$1,290,000

$3,140,000

$0

$3,140,000

MUL020

BLM Polygon

Floodplain sediments (underlying tailings pond)

C11j

$5,090,000

$3,560,000

$8,650,000

$102,000

$8,752,000





Floodplain tailings - active facilities

C09

$2,710,000

$1,900,000

$4,610,000

$543,000

$5,153,000





Groundwater

WT01

$30,200

$32,300

$62,500

$9,150

$71,650

MUL021

BLM Polygon

Floodplain waste rock

C01

$124,000

$87,000

$211,000

$0

$211,000







C08a

$514,000

$360,000

$874,000

$72,000

$946,000







HAUL-2

$159,000

$112,000

$271,000

$0

$271,000

MUL022

BLM Polygon

Upland waste rock (erosion potential)

C02a

$29,500

$20,700

$50,200

$3,840

$54,040

MUL023

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000





Floodplain waste rock

C01

$134,000

$93,500

$227,500

$0

$227,500







C08a

$552,000

$387,000

$939,000

$77,300

$1,016,300







HAUL-2

$171,000

$120,000

$291,000

$0

$291,000

MUL024

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000

Page 35 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)





Upland waste rock

C02b

$187,000

$131,000

$318,000

$24,300

$342,300

MUL025

BLM Polygon

Upland waste rock

C02a

$85,100

$59,600

$144,700

$11,100

$155,800

MUL026

BLM Polygon

Upland waste rock

C02b

$170,000

$119,000

$289,000

$22,100

$311,100

MUL027

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$221,000

$155,000

$376,000

$547,000

$923,000





Upland waste rock

C01

$102,000

$71,200

$173,200

$0

$173,200







C07

$349,000

$244,000

$593,000

$76,800

$669,800

MUL028

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$388,000

$272,000

$660,000

$600,000

$1,260,000





Floodplain waste rock

C01

$437,000

$306,000

$743,000

$0

$743,000







C07

$1,500,000

$1,050,000

$2,550,000

$330,000

$2,880,000

MUL029

BLM Polygon

Floodplain waste rock

C01

$87,300

$61,100

$148,400

$0

$148,400







C07

$300,000

$210,000

$510,000

$66,000

$576,000

MUL030

BLM Polygon

Floodplain waste rock

C01

$37,000

$25,900

$62,900

$0

$62,900







C07

$127,000

$88,900

$215,900

$27,900

$243,800

MUL031

BLM Polygon

Upland waste rock (erosion potential)

C01

$34,900

$24,400

$59,300

$0

$59,300







C07

$120,000

$84,000

$204,000

$26,400

$230,400

MUL032

BLM Polygon

Upland waste rock

C02a

$28,700

$20,100

$48,800

$3,730

$52,530

MUL033

BLM Polygon

Floodplain waste rock

C01

$67,800

$47,500

$115,300

$0

$115,300







C07

$233,000

$163,000

$396,000

$51,200

$447,200

MUL034

BLM Polygon

Upland waste rock

C02b

$73,500

$51,400

$124,900

$9,550

$134,450

MUL035

BLM Polygon

Upland waste rock

C02a

$25,300

$17,700

$43,000

$3,290

$46,290

MUL036

BLM Polygon

Upland waste rock

C02a

$23,600

$16,500

$40,100

$3,070

$43,170

MUL037

BLM Polygon

Floodplain sediments

C01b

$595,000

$417,000

$1,012,000

$0

$1,012,000







C08a

$781,000

$546,000

$1,327,000

$109,000

$1,436,000







HAUL-2

$242,000

$169,000

$411,000

$0

$411,000





Floodplain sediments (underlying tailings pond)

C11j

$5,410,000

$3,780,000

$9,190,000

$108,000

$9,298,000





Floodplain tailings - active facilities

C09

$2,470,000

$1,730,000

$4,200,000

$494,000

$4,694,000





Groundwater

WT01

$30,200

$32,300

$62,500

$9,150

$71,650

MUL038

BLM Polygon

Floodplain tailings

C01

$55,600

$38,900

$94,500

$0

$94,500







C08a

$230,000

$161,000

$391,000

$32,200

$423,200







HAUL-2

$71,400

$50,000

$121,400

$0

$121,400





Floodplain waste rock

C01

$285,000

$199,000

$484,000

$0

$484,000







C08a

$1,180,000

$824,000

$2,004,000

$165,000

$2,169,000







HAUL-2

$365,000

$255,000

$620,000

$0

$620,000

MUL040

BLM Polygon

Upland waste rock

C02a

$16,000

$11,200

$27,200

$2,080

$29,280

MUL041

BLM Polygon

Upland waste rock

C02a

$314,000

$220,000

$534,000

$40,800

$574,800

MUL042

BLM Polygon

Floodplain waste rock

C01

$59,600

$41,700

$101,300

$0

$101,300







C07

$205,000

$143,000

$348,000

$45,000

$393,000

MUL043

BLM Polygon

Floodplain waste rock

C01

$75,000

$52,500

$127,500

$0

$127,500







C07

$258,000

$180,000

$438,000

$56,700

$494,700

MUL045

BLM Polygon

Floodplain waste rock

C01

$118,000

$82,700

$200,700

$0

$200,700

Page 36 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)







C07

$406,000

$284,000

$690,000

$89,300

$779,300

MUL046

BLM Polygon

Upland waste rock

C02a

$29,500

$20,700

$50,200

$3,840

$54,040

MUL047

BLM Polygon

Floodplain waste rock

C01

$23,600

$16,500

$40,100

$0

$40,100







C07

$81,100

$56,800

$137,900

$17,900

$155,800

MUL048

BLM Polygon

Floodplain waste rock

C01

$91,400

$64,000

$155,400

$0

$155,400







C08a

$378,000

$265,000

$643,000

$52,900

$695,900







HAUL-2

$117,000

$82,100

$199,100

$0

$199,100

MUL049

BLM Polygon

Upland waste rock (erosion potential)

C02a

$25,300

$17,700

$43,000

$3,290

$46,290

MUL050

BLM Polygon

Upland waste rock

C02a

$31,200

$21,800

$53,000

$4,050

$57,050

MUL051

BLM Polygon

Floodplain waste rock

C01

$123,000

$86,300

$209,300

$0

$209,300







C07

$423,000

$296,000

$719,000

$93,100

$812,100

MUL052

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$390,000

$273,000

$663,000

$1,160,000

$1,823,000





Floodplain waste rock

C01

$64,200

$44,900

$109,100

$0

$109,100







C07

$221,000

$154,000

$375,000

$48,500

$423,500

MUL053

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$667,000

$467,000

$1,134,000

$1,330,000

$2,464,000





Upland waste rock (erosion potential)

C01

$312,000

$219,000

$531,000

$0

$531,000







C07

$1,070,000

$751,000

$1,821,000

$236,000

$2,057,000

MUL054

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$173,000

$121,000

$294,000

$536,000

$830,000





Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

MUL055

BLM Polygon

Upland waste rock

C02a

$220,000

$154,000

$374,000

$28,600

$402,600

MUL056

BLM Polygon

Upland waste rock (erosion potential)

C02a

$29,500

$20,700

$50,200

$3,840

$54,040

MUL057

BLM Polygon

Upland waste rock (erosion potential)

C02a

$66,600

$46,600

$113,200

$8,660

$121,860

MUL058

BLM Polygon

Floodplain sediments

C01b

$1,890,000

$1,320,000

$3,210,000

$0

$3,210,000







C08a

$2,480,000

$1,730,000

$4,210,000

$347,000

$4,557,000







HAUL-2

$769,000

$538,000

$1,307,000

$0

$1,307,000





Floodplain sediments (underlying tailings pond)

C11j

$9,700,000

$6,790,000

$16,490,000

$194,000

$16,684,000





Floodplain tailings - active facilities

C09

$8,540,000

$5,980,000

$14,520,000

$1,710,000

$16,230,000





Groundwater

WT01

$30,200

$32,300

$62,500

$9,150

$71,650

MUL059

BLM Polygon

Floodplain waste rock

C01

$96,600

$67,600

$164,200

$0

$164,200







C08a

$399,000

$280,000

$679,000

$55,900

$734,900







HAUL-2

$124,000

$86,700

$210,700

$0

$210,700

MUL060

BLM Polygon

Floodplain waste rock

C01

$21,600

$15,100

$36,700

$0

$36,700







C08a

$89,200

$62,400

$151,600

$12,500

$164,100







HAUL-2

$27,700

$19,400

$47,100

$0

$47,100

MUL061

BLM Polygon

Upland waste rock

C02a

$29,500

$20,700

$50,200

$3,840

$54,040

MUL062

BLM Polygon

Upland waste rock

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

MUL063

BLM Polygon

Floodplain waste rock

C01

$21,600

$15,100

$36,700

$0

$36,700







C08a

$89,200

$62,400

$151,600

$12,500

$164,100

Page 37 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







HAUL-2

$27,700

$19,400

$47,100

$0

$47,100

MUL064

BLM Polygon

Upland waste rock

C02a

$47,200

$33,000

$80,200

$6,140

$86,340

MUL065

BLM Polygon

Floodplain waste rock

C01

$31,800

$22,300

$54,100

$0

$54,100







C08a

$132,000

$92,200

$224,200

$18,400

$242,600







HAUL-2

$40,800

$28,600

$69,400

$0

$69,400

MUL066

BLM Polygon

Upland waste rock

C02a

$79,200

$55,500

$134,700

$10,300

$145,000

MUL067

BLM Polygon

Upland waste rock

C02a

$113,000

$79,100

$192,100

$14,700

$206,800

MUL068

BLM Polygon

Upland waste rock

C02a

$30,300

$21,200

$51,500

$3,950

$55,450

MUL069

BLM Polygon

Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

MUL071

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200





Floodplain waste rock

C01

$10,700

$7,490

$18,190

$0

$18,190







C08a

$44,300

$31,000

$75,300

$6,200

$81,500







HAUL-2

$13,700

$9,610

$23,310

$0

$23,310

MUL072

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$311,000

$218,000

$529,000

$1,040,000

$1,569,000





Upland waste rock

C02a

$64,900

$45,400

$110,300

$8,440

$118,740

MUL073

BLM Polygon

Upland waste rock

C02a

$174,000

$122,000

$296,000

$22,600

$318,600

MUL074

BLM Polygon

Upland waste rock

C02a

$38,800

$27,100

$65,900

$5,040

$70,940

MUL075

BLM Polygon

Upland waste rock

C02a

$25,300

$17,700

$43,000

$3,290

$46,290

MUL076

BLM Polygon

Upland waste rock

C02a

$29,500

$20,700

$50,200

$3,840

$54,040

MUL077

BLM Polygon

Upland waste rock

C02a

$20,200

$14,200

$34,400

$2,630

$37,030

MUL078

BLM Polygon

Upland waste rock

C02a

$96,100

$67,300

$163,400

$12,500

$175,900

MUL079

BLM Polygon

Upland waste rock

C02a

$75,000

$52,500

$127,500

$9,750

$137,250

MUL080

BLM Polygon

Upland waste rock

C02a

$28,700

$20,100

$48,800

$3,730

$52,530

MUL081

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT03

$164,000

$115,000

$279,000

$536,000

$815,000





Floodplain waste rock

C01

$34,200

$24,000

$58,200

$0

$58,200







C08a

$142,000

$99,100

$241,100

$19,800

$260,900







HAUL-2

$43,900

$30,700

$74,600

$0

$74,600

MUL082

BLM Polygon

Upland waste rock

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

MUL083

BLM Polygon

Floodplain waste rock

C01

$65,700

$46,000

$111,700

$0

$111,700







C08a

$272,000

$190,000

$462,000

$38,100

$500,100







HAUL-2

$84,300

$59,000

$143,300

$0

$143,300

MUL084

BLM Polygon

Upland waste rock

C02a

$95,300

$66,700

$162,000

$12,400

$174,400

MUL103

BLM Polygon

Adit drainage

C10

$9,680

$6,780

$16,460

$1,740

$18,200







WT02

$493,000

$345,000

$838,000

$1,190,000

$2,028,000





Floodplain waste rock

C01

$27,000

$18,900

$45,900

$0

$45,900







C08a

$112,000

$78,100

$190,100

$15,600

$205,700







HAUL-2

$34,600

$24,200

$58,800

$0

$58,800

MUL107

BLM Polygon

Upland waste rock

C02a

$11,000

$7,670

$18,670

$1,420

$20,090

MUL108

BLM Polygon

Upland waste rock

C02a

$11,800

$8,260

$20,060

$1,530

$21,590

MUL109

BLM Polygon

Upland waste rock

C02a

$14,300

$10,000

$24,300

$1,860

$26,160

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)

Page 38 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

MUL110

BLM Polygon

Upland waste rock

C02a

$11,800

$8,260

$20,060

$1,530

$21,590

MUL111

BLM Polygon

Upland waste rock

C02a

$16,000

$11,200

$27,200

$2,080

$29,280

MUL112

BLM Polygon

Upland waste rock

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

MUL113

BLM Polygon

Upland waste rock

C02a

$17,700

$12,400

$30,100

$2,300

$32,400

MUL114

BLM Polygon

Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

MUL115

BLM Polygon

Upland waste rock

C02a

$20,200

$14,200

$34,400

$2,630

$37,030

MUL116

BLM Polygon

Upland waste rock

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

MUL117

BLM Polygon

Upland waste rock

C02a

$23,600

$16,500

$40,100

$3,070

$43,170

MUL118

BLM Polygon

Upland waste rock

C02a

$27,000

$18,900

$45,900

$3,510

$49,410

MUL119

BLM Polygon

Upland waste rock (erosion potential)

C02a

$23,600

$16,500

$40,100

$3,070

$43,170

MUL120

BLM Polygon

Floodplain waste rock

C01

$2,400

$1,680

$4,080

$0

$4,080







C08a

$9,910

$6,940

$16,850

$1,390

$18,240







HAUL-2

$3,070

$2,150

$5,220

$0

$5,220

MUL121

BLM Polygon

Upland waste rock

C02a

$13,500

$9,440

$22,940

$1,750

$24,690

MUL122

BLM Polygon

Upland waste rock

C02a

$17,700

$12,400

$30,100

$2,300

$32,400

MUL123

BLM Polygon

Upland waste rock

C02a

$12,600

$8,850

$21,450

$1,640

$23,090

MUL124

BLM Polygon

Upland waste rock

C02a

$15,200

$10,600

$25,800

$1,970

$27,770

MUL125

BLM Polygon

Upland waste rock

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

MUL126

BLM Polygon

Upland waste rock

C02a

$18,500

$13,000

$31,500

$2,410

$33,910

MUL127

BLM Polygon

Upland waste rock

C02a

$19,400

$13,600

$33,000

$2,520

$35,520

MUL128

BLM Polygon

Upland waste rock

C02a

$16,000

$11,200

$27,200

$2,080

$29,280

MUL129

BLM Polygon

Floodplain waste rock

C01

$114,000

$79,800

$193,800

$0

$193,800







C08a

$472,000

$330,000

$802,000

$66,000

$868,000







HAUL-2

$146,000

$102,000

$248,000

$0

$248,000

MUL130

BLM Polygon

Upland waste rock

C02a

$149,000

$104,000

$253,000

$19,400

$272,400

MUL131

BLM Polygon

Upland tailings

C01

$28,200

$19,800

$48,000

$0

$48,000







C08a

$117,000

$81,800

$198,800

$16,400

$215,200







HAUL-2

$36,200

$25,400

$61,600

$0

$61,600

MUL132

BLM Polygon

Upland tailings

C01

$7,700

$5,390

$13,090

$0

$13,090







C08a

$31,900

$22,300

$54,200

$4,460

$58,660







HAUL-2

$9,880

$6,920

$16,800

$0

$16,800

MUL133

BLM Polygon

Upland waste rock

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

MUL134

BLM Polygon

Upland waste rock

C02a

$48,900

$34,200

$83,100

$6,360

$89,460

MUL135

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

MUL136

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

MUL137

BLM Polygon

Upland waste rock

C02a

$30,300

$21,200

$51,500

$3,950

$55,450

MUL138

BLM Polygon

Upland waste rock

C02a

$68,300

$47,800

$116,100

$8,880

$124,980

MUL139

BLM Polygon

Upland waste rock (erosion potential)

C01

$856

$599

$1,455

$0

$1,455







C07

$2,940

$2,060

$5,000

$647

$5,647

MUL140

BLM Polygon

Upland waste rock

C02a

$14,300

$10,000

$24,300

$1,860

$26,160

Page 39 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID









2009 Total



Direct and









Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description

(Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

MUL141

BLM Polygon

Floodplain sediments

C01b

$130,000

$91,200

$221,200

$0

$221,200







C08a

$171,000

$120,000

$291,000

$23,900

$314,900







HAUL-2

$53,000

$37,100

$90,100

$0

$90,100

MUL142

BLM Polygon

Floodplain sediments

C01b

$463,000

$324,000

$787,000

$0

$787,000







C08a

$607,000

$425,000

$1,032,000

$85,000

$1,117,000







HAUL-2

$188,000

$132,000

$320,000

$0

$320,000

MUL143

BLM Polygon

Upland waste rock

C02a

$30,300

$21,200

$51,500

$3,950

$55,450

MUL144

BLM Polygon

Upland waste rock

C02a

$20,200

$14,200

$34,400

$2,630

$37,030

MUL145

BLM Polygon

Floodplain sediments

C01b

$56,700

$39,700

$96,400

$0

$96,400







C08a

$74,300

$52,000

$126,300

$10,400

$136,700







HAUL-2

$23,100

$16,100

$39,200

$0

$39,200

MUL146

BLM Polygon

Upland waste rock (erosion potential)

C01

$135,000

$94,200

$229,200

$0

$229,200







C07

$462,000

$324,000

$786,000

$102,000

$888,000

MUL147

BLM Polygon

Upland waste rock

C02a

$16,000

$11,200

$27,200

$2,080

$29,280

MUL148

BLM Polygon

Upland waste rock

C02b

$112,000

$78,300

$190,300

$14,500

$204,800

MUL149

BLM Polygon

Floodplain sediments

C01b

$76,300

$53,400

$129,700

$0

$129,700







C08a

$100,000

$70,000

$170,000

$14,000

$184,000







HAUL-2

$31,000

$21,700

$52,700

$0

$52,700

MUL150

BLM Polygon

Floodplain sediments

C01b

$204,000

$143,000

$347,000

$0

$347,000







C08a

$267,000

$187,000

$454,000

$37,400

$491,400







HAUL-2

$82,900

$58,000

$140,900

$0

$140,900

MUL151

BLM Polygon

Upland waste rock

C02a

$21,100

$14,800

$35,900

$2,740

$38,640

MUL152

BLM Polygon

Upland waste rock

C02a

$14,300

$10,000

$24,300

$1,860

$26,160

MUL153

BLM Polygon

Floodplain sediments

C01b

$103,000

$71,800

$174,800

$0

$174,800







C08a

$135,000

$94,200

$229,200

$18,800

$248,000







HAUL-2

$41,700

$29,200

$70,900

$0

$70,900

MUL154

BLM Polygon

Upland waste rock

C02a

$147,000

$103,000

$250,000

$19,100

$269,100

MUL155

BLM Polygon

Upland waste rock

C02a

$32,000

$22,400

$54,400

$4,160

$58,560

MUL156

BLM Polygon

Upland waste rock

C02a

$14,300

$10,000

$24,300

$1,860

$26,160

MUL157

BLM Polygon

Upland waste rock

C02a

$9,270

$6,490

$15,760

$1,210

$16,970

THO019

BLM Polygon

Upland waste rock

C02a

$28,700

$20,100

$48,800

$3,730

$52,530

TH0020

BLM Polygon

Floodplain waste rock

C01

$29,800

$20,900

$50,700

$0

$50,700







C08a

$123,000

$86,200

$209,200

$17,200

$226,400







HAUL-2

$38,200

$26,700

$64,900

$0

$64,900

THO021

BLM Polygon

Upland waste rock

C02a

$25,300

$17,700

$43,000

$3,290

$46,290

UG01-1

Bioengineering Reach

BioReach General Characteristics

FP/RP-AVG

$14,200

$9,930

$24,130

$2,550

$26,680

UG01-4

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$6,220

$4,360

$10,580

$1,870

$12,450







VBS-AVG

$5,360

$3,750

$9,110

$1,610

$10,720

UG01-5

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$190,000

$133,000

$323,000

$57,000

$380,000







CD-AVG

$63,900

$44,700

$108,600

$19,200

$127,800







FP/RP-AVG

$124,000

$87,100

$211,100

$22,400

$233,500







VBS-AVG

$81,000

$56,700

$137,700

$24,300

$162,000

Page 40 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

Segment ID







2009 Total



Direct and







Trait Description



Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Source Type Description (Waste Types)

TCD

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

UG01-6

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$171,000

$120,000

$291,000

$51,200

$342,200





CD-AVG

$61,800

$43,300

$105,100

$18,500

$123,600





FP/RP-AVG

$485,000

$340,000

$825,000

$87,400

$912,400





OFFCH-AVG

$1,580,000

$1,110,000

$2,690,000

$285,000

$2,975,000





VBS-AVG

$135,000

$94,600

$229,600

$40,600

$270,200

UG01-7

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$98,200

$68,700

$166,900

$29,500

$196,400





CD-AVG

$53,600

$37,500

$91,100

$16,100

$107,200





FP/RP-AVG

$281,000

$197,000

$478,000

$50,600

$528,600





VBS-AVG

$77,700

$54,400

$132,100

$23,300

$155,400

UG01-8

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$39,800

$27,800

$67,600

$11,900

$79,500





CD-AVG

$16,500

$11,500

$28,000

$4,940

$32,940





FP/RP-AVG

$206,000

$144,000

$350,000

$37,000

$387,000





VBS-AVG

$14,800

$10,400

$25,200

$4,450

$29,650

UG01-9

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$175,000

$123,000

$298,000

$52,500

$350,500





CD-AVG

$82,400

$57,700

$140,100

$24,700

$164,800





FP/RP-AVG

$133,000

$92,900

$225,900

$23,900

$249,800





VBS-AVG

$139,000

$97,000

$236,000

$41,600

$277,600

UG01-10

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$150,000

$105,000

$255,000

$45,100

$300,100





CD-AVG

$63,900

$44,700

$108,600

$19,200

$127,800





FP/RP-AVG

$156,000

$109,000

$265,000

$28,100

$293,100





VBS-AVG

$56,000

$39,200

$95,200

$16,800

$112,000

UG01-11

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$42,700

$29,900

$72,600

$12,800

$85,400





CD-AVG

$18,500

$13,000

$31,500

$5,560

$37,060





FP/RP-AVG

$143,000

$100,000

$243,000

$25,800

$268,800





VBS-AVG

$33,800

$23,700

$57,500

$10,100

$67,600

UG01-12

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$541,000

$379,000

$920,000

$162,000

$1,082,000





CD-AVG

$183,000

$128,000

$311,000

$55,000

$366,000





FP/RP-AVG

$1,160,000

$814,000

$1,974,000

$209,000

$2,183,000





OFFCH-AVG

$623,000

$436,000

$1,059,000

$112,000

$1,171,000





VBS-AVG

$231,000

$161,000

$392,000

$69,200

$461,200

UG01-13

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$297,000

$208,000

$505,000

$89,100

$594,100





CD-AVG

$101,000

$70,700

$171,700

$30,300

$202,000





FP/RP-AVG

$65,200

$45,600

$110,800

$11,700

$122,500





OFFCH-AVG

$503,000

$352,000

$855,000

$90,500

$945,500





VBS-AVG

$127,000

$88,600

$215,600

$38,000

$253,600

UG01-14

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$57,600

$40,300

$97,900

$17,300

$115,200





CD-AVG

$18,500

$13,000

$31,500

$5,560

$37,060





FP/RP-AVG

$19,000

$13,300

$32,300

$3,410

$35,710





VBS-AVG

$24,500

$17,200

$41,700

$7,360

$49,060

UG01-15

Bioengineering Reach BioReach General Characteristics

BSBR-AVG

$207,000

$145,000

$352,000

$62,000

$414,000





CD-AVG

$70,000

$49,000

$119,000

$21,000

$140,000





FP/RP-AVG

$5,400

$3,780

$9,180

$973

$10,153

Page 41 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total

2009 Total Direct and
Direct Capital 2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
TCD	Cost	Capital Cost	Cost	Year NPV) Year NPV)







VBS-AVG

$88,100

$61,700

$149,800

$26,400

$176,200

UG01-16

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$190,000

$133,000

$323,000

$57,000

$380,000







CD-AVG

$61,800

$43,300

$105,100

$18,500

$123,600







FP/RP-AVG

$381,000

$267,000

$648,000

$68,700

$716,700







VBS-AVG

$150,000

$105,000

$255,000

$45,100

$300,100

UG01-17

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$386,000

$271,000

$657,000

$116,000

$773,000







CD-AVG

$152,000

$107,000

$259,000

$45,700

$304,700







FP/RP-AVG

$1,000,000

$703,000

$1,703,000

$181,000

$1,884,000







OFFCH-AVG

$831,000

$582,000

$1,413,000

$150,000

$1,563,000







VBS-AVG

$306,000

$214,000

$520,000

$91,800

$611,800

UG01-18

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$364,000

$255,000

$619,000

$109,000

$728,000







CD-AVG

$124,000

$86,500

$210,500

$37,100

$247,600







FP/RP-AVG

$20,000

$14,000

$34,000

$3,610

$37,610







VBS-AVG

$155,000

$109,000

$264,000

$46,500

$310,500

UG01-19

Bioengineering Reach

BioReach General Characteristics

BSBR-AVG

$59,800

$41,800

$101,600

$17,900

$119,500







CD-AVG

$14,400

$10,100

$24,500

$4,330

$28,830







FP/RP-AVG

$37,600

$26,300

$63,900

$6,770

$70,670







OFFCH-AVG

$46,300

$32,400

$78,700

$8,340

$87,040







VBS-AVG

$47,300

$33,100

$80,400

$14,200

$94,600

WAL013

BLM Polygon

Floodplain waste rock

C01

$34,900

$24,400

$59,300

$0

$59,300







C08a

$144,000

$101,000

$245,000

$20,200

$265,200







HAUL-2

$44,800

$31,400

$76,200

$0

$76,200

WAL038

BLM Polygon

Floodplain sediments

C01b

$4,470,000

$3,130,000

$7,600,000

$0

$7,600,000







C08a

$5,860,000

$4,100,000

$9,960,000

$821,000

$10,781,000







C11j

$41,300,000

$28,900,000

$70,200,000

$827,000

$71,027,000







HAUL-2

$1,820,000

$1,270,000

$3,090,000

$0

$3,090,000

WAL038

BLM Polygon

Groundwater

WT01

$1,820,000

$1,940,000

$3,760,000

$2,750,000

$6,510,000

WAL068

BLM Polygon

Upland waste rock

C02a

$24,400

$17,100

$41,500

$3,180

$44,680

WAL076

BLM Polygon

Floodplain waste rock

C01

$175,000

$122,000

$297,000

$0

$297,000







C08a

$722,000

$506,000

$1,228,000

$101,000

$1,329,000







HAUL-2

$224,000

$157,000

$381,000

$0

$381,000

WAL077

BLM Polygon

Floodplain sediments

C01b

$567,000

$397,000

$964,000

$0

$964,000







C08a

$743,000

$520,000

$1,263,000

$104,000

$1,367,000







HAUL-2

$231,000

$161,000

$392,000

$0

$392,000

Notes:

This Table does not include Central Treatment Plant (CTP) Sludge Pond Closure costs, these costs will be applied to the Total Alternative Cost.
This Table does not include Roads and Bridges costs, these costs will be applied to the Total Alternative Cost.

