FIFTH FIVE-YEAR REVIEW REPORT FOR
ABC ONE-HOUR CLEANERS SUPERFUND SITE
ONSLOW COUNTY, NORTH CAROLINA

&EPA

JUNE 2023

Prepared by

U.S. Environmental Protection Agency
Region 4
Atlanta, Georgia

Digitally signed by WILLIAM

WILLIAM KEEFER KEEFER

Date: 2023.06.14 13:35:35 -04'00'

For:

Randall ChafFins, Acting Director
Superfund & Emergency Management Division

6/14/2023

Date


-------
ii


-------
Table of Contents

LIST OF ABBREVIATIONS AND ACRONYMS	iii

I.	INTRODUCTION	1

Site Background	1

Five-Year Review Summary Form	2

II.	RESPONSE ACTION SUMMARY	4

Basis for Taking Action and Response Actions	4

Status of OU-3 Implementation	8

Institutional Control (IC) Review	10

Operations and Maintenance	11

III.	PROGRESS SINCE THE PREVIOUS REVIEW	15

IV.	FIVE-YEAR REVIEW PROCESS	19

Community Notification, Community Involvement and Site Interviews	19

Data Review	19

Site Inspection	21

V.	TECHNICAL ASSESSMENT	22

QUESTION A: Is the remedy functioning as intended by the decision documents?	22

QUESTION B: Are the exposure assumptions, toxicity data, cleanup levels and RAOs used at the

time of the remedy selection still valid9	22

QUESTION C: Has any other information come to light that could call into question the
protectiveness of the remedy9	23

VI.	ISSUES/RECOMMENDATIONS	24

VII.	PROTECTIVENESS STATEMENT	24

VIII.	NEXT REVIEW	24

APPENDIX A - REFERENCE LIST	A-1

APPENDIX B - CURRENT SITE STATUS	B-l

APPENDIX C - SITE CHRONOLOGY	C-l

APPENDIX D - SITE MAPS	D-l

APPENDIX E - PRESS NOTICE	E-l

APPENDIX F - INTERVIEW FORMS	F-l

APPENDIX G - SITE INSPECTION CHECKLIST	G-l

APPENDIX H - SITE INSPECTION PHOTOS	H-l

Tables

Table 1: Overview of Overview of the OU-1 and OU-2 Efforts	7

Table 2: Remedial Action Objectives	8

Table 3: Cleanup Levels	8

Table 4: Overview of the OU-3 Efforts	10

Table 5: Summary of Planned and/or Implemented ICs	 14

Table 6: Protectiveness Determinations and Statements from the 2018 FYR Report	15

Table 7: Status of Recommendations from the 2018 FYR Report 	 16

Table C-l: Site Chronology	C-l

iii


-------
Figures

Figure 1: Site Vicinity Map	3

Figure 2: Site Detail Map	5

Figure 3: Groundwater Plume Originating from the Site	 12

Figure 4: Institutional Controls Map for the South/Southeast Component of the Groundwater Plume... 13

Figure D-l: Groundwater Elevations - Surficial Aquifer	D-1

Figure D-2: Groundwater Elevations - Castle-Hayne Aquifer	D-2

Figure D-3: 2017 PCE Concentrations - Surficial Aquifer	D-3

Figure D-4: 2017 PCE Concentrations - Castle-Hayne Aquifer	D-4

Figure D-5: 2018 Remedial Design Surface Soil Sampling	D-5

Figure D-6: 2018 Remedial Design Subsurface Soil Sampling	D-6

Figure D-7: 2018 Remedial Design Inferred NAPL Locations	D-7

Figure D-8: 2019 Soil-gas Sampling	D-8

li


-------
CERCLA
CFR
COC
DCE

DNAPL

DPT

EPA

ESD

FS

FYR

HH&E

HHRA

IC

ISTR

MCBCL

MCL

mg/ft3

mg/kg

|ig/kg

MNA

NAPL

NCDENR

NCDEQ

NCP

NPL

O&M

OU

PCE

PRP

PTW

RAO

RD

RI

ROD

RPM

SB

SVE

TCE

TCRA

UU/UE

VI

LIST OF ABBREVIATIONS AND ACRONYMS

Comprehensive Environmental Response, Compensation, and Liability Act
Code of Federal Regulations
Contaminant of Concern
Di chl oroethyl ene

Dense Non-Aqueous Phase Liquid

Direct Push Technology

United States Environmental Protection Agency

Explanation of Significant Differences

Feasibility Study

Five-Year Review

Human Health and Environment

Human Health Risk Assessment

Institutional Control

In-Situ Thermal Remediation

Marine Corps Base Camp Lejeune

Maximum Contaminant Level

Milligrams per cubic Feet

Milligrams per Kilogram

Micrograms per Kilogram

Monitored Natural Attenuation

Non-Aqueous Phase Liquid

North Carolina Department of Environment and Natural Resources

North Carolina Department of Environmental Quality

National Contingency Plan

National Priorities List

Operation and Maintenance

Operable Unit

T etrachl oroethyl ene

Potentially Responsible Party

Principal Threat Waste

Remedial Action Objective

Remedial Design

Remedial Investigation

Record of Decision

Remedial Project Manager

Soil Boring

Soil Vapor Extraction

T ri chl oroethylene

Time-Critical Removal Action

Unlimited Use and Unrestricted Exposure

Vapor Intrusion

111


-------
I. INTRODUCTION

The purpose of a five-year review (FYR) is to evaluate the implementation and performance of a remedy
to determine if the remedy is and will continue to be protective of human health and the environment
(HH&E). The methods, findings and conclusions of reviews are documented in FYR reports such as this
one. In addition, FYR reports identify issues found during the review, if any, and document
recommendations to address them.

The U.S. Environmental Protection Agency (EPA) is preparing this FYR pursuant to the Comprehensive
Environmental Response, Compensation, and Liability Act (CERCLA) Section 121, consistent with the
National Contingency Plan (NCP) (40 Code of Federal Regulations (CFR) Section 300.430(f)(4)(ii)) and
considering EPA policy.

This is the fifth FYR for the ABC One-Hour Cleaners Superfund site (the Site). The triggering action for
this statutory review is the completion date of the previous FYR. The FYR has been prepared because
hazardous substances, pollutants or contaminants remain at the Site above levels that allow for unlimited
use and unrestricted exposure (UU/UE).

Prior to 2018, the Site consisted of two operable units (OUs). OU-1 addressed groundwater
contamination. OU-2 addressed soil contamination. In 2018, the EPA determined that the remedial
action efforts were not effective due to the contaminated media not being fully characterized.
Investigations determined that the contaminated soil was still contributing to the groundwater
contamination and could pose potential indoor air concerns in adjoining properties. As a result, the EPA
has adopted a phased-remedial action approach managed under one effort, OU-3. The soil media will be
addressed prior to the selection of a groundwater remedy. This FYR Report will present information for
OlJ-1, OlJ-2 and OU-3 yet will provide one protectiveness determination for OlJ-3.

The EPA remedial project manager (RPM), Anna Martin, led the FYR, with support from North
Carolina Department of Environmental Quality (NCDEQ) project manager Beth Hartzell and Ryan
Burdge and Alison Cattani from the EPA FYR support contractor Skeo. The review began on 9/6/2022.

Appendix A provides a list of documents reviewed for this FYR. Appendix B provides site status
information. Appendix C provides the Site's chronology of events.

Site Background

The one-acre Site is located at 2127 Lejeune Boulevard in the city of Jacksonville in Onslow County,

North Carolina, and is part of a larger commercial retail district (Figure 1). The Site is located
approximately two miles northeast of the Marine Corps Base Camp Lejeune (MCBCL). From 1964 to
2005, ABC One-Hour Cleaners operated as a small, family-owned dry-cleaning business. The business
operations were conducted within a complex which consisted of three buildings (the front, middle, and
north buildings). The middle building housed the dry-cleaning operations, which included the use of
the washer and a septic tank system. Tetrachloroethylene (PCE), a common dry-cleaning solvent, was
used as part of the operations and was released into the soil and groundwater by the septic tank system.
PCE was also buried outside the middle building. These disposal practices resulted in soil and
groundwater contamination.

In 2005, ABC One-Hour Cleaners was sold and renamed A-1 Cleaners, where it served as a drop-off-
only location. All operations ended in 201 1. The buildings remained vacant until December 2017, when

1


-------
they were demolished.1 The concrete foundation of the former buildings remained to prevent exposure
to the underlying contaminated soils. The footprint of the former buildings is fenced. The fence is locked
and has signage posted notifying the public that the property is a Superfund site.

The city of Jacksonville zoned the site property for commercial uses. Commercial areas are east and
west of the Site. A retail furniture store is east and downgradient of the Site. The area north of the Site
hosts residential and commercial land uses. The site property is anticipated to remain zoned for
commercial uses for the foreseeable future.

Groundwater beneath the Site is classified as a current and potential source of drinking water (EPA
Class II), but there are no known users of groundwater at or near the Site. A surficial aquifer and the
underlying Castle Hayne aquifer generally flow southeast beneath the Site (Figures D-1 and D-2). In
North Carolina, all groundwater classifications of aquifers are potential sources of drinking water and
are expected to be remediated for beneficial use.

Five-Year Review Summary Form

SITE IDENTIFICATION

Site Name: ABC One-Hour Cleaners

EPA ID: NCD024644494

Region: 4

State: North Carolina City/County: Jacksonville/Onslow

NPL Status: Final

Multiple OUs?
Yes

Has the Site achieved construction completion?

No

REVIEW SI A I I S

Lead agency: EPA

Author name: Anna Martin, EPA Region 4

Author affiliation: EPA with support provided by Skeo

Review period: 9/6/2022 - 6/5/2023

Date of site inspection: 1/17/2023

Type of rev iew: Statutory

Review number: 5

Triggering action date: 6/5/2018

Due date (fiveyears after triggering action date): 6/5/2023

1 By 2001, dry-cleaning operations ended, and the ABC One-Hour Cleaners' buildings were unoccupied. The city of
Jacksonville condemned the ABC One-Hour Cleaners' buildings in 2011 due to extensive damage caused by Hurricane Irene.
The buildings were demolished by December 2017. Due to the presence of the soils highly affected by PCE, building
foundation slabs were left intact.

2


-------
Figure 1: Site Vicinity Map

N ABC One-Hour Cleaners Superfund Site

A City of Jacksonville, Onslow County, North Carolina

i	1	1

ft	Cftft	1 ftftft t.. I

Disclaimer: This map and any boundary lines within the map are approximate and subject to
change. The map is not a survey. The map is for informational purposes only regarding the EPA's
response actions at the Site. Map image is the intellectual property of Esn and is used herein
under license. Copyright © 2020 Esri and its licensors. All rights reserved. Sources: Esri, NC
CGI A. Maxar and the 2013 FYR Report.

3


-------
II. RESPONSE ACTION SUMMARY

Basis for Taking Action and Response Actions

Initial Basis for Taking Action

PCE was used as a cleaning solvent as a part of the former dry-cleaning operations. No regulations to
dispose of the spent PCE were in place when the dry-cleaning operations began. As a result, the spent
PCE was disposed of as follows: (1) direct discharge of PCE solvent into the septic tank and the
adjoining floor drain; (2) burial of PCE residues in the surface soils outside the three buildings;
(3) leachate from the buried PCE residues moving into subsurface soils and underlying groundwater;
and (4) volatilization of PCE-contaminated soil and groundwater. The disposal practices resulted in PCE
contaminated soil at the Site and beneath the adjoining building; PCE contaminated groundwater
migrating from the Site onto several properties downgradient of the Site; as well as contaminated
volatilized soil-gas that potentially migrated into the adjoining building.

