TRUST PROJECT TIMELINE FOR WORK AT THE FORMER EXIDE FACILITY 2020 2021 2022-2023 DECONTAMINATION & DECONSTRUCTION Pre-Oct Smelter Building Segment 1 Completed by Exide Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May-Dec Areas that processed hazardous waste including five buildings will be cleaned and removed. Smelter Building Segment 2** Started by Exide Resumed by the Trust Smelter Building Segment 3* *Work was paused due to processing of an AQMD Permit Modification and to proactively address increased lead. concentrations in ambient air atone of the five monitors. Two Hazardous Waste Storage Structures and Tanks Finished Lead Building Removal of interior equipment BOARDING UP The ancillary (support) buildings, that did not process hazardous waste, will be boarded up on site. Ancillary Buildings Deconstruction Planning Unanticipated actions required by AQMD for deconstruction and decontamination of ancillary buildings has resulted in exceedance of available funds. Buildings were boarded up. OPERATION & MAINTENANCE Site controls such as wastewater treatment operations and air monitoring will occur for two years costing about $5.2 million. Wastewater Treatment Plant Waste Removal Continuation of Site Controls *The EPA's health-based standard for lead in the ambient air was not exceeded. Click here for more information on the temporary shutdown and the mitigation action taken. **This includes the dismantle of the Full Enclosure Unit. ------- |