O&M = Operations and Maintenance
NPV = Net Present Value

Trait Description

Segment ID	Source ID Source Type Description (Waste Types)

Page 42 of 43


-------

-------
TABLE D-38

Summary of Estimated Costs for Sites by Trait and TCD, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

Segment ID

Trait Description
Source ID Source Type Description (Waste Types)

TCD

2009 Total
Direct Capital
Cost

2009 Total
Direct and

2009 Indirect Indirect Capital O&M Cost (30- Total Cost (30-
Capital Cost	Cost	Year NPV) Year NPV)

Typical Conceptual Design (TCD) Codes

BSBR-AVG = Bank Stabilization via Revetments - Average Cost

C01 = Excavation (dry)

C01 b = Excavation (60% dry/40% wet)

C02a = Regrade/Consolidate/Vegetative Cover: Lower Part of Pile in 100-Year Floodplain

C02b = Regrade/Consolidate/Vegetative Cover: Waste Rock Pile in Stream Valley

C06 = Waste Consolidation Area with Erosion Protection

C07 = Waste Consolidation Area Above Flood Level

C08a = Repository, 1 million cy

C09 = Impoundment Closure

C10 = Adit Drainage Collection

C11j = Hydraulic Isolation Using Slurry Wall (with drain, 30 ft deep)

C14c = Stream Lining (100 feet wide)

C15b = French Drain (15 feet bgs)

CD-AVG = Current Deflector Average Cost

CD-SED = Current Deflector Sediment Traps

CH REAL-1 = Channel Realignment

FP/RP-AVG = Floodplain and Riparian Replanting - Average Cost
HAUL-2 = Haul to Repository
HH-4 = Millsite Demolition/Disposal

OFFCH-AVG = Off-Channel Hydrologic Feature Average Cost

PIPE-1 = Conveyance Pipeline (6-inch)

PIPE-2 = Conveyance Pipeline (12-inch)

PIPE-3 = Conveyance Pipeline (24-inch)

VBS-AVG = Vegetative Bank Stabilization - Average Cost

WT01 = Centralized High-Density Sludge (HDS) Treatment at Central Treatment Plant (CTP)

WT02 = Onsite Semi-Passive Water Treatment Using Lime Addition and Settling Pond(s)

WT03 = Onsite Semi-Passive Water Treatment Using Sulfate-Reducing Bioreactor (SRB) System

NOTE: The above costs are presented rounded to three significant figures

NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of -30 percent to +50 percent (-30/+50%).
NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-magnitude cost opinion shown
has been prepared for guidance in project evaluation from the information available at the time of preparation. The final costs of the
project will depend on actual labor and material costs, actual site conditions, productivity, competitive market conditions, the final
project scope, the final project schedule, and other variable factors. As a result, the final project costs will vary from those presented
above. Because of these factors, funding needs must be carefully reviewed prior to making specific financial decisions or establishing
final budgets.

Page 43 of 43


-------

-------
TABLE D-39

Summary of Total Estimated Costs by Site, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









2009 Total









2009 Total



Direct and









Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID

Source ID

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

BigCrkSegOl

POL044

$4,470

$3,100

$7,600

$1,030

$8,630



POL052

$87,300

$61,000

$148,000

$14,900

$163,000

BigCrkSeg03

POL001

$5,070

$3,600

$8,620

$1,170

$9,790



POL002

$32,300

$23,000

$54,900

$5,500

$60,400



POL067

$531,000

$370,000

$902,000

$1,210,000

$2,110,000



POL068

$16,900

$12,000

$28,700

$2,190

$30,900

BigCrkSeg04

BIG04-2

$238,000

$170,000

$405,000

$92,700

$498,000



BIG04-3

$2,350,000

$1,600,000

$4,000,000

$704,000

$4,710,000



KLE025

$5,930,000

$4,200,000

$10,100,000

$1,190,000

$11,300,000



KLE026

$182,000

$130,000

$309,000

$41,800

$351,000



KLE027

$1,770,000

$1,200,000

$3,010,000

$301,000

$3,310,000



KLE047

$122,000

$85,000

$207,000

$8,230

$216,000



KLE053

$3,730,000

$2,600,000

$6,340,000

$636,000

$6,980,000



KLE054

$3,760,000

$2,600,000

$6,400,000

$1,180,000

$7,580,000



KLE071

$1,440,000

$1,000,000

$2,450,000

$97,100

$2,540,000



KLE073

$3,670,000

$2,600,000

$6,240,000

$248,000

$6,490,000



POL008

$155,000

$110,000

$263,000

$26,400

$290,000



POL010

$86,500

$61,000

$147,000

$14,700

$162,000



POL011

$59,300

$41,000

$101,000

$10,100

$111,000



POL022

$12,700

$8,900

$21,600

$2,910

$24,500



POL066

$3,800

$2,700

$6,460

$647

$7,100

CCSeg

PIPECC

$6,810,000

$4,800,000

$11,600,000

$546,000

$12,100,000

CCSegOl

BUR105

$88,600

$62,000

$151,000

$7,290

$158,000



BUR109

$281,000

$200,000

$477,000

$30,800

$508,000



BUR185

$70,000

$49,000

$119,000

$8,370

$127,000



BUR187

$56,500

$40,000

$96,000

$6,750

$103,000



THO023

$43,000

$30,000

$73,000

$5,130

$78,100

CCSeg02

BUR107

$783,000

$570,000

$1,350,000

$184,000

$1,540,000



BUR130

$539,000

$380,000

$915,000

$64,300

$980,000



BUR132

$455,000

$320,000

$773,000

$45,100

$818,000



BUR133

$101,000

$70,000

$171,000

$17,100

$188,000



BUR134

$274,000

$190,000

$465,000

$46,600

$511,000



BUR135

$131,000

$92,000

$223,000

$15,700

$238,000



BUR145

$1,060,000

$740,000

$1,810,000

$181,000

$1,990,000



BUR150

$334,000

$230,000

$567,000

$36,700

$604,000



BUR153

$642,000

$450,000

$1,090,000

$43,400

$1,130,000



CC02-1

$1,440,000

$1,000,000

$2,450,000

$396,000

$2,840,000

CCSeg03

BUR087

$927,000

$650,000

$1,580,000

$105,000

$1,680,000



BUR088

$70,000

$71,000

$141,000

$47,400

$189,000



BUR089

$45,200

$32,000

$76,800

$5,400

$82,200



BUR090

$2,980,000

$2,100,000

$5,060,000

$380,000

$5,440,000



BUR099

$70,000

$71,000

$141,000

$47,400

$189,000



BUR146

$935,000

$660,000

$1,590,000

$63,200

$1,650,000



BUR149

$124,000

$87,000

$210,000

$13,800

$224,000



BUR166

$74,500

$52,000

$127,000

$8,910

$136,000



BUR180

$56,500

$40,000

$96,000

$6,210

$102,000

CCSeg04

BUR066

$73,500

$51,000

$125,000

$8,100

$133,000



BUR067

$5,400,000

$4,100,000

$9,530,000

$1,430,000

$11,000,000



BUR068

$227,000

$160,000

$386,000

$38,800

$425,000



BUR072

$392,000

$270,000

$666,000

$47,000

$713,000



BUR073

$1,300,000

$910,000

$2,200,000

$142,000

$2,350,000



BUR075

$66,500

$47,000

$113,000

$11,300

$124,000



BUR094

$118,000

$83,000

$201,000

$15,300

$216,000



BUR096

$135,000

$96,000

$230,000

$21,000

$251,000



BUR097

$952,000

$990,000

$1,940,000

$670,000

$2,610,000



BUR098

$1,960,000

$1,700,000

$3,660,000

$1,080,000

$4,740,000

Page 1 of 8


-------
TABLE D-39

Summary of Total Estimated Costs by Site, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site







2009 Total







2009 Total



Direct and







Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

BUR112

$70,000

$71,000

$141,000

$47,400

$189,000

BUR117

$284,000

$200,000

$483,000

$35,800

$519,000

BUR118

$626,000

$440,000

$1,060,000

$107,000

$1,170,000

BUR119

$175,000

$120,000

$298,000

$22,800

$321,000

BUR120

$78,400

$55,000

$133,000

$10,200

$144,000

BUR121

$1,230,000

$1,100,000

$2,350,000

$573,000

$2,920,000

BUR122

$275,000

$190,000

$467,000

$30,200

$498,000

BUR124

$84,300

$59,000

$143,000

$11,000

$154,000

BUR125

$27,000

$19,000

$45,900

$3,510

$49,400

BUR128

$960,000

$670,000

$1,630,000

$147,000

$1,780,000

BUR129

$170,000

$140,000

$311,000

$64,400

$375,000

BUR141

$807,000

$570,000

$1,370,000

$54,500

$1,430,000

BUR142

$727,000

$510,000

$1,240,000

$89,400

$1,320,000

BUR143

$1,170,000

$820,000

$2,000,000

$79,300

$2,070,000

BUR144

$605,000

$420,000

$1,030,000

$68,600

$1,100,000

BUR176

$126,000

$88,000

$214,000

$15,100

$230,000

BUR177

$153,000

$110,000

$260,000

$18,400

$279,000

BUR178

$113,000

$79,000

$193,000

$12,400

$205,000

BUR189

$45,200

$32,000

$76,800

$5,400

$82,200

BUR190

$312,000

$330,000

$641,000

$167,000

$808,000

BUR191

$131,000

$92,000

$223,000

$17,000

$240,000

BUR192

$334,000

$230,000

$567,000

$40,200

$608,000

BUR204

$43,000

$30,000

$73,000

$5,130

$78,100

CC04-1

$2,170,000

$1,500,000

$3,690,000

$803,000

$4,490,000

HHWPCC04-1

$58,400

$41,000

$99,300

$7,600

$107,000

HHWPCC04-2

$58,400

$41,000

$99,300

$7,600

$107,000

HHWPCC04-3

$58,400

$41,000

$99,300

$7,600

$107,000

CCSeg05 CC05-1

$1,080,000

$750,000

$1,830,000

$224,000

$2,060,000

CC05-2

$6,560,000

$4,600,000

$11,200,000

$1,340,000

$12,500,000

OSB047

$128,000

$90,000

$217,000

$8,640

$226,000

WAL010

$37,500

$26,000

$63,700

$2,530

$66,200

WAL011

$141,000

$120,000

$262,000

$51,200

$313,000

WAL039

$343,000

$240,000

$584,000

$31,000

$615,000

WAL040

$475,000

$330,000

$808,000

$32,100

$840,000

WAL041

$146,000

$100,000

$247,000

$9,830

$257,000

WAL042

$579,000

$410,000

$985,000

$69,500

$1,050,000

WAL081

$78,200

$55,000

$133,000

$7,060

$140,000

WP-OPTIONC

$9,270,000

$6,700,000

$15,900,000

$776,000

$16,700,000

MIDGradSeg PIPEMG

$12,600,000

$8,800,000

$21,400,000

$1,010,000

$22,400,000

MIDGradSegOl HHWPMG01-1

$58,400

$41,000

$99,300

$7,600

$107,000

HHWPMG01-2

$58,400

$41,000

$99,300

$7,600

$107,000

HHWPMG01-3

$58,400

$41,000

$99,300

$7,600

$107,000

HHWPMG01-4

$58,400

$41,000

$99,300

$7,600

$107,000

HHWPMG01-5

$58,400

$41,000

$99,300

$7,600

$107,000

KLE011

$1,940,000

$1,400,000

$3,300,000

$388,000

$3,690,000

KLE016

$140,000

$98,000

$238,000

$16,700

$255,000

KLE020

$364,000

$250,000

$618,000

$40,000

$658,000

KLE021

$146,000

$100,000

$248,000

$17,600

$266,000

KLE023

$259,000

$180,000

$440,000

$31,100

$471,000

KLE033

$381,000

$270,000

$648,000

$43,200

$692,000

KLE034

$534,000

$370,000

$908,000

$61,800

$970,000

KLE035

$3,420,000

$2,400,000

$5,820,000

$370,000

$6,190,000

KLE040

$14,000,000

$9,900,000

$23,900,000

$985,000

$24,900,000

KLE042

$2,080,000

$1,500,000

$3,540,000

$166,000

$3,710,000

KLE048

$14,100,000

$10,000,000

$24,000,000

$1,070,000

$25,100,000

KLE049

$14,900,000

$11,000,000

$25,400,000

$1,200,000

$26,600,000

Page 2 of 8


-------
TABLE D-39

Summary of Total Estimated Costs by Site, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Segment ID







2009 Total







2009 Total



Direct and







Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

KLE051

$74,500

$52,000

$127,000

$8,910

$136,000

KLE062

$954,000

$670,000

$1,620,000

$64,400

$1,690,000

KLE066

$85,700

$60,000

$146,000

$10,300

$156,000

KLE067

$68,500

$48,000

$117,000

$5,400

$122,000

KLE068

$266,000

$190,000

$452,000

$45,300

$497,000

KLE069

$97,300

$68,000

$165,000

$11,300

$177,000

KLE070

$94,700

$66,000

$161,000

$11,300

$172,000

KLE074

$402,000

$280,000

$683,000

$52,100

$735,000

KLE075

$75,900

$53,000

$129,000

$12,900

$142,000

MG01-1

$216,000

$150,000

$367,000

$91,100

$458,000

MG01-10

$148,000

$100,000

$252,000

$46,900

$299,000

MG01-11

$600,000

$420,000

$1,020,000

$145,000

$1,170,000

MG01-12

$3,100,000

$2,200,000

$5,260,000

$605,000

$5,860,000

MG01-13

$5,660,000

$4,000,000

$9,630,000

$1,090,000

$10,700,000

MG01-14

$956,000

$670,000

$1,620,000

$196,000

$1,820,000

MG01-15

$2,810,000

$2,000,000

$4,770,000

$538,000

$5,310,000

MG01-16

$505,000

$350,000

$858,000

$106,000

$964,000

MG01-17

$3,250,000

$2,300,000

$5,530,000

$666,000

$6,200,000

MG01-18

$1,800,000

$1,300,000

$3,070,000

$370,000

$3,440,000

MG01-2

$261,000

$180,000

$444,000

$83,900

$528,000

MG01-3

$411,000

$290,000

$699,000

$110,000

$809,000

MG01-4

$2,050,000

$1,400,000

$3,500,000

$462,000

$3,960,000

MG01-5

$188,000

$130,000

$320,000

$63,000

$383,000

MG01-6

$2,100,000

$1,500,000

$3,570,000

$495,000

$4,070,000

MG01-7

$2,080,000

$1,500,000

$3,530,000

$462,000

$4,000,000

MG01-8

$5,430,000

$3,800,000

$9,240,000

$1,040,000

$10,300,000

MG01-9

$728,000

$510,000

$1,240,000

$152,000

$1,390,000

MUL085

$94,900

$66,000

$161,000

$21,600

$183,000

MUL086

$310,000

$220,000

$526,000

$34,000

$560,000

OSB025

$123,000

$86,000

$209,000

$13,500

$223,000

OSB030

$101,000

$71,000

$172,000

$12,200

$184,000

OSB065

$102,000,000

$71,000,000

$173,000,000

$4,050,000

$177,000,000

OSB070

$320,000

$220,000

$543,000

$35,100

$578,000

OSB072

$52,000

$36,000

$88,300

$6,210

$94,500

OSB073

$150,000

$100,000

$254,000

$15,700

$270,000

OSB074

$503,000

$350,000

$854,000

$1,190,000

$2,050,000

OSB075

$63,200

$44,000

$107,000

$7,560

$115,000

OSB076

$45,200

$32,000

$76,800

$5,400

$82,200

OSB078

$18,200

$13,000

$30,900

$2,160

$33,100

OSB117

$266,000

$190,000

$452,000

$45,300

$497,000

OSB118

$2,200,000

$1,500,000

$3,740,000

$149,000

$3,890,000

OSB119

$11,100,000

$7,800,000

$19,000,000

$246,000

$19,200,000

OSB120

$65,300,000

$46,000,000

$111,000,000

$2,830,000

$114,000,000

POL018

$224,000

$160,000

$380,000

$24,600

$405,000

POL019

$1,880,000

$1,300,000

$3,200,000

$434,000

$3,630,000

POL021

$149,000

$100,000

$253,000

$17,800

$271,000

POL064

$45,200

$32,000

$76,800

$5,400

$82,200

WAL001

$29,800,000

$21,000,000

$50,600,000

$3,550,000

$54,100,000

WAL002

$206,000

$140,000

$351,000

$25,600

$377,000

WAL004

$37,300,000

$26,000,000

$63,600,000

$1,790,000

$65,400,000

WAL014

$395,000

$280,000

$673,000

$43,500

$716,000

WAL016

$3,800

$2,700

$6,460

$647

$7,100

WAL020

$1,610,000

$1,100,000

$2,730,000

$157,000

$2,890,000

WAL024

$97,000

$68,000

$165,000

$11,600

$176,000

WAL034

$1,430,000

$1,000,000

$2,430,000

$96,600

$2,530,000

WAL035

$1,450,000

$1,000,000

$2,460,000

$159,000

$2,620,000

Page 3 of 8


-------
TABLE D-39

Summary of Total Estimated Costs by Site, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









2009 Total









2009 Total



Direct and









Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID

Source ID

Cost

Capital Cost

Cost

Year NPV)

Year NPV)



WAL036

$635,000

$450,000

$1,080,000

$72,800

$1,150,000



WAL037

$227,000

$160,000

$386,000

$38,800

$425,000



WAL046

$58,700

$41,000

$99,800

$7,020

$107,000



WAL055

$38,500

$27,000

$65,400

$4,590

$70,000



WAL056

$54,200

$38,000

$92,100

$6,480

$98,600



WAL057

$22,700

$16,000

$38,600

$2,700

$41,300



WAL058

$20,500

$14,000

$34,800

$2,430

$37,200



WAL062

$43,000

$30,000

$73,000

$5,130

$78,100



WAL064

$79,000

$55,000

$134,000

$9,450

$144,000



WAL072

$18,200

$13,000

$30,900

$2,160

$33,100



WAL073

$22,700

$16,000

$38,600

$2,700

$41,300

MIDGradSeg02

KLW061

$2,320,000

$1,600,000

$3,940,000

$301,000

$4,240,000



KLW062

$356,000

$250,000

$605,000

$46,200

$651,000



KLW070

$342,000

$240,000

$583,000

$23,200

$606,000



KLW095

$137,000

$96,000

$233,000

$17,800

$251,000



MG 02-10

$38,500

$27,000

$65,500

$22,200

$87,700



MG02-11

$22,500

$16,000

$38,200

$17,400

$55,500



MG02-12

$6,360

$4,500

$10,800

$1,660

$12,500

MoonCrkSegOl

KLE061

$5,500

$3,800

$9,340

$496

$9,840



MC01-2

$498,000

$350,000

$847,000

$174,000

$1,020,000

MoonCrkSeg02

KLE008

$109,000

$76,000

$185,000

$14,100

$199,000



KLE014

$5,500

$3,800

$9,340

$496

$9,840



KLE041

$121,000

$85,000

$206,000

$8,180

$214,000



KLE063

$25,100

$18,000

$42,600

$3,260

$45,900



KLE064

$21,700

$15,000

$36,900

$2,820

$39,700



KLE065

$38,400

$27,000

$65,300

$4,990

$70,300



MC02-2

$817,000

$570,000

$1,390,000

$266,000

$1,650,000



MC02-3

$476,000

$330,000

$809,000

$148,000

$957,000



MC02-4

$369,000

$260,000

$628,000

$120,000

$747,000

NMSeg

PIPENM

$1,560,000

$1,100,000

$2,650,000

$125,000

$2,780,000

NMSegOl

BUR051

$503,000

$350,000

$854,000

$1,190,000

$2,050,000



BUR052

$39,400

$28,000

$67,000

$4,320

$71,300



BUR053

$5,110,000

$3,600,000

$8,680,000

$494,000

$9,170,000



BUR140

$367,000

$260,000

$624,000

$24,800

$649,000



BUR160

$1,070,000

$750,000

$1,820,000

$245,000

$2,060,000



NM01-1

$1,080,000

$750,000

$1,830,000

$344,000

$2,170,000

NMSeg02

BUR054

$5,660,000

$4,000,000

$9,610,000

$1,250,000

$10,900,000



BUR055

$468,000

$330,000

$795,000

$58,900

$854,000



BUR056

$2,230,000

$1,600,000

$3,790,000

$290,000

$4,080,000



BUR058

$503,000

$350,000

$854,000

$1,190,000

$2,050,000



BUR139

$295,000

$210,000

$501,000

$35,400

$536,000



BUR170

$677,000

$470,000

$1,150,000

$1,190,000

$2,340,000



BUR171

$489,000

$340,000

$830,000

$1,080,000

$1,910,000



BUR172

$96,800

$68,000

$165,000

$11,600

$176,000



NM02-1

$2,040,000

$1,400,000

$3,470,000

$655,000

$4,120,000



OSB040

$620,000

$440,000

$1,050,000

$41,900

$1,100,000



OSB044

$10,300,000

$7,200,000

$17,500,000

$922,000

$18,400,000



OSB048

$12,600

$8,900

$21,500

$1,640

$23,100



OSB056

$58,700

$41,000

$99,700

$3,960

$104,000



OSB057

$477,000

$330,000

$811,000

$32,200

$844,000



OSB058

$58,700

$41,000

$99,700

$3,960

$104,000



OSB088

$13,600

$11,000

$24,600

$4,710

$29,300



OSB089

$20,300

$18,000

$38,400

$10,400

$48,800

NMSeg03

NM03-1

$921,000

$640,000

$1,570,000

$238,000

$1,800,000

NMSeg04

NM04-1

$1,860,000

$1,300,000

$3,160,000

$405,000

$3,560,000



NM04-2

$741,000

$520,000

$1,260,000

$157,000

$1,420,000

Page 4 of 8


-------
TABLE D-39

Summary of Total Estimated Costs by Site, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site