In 1984, the U.S. Department of the Navy collected groundwater samples from the Tarawa Terrace
community. Concentrations of PCE and PCE-daughter products, including trichloroethylene (TCE) and
dichloroethylene (DCE), were detected in the sampled water supply wells. To characterize groundwater
conditions further, the Agency for Toxic Substances and Disease Registry conducted an investigation
where exceedances of maximum contaminant levels (MCLs) for PCE, DCE and TCE were confirmed in
several wells in the Tarawa Terrace community. The North Carolina Department of Natural Resources
(NCDENR, now the NCDEQ), conducted an investigation that confirmed that ABC One-Hour Cleaners
was one of the most likely sources of groundwater contamination at Tarawa Terrace. In 1986, the
NCDEQ submitted a notice of violation to the Site's potentially responsible parties (PRPs), as the dry-
cleaning operations were not in compliance with state statutes.

Due to the high levels of PCE detected in the soil and groundwater and the extent of contamination
identified at the Site and nearby, the EPA listed the Site on the Superfund program's National Priorities
List (NPL) in March 1989. The EPA submitted a letter of notification to the PRPs regarding the
potential responsibility of the release of hazardous substances. As the PRPs were unable to fully fund
required remedial efforts, the Superfund program funded remedial activities at the Site.

The EPA initially managed the site as separate OUs: OU-1 groundwater and OU-2 soils. To characterize
the Site contamination, the EPA conducted its 1992 remedial investigations (RIs) at OlJ-1 and OlJ-2.
The RIs concluded the following:

•	Identified site contaminants of concern (COCs) as PCE, TCE, DCE and vinyl chloride;

•	Confirmed the presence of the COCs at levels that exceeded federal and state thresholds; and

•	Identified ingestion of groundwater and soil as the human exposure pathways.

4


-------
Figure 2: Site Detail Map

Approximate Location
of Former Abandoned

Approximate Location
IjfofMorrnerjlarikK

Formers
BoMerl

Former
Washers

Former Washer
With Containment

Shopping
Center

Former ABC
One-Hour
Cleaners Building

^3 Approximate Site Boundary
—~ Groundwater Flow Direction

Septic Drain Field

Former Clay

Former
Dryer

Furniture
Store

N ABC One-Hour Cleaners Superfund Site

A City of Jacksonville, Onslow County, North Carolina

i	1	1	1

a	en	inn	icn

Disclaimer This map and any boundary lines within the map are approximate and subject to
change. The map is not a survey. The map is for informational purposes only regarding the EPA's
response actions at the Site. Map Image Is the intellectual property of Esri and is used herein
under license. Copyright © 2020 Esri and its licensors All rights reserved. Sources: Esri. NC
CGIA, Maxar. Microsoft, the 2013 FYR Report and the 2020 Remedial Design Plan

^Skeo

Last Modified: 2/28/2023

5


-------
Initial Response Actions

The EPA issued Records of Decision (RODs) for OU-land OU-2 in 1993 and 1994, respectively, where
pump-and-treat coupled with monitored natural attenuation (MNA) and soil vapor extraction (SVE)
were selected as the respective remedies.

The remedial action objectives (RAOs) as identified in the RODs include:

•	To address the soil contamination by removing the principal threat remaining at the Site by
treating the contaminated soil and preventing the contaminants from adversely impacting
the groundwater.

•	To restore contaminated groundwater to levels protective of human health and the environment.

•	To control exposure and control migration of contaminated groundwater.

The EPA implemented the OU-1 and OlJ-2 remedies by 2001. In 201 1, the pump-and-treat system was
turned off as prescribed in the 1993 ROD to allow groundwater conditions to return to natural conditions
and the SVE system was dismantled due to impacts sustained from Hurricane Irene.

Focused RI

In 2012, as part of the third FYR, the EPA determined that the OU-1 and OlJ-2 remedies were not
protective of HH&E. The determination was based on the soil and groundwater contamination not being
adequately characterized, and therefore, the selected remedies were not effective. The EPA followed up
by conducting a three-year focused remedial investigation (Focused RI) to better characterize the
Site conditions; identify more effective methods to address the residual groundwater and soil
contamination; and confirm the potential for contaminated volatilized soil-gas to migrate into the
adjoining building.

The investigations involved the collection of a number of soil and groundwater samples using direct
push technology (DPT) and a membrane interface probe. The Focused RI resulted in the
following findings:

Finding 1: Identification of Source Material

•	Source material was defined as soils with high PCE concentrations that are directly affected by
PCE residues or solvents.

•	All soils found within the footprint of the former buildings and beneath the adjoining property
east of the Site are considered source material.

•	The highest PCE concentrations detected in the soils were found within the footprint of the
middle building, specifically near the former septic tank, floor drain and washer.

Finding 2: Impact of the Groundwater on the Source Material

•	Source material continues to expand beyond the characterized area with the fluctuation and
movement of the groundwater.

6


-------
•	The area where the groundwater mingles with the source material was identified as the
'transition zone".

•	The transition zone potentially transports contaminated groundwater that is impacted by the PCE
contaminants having leached from the source material resulting in expanding both the source
material and groundwater plume.

Finding 3: Vapor Intrusion

•	Indoor air quality of the adjoining building located east of the Site was suspected to have been
impacted by the presence of contaminated soil vapors that migrated from the underlying
source material.

•	As a part of the Focused RI, a vapor intrusion (VI) study was conducted at the adjoining building
located east of the Site.

•	The VI study determined that the soil vapors that migrated from the underlying source material
do not pose an imminent threat to the occupants of the adjoining building east of the Site.

These findings resulted in the EPA, with concurrence from NCDEQ, adopting a phased-impiementation
approach where the soil and groundwater media are addressed separately. EPA established OU-3 and will
manage the site cleanup through this new OU. Table 1 provides an overview of OU-1 and OU-2 efforts.

Table 1: Overview of the OU-1 and OU-2 Efforts

OU

Description

Year

Description of Activities

OU-1

Groundwater
Contamination

1992

Detection of high PCE concentrations

1993

EPA issued the OU-1 ROD which presents the selected remedy:
pump-and-treat coupled with MNA

2002

Remedy was constructed

201 1

Remedy was turned off

2012

EPA determined the remedy was not protective of HH&E

2018

EPA established OU-3

OU-2

Soil

Contamination

1994

Detection of high PCE concentrations

1994

EPA issued the OU-1 ROD which presents the selected remedy:

SVE

2002

Remedy was constructed

201 1

Remedy was dismantled

2012

EPA determined the remedy was not protective of HH&E

7


-------
Status of OU-3 Implementation

Interim Remedial Action for the Source Material

The determinations gathered from the Focused RI resulted in the EPA issuing the 2018 Interim Record
of Decision for OU-3 Soils (IROD). The I ROD presented the remedy that will address the source
material, the principal threat waste (PTW) and eliminate further leaching into the groundwater. This
effort, in turn, will result in a smaller volume of contaminated groundwater requiring subsequent
remedial action and shorter remedial timeframes. Furthermore, by addressing the PTW, contaminated
soil vapors that have the potential to migrate into adjoining buildings will be reduced or eliminated. The
remedy that was selected by the EPA, with concurrence from NCDEQ and the public, is in-situ thermal
remediation coupled with SVE (ISTR).

Tables 2 and 3 presented the Remedial Action Objectives and cleanup levels that are used to measure
the effectiveness of the ISTR.

Table 2: Remedial Action Objectives

Remedial Action Objectives as Presented in the 2018 IROD

RAO 1

Prevent ingestion, dermal contact and/or inhalation of soils or soil vapors in the source
area, as well as within the unsaturated soil zone and the saturated soil zone, containing
COCs at concentrations that could result in adverse health effects to humans under
commercial land use.

RAO 2

Reduce or eliminate long-term leachability of soil COCs into groundwater by meeting
soil leachability criteria.

Table 3: Cleanup Levels

Cleanup Levels for Soil Contaminants of Concern as Presented in the 2018 IROD

COC

Cleanup Level * milligrams per
kilogram

Criteria

PCE

0.0063

Protection of groundwater

TCE

0.021

Protection of groundwater

DCE

0.41

Protection of groundwater

Vinyl chloride

0.00021

Protection of groundwater

*Cleanup levels are based on the Preliminary Soil Remediation Goals which are derived by NCDEQ to
prevent leaching into the groundwater media

8


-------
Time-Critical Removal Action

The EPA Removal Program conducted a Time-Critical Removal Action (TCRA). The TCRA was
approved in July 2018 and included three components: the installation of a Site fence; removal of the
septic tank system and surrounding source material; and re-paving the aged concrete pad. In
September 2019, EPA Removal surveyed the Site to determine the property boundary, utility lines and
the location of the septic tank system and associated drainage field.

1.	An eight-foot-high chain-link property fence was installed to prevent access to the Site and
exposure to the contamination. The fence surrounds the footprint of the former buildings. The
fence was installed with a padlock keypad and EPA signage in October 2019.

2.	The septic tank system, associated drainage field, and approximately 60 cubic feet of
surrounding contaminated soil were removed and disposed of at an EPA-approved landfill. The
area where the septic tank was removed was backfilled with clean soil and completed in
January 2020.

3.	The concrete foundation originating from the former buildings was re-paved as indications that
the concrete was aged and may not be effective in preventing exposure to the underlying
contaminated soils. This component was completed in February 2020.

Confirmation VI Study

Soil-gas samples were collected in 2019 and demonstrated that although elevated PCE levels were
detected beneath the adjoining building located east of the Site, there is no complete exposure pathway.
Therefore, no unacceptable risks to the occupants of the adjoining building located east of the Site were
identified. It was determined that the height from where the indoor air samples were collected was not
significant in magnitude as to alter the conclusion that no unacceptable risks are posed to the occupants
of the adjoining building under existing conditions. However, as a precaution, the 2020 FYR Report
Addendum recommended that VI monitoring be conducted at the adjoining building.

Remedial Design for OU-3 Soils

In 2020, the EPA completed the Remedial Design for OU-3 Soils (RD). The RD details the
specifications required to construct and operate the ISTR treatment system in efforts of achieving the
NCDEQ derived cleanup levels.

Remedial Action for OU-3 Soils

The remedial action prescribed to address the source material at the Site was initiated in September 2022
with the selection of the contractor responsible for constructing and operating the ISTR treatment
system. In February 2023, samples were collected to establish a more current understanding of the Site
conditions prior to the construction of the ISTR treatment system. To ensure public awareness of the
construction activities as required by the EPA National Contingency Plan, the EPA issued a public
notice in March 2023. The notice mentioned the potential impacts that the community may experience
as the construction activities are conducted and the anticipated timeframe of the remedial action.

9


-------
To monitor the performance of the ISTR treatment system, achievement of the lines of evidence and Site
conditions; soil, groundwater, and soil vapor samples will be collected and analyzed throughout the
construction and operation of the ISTR treatment system. Samples will also be collected after the ISTR
treatment system has operated and the Site is undergoing restoration.

Addressing the Contaminated Groundwater

The Site's contaminated groundwater extends in two directions as presented in Figure 3. One plume
extends south/southeast onto the MCBCL Tarawa Terrace property and the second flows in the direction
of groundwater, towards the east, along Lejeune Boulevard. Based on current data, the EP A has
delineated the east component groundwater plume to have extended about 3,000 feet east of the Site,
affecting nearly 30 parcels.

