TRUST PROJECT TIMELINE FOR WORK AT THE FORMER EXIDE FACILITY

2020

2021

2022-2023

DECONTAMINATION
& DECONSTRUCTION

Pre-Oct

Smelter Building
Segment 1

Completed by Exide

Oct

Nov Dec

Jan

Feb

Mar

Apr May Jun Jul Aug Sep

Oct

Nov

Dec Jan Feb

Mar

Apr

May-Dec

Areas that processed
hazardous waste
including five buildings will
be cleaned and removed.

Smelter Building Segment 2**

Started by Exide

Resumed by the Trust

Smelter Building Segment 3*

*Work was paused due to processing of an AQMD Permit
Modification and to proactively address increased lead.
concentrations in ambient air atone of the five monitors.

Two Hazardous
Waste Storage
Structures and Tanks

Finished Lead Building

Removal of interior
equipment

BOARDING UP

The ancillary (support)
buildings, that did not
process hazardous waste,
will be boarded up on site.

Ancillary Buildings

Deconstruction
Planning

Unanticipated actions required by AQMD for deconstruction and decontamination of ancillary
buildings has resulted in exceedance of available funds. Buildings were boarded up.

OPERATION &
MAINTENANCE

Site controls such as
wastewater treatment
operations and air
monitoring will occur for
two years costing about
$5.2 million.

Wastewater
Treatment
Plant Waste
Removal

Continuation
of Site Controls

*The EPA's health-based standard for lead in the ambient air was not exceeded. Click here for more information on the temporary shutdown and the mitigation action taken.
**This includes the dismantle of the Full Enclosure Unit.


-------