2009 Total







2009 Total



Direct and







Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

NM04-3

$5,130,000

$3,600,000

$8,730,000

$1,100,000

$9,830,000

OSB032

$206,000

$140,000

$350,000

$22,700

$373,000

OSB033

$167,000

$120,000

$283,000

$18,400

$302,000

OSB038

$315,000

$220,000

$535,000

$34,600

$570,000

OSB039

$763,000

$530,000

$1,300,000

$74,500

$1,370,000

OSB052

$1,370,000

$960,000

$2,330,000

$273,000

$2,600,000

OSB059

$1,210,000

$850,000

$2,060,000

$81,800

$2,140,000

OSB060

$22,600

$16,000

$38,400

$2,590

$41,000

OSB061

$133,000

$93,000

$226,000

$22,600

$249,000

OSB082

$133,000

$93,000

$226,000

$14,600

$241,000

OSB115

$76,700

$54,000

$130,000

$9,180

$140,000

WAL006

$56,500

$40,000

$96,000

$6,750

$103,000

WAL033

$930,000

$650,000

$1,580,000

$107,000

$1,690,000

PineCrkSegOl HHWPPC01-1

$58,400

$41,000

$99,300

$7,600

$107,000

HHWPPC01-2

$58,400

$41,000

$99,300

$7,600

$107,000

MAS006

$4,190,000

$2,900,000

$7,130,000

$266,000

$7,390,000

MAS007

$973,000

$680,000

$1,650,000

$646,000

$2,300,000

MAS008

$475,000

$330,000

$807,000

$80,900

$888,000

MAS009

$141,000

$99,000

$240,000

$24,100

$264,000

MAS011

$146,000

$100,000

$248,000

$529,000

$777,000

MAS012

$512,000

$360,000

$871,000

$1,190,000

$2,060,000

MAS013

$89,200

$63,000

$152,000

$15,200

$167,000

MAS014

$1,420,000

$990,000

$2,410,000

$2,420,000

$4,830,000

MAS015

$181,000

$130,000

$307,000

$533,000

$840,000

MAS016

$586,000

$410,000

$997,000

$604,000

$1,600,000

MAS017

$1,690,000

$1,200,000

$2,880,000

$1,390,000

$4,270,000

MAS018

$51,300

$36,000

$87,200

$8,730

$95,900

MAS019

$19,000

$13,000

$32,300

$3,230

$35,500

MAS020

$401,000

$280,000

$681,000

$552,000

$1,230,000

MAS021

$560,000

$390,000

$951,000

$1,180,000

$2,130,000

MAS022

$911,000

$640,000

$1,550,000

$155,000

$1,700,000

MAS023

$19,000

$13,000

$32,300

$3,230

$35,500

MAS025

$150,000

$110,000

$255,000

$0

$255,000

MAS027

$575,000

$400,000

$977,000

$65,300

$1,040,000

MAS028

$205,000

$140,000

$349,000

$34,900

$384,000

MAS029

$13,300

$9,300

$22,600

$2,260

$24,900

MAS030

$68,800

$48,000

$117,000

$7,560

$124,000

MAS031

$82,000

$57,000

$139,000

$14,000

$153,000

MAS032

$1,520

$1,100

$2,590

$259

$2,840

MAS033

$91,100

$64,000

$155,000

$15,500

$170,000

MAS035

$152,000

$110,000

$259,000

$25,900

$284,000

MAS036

$51,300

$36,000

$87,200

$8,730

$95,900

MAS040

$50,600

$35,000

$86,000

$3,420

$89,400

MAS041

$85,800

$60,000

$146,000

$5,800

$152,000

MAS042

$39,600

$28,000

$67,400

$2,680

$70,100

MAS043

$110,000

$77,000

$187,000

$7,430

$195,000

MAS045

$110,000

$77,000

$187,000

$7,430

$195,000

MAS046

$875,000

$610,000

$1,490,000

$59,100

$1,550,000

MAS048

$404,000

$280,000

$686,000

$68,800

$755,000

MAS049

$683,000

$480,000

$1,160,000

$116,000

$1,280,000

MAS050

$813,000

$570,000

$1,380,000

$1,190,000

$2,570,000

MAS052

$54,000

$38,000

$91,900

$5,940

$97,800

MAS053

$3,800

$2,700

$6,460

$647

$7,100

MAS054

$394,000

$280,000

$670,000

$574,000

$1,240,000

MAS055

$3,800

$2,700

$6,460

$647

$7,100

MAS057

$3,800

$2,700

$6,460

$647

$7,100

Page 5 of 8


-------
TABLE D-39

Summary of Total Estimated Costs by Site, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site









2009 Total









2009 Total



Direct and









Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Segment ID

Source ID

Cost

Capital Cost

Cost

Year NPV)

Year NPV)



MAS065

$3,800

$2,700

$6,460

$647

$7,100



MAS068

$36,200

$25,000

$61,500

$4,320

$65,800



MAS072

$3,800

$2,700

$6,460

$647

$7,100



MAS078

$364,000

$250,000

$617,000

$580,000

$1,200,000



MAS079

$588,000

$410,000

$999,000

$51,300

$1,050,000



MAS081

$177,000

$120,000

$301,000

$23,000

$324,000



MAS083

$911,000

$640,000

$1,550,000

$102,000

$1,650,000



MAS084

$569,000

$400,000

$968,000

$97,000

$1,060,000

PineCrkSeg02

TWI002

$109,000

$77,000

$186,000

$18,600

$205,000



TWI006

$91,100

$64,000

$155,000

$15,500

$170,000



TWI008

$3,800

$2,700

$6,460

$647

$7,100



TWI009

$123,000

$86,000

$209,000

$21,000

$230,000



TWI011

$3,800

$2,700

$6,460

$647

$7,100



TWI012

$72,800

$51,000

$124,000

$12,400

$136,000



TWI013

$146,000

$100,000

$248,000

$24,800

$273,000



TWI014

$114,000

$80,000

$194,000

$19,400

$213,000



TWI018

$3,800

$2,700

$6,460

$647

$7,100



TWI020

$3,800

$2,700

$6,460

$647

$7,100



TWI027

$3,800

$2,700

$6,460

$647

$7,100



TWI029

$3,800

$2,700

$6,460

$647

$7,100



TWI030

$3,800

$2,700

$6,460

$647

$7,100

PineCrkSeg03

KLW075

$323,000

$230,000

$549,000

$55,100

$604,000



KLW077

$209,000

$150,000

$356,000

$35,700

$392,000



KLW079

$182,000

$130,000

$310,000

$31,000

$341,000



KLW080

$98,300

$69,000

$167,000

$8,100

$175,000



KLW082

$155,000

$110,000

$263,000

$26,400

$290,000



KLW083

$265,000

$180,000

$449,000

$45,000

$494,000



KLW085

$274,000

$190,000

$465,000

$46,600

$511,000



MAS003

$980,000

$690,000

$1,670,000

$226,000

$1,890,000



PC03-1

$1,540,000

$1,100,000

$2,620,000

$372,000

$2,990,000



PC03-2

$1,340,000

$940,000

$2,270,000

$302,000

$2,580,000



PC03-3

$575,000

$400,000

$978,000

$148,000

$1,130,000

UpperSFCDRSeg

PIPEUG

$11,800,000

$8,200,000

$20,000,000

$940,000

$20,900,000

UpperSFCDRSegOl

HHWPUG01-1

$58,400

$41,000

$99,300

$7,600

$107,000



HHWPUG01-2

$58,400

$41,000

$99,300

$7,600

$107,000



HHWPUG01-3

$58,400

$41,000

$99,300

$7,600

$107,000



HHWPUG01-4

$58,400

$41,000

$99,300

$7,600

$107,000



HHWPUG01-5

$58,400

$41,000

$99,300

$7,600

$107,000



LOK001

$109,000

$76,000

$185,000

$14,100

$199,000



LOK002

$107,000

$75,000

$182,000

$13,900

$196,000



LOK004

$1,690,000

$1,200,000

$2,880,000

$1,410,000

$4,290,000



LOK005

$15,200

$11,000

$25,800

$1,970

$27,800



LOK006

$63,800

$45,000

$109,000

$7,020

$116,000



LOK007

$22,800

$16,000

$38,700

$2,960

$41,700



LOK008

$93,300

$65,000

$159,000

$10,300

$169,000



LOK009

$420,000

$290,000

$713,000

$71,400

$784,000



LOK010

$34,400

$24,000

$58,500

$3,780

$62,300



LOK011

$4,670,000

$4,600,000

$9,280,000

$2,810,000

$12,100,000



LOK017

$844,000

$590,000

$1,430,000

$98,000

$1,530,000



LOK024

$503,000

$350,000

$854,000

$1,190,000

$2,050,000



LOK048

$22,800

$16,000

$38,700

$2,960

$41,700



LOK050

$247,000

$170,000

$420,000

$42,000

$462,000



LOK051

$161,000

$110,000

$274,000

$20,900

$295,000



LOK053

$26,100

$18,000

$44,400

$3,400

$47,800



MUL001

$1,430,000

$1,000,000

$2,430,000

$244,000

$2,680,000



MUL002

$436,000

$310,000

$742,000

$74,400

$817,000

Page 6 of 8


-------
TABLE D-39

Summary of Total Estimated Costs by Site, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Segment ID







2009 Total







2009 Total



Direct and







Direct Capital

2009 Indirect

Indirect Capital

O&M Cost (30-

Total Cost (30-

Source ID

Cost

Capital Cost

Cost

Year NPV)

Year NPV)

MUL004

$202,000

$140,000

$343,000

$22,100

$365,000

MUL006

$179,000

$130,000

$305,000

$19,700

$324,000

MUL007

$80,100

$56,000

$136,000

$10,400

$147,000

MUL008

$330,000

$230,000

$561,000

$36,200

$597,000

MUL009

$21,100

$15,000

$35,900

$2,740

$38,600

MUL012

$2,200,000

$1,600,000

$3,820,000

$381,000

$4,200,000

MUL013

$44,700

$31,000

$76,000

$5,810

$81,800

MUL014

$1,190,000

$1,200,000

$2,420,000

$843,000

$3,270,000

MUL015

$787,000

$550,000

$1,340,000

$102,000

$1,440,000

MUL018

$274,000

$190,000

$465,000

$46,600

$511,000

MUL019

$6,580,000

$4,800,000

$11,400,000

$1,300,000

$12,700,000

MUL020

$7,830,000

$5,500,000

$13,300,000

$654,000

$14,000,000

MUL021

$297,000

$210,000

$505,000

$32,700

$538,000

MUL022

$29,500

$21,000

$50,200

$3,840

$54,000

MUL023

$1,100,000

$770,000

$1,860,000

$1,290,000

$3,150,000

MUL027

$396,000

$280,000

$673,000

$570,000

$1,240,000

MUL028

$1,440,000

$1,000,000

$2,450,000

$717,000

$3,170,000

MUL029

$387,000

$270,000

$658,000

$66,000

$724,000

MUL030

$88,400

$62,000

$150,000

$9,720

$160,000

MUL031

$28,700

$20,000

$48,800

$3,730

$52,500

MUL033

$301,000

$210,000

$511,000

$51,200

$563,000

MUL037

$9,500,000

$6,700,000

$16,100,000

$718,000

$16,900,000

MUL038

$927,000

$650,000

$1,580,000

$117,000

$1,690,000

MUL042

$265,000

$180,000

$449,000

$45,000

$494,000

MUL043

$333,000

$230,000

$566,000

$56,700

$622,000

MUL045

$524,000

$370,000

$891,000

$89,300

$980,000

MUL047

$56,500

$40,000

$96,000

$6,210

$102,000

MUL048

$405,000

$280,000

$689,000

$69,100

$759,000

MUL049

$25,300

$18,000

$43,000

$3,290

$46,300

MUL051

$295,000

$210,000

$501,000

$32,400

$533,000

MUL052

$711,000

$500,000

$1,210,000

$1,200,000

$2,410,000

MUL053

$266,000

$190,000

$452,000

$34,600

$487,000

MUL054

$79,200

$56,000

$135,000

$10,300

$145,000

MUL056

$29,500

$21,000

$50,200

$3,840

$54,000

MUL057

$66,600

$47,000

$113,000

$8,660

$122,000

MUL058

$23,400,000

$16,000,000

$39,800,000

$2,260,000

$42,100,000

MUL059

$429,000

$300,000

$728,000

$73,000

$801,000

MUL060

$51,600

$36,000

$87,700

$5,670

$93,400

MUL063

$51,600

$36,000

$87,700

$5,670

$93,400

MUL065

$76,200

$53,000

$129,000

$8,370

$138,000

MUL071

$1,830,000

$1,300,000

$3,110,000

$220,000

$3,330,000

MUL073

$174,000

$120,000

$296,000

$22,600

$319,000

MUL081

$178,000

$120,000

$303,000

$20,500

$323,000

MUL083

$157,000

$110,000

$267,000

$17,300

$285,000

MUL103

$217,000

$150,000

$369,000

$25,400

$395,000

MUL119

$23,600

$17,000

$40,100

$3,070

$43,200

MUL120

$77,000

$54,000

$131,000

$9,180

$140,000

MUL129

$273,000

$190,000

$464,000

$30,000

$494,000

MUL131

$125,000

$88,000

$213,000

$21,300

$234,000

MUL132

$34,200

$24,000

$58,100

$5,820

$63,900

MUL135

$15,200

$11,000

$25,800

$1,970

$27,800

MUL136

$10,100

$7,100

$17,200

$1,320

$18,500

MUL139

$3,800

$2,700

$6,460

$647

$7,100

MUL141

$136,000

$95,000

$231,000

$15,600

$247,000

MUL142

$484,000

$340,000

$822,000

$55,500

$878,000

MUL145

$59,300

$41,000

$101,000

$6,790

$107,000

Page 7 of 8


-------
TABLE D-39

Summary of Total Estimated Costs by Site, Alternative 3+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Segment ID

Source ID

2009 Total
Direct Capital
Cost

2009 Indirect
Capital Cost

2009 Total
Direct and
Indirect Capital
Cost

O&M Cost (30-
Year NPV)

Total Cost (30-
Year NPV)



MUL146

$430,000

$300,000

$730,000

$35,400

$766,000



MUL149

$79,600

$56,000

$135,000

$9,140

$145,000



MUL150

$213,000

$150,000

$362,000

$24,400

$386,000



MUL153

$107,000

$75,000

$182,000

$12,300

$195,000



THO020

$71,300

$50,000

$121,000

$7,830

$129,000



UG01-10

$445,000

$310,000

$756,000

$148,000

$904,000



UG01-11

$238,000

$170,000

$405,000

$64,000

$469,000



UG01-12

$1,660,000

$1,200,000

$2,810,000

$508,000

$3,320,000



UG01-13

$651,000

$460,000

$1,110,000

$232,000

$1,340,000



UG01-14

$123,000

$86,000

$210,000

$44,000

$254,000



UG01-15

$371,000

$260,000

$631,000

$147,000

$778,000



UG01-16

$911,000

$640,000

$1,550,000

$244,000

$1,790,000



UG01-17

$2,190,000

$1,500,000

$3,730,000

$569,000

$4,300,000



UG01-18

$641,000

$450,000

$1,090,000

$256,000

$1,350,000



UG01-19

$167,000

$120,000

$283,000

$47,500

$331,000



UG01-4

$11,600

$8,100

$19,700

$3,480

$23,200



UG01-5

$377,000

$260,000

$642,000

$131,000

$773,000



UG01-6

$1,370,000

$960,000

$2,330,000

$323,000

$2,650,000



UG01-7

$510,000

$360,000

$868,000

$147,000

$1,010,000



UG01-8

$71,100

$50,000

$121,000

$29,800

$151,000



UG01-9

$601,000

$420,000

$1,020,000

$198,000

$1,220,000



WAL013

$83,500

$58,000

$142,000

$9,180

$151,000



WAL038

$10,200,000

$7,200,000

$17,400,000

$690,000

$18,100,000



WAL076

$775,000

$540,000

$1,320,000

$132,000

$1,450,000



WAL077

$1,540,000

$1,100,000

$2,620,000

$104,000

$2,720,000

Notes:

This Table does not include Central Treatment Plant (CTP) Sludge Pond Closure costs, these costs will be applied to the Total Alternative Cost.

This Table does not include Roads and Bridges costs, these costs will be applied to the Total Alternative Cost.

O&M = Operations and Maintenance
NPV = Net Present Value

NOTE: The above costs are presented rounded to three significant figures

NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of -30 percent to +50 percent (-30/+50%).

NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-magnitude cost opinion shown has been prepared for
guidance in project evaluation from the information available at the time of preparation. The final costs of the project will depend on actual labor and material
costs, actual site conditions, productivity, competitive market conditions, the final project scope, the final project schedule, and other variable factors. As a
result, the final project costs will vary from those presented above. Because of these factors, funding needs must be carefully reviewed prior to making
specific financial decisions or establishing final budgets.

Page 8 of 8


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site





2009 Total



2009 Total Direct









Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Segment ID

Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)

BigCrkSegOl

POL044

$5,500

$3,800

$9,340

$496

$9,840



POL045

$16,000

$11,000

$27,200

$2,080

$29,300



POL046

$15,200

$11,000

$25,800

$1,970

$27,800



POL047

$18,500

$13,000

$31,500

$2,410

$33,900



POL048

$14,300

$10,000

$24,300

$1,860

$26,200



POL049

$11,000

$7,700

$18,700

$1,420

$20,100



POL050

$18,500

$13,000

$31,500

$2,410

$33,900



POL051

$33,400

$23,000

$56,800

$4,340

$61,100



POL052

$126,000

$89,000

$215,000

$11,400

$226,000

BigCrkSeg02

POL024

$16,900

$12,000

$28,700

$2,190

$30,900



POL025

$22,800

$16,000

$38,700

$2,960

$41,700



POL026

$19,400

$14,000

$33,000

$2,520

$35,500



POL027

$39,600

$28,000

$67,300

$5,150

$72,500



POL028

$11,000

$7,700

$18,700

$1,420

$20,100



POL036

$43,000

$30,000

$73,100

$5,590

$78,700



POL037

$23,600

$17,000

$40,100

$3,070

$43,200



POL038

$14,300

$10,000

$24,300

$1,860

$26,200



POL039

$17,700

$12,000

$30,100

$2,300

$32,400



POL040

$78,500

$55,000

$133,000

$10,200

$144,000



POL041

$31,200

$22,000

$53,000

$4,050

$57,100



POL042

$28,700

$20,000

$48,800

$3,730

$52,500



POL043

$29,500

$21,000

$50,200

$3,840

$54,000



POL053

$21,100

$15,000

$35,900

$2,740

$38,600



POL054

$25,300

$18,000

$43,000

$3,290

$46,300



POL056

$35,400

$25,000

$60,200

$4,600

$64,800



POL062

$27,000

$19,000

$45,900

$3,510

$49,400



POL063

$18,500

$13,000

$31,500

$2,410

$33,900

BigCrkSeg03

POL001

$224,000

$160,000

$381,000

$20,200

$401,000



POL002

$279,000

$200,000

$475,000

$553,000

$1,030,000



POL004

$330,000

$230,000

$560,000

$1,030,000

$1,590,000



POL067

$572,000

$400,000

$973,000

$1,220,000

$2,190,000



POL068

$5,500

$3,800

$9,340

$496

$9,840



POL069

$24,400

$17,000

$41,500

$3,180

$44,700



POL070

$35,100

$25,000

$59,600

$4,560

$64,200



POL071

$23,400

$16,000

$39,800

$3,040

$42,800

BigCrkSeg04

BIG04-2

$239,000

$170,000

$406,000

$71,500

$477,000



BIG04-3

$2,450,000

$1,700,000

$4,160,000

$572,000

$4,730,000



KLE024

$19,600,000

$14,000,000

$33,300,000

$2,810,000

$36,100,000



KLE025

$11,500,000

$8,000,000

$19,500,000

$1,020,000

$20,500,000



KLE026

$2,420,000

$1,700,000

$4,110,000

$218,000

$4,330,000



KLE027

$2,560,000

$1,800,000

$4,350,000

$231,000

$4,580,000



KLE029

$187,000

$130,000

$318,000

$24,300

$342,000



KLE047

$122,000

$85,000

$207,000

$8,230

$216,000



KLE053

$5,400,000

$3,800,000

$9,190,000

$487,000

$9,670,000



KLE054

$5,120,000

$3,600,000

$8,700,000

$1,060,000

$9,760,000



KLE071

$1,800,000

$1,300,000

$3,060,000

$121,000

$3,180,000



KLE073

$3,670,000

$2,600,000

$6,240,000

$248,000

$6,490,000



POL005

$56,800

$40,000

$96,500

$7,380

$104,000



POL006

$31,700

$22,000

$53,900

$4,120

$58,000



POL008

$224,000

$160,000

$381,000

$20,200

$401,000



POL010

$125,000

$88,000

$213,000

$11,300

$224,000



POL011

$85,700

$60,000

$146,000

$7,730

$153,000



POL022

$274,000

$190,000

$466,000

$540,000

$1,010,000



POL023

$50,100

$35,000

$85,200

$6,510

$91,700



POL066

$5,500

$3,800

$9,340

$496

$9,840



POL075

$33,400

$23,000

$56,800

$4,340

$61,100

Page 1 of 14


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site





2009 Total



2009 Total Direct









Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Segment ID

Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)

CCS eg

PIPECC

$7,400,000

$5,200,000

$12,600,000

$592,000

$13,200,000

CCSegOl

BUR102

$120,000

$84,000

$204,000

$15,600

$219,000



BUR105

$123,000

$86,000

$210,000

$21,000

$231,000



BUR109

$590,000

$440,000

$1,030,000

$136,000

$1,160,000



BUR110

$24,400

$17,000

$41,500

$3,180

$44,700



BUR182

$13,500

$9,400

$22,900

$1,750

$24,700



BUR183

$18,500

$13,000

$31,500

$2,410

$33,900



BUR184

$17,700

$12,000

$30,100

$2,300

$32,400



BUR185

$3,800

$2,700

$6,460

$647

$7,100



BUR186

$20,200

$14,000

$34,400

$2,630

$37,000



BUR187

$3,800

$2,700

$6,460

$647

$7,100



BUR188

$36,200

$25,000

$61,600

$4,710

$66,300



THO012

$27,800

$20,000

$47,300

$3,620

$50,900



THO013

$29,500

$21,000

$50,200

$3,840

$54,000



THO014

$23,600

$17,000

$40,100

$3,070

$43,200



THO015

$34,600

$24,000

$58,800

$4,490

$63,300



THO016

$11,000

$7,700

$18,700

$1,420

$20,100



THO017

$45,500

$32,000

$77,400

$5,920

$83,300



THO018

$16,900

$12,000

$28,700

$2,190

$30,900



THO023

$3,800

$2,700

$6,460

$647

$7,100

CCSeg02

BUR100

$21,100

$15,000

$35,900

$2,740

$38,600



BUR106

$21,100

$15,000

$35,900

$2,740

$38,600



BUR107

$2,700,000

$1,900,000

$4,620,000

$497,000

$5,120,000



BUR130

$56,900

$40,000

$96,800

$9,700

$106,000



BUR131

$37,900

$27,000

$64,500

$4,930

$69,400



BUR132

$1,740,000

$1,200,000

$2,970,000

$298,000

$3,270,000



BUR133

$101,000

$70,000

$171,000

$17,100

$188,000



BUR134

$274,000

$190,000

$465,000

$46,600

$511,000



BUR135

$3,800

$2,700

$6,460

$647

$7,100



BUR138

$48,900

$34,000

$83,100

$6,360

$89,500



BUR145

$1,060,000

$740,000

$1,810,000

$181,000

$1,990,000



BUR150

$896,000

$630,000

$1,520,000

$80,800

$1,600,000



BUR151

$148,000

$100,000

$252,000

$19,300

$271,000



BUR153

$1,290,000

$900,000

$2,190,000

$86,700

$2,270,000



CC02-1

$1,600,000

$1,100,000

$2,720,000

$374,000

$3,100,000

CCSeg03

BUR085

$537,000

$380,000

$913,000

$1,200,000

$2,110,000



BUR086

$141,000

$99,000

$240,000

$18,300

$258,000



BUR087

$545,000

$400,000

$948,000

$128,000

$1,080,000



BUR088

$70,000

$71,000

$141,000

$47,400

$189,000



BUR089

$3,800

$2,700

$6,460

$647

$7,100



BUR090

$1,870,000

$1,300,000

$3,180,000

$252,000

$3,430,000



BUR091

$94,400

$88,000

$183,000

$50,600

$233,000



BUR092

$16,000

$11,000

$27,200

$2,080

$29,300



BUR099

$87,700

$84,000

$171,000

$49,700

$221,000



BUR101

$20,200

$14,000

$34,400

$2,630

$37,000



BUR146

$1,870,000

$1,300,000

$3,180,000

$126,000

$3,310,000



BUR149

$198,000

$140,000

$336,000

$33,600

$369,000



BUR165

$17,700

$12,000

$30,100

$2,300

$32,400



BUR166

$3,800

$2,700

$6,460

$647

$7,100



BUR167

$35,400

$25,000

$60,200

$4,600

$64,800



BUR179

$20,200

$14,000

$34,400

$2,630

$37,000



BUR180

$104,000

$73,000

$178,000

$17,800

$195,000

CCSeg04

BUR063

$159,000

$110,000

$271,000

$20,700

$292,000



BUR064

$34,600

$24,000

$58,800

$4,490

$63,300



BUR065

$85,100

$60,000

$145,000

$11,100

$156,000



BUR066

$192,000

$130,000

$327,000

$17,300

$344,000

Page 2 of 14


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Segment ID



2009 Total



2009 Total Direct







Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)