As discussed in the 2018 IROD, the PCE-contaminated soil serves as the source of the groundwater
contamination. The groundwater contamination continues to migrate off-site by following the natural
direction of groundwater. The soil contamination will be addressed prior to the selection of a
groundwater remedy.

Upon the successful completion of the ISTR treatment, the EPA will collect data to support the selection
of the groundwater remedy. A separate IROD will document the selected groundwater remedy. Based on
current data, the EPA has delineated the groundwater plume to have extended about 3,000 feet east of
the Site, affecting nearly 30 parcels. These affected parcels are not suspected to be impacted by VI
issues as the buildings, as opposed to the adjoining property, do not sit directly above or within the
contaminated groundwater plumes.

Table 4: Overview of the OU-3 Efforts

OH

Description

Year

Description of Activities

OU-3

Phased
Implementation -
Soil

2018

EPA issued the IROD which presents the selected remedy, ISTR

2019

Completed the VI Study

2020

EPA Removal Program completed the TCRA.

2020

EPA completed the RD

2022

Initiated the remedial action

2023

Issued public notice about remedial action efforts.
Initiated construction of the ISTR treatment system.

Institutional Control (IC) Review

The 2018 IROD requires the implementation of institutional controls (ICs) to be included with the
construction and operation of the ISTR. The ICs, once implemented, will (1) restrict the Site's land uses
to commercial and industrial and (2) prevent the installation of any wells at the affected parcels that are
located within the east component of the groundwater plume. ICs will be required until contaminant
levels that allow for UU/UE are achieved. The NCDEQ will take primary responsibility for monitoring
and enforcing the ICs for the offsite properties. ICs will be implemented according to the Explanation of

10


-------
Significant Differences (ESD) which is anticipated to be issued by July 2023. To supplement the
requirements presented in the ESD, a Notice of Contaminated Site will be filed.

ICs have been implemented and are enforced by the MCBCL to prevent exposure to the south/southeast
groundwater component which impacts the Tarawa Terrace which is presented in Figure 4. Table 5
summarizes the ICs that will be implemented under this effort as well as the ICs that have been
implemented by MCBCL.

Operations and Maintenance

Should cleanup levels not achieve UU/UE, the ICs implemented to restrict both the use of the Site and
installation of wells at those properties affected by the groundwater contamination will remain in place.
These ICs will require monitoring and enforcement by the State.

1 1


-------
Figure 3: Groundwater Plume Originating from the Site

L*9»nd

mm
***&//////;.

CK1 * wtf Jit asu rt»f

•////////

3«n«faiisec Plume
ABC Qnt-Hoyr CtNners
Jstksofiv <=. Qratow Cowtfy, Ntirtfi Carolina

12


-------
Figure 4: Institutional Controls Map for the South/Southeast Component of the Groundwater Plume

N ABC One-Hour Cleaners Superfund Site

A City of Jacksonville, Onslow County, North Carolina

Disclaimer This map and any boundary lines within the map are approximate and subject to
change. The map Is not a survey. The map is for informational purposes only regarding the EPA's
response actions at the Site. Map Image is the Intellectual property of Esri and Is used herein
under license. Copynght © 2020 Esn and its licensors. All nghts reserved. Sources: Esri. NC
CGI A. Maxar. Maxar and the 2018 FYR Report.

Last Modified: 2/28/2023

Approximate Site Boundary
Groundwater Use Restriction Area
Camp Lejeune Extent
Approximate Groundwater Flow Direction

13


-------
Table 5: Summary of Planned and/or Implemented ICs

Media,
Engineered
Controls,
and Areas*

ICs
Required?

ICs Required
by Decision
Document(s)

Currently
Understood
Affected Parcel(s)

IC

Objective

Title of IC Instrument
Implemented and
Date (or planned)

Land use

Yes

Yes

352-H17
(see Figure 3)

Restrict land
uses to industrial

or commercial
uses

Planned Notice of
Contaminated Site

Groundwater

Yes

Yes

East Component:

All parcels located
downgradient of
the Site

South/Southeast
Component:

Tarawa Terrace

Prohibit
groundwater use

East Component:

Planned to be presented
in the ESD and Notice
of Contaminated Site

South/Southeast
Component:

Implemented and
monitored by MCBCL

* That Do Not Support UU/UE Based on Current Conditions

14


-------
III. PROGRESS SINCE THE PREVIOUS REVIEW

This section summarizes the issues, recommendations, and protectiveness determinations and statements
from the FYR efforts conducted since the 2018 IROD. The summaries are presented in Tables 6, 7, and 8.

Table 6: Protectiveness Determinations and Statements from the 2018 FYR Report

ou

Protectiveness
Determination

Protectiveness Statement

OU-1

Short-term Protective

The remedy at OU-1 (to be combined into OU-3) currently
protects human health and the environment because there are no
current human exposure pathways to contaminated groundwater
since no one is drinking the contaminated groundwater. For the
remedy to be protective in the long term, the following needs to
occur: finalize and implement the combined OU-3 soil and
groundwater remedy and implement land use and groundwater use
restrictions at appropriate properties and consider current
standards in the assessment of remedial options and modify
groundwater cleanup goals as needed in a decision document.

OU-2

Protectiveness
Deferred

A protectiveness determination of the remedy at OU-2 cannot be
made at this time until further information is obtained. Further
information will be obtained by taking the following actions:
conducting additional VI monitoring at the off-site property and
conducting a VI study at other adjoining properties if deemed
appropriate. It is expected that these actions will take
approximately one and a half years to complete, at which time a
protectiveness determination will be made.

Sitewide

Protectiveness
Deferred

A site-wide protectiveness determination cannot be made at this
time until further information is obtained. Further information will
be obtained by taking the following actions: conducting additional
VI monitoring at the off-site property and conducting a VI study at
other adjoining properties if deemed appropriate. It is expected
that these actions will take approximately one and a half years to
complete, at which time a protectiveness determination will
be made.

15


-------
Table 7: Status of Recommendations from the 2018 FYR Report

OIJ #

Issue

Recommendations

Current
Status

Current Implementation Status Description

Completion
Date

(if

applicable)

OU-1
and

OU-2

The OU-1 and OU-2
remedies are not functioning
as intended as the remedial
systems are offline and
additional source material
was discovered in 2013 and
2017. Soil and groundwater
investigations were
conducted from 2012 to 2017
to support the selection of
new, combined effective soil
and groundwater remedies.

Select and implement the
OlJ-3 remedies. The
selection of the OlJ-3
remedies will be discussed
in the decision document,
which is anticipated to be
issued in 2018. The
implementation of the
OlJ-3 remedies is
anticipated to begin in
2019.

Completed

The EPA signed the 2018 I ROD that defines
OlJ-3 as encompassing all site contamination.
Remedial action began in 2022. The construction
efforts are anticipated to begin in May 2023

The 2018 I ROD presented the phased approach
where soil media will be addressed prior to the
selection of a groundwater remedy as well as the
selected soil remedy, the former OlJ-2
component.

9/26/2018

OU-1
and
OU-2

Institutional controls are not
in place at all affected
properties. Affected
properties include:

(1)	properties that are
affected by the groundwater
plume;

(2)	properties where
contamination has spread or
is anticipated to spread above
remedial goals; and (3) areas
of the Site where restrictions
are not in place to prevent
unacceptable exposures to
remaining sub-slab soil
waste.

Implement land use and
groundwater use
restrictions at appropriate
properties. The revised
institutional controls will
be discussed in the
decision document that is
anticipated to be issued in
2018. The revised
institutional controls will
be implemented once the
remedies have been
implemented, upon the
completion of the soil and
groundwater remedies
being constructed.

Addressed

in Next
FYR

The selected 2018 OlJ-3 interim soil remedy
includes the implementation of both land use and
groundwater use restrictions. The groundwater
use restrictions will be implemented at the Site as
well as the affected properties.

Not
applicable

16


-------
on #

Issue

Recommendations

Current
Status

Current Implementation Status Description

Completion
Date

(if

applicable)

OU-1

Groundwater standards for
PCE and vinyl chloride are
now more stringent.

Consider current standards
in the assessment of
remedial options and
modify groundwater
remedial goals as needed
in the decision document,
which is anticipated to be
issued in 2018.

Addressed

in Next
FYR

The groundwater remedy will be selected after
the soil remedy has operated. The selected
groundwater remedy will be reflected in the 2018
I ROD for groundwater where the appropriate
standards will be identified.

Not
applicable

OU-2

Elevated contaminant
concentrations in sub-slab gas
of the off-site property
indicate the potential for
vapor intrusion from the
subsurface into the building if
conditions change.

Additional source material
may be present at other
adjoining properties that
could result in the potential
for vapor intrusion from the
subsurface.

Conduct more vapor
intrusion monitoring at the
off-site property and other
adjoining properties if
deemed appropriate.

Completed

Soil-gas samples collected in 2019 detected
source material beneath the adjoining building
that validated the results of the sub-slab samples
collected during the 2017 VI study. The indoor
air sample results collected from the study
demonstrated that although elevated PCE levels
were detected beneath the building, there is no
complete exposure pathway and, therefore, no
risks are posed to the occupants of the adjoining
building. However, indoor air samples are
recommended to be collected regularly A
supplemental study was conducted in 2019 and a
human health risk assessment (HHRA) was
completed in 2020 (see Data Review section of
this FYR Report).

1/13/2020

17


-------
Table 8: Protectiveness Determinations/Statements from the 2020 FYR Report Addendum

OIJ #

Protectiveness
Determination

Protectiveness Statement

OU-3
Former OU-2

Phase 1: Source
Material (Soil)

Short-term
Protective

The remedy at OU-3, the former OlJ-2 component, is determined
to be protective in the short term of human health and the
environment. Soil-gas samples collected in October 2019 indicate
the presence of source material beneath the adjoining building,
but data collected as part of the 2017 vapor intrusion study and
assessed by the EPA Region 4's Scientific Support Section show
that no vapor intrusion exposure pathway currently exists.
However, due to the potential for changes in site conditions, such
as the development of cracks in the foundation of the adjoining
building, additional vapor intrusion sampling is recommended to
ensure that no unacceptable risks are posed to the occupants in
the future, until the source material can be addressed by the
interim remedial action. Implementation of the interim remedy
components, including ISTR coupled with SVE, will treat the
source material and eliminate any future potential or actual
exposure pathway. For the remedy at OU-3, the former OlJ-2
component, to be long-term protective, the following actions are
recommended: address potential vapor intrusion impacts at the
adjoining building; implement the ICs; and construct and operate
the soil remedy.

Sitewide

Short-term
Protective

Site-wide conditions are determined to be protective in the short
term of human health and the environment. As described in the
2018 FYR Report, OU-3, the former OU-1 component
(groundwater), currently protects human health and the
environment because no one is drinking the contaminated
groundwater, meaning that no exposure pathway currently exists.
As described in this Addendum, OU-3, the former OlJ-2
component (soil), currently protects human health and the
environment because no vapor intrusion exposure pathway
currently exists. Nonetheless, because contaminants remain in the
groundwater above MCLs for drinking water and because soil-
gas samples from October 2019 indicate the presence of source
material beneath the building adjoining the Site, in order for the
remedy to be protective in the long term, the following actions
are recommended: address the potential vapor intrusion impacts
at the adjoining building; implement the ICs; construct and
operate the soil remedy; and select, construct, and operate a
groundwater remedy.

