EPA 530-R-25-012

Resource Conservation and Recovery Act (RCRA)
Hazardous Waste Model Permit
General Facility Conditions Module

This module provides guidance to EPA, state, and territorial permitting authorities. The
statements in this document are intended solely as guidance. This document is not intended,
nor can it be relied upon, to create any rights enforceable by any party in litigation with the
United States. Permitting authorities may decide to follow the guidance provided in this
document, or to act at variance with the guidance based on its analysis of the specific facts
presented.

When EPA releases a new or revised model permit module, it replaces the corresponding
module, including the corresponding module in the 1988 Model RCRA Permit for Hazardous
Waste Management Facilities (Draft).

EPA RCRA Hazardous Waste Model Permit (Guidance)	Last Updated: April 2025


-------
RCRA PERMIT

{Facility Name and Location}

EPA ID# {XXX}

MODULE II, Page 1 of 11
{Date}

MODULE II. GENERAL FACILITY CONDITIONS

{Permit Writer: This permit module contains conditions covering the general facility standards of
40 CFR part 264, Subpart B. (Note that some requirements in Subpart B, such as the General
Waste Analysis, are included in other Modules.)

The model permit conditions in this module reference federal regulations and guidance. Permit
Writers should confirm their regulatory citations and their authority's guidance for each permit
condition and replace (or add to) the federal citations with state analogous regulatory citations
and/or references as applicable. When jointly issuing permits, the federal Permit Writer will
issue the federal permit citing the federal regulations while the state Permit Writer will cite the
state analogous regulatory citation in the state's jointly issued permit.

Permit Writers can insert the title(s) of their regulatory authority's appropriate officiol(s) for or
in addition to instances where the module uses "Director." When jointly issuing permits, the
federal Permit Writer will cite the EPA Region's appropriate official in the federal permit and the
state will cite the state's appropriate official in the state's permit.}

11.A. GENERAL FACILITY DESCRIPTION

{Insert a narrative description of the Facility, including general overview of hazardous wastes
generated and/or received and managed by the Facility. Include in the general overview, such
as in the table below, hazardous waste units subject to this permit; solid waste management
units and areas of concern subject to corrective action; and other units that manage hazardous
waste or hazardous secondary material, but which are not subject to permitting, such as
hazardous wastes managed in an exempt recycling unit or approved hazardous secondary
materials excluded from regulation. Include a Facility Map as an appendix or attachment to the
permit. Reference the Facility map in the Facility Description. Indicate the location of all
hazardous waste management units (HWMUs), solid waste management units (SWMUs), areas
of concern (AOCs), a generator's less-than-90-day accumulation unit, recycling units, and other
exempted units on the referenced Facility Map. Include in the Facility description, how
residuals and newly generated hazardous waste streams from production processes, hazardous
waste treatment, or recycling processes at the Facility will be managed, (e.g., wastewater is
sent through a wastewater treatment system and is discharged to the local publicly owned
treatment works pursuant to a Clean Water Act discharge permit).} [Refer to 40 CFR
270.14(b)(1).]

II.A.l. The Permittee is authorized to {treat, store, dispose of, or manage} the following
hazardous wastes in, and only in, the following hazardous waste management units (HWMUs)
and solid waste management units (SWMUs), subject to the terms of this Permit. [Refer to 40
CFR 270.13(j).]

EPA RCRA Hazardous Waste Model Permit (Guidance)

Last Updated: April 2025


-------
RCRA PERMIT

{Facility Name and Location}
EPA ID# {XXX}

MODULE II, Page 2 of 11
{Date}

Unit Name

Type of Unit

Status: Active/Post-closure

Hazardous Waste Codes
Managed

ex. Dropout Tank 12

5000 gal Tank

Active

D001, D019, K031

















II.A.2. The Permittee also has the following units that manage hazardous waste or hazardous
secondary material and which are excluded or exempt from this Permit's requirements. [40 CFR
270.13(j).]