BUR067

$10,600,000

$7,800,000

$18,500,000

$1,600,000

$20,100,000

BUR068

$329,000

$230,000

$560,000

$29,700

$590,000

BUR069

$88,500

$62,000

$151,000

$11,500

$162,000

BUR070

$237,000

$170,000

$403,000

$30,800

$434,000

BUR071

$166,000

$120,000

$282,000

$21,600

$304,000

BUR072

$393,000

$270,000

$668,000

$35,400

$703,000

BUR073

$3,460,000

$2,400,000

$5,880,000

$312,000

$6,190,000

BUR074

$145,000

$100,000

$246,000

$18,800

$265,000

BUR075

$244,000

$170,000

$415,000

$27,900

$442,000

BUR076

$9,270

$6,500

$15,800

$1,210

$17,000

BUR093

$11,800

$8,300

$20,100

$1,530

$21,600

BUR094

$118,000

$83,000

$201,000

$15,300

$216,000

BUR095

$18,500

$13,000

$31,500

$2,410

$33,900

BUR096

$135,000

$96,000

$230,000

$21,000

$251,000

BUR097

$952,000

$990,000

$1,940,000

$670,000

$2,610,000

BUR098

$2,430,000

$2,000,000

$4,460,000

$1,030,000

$5,490,000

BUR111

$20,200

$14,000

$34,400

$2,630

$37,000

BUR112

$181,000

$150,000

$330,000

$61,900

$392,000

BUR113

$22,800

$16,000

$38,700

$2,960

$41,700

BUR114

$169,000

$140,000

$309,000

$60,200

$369,000

BUR115

$49,700

$35,000

$84,500

$6,470

$91,000

BUR116

$27,800

$20,000

$47,300

$3,620

$50,900

BUR117

$4,040,000

$2,800,000

$6,860,000

$363,000

$7,230,000

BUR118

$906,000

$630,000

$1,540,000

$81,800

$1,620,000

BUR119

$175,000

$120,000

$298,000

$22,800

$321,000

BUR120

$78,400

$55,000

$133,000

$10,200

$144,000

BUR121

$3,520,000

$2,700,000

$6,240,000

$774,000

$7,010,000

BUR122

$742,000

$520,000

$1,260,000

$66,900

$1,330,000

BUR123

$83,500

$81,000

$164,000

$49,200

$213,000

BUR124

$154,000

$130,000

$285,000

$58,400

$343,000

BUR125

$27,000

$19,000

$45,900

$3,510

$49,400

BUR126

$39,600

$28,000

$67,300

$5,150

$72,500

BUR127

$14,300

$10,000

$24,300

$1,860

$26,200

BUR128

$2,880,000

$2,000,000

$4,900,000

$327,000

$5,220,000

BUR129

$214,000

$170,000

$386,000

$60,400

$447,000

BUR141

$807,000

$570,000

$1,370,000

$54,500

$1,430,000

BUR142

$2,120,000

$1,500,000

$3,610,000

$192,000

$3,800,000

BUR143

$1,170,000

$820,000

$2,000,000

$79,300

$2,070,000

BUR144

$1,070,000

$750,000

$1,820,000

$96,600

$1,920,000

BUR174

$427,000

$300,000

$726,000

$55,500

$782,000

BUR175

$21,100

$15,000

$35,900

$2,740

$38,600

BUR176

$5,500

$3,800

$9,340

$496

$9,840

BUR177

$5,500

$3,800

$9,340

$496

$9,840

BUR178

$303,000

$210,000

$514,000

$27,300

$541,000

BUR189

$5,500

$3,800

$9,340

$496

$9,840

BUR190

$312,000

$330,000

$641,000

$167,000

$808,000

BUR191

$131,000

$92,000

$223,000

$17,000

$240,000

BUR192

$827,000

$580,000

$1,410,000

$74,600

$1,480,000

BUR193

$63,200

$44,000

$108,000

$8,220

$116,000

BUR194

$58,200

$41,000

$98,900

$7,560

$106,000

BUR195

$35,400

$25,000

$60,200

$4,600

$64,800

BUR198

$114,000

$80,000

$194,000

$14,800

$209,000

BUR199

$27,000

$19,000

$45,900

$3,510

$49,400

BUR200

$19,400

$14,000

$33,000

$2,520

$35,500

BUR202

$9,270

$6,500

$15,800

$1,210

$17,000

BUR203

$10,100

$7,100

$17,200

$1,320

$18,500

Page 3 of 14


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site



2009 Total



2009 Total Direct







Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)

BUR204

$5,500

$3,800

$9,340

$496

$9,840

CC04-1

$7,140,000

$5,000,000

$12,100,000

$1,540,000

$13,700,000

CCSeg05 CC05-1

$21,000,000

$15,000,000

$35,700,000

$3,820,000

$39,600,000

CC05-2

$6,890,000

$4,800,000

$11,700,000

$1,360,000

$13,100,000

OSB047

$624,000

$440,000

$1,060,000

$42,100

$1,100,000

WAL009

$69,500,000

$49,000,000

$118,000,000

$6,000,000

$124,000,000

WAL010

$551,000

$390,000

$937,000

$37,200

$974,000

WAL011

$702,000

$510,000

$1,220,000

$96,200

$1,310,000

WAL039

$343,000

$240,000

$584,000

$31,000

$615,000

WAL040

$661,000

$460,000

$1,120,000

$44,600

$1,170,000

WAL041

$1,320,000

$920,000

$2,250,000

$89,200

$2,330,000

WAL042

$16,800,000

$12,000,000

$28,500,000

$1,510,000

$30,000,000

WAL081

$157,000

$110,000

$266,000

$14,100

$280,000

MIDGradSeg PIPEMG

$12,600,000

$8,800,000

$21,400,000

$1,010,000

$22,400,000

MIDGradSegOl KLE004

$29,500

$21,000

$50,200

$3,840

$54,000

KLE005

$54,000

$38,000

$91,800

$7,010

$98,800

KLE006

$115,000

$81,000

$196,000

$15,000

$211,000

KLE011

$2,250,000

$1,600,000

$3,830,000

$203,000

$4,040,000

KLE016

$5,500

$3,800

$9,340

$496

$9,840

KLE020

$989,000

$690,000

$1,680,000

$89,200

$1,770,000

KLE021

$5,500

$3,800

$9,340

$496

$9,840

KLE022

$88,500

$62,000

$151,000

$11,500

$162,000

KLE023

$5,500

$3,800

$9,340

$496

$9,840

KLE032

$23,600

$17,000

$40,100

$3,070

$43,200

KLE033

$687,000

$480,000

$1,170,000

$62,000

$1,230,000

KLE034

$604,000

$420,000

$1,030,000

$54,500

$1,080,000

KLE035

$4,980,000

$3,500,000

$8,470,000

$516,000

$8,990,000

KLE036

$58,200

$41,000

$98,900

$7,560

$106,000

KLE038

$307,000

$220,000

$522,000

$39,900

$562,000

KLE039

$962,000

$670,000

$1,640,000

$86,700

$1,720,000

KLE040

$4,510,000

$3,300,000

$7,820,000

$887,000

$8,700,000

KLE042

$2,190,000

$1,500,000

$3,730,000

$156,000

$3,880,000

KLE048

$16,400,000

$12,000,000

$28,100,000

$1,230,000

$29,300,000

KLE049

$14,900,000

$11,000,000

$25,400,000

$1,200,000

$26,600,000

KLE051

$5,500

$3,800

$9,340

$496

$9,840

KLE056

$30,300

$21,000

$51,500

$3,950

$55,500

KLE057

$15,200

$11,000

$25,800

$1,970

$27,800

KLE058

$19,400

$14,000

$33,000

$2,520

$35,500

KLE059

$11,800

$8,300

$20,100

$1,530

$21,600

KLE060

$20,200

$14,000

$34,400

$2,630

$37,000

KLE062

$1,230,000

$860,000

$2,090,000

$101,000

$2,200,000

KLE066

$5,500

$3,800

$9,340

$496

$9,840

KLE067

$1,030,000

$720,000

$1,760,000

$1,080,000

$2,840,000

KLE068

$385,000

$270,000

$654,000

$34,700

$688,000

KLE069

$35,700

$25,000

$60,700

$3,220

$63,900

KLE070

$5,500

$3,800

$9,340

$496

$9,840

KLE074

$2,070,000

$1,400,000

$3,520,000

$254,000

$3,780,000

KLE075

$110,000

$77,000

$187,000

$9,910

$197,000

MG01-1

$217,000

$150,000

$368,000

$59,300

$428,000

MG01-10

$3,560,000

$2,500,000

$6,040,000

$659,000

$6,700,000

MG01-11

$389,000

$270,000

$662,000

$96,100

$758,000

MG01-12

$460,000

$320,000

$782,000

$110,000

$891,000

MG01-13

$5,180,000

$3,600,000

$8,810,000

$979,000

$9,790,000

MG01-14

$692,000

$480,000

$1,180,000

$138,000

$1,310,000

MG01-15

$3,070,000

$2,100,000

$5,220,000

$589,000

$5,810,000

MG01-16

$1,630,000

$1,100,000

$2,770,000

$314,000

$3,080,000

Page 4 of 14


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Segment ID



2009 Total



2009 Total Direct







Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)

MG01-17

$4,570,000

$3,200,000

$7,780,000

$871,000

$8,650,000

MG01-18

$1,810,000

$1,300,000

$3,080,000

$350,000

$3,430,000

MG01-2

$264,000

$180,000

$448,000

$63,100

$511,000

MG01-3

$847,000

$590,000

$1,440,000

$187,000

$1,630,000

MG01-4

$1,430,000

$1,000,000

$2,430,000

$323,000

$2,750,000

MG01-5

$987,000

$690,000

$1,680,000

$196,000

$1,870,000

MG01-6

$5,770,000

$4,000,000

$9,810,000

$1,110,000

$10,900,000

MG01-7

$1,570,000

$1,100,000

$2,660,000

$358,000

$3,020,000

MG01-8

$7,550,000

$5,300,000

$12,800,000

$1,400,000

$14,200,000

MG01-9

$454,000

$320,000

$771,000

$91,600

$863,000

MUL085

$1,110,000

$780,000

$1,880,000

$1,680,000

$3,560,000

MUL086

$824,000

$580,000

$1,400,000

$74,300

$1,480,000

MUL087

$31,200

$22,000

$53,000

$4,050

$57,100

OSB024

$54,800

$38,000

$93,200

$7,120

$100,000

OSB025

$329,000

$230,000

$560,000

$29,700

$590,000

OSB026

$65,800

$46,000

$112,000

$8,550

$120,000

OSB027

$100,000

$70,000

$170,000

$13,000

$183,000

OSB028

$9,270

$6,500

$15,800

$1,210

$17,000

OSB030

$5,500

$3,800

$9,340

$496

$9,840

OSB065

$103,000,000

$72,000,000

$175,000,000

$4,110,000

$179,000,000

OSB070

$852,000

$600,000

$1,450,000

$76,800

$1,520,000

OSB071

$27,000

$19,000

$45,900

$3,510

$49,400

OSB072

$5,500

$3,800

$9,340

$496

$9,840

OSB073

$604,000

$420,000

$1,030,000

$54,500

$1,080,000

OSB074

$524,000

$370,000

$890,000

$1,190,000

$2,080,000

OSB075

$5,500

$3,800

$9,340

$496

$9,840

OSB076

$154,000

$110,000

$262,000

$530,000

$792,000

OSB078

$5,500

$3,800

$9,340

$496

$9,840

OSB079

$13,500

$9,400

$22,900

$1,750

$24,700

OSB080

$173,000

$120,000

$295,000

$533,000

$828,000

OSB117

$385,000

$270,000

$654,000

$34,700

$688,000

OSB118

$2,200,000

$1,500,000

$3,740,000

$149,000

$3,890,000

OSB119

$22,900,000

$16,000,000

$38,900,000

$1,040,000

$39,900,000

OSB120

$72,300,000

$51,000,000

$123,000,000

$3,300,000

$126,000,000

POL015

$27,000

$19,000

$45,900

$3,510

$49,400

POL016

$25,300

$18,000

$43,000

$3,290

$46,300

POL017

$21,100

$15,000

$35,900

$2,740

$38,600

POL018

$604,000

$420,000

$1,030,000

$54,500

$1,080,000

POL019

$5,500,000

$3,800,000

$9,340,000

$496,000

$9,840,000

POL020

$16,000

$11,000

$27,200

$2,080

$29,300

POL021

$5,500

$3,800

$9,340

$496

$9,840

POL029

$13,500

$9,400

$22,900

$1,750

$24,700

POL030

$40,500

$28,000

$68,800

$5,260

$74,100

POL031

$36,200

$25,000

$61,600

$4,710

$66,300

POL032

$19,400

$14,000

$33,000

$2,520

$35,500

POL033

$19,400

$14,000

$33,000

$2,520

$35,500

POL034

$69,100

$48,000

$118,000

$8,990

$126,000

POL035

$165,000

$120,000

$281,000

$21,500

$303,000

POL055

$37,900

$27,000

$64,500

$4,930

$69,400

POL057

$15,200

$11,000

$25,800

$1,970

$27,800

POL058

$19,400

$14,000

$33,000

$2,520

$35,500

POL059

$22,800

$16,000

$38,700

$2,960

$41,700

POL060

$17,700

$12,000

$30,100

$2,300

$32,400

POL061

$32,000

$22,000

$54,400

$4,160

$58,600

POL064

$5,500

$3,800

$9,340

$496

$9,840

POL065

$17,700

$12,000

$30,100

$2,300

$32,400

Page 5 of 14


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Segment ID



2009 Total



2009 Total Direct







Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)

POL077

$16,900

$12,000

$28,700

$2,190

$30,900

POL078

$13,500

$9,400

$22,900

$1,750

$24,700

POL079

$15,200

$11,000

$25,800

$1,970

$27,800

POL080

$13,500

$9,400

$22,900

$1,750

$24,700

POL081

$18,500

$13,000

$31,500

$2,410

$33,900

POL082

$18,500

$13,000

$31,500

$2,410

$33,900

POL083

$15,200

$11,000

$25,800

$1,970

$27,800

POL084

$13,500

$9,400

$22,900

$1,750

$24,700

POL085

$11,800

$8,300

$20,100

$1,530

$21,600

POL086

$15,200

$11,000

$25,800

$1,970

$27,800

POL087

$15,200

$11,000

$25,800

$1,970

$27,800

POL088

$27,000

$19,000

$45,900

$3,510

$49,400

POL089

$18,500

$13,000

$31,500

$2,410

$33,900

POL090

$9,270

$6,500

$15,800

$1,210

$17,000

POL091

$16,000

$11,000

$27,200

$2,080

$29,300

POL092

$23,600

$17,000

$40,100

$3,070

$43,200

WAL001

$29,800,000

$21,000,000

$50,600,000

$3,550,000

$54,100,000

WAL002

$15,800

$11,000

$27,100

$2,600

$29,700

WAL003

$277,000

$190,000

$471,000

$36,100

$507,000

WAL004

$37,700,000

$27,000,000

$64,200,000

$1,810,000

$66,100,000

WAL005

$28,700

$20,000

$48,800

$3,730

$52,500

WAL014

$1,070,000

$750,000

$1,820,000

$96,600

$1,920,000

WAL016

$5,500

$3,800

$9,340

$496

$9,840

WAL017

$175,000

$120,000

$297,000

$22,700

$320,000

WAL019

$24,400

$17,000

$41,500

$3,180

$44,700

WAL020

$3,820,000

$2,700,000

$6,490,000

$344,000

$6,830,000

WAL021

$15,200

$11,000

$25,800

$1,970

$27,800

WAL022

$11,000

$7,700

$18,700

$1,420

$20,100

WAL023

$13,500

$9,400

$22,900

$1,750

$24,700

WAL024

$5,500

$3,800

$9,340

$496

$9,840

WAL025

$16,900

$12,000

$28,700

$2,190

$30,900

WAL026

$7,590

$5,300

$12,900

$986

$13,900

WAL027

$76,700

$54,000

$130,000

$9,970

$140,000

WAL028

$15,200

$11,000

$25,800

$1,970

$27,800

WAL029

$30,300

$21,000

$51,500

$3,950

$55,500

WAL034

$2,860,000

$2,000,000

$4,860,000

$193,000

$5,050,000

WAL035

$3,850,000

$2,700,000

$6,540,000

$347,000

$6,880,000

WAL036

$1,650,000

$1,200,000

$2,810,000

$112,000

$2,920,000

WAL037

$329,000

$230,000

$560,000

$29,700

$590,000

WAL046

$5,500

$3,800

$9,340

$496

$9,840

WAL047

$18,500

$13,000

$31,500

$2,410

$33,900

WAL048

$102,000

$71,000

$173,000

$13,300

$187,000

WAL049

$95,300

$67,000

$162,000

$12,400

$174,000

WAL050

$70,800

$50,000

$120,000

$9,210

$130,000

WAL051

$54,000

$38,000

$91,800

$7,010

$98,800

WAL052

$70,800

$50,000

$120,000

$9,210

$130,000

WAL053

$27,000

$19,000

$45,900

$3,510

$49,400

WAL054

$58,200

$41,000

$98,900

$7,560

$106,000

WAL055

$5,500

$3,800

$9,340

$496

$9,840

WAL056

$5,500

$3,800

$9,340

$496

$9,840

WAL057

$5,500

$3,800

$9,340

$496

$9,840

WAL058

$5,500

$3,800

$9,340

$496

$9,840

WAL059

$35,400

$25,000

$60,200

$4,600

$64,800

WAL060

$20,200

$14,000

$34,400

$2,630

$37,000

WAL061

$32,000

$22,000

$54,400

$4,160

$58,600

WAL062

$5,500

$3,800

$9,340

$496

$9,840

Page 6 of 14


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site





2009 Total



2009 Total Direct









Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Segment ID

Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)



WAL063

$24,400

$17,000

$41,500

$3,180

$44,700



WAL064

$5,500

$3,800

$9,340

$496

$9,840



WAL065

$31,200

$22,000

$53,000

$4,050

$57,100



WAL066

$27,800

$20,000

$47,300

$3,620

$50,900



WAL067

$58,200

$41,000

$98,900

$7,560

$106,000



WAL070

$59,900

$42,000

$102,000

$7,780

$110,000



WAL071

$16,900

$12,000

$28,700

$2,190

$30,900



WAL072

$5,500

$3,800

$9,340

$496

$9,840



WAL073

$5,500

$3,800

$9,340

$496

$9,840



WAL074

$21,900

$15,000

$37,200

$2,850

$40,100

MIDGradSeg02

KLW061

$2,320,000

$1,600,000

$3,940,000

$301,000

$4,240,000



KLW062

$356,000

$250,000

$605,000

$46,200

$651,000



KLW070

$342,000

$240,000

$583,000

$23,200

$606,000



KLW071

$576,000

$400,000

$979,000

$74,900

$1,050,000



KLW095

$137,000

$96,000

$233,000

$17,800

$251,000



KLW123

$15,200

$11,000

$25,800

$1,970

$27,800



KLW124

$61,800

$43,000

$105,000

$8,030

$113,000



KLW125

$38,400

$27,000

$65,300

$4,990

$70,300



KLW126

$21,900

$15,000

$37,200

$2,850

$40,100



KLW127

$21,700

$15,000

$36,900

$2,820

$39,700



KLW128

$212,000

$150,000

$360,000

$27,600

$388,000



MAS070

$33,700

$24,000

$57,300

$4,380

$61,700



MG02-10

$50,500

$35,000

$85,800

$13,100

$98,900



MG02-11

$43,900

$31,000

$74,600

$11,400

$86,000



MG02-12

$18,900

$13,000

$32,100

$4,920

$37,000



KLE007

$104,000

$73,000

$177,000

$13,500

$190,000



KLE061

$5,500

$3,800

$9,340

$496

$9,840



MC01-2

$498,000

$350,000

$847,000

$174,000

$1,020,000



KLE008

$109,000

$76,000

$185,000

$14,100

$199,000



KLE009

$116,000

$81,000

$197,000

$15,100

$213,000



KLE013

$88,500

$62,000

$151,000

$11,500

$162,000



KLE014

$5,500

$3,800

$9,340

$496

$9,840



KLE041

$121,000

$85,000

$206,000

$8,180

$214,000



KLE063

$25,100

$18,000

$42,600

$3,260

$45,900



KLE064

$21,700

$15,000

$36,900

$2,820

$39,700



KLE065

$38,400

$27,000

$65,300

$4,990

$70,300



MC02-2

$817,000

$570,000

$1,390,000

$192,000

$1,580,000



MC02-3

$477,000

$330,000

$810,000

$116,000

$926,000



MC02-4

$370,000

$260,000

$629,000

$87,600

$716,000

NMSeg

PIPENM

$1,560,000

$1,100,000

$2,650,000

$125,000

$2,780,000

NMSegOl

BUR051

$656,000

$460,000

$1,110,000

$1,210,000

$2,330,000



BUR052

$75,900

$53,000

$129,000

$12,900

$142,000



BUR053

$13,200,000

$9,200,000

$22,400,000

$2,240,000

$24,600,000



BUR077

$96,100

$67,000

$163,000

$12,500

$176,000



BUR081

$554,000

$390,000

$942,000

$1,200,000

$2,140,000



BUR082

$35,400

$25,000

$60,200

$4,600

$64,800



BUR083

$27,000

$19,000

$45,900

$3,510

$49,400



BUR084

$22,800

$16,000

$38,700

$2,960

$41,700



BUR140

$367,000

$260,000

$624,000

$24,800

$649,000



NM01-1

$1,050,000

$730,000

$1,780,000

$283,000

$2,070,000

NMSeg 02

BUR054

$8,470,000

$5,900,000

$14,400,000

$1,290,000

$15,700,000



BUR055

$587,000

$410,000

$997,000

$48,300

$1,040,000



BUR056

$8,050,000

$5,600,000

$13,700,000

$726,000

$14,400,000



BUR057

$76,700

$54,000

$130,000

$9,970

$140,000



BUR058

$584,000

$410,000

$993,000

$1,200,000

$2,200,000



BUR059

$147,000

$100,000

$250,000

$19,100

$269,000

Page 7 of 14


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site



2009 Total



2009 Total Direct







Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)