18


-------
IV. FIVE-YEAR REVIEW PROCESS

Community Notification, Community Involvement and Site Interviews

The EPA issued an online news release on October 19, 2022, to announce that the FYR was underway.
A copy of the news release is available online at https://www.epa.gov/newsreleases/epa-review-
cleanups-45-southeast-superfund-sites and is included in Appendix E. The results of the review and the
completed FYR Report will be made available on the EPA's site profile page:
www.epa.gov/superfund/abc-one-hour-cleaners.

During the FYR process, interviews were conducted to document any perceived problems or successes
with the remedy that has been implemented to date. The interviews are summarized below.

The NCDEQ project manager Beth Hartzell noted that the OU-3 remedy is just beginning but is
expected to address remaining site contamination. The NCDEQ noted no issues with the Site.

Marine Corps Base Camp Lejeune representative Thomas Richard is aware of the site history and
current plans for interim remedial actions. He reported no concerns or issues.

Data Review

The construction of the OU-3 remedy is anticipated to begin in May 2023. As efforts to construct the
OU-3 remedy are being conducted monitoring data are not available for this FYR. This FYR Report
includes a summary of data collected from the investigations conducted during the 2020 RD. To address
the data gaps identified in the 2018 IROD and ensure the remedy is effectively and efficiently
constructed, additional surface and subsurface soil samples were collected during the RD. The RD
verified the presence of a localized "hot spot" that was later identified as the source area. This area is
largely found within the footprint of the former buildings. The data used to verify this determination is
based on the results collected from the surface and subsurface soils.

Surface Soil RD Investigation: This investigation was conducted to determine whether the extent of
contamination extended beyond the footprint of the former buildings to the northern grassy part of the
Site in the surface soils. Sixty-two surface soil samples were collected north of the concrete pad and one
surface soil sample was collected east of the concrete pad using a grid system. Figure D-5 presents the
results collected from the 63 surface soil samples. PCE was detected above the ROD cleanup level
(0.0063 milligrams per kilogram [mg/kg]) in 12 of the soil samples, primarily within the footprint of the
former buildings.

Subsurface Soil RD Investigation: This investigation was conducted to determine whether the extent of
contamination extended beyond the footprint of the former buildings to the northern grassy part of the
Site in the subsurface soils. Thirteen subsurface soil sample locations were identified within the concrete
pad and along the perimeter of the concrete pad (Figure D-6). The subsurface soil depths of the
identified sample locations were pre-determined considering the results from previous and historical
investigations, which totaled 55 subsurface soil samples. PCE exceedances were detected in six
subsurface soil samples. The highest PCE concentration was detected in DPT221, at a concentration of
0.740 mg/kg at 39 feet to 40 feet below ground surface. TCE exceedances were also detected in samples
DPT220 at 19 feet to 20 feet below ground surface and DPT224 at 29 feet to 30 feet below ground
surface at concentrations of 0.064 mg/kg and 0.025 mg/kg, respectively. One exceedance of the vinyl
chloride cleanup level was detected. However, more exceedances may be present, as the vinyl chloride
cleanup level is below the laboratory reporting limit.

19


-------
Dense Non-Aqueous Phase LiquidRD Investigation: To evaluate the presence and location of any dense
non-aqueous phase liquid (DNAPL), PCE non-aqueous phase liquid (NAPL) saturation concentrations
were calculated. Figure D-7 shows potential NAPL locations. Based on the investigations at the Site,
DNAPL detected in the soil was determined to be mobile as it moves through preferential pathways
within a low-permeability barrier layer. This observation supports the detection of high PCE
concentrations in soil and groundwater as well as the potential infiltration of contaminated vapors into
adjacent buildings.

Vapor Intrusion Study: The EPA determined that there is no complete exposure pathway and,
subsequently, no risks posed to the occupants of the adjoining building. In response to the 2020 FYR
Report Addendum's recommendation, the EPA conducted a supplemental VI study in 2019 to confirm
the presence of source material beneath the adjoining buildings and re-evaluate the potential impact of
the source material on the indoor air quality of the buildings. A VI human health risk assessment
(HHRA) was conducted in 2020. Due to access issues, indoor air samples could not be obtained
and were, therefore, estimated based on soil-gas sample results collected from the exterior of the
buildings (Figure D-8).

The 2020 HHRA determined there are no potential carcinogenic or noncancer risks identified for one of
the adjacent buildings; however, potential carcinogenic and noncancer risks were identified for the
building east of the Site. The total estimated cancer risk based on measured soil-gas concentrations near
the building east of the Site exceeds the acceptable risk range (1 x 10"4 to 1 x 10"6) for the current/future
worker. The COCs contributing to the potential total cancer risk estimate include PCE (cancer risk of 4 x
10"5), TCE (cancer risk of 2.5 x 10"4) and vinyl chloride (cancer risk of 2.7 x 10"6). These results,
however, were not solely used to determine the VI condition of the buildings as the indoor air
concentrations were estimated due to challenges in receiving access agreements and the identical gases
are emitted from the furniture housed in the adjoining building east of the Site. In this, the EPA
determined that there are no imminent threats of indoor air quality posed to the occupants of the
adjoining building east of the Site providing that the current Site conditions do not change. As a
precaution, however, the EPA further recommended, in addition to conducting indoor air monitoring,
that a VI mitigation system be installed in the adjoining building east of the Site.

Groundwater

The most recent groundwater data are from 2017 and 2018 (Figures D-3 and D-4). The EPA is confident
the downgradient plume is stable and that conditions are unlikely to have changed. Following the
operation of the ISTR, the EPA will address the downgradient groundwater contamination. ICs that will
restrict the use of the Site and prevent exposure to the groundwater media, however, will be
implemented until COC concentrations achieve UU/UE.

20


-------
Site Inspection

The site inspection was conducted on 1 /17/2023. Participants included Beth Hartzell from the NCDEQ
and Ryan Burdge from Skeo. The purpose of the inspection was to assess the protectiveness of the remedy.

Site inspection participants met at the Site property to conduct the inspection. Remedial contractors were
on-site conducting field work related to the pending OU-3 soil remedy. The Site property is secured by
an eight-foot-high fence. There were no signs of fence damage or trespassing. The Site no longer has
buildings or features other than remaining concrete pad and flush-mounted sampling well locations. No
issues were noted. The site inspection checklist and photographs are included in Appendix G and
Appendix H, respectively.

21


-------
V. TECHNICAL ASSESSMENT

QUESTION A: Is the remedy functioning as intended by the decision documents?

Yes, the OU-3 interim remedy is expected to function as intended. Currently, the efforts conducted
through the TCRA which was completed in 2018 resulted in measures that protect human health and the
environment which include the removal of highly contaminated soil, backfilling the excavated area with
clean soil, and installation of a concrete pad and fence which prevent access to the contaminated soil
and groundwater.

The EPA selected the OU-3 interim remedial action to address the source material in 2018. The
selection of the OU-3 interim remedy is based on the importance of aggressively removing source
material to address the PTW and reduce or eliminate long-term leachability of soil COCs into the
groundwater. This effort, in turn, will result in a smaller volume of contaminated groundwater requiring
subsequent remedial action and shorter remedial timeframes. Furthermore, by addressing the PTW,
contaminated soil vapors that have the potential to migrate into adjoining buildings will be reduced or
eliminated. By achieving the RAOs and cleanup levels, exposure to source material will be eliminated,
and the potential for adverse human health effects under commercial land use will be mitigated.

Construction of the remedy is anticipated to begin in the Spring 2023 and operate by the Fall 2023. The
effectiveness of the OlJ-3 interim remedy will be evaluated using data that will be collected before the
construction of the OlJ-3 interim remedy; during the operation of the OlJ-3 interim remedy; and after
the operation of the OlJ-3 interim remedy is completed. The data collected after the OlJ-3 interim
remedy has completed its operations will also be used to evaluate the appropriateness of the
groundwater remedial alternatives and select an appropriate groundwater remedy considering the
resulting outcomes of the selected soil remedy.

The EPA has delineated the groundwater contamination as extending about 3,000 feet east of the Site.
ICs will be implemented to restrict Site uses to commercial use and restrict the use of groundwater at the
Site and properties impacted by the contaminated media downgradient of the Site. These restrictions will
be required to remain in place until COC concentrations that allow for UU/UE are achieved.

The Site's 2020 HHRA indicates there are potential VI risks in the building immediately east of the Site.
However, these risks will only pose an unacceptable risk to occupants of the adjacent building if current
conditions change. No other buildings have been identified for potential VI.

QUESTION B: Are the exposure assumptions, toxicity data, cleanup levels and RAOs used at the
time of the remedy selection still valid?

Yes, the exposure assumptions, toxicity data, cleanup levels and RAOs in the 2018 I ROD remain valid.
The EPA will assess and update its risk characterization and cleanup levels in subsequent decision
documents and determine if additional response actions or ICs are warranted.

VI remains a potential concern that the EPA continues to consider. Currently, based on the 2020 HHRA,
there are no potential carcinogenic or noncancer risks identified for the adjacent building west of the
Site. The HHRA, however, identified potential risk at the adjacent building east of the Site. The OlJ-3
interim remedy will ensure that conditions improve and do not change in a manner that would pose
unacceptable risks to the occupants of this adjacent building.

22


-------
QUESTION C: Has any other information conic to light that could call into question the
protectiveness of the remedy?

No other information has come to light that could call into question the protectiveness of the remedy.

23


-------
VI. ISSUES/RECOMMENDATIONS

Issues/RtToniiiKMuliil ions

OU(s) without Issues/Recommendations Identified in the FYR:

OU-3

VII. PROTECTIVENESS STATEMENT

Operable Unit:

OU-3

I'rolccliMMicss Sl;ilcmcnl(s)

Protectiveness Determination:

Will be Protective

Protectiveness Statement:

The remedy at OU-3 will be protective on completion. In the interim, the Site property is secured and
there are no known completed exposure pathways.

VIII. NEXT REVIEW

The next FYR Report for the ABC One-Hour Cleaner Superfund site is required five years from the
completion date of this review.

24


-------
APPENDIX A - REFERENCE LIST

Addendum to Third Superfund Five-Year Review Report for Operable Unit One of the ABC One-Hour
Cleaners Site, Jacksonville, Onslow County, North Carolina. EPA Region 4. July 2014.

Addendum to Third Superfund Five-Year Review Report for Operable Unit One of the ABC One-Hour
Cleaners Site, Jacksonville, Onslow County, North Carolina. EPA Region 4. July 2020.

Interim Record of Decision: ABC One-Hour Cleaners, EPA ID: NC024644494, OU 03,

Jacksonville, NC. EPA Region 4. September 2018.

Record of Decision: ABC One-Hour Cleaners, EPA ID: NC024644494, OU 01, Jacksonville, NC.
EPA Region 4. January 1993.

Record of Decision: ABC One-Hour Cleaners, EPA ID: NC024644494, OU 02, Jacksonville, NC.
EPA Region 4. September 1994.

Second Superfund Five-Year Review Report, ABC One-Hour Cleaners Site, Jacksonville, Onslow
County, North Carolina. Prepared by North Carolina Department of Environment and Natural
Resources, Division of Waste Management. August 2008.

Superfund Five-Year Review Report, ABC One-Hour Cleaners, Jacksonville, Onslow County,

North Carolina. Prepared by North Carolina Department of Environment and Natural Resources,
Division of Waste Management. August 2003.