Unit Name

Type of Unit

(Unit

managing

excluded

HSM*, 90-day

accumulation)

Status

Active/Inactive
/Closed

Decision
Issuance and
Expiration
Dates

Hazardous Waste
Codes or Hazardous
Secondary Material
Managed

Exemption or
Exclusion Citation

ex. Solvent
Purifier

Distillation
Unit

Active

Conditional
5/10/2010 -
5/10/2020

Toluene

40 CFR 261.4(a)(27),
40 CFR 260.43

























*{Permit Writer: If the permitting authority has sufficient information from the permit
application to clearly identify that one or more units or activities managing a hazardous waste
has been granted an exemption, exclusion, variance, non-waste determination, or has been
determined to satisfy legitimate recycling of hazardous secondary material criteria, the Permit
Writer can identify the waste code or hazardous secondary material in the 'Hazardous Waste
Codes Managed' column of the above Table. This documentation of the exemption or exclusion
granted or legitimate recycling determination and supporting demonstration can be
documented in the Approved Permit Application and available in the Administrative Record. For
units that satisfy an exemption, the Permit Writer can state the applicable citation for the
exemption, exclusion, variance, non-waste determination, or recyclable material regulatory
criteria that the applicant satisfies and with which it is complying and include the issuance and
expiration date of the regulatory authority's decision. The regulatory authority's issued decision
granting the exemption, exclusion, or legitimate recycling determination may include conditions.
The permit application can include the decision document to clarify the authority's full decision.
If the decision is conditional, note "conditional" in the 'Issuance and Expiration Date' column.}

II.A.3. Should the Director receive any information that this general Facility description is
inaccurate or incomplete and one or more of the causes listed in 40 CFR 270.41 (a) and (b) for
modification or revocation and reissuance exist, the Director may modify or revoke and reissue

EPA RCRA Hazardous Waste Model Permit (Guidance)

Last Updated: April 2025


-------
RCRA PERMIT

{Facility Name and Location}

EPA ID# {XXX}

MODULE II, Page 3 of 11
{Date}

the permit accordingly. This includes material and substantial alterations or additions to the
permitted Facility or activity which occurred after permit issuance which justify the application
of permit conditions that are different or absent in the existing permit. This also includes
information not available at the time of permit issuance which would have justified the
application of different permit conditions at the time of issuance. [Refer to 40 CFR 270.41.]

II.B. PERMITTED AND PROHIBITED WASTE

II.B.l. Permitted Waste Management

The Permittee may treat, store, and dispose only those hazardous wastes identified in Permit
Condition 11.A. only in hazardous waste management units (HWMUs) as specified in this Permit,
and subject to the terms of this Permit. [Refer to 40 CFR 270.13(j).]

II.B.2. Prohibited Waste Management

The Permittee is prohibited from treating, storing, or disposing of the following materials:
{include a list of prohibited wastes. For example, "Hazardous Waste Nos. F020, F021, F022,
F023, F026, F027; Toxic Substances Control Act (TSCA)-regulated polychlorinated biphenyl (PCB)
waste(s) subject to the disposal requirements of 40 C.F.R. Part 761 Subpart D; regulated
infectious waste; regulated radioactive waste; compressed gases; explosives."} The Permittee is
prohibited from treating, storing, or disposing hazardous wastes that are not identified in
Condition II.B.l.

II.C. REQUIRED NOTICES

{Permit Writer: Include permit conditions II.C.l, and II.C.2, if applicable. Permit Condition II.C.l
should be included in the Permit only if the Facility receives waste from a foreign source. If
Permit Condition II.C.l does not apply, the Permit should specify that the Permittee may not
receive hazardous waste from a foreign source, for example, in Permit Condition I.A.I, in
Module I.}

II.C.l. If the Permittee will arrange to receive hazardous waste subject to 40 CFR part 262,
subpart H, from a foreign source, the Permittee must submit notice of such import in
accordance with required notices requirements in 40 CFR 264.12(a) and must comply with the
imports of hazardous waste requirements in 40 CFR 262.84, and the use of manifest system
requirements in 40 CFR 264.71(a)(3) and 264.71(d). [Refer to 40 CFR 264.12(a).]

{Permit Writer: Permit Condition II.C.2 should be included in the Permit only if the Facility
receives waste from offsite. If Permit Condition II.C.2 does not apply, the Permit should specify
that the Permittee may not receive hazardous waste from offsite, for example, in Permit

EPA RCRA Hazardous Waste Model Permit (Guidance)

Last Updated: April 2025


-------
RCRA PERMIT

{Facility Name and Location}

EPA ID# {XXX}

MODULE II, Page 4 of 11
{Date}

Condition I.A.I.}

II.C.2. When the Permittee is to receive hazardous waste from an offsite source (except where
the Permittee is also the generator), the Permittee must inform the generator in writing that
the Permittee has the appropriate hazardous waste permit(s) for, and will accept, the waste the
generator is shipping. The Permittee must keep a copy of this written notice as part of the
Facility's Operating Record in accordance with 40 CFR 264.73. [Refer to 40 CFR 264.12(b).]