BUR060

$180,000

$130,000

$306,000

$23,500

$330,000

BUR061

$120,000

$84,000

$204,000

$15,600

$219,000

BUR062

$57,300

$40,000

$97,400

$7,450

$105,000

BUR170

$765,000

$540,000

$1,300,000

$1,190,000

$2,490,000

BUR171

$340,000

$240,000

$577,000

$1,060,000

$1,640,000

BUR196

$26,100

$18,000

$44,400

$3,400

$47,800

BUR197

$38,800

$27,000

$65,900

$5,040

$70,900

BUR205

$54,800

$38,000

$93,200

$7,120

$100,000

NM02-1

$1,990,000

$1,400,000

$3,390,000

$535,000

$3,920,000

OSB040

$697,000

$490,000

$1,190,000

$47,100

$1,230,000

OSB044

$10,700,000

$7,500,000

$18,200,000

$959,000

$19,200,000

OSB045

$70,800

$50,000

$120,000

$9,210

$130,000

OSB046

$29,500

$21,000

$50,200

$3,840

$54,000

OSB048

$12,600

$8,900

$21,500

$1,640

$23,100

OSB056

$58,700

$41,000

$99,700

$3,960

$104,000

OSB057

$477,000

$330,000

$811,000

$32,200

$844,000

OSB058

$58,700

$41,000

$99,700

$3,960

$104,000

OSB088

$13,600

$11,000

$24,600

$4,710

$29,300

OSB089

$20,300

$18,000

$38,400

$10,400

$48,800

NMSeg03 NM03-1

$994,000

$700,000

$1,690,000

$217,000

$1,910,000

OSB041

$69,100

$48,000

$118,000

$8,990

$126,000

OSB042

$16,000

$11,000

$27,200

$2,080

$29,300

OSB043

$113,000

$79,000

$192,000

$14,700

$207,000

OSB049

$46,400

$33,000

$78,900

$6,030

$84,900

OSB081

$11,800

$8,300

$20,100

$1,530

$21,600

OSB087

$8,430

$5,900

$14,300

$1,100

$15,400

NMSeg04 NM04-1

$1,860,000

$1,300,000

$3,160,000

$372,000

$3,530,000

NM04-2

$735,000

$510,000

$1,250,000

$145,000

$1,390,000

NM04-3

$5,090,000

$3,600,000

$8,670,000

$1,020,000

$9,680,000

OSB031

$47,200

$33,000

$80,200

$6,140

$86,300

OSB032

$550,000

$380,000

$934,000

$49,600

$984,000

OSB033

$439,000

$310,000

$747,000

$39,600

$786,000

OSB034

$25,300

$18,000

$43,000

$3,290

$46,300

OSB035

$41,300

$29,000

$70,200

$5,370

$75,600

OSB036

$21,100

$15,000

$35,900

$2,740

$38,600

OSB037

$59,900

$42,000

$102,000

$7,780

$110,000

OSB038

$852,000

$600,000

$1,450,000

$76,800

$1,520,000

OSB039

$3,800,000

$2,700,000

$6,470,000

$435,000

$6,900,000

OSB052

$5,500,000

$3,800,000

$9,340,000

$496,000

$9,840,000

OSB055

$44,000

$32,000

$76,300

$8,750

$85,100

OSB059

$1,210,000

$850,000

$2,060,000

$81,800

$2,140,000

OSB060

$29,400

$21,000

$49,900

$1,980

$51,900

OSB061

$192,000

$130,000

$327,000

$17,300

$344,000

OSB082

$357,000

$250,000

$607,000

$32,200

$639,000

OSB083

$64,900

$45,000

$110,000

$8,440

$119,000

OSB114

$18,500

$13,000

$31,500

$2,410

$33,900

OSB115

$5,500

$3,800

$9,340

$496

$9,840

OSB116

$26,100

$18,000

$44,400

$3,400

$47,800

WAL006

$5,500

$3,800

$9,340

$496

$9,840

WAL033

$1,250,000

$870,000

$2,120,000

$84,300

$2,210,000

WAL069

$20,200

$14,000

$34,400

$2,630

$37,000

WAL075

$7,590

$5,300

$12,900

$986

$13,900

WAL078

$22,800

$16,000

$38,700

$2,960

$41,700

PineCrkSegOl MAS004

$403,000

$280,000

$685,000

$1,060,000

$1,750,000

MAS005

$24,400

$17,000

$41,500

$3,180

$44,700

MAS006

$1,150,000

$810,000

$1,960,000

$104,000

$2,070,000

Page 8 of 14


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Segment ID



2009 Total



2009 Total Direct







Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)

MAS007

$1,680,000

$1,200,000

$2,850,000

$716,000

$3,570,000

MAS008

$687,000

$480,000

$1,170,000

$62,000

$1,230,000

MAS009

$349,000

$240,000

$594,000

$547,000

$1,140,000

MAS011

$146,000

$100,000

$248,000

$529,000

$777,000

MAS012

$516,000

$360,000

$878,000

$1,190,000

$2,070,000

MAS013

$129,000

$90,000

$220,000

$11,600

$231,000

MAS014

$1,580,000

$1,100,000

$2,690,000

$2,480,000

$5,170,000

MAS015

$189,000

$130,000

$321,000

$532,000

$853,000

MAS016

$784,000

$550,000

$1,330,000

$586,000

$1,920,000

MAS017

$2,220,000

$1,600,000

$3,780,000

$1,350,000

$5,130,000

MAS018

$74,200

$52,000

$126,000

$6,690

$133,000

MAS019

$27,500

$19,000

$46,700

$2,480

$49,200

MAS020

$401,000

$280,000

$681,000

$552,000

$1,230,000

MAS021

$426,000

$300,000

$724,000

$1,140,000

$1,870,000

MAS022

$1,320,000

$920,000

$2,240,000

$119,000

$2,360,000

MAS023

$27,500

$19,000

$46,700

$2,480

$49,200

MAS025

$1,690,000

$1,200,000

$2,870,000

$749,000

$3,620,000

MAS027

$192,000

$130,000

$327,000

$17,300

$344,000

MAS028

$297,000

$210,000

$504,000

$26,800

$531,000

MAS029

$168,000

$120,000

$285,000

$531,000

$817,000

MAS030

$185,000

$130,000

$314,000

$16,700

$331,000

MAS031

$119,000

$83,000

$202,000

$10,700

$212,000

MAS032

$2,200

$1,500

$3,740

$198

$3,940

MAS033

$132,000

$92,000

$224,000

$11,900

$236,000

MAS034

$12,600

$8,900

$21,500

$1,640

$23,100

MAS035

$220,000

$150,000

$374,000

$19,800

$394,000

MAS036

$74,200

$52,000

$126,000

$6,690

$133,000

MAS040

$50,600

$35,000

$86,000

$3,420

$89,400

MAS041

$85,800

$60,000

$146,000

$5,800

$152,000

MAS042

$39,600

$28,000

$67,400

$2,680

$70,100

MAS043

$110,000

$77,000

$187,000

$7,430

$195,000

MAS045

$110,000

$77,000

$187,000

$7,430

$195,000

MAS046

$875,000

$610,000

$1,490,000

$59,100

$1,550,000

MAS048

$584,000

$410,000

$993,000

$52,700

$1,050,000

MAS049

$989,000

$690,000

$1,680,000

$89,200

$1,770,000

MAS050

$971,000

$680,000

$1,650,000

$1,200,000

$2,860,000

MAS051

$38,400

$27,000

$65,300

$4,990

$70,300

MAS052

$145,000

$100,000

$247,000

$13,100

$260,000

MAS053

$5,500

$3,800

$9,340

$496

$9,840

MAS054

$484,000

$340,000

$823,000

$566,000

$1,390,000

MAS055

$5,500

$3,800

$9,340

$496

$9,840

MAS056

$31,700

$22,000

$53,900

$4,120

$58,000

MAS057

$5,500

$3,800

$9,340

$496

$9,840

MAS058

$25,300

$18,000

$43,000

$3,290

$46,300

MAS059

$23,600

$17,000

$40,100

$3,070

$43,200

MAS060

$45,100

$32,000

$76,700

$5,860

$82,600

MAS061

$26,100

$18,000

$44,400

$3,400

$47,800

MAS062

$38,400

$27,000

$65,300

$4,990

$70,300

MAS063

$12,600

$8,900

$21,500

$1,640

$23,100

MAS065

$5,500

$3,800

$9,340

$496

$9,840

MAS067

$30,300

$21,000

$51,500

$3,950

$55,500

MAS068

$5,500

$3,800

$9,340

$496

$9,840

MAS069

$159,000

$110,000

$271,000

$20,700

$292,000

MAS072

$5,500

$3,800

$9,340

$496

$9,840

MAS075

$16,000

$11,000

$27,200

$2,080

$29,300

MAS076

$37,900

$27,000

$64,500

$4,930

$69,400

Page 9 of 14


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site





2009 Total



2009 Total Direct









Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Segment ID

Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)



MAS077

$91,900

$64,000

$156,000

$11,900

$168,000



MAS078

$364,000

$250,000

$617,000

$580,000

$1,200,000



MAS079

$1,030,000

$720,000

$1,740,000

$92,400

$1,830,000



MAS080

$36,200

$25,000

$61,600

$4,710

$66,300



MAS081

$177,000

$120,000

$301,000

$23,000

$324,000



MAS082

$104,000

$73,000

$177,000

$13,500

$190,000



MAS083

$1,020,000

$710,000

$1,730,000

$92,100

$1,830,000



MAS084

$824,000

$580,000

$1,400,000

$74,300

$1,480,000

PineCrkSeg02

TWI001

$47,200

$33,000

$80,200

$6,140

$86,300



TWI002

$158,000

$110,000

$269,000

$14,300

$283,000



TWI003

$13,500

$9,400

$22,900

$1,750

$24,700



TWI004

$19,400

$14,000

$33,000

$2,520

$35,500



TWI005

$25,300

$18,000

$43,000

$3,290

$46,300



TWI006

$132,000

$92,000

$224,000

$11,900

$236,000



TWI007

$41,800

$29,000

$71,000

$5,430

$76,400



TWI008

$5,500

$3,800

$9,340

$496

$9,840



TWI009

$178,000

$120,000

$303,000

$16,100

$319,000



TWI010

$55,100

$39,000

$93,700

$7,160

$101,000



TWI011

$5,500

$3,800

$9,340

$496

$9,840



TWI012

$106,000

$74,000

$179,000

$9,520

$189,000



TWI013

$211,000

$150,000

$359,000

$19,000

$378,000



TWI014

$165,000

$120,000

$280,000

$14,900

$295,000



TWI015

$53,400

$37,000

$90,800

$6,950

$97,800



TWI016

$41,800

$29,000

$71,000

$5,430

$76,400



TWI017

$22,800

$16,000

$38,700

$2,960

$41,700



TWI018

$5,500

$3,800

$9,340

$496

$9,840



TWI019

$55,100

$39,000

$93,700

$7,160

$101,000



TWI020

$5,500

$3,800

$9,340

$496

$9,840



TWI021

$18,500

$13,000

$31,500

$2,410

$33,900



TWI022

$61,500

$43,000

$105,000

$8,000

$113,000



TWI023

$42,200

$30,000

$71,700

$5,480

$77,200



TWI024

$35,400

$25,000

$60,200

$4,600

$64,800



TWI025

$25,300

$18,000

$43,000

$3,290

$46,300



TWI026

$116,000

$81,000

$197,000

$15,100

$213,000



TWI027

$5,500

$3,800

$9,340

$496

$9,840



TWI028

$30,100

$21,000

$51,100

$3,910

$55,000



TWI029

$5,500

$3,800

$9,340

$496

$9,840



TWI030

$5,500

$3,800

$9,340

$496

$9,840

PineCrkSeg03

KLW072

$87,700

$61,000

$149,000

$11,400

$161,000



KLW073

$231,000

$160,000

$393,000

$20,800

$413,000



KLW075

$468,000

$330,000

$796,000

$42,200

$838,000



KLW077

$303,000

$210,000

$515,000

$27,400

$543,000



KLW079

$264,000

$180,000

$449,000

$23,800

$472,000



KLW080

$137,000

$96,000

$233,000

$23,300

$256,000



KLW081

$166,000

$120,000

$281,000

$534,000

$815,000



KLW082

$224,000

$160,000

$381,000

$20,200

$401,000



KLW083

$382,000

$270,000

$649,000

$34,500

$684,000



KLW084

$28,700

$20,000

$48,800

$3,730

$52,500



KLW085

$396,000

$280,000

$672,000

$35,700

$708,000



MAS001

$91,000

$64,000

$155,000

$11,800

$167,000



MAS003

$476,000

$330,000

$808,000

$606,000

$1,410,000



MAS064

$21,100

$15,000

$35,900

$2,740

$38,600



MAS066

$5,500

$3,800

$9,340

$496

$9,840



PC03-1

$1,540,000

$1,100,000

$2,620,000

$331,000

$2,950,000



PC03-2

$1,280,000

$890,000

$2,170,000

$270,000

$2,440,000



PC03-3

$576,000

$400,000

$979,000

$127,000

$1,110,000

Page 10 of 14


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site



2009 Total



2009 Total Direct







Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)

UpperSFCDRSeg PIPEUG

$11,800,000

$8,300,000

$20,100,000

$947,000

$21,100,000

UpperSFCDRSegOl BUR136

$25,300

$18,000

$43,000

$3,290

$46,300

BUR137

$27,000

$19,000

$45,900

$3,510

$49,400

LOK001

$109,000

$76,000

$185,000

$14,100

$199,000

LOK002

$107,000

$75,000

$182,000

$13,900

$196,000

LOK003

$20,200

$14,000

$34,400

$2,630

$37,000

LOK004

$2,210,000

$1,500,000

$3,760,000

$1,360,000

$5,120,000

LOK005

$15,200

$11,000

$25,800

$1,970

$27,800

LOK006

$171,000

$120,000

$291,000

$15,500

$307,000

LOK007

$123,000

$86,000

$209,000

$21,000

$230,000

LOK008

$243,000

$190,000

$435,000

$76,900

$512,000

LOK009

$420,000

$290,000

$713,000

$71,400

$784,000

LOK010

$92,300

$65,000

$157,000

$8,330

$165,000

LOK011

$4,670,000

$4,600,000

$9,280,000

$2,810,000

$12,100,000

LOK012

$122,000

$86,000

$208,000

$15,900

$224,000

LOK013

$108,000

$76,000

$184,000

$14,000

$198,000

LOK014

$543,000

$380,000

$923,000

$1,200,000

$2,120,000

LOK015

$10,100

$7,100

$17,200

$1,320

$18,500

LOK016

$69,100

$48,000

$118,000

$8,990

$126,000

LOK017

$1,020,000

$710,000

$1,730,000

$611,000

$2,340,000

LOK018

$47,200

$33,000

$80,200

$6,140

$86,300

LOK019

$254,000

$180,000

$432,000

$543,000

$975,000

LOK020

$45,500

$32,000

$77,400

$5,920

$83,300

LOK021

$96,100

$67,000

$163,000

$12,500

$176,000

LOK022

$124,000

$87,000

$211,000

$16,100

$227,000

LOK024

$614,000

$430,000

$1,040,000

$1,210,000

$2,250,000

LOK025

$32,000

$22,000

$54,400

$4,160

$58,600

LOK026

$28,700

$20,000

$48,800

$3,730

$52,500

LOK027

$16,000

$11,000

$27,200

$2,080

$29,300

LOK028

$541,000

$380,000

$920,000

$1,200,000

$2,120,000

LOK041

$79,200

$56,000

$135,000

$10,300

$145,000

LOK044

$127,000

$89,000

$216,000

$16,500

$232,000

LOK045

$31,200

$22,000

$53,000

$4,050

$57,100

LOK047

$191,000

$130,000

$324,000

$24,800

$349,000

LOK048

$123,000

$86,000

$209,000

$21,000

$230,000

LOK050

$357,000

$250,000

$607,000

$32,200

$639,000

LOK051

$1,260,000

$880,000

$2,140,000

$114,000

$2,250,000

LOK052

$26,100

$18,000

$44,400

$3,400

$47,800

LOK053

$26,100

$18,000

$44,400

$3,400

$47,800

LOK054

$11,000

$7,700

$18,700

$1,420

$20,100

MUL001

$2,090,000

$1,500,000

$3,570,000

$203,000

$3,770,000

MUL002

$631,000

$440,000

$1,070,000

$57,000

$1,130,000

MUL003

$231,000

$160,000

$393,000

$30,000

$423,000

MUL004

$540,000

$380,000

$919,000

$48,800

$968,000

MUL005

$28,700

$20,000

$48,800

$3,730

$52,500

MUL006

$481,000

$340,000

$818,000

$43,400

$861,000

MUL007

$80,100

$56,000

$136,000

$10,400

$147,000

MUL008

$906,000

$630,000

$1,540,000

$81,800

$1,620,000

MUL009

$21,100

$15,000

$35,900

$2,740

$38,600

MUL010

$27,000

$19,000

$45,900

$3,510

$49,400

MUL011

$12,600

$8,900

$21,500

$1,640

$23,100

MUL012

$4,320,000

$3,100,000

$7,420,000

$898,000

$8,320,000

MUL013

$115,000

$100,000

$217,000

$53,300

$271,000

MUL014

$1,260,000

$1,300,000

$2,540,000

$859,000

$3,400,000

MUL015

$436,000

$310,000

$742,000

$74,400

$817,000

MUL016

$46,400

$33,000

$78,900

$6,030

$84,900

Page 11 of 14


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Segment ID



2009 Total



2009 Total Direct







Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)

MUL017

$45,500

$32,000

$77,400

$5,920

$83,300

MUL018

$396,000

$280,000

$672,000

$35,700

$708,000

MUL019

$13,800,000

$9,900,000

$23,700,000

$1,800,000

$25,500,000

MUL020

$7,830,000

$5,500,000

$13,300,000

$654,000

$14,000,000

MUL021

$797,000

$560,000

$1,360,000

$72,000

$1,430,000

MUL022

$29,500

$21,000

$50,200

$3,840

$54,000

MUL023

$1,360,000

$950,000

$2,310,000

$1,270,000

$3,580,000

MUL024

$690,000

$480,000

$1,170,000

$1,220,000

$2,390,000

MUL025

$85,100

$60,000

$145,000

$11,100

$156,000

MUL026

$170,000

$120,000

$289,000

$22,100

$311,000

MUL027

$682,000

$480,000

$1,160,000

$626,000

$1,780,000

MUL028

$2,330,000

$1,600,000

$3,970,000

$932,000

$4,900,000

MUL029

$387,000

$270,000

$658,000

$66,000

$724,000

MUL030

$164,000

$110,000

$279,000

$27,900

$307,000

MUL031

$155,000

$110,000

$263,000

$26,400

$290,000

MUL032

$28,700

$20,000

$48,800

$3,730

$52,500

MUL033

$301,000

$210,000

$511,000

$51,200

$563,000

MUL034

$73,500

$51,000

$125,000

$9,550

$134,000

MUL035

$25,300

$18,000

$43,000

$3,290

$46,300

MUL036

$23,600

$17,000

$40,100

$3,070

$43,200

MUL037

$9,530,000

$6,700,000

$16,200,000

$720,000

$16,900,000

MUL038

$2,190,000

$1,500,000

$3,710,000

$197,000

$3,910,000

MUL040

$16,000

$11,000

$27,200

$2,080

$29,300

MUL041

$314,000

$220,000

$534,000

$40,800

$575,000

MUL042

$265,000

$180,000

$449,000

$45,000

$494,000

MUL043

$333,000

$230,000

$566,000

$56,700

$622,000

MUL045

$524,000

$370,000

$891,000

$89,300

$980,000

MUL046

$29,500

$21,000

$50,200

$3,840

$54,000

MUL047

$105,000

$73,000

$178,000

$17,900

$196,000

MUL048

$586,000

$410,000

$998,000

$52,900

$1,050,000

MUL049

$25,300

$18,000

$43,000

$3,290

$46,300

MUL050

$31,200

$22,000

$53,000

$4,050

$57,100

MUL051

$546,000

$380,000

$928,000

$93,100

$1,020,000

MUL052

$685,000

$480,000

$1,160,000

$1,210,000

$2,370,000

MUL053

$2,060,000

$1,400,000

$3,500,000

$1,570,000

$5,070,000

MUL054

$186,000

$130,000

$317,000

$538,000

$855,000

MUL055

$220,000

$150,000

$374,000

$28,600

$403,000

MUL056

$29,500

$21,000

$50,200

$3,840

$54,000

MUL057

$66,600

$47,000

$113,000

$8,660

$122,000

MUL058

$23,400,000

$16,000,000

$39,800,000

$2,260,000

$42,100,000

MUL059

$620,000

$430,000

$1,050,000

$55,900

$1,110,000

MUL060

$139,000

$97,000

$235,000

$12,500

$248,000

MUL061

$29,500

$21,000

$50,200

$3,840

$54,000

MUL062

$21,100

$15,000

$35,900

$2,740

$38,600

MUL063

$139,000

$97,000

$235,000

$12,500

$248,000

MUL064

$47,200

$33,000

$80,200

$6,140

$86,300

MUL065

$205,000

$140,000

$348,000

$18,400

$366,000

MUL066

$79,200

$56,000

$135,000

$10,300

$145,000

MUL067

$113,000

$79,000

$192,000

$14,700

$207,000

MUL068

$30,300

$21,000

$51,500

$3,950

$55,500

MUL069

$18,500

$13,000

$31,500

$2,410

$33,900

MUL071

$78,400

$55,000

$133,000

$7,940

$141,000

MUL072

$386,000

$270,000

$656,000

$1,050,000

$1,710,000

MUL073

$174,000

$120,000

$296,000

$22,600

$319,000

MUL074

$38,800

$27,000

$65,900

$5,040

$70,900

MUL075

$25,300

$18,000

$43,000

$3,290

$46,300

Page 12 of 14


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site

Segment ID



2009 Total



2009 Total Direct







Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)

MUL076

$29,500

$21,000

$50,200

$3,840

$54,000

MUL077

$20,200

$14,000

$34,400

$2,630

$37,000

MUL078

$96,100

$67,000

$163,000

$12,500

$176,000

MUL079

$75,000

$53,000

$128,000

$9,750

$137,000

MUL080

$28,700

$20,000

$48,800

$3,730

$52,500

MUL081

$394,000

$280,000

$669,000

$558,000

$1,230,000

MUL082

$21,100

$15,000

$35,900

$2,740

$38,600

MUL083

$422,000

$300,000

$717,000

$38,100

$755,000

MUL084

$95,300

$67,000

$162,000

$12,400

$174,000

MUL103

$676,000

$470,000

$1,150,000

$1,210,000

$2,360,000

MUL107

$11,000

$7,700

$18,700

$1,420

$20,100

MUL108

$11,800

$8,300

$20,100

$1,530

$21,600

MUL109

$14,300

$10,000

$24,300

$1,860

$26,200

MUL110

$11,800

$8,300

$20,100

$1,530

$21,600

MUL111

$16,000

$11,000

$27,200

$2,080

$29,300

MUL112

$15,200

$11,000

$25,800

$1,970

$27,800

MUL113

$17,700

$12,000

$30,100

$2,300

$32,400

MUL114

$18,500

$13,000

$31,500

$2,410

$33,900

MUL115

$20,200

$14,000

$34,400

$2,630

$37,000

MUL116

$15,200

$11,000

$25,800

$1,970

$27,800

MUL117

$23,600

$17,000

$40,100

$3,070

$43,200

MUL118

$27,000

$19,000

$45,900

$3,510

$49,400

MUL119

$23,600

$17,000

$40,100

$3,070

$43,200

MUL120

$15,400

$11,000

$26,200

$1,390

$27,500

MUL121

$13,500

$9,400

$22,900

$1,750

$24,700

MUL122

$17,700

$12,000

$30,100

$2,300

$32,400

MUL123

$12,600

$8,900

$21,500

$1,640

$23,100

MUL124

$15,200

$11,000

$25,800

$1,970

$27,800

MUL125

$21,100

$15,000

$35,900

$2,740

$38,600

MUL126

$18,500

$13,000

$31,500

$2,410

$33,900

MUL127

$19,400

$14,000

$33,000

$2,520

$35,500

MUL128

$16,000

$11,000

$27,200

$2,080

$29,300

MUL129

$732,000

$510,000

$1,240,000

$66,000

$1,310,000

MUL130

$149,000

$100,000

$253,000

$19,400

$272,000

MUL131

$181,000

$130,000

$308,000

$16,400

$325,000

MUL132

$49,500

$35,000

$84,100

$4,460

$88,600

MUL133

$21,100

$15,000

$35,900

$2,740

$38,600

MUL134

$48,900

$34,000

$83,100

$6,360

$89,500

MUL135

$3,800

$2,700

$6,460

$647

$7,100

MUL136

$3,800

$2,700

$6,460

$647

$7,100

MUL137

$30,300

$21,000

$51,500

$3,950

$55,500

MUL138

$68,300

$48,000

$116,000

$8,880

$125,000

MUL139

$3,800

$2,700

$6,460

$647

$7,100

MUL140

$14,300

$10,000

$24,300

$1,860

$26,200

MUL141

$354,000

$250,000

$602,000

$23,900

$626,000

MUL142

$1,260,000

$880,000

$2,140,000

$85,000

$2,220,000

MUL143

$30,300

$21,000

$51,500

$3,950

$55,500

MUL144

$20,200

$14,000

$34,400

$2,630

$37,000

MUL145

$154,000

$110,000

$262,000

$10,400

$272,000

MUL146

$597,000

$420,000

$1,020,000

$102,000

$1,120,000

MUL147

$16,000

$11,000

$27,200

$2,080

$29,300

MUL148

$112,000

$78,000

$190,000

$14,500

$205,000

MUL149

$207,000

$150,000

$352,000

$14,000

$366,000

MUL150

$554,000

$390,000

$942,000

$37,400

$979,000

MUL151

$21,100

$15,000

$35,900

$2,740

$38,600

MUL152

$14,300

$10,000

$24,300

$1,860

$26,200

Page 13 of 14


-------
TABLE D-40

Summary of Total Estimated Costs by Site, Alternative 4+

Focused Feasibility Study, Upper Basin of the Coeur d'Alene River, Bunker Hill Superfund Site