Third Five-Year Review Report for ABC One-Hour Cleaners, Jacksonville, Onslow County,

North Carolina. EPA Region 4. August 2013.

Fourth Five-Year Review Report for ABC One-Hour Cleaners, Jacksonville, Onslow County,

North Carolina. EPA Region 4. June 2018.

A-l


-------
APPENDIX B - CURRENT SITE STATUS

K11 vi roil in en 1 ;i I I ml iesi 1 ors

-	Current human exposures at the Site are under control.

-	Current groundwater migration is under control.



Arc Necessary Inslilnlion;il Controls in I'hiee

I I All O Some ^ None

Ihis (lie KPA Designated (lie Site sis Silewide Ueady lor Anticipated I so?

|D Yes El

No



I his (lie Silo Keen Put into Uense.

I I Yes No

B-l


-------
APPENDIX C - SITE CHRONOLOGY

Table C-l: Site Chronology

Event

Date

ABC One-Hour Cleaners disposed of spent solvents and still bottoms (powder residue) on

the property; the property's septic tank also may have leaked

1964-1985

The U.S. Department of the Navy discovered PCE, TCE and DCE in community wells at
the Tarawa Terrace housing development during routine water quality evaluations

July 1984

The EPA was notified of site contamination

January 1985

The NCDENR (now the NCDEQ) identified ABC One-Hour Cleaners as the source of site
contamination

September 1985

The North Carolina Department of Health Services completed a preliminary site
assessment

September 1986

The North Carolina Department of Health Services completed a site inspection

May 1987

The EPA proposed the Site for listing on the NPL

June 1988

The EPA started Rl/feasibility study (FS) negotiations for the Site

September 1988

The EPA finalized the Site's listing on the NPL

March 1989

The EPA completed a risk/health assessment for site groundwater (OU-1)

November 1992

The EPA completed the RI/FS and signed the ROD for OU-1

January 1993

The EPA began the remedial design for OU-1

August 1993

The EPA completed the soil (OlJ-2) RI/FS, issued the ROD for OU-2 and began the
remedial design

September 1994

The EPA completed the remedial design for OU-1

September 1995

The EPA completed the remedial design for OU-2

September 1995

The EPA began the remedial action for OU-1

September 1996

A right-of-way agreement was signed for access for pipe installation beneath the railroad

August 1998

The EPA began the remedial action for OLJ-2

August 1998

Maclaren Hart, a subcontractor for the Site, initiated installation of the SVE system

April 2000

The EPA issued an Administrative Order on Consent for the Site

August 2000

The EPA extended the discharge pipe to discharge into Northeast Creek

October 2001

The EPA completed the Site's Interim Remedial Action Report

May 2002

The EP A completed construction of the components of the remedial action for OU-2

August 2002

C-l


-------
Event

Date

The EPA completed the Preliminary Close-Out Report for OU-1

August 2002

The EP A completed construction of components of the remedial action for OU-1

August 2002

The EPA issued the Site's first FYR Report

August 2003

Weston Solutions (EPA contractor) submitted OlJ-1 and OU-2 project summaries

March 2007

Black & Veatch (EPA contractor) submitted the 2007 Annual Groundwater Sampling
Report

September 2007

The EPA issued the Site's second FYR Report

September 2008

The EPA discontinued the OU-1 remedy to allow groundwater to return to natural
conditions

January 201 1

The Surface Characterization Using Membrane Interface Probe and Soil Conductivity
Technologies Report was completed

June 201 1

Hurricane Irene made landfall in the Jacksonville area

August 201 1

The city of Jacksonville condemned the former ABC Cleaners building

September 2011

Black & Veatch submitted an SVE Evaluation Report

October 2011

The EPA dismantled the SVE system

December 2011

The EPA issued the Site's third FYR Report

August 2013

The EPA completed the Addendum to the Site's third FYR Report

July 2014

A 2015 System Performance Assessment Update and Data Gap Evaluation was completed

January 2016

An EPA contractor completed the OU-3 RI/FS

June 2018

The EPA issued the Site's fourth FYR Report

June 5, 2018

The EPA signed the interim ROD for OU-3

September 26, 2018

The EPA completed the supplemental vapor intrusion assessment and removal of the septic
tank and surrounding soil

January 31, 2020

The EPA completed the Addendum to the Site's fourth FYR Report

April 2, 2020

Black & Veatch submitted the final remedial design for OU-3 for ISTR and SVE

April 20, 2020

C-2


-------
APPENDIX D - SITE MAPS

D-l


-------
Figure D-l: Groundwater Elevations - Surficial Aquifer

[RWSOtA

[§WS*0"2A- *

B'7^33'JL



'RWS'QffAl

tmm

RWS03A

¦F.WS13

m&2\

Legend

& Monitoring Well
Recovery Well
- - - GW_Contours

Groundwater Elevations Contour Map - Surficial Aquifer
ABC One-Hour Cleaners OU3
Jacksonville, Onslow County, North Carolina

Feet

NAD83 State Plane NC. Feet

D-l


-------
Figure D-2: Groundwater Elevations - Castle Hayne Aquifer

RWC01
15.08'

leweoa

6l3i93jB

l1I4%9ll

mm
mm



Legend

^ Monitoring Well
It Recovery Well
- - - Groundwater Contour (Feet)

Groundwater Elevations Contour Map - Castle-Hayne Aquifer
ABC One-Hour Cleaners OU3
Jacksonville, Onslow County, North Carolina

Feet

NAD83 State Plane NC, Feet

D-2


-------
Figure D-3: PCE Concentrations - Surficial Aquifer, 2017

Legend

Groundwater DPT with PCE Concentrations
Below the 0.7 ^g/L Recommended Goal
Groundwater DPT with PCE Concentrations
* Above the 0.7 |jg/L Recommended Goal
Surficial Aquifer Well

Monitoring Well with PCE Concentrations
Below the 0.7 ng/L Recommended Goal
_ Monitoring Well with PCE Concentrations
^ Above the 0.7 pg/L Recommended Goal
Recovery Well with PCE Concentrations
™ Above the 0,7 pg/L Recommended Goal
PCE Isoconcentrations in Groundwater

—	10.000 ng/L

—	500 (Jfl'L
	10yg/L

0.7 |jg/L

—	— Dashed where inferred
I I Site Property Boundary
CO5 Well ID

T - NS T - PDB sample at top of screen interval
M - NS M - PDB sample at middle of screen interval
B - 0.5 U B - PDB sample at bottom of screen interval
PDB Passive Diffusive Bag
-Results displayed in micrograms per liter (|jg/L)

-Vertical profile groundwater sample collection dates:
SB104-SB119 results are from Sept 2015: DPT202-DPT211
results are from April 2015; DPT212-DPT224 results are
from April 2019; VP100, VP101, and VP102 results are from
Sept 2016; VP103 and VP105 results are from Jan 2017
-Permanent well groundwater results are from May 2017,
except S20 collected in March 2019 and C22 collected
in Feb/March 2019



SBTOfiJ^,
220'(46^0 ft)*

VP103
5.2 (30-35 ft)
7-^(45x5,0 ft)
I 2.7 (55-60 ft)

, VP105
2.6 (35-40 ft)
&5f55-60 ft)

[RWSp"1T^

HwMi]

F - b|i.7

j@T(-3^40iTO

I :DPT217
7.1 (15 ft)
[DBT-215\i^5U:'(35 ft)

1—\ r-
WW^Tl I '
mb

~^'j,Q?(cf5:ft) —M

DPT214
f- 5U <15-ft>
5U£{35 ft)

DPT213

5U (15 ft) DPT212
5U (35 ft)5U(15ft)

fc,5U <35 ft)

^— 36 (15 ft) ,
5U (35 ft)

		SB119-

160.000'(36:<38ft) SO

IRWS02A

figfe .
Ip4 _

[§£.14 4

R/VS12-
T-NISaJ

m'JRsI

B-12%

RWS03A

;;DPT219

"2'2*jfO(15 ft) ¦
5U (35 ft)

RWS04A*
T-7.5
Mi11CJ,0
B^O.86'

pioo

K22 (10-15 ft)
^900 (40-45 ft)^_
[BPT221
^00 (15 ft)
fco (35 ft)

DPT204
/ 49 (55-57 fl)

DPT209 X
teTI000.(4Q-42 ft)'

PMBBT203|
RSl;(,i:8-"20*ft)l

r?pvsi3^ji
S®T-Kis
M-NS
p ' B-0.48 J,0

DPT220,
15(15 fin
5U(35$]

DPT202

36,000:1,36-38 ft)

VPi01
33 (10-15 ft)
3.600 (30-35 ft)
. ^ . 140 (50-55 ft)

DPT205

56,000 (35-37 ft)

DPT206
380 (38-40 ft)

SB109 —
170 (43-45 ft) .

Tdpj|2iiB

22.000 (24-26 ft)

DPT224
1.400 (15 ft)—-
2.4 J.O (35 ft)

DPT208
150 (28-30 ft)"

DPT210
26(38^-40^

DPT207
0.57 (40-42 ft)

DPT223
16 (15 ft)
5U (35 ft)

VP 102 1 B
5.0U.O (20-25 ft)
5.OU (60-65 ft)
120^(70-75 ft)

INSET MAP

Groundwater PCE Concentrations - Surficial Aquifer
ABC One-Hour Cleaners OU3
Jacksonville, Onslow County, North Carolina

Feet

NAD83 State Plane NC; Feet

D-3


-------
Figure D-4: PCE Concentrations - Castle Hayne Aquifer, 2017

' C22JB
. If 0.79 (70-75 ftJBS
0.5U (90-95 ft)
0.5U (120-125-ft) v
0.5U (130-135 ft) ^
0.5U (14-5-150 ft)

VP100
(^,160 (70-75 ft)
Hp3pj.0l.105jftW^

fmrnmiAs ft i —/
^5^(i45j15g(tCT

V- - 4^:(,1!70^175{ft) Jig
|pW(^200mM^M
V-,3r3;(220-22Sft)> T]

vpioi1 Tl
19 (70-75" ft)
•4.5 J,O (100-105 ft)
2.4 J,0(110-115 ft)
2.9 J,Ol(.120-125 ft)

C09 •

VP 103
81 (75-80 ft)
•180 (95-100 ft)

¦111^^02]

KMTi;^2oa't)1

C03-
T-3;5.
M-NS
B-10

^ J

0.46J(75M)1
|^b.63:~Jp6|9^t)l
r0.98 J (110-115 ft)
JO as J (125-130 ft)
0.93 J (145-150 ft)

RWC01
T-0.5U ,
M-NS
¦iBl0.5Uw

Legend

Groundwater DPT with PCE Concentrations
® Above the 0.7 |ig/L Recommended Goal
Castle Hayne Aquifer Wells

Monitoring Well with PCE Concentrations
Below the 0,7 M9"- Recommended Goal
Monitoring Well with PCE Concentrations
^ Above the 0.7 pg/L Recommended Goal
Recover Well with PCE Concentrations
Below the 0.7 pg/L Recommended Goal
Abandoned/Destroyed Well
PCE Is oco nee titrations in Groundwater

	1,000 ua'L

100 pg/L
— 10 |jg/L
0.7 yg/L

Dashed where inferred
_J Site Property Boundary
C05 Well ID

T - NS T - PDB sample at top of screen interval
M - NS M - PDB sample at middle of screen interval
B - 0.5 U B - PDB sample at bottom of screen interval
PDB Passive Diffusive Bag
Results displayed in micrograms per liter (ms/L)
VP100, VFP101: and VP102 results are from Sept 2016;
VP103 and VP105 results are from Jan 2017: other well
results are from May 2017. except C22 and C23
collected in Feb/March 2019	