II.D. SECURITY

{Permit Writer: If the Permittee successfully demonstrates, in accordance with 40 CFR 264.14(a),
that the security requirements in 40 CFR 264.14(b) and (c) are not necessary, these security
permit conditions are not needed. This demonstration must be documented in the
Administrative Record and the Permittee's Approved Permit Application.}

II.D.l. The Permittee must prevent the unknowing entry, and minimize the possibility for the
unauthorized entry, of persons or livestock onto the active portion of the Facility in accordance
with Section {XXX} of the Approved Permit Application. [Refer to 40 CFR 264.14(a).]

II.D.2. {Permit Writer: Include here specific and applicable security provisions as necessary to
ensure compliance with 40 CFR 264.14(b), including whether the Facility must use a 24-hour
surveillance system or an artificial or natural barrier along with a means to control entry.} [Refer
to 40 CFR 264.14(b).]

II.D.3. The Permittee must post at each entrance to the active portion of the Facility {and in
(insert other locations as needed)} a sign that says "Danger - Unauthorized Personnel Keep
Out." The sign must be written in English language {and in (insert other predominantly spoken
languages) in the area surrounding the Facility}. The sign must be legible from a distance of at
least 25 feet. [Refer to 40 CFR 264.14(c).]

II.E. GENERAL INSPECTION REQUIREMENTS

II.E.l. The Permittee must inspect the Facility for malfunctions and deterioration, operator
errors, and discharges which may be causing - or may lead to (1) release of hazardous waste
constituents to the environment or (2) a threat to human health. The Permittee must conduct
these inspections {insert frequency; must be frequently enough to prevent harm to human
health or the environment} in accordance with the Inspection Plan, Section {XXX} of the
Approved Permit Application to identify problems in time to correct them before they harm
human health or the environment. [Refer to 40 CFR 264.15(a) and 270.14(b)(5).]

II.E.2. The Permittee must follow the written schedule ("inspection schedule") for inspecting

EPA RCRA Hazardous Waste Model Permit (Guidance)

Last Updated: April 2025


-------
RCRA PERMIT

{Facility Name and Location}

EPA ID# {XXX}

MODULE II, Page 5 of 11
{Date}

monitoring equipment, safety and emergency equipment, security devices, and operating and
structural equipment that are important to preventing, detecting, or responding to
environmental or human health standards in accordance with Section {XXX} of the Approved
Permit Application. The Permittee must maintain a copy of this written inspection schedule
with the Inspection Plan at the Facility. [Refer to 40 CFR 264.15(b)(1) and (b)(2) and
270.14(b)(5)]

II.E.3. The inspection form and instructions must identify the types of problems (e.g.,
malfunctions or deterioration) which are to be looked for during the inspection in accordance
with the written Inspection Plan, Section {XXX} of the Approved Permit Application. The
inspection form must state the frequency of inspection for each item. The frequency of
inspection of the items identified in Section {XXX} of the Approved Permit Application must be
based on the rate of deterioration of the equipment and the probability of an environmental or
human health incident if the deterioration, malfunction, or operator error goes undetected
between inspections. [Refer to 40 CFR 264.15(b)(3) and (b)(4) and 270.14(b)(5).]

II.E.4. The Inspection Plan must include at a minimum, the items and inspection frequencies
identified in 40 CFR {264.174, 264.193, 264.195, 264.226, 264.254, 264.278, 264.303, 264.347,
264.602, 264.1033, 264.1052, 264.1053, 264.1058, and 264.1083 through 264.1089}. [Refer to
40 CFR 264.15(b)(4) and 270.14(b)(5).]

II.E.5. The Permittee must remedy any deterioration or malfunction of equipment or structures
identified during the inspection, on a schedule which ensures that the problem does not lead to
an environmental or human health hazard in accordance with Section {XXX} of the Approved
Permit Application. Where a hazard is imminent or has already occurred, the Permittee must
take remedial action immediately in accordance with the Contingency Plan in Section {XXX} of
the Approved Permit Application. [Refer to 40 CFR 264.15(c) and 40 CFR Part 264, Subpart D,
including 40 CFR 264.50, 270.14(b)(5), and 270.14(b)(7).]