2009 Total



2009 Total Direct







Direct Capital

2009 Indirect

and Indirect

O&M Cost (30-

Total Cost (30-

Segment ID Source ID

Cost

Capital Cost

Capital Cost

Year NPV)

Year NPV)

MUL153

$280,000

$200,000

$475,000

$18,800

$494,000

MUL154

$147,000

$100,000

$250,000

$19,100

$269,000

MUL155

$32,000

$22,000

$54,400

$4,160

$58,600

MUL156

$14,300

$10,000

$24,300

$1,860

$26,200

MUL157

$9,270

$6,500

$15,800

$1,210

$17,000

THO019

$28,700

$20,000

$48,800

$3,730

$52,500

THO020

$191,000

$130,000

$325,000

$17,200

$342,000

THO021

$25,300

$18,000

$43,000

$3,290

$46,300

UG01-1

$14,200

$9,900

$24,100

$2,550

$26,700

UG01-10

$426,000

$300,000

$724,000

$109,000

$833,000

UG01-11

$238,000

$170,000

$405,000

$54,300

$459,000

UG01-12

$2,740,000

$1,900,000

$4,660,000

$607,000

$5,260,000

UG01-13

$1,090,000

$760,000

$1,860,000

$260,000

$2,120,000

UG01-14

$120,000

$84,000

$203,000

$33,600

$237,000

UG01-15

$371,000

$260,000

$630,000

$110,000

$740,000

UG01-16

$783,000

$550,000

$1,330,000

$189,000

$1,520,000

UG01-17

$2,680,000

$1,900,000

$4,550,000

$585,000

$5,140,000

UG01-18

$663,000

$460,000

$1,130,000

$196,000

$1,320,000

UG01-19

$205,000

$140,000

$349,000

$51,500

$401,000

UG01-4

$11,600

$8,100

$19,700

$3,480

$23,200

UG01-5

$459,000

$320,000

$780,000

$123,000

$903,000

UG01-6

$2,430,000

$1,700,000

$4,140,000

$483,000

$4,620,000

UG01-7

$511,000

$360,000

$868,000

$120,000

$988,000

UG01-8

$277,000

$190,000

$471,000

$58,300

$529,000

UG01-9

$529,000

$370,000

$900,000

$143,000

$1,040,000

WAL013

$224,000

$160,000

$381,000

$20,200

$401,000

WAL038

$55,300,000

$39,000,000

$94,600,000

$4,400,000

$99,000,000

WAL068

$24,400

$17,000

$41,500

$3,180

$44,700

WAL076

$1,120,000

$790,000

$1,910,000

$101,000

$2,010,000

WAL077

$1,540,000

$1,100,000

$2,620,000

$104,000

$2,720,000

Notes:

This Table does not include Central Treatment Plant (CTP) Sludge Pond Closure costs, these costs will be applied to the Total Alternative Cost.
This Table does not include Roads and Bridges costs, these costs will be applied to the Total Alternative Cost.

O&M = Operations and Maintenance
NPV = Net Present Value

NOTE: The above costs are presented rounded to three significant figures

NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of -30 percent to +50 percent (-30/+50%).

NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-magnitude cost opinion shown has been prepared for
guidance in project evaluation from the information available at the time of preparation. The final costs of the project will depend on actual labor and material
costs, actual site conditions, productivity, competitive market conditions, the final project scope, the final project schedule, and other variable factors. As a
result, the final project costs will vary from those presented above. Because of these factors, funding needs must be carefully reviewed prior to making
specific financial decisions or establishing final budgets.

Page 14 of 14


-------
TABLE D-41

Summary of Total Estimated Costs by Watershed

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site





2009 Total



2009 Total Direct









Direct Capital

2009 Indirect

and Indirect Capital

O&M Cost (30-

Total Cost (30-Year

Alternative

Watershed ID

Cost

Capital Cost

Cost

Year NPV)

NPV)

3+

BIG

$24,200,000

$16,900,000

$41,100,000

$5,790,000

$46,900,000



CC

$39,900,000

$29,400,000

$69,300,000

$8,220,000

$77,500,000



CCWP

$18,800,000

$13,400,000

$32,200,000

$2,550,000

$34,800,000



MGS

$361,000,000

$253,000,000

$614,000,000

$27,900,000

$642,000,000



MN

$2,490,000

$1,740,000

$4,230,000

$741,000

$4,970,000



NM

$47,800,000

$33,400,000

$81,200,000

$11,800,000

$93,000,000



PC

$26,800,000

$18,700,000

$45,500,000

$14,100,000

$59,600,000



UG

$112,000,000

$80,400,000

$192,000,000

$22,500,000

$215,000,000

4+

BIG

$58,100,000

$40,700,000

$98,800,000

$10,400,000

$109,000,000



CC

$72,100,000

$52,100,000

$124,000,000

$12,600,000

$137,000,000



CCWP

$119,000,000

$83,000,000

$202,000,000

$13,000,000

$215,000,000



MGS

$406,000,000

$285,000,000

$692,000,000

$35,700,000

$727,000,000



MN

$2,800,000

$1,960,000

$4,750,000

$643,000

$5,400,000



NM

$74,800,000

$52,300,000

$127,000,000

$15,500,000

$143,000,000



PC

$32,200,000

$22,500,000

$54,700,000

$17,700,000

$72,400,000



UG

$189,000,000

$135,000,000

$324,000,000

$38,000,000

$362,000,000

Notes:

This Table does not include Central Treatment Plant (CTP) Sludge Pond Closure costs, these costs will be applied to the Total Alternative Cost.
This Table does not include Roads and Bridges costs, these costs will be applied to the Total Alternative Cost.

O&M = Operations and Maintenance
NPV = Net Present Value

BIG = Big Creek
CC = Canyon Creek

CCWP = Canyon Creek - Woodland Park
MGS = Mainstem, SFCDR
MN = Moon Creek

Page 1 of 2


-------
TABLE D-41

Summary of Total Estimated Costs by Watershed

Focused Feasibility Study, Upper Basin of the Coeurd'Aiene River, Bunker Hill Superfund Site

2009 Total 2009 Total Direct
Direct Capital 2009 Indirect and Indirect Capital O&M Cost (30- Total Cost (30-Year
Alternative	Watershed ID	Cost	Capital Cost	Cost	Year NPV)	NPV)	

NM = Ninemile
PC = Pine Creek
UG = Upper South Fork

NOTE: The above costs are presented rounded to three significant figures

NOTE: The above cost opinion is a Feasibility-Study-level estimate with a nominal accuracy of-30 percent to +50
percent (-30/+50%).

NOTE: The above cost opinion is in 2009 dollars and does not include future escalation. The order-of-magnitude
cost opinion shown has been prepared for guidance in project evaluation from the information available at the
time of preparation. The final costs of the project will depend on actual labor and material costs, actual site
conditions, productivity, competitive market conditions, the final project scope, the final project schedule, and
other variable factors. As a result, the final project costs will vary from those presented above. Because of these
factors, funding needs must be carefully reviewed prior to making specific financial decisions or establishing final
budgets.

Page 2 of 2


-------
Attachment D-l
Technical Memorandum: CTP Expansion
for Treatment of Other OU 2 and OU 3 Waters


-------

-------
TECHNICAL MEMORANDUM

CH2MHILL

CTP Expansion for Treatment of Other OU 2
and OU 3 Waters

PREPARED FOR:	Ed Moreen/ USEPA

Bill Adams/USEPA

PREPARED BY:	Jim Stefanoff, P.E./CH2M HILL

DATE:	January 14, 2010

1.0 Introduction

The purpose of this technical memorandum is to describe expansion of the Bunker Hill
Central Treatment Plant (CTP), located in Kellogg, Idaho, for treatment of other Operable
Unit 2 (OU 2) and OU 3 waters. The CTP primarily treats acid mine drainage (AMD) from
the Bunker Hill mine along with relatively minor amounts of other OU 2 waters consisting
of stormwater from the mine yard, drainage from the smelter closure area, vehicle
decontamination water, and decontamination water associated with sampling.

The historical background of the CTP (Section 2.0) describes the 2001 Mine Water ROD
Amendment (USEPA, 2001a), which selected a final remedy for managing Bunker Hill
AMD, including improvements needed at the CTP. This is presented because improvements
needed to expand CTP capacity for additional waters must consider interface with the CTP's
role of treating its current inflows, and particularly Bunker Hill AMD (Section 3.0).

Section 4.0 describes the estimated capital and O&M costs for a range of potential expanded
CTP capacities.

This technical memorandum has been developed for the U.S. Environmental Protection
Agency (USEPA) Region 10 under the requirements of CH2M HILL's USEPA Region 10
Architect and Engineering Service (AES) Contract 68-57-04-01.

2.0	Background

2.1	CTP Historical Background

Before 1928, liquid and solid waste from the Bunker Hill Mining and Metallurgical Complex
was discharged directly into the South Fork of the Coeur d'Alene River (SFCDR) and its
tributaries. In 1928 the waste was directed to a nearby floodplain where a Central
Impoundment Area (CIA) was developed. AMD and wastewater from the complex were
discharged to the CIA, where a pond was constructed to settle solids before discharging the
liquids to the river. This primary treatment mechanism was one of the first major pollution
control features instituted by the mining industry.

The CTP was constructed in 1974 by the Bunker Hill Mining Company to treat AMD from
the mine and various sources of wastewater from their metallurgical complex. Bunker Hill
mine AMD is the single strongest source of contaminated water in either OU 2 or OU 3,

CTP EXPANSION UPGRADES AND COSTSTM.DOC


-------
having an average zinc concentration of about 170 milligrams per liter (mg/ L), and a range
of between about 60 and 700 mg/L. The average annual zinc load is about 3,000 pounds per
day (lb/day).

The CTP uses the lime neutralization process to increase influent pH and to precipitate
dissolved metals as oxy-hydroxide precipitates, which are settled in a clarifier and pumped
into a sludge disposal pond located on the top of the adjacent CIA. Polymer is added prior
to the clarifier to promote flocculation and settling of the precipitates. The CTP does not
have filters to remove precipitates that do not settle in the clarifier.

In 1974, when the CTP was first brought online, AMD and complex waters were stored in an
unlined pond on top of the CIA before being decanted to the CTP. When the smelter closed
in 1981, the CIA was no longer required to impound wastewater from the complex,
although surface runoff from the complex and AMD from the mine were still routed to the
CIA before treatment. Sludge formed during the treatment process was also disposed of in
unlined ponds on top of the CIA.

Ownership of the mine has passed through a number of companies during the more than
100-year history of the site, finally ending up under the direction of the New Bunker Hill
Mining Company (NBHMC). NBHMC did not, however, purchase the CTP. Bunker Limited
Partnership (BLP), and then the Gulf and Pintlar corporations as creditors of BLP, continued
to operate the treatment plant using money from a trust fund established as part of the BLP
bankruptcy. The federal and state governments assumed operation of the CTP in November
1994, following the bankruptcy of the Gulf and Pintlar corporations. In that same year,
USEPA issued a Unilateral Administrative Order to NBHMC directing the company to keep
the mine pool pumped to an elevation below the level of the SFCDR to prevent discharges
to the river, to convey mine water to the CTP for treatment unless an alternative form of
treatment was approved, and to provide for emergency mine water storage within the mine.
The CTP was operated by the BLP, under the direction of USEPA, from November 1994 to
February 1996 using money from the BLP trust fund. At that time, it was determined that
the BLP trust fund monies would be better spent on ongoing site cleanup.

Since February 1996, the ongoing treatment of AMD has been conducted and funded by the
federal and state governments. The U.S. Army Corps of Engineers currently operates the
CTP for USEPA using a contractor. The CTP includes all associated mine water
infrastructure components external to the mine (the AMD collection ditch at the Kellogg
Tunnel portal [the main entrance to the mine], the AMD conveyance pipelines to the CTP,
and the lined pond [a 7 million-gallon lined AMD storage pond]), the CTP, and the sludge
disposal pond located on the CIA used for treatment residuals. The NBHMC is currently
operating the Bunker Hill mine and maintaining its infrastructure, including the AMD
collection ditches within the mine, the mine pool pumping system used to pump the lower
workings water to the 9 Level (the main operations level which drains AMD out through
the Kellogg Tunnel ditch system), and the Kellogg Tunnel itself.

2.2 Record of Decision Amendment

An amendment to the OU 2 1992 Non-Populated Areas Record of Decision (ROD), which
addressed management of AMD from the mine, was issued in December 2001 (USEPA,
2001a). The ROD Amendment was necessary to address shortcomings presented by the

CTP EXPANSION UPGRADES AND C0STSTM.DOC

2


-------
existing mine water control systems that resulted in continued generation and discharge of
AMD from the mine and the antiquated state of the CTP. The ROD Amendment identified
decreasing water entry to the underground workings as the most viable way to reduce the
magnitude of the AMD problem. The selected remedy for managing AMD from the Bunker
Hill mine was Alternative 3 - Phased Source Control/Treatment. Each component of the
remedy and its current status is described below.

AMD Mitigation

This component of the remedy includes actions to reduce the quantity of surface water
entering the mine and AMD created within the mine. This would provide the following
benefits:

•	Reduced in-mine maintenance associated with drifts and drainage ditches

•	Reduced mine water pumping from the lower workings

•	Improved reliability of conveying mine water to the portal for collection

•	Reduced peak treatment flows at the CTP

•	Generation of less sludge

•	Reduced CTP operations costs

The mitigations include constructing a stream diversion on the West Fork of Milo Creek,
modification of the Phil Sheridan raise system, and plugging in-mine drill holes, as a first
phase of source control. These efforts are expected to have the greatest impact on reducing
the magnitude of mine water flows and the strength of the flows (in terms of the amount of
dissolved metal contaminants) exiting the mine through the Kellogg Tunnel. Other flow
reduction measures would be considered in future phases, based on performance
monitoring and an evaluation of the ability of additional measures to provide cost-effective
water and/or contaminant reductions.

AMD Collection

This component includes collection of AMD within the mine. The ROD Amendment
specified use of the existing AMD collection system within the mine and transport through
the Kellogg Tunnel using the existing ditch system—given that the mine, at the time of the
ROD Amendment and also currently, is an open and operational mine.

AMD Storage

AMD storage is required during those times when the treatment plant is shut down for
maintenance or repairs, or when the mine water flow exceeds treatment capacity. Mine
water flows in excess of 2,500 gallons per minute (gpm) would be temporarily stored in the
existing lined pond or in the mine using a new gravity system to divert water into the mine
pool. A new mine pool extraction system would be installed to reduce the time needed to
extract the stored water and to increase reliability.

AMD Conveyance

This component of the remedy includes the conveyance of mine water from the Kellogg
Tunnel to the CTP. A new section of pipe would be added to allow direct flow of AMD to
the CTP rather than to the lined pond, where it requires pumping because its elevation is
lower than that of the CTP.

CTP EXPANSION UPGRADES AND COSTSTM.DOC

3


-------
AMD Treatment

The CTP would be upgraded to improve efficiency and increase reliability, to make less
sludge, and to achieve lower concentrations of metals in the plant's discharge allowing
compliance with the State of Idaho's water quality criteria. The existing CTP cannot
consistently meet the criteria because of the lack of media (sand) filters, and operates under
an expired National Pollutant Discharge Elimination System (NPDES) permit. Under the
ROD Amendment remedy, the CTP was to have an initial treatment capacity using media
filters of 2,500 gpm, but an overall treatment capacity of 5,000 gpm. Flows in excess of
2,500 gpm would either be bypassed around the filters or passed through the filters at
higher than design-flow rates. Additional filtration capacity could be added if determined to
be necessary based on the performance of the AMD mitigations for reducing peak AMD
flows.

Sludge Management

USEPA selected sludge disposal Option A (disposal of sludge in beds on top of the CIA).
However, because of community concerns about competing disposal needs, preserving
developable site land, and potentially developing regional disposal areas as part of the
Coeur d'Alene River Basin cleanup efforts, sludge disposal was to be implemented in the
following manner:

1.	Execute initial upgrades to the CTP. These upgrades will reduce the current amount of
sludge produced by about half, thereby doubling the expected life of the current
disposal area.

2.	Reevaluate whether additional regional sludge disposal capacity has become available
as part of the Basin (OU 3) cleanup efforts, which would make offsite disposal more
cost-effective. If so, pursue offsite sludge disposal. If not, construct one 10-year disposal
bed on the CIA, and close the existing sludge disposal area using a capping system
similar to the rest of the CIA.

3.	Reconsider Step 2 before the construction of additional sludge beds on the CIA.

Performance Monitoring

Monitoring of the remedy was to include an assessment of untreated mine water within the
mine and at the Kellogg Tunnel portal, the quality of water treated at the CTP and measured
where effluent is discharged into Bunker Creek, and the performance of source control
actions (mitigations) to determine if additional flow reduction measures or treatment
capacity are warranted.

2.3 Status of Mine Water Remedy

A number of actions associated with the mine water remedy have been completed since the
signing of the ROD Amendment. The completed actions are discussed below by remedy
component, as presented in the ROD Amendment. In addition, this section identifies the
remedy actions that have yet to be implemented. This information is provided because
upgrades to the CTP for treatment of other OU 2 and OU 3 waters need to consider how to
integrate required changes with the existing mine water-related treatment infrastructure.

CTP EXPANSION UPGRADES AND C0STSTM.DOC

4


-------
AMD Mitigations/Source Control

The original mitigation actions to be constructed as part of the remedy include diverting
West Fork Milo Creek around the Guy Cave area (an area of known infiltration to the worst
AMD-forming areas of the mine), modifying the Phil Sheridan Diversion, and plugging
various in-mine drill holes that produce water. None of these actions has been constructed.
A 95 percent complete design was developed for the West Fork Milo Creek Diversion,
which includes modifying the Phil Sheridan Diversion.

AMD Collection

The AMD collection approach presented in the ROD Amendment consisted of gathering the
AMD within the mine using the existing collection system. Under the existing system, mine
water from the upper portions of the mine flows by gravity to the 9 Level and out the
Kellogg Tunnel. A portion of the flow from the upper mine bypasses the 9 Level and
discharges to the submerged workings (the mine pool), along with an unknown amount of
water coming from the cross-connected Crescent Mine. The mine pool water is pumped
from near the 11 Level up to the 9 Level through Shaft No. 2, where it joins the gravity
drainage water in the 9 Level ditch system and flows out the Kellogg Tunnel. The current
collection system requires that a large portion of the mine infrastructure, including the
Kellogg Tunnel, a large portion of 9 Level, Raise No. 2 and the hoist, and the Cherry Raise
and hoist, be maintained to allow for maintenance and periodic cleaning. However, these
areas must also be maintained this way to support the ongoing mine operations.

This remedy used the existing AMD collection procedure, which is still in use today. Thus,
no new AMD collection actions were included in the remedy as the mine was, and still is,
open and operational.

AMD Conveyance

This remedy included construction of a new pipeline to allow AMD to drain directly to the
CTP rather than to the lined pond, where it was resulting in an accumulation of sediment,
and the need to continuously pump the AMD to the CTP because of the pond's lower
elevation. This new section of pipeline is known as the Direct Feed pipeline.

The Direct Feed pipeline was installed in 2002. The pipeline is constructed of 20-inch high-
density polyethylene (HDPE) and includes valves to allow AMD to flow to either the lined
pond or directly to the CTP. A cleaning vault was constructed to allow periodic inspection
of the pipeline and cleaning by "pigging."

AMD Storage

Current mine water storage options consist of storing mine water either in the lined pond or
the lower portions of the mine itself. The remedy did not change this storage approach but
included construction of a new gravity diversion system to increase the flexibility of storing
water in the mine pool. The new gravity diversion would route water from the upper
workings of the mine into the mine pool for temporary storage when the lined pond did not
provide sufficient storage capacity. An evaluation conducted during the Remedial
Instruction/Feasibility Study (RI/FS) (USEPA, 2001b) indicated that the water in the mine
pool could rise up to the 10 Level with no net gravity head of mine pool water towards the
SFCDR. This remedy also included a new mine pool extraction system to reduce the time

CTP EXPANSION UPGRADES AND C0STSTM.DOC

5


-------
needed to extract the stored water. The conceptual design of the new extraction system
consisted of two 700 gpm pumps installed below 11 Level and an upgrade of the current
mine electrical system to support the pumping operation. The remedy also included
continued repair and maintenance of the existing lined pond.

An alternate and simpler approach to the remedy gravity diversion system was proposed
and implemented by the mine owner. This system consists of temporarily constructing a
sandbag cutoff dam at the back of the Kellogg Tunnel to impound AMD and to back up the
AMD into the Barney Vent Raise, where it flows down to 10 Level and subsequently into the
mine pool. This system was funded by the mine owner; therefore, no USEPA or state
funding was required.

Although not specified in the remedy, the lined pond was cleaned of accumulated sediment
in 2003 to improve storage capacity. This was done after the construction of the Direct Feed
pipeline.

AMD Treatment

As described previously, the CTP was built in 1974 and had not been updated in any
significant way at the time the ROD Amendment was adopted. Much of the equipment was
nearly worn out, and many of the automated control systems no longer functioned or had
been removed. The plant's sand filters, previously used to remove solids from the discharge,
had also been removed. Their removal resulted in the plant being unable to function in
high-density sludge (HDS) mode ( a mode of lime treatment whereby significantly less
sludge is produced) as it had originally; the plant also was unable to consistently meet the
discharge standards of its expired NPDES permit. The plant had no backup power and went
offline periodically because of electrical interference from lightning storms or localized
power surges. All original alarm systems were inoperative. A Radio Shack™ phone auto-
dial box was the only alarm system and it was unreliable due in part to leaks in the electrical
room roof. Buildup of solids in plant pipes had reduced its capacity from 5,000 gpm to
about 3,500 gpm. The lime storage silo was caked with hardened lime, and the lime makeup
and feed system was manual requiring significant operator attention. The wall upon which
the electrical equipment was mounted leaked, and constant seepage had rusted out the back
of many of the electrical panels. In summary, the plant was far below modern operational
standards, was prone to failure, and was labor intensive to operate. The CTP Master Plan
(Bunker Hill RI/FS, Appendix E) specified needed improvements to address these
problems. These improvements were adopted as part of the ROD Amendment.

As mentioned above, the CTP was originally designed to use lime HDS treatment
technology. This process uses lime to remove acidity and to precipitate the dissolved metals
as hydroxides, which creates solids known as "sludge." The HDS process creates sludge of
much higher density than conventional lime treatment. HDS sludge dewaters to a greater
extent and requires much less disposal space than conventional lime sludge, thereby
significantly reducing cost.

At the time of its construction in 1974, only a few HDS plants were on-line in the world. This
technology is still state-of-the-art and used at hundreds of mine and industrial sites.
However, while originally designed as an HDS plant, the CTP currently must be operated in
a "low-density sludge" mode, which prevents the formation of true HDS. This is because

CTP EXPANSION UPGRADES AND C0STSTM.DOC

6


-------
the sand filters, needed for polishing excess suspended solids from the clarifier overflow,
have been removed. Filters are also needed to allow the CTP to not only consistently meet
its current discharge standards established by the expired NPDES permit, but also the much
more rigorous standards yet to be enacted pursuant to Idaho water quality standards. This
is primarily because excess solids periodically overflow into the plant effluent, increasing
the concentration of zinc beyond discharge standards. New discharge standards, in
conformance with current Idaho water quality standards, were established for the CTP as
part of the ROD Amendment. These new standards will be adopted once filters are
constructed. Filter construction would also allow the plant to be operated in HDS mode,
significantly reducing long-term sludge disposal costs.