RWC024
_^T-N$ I
MP0.37 J,01
B-NS ' .

lmsf
JK£ns
|B?of5y

^ TCjli7Di

Groundwater PCE Concentrations - Castle-Hayne Aquifer
ABC One-Hour Cleaners OU3
Jacksonville, Onslow County, North Carolina

Feet

NAD83 State Plane NO Feet

D-4


-------
Figure D-5: Remedial Design Surface Soil Sampling Results, 2018

;SSD13i.

r|Sample Location

Sample Location

S5A10

SSB1Q

Sample Date

12/11/2018

Sample Location

Sample Location

5SC10

|Sarnple Location

12/10/2018

12/11/2018

Sample Date
PCE(ug/kg)

12/10/2018

Sample Location

12/11/20181

Sample Date

Sample Location

SSD10

SSElj]

12/11/2018

Sample Date

|Sample Location

PCE(ug/kg)

12/12/2018

|Sample Date

[PCE(ug/kg)

[SSF.10]

jSample Location

Warehouse

12/10/2018

|Sample Date
|PCE(ug/kg)

Sample Location

Sample Location

jSample Location

Sample Date

12/11/2018

12/12/2018

12/11/20181

PCE(ug/kg)

PCE (ug/kg)

Sample Location

12/12/2018

Sample Date

jSample Locatior

SSF5

|Sample Location

12/12/20181

Sample Date

12/12/2018

5 Sample Location

Sample Location
Sample Date
PCE(ug/kg)	

12/12/2018|

12/12/2018

PCE(ug/kg)

Sample Location

Sample Location

12/12/20181

12/12/2018

Sample Location

12/12/2018

Sample Date

PCE(ug/kg)

TCE(ug/kg)

ABC
One-Hour
Cleaners

Sample Location

Sample Location

12/11/2018

12/12/2018|

Sample Date

Sample Location

12/12/2018|

Sample Date

Furniture Store

[Sho p p i nq'Ce n terj

12/11/2018

Legend

Surface Soil Samples with
PCE Concentrations Below
the 6.3 ug/kg Cleanup Level

Surface Soil Samples with
PCE Concentrations Above
the 6.3 ug/kg Cleanup Level

Former ABC One-Hour
Cleaners Building

Dollar Tree

Notes:

1.	Results only shown if they were above
the detection limit.

2.	BOLD results indicate detections.

3.	Shaded results exceed the cleanup level

4.	All surface soil samples were collected from
0 to 0.5 ft bas.

Surface Soil Samples - December 2018
ABC One-Hour Cleaners OU3
Jacksonville, Onslow County, North Carolina

Figure
3-6

D-5


-------
Figure D-6: Remedial Design Subsurface Soil Sampling Results, 2018

Sample Location

DPT215

DPT212

DPT213

TCE (ug/kg)

Sample Location

DPT 218

4/6/2019

Start Depth (ft)
End Depth (ft)

cis-1,2 DCE [ug/kg)

Sample Location

DPT 217

4/6/2019

End Depth (ft)
cis-1,2 DCE (ug/kg)

Equipment
Compound

DPT223

Sample Location

DPT 221

Sample Date

4/8/2019

Start Depth (ft)

29

39

End Depth (ft)

30

40

cis-1,2 DCE (ug/kg)

2.5J.O

6 U

PCE(ug/kg)

740 J,0

19

TCE(ug/kg)

15

6 U

Sample Date

4/8/2019

End Depth (ft)
cis-1,2 DCE (ug/kg)

PCE(ug/kg)

TCE(ug/kg)

Sample Location

/





Sample Location

DPT216



Sample Date

4/5/2019

/ , ^ DPT219

Istart Depth (ft)

29

End Depth (ft)

30

/ ¦ S3

TCE(ug/kg)

11



Sample Location

DPT 220

Sample Date

4/7/2019

Start Depth (ft)

19

24

End Depth (ft)

20

25

cis-1,2 DCE (ug/kg)

35

7.9 J

PCE (ug/kg)

120

3.3J

TCE (ug/kg)

64

5J

Vinyl chloride

3.2 J

4.5 U

Center



DPT 224

Sample Date

4/9/2019

Start Depth (ft)

19

29

End Depth (ft)

20

30

cis-1,2 DCE (ug/kg)

13

33

PCE (ug/kg)

26

91

TCE(ug/kg)

9.9

25

Legend

	Former ABC One-Hour Cleaners Building

~ Parcel
Notes:

1.	Results only shown if they were above the
detection limit.

2.	BOLD results indicate detections.

3.	Shaded results exceed the cleanup level

4/4/2019

2.3 J,O

3.41,0

Furniture Store

"¦L

Sample Date
Start Depth (ft)
End Depth (ft)

A

Feet

NAD83 State Plane NC, Feet

Subsurface Soil DPT Results - April 2019
ABC One-Hour Cleaners OU3
Jacksonville, Onslow County, North Carolina

Figure

3-7

D-6


-------
Figure D-7: Remedial Design-Inferred NAPL Locations, 2018

DPT Soil Boring (2011)

DPT Soil Boring (2016)

,	1 Former ABC One-Hour

I	J Cleaners Building

Locations of Potential NAPL Inferred from
PCE Concentrations in Soil and MIP Results

ABC One-Hour Cleaners
Jacksonville, Onslow County, North Carolina

Figure
3-8

D-7


-------
Figure D-8: Soil-gas Sampling Results, 2019

L m

rv

D-8


-------
APPENDIX E - PRESS NOTICE

U.S. ENVIRONMENTAL PROTECTION AGENCY

NEWS RELEASE

EPA.GOV/NEWSROOM

EPA to Review Cleanups at 45 Southeast Superfund Sites

Contact Information: region4press@epa.gov, 404-562-8400

ATLANTA (Oct. 19, 2022)-Today, the U.S. Environmental Protection Agency (EPA) announced that
comprehensive reviews will be conducted of completed cleanup work at 45 National Priority List (NPL) Superfund
sites in the Southeast.

The sites, located in Alabama, Florida, Georgia, Kentucky, Mississippi, North Carolina, South Carolina, and
Tennessee, will undergo a legally required Five-Year Review to ensure that previous remediation efforts at the
sites continue to protect public health and the environment.

"The Southeast Region will benefit tremendously from the full restoration of Superfund sites, which can become
valuable parts of the community landscape," said EPA Region 4 Administrator Daniel Blackmon. "The Five-
Year Review evaluations ensure that remedies put in place to protect public health remain effective overtime."
The Superfund Sites where EPA will conduct Five-Year Reviews in 2022 are listed below. The web links provide
detailed information on site status as well as past assessment and cleanup activity. Once the Five-Year Review is
complete, its findings will be posted in a final report at https://www.epa.gov/superfund/search-superfund-five-year-
reviews.

Alabama

Alabama Army Ammunition Plant https://www.epa.gov/superfund/alabama-army-ammunition-plant
Alabama Plating Company, Inc. https://www.epa.gov/superfund/alabama-piating-co
Mowbray Engineering Co. https://www.epa.gov/superfund/rnowbray-engineering
US NASA Marshall Space Flight Center

US Army/NASA Redstone Arsenal https://www.epa.gov/superfund/redstone-aresenal
Florida

ALARIC Area GW Plume https://www.epa.gov/superfund/alaric-area-groundwater-plume
Beulah Landfill https://www.epa.gov/superfund/beulah-landfill

Chevron Chemical Co. (Ortho Division) https://www.epa.gov/superfund/chevron-chemical-company

Florida Petroleum Reprocessors https://www.epa.gov/superfund/florida-petroleum-reprocessors

Miami Drum Services https://www.epa.gov/superfund/miami-drum-services

Pensacola Naval Air Station https://www.epa.gov/superfund/naval-air-station-pensacola

Raleigh Street Dump https://www.epa.gov/superfund/raleigh-street-dump

Taylor Road Landfill https://www.epa.gov/superfund/taylor-road-landfill

Tower Chemical Co. https://www.epa.gov/superfund/tower-chemical-company

Georgia

Alternate Energy Resources Inc. https://www.epa.gov/superfund/alternate-energy-resources

Peach Orchard & Nutrition Co. Rd PCE Groundwater Plume Site https://www.epa.gov/superfund/peach-orchard-

road-pce-plume

Powersville Site https://www.epa.gov/superfund/powersville-site

T.H. Agriculture & Nutrition Co (Albany Plant) https://www.epa.gov/superfund/t-h-agriculture
Kentucky

A.L. Taylor (Valley of the Drums) https://www.epa.gov/superfund/al-taylor-valley-of-drums

E-l


-------
Brantley Landfill https://www.epa.gov/superfund/brantley-landfill
Distler Brickyard https://www.epa.gov/superfund/distler-brickyard

Distler Farm https://www.epa.gov/superfun https://www.epa.gov/superfund/lee-lane-landfilld/distler-farm
Lee's Lane Landfill https://www.epa.gov/superfund/lee-lane-landfill

National Electric Coil Co./Cooper Industries https://www.epa.gov/superfund/national-electric-coil-cooper-
industries

Tri City Disposal Co. https://www.epa.gov/superfund/tri-city-disposal
North Carolina

ABC One Hour Cleaners https://www.epa.gov/superfund/abc-one-hour-cleaners

Aberdeen Pesticide Dumps https://www.epa.gov/superfund/aberdeen-contaminated-groundwater

Benfield Industries, Inc. https://www.epa.gov/superfund/benfield-industries

Cherry Point Marine Corps Air Station https://www.epa.gov/superfund/cherry-point-marine-corps

CTS of Ashville, Inc. https://www.epa.gov/superfund/cts-millsgap

GEIGY Chemical Corp (Aberdeen Plant) https://www.epa.gov/superfund/ciba-geigy-corporation
Gurley Pesticide Burial https://www.epa.gov/superfund/gurley-pesticide-burial

North Carolina State University (Lot 86, Farm Unit #1) https://www.epa.gov/superfund/north-carolina-state-
university

Sigmon's Septic Tank Service https://www.epa.gov/superfund/sigmon-septic-tank
South Carolina

Admiral Home Appliances https://www.epa.gov/superfund/admiral-home-appliances

Beaunit Corp (Circular Knit & Dyeing Plant) https://www.epa.gov/superfund/beaunit

Carolawn Inc. https://www.epa.gov/superfund/carolawn

Elmore Waste Disposal https://www.epa.gov/superfund/elmore-waste-disposal

International Minerals and Chemicals (IMC) https://www.epa.gov/superfund/imc

Kalama Specialty Chemicals https://www.epa.gov/superfund/kalama-specialty-chemicals

Koppers Company, Inc. (Charleston Plant) https://www.epa.gov/superfund/koppers-charleston-plant

Savannah River Site (USDOE) https://www.epa.gov/superfund/savannah-river-site

SCRDI Bluff Road https://www.epa.gov/superfund/scrdi-dixiana

Tennessee

Mallory Capacitor Co. https://www.epa.gov/superfund/mallory-capacitor

Memphis Defense Depot (DLA) https://www.epa.gov/superfund/memphis-defense-depot

Background

Throughout the process of designing and constructing a cleanup at a hazardous waste site, EPA's primary goal is
to make sure the remedy will be protective of public health and the environment. At many sites, where the remedy
has been constructed, EPA continues to ensure it remains protective by requiring reviews of cleanups every five
years. It is important for EPA to regularly check on these sites to ensure the remedy is working properly. These
reviews identify issues (if any) that may affect the protectiveness of the completed remedy and, if necessary,
recommend action(s) necessary to address them.