II.E.6. The Permittee must record inspections in an inspection log or form in the Facility's
operating record available upon request. The Permittee must retain these records of inspection
for at least three (3) years from the date of inspection. At a minimum, the inspection record
must include the date and time of the inspection, name of the inspector, notations of the
observations or monitor measurement for each item inspected, and the date and nature of any
repairs or other remedial action to address the inspection observation. [Refer to 40 CFR
264.15(d).]

{Permit Writer: The Permittee is required to submit the inspection plan that includes the
inspection schedule with their RCRA permit application. The Permit Writer may request the
applicant modify or amend the schedule as necessary as part of the permit application review
and approval process. The Permit Writer may clarify any specific conditions relating to the

EPA RCRA Hazardous Waste Model Permit (Guidance)

Last Updated: April 2025


-------
RCRA PERMIT

{Facility Name and Location}

EPA ID# {XXX}

MODULE II, Page 6 of 11
{Date}

inspection schedule and/or reference the appropriate section of the Approved Permit
Application. Other Conditions may be included such as specific instructions; for example, that
monitoring event record measurements must include all or just the highest measurements
monitored for each monitoring point or that measurements must be captured to the second
decimal. The Permit Writer should confirm their authorized program's requirements for
inspection reports, including data quality and include any additional permit conditions needed
to clarify the program's reporting requirements. The Permit Writer should include any additional
data quality information (e.g., calibrations, monitoring time, recorded monitor measurement) in
the conditions that their authority requires to document a complete inspection or monitoring
record.}

II.F. PERSONNEL TRAINING

II.F.l. Facility personnel, including any operators and contractors, must successfully complete a
training program for their position and responsibilities at the Facility, in accordance with
Section {XXX} of the Approved Permit Application. [Refer to 40 CFR 264.16(a)(1) and
270.14(b)(12).]

II.F.2. The program must be directed by the person identified in Section {XXX} of the Approved
Permit Application who is trained in hazardous waste management procedures, and must
include instruction for Facility personnel in the hazardous waste management procedures
relevant to their positions in which they are employed. [Refer to 40 CFR 264.16(a)(2) and
270.14(b)(12).]

II.F.3. The training program must be designed to ensure that Facility personnel are able to
respond effectively to emergencies by familiarizing them with emergency procedures,
emergency equipment, and emergency systems in accordance with Section {XXX} of the
Approved Permit Application. [Refer to 40 CFR 264.16(a)(3) and 270.14(b)(12).]

{Permit Writer: If the Permittee elects that the Facility employees that receive emergency
response training pursuant to Occupational Safety and Health Administration (OSHA)
regulations 29 CFR 1910.120(p)(8) and 1910.120(q), use the following condition in lieu of
condition above.)

(Alternate) II.F.3. The Permittee has elected to train Facility employees that receive emergency
response training pursuant to Occupational Safety and Health Administration (OSHA)
regulations 29 CFR 1910.120(p)(8) and 1910.120(q), therefore the Facility is not required to
provide separate emergency response training pursuant to this section. The Permittee must
review the overall Facility training and certify that it continues to satisfy all the requirements of
40 CFR 264.16 and Section {XXX} of the Approved Permit Application {annually}, by {June 1} of
each calendar year, in the Facility's operating record. Upon review, if the overall Facility training

EPA RCRA Hazardous Waste Model Permit (Guidance)

Last Updated: April 2025


-------
RCRA PERMIT

{Facility Name and Location}

EPA ID# {XXX}

MODULE II, Page 7 of 11
{Date}

program no longer satisfies 40 CFR 264.16 and Section {XXX} of the Approved Permit
Application, the Permittee must revise Section {XXX} of the Approved Permit Application to
provide emergency response training and request a permit modification. [Refer to 40 CFR
264.16(a)(4) and 270.14(b)(12).]

II.F.4. Facility personnel must successfully complete the Facility's training program for their
position in accordance with conditions II.F.l. through II.F.4. and Section {XXX} of the Approved
Permit Application, within six months after the date of their employment or assignment to the
Facility, or to a new position at the Facility, whichever is later. [Refer to 40 CFR 264.16(b) and
270.14(b)(12).]