Since the ROD Amendment, USEPA and the State of Idaho have moved forward with a
number of CTP improvements specified in the CTP Master Plan. The following
improvements were performed as part of time critical actions taken to replace the most
failure-prone equipment and plant systems:

•	Replaced and upgraded the lime storage and feeding system

•	Refurbished the thickener

•	Updated the plant electrical system

•	Constructed a new control building and updated the plant control system including new
alarm systems

•	Increased the hydraulic capacity to 5,000 gpm by replacing the pipeline between the
thickener and the polishing pond

•	Installed a backup diesel electrical generator and sound-deadening enclosure

•	Installed a new sludge recycle pump and disposal pipeline from the CTP to the sludge
disposal cell

The following actions remain to be implemented. Addition of the filters would allow the
plant to meet Idaho water quality standards and to operate in the HDS mode, thus
significantly reducing sludge disposal volumes. The other items listed below are needed to
complete plant modernization.

•	Add 2,500 gpm of filters and associated piping and pump stations, and a new building
to house the filters

•	Replace Reactor A (sludge conditioning tank/rapid mix tank) and agitator

•	Replace the Aeration Basin with a new Reactor B, agitator, and air blower

•	Replace the manual polymer makeup system with an automated system, and replace the
feed pumps and pipes

•	Replace the other sludge recycle and wasting pumps

•	Add an influent flow meter and replace the effluent Parshall flume

Sludge Management

A new sludge pipeline from the CTP to the existing CIA sludge bed was installed. This was
needed because the old pipeline was periodically developing leaks and was in poor

CTP EXPANSION UPGRADES AND C0STSTM.DOC

7


-------
condition. The existing CIA sludge bed is still being used and estimated to have about
12 years of remaining life.

Performance Monitoring

A major aspect of the remedy was the phased approach to implement AMD source control
measures (mitigations). Information collected from the monitoring program would be used
to help determine if additional mitigations were required beyond those included in the first
phase. The remedy includes performance monitoring of:

1.	AMD at various locations within the mine (for a 10-year period as part of the phased
implementation approach for source control measures/CTP capacity) and at the at the
Kellogg Tunnel portal

2.	Treated CTP effluent at its discharge

3.	Source control actions to determine if additional flow reduction measures or treatment
capacity are warranted (for a 10-year period as part of the phased implementation
approach for source control measures/CTP capacity)

Treated CTP effluent is monitored at the outfall to Bunker Creek. Periodic samples of the
AMD from the Kellogg Tunnel portal are also collected along with flow rate. No in-mine
AMD monitoring has been conducted, nor has monitoring associated with source control
action areas such as Milo Creek and its tributaries.

3.0	CTP Treatment Capacity Expansion

The CTP could be effectively expanded to treat other metals impacted water from OU 2 or
OU 3, such as groundwater or AMD from other mines. The 2005 Canyon Creek treatability
study (CH2M HILL, 2006) demonstrated that Canyon Creek groundwater could be
successfully co-treated with Bunker Hill mine AMD using the lime HDS treatment process,
which is the same process used at the CTP — although the CTP is currently operated in a
low-density sludge mode because of lack of media filters as described earlier.

The 2005 Canyon Creek treatability study also demonstrated that the lime HDS process can
successfully treat much more dilute streams than the combination of Bunker Hill mine
water and Canyon Creek groundwater. A separate test was conducted on just Canyon Creek
groundwater. While the effluent quality was as good, the sludge was not as dense as the
combined Bunker Hill mine and Canyon Creek groundwater, although it was much denser
than what would be produced from traditional lime treatment not employing the HDS
approach.

3.1	CTP Capacity

The CTP could be expanded to treat very large inflows. Equipment could be upsized and/or
replicated as needed. Constraints on ultimate capacity are primarily limited to availability of
land and related infrastructure. The largest single piece of equipment needed is the clarifier.
While additional clarifiers could be added, the existing 236-foot-diameter unit has a
maximum hydraulic capacity, based on the results of the Canyon Creek treatability testing
program, of about 30,000 gpm. Higher flows than this may be effectively treated, but given

CTP EXPANSION UPGRADES AND COSTSTM.DOC

8


-------
available information, this flow is a reasonable upper end limit without addition of a second
clarifier.

3.2	Modifications Needed

The following CTP modifications would be needed to treat up to 30,000 gpm and to meet
Idaho water quality standards. Below are the required modifications, which are already
planned as part of the remaining ROD Amendment upgrades:

•	Add 2,500 gpm of media filters, associated piping and pump stations, and a new
building to house the filters

•	Replace Reactor A (sludge conditioning tank/rapid mix tank) and agitator

•	Replace the manual polymer makeup system with an automated system, and replace the
feed pumps and pipes

•	Replace the existing nearly worn-out sludge recycle and wasting pumps

•	Add electrical, instrumentation, and controls associated with the new equipment

The follow modifications are required to treat additional OU 2 and OU 3 waters that are not
part of the remaining ROD amendment upgrades:

•	Add additional media filters, associated piping and pump stations, and a new building
to house the filters if needed

•	Replace the Aeration Basin with two new Reactor B tanks, each with an agitator, air
blower, and associated inlet and outlet piping

•	Increase the hydraulic capacity of the clarifier feed trough, clarifier effluent launder, and
perhaps the feedwell

•	Add a larger influent flow meter and a larger effluent Parshall flume

•	Add electrical, instrumentation, and controls associated with the new equipment

•	Install an additional backup diesel generator if needed (the existing one may have
sufficient capacity depending on plant configuration and operation)

3.3	Implementation

Increasing the CTP capacity up to 30,000 gpm is implementable. The lime HDS process is a
proven treatment technology, whose effectiveness was demonstrated during the Canyon
Creek treatability study. The necessary equipment, materials, and labor force to construct
the required changes are available. The additional treatment chemicals (lime and polymer)
are available from existing suppliers. The additional power requirements are available from
the local utility (Avista). The Canyon Creek treatability study demonstrated that Idaho
water quality standards could be met.

CTP expansion would likely be conducted in phases to accommodate when additional
influent sources would be available. This approach is similar to the two-phased approach
described in Appendix E of the mine water RI/FS document (USEPA, 2001b). One approach
would be to use two phases, whereby one-half of the maximum needed capacity would be

CTP EXPANSION UPGRADES AND C0STSTM.DOC

9


-------
constructed in Phase 1 and the second half in Phase 2. This would allow capacity to better
accommodate the timing of influent demand.

4.0 Capital and O&M Costs

An order-of-magnitude cost opinion was developed to increase the CTP to various
maximum capacities. This one done using the capital and O&M cost estimates developed for
the mine water RI/FS and updated in 2006, and then modifying them for maximum
capacities of either 5,000; 10,000; 15,000; or 20,000 gpm. These costs were escalated to
2009 dollars and used to develop a capital cost curve and an O&M cost curve relating cost to
capacity. The cost estimates and curves are attached to the back of this technical
memorandum.

The curves are quite linear with respect to capacity, as was expected, because the size of the
required upgrades, and particularly the filters, is proportional to flow. The capital costs
represent the total cost to upgrade the existing plant to the desired capacity. The annual
O&M costs include treatment of the Bunker Hill mine water, and O&M associated with all
existing mine water systems consisting of the Kellogg Tunnel portal collection system, the
AMD pipelines, the lined pond, and the CIA sludge disposal bed.

The largest single capital cost component is associated with adding the media filters. Media
filters are sized based on flow (gpm) per media filter surface area (square feet). Thus,
increasing the treatment capacity from 2,500 gpm to 20,000 gpm requires 8 times the area of
filters. The next largest capital cost is associated with constructing the neutralization/
aeration reactors. These are sized using treatment residence time, which is also proportional
to flow.

While the capital cost required to construct 20,000 gpm of capacity is about 5 times that
required to provide 2,500 gpm capacity, the annual O&M cost increases by only about
0.5 times, or about 50 percent. This is because once the plant treatment capacity is available,
the incremental cost, on a per-gallon basis, to treat additional water is relatively low. Little
additional operations labor is required, and the increased lime and polymer consumption is
also relatively low because of the much more dilute nature of the other OU 2/OU 3 waters
as compared to Bunker Hill mine water.

The attached cost opinions are considered order-of-magnitude, with an expected accuracy of
minus 30 percent to plus 50 percent. Estimated capital and operating costs were derived
from vendor quotes, cost estimating manuals, historical operating budgets, and similar
projects. Costs are for comparative purposes only. Net present value (NPV) costs are based
on 30 years of operation at a 7 percent interest rate. The order-of-magnitude cost opinions
are in 2009 dollars. They have been prepared for guidance in project evaluation and should
be carefully reviewed before making specific financial decisions or establishing final project
budgets. The actual costs are expected to vary from the costs shown here based on actual
labor and material costs, competitive market conditions, final project scope, and other
variable factors.

CTP EXPANSION UPGRADES AND C0STSTM.DOC

10


-------
5.0 References

CH2M HILL. 2006. Canyon Creek Phase II Treatability Study. Prepared for the United States
Environmental Protection Agency. October 2006.

U.S. Environmental Protection Agency (USEPA). 2001a. Record of Decision Amendment, Non-
Populated Areas Operable Unit, Bunker Hill Mining and Metallurgical Complex, Shoshone County,
Idaho. December 2001

U.S. Environmental Protection Agency (USEPA). 2001b. Bunker Hill Remedial
Investigation/Feasibility Study. April 2001.

CTP EXPANSION UPGRADES AND COSTSTM.DOC

11


-------

-------
Figures and Tables


-------

-------
CTP Expansion Capital Cost
Direct and Indirect Costs

Treatment Capacity (gpm)


-------

-------
CTP Annual O&M Cost Curve

$3,000,000

$2,500,000


-------

-------
Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 2,500 gpm

Order of Magnitude Cost Opinion	

	Description	Quantity	Unit

HPS (Hydroxide)

Sitework/Yard Piping

Fencing 1,000	LF

Gravel Surfacing & Misc 1	LS

Connections & Relocations of Existing Piping 1	LS

Reactor A (Sludge Conditioning Tank)

Earthwork & Concrete for Slab	1	LS

Elevated Platform for Reactor A&B	1	LS

Paint	1	LS

Sludge Conditioning Tank, 2500gal FRP	1	EA

Mixer, 3hp	1	EA

Inlet Piping, 24" SDR 15.5	120	LF

Inlet Piping, 18" SDR 15.5	120	LF

Valves, vaults, etc	1	LS

Neutralization/Oxidation System

Distribution Piping, 24" HDPE	170	LF

Retaining Wall to Accommodate New Tank	450	SF

Earthwork for Retaining Wall	1	LS

Earthwork & Concrete for Slab	1	LS

Paint	1	LS

Aeration Tank (Reactor B), 75,000gal Steel Tank	1	EA

Submerged Turbine Aerator/Mixer	1	EA

Positive Displacement Blower	1	EA

Pipe Supports, Hangers, etc	1	LS

Automated Polymer Make-up & Feed System

Earthwork & Concrete for Slab

1

LS

Paint

1

LS

Polymer Make-up System

2

EA

Polymer Make-up Tank, 2000gal

1

EA

Mixer

2

EA

Transfer Pump, 20gpm

2

EA

Polymer Feed Tank, 2000gal

1

EA

Water Treatment TCD Unit Costs Master File.xls

Direct Capital
Unit Cost

Comments

The Following Costs are in Year 2000 Dollars. See Escalation Factor at Bottom.

$10,000 allowance
$25,000 allowance
$30,000 allowance

$19,872 apx 50cy @ $400/cy

$60,000 asm 40x20 @ $75/sf high level and to support reactor A
$10,000 allowance for subcontract
$42,695 quote + 5% infla. + 5%frt + 10%mu
$13,803 quote + 5% infla. + 5%frt + 10%mu

$23,242 constrained schedule & access w/obstacles, ftgs, valves, connections, etc
$17,634 constrained schedule & access w/obstacles, ftgs, valves, connections, etc
$50,000 allowance

$32,926 constrained schedule & access w/obstacles, ftgs, valves, connections, etc
$11,250 45'x 8'H + 2' below grade, CIP cantelever
$6,814

$65,578 apx 165cy @ $400/cy
$50,000 allowance for subcontract
$56,250 revised to $.75/gal
$73,520 use same a 5000gpm estimate
$13,205
$2,500 allowance

$0 in bldg
$5,000 allowance for subcontract
$20,433
$3,974

$4,674 corrected hours
$6,548 corrected hours
$3,974

Page 1 of 3

1/15/2010 9:34 AM


-------
Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 2,500 gpm

Order of Magnitude Cost Opinion	

	Description	Quantity	Unit

Variable Speed Gear Pump, 1 gpm	2	EA

Piping to Feed Point	100	LF

Thickener

Clean & Decommission Existing Floe System	1	LS

Replace Weir	0	LS

Groundwater Test & Empty Tank	0	LS

Replace Thickener Rake System Complete	0	LS

E-DUC Feed & Floe System & Center Well Mods	1	LS

Surface Prep & Coat	0	LS

Sludge Wasting & Recycle Pumps

Earthwork & Concrete for Slab	0	LS

Remove Existing Pumps	1	LS

Paint	1	LS

Sludge Recycle Pump, 400gpm	2	EA

Sludge Recycle Pump, 800gpm	1	EA

Sludge Waste Pump, 400gpm, 200' tdh	1	EA

Sludge Recycle Piping, 8" Dl	150	LF

Sludge Wasting Piping, 6" Dl	0	LF

l&C and Electrical

Total l&C	1	LS

New Magnetic Flowmeter in Existing Vault	1	EA

Parshall Flume @ Effluent	1	EA

Electrical	1	LS

Existing Plant Demolition

Earthwork	1	LS

Concrete Slab & Footings	100	CY

Relocate Existing Filtration Bldg, etc	1	LS

Repairs, Touchup, etc	1	LS

Water	1	LS

Sanitary	1	LS

Drains	1	LS

Water Treatment TCD Unit Costs Master File.xls

Direct Capital
Unit Cost

$8,421
$1,990

Comments

$1,775

$0 quote + frt & markup=$19/lf & allow for removal & replacement
$0 allowance
$0 quote + frt & markup
$45,934 quote + frt & markup + add'l parts for mods
$0 allowance for interior walls & mechanism

$0 apx 200cy @ $400/cy
$2,474

$20,000 allowance for subcontract
$29,234 new cost for smaller pump
$22,048 new cost for smaller pump
$26,380 new cost for larger pump
$10,271 including ftgs, valves, etc, revised cost
$0 including ftgs, valves, etc, revised cost

$41,371 use 5% of above
$10,269 24"

$3,037 12"

$70,568 use 8% of above

$7,314

$25,536 assume 18" avg thickness to account for ftgs, etc
$34,071 60' x 30' x 10' eave ht metal bldg-remove contents, dismantle & re-erect
$5,000 allowance for some painting, sealants, doors, etc
$4,235 sink, emer. Shower, hose bibbs, piping & service
$1,917 toilet, piping & service
$2,117

Page 2 of 3

1/15/2010 9:34 AM


-------
Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 2,500 gpm

Order of Magnitude Cost Opinion	

	Description	Quantity	Unit

HVAC	1	LS

Electrical	1	LS

Tertiary Media Filters

HDS Pump Station Complete	1	LS

Water Reuse Pump Station Complete	1	LS

Distribution Piping	500	LF

Media Filter System	1	LS

Liquid Polymer System	0	LS

Backwash Pumping Complete	1	LS

Dirty Backwash Storage Tank, 30,000gal	1	EA

Dirty Backwash Storage Tank Mixer	1	EA

Dirty Backwash Return Pump	1	EA

Clean Backwash Supply Tank, 30,000gal	1	EA

Clean Backwash Supply Pump	1	EA

Building Complete	1	LS

Electrical/l&C	1	LS

Mechanical	1	LS

Backflow Preventer	1	EA

Distribution Piping 1,000	LF

Paint	1	LS

CAPITAL TOTAL (ROUNDED) (Yr 2000 Dollars)

Escalate from Yr 2000 to Yr 2009 Dollars (factor of 1.358)

NOTE: The above cost opinion is in October 2000 dollars and does not include escalation.
The order of magnitude cost opinion shown has been prepared for guidance in project evaluation
at the time of preparation. The final costs of the project will depend on actual labor and material
costs, actual site conditions, productivity, competitive market conditions, final project scope, final
schedule and other variable factors. As a result, the final project costs will vary from those
presented above. Because of these factors, funding needs must be carefully reviewed prior to
making specific financial decisions or establishing final budgets.

Water Treatment TCD Unit Costs Master File.xls

Direct Capital

Unit Cost	Comments

$1,617 reinstall unit heaters

$4,933 reinstall, fixtures, panels, wiring, etc

$70,000 cost by DAH
$30,000 cost by DAH
$17,500 4" plastic, below grade
$566,834 quote=430000 + 10% frt + 10% mu & 100hrs to install

$0 Not required per JS 11/28/2000
$133,461 Bob York spreadsheet + 10% OH&P, scaled to 2500gpm + escalation to 2(
$22,500 $.75/gal
$3,737 allowance
$13,885 allowance
$22,500 $.75/gal
$13,885
$318,750 85'x 50 @ $75/sf
$0 included
$0 included
$10,000 allowance
$23,000 2" plastic
$5,000 misc painting allowance

$4,736,050 Year 2000 Dollars
$6,432,827 Year 2009 Dollars

Page 3 of 3

1/15/2010 9:34 AM


-------

-------
AT_5,000 gpm ExpanCapital_09

Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 5,000 gpm

Order of Magnitude Cost Opinion	

Description

Quantity Unit

Direct Capital
Unit Cost

Comments

HPS (Hydroxide)

Sitework/Yard Piping

Fencing

Gravel Surfacing & Misc

Connections & Relocations of Existing Piping

1,000
1
1

LF
LS
LS

The Following Costs are in Year 2000 Dollars. See Escalation Factor at Bottom.

$10,000 allowance
$30,000 allowance
$30,000 allowance

Reactor A (Sludge Conditioning Tank)

Earthwork & Concrete for Slab
Elevated Platform for Reactor A&B
Paint

Sludge Conditioning Tank, 2500gal FRP
Mixer, 3hp

Inlet Piping, 24" SDR 15.5
Inlet Piping, 18" SDR 15.5
Valves, vaults, etc

1
1
1
1
1

120
120
1

LS
LS
LS
EA
EA
LF
LF
LS

$19,872 apx 50cy @ $400/cy

$60,000 asm 40x20 @ $75/sf high level and to support reactor A
$10,000 allowance for subcontract
$42,695 quote + 5% infla. + 5%frt + 10%mu
$13,803 quote + 5% infla. + 5%frt + 10%mu

$23,242 constrained schedule & access w/obstacles, ftgs, valves, connections, etc
$17,634 constrained schedule & access w/obstacles, ftgs, valves, connections, etc
$50,000 allowance

Neutralization/Oxidation System

Distribution Piping, 24" HDPE	85	LF

Retaining Wall to Accommodate New Tanks	225	SF

Earthwork for Retaining Wall	1	LS

Earthwork & Concrete for Slab	1	LS

Paint	2	LS

Aeration Tank (Reactor B), (2) 75000 gal Steel Tank	2	EA

Submerged Turbine Aerator/Mixer	2	EA

Positive Displacement Blower	2	EA

Pipe Supports, Hangers, etc	1	LS

$16,463 constrained schedule & access w/obstacles, ftgs, valves, connections, etc
$5,625 90'x 8'H + 2' below grade, CIP cantelever
$13,629

$95,337 apx 450cy @ $400/cy
$100,000 allowance for subcontract
$112,500 $0.75/gal
$130,583
$23,031
$5,000 allowance

Automated Polymer Make-up & Feed System

Earthwork & Concrete for Slab
Paint

Polymer Make-up System
Polymer Make-up Tank, 2000gal
Mixer

Transfer Pump, 20gpm

Water Treatment TCD Unit Costs Master File.xls

LS
LS
EA
EA
EA
EA

$0 in bldg
$5,000 allowance for subcontract
$20,433
$3,974

$4,674 corrected hours
$6,548 corrected hours

Page 1 of 4

1/15/2010 9:21 AM


-------
AT_5,000 gpm ExpanCapital_09

Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 5,000 gpm

Order of Magnitude Cost Opinion	

Description

Quantity Unit

Direct Capital
Unit Cost

Comments

Polymer Feed Tank, 2000gal
Variable Speed Gear Pump, 1gpm
Piping to Feed Point

1

2

100

EA
EA
LF

$3,974
$8,421
$1,990

Thickener

Clean & Decommission Existing Floe System	1	LS	$1,775

Replace Weir	1	LS	$28,905

E-DUC Feed & Floe System & Hydraulic Mods	1	LS	$32,334

Sludge Wasting & Recycle Pumps

Earthwork & Concrete for Slab	0

Remove Existing Pumps	1

Paint	1

Sludge Recycle Pump, 400gpm	2

Sludge Recycle Pump, 800gpm	1

Sludge Waste Pump, 400gpm, 200' tdh	1

Sludge Recycle Piping, 8" Dl	150

Sludge Wasting Piping, 6" Dl	0

LS	$0 apx 200cy @ $400/cy

LS	$2,474

LS	$20,000

EA	$29,234

EA	$22,048

EA	$26,380

LF	$10,271 including ftgs, valves, etc, revised cost
LF $0 including ftgs, valves, etc, revised cost

l&C and Electrical

Total l&C

New Magnetic Flowmeter in Existing Vault

Parshall Flume @ Effluent

Electrical

1	LS	$51,892 use 5% of above

1	EA	$10,269 24"

1	EA $5,537

1	LS	$88,444 use 8% of above

Existing Plant Demolition

Remove Reactor A

Remove Aeration Basin, Ret Wall, Stairs, etc
Remove Flocculation Basin
Remove Associated Piping
Remove Associated Electrical
Regrade Area

Connections & Relocations of Existing Piping
Earthwork

Water Treatment TCD Unit Costs Master File.xls

1

LS

$2,810



1

LS

$127,768

_C
>
o
o
o

CM

ฎ

O
O
O
O
CD

1

LS

$18,734

allow 40hrs

1

LS

$1,873



1

LS

$1,873



1

LS

$1,704



1

LS

$5,000

allowance

1

LS

$7,314



Page 2 of 4

1/15/2010 9:21 AM


-------
AT_5,000 gpm ExpanCapital_09

Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 5,000 gpm

Order of Magnitude Cost Opinion

Description

Quantity

Unit

Direct Capital

Unit Cost Comments

Concrete Slab & Footings

100

CY

$25,536 assume 18" avg thickness to account for ftgs, etc

Relocate Existing Filtration Bldg, etc

1

LS

$34,071 60' x 30' x 10' eave ht metal bldg-remove contents, dismantle & re-erect

Repairs, Touchup, etc

1

LS

$5,000 allowance for some painting, sealants, doors, etc

Water

1

LS

$4,235 sink, emer. Shower, hose bibbs, piping & service

Drains

1

LS

$2,117

Electrical

1

LS

$4,933 reinstall, fixtures, panels, wiring, etc

Tertiarv Media Filters







Filter Pump Station Complete

1

LS

$106,100

Water Reuse Pump Station Complete

1

LS

$30,000 cost by DAH

Distribution Piping

500

LF

$17,500 4" plastic, below grade

Media Filter System

2

LS

$1,133,668 quote=430000 + 10% frt + 10% mu & 10Ohrs to install

Liquid Polymer System

0

LS

$0 Not required as per JS 11/28/2000

Backwash Pumping Complete

1

LS

$190,677

Dirty Backwash Storage Tank

1

EA

$45,000 $.75/gal

Dirty Backwash Storage Tank Mixer

1

EA

$5,182 allowance

Dirty Backwash Return Pump

1

EA

$20,080 allowance

Clean Backwash Supply Tank

1

EA

$45,000 $.75/gal

Clean Backwash Supply Pump

1

EA

$20,080

Building Complete

1

LS

$637,500 $75/sf

Electrical/l&C

1

LS

$0 included

Mechanical

1

LS

$0 included

Backflow Preventer

1

EA

$10,000 allowance

Distribution Piping

2,000

LF

$46,000 2" plastic

Paint

1

LS

$10,000 misc painting allowance

CAPITAL TOTAL (ROUNDED) (Yr 2000 Dollars)

Escalate from Yr 2000 to Yr 2009 Dollars (factor of 1.358)

NOTE: The above cost opinion is in October 2000 dollars and does not include escalation.
The order of magnitude cost opinion shown has been prepared for guidance in project evaluation
at the time of preparation. The final costs of the project will depend on actual labor and material
costs, actual site conditions, productivity, competitive market conditions, final project scope, final
schedule and other variable factors. As a result, the final project costs will vary from those

$7,760,880 Year 2000 Dollars
$10,541,358 Year 2009 Dollars

Water Treatment TCD Unit Costs Master File.xls

Page 3 of 4	1/15/2010 9:21 AM


-------
AT_5,000 gpm ExpanCapital_09

Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 5,000 gpm

Order of Magnitude Cost Opinion	

Direct Capital

	Description	Quantity Unit	Unit Cost	Comments

presented above. Because of these factors, funding needs must be carefully reviewed prior to
making specific financial decisions or establishing final budgets.