There are many phases of the Superfund cleanup process including considering future use and redevelopment at
sites and conducting post cleanup monitoring of sites. EPA must ensure the remedy is protective of public health
and the environment and any redevelopment will uphold the protectiveness of the remedy into the future.
The Superfund program, a federal program established by Congress in 1980, investigates and cleans up the most
complex, uncontrolled or abandoned hazardous waste sites in the country and endeavors to facilitate activities to
return them to productive use. In total, there are more than 280 Superfund sites across the Southeast.

More information:

EPA's Superfund program: https://www.epa.gov/superfund

O0©G

E-2


-------
APPENDIX F - INTERVIEW FORMS

ABC ONE-HOUR CLEANERS SUPERFIJND SITE
FIVE-YEAR REVIEW INTERVIEW FORM

Site Name: ABC ONE-HOUR CLEANERS

EPA ID: NCD024644494

Interviewer name:

Interviewer affiliation:

Subject name: Beth Hartzell

Subject affiliation: NCDEQ

Subject contact information: b et h. h a rtzel 1 @ncdenr.gov

Interview date: 2/3/23

Interview time: 2:00 p.m.

Interview location: Email

Interview format: In Person Phone Mail Email Other:

Interview category: State Agency

1.	What is your overall impression of the project, including cleanup, maintenance and reuse
activities (as appropriate)?

The project is well run. There has been a delay in starting the remediation due to funding issues but
funding is available and the remediation is in progress.

2.	What is your assessment of the current performance of the remedy in place at the Site?

The remedial action is just beginning. The previous remedy (pump and treat) has been shut down.

3.	Are you aware of any complaints or inquiries regarding site-related environmental issues or
remedial activities from residents in the past five years?

No.

4.	Has your office conducted any site-related activities or communications in the past five years?
If so, please describe the purpose and results of these activities.

Participated in an inspection with the NPDES group to look at the pump-and-treat system. As the
system was no longer running there were no issues.

F-l


-------
5.	Arc you aware of any changes to state laws that might affect the protectiveness of the Site's

remedy?

No.

6.	Are you comfortable with the status of the institutional controls at the Site? If not, what are
the associated outstanding issues?

There are no institutional controls in place at the Site but they will be implemented as part of the

remedy.

7.	Are you aware of any changes in projected land use(s) at the Site?

No.

8.	Do you have any comments, suggestions or recommendations regarding the management or
operation of the Site's remedy?

The Site is well managed. Looking forward to remedy implementation.

9.	Do you consent to have your name included along with your responses to this questionnaire in
the FYR report?

Yes.

F-2


-------
ABC ONE-HOUR CLEANERS SUPERFIJND SITE
FIVE-YEAR REVIEW INTERVIEW FORM

Site Name: ABC ONE-HOUR CLEANERS

EPA ID: NCD024644494

Interviewer name:

Interviewer affiliation:

Subject name: Thomas Richard

Subject affiliation: MCB Camp Lejeune

Subject contact information: Thomas.richard@iismc.mii

Interview date: 2/14/2023

Interview time: 07:59

Interview location: By email

Interview format: In Person Phone Mail Email Other:

Interview category: Federal Agency

1.	What is your overall impression of the project, including cleanup, maintenance and reuse
activities (as appropriate)?

I am pleased that progress has been made towards remedial action at the site.

2.	What is your assessment of the current performance of the remedy in place at the Site?

I understand that an interim remedial action is planned, but that remediation at the site is currently
incomplete. While the UST was removed, the source area has not been fully remediated.

3.	Are you aware of any complaints or inquiries regarding site-related environmental issues or
remedial activities from residents in the past five years?

Other than past issues with damaged fencing, I am not aware of any site related environmental
issues/activities.

4.	Has your office conducted any site-related activities or communications in the past five years?
If so, please describe the purpose and results of these activities.

MCB Camp Lejeune conducts semi-annual site inspections to ensure no impacts to land use have
occurred to the ABC Cleaner site. No impacts have been observed. In October 2020, the Installation
Restoration Section of the Environmental Management Division escorted an NCDEQ inspector onto
Base property to inspect an EPA constructed inactive pump & treat groundwater treatment system.

F-3


-------
5.	Arc you aware of any changes to state laws that might affect the protectiveness of the Site's

remedy?

I am unaware of any changes that would impact the protectiveness of the Site's remedy.

6.	Are you comfortable with the status of the institutional controls at the Site? If not, what are
the associated outstanding issues?

I am comfortable with the institutional controls. MCB Camp Lejeune maintains aquifer use
management within the installation boundaries to ensure protection of impacted aquifers.

7.	Are you aware of any changes in projected land use(s) at the Site?

MCB Camp Lejeune was notified of a proposal for recreational use in the area of this site, but I am
not aware if this was pursued at the ABC cleaner's site. I am aware that the building structure was
demolished, and a fence was installed onsite.

8.	Do you have any comments, suggestions or recommendations regarding the management or
operation of the Site's remedy?

Please continue to keep MCB Camp Lejeune in the loop with site progress. I have no additional
comments or suggestions.

9.	Do you consent to have your name included along with your responses to this questionnaire in
the FYR report?

I consent to have my name and responses included in the FYR.

F-4


-------
APPENDIX G - SITE INSPECTION CHECKLIST

FIVE-YEAR REVIEW SITE INSPECTION C HEC KLIST

I. SITE INFORMATION

Site Name: ABC One Hour Cleaners

Date of Inspection: 1/17/2023

Location and Region: Jacksonville. North

Carolina. EPA Region 4

EPA ID: NCD024644494

Agency, Office or Company Leading the
Five-Year Review: EPA

Weather/Temperature: Sunny/55 degrees

Remedy Includes: (Check all that apply)

I I Landfill cover/containment
~ Access controls
[X] Institutional controls
I I Groundwater pump and treatment
I I Surface water collection and treatment

I I Monitored natural attenuation
I I Groundwater containment
~ Vertical barrier walls

Attachments: [U Inspection team roster attached O Site map attached

II. INTERVIEWS (check all that apply)

1. O&M Site



Manager Name Title
Interviewed 1 1 at site 1 1 at office 1 1 bv phone Phone:
Problems, suggestions | | Report attached:

Date

2. O&M Staff



Name Title
Interviewed 1 1 at site 1 1 at office 1 1 bv phone Phone:
Problems/suggestions | | Report attached:

Date

3. Local Regulatory Authorities and Response Agencies (i.e., state and tribal offices, emergency

response office, police department, office of public health or environmental health, zoning office,
recorder of deeds, or other city and county offices). Fill in all that apply.

Agency NCDEO

Contact Beth Hartzell		

Problems/suggestions Q Report attached: Yes

2/3/2023

4. Other Interviews (optional) Q Report attached:

Charity Delaney, USMC - Camp Lejeune

III. ON-SITE DOCUMENTS AND RECORDS VERIFIED (check all that apply)

1. O&M Documents

I I O&M manual Q Readily available Q Up to date

~ As-built drawings O Readily available O Up to date

§N/A

N/A

G-l


-------
1 1 Maintenance logs Q Readily available Q Up to date X N/A
Remarks:

2.

Site-Specific Health and Safety Plan

1 1 Contingency plan/emergency
response plan

Remarks:

1 1 Readily available
1 1 Readily available

1 1 Up to date ^
1 1 Up to date [>

3 N/A
3 N/A

3.

O&M and OSHA Training Records

Remarks:

1 1 Readily available

1 1 Up to date [>

3 N/A

4.

Permits and Service Agreements

1 1 Air discharge permit
1 1 Effluent discharge
1 1 Waste disposal, POTW
1 1 Other permits:

Remarks:

1 1 Readily available
1 1 Readily available
1 1 Readily available
1 1 Readily available

1 1 Up to date [>
1 1 Up to date ^
1 1 Up to date ^
1 1 Up to date E

3 N/A

3 N/A
3 N/A
3 N/A

5.

Gas Generation Records

Remarks:

1 1 Readily available

1 1 Up to date ^

3 N/A

6.

Settlement Monument Records

Remarks:

1 1 Readily available

1 1 Up to date ^

3 N/A

7.

Groundwater Monitoring Records

Remarks:

1 1 Readily available

1 1 Up to date E

3 N/A

8.

Leachate Extraction Records

Remarks:

1 1 Readily available

1 1 Up to date ^

3 n/a

9.

Discharge Compliance Records

1 1 Air O Readily available O Up to date ^ N/A
1 1 Water (effluent) Q Readily available Q Up to date X N/A
Remarks:



10.

Daily Access/Security Logs

Remarks:

1 1 Readily available

1 1 Up to date E

3 N/A

IV. O&M COSTS

1.

O&M Organization

1 1 State in-house
1 1 PRP in-house
1 1 Federal facility in-house
153 Not in O&M

1 1 Contractor for state
1 1 Contractor for PRP
1 1 Contractor for Federal facility



G-2


-------
2.

O&M Cost Records

1 1 Readily available O Up to date





1 1 Funding mechanism/agreement in place Unavailable



Original O&M cost estimate: 1 1 Breakdown attached



Total annual cost by year for review period if available



From: To:

1 1 Breakdown attached



Date Date Total cost





From: To:

1 1 Breakdown attached



Date Date Total cost





From: To:

1 1 Breakdown attached



Date Date Total cost





From: To:

1 1 Breakdown attached



Date Date Total cost





From: To:

1 1 Breakdown attached



Date Date Total cost



3.

Unanticipated or Unusually High O&M Costs during Review Period

Describe costs and reasons: No O&M is currently occurring at the Site.



V. ACCESS AND INSTITUTIONAL CONTROLS

1X1 Applicable [J N/A

A. Fencing

1.

Fencing Damaged O Location shown on site map
Remarks: Fencing in good condition

1 1 Gates secured O N/A

B.

Other Access Restrictions



1.

Signs and Other Security Measures Q Location shown on site map Q N/A



Remarks: No trespassing signs on fence.



C.

Institutional Controls (ICs)



G-3


-------
1.

Implementation and Enforcement

Site conditions imply ICs not properly implemented

[El N/A

Site conditions imply ICs not being fully enforced

[El N/A

Type of monitoring (e.g., self-reporting, drive bv):
Freciuencv:

Responsible partv/agencv:

Contac

t



1 1 Yes ~ No
1 1 Yes ~ No



Name Title

Date

Phone no.



Reporting is up to date

~ Yes

~ No IKIn/a



Reports are verified by the lead agency

~ Yes

~ No M
N/A



Specific requirements in deed or decision documents have
been met

~ Yes

~ No M
N/A



Violations have been reported

~ Yes

~ No M
N/A



Other problems or suggestions: ~ Report attached





2.

Adequacy ~ ICs are adequate ~ ICs are
Remarks: Institutional controls have not been implemented

inadequate

X N/A

D.

General





1.

Vandalisni/Trespassing ~ Location shown on site map
evident

1^1 No vandalism



Remarks:





2.

Land Use Changes On Site ~ N/A

Remarks: Buildings have been demolished





3.

Land Use Changes Off Site X N/A

Remarks:





VI. GENERAL SITE CONDITIONS

A. Roads [J Applicable [X] N/A

1.

Roads Damaged Location shown on site
~ N/A

Remarks:

map

1 1 Roads adequate

B.