II.F.5. Facility personnel must take part in an annual review of the material included in their
initial training, see conditions II.F.l. through II.F.4. The Permittee must document that each
Facility employee has completed this annual review of the initial training compliant with this
Permit and Section {XXX} of the Approved Permit Application, by {June 1} of each calendar year,
in the Facility's operating record. If the review identifies any changes in the training program
necessary to remain in compliance with this Permit, the Permittee must request a permit
modification indicating the necessary revisions to the training program in the Approved Permit
Application by {June 1} of each calendar year. [Refer to 40 CFR 264.16(c) and 270.14(b)(12).]

II.F.6. The Permittee must record both introductory and continuing training that is given to each
person related to hazardous waste management, in the employee's personnel record. Training
records must include a description of the type and amount of the training, including training
content, date of training, total training hours for the training date, certification date as
applicable, and other relevant training information like the name of the instructor or training
provider and their qualification to instruct the training event. [Refer to 40 CFR 264.16(d).]

II.F.7. The Permittee must maintain and keep training documents on current personnel at the
Facility until closure of the facility in accordance with 40 CFR 264.16(d) and (e), Section {XXX} of
the Approved Permit Application and permit condition 1.1.I.e. Training records on former
employees must be kept for at least three years from the date the employee last worked at the
facility. Personnel training records may accompany personnel transferred within the same
company, and records [Refer to 40 CFR 264.16(e) and 270.14(b)(12).]

{Permit Writer: The Permittee's training program must be included in the Approved Permit
Application. The training program must demonstrate how the Permittee will comply with 40 CFR
264.16.}

II.G. REQUIREMENTS FOR IGNITABLE. REACTIVE. OR INCOMPATIBLE WASTES

II.G.l. The Permittee must take precautions, as documented in Section {XXX} of the Approved
EPA RCRA Hazardous Waste Model Permit (Guidance)	Last Updated: April 2025


-------
RCRA PERMIT

{Facility Name and Location}

EPA ID# {XXX}

MODULE II, Page 8 of 11
{Date}

Permit Application, to prevent accidental ignition or reaction of ignitable or reactive waste. The
Permittee must separate and protect ignitable and reactive waste from sources of ignition or
reaction including but not limited to open flames, smoking, cutting and welding, hot surfaces,
frictional heat, sparks (static, electrical, or mechanical), spontaneous ignition (e.g., from heat-
producing chemical reactions), and radiant heat. While ignitable or reactive waste is being
handled, the Permittee must confine smoking and open flame to specially designated locations.
The Permittee must conspicuously place "No Smoking" signs wherever there is a hazard from
ignitable or reactive waste. [Refer to 40 CFR 264.17(a) and 270.14(a)(9).]

II.G.2. The Permittee must take precautions to prevent reactions which generate extreme heat
or pressure, fire or explosions, or violent reactions; produce uncontrolled toxic mists, fumes,
dusts, or gases in sufficient quantities to threaten human health or the environment; produce
uncontrolled flammable fumes or gases in sufficient quantities to pose a risk of fire or
explosions; damage the structural integrity of the device or Facility; and through other like
means threaten human health or the environment. [Refer to 40 CFR 264.17(b).]

II.G.3. The Permittee must demonstrate compliance with conditions II.G.l and II.G.2. in the
Facility's operating records in accordance with Section {XXX} of the Approved Permit
Application. This documentation may be based on references to published scientific or
engineering literature, data from trial tests (e.g., bench scale or pilot scale tests), waste
analyses (as specified in 40 CFR 264.13), or the results of the treatment of similar wastes by
similar treatment processes and under similar operating conditions. [Refer to 40 CFR 264.17(c)
and 270.14(a)(9).]

{Permit Writer: The permitting authority can require documentation of compliance be updated
on a specific timeline (e.g., daily, weekly, monthly) if site specific information supports it.

Permits must include specific handling procedures tailored to the hazardous wastes to be
treated, stored, or disposed at the Facility and the units in which the wastes will be handled.
During permit application review, Permit Writers should evaluate the characteristics of each
hazardous waste in relationship to the Facility's HWMU design and management practices to
ensure that the Permittee has anticipated potential hazardous conditions or activities that could
cause fire or uncontrolled reactions and that the Permittee has proposed an adequate
prevention and contingency plan for all anticipated hazardous conditions and events in the
Facility's permit application prior to determining the permit application complete. Refer to the
Preparedness and Prevention, and Contingency Plan modules of the RCRA Hazardous Waste
Model Permit.}

II.H. LOCATION STANDARDS

{Permit Writer: Include permit condition II. H., if applicable.