Water Treatment TCD Unit Costs Master File.xls

Page 4 of 4

1/15/2010 9:21 AM


-------
AT_10,000gpm ExpanCapital_09

Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 10,000 gpm

Order of Magnitude Cost Opinion	

Description

Quantity Unit

Direct Capital
Unit Cost

Comments

HPS (Hydroxide)

Sitework/Yard Piping

Fencing

Gravel Surfacing & Misc
Connections & Relocations of Existing Piping
Reactor A (Sludge Conditioning Tank)

Earthwork & Concrete for Slab
Elevated Platform for Reactor A&B
Paint

Sludge Conditioning Tank, 2500gal FRP
Mixer, 3hp

Inlet Piping, 24" SDR 15.5
Inlet Piping, 18" SDR 15.5
Valves, vaults, etc

1,000
1
1

1
1
1
1
1

120
120
1

LF
LS
LS

LS
LS
LS
EA
EA
LF
LF
LS

The Following Costs are in Year 2000 Dollars. See Escalation Factor at Bottom.

$10,000 allowance
$35,000 allowance
$30,000 allowance

$19,872 apx 50cy @ $400/cy

$60,000 asm 40x20 @ $75/sf high level and to support reactor A
$10,000 allowance for subcontract
$42,695 quote + 5% infla. + 5%frt + 10%mu
$13,803 quote + 5% infla. + 5%frt + 10%mu

$23,242 constrained schedule & access w/obstacles, ftgs, valves, connections, etc
$17,634 constrained schedule & access w/obstacles, ftgs, valves, connections, etc
$50,000 allowance

Neutralization/Oxidation System

Distribution Piping, 24" HDPE	170	LF

Retaining Wall to Accommodate New Tanks	450	SF

Earthwork for Retaining Wall	1	LS

Earthwork & Concrete for Slab	1	LS

Paint	2	LS

Aeration Tank (Reactor B), 150,000 gal Steel Tank	2	EA

Submerged Turbine Aerator/Mixer	2	EA

Positive Displacement Blower	2	EA

Pipe Supports, Hangers, etc	1	LS

$32,926 constrained schedule & access w/obstacles, ftgs, valves, connections, etc

$11,250 90'x 8'H + 2' below grade, CIP cantelever

$13,629

$123,174 apx 450cy @ $400/cy
$151,572 allowance for subcontract
$225,000 $0.75/gal
$197,926
$32,010

$10,000 allowance

Automated Polymer Make-up & Feed System

Earthwork & Concrete for Slab

1

LS

$0 in bldg

Paint

1

LS

$5,000 allowance for subcontract

Polymer Make-up System

2

EA

$20,433

Polymer Make-up Tank, 2000gal

1

EA

$3,974

Mixer

2

EA

$4,674 corrected hours

Transfer Pump, 20gpm

2

EA

$6,548 corrected hours

Polymer Feed Tank, 2000gal

1

EA

$3,974

Water Treatment TCD Unit Costs Master File.xls

Page 1 of 3

1/15/2010 9:18 AM


-------
AT

Bunker Hill CTP
Bunker Hill Mine Water
Upgrade Existing CTP to Treat 10,000 gpm

Order of Magnitude Cost Opinion	

	Description	Quantity

Variable Speed Gear Pump, 1gpm	2

Piping to Feed Point	100

Thickener

Clean & Decommission Existing Floe System	1

Replace Weir	1

E-DUC Feed & Floe System & Hydraulic Mods	1

Sludge Wasting & Recycle Pumps

Remove Existing Pumps	1

Paint	1

Sludge Recycle Pump, 400gpm	2

Sludge Recycle Pump, 800gpm	1

Sludge Waste Pump, 400gpm, 200' tdh	1

Sludge Recycle Piping, 8" Dl	150

Sludge Wasting Piping, 6" Dl	0

l&C and Electrical

Total l&C	1

New Magnetic Flowmeter in Existing Vault	1

Parshall Flume @ Effluent	1

Electrical	1

Existing Plant Demolition

Remove Reactor A	1

Remove Aeration Basin, Ret Wall, Stairs, etc	1

Remove Flocculation Basin	1

Remove Associated Piping	1

Remove Associated Electrical	1

Regrade Area	1

Connections & Relocations of Existing Piping	1

Earthwork	1

Concrete Slab & Footings	100

Relocate Existing Filtration Bldg, etc	1

Water Treatment TCD Unit Costs Master File.xls

10,000gpm ExpanCapital_09

Direct Capital

Unit	Unit Cost	Comments	

EA	$8,421

LF	$1,990

LS	$1,775

LS	$43,010

LS	$45,934

LS	$2,474

LS	$20,000

EA	$29,234

EA	$22,048

EA	$26,380

LF	$10,271 including ftgs, valves, etc, revised cost

LF	$0 including ftgs, valves, etc, revised cost

LS	$68,294 use 5% of above

EA	$10,269 24"

EA	$5,537

LS	$115,998 use 8% of above

LS	$2,810

LS	$127,768 6000cy @ 200cy/hr

LS	$18,734 allow 40hrs

LS	$1,873

LS	$1,873

LS	$1,704

LS	$5,000 allowance

LS	$7,314

CY	$25,536 assume 18" avg thickness to account for ftgs, etc

LS	$34,071 60' x 30' x 10' eave ht metal bldg-remove contents, dismantle & re-erect

Page 2 of 3

1/15/2010 9:18 AM


-------
AT_10,000gpm ExpanCapital_09

Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 10,000 gpm

Order of Magnitude Cost Opinion	

Description

Quantity Unit

Direct Capital
Unit Cost

Comments

Repairs, Touchup, etc

Water

Drains

Electrical

LS
LS
LS
LS

$5,000 allowance for some painting, sealants, doors, etc
$4,235 sink, emer. Shower, hose bibbs, piping & service
$2,117

$4,933 reinstall, fixtures, panels, wiring, etc

Tertiary Media Filters

Filter Pump Station Complete

Water Reuse Pump Station Complete

Distribution Piping

Media Filter System

Liquid Polymer System

Backwash Pumping Complete

Dirty Backwash Storage Tank

Dirty Backwash Storage Tank Mixer

Dirty Backwash Return Pump

Clean Backwash Supply Tank

Clean Backwash Supply Pump

Building Complete

Electrical/l&C

Mechanical

Backflow Preventer

Distribution Piping

Paint

CAPITAL TOTAL (ROUNDED) (Yr 2000 Dollars)

Escalate from Yr 2000 to Yr 2009 Dollars (factor of 1.358)

1

LS

$160,818



1

LS

$30,000

cost by DAH

500

LF

$17,500

4" plastic, below grade

4

LS

$2,267,336

quote=430000 + 10% frt

0

LS

$0

Not required as per JS 1

1

LS

$289,013



1

EA

$90,000

$.75/gal

1

EA

$7,371

allowance

1

EA

$29,470

allowance

1

EA

$90,000

$.75/gal

1

EA

$29,470



1

LS

$1,275,000

$75/sf

1

LS

$0

included

1

LS

$0

included

1

EA

$10,000

allowance

000

LF

$92,000

2" plastic

1

LS

$20,000

misc painting allowance





$12,862,956

Year 2000 Dollars





$17,471,346

Year 2009 Dollars

NOTE: The above cost opinion is in October 2000 dollars and does not include escalation.
The order of magnitude cost opinion shown has been prepared for guidance in project evaluation
at the time of preparation. The final costs of the project will depend on actual labor and material
costs, actual site conditions, productivity, competitive market conditions, final project scope, final
schedule and other variable factors. As a result, the final project costs will vary from those
presented above. Because of these factors, funding needs must be carefully reviewed prior to
making specific financial decisions or establishing final budgets.

Water Treatment TCD Unit Costs Master File.xls

Page 3 of 3	1/15/2010 9:18 AM


-------

-------
Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 15,000 gpm

Order of Magnitude Cost Opinion	

AT_15,000gpm ExpanCapital_09

Description

Quantity Unit

Direct Capital
Unit Cost

Comments

HPS (Hydroxide)

Sitework/Yard Piping

Fencing

Gravel Surfacing & Misc

Connections & Relocations of Existing Piping

1,000
1
1

LF
LS
LS

The Following Costs are in Year 2000 Dollars. See Escalation Factor at Bottom.

$10,000 allowance
$40,000 allowance
$30,000 allowance

Reactor A (Sludge Conditioning Tank)

Earthwork & Concrete for Slab	1	LS

Elevated Platform for Reactor A&B	1	LS

Paint	1	LS

Sludge Conditioning Tank, 2500gal FRP	1	EA

Mixer, 3hp	1	EA

Inlet Piping, 24" SDR 15.5	120	LF

Inlet Piping, 18" SDR 15.5	120	LF

Valves, vaults, etc	1	LS

Neutralization/Oxidation System

Distribution Piping, 24" HDPE	261	LF

Retaining Wall to Accommodate New Tanks	690	SF

Earthwork for Retaining Wall	1	LS

Earthwork & Concrete for Slab	1	LS

Paint	2	LS

Aeration Tank (Reactor B), 230,000 gal Steel Tank	2	EA

Submerged Turbine Aerator/Mixer	2	EA

Positive Displacement Blower	2	EA

Pipe Supports, Hangers, etc	1	LS

Automated Polymer Make-up & Feed System

Earthwork & Concrete for Slab	1	LS

Paint	1	LS

Polymer Make-up System	2	EA

Polymer Make-up Tank, 2000gal	1	EA

Mixer	2	EA

Water Treatment TCD Unit Costs Master File.xls

$19,872 apx 50cy @ $400/cy

$60,000 asm 40x20 @ $75/sf high level and to support reactor A
$10,000 allowance for subcontract
$42,695 quote + 5% infla. + 5%frt + 10%mu
$13,803 quote + 5% infla. + 5%frt + 10%mu

$23,242 constrained schedule & access w/obstacles, ftgs, valves, connections, etc
$17,634 constrained schedule & access w/obstacles, ftgs, valves, connections, etc
$50,000 allowance

$50,487 constrained schedule & access w/obstacles, ftgs, valves, connections, etc

$17,250 90'x 8'H + 2' below grade, CIP cantelever

$13,629

$151,011 apx 450cy @ $400/cy
$195,884 allowance for subcontract
$345,000 $0.75/gal
$255,791
$39,726

$15,000 allowance

$0 in bldg
$5,000 allowance for subcontract
$20,433
$3,974

$4,674 corrected hours

Page 1 of 4

1/15/2010 9:16 AM


-------
AT

Bunker Hill CTP
Bunker Hill Mine Water
Upgrade Existing CTP to Treat 15,000 gpm

Order of Magnitude Cost Opinion	

	Description	Quantity

Transfer Pump, 20gpm	2

Polymer Feed Tank, 2000gal	1

Variable Speed Gear Pump, 1gpm	2

Piping to Feed Point	100

Thickener

Clean & Decommission Existing Floe System	1

Replace Weir	1

E-DUC Feed & Floe System & Hydraulic Mods	1

Surface Prep & Coat	0

Sludge Wasting & Recycle Pumps

Remove Existing Pumps	1

Paint	1

Sludge Recycle Pump, 400gpm	2

Sludge Recycle Pump, 800gpm	1

Sludge Waste Pump, 400gpm, 200' tdh	1

Sludge Recycle Piping, 8" Dl	150

Sludge Wasting Piping, 6" Dl	0

l&C and Electrical

Total l&C	1

New Magnetic Flowmeter in Existing Vault	1

Parshall Flume @ Effluent	1

Electrical	1

Existing Plant Demolition

Remove Reactor A	1

Remove Aeration Basin, Ret Wall, Stairs, etc	1

Remove Flocculation Basin	1

Remove Associated Piping	1

Remove Associated Electrical	1

Regrade Area	1

Connections & Relocations of Existing Piping	1

Water Treatment TCD Unit Costs Master File.xls

15,000gpm ExpanCapital_09

Direct Capital

Unit	Unit Cost	Comments

EA	$6,548 corrected hours

EA	$3,974

EA	$8,421

LF	$1,990

LS	$1,775

LS	$57,115

LS	$59,534

LS	$0 allowance for interior walls & mechanism

LS	$2,474

LS	$20,000

EA	$29,234

EA	$22,048

EA	$26,380

LF	$10,271 including ftgs, valves, etc, revised cost

LF	$0 including ftgs, valves, etc, revised cost

LS	$84,243 use 5% of above

EA	$10,269 24"

EA	$5,537

LS	$142,793 use 8% of above

LS	$2,810

LS	$127,768 6000cy @ 200cy/hr

LS	$18,734 allow 40hrs

LS	$1,873

LS	$1,873

LS	$1,704

LS	$5,000 allowance

Page 2 of 4	1/15/2010 9:16 AM


-------
AT_15,000gpm ExpanCapital_09

Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 15,000 gpm

Order of Magnitude Cost Opinion

Description

Quantity

Unit

Direct Capital

Unit Cost Comments

Earthwork

1

LS

$7,314

Concrete Slab & Footings

100

CY

$25,536 assume 18" avg thickness to account for ftgs, etc

Relocate Existing Filtration Bldg, etc

1

LS

$34,071 60' x 30' x 10' eave ht metal bldg-remove contents, dismantle & re-erect

Repairs, Touchup, etc

1

LS

$5,000 allowance for some painting, sealants, doors, etc

Water

1

LS

$4,235 sink, emer. Shower, hose bibbs, piping & service

Drains

1

LS

$2,117

Electrical

1

LS

$4,933 reinstall, fixtures, panels, wiring, etc

Tertiarv Media Filters







Filter Pump Station Complete

1

LS

$205,111

Water Reuse Pump Station Complete

1

LS

$30,000 cost by DAH

Distribution Piping

500

LF

$17,500 4" plastic, below grade

Media Filter System

6

LS

$3,401,004 quote=430000 + 10% frt + 10% mu & 10Ohrs to install

Liquid Polymer System

0

LS

$0 Not required as per JS 11/28/2000

Backwash Pumping Complete

1

LS

$368,614

Dirty Backwash Storage Tank

1

EA

$135,000 $.75/gal

Dirty Backwash Storage Tank Mixer

1

EA

$9,143 allowance

Dirty Backwash Return Pump

1

EA

$37,070 allowance

Clean Backwash Supply Tank

1

EA

$135,000 $.75/gal

Clean Backwash Supply Pump

1

EA

$37,070

Building Complete

1

LS

$1,912,500 $75/sf

Electrical/l&C

1

LS

$0 included

Mechanical

1

LS

$0 included

Backflow Preventer

1

EA

$10,000 allowance

Distribution Piping

6,000

LF

$138,000 2" plastic

Paint

1

LS

$30,000 misc painting allowance

CAPITAL TOTAL (ROUNDED) (Yr 2000 Dollars)





$17,875,000 Year 2000 Dollars

Escalate from Yr 2000 to Yr 2009 Dollars (factor of

1.358)



$24,279,000 Year 2009 Dollars

NOTE: The above cost opinion is in October 2000 dollars and does not include escalation.
The order of magnitude cost opinion shown has been prepared for guidance in project evaluation
at the time of preparation. The final costs of the project will depend on actual labor and material

Water Treatment TCD Unit Costs Master File.xls

Page 3 of 4	1/15/2010 9:16 AM


-------
AT_15,000gpm ExpanCapital_09

Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 15,000 gpm

Order of Magnitude Cost Opinion	

Direct Capital

	Description	Quantity Unit	Unit Cost	Comments

costs, actual site conditions, productivity, competitive market conditions, final project scope, final
schedule and other variable factors. As a result, the final project costs will vary from those
presented above. Because of these factors, funding needs must be carefully reviewed prior to
making specific financial decisions or establishing final budgets.

Water Treatment TCD Unit Costs Master File.xls

Page 4 of 4

1/15/2010 9:16 AM


-------
AT_20,000gpm ExpanCapital_09

Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 20,000 gpm

Order of Magnitude Cost Opinion	

Description

Quantity Unit

Direct Capital
Unit Cost

Comments

HPS (Hydroxide)

Sitework/Yard Piping

Fencing

Gravel Surfacing & Misc

Connections & Relocations of Existing Piping

1,000
1
1

LF
LS
LS

The Following Costs are in Year 2000 Dollars. See Escalation Factor at Bottom.

$10,000 allowance
$45,000 allowance
$30,000 allowance

Reactor A (Sludge Conditioning Tank)

Earthwork & Concrete for Slab	1	LS

Elevated Platform for Reactor A&B	1	LS

Paint	1	LS

Sludge Conditioning Tank, 2500gal FRP	1	EA

Mixer, 3hp	1	EA

Inlet Piping, 24" SDR 15.5	120	LF

Inlet Piping, 18" SDR 15.5	120	LF

Valves, vaults, etc	1	LS

Neutralization/Oxidation System

Distribution Piping, 24" HDPE	340	LF

Retaining Wall to Accommodate New Tanks	900	SF

Earthwork for Retaining Wall	1	LS

Earthwork & Concrete for Slab	1	LS

Paint	2	LS

Aeration Tank (Reactor B), 300,OOOgal Steel Tank	2	EA

Submerged Turbine Aerator/Mixer	2	EA

Positive Displacement Blower	2	EA

Pipe Supports, Hangers, etc	1	LS

Automated Polymer Make-up & Feed System

Earthwork & Concrete for Slab	1	LS

Paint	1	LS

Polymer Make-up System	2	EA

Polymer Make-up Tank, 2000gal	1	EA

Mixer	2	EA

Water Treatment TCD Unit Costs Master File.xls

$19,872 apx 50cy @ $400/cy

$60,000 asm 40x20 @ $75/sf high level and to support reactor A
$10,000 allowance for subcontract
$42,695 quote + 5% infla. + 5%frt + 10%mu
$13,803 quote + 5% infla. + 5%frt + 10%mu

$23,242 constrained schedule & access w/obstacles, ftgs, valves, connections, etc
$17,634 constrained schedule & access w/obstacles, ftgs, valves, connections, etc
$50,000 allowance

$65,853 constrained schedule & access w/obstacles, ftgs, valves, connections, etc

$22,500 90'x 8'H + 2' below grade, CIP cantelever

$13,629

$178,848 apx 450cy @ $400/cy
$229,740 allowance for subcontract
$450,000 $0.75/gal
$300,000
$45,620

$20,000 allowance

$0 in bldg
$5,000 allowance for subcontract
$20,433
$3,974

$4,674 corrected hours

Page 1 of 4

1/15/2010 9:15 AM


-------
AT_20,000gpm ExpanCapital_09

Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 20,000 gpm

Order of Magnitude Cost Opinion	

Direct Capital

Description

Quantity

Unit

Unit Cost

Transfer Pump, 20gpm

2

EA

$6,548 corrected hours

Polymer Feed Tank, 2000gal

1

EA

$3,974

Variable Speed Gear Pump, 1gpm

2

EA

$8,421

Piping to Feed Point

100

LF

$1,990

Comments

Thickener

Clean & Decommission Existing Floe System	1	LS	$1,775

Replace Weir	1	LS	$71,040

E-DUC Feed & Floe System & Hydraulic Mods	1	LS	$73,134

Sludge Wasting & Recycle Pumps

Remove Existing Pumps	1

Paint	1

Sludge Recycle Pump, 400gpm	2

Sludge Recycle Pump, 800gpm	1

Sludge Waste Pump, 400gpm, 200' tdh	1

Sludge Recycle Piping, 8" Dl	150

Sludge Wasting Piping, 6" Dl	0

LS	$2,474

LS	$20,000

EA	$29,234

EA	$22,048

EA	$26,380

LF	$10,271 including ftgs, valves, etc, revised cost
LF $0 including ftgs, valves, etc, revised cost

l&C and Electrical

Total l&C

New Magnetic Flowmeter in Existing Vault

Parshall Flume @ Effluent

Electrical

1	LS	$97,990 use 5% of above

1	EA	$10,269 24"

1	EA	$5,537

1	LS	$165,888 use 8% of above

Existing Plant Demolition

Remove Reactor A

Remove Aeration Basin, Ret Wall, Stairs, etc
Remove Flocculation Basin
Remove Associated Piping
Remove Associated Electrical
Regrade Area

Connections & Relocations of Existing Piping
Earthwork

Water Treatment TCD Unit Costs Master File.xls

1

LS

$2,810



1

LS

$127,768

_C
>
o
o
o

CM

ฎ

O
O
O
O
CD

1

LS

$18,734

allow 40hrs

1

LS

$1,873



1

LS

$1,873



1

LS

$1,704



1

LS

$5,000

allowance

1

LS

$7,314



Page 2 of 4

1/15/2010 9:15 AM


-------
AT_20,000gpm ExpanCapital_09

Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 20,000 gpm

Order of Magnitude Cost Opinion

Description

Quantity

Unit

Direct Capital

Unit Cost Comments

Concrete Slab & Footings

100

CY

$25,536 assume 18" avg thickness to account for ftgs, etc

Relocate Existing Filtration Bldg, etc

1

LS

$34,071 60' x 30' x 10' eave ht metal bldg-remove contents, dismantle & re-erect

Repairs, Touchup, etc

1

LS

$5,000 allowance for some painting, sealants, doors, etc

Water

1

LS

$4,235 sink, emer. Shower, hose bibbs, piping & service

Drains

1

LS

$2,117

Electrical

1

LS

$4,933 reinstall, fixtures, panels, wiring, etc

Tertiarv Media Filters







Filter Pump Station Complete

1

LS

$243,600

Water Reuse Pump Station Complete

1

LS

$30,000 cost by DAH

Distribution Piping

500

LF

$17,500 4" plastic, below grade

Media Filter System

8

LS

$4,534,673 quote=430000 + 10% frt + 10% mu & 10Ohrs to install

Liquid Polymer System

0

LS

$0 Not required as per JS 11/28/2000

Backwash Pumping Complete

1

LS

$464,445

Dirty Backwash Storage Tank

1

EA

$180,000 $.75/gal

Dirty Backwash Storage Tank Mixer

1

EA

$10,683 allowance

Dirty Backwash Return Pump

1

EA

$43,675 allowance

Clean Backwash Supply Tank

1

EA

$180,000 $.75/gal

Clean Backwash Supply Pump

1

EA

$43,675

Building Complete

1

LS

$2,550,000 $75/sf

Electrical/l&C

1

LS

$0 included

Mechanical

1

LS

$0 included

Backflow Preventer

1

EA

$10,000 allowance

Distribution Piping

8,000

LF

$184,000 2" plastic

Paint

1

LS

$40,000 misc painting allowance

CAPITAL TOTAL (ROUNDED) (Yr 2000 Dollars)

Escalate from Yr 2000 to Yr 2009 Dollars (factor of 1.358)

$22,800,505 Year 2000 Dollars
$30,969,204 Year 2009 Dollars

NOTE: The above cost opinion is in October 2000 dollars and does not include escalation.
The order of magnitude cost opinion shown has been prepared for guidance in project evalu;
at the time of preparation. The final costs of the project will depend on actual labor and mate
costs, actual site conditions, productivity, competitive market conditions, final project scope, 1

Water Treatment TCD Unit Costs Master File.xls

Page 3 of 4

1/15/2010 9:15 AM


-------
AT_20,000gpm ExpanCapital_09

Bunker Hill CTP

Bunker Hill Mine Water

Upgrade Existing CTP to Treat 20,000 gpm

Order of Magnitude Cost Opinion	

Direct Capital

	Description	Quantity Unit	Unit Cost	Comments

schedule and other variable factors. As a result, the final project costs will vary from those
presented above. Because of these factors, funding needs must be carefully reviewed prior
making specific financial decisions or establishing final budgets.

Water Treatment TCD Unit Costs Master File.xls

Page 4 of 4

1/15/2010 9:15 AM


-------