Other Site Conditions





Remarks:

G-4


-------


VII. LANDFILL COVERS ~ Applicable

3 N/A

A. Landfill Surface

1.

spots)

Settlement (low

A rial extent:
Remarks:

1 1 Location shown on site map

1 1 Settlement not evident

Depth:

2.

Cracks

Lengths:
Remarks:

1 1 Location shown on site map
Widths:

1 1 Cracking not evident

Depths:

3.

Erosion

A rial extent:
Remarks:

1 1 Location shown on site map

1 1 Erosion not evident

Depth:

4.

Holes

A rial extent:
Remarks:

1 1 Location shown on site map

1 1 Holes not evident

Depth:

5.

Vegetative Cover

1 1 No signs of stress
Remarks:

1 1 Grass O Cover properly

established

1 1 Trees/shrubs (indicate size and locations on a diagram)

6.

Alternative Cover (e.g., armored rock, concrete)
Remarks:

~ N/A

7.

Bulges

A rial extent:
Remarks:

1 1 Location shown on site map

1 1 Bulges not evident

Height:

8. Wet Areas/Water

Damage

1 1 Wet areas

1 1 Ponding
1 1 Seeps
1 1 Soft subgrade
Remarks:

1 1 Wet areas/water damage not evident

1 1 Location shown on site Arial extent:

map

1 1 Location shown on site Arial extent:

map

1 1 Location shown on site Arial extent:

map

1 1 Location shown on site Arial extent:

map

9.

Slope Instability

1 1 Slides

1 1 Location shown on site

G-5


-------






map



1 1 No evidence of slope instability





A rial extent:







Remarks:





B.

Benches O Applicable O N/A





(Horizontally constructed mounds of earth placed across a steep landfill side slope to interrupt
the slope in order to slow down the velocity of surface runoff and intercept and convey the
runoff to a lined channel.)

1.

Flows Bypass Bench
Remarks:

1 1 Location shown on site
map

1 1 N/A or okay

2.

Bench Breached

Remarks:

1 1 Location shown on site
map

1 1 N/A or okay

3.

Bench Overtopped

Remarks:

1 1 Location shown on site
map

1 1 N/A or okay

C.

Letdown Channels

1 1 Applicable [J N/A





(Channel lined with erosion control mats, riprap, grout bags or gabions that descend down the
steep side slope of the cover and will allow the runoff water collected by the benches to move



off of the landfill cover without creating erosion gullies.)



1.

Settlement (Low

I | Location shown on site map

I ] No evidence of

spots)



settlement



A rial extent:



Depth:



Remarks:





2.

Material

1 1 Location shown on site map

1 1 No evidence of

Degradation



degradation



Material tvpe:



Arial extent:



Remarks:





3.

Erosion

A rial extent:
Remarks:

1 1 Location shown on site map

1 1 No evidence of erosion

Depth:

4.

Undercutting

A rial extent:
Remarks:

1 1 Location shown on site map

1 1 No evidence of
undercutting

Depth:

5.

Obstructions

Type:

1 1 No obstructions

G-6


-------


1 1 Location shown on site map

A rial extent:





Size:







Remarks:





6.

Excessive Vegetative Growth
1 1 No evidence of excessive growth

Type:





1 1 Vegetation in channels does not obstruct flow





1 1 Location shown on site map

A rial extent:





Remarks:





D.

Cover Penetrations O Applicable O N/A



1.

Gas Vents Q Active



1 1 Passive



~ Properly ~
secured/locked Functioning

1 1 Routinely
sampled

1 1 Good condition



1 1 Evidence of leakage at penetration

1 1 Needs
maintenance

~ N/A



Remarks:





2.

Gas Monitoring Probes







~ Properly ~
secured/locked Functioning

1 1 Routinely
sampled

1 1 Good condition



1 1 Evidence of leakage at penetration

1 1 Needs
maintenance

~ N/A



Remarks:





3.

Monitoring Wells (within surface area

of landfill)





~ Properly ~
secured/locked Functioning

1 1 Routinely
sampled

1 1 Good condition



1 1 Evidence of leakage at penetration

~ Needs
maintenance

~ N/A



Remarks:





4.

Extraction Wells Leachate







~ Properly ~
secured/locked Functioning

1 1 Routinely
sampled

1 1 Good condition



1 1 Evidence of leakage at penetration

1 1 Needs
maintenance

~ N/A



Remarks:





5. Settlement Q Located
IVIonunients

1 1 Routinely

surveyed

~ N/A



Remarks:





E.

Gas Collection and Treatment

HI Applicable

~ N/A

G-7


-------
1.

Gas Treatment Facilities

1 1 Flaring Q Thermal destruction Q Collection for

reuse

1 1 Good condition Q Needs maintenance
Remarks:

2.

Gas Collection Wells, Manifolds and Piping

1 1 Good condition Q Needs maintenance
Remarks:

3.

Gas Monitoring Facilities (e.g., gas monitoring of adjacent homes or buildings)
1 1 Good condition Q Needs maintenance Q N/A
Remarks:

F.

Cover Drainage Layer Q Applicable Q N/A

1.

Outlet Pipes Inspected Q Functioning Q N/A
Remarks:

2.

Outlet Rock Inspected Q Functioning Q N/A
Remarks:

G. Deten ti on/Sed i men tati on Ponds Q Applicable Q N/A

1.

Siltation Area extent: Depth: 1 1 N/A

1 1 Siltation not evident

Remarks:

2.

Erosion Area extent: Depth:

1 1 Erosion not evident

Remarks:

3.

Outlet Works Q Functioning Q N/A
Remarks:

4.

Dam O Functioning Q N/A
Remarks:

H. Retaining Walls Q Applicable Q N/A

1.

Deformations O Location shown on site map Q Deformation not evident
Horizontal displacement: Vertical displacement:

Rotational displacement:

Remarks:

2.

Degradation Q Location shown on site map Q Degradation not evident
Remarks:

G-8


-------
1. Perimeter Ditches/Off-Site Discharge Q Applicable Q N/A

1.

Siltation

1 1 Location shown on site

1 1 Siltation not evident





map





Area extent:



Depth:



Remarks:





2.

Vegetative Growth

1 1 Location shown on site

~ N/A





map





1 1 Vegetation does not impede flow





Area extent:



Type:



Remarks:





3.

Erosion

1 1 Location shown on site

1 1 Erosion not evident





map





Area extent:



Depth:



Remarks:





4.

Discharge Structure O Functioning

~ N/A



Remarks:





VIII. V ERTIC AL BARRIER WALLS ~ Applicable

IK1n/a

1.

Settlement

1 1 Location shown on site

1 1 Settlement not evident





map





Area extent:



Depth:



Remarks:





2.

Performance

Tvpe of monitoring:





Monitoring







1 1 Performance not monitored





Freciuencv:



1 1 Evidence of breaching



Head differential:







Remarks:





IX.

GROUND WATER/SURFACE WATER REMEDIES

1 1 Applicable [>3 N/A

A.

Groundwater Extraction Wells, Pumps and Pipelines

1 1 Applicable [XI N/A

1.

Pumps, Wellhead Plumbing and Electrical





1 1 Good

1 1 All required wells properly

1 1 Needs |[X] N/A



condition

operating

maintenance



Remarks: Svstem is not currently operating.



2.

Extraction System Pipelines, Valves, Valve Boxes and Other Appurtenances



I ] Good

I | Needs maintenance





condition





G-9


-------
Remarks: Svstem is not currently operating.

3.

Spare Parts and Equipment





1 1 Readily Q Good condition Q Requires upgrade Q Needs to be
available provided



Remarks: Svstem is not currently operating.



B. Surface Water Collection Structures, Pumps and Pipelines

I] Applicable N/A

1.

Collection Structures, Punips and Electrical

1 1 Good O Needs maintenance
condition

Remarks:



2.

Surface Water Collection System Pipelines, Valves, Valve Boxes and Other
Appurtenances



1 1 Good O Needs maintenance
condition





Remarks:



3.

Spare Parts and Equipment





1 1 Readily Q Good condition Q Requires upgrade Q Needs to be
available provided



Remarks:



C.

Treatnient System Q Applicable [X] N/A



1.

Treatment Train (check components that apply)





1 1 Metals removal Q Oil/water separation

1 1 Bioremediation



1 1 Air stripping Q Carbon adsorbers





1 1 Filters:





1 1 Additive (e.g.. chelation agent. flocculent):





1 1 Others:





1 1 Good condition Q Needs maintenance





1 1 Sampling ports properly marked and functional





1 1 Sampling/maintenance log displayed and up to date





1 1 Equipment properly identified





1 1 Ouantitv of groundwater treated annuallv:





1 1 Ouantitv of surface water treated annuallv:





Remarks: Svstem is not currently operating.



2.

Electrical Enclosures and Panels (properly rated and functional)
[xl N/A O Good condition Q Needs maintenance

G-10


-------
Remarks:

Tanks, Vaults, Storage Vessels

[Xl N/A O Good condition Q Proper secondary

containment

~ Needs
maintenance

Remarks:

Discharge Structure and Appurtenances

[x] N/A	Q Good condition Q Needs maintenance

Remarks:	

Treatment Building(s)

E n/a	~ Good condition (esp. roof and doorways) ~ Needs repair

Chemicals and equipment properly stored

Remarks:

6. Monitoring Wells (pump and treatment remedy)

I I Properly
secured/locked

I I All required wells
located

Remarks:	

I I	I I Routinely

Functioning sampled

I I Needs maintenance

I I Good condition

El n/a

D. Monitoring Data

1. Monitoring Data

~ Is routinely submitted on time

~ Is of acceptable quality

2. Monitoring Data Suggests:

I I Groundwater plume is effectively
contained

Contaminant concentrations are declining

E. Monitored Natural Attenuation

1. Monitoring Wells (natural attenuation remedy)

I I Properly secured/locked Q	Q Routinely

Functioning sampled

I I All required wells located Q Needs maintenance

Remarks:	

I I Good
condition

~ N/A

X. OTHER REMEDIES

If there are remedies applied at the site and not covered above, attach an inspection sheet describing
the physical nature and condition of any facility associated with the remedy. An example would be soil
vapor extraction.	

XI. OVERALL OBSERVATIONS

Implementation of the Remedy

G-ll


-------
Describe issues and observations relating to whether the remedy is effective and functioning as
designed. Begin with a brief statement of what the remedy is designed to accomplish (e.g., to
contain contaminant plume, minimize infiltration and gas emissions).

The remedies previously consisted of soil and groundwater treatment systems. The groundwater
	mdsoiljregment^stems=ge=cm^Ji^=ma^	

B.	Adequacy of O&M	

Describe issues and observations related to the implementation and scope of O&M procedures.
In particular, discuss their relationship to the current and long-term protectiveness of the
remedy.

	No issues noted.	

C.	Early Indicators of Potential Remedy Problems	

Describe issues and observations such as unexpected changes in the cost or scope of O&M or a
high frequency of unscheduled repairs that suggest that the protectiveness of the remedy may be
compromised in the future.

	^	

D.	Opportunities for Optimization	

Describe possible opportunities for optimization in monitoring tasks or the operation of the
remedy.

None identified.

G-12


-------
APPENDIX H - SITE INSPECTION PHOTOS

H-l


-------
EPA Superfurid Site

No Trespassing

In Case oF Emergency Call 40^-562-8700

Fencing and signage

H-2


-------
Alley between the eastern side of the Site and the furniture store

H-3


-------
South-facing view from within the site fencing

H-4


-------
North-facing view from within the site fencing

H-5


-------