EPA RCRA Hazardous Waste Model Permit (Guidance)

Last Updated: April 2025


-------
RCRA PERMIT

{Facility Name and Location}

EPA ID# {XXX}

MODULE II, Page 9 of 11

{Date}

EPA has prepared guidance on locating hazardous waste management facilities in sensitive
locations. These locations include floodplains, wetlands, groundwater earthquake zones, karst
soils, unstable terrain, unfavorable weather conditions, and incompatible land use. If a facility
will be located in a sensitive area, the Permit Writer can insert permit conditions deemed
necessary to protect human health and the environment. For example, more frequent facility
inspections, special operating restrictions, or construction of thicker floors or liners could be
required. Such permit conditions are authorized by 40 CFR 270.3, 270.32(a), and 270.32(b)(2).
Refer to Sensitive Environments and the Siting of Hazardous Waste Management Facilities at
https://nepis. epa. gov/Exe/ZyPDF. cgi/1 OOOOMVX. PDF?Dockey=l OOOOMVX. PDF.

Portions of new facilities where treatment, storage, or disposal of hazardous waste will be
conducted must not be located within 61 meters (200 feet) of a fault which has had
displacement in Holocene time. Procedures for demonstrating compliance with this standard
must be documented in the Permittee's Approved Permit Application and are specified in 40 CFR
270.14(b)(ll). Facilities which are located in political jurisdictions other than those listed in
Appendix VI of part 264 are assumed to be in compliance with this requirement. [Refer to 40
264.18(a).]

For facilities located in a 100-year floodplain, the Permit Writer should specify measures the
Permittee must take to satisfy the requirements of 40 CFR 264.18(b), such as specific design,
construction, operation, or maintenance requirements that will prevent washout of any
hazardous waste, unless the Permittee can demonstrate that procedures are in effect that will
ensure the waste will be removed safely, before flood waters can reach the Facility, to a location
where the wastes will not be vulnerable to flood waters as necessary. Response to potential
flood events should be fully addressed in the Approved Permit Application Contingency Plan to
demonstrate how the Permittee's flood contingency plans satisfy 40 CFR 264.18(b). Conditions
are not needed for existing surface impoundments, waste piles, land treatment units, and
landfills if the Permittee has demonstrated, in accordance with 40 CFR 264.18(b)(1)(H), that
there will be no adverse effects on human health or the environment if washout occurred. This
demonstration must be documented in the Administrative Record and the Approved Permit
application with the regulatory authority's determination. If the Facility is not located in a 100-
year floodplain, the Permit Writer can delete permit condition II.H.l from the permit and mark
as "Reserved".}

II.H.l. The Permittee must design, construct, operate, and maintain units located in a 100-year
floodplain to prevent washout of any hazardous waste per Section {XXX} of the Approved
Permit Application. [Refer to 40 CFR 264.18(b) and 270.14(b)(ll)(iv).]

{Permit Writer: Resources available for the 100-year floodplain maps include the NOAA Sea
Level Rise Viewer (https://coast.noaa.g0v/slr/#/layer/slr), and the FEMA Flood Maps

EPA RCRA Hazardous Waste Model Permit (Guidance)

Last Updated: April 2025


-------
RCRA PERMIT

{Facility Name and Location}

EPA ID# {XXX}

MODULE II, Page 10 of 11
{Date}

(https://msc.fema.gov/portal/home). The Permit Writer should review the flood information
and tools and adjust for the regulatory authority's preferred sources and tools.}

ILL CONSTRUCTION QUALITY ASSURANCE PROGRAM

{Permit Writer: Include permit condition 11.1.1. if the Permittee has surface impoundments,
waste piles, or landfill units required to comply with 40 CFR 264.221(c) and (d), 264.251(c) and
(d), 264.301(c) and (d). If not applicable, you can delete permit condition II.1.1 and mark
"Reserved."}

II.1.1. The Permittee must maintain a construction quality assurance (CQA) program and
implement their written CQA plan compliant with 40 CFR 264.19 in Section {XXX} of the
Approved Permit Application. Requirements under the CQA for specific units are referenced in
the unit-specific sections of this permit and the Approved Permit Application. [Refer to 40 CFR
264